no.4
Determination of areas and side widths
Submitted by:
John lester b. cabungcal
13-48578/Ce-3202
submitted to:
Engr. Antonio Gamboa
january 20,2016
earth
works
Determination of
Areas and side
widths
Problem no.1
In a certain portion of road to be constructed the data
were taken.
Sideslopes=1:1
Sideslopes=1.5:1
Problem no.1
Given:
Required:
Base of cut=9m
Base of fill=8m
Problem no.1
Solution:
Problem no.2
Given the following section of an earthworks for a proposed road
construction on a hilly portion of the route. The width of the road
base for cut is. for allowance of drainage canals and for fill. Slide
slopes for cut is 1:1 and for fill is 1:5:1.
Problem no.2
Given:
Required:
Base of cut=6m
Value of x=?
Base of fill=5m
Area of fill=?
Area of cut=?
Problem no.2
Solution:
Value of x:
Area of fill:
Area of cut:
=)