Professional Documents
Culture Documents
whatispiping.com/steam-blowing-part-1/
Steam blowing is one of the initial cleaning operations before starting any power plant or
steam lines. Steam Blowing of MS lines, CRH, HRH, SH, RH, HP & LP bypass pipelines
of the turbine are carried out in order to remove welding slag, weld bead deposits, loose
foreign materials, iron pieces, rust, etc. from the system, generated during manufacturing,
transportation & erection prior to turbine operation. The cleaning is accomplished by
subjecting the piping systems to heating, blowing steam, and cooling cycles in sufficient
number and duration until clean steam is obtained.
Thermal shock
Removal force of steam
Cleaning force of steam
CFR (Cleaning Force Ratio) is also known as Cleaning Factor or CF. CFR is an industry-
accepted factor that determines the required dynamic pressure. CFR in steam blowing
can be defined as the ratio of required dynamic pressure for cleaning to maximum
dynamic pressure experienced during system operation.
1/11
Cleaning Force required (CFR) or distribution Factor
2/11
Flow nozzle, control valves, and NRV flaps wherever applicable should be not
erected before steam blowing and suitable spool pieces are erected. Strainers in
the path should be removed.
Required number of Target Plates and holders made available
3/11
Acid cleaning will be followed by PASSIVATION so that the uniform protective
coating of GAMMA FERRIC OXIDE is formed on the metal surface and
corrosion/oxidation damage to the metal surface is prevented and continue during
normal operation by dosing oxygen. The gamma ferric Oxide formed by using the
chemical 1-2 % sodium Nitrite(NaNO2)
PUFFING METHOD
PURGING METHOD / CONTINUOUS BLOW METHOD
Procedure: Raise the boiler pressure to a pre-determined value (40-60 kg/cm2), shut off
firing, and at the same time open the quick opening valve(EOTV), thus allowing the steam
to escape to atm. with high velocity carrying with it the loose debris.
The Pressure drop allowed in the drum is limited to the corresponding saturation temp.
change of 40 OC.
Stage-1(a):
Advertisements
SH, MSL, ESV, temporary lines from ESV to EOTV, EOTV to CRH line, CRH lines
up to boiler end with the temporary exhaust pipe.
Tap-off lines from CRH to deaerator, auxiliary PRDS, HP heater 6a & 6b, gland
sealing, etc. shall remain closed/isolated.
Stage 1a endpoint will be concluded by observing the indents on the target plate.
Stage- 1(b):
4/11
Stage-2(a):
Stage- 2(b):
5/11
Stage-3:
All auxiliary steam lines will be steam blown by the continuous blowing method
Stage-4:
The following Aux steam lines, connected to the deaerator are steam blown using
auxiliary steam from the Auxiliary PRDS header.
4a)PRDS to Deaerator.
4b)Extraction 4 to
4c) PRDS to Gland steam header
6/11
Dynamic steam pressure = 3.5 MPa
MS temp = 420(not to exceed)
HRH temp = 480( not to exceed)
Steam flow = 845 TPH
Corresponding Drum pr. = 40 Ksc
Furnace load ≈ 39%
Preliminary Cleaning
PURPOSE-
Primary cleaning out sundries and bulky grain deposited in the RH and main steam
system
To ensure the fastness of supports and hangers with proper expansion
Know well about the operation property of the oil-burning system, condensate water,
and feed water systems
7/11
SH & RH desuperheater water system also cleaned
8/11
Debris Filter
9/11
Less time is required to normalize the system for final light-up to synchronization
This reduces the reactionary forces on the temporary pipes
Stresses on the boiler system are lower
— More time is required for complete steam — Less time required for
blowing due to stage-wise blowing(8-10 completion (3-4 days)
days) — Less time is required
as only
— More
time is required for stage-wise valves are to be opened for
temporary pipe erection and shifting of the different systems
blowing device — Minimum 02 nos.
of mill
— System normalization
time after steam during steam blowing is a challenge
blowing is more — System normalization time after
— Silencer use
is optional steam blowing is less.
10/11
11/11