You are on page 1of 517

SUBESTIMATE:CONSTRUCTIONOFSEPTICTANK

NAME OF THE WORK :- CONSTRUCTION OF PARAMANENT GOVT. POLYTECHNIC COLLEGE FOR WOMEN
JOGIPET (V), ANDOLE (M) IN MEDAK DIST
Construction of Septic Tank of size 8.90 x 2.70 x 2.10Mt (Clear Size) and
1985 )
Sl.No Description of work
1

No.

Measurements

Qty

Septic Tank
for Soak pit

1
1

X
X

1
1

10.20
3.00

3.90
3.00

2.20
1.20

For bottom of
septic tank

10.20

3.90

0.10

8.90

2.70

0.08

1.92
2.00 Cum

6509.35 1Cum

Random Rubble stone masonry, in CM (1:8) prop: (Cement: Sand) using Hard blasted Granite stones from
approved quarry including cost and conveyance of all materials like Granite stones, cement, sand, water,
etc., to site sales & other taxes on all materials, all operational, incidental, and labour charges such as
cutting stones to required size and shape, mixing of cement mortar, constructing masonry, curing etc.,
complete but excluding seigniorage charges for finished item of work for foundation and basement (APSS
No. 601 & 615)
Alround
1
X
1
25.00 0.60
1.20
18.00
X

25.00

0.45

1.35

15.19

Total

33.19

Say

34.00 Cum

2680.45 Cum

Construction of 50.8mm thick RCM Baffle wall with 2.267 Kg steel and rabit wire mesh in CM (1:3) prop: with
fine rendering in neat cement in septic tank including cost and convenyance of all materials to site,
seigonarage charges sales and othe taxes on all materials , and all labour charges etc., complete for finished
item of work.
For baffle walls

3.00 -

0.6

3.60 Sqmt

286.15 1Sqmt

Construction of Perforated Dry Brick Masonry without using CM and keeping vertical dry joints of 15 to 20mm
as directed by the Engineer in Charge including cost and conveyance of all amterials to site seignorage
charges, sales and other taxes, all labour charges etc., complete item of work for Soak Pit.
1

S Tank

3388.15 1Cum

Plain Cement Concrete corresponding to M15 grade as per IS 456 equivalent to (1:2:4) proportion nominal
mix (cement: fine aggregate: Coarse aggregate) using 20mm size Hard Blasted Granite (IS383, 1970)
Machine Crushed graded metal from approved quarry including cost and conveyance of all materials like
cement, sand, coarse aggregate, water etc. to site, including sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing, laying, curing concrete, etc., complete but
excluding seigniorage charges for finished item of work (APSS No. 402)

Per

3.98
4.00 Cum

Say

Rate

87.52 Cum
10.80
98.32
100.00 Cum
122.45 1Cum
Plain Cement Concrete corresponding to M5 grade as per IS 456 equivalent to (1:5:10) proportion nominal
mix (cement: fine aggregate: Coarse aggregate) using 40mm size Hard Blasted Granite (IS383, 1970) metal
from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate,
water etc. to site, including sales & other taxes on all materials, all operational, incidental, and labour
charges such as mixing, laying and ramming concrete in layers in position not exceeding 15cm, finishing top
surface, curing concrete, etc., complete but excluding seigniorage chargesfor finished item of work for
Foundations and Flooring Bed (APSS No. 402)

For bottom of
septic tank
4

Unit

L
B
D
Earth work excavation and depositing on bank (Manual means) with initial lead of 10m and initial lift of 3m in
Loamy & Clayey Soils like BC Soils, Red Earth & Ordinary Gravelly Soils ( SS 20-B) including all operational
incidental labour charges such as shoring, strutting, sheeting, planking and dewatering including cost of hire
charges of T & P, labour charges etc., complete for finished item of work excluding seignerage charges and
dewatering charges etc., complete for Septic tank soak pit and sump.(APSS No. 308)

Say
3

soak pit of 3.00 x 3.00 Mt. size ( IS 2470 -

3.00

0.12

1.50

2.16 Cum

P No 1

OR Say
2.25 Cum
3977.47 Cum
Providing impervious coat over RCC roof slab to required slopes with CM (1:3) prop. 20mm thick (average)
mixed with water proofing compound manufactured by reputed manufacturers as approved by Engineer-incharge at 1Kg/bag of cement, laid over roof slab when it is green, finished smooth with a floating coat of neat
cement and thread lining at regular intervals of 45cmx45cm including cost and conveyance of all materials
like cement, sand, water proofing compound, water etc., to site, sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing mortar, laying, rounding off at junctions of wall and
slab, rendering smooth with thread lining, curing, lift charges, etc., complete but excluding seigniorage
charges for finished item of work (APSS No. 901 & 903).
Long walls
Short walls
Bottom of septic
tank

1
1
1

X
X
X

2
4
1

8.90
2.70
8.90

2.20
2.20
2.70 Say

328.75 1Sqmt

Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard
blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimum
quantity of 350 kgs. of cement per 1 cum of concrete including cost and conveyance of all materials like
cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost of all materials including
centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross members
etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding
cost of steel and its fabrication charges but excluding seigniorage charges for finished item of work (APSS
No. 402 & 403) for 125 mm thick slab
125mm thick slab

9.90

3.60 Say

39.16
23.76
24.03
86.95
87.00 Sqmt

35.64
36.00 Sqmt

1066.20 1Sqmt

Providing High Yield Strength Deformed (HYSD) steel bars (Fe 415 grade as per IS 1786-1985) of 8mm to
40mm diameters, cutting, bending, to required sizes and shapes placing in position with cover blocks of
approved size and binding wire of 20SWG, forming grills for reinforcement work as per approved designs
and drawings including cost and conveyance of bars from approved sources to site of work, including cost
and conveyance of binding wire, cover blocks, chairs, overlaps, spacers, dowels, wastage etc., and all
operational, incidental, and labour charges such as cutting, bending, placing in position, tying etc., and sales
& other taxes,on cost of all materials complete for finished item of work (APSS No.126)

36*0.125*110 =
1
X
1
0.5
0.50 MT
58571.30
1 MT
495 Kgs
10 Supply and fixing of 100 mm dia CI Vent pipe of 3 mts length double socket fitted with AC cowl and mosquito
proof wire mesh including cost and conveyance of all materials to site and labour charges for placing and
fixing in position etc., complete for finished item of work.
11

1
X
1
1 No.
2561.60 Each
Supply & Fixing of 22" dia RCC Cover for manhole with nominal reinforecement 3" thick with hooks for lfifting
including cost and conveyance of all materials, labour charges etc., complete for finished tiem of work
1
X
2
2 Nos.
803.70 Each

12 Supply and Fixing of CI Steps for Septic Tank / Manhole complete for finished item of work including cost and
conveyance of all materials to site, all labour charges, sales and other taxes on all materials etc., complete
for finished item of work.
1

5 Nos.

70.70 Each
TOTAL

#REF!

S Tank

Dy. Executive Engineer

Asst. Executive Engineer

APEWIDC, MADANAPALLI

APEWIDC, KUPPAM

P No 2

Superintending Engineer
APEWIDC, KADAPA

S Tank

P No 3

CONSTRUCTIONOFSEPTICTANK

OF PARAMANENT GOVT. POLYTECHNIC COLLEGE FOR WOMEN AT


T (V), ANDOLE (M) IN MEDAK DIST

10Mt (Clear Size) and

soak pit of 3.00 x 3.00 Mt. size ( IS 2470 Amount

12245.00

13553.00

13019.00

91135.00

1030.00

S Tank

P No 4

8949.00

28601.00

38383.00

29286.00

2562.00

1607.00

354.00
240724.00

S Tank

P No 5

S Tank

P No 6

Name of the work

Section

Sub - Division

Division

Circle

ABOUT ESTIMATE
Construction of Govt. Degree College at KUPPAM(V) of KUPPAM (M)
CHITTOOR District
Asst. Engineer (APEWIDC)
Section : KUPPAM
Dy. Executive Engineer (APEWIDC)
Sub-Division : CHITTOOR
Executive Engineer (APEWIDC)
Division : CHITTOOR
Superintending Engineer (APEWIDC)
Circle : KADAPA

WORKING ESTIMATE
NAME OF THE WORK: C/O HOSTEL BUILDING AT APSWRSC(B), WARDANNAPET AT MADIKONDA(V) OF HANAMKO
WARANGAL DIST.
SUB ESTIMATE: OLD DORMITARY
SNo
Description of work
No
L
B
D Qty
Rate
1 Earth work excavation and depositing on bank with initial lead of 10m and initial lift
of 3m in Loamy & Clayey Soils like BC Soils, Red Earth & Ordinary Gravelly Soils
( SS 20-B) including all operational incidental labour charges such as shoring,
strutting, sheeting, planking and dewatering including cost of hire charges of T & P,
labour charges etc., complete for finished item of work including seignerage charges
excluding dewatering charges etc., complete for Foundation of Building.(APSS No.
308)
MB. No.326/A/MD, Pg. No.1 to 4

For Foundation pits


A6/F5
A8/F4
A9/F4
A11/F4
A16/F4
A18/F4
A19/F4
A21/F5
B1/F3
B3/F1
B4/F8
B23/F8
B24/F1
B26/F3
C6/F3
C8/F3
C9/F3
C11/F3
C16/F3
C18/F3
C19/F3
C21/F3
D1,E1/CF1
D3,E3/CF1
D4,E4/CF2
D23,E23/CF2
D24,E24/CF1
D26,E26/CF1
F12,G11/CF3
F15,G16/CF3
G6/F3
G8/F3
G9/F3
G18/F3
G19/F3
G21/F3
H1/F2
H3/F3
H4/F6
H23/F6
H24/F3
H26/F2
J1/F3
J3/F3
J4/F7

GF-AHDC

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

Page 8 of 517

2.10
2.20
2.20
2.20
2.20
2.20
2.20
2.10
2.35
2.60
1.60
1.60
2.60
2.35
2.35
2.35
2.35
2.35
2.35
2.35
2.35
2.35
3.45
3.45
2.90
2.90
3.45
3.45
2.50
2.50
2.35
2.35
2.35
2.35
2.35
2.35
2.45
2.35
1.95
1.95
2.35
2.45
2.35
2.35
1.75

2.10
2.20
2.20
2.20
2.20
2.20
2.20
2.10
2.35
2.60
1.60
1.60
2.60
2.35
2.35
2.35
2.35
2.35
2.35
2.35
2.35
2.35
3.45
3.45
2.90
2.90
3.45
3.45
2.10
2.10
2.35
2.35
2.35
2.35
2.35
2.35
2.45
2.35
1.95
1.95
2.35
2.45
2.35
2.35
1.75

1.90
1.75
1.76
1.78
1.92
1.68
1.85
1.75
1.68
1.71
1.65
1.65
1.68
1.70
1.72
1.82
1.69
1.71
1.72
1.75
1.76
1.73
1.79
1.95
1.70
1.74
1.69
1.73
1.74
1.79
1.69
1.71
1.80
1.82
1.83
1.82
1.79
1.82
1.80
2.02
1.89
1.75
1.80
1.92
1.85

8.37
8.47
8.51
8.61
9.29
8.13
8.95
7.71
9.27
11.55
4.22
4.22
11.35
9.38
9.49
10.05
9.33
9.44
9.49
9.66
9.71
9.55
21.30
23.20
14.29
14.63
20.11
20.59
9.13
9.39
9.33
9.44
9.94
10.05
10.10
10.05
10.74
10.05
6.84
7.68
10.43
10.50
9.94
10.60
5.66

J5/F6
J22/F6
J23/F7
J24/F3
J26/F2
K6/FR1
K8/F3
K9/F3
K11/F1
K16/F1
K18/F3
K19/F3
K21/FR1
L1/F5
L3/F2
L4/F6
L23/F6
L24/F2
L26/F5
M2/F5
M4/F5
M6/FR2
M8/F2
M10/F3
M13/F2
M15/F2
M17/F3
M20/F2
M22/FR2
M23/F5
M25/F5
N2/F7
N4/F7
N23/F7
N25/F7
P6/F5
P7/F3
P10/F3
P13/F4
P14/F4
P17/F3
P20/F3
P21/F5

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

1.95
1.95
1.75
2.35
2.45
1.80
2.35
2.35
2.60
2.60
2.35
2.35
1.80
2.10
2.45
1.95
1.95
2.45
2.10
2.10
2.10
2.10
2.45
2.35
2.45
2.45
2.35
2.45
2.10
2.10
2.10
1.75
1.75
1.75
1.75
2.10
2.35
2.35
2.20
2.20
2.35
2.35
2.10

1.95
1.95
1.75
2.35
2.45
2.85
2.35
2.35
2.60
2.60
2.35
2.35
2.85
2.10
2.45
1.95
1.95
2.45
2.10
2.10
2.10
3.55
2.45
2.35
2.45
2.45
2.35
2.45
3.55
2.10
2.10
1.75
1.75
1.75
1.75
2.10
2.35
2.35
2.20
2.20
2.35
2.35
2.10

1.82
1.92
1.85
1.86
1.88
1.83
1.96
1.92
1.85
1.87
1.89
1.85
1.86
1.87
1.89
1.86
1.88
1.85
1.79
1.82
1.78
1.79
1.80
1.84
1.81
1.86
1.80
1.79
1.76
1.80
1.85
1.82
1.79
1.80
1.85
1.83
1.82
1.79
1.80
1.84
1.86
1.82
1.84

6.92
7.30
5.66
10.27
11.28
9.38
10.82
10.60
12.50
12.64
10.43
10.21
9.54
8.24
11.34
7.07
7.14
11.10
7.89
8.02
7.84
13.34
10.80
10.16
10.86
11.16
9.94
10.74
13.12
7.93
8.15
5.57
5.48
5.51
5.66
8.07
10.05
9.88
8.71
8.90
10.27
10.05
8.11
867.39

MB. No.326/A/MD, Pg. No.6 to 9


G1/F1
F1/F1
E1/F1
D1/F1
B1/F1
I2/F1
G2/F1
F2/F3

1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x

1
1
1
1
1
1
1
1

1.95
1.95
1.95
1.95
1.95
1.95
1.95
2.35

1.95
1.95
1.95
1.95
1.95
1.95
1.95
2.35

1.50
1.60
1.56
1.66
1.64
1.39
1.46
1.46

5.70
6.06
5.91
6.29
6.21
5.26
5.53
8.03

E2/F3
D2/F3
B2/F2
J3/F1
H3/F4
G3/F3

1
1
1
1
1
1

x
x
x
x
x
x

1
1
1
1
1
1

2.35
2.35
2.15
1.95
2.55
2.35

2.35
2.35
2.15
1.95
2.55
2.35

1.63
1.63
1.50
1.47
1.63
1.56

8.97
8.97
6.91
5.57
10.56
8.58

GF-AHDC

Page 9 of 517

F3/F2
E4/F2
D4/F2
B4/F1
E5/F2
C5/F2
J6/F3
H6/F3
G6/RF1
F6/F3
J7/F2
I7/RF1
G7/RF1
F7/F3
E7/F3
C7/F3
B7/F2
J8/F2
H8/F4
G8/F5
E8/F4
C8/F2
B8/F1
I9/F1
G9/F2
F9/F2
E9/F2
D9/F2
B9/F1
I10/F5
G10/F5

GF-AHDC

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

2.15
2.15
2.15
1.95
2.15
2.15
2.35
2.35
2.25
2.35
2.15
2.25
2.25
2.35
2.35
2.35
2.15
2.15
2.55
2.75
2.55
2.15
1.95
1.95
2.15
2.15
2.15
2.15
1.95
2.75
2.75

Page 10 of 517

2.15
2.15
2.15
1.95
2.15
2.15
2.35
2.35
2.95
2.35
2.15
2.95
2.95
2.35
2.35
2.35
2.15
2.15
2.55
2.75
2.55
2.15
1.95
1.95
2.15
2.15
2.15
2.15
1.95
2.75
2.75

1.44
1.88
1.85
1.76
1.82
1.83
1.31
1.67
1.77
1.86
1.79
1.68
1.83
1.98
1.98
2.01
1.92
1.68
1.63
1.70
1.78
1.98
2.08
1.93
2.08
2.21
2.15
2.26
2.33
1.68
1.97

6.63
8.66
8.52
6.67
8.38
8.43
7.20
9.19
11.71
10.24
8.25
11.11
12.11
10.90
10.90
11.07
8.85
7.74
10.56
12.85
11.54
9.12
7.89
7.31
9.59
10.19
9.91
10.42
8.84
12.70
14.89

F10/F3
E10/F6
B10/F5
I11/F5
G11/F5
F11/F3
E11/F6
B11/F5
I12/F1
J13/F2
H13/F4
J14/F2
I14/RF1
G14/RF1
F14/F3
E14/F3
C14/F3
B14/F2
J15/F3
H15/F3
G15/RF1
F15/F3
E16/F2
C16/F2
E17/F2
D17/F2
B17/F1
J18/F1
H18/F4
G18/F3
F18/F2
I19/F1
G19/F1
F19/F3
E19/F3
D19/F3
B19/F2
I20/F1
G20/F1
F20/F1
E20/F1
D20/F1
B20/F1
To be done
A10/F7
A11/F7
G12/F2
F12/F2
E12/F2
D12/F2
B12/F1
G13/F5
E13/F4
C13/F2
B13/F1
For Foundation of External Walls
To be done

B1-B2
B2-B4

GF-AHDC

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

2.35
2.95
2.75
2.75
2.75
2.35
2.95
2.75
1.95
2.15
2.55
2.15
2.25
2.25
2.35
2.35
2.35
2.15
2.35
2.35
2.25
2.35
2.15
2.15
2.15
2.15
1.95
1.95
2.55
2.35
2.15
1.95
1.95
2.35
2.35
2.35
2.15
1.95
1.95
1.95
1.95
1.95
1.95

2.35
2.95
2.75
2.75
2.75
2.35
2.95
2.75
1.95
2.15
2.55
2.15
2.95
2.95
2.35
2.35
2.35
2.15
2.35
2.35
2.95
2.35
2.15
2.15
2.15
2.15
1.95
1.95
2.55
2.35
2.15
1.95
1.95
2.35
2.35
2.35
2.15
1.95
1.95
1.95
1.95
1.95
1.95

2.04
1.93
1.66
2.10
2.25
2.25
2.25
2.15
2.10
2.10
2.25
2.05
1.90
1.95
2.10
2.30
2.65
2.70
2.00
1.92
2.05
2.20
2.40
2.55
2.40
2.50
2.65
2.30
2.35
2.40
2.45
1.79
1.93
2.02
2.23
2.20
2.42
1.99
2.01
1.95
2.11
1.90
2.13

11.23
16.79
12.55
15.88
17.01
12.42
19.58
16.25
7.98
9.70
14.63
9.47
12.61
12.94
11.59
12.70
14.63
12.48
11.04
10.60
13.60
12.14
11.09
11.78
11.09
11.55
10.07
8.74
15.28
13.25
11.32
6.78
7.31
11.12
12.29
12.12
11.16
7.54
7.62
7.39
8.00
7.20
8.08
899.52

1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x

1
1
1
1
1
1
1
1
1
1
1

1.55
1.55
2.15
2.15
2.15
2.15
1.95
2.75
2.55
2.15
1.95

1.55
1.55
2.15
2.15
2.15
2.15
1.95
2.75
2.55
2.15
1.95

2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00
2.00

4.80
4.80
9.24
9.24
9.24
9.24
7.60
15.12
13.00
9.24
7.60

1
1

x
x

1
1

3.18
3.18

0.60
0.60

0.75
0.75

1.43
1.43

Page 11 of 517

B7-B8
B9-B10
B10-B11
B11-B12
B13-B14
B17-B19
B19-B20
C6-C7
C14-C16
E1-E1'
E4-E5
E8-E9
E12-E13
E16-E17
E20'-E20
F1-F1'
F2-F3
F18-F19
G6-G7
G8-G9
G12-G13
G14-G15
I1-I2
I9-I10
I10-I11
I11-I12
I19-I20
J3-J6
J7-J8
J13-J14
J15-J18
B1-D1
D1-E1
F1-G1
G1-I1
E1'-F1'
F2-G2
G2-I2
F3-G3
G3-H3
H3-J3
B4-D4
D4-E4
C5-E5
G6-H6
H6-J6
B7-C7
C7-E7
G7-H7
H7-J7
B8-D8
D8-E8
G8-H8
H8-J8
B9-D9
D9-E9
G9-I9
B12-D12
D12-E12
G12-I12

GF-AHDC

1
1
1
1
1
1
1
1
1
0
1
1
1
1
0
0
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
X
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

3.18
2.98
2.48
2.98
3.18
3.18
3.18
0.01
0.01
-0.02
0.08
0.88
0.88
0.08
-0.02
-0.02
0.99
0.99
0.01
0.78
0.78
0.01
3.28
2.88
2.48
2.88
3.28
3.11
3.08
3.08
3.11
2.56
1.75
1.56
2.75
0.78
1.66
2.75
1.56
1.95
1.66
2.46
1.85
3.12
2.05
1.56
2.26
2.32
1.35
1.76
2.46
1.64
1.65
1.96
2.46
1.85
2.65
2.46
1.85
2.65

Page 12 of 517

0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60

0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75

1.43
1.34
1.11
1.34
1.43
1.43
1.43
0.00
0.00
0.00
0.03
0.39
0.39
0.03
0.00
0.00
0.44
0.44
0.00
0.35
0.35
0.00
1.47
1.29
1.11
1.29
1.47
1.39
1.38
1.38
1.39
1.14
0.78
0.69
1.23
0.35
0.74
1.23
0.69
0.87
0.74
1.10
0.83
1.40
0.92
0.70
1.01
1.04
0.60
0.78
1.10
0.73
0.74
0.87
1.10
0.83
1.19
1.10
0.83
1.19

B13-D13
D13-E13
G13-H13
H13-J13
B14-C14
C14-E14
G14-H14
H14-J14
G15-H15
H15-J15
C16-E16
B17-D17
D17-E17
F18-G18
G18-H18
H18-J18
F19-G19
G19-I19
B20-D20
D20-E20
E20'-F20'
F20-G20
G20-I20

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
X

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

2.46
1.64
1.65
1.96
2.26
2.32
1.35
1.76
2.05
1.56
3.12
2.46
1.85
1.56
1.95
1.66
1.66
2.75
2.56
1.75
0.78
1.56
2.75

0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60

0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75

1.10
0.73
0.74
0.87
1.01
1.04
0.60
0.78
0.92
0.70
1.40
1.10
0.83
0.69
0.87
0.74
0.74
1.23
1.14
0.78
0.35
0.69
1.23

172.88
1,939.79 Cum
2

#REF!

Plain Cement Concrete corresponding to M7.5 grade as per IS 456 equivalent to


(1:4:8) proportion nominal mix (cement: fine aggregate: Coarse aggregate) using
40mm size Hard Blasted Granite (IS383, 1970) metal from approved quarry
including cost and conveyance of all materials like cement, sand, coarse aggregate,
water etc. to site, including seigniorage charges, sales & other taxes on all materials,
all operational, incidental, and labour charges such as mixing, laying and ramming
concrete in layers in position not exceeding 15cm, finishing top surface, curing
concrete, etc., complete for finished item of work for Foundations (APSS No. 402)

MB. No.326/A/MD, Pg. No.10

In F1-Footings
In F2-Footings
In F3-Footings
In F4-Footings
In F5-Footings
In F6-Footings
In RF1-Footings

23

1.95

1.95

0.15

13.12

1
1
1
1
1
1

x
x

23
22
5
7
2
6

2.15
2.35
2.55
2.75
2.95
2.25

2.15
2.35
2.55
2.75
2.95
2.95

0.15
0.15
0.15
0.15
0.15
0.15

15.95
18.22
4.88
7.94
2.61
5.97
68.69

1
1
1
1
1

x
x
x
x
x

2
5
1
1
2

1.95
2.15
2.55
2.75
1.40

1.95
2.15
2.55
2.75
1.4

0.15
0.15
0.15
0.15
0.15

1.14
3.46
0.97
1.13
0.58

To be done

In F1-Footings
In F2-Footings
In F4-Footings
In F5-Footings
In F7-Footings

7.28
75.97 Cum

GF-AHDC

Page 13 of 517

#REF!

Plain Cement Concrete corresponding to M5 grade as per IS 456 equivalent to


(1:5:10) proportion nominal mix (cement: fine aggregate: Coarse aggregate) using
40mm size Hard Blasted Granite (IS383, 1970) metal from approved quarry
including cost and conveyance of all materials like cement, sand, coarse aggregate,
water etc. to site, including seigniorage charges, sales & other taxes on all materials,
all operational, incidental, and labour charges such as mixing, laying and ramming
concrete in layers in position not exceeding 15cm, finishing top surface, curing
concrete, etc., complete for finished item of work for Foundations (APSS No. 402)

For External RR Masonry (outer grid beams)


To be done

B1-B2
B2-B4
B7-B8
B9-B10
B10-B11
B11-B12
B13-B14
B17-B19
B19-B20
C5-C7
C14-C16
E1-E1'
E4-E5
E8-E9
E12-E13
E16-E17
E20'-E20
F1-F1'
F2-F3
F18-F19
F20'-F20
G6-G7
G8-G9
G12-G13
G14-G15
I1-I2
I9-I10
I10-I11
I11-I12
I19-I20
J3-J6
J7-J8
J13-J14
J15-J18
B1-D1
D1-E1
F1-G1
G1-I1
E1'-F1'
F2-G2
G2-I2
F3-G3
G3-H3
H3-J3
B4-D4
D4-E4
C5-E5
G6-H6
H6-J6

GF-AHDC

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
X
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

4.90
4.90
4.86
4.56
5.00
4.63
4.86
4.93
4.86
3.07
3.07
0.73
1.93
3.00
3.00
1.93
0.73
0.73
3.01
3.01
0.73
2.03
3.00
3.00
2.03
4.86
4.86
4.86
4.86
4.86
4.89
4.93
4.93
4.89
3.87
3.29
3.06
3.95
2.50
2.91
4.10
3.21
3.37
3.59
3.87
3.14
4.00
3.22
3.59

Page 14 of 517

0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60

0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15

0.44
0.44
0.44
0.41
0.45
0.42
0.44
0.44
0.44
0.28
0.28
0.07
0.17
0.27
0.27
0.17
0.07
0.07
0.27
0.27
0.07
0.18
0.27
0.27
0.18
0.44
0.44
0.44
0.44
0.44
0.44
0.44
0.44
0.44
0.35
0.30
0.27
0.36
0.23
0.26
0.37
0.29
0.30
0.32
0.35
0.28
0.36
0.29
0.32

B7-C7
C7-E7
G7-H7
H7-J7
B8-D8
C8-E8
G8-H8
H8-J8
B9-D9
D9-E9
G9-I9
B12-D12
D12-E12
G12-I12
B13-C13
C13-E13
G13-H13
H13-J13
B14-C14
C14-E14
G14-H14
H14-J14
G15-H15
H15-J15
C16-E16
B17-D17
D17-E17
F18-G18
G18-H18
H18-J18
F19-G19
G19-I19
B20-D20
D20-E20
E20'-F20'
F20-G20
G20-I20
Under Internal Plinth beams
A10-A11
C7-C8,C13-C14
D1-D2,D2-D4,D9-D10,D11-D12,D17D19,D19-D20.
E1-E2,E2-E4.E7-E8,
E9E10,E10-E11,E11-E12,
E13E14,E17-E19,E19-E20.

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
X

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

3.00
4.00
3.22
3.59
3.00
4.00
3.22
3.59
3.87
3.14
3.95
3.87
3.14
3.95
3.59
3.00
4.00
3.22
3.00
4.00
3.22
3.59
3.22
4.00
4.00
4.00
3.69
3.21
3.37
3.59
2.91
4.10
3.87
3.29
3.06
3.95
2.50

0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60

0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15

0.27
0.36
0.29
0.32
0.27
0.36
0.29
0.32
0.35
0.28
0.36
0.35
0.28
0.36
0.32
0.27
0.36
0.29
0.27
0.36
0.29
0.32
0.29
0.36
0.36
0.36
0.33
0.29
0.30
0.32
0.26
0.37
0.35
0.30
0.27
0.36
0.23

1
1
1

X
X
X

1
2
6

5.00
4.56
5.23

0.45
0.45
0.45

0.15
0.15
0.15

0.34
0.62
2.12

5.00

0.45

0.15

3.04

E5-E7,E14-E16
F1-F2,F3-F6,F7-F8,F9-F10, F10F11,F11-F12,F13-F14, F15-F18,F19-F20

1
1

X
X

2
9

3.07
5.00

0.45
0.45

0.15
0.15

0.41
3.04

F6-F7,F14-F15
G1-G2,G3-G6,G7-G8,G9-G10, G10G11,G11-G12,G13-G14, G15-G18,G19G20

1
1

X
X

2
9

2.03
5.00

0.45
0.45

0.15
0.15

0.27
3.04

H3-H6,H7-H8,H13-H14,
B2-D2
D2-E2
F6-G6
F7-G7
E8-G8
E9-G9

1
1
1
1
1
1
1

X
X
X
X
X
X
X

4
1
1
1
1
1
1

5.00
3.87
3.29
3.21
3.21
6.01
6.01

0.45
0.45
0.45
0.45
0.45
0.45
0.45

0.15
0.15
0.15
0.15
0.15
0.15
0.15

1.35
0.26
0.22
0.22
0.22
0.41
0.41

GF-AHDC

H15-H18.

Page 15 of 517

A10-B10
B10-E10
E10-F10
F10-G10
G10-I10
A11-B11
B11-E11
E11-F11
F11-G11
G11-I11
F12-G12
E13-G13
E14-G14
F15-G15
B19-D19
D19-E19
E19-F19
Under flooring
Dormitory Halls
Toilets
Wash area
Wardens room cum Lounge
Clinic hall
Type-1 Stair case
Type-2 Stair case
Entrance Lobby
Corridor
Under entrance steps
Under 115 mm thick Brick walls
in Toilets
in Clinic room

in Wardens room cum Lounge

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

7.00
7.38
2.50
3.06
3.80
7.00
7.38
2.50
3.06
3.80
6.01
6.01
5.71
3.21
3.87
3.29
3.21

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15

0.47
0.50
0.17
0.21
0.26
0.47
0.50
0.17
0.21
0.26
0.41
0.41
0.39
0.22
0.26
0.22
0.22

1
1
1
1
1
1
1
1
1
1
1

X
X
X
X
X
X
X
X
X
X
X

10
4
2
1
1
2
1
1
1
2
1

7.67
8.00
15.75
7.67
7.67
4.56
7.67
7.67
63.32
5.00
5.00

5.00
5.00
3.28
5.00
5.00
3.07
5.00
5.00
2.50
1.00
0.90

0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10

38.35
16.00
10.32
3.84
3.84
2.80
3.84
3.84
15.83
1.00
0.45

4
4
1
1
1
1
1
1
1

X
X
X
X
X
X
X
X
X

10
2
1
1
1
1
1
1
1

1.50
7.78
1.50
2.12
5.00
3.35
5.00
1.50
2.12

0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30

0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
Or say

1.80
1.87
0.05
0.06
0.15
0.10
0.15
0.05
0.06
152.98
153.00 cum

Random Rubble stone masonry, in CM (1:8) prop: (Cement: Sand) using Hard
blasted Granite stones from approved quarry including cost and conveyance of all
materials like Granite stones, cement, sand, water, etc., to site including
seigniorage charges, sales & other taxes on all materials, all operational, incidental,
and labour charges such as cutting stones to required size and shape, mixing of
cement mortar, constructing masonry, curing etc., complete for finished item of work
for foundation and basement (APSS No. 601 & 615)
Below Ground Level
B1-B2
B2-B4
B7-B8
B9-B10
B10-B11
B11-B12
B13-B14
B17-B19
B19-B20
C5-C7
C14-C16

GF-AHDC

1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x

1
1
1
1
1
1
1
1
1
1
1

4.90
4.90
4.86
4.56
5.00
4.63
4.86
4.93
4.86
3.07
3.07

Page 16 of 517

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60

1.32
1.32
1.31
1.23
1.35
1.25
1.31
1.33
1.31
0.83
0.83

#REF!

E1-E1'
E4-E5
E8-E9
E12-E13
E16-E17
E20'-E20
F1-F1'
F2-F3
F18-F19
F20'-F20
G6-G7
G8-G9
G12-G13
G14-G15
I1-I2
I9-I10
I10-I11
I11-I12
I19-I20
J3-J6
J7-J8
J13-J14
J15-J18
B1-D1
D1-E1
F1-G1
G1-I1
E1'-F1'
F2-G2
G2-I2
F3-G3
G3-H3
H3-J3
B4-D4
D4-E4
C5-E5
G6-H6
H6-J6
B7-C7
C7-E7
G7-H7
H7-J7
B8-D8
C8-E8
G8-H8
H8-J8
B9-D9
D9-E9
G9-I9
B12-D12
D12-E12
G12-I12
B13-C13
C13-E13
G13-H13
H13-J13
B14-C14
C14-E14
G14-H14
H14-J14

GF-AHDC

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
X
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

0.73
1.93
3.00
3.00
1.93
0.73
0.73
3.01
3.01
0.73
2.03
3.00
3.00
2.03
4.86
4.86
4.86
4.86
4.86
4.89
4.93
4.93
4.89
3.87
3.29
3.06
3.95
2.50
2.91
4.10
3.21
3.37
3.59
3.87
3.14
4.00
3.22
3.59
3.00
4.00
3.22
3.59
3.00
4.00
3.22
3.59
3.87
3.14
3.95
3.87
3.14
3.95
3.59
3.00
4.00
3.22
3.00
4.00
3.22
3.59

Page 17 of 517

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60

0.20
0.52
0.81
0.81
0.52
0.20
0.20
0.81
0.81
0.20
0.55
0.81
0.81
0.55
1.31
1.31
1.31
1.31
1.31
1.32
1.33
1.33
1.32
1.04
0.89
0.82
1.07
0.68
0.78
1.11
0.87
0.91
0.97
1.04
0.85
1.08
0.87
0.97
0.81
1.08
0.87
0.97
0.81
1.08
0.87
0.97
1.04
0.85
1.07
1.04
0.85
1.07
0.97
0.81
1.08
0.87
0.81
1.08
0.87
0.97

G15-H15
H15-J15
C16-E16
B17-D17
D17-E17
F18-G18
G18-H18
H18-J18
F19-G19
G19-I19
B20-D20
D20-E20
E20'-F20'
F20-G20
G20-I20
Above Ground level
B1-B2
B2-B4
B7-B8
B9-B10
B10-B11
B11-B12
B13-B14
B17-B19
B19-B20
C5-C7
C14-C16
E1-E1'
E4-E5
E8-E9
E12-E13
E16-E17
E20'-E20
F1-F1'
F2-F3
F18-F19
F20'-F20
G6-G7
G8-G9
G12-G13
G14-G15
I1-I2
I9-I10
I10-I11
I11-I12
I19-I20
J3-J6
J7-J8
J13-J14
J15-J18
B1-D1
D1-E1
F1-G1
G1-I1
E1'-F1'
F2-G2
G2-I2
F3-G3
G3-H3
H3-J3

GF-AHDC

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x
X

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

3.22
4.00
4.00
4.00
3.69
3.21
3.37
3.59
2.91
4.10
3.87
3.29
3.06
3.95
2.50

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
X
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

4.90
4.90
4.86
4.56
5.00
4.63
4.86
4.93
4.86
3.07
3.07
0.73
1.93
3.00
3.00
1.93
0.73
0.73
3.01
3.01
0.73
2.03
3.00
3.00
2.03
4.86
4.86
4.86
4.86
4.86
4.89
4.93
4.93
4.89
3.87
3.29
3.06
3.95
2.50
2.91
4.10
3.21
3.37
3.59

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60

Page 18 of 517

0.87
1.08
1.08
1.08
1.00
0.87
0.91
0.97
0.78
1.11
1.04
0.89
0.82
1.07
0.68
0.00
1.32
1.32
1.31
1.23
1.35
1.25
1.31
1.33
1.31
0.83
0.83
0.20
0.52
0.81
0.81
0.52
0.20
0.20
0.81
0.81
0.20
0.55
0.81
0.81
0.55
1.31
1.31
1.31
1.31
1.31
1.32
1.33
1.33
1.32
1.04
0.89
0.82
1.07
0.68
0.78
1.11
0.87
0.91
0.97

B4-D4
D4-E4
C5-E5
G6-H6
H6-J6
B7-C7
C7-E7
G7-H7
H7-J7
B8-D8
C8-E8
G8-H8
H8-J8
B9-D9
D9-E9
G9-I9
B12-D12
D12-E12
G12-I12
B13-C13
C13-E13
G13-H13
H13-J13
B14-C14
C14-E14
G14-H14
H14-J14
G15-H15
H15-J15
C16-E16
B17-D17
D17-E17
F18-G18
G18-H18
H18-J18
F19-G19
G19-I19
B20-D20
D20-E20
E20'-F20'
F20-G20
G20-I20

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
X

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

3.87
3.14
4.00
3.22
3.59
3.00
4.00
3.22
3.59
3.00
4.00
3.22
3.59
3.87
3.14
3.95
3.87
3.14
3.95
3.59
3.00
4.00
3.22
3.00
4.00
3.22
3.59
3.22
4.00
4.00
4.00
3.69
3.21
3.37
3.59
2.91
4.10
3.87
3.29
3.06
3.95
2.50

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
Or say

GF-AHDC

Page 19 of 517

1.04
0.85
1.08
0.87
0.97
0.81
1.08
0.87
0.97
0.81
1.08
0.87
0.97
1.04
0.85
1.07
1.04
0.85
1.07
0.97
0.81
1.08
0.87
0.81
1.08
0.87
0.97
0.87
1.08
1.08
1.08
1.00
0.87
0.91
0.97
0.78
1.11
1.04
0.89
0.82
1.07
0.68
164.08
165.00 cum

#REF!

