Professional Documents
Culture Documents
03 Material Takeoff
03 Material Takeoff
COSC 621
2nd Project
3rd Project
4th Project
Drawings
Construction
Method
Contingency
Analysis
Activity
Network
Work
Packages
Activity
Time & Cost
Total
Project Cost
Critical
Path
Material
Takeoff
Total
Project Time
5th Project
Cash Flow
Profile
General
z
z
z
z
z
z
z
z
Site Information
z
z
z
z
z
z
z
Buildings
z
z
z
z
z
z
z
Regulatory Requirements
z
z
z
z
z
Project Breakdown
z
Production activities
z Activities that involve the use of resources such as labor,
material, equipment, or subcontractors
Procurement activities
z Activities that specify the time needed to procure for materials
and/or manufacture equipment that are needed for any
production activity
Management decision activities
z Activities that are related to management decisions such as
special delays or approvals
Hammock activities
z Activities that depend on other activities and are not needed for
themselves, eg. Dewatering that is required as long as
excavation is progressing
Dummy activities
Project Breakdown
z
Division 9: Finishes
Division 10: Specialties
Division 11: Equipment
Division 12: Furnishings
Division 13: Special Construction
Division 14: Conveying Systems
Division 15: Mechanical
Division 16: Electrical
z
z
z
z
z
z
z
z
z
z
02010 Subsurface
Investigation
02050 Demolition
02110 Site Preparation
02140 Dewatering
02150 Shoring and
Underpinning
02160 Excavation Support
Systems
02170 Cofferdams
02200 Earthwork
02300 Tunneling
02350 Piles and Caissons
02450 Railroad Work
z
z
z
z
z
z
z
z
z
z
z
Division 3 - Concrete
z
z
z
z
z
z
z
z
z
z
Division 4 - Masonry
z
z
z
z
z
z
z
04110 Mortar
04150 Masonry Accessories
04200 Unit Masonry
04400 Stone
04500 Masonry Restoration and Cleaning
04550 Refractories
04600 Corrosion Resistant Masonry
Division 5 - Metals
z
z
z
z
z
z
z
z
z
z
z
z
07100 Waterproofing
07150 Damproofing
07190 Vapor and Air Retarders
07200 Insulation
07250 Fireproofing
07300 Shingles and Roofing Tiles
07400 Preformed Roofing Cladding and Siding
07500 Membrane Roofing
07570 Traffic Topping
07600 Flashing and Sheet Metal
07700 Roof Specialties and Accessories
07800 Skylights
07900 Joint Sealers
Division 9 - Finishes
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
Division 10 - Specialties
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
Division 11 - Equipment
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
z
10
Division 12 - Furnishings
z
z
z
z
z
z
z
z
12050 Fabrics
12100 Artwork
12300 Manufactured Casework
12500 Window Treatment
12600 Furniture and Accessories
12670 Rugs and Mats
12700 Multiple Seating
12800 Interior Plants and Planters
z
z
z
z
z
z
z
z
z
z
z
11
14100 Dumbwaiters
14200 Elevators
14300 Moving Stairs and Walks
14400 Lifts
14500 Material Handling Systems
14600 Hoists and Cranes
14700 Turntables
14800 Scaffolding
14900 Transportation Systems
Division 15 - Mechanical
z
z
z
z
z
z
z
z
z
z
z
z
12
Division 16 - Electrical
z
z
z
z
z
z
z
z
z
z
Project Breakdown
Project
WBS
Concrete
Foreman
Area 1
Area 2
Area 3
Beams
Columns
Slabs
Install
Framework
Place
Reinforcement
Pour
Concrete
Control Account
Rebar
Foreman
Formwork
Foreman
Electrical
Mechanical
Civil
Superintendent Superintendent Superintendent
Subcontractor
B
General
Contractor
Subcontractor
A
Project Manager
OBS
13
RS Means
Building Construction Cost Data
z
Division Number/Title
z
(033/Cast-in-Place Concrete)
Line Numbers
z
Master Format
Medium scope
Means
Major
Classification
Means
Individual
Line Number
RS Means
Building Construction Cost Data
z
Description
z
Crew
z
14
Crew
Crew No.
Crew C-14A
1 Carpenter Foreman (out)
16 Carpenters
4 Rodmen (reinf.)
2 Laborers
1 Cement Finisher
1 Equip. Oper. (med)
1 Gas Engine Vibrator
1 Concrete Pump (small)
200 L.H., Daily Totals
Daily
28.45
26.45
29.45
20.65
25.40
27.55
227.60
3,385.60
942.40
330.40
203.20
220.40
37.20
632.80
5,979.60
Cost Per
Labor-Hour
Daily
Bare
Costs
Incl.
O&P
358.40
5,331.20
1,636.80
520.00
303.20
335.20
40.90
696.10
26.55
42.42
3.35
3.69
9,221.80
29.90
46.11
15
Bare Costs
Material : $207
Labor
$26.55 12.804 = $340
Equip.
$3.35 12.804 = $43
Total
$207 + $340 + $43 = $590
= $228
= $ 544
Total
= $820
= $48
16
Earth Work
z
z
z
Slope
Bracing or sheet-piling
Dewatering
Specifications
z
z
z
z
z
z
z
z
17
Soil
z
z
z
Type of soil
Soil borings
Site visitation
z
z
Swell
Shrinkage
10 to 18%
95 to 100%
Loam
15 to 25%
90 to 100%
Dense Clay
20 to 35%
90 to 100%
Solid Rock
40 to 60%
85%
18
= 1,000 cy x 1.3
= 1,300 cy
= 526 cy / 7 cy/load
= 75 loads
19
Earth Work
z
z
z
20
Cross-Section Method
z
Site
Required changes
Required level of accuracy
z
Cross-Section Method
z
z
z
21
Labeling Convention
Proposed Elevation
Cut
Current Elevation
Fill
22
Planned
Elevation
Existing
Elevation
Fill (ft.)
F2
104.9
103.6
1.3
G2
104.5
103.0
1.5
F3
104.0
103.6
0.4
G3
105.0
103.2
1.8
1.3'+1.5'+0.4'+1.8'
2,500 sf
4
= 3,125cf
Fill =
Planned
Elevation
Existing
Elevation
Cut (ft.)
E6
104.0
104.1
0.1
F6
104.0
104.8
0.8
E7
103.6
103.6
0.0
F7
104.2
104.2
0.0
0.1'+0.8'+0.0'+0.0'
2,500sf
4
= 563cf
Cut =
23
24
Fill area
= 15 x 50
= 750sf
Fill area
= .5 x 14 x 50
= 350sf
Total fill area = 750sf + 350sf
= 1,100sf
.3'+.4'+0'+0'
1,100sf
4
= 193cf of fill
.3'+.7'+0'+0'
1,400sf
4
= 350cf of cut
25
Fill at Intersections
1
0.3
0.4
0.7
1.3
1.5
0.4
4
0
1.8
Cut
Pnts
Total
Ave.
Area
0.175
1100
193
0.7
0.3
0.233
287.5
67
0.7
0.8
1.25
2500
3,125
0.5
0.5
0.1
0.8
36,317
Cubic Yards
Shrinkage Factor
Cut at Intersections
1,345
0.95
1,416
1,071
0.3
Pnts
Ave.
Area
0.25
1400
350
0.3
2212.5
664
0.475
2500
1,188
Total
7,453
Cubic Yards
Swell Factor
276
0.25
345
26