AMC Process in Plant Maintenance

Purpose: - In any SAP Plant Maintenance implementation, customer will ask about how to handle the Annual
Maintenance Contract Process (AMC Process) in SAP. People might follow different procedures, here I have
documented one process and this might be useful for the freshers.
AMC Process for Preventive Maintenance :
1.
2.
3.
4.
5.
6.
7.
8.
9.

Create Service Master.


Create Outline Agreement
Create General Maintenance Task list
Create Maintenance Plan
Schedule Maintenance Plan
Release Maintenance Order
Create Purchase Order against the Purchase Requisition
Create Service Entry sheet against the Purchase Order
Perform TECO for the Maintenance Order

Step 1:- Create Service Master by using the transaction code AC01.

Generated by Jive on 2016-01-08+01:00


1

AMC Process in Plant Maintenance

Step 2:- Create Outline Agreement / Service Contract for AMC by using the Transaction Code ME31K
Enter necessary data like Vendor, Agreement Type, Item Category as D and Acct Assignment
Cat. as F

Generated by Jive on 2016-01-08+01:00


2

AMC Process in Plant Maintenance

Enter the service short text, here I have taken 4 visits for Preventive and two visits for Free Break Down.
Since system will not allow zero price, entered minimum amount as 0.01 USD for Free Break Down Services.

Generated by Jive on 2016-01-08+01:00


3

AMC Process in Plant Maintenance

Details of Service specifications for Preventive Maintenance are as below

Generated by Jive on 2016-01-08+01:00


4

AMC Process in Plant Maintenance

Details of Service specifications for Free Break down Services.

SAVE the Outline Agreement after entering all the details. System will generate Outline agreement number.
Step 3:- Create General Maintenance Task List by using the transaction Code IA05 and enter the control key
as PM03 and enter the Outline agreement number as shown below.

Generated by Jive on 2016-01-08+01:00


5

AMC Process in Plant Maintenance

By using the service specifications button copy the services from the agreement

Generated by Jive on 2016-01-08+01:00


6

AMC Process in Plant Maintenance

Step 4:- Create single cycle maintenance plan by using the transaction code IP41 and enter the Task List
which was created earlier.

Generated by Jive on 2016-01-08+01:00


7

AMC Process in Plant Maintenance

Step 5:- Schedule Maintenance Plan and Release Maintenance Order


1. Maintenance Plan can be scheduled manually by using the Transaction IP10, in regular practice these
maintenance plans will be run on batch job in background.
2. Upon scheduling , Maintenance Orders will be triggered with reference to the intervals maintained in
Maintenance Plan
3. The Maintenance Orders (Preventive) called will be released to process further
4. Purchase requisition will be triggered on release of Maintenance Order.

Generated by Jive on 2016-01-08+01:00


8

AMC Process in Plant Maintenance

Step 6:- Process of Purchase Requisition to Purchase Orders


Use the transaction ME21n, Create Purchase Order with reference to the Purchase Requisition number
which was created in the Maintenance Order.

Generated by Jive on 2016-01-08+01:00


9

AMC Process in Plant Maintenance

Step 7:-Use the transaction ML81n, Create service entry sheet with reference to the Purchase Order which
was created from Purchase Requisition shown in the earlier screen shot.

Generated by Jive on 2016-01-08+01:00


10

AMC Process in Plant Maintenance

After completion of the Service entry sheet service cost will reflect in the Maintenance Order and do the TECO
and other normal PM process like settlement and business completion of the order.
AMC for Breakdown Maintenance Process
Use the Transaction IW31 and create Break down Maintenance Order as like normal PM Process.
Enter the Control Key as PM03 for the Operation which is to be done by the vendor as per the Outline
Agreement and enter the Outline Agreement number with Item number 0020

Generated by Jive on 2016-01-08+01:00


11

AMC Process in Plant Maintenance

Process of Breakdown Maintenance Order similar to Preventive Maintenance Order


1. Release the Maintenance Order
2. Purchase Requisition created from Maintenance Order is further processed to Purchase Order.
3. Create a Service Entry Sheet against the Purchase Order.
4. Accept the Service Entry Sheet.
5. Perform Maintenance Order for Technical Completion and Settlement.
6. Perform Business Completion
Upon releasing of the Break Down Order system will create Purchase Requisition and with reference to PR,
PO has ben created.

Generated by Jive on 2016-01-08+01:00


12

AMC Process in Plant Maintenance

Create Service Entry Sheet with reference to Purchase Order

Generated by Jive on 2016-01-08+01:00


13

AMC Process in Plant Maintenance

Similarly for any Paid Break Down Services, we can create one more line item in the Outline Agreement and
process the same like Break Down Order.
Hope this will be useful....