Filling with useful available excavated earth (excluding rock) in trenches, sides of
foundations and basement with initial lead in layers not exceeding 15cm thick,
consolidating each deposited layer by watering and ramming including cost and
conveyence of water to work site and all operational, incidental, labour charges, hire
charges of T & P etc., complete for finished item of work. (APSS NO. 309 & 310)
MB. No.326/A/MD, Pg. No.5

867.39
To be done
Total Qty of excavated earth

1,072.40
1,939.79 Cum

Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using


20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse
aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement
per 1 cum of concreteincluding cost and conveyance of all materials like cement,
fine aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage
charges on all materials including centering using Steel scaffolding pipes, jack
props, wallers, foot plates, brackets, steel centering plates, etc., shuttering , machine
For
Footings
mixing,
laying concrete, vibrating,lift charges, curing etc., complete but excluding
MB.
No.326/A/MD,
Pg. No.13 charges for finished item of work.(APSS No. 402 &
cost of
steel and its fabrication
403)
1.80
1.80
0.38
In F1-Footings
1
x 24

29.16

In F2-Footings

23

2.00

2.00

0.38

34.50

In F3-Footings

22

2.20

2.20

0.43

45.25

In F4-Footings

2.40

2.40

0.48

13.68

In F5-Footings

2.60

2.60

0.55

26.03

2.80

0.55

8.62

2.80

0.28

9.70

In F6-Footings

2.80

In RF1-Footings

2.10

#REF!

166.95

To be done
In F1-Footings
In F2-Footings
In F4-Footings
In F5-Footings
In F7-Footings

1
1
1
1
1

x
x
x
x
x

2
5
1
1
2

1.80
2.00
2.40
2.60
1.40

1.80
2.00
2.40
2.60
1.40

0.38
0.38
0.43
0.48
0.48

2.43
7.50
2.44
3.21
1.86

17.44
184.39 cum

#REF!

For Pedestals
MB. No.326/A/MD, Pg. No.13 &14

In F1-Footings

24

0.60

0.60

0.60

5.18

In F2-Footings

23

0.75

0.75

0.60

7.76

In F3-Footings

22

0.75

0.75

0.60

7.42

In F4-Footings

0.75

0.75

0.60

1.68

In F5-Footings

0.75

0.75

0.60

2.36

In F6-Footings

0.75

0.75

0.60

0.67

In RF1-Footings

0.75

0.75

0.60

2.02
27.09

To be done

In F1-Footings
In F2-Footings
In F4-Footings
In F5-Footings
In F7-Footings

1
1
1
1
1

x
x

2
5
1
1
2

0.60
0.75
0.75
0.75
0.60

0.60
0.75
0.75
0.75
0.60

0.60
0.60
0.60
0.60
0.60

0.43
1.68
0.33
0.33
0.43
3.20
30.29 cum

For Plinth Beams

GF-AHDC

Page 20 of 517

#REF!

For External Plinth Beams


B1-B2

4.90

0.23

0.30

0.34

B2-B4

4.90

0.23

0.30

0.34

B7-B8

4.86

0.23

0.30

0.34

B9-B10

4.56

0.23

0.30

0.31

B10-B11

5.00

0.23

0.30

0.35

B11-B12

4.63

0.23

0.30

0.32

B13-B14

4.86

0.23

0.30

0.34

B17-B19

4.93

0.23

0.30

0.34

B19-B20

4.86

0.23

0.30

0.34

C5-C7

3.07

0.23

0.30

0.21

C14-C16

3.07

0.23

0.30

0.21

E1-E1'

0.73

0.23

0.30

0.05

E4-E5

1.93

0.23

0.30

0.13

E8-E9

3.00

0.23

0.30

0.21

E12-E13

3.00

0.23

0.30

0.21

E16-E17

1.93

0.23

0.30

0.13

E20'-E20

0.73

0.23

0.30

0.05

F1-F1'

0.73

0.23

0.30

0.05

F2-F3

3.01

0.23

0.30

0.21

F18-F19

3.01

0.23

0.30

0.21

F20'-F20

0.73

0.23

0.30

0.05

G6-G7

2.03

0.23

0.30

0.14

G8-G9

3.00

0.23

0.30

0.21

G12-G13

3.00

0.23

0.30

0.21

G14-G15

2.03

0.23

0.30

0.14

I1-I2

4.86

0.23

0.30

0.34

I9-I10

4.86

0.23

0.30

0.34

I10-I11

4.86

0.23

0.30

0.34

I11-I12

4.86

0.23

0.30

0.34

I19-I20

4.86

0.23

0.30

0.34

J3-J6

4.89

0.23

0.30

0.34

J7-J8

4.93

0.23

0.30

0.34

J13-J14

4.93

0.23

0.30

0.34

J15-J18

4.89

0.23

0.30

0.34

B1-D1

3.87

0.23

0.30

0.27

D1-E1

3.29

0.23

0.30

0.23

F1-G1

3.06

0.23

0.30

0.21

G1-I1

3.95

0.23

0.30

0.27

E1'-F1'

2.50

0.23

0.30

0.17

F2-G2

2.91

0.23

0.30

0.20

G2-I2

4.10

0.23

0.30

0.28

F3-G3

3.21

0.23

0.30

0.22

G3-H3

3.37

0.23

0.30

0.23

H3-J3

3.59

0.23

0.30

0.25

B4-D4

3.87

0.23

0.30

0.27

D4-E4

3.14

0.23

0.30

0.22

C5-E5

4.00

0.23

0.30

0.28

G6-H6

3.22

0.23

0.30

0.22

GF-AHDC

Page 21 of 517

H6-J6

3.59

0.23

0.30

0.25

B7-C7

3.00

0.23

0.30

0.21

C7-E7

4.00

0.23

0.30

0.28

G7-H7

3.22

0.23

0.30

0.22

H7-J7

3.59

0.23

0.30

0.25

B8-D8

3.00

0.23

0.30

0.21

C8-E8

4.00

0.23

0.30

0.28

G8-H8

3.22

0.23

0.30

0.22

H8-J8

3.59

0.23

0.30

0.25

B9-D9

3.87

0.23

0.30

0.27

D9-E9

3.14

0.23

0.30

0.22

G9-I9

3.95

0.23

0.30

0.27

B12-D12

3.87

0.23

0.30

0.27

D12-E12

3.14

0.23

0.30

0.22

G12-I12

3.95

0.23

0.30

0.27

B13-C13

3.59

0.23

0.30

0.25

C13-E13

3.00

0.23

0.30

0.21

G13-H13

4.00

0.23

0.30

0.28

H13-J13

3.22

0.23

0.30

0.22

B14-C14

3.00

0.23

0.30

0.21

C14-E14

4.00

0.23

0.30

0.28

G14-H14

3.22

0.23

0.30

0.22

H14-J14

3.59

0.23

0.30

0.25

G15-H15

3.22

0.23

0.30

0.22

H15-J15

4.00

0.23

0.30

0.28

C16-E16

4.00

0.23

0.30

0.28

B17-D17

4.00

0.23

0.30

0.28

D17-E17

3.69

0.23

0.30

0.25

F18-G18

3.21

0.23

0.30

0.22

G18-H18

3.37

0.23

0.30

0.23

H18-J18

3.59

0.23

0.30

0.25

F19-G19

2.91

0.23

0.30

0.20

G19-I19

4.10

0.23

0.30

0.28

B20-D20

3.87

0.23

0.30

0.27

D20-E20

3.29

0.23

0.30

0.23

E20'-F20'

3.06

0.23

0.30

0.21

F20-G20

3.95

0.23

0.30

0.27

G20-I20

2.50

0.23

0.30

0.17

A10-A11

5.00

0.23

0.30

0.35

C7-C8,C13-C14

4.56

0.23

0.30

0.63

D1-D2,D2-D4,D9-D10,D11-D12,D17D19,D19-D20.
E1-E2,E2-E4.E7-E8,
E9-

5.23

0.23

0.30

2.17

5.00

0.23

0.30

3.11

E10,E10-E11,E11-E12,
E13E5-E7,E14-E16
E14,E17-E19,E19-E20.
F1-F2,F3-F6,F7-F8,F9-F10, F10F11,F11-F12,F13-F14,
F15-F18,F19F6-F7,F14-F15
F20
G1-G2,G3-G6,G7-G8,G9-G10, G10G11,G11-G12,G13-G14,
H3-H6,H7-H8,H13-H14, G15-G18,G19H15-H18.
G20
B2-D2

3.07

0.23

0.30

0.42

5.00

0.23

0.30

3.11

2.03

0.23

0.30

0.28

5.00

0.23

0.30

3.11

5.00

0.23

0.30

1.38

3.87

0.23

0.30

0.27

For Internal Plinth Beams

GF-AHDC

Page 22 of 517

D2-E2

3.29

0.23

0.30

0.23

F6-G6

3.21

0.23

0.30

0.22

F7-G7

3.21

0.23

0.30

0.22

E8-G8

6.01

0.23

0.30

0.41

E9-G9

6.01

0.23

0.30

0.41

A10-B10

7.00

0.23

0.30

0.48

B10-E10

7.38

0.23

0.30

0.51

E10-F10

2.50

0.23

0.30

0.17

F10-G10

3.06

0.23

0.30

0.21

G10-I10

3.80

0.23

0.30

0.26

A11-B11

7.00

0.23

0.30

0.48

B11-E11

7.38

0.23

0.30

0.51

E11-F11

2.50

0.23

0.30

0.17

F11-G11

3.06

0.23

0.30

0.21

G11-I11

3.80

0.23

0.30

0.26

F12-G12

6.01

0.23

0.30

0.41

E13-G13

6.01

0.23

0.30

0.41

E14-G14

5.71

0.23

0.30

0.39

F15-G15

3.21

0.23

0.30

0.22

B19-D19

3.87

0.23

0.30

0.27

D19-E19

3.29

0.23

0.30

0.23

E19-F19

3.21

0.23

0.30

0.22
42.70

or say
7

43.00 cum

#REF!

#REF!

To be done
Column upto bottom of Plinth Beam
C1

10

0.30

0.45

0.90

1.22

C2

22

0.30

0.45

0.90

2.67

C3

18

0.30

0.45

0.90

2.19

C4

22

0.30

0.45

0.90

2.67

C5

0.30

0.60

0.90

1.30

C6

10

0.30

0.60

0.90

1.62

C7

0.30

0.60

0.90

1.30

C8

0.38

0.38

0.90

0.26
13.22

Or say
8

Providing High Yield Strength Deformed steel bars (Fe 415grade as per IS 17861979) of different diameters, including labour charges for cutting, bending to
required sizes and shapes placing in position with cover blocks of approved
materials and size and tying with binding wire of 20SWG, foRMing grills for
reinforcement work as per approved designs and drawings, including cost and
conveyance of steel bars, including all wastages such as overlaps, couplings,
MB.
No.327/A/MD,
Pg. spacer
No.5
welded
joints, chairs,
bars including cost and conveyance of binding wire,
cover
blocks and all incidental, operational, labour charges such as cutting, bending,
To
be done
placing in position, tying including sales and other taxes and all materials etc.,
complete for finished item of work in all floors.(APSS No.126)

GF-AHDC

Page 23 of 517

14.00 cum

24.252
2.197
26.45

MT

#REF!

#REF!

Flush Pointing to CRS Masonry in CM(1:3) Prop: including cost and conveyance of
all materials like cement, sand, water etc., to site, including seigniorage charges,
sales & other taxes on all materials, all operational, incidental charges and labour
charges such as mixing mortar, finishing, curing, etc., complete for finished item of
work. (APSS 901,906)
Above Ground level
B1-B2
B2-B4
B7-B8
B9-B10
B10-B11
B11-B12
B13-B14
B17-B19
B19-B20
C5-C7
C14-C16
E1-E1'
E4-E5
E8-E9
E12-E13
E16-E17
E20'-E20
F1-F1'
F2-F3
F18-F19
F20'-F20
G6-G7
G8-G9
G12-G13
G14-G15
I1-I2
I9-I10
I10-I11
I11-I12
I19-I20
J3-J6
J7-J8
J13-J14
J15-J18
B1-D1
D1-E1
F1-G1
G1-I1
E1'-F1'
F2-G2
G2-I2
F3-G3
G3-H3
H3-J3
B4-D4
D4-E4
C5-E5
G6-H6
H6-J6
B7-C7
C7-E7
G7-H7
H7-J7
B8-D8

GF-AHDC

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
X
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

4.90
4.90
4.86
4.56
5.00
4.63
4.86
4.93
4.86
3.07
3.07
0.73
1.93
3.00
3.00
1.93
0.73
0.73
3.01
3.01
0.73
2.03
3.00
3.00
2.03
4.86
4.86
4.86
4.86
4.86
4.89
4.93
4.93
4.89
3.87
3.29
3.06
3.95
2.50
2.91
4.10
3.21
3.37
3.59
3.87
3.14
4.00
3.22
3.59
3.00
4.00
3.22
3.59
3.00

Page 24 of 517

0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90

4.41
4.41
4.37
4.10
4.50
4.17
4.37
4.44
4.37
2.76
2.76
0.65
1.74
2.70
2.70
1.74
0.65
0.65
2.71
2.71
0.65
1.83
2.70
2.70
1.83
4.37
4.37
4.37
4.37
4.37
4.40
4.44
4.44
4.40
3.48
2.96
2.75
3.55
2.25
2.61
3.69
2.88
3.03
3.23
3.48
2.82
3.60
2.89
3.23
2.70
3.60
2.89
3.23
2.70

C8-E8
G8-H8
H8-J8
B9-D9
D9-E9
G9-I9
B12-D12
D12-E12
G12-I12
B13-C13
C13-E13
G13-H13
H13-J13
B14-C14
C14-E14
G14-H14
H14-J14
G15-H15
H15-J15
C16-E16
B17-D17
D17-E17
F18-G18
G18-H18
H18-J18
F19-G19
G19-I19
B20-D20
D20-E20
E20'-F20'
F20-G20
G20-I20
C1
C2
C3
C4
C5
C6
C7

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
X
x
x
x
x
x
x
x

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
10
22
6
17
7
6
6

4.00
3.22
3.59
3.87
3.14
3.95
3.87
3.14
3.95
3.59
3.00
4.00
3.22
3.00
4.00
3.22
3.59
3.22
4.00
4.00
4.00
3.69
3.21
3.37
3.59
2.91
4.10
3.87
3.29
3.06
3.95
2.50
0.45
0.45
0.45
0.45
0.60
0.60
0.60

0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
0.90
or say

3.60
2.89
3.23
3.48
2.82
3.55
3.48
2.82
3.55
3.23
2.70
3.60
2.89
2.70
3.60
2.89
3.23
2.89
3.60
3.60
3.60
3.32
2.88
3.03
3.23
2.61
3.69
3.48
2.96
2.75
3.55
2.25
4.05
8.91
2.43
6.89
3.78
3.24
3.24
306.00
306.00 Sqm

#REF!

Part A
10 Vibrated reinforced cement concrete M20 Grade

Desing mix ( by weigh batching) using 20 mm


size (SS5) hard granite machine crushed graded
metal (coarse aggregate) from approved quarry
using miminum quantity of 350 Kgs of cement per
1 Cum of concrete including cost and conveyance
of all materials like cement, fine aggregate (Sand),
coarse aggregate, water etc. to site including
Column
bottom
BeamonGround
Floor
seigniorageupto
charges,
sales of
& Roof
other taxes
all
C1
x 10
materials, all operational, incidental, and labor 1
charges such as Providing Centring, shuttering and 1
C2
x 22
scaffolding
with
props
and
steel
plate
as
per
the
C3
1
x 18
approved shuttering plan and other accessories as
C4
1
x 22
per the norms and stability calculations including
C5
x 8
cost and conveyance of all accessories Using 1
Cashewrina Ballies and Wooden runners & staging 1
C6
x 10
including all bracings, cross members etc complete
C7
1
x 8
for finished item of work, lift charges, machine
C8
x 2
mixing, laying concrete, vibrating, curing concrete 1
etc, complete but excluding cost of steel and its
fabrication
charges etc complete for finished item
FF
of work (APSS No.402 & 403)

0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.38

SF

GF-AHDC

Page 25 of 517

0.45
0.45
0.45
0.45
0.6
0.6
0.6
0.38

3.18
3.18
3.18
3.18
3.18
3.18
3.18
3.00

1.35
2.97
2.43
2.97
1.44
1.80
1.44
0.29
14.69 cum
14.40 cum
14.40 cum

#REF!

TF
C2
C3
C4
C6

For Roof Beams


B1
B1
B2
B3
B4
B5
B5A
B5A
B6
B7
B8
B9
B10
B11
B12
B13
B14
B15
B16
B17
B18
B18A
B19
B20
B21
B21A
B22
B22
B23
B23A
B24A
B24
Mid landing Beams

1
1
1
1

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
2
1
1
1
1
1
1
1
1
1
1
2
1

x
x
x
x

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

2
2
6
4

4
4
4
4
4
2
4
2
1
2
2
2
2
1
2
1
1
1
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

0.30
0.30
0.30
0.30

5.49
5.46
5.46
5.49
5.46
5.46
5.49
5.03
5.23
22.94
18.91
22.94
10.69
15.92
10.69
15.92
5.46
5.46
18.76
18.76
8.24
3.66
8.35
4.79
8.35
11.63
14.25
8.12
18.76
5.78
7.90
7.90
3.67
5.60

0.45
0.45
0.45
0.6

0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23

2.80
2.80
2.80
2.80

0.33
0.30
0.30
0.33
0.30
0.30
0.33
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.33
0.30
0.30
0.30
0.30
0.30
0.30
0.33
0.30
0.30
0.30
0.48
0.30
0.30

FF
SF
TF
2
2
1
1

For 125 mm Thick Roof Slab


On entire area

GF-AHDC

1
1
1
1
1

x
x
x
x

x
x
x
x
x

2
2
2
2

1
2
2
2
1

3.90
4.67
5.46
5.12

0.23
0.23
0.23
0.23

64.82 22.37
11.51
3.01
8.01 2.03
8.01 3.23
15.69
3.61

Page 26 of 517

0.30
0.30
0.30
0.30

0.27
0.27
0.81
0.72
2.07 cum

1.64
1.51
1.51
1.64
1.51
0.75
1.64
0.69
0.36
3.17
2.61
3.17
1.48
1.10
1.48
1.10
0.38
0.38
2.59
2.59
2.46
1.01
1.15
0.66
1.15
1.60
1.97
1.21
2.59
0.80
1.09
1.73
1.01
0.77
50.48 cum
49.47 cum
49.47 cum
1.08
1.29
0.75
0.71
3.82 cum

1,450.02
-69.29
-32.50
-51.71
-56.64

#REF!

#REF!

#REF!

over portico

1
1
1
1
1

x
x
x
x
x

2
2
2
1
1

5.23
5.30
3.00
7.67
7.35

3.61
7.67
7.67
5.00
5.23
or say

FF
SF
TF
1
1

x
x

2
1

3.53
5.46

4.9
5.115

34.59
27.93
62.52 sqm

#REF!

#REF!

For 175 mm thick slab For GF,FF &SF.


Type-1 Staircase waist slab
Mid landing
Type-2 Staircase waist slab
Mid landing

2
1
1
1

x
x
x
x

2
2
1
1

3.41
3.07
3.41
5.00

1.5
1.67
2
2.23
or say

FF
SF

11

-37.76
-81.30
-46.02
-38.35
38.41
1,074.86
1,075.00 sqm
1,036.59 sqm
1,036.59 sqm

Reinforced cement concrete M20 Grade Desing mix ( by weigh batching) using 20
mm size (SS5) hard granite machine crushed graded metal (coarse aggregate)
from approved quarry using miminum quantity of 350 Kgs of cement per 1 cum of
concrete including cost and conveyance of all materials like cement, fine aggregate
(Sand), coarse aggregate, water etc. to site including seigniorage charges, sales &
other taxes on all materials, all operational, incidental, and labor charges such as
Providing Centring, shuttering and scaffolding with props and steel plate as per the
GF
approved shuttering plan and other accessories as per the norms and stability
calculations including cost and conveyance of all accessories Using Cashewrina
Ballies
andDoor-MD
Wooden runners & staging including
cross 0.23
members0.15
etc
Over Main
1
x all1bracings,5.00
complete
for finished item of work, lift charges,
mixing,
Over Door-D1
1
x machine
11
1.50 laying
0.23concrete,
0.15
vibrating,
curing concrete etc, complete but excluding
its fabrication
Over Door-D2
1
x 3cost of steel
1.35and0.115
0.15
charges etc complete for finished item of work (APSS No.402 & 403) for Lintels
Over Door-D6
1
x 50
1.05 0.115
0.15
Over windows-W3
1
x 58
1.80 0.23
0.15
Over Grill windows-GW
2
x 2
3.19 0.23
0.15
Over Grill windows-GW1
2
x 2
3.70 0.23
0.15
Over Grill windows-GW2
2
x 2
2.72 0.23
0.15
Over Grill windows-GW3
1
x 2
3.51 0.23
0.15
Over Ventilator-V
2
x 2
2.80 0.23
0.15
Over Ventilator-V1
1
x 50
1.20 0.23
0.15
or say
FF,
Over Main Door-MD
Over Door-D1
Over Door-D2
Over Door-D6
Over windows-W3
Over Grill windows-GW
Over Grill windows-GW1
Over Grill windows-GW2
Over Grill windows-GW3
Over Ventilator-V
Over Ventilator-V1

GF-AHDC

0
1
0
1
1
2
2
2
1
2
1

x
x
x
x
x
x
x
x
x
x
x

1
11
3
48
58
2
2
2
2
2
48

5.00
1.50
1.35
1.05
1.80
3.19
3.70
2.72
3.51
2.80
1.20

Page 27 of 517

0.23
0.23
0.115
0.115
0.23
0.23
0.23
0.23
0.23
0.23
0.23

0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15

20.46
10.25
6.82
11.15
48.68
49.00 sqm
49.00 sqm
49.00 sqm

#REF!

0.17
0.57
0.07
0.91
3.60
0.44
0.51
0.38
0.24
0.39
2.07
9.34
10.00 cum

#REF!

0.00
0.57
0.00
0.87
3.60
0.44
0.51
0.38
0.24
0.39
1.99
8.98 cum

#REF!

SF
12 Reinforced cement concrete with M 25 grade Design mix ( by weigh batching ) as
per using 20mm size (SS 5) machine crushed hard granite graded metal (coarse
aggregate) from approved quarry using a minimum quantity of 350 Kg of cement
per 1 Cum of concrete including cost and conveyance of all materials like cement,
fine aggregate (sand) ,coarse aggregate, water etc. to site and cost of
seigniorage charges on all materials including centering using Cashewrina
Ballies and Wooden runners & staging including all bracings, cross members
etc., shuttering, machine mixing, laying concrete, 7.5cm thick at fixed end and
5cm thick at free end with an average thickness of 6.25cm including labour
charges for mixing, laying, curing etc., complete but excluding cost of steel and
its fabrication charges for finished item of work for 60cm wide sun-shades(APSS No.
402, 403 & 903)

8.98 cum

#REF!

GF
Over windows-W3
Over Grill windows-GW1
Over Grill windows-GW2
Over Grill windows-GW3
Over Ventilator-V
Over Ventilator-V1

1
2
2
1
0
0

x
x
x
x
x
x

58
2
2
2
2
50

1.80
3.70
2.72
3.51
2.80
1.20

0.6
0.6
0.6
0.6
0.6
0.6
or say

FF,SF

13 50mm thick Platform for hand wash in Toilet blocks


GF,FF&SF
1
x 4
1
x 4

9.78
7.01

0.6
0.6

FF
SF
14 Plain Cement Concrete corresponding to M10 grade as per IS 456 equivalent to
(1:3:6) proportion nominal mix (cement: fine aggregate: Coarse aggregate) using
20mm size Hard Blasted Granite (IS383, 1970) Machine Crushed graded metal from
approved quarry including cost and conveyance of all materials like cement, sand,
coarse aggregate, water etc. to site, including seigniorage charges, sales & other
taxes on all materials, all operational, incidental and labour charges such as mixing,
laying, curing concrete, etc., complete for finished item of work for Bed Blocks and
Hold Fasts (APSS No. 402)
Main Door-MD
D1
D2
D6
Grill windows-GW
Grill windows-GW1
Grill windows-GW2
Grill windows-GW3
Ventilator-V
Ventilator-V1

1
11
3
50
4
4
4
2
4
48
2

x
x
x
x
x
x
x
x
x
x
x

6
6
6
6
4
4
4
4
4
4
4

0.23
0.23
0.12
0.12
0.23
0.23
0.23
0.23
0.23
0.23
0.23

0.23
0.23
0.115
0.115
0.23
0.23
0.23
0.23
0.23
0.23
0.23

0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
or say

FF,
SF

GF-AHDC

Page 28 of 517

62.64
8.88
6.53
4.21
0.00
0.00
82.26
83.00 sqm
83.00 sqm
83.00 sqm

23.47
16.82
40.30 sqm
40.30 sqm
40.30 sqm

0.05
0.52
0.04
0.60
0.13
0.13
0.13
0.06
0.13
1.52
0.06
3.36
3.50 cum
3.40 cum
3.40 cum

#REF!

#REF!
#REF!

#REF!

15 Plain Cement Concrete M20 Design Mix ( by weigh batching ) using 20mm size
(SS5) hard blasted granite machine crushed graded metal (Coarse aggregate) from
approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of
concrete including cost and conveyance of all materials like cement, fine
aggregate (Sand), coarse aggregate, water etc., to site and cost of seigniorage
charges on all materials including steel centering, shuttering, machine mixing, laying
concrete, lift charges, curing etc., complete for finished item of work for steps (APSS
No. 402 )
GF
Type-1 staircase steps
0.5 x 42
1.50
0.3
0.15
Type-2 Staircase steps
0.5 x 22
2.00
0.3
0.15
Steps at entrances
0.5 x 8
1.00
0.5
0.15
0.5 x 6
1.00
0.3
0.15
0.5 x 3
5.23
0.3
0.15

1.42
0.99
0.30
0.14
0.35
3.20

MB. No.326/A/MD, Pg. No.12

I1 F1
Av. Irregular depth

1
1

x
x

1
1

1.95
1.95

1.95
1.95

0.05
0.30

or say
FF
SF
16 Brick Masonry in superstructure with CM (1:8) prop: using second class bricks from
approved source having minimum crushing strength of 40 Kg/Sqcm. including cost
and conveyance of all materials like cement, sand, bricks, water etc., to site,
including seigniorage charges, sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing cement mortar, constructing masonry,
scaffolding charges, lift charges, curing, etc., complete for finished item of work.
(APSS No. 501 & 504).

Dormitory Rooms
Long walls
Cross walls
Clinic Hall
Long walls
Cross walls
Wardens room cum Lounge
Long walls
Cross walls
Entrance Lobby
Type-1 Staircase
Long walls
Cross walls
Type-2 Staircase
Beside Type-1 Staircase
Beside Clinic hall
Beside Toilets
Toilet Block
Cross walls
Long walls
Cross walls
Corridor side walls
Corridor end walls
Lintel Deductions
Over Main Door-MD
Over Door-D1
Over Door-D2
Over Door-D6
Over windows-W3
Over Grill windows-GW
Over Grill windows-GW1

GF-AHDC

0.19
1.14
1.33
4.53 cum
2.41 cum
2.41 cum

1
2

x
x

18
10

7.38
5.00

0.23
0.23

3.18
3.18

97.01
73.03

1
1

x
x

2
2

7.38
5.00

0.23
0.23

3.18
3.18

10.78
7.30

1
1
1

x
x
x

2
2
1

7.38
5.00
5.00

0.23
0.23
0.23

3.18
3.18
3.18

8.08
7.30
3.65

1
1
1
1
2
1

x
x
x
x
x
x

2
2
1
2
2
2

4.11
3.05
5.00
2.03
3.00
3.01

0.23
0.23
0.23
0.23
0.23
0.23

3.18
3.18
3.18
3.18
3.18
3.18

6.00
4.45
3.65
2.96
8.76
4.40

1
4
2
1
1

x
x
x
x
x

2
2
4
2
2

3.28
7.49
5.00
15.53
2.50

0.23
0.23
0.23
0.23
0.23

3.18
3.15
3.15
3.18
3.18

4.78
43.38
28.98
22.68
3.65

1
1
0
0
1
2
2

x
x
x
x
x
x
x

1
11
3
50
58
2
2

5.00
1.50
1.35
1.05
1.80
3.19
3.70

0.23
0.23
0.115
0.115
0.23
0.23
0.23

0.15
0.15
0.15
0.15
0.15
0.15
0.15

-0.17
-0.57
0.00
0.00
-3.60
-0.44
-0.51

Page 29 of 517

#REF!

Over Grill windows-GW2


Over Grill windows-GW3
Over Ventilator-V
Over Ventilator-V1
Deductions
Main Door-MD
Door-D1
Door-D2
Door-D6
windows-W3
Grill windows-GW
Grill windows-GW1
Grill windows-GW2
Grill windows-GW3
Ventilator-V
Ventilator-V1
for Columns Deduction
C1
C2
C3

2
1
2
1

x
x
x
x

2
2
2
50

2.72
3.51
2.80
1.20

0.23
0.23
0.23
0.23

0.15
0.15
0.15
0.15

-0.38
-0.24
-0.39
-2.07

1
1
0
0
1
2
2
2
1
2
4

x
x
x
x
x
x
x
x
x
x
x

1
11
3
12
58
2
2
2
2
2
12

4.00
1.20
1.05
0.75
1.50
2.73
3.24
2.26
3.05
2.50
0.90

0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23

2.13
2.13
2.13
2.13
1.35
1.35
1.35
1.35
1.35
0.45
0.45

-1.96
-6.47
0.00
0.00
-27.01
-3.39
-4.02
-2.81
-1.89
-1.04
-4.47

1
1
1

x
x
x

10
15
15

0.45
0.45
0.45

0.23
0.23
0.23

3.18
3.18
3.18

-3.29
-4.93
-4.93
266.29
267.00 cum
267.00
-18.08
-15.39
10.80
1.96
246.29 cum
267.00
-18.08
-15.39
10.80
1.96
246.29 cum

or say
FF

14.79

0.23

3.18

SF

TF
Head room

Parapet wall

Over Door D1

1
1
1
1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x

4
4
2
2
2
2
2
2
2
6
6
2
3
3

14.79

4.67
3.07
5.00
7.67
64.82
19.20
11.51
7.90
4.40
8.01
7.90
4.67
1.50
1.20

0.23

0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23

3.18

2.80
2.80
2.80
2.80
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
0.15
2.13

17 Reinforced Flyash Brick Masonry for partition walls


in CM (1:4) prop.
(Cement:Sand) using Flyash bricks of size 290x100x140 mm with crushing
strength not less than 40Kg per Sq.cm and placing 2 nos of 6mm MS plain rods in
every third layer with free ends of the reinforcement pegged into mortar joints of
main brick walls where applicable including cost and conveyance of all materials like
cement, sand, bricks, water etc., to site, including seigniorage charges, sales and
other taxes on all materials, scaffolding charges and cost of all labour charges like
mixing cement mortar, lift charges, curing etc., complete but excluding cost of steel
and its fabrication charges for finished item of work (APSS No. 501 & 509)

GF-AHDC

Page 30 of 517

12.03
7.91
6.44
9.88
29.82
8.83
5.29
3.63
2.02
11.05
10.90
2.15
-0.16
-1.76
108.03 cum

#REF!

#REF!

#REF!

#REF!

GF
Toilet Block
Long walls
Cross walls
In clinic & Warden room

Lintels Over Door-D2


Over Door-D6
D2
D6

4
2
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x

10
4
2
2
2
1
3
50
3
50

1.50
7.78
2.00
1.62
5.00
3.00
1.35
1.05
1.05
0.75

2.85
2.85
2.88
2.88
3.18
3.48
0.15
0.15
2.13
2.13
or say

FF
Lintels Over Door-D2
D2
D6
SF
Lintels Over Door-D2
D2
D6

1
1
1

1
1
1

x
x
x

0
x
x

3
3
2

3
3
2

1.35
1.05
0.75

1.35
1.05
0.75

0.15
2.13
2.13

0.15
2.13
2.13

18 Providing High Yield Strength Deformed steel bars (Fe 415grade as per IS 17861979) of different diameters, including labour charges for cutting, bending to
required sizes and shapes placing in position with cover blocks of approved
materials and size and tying with binding wire of 20SWG, foRMing grills for
reinforcement work as per approved designs and drawings, including cost and
conveyance of steel bars, including all wastages such as overlaps, couplings,
welded joints, chairs, spacer bars including cost and conveyance of binding wire,
cover blocks and all incidental, operational, labour charges such as cutting, bending,
Ground
Floor
placing in
position, tying including sales and other taxes and all materials etc.,
First
Floor
complete for finished item of work in all floors.(APSS No.126)
Second Floor
Third Floor

19 Providing Mild steel bars (Fe 250 grade as per IS 432) of different diameters,
including labour charges for cutting, bending to required sizes and shapes placing in
position with cover blocks of approved materials and size and tying with binding wire
of 20SWG, foRMing grills for reinforcement work as per approved designs and
drawings, including cost and conveyance of steel bars, including all wastages such
as overlaps, couplings, welded joints, chairs, spacer bars including cost and
conveyance of binding wire, cover blocks and all incidental, operational, labour
charges such as cutting, bending, placing in position, tying including sales and other
Ground
taxes onFloor
all materials etc., complete for finished item of work in all floors.(APSS
First Floor
No.126)
Second Floor

171.00
177.27
11.50
9.29
31.75
10.43
-0.61
-7.88
-6.71
-79.88
316.16
317.00 sqm
254.04
0.61
6.71
3.20
264.55 sqm
254.04
0.61
6.71
3.20
264.56 sqm

GF-AHDC

10

7.67

Page 31 of 517

3.48

#REF!

#REF!

Mt
Mt
Mt
Mt

#REF!

1.00 Mt
1.00 Mt
1.00 Mt

#REF!

22.00
27.00
27.00
4.24

20 Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and top
coat of 4mm thick in CM (1:4) dubara sponge finish including cost and conveyance
of all materials like cement, sand, water etc., to site, seigniorage charges, sales &
other taxes on all materials,all operational, incidental and labour charges such as
mixing mortar, scaffolding charges, lift charges, including cutting of Grooves
wherever necessary as directed by Engineer - in - charge, finishing, curing, etc.,
complete for Even Surfaces of Wall for finished item of work. (APSS 901,903 &
904)
Dormitory Rooms
Long walls

#REF!

