TIME SCHEDULE OF S/S 9002

ID Task Name

Duration

Start

Finish

1 IDs and Permission

14 days

Sun 2/15/15

Sat 2/28/15

2 Mobilization & Precurement of Material

12 days

Sun 3/1/15

Thu 3/12/15

3 Earth Work Excavation for ACDB & Aux T/F

10 days

Thu 3/14/15

Tue 3/24/15

1 Lean Concrete for Column Foundations

2 days

Wed 3/25/15

Thu 3/26/15

2 RCC for Column neck

6 days

Sat 3/28/15

Thu 4/02/15

3 Backfilling & Compaction

4 days

Sat 4/04/15

Tue 4/7/15

4 RCC Grade Beams

6 days

Wed 4/8/15

Tue 4/14/15

5 RCC columns

6 days

Wed 4/15/15

Mon 4/20/15

6 RCC roof beams & slab

7 days

Tue 4/21/15

Mon 4/27/15

7 Parapet Wall

2 days

Tue 4/28/15

Wed 4/29/15

8 Block Masonary work

3 days

Thu 4/30/15

Sat 5/2/16

9 Roof water proofing

3 days

Sun 5/3/15

Tue 5/5/15

10 Internal/External paint

4 days

Wed 5/6/15

Sat 5/9/15

11 Raised Floor

2 days

Sun 5/10/15

Mon 5/11/15

12 False Ceiling

2 days

Tue 5/12/15

Wed 5/13/15

1 Lean Concrete for Manholes 1&2

2 days

Wed 3/25/15

Thu 3/26/15

2 RCC Manholes wall

4 days

Sat 3/28/15

Wed 4/1/15

3 RCC Manholes roof

3 days

Thu 4/2/15

Sun 4/5/15

4 RCC Duct bank

6 days

Sat 3/28/15

Wed 4/4/15

1 Lean Concrete

2 days

Sat 4/11/15

Sun 4/12/15

2 RCC Pad 1 & 2

8 days

Mon 4/13/15

Tue 4/21/15

1 Lean Concrete

2 days

Sat 4/11/15

Sun 4/12/15

2 RCC for Aux. foundation

8 days

Mon 4/13/15

Tue 4/21/15

3 RCC Tranch Walls

8 days

Wed 4/22/15

Thu 4/30/15

4 RCC Fire Wall

5 days

Sat 5/2/15

Thu 5/7/16

2 days

Thu 5/14/15

Sat 5/16/15

ACDB Room

Duct Banks & Manholes

PACU Unit Pads

Auxiliary Transformers

Site Cleaning & Handing Over