I.

1.1
a.

SAFETY & SECURITY


HSE
The number of manpower having successfully completed Safety Induction Course and
updated are as follows:
PT Deluge Engineering Construction
: 11
PT Surabaya Prakarsa Fire Service (Fire Alarm)
:8
PT Piping System Indonesia (Aboveground)
: 25
PT Valvtrol Global Flowsystem (Underground)
: 16
Total Manpower
: 60

1.2

Manpower (PT Deluge Site Project Management)


a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
k)

II.

III.
a.
b.

Soh Kee Hong


Eko Kurniawan
Ismail
Amin
Limhot
Angga
Aditya
Rahmat
Lito Nosa
Joey
Rahman

(Project Manager Ph. 0812 9605 0510)


(Construction Manager Ph. 0812 9396 1612)
(Doc, QA/QC Control - Ph. 0821 1062 4212)
(Safety Coordinator Ph. 0813 6844 1153)
(Draftsman Ph. 0813 1010 7275)
(Storeman Ph. 081 286 45 3134)
(Site Enginer Ph. 085659636791)
(Draftsman Ph. 085788087472)
(Design Manager)
(Asst Design Manager)
(Fire Alarm Engineer)

SITE FACILITIES
- Sandblasting activities is on going at PT. Deluge Site Office Workshop.
QA/ QC
PT. Deluge re-submitted Hydrotest Procedure for Fire Fighting Under Ground on
February, 26th 2016.
4 Welder passed Visual Test (RT will be do on Monday, 29th Feb 2016 at 22.00 oclock)

PROGRESS
Engineering Issues
Drawing Submission
- Attached
b.
Document Submission
- Attached
IV.
1.
a.

2.

3.

Material Deliveries
- 3 Unit of Dust Suppression pumps will delivered temporary to PTCL MM2100
Warehouse on Monday, 29th Feb 2016.
Time Schedule

Cikarang Power Station Project


Babelan, Bekasi, Jakarta, Indonesia