533.07

Cross walls
Clinic Hall
Long walls
Cross walls
Wardens room cum Lounge
Long walls
Cross walls
Entrance Lobby
Type-1 Staircase
Long walls
Cross walls
Type-2 Staircase
Toilet Block
Cross walls
Cross walls
Corridor side walls
Corridor end walls
Deductions
Main Door-MD
Door-D1
Door-D2
Door-D6
windows-W3
Grill windows-GW
Grill windows-GW1
Grill windows-GW2
Grill windows-GW3
Ventilator-V
Ventilator-V1
Toilet Block
Long walls
Cross walls
In clinic & Warden room

10

5.00

3.48

347.50

1
2

x
x

2
2

7.67
5.00

3.48
3.48

53.31
69.50

1
1
1

x
x
x

1.5
2
1

7.67
5.00
5.00

3.48
3.48
3.48

39.98
34.75
17.38

2
1
1
1

x
x
x
x

2
2
1
2

4.11
3.05
5.00
7.67

3.48
3.48
3.48
3.48

57.13
21.20
17.38
53.31

2
2
2
1

x
x
x
x

2
4
2
2

3.28
5.00
15.53
2.50

3.48
3.48
3.48
3.48

45.52
139.00
215.87
17.38

0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5

x
x
x
x
x
x
x
x
x
x
x

1
11
3
50
58
4
4
4
2
4
48

4.00
1.20
1.05
0.75
1.50
2.73
3.24
2.26
3.05
2.50
0.90

2.13
2.13
2.13
2.13
1.35
1.35
1.35
1.35
1.35
0.45
0.45

-4.26
-14.06
-3.35
-39.94
-58.73
-7.37
-8.75
-6.10
-4.12
-2.25
-9.72

2
2
2
2
2
1

x
x
x
x
x
x

40
4
2
2
2
2

1.50
7.78
2.00
1.62
5.00
3.00

3.18
3.18
3.18
3.18
3.48
3.48
or say

FF
1

14.79

3.48

0.5

0.75

2.13

381.00
197.49
25.40
20.51
69.50
20.85
2,218.35
2,219.00 sqm
2,219.00
-136.26
102.79
4.26
3.35
1.60
2,194.74 sqm

#REF!

2,194.74 sqm

#REF!

#REF!

SF
TF
Head room

Parapet wall

GF-AHDC

2
2
2
2
2
2
2
2
2
2
2

x
x
x
x
x
x
x
x
x
x
x

4
4
2
2
2
2
2
2
2
6
6

4.67
3.07
5.00
7.67
64.82
19.20
11.51
7.90
4.40
8.01
7.90

Page 32 of 517

3.10
3.10
3.10
3.10
1.00
1.00
1.00
1.00
1.00
1.00
1.00

115.82
76.14
62.00
95.11
259.28
76.80
46.04
31.60
17.58
96.06
94.80

Over Door D1

Out Side Plastering


For Un- evenside
Long walls
Short walls
Dormitory Rooms out side
Type-1 Staircase out side
Toilet Block out side
Corridor walls
Deductions
Main Door-MD
Door-D1
Door-D2
Door-D6
windows-W3
Grill windows-GW
Grill windows-GW1
Grill windows-GW2
Grill windows-GW3
Ventilator-V
Ventilator-V1
Column projections

2
1
1

x
x
x

2
3
3

4.67
1.50
1.20

1.00
0.15
2.13

1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x

2
2
8
2
2
2
6
2

64.82
19.20
8.12
4.67
4.73
11.85
8.61
64.36

3.60
3.60
3.60
3.60
3.60
3.60
3.60
3.48

0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
2
2

x
x
x
x
x
x
x
x
x
x
x
x
x

1
11
3
50
58
4
4
4
2
4
48
26
2

4.00
1.20
1.05
0.75
1.50
2.73
3.24
2.26
3.05
2.50
0.90
0.34
0.76

2.13
2.13
2.13
2.13
1.35
1.35
1.35
1.35
1.35
0.45
0.45
3.60
3.60
or say

FF

Door-D6

0.5

0.75

2.13

21 Ornamental Plastering 12mm thick in two coats with base coat of 8mm thick in CM
(1:5) and top coat of 4mm thick in CM (1:3) dubara sponge finish including cost and
conveyance of all materials like cement, sand, water etc., to site, seigniorage
charges, sales & other taxes on all materials,all operational, incidental and labour
charges such as mixing mortar, scaffolding charges, lift charges, including cutting of
Grooves wherever necessary as directed by Engineer - in - charge, finishing, curing,
etc., complete for Even Surfaces of Wall for finished item of work. (APSS 901,903
& 904)
Dormitory Halls
1
x 10
7.67
5
Beam sides
2
x 10
5.00
0.30
Clinic Hall
1
x 1
7.67
5
Beam sides
2
x 1
5.00
0.30
Wardens room cum Lounge
1
x 1
7.67
5
Beam sides
2
x 1
5.00
0.30
Entrance Lobby
1
x 1
7.67
5
Beam sides
2
x 3
5.00
0.30
Toilet blocks
1
x 4
8.00
5
Beam sides
2
x 8
5.00
0.33
Wash area
1
x 2
15.75 3.275
Beam sides
2
x 8
3.28
0.30
Corridor
1
x 1
64.36
2.5
Beam sides
2
x 10
2.50
0.30
Portico
1
x 1
7.53 5.46

Page 33 of 517

#REF!

466.70
138.24
233.86
33.62
34.06
85.28
185.87
447.30
-4.26
-14.06
-3.35
-39.94
-58.73
-7.37
-8.75
-6.10
-4.12
-2.25
-9.72
62.71
10.94
1,539.95
1,540.00 sqm
1,540.00
4.26
3.35
1.60
1,549.21 sqm
1,549.21 sqm

SF

GF-AHDC

18.68
-0.68
-7.67
981.56 sqm

383.50
100.00
38.35
10.00
38.35
10.00
38.35
30.00
160.00
80.00
103.16
52.40
160.90
50.00
41.11

#REF!

#REF!
#REF!

Beam sides
Beam sides
Bottom Type-1 Staircase waist slab
Bottom Mid landing
Bottom Type-2 Staircase waist slab
Bottom Mid landing
Sides to steps

Sunshades top & Bottom


windows-W3
Grill windows-GW1
Grill windows-GW2
Grill windows-GW3
Ventilator-V
Ventilator-V1

2
2
2
1
1
1
0.5
0.5
0.5
0.5
0.5
2
2
2
2
0
2

x 2
x 2
x 2
x 2
x 1
x 1
x 42.0
x 22.0
x 8.0
x 6.0
x 3.0

5.46
7.53
3.41
3.07
3.41
5.00

x
x
x
x
x
x

1.80
3.70
2.72
3.51
2.80
1.20

58
4
4
2
4
48

0.30
0.48
1.5
1.67
2
2.23
0.3
0.3
0.5
0.3
0.3

0.15
0.15
0.15
0.15
0.15

0.6
0.6
0.6
0.6
0.6
0.6
or say

FF

SF
TF
Slab
beam side

2
2
1
1

x
x
x
x

2
2
2
2

3.90
4.67
5.46
5.12

0.30
0.30
0.30
0.30

22 Providing impervious coat to exposed RCC roof slab surfaces to required slopes
with CM (1:3) prop. 20mm thick (average) mixed with water proofing compound
manufactured by reputed manufacturers as approved by Engineer-in-charge at 1 Kg
per one bag of cement, laid over roof slab when it is green, finished smooth with a
floating coat of neat cement and thread lining at regular intervals of 45cmx45cm
including cost and conveyance of all materials like cement, sand, water proofing
compound, water etc., to site, including seigniorage charges, sales & other taxes on
over
portico in
GFoperational, incidental, and labour charges for mixing mortar,
all
materials
and
or say
laying, lift charges, rendering smooth and thread lining, curing including rounding
off
junctions
of wall and slab etc., complete for finished item of work. (APSS No. 901 &
SF
903)
TF
23 Flooring with Polished Shabad/Tandur blue Slabas 15 to 18 mm thick (0.457M x
0.457M) set over a base coat of CM (1:8), 12mm thick (joints of stone must be
flushed) over C.C. bed already laid or R.C.C. roof slab only after it is properly
cured, cleaned, moistered and where necessary treated with neat grey cement
slurry of honey like consistency spred at3.3 kgs of cement for 1 sqm. and jointed
with neat cement paste to full depth, including cost and conveyance of all materials
GF
like cement, sand, water, flooring stones etc. to site, seigniorage charges, sales and
other taxes on all materials, all operational, incidental and labour charges such as
Dormitory Halls
1
x 10
7.67 5.00
dressing of flooring stones to the required sizes, mixing of cement mortar, laying,
Clinic
Hall
1
x
1
7.67 5.00No.703 &
jointing, curing, lift charges etc., complete for finished item of work.(APSS
Wardens
room
cum
Lounge
1
x
1
7.67 5.00
701)
Entrance Lobby
1
x 1
7.67 5.00
Toilet blocks
1
x 4
8.00 1.77
Wash area
1
x 2
15.75
3.28
Corridor
1
x 1
64.36
2.50
Single staircase room
1
x 2
4.67 3.05

GF-AHDC

Page 34 of 517

21.84
30.12
20.46
10.25
6.82
11.15
6.30
3.30
2.00
0.90
0.45
125.28
17.76
13.06
8.42
0.00
69.12
1,643.36
1,644.00 sqm

#REF!

1,644.00
-41.11
-21.84
1,581.05 sqm

#REF!

1,581.05 sqm

#REF!

62.52
15.60
18.68
10.92
10.23
117.95 sqm

#REF!

38.41
39.00 sqm
1,036.59 sqm
62.52 sqm

383.50
38.35
38.35
38.35
56.64
103.16
160.90
28.49

#REF!

On midlanding
Double staircase area
On midlanding
At entrance area
Toilets

1
1
1
1
1

x
x
x
x
x

2
1
1
1
2

3.07
7.67
5.00
7.00
2.00

1.67
5.00
2.23
1.00
1.50

10.25
38.35
11.15
7.00
-6.00
908.49
909.00 sqm

#REF!

FF

909.00 sqm

#REF!

SF

909.00 sqm

#REF!

or say

24 Flooring with ceramic non-skid tiles of first quality as approved by Engineer-incharge 7.3mm thick manufactured by ISO approved firm of size 300mm x300mm
of colour and size as approved by the Engineer-in-charge set over a base coat of
CM (1:8) prop. 12mm thick over CC bed already laid including neat cement slurry
of honey like consistency spread at the rate of 3.30kgs of cement per Sqm. and
filling the joints with white cement paste mixed with pigment of matching shade
including cost and conveyance of all materials like cement, sand, water, ceramic
tiles, white cement etc., to site, (excluding cost of C.C. bed) including cost of
seigniorage charges and all other taxes on all materials, cost of base coat and all
labour charges for mixing of cement mortar, laying tiles to required slope as directed
by the Engineer-in-charge curing etc., in toilets for finished item of work for all
floors(APSS No.701 & 707). Ground Floor
Toilet Block
on hand wash platforms
Toilets in Clinic room & wardens room

4
1
1
1

x
x
x
x

12
2
2
2

1.50
11.02
2.68
2.00

1.2
0.6
0.6
1.5
or say

FF

SF

25 Providing skirting to internal walls 12.5cm high with polished Betamcherla pure white
stone minimum of 25 mm thick (.254Mx.254M) set over a base coat of CM(1:3),
12mm thick (joints of stone must be flushed) over C.C bed already laid or RCC roof
slab only after it is pr0perly cured, cleaned, moistered and where necessary treated
with neat grey cement slurry of honey like consistency spred at 3.3 kgs of cement for
1 sqm. and jointed with neat cement paste to full depth,including cost and
GF
conveyence of all materials like cement sand, water, flooring stones etc. to site ,
seigniorage
on 25.34
all materials 0.13
,all
Dormitory Hallscharges , sales and other
1
x taxes
10
operational,incidental and labour charges such as dressing of flooring stones to the
Clinic Hall
1
x 1
25.34
0.13
require sizes, mixing of cement mortar,laying,jointing,curing,lift charges etc.,
Wardens
room
cum
Lounge
1
x
1
25.34
0.13
complete for finished item.(APSS No.701&707)
Entrance Lobby
1
x 1
25.34
0.13
Toilet blocks
1
x 4
19.54
0.13
Wash area
1
x 2
38.05
0.13
Corridor
1
x 1
133.72
0.13
Single staircase room
1
x 2
15.44
0.13
On midlanding
1
x 2
9.48
0.13
Double staircase area
1
x 1
25.34
0.13
On midlanding
1
x 1
14.46
0.13
At entrance area
1
x 1
16.00
0.13
or say
FF

GF-AHDC

Page 35 of 517

86.40
13.22
3.21
6.00
108.83
109.00 sqm
109.00
-6.00
103.00 sqm

#REF!

#REF!

103.00 sqm

#REF!

31.68
3.17
3.17
3.17
9.77
9.51
16.72
3.86
2.37
3.17
1.81
2.00
90.38
91.00 sqm

#REF!

91.00 sqm

#REF!

91.00 sqm

SF
26 Dadooing to walls with white glazed tiles 1st. quality of any size of brand as
approved by Engineer - in - charge and set over a base coat of CM (1:5), 12mm
thick and neat cement paste at the rate of 3.3 Kg/Sqmt. and jointed with white
cement paste mixed with pigment of matching shade including cost and conveyance
of all materials like cement, sand, water, tiles, etc. to site, seigniorage charges, sales
and other taxes on all materials, C921 such as mixing of cement mortar, laying in
position, curing, lift charges etc., complete for finished item of work (APSS No.701
& 707) in All Floors
5.40
Toilet Blocks
4
x 12
1.80
8.00
Passage
4
x 2
1.80
0.75
Deduct doors
4
x 12
1.80
38.05
Wash basin area
1
x 2
1.80
3.00
Deduct Openings
1
x 1
1.80
Clinic Hall&Warden room toilets
7.00
1
x 2
1.80
0.75
Deduct doors
1
x 2
1.80
or say
FF

652.20 sqm

SF
27 Supplying and fixing of polished Black kadapa slabs of 15mm thick in a single piece
with the edges flat nosed and set over a base coat of CM(1:8) 12mm thick, and
fixing in position with neat cement paste including cost and conveyence of all
materials like cement,sand ,water,stones etc.to site , seigniorage charges , sales
and other taxes on all materials ,all operational,incidental and labour charges such
as dressing of flooring stones to the require sizes, mixing of cement
mortar,laying,jointing,curing,lift charges etc., complete for finished item.(APSS
No.701&707)
For Treads
At entrance area
2
x 4
1.00
0.5
2
x 3
1.00
0.3
Staircase
1
x 3
7.80
0.3
2
x 23
1.50
0.3
1
x 23
2.00
0.3
or say
FF

Staircase

2
2
1
2
1

x
x
x
x
x

4
3
3
23
23

1.00
1.00
7.80
1.50
2.00

0.15
0.15
0.15
0.15
0.15
or say

FF

1.20
0.90
3.51
10.35
6.90
22.86
23.00 sqm
23.00
-2.10
20.90 sqm
20.90 sqm

SF

GF-AHDC

4.00
1.80
7.02
20.70
13.80
47.32
48.00 sqm
48.00
-5.80
42.20 sqm
42.20 sqm

SF
Risers
At entrance area

466.56
115.20
-64.80
136.98
-5.40
25.20
-2.70
671.04
672.00 sqm
672.00
-25.20
5.40
652.20 sqm

Page 36 of 517

#REF!

#REF!

#REF!
#REF!

#REF!

#REF!
#REF!

#REF!

#REF!
#REF!

28 Granolithic concrete flooring 20mm thick with C.C. (1:1:2) proportion using 6mm to 12mm size
graded hard granite machine crushed metal laid monolithically over a bed of C.C. (1:5:10) prop.
10cm thick already laid in alternate panels of size not exceeding 1.50m x1.50m and providing 5mm
thick glass strips between the panels and finishing the top surface to required smoothness and
slopes, including cost and conveyance of all materials to work site (excluding cost of CC bed)
including cost of seigniorage charges and all other taxes on all materials and all operational,
incidental, labour charges such as mixing concrete, centering, laying, curing etc., complete for
Betweenitem
dormitory
halls
1
x 4
7.90 3.23
102.07
finished
of work
for all floors.(APSS No.710)
Between Toilet blocks

8.01

2.26

36.18

Between Toilet blocks & dormitory halls

4.40

3.23

28.39

4.67

2.23

20.83
187.47 sqm

29 Reinforced cement mortar facia 5cm thick in CM (1:3) for drop walls, fins & staircase
railing with rabbit wire mesh & nominal reinforcement as directed by Engineer-incharge with dubara sponge finishing, including cost & conveyance of all materials to
site, including seigniorage charges, sales and other taxes on all materials,
operational, incidental charges, cost & conveyance of cement, wire mesh, and water
to
site,area
centering, scaffolding and form1work,
curing etc., complete
At work
entrance
x lift2charges 5.20
0.90
but excluding cost of steel & its fabrication charges, as directed by Engineer -inStaircase
2
x
2
3.50
0.90
charge for finished item of work (APSS No.403 & 903) .
1
x 2
4.50
0.90
or say
FF

21.64 sqm

SF

GF-AHDC

9.36
12.60
8.10
30.06
31.00 sqm
31.00
-9.36
21.64 sqm

Page 37 of 517

#REF!

#REF!

#REF!
#REF!

30 Providing & Applying Synthetic Plaster Putty or Plaster of Paris Putty or Lime
punning of average 1 to 2mm thick over plastered surface to prepare the surface
even and smooth after thoroughly brushing the surface to remove all dirt and
remains of loose powdered materials, applying emery paper, sand the surface, clean
& wipe off loose dust, applying knifing paste filler by putty knife/muslin pad, air dry
for 2-3 hours, sand with 180 and 320 No, emery paper for the surface preparation
Same as 12
mmand
thick
plastering Qty.
including
cost
conveyance
of all materials to site, sales & other taxes, all
operational,
incidental12
and
labour
etc.,
complete for finished item of work for
Same as ornamental
mm
thick charges
plastering
Qty.
internal walls.
FF
Same as 12 mm thick plastering Qty.
Same as ornamental 12 mm thick plastering Qty.
SF
Same as 12 mm thick plastering Qty.
Same as ornamental 12 mm thick plastering Qty.

TF
Same as 12 mm thick plastering Qty.
Same as ornamental 12 mm thick plastering Qty.

All floors
31 Painting to new walls with 2 coats of Acrylic based Oil bound Washable Distemper
having VOC content less than 50 grams/litre over promer coat using white cemnt as
approved by Engineer-In-Charge, making 3 coats in all to give an even shade after
thourughly brushing the surface to remove all dirt and remains of loose powdered
materials, including cost and conveyance of all materials to work site and all
operational, incidental, labour charges etc., and overheads & contractors profit
Same as 12
thickitem
plastering
complete
for mm
finished
of workQty.
as per APSS 911 for internal walls in all floors.
Same as ornamental 12 mm thick plastering Qty.

FF
Same as 12 mm thick plastering Qty.
Same as ornamental 12 mm thick plastering Qty.
SF
Same as 12 mm thick plastering Qty.
Same as ornamental 12 mm thick plastering Qty.

TF
Same as 12 mm thick plastering Qty.
Same as ornamental 12 mm thick plastering Qty.

All floors
32 Providing and applying Altek / PMCC / Deco orient base or Equivalent exterior
Texture of average 2 to 3 mm thickness over plastered surface to prepare the
surface even and smooth after thoroughly brushing the surface to remove all dirt and
remains of loose powdered materials, applying emery paper, Sand the surface,
clean & wipe off loose dust, applying putty/ texture paint filler by putty knife / muslin
pad, air dry for
2 - 3 hrs for the surface preparation including cost and
conveyance of all materials to work site and all operational, incidental, labour
charges, scaffolding charges, overheads and
profit
etc., complete
for
1 contractors
x 1
64.82
11.70
finished item of work in all floors for external walls

GF-AHDC

Page 38 of 517

2,219.00
1,644.00
3,863.00 sqm

2,194.74
1,581.05
3,775.79 sqm
76.14
15.60
3,775.79 sqm

490.78
117.95
608.73
12,023.31 sqm

#REF!

2,219.00
1,644.00
3,863.00

2,194.74
1,581.05
3,775.79
2,194.74
1,581.05
3,775.79

490.78
117.95
608.73
12,023.31 sqm

#REF!

758.39 sqm

#REF!

33 Painting with weather proof plastic emulson grade -1 paint to exterior faces of new
walls with 3 coats of approved make shade and colour including self prime coat
including c/c of all materials like plastic emulsinn paint of Grade-1 to sitee including
cost of brushes scaffolding charges, lifiting charges and labour charges such as
preparing the wall applying three coats of plastik emlsion etc., complete for finished
item of work (APSS No 910,911 7 1201) in all floors
Same as 12 mm thick plastering Qty. for external walls

1,644.00

FF,
Same as 12 mm thick plastering Qty. for external walls

1,549.21

SF

1,549.21

TF
Same as 12 mm thick plastering Qty. for external walls

490.78
5,233.20 sqm

All floors
34 Supply and Fixing of Door with Double leaf shutter, Door Size 1.22x2.13 Mt. with
Medium Teak wood Frame of sections size 75mm x 100mm with Flush Door Shutter
Solid Bond Wood black board type with commercial ply on both faces of 35mm thick
including cost of fixtures such as M.S.Powder Coated Tower Bolts 250mm long 2
Nos, Alluminimum Handles 150mm long 2 Nos, 300mm long M.S.Powder Coated
Aldrops 1No, 125mm long M.S.Powder Coated butt hinges 6Nos, 300 mm long
GF
M.S.Powder
Coated Flat latch 1No, Door stoppers 2 Nos, MS Hold fasts 6Nos,
Sales and Other Taxes cost and convenyance of all materials to site all Labour
D1
1
x Fixing
11 in position , with Hardware
charges such as Fixing of Door Frame on shutter
FF,SF
fixtures etc., complete for finsihed item of work.
D1
2
x 11
TF
D1
1
x 3
35 Supplying & fixing of Medium Teak Wood Panneled Main Door of Size 4.00 Mts X
2.70 Mts made with outer frame of section 4"x5"(100x125mm) two horizontal and
four verticals fixed frame,Both sides fixed with Iron grill (size:1900 x 500mm) ,
(1850x500mm)madeup of Vertical & Horizontal bars of 10mm Square welded to
MS Flat 20x5mm alround forming (100x125mm) grid and with 5mm thick pin
headed glass panels (2Nos of 500mmX1900mm,
of
1
x 2'nos
1 of 500mm
1.00x 500mm,1 no
1.00
2600mmx500mm),
MT
beading
.The
shutters
should
be
made
up
of
size
650mm
36 Supply and Fixing of Door with Double leaf shutter, Door Size1.05x2.13 Mt. withx
1900mm
(4nos)
frame
with
2"thick(50mm)
and xscantlings(planks)
be 1"
Medium Teak
wood
Frame
of sections
size 75mm
100mm with Flushshould
Door Shutter
(25mm
thick)
including
fixing type
all fixtures
such as ply
350mm
Brass
Aldrops
Solid Bond
Wood
black board
with commercial
on bothlong
faces
of 35mm
thick,
200mm
Long
Towetr
bolts(8
nos),
Brass
fancy
Door
Handles
200mm
long
(2nos)out
including cost of fixtures such as M.S.Powder Coated Tower Bolts 250mm long 2
side,
150mm long Handles
(2nos) inside,
BrassHinges
150mm
long
(4x4=16Nos)
Nos, Alluminimum
150mm
long 2 Nos,
300mm
long
M.S.Powderincluding
Coated
polishing
with
melamine
finish
including
all
labour
charges
for
wrought
all
Aldrops 1No, 125mm long M.S.Powder Coated butt hinges 6Nos,
300&put
mmuplong
other
charges
stc.,
complete
for
finished
item
of
work.
M.S.Powder
Coated Flat latch 1No, Door 1stoppers
D2
x 32 Nos, MS Hold fasts 6Nos,
Sales
and
Other
Taxes
cost
and
convenyance
FF,SF
2
xof all
3 materials to site all Labour
charges such as Fixing of Door Frame on shutter Fixing in position , with Hardware
fixtures etc., complete for finsihed utem of work. D2
37 Providing and fixing factory made Polyvinyl chloride (PVC) Door Frame of the size
50 x 47mm with a wall thickness of 5mm, made out of extruded 5mm rigid PVC
foam sheet, mitre cut at two corners and joined with 2nos. of 150mm long brackets
of 15x15mm M.S. square tube. The two vertical door profiles are to be reinforced
with 19x19mm M.S. Square tube of 19 gauge. The door frame shall be fixed to the
wall using 65/100mm long M.S. Screws through the frame by using PVC fasteners.
A minimum of 4nos. of screws to be provided for each vertical member & minimum
2nos. for horizontal member etc. complete as per manufacturers specification and
direction of Engineer-in-Charge for finished item of work

11.00
22.00
3.00
36.00 Nos

#REF!

1.00 No

#REF!

3.00
6.00
9.00 Nos

#REF!

GF
D6
FF,SF
D6

GF-AHDC

50

5.00

250.00

48

5.00

480.00

Page 39 of 517

#REF!

730.00 Rmt
38 Providing and fixing 30mm thick Solid panel PVC door shutter consisting of frame
made out of M.S. tubes of 19 gauge thickness and size of 19mm x 19mm for stiles,
& 15mm x 15mm for top & bottom rails. M.S. frame shall have a coat of steel
primers of approved make and manufacture. M.S. frame shall be covered with 5mm
thick heat moulded PVC C channel of size 30 x 50mm forming stiles, and 5mm
thick, 75mm wide PVC sheets for top rail, lock rail & bottom rail on either side, and
10mm (5mm x 2) thick, 20mm wide cross PVC sheet as gap insert for top rail &
GF
bottom
rail. Panelling of 5mm thick PVC sheet to be fitted in the M.S. frame welded /
sealed
to the stiles & rails with 30mm wide
sheet beading2.13
on
D6
1 x 5mm
x 50thick PVC
0.75
either side, and joined together with solvent cement adhesive etc. An additional
5mm thick PVC strip of 20mm width is to be stuck on the interior side of the C
FF,SF
Channel using PVC solvent adhesive. Complete as per direction of Engineer-inD6
2 forx finished
48
2.13
charge, manufacturers specification & drawing
item0.75
of work .

39 Providing & Fixing of Openable Windows with Fly-mesh made of pre-painted steel
(Base Steel as per IS 513 of 0.6mm thick galvanized as per IS 277 with zinc of 150
GSM) primer coated with epoxy primer of 5-7 microns thick, finish painted with a
polyester paint of 12-16 microns thick and back coated with 5-7 microns thick alkyd
backer and the section for outer frame of 72 x 55mm, centre mullion of 72 x 50mm,
section for fixed glass beading section of 12 x 12 mm and section for shutters of 47
x 20 mm and outer frame & mullion sections with rebate for glazed shutters, fly
mesh
and a 20 mm provision for guard bars/grills and fly mesh shutter section of 20
GF,FF,SF
x 40 mm and the sections cut to length metre joined with corner bracket, centre
mullions
fixed with mullion cap, stay, handles,
2 Nos of 1.50
heavy duty stainless
W3
3 latch
x 58
1.35
steel pivot hinges per shutter and panelled with 5mm thick plain float glass and S.S.
Mesh for fly mesh shutter (304 grade), fitted using rubber gaskets

#REF!

79.88

153.36
233.24 sqm

#REF!

352.35 sqm

#REF!

40 #REF!

Ventilators
GF
V
V1

2
1

x
x

2
50

2.50
0.90

0.45
0.45

4.50
20.25
24.75

FF,SF
V
V1

2
1

x
x

2
48

2.50
0.90

0.45
0.45

4.50
19.44
47.88
72.63 sqm

41 Painting to wood work, flush shutters with luppam finish including applying luppam
coat over a primary coat and two coats of synthetic enamel paint of 1st grade and
approved brand and shade over a primary coat (Total 3 coats) including cost and
conveyance of all materials to site, cost of primer coat, brushes, and all labour
charges etc., complete. (APSS No. 1201, 1207 & 1212) for all floors.
D1
2.25 x 11
1.20
2.13
D2
2.25 x 3
1.05
2.13

63.26
15.10
78.36

FF,SF
D1

2.25 x

22

1.20

2.13

126.52

TF
D1
Main Door-MD

2.25 x
2.25 x

3
1

1.20
4.00

2.13
2.70

17.25
24.30
sqm

GF-AHDC

Page 40 of 517

#REF!

#REF!

42 Painting two coats with synthetic enamel paint 1st grade to new iron work including
cost and conveyance of all materials to site and all labour charges including lift
charges etc., complete for finished item of work. (SS NO. 1201,& 1212 & 1207) for
all floors.
GW
GW1
GW2
GW3

43

2
2
2
1

x
x
x
x

2
2
2
2

2.73
3.24
2.26
3.05

1.35
1.35
1.35
1.35

14.74
17.50
12.20
8.24
52.68 sqm

#REF!

Providing 110mm Dia P.V.C. down water take pipes 2.5mm thick and of 4 kg /

Sq.cm pressure of ISI marked including cost and conveyance of necessary P.V.C.
Bends, shoes, iron, clamps and all other accessories and fixing in position
including cost and conveyance of all materials to site including all labour charges for
fixing at site etc., complete or finished item of work.(APSS No.1328)

44

Providing and Fixing of expansion join filler board for Buildings , Columns , Beams
and Slabs Armour Board " sillfill including cost and convenyance of all materials to
site, all incidental, operational , labour charges etc., complete for finished item of
work as per approved drawing for all floors

45

Providing Expansion joint treatment with poly sulphide compound of approved


make of finished size 25 x 12mm including making of 25mm x 12mm groove and
primer coat over finished groove with finishing of edges true to straight line and
level over the finished surface of expansion joint including cost and conveyance of
all materials to site, all incidental, operational, labour charges etc. complete for
finished item of work as per approved drawing (for all floors on top of slab i.e in
the flooring
and
for internal
vertical
joints of grooves
in dadooing
surface)
Providing
and
fixing
of 24 gauge
alluminium
sheet over
expansion
joint groove of
width 15cm fixed to walls / columns at one edge and resting over the other block
walls/columns concealing expansion joint with slotted holes for free edge of
aluminium sheet to facilitate free movement of aluminium sheet over the finished
surface of expansion joint and wall face using sheet metal screws with nylon
receiverand
complete
all materials
to roof
site, slab
all
Supply
fixing ofincluding
230 mmcost
wideand
PVCconveyance
water bar atofexpansion
joint over
incidental,
operational,
charges
complete
finished
item
of work
as
including cost,
all taxes andlabour
conveyance
of alletc.
materials
to sitefor
and
all labour
charges,
cutting
per fixing
approved
drawing
(for allfor
floors
for vertical
joints and bottom of slab)
and
charges
etc. complete
finished
item of work.

46

47

48

248.00

Rmt

#REF!

35.00

Sqm

#REF!

192.00

Sqm

#REF!

31.00

Sqm

#REF!

0.00

Rmt

#REF!

50.00

Rmt

#REF!

155.57
46.08
27.62
18.96
10.55
57.64
56.88
11.21
384.50

Sqm

#REF!

Supplying, laying, aligning & jointing of RCC Hume Pipes of 300mm dia NP2 Class

including all necessary fixtures like collars of respective diametre including cost and
conveyance of all materials to site, sales and other taxes on all materials, lifting, placing and
fixing in position, all labour charges, curing etc complete for finished item of work.

49 Providing Plinth protection with a bed of 100mm thick PCC(1:5:10) using 40mm

size HBG metal and on top of PCC, 20mm thick granolithic concrete flooring with
CC(1:1:2) prop.using 6mm to 12mm size graded hard granite machine crushed
metal laid monolithically already laid, in alternate panels of size not exceeding 1.5
x 1.5 Mts. and providing 5mm thick glass strips between the pannels and finishing
the top surface to required smoothness and slopes including Grooves, thread lining
as directed by the Engineer - in - charge including cost and conveyance of all
materials to site including seigniorage charges, sales & other taxes on all
x charges
2
64.82
0.60
materials and operational & incidental and2 labour
like
mixing of cement
x 2including
19.20
concrete, laying, curing, lift charges etc., 2
complete
cost of CC bed0.60
for
finished item of work. (APSS No.701 & 710) 2
x 2
11.51
0.60

2
2
2
2
2

GF-AHDC

x
x
x
x
x

2
2
6
6
2

7.90
4.40
8.01
7.90
4.67

Page 41 of 517

0.60
0.60
0.60
0.60
0.60

50 Construction of Rain water harvesting structure as per the approved drawing and
design of size 2 x 1.5 m x 2.0 mm including earth work excavation of filling of 40 mm
size HBG metal up to 50% of volume, filling of 20 mm size 15% of colume.
Sonstruction of side walls in brickmasonry in CM (1:6) 230 mm thick and 450 mm
height, plastering the side walls in (1:6) 16 mm thick base coat and top coat of 4 mm
51 Filling
with Gravel
trenches,
sidesproviding
of foundations
and basement
with initial
in
thick with
dubara insponge
tinish,
coir mat
to avoid spillage
of lead
water
layers
not
exceeding
15cm
thick,
consolidating
each
deposited
layer
by
watering
and
including cost and conveyance of all materials to site and all albour charges etc.,
ramming
cost
andofconveyence
of water to the work site and all operational,
complete including
for finished
item
work.
incidental, labour charges, seignorage charges, hire charges of T & P etc., complete
for finished item of work. (APSS NO. 309 & 310)
Dormitory Halls
Toilets
Wash area
Wardens room cum Lounge
Clinic hall
Type-1 Stair case
Type-2 Stair case
Entrance Lobby
Corridor
Under entrance steps

1
1
1
1
1
1
1
1
1
1

X
X
X
X
X
X
X
X
X
X

10
4
2
1
1
2
1
1
1
1

7.67
5
8.00
5
15.75 3.275
7.67
5
7.67
5
4.56 3.07
7.67
5
7.67
5
63.32
2.5
7.00
1

1.90
1.90
1.90
1.90
1.90
1.90
1.90
1.90
1.90
1.90

or say
52 Filling with light weight cider material in sunken slabs including cost and conveyance
of all materials and labour charges etc. complete for finished item of work
2
53

8.00

0.15

4.00 Nos

#REF!

728.65
304.00
196.01
72.87
72.87
53.14
72.87
72.87
300.77
13.30
1,887.33
1,888.00 cum

#REF!

48.00 cum

#REF!

19.20

Rmt

#REF!

19.20

Rmt

#REF!

Drilling 25mm dia holes in Sheet Rock with Pneumatic Compessor including hire
chrges of T&P and labour charges etc., complete for finished item of work.
MB. No.326/A/MD, Pg. No.10

54

1
x 24
0.80
Grouting 25mm dia holes in Sheet Rock with neat cement slurry including cost and
conveyance of all materials and labour charges etc., complete, but excluding cost of
steel and its fabrication chares for finished item of work.
MB. No.326/A/MD, Pg. No.11

1
x
PART B

24

0.80

PART A+B

Asst. Engineer(HNK)
APEWIDC, WARANGAL

GF-AHDC

Dy. E.E, HNK


APEWIDC, WGL

Page 42 of 517

Executive Engineer
APEWIDC, WARANGAL

Superintending
APEWIDC, H

HANAMKONDA(M) IN

Per

GF-AHDC

Amount

Page 43 of 517

GF-AHDC

Page 44 of 517

GF-AHDC

Page 45 of 517

GF-AHDC

Page 46 of 517

GF-AHDC

Page 47 of 517

1 Cum

#REF!

1 Cum

#REF!

GF-AHDC

Page 48 of 517

GF-AHDC

Page 49 of 517

GF-AHDC

Page 50 of 517

1 cum

GF-AHDC

#REF!

Page 51 of 517

GF-AHDC

Page 52 of 517

GF-AHDC

Page 53 of 517

1 cum

GF-AHDC

#REF!

Page 54 of 517

1 Cum

#REF!

1 cum

#REF!

1 cum

#REF!

GF-AHDC

Page 55 of 517

GF-AHDC

Page 56 of 517

GF-AHDC

Page 57 of 517

1 cum

#REF!

1 cum

#REF!

1 MT

#REF!

GF-AHDC

Page 58 of 517

GF-AHDC

Page 59 of 517

1 Sqm

#REF!
#REF!

1 cum
1 cum
1 cum

#REF!

GF-AHDC

Page 60 of 517

1 cum

#REF!

1 cum
1 cum
1 cum

#REF!

1 cum

#REF!

GF-AHDC

Page 61 of 517

1 sqm
1 sqm
1 sqm

#REF!

1 sqm

#REF!

1 sqm
1 sqm
1 sqm

#REF!

1 cum

#REF!

1 cum

#REF!

GF-AHDC

Page 62 of 517

1 cum

#REF!

