Professional Documents
Culture Documents
1.1
a.
1.2
II.
III.
a.
b.
SITE FACILITIES
- Sandblasting activities is on going at PT. Deluge Site Office Workshop.
QA/ QC
PT. Deluge re-submitted Hydrotest Procedure for Fire Fighting Under Ground on
February, 26th 2016.
4 Welder passed Visual Test (RT will be do on Monday, 29th Feb 2016 at 22.00 oclock)
PROGRESS
Engineering Issues
Drawing Submission
- Attached
b.
Document Submission
- Attached
IV.
1.
a.
2.
3.
Material Deliveries
- 3 Unit of Dust Suppression pumps will delivered temporary to PTCL MM2100
Warehouse on Monday, 29th Feb 2016.
Time Schedule