SSH HSE Monthly Statistical Report for RE Supervision Sites

Project :

Bid Pack 5A,B -Roads, Site Utilities, Substations, Surface Parking ,Land Scaping and Oasis works

Main Contractor:

Sinohydro Corporation Limited (China) JV. M/s. Copri Co

Location:

SABAH AL- SALEM UNIVERSITY CITY - KUWAIT UNIVERSITY

Month/Year:

February 2016

By:

Naveed

Description

Quantity Surveyor

Position:

Cumulative

Previous

Current Month

from start of

Month

year

General Project HSE Information


Average Number of Employees on Site per Day (SSHI + Contractor)

(47+397) = 444

(47+500) = 547

547

Total Man-hours Worked ( 10 hours per employee x days worked)

102,120

128,195

230,315

Number Environmental Impact Assessments submitted by contractor for

Number of Risk Assessments Submitted by contractor for review

Number of dedicated HSE Staff for Project

Fatalities (FAT)

Lost-time Injuries (LTI)

Number of Lost Workdays

Medical Treatment Cases (MTC) visits to Offsite Clinic or Hospital

First Aid Cases (FAC) seen on site work related

Number of Near Miss Incidents

Number of Property Damage Incidents

Number of Fire Incidents

Number of Environmental incidents

Regulatory Notifications/Prohibition/Penalties (number issued)

Safety Violation Notices (SVN) / relevant to HSE Issued by RE

12

Safety Violation Notices (SVN) / relevant Overdue for Closure (Contractor

review

Lagging Key Performance Indicator (KPI) Monthly Metrics

0
0
0
0
0

12

11
12

12

12

10

19

Number of HSE Induction Training Programs Held

Number of Attendees to HSE Induction

N/A

0
N/A
3
0
5
0
NA
NA

0
0
0
0
15

Does Not Respond in Prescribed Time (i.e. 48 Hours))


Safety Violation Notices (SVN) Closed in prescribed time (closed without
time constrain)
Leading Key Performance Indicator (KPI) Monthly Metrics (Internal)
Number of HSE Meetings Held (not tool box talks) which SSH Attend

Number of HSE Inspections which SSH attend

rd

Number of HSE Audits by either SSH or 3 party

Total HSE Training Hours conducted during the month

Number of Emergency Drills &/or Exercises conducted

Total amount of waste produced and removed from site ( in cubic metres)

NA

Total amount of recycled waste (in cubic metres)

NA

Signature:
April, 2015

N/A
6
0
9
NA
NA

Date: 06 March 2016


Doc Number: QSE01_FRM_009_v2.0_CD

Page 1 of 2

SSH HSE Monthly Statistical Report for RE Supervision Sites

April, 2015

Doc Number: QSE01_FRM_009_v2.0_CD

Page 2 of 2