1 sqm
1 sqm
1 sqm

#REF!

sqm
sqm
sqm

#REF!

1 cum
1 cum
1 cum

#REF!

GF-AHDC

Page 63 of 517

1 cum
1 cum
1 cum

GF-AHDC

#REF!

Page 64 of 517

1 cum

#REF!

1 cum

#REF!

1 cum

#REF!

1 cum

#REF!

GF-AHDC

Page 65 of 517

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

1
1
1
1

Mt
Mt
Mt
Mt

#REF!

1 Mt
1 Mt
1 Mt

#REF!

GF-AHDC

Page 66 of 517

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

GF-AHDC

Page 67 of 517

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

GF-AHDC

Page 68 of 517

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

1 sqm
1 sqm
1 sqm

#REF!

GF-AHDC

Page 69 of 517

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

GF-AHDC

Page 70 of 517

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

GF-AHDC

Page 71 of 517

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

GF-AHDC

Page 72 of 517

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

GF-AHDC

Page 73 of 517

1 sqm

#REF!

1 Nos

#REF!

#REF!

No

1 Nos

GF-AHDC

#REF!

Page 74 of 517

1 Rmt

#REF!

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

1 sqm

#REF!

GF-AHDC

Page 75 of 517

#REF!

1 Rmt

#REF!

1 Sqm

#REF!

1 Sqm

#REF!

1 Sqm

#REF!

Rmt

#REF!

Rmt

#REF!

1 Sqm

GF-AHDC

#REF!

Page 76 of 517

#REF!

1 cum

#REF!

1 cum

#REF!

1 Rmt

#REF!

1 Rmt

#REF!

#REF!
#REF!

erintending Engineer
PEWIDC, HYDERABAD

GF-AHDC

Page 77 of 517

WORKING ESTIMATE
Name of the Work :- Construction of Govt. Degree College at KUPPAM(V) of KUPPAM (M) CHITTOOR District
Sl. No

Description

General Abstract Comparative Statement


As per Sanction
As per Working
Estimate
Estimate

1 Schooll Building (G +1)


1 Civil Work

36149188.00

Internal and External water Supply and Sanitary


2
items
3 Internal Electrification
Sub Total:
2 Dormitory (G+1)
1 Civil Work
2

Internal and External Water Supply and Sanitary


items

3 Internal Electrification
Sub Total:
3 Kitchen Block cum Dining
1 Civil Work
2

Internal and External Water Supply and Sanitary


items

3 Internal Electrification
Sub Total:
4 Principal Quarter
1 Civil Work
2

Internal and External Water Supply and Sanitary


items

3 Internal Electrification
Sub Total:
5 Teaching Staff Quarters (G + 2) 1 block
1 Civil Work
2

Internal and External Water Supply and Sanitary


items

Excess

Less

#REF!

Due to
change of
Site &
Designs

743252.00
1395681.00
38288121.00

#REF!

44081148.00

#REF!

#REF!

#REF!

1042228.00
1784147.00
46907523.00

#REF!

8507495.00

#REF!

#REF!

#REF!

Due to
change of
Site &
Designs

Due to
change of
Site

156928.00
661112.00
9325535.00

#REF!

1866275.00

#REF!

#REF!

#REF!

Due to
change of
Site

156944.00
153548.00
2176767.00

#REF!

6574642.00

#REF!

606831.00

Remarks

#REF!

#REF!

Due to
change of
Site

3 Internal Electrification
Sub Total:
6
7
8
9
10

Septic Tank for 200 users (1No)


Septic Tank for 100 users
For Construction of Sump
Provision for 60,000 liters capacity OHSR
For External Electrification as per sub estimate

478393.00
7659866.00
2139322.00
648609.00
567478.00
1652103.00
787709.00

Due to
change of
Site
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#VALUE!
#VALUE!

#REF!
#REF!
#REF!
#REF!
0.00
0.00

11
12
13

For Construction of Compound Wall


for External Drainage

#VALUE!
#VALUE!

0.00
0.00

#REF!

#REF!

154850.00

0.00

0.00

100000.00
500000.00
1000000.00
2000000.00
1000000.00
5554871.00
5554871.00
1110974.00
1110974.00
555487.00

100000.00
500000.00
1000000.00
2000000.00
1000000.00
#REF!
#REF!
#REF!
#REF!
#REF!

0.00
0.00
0.00
0.00
0.00
#REF!
#REF!
#REF!
#REF!
#REF!

0.00
0.00
0.00
0.00
0.00
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!

311933.00

#REF!

#REF!

Grand Total: Rs.

#REF!

#REF!

#REF!

#REF!

As per Sanction Estimate


As per Working Estimate
Difference

#REF!
#REF!
#REF!

Excess
Less
Difference

#REF!
#REF!
#REF!

Sub Total:
Deduct Tender Premium @ ( - ) 2.70% Less

14

Providing 4 Bore Wells, 2 fitted with motors &


fitted with hand pump sets

15
16
17
18
19
20
21
22
23
24

Provision
Provision
Provision
Provision
Provision
Provision
Provision
Provision
Provision
Provision

25

Provision for variation in Quantities, Tender


publication charges unforseen items and
rounding off

for
for
for
for
for
for
for
for
for
for

site development
Transformer
Internal roads
furniture and equipment
Tender premium and price escalation
VAT @ 5%
Supervision Charges @ 5%
Seignorage Charges @ 1%
Cess @ 1%
Q.C Charges @ 0.5%

Asst. Engineer(HNK)
APEWIDC, Warangal

314818.00
629567.00
6739606.00
111097418.00
0.00
111097418.00

#REF!
#REF!
#REF!
#REF!

154850.00

Dy. Executive Engineer(HNK)


APEWIDC, Warangal

Executive Engineer
APEWIDC, Warangal

Superintending Engineer
APEWIDC, Hyderabad

Chief Engineer
APEWIDC, Hyderabad

Septic Tank 200 Users Civil Abstract.

Units

ABSTRACT ESTIMATE OF SEPTIC TANK FOR 200 USERS


Name of the Work :- Construction of Govt. Degree College at KUPPAM(V) of KUPPAM (M)
CHITTOOR District
Sl.
No
1

Description of Work

Quantity

Unit

Unit

Rate (Rs)

CIVIL WORK
Earth work excavation for foundation of Septic
Tank and depositing the earth on bank with an
initial lead of 10m and lift of 2m in Loamy, and
clayey soils like Black cotton, red earth, ordinary
gravelly soils including shoring, strutting, sheeting,
planking and dewatering including hire charges of
T&P, labour charges etc., complete for finished item
of work. (APSS. No.308)
0 CUM

1 ONE CUM

132.35

0 CUM

1 ONE CUM

3413.65

0.00 CUM

1 ONE CUM

6401.60

Plain Cement Concrete in (1:5:10) proportion


nominal mix (cement: fine aggregate: Coarse
aggregate) for foundations and under flooring bed
using 40mm size (SS 5) hard machine crushed
granite metal including cost and conveyance of all
materials like cement, sand, coarse aggregate,
water etc., to site, including seigniorage charges,
sales and other taxes on all materials and including
all charges for machine mixing, laying concrete in
foundations and for flooring bed, ramming, finishing
top surface to the required level, curing etc.,
complete for finished item of work (APSS No.402).

Plain Cement Concrete (1:2:4) proportion nominal


mix (Cement:Fine aggregate: Coarse aggregate)
using 20mm size (SS5) graded machine crushed
Hard granite metal (Coarse Aggregate) from
approved quarry including cost & conveyance of all
materials like cement, Fine aggregate(Sand),
Coarse Aggregate, water etc. to site including
seigniorage charges, sales and other taxes on all
materials and all operational, incidental, labour
charges such as centering, shuttering, machine
mixing, laying concrete, curing etc., complete but
excluding cost of steel & its fabrication charges, for
Septic Tank for finished item of work. (APSS No.
402 & 03)

Page 1

Septic Tank 200 Users Civil Abstract.


Sl.
Description of Work
No
4 Brick Masonry for foundation and basement with
CM (1:6) prop: using Fly ASH Bricks of size
290x225x140mm with compressive of 50 Kgs /
Sqcm from approved source including cost and
conveyance of all materials like cement, sand, fly
ash bricks, water etc., to site, including seigniorage
charges, sales & other taxes on all materials, all
operational, incidental and labour charges such as
mixing cement mortar, constructing masonry,
scaffolding charges, lift charges, curing, etc.,
complete for finished item of work. (APSS No. 501
& 504). for soak pit

Quantity

Unit

Unit

Rate (Rs)

0 CUM

1 ONE CUM

5036.65

0 CUM

1 ONE CUM

#REF!

a) 150 mm thick Slab

0 SQM

1 ONE SQM

1206.75

b) 115 mm thick Roof Slab

0 SQM

1 ONE SQM

999.15

Cum

1 ONE Cum

9477.10

Filling with useful available excavated earth


(excluding rock) in trenches, sides of foundations
and basement with initial lead in layers not
exceeding 15cm thick, consolidating each
deposited layer by watering and ramming including
all operational, incidental labour charges , hire
charges of T&P etc., complete for finished item of
work.(APSS No. 309 &310)

Vibrated reinforced cement concrete M20 Grade


Desing mix ( by weigh batching) using 20 mm
size (SS5) hard granite machine crushed graded
metal (coarse aggregate) from approved quarry
using miminum quantity of 350 Kgs of cement per 1
cum of concrete including cost and conveyance of
all materials like cement, fine aggregate (Sand),
coarse aggregate, water etc. to site including
seigniorage charges, sales & other taxes on all
materials, all operational, incidental, and labor
charges such as Providing Centring, shuttering and
scaffolding with props and steel plate as per the
approved shuttering plan and other accessories as
per the norms and stability calculations including
cost and conveyance of all accessories Using
Cashewrina Ballies and Wooden runners & staging
including all bracings, cross members etc complete
for finished item of work, lift charges, machine
mixing, laying concrete, vibrating, curing concrete
etc, complete but excluding cost of steel and its
fabrication charges etc complete for finished item
of work (APSS No.402 & 403)

c) 150mm & 200mm Thick Side walls

0.00

Page 2

Septic Tank 200 Users Civil Abstract.


Sl.
Description of Work
No
7 Providing High Yield Strength Deformed steel bars
(Fe 415grade as per IS 1786-1979) of different
diameters, including labour charges for cutting,
bending to required sizes and shapes placing in
position with cover blocks of approved materials
and size and tying with binding wire of 20SWG,
foRMing grills for reinforcement work as per
approved designs and drawings, including cost and
conveyance of steel bars, including all wastages
such as overlaps, couplings, welded joints, chairs,
spacer bars including cost and conveyance of
binding wire, cover blocks and all incidental,
operational, labour charges such as cutting,
bending, placing in position, tying including sales
and other taxes and all materials etc., complete for
finished item of work in all floors.(APSS No.126)

Quantity

Unit

Unit

Rate (Rs)

0 MT

1 ONE MT

#REF!

0 SQM

1 ONE SQM

337.25

0 Nos

1 ONE EACH

2295.05

0 Nos

1 ONE Nos

2552.95

Providing impervious coat to exposed RCC roof


slab surfaces of sump, sump side wall, sump
bottom slab, in side of septic tank, in sunken
slabs etc., to required slopes with CM (1:3) prop.
20 mm thick mixed with water proofing compound
manufactured by reputed manufacturers as
approved by Engineer-in-charge at 1 Kg per one
bag of cement, laid over roof slab when it is green,
finished smooth with a floating coat of neat cement
and thread lining at regular intervals of 45cmx45cm
where ever necessary including cost and
conveyance of all materials like cement, sand,
water proofing compound, water etc., to site,
including seigniorage charges, sales & other taxes
on all materials and operational, incidental, and
labour charges for mixing mortar, laying, lift
charges, rendering smooth and thread lining, curing
including rounding off junctions of wall and slab
etc., complete for finished item of work(APSS No.
901 & 903).

Supply and Fixing of 914.4mm x 457.2mm Light


Weight CI Manhole Frame and Cover (30 Kgs)
complete for finished item of work including cost
and conveyance of all materials to site, all labour
charges, sales and other taxes on all materials
etc., complete for finished item of work.
Initial cost SSR item No 656

10 Supply and fixing of 100 mm dia CI Vent pipe of 3


mts lenth fitted with AC cowl and mosquito proof
wire mesh including cost and conveyance of all
materials to site complete for finished item of work.

Page 3

Septic Tank 200 Users Civil Abstract.


Sl.
No

Description of Work

Quantity

Unit

Unit

Rate (Rs)

11 Plastering 12mm thick in two coats with base coat


of 8mm thick in CM(1:6) and top coat of 4mm thick
in CM(1:4) dubara sponge finish including cost and
conveyance of all materials like cement, sand
,water etc. to site, seigniorage charges,sales &
other taxes on all materials,all operational,icidental
and labour charges such as mixing mortar,
scaffolding charges, lift charges, including cutting of
Grooves wherevver necessary as directed by
Engineer-in-charge,finishing mcuring,etc.,complete
for Even surfaces of wall for finished item of work
(APSS901,903&904) in Ground floor

0 SQM

1 ONE SQM

Sub Total - Civil

Rs

Asst. Engineer (APEWIDC)


Section : KUPPAM

Dy. Executive Engineer (APEWIDC)


Sub-Division : CHITTOOR

Executive Engineer (APEWIDC)


Division : CHITTOOR

Superintending Engineer (APEWIDC)


Circle : KADAPA

Page 4

289.05

Septic Tank 200 Users Civil Abstract.

MATE OF SEPTIC TANK FOR 200 USERS


of Govt. Degree College at KUPPAM(V) of KUPPAM (M)
CHITTOOR District
Amount
(Rs.)

Page 5

Septic Tank 200 Users Civil Abstract.


Amount
(Rs.)

0
0
0

Page 6

Septic Tank 200 Users Civil Abstract.


Amount
(Rs.)

#REF!

Page 7

Septic Tank 200 Users Civil Abstract.


Amount
(Rs.)

#REF!

Page 8

SPECIFICATION REPORT
Est.cost: Rs.1030.00 Lakhs
Name of the Work :- Construction of Govt. Degree College at KUPPAM(V) of KUPPAM
(M) CHITTOOR District

Authority:
The work const. of Govt. Degree College at Kuppam in Chittoor dist was administratively
sanctioned for Rs. 1030.00 lakhs vide G.O.Rt.No. 2973 Finance (FMU Education) Dept., dt: 29
12-2015 . The Secretary to Govt. (B & IF), A.P., Hyderabad has accorded administrative sanction
for Rs. 1030.00 lakhs.

Ground Floor
Pricipal room

1 No

Ante room

1 No

Office room

1 No

Staff room

1 No

Labs

6 Nos

NSS coordinator room

1 No

Open auditorium

1 No

Toilet blocks

2 units

Stair case

2 Nos

Portico

1 No

First Floor
Class rooms

7 Nos

Lunch rooms

2 Nos

Library cum recreation hall

1 No

PET room

1 No

Toilet blocks

2 units

Stair case

2 Nos

Lobby

1 No

Second Floor
Computer lab
Audio & Video room
Stair case
Head rooms
RCC water tank

:
:
:
:
:

1
1
2
2
1

No
No
Nos
Nos
No

Provisions:
The Detailed Estimates are prepared with following common provisions:

A)

Foundations and Sub-Structure:

1. Earth work excavation in all types of soils for open foundations

2. P.C.C (1:5:10) prop: nominal mix for levelling course in foundations and as bed concrete
for flooring.
3. P.C.C (1:4:8) prop: nominal mix for foundations for columns.

4. VRCC M 20 grade design mix ( by weigh batching), using 20mm HBG machine crushed
graded metal for Footings, Pedestals, Plinth beams and Columns up to plinth level.
5. Random Rubble Stone masonry in CM(1:8) prop, for basement.

6. Filling with useful available excavated earth in trenches, sides of foundations and fo
basement.
7. Flush pointing to RRS masonry in CM (1:3) for basement.
B)

Superstructure:

1. VRCC M 20 grade design mix ( by weigh batching), using 20mm HBG machine crushed
graded metal for Columns, Roof Beams, Roof Slabs.
2. Providing HYSD bars Fe 415 for all diameters more than 6mm for VRCC & RCC work.
3. Providing Mild Steel Fe 250 for 6mm bars for VRCC & RCC work.

4. P.C.C (1:3:6) prop: nominal mix for Bed Blocks and Hold Fasts.
5. RCC (1:2:4) prop. Nominal mix using 12mm HBG machine crushed graded metal fo
Lintels, 50mm thick platforms.

6. RCC M 25 grade design mix ( by weigh batching), using 20mm HBG machine crushed
graded metal for sun shades, 7.5cm thick at fixed end and 5.0 cm thick at free end, o
any width as per approved plan .

7. PCC M20 grade Design Mix ( by weigh batching), using 20mm HBG machine crushed
gradedmetal for steps .
8. Brick masonry in CM(1:8) prop. using 2nd class traditional bricks for Superstructure.

9. Reinforced Brick masonry 115mm thick in CM(1:4) prop. using 2 nd class traditional brick
for Partition walls.

10. Plastering 12 mm thick in two coats, base coat 8mm thick in CM(1:6) and top coat 4mm
thick in CM(1:4) for even face of walls.

11. Plastering 20 mm thick in two coats, base coat 16mm thick in CM(1:6) and top coat 4mm
thick in CM(1:4) for uneven face of walls.
12. Ornamental Plastering to ceiling, 12 mm thick in single coat in CM(1:4).
13. Providing impervious coat over RCC roof slab, in side of septic tank to required slope
with CM (1:3) prop. 20 mm thick (average) mixed with water proofing compound.

14. Flooring with Polished Shabad/Tandur blue Slabas 15 to 18 mm thick (0.457M x 0.457M
set over a base coat of CM (1:8), 12mm thick over already laid C.C. bed or R.C.C. roo
slabs.

15. Providing Skirting to internal walls to 12.5 cm height with Rough shabad / Tandur Stone
slabs of minimum 40 mm thick (0.457 x 457M) slabs 15mm to 18mm thick.

16. Dadooing to walls with coloured glazed tiles 1st. quality of size not less than 300mm x
200mm.
17. Whiting to new walls and ceiling in two coats with Birla white or equavalent quality fo
internal walls.

18. Painting with Plastic emulsion grade -1 paint to exterior faces of new walls with 3 coats o
approved make shade and colour.
19. Painting to wood work, flush shutters with luppam finish.
20. Painting two coats with synthetic enamel paint 1st grade to new iron work.
21. Supply and Fixing of Collapseble Gate of Size 2.0X2.10 mtrs

22. Supply and Fixing of Door with Double leaf shutter, Door Size 1.22x2.13 mtrs with
Medium teak wood Frame

23. Supply and Fixing of Door with Single leaf shutter, Door Size 0.90x2.13 mtrs with
Medium Teak Wood Frame of sections size 75mm x 100mm with Flush Door Shutter Solid
Bond Wood black board type with commercial ply

24. Providing & Fixing of Openable Windows with Double shutter made of pre-painted stee
(Base Steel as per IS 513 of 0.6mm thick galvanized as per IS 277 with zinc of 150 GSM
primer coated with epoxy primer of 5-7 microns thick

25. Supply and fixing of MS Ventilators with sections made of MS angles of 25mm X 25mm X 3mm and
10mm X 10mm square rods ( Sizes: 1200 mm x 450 mm & 900 mm x 450 mm).
AMENITIES:

1) Sub-Estimate is prepared for Water supply and Sanitary Arrangements as per the
requirements based on approved plan.

2) Sub-Estimate is prepared for Internal Electrification as per the requirements based on


approved plan.
3) Sub-Estimate is prepared for
plan.

CC roads

as per the requirements based on approved

DATAS & RATES:

The Data of all the items are adopted as per the Revised Standard Data Part-II
(Buildings) and the rates are worked out based on current SSR i.e Building SSR 2014-2015
Cement and Steel rates are adopted as approved by the Committee of the Chief Engineers for
May, 2015
SPECIFICATIONS:

The Standard specifications as per APSS are adopted and the work will be carried ou
true to the relevant standard specification of APSS and as per the agreement conditions.
Quarries:

The nearest leads, quarries are adopted while preparing the Datas, and as per the
location of the site 0% allowance on labour is proposed towards Rural area allowence

Overhead Charges & Contractors Profit:

14% towards overhead charges and contractors profit put together has been proposed in
the estimates which is as per the Revised Standard Data - Part-III (Buildings), ordered
by the Government of A.P vide G.O.Ms.No.49, IRRIGATION & CAD (PW-REFORMS
DEPARTMENT Dated: 2-3-2009, for adoption by all Engineering /Public Work
Departments and other organizations.

Lump sum amounts at the rate of 5% towards VAT has been added in the Abstracts of
the estimates ,, which is as per the Revised Standard Data - Part-III (Buildings), and the
same is provided at 5% of ECV.
The estimate is submitted for according technical sanction.

Executive Engineer
Dy. Executive Engineer
APEWIDC, CHITTOOR APEWIDC, MADANAPALLI

Superintending Engineer
APEWIDC, KADAPA

Asst. Executive Enginee


APEWIDC, KUPPAM

0.00 Lakhs

KUPPAM(V) of KUPPAM

oor dist was administratively


U Education) Dept., dt: 29rded administrative sanction

provisions:

dations and as bed concrete

0mm HBG machine crushed


mns up to plinth level.

nt.

des of foundations and for

0mm HBG machine crushed

m for VRCC & RCC work.

rk.

s.
e crushed graded metal for

0mm HBG machine crushed


5.0 cm thick at free end, of

0mm HBG machine crushed

ks for Superstructure.

ng 2 nd class traditional bricks


CM(1:6) and top coat 4mm

n CM(1:6) and top coat 4mm

n CM(1:4).

ptic tank to required slopes


proofing compound.

m thick (0.457M x 0.457M)


laid C.C. bed or R.C.C. roof

ough shabad / Tandur Stone


to 18mm thick.

size not less than 300mm x

te or equavalent quality for


of new walls with 3 coats of

ew iron work.
Size 1.22x2.13 mtrs with

Size 0.90x2.13 mtrs with


with Flush Door Shutter Solid

r made of pre-painted steel


S 277 with zinc of 150 GSM)

s of 25mm X 25mm X 3mm and


450 mm).

Arrangements as per the

the requirements based on

ements based on approved

ised Standard Data Part-III


e Building SSR 2014-2015.
of the Chief Engineers for

the work will be carried out


ement conditions.

g the Datas, and as per the


area allowence

gether has been proposed in


Part-III (Buildings), ordered
ON & CAD (PW-REFORMS)
Engineering /Public Works

n added in the Abstracts of


Part-III (Buildings), and the

Asst. Executive Engineer


APEWIDC, KUPPAM

Sl.
No
1
2

GENERAL ABSTRACT
Name of the work : CONSTRUCTION OF GOVT.JUNIOR COLLEGE AT
GUDIPALLI(V), GUDIPALLI(M), IN CHITOOR DIST.
Name of Component
Ground Floor

Amount in Rs.
17085825

First Floor

10850537

Second Floor

3516470

Construction of Septic Tank (as per sub


estimate)

238294

Providing Water Supply & Sanitary


Arrangements (as per sub estimate)

692246

Internal Electrification (as per sub estimate)

1700465

Const. of Compound wall of 650mts length (as


per sub estimate)

3586912

Laying of internal CC roads of 340mtrs length


(as per sub estimate)

1391625

Play ground levelling & filling low level area


with gravel (as per sub estimate)

2043828

Sub Total >>>

41106202
2055310

10

Provision for VAT @ 5%

11

Provision for PS Charges @ 7%

12

Provision for Q.C charges @ 0. 5%

205531

13

Provision for Labour Cess @ 1 %

411062

14

Provision for Seinarage Charges @ 1%

411062

15

Provision for NAC charges @ 0.1%

16
17

Towards Drilling of bore wells & fixing of


submersible pumpset
L.S.
Provision for laying of foundation stone &
Inaguration
L.S.

18

Provision for DPR including surveying &


preparation of layouts & SBC structural
architectural drawings etc. (30910 Sft x 8.00)
L.S.

19

Provision for Tender Publication chargesL.S.

2877434

41106
400000
50000

250000

50000

20
21

Towards Price Escalation for Steel & Cement


L.S.
External Electrification ( Poles, Transformer
etc.)
L.S

300000
200000

22

Provision for RO plant

L.S.

300000

23

Provision for unforeseen items

L.S.

54342293

Grand Total of Civil Works >>>


24

Add L.S towards furniture & Lab equipement


L.S.

103000000
4000000

Grand Total of Civil Works >>>

107000000

Or say

1070.00

Executive Engineer
APEWIDC, CHITTOOR

Dy. Executive Engineer


APEWIDC, MADANAPALLI

Superintending Engineer
APEWIDC, KADAPA

Asst. Executive Engineer

APEWIDC, KUPPAM

Name of the Work :- Construction of Govt. Degree College at KUPPAM(V) of KUPPAM (M) CH
District
Measurements

Sl.
Description of item
No.

Nos.

QTY

Unit

2
3
4
5
6
7
GROUND FLOOR
1 Cutting of gravel & leveling of ground by,Earth work excavation for foundations
(Mechanical Means) for buildings in ordinary soils and depositing on bank for all
lifts and with an initial lead of 10m and up to 3m depth including all
operational,incidental, labour charges such as shoring, sheeting, planking,
strutting etc., and overheads & contractors profit complete for finished item of
work excluding dewatering charges etc., as per SS 20 B(APSS 308)
For building area

720.00
720.00
Or say
720.00 Cum
2 Earth work excavation and depositing on bank (manual means) with initial lead
of 10m and initial lift of 3m in Loamy & Clayey Soils like BC Soils, Red Earth &
Ordinary Gravelly Soils ( SS 20-B) including all operational incidental labour
charges such as shoring, strutting, sheeting, planking and dewatering including
cost of hire charges of T & P, labour charges etc., complete for finished item of
work excluding seignerage charges and dewatering charges etc., complete for
Foundation of Building.(APSS No. 308)

80.00

10.00

1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x

11
20
20
7
19
14
18
2
4
6

2.60
2.50
2.30
2.15
2.00
1.80
1.65
1.40
1.80
2.95

2.60
2.50
2.30
2.15
2.00
1.80
1.65
1.40
1.50
2.55

1.80
1.80
1.80
1.80
1.80
1.80
1.80
1.80
1.80
1.80

133.85
225.00
190.44
58.24
136.80
81.65
88.21
7.06
19.44
81.24

F1
For external walls
L/w's

1.05

1.05

1.80

7.94

1
1
1
1
1
1
1

x
x
x
x
x
x
x

1
1
2
4
2
4
1

46.17
64.63
9.75
21.48
24.40
6.08
7.00

0.75
0.75
0.75
0.75
0.75
0.75
1.60

0.60
0.60
0.60
0.60
0.60
0.60
0.25

20.78
29.08
8.78
38.66
21.96
10.94
2.80

4.18

0.75

0.60

3.76

11 of 517

0.90

F1
F2
F3
F4
F5
F6
F7
F8
CF1
CF2
For Watch men room

Near open to sky


S/W's
Near open to sky
Entrance steps
For Watch men room

G.F.

Per
Unit

Rate

98.90

Measurements

Sl.
Description of item
No.
1

2
1
Deductions
F1
F1
F2
F3
F4
F5
F6
F7
F8
CF1
CF2
Deduct blasting qty

Nos.

3
x

4
3.08

5
0.75

6
0.60

x 4
x
6
x 15
x 10
x
7
x 12
x 10
x 18
x
2
x
4
x
6

1.05
2.6
2.5
2.3
2.15
2
1.8
1.65
1.4
1.8
2.95

0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75

0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60

QTY

Unit
7

25% of E/W Quantity


255.48
1021.93 x 0.25 = 255.48
Or say
260.00 Cum
4 Plain Cement Concrete corresponding to M7.5 grade as per IS 456 equivalent to
(1:4:8) proportion nominal mix (cement: fine aggregate: Coarse aggregate)
using 40mm size Hard Blasted Granite (IS383, 1970) metal from approved
quarry including cost and conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site, including sales & other taxes on all materials, all
operational, incidental, and labour charges such as mixing, laying and ramming
concrete in layers in position not exceeding 15cm, finishing top surface, curing
concrete, etc., complete but excluding seigniorage charges, for finished item
of work for Foundations (APSS No. 402)

G.F.

1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x

11
20
20
7
19
14
18
2
4
6

2.60
2.50
2.30
2.15
2.00
1.80
1.65
1.40
1.80
2.95

2.60
2.50
2.30
2.15
2.00
1.80
1.65
1.40
1.50
2.55

12 of 517

0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10

2.77

-1.89
1
-7.02
1
-16.88
1
-10.35
1
-6.77
1
-10.80
1
-8.10
1
-13.37
1
-1.26
1
-3.24
1
-7.97
-260.00
821.77
Or say
825.00 Cum
3 Earth work excavation for foundations for buildings in hard rock (requiring
blasting) and depositing on bank for all lifts and with an initial lead of 10m and
up to 3m depth including all operational,incidental, labour charges such as
shoring, sheeting, planking, strutting etc., and overheads & contractors profit
complete for finished item of work excluding dewatering charges etc., as per SS
20 B(APSS 308)

F1
F2
F3
F4
F5
F6
F7
F8
CF1
CF2
For Watch men room

Per
Unit

Rate

7.44
12.50
10.58
3.24
7.60
4.54
4.90
0.39
1.08
4.51

231.60

597.90

Measurements

Sl.
Description of item
No.
1

Nos.

3
1x

F1

4
1.05

5
1.05

D
6
0.10
Or say

QTY

Unit

Per
Unit

Rate

0.44
57.21

Cum

57.50

Cum

3627.55

Cum

8211.70

Cum

8573.00

5 Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching )


using 20mm size (SS5) hard blasted granite machine crushed graded metal
(Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs.
of cement per 1 cum of concreteincluding cost and conveyance of all materials
like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and
cost of all materials including centering using Cashewrina Ballies and Wooden
runners & staging including all bracings, cross members etc., shuttering ,
machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but
excluding cost of steel and its fabrication charges for finished item of work but
excluding seigniorage charges (APSS No. 402 & 403)

A FOR FOOTINGS
F1
F2
F3
F4
F5
F6
F7
F8
CF1
CF2
For Watch men room
F1

B FOR PEDESTALS
P1
P2
P3
P4
P5
P6
P7
P8
P9
For Watch men room
Pedestal

1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x

11
20
20
7
19
14
18
2
4
6

x 4

2.40
2.30
2.10
1.95
1.80
1.60
1.45
1.20
1.60
2.75
0.9

2.40
2.30
2.10
1.95
1.80
1.60
1.45
1.20
1.30
2.35
0.9

31.68
50.26
39.69
11.98
24.62
14.34
11.35
0.86
2.08
19.39

0.25
Or say

0.81
207.06
207.50

1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x

11
32
6
10
25
2
19
2
24

0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.45
0.45

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60
0.60

1.78
5.18
0.97
1.62
4.05
0.32
3.08
0.24
2.92

0.38

0.45

0.60
Or say

0.41
20.58
21.00

1.50
1.53

2.23
6.59

C FOR COLUMNS upto bottom of the plinth beam


C1
1 x
11
0.45
0.3
C2
1 x
32
0.45
0.3
G.F.

0.5
0.475
0.45
0.45
0.4
0.4
0.3
0.3
0.25
0.5

13 of 517

Measurements

Sl.
Description of item
No.
1

2
C3
C4
C5
C6
C7
C8
C9
For Watch men room
C1

Nos.
3
1 x
1 x
1 x
1 x
1 x
1 x
0.78 x
1

6
10
25
2
19
2
24

4
0.45
0.45
0.45
0.45
0.45
0.3
0.3

5
0.3
0.3
0.3
0.3
0.3
0.3
0.3

6
1.55
1.55
1.60
1.60
1.70
1.70
1.75

0.23

0.3

1.50

Unit

Near open to sky


S/W's
Near open to sky
Entrance steps
For Watch men room

x
x
x
x

1
1
2
4

46.17
64.63
9.75
21.48

0.75
0.75
0.75
0.75

0.10
0.10
0.10
0.10

3.46
4.85
1.46
6.44

1
1
1

x
x
x

2
4
1

24.4
6.08
7

0.75
0.75
1.6

0.10
0.10
0.10

3.66
1.82
1.12

0.10
0.10

0.63
0.46

G.F.

x 2
x 2

4.18
3.08

0.75
0.75

Deductions
P1
P2
P3
P4
P5
P6
P7
P8
P9
under flooring

1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x

8
15
6
10
10
2
14
2
24

0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.45
0.45

0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75
0.75

0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10

-0.36
-0.68
-0.27
-0.45
-0.45
-0.09
-0.63
-0.07
-0.81

Lab-1

9.96

6.60

0.08

5.26

14 of 517

1.26
2.09
5.40
0.43
4.36
0.31
2.95

1
1
1
1

1
1

Per
Unit

Rate

0.41
26.02
Or say
26.50 Cum
6 Plain Cement Concrete corresponding to M5 grade as per IS 456 equivalent to
(1:5:10) proportion nominal mix (cement: fine aggregate: Coarse aggregate)
using 40mm size Hard Blasted Granite (IS383, 1970) metal from approved
quarry including cost and conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site, including sales & other taxes on all materials, all
operational, incidental, and labour charges such as mixing, laying and ramming
concrete in layers in position not exceeding 15cm, finishing top surface, curing
concrete, etc., complete but excluding seigniorage chargesfor finished item of
work for Foundations and Flooring Bed (APSS No. 402)

For external walls


L/w's

QTY

9477.10

Measurements

Sl.
Description of item
No.
1

Nos.

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

3
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

1
2
2
1
1
1
1
1
1
1
1
1
1
2
2
2
2
2
1
2
1
1

4
8.95
9.07
9.00
6.60
6.60
6.60
6.00
13.27
6.60
2.36
2.36
2.36
12.41
4.86
4.00
2.58
45.19
18.30
7.60
5.63
6.57
3.6

5
6.60
6.60
6.60
5.80
5.85
5.88
4.92
6.60
4.11
2.10
2.17
2.10
6.83
4.00
1.70
1.70
2.17
2.17
6.00
3.58
6.46
3.2

6
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08
0.08

2
2
2
2
1
2
2
2
2
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x

7
7
7
7
1
6
2
6
16
2
2
2

3.34
3.04
6.38
6.38
4.627
3.1
6.38
2.17
2.17
4
7.06
5.9

0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23

0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10
0.10

2
Lab-2
Lab-3,6
Lab-4,5
Staff room
Ncc room
Ncc coordinator room
Entry hall
Office room
Principal room
Record room
Anti room
Attached wc
Open auditorium
Toilet blocks
Hand wash
WC
passage
Passage
Staircase room
Portico
Watch room
Under plinth beem.
Plinth beam-P1
P1
P2
P3
P3
P4
P5
P6
P6
P7
P8
P9

Or say

G.F.

15 of 517

QTY

Unit

Per
Unit

Rate

4.73
9.58
9.50
3.06
3.09
3.10
2.36
7.01
2.17
0.40
0.41
0.40
6.78
3.11
1.09
0.70
15.69
6.35
3.65
3.22
3.40
0.92
1.08
0.98
2.05
2.05
0.11
0.86
0.59
0.60
1.60
0.18
0.32
0.27
126.77
127.00

Cum

3413.65

Measurements

Sl.
Description of item
No.

Nos.

QTY

1
2
3
4
5
6
7
7 Random Rubble stone masonry, in CM (1:8) prop: (Cement: Sand) using Hard
blasted Granite stones from approved quarry including cost and conveyance of
all materials like Granite stones, cement, sand, water, etc., to site sales &
other taxes on all materials, all operational, incidental, and labour charges such
as cutting stones to required size and shape, mixing of cement mortar,
constructing masonry, curing etc., complete but excluding seigniorage charges
for finished item of work for foundation and basement (APSS No. 601 & 615)

below ground
For external walls
L/w's

Near open to sky


S/W's

1
1
1
1
1

x
x
x
x
x

1
1
2
4
2

46.02
64.48
9.60
21.33
24.55

0.45
0.45
0.45
0.45
0.45

0.60
0.60
0.60
0.60
0.60

12.43
17.41
5.18
23.04
13.26

Near open to sky

6.23

0.45

0.60

6.73

x 2

4.18

0.45

0.60

2.26

x 2

3.08

0.45

0.60

1.66

C1

0.45

0.45

0.80

-1.30

C2

15

0.45

0.45

0.83

-2.51

C3

0.45

0.45

0.85

-1.03

C4

10

0.45

0.45

0.85

-1.72

C5

10

0.45

0.45

0.90

-1.82

C6

0.45

0.45

0.90

-0.36

C7

14

0.45

0.45

1.00

-2.84

C8

0.3

0.45

1.00

-0.27

C9

24

0.3

0.45

1.05

-3.40

P1
P2
P3
P4
P5
P6
P7
P8
P9
above ground
For external walls
L/w's

1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x

8
15
6
10
10
2
14
2
24

0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.45
0.45

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

0.10
0.08
0.05
0.05
0.00
0.00
-0.10
-0.10
-0.15

-0.22
-0.30
-0.08
-0.14
0.00
0.00
0.38
0.04
0.73

1
1
1

x 1
x 1
x 2

46.02
64.48
9.6

0.45
0.45
0.45

0.70
1.20
1.20

14.50
34.82
10.37

For Watch men room

Deductions

G.F.

