Dear Engineer,
RE: Water Supply and Sanitation Improvement Works in Mansa and Samfya (Luapula
Province) – Lots 1 and 2
The Contractor wishes to bring to the attention of the Engineer the current challenges along the
sewer network, particularly with regards to connecting the remaining houses to the system. As we
verbally mentioned, there is a lack of existing sewer inspection manholes for many of these
houses within the remaining 480 m of sewer network rehabilitation work.
Most of these houses are located in suburbs and Medium-density compounds. Further, there are
only a few houses with existing inspection chambers which are currently been connected to the
new system, and within the next 10 days the connection work on these houses with existing
manholes will be completed. As a consequence, we will be unable to proceed with the expected
workmanship as there will be no place to work from.
We trust this information is useful and look forward to constructive advice from the Project
Engineer. Should you have any questions or require further information, please do not hesitate to
contact us.
Sincerely,