GROUTING RECORD

LOGUNG DAM PROJECT


LOCATION
DATE

:
:

TIME
FROM
(hour : min)

DEPTH
:
TEST LENGTH :
LU VALUE
:

HOLE NO
:
STAGE NO :
SEQUENCE :

UP TO
(hour : min)

MIX PROPORTION
PERIOD

C:W

Water
Cement
(ltr / batch) (kg / batch)

GROUT
MIXED
batch

liter

BALANCE

INJECTED

liter

liter

to

m.
m.

INJECTED
CEMENT

INJECTED
PRESSURE

kg

kg/cm2

APPROVED

CHECKED

SUBMITTED

INSPECTOR

CONSULTANT

CONTRACTOR

REMARKS