16 of 517

Unit

Per
Unit

Rate
8

Measurements

Sl.
Description of item
No.
1

2
Near open to sky
S/W's
Near open to sky
For Watch men room

Deductions
C1
C2
C3
C4
C5
C6
C7
C8
C9

QTY

Nos.

1
1
1

3
x 4
x 2
x 4

4
21.33
24.55
6.23

5
0.45
0.45
0.45

6
1.20
1.20
1.20

7
46.07
26.51
13.46

1
1

x 2
x 2

0.45
0.45

1.20
1.20

4.51
3.33

1
1
1
1
1
1
1
1
1

X
X
X
X
X
X
X
X
X

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.45

0.70
0.70
0.70
0.70
0.70
0.70
0.70
0.70
0.70

4.18
3.08

1
1
1
1
1
1

Near open to sky


S/W's
Near open to sky
For Watch men room
1
1

x
x
x
x
x
x
x 2
x 2

1
1
2
4
2
4

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.3
0.3

46.02
64.48
9.6
21.33
24.55
6.23

1.00
1.00
1.00
1.00
1.00
1.00

4.06
3.66

1.00
1.00

Or say

G.F.

17 of 517

2709.55

63.95

199.60

46.02
64.48
19.20
85.32
49.10
24.92

8.12
7.32
304.48
Or say
310.00 Sqm
9 Filling with useful available excavated earth (excluding rock) in trenches, sides
of foundations and basement with initial lead in layers not exceeding 15cm thick,
consolidating each deposited layer by watering and ramming including cost and
conveyence of water to work site and all operational, incidental, labour charges,
hire charges of T & P etc., complete for finished item of work. (APSS NO. 309 &
310)
Same as Earth Work Quantity

Per
Unit

Rate
8

-1.13
-2.13
-0.85
-1.42
-1.42
-0.28
-1.98
-0.19
-2.27
209.02
Or say
210.00 Cum
8 Flush Pointing to CRS Masonry in CM(1:3) Prop: including cost and conveyance
of all materials like cement, sand, water etc., to site, including sales & other
taxes on all materials, all operational, incidental charges and labour charges
such as mixing mortar, finishing, curing, etc., complete but excluding
seigniorage charges for finished item of work. (APSS 901,906)
above ground
For external walls
L/w's

8
15
6
10
10
2
14
2
24

Unit

825.00
825.00

Cum

Measurements

Sl.
Description of item
No.

Nos.

QTY

Unit

1
2
3
4
5
6
7
10 Filling with Gravel in trenches, sides of foundations and basement with initial
lead in layers not exceeding 15cm thick, consolidating each deposited layer by
watering and ramming including cost and conveyence of water to the work site
and all operational, incidental, labour charges, hire charges of T & P etc.,
completebut but excluding seignorage charges, for finished item of work. (APSS
NO. 309 & 310)
Lab-1
Lab-2
Lab-3,6
Lab-4,5
Staff room
Ncc room
Ncc coordinator room
Entry hall
Office room
Principal room
Record room
Anti room
Attached wc
Open auditorium
Toilet blocks
Hand wash
WC
passage

65.74
59.07
119.72
118.80
38.28
38.61
38.81
29.52
87.58
27.13
4.96
5.12
4.96
84.76
38.88
13.60
8.77
196.12
79.42
Passage
45.60
Staircase room
40.31
1145.76
Or say
1150.00 Cum
11 Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching )
using 20mm size (SS5) hard blasted granite machine crushed graded metal
(Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs.
of cement per 1 cum of concreteincluding cost and conveyance of all materials
like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and
cost of all materials including centering using Cashewrina Ballies and Wooden
runners & staging including all bracings, cross members etc., shuttering ,
machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but
excluding cost of steel and its fabrication charges for finished item of work but
excluding seigniorage charges (APSS No. 402 & 403)

A FOR PLINTH BEAM


Plinth beam-P1
P1

G.F.

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

4x
4x

1
1
2
2
1
1
1
1
1
1
1
1
1
1
2
2
2
2
2
1
2

9.96
8.95
9.07
9
6.6
6.6
6.6
6
13.27
6.6
2.36
2.36
2.36
12.41
4.86
4
2.58
45.19
18.3
7.6
5.63

7
7

6.6
6.6
6.6
6.6
5.8
5.85
5.88
4.92
6.6
4.11
2.1
2.17
2.1
6.83
4
1.7
1.7
2.17
2.17
6
3.58

3.34 0.23
3.04 0.23

18 of 517

Per
Unit

Rate
8

1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00

0.30
0.30

6.45
5.87

380.70

Measurements

Sl.
Description of item
No.
1

Nos.

2
P2
P3
P3
P4
P5
P6
P6
P7
P8
P9
For Watchmen room

3
2x
2x
1x
4x
2x
2x
2x
1x
1x
1x

7
7
1
6
2
6
16
2
2
2

1x
1x

2
2

B FOR COLUMNS upto roof level


C1
1 x
C2
1 x
C3
1 x
C4
1 x
C5
1 x
C6
1 x
C7
1 x
C8
1 x
C9
0.78 x
For Watchmen room
C1
1x

C FOR ROOF BEAM


RB1
RB2
RB3
RB4
RB5
RB6
RB7
RB8
RB9
RB10
RB11
RB12
Brusummer beam

G.F.

4
4
2
2
2
2
2
1
2
1
2
1
2
2
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

11
32
6
10
25
2
19
2
24

7
7
16
12
7
7
16
2
13
2
2
2
7
7
2

Unit

5
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23

6
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30

3.66 0.23
3.6 0.23

0.30
0.30

0.51
0.50
41.80

Or say

42.50

2.925
2.925
2.925
2.925
3.075
2.925
3.075
3.075
3.075

4.34
12.64
2.37
3.95
10.38
0.79
7.89
0.55
5.18

2.335

0.64

Or say

48.73
49.00

0.30
0.30
0.41
0.30
0.41
0.30
0.30
0.30
0.30
0.41
0.41
0.30
0.23
0.23
0.23

6.53
5.87
21.70
5.13
9.49
2.10
4.79
0.97
3.89
1.32
2.88
0.49
2.50
2.25
0.75

4
6.38
6.38
4.627
3.1
6.38
2.17
2.17
4
7.06
5.93

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.3
0.3
4

QTY

0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3

0.23

3.38
3.04
7.28
3.10
7.28
2.17
2.17
7.06
2.17
7.06
5.93
3.53
3.38
3.04
7.06

0.3

0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.30
0.23
0.23
0.23
0.23

19 of 517

Per
Unit

Rate

6.16
6.16
0.32
5.13
1.76
1.80
4.79
0.55
0.97
0.82

Cum

10172.70

Cum

1135.68

Measurements

Sl.
Description of item
No.
1

2
staircase Mid landing
beam
For Watchmen room

Nos.

3
x

4
3.53

5
0.23

6
0.45

1
1

x
x

2
2

4.05
3.20

0.23
0.23

0.30
0.30
Or say

D FOR ROOF SLAB 125 MM THICK


Entire area
1 x
Portico
1 x
Duct area
1 x
open to sky
1 x
Watch men room
1 x

1
1
4
2
1

64.11
6.57
4.63
20.38
4.06

25.38
6.46
1.00
6.48
3.66
Or say

F FOR STAIRCASE WAIST SLAB 175 MM THICK


1st & 2nd flight
2 x
2
4.00
landing
1 x
2
3.53

QTY

Unit
7

0.73
0.56
0.44
72.40
72.50

Cum

8731.00

1627.11
42.44
-18.52
-264.12
14.86
1401.77
1402.00 Sqm

1058.45

1364.10

6409.55

24.80
10.59
35.39
Or say
35.50 Sqm
12 Plain Cement Concrete M20 Design Mix ( by weigh batching ) using 20mm size
(SS5) hard blasted granite machine crushed graded metal (Coarse aggregate)
from approved quarry, using a minimum quantity of 350 kgs. of cement per 1
cum of concrete including cost and conveyance of all materials like cement,
fine aggregate (Sand), coarse aggregate, water etc., to site and cost of all
materials including steel centering, shuttering, machine mixing, laying concrete,
lift charges, curing etc., complete but excluding seigniorage charges for finished
item of work for steps (APSS No. 402 )

Steps at entrance
stair case steps

4
22
22

x
x
x

0.5
0.5
0.5

6.46
1.50
1.50

1.55
1.50

0.3
0.30
0.30

0.15
0.15
0.15

0.58

0.74
0.74
2.07
Or say
2.50
Cum
13 Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using
20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse
aggregate) from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete including cost and conveyance of all materials
like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and
cost of all materials including centering using Cashewrina Ballies and Wooden
runners & staging including all bracings, cross members etc., shuttering ,
machine mixing, laying concrete, lift charges, curing etc., complete but excluding
cost of steel and its fabrication charges but excluding seigniorage charges for
finished item of work (APSS No. 402 & 403) for Lintels

OVER DOORS & WINDOWS


CG
G.F.

Per
Unit

Rate

0.23

20 of 517

0.23

0.32

Measurements

Sl.
Description of item
No.
1

2
D2
D3
D4
W1
W2
GW
V2

3
x
x
x
x
x
x
x

4
1.5
1.35
1.05
1.8
1.05
2.3
1.2

5
0.23
0.23
0.115
0.23
0.23
0.23
0.23

6
0.15
0.15
0.15
0.15
0.15
0.15
0.15

19
2
14
55
15
2
19

Unit

L/w in Entrance area


S/W in Entrance area
L/W in Lab -1

1
1
1

x
x
x

1
2
2

6.00
4.92
9.50

0.23
0.23
0.23

3.175
3.070
3.175

4.38
6.95
13.87

S/W in Lab-1
L/W in Lab -2

1
1

x
x

2
2

6.38
8.49

0.23
0.23

3.070
3.175

9.01
12.40

S/W in Lab-2
L/W in Lab -3,5

1
2

x
x

2
2

6.38
8.61

0.23
0.23

3.070
3.175

9.01
25.15

S/W in Lab-3,5
L/W in Lab -4,6

2
2

x
x

2
2

6.38
8.54

0.23
0.23

3.070
3.175

18.02
24.95

S/W in Lab-4,6
L/W in open auditorium

1
1

x
x

2
1

6.38
11.94

0.23
0.23

3.070
3.175

9.01
8.72

L/W in principal room

5.92

0.23

3.070

8.36

S/W in principal room


L/W in office room

1
1

x
x

3
2

3.88
12.58

0.23
0.23

3.175
3.175

8.50
18.37

S/W in office room


L/W in staff room

0
1

x
x

2
2

6.38
5.65

0.23
0.23

3.070
3.175

0.00
8.25

S/W in staff room


L/W in Ncc room

0
1

x
x

2
2

6.38
5.62

0.23
0.23

3.070
3.175

0.00
8.21

S/W in Ncc room


L/W in Ncc coordinator
room

2
1

x
x

2
2

6.38
5.65

0.23
0.23

3.070
3.175

18.02
8.25

S/W in Ncc coordinator


room
L/W in toilet blocks

6.38

0.23

3.070

9.01

4.64

0.23

3.070

13.11

2
1
2

x
x
x

2
2
2

6.52
3.77
2.17

0.23
0.23
0.23

3.175
3.175
3.175

6.76
6.76
6.76

S/W in toilet blocks


At passage

21 of 517

Per
Unit

Rate

0.98
0.09
0.25
3.42
0.54
0.16
0.79
6.55
Or say
7.00
Cum
14 Brick Masonry in superstructure with CM (1:8) prop: using Fly ASH Bricks of size
290x225x140mm with compressive of 50 Kgs / Sqcm from approved source
including cost and conveyance of all materials like cement, sand, fly ash bricks,
water etc., to site, including sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing cement mortar, constructing
masonry, scaffolding charges, lift charges, curing, etc., complete but excluding
seigniorage charges for finished item of work. (APSS No. 501 & 504).

G.F.

1
1
1
1
1
1
1

Nos.

QTY

9412.50

Measurements

Sl.
Description of item
No.
1

Nos.

2
1
1

3
x
x
x

2
2
2

4
5.38
3.58
7.06

5
0.23
0.23
0.23

6
3.075
3.175
3.175

6.76
6.76
6.76

2
2
1
2
2
1
1
1

x
x
x
x
x
x
x
x

7
7
2
7
7
2
2
2

3.38
3.04
7.06
3.38
3.04
7.06
3.60
3.20

0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23

0.815
0.815
0.815
0.900
0.900
0.900
2.335
2.335

6.76
6.76
6.76
6.76
6.76
6.76
6.76
6.76

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

1
19
2
14
55
15
2
19
6
1
19
2
14
55
15
2
19

6
1.5
1.35
1.05
1.8
1.05
2.3
1.2
0.23
6
1.2
1.05
0.75
1.5
0.75
2
0.9

0.23
0.23
0.23
0.115
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23

0.23
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
2.70
2.13
2.13
2.13
1.35
1.35
1.35
0.45

2
Stair case

QTY

Unit
7

Per
Unit

Rate
8

above brusummer beam

Dwarf walls

Watch men room

Deductions of Lintels
OVER DOORS & WINDOWS
CG
1
D2
1
D3
1
D4
0
W1
1
W2
1
GW
1
V2
1
bed blocks for rooms
38
CG
1
D2
1
D3
1
D4
0
W1
1
W2
1
GW
1
V2
1

-0.32
-0.98
-0.09
0.00
-3.42
-0.54
-0.16
-0.79
-1.81
-3.73
-11.17
-1.03
0.00
-25.62
-3.49
-1.24
-1.77
280.06
say
281.00 Cum
15 Reinforced Fly Ash Brick Masonry 10cm thick for partition walls in CM (1:4) prop:
Fly Bricks of size 290x100x140mm with compressive of 50 Kgs / Sqcm from
approved source and placing 2nos. of 6mm dia MS bars embedded in every 3rd
layer with free ends of reinforcement keyed into mortar joints of the main brick
work whereever applicable including cost and conveyance of all materials like
cement, sand, bricks, water etc., to site, sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing cement mortar,
constructing masonry, scaffolding charges, lift charges, curing, etc., but
excluding cost and conveyance of steel and its fabrication charges & seignerage
charges complete for finished item of work. (APSS No. 501 & 509).

toilet blocks

G.F.

22 of 517

5359.40 1

Measurements

Sl.
Description of item
No.
1

Nos.

3
x
3
x
3
x
4
x
4
x
2
x
2
x
1
x
2
x
14

4
1.50
1.10
1.30
1.10
1.72
2.10
2.17
2.36
0.75

6
2.50
2.50
2.50
2.50
2.50
2.50
2.50
2.50
2.13

QTY

Unit

7
L/w's
1
11.25
1
8.25
2
26.00
2
22.00
1
8.60
Record room
1
10.50
1
5.43
1
11.80
deducting door-D4
1
-22.37
81.46
Or say
82.00 Sqm
16 Reinforced cement concrete with M 20 grade Design mix ( by weigh batching )
using 20mm size (SS 5) machine crushed hard blasted granite graded metal
(coarse aggregate) from approved quarry using a minimum quantity of 350 Kg
of cement per 1 Cum of concrete including cost and conveyance of all materials
like cement, fine aggregate (sand) ,coarse aggregate, water etc. to site and
cost of
all materials including centering using Cashewrina Ballies and
Wooden runners & staging including all bracings, cross members etc.,
shuttering, machine mixing, laying concrete, for sunshade of 7.5cm thick at
fixed end and 5cm thick at free end with an average thickness of 6.25cm
including labour charges for mixing, laying, curing etc., complete but
excluding cost of steel and its fabrication charges but excluding seigniorage
charges for finished item of work For sunshade of 625 mm thick

Per
Unit

Rate
8

621.80 1

for sun shades


On out side windows
W1
open to sky

1
1
1
1

x
x
x
x

41
2
2
2

1.8
19.76
17.76
5.26

0.60
0.60
0.60
0.60
Or say

44.28
23.71
21.31
6.31
95.62
96.00

17 Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using


20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse
aggregate) from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete including cost and conveyance of all materials
like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and
cost of all materials including centering using Cashewrina Ballies and Wooden
runners & staging including all bracings, cross members etc., shuttering ,
machine mixing, laying concrete, lift charges, curing etc., complete but excluding
cost of steel and its fabrication charges but excluding seigniorage charges for
finished item of work (APSS No. 402 & 403) For 75 mm thick slab for Platforms

slab 75 mm thick
for lab platform

G.F.

9.00

0.900

48.60

13.20

0.900

71.28

23 of 517

Sqm

703.70

Measurements

Sl.
Description of item
No.
1

Nos.

QTY

Unit

7
119.88
Or say
120.00 Sqm
18 Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using
20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse
aggregate) from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete including cost and conveyance of all materials
like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and
cost of all materials including centering using Cashewrina Ballies and Wooden
runners & staging including all bracings, cross members etc., shuttering ,
machine mixing, laying concrete, lift charges, curing etc., complete but excluding
cost of steel and its fabrication charges but excluding seigniorage charges for
finished item of work (APSS No. 402 & 403) For 25 mm thick racks

for RCC Rock 25 mm


thick, for shelves in
AOSE & office rooms

1.50

0.40

Or say

6.00
6.00
6.00

Per
Unit

Rate
8
757.90

Sqm

463.95

Sqm

337.25

19 Providing impervious coat over RCC roof slab to required slopes with CM (1:3)
prop. 20mm thick (average) mixed with water proofing compound manufactured
by reputed manufacturers as approved by Engineer-in-charge at 1Kg/bag of
cement, laid over roof slab when it is green, finished smooth with a floating coat
of neat cement and thread lining at regular intervals of 45cmx45cm including
cost and conveyance of all materials like cement, sand, water proofing
compound, water etc., to site,
sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing mortar, laying,
rounding off at junctions of wall and slab, rendering smooth with thread lining,
curing, lift charges, etc., complete but excluding seigniorage charges for
finished item of work (APSS No. 901 & 903).
Ground floor over
portico

6.57

6.46

42.44

Or say

42.44
43.00

20 Plain Cement Concrete corresponding to M10 grade as per IS 456 equivalent to


(1:3:6) proportion nominal mix (cement: fine aggregate: Coarse aggregate)
using 20mm size Hard Blasted Granite (IS383, 1970) Machine Crushed graded
metal from from approved quarry including cost and conveyance of all materials
like cement, sand, coarse aggregate, water etc. to site, including sales & other
taxes on all materials, all operational, incidental and labour charges such as
mixing, laying, curing concrete, etc., complete but excluding seigniorage
charges for finished item of work for Bed Blocks and Hold Fasts (APSS No. 402)

D2
D3
D4
W1
W2
V2
G.F.

19
2
14
55
15
19

x
x
x
x
x
x

6
6
6
4
4
4

0.23
0.23
0.115
0.23
0.23
0.23

0.23
0.23
0.115
0.23
0.23
0.23

24 of 517

0.15
0.15
0.15
0.15
0.15
0.15

0.90
0.10
0.17
1.75
0.48
0.60

Measurements

Sl.
Description of item
No.
1

Nos.

QTY

Unit
7

3.99
Or say
4.00
Cum
21 Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and
top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and
conveyance of all materials like cement, sand, water etc., to site, sales & other
taxes on all materials,all operational, incidental and labour charges such as
mixing mortar, scaffolding charges, lift charges, including cutting of Grooves
wherever necessary as directed by Engineer - in - charge, finishing, curing, etc.,
complete but excluding seigniorage charges for Even Surfaces of Wall for
finished item of work. (APSS 901,903 & 904)
L/w in Entrance area
S/W in Entrance area
L/W in Lab -1
S/W in Lab-1
L/W in Lab -2

1
1
1
1
1

x
x
x
x
x

1
2
2
2
2

6.00
4.92
9.96
6.60
8.95

3.50
3.50
3.50
3.50
3.50

21.00
34.44
69.72
46.20
62.65

S/W in Lab-2
L/W in Lab -3,5
S/W in Lab-3,5
L/W in Lab -4,6
S/W in Lab-4,6
L/W in open auditorium
L/W in principal room
S/W in principal room
L/W in office room
S/W in office room
L/W in staff room
S/W in staff room
L/W in Ncc room
S/W in Ncc room
L/W in Ncc coordinator
S/W in Ncc coordinator
L/W in toilet blocks

1
2
2
2
1
1
1
1
1
1
1
1
1
2
1
1
2
2
1
2

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2

6.60
9.07
6.60
9.00
6.60
6.83
6.6
4.11
13.27
6.6
5.8
6.6
5.85
6.6
5.88
6.6
4.64
6.515
3.77
5.38

3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50
3.50

46.20
126.98
92.40
126.00
46.20
47.81
46.20
28.77
92.89
46.20
40.60
46.20
40.95
92.40
41.16
46.20
64.96
91.21
26.39
75.32

3.58

3.50

25.06

3.38

1.10

52.05

3.04

1.10

46.82

7.06

1.10

15.53

3.38

0.90

42.59

3.04

0.90

38.30

S/W in toilet blocks


Stair case
above brusummer beam

Dwarf walls

G.F.

25 of 517

Per
Unit

Rate
8
5161.95

Measurements

Sl.
Description of item
No.

QTY

Nos.

4
7.06

3
x

6
0.90

7
12.71

1.5

2.80

25.20

1.1

2.80

18.48

1.3

2.80

58.24

1.1

2.80

49.28

1.72

2.80

19.26

2.1

2.80

23.52

2.17

2.80

12.15

2.36

2.80

26.43

deducting door-D4

14

0.75

2.13

-22.37

Watch men room

3.6

2.75

19.80

3.2

2.75

17.60

1.5

0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
4

x
x
x
x
x
x
x
x
x

1
19
2
14
55
15
2
19
5

6.00
1.20
1.05
0.75
1.50
0.75
2.00
0.90
0.5

Unit

Per
Unit

Rate
8

toilet blocks
L/w's

Record room

for RCC Rock 25 mm


thick, for shelves in
CG
D2
D3
D4
W1
W2
GW
V2

0.4

12.00
2.7
2.13
2.13
2.13
1.35
1.35
1.35
0.45

0.4

-8.10
-24.28
-2.24
-11.18
-55.69
-7.59
-2.70
-3.85
4.00
1880.08

Or say
1890.00 Sqm
22 Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and
top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and
conveyance of all materials like cement, sand, water etc., to site, sales & other
taxes on all materials,all operational, incidental and labour charges such as
mixing mortar, scaffolding charges, lift charges, including cutting of Grooves
wherever necessary as directed by Engineer - in - charge, finishing, curing, etc.,
complete but excluding seigniorage charges for Even Surfaces of Wall for
finished item of work. (APSS 901,903 & 904)
out side L/w's
out side c/w 's
in varandah L/w's

1
1
1
1
1
2
2

near stair case


Cutout
Dwarf walls
G.F.

x
x
x
x
x
x
x
x 7

2
2
2
2
2
4
4

64.11
25.38
45.66
18.30
7.06
4.63
1.00
3.38
26 of 517

3.60
3.60
3.475
3.475
3.475
3.60
3.60
0.9

461.59
182.74
317.34
127.19
49.07
133.34
28.80
42.59

289.05

Measurements

Sl.
Description of item
No.
1

2
2
1
above
beam

Nos.

3
x 7
x 2

4
3.04
7.06

x
x
x
x

7
7
2
2

QTY

0.9
0.9

7
38.30
12.71

3.38
3.04
7.06
6

1.47
1.47
1.47
3.60

69.56
62.56
41.51
86.40

out

Watch men room

x 2

4.06

2.88

23.35

x 2

3.66

2.88

21.05

Deduction of doors & windows


CG
0.5 x
D2
0.5 x
D3
0.5 x
D4
0.5 x
W1
0.5 x
W2
0.5 x
GW
0.5 x
V2
0.5 x
Column faces
2 x

-8.10
-24.28
-2.24
-11.18
-55.69
-7.59
-2.70
-3.85
82.37
1664.83
Or say
1665.00 Sqm
23 Ornamental Plastering 12mm thick in two coats with base coat of 8mm thick in
CM (1:5) and top coat of 4mm thick in CM (1:3) dubara sponge finish including
cost and conveyance of all materials like cement, sand, water etc., to site, sales
& other taxes on all materials,all operational, incidental and labour charges such
as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves
wherever necessary as directed by Engineer - in - charge, finishing, curing, etc.,
complete for Even Surfaces of Wall but excluding seigniorage charges for
finished item of work. (APSS 901,903 & 904)

Lab-1
Lab-2
Lab-3,6
Lab-4,5
Staff room
Ncc room
Ncc coordinator room
Entry hall
Office room
Principal room
Record room
Anti room

G.F.

Per
Unit

Rate
8

brusummer
2
2
2
side 2

Stair case
walls

Unit

1
1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x

1
19
2
14
55
15
2
19
52

1
1
2
2
1
1
1
1
1
1
1
1

6.00
1.20
1.05
0.75
1.50
0.75
2.00
0.90
0.22

9.96
8.95
9.07
9.00
6.60
6.60
6.60
6.00
13.27
6.60
2.36
2.36

2.7
2.13
2.13
2.13
1.35
1.35
1.35
0.45
3.60

6.60
6.60
6.60
6.60
5.80
5.85
5.88
4.92
6.60
4.11
2.10
2.17

27 of 517

65.74
59.07
119.72
118.80
38.28
38.61
38.81
29.52
87.58
27.13
4.96
5.12

289.05 1

Measurements

Sl.
Description of item
No.
1

2
Attached wc
Open auditorium
Toilet blocks
Hand wash
WC
passage
Passage
Staircase room
Portico
Beam bottom
Staircase waist slab
bottom
landing slab bottom
Sunshades bottom &
top
Brusummer beam

Nos.

QTY

Unit

4
2.36
12.41
4.86
4.00
2.58
45.19
18.30
7.60
5.63
6.57
6.38
2.17
4.00

5
2.10
6.83
4.00
1.70
1.70
2.17
2.17
6.00
3.58
6.46

1
1
1
1
1
1
1
1
0
0
1
1
2

3
x
1
x
1
x
2
x
2
x
2
x
2
x
2
x
1
x
2
x
1
x 21
x 46
x
2

1.50

4.96
84.76
38.88
13.60
8.77
196.12
79.42
45.60
0.00
0.00
30.82
22.96
24.00

1
2

x
x

2
38

3.58
1.80

1.50
0.60

10.74
82.08

1
1
1
2
2
2
1

x
x
x
x
x
x
x

7
7
2
2
2
2
1

3.38
3.05
7.06
19.76
17.76
5.26
3.6

0.23
0.23

5.44
4.91
3.25
open to sky sunshade
0.6
47.42
0.6
42.62
0.6
12.62
Watch men room
3.2
11.52
1403.83
Or say
1410.00 Sqm
24 Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using
20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse
aggregate) from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete including cost and conveyance of all materials
like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and
cost of all materials including centering using Cashewrina Ballies and Wooden
runners & staging including all bracings, cross members etc., shuttering ,
machine mixing, laying concrete, lift charges, curing etc., complete but excluding
cost of steel and its fabrication charges but excluding seigniorage charges for
finished item of work (APSS No. 402 & 403) for 50 mm thick slab

for RCC platform 50


mm thick for hand wash

0.23
0.23
0.23

2.50

0.30

1.50

1.00

0.30

0.30
1.80
2.00

Or say

G.F.

Per
Unit

Rate

28 of 517

Sqm

304.49

610.95

Measurements

Sl.
Description of item
No.

Nos.

QTY

Unit

1
2
3
4
5
6
7
25 Flooring with Polished bethamcherla colour stone of 25 mm thick
(0.254x0.254M) set over a base coat of CM (1:8), 12mm thick (joints of stone
must be flushed) over C.C. bed already laid or R.C.C. roof slab only after it is
properly cured, cleaned, moistered and where necessary treated with neat
grey cement slurry of honey like consistency spred at3.3 kgs of cement for 1
sqm. and jointed with neat cement paste to full depth, including cost and
conveyance of all materials like cement, sand, water, flooring stones etc. to site,
sales and other taxes on all materials, all operational, incidental and labour
charges such as dressing of flooring stones to the required sizes, mixing of
cement mortar, laying, jointing, curing, lift charges etc., complete but excluding
seigniorage charges for finished item of work.(APSS No.703 & 701)

Lab-1
Lab-2
Lab-3,6
Lab-4,5
Staff room
Ncc room
Ncc coordinator room
Entry hall
Office room
Principal room
Record room
Anti room
Attached wc
Open auditorium
passage
Passage
Staircase room
Portico
landing slab bottom
Watch men room

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

1
1
2
2
1
1
1
1
1
1
1
1
1
1
2
2
1
2
1
2
1

9.96
8.95
9.07
9
6.6
6.6
6.6
6
13.27
6.6
2.36
2.36
2.36
12.41
45.19
18.3
7.6
5.63
6.57
3.58
3.6

6.6
6.6
6.6
6.6
5.8
5.85
5.88
4.92
6.6
4.11
2.1
2.17
2.1
6.83
2.17
2.17
6
3.58
6.46
1.5
3.2

29 of 517

65.74
59.07
119.72
118.80
38.28
38.61
38.81
29.52
87.58
27.13
4.96
5.12
4.96
84.76
196.12
79.42
45.60
40.31
42.44
10.74
11.52
1149.21
Or say

G.F.

Per
Unit

Rate

1150.00 Sqm

947.10

Measurements

Sl.
Description of item
No.

Nos.

QTY

Unit

1
2
3
4
5
6
7
26 Providing skirting to internal walls 12.5 Cm high with Polished bethamcherla
colour stone of 25 mm thick (0.254x0.254M) with length equal to flooring stones
set over a base coat of CM (1:3), 12mm thick with cement slurry of honey like
consistency spread @ 3.3 Kgs per sqm and jointed with neat cement paste
mixed with pigment of matching shade to full depth (joints of stone should be
flushed), including cost and conveyance of all materials like cement, sand,
water, flooring stones etc. to site, sales and other taxes on all materials, all
operational, incidental and labour charges such as dressing of flooring stones to
the required sizes, mixing of cement mortar, laying, jointing, curing, lift charges
etc., complete but excluding seigniorage charges for finished item of work.
(APSS No.701 & 707)
Lab-1
Lab-2
Lab-3,6
Lab-4,5
Staff room
Ncc room
Ncc coordinator room
Entry hall
Office room
Principal room
Record room
Anti room
Attached wc
Open auditorium
passage

4.14
3.89
7.84
7.80
3.10
3.11
3.12
2.73
4.97
2.68
1.12
1.13
1.12
4.81
23.68
10.24
Passage
3.40
Staircase room
4.61
Portico
3.26
landing slab bottom
2.54
Watch men room
1.70
100.96
Or say
101.00 Sqm
27 Supplying and fixing of Polished Black Kadapa slabs minimum of 15 mm thick
(0.457M x 0.457M) in Single piece with the edges flat nosed and set over a base
coat of CM (1:8), 12mm thick, and fixing in position with neat cement paste
including cost and conveyance of all materials like cement, sand, water, stones
etc. to site, seigniorage charges, sales and other taxes on all materials, all
operational, incidental and labour charges such as dressing of stones to the
required sizes, mixing of cement mortar, fixing in position, curing, lift charges
etc., complete for finished item of work for Treads (APSS No.701 & 707)

staircase steps

G.F.

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

1
1
2
2
1
1
1
1
1
1
1
1
1
1
2
2
1
2
1
2
1

33.12
31.10
31.34
31.20
24.80
24.90
24.96
21.84
39.74
21.42
8.92
9.06
8.92
38.48
94.72
40.94
27.20
18.42
26.06
10.16
13.60

22

1.50

Per
Unit

Rate
8

0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125

0.300

30 of 517

19.80

999.05

Measurements

Sl.
Description of item
No.
1

2
Entrance

Nos.

3
x

4
6.57

5
0.300

QTY

Unit

Per
Unit

Rate

7.88
27.68
Or say

28.00

Sqm

615.12

1259.90

28 Supplying and fixing of Polished Black Kadapa slabs minimum of 15 mm thick


(0.457M x 0.457M) in Single piece with the edges flat nosed and set over a base
coat of CM (1:3), 12mm thick, and fixing in position with neat cement paste
including cost and conveyance of all materials like cement, sand, water, stones
etc. to site, seigniorage charges, sales and other taxes on all materials, all
operational, incidental and labour charges such as dressing of stones to the
required sizes, mixing of cement mortar, fixing in position, curing, lift charges
etc., complete for finished item of work For raisers (APSS No.701 & 707)

staircase
Entrance

2
1

10.35
3.94
14.29
Or say
14.50 Sqm
29 Supply and Fixing of Door with Double leaf shutter, Door Size 1.22x2.13 mtrs
with Sal wood Frame of sections size 75mm x 100mm with Flush Door Shutter
Solid Bond Wood black board type with commercial ply on both faces of 35mm
thick including cost of fixtures such as M.S.Powder Coated Tower Bolts 250mm
long 2 Nos, MS powder coated Handles 150mm long 2 Nos, 300mm long
M.S.Powder Coated Aldrops 1No, 125mm long M.S.Powder Coated butt hinges
6Nos, 300 mm long M.S.Powder Coated Flat latch 1No, Door stoppers 2 Nos,
MS Hold fasts 6Nos, Sales and Other Taxes cost and convenyance of all
materials to site all Labour charges such as Fixing of Door Frame on shutter
Fixing in position , with Hardware fixtures etc., complete for finsihed utem of
work.

x
x

1.50
6.57

0.150
0.150

19.00
Or say
19.00 Each 11672.45
30 Supply and Fixing of Door with Double leaf shutter, Door Size 1.05x2.13 mtrs
with Sal Wood Frame of sections size 75mm x 100mm with Flush Door Shutter
Solid Bond Wood black board type with commercial ply on both faces of 35mm
thick including cost of fixtures such as M.S.Powder Coated Tower Bolts 250mm
long 2 Nos, MS Powder coated Handles 150mm long 2 Nos, 300mm long
M.S.Powder Coated Aldrops 1No, 125mm long M.S.Powder Coated butt hinges
6Nos, 300 mm long M.S.Powder Coated Flat latch 1No, Door stoppers 2 Nos,
MS Hold fasts 6Nos, Sales and Other Taxes cost and convenyance of all
materials to site all Labour charges such as Fixing of Door Frame on shutter
Fixing in position , with Hardware fixtures etc., complete for finsihed utem of
work.
1

23
4

19

2
Or say

G.F.

31 of 517

2.00
2.00

Each 10741.70

Measurements

Sl.
Description of item
No.

Nos.

