UNDERGROUND HDPE PIPE HYDROTEST CHART

1. Pre-Test Chart

20 Bar

15 Bar Test Pressure (Example)

10 Bar

5 Bar

0 Bar

0 1 2 3 4 5 6 7 8 9 10 11 12 Hour

Filling #1 1 Hr 30 min Filling #2 1 Hr 30 min Filling #3 1 Hr Holding Time and maintained to restore the test pressure 6 Hrs

*Water filling can not more than 2 l/s.


*Pre-Test pressure is depend to the pipe temperature and refer to chart in the attached procedure.
*During 6 hours pre-test periode, pressure must be maintained to the test pressure.
*This chart is for pipe with length more than 100 meter.

2. Main Test Chart

20 Bar

15 Bar
Test Pressure (Example) x 0.85
12.75 Bar
10 Bar

5 Bar

0 Bar

0 1 2 3 4 5 6 7 8 9 10 11 12 Hour

Holding Time Main Test 6 Hrs Release 30 min Release pressure to 1 bar

*Main Test pressure is depend to the pipe temperature and refer to chart in the attached procedure.
*This chart is for pipe with length more than 100 meter.