Republic of the Philippines

Department of Public Works and Highways


Albay 2nd District Engineering Office
RES V Compound
Airport Site, Legazpi City

August 24, 2020

APOLINARIO S. ALVAREZ
Chief Operating Officer
Albay Power and Energy Corporation
Old Albay District, Legazpi City

SUBJECT : Reiteration on the Request for Additional Requirements in


Relation to the Payment for Relocation of Poles

Dear Mr. Alvarez:

Greetings!

This is to reiterate our request for additional requirements we requested with your office on
the following projects we sent on July 06, 2020, May 26, 2020, February 24, 2020, and
February 05, 2020 in reference to the affected utilities of Albay Power and Energy
Corporation by the infrastructure project implemented under this office, to wit:

Seq Project Title Location


.
No.
1. Improvement/ Widening of National Roads, Daang
Maharlika Jct.- Legazpi-Sto. Domingo-Tabaco-Camarines Legazpi City
Sur Bdry. Road, including RROW, K0534+000-K0534+360
2. Improvement/ Widening of National Roads, Daang
Maharlika Jct.- Legazpi-Sto. Domingo-Tabaco-Camarines Legazpi City
Sur Bdry. Road, including RROW, K0534+360-K0535+040
3. Improvement/Asphalt Overlay Along Tahao Road (Imelda Legazpi City
Roces Avenue)
4. Construction/ Improvement of Access Roads leading to
declared Tourism Destinations-Access Road leading to Daraga, Albay
Mayon Southeast Quadrant Road, Budiao-Bañadero,
Daraga, Albay
5. Construction/ Improvement of Access Roads Leading to
Airports – Guicadale Road Network, Iluluan-Manawan Road Pinaric, Albay
Section, Camalig, Albay
6. Construction/ Improvement of Access Roads Leading to
Airports – Guicadale Road Network, Iluluan-Manawan Road Camalig, Albay
Section, Camalig, Albay
7. Construction/ Improvement of Access Roads Leading to
Airports – Guicadale Road Network, Taloto-Mabunga Road Camalig, Albay
Section, Camalig, Albay
8. Concreting/ Rehabilitation of Taplacon – Quitinday Road Camalig, Albay
Republic of the Philippines
Department of Public Works and Highways
Albay 2nd District Engineering Office
RES V Compound
Airport Site, Legazpi City
9. Construction/ Rehabilitation of Palanog - Quibongbongan Guinobatan, Albay
Road

As per our letter preceding this, we informed you that we shall be returning the fund
allotted for the said relocation in case there is a failure to submit the requested
requirements. In view hereof, in order to finalize the procedure, we would like to request an
audience with you in relation to the above-mentioned on August 25, 2020, at your office at
1:00 pm.

We are looking forward to your positive response on the matter.

Very truly yours,

DANILO J. VILLA, JR.


District Engineer