QTY

Unit

1
2
3
4
5
6
7
31 Providing and fixing factory made polyvinyl chloride (PVC) Door Frame of the
size 50 x 47mm with a wall thickness of 5mm, made out of extruded 5mm rigid
PVC foam sheet, mitre cut at two corners and joined with 2nos. of 150mm long
brackets of 15x15mm M.S. square tube. The two vertical door profiles are to be
reinforced with 19x19mm M.S. Square tube of 19 gauge. The door frame shall
be fixed to the wall using 65/100mm long M.S. Screws through the frame by
using PVC fasteners. A minimum of 4nos. of screws to be provided for each
vertical member & minimum 2nos. for horizontal member etc. complete as per
manufacturers specification and direction of Engineer-in-Charge for finished
item of work
Toilet

14

x 14

5.00

20.38
20.38
Or say
20.50 Sqm
33 Reinforced cement mortar Facia 5 cm thick in CM (1:3) for drop walls, Fins &
staircase railing with rabbit wire mesh & nominal reinforcement as directed by
Engineer-in-charge with dubara spong finishing including cost & conveyence of
all materials to site, including sales and other taxes on all materials and all
operational, incidental charges such as labour charges, like mixing cement
mortar, scaffolding charges, lift charges, curing, for making 50 mm thick RCM
Paradah walls (RCM Drop walls) including tying Rabbit (chicken) wire mesh to
the existing mild steel / HYSD Steel reinforcement applying mortar lumps,
finishing, plastering to both faces, sponge finishing etc complete for finished
item of work but excluding cost of steel and its fabrication charges and
seigniorage charges in All Floors
for hand wash
for stair case

70.00
70.00
Or say
70.00 Rmt
32 Providing and fixing 30mm thick Solid panel PVC door shutter consisting of
frame made out of M.S. tubes of 19 gauge thickness and size of 19mm x 19mm
for stiles, & 15mm x 15mm for top & bottom rails. M.S. frame shall have a coat
of steel primers of approved make and manufacture. M.S. frame shall be
covered with 5mm thick heat moulded PVC C channel of size 30 x 50mm
forming stiles, and 5mm thick, 75mm wide PVC sheets for top rail, lock rail &
bottom rail on either side, and 10mm (5mm x 2) thick, 20mm wide cross PVC
sheet as gap insert for top rail & bottom rail. Panelling of 10mm thick PVC sheet
to be fitted in the M.S. frame welded / sealed to the stiles & rails with 30mm
wide x 5mm thick PVC sheet beading on either side, and joined together with
solvent cement adhesive etc. An additional 5mm thick PVC strip of 20mm width
is to be stuck on the interior side of the C Channel using PVC solvent adhesive.
Complete as per direction of Engineer-in-charge, manufacturers specification &
drawing for finished item of work .

Toilet

1
2

x
x

0.70

2
2

369.25

2683.60

1604.30

2.080

2.45
4.00

1.00
1.00
Or say

G.F.

Per
Unit

Rate

32 of 517

4.89
16.00
20.89
21.00

Sqm

Measurements

Sl.
Description of item
No.

Nos.

QTY

Unit

1
2
3
4
5
6
7
34 Flooring with Ceramic Tiles of 7.3mm thick 1st. quality of any shade as
approved by Engineer - in - charge set over a base coat of CM (1:8), 12mm
thick laid over flooring bed / V.R.C.C. slab, with neat cement slurry of honey like
consistency spread at the rate of 3.3 Kgs of cement per Sq.m and jointed with
neat white cement paste to full depth mixed with pigment of matching shade
including cost and conveyance of all materials like cement, sand, water, ceramic
tiles etc. to site, sales and other taxes on all materials, all operational, incidental
and labour charges such as mixing of cement mortar, laying, curing, lift charges
etc., complete but excluding seigniorage charges for finished item of work.
(APSS No.701 & 707) in All Floors
toilet rooms

11.44
4.95
8.35
9.91
toilet passage
6.17
9.14
for hand wash
13.92
63.88
Or say
65.00 Sqm
35 Dadooing to walls with white glazed tiles 1st. quality of any size of brand as
approved by Engineer - in - charge and set over a base coat of CM (1:5), 12mm
thick and neat cement paste at the rate of 3.3 Kg/Sqmt. and jointed with white
cement paste mixed with pigment of matching shade including cost and
conveyance of all materials like cement, sand, water, tiles, etc. to site, sales
and other taxes on all materials, C921 such as mixing of cement mortar, laying
in position, curing, lift charges etc., complete but excluding seigniorage charges
for finished item of work (APSS No.701 & 707) in All Floors
toilet rooms

toilet passage

2
1
1
1
1
1
1

x
x
x
x
x
x
x

4
3
2
2
1
1
2

1.10
1.10
1.74
2.10
1.27
1.88
1.74

2
1

x 4
x 3

4.80
5.20

x 2

8.28

1
1
1
1
0.5

x
x
x
x
x

8.92
12.26
13.48
11.48
0.75

2
1
1
2
14

Portico

G.F.

6.57

1.300
1.500
2.400
2.360
4.860
4.860
4.00

1.500
1.500
1.500

57.60
23.40
24.84

1.500
1.500

26.76
18.39

20.22
34.44
-7.88
197.78
Or say
200.00 Sqm
36 Plastering with CM(1:4) Prop: 20mm thick in single coat including cost and
conveyance of all materials like cement, sand, water etc., to site, including sales
& other taxes on all materials, all operational, incidental charges and labour
charges such as mixing mortar, finishing, curing, etc., complete but excluding
seigniorage charges for finished item of work. (APSS 901,906)
for hand wash
D6

Per
Unit

Rate

875.85

540.35

1.500
1.500
1.50

6.46

33 of 517

42.44
42.44

Measurements

Sl.
Description of item
No.
1

Nos.

QTY

Unit

6
7
Or say
45.00 Sqm
37 Providing and Fixing of openable double shutter windows made of pre-painted
steel (Base steel as per IS 513 of 0.58 mm thick galvanized as per IS 277 with
Zinc of 120 GSM). Primer coated with epoxy primer of 5-7 microns thick, finish
painted with a polyester paint of 12-16 microns thick and back coated with 5-7
microns thick alkyd backer. Section for outer frame should be of 48x50mm,
centre mullion should be of 48x50mm, section for shutter should be of 48x25mm
and fixed panel beading section should be 12x12mm. Outer frame and mullions
to have rebate for Galvalume corrugated sheet shutter and a 20mm provision
for Guard bars/Grills. The sections are to be cut to length metre joined with
corner bracket. Centre mullion is to be fixed with mullion cap. Handle, stay, 2
nos. of Stainless Steel heavy duty Pivot hinges shall be provided per shutter.
The windows should be panelled with 0.60 mm thick Galvalume corrugated
sheet having tensile strength of 550 MPA,(BMS-W.55). The above frames
should be fixed to the concrete/masonry wall by means of self expanding
screws, Including 10mm Square guard bars with 6 (152.4mm) pitch etc.,
complete for finished item of work.

Per
Unit

Rate
8
188.35

Double shutter Window with vertical mullion 4100 x 40 ( 1520mm x 1350mm)


outer frame section size of 48x50mm shutter frame section size of 48 x 25 mm.
Mullion section size of 48x50mm.SSR Rate
W1
W2

1
1

x
x

55
15

1.50
0.75

1.35
1.35

111.38
15.19
126.56
Or say
127.00
38 Supply and fixing of M.S. Grills including cost and conveyance of all materials
and all labour charges etc., complete
for main gate of size
6.00 x 2.70m
GW - 2.00 x 1.35m
GW1 - 1.35 x 1.35m
V1 - 2.10 x 0.45m
V2 - 0.90 x 0.45m
V3 - 1.22 x 0.30 over D

1
1
1
1
1
1

x
x
x
x
x
x

1
2
4
8
8
15

500.00
65.00
45.00
25.00
15.00
7.00

500.00
130.00
180.00
200.00
120.00
105.00

V4 - 1.50 x 0.30 over w

23

9.00

207.00

Sqm

1442.00 Kg

G.F.

34 of 517

7915.60 1

74.20

Measurements

Sl.
Description of item
No.

Nos.

QTY

Unit

1
2
3
4
5
6
7
39 Providing expansion joint treatment with ploy sulphide compound of approved
make of finsihed size 25 x 12 mm including making of 25mm x 12mm groove
and primer coat over finished groove with finishing of edges true to straight line
and level over the finished surface of expansion joint including cost and
convenyance of all materials to site, all incidental , operational , labour charges
etc., complete for finished item of work as per approved drawing ( for all floors
on top slab i.e, in the flooring and for internal vertical joints of grooves in
dadooing surface).
1

15.23
15.23
Or say
15.50 Sqm
40 Providing and Fixing of 24 guage alluminium sheet over expansion joint groove
of width 15cm fixed to walls / columns at one edge and resting over the other
blcok walls / columns concealing expansion joint with slotted holes for free edge
of aluminium sheet to faciliate free movement of aluminium sheet over the
finished surface of expansion joint and wall face using sheet metal screws with
nylon receiver complete including cost and convenyance of all materials to site,
all incidental , operational labour charges etc.,, complete for finsihed item of
work as per approved drawing ( for all floors for vertical joints and bottom of
slab).
1

25.38

25.38

329.50

493.10

457.90

975.65

0.300

0.300

10.00
10.00
Or say
10.00 No
43 Whiting to new walls and ceiling in two coats with Birla White or equavalent
quality to give an even shade after thoroughly brushing the surface to remove all
loose powdered materials including cost and conveyance of all materials and
water to site, sales & other taxes, all operational, incidental and labour charges
such as cleaning the surface, painting, curing etc., complete for finished item of
work for internal walls. (APSS No.901 & 908) in All Floors

10.00

As per ornamental plastering area in Qty.

G.F.

0.300

22.84
22.84
Or say
23.00 Sqm
42 Supplying , laying , aligning & jointing of RCC Hume Pipes of 300mm dia NP2
class including all necessary fixtures like collars of respective diameter including
cost and convenyance of all materilas to site, sales and othe taxes on all
materials , lifting, placing and fixing in position for finished item of work.
1

25.38

15.23
15.23
Or say
15.50 Sqm
41 Providing and Fixing of expansion joint filler board for Buildings , Columns ,
Beams and Slabs Armour Board " sillfill including cost and convenyance of all
materials to site, all incidental, operational , labour charges etc., complete for
finished item of work as per approved drawing for all floors
1

Per
Unit

Rate

1410.00

35 of 517

1410.00

Measurements

Sl.
Description of item
No.
1

Nos.

2
3
As per 12mm plastering area in Qty.

6
1890.00
Or say

QTY

Unit

Per
Unit

Rate

7
1890.00

3300.00
3300.00 Sqm

26.90

126.55

155.90

85.30

44 Painting to New walls with two coats of Plastic Emulsion paint of superior quality
of approved brand and shade over base coat of cement primer grade -I making
three coats in all to give an even shade after thoroughly brushing the surface to
remove all loose powdered materials, including cost and conveyance of all
materials, including cost and conveyance of all materials, cost of brushes, water
to site, etc., sales & other taxes, all operational, incidental and labour charges
such as scaffolding charges, lift charges, curing etc., complete for finished item
of work in all floors for Walls.(APSS No. 912) in All Floors

As per 12 mm plastering area in Qty. out side

1665.00

1665.00

1665.00
Or say
1665.00 Sqm
45 Painting to New wood work with two coats of ready mixed synthetic enamel
paint first quality all shades to give an even shade over base coat Primer with
Luppam finishing after thoroughly brushing the surface to remove all remains
including cost and conveyance of all materials to site, sales & other taxes, all
operational, incidental and labour charges etc., complete for finished item of
work.(3 coats) (APSS No. 1201 & 1212).in All Floors
D2
D5

19 x
2 x

2.25
2.25

1.20
1.05

2.13
2.13
Or say

109.27
10.06
119.33
119.50

Sqm

46 Painting to New Iron work with two coats of ready mixed synthetic enamel paint
first quality all shades over an existing steel primer including cost and
conveyance of all materials to site, sales & other taxes, incidental, operational
and all labour charges etc., complete for finished item of work. (APSS No. 1201,
1207 & 1212).in All Floors
Entrance gate

6.00

2.70

GW
GW 1
V1
V2
V3
V4

1
1
1
1
1
1

x
x
x
x
x
x

2
4
8
8
15
23

2.00
1.35
2.10
0.90
1.20
1.50

1.35
1.35
0.45
0.45
0.30
0.30

16.20

5.40
7.29
7.56
3.24
5.40
10.35
55.44
Or say
55.50 Sqm
47 Ornamental borders by providing 20 mm thick raised bands of 50 mm wide in
plain cement mortor bands in CM(1:4) including cost and conveyence of all
materials and labou charges for finished item of work.
bands for columns
for portico
G.F.

1
1

x
x

96
2

0.80
16.00
36 of 517

76.80
32.00

Measurements

Sl.
Description of item
No.
1

Nos.

QTY

Unit

7
108.80
Or say
109.00 rmt
48 Providing High Yield Strength Deformed (HYSD) steel bars (Fe 415 grade as
per IS 1786-1985) of 8mm to 40mm diameters, cutting, bending, to required
sizes and shapes placing in position with cover blocks of approved size and
binding wire of 20SWG, forming grills for reinforcement work as per approved
designs and drawings including cost and conveyance of bars from approved
sources to site of work, including cost and conveyance of binding wire, cover
blocks, chairs, overlaps, spacers, dowels, wastage etc., and all operational,
incidental, and labour charges such as cutting, bending, placing in position, tying
etc., and sales & other taxes,on cost of all materials complete for finished item
of work (APSS No.126) in Ground floor

Footings qty
Pedastals qty
Plinth beem qty
Columns Qty
Roof Beams Qty
Roof Slab 125mm th
Waist Slab 175mm th
Lintels Qty
Sunshades Qty

207.50 cum @
21.00 cum @
42.50 cum @
75.50 cum @
72.50 cum @
1402.00 sqm @
35.50 sqm @
7.00 cum @
96.00 sqm @

80
130
130
150
150
11
15
120
15

say

16600
2730
5525
11325
10875
15422
533
840
1440
65290
65.29
66.00

Per
Unit

Rate
8
20.50

MT

47131.20

Rm

3702.91

kgs

49 Supplying and fixing of stainless steel hand railing as per approved drawing with
top rail of 64mm dia (outer) 2mm thick pipe, vertical balusters of 50mm dia 2mm
thick at 600mm c/c spacing (7 Nos)and 3 nos 25mm dia (outer) 1.6mm thick
stainless steel pipes below top rail with equal spacings and 50mm wide 8mm
thick SS plate for fixing vertical balusters at 600mm centre with 100x100mm
stainless steel base plate to be fixed to the steps with Anchor fasteners. The
rate should include providing and using bonding agent, drilling of 25mm holes of
fixing railing , polishing of all nos of railing thouroughly and also including cost
and conveyance of all materials, electrodes, welding charges, cost of all
consumables, labour charges such as for fabrication of SS pipes, buffing,
polishing etc., complete for finished item of work.

For staircase railing


At landing

G.F.

2
2

x
x

2
2

4.00
1.50

37 of 517

16.00
6.00
22.00

Measurements

Sl.
Description of item
No.

Nos.

QTY

Unit

1
2
3
4
5
6
7
50 Providing Antitermite treatment as per IS 6315 (Part - 2) 2001 (Preconstructional chemical treatment measures) along the internal & external
vertical faces of the columns, plinth beams, basement and top surface of the
basement filling below flooring bed as per the specified procedure conforming to
IS 6315 (Part-2) 2001 and other relevant approved specification duly using
Chlorpyriphos/ Lindane emulsifiable concentrate 20% with 1% concentration @
7.5 Liters/ sqm of the vertical surface & @ 5.0 Liters/ sqm of the horizontal
surface of the substructure to a depth of 500 mm around columns & 300 mm
deep around plinth beams, basements & floor filling area including excavation
channel along the wall & rodding etc & cost & conveyance of all materials to the
site, cost of labour for spraying, rodding etc complete for finished item of work
as per the approval of the Engineer-in-Charge

G.F. Plinth area

1310.00

1310.00 Sqm

Per
Unit

Rate
8

254.50

TOTAL >>>

Executive Engineer
APEWIDC, CHITTOOR

Dy. Executive Engineer


APEWIDC, Madanapalli

Superintending Engineer
APEWIDC, KADAPA

G.F.

38 of 517

Asst. Executiv
APEWIDC, K

PPAM (M) CHITTOOR


Per
Unit
8

Amount
9

Cum

G.F.

71208

39 of 517

Per
Unit
8

Amount
9

Cum

191070

Cum

155454

G.F.

40 of 517

Per
Unit
8

Amount
9

Cum

208584

Cum

1703928

Cum

180033

G.F.

41 of 517

Per
Unit
8

Amount
9

Cum

G.F.

251143

42 of 517

Per
Unit
8

Amount
9

Cum

G.F.

433534

43 of 517

Per
Unit
8

Amount
9

G.F.

44 of 517

Per
Unit
8

Amount
9

Cum

569006

Sqm

19825

Cum

164670

G.F.

45 of 517

Per
Unit
8

Amount
9

Cum

G.F.

437805

46 of 517

Per
Unit
8

Amount
9

Cum

432340

Cum

55648

G.F.

47 of 517

Per
Unit
8

Amount
9

Cum

632998

Sqm

1483947

Sqm

48426

Cum

16024

G.F.

48 of 517

Per
Unit
8

Amount
9

Cum

G.F.

65888

49 of 517

Per
Unit
8

Amount
9

Cum

G.F.

1505991

50 of 517

Per
Unit
8

Amount
9

Sqm

50988

Sqm

67555

G.F.

51 of 517

Per
Unit
8

Amount
9

Sqm

90948

Sqm

2784

Sqm

14502

G.F.

52 of 517

Per
Unit
8

Amount
9

Cum

G.F.

20648

53 of 517

Per
Unit
8

Amount
9

Sqm

G.F.

546305

54 of 517

Per
Unit
8

Amount
9

Sqm

G.F.

481268

55 of 517

Per
Unit
8

Amount
9

Sqm

429325

Sqm

1222

G.F.

56 of 517

Per
Unit
8

Amount
9

Sqm

G.F.

1089165

57 of 517

Per
Unit
8

Amount
9

Sqm

G.F.

100904

58 of 517

Per
Unit
8

Amount
9

Sqm

17223

Sqm

18269

Each

221777

Each

21483

G.F.

59 of 517

Per
Unit
8

Amount
9

Rmt

25848

Sqm

55014

Sqm

33690

G.F.

60 of 517

Per
Unit
8

Amount
9

Sqm

56930

Sqm

108070

G.F.

61 of 517

Per
Unit
8

Amount

Sqm

9
8476

Sqm

1005281

Kg

G.F.

106996

62 of 517

Per
Unit
8

Amount
9

Sqm

5107

Sqm

7643

Sqm

10532

Rmt

9757

G.F.

63 of 517

Per
Unit
8

Amount
9

Sqm

88770

Sqm

210706

Sqm

18630

Sqm

4734

G.F.

64 of 517

Per
Unit
8

Amount
9

Rmt

2235

MT

3110659

Rm

81464

G.F.

65 of 517

Per
Unit
8

Amount
9

Sqm

333395
17085825

Asst. Executive Engineer


APEWIDC, KUPPAM

G.F.

66 of 517

FIRST FLOOR SUB ESTIMATE

Name of the Work :- Construction of Govt. Degree College at KUPPAM(V) of KUPPAM (M) CHITTOO
Measurements

Sl.
Description of item
No.

Nos.
3

L
4

B
5

QTY

D
6

Unit

2
7
FIRST FLOOR
1 Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching /
Mixer ) using 20mm size (SS5) hard granite machine crushed graded metal
(Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs.
of cement per 1 cum of concreteincluding cost and conveyance of all materials
like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost
of all materials including centering using Cashewrina Ballies and Wooden
runners & staging including all bracings, cross members etc., shuttering , machine
mixing, laying concrete, vibrating,lift charges, curing etc., complete but excluding
cost of steel and its fabrication charges but excluding seigniorage charges for
finished item of work (APSS No. 402 & 403) for columns in first floor

a For Columns upto bottom roof level


C1
1 x 11
C2
1 x 32
C3
1 x 6
C4
1 x 10
C5
1 x 25
C6
1 x 2
C7
1 x 19
C8
1 x 2
C9
0.78 x 24

0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.3
0.3

0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3

2.925
2.925
2.925
2.925
3.075
2.925
3.075
3.075
3.075
Or say

F.F.

4.34
12.64
2.37
3.95
10.38
0.79
7.89
0.55
5.18
48.09
48.50 Cum

For Roof Beams


RB1
RB2

4
4

x
x

7
7

3.38
3.04

0.23
0.23

0.3
0.3

6.53
5.87

RB3

16

7.28

0.23

0.405

21.70

RB4

12

3.1

0.23

0.3

5.13

RB5

7.28

0.23

0.405

9.49

RB6

2.17

0.23

0.3

2.10

RB7

16

2.17

0.23

0.3

4.79

RB8

7.06

0.23

0.3

0.97

RB9

13

2.17

0.23

0.3

3.89

RB10

7.06

0.23

0.405

1.32

RB11

5.93

0.3

0.405

2.88

RB12

3.53

0.23

0.3

0.49

Brusummer beam

3.38

0.23

0.23

2.50

3.04

0.23

0.23

2.25

7.06

0.23

0.23

0.75

67 of 517

Pe
Un

Rate
8

1180.10

Sl.
Description of item
No.
1

2
staircase Mid landing
beam

Measurements
Nos.
3
1 x 2

L
4
3.53

B
5
0.23

D
6
0.45

QTY

Unit

Pe
Un

Rate

7
0.73

71.40
c FOR ROOF SLAB 125 MM THICK
Entire area
1 x 1
Duct area
1 x 4
open to sky
1 x 2

64.11
4.63
20.38

71.50 Cum

8979.25

Or say

1627.11
-18.52
-264.12
1344.47
1344.50 Sqm

1087.95

1400.15

6492.55

357.25

25.38
1
6.48

d FOR STAIRCASE WAIST SLAB 175 MM THICK


1st & 2nd flight
2 x 2
4.00
landing

Or say

3.53

1.55

24.80

1.50

10.59
35.39
Or say

35.50 Sqm

2 Plain Cement Concrete M20 Design Mix ( by weigh batching ) using 20mm size
(SS5) hard blasted granite machine crushed graded metal (Coarse aggregate)
from approved quarry, using a minimum quantity of 350 kgs. of cement per 1 cum
of concrete including cost and conveyance of all materials like cement, fine
aggregate (Sand), coarse aggregate, water etc., to site and cost of all materials
including steel centering, shuttering, machine mixing, laying concrete, lift charges,
curing etc., complete but excluding seigniorage charges for finished item of work
for steps (APSS No. 402 ) in First floor

stair case steps

22 x

0.5 1.5

0.3

0.15

0.74

22 x

0.5 1.5

0.3

0.15

0.74
1.485

Or say
1.50 Cum
3 Providing impervious coat over RCC roof slab to required slopes with CM (1:3)
prop. 20mm thick (average) mixed with water proofing compound manufactured by
reputed manufacturers as approved by Engineer-in-charge at 1Kg/bag of cement,
laid over roof slab when it is green, finished smooth with a floating coat of neat
cement and thread lining at regular intervals of 45cmx45cm including cost and
conveyance of all materials like cement, sand, water proofing compound, water
etc., to site, sales & other taxes on all materials, all operational, incidental and
labour charges such as mixing mortar, laying, rounding off at junctions of wall and
slab, rendering smooth with thread lining, curing, lift charges, etc., complete but
excluding seigniorage charges for finished item of work (APSS No. 901 & 903). In
first floor

On entire slab

989.50
989.50
Or say 990.00

F.F.

68 of 517

Sqm

Measurements

Sl.
Description of item
No.

QTY
Unit
Nos.
L
B
D
1
2
3
4
5
6
7
4 Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm
size (SS5)
hard blasted granite machine crushed graded metal (Coarse
aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement
per 1 cum of concrete including cost and conveyance of all materials like cement,
fine aggregate (Sand), coarse aggregate, water etc., to site and cost of all
materials including centering using Cashewrina Ballies and Wooden runners &
staging including all bracings, cross members etc., shuttering , machine mixing,
laying concrete, lift charges, curing etc., complete but excluding cost of steel and
its fabrication charges but excluding seigniorage charges for finished item of work
(APSS No. 402 & 403) for Lintels in first floor

D2
D3
D4
W1
W2
GW
V2

0.98
0.09
0.25
3.42
0.54
0.16
0.79
6.23
Or say
6.50
Cum
5 Reinforced cement concrete with M 20 grade Design mix ( by weigh batching )
using 20mm size (SS 5) machine crushed hard blasted granite graded metal
(coarse aggregate) from approved quarry using a minimum quantity of 350 Kg of
cement per 1 Cum of concrete including cost and conveyance of all materials like
cement, fine aggregate (sand) ,coarse aggregate, water etc. to site and cost of
all materials including centering using Cashewrina Ballies and Wooden runners
& staging including all bracings, cross members etc., shuttering, machine mixing,
laying concrete, for sunshade of 7.5cm thick at fixed end and 5cm thick at free
end with an average thickness of 6.25cm including labour charges for
mixing, laying, curing etc., complete but excluding cost of steel and its
fabrication charges but excluding seigniorage charges for finished item of work for
First floor
for sun shades
On out side windows
W1
open to sky

1
1
1
1
1
1
1

x
x
x
x
x
x
x

19
2
14
55
15
2
19

1.5
1.35
1.05
1.8
1.05
2.3
1.2

0.23
0.23
0.115
0.23
0.23
0.23
0.23

41

1.8

0.6

44.28

1
1
1

x
x
x

2
2
2

19.76
17.76
5.26

0.6
0.6
0.6

23.712
21.312
6.312
95.62
96.00

69 of 517

0.15
0.15
0.15
0.15
0.15
0.15
0.15

Or say

F.F.

Pe
Un

Rate

Sqm

9739.45

727.85

Measurements

Sl.
Description of item
No.

QTY
Unit
Nos.
L
B
D
1
2
3
4
5
6
7
6 Brick Masonry in superstructure with CM (1:8) prop: using Fly ASH Bricks of size
290x225x140mm with compressive of 50 Kgs / Sqcm from approved source
including cost and conveyance of all materials like cement, sand, fly ash bricks,
water etc., to site, including sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing cement mortar, constructing
masonry, scaffolding charges, lift charges, curing, etc., complete but excluding
seigniorage charges for finished item of work. (APSS No. 501 & 504).for first floor

L/w in Lobby area

0.23

3.175

4.38

S/w in Lobby area

4.92

0.23

3.07

6.95

L/w in Lunch room-1

9.5

0.23

3.175

13.87

S/w in Lunch room-1

6.38

0.23

3.07

9.01

L/w in Lunch room-2

8.49

0.23

3.175

12.40

S/w in Lunch room-2

6.38

0.23

3.07

9.01

L/w in class room-1,5

8.61

0.23

3.175

25.15

S/w in class room-1,5

6.38

0.23

3.07

18.02

L/w in class room-2,6

8.54

0.23

3.175

24.95

S/w in class room-2,6

6.38

0.23

3.07

9.01

L/W in open auditorium

11.94

0.23

3.175

17.44

L/w in class room-3

9.44

0.23

3.175

13.79

S/w in class room-3

6.38

0.23

3.07

13.51

L/w in class room-4

9.44

0.23

3.175

13.79

S/w in class room-4

6.38

0.23

3.07

0.00

L/w in physical dic.

8.46

0.23

3.175

12.36

S/w in physical dic.

6.38

0.23

3.07

0.00

L/w in class room-5

8.69

0.23

3.175

12.69

S/w in class room-5

6.38

0.23

3.07

18.02

L/W in toilet blocks

4.64

0.23

3.07

13.11

6.515

0.23

3.175

19.03

S/W in toilet blocks

3.77

0.23

3.175

5.51

At passage

2.17

0.23

3.175

6.34

Stair case

5.38

0.23

3.075

15.22

3.58

0.23

3.175

5.23

7.06

0.23

3.175

10.31

2
2
1
2
2
1

x
x
x
x
x
x

7
7
2
7
7
2

3.38
3.04
7.06
3.38
3.04
7.06

0.23
0.23
0.23
0.23
0.23
0.23

0.815
0.815
0.815
0.9
0.9
0.9

8.87
7.98
2.65
9.80
8.81
2.92

above brusummer beam

Dwarf walls

Deductions of Lintels
F.F.

70 of 517

Pe
Un

Rate
8

Measurements

Sl.
Description of item
No.
1

2
OVER DOORS & WINDOWS
D2
1
D4
1
W1
1
W2
1
GW
1
V2
1
bed blocks for rooms
D2
1
D4
0
W1
1
W2
1
GW
1
V2
1

Nos.
3

F.F.

x
x
x
x
x
x

3
3
4
4
2
13

1.5
1.05
1.8
1.05
2.3
1.2

0.23
0.115
0.23
0.23
0.23
0.23

D
6

QTY

Unit
7

19

1.50
1.10
1.30
1.10
1.72
0.75

0.23

Pe
Un

Rate
8

0.15
0.15
0.15
0.15
0.15
0.15

11.25
8.25
26.00
22.00
8.60
deducting door-D4
-20.77
55.33
Or say
55.50
Sqm
8 Plain Cement Concrete corresponding to M10 grade as per IS 456 equivalent to
(1:3:6) proportion nominal mix (cement: fine aggregate: Coarse aggregate) using
20mm size Hard Blasted Granite (IS383, 1970) Machine Crushed graded metal
from from approved quarry including cost and conveyance of all materials like
cement, sand, coarse aggregate, water etc. to site, including sales & other taxes
on all materials, all operational, incidental and labour charges such as mixing,
laying, curing concrete, etc., complete but excluding seigniorage charges for
finished item of work for Bed Blocks and Hold Fasts (APSS No. 402)

D2

1
1
2
2
1
1

19
13
58
11
2
18

B
5

-0.98
-0.24
-3.60
-0.40
-0.16
-0.75
-4.00
x 19
1.20
0.23
2.13
-11.17
x 13
0.75
0.23
2.13
0.00
x 58
1.50
0.23
1.35
-27.01
x 11
0.75
0.23
1.35
-2.56
x 2
2.00
0.23
1.35
-1.24
x 18
0.90
0.23
0.45
-1.68
296.32
Or say
297.00 Cum
7 Reinforced Fly Ash Brick Masonry 10cm thick for partition walls in CM (1:4) prop:
Fly Bricks of size 290x100x140mm with compressive of 50 Kgs / Sqcm from
approved source and placing 2nos. of 6mm dia MS bars embedded in every 3rd
layer with free ends of reinforcement keyed into mortar joints of the main brick
work whereever applicable including cost and conveyance of all materials like
cement, sand, bricks, water etc., to site, sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing cement mortar,
constructing masonry, scaffolding charges, lift charges, curing, etc., but excluding
cost and conveyance of steel and its fabrication charges & seignerage charges
complete for finished item of work. (APSS No. 501 & 509). for first floor

toilet blocks
L/w's

x
x
x
x
x
x

L
4

5651.45 1

2.50
2.50
2.50
2.50
2.50
2.13

0.23

71 of 517

0.15

0.90

666.70 1

Measurements

Sl.
Description of item
No.
1

2
D4
W1
W2
GW
V2

6
4
4
4
4

Nos.
3
x 13
x 58
x 11
x 2
x 18

L
4
0.115
0.23
0.23
0.23
0.23

B
5
0.115
0.23
0.23
0.23
0.23

D
6
0.15
0.15
0.15
0.15
0.15

QTY

Unit
7

0.15
1.84
0.35
0.06
0.57
3.88
Or say
4.00
Cum
9 Supply and Fixing of Door with Double leaf shutter, Door Size 1.22x2.13 mtrs with
Sal wood Frame of sections size 75mm x 100mm with Flush Door Shutter Solid
Bond Wood black board type with commercial ply on both faces of 35mm thick
including cost of fixtures such as M.S.Powder Coated Tower Bolts 250mm long 2
Nos, MS powder coated Handles 150mm long 2 Nos, 300mm long M.S.Powder
Coated Aldrops 1No, 125mm long M.S.Powder Coated butt hinges 6Nos, 300 mm
long M.S.Powder Coated Flat latch 1No, Door stoppers 2 Nos, MS Hold fasts
6Nos, Sales and Other Taxes cost and convenyance of all materials to site all
Labour charges such as Fixing of Door Frame on shutter Fixing in position , with
Hardware fixtures etc., complete for finsihed utem of work.

19.00
Or say 19.00
Each
10 Providing and Fixing of openable double shutter windows made of pre-painted
steel (Base steel as per IS 513 of 0.58 mm thick galvanized as per IS 277 with
Zinc of 120 GSM). Primer coated with epoxy primer of 5-7 microns thick, finish
painted with a polyester paint of 12-16 microns thick and back coated with 5-7
microns thick alkyd backer. Section for outer frame should be of 48x50mm, centre
mullion should be of 48x50mm, section for shutter should be of 48x25mm and
fixed panel beading section should be 12x12mm. Outer frame and mullions to
have rebate for Galvalume corrugated sheet shutter and a 20mm provision for
Guard bars/Grills. The sections are to be cut to length metre joined with corner
bracket. Centre mullion is to be fixed with mullion cap. Handle, stay, 2 nos. of
Stainless Steel heavy duty Pivot hinges shall be provided per shutter. The
windows should be panelled with 0.60 mm thick Galvalume corrugated sheet
having tensile strength of 550 MPA,(BMS-W.55). The above frames should be
fixed to the concrete/masonry wall by means of self expanding screws, Including
10mm Square guard bars with 6 (152.4mm) pitch etc., complete for finished item
of work.

Pe
Un

Rate
8

5245.00

11672.45

19

Double shutter Window with vertical mullion 410 x 40 ( 1520mm x 1350mm)


outer frame section size of 48x50mm shutter frame section size of 48 x 25 mm.
Mullion section size of 48x50mm.
W1
W2

117.45
11.14
128.59
Or say 129.00
Sqm
14 Supply and fixing of M.S. Grills including cost and conveyance of all materials and
all labour charges etc., complete

F.F.

1
1

x
x

58
11

1.5
0.75

1.35
1.35

72 of 517

7915.60 1

Measurements

Sl.
Description of item
No.
1

Nos.
3
x 2
x 4
x 8
x 8
x 17
x 28

2
GW - 2.00 x 1.35m
GW1 - 1.35 x 1.35m
V1 - 2.10 x 0.45m
V2 - 0.90 x 0.45m
V3 - 1.22 x 0.30 over D
V4 - 1.50 x 0.30 over w

L
4
65.00
45.00
25.00
15.00
7.00
9.00

B
5

D
6

QTY

Unit

7
1
130.00
1
180.00
1
200.00
1
120.00
1
119.00
1
252.00
1001.00
Kg
15 Providing and fixing factory made polyvinyl chloride (PVC) Door Frame of the size
50 x 47mm with a wall thickness of 5mm, made out of extruded 5mm rigid PVC
foam sheet, mitre cut at two corners and joined with 2nos. of 150mm long brackets
of 15x15mm M.S. square tube. The two vertical door profiles are to be reinforced
with 19x19mm M.S. Square tube of 19 gauge. The door frame shall be fixed to the
wall using 65/100mm long M.S. Screws through the frame by using PVC fasteners.
A minimum of 4nos. of screws to be provided for each vertical member & minimum
2nos. for horizontal member etc. complete as per manufacturers specification and
direction of Engineer-in-Charge for finished item of work

Toilet

65.00
65.00
Or say
65.00 rmt
19 Providing and fixing 30mm thick Solid panel PVC door shutter consisting of frame
made out of M.S. tubes of 19 gauge thickness and size of 19mm x 19mm for
stiles, & 15mm x 15mm for top & bottom rails. M.S. frame shall have a coat of
steel primers of approved make and manufacture. M.S. frame shall be covered
with 5mm thick heat moulded PVC C channel of size 30 x 50mm forming stiles,
and 5mm thick, 75mm wide PVC sheets for top rail, lock rail & bottom rail on either
side, and 10mm (5mm x 2) thick, 20mm wide cross PVC sheet as gap insert for
top rail & bottom rail. Panelling of 10mm thick PVC sheet to be fitted in the M.S.
frame welded / sealed to the stiles & rails with 30mm wide x 5mm thick PVC sheet
beading on either side, and joined together with solvent cement adhesive etc. An
additional 5mm thick PVC strip of 20mm width is to be stuck on the interior side of
the C Channel using PVC solvent adhesive. Complete as per direction of
Engineer-in-charge, manufacturers specification & drawing for finished item of
work .1

Toilet

13

13

74.20

369.25

2683.60

5.00

0.70

2.080
Or say

F.F.

Pe
Un

Rate

73 of 517

18.93
18.93
19.00 Sqm

Measurements

Sl.
Description of item
No.

QTY
Unit
Nos.
L
B
D
1
2
3
4
5
6
7
20 Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm
size (SS5)
hard blasted granite machine crushed graded metal (Coarse
aggregate) from approved quarry, using a minimum quantity of 350 kgs. of cement
per 1 cum of concrete including cost and conveyance of all materials like cement,
fine aggregate (Sand), coarse aggregate, water etc., to site and cost of all
materials including centering using Cashewrina Ballies and Wooden runners &
staging including all bracings, cross members etc., shuttering , machine mixing,
laying concrete, lift charges, curing etc., complete but excluding cost of steel and
its fabrication charges but excluding seigniorage charges for finished item of work
(APSS No. 402 & 403) for 50 mm thick platform

for RCC platform 50 mm


thick for hand wash

2.50

0.30

1
2

x
x

2
2

2.45
4.00

1.00
1.00
Or say

4.89
16.00
20.89
21.00

22 Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and
top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and
conveyance of all materials like cement, sand, water etc., to site, sales & other
taxes on all materials,all operational, incidental and labour charges such as mixing
mortar, scaffolding charges, lift charges, including cutting of Grooves wherever
necessary as directed by Engineer - in - charge, finishing, curing, etc., complete
but excluding seigniorage charges for Even Surfaces of Wall for finished item of
work. (APSS 901,903 & 904)

F.F.

