Summary of Activities
February 21, 2016

ATTS Monitoring and Advisory


FRCR for the month of January

February 22, 2016

ATTS monitoring and Advisory


PMR with Engr. Jim Bacolod at Cabuyao 1 (Smart Site)
Joint PMR with MJJS at Malitlit, Sta. Rosa (Smart Site)

February 24, 2016

Went to Don Jose Sta. Rosa and Gulod Site to change the Access Point (AP) of
the canopy.
Configured all the AP using its own IP address similar to a router.
Alarms clearing at Bigaa Cabuyao, Laguna because of a router outage.
Fiber testing using OTDR at DLSU STC
Alarms clearing at Sta. Rosa (Labas) due to a failure Access Point of the Canopy.

February 25, 2016

Outage restoration at San Pedro Muntinlupa Boundary Site because of a fiber


break.
Core Break at San Pedro 2 because of the fiber break at San Pedro Muntinlupa.

Noted by:
______________________
Engr. Ruel C. Aspe
Sr. Supervisor | Technical Operations
Access and Transport Wireless Operations
South Luzon | Cluster 8 North Laguna