L/w in Lobby area


S/w in Lobby area
L/w in Lunch room-1
S/w in Lunch room-1

1
1
1
1

x
x
x
x

1
2
2
2

6
4.92
9.96
6.60

3.500
3.500
3.500
3.500

21.00
34.44
69.72
46.20

L/w in Lunch room-2

8.95

3.500

62.65

74 of 517

1.50

1.50
Or say
2.00
Sqm
21 Reinforced cement mortar Facia 5 cm thick in CM (1:3) for drop walls, Fins &
staircase railing with rabbit wire mesh & nominal reinforcement as directed by
Engineer-in-charge with dubara spong finishing including cost & conveyence of all
materials to site, including sales and other taxes on all materials and all
operational, incidental charges such as labour charges, like mixing cement mortar,
scaffolding charges, lift charges, curing, for making 50 mm thick RCM Paradah
walls (RCM Drop walls) including tying Rabbit (chicken) wire mesh to the existing
mild steel / HYSD Steel reinforcement applying mortar lumps, finishing, plastering
to both faces, sponge finishing etc complete for finished item of work but excluding
cost of steel and its fabrication charges and seigniorage charges in All Floors

for hand wash


for stair case

Pe
Un

Rate

Sqm

631.40

1734.00

Sl.
Description of item
No.
1

Measurements
B
5

D
6
3.500

QTY

2
S/w in Lunch room-2

Nos.
3
1 x 2

L
4
6.60

L/w in class room-1,5


S/w in class room-1,5

2
2

x
x

2
2

9.07
6.60

3.500
3.500

126.98
92.40

L/w in class room-2,6


S/w in class room-2,6

2
1

x
x

2
2

9.00
6.60

3.500
3.500

126.00
46.20

L/W in open auditorium

12.41

3.500

86.87

S/W in open auditorium

6.60

3.500

46.20

L/w in class room-3

9.90

3.500

69.30

S/w in class room-3

6.60

3.500

69.30

L/w in class room-4

9.97

3.500

69.79

S/w in class room-4

6.60

3.500

46.20

L/w in physical dic.

8.92

3.500

62.44

S/w in physical dic.

6.60

3.500

46.20

L/w in class room-5

8.92

3.500

62.44

S/w in class room-5

6.60

3.500

92.40

L/W in toilet blocks

4.64

3.500

64.96

6.52

3.500

91.21

S/W in toilet blocks

3.77

3.500

26.39

Stair case

5.38

3.500

75.32

3.58

3.500

25.06

above brusummer beam

Dwarf walls

0.00
2

3.38

1.100

52.05

3.04

1.100

46.82

7.06

1.100

15.53

3.38

0.900

42.59

2
1

x
x

7
2

3.04
7.06

0.900
0.900

38.30
12.71

toilet blocks
L/w's

7
46.20

0.00
2

1.5

2.800

25.20

1.1

2.800

18.48

1.3

2.800

58.24

1.1

2.800

49.28

1.72

2.800

19.26

13

0.75

2.130

-20.77

D2

0.5 x

19

1.2

2.13

-24.28

D4

0.5 x

13

0.75

2.13

-10.38

deducting door-D4
Deductions

F.F.

75 of 517

Unit

Pe
Un

Rate
8

Sl.
Description of item
No.

Measurements

W1

1.5

D
6
1.35

W2

0.5 x

11

0.75

1.35

-5.57

GW

0.5 x

1.35

-2.70

V2

0.5 x

18

0.9

0.45

-3.65

L
4

B
5

QTY

Nos.
3
0.5 x 58

Unit

Pe
Un

Rate

7
-58.73

1858.26
Or say
1860.00 Sqm
23 Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and
top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and
conveyance of all materials like cement, sand, water etc., to site, sales & other
taxes on all materials,all operational, incidental and labour charges such as mixing
mortar, scaffolding charges, lift charges, including cutting of Grooves wherever
necessary as directed by Engineer - in - charge, finishing, curing, etc., complete
but excluding seigniorage charges for Even Surfaces of Wall for finished item of
work. (APSS 901,903 & 904)
out side L/w's
out side c/w 's
in varandah L/w's
near stair case
Cutout
Dwarf walls

1
1
1
1
1
2
2
2
2
1

x
x
x
x
x
x
x
x
x
x

2
2
2
2
2
4
4
7
7
2

64.11
25.38
45.66
18.3
7.06
4.63
1
3.38
3.04
7.06

3.6
3.6
3.475
3.475
3.475
3.6
3.6
0.9
0.9
0.9

461.59
182.74
317.34
127.19
49.07
133.34
28.80
42.59
38.30
12.71

2
2
2
2

x
x
x
x

7
7
2
2

3.38
3.04
7.06
6

1.47
1.47
1.47
3.6

69.56
62.56
41.51
86.40

0.5
0.5
0.5
0.5
0.5
0.5
2

x
x
x
x
x
x
x

19
13
58
11
2
18
52

1.2
0.75
1.5
0.75
2
0.9
0.22

2.13
2.13
1.35
1.35
1.35
0.45
3.60

315.45

above brusummer beam

Stair case out side walls


Deductions
D2
D4
W1
W2
GW
V2
Column faces

Or say

F.F.

76 of 517

-24.28
-10.38
-58.73
-5.57
-2.70
-3.65
82.37
1630.76
1635.00

Sqm

315.45 1

Measurements

Sl.
Description of item
No.

QTY
Unit
Nos.
L
B
D
1
2
3
4
5
6
7
24 Ornamental Plastering 12mm thick in two coats with base coat of 8mm thick in CM
(1:5) and top coat of 4mm thick in CM (1:3) dubara sponge finish including cost
and conveyance of all materials like cement, sand, water etc., to site, sales & other
taxes on all materials,all operational, incidental and labour charges such as mixing
mortar, scaffolding charges, lift charges, including cutting of Grooves wherever
necessary as directed by Engineer - in - charge, finishing, curing, etc., complete
for Even Surfaces of Wall but excluding seigniorage charges for finished item of
work. (APSS 901,903 & 904)
Lobby area
Lunch room-1
Lunch room-2
class room-1,5
Class room-2,6
open auditorium
class room-3
class room-4
physical dic.
class room-5
toilet blocks
WC
Hand wash
passage

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Passage
1
Staircase room
0
Beam bottom
1
1
Staircase waist slab botto 2
landing slab bottom
1
Sunshades bottom & top 2
Brusummer beam
1
1
1
open to sky sunshade
2
2
2

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

1
1
1
2
2
1
1
1
1
1
2
2
2
2
2
1
2
21
46
2
2
38
7
7
2
2
2
2

6.00
9.96
8.95
9.07
9.00
12.41
9.90
9.97
8.92
8.92
4.86
1.74
1.74
45.19
18.3
7.6
5.63
6.38
2.17
4
3.58
1.8
3.38
3.05
7.06
19.76
17.76
5.26

4.92
6.60
6.60
6.60
6.600
6.60
6.60
6.60
6.60
6.60
4.00
2.40
4.00
2.17
2.17
6
3.58
0.23
0.23
1.5
1.5
0.6
0.23
0.23
0.23
0.6
0.6
0.6
Or say

F.F.

77 of 517

29.52
65.74
59.07
119.72
118.80
81.91
65.34
65.80
58.87
58.87
38.88
8.35
13.92
196.12
79.42
45.60
0.00
30.82
22.96
24.00
10.74
82.08
5.44
4.91
3.25
47.42
42.62
12.62
1392.81
1395.00

Sqm

Pe
Un

Rate
8

304.49

Measurements

Sl.
Description of item
No.

QTY
Unit
Nos.
L
B
D
1
2
3
4
5
6
7
25 Flooring with Polished bethamcherla colour stone of 25 mm thick (0.254x0.254M)
set over a base coat of CM (1:8), 12mm thick (joints of stone must be flushed)
over C.C. bed already laid or R.C.C. roof slab only after it is properly cured,
cleaned, moistered and where necessary treated with neat grey cement slurry of
honey like consistency spred at3.3 kgs of cement for 1 sqm. and jointed with neat
cement paste to full depth, including cost and conveyance of all materials like
cement, sand, water, flooring stones etc. to site, sales and other taxes on all
materials, all operational, incidental and labour charges such as dressing of
flooring stones to the required sizes, mixing of cement mortar, laying, jointing,
curing, lift charges etc., complete but excluding seigniorage charges for finished
item of work.(APSS No.703 & 701)

Lobby area
Lunch room-1
Lunch room-2
class room-1,5
Class room-2,6
open auditorium
class room-3
class room-4
physical dic.
class room-5
passage

29.52
65.74
59.07
119.72
118.80
81.91
65.34
65.80
58.87
58.87
196.12
79.42
Passage
45.60
landing slab bottom
10.74
1055.53
Or say
1060.00 Sqm
26 Providing skirting to internal walls 12.5 Cm high withPolished bethamcherla colour
stone of 25 mm thick (0.254x0.254M) with length equal to flooring stones set over
a base coat of CM (1:3), 12mm thick with cement slurry of honey like consistency
spread @ 3.3 Kgs per sqm and jointed with neat cement paste mixed with pigment
of matching shade to full depth (joints of stone should be flushed), including cost
and conveyance of all materials like cement, sand, water, flooring stones etc. to
site, sales and other taxes on all materials, all operational, incidental and labour
charges such as dressing of flooring stones to the required sizes, mixing of
cement mortar, laying, jointing, curing, lift charges etc., complete but excluding
seigniorage charges for finished item of work.(APSS No.701 & 707)

Lobby area
Lunch room-1
Lunch room-2
class room-1,5
Class room-2,6

F.F.

1
1
1
1
1
1
1
1
1
1
1
1
1
1

1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x

x
x
x
x
x

1
1
1
2
2
1
1
1
1
1
2
2
1
2

1
1
1
2
2

6
9.96
8.95
9.07
9
12.41
9.9
9.97
8.92
8.92
45.19
18.3
7.6
3.58

Pe
Un

Rate
8

4.92
6.6
6.6
6.6
6.6
6.6
6.6
6.6
6.6
6.6
2.17
2.17
6
1.5

10.92
16.56
15.55
15.67
15.60

78 of 517

0.125
0.125
0.125
0.125
0.125

1.37
2.07
1.94
3.92
3.90

969.95

Measurements

Sl.
Description of item
No.
1

2
open auditorium
class room-3
class room-4
physical dic.
class room-5
passage
Passage
landing slab bottom

1
1
1
1
1
1
1
1
1

Nos.
3
x 1
x 1
x 1
x 1
x 1
x 2
x 2
x 1
x 2

L
4
19.01
16.50
16.57
15.52
15.52
47.36
20.47
13.60
5.08

B
5

D
6
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125
0.125

QTY

Unit
7

11.44
4.95
8.35
toilet passage
6.17
9.14
for hand wash
13.92
53.97
Or say
54.00
Sqm
28 Dadooing to walls with white glazed tiles 1st. quality of any size of brand as
approved by Engineer - in - charge and set over a base coat of CM (1:5), 12mm
thick and neat cement paste at the rate of 3.3 Kg/Sqmt. and jointed with white
cement paste mixed with pigment of matching shade including cost and
conveyance of all materials like cement, sand, water, tiles, etc. to site, sales and
other taxes on all materials, C921 such as mixing of cement mortar, laying in
position, curing, lift charges etc., complete but excluding seigniorage charges for
finished item of work (APSS No.701 & 707) in All Floors
toilet rooms

toilet passage

for hand wash

F.F.

2
1
1
1
1
1

x
x
x
x
x
x

4
3
2
1
1
2

1.10
1.10
1.74
1.27
1.88
1.74

2.38
2.06
2.07
1.94
1.94
11.84
5.12
1.70
1.27
43.51

Or say 44.00
Sqm
27 Flooring with Ceramic Tiles of 7.3mm thick 1st. quality of any shade as approved
by Engineer - in - charge set over a base coat of CM (1:8), 12mm thick laid over
flooring bed / V.R.C.C. slab, with neat cement slurry of honey like consistency
spread at the rate of 3.3 Kgs of cement per Sq.m and jointed with neat white
cement paste to full depth mixed with pigment of matching shade including cost
and conveyance of all materials like cement, sand, water, ceramic tiles etc. to site,
sales and other taxes on all materials, all operational, incidental and labour
charges such as mixing of cement mortar, laying, curing, lift charges etc.,
complete but excluding seigniorage charges for finished item of work.(APSS
No.701 & 707) in All Floors
toilet rooms

Pe
Un

Rate

1024.70

902.25

1.300
1.500
2.400
4.860
4.86
4.00

4.800

1.50

14.40

5.200

1.50

23.40

8.280

1.50

24.84

12.260

1.50

18.39

13.480

1.50

20.22

11.480

1.50

34.44

79 of 517

Measurements

Sl.
Description of item
No.
1

Nos.
3

L
4

B
5

D
6
Or say

QTY

Unit

7
135.69
136.00

Pe
Un

Rate
8

Sqm

546.95

Sqm

637.73

1259.90

155.90

29 Supplying and fixing of Polished Black Kadapa slabs minimum of 15 mm thick


(0.457M x 0.457M) in Single piece with the edges flat nosed and set over a base
coat of CM (1:8), 12mm thick, and fixing in position with neat cement paste
including cost and conveyance of all materials like cement, sand, water, stones
etc. to site, seigniorage charges, sales and other taxes on all materials, all
operational, incidental and labour charges such as dressing of stones to the
required sizes, mixing of cement mortar, fixing in position, curing, lift charges etc.,
complete for finished item of work for Treads (APSS No.701 & 707)
staircase steps

11

1.50

0.300

19.80
19.80
Or say

20.00

30 Supplying and fixing of Polished Black Kadapa slabs minimum of 15 mm thick


(0.457M x 0.457M) in Single piece with the edges flat nosed and set over a base
coat of CM (1:3), 12mm thick, and fixing in position with neat cement paste
including cost and conveyance of all materials like cement, sand, water, stones
etc. to site, seigniorage charges, sales and other taxes on all materials, all
operational, incidental and labour charges such as dressing of stones to the
required sizes, mixing of cement mortar, fixing in position, curing, lift charges etc.,
complete for finished item of work For raisers (APSS No.701 & 707)

staircase

23

1.50

0.150

10.35

10.35
Or say
10.50
Sqm
31 Painting to New wood work with two coats of ready mixed synthetic enamel paint
first quality all shades to give an even shade over base coat Primer with Luppam
finishing after thoroughly brushing the surface to remove all remains including
cost and conveyance of all materials to site, sales & other taxes, all operational,
incidental and labour charges etc., complete for finished item of work.(3 coats)
(APSS No. 1201 & 1212).in All Floors
D2

109.27
109.27
Or say 109.50
Sqm
32 Painting to New Iron work with two coats of ready mixed synthetic enamel paint
first quality all shades over an existing steel primer including cost and conveyance
of all materials to site, sales & other taxes, incidental, operational and all labour
charges etc., complete for finished item of work. (APSS No. 1201, 1207 & 1212).in
All Floors
GW
GW 1
V1
V2

F.F.

19 x 2.25 1.20

1
1
1
1

x
x
x
x

2
4
8
8

2.1

2.00
1.35
2.10
0.90

1.35
1.35
0.45
0.45

80 of 517

5.40
7.29
7.56
3.24

Sl.
Description of item
No.
1

2
V3
V4

Measurements
Nos.
3
1 x 17
1 x 28

L
4
1.20
1.50

B
5

D
6
0.30
0.30

QTY

Unit

Pe
Un

Rate

6.12
12.60
42.21
Or say 42.50
Sqm
33 Whiting to new walls and ceiling in two coats with Surya cem or equavalent quality
to give an even shade after thoroughly brushing the surface to remove all loose
powdered materials including cost and conveyance of all materials and water to
site, sales & other taxes, all operational, incidental and labour charges such as
cleaning the surface, painting, curing etc., complete for finished item of work for
internal walls. (APSS No.901 & 908) in All Floors

85.30

26.90

Sqm

126.55

Rmt

548.80

2.70
2.70
3.00 Sqm

457.90

As per Ornamental Plastering area Qty


As per 12 MM Plastering area Qty

1395.00
1860.00
3255.00
Or say 3255.00
Sqm
34 Painting to New walls with two coats of Plastic Emulsion paint of superior quality of
approved brand and shade over base coat of cement primer grade -I making three
coats in all to give an even shade after thoroughly brushing the surface to remove
all loose powdered materials, including cost and conveyance of all materials,
including cost and conveyance of all materials, cost of brushes, water to site, etc.,
sales & other taxes, all operational, incidental and labour charges such as
scaffolding charges, lift charges, curing etc., complete for finished item of work in
all floors for Walls.(APSS No. 912) in All Floors

As per 12 MM Plastering area Qty out side

1635.00
Or say 1635.00

35 Supply and fixing of 110mm dia ISI mark PVC rain water spouts of 2.5 Kg/cm2
pressure including Cost of necessary pvc bends, shoes and M.S.clamps and all
other accessories and fixing in position including cost and conveyance of all
materials to site , seigniorage charges sales and other taxes on all materials, all
operational, incidental and labour cahrges such as fixing in alignment etc.,
complete for finished item of work.(APSS NO1328) in All Floors
1

25

7.60

190.00
190.00
Or say 190.00

36 Providing and Fixing of expansion joint filler board for Buildings , Columns , Beams
and Slabs Armour Board " sillfill including cost and convenyance of all materials to
site, all incidental, operational , labour charges etc., complete for finished item of
work as per approved drawing for all floors
1

3.00

0.300
Or say

F.F.

81 of 517

Measurements

Sl.
Description of item
No.

QTY
Unit
Nos.
L
B
D
1
2
3
4
5
6
7
37 Providing expansion joint treatment with ploy sulphide compound of approved
make of finsihed size 25 x 12 mm including making of 25mm x 12mm groove and
primer coat over finished groove with finishing of edges true to straight line and
level over the finished surface of expansion joint including cost and convenyance
of all materials to site, all incidental , operational , labour charges etc., complete
for finished item of work as per approved drawing ( for all floors on top slab i.e, in
the flooring and for internal vertical joints of grooves in dadooing surface).

9.00
9.00
Or say 9.00
Sqm
38 Providing and Fixing of 24 guage alluminium sheet over expansion joint groove of
width 15cm fixed to walls / columns at one edge and resting over the other blcok
walls / columns concealing expansion joint with slotted holes for free edge of
aluminium sheet to faciliate free movement of aluminium sheet over the finished
surface of expansion joint and wall face using sheet metal screws with nylon
receiver complete including cost and convenyance of all materials to site, all
incidental , operational labour charges etc.,, complete for finsihed item of work as
per approved drawing ( for all floors for vertical joints and bottom of slab).

10

9.80

329.50

493.10

318.15

0.150

43.00
43.00
Or say 43.00
Sqm
40 Providing High Yield Strength Deformed (HYSD) steel bars (Fe 415 grade as per
IS 1786-1985) of 8mm to 40mm diameters, cutting, bending, to required sizes and
shapes placing in position with cover blocks of approved size and binding wire of
20SWG, forming grills for reinforcement work as per approved designs and
drawings including cost and conveyance of bars from approved sources to site of
work, including cost and conveyance of binding wire, cover blocks, chairs,
overlaps, spacers, dowels, wastage etc., and all operational, incidental, and labour
charges such as cutting, bending, placing in position, tying etc., and sales & other
taxes,on cost of all materials complete for finished item of work (APSS No.126) in
first floor

F.F.

3.00

8.82
8.82
Or say 9.00
Sqm
39 Supply and Fixing of 230mm wide PVC water bar at expansion joint over roof slab
including cost , all taxes and convenyance of all materials to site and all labour
charges , cutting and fixing charges etc., complete for finsihed item of work.
1

Pe
Un

Rate

4.30

Columns Qty

48.50

cum @

150

7275

Roof Beams Qty

71.50

cum @

150

10725

Roof Slab 125mm th Qty

1344.50

sqm @

11

14789.5

82 of 517

Measurements

Sl.
Description of item
No.
1

Nos.
3

B
5
sqm @

15

532.5

Lintels Qty

6.50

cum @

120

780

Sunshades Qty

96.00

sqm @

10

960

2
Waist Slab 175mm th
Qty

D
6

QTY

L
4
35.50

Unit
7

35062.00 kgs
Or say
35.50
MT
41 Supplying and fixing of stainless steel hand railing as per approved drawing with
top rail of 64mm dia (outer) 2mm thick pipe, vertical balusters of 50mm dia 2mm
thick at 600mm c/c spacing (7 Nos)and 3 nos 25mm dia (outer) 1.6mm thick
stainless steel pipes below top rail with equal spacings and 50mm wide 8mm thick
SS plate for fixing vertical balusters at 600mm centre with 100x100mm stainless
steel base plate to be fixed to the steps with Anchor fasteners. The rate should
include providing and using bonding agent, drilling of 25mm holes of fixing railing ,
polishing of all nos of railing thouroughly and also including cost and conveyance
of all materials, electrodes, welding charges, cost of all consumables, labour
charges such as for fabrication of SS pipes, buffing, polishing etc., complete for
finished item of work.

For staircase railing


At landing

2
2

x
x

Executive Engineer
APEWIDC, CHITTOOR

2
2

4.00
1.50

16.00
6.00
22.00

Dy. Executive Engineer


MAHABUBNAGAR

Superintending Engineer
APEWIDC, KADAPA

F.F.

83 of 517

Pe
Un

Rate

Rm

47971.95

3702.91
1
TOTAL >>>

Asst. Executive Enginee


APEWIDC, KUPPAM

M) CHITTOOR District
Per
Unit
8

Amount
9

Cum 57235

F.F.

84 of 517

Per
Unit

Amount

Cum 642016

Sqm 1462749

Sqm 49705

Cum 9739

Sqm 353678

F.F.

85 of 517

Per
Unit
8

Amount
9

Cum 63306

Sqm 69874

F.F.

86 of 517

Per
Unit
8

Amount
9

F.F.

87 of 517

Per
Unit
8

Amount
9

Cum 1678481

Sqm 37002

F.F.

88 of 517

Per
Unit
8

Amount
9

Cum 20980

Each 221777

Sqm 1021112

F.F.

89 of 517

Per
Unit
8

Amount
9

Kg

74274

rmt

24001

Sqm 50988

F.F.

90 of 517

Per
Unit

Amount

Sqm 1263

Sqm 36414

F.F.

91 of 517

Per
Unit
8

Amount
9

F.F.

92 of 517

Per
Unit
8

Amount
9

Sqm 586737

Sqm 515761

F.F.

93 of 517

Per
Unit
8

Amount
9

Sqm 424757

F.F.

94 of 517

Per
Unit
8

Amount
9

Sqm 1028147

F.F.

95 of 517

Per
Unit
8

Amount
9

Sqm 45087

Sqm 48722

F.F.

96 of 517

Per
Unit
8

Amount
9

Sqm 74385

Sqm 12755

Sqm 13229

Sqm 17071

F.F.

97 of 517

Per
Unit

Amount

Sqm 3625

Sqm 87560

Sqm 206909

Rmt 104272

Sqm 1374

F.F.

98 of 517

Per
Unit

Amount

Sqm 2966

Sqm 4438

Sqm 13680

F.F.

99 of 517

Per
Unit
8

Amount
9

MT

1703004

Rm

81464
10850537

AL >>>

utive Engineer
C, KUPPAM

F.F.

100 of 517

SUB ESTIMATE

Name of the Work :- Construction of Govt. Degree College at KUPPAM(V) of KUPPAM (M) CHITTOO
SECOND FLOOR
Sl.
No.

Measurements
Description of item

QTY
Nos.

Unit

1
2
3
4
5
6
7
1 Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching /
Mixer ) using 20mm size (SS5) hard granite machine crushed graded metal
(Coarse aggregate) from approved quarry, using a minimum quantity of 350 kgs.
of cement per 1 cum of concreteincluding cost and conveyance of all materials
like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and
cost of all materials including centering using Cashewrina Ballies and Wooden
runners & staging including all bracings, cross members etc., shuttering ,
machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but
excluding cost of steel and its fabrication charges but excluding seigniorage
charges for finished item of work (APSS No. 402 & 403) FOR COLUMNS in
second floor

a Columns for head room


C1
1x
C2
1x
C4
1x
C5
1x
C7
1x
C9
0.78 x
for elevation
1 x
for water tank
1 x

5
9
6
5
5
6
14
4

0.45
0.45
0.45
0.45
0.45
0.3
0.45
0.45

0.3
0.3
0.3
0.3
0.3
0.3
0.30
0.30

2.925
2.925
2.500
3.075
3.075
3.075
1.50
1.50
Or say

b FOR ROOF BEAM


for head room
Long beams
short beams
RB1
RB2
RB3
RB4
RB5
RB5
Brusummer beam
for elevation
for elevation
for water tank

S.F.

2
1
1
2
2
2
2
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x

2
2
2
3
3
4
3
3
3
3
3
10
4
1

5.93
3.53
7.06
3.38
3.05
7.28
6.00
3.53
3.03
3.53
3.03
8.00
10.00
15.00

101 of 517

0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23

1.97
3.55
2.03
2.08
2.08
1.30
2.84
0.81
16.64
17.00

0.41
0.30
0.41
0.30
0.30
0.41
0.30
0.30
0.30
0.23
0.23
0.15
0.15
0.30

2.21
0.49
1.32
1.40
1.26
5.43
2.48
0.73
0.63
0.56
0.48
2.76
1.38
1.04
22.16

Or say

23.00

Cum

Cum

Sl.
No.

Measurements
Description of item

QTY
Nos.

1
2
3
c FOR ROOF SLAB 125 MM THICK

Head room ,Labs ect.&


varandah
Water tank top slab
Water tank side walls

Unit
7

26.90

9.50

255.55

1
1
1

x
x
x

1
1
1

6.10
6.95
22.10

6.50
4.10

39.65
28.50
26.52
350.22

1.20
Or say

355.00

Sqm

d FOR ROOF SLAB 200 MM THICK


for water tank

6.95

4.10

28.495
28.50
Or say

30.00

Sqm

e FOR ROOF SLAB 175 MM THICK


for waist slab
Landing

2
2

x
x

2
1

4.00
4.10

1.50
1.50

24.00
12.3
36.30
Or say

40.00

Sqm

2 Providing impervious coat over RCC roof slab to required slopes with CM (1:3)
prop. 20mm thick (average) mixed with water proofing compound manufactured
by reputed manufacturers as approved by Engineer-in-charge at 1Kg/bag of
cement, laid over roof slab when it is green, finished smooth with a floating coat
of neat cement and thread lining at regular intervals of 45cmx45cm including
cost and conveyance of all materials like cement, sand, water proofing
compound, water etc., to site,
sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing mortar, laying,
rounding off at junctions of wall and slab, rendering smooth with thread lining,
curing, lift charges, etc., complete but excluding seigniorage charges for
finished item of work (APSS No. 901 & 903).

As per roof area


Or say

355.00
355.00
355.00

3 Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using


20mm size (SS5) hard blasted granite machine crushed graded metal (Coarse
aggregate) from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete including cost and conveyance of all materials
like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and
cost of all materials including centering using Cashewrina Ballies and Wooden
runners & staging including all bracings, cross members etc., shuttering ,
machine mixing, laying concrete, lift charges, curing etc., complete but excluding
cost of steel and its fabrication charges but excluding seigniorage charges for
finished item of work (APSS No. 402 & 403) FOR LINTELS

S.F.

102 of 517

Sqm

Measurements

Sl.
No.

Description of item

QTY
Nos.

5
0.23
0.23
0.23
0.23

6
0.15
0.15
0.15
0.15

Unit

D1
W1
W2
GW

1
1
1
1

x
x
x
x

4
10
4
2

4
1.50
1.80
1.05
2.30

W1

1.80

0.60

head room long wall

2
2
1
1
1
1
1
1

x
x
x
x
x
x
x
x

2
1
2
2
2
2
1
2

5.03
3.53
9.51
6.38
8.46
6.38
6.00
16.14

0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23

2.500
2.500
3.175
3.070
3.175
3.070
3.175
0.818

11.57
4.06
13.89
9.01
12.36
9.01
4.38
6.07

191.16

0.23

1.00

43.97

102.60

0.23

1.00

47.20

1.5

0.23

0.15

-0.21

1
1

x
x

10
4

1.8
1.05

0.23
0.23

0.15
0.15

-0.62
-0.14

0.21
0.62
0.14
0.16
0.83
Or say
1.00
Cum
4 Reinforced cement concrete with M 20 grade Design mix ( by weigh batching )
using 20mm size (SS 5) machine crushed hard blasted granite graded metal
(coarse aggregate) from approved quarry using a minimum quantity of 350 Kg
of cement per 1 Cum of concrete including cost and conveyance of all materials
like cement, fine aggregate (sand) ,coarse aggregate, water etc. to site and
cost of
all materials including centering using Cashewrina Ballies and
Wooden runners & staging including all bracings, cross members etc.,
shuttering, machine mixing, laying concrete, for sunshade of 7.5cm thick at
fixed end and 5cm thick at free end with an average thickness of 6.25cm
including labour charges for mixing, laying, curing etc., complete but
excluding cost of steel and its fabrication charges but excluding seigniorage
charges for finished item of work

7.56
7.56
Or say
8.00
Sqm
5 Brick Masonry in superstructure with CM (1:8) prop: using Fly ASH Bricks of size
290x225x140mm with compressive of 50 Kgs / Sqcm from approved source
including cost and conveyance of all materials like cement, sand, fly ash bricks,
water etc., to site, including sales & other taxes on all materials, all operational,
incidental and labour charges such as mixing cement mortar, constructing
masonry, scaffolding charges, lift charges, curing, etc., complete but excluding
seigniorage charges for finished item of work. (APSS No. 501 & 504).

Audio visual room


Computer lab
lobby
Above brusummer
beam
Parapet wall around
building out side
open to sky
Deduction of lintels
D1
W1
W2
S.F.

103 of 517

Measurements

Sl.
No.

Description of item

2
GW

QTY

Nos.

5
0.23

6
0.15

Deduction of doors & windows


D1
1x
W1
1x
W2
1x
GW
1x

4
10
4
2

2.3
1.2
1.5
0.75
2

0.23
0.23
0.23
0.23

2.13
1.35
1.35
1.35

Unit

7
-0.16
-2.35
-4.66
-0.93
-1.24

151.20
Or say
151.50 Cum
5 Plain Cement Concrete corresponding to M10 grade as per IS 456 equivalent to
(1:3:6) proportion nominal mix (cement: fine aggregate: Coarse aggregate) using
20mm size Hard Blasted Granite (IS383, 1970) Machine Crushed graded metal
from from approved quarry including cost and conveyance of all materials like
cement, sand, coarse aggregate, water etc. to site, including sales & other taxes
on all materials, all operational, incidental and labour charges such as mixing,
laying, curing concrete, etc., complete but excluding seigniorage charges for
finished item of work for Bed Blocks and Hold Fasts (APSS No. 402)

D1

0.23

0.23

0.15

0.19

W1

10

0.23

0.23

0.15

0.32

W2

0.23

0.23

0.15

0.13
0.63

Or say

1.00

Cum

6 Supply and Fixing of 50mm thick Jali including cost and conveyance of all
materials to site, sales & other taxes, all operational, incidental and labour
charges etc., complete for finished item of work in All Floors.
2

4.38

1.00

17.52
17.52
Or say

18.00

Sqm

7 Plain Cement Concrete corresponding to M15 grade as per IS 456 equivalent to


(1:2:4) proportion nominal mix (cement: fine aggregate: Coarse aggregate) using
20mm size Hard Blasted Granite (IS383, 1970) Machine Crushed graded metal
from approved quarry including cost and conveyance of all materials like cement,
sand, coarse aggregate, water etc. to site, including sales & other taxes on all
materials, all operational, incidental and labour charges such as mixing, laying,
curing concrete, etc., complete but excluding seigniorage charges for finished
item of work (APSS No. 402)

Parapet wall around


building out side
open to sky

191.16

0.23

0.05

2.20

102.6

0.23

0.05

2.36
4.56

Or say
S.F.

104 of 517

5.00

Sqm

Sl.
No.

Measurements
Description of item

QTY
Nos.

Unit

1
2
3
4
5
6
7
8 Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and
top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and
conveyance of all materials like cement, sand, water etc., to site, sales & other
taxes on all materials,all operational, incidental and labour charges such as
mixing mortar, scaffolding charges, lift charges, including cutting of Grooves
wherever necessary as directed by Engineer - in - charge, finishing, curing, etc.,
complete but excluding seigniorage charges for Even Surfaces of Wall for
finished item of work. (APSS 901,903 & 904)

head room long wall

5.63

2.80

63.06

3.53

2.80

19.77

9.97

3.475

69.29

6.6

3.475

45.87

8.97

3.475

62.34

6.6

3.475

45.87

lobby

4.92

3.475

34.19

Above brusummer
beam

16.14

1.38

44.39

Parapet wall around


building out side

191.16

1.00

191.16

open to sky

102.6

1.00

205.20

Deduction of doors & windows


D1
0.5 x

1.2

2.13

-5.11

W1

0.5

10

1.5

1.35

-10.13

W2

0.5

0.75

1.35

-2.03

GW

0.5

1.35

-2.70

Audio visual room

Computer lab

761.17
Or say

770.00

9 Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and
top coat of 4mm thick in CM (1:4) dubara sponge finish including cost and
conveyance of all materials like cement, sand, water etc., to site, sales & other
taxes on all materials,all operational, incidental and labour charges such as
mixing mortar, scaffolding charges, lift charges, including cutting of Grooves
wherever necessary as directed by Engineer - in - charge, finishing, curing, etc.,
complete but excluding seigniorage charges for Even Surfaces of Wall for
finished item of work. (APSS 901,903 & 904)

head room long wall

S.F.

5.93

105 of 517

2.925

69.38

Sqm

Measurements

Sl.
No.

Description of item

QTY
Nos.

7
22.00

3.76

6
2.925

10.43

3.600

75.10

6.83

3.600

49.18

9.43

3.600

67.90

6.83

3.600

49.18

Above brusummer
beam

16.14

1.3875

44.79

Parapet wall around


building out side

191.16

191.16

open to sky

102.6

205.20

Deduction of doors & windows


D1
0.5 x

1.2

2.13

-5.11

W1

0.5

10

1.5

1.35

-10.13

W2

0.5

0.75

1.35

-2.03

GW

0.5

1.35

-2.70

Audio visual room

Computer lab

Unit

753.91
Or say

760.00

10 Ornamental Plastering 12mm thick in two coats with base coat of 8mm thick in
CM (1:5) and top coat of 4mm thick in CM (1:3) dubara sponge finish including
cost and conveyance of all materials like cement, sand, water etc., to site, sales
& other taxes on all materials,all operational, incidental and labour charges such
as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves
wherever necessary as directed by Engineer - in - charge, finishing, curing, etc.,
complete for Even Surfaces of Wall but excluding seigniorage charges for
finished item of work. (APSS 901,903 & 904)

for head room


Corridor
Audio visual room
Computer lab
lobby
Beams bottom

Sunshades bottom &


top

1
1
1
1
1
1
2
4
2
1
2

x
x
x
x
x
x
x
x
x
x
x

2
1
1
1
1
1
6
4
6
2
7

5.63
7.06
25.40
9.97
8.97
6.00
6.60
2.17
6.00
16.14
1.80

3.53
6
2.17
6.6
6.6
4.97
0.30
0.30
0.30
0.23
0.6

39.75
42.36
55.12
65.80
59.20
29.82
23.76
10.42
21.60
7.42
15.12
370.37

S.F.

106 of 517

Sqm

Measurements

Sl.
No.

Description of item

QTY
Nos.

Unit

6
7
Or say
370.50 Sqm
11 Supply and Fixing of Door with Double leaf shutter, Door Size 1.22x2.13 mtrs
with Sal wood Frame of sections size 75mm x 100mm with Flush Door Shutter
Solid Bond Wood black board type with commercial ply on both faces of 35mm
thick including cost of fixtures such as M.S.Powder Coated Tower Bolts 250mm
long 2 Nos, MS powder coated Handles 150mm long 2 Nos, 300mm long
M.S.Powder Coated Aldrops 1No, 125mm long M.S.Powder Coated butt hinges
6Nos, 300 mm long M.S.Powder Coated Flat latch 1No, Door stoppers 2 Nos,
MS Hold fasts 6Nos, Sales and Other Taxes cost and convenyance of all
materials to site all Labour charges such as Fixing of Door Frame on shutter
Fixing in position , with Hardware fixtures etc., complete for finsihed utem of
work.
1

4.00
Or say
4.00
Each
12 Providing and Fixing of openable double shutter windows made of pre-painted
steel (Base steel as per IS 513 of 0.58 mm thick galvanized as per IS 277 with
Zinc of 120 GSM). Primer coated with epoxy primer of 5-7 microns thick, finish
painted with a polyester paint of 12-16 microns thick and back coated with 5-7
microns thick alkyd backer. Section for outer frame should be of 48x50mm,
centre mullion should be of 48x50mm, section for shutter should be of 48x25mm
and fixed panel beading section should be 12x12mm. Outer frame and mullions
to have rebate for Galvalume corrugated sheet shutter and a 20mm provision for
Guard bars/Grills. The sections are to be cut to length metre joined with corner
bracket. Centre mullion is to be fixed with mullion cap. Handle, stay, 2 nos. of
Stainless Steel heavy duty Pivot hinges shall be provided per shutter. The
windows should be panelled with 0.60 mm thick Galvalume corrugated sheet
having tensile strength of 550 MPA,(BMS-W.55). The above frames should be
fixed to the concrete/masonry wall by means of self expanding screws, Including
10mm Square guard bars with 6 (152.4mm) pitch etc., complete for finished
item of work.

Double shutter Window with vertical mullion 30 x 40 ( 914.4mm x 1219.2mm)


outer frame section size of 48x50mm shutter frame section size of 48x25mm.
Mullion section size of 48x50mm.
W1

10

1.5

1.35

20.25

W2

0.75

1.35

4.05
24.3

Or say
28.35 Sqm
13 Supply and fixing of M.S. Grills including cost and conveyance of all materials
and all labour charges etc., complete

S.F.

GW - 2.00 x 1.35m

65.00

130.00

V3 - 1.22 x 0.30over D

7.00

42.00

V4 - 1.50 x 0.30over w

9.00

54.00

107 of 517

Measurements

Sl.
No.

Description of item

QTY
Nos.

Unit

7
226.00 kgs
14 Supply and Fixing MS Purlins 50mm dia including Labour Charges for fixing
complete including cost and conveyance of all materials to site, sales and other
taxes, all labour charges etc., complete for finished item of work
for elevation
for elevation

2
1

x
x

3
3

7.20
8.00

43.20
24.00
67.20
Or say
68.00 Rmt
13 Whiting to new walls and ceiling in two coats with Birla White or equavalent
quality to give an even shade after thoroughly brushing the surface to remove all
loose powdered materials including cost and conveyance of all materials and
water to site, sales & other taxes, all operational, incidental and labour charges
such as cleaning the surface, painting, curing etc., complete for finished item of
work for internal walls. (APSS No.901 & 908) in All Floors
As per ornamental plastering area in QTY
As per 12mm thick plastering area in QTY

370.50
770.00
1140.50
Or say 1140.50 Sqm
14 Painting to New walls with two coats of Plastic Emulsion paint of superior quality
of approved brand and shade over base coat of cement primer grade -I making
three coats in all to give an even shade after thoroughly brushing the surface to
remove all loose powdered materials, including cost and conveyance of all
materials, including cost and conveyance of all materials, cost of brushes, water
to site, etc., sales & other taxes, all operational, incidental and labour charges
such as scaffolding charges, lift charges, curing etc., complete for finished item
of work in all floors for Walls.(APSS No. 912) in All Floors

As per 12 mm thick plastering area in QTY out side

760.00
760.00
Or say
760.00 Sqm
15 Painting to New wood work with two coats of ready mixed synthetic enamel
paint Grade I all shades to give an even shade over base coat Primer with
Luppam finishing after thoroughly brushing the surface to remove all remains
including cost and conveyance of all materials to site, sales & other taxes, all
operational, incidental and labour charges etc., complete for finished item of
work.(3 coats) (APSS No. 1201 & 1212).in All Floors
doors

23.00
23.00
Or say
23.50 Sqm
16 Painting to New Iron work with two coats of ready mixed synthetic enamel paint
first quality all shades over an existing steel primer including cost and
conveyance of all materials to site, sales & other taxes, incidental, operational
and all labour charges etc., complete for finished item of work. (APSS No. 1201,
1207 & 1212).in All Floors

S.F.

2.25 x

1.20

108 of 517

2.13

Sl.
No.
1

Measurements
Description of item

QTY
Nos.

4
7.20
8.00
2.00
1.20
1.50

6
1.00
1.00
1.35
0.30
0.30

2
for elevation
for elevation
GW
V3
V4

Unit

7
2.25 x
6
97.20
2.25 x
3
54.00
2.25 x
2
12.15
1 x
4
1.44
1 x
6
2.70
167.49
Or say
168.00 Sqm
17 Supply and fixing of 110mm dia ISI mark PVC rain water spouts of 4 Kg/cm2
pressure including Cost of necessary pvc bends, shoes and M.S.clamps and all
other accessories and fixing in position including cost and conveyance of all
materials to site , seigniorage charges sales and other taxes on all materials, all
operational, incidental and labour cahrges such as fixing in alignment etc.,
complete for finished item of work.(APSS NO1328) in All Floors

22.00
Or say
22.00 rmt
18 Providing High Yield Strength Deformed (HYSD) steel bars (Fe 415 grade as per
IS 1786-1985) of 8mm to 40mm diameters, cutting, bending, to required sizes
and shapes placing in position with cover blocks of approved size and binding
wire of 20SWG, forming grills for reinforcement work as per approved designs
and drawings including cost and conveyance of bars from approved sources to
site of work, including cost and conveyance of binding wire, cover blocks, chairs,
overlaps, spacers, dowels, wastage etc., and all operational, incidental, and
labour charges such as cutting, bending, placing in position, tying etc., and sales
& other taxes,on cost of all materials complete for finished item of work (APSS
No.126) for second floor

S.F.

11.00

Columns Qty
Roof Beams Qty
Roof Slab 125mm th Qty

17.00
23.00
355.00

cum @
cum @
sqm @

140
140
11

2380
3220
3905

Waist Slab 175mm th Qty

40.00

sqm @

15

600

Lintels Qty
Sunshades Qty

1.00
8.00

cum @
sqm @

120
10

120
80
10305.00 kgs
10.31
10.50 MT

109 of 517

Sl.
No.

Measurements
Description of item

QTY
Nos.

Unit

1
2
3
4
5
6
7
19 Supplying and fixing of stainless steel hand railing as per approved drawing with
top rail of 64mm dia (outer) 2mm thick pipe, vertical balusters of 50mm dia 2mm
thick at 600mm c/c spacing (7 Nos)and 3 nos 25mm dia (outer) 1.6mm thick
stainless steel pipes below top rail with equal spacings and 50mm wide 8mm
thick SS plate for fixing vertical balusters at 600mm centre with 100x100mm
stainless steel base plate to be fixed to the steps with Anchor fasteners. The rate
should include providing and using bonding agent, drilling of 25mm holes of
fixing railing , polishing of all nos of railing thouroughly and also including cost
and conveyance of all materials, electrodes, welding charges, cost of all
consumables, labour charges such as for fabrication of SS pipes, buffing,
polishing etc., complete for finished item of work.

For staircase railing


At landing

2
2

x
x

Executive Engineer
APEWIDC, CHITTOOR

2
2

4.00
1.50

Dy. Executive Engineer


MAHABUBNAGAR

Superintending Engineer
APEWIDC, KADAPA

S.F.

110 of 517

16.00
6.00
22.00

Rm

Asst. Executive Enginee


APEWIDC, KUPPAM

(V) of KUPPAM (M) CHITTOOR District

Per
Unit

Rate
8

Amount
9

1224.53

1 Cum

20817.00

9227.45

1 Cum

212231.00

S.F.

111 of 517

Per
Unit

Rate
8

Amount
9

1117.50

1 Sqm

396713.00

1590.45

1 Sqm

47714.00

1436.15

1 Sqm

57446.00

377.25

1 Sqm

133924.00

S.F.

112 of 517

Per
Unit

Rate
8

10066.40

S.F.

Amount
9

1 Cum

10066.00

752.00 1 Sqm

6016.00

113 of 517

Per
Unit

Rate
8

Amount
9

5943.40 1 Cum

900425.00

5328.00

1 Sqm

5328.00

456.75

1 Sqm

8222.00

6619.70

1 Sqm

33099.00

S.F.

114 of 517

Per
Unit

Rate
8

341.85

S.F.

Amount
9

1 Sqm

263225.00

115 of 517

Per
Unit

Rate
8

341.85 1 Sqm

S.F.

Amount
9

259806.0

116 of 517

Per
Unit

Rate
8

Amount

362.95

1 Sqm

9
134471.00

11672.45

1 Each

46690.00

6358.95

1 Sqm

180276.00

S.F.

117 of 517

Per
Unit

Rate
8

Amount

74.20

1 kgs

9
16769.00

475.15

1 Rmt

32310.00

26.90

1 Sqm

30679.00

126.55

1 Sqm

96178.00

155.90

1 Sqm

3664.00

S.F.

118 of 517

Per
Unit

Rate
8

Amount
9

85.30

1 Sqm

14330.00

548.80

1 rmt

12074.00

48812.70

1 MT

512533.00

S.F.

119 of 517

Per
Unit

Rate
8

3702.91
TOTAL >>>

Amount
9

1 Rm

81464.00

3516470.00

Asst. Executive Engineer


APEWIDC, KUPPAM

S.F.

120 of 517

SUB ESTIMATE
WATER SUPPLY & SANITARY ARRANGEMENTS

Name of the Work :- Construction of Govt. Degree College at KUPPAM(V) of KUPPAM


CHITTOOR District
Sl.
No.

Description of item

Measurements
Nos.
3

L
4

B
5

D
6

QTY

Unit
7

Per
Unit

Rate
8

WATER SUPPLY & SANITARY ARRANGEMENTS


1 Constructing 457.2mm x 457.2mm (1'-6" x 1'-6") brick in CM (1:6) prop. Masonry
inspection chamber upto 914.4mm (3'-0") and fitted with light weight 457.2mm x
457.2mm (1'-6" x 1"-6") frame and cover of 20kg., including cost and
convenyance of all materials to site, all labour charges, sales and otehr taxes on
all materials etc., complete for finished item of work.
at septic tank

2 x

16.00
16.00
Nos 4345.80
2 Constructing 904.0 mm (30) dia solid block masonry inspection chamber as per
IS - 4111: Part-1:1986 with cement mortar (1:6) prop using fly ash blocks of
225mm thick from approved source having a minimum crushing strength of 10
N/sq.mm including plastering with cement mortar 1:3 prop; thick both inside
and outside fitted with 20 dia RCC manhole covers and frames including
excavating pits up to a depth of 904 mm (3'-0") in all sorts of soils (exculding
rock) and laying cement conrete (1:4:8) 150 mm thick using 40 mm HBG Metal
and P.C.C. 1:2:4 benching and channel 100 mm thick as per Standard
specification and including cost and conveyance of all materials like cement,
sand, bricks, water etc., to site, cost of seigniorage charges on all materials and
all incidental and operational, labour charges like mixing cement mortar,
constructing masonry, lift charges, curing etc., complete for finished item of work
as per Standard specification.

1 x 6
6.00
Nos
3 Supplying and fixing 580 mm x 440 mm long Orissa pan white glazed Water
Closet 1st qualityISI marked confirming to IS:2556-Part-3-1981 with "P" or "S"
trap Hindware / Parryware / Neycer with brick masonry seat, CC squatting plate
and fixing 12.70mm dia NP Push cock 1st quality , P trap or S trap of Indian
W.C. shall be encased on CC (1:2:4) 150mm alround well above the joint to stop
leakage at the joint etc., complete including cost and conveyance of all materials
to site, cost of CC bed, labour charges and seigniorage charges etc., complete
for finished item of work.

7646.30

Ground & First floor


30.00
Nos
4 Supplying and fixing NP bib taps of size 12.70mm dia of Indian make Seiko or
equivalent including cost and conveyance of all materials, labour charges etc.,
complete for finished item of work in all floors.300 grams

2172.36

293.15

ground floor
first floor

WSA

19.00
18.00
37.00

121 of 517

Nos
Nos
Nos

Sl.
No.

Measurements

Description of item

QTY

Unit

Nos.
L
B
D
1
2
3
4
5
6
7
5 Supplying and fixing Indian make Flat Back Wash Hand Basin (HSW/Parryware/
Neycer) 1st quality conforming to IS:2556-Part-4:1972 of size 550mm x 400mm
with waste fittings like rubber plug, chain, 32 mm nominal size C.P. Fitting with
parallel pipe thread conforming to IS:2963-1979 and fitted with 15 mm nominal
bore Chromium Plated Pillar Tap of 1st quality Indian make 400 grams Seiko/
Esso or equivalent complete with standard CI brackets including wooden block ,1
No.12.70mm PVC connection with brass union nuts CP coated , 1 No.12.70mm
NP bib tap 300 gms Seiko or equivalent including cost and conveyance of all
materials to site, labour charges etc. complete for finished item of work

in toilet blocks GF&FF

1 x 30

Per
Unit

Rate
8

30.00
30.00
30.00

Nos

2977.95

6.85

4999.06

1012.35

1653.10

307.90

6 Providing and placing on terrace (at all floor levels) polyetheylene water storage
tank with double layer approved brand and manufacture with cover and suitable
locking arrangement and making necessary holes for inlet and outlets and over
flow pipes but without fittings and base support for tanks including cost and
conveyance of all materials and labour charges for placing and fixing in position
as directed by Engineer-in-Charge.
1 x 2 1000.00
2000.00 Lts
7 Supply and fixing of European Water Closet of 1st quality conforming to IS: 2556Part-2-1973 of Hindustan/Neycer of Parryware make white glazed with 'P' trap.
toilet

1 x

7.00
7.00

Nos
7.00
8 Supply and fixing best indian make plastic seat and lid for European water
closets with rubber or plastic buffers as per IS 2548 -1996
toilet

1 x

7.00
7.00

Nos
7.00
9 Supply and fixing of PVC low level system parry ware, slim line with internal
components & short bend: 10 litres capacity single flush
in Ground & First floor

1 x 37

37.00
37.00

37.00 Nos
10 Supplying and fixing NP Push cock of size 12.70mm dia of Indian make Seiko or
equivalent including cost and conveyance of all materials, labour charges etc.,
complete for finished item of work in all floors.
in Ground & First floor

1 x 37

37.00
37.00
37.00

WSA

122 of 517

NOs

Sl.
No.

Measurements

Description of item

QTY

Unit

Nos.
L
B
D
1
2
3
4
5
6
7
11 Supplying & fixing Ashirvad/Astral flow guard for equivalent CPVC Pipes with
fittings in ground or on wall including cost of tees, elbows, bends, reducers,
couplings, running joints, union flanges, unions etc. with necessary excavation in
all types of soils except rock requiring blasting, refilling, chiselling masonry walls
and making good the walls & floors to the original surface and fixing MS clamps
on TW blocks on walls including cost and conveyance of all materials and labour
charges complete for finished item of work.

Per
Unit

Rate
8

54.0mm OD pipe - SDR 11


1 x 1
100.00
100.00 Rmt
12 Supplying & fixing Ashirvad/Astral flow guard for equivalent CPVC Pipes with
fittings in ground or on wall including cost of tees, elbows, bends, reducers,
couplings, running joints, union flanges, unions etc. with necessary excavation in
all types of soils except rock requiring blasting, refilling, chiselling masonry walls
and making good the walls & floors to the original surface and fixing MS clamps
on TW blocks on walls including cost and conveyance of all materials and labour
charges complete for finished item of work.

596.50

409.05

240.90

214.75

41.30mm OD pipe - SDR 11


1 x 1
100.00
100.00 Rmt
13 Supplying & fixing Ashirvad/Astral flow guard for equivalent CPVC Pipes with
fittings in ground or on wall including cost of tees, elbows, bends, reducers,
couplings, running joints, union flanges, unions etc. with necessary excavation in
all types of soils except rock requiring blasting, refilling, chiselling masonry walls
and making good the walls & floors to the original surface and fixing MS clamps
on TW blocks on walls including cost and conveyance of all materials and labour
charges complete for finished item of work.

28.60mm OD pipe - SDR 11


1 x 1
120.00
120.00 Rmt
14 Supplying & fixing Ashirvad/Astral flow guard for equivalent CPVC Pipes with
fittings in ground or on wall including cost of tees, elbows, bends, reducers,
couplings, running joints, union flanges, unions etc. with necessary excavation in
all types of soils except rock requiring blasting, refilling, chiselling masonry walls
and making good the walls & floors to the original surface and fixing MS clamps
on TW blocks on walls including cost and conveyance of all materials and labour
charges complete for finished item of work.

22.20mm OD pipe - SDR 11


1 x

WSA

80.00

123 of 517

80.00

Rmt

Sl.
No.

Measurements

Description of item

QTY

Unit

Nos.
L
B
D
1
2
3
4
5
6
7
15 Supplying & fixing Ashirvad/Astral flow guard for equivalent CPVC Pipes with
fittings in ground or on wall including cost of tees, elbows, bends, reducers,
couplings, running joints, union flanges, unions etc. with necessary excavation in
all types of soils except rock requiring blasting, refilling, chiselling masonry walls
and making good the walls & floors to the original surface and fixing MS clamps
on TW blocks on walls including cost and conveyance of all materials and labour
charges complete for finished item of work.

Per
Unit

Rate
8

15.90mm OD pipe - SDR 11


1 x 1
40.00
40.00 Rmt
16 Supplying and fixing PPR ball valve of 25 mm dia confirming to DIN standards
8077/8092 , Indian make heavy type including cost and conveyance of all
materials , labour charges etc. complete for finished item of work.

160.20

278.40

NOs
6.00
18 Supplying and fixing of SWR/ PVC pipes (as per ISI standards) 4 Kg/Sq.cm.
Prince/sudhakar or any ISI brand and fixing all special such as plain bends, off
sets, door bends, single junctions, double junctions as per site requirement, fixing
with PVC clamps if necessary with required number of Bombay nails including
cost and conveyance of all materials to site, labour charges etc.complete for
finished item of work at all floor levels. (APSS No. 1302 1319 & 1326) for 110
mm dia single socket pipe

597.65

1 x 1
120.00
120.00 Rmt
19 Supplying and fixing of SWR/ PVC pipes (as per ISI standards) 4 Kg/Sq.cm.
Prince/sudhakar or any ISI brand and fixing all special such as plain bends, off
sets, door bends, single junctions, double junctions as per site requirement, fixing
with PVC clamps if necessary with required number of Bombay nails including
cost and conveyance of all materials to site, labour charges etc.complete for
finished item of work at all floor levels. (APSS No. 1302 1319 & 1326) for 90 mm
dia single socket pipe

183.35

153.40

1 x 15

15
15

15.00 NOs
17 Supplying and fixing PPR ball valve of 40 mm dia confirming to DIN standards
8077/8092 , Indian make heavy type including cost and conveyance of all
materials , labour charges etc. complete for finished item of work.
1 x

1 x

WSA

6
6

60.00

124 of 517

60.00

Rmt

Sl.
No.

Measurements

Description of item

QTY

Unit

Nos.
L
B
D
1
2
3
4
5
6
7
20 Supplying and fixing of SWR/ PVC pipes (as per ISI standards) 4 Kg/Sq.cm.
Prince/sudhakar or any ISI brand and fixing all special such as plain bends, off
sets, door bends, single junctions, double junctions as per site requirement, fixing
with PVC clamps if necessary with required number of Bombay nails including
cost and conveyance of all materials to site, labour charges etc.complete for
finished item of work at all floor levels. (APSS No. 1302 1319 & 1326) for 160
mm dia single socket pipe

1 x

80.00

80.00

Rmt

Per
Unit

Rate
8

436.70

1 x 1
20.00
20.00 Nos
22 Supplying and fixing 150.00mmx100.00mm SWG gully trap 1st class confirming
to ISI 651 & 4127with CI grating and constructing single brick masonry wall
chamber of size 20" x 14" x 12 in CM (1:6) prop. Over a CC (1:5:10)prop. bed,
and plastering 12mm thk. in CM (1:4) prop. both inside and outside surfaces and
fitted with 304.8MM X 288.6 MM (12"X9") CI frame and hinged cover including
labour for fixing and laying the SWG junctions/plugs/bends with air tightcement
joints etc., complete including cost and conveyance of all materials to site, labour
charges etc., complete for finished item of work as directed by Engineer-incharge.

154.55

12.00 Nos
23 Supplying and fixing TV shape mirror with plastic frame of size 609.6mm x
457.2mm , plywood back with NP screws 1st quality including cost and
conveyance of all materials, labour charges etc., complete for finished item of
work in all floors.

645.35

Nos
8.00
24 Supply and fixing of white glazed flat back bowl urinals of size 440 mm x 265 mm
x 315 mm with internal rim flushing mm fixied with screws complete inidan make
(HS W/Parry/Neycer) conforming to IS 2556 -1995 as approved be Engineer - in
- charge 12.7 mm PVC connection with brass plumber union nuts CM Coated.
including 12.70 mm push cock 1st qulaity of approved make including supply &
fixing 31.75 m dia PVC flexible waser pipe of 914.40 mm lenght of 1st including
cost and conveyance of all materials to site labour charges etc., complete for
finished item of work for all floors

582.85

20.00 Nos
25 Supply and fixing of 100 mm dia CI Vent pipe of 3 mts length double socket fitted
with AC cowl and mosquito proof wire mesh including cost and conveyance of all
materials to site and labour charges for placing and fixing in position etc.,
complete for finished item of work.

1056.65

2552.95

21 Supplying and fixing CI Nahani traps 100 mm dia Inlet- 75 mm (3") outlet pipe - 4
Kgs 1st quality ISI marked conforming to IS:1729-1979 with C.P. Grating fixing
with white cement as per site requirements with standard practice for all floors
including cost and conveyance of all materials to site, labour charges etc.,
complete for finished item of work.

1 x

1 x

WSA

1 x

1 x

12.00

8.00

20.00

2.00
125 of 517

Nos

Sl.
No.

Description of item

Measurements
Nos.
3

L
4

B
5

D
6

QTY

Unit
7

Per
Unit

Rate
8

TOTAL >>

Executive Engineer
APEWIDC, CHITTOOR

Dy. Executive Engineer


APEWIDC, MADANAPALLI

Superintending Engineer
APEWIDC, KADAPA

WSA

126 of 517

Asst. Executive Engi


APEWIDC, KUPPAM

V) of KUPPAM (M)
Amount
9

69533.00

45878.00

65171.00

10847.00

WSA

127 of 517

Amount
9

89339.00

13700.00

34993.00

7086.00

61165.00

11392.00

WSA

128 of 517

Amount
9

59650.00

40905.00

28908.00

17180.00

WSA

129 of 517

Amount
9

6408.00

4176.00

3586.00

22002.00

9204.00

WSA

130 of 517

Amount
9

34936.00

3091.00

7744.00

4663.00

21133.00

5106.00

WSA

131 of 517

Amount
9

692246.00

Executive Engineer
EWIDC, KUPPAM

WSA

132 of 517

PLAY GROUND LEVELLING - SUB ESTIMATE

Name of the work : CONSTRUCTION OF GOVT.JUNIOR COLLEGE AT GUDIPALLI


GUDIPALLI(M), IN CHITOOR DIST.
Measurements

Sl.
Description of item
No.
1

Nos.

QTY

Unit
7

1 Cutting of gravel & leveling of ground by,Earth work excavation for foundations
(Mechanical Means) for buildings in ordinary soils and depositing on bank for all
lifts and with an initial lead of 10m and up to 3m depth including all
operational,incidental, labour charges such as shoring, sheeting, planking,
strutting etc., and overheads & contractors profit complete for finished item of
work excluding dewatering charges etc., as per SS 20 B(APSS 308)

for ply fields North side

90.00

50.00

0.45

2025.00

for ply fields South side

90.00

35.00

0.30

945.00

2970.00
Or say
2970.00 Cum
2 Earth work excavation and depositing on bank (manual means) with initial lead
of 10m and initial lift of 3m in Loamy & Clayey Soils like BC Soils, Red Earth &
Ordinary Gravelly Soils ( SS 20-B) including all operational incidental labour
charges such as shoring, strutting, sheeting, planking and dewatering including
cost of hire charges of T & P, labour charges etc., complete for finished item of
work excluding seignerage charges and dewatering charges etc., complete for
Foundation of Building.(APSS No. 308)

Retaining wall for play


fields

200.00

0.90

0.90

162.00

Or say
162.00 Cum
3 Earth work excavation for foundations for buildings in hard rock (requiring
blasting) and depositing on bank for all lifts and with an initial lead of 10m and
up to 3m depth including all operational,incidental, labour charges such as
shoring, sheeting, planking, strutting etc., and overheads & contractors profit
complete for finished item of work excluding dewatering charges etc., as per SS
20 B(APSS 308)
25% of E/W Quantity
2970 x 0.10 = 297.00

Or say

133 of 517

297.00
300.00

Cum

Playground Levelling

Measurements

Sl.
Description of item
No.

Nos.

QTY

Unit

1
2
3
4
5
6
7
4 Plain Cement Concrete corresponding to M5 grade as per IS 456 equivalent to
(1:5:10) proportion nominal mix (cement: fine aggregate: Coarse aggregate)
using 40mm size Hard Blasted Granite (IS383, 1970) metal from approved
quarry including cost and conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site, including sales & other taxes on all materials, all
operational, incidental, and labour charges such as mixing, laying and ramming
concrete in layers in position not exceeding 15cm, finishing top surface, curing
concrete, etc., complete but excluding seigniorage chargesfor finished item of
work for Foundations and Flooring Bed (APSS No. 402)

For play fields retaining


wall

200.00

0.9

0.10
Or say

18.00
18.00
18.00

Cum

5 Random Rubble stone masonry, in CM (1:8) prop: (Cement: Sand) using Hard
blasted Granite stones from approved quarry including cost and conveyance of
all materials like Granite stones, cement, sand, water, etc., to site sales &
other taxes on all materials, all operational, incidental, and labour charges such
as cutting stones to required size and shape, mixing of cement mortar,
constructing masonry, curing etc., complete but excluding seigniorage charges
for finished item of work for foundation and basement (APSS No. 601 & 615)

For play fields retaining


wall
I st. step
1

200.00

0.75

0.60

90.00

II nd. Step

200.00

0.6

0.60

72.00

III rd. step

200.00

0.45

0.60

54.00

216.00
Or say
216.00 Cum
6 Flush Pointing to CRS Masonry in CM(1:3) Prop: including cost and conveyance
of all materials like cement, sand, water etc., to site, including sales & other
taxes on all materials, all operational, incidental charges and labour charges
such as mixing mortar, finishing, curing, etc., complete but excluding
seigniorage charges for finished item of work. (APSS 901,906)

For retaining wall

200.00

200.00
200.00
Or say
200.00 Sqm
7 Filling with Gravel in trenches, sides of foundations and basement with initial
lead in layers not exceeding 15cm thick, consolidating each deposited layer by
watering and ramming including cost and conveyence of water to the work site
and all operational, incidental, labour charges, hire charges of T & P etc.,
completebut but excluding seignorage charges, for finished item of work. (APSS
NO. 309 & 310)

134 of 517

1.00

Playground Levelling

Sl.
Description of item
No.
1

2
For play fields North 1
side
For play fields South 1
side

Measurements
QTY

Nos.

3
x 1

90

50

6
0.30

7
1350.00

x 1

90

35

0.30

945.00

Or say

Executive Engineer
APEWIDC, CHITTOOR

Unit

2295.00
2295.00 Cum

Dy. Executive Engineer


MAHABUBNAGAR

Superintending Engineer
APEWIDC, KADAPA

135 of 517

Playground Levelling

TIMATE

COLLEGE AT GUDIPALLI(V),
T.
Per
Unit

Rate
8

Amount
9

98.90

1 Cum 293733

231.60

1 Cum 37519

597.90

1 Cum 179370

136 of 517

Playground Levelling

Per
Unit

Rate
8

Amount
9

3413.65

1 Cum 61446

2709.55

1 Cum 585263

63.95

1 Sqm 12790

137 of 517

Playground Levelling

Per
Unit

Rate
8

Amount
9

380.70
1 Cum 873707
TOTAL >>>
2043828

Asst. Executive Engineer


APEWIDC, KUPPAM

138 of 517

Playground Levelling

Sub Work : Providing CC Road

Name of the Work :- Construction of Govt. Degree College at KUPPAM(V) of KUPPA


CHITTOOR District
SNo
1

No
L
B
D Qty
Unit
Description of work
Forming embankment with Side earth by mechanical means upto SDR
including pre-watering of soil , removal of top soil, excavation of soils ,
depositing the soils on the embankment, spreading soil, breaking clods,
sectioning , grading and consolidation with 8 to 10 Tonnes Vibratory Road
Roller @ OMC to meet requirement of table 300-2 of MoRT&H, including
all hire and operational charges of T&P and , complete for finished item
of work as per MoRT&H specification 305 (4th revision) (Payment will be
made based on level for finished item of work).

x 1

250.00

6.00

0.30

Rate

450.00
450.00

say 450.00 Cum


Providing Plain Cement Concrete (1:4:8) mix using 40mm size HBG
crushed stone aggregate and fine aggregate conforming to table 1000-2
of MoRT&H including cost, seigniorage conveyance of all materials to site
and labour charges, centering, machine mixing, laying, Vibrating, curing
etc., including all other incidental and operational charges of all T&P etc.,
complete for finished item of work as per MoRT&H specification
1500,1700, 2100 (4th Revision) and as directed by the Engineer-inCharge for base coarse below CC Pavement.

100.00
100.00
Say 100.00 Cum
Vibrated cement concrete M.25 grade using 20mm & 10mm HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1
and fine aggregate conforming to table 1000-2) including cost,
seigniorage conveyance of all materials to site and labour charges,
centering, machine mixing, laying, vibrating, curing etc., including all
other incidental and operational charges of all T&P etc., complete for
finished item of work as per Approved drawing but excluding cost of steel
and its fabrication charges as per MoRT&H specification
1500,
1600,1700, & 2704 (4th Revision) and as directed by the Engineer-inCharge for CC Pavements.

250.00

250.00

4.00

4.00

185.00

0.10

0.15

3278.00

150.00
150.00

Say

139 of 517

150.00 Cum

6288.00

CC Road

SNo
4

No
L
B
D Qty
Unit
Description of work
Construction of Gravel shoulders including cost, and conveyance of all
materials to work site and spreading in uniform layers by approved
means, on prepared surface and compacting with vibratory roller to
achieve the desired density at OMC etc., complete for finished item of
work as per MoRT&H Specification 401& 407 (4th revision) and as
directed by the Engineer-in-charge.
( Payment will be made based on levels for finished item of work ).

Gravel Shoulders

250.00

1.00

0.25
Say

125.00
125.00 Cum

Rate

299.00

TOTAL

Executive Engineer
APEWIDC, CHITTOOR

Dy. Executive Engineer


APEWIDC, MADANAPALLI

Asst. Exe.Eng
APEWIDC, KU

Superintending Engineer
APEWIDC, KADAPA

140 of 517

CC Road

PPAM(V) of KUPPAM (M)

Per

Unit

Amount

Cum

83250

Cum

327800

Cum

943200

141 of 517

CC Road

Per

Unit

Amount

Cum
37375
TOTAL: 1391625

Asst. Exe.Engineer
APEWIDC, KUPPAM

142 of 517

CC Road

LEAD CHART
Name of the Work :- Construction of Govt. Degree College at KUPPAM(V) of KUPPAM (M) CHITTOOR District
RATES AS PER COMMON SSR OF 2015-2016 with cement and steel rates of November
Lead in KM
Sl.
No.

Description

(1)
(2)
1 Sand for Mortar
2

Sand for Plastering

Avg.
Thickn
SSR Sl.No.
ess in
mm
(3)
M-005
M-006

3
4

Sand for filling& blindage


M-004
Gravel
M-008
R.R. Stone(Granite, Dolamite
5
M-148
&Trap variety)
C.R. Stone(Granite, Dolamite
6
CSSR-A.14
&Trap variety)
trough stones25 x25x45 to 60
7
CSSR-A.76
cms
40mm HBG Metal
8
M-055
(IS383-1970)
20mm M/c chips
9
M-053
(IS383-1970)
13.2/12.5 mm M/c chips
10
M-052
(IS383-1970)
10mm M/c chips
11
M-051
(IS383-1970)
6mm M/c chips
12
M-050
(IS383-1970)
13

2nd Class Bricks of size


BMT-A.01
23x11x7cm

(4)

Source of Material
MR

CT

(5)
Kangundi

(6)
45.00

(7)
0.50

Kangundi

45.00

Kangundi
LOCAL

Total

Add
Convence
Initial Cost Differenc
Charges
1%
including
in
including
towards
Stacking SeignioStacking
storage
Charges
rage
Charges
Charges

Loading unloadin
charges g charges

(8)
46.00

(9)
464.09

(10)
610.00

(11)
0.00

(12)
0.00

(13)
0.00

(14)
0.00

0.50

46.00

464.09

677.00

0.00

0.00

0.00

0.00

45.00
5.00

0.50
0.50

46.00
6.00

464.09
56.41

460.00
103.00

0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00

Gundlasagaram

10.00

0.50

11.00

111.01

252.00

0.00

0.00

0.00

0.00

Gundlasagaram

10.00

0.50

11.00

111.01

288.00

0.00

0.00

0.00

0.00

Gundlasagaram

10.00

0.50

11.00

111.01

1040.00

0.00

0.00

0.00

0.00

Gundlasagaram

10.00

0.50

11.00

111.01

845.00

0.00

0.00

0.00

0.00

V.Kota

54.00

0.50

55.00

545.99

1365.00

0.00

0.00

0.00

0.00

V.Kota

54.00

0.50

55.00

545.99

1097.00

0.00

0.00

0.00

0.00

V.Kota

54.00

0.50

55.00

545.99

935.00

0.00

0.00

0.00

0.00

V.Kota

54.00

0.50

55.00

545.99

735.00

0.00

0.00

0.00

0.00

LOCAL

8.00

0.50

9.00

143.25

5200.00

0.00

0.00

41.88

41.88

143 of 517

LEAD

Lead in KM
Sl.
No.

Description

Avg.
Thickn
SSR Sl.No.
ess in
mm

Fly Ash Bricks of size 290


x100
x140
mm
with
14
BMT-A.13 2.29249
compressive strength of 50
Kg /sq.cm
Fly Ash Bricks of size 290
x225 x 140 mm with
15
BMT-A.10 5.1581
compressive strength of 50
Kg/sq .cm
Polished Bethamcherla pure
white stone minimum of 25
16
BMT-B.07
25
mm thick (0.254M x
0.254M)

Source of Material
MR

CT

Total

Add
Convence
Initial Cost Differenc
Charges
1%
including
in
including
towards
Stacking SeignioStacking
storage
Charges
rage
Charges
Charges

Loading unloadin
charges g charges

LOCAL

8.00

0.50

9.00

328.40

11000.00

0.00

0.00

96.01

96.01

LOCAL

8.00

0.50

9.00

738.90

24000.00

0.00

0.00

216.02

216.02

435.00

0.50

436.00

147.51

385.90

0.00

0.00

0.76

0.38

bethamcherla

144 of 517

LEAD

Lead in KM
Sl.
No.

Description

Avg.
Thickn
SSR Sl.No.
ess in
mm

Source of Material
MR

CT

Total

Add
Convence
Initial Cost Differenc
Charges
1%
including
in
including
towards
Stacking SeignioStacking
storage
Charges
rage
Charges
Charges

Loading unloadin
charges g charges

17

Polished Black Kadapa Slabs


BMT-B.06
of 15 mm thick

15

Yerraguntla

290.00

0.50

291.00

59.40

137.90

0.00

0.00

0.46

0.23

18

Rough Kadapa slabs of 40


mm thick (0.457 x 457M)

BMT-B.01

40

Yerraguntla

290.00

0.50

291.00

158.41

96.00

0.00

0.00

1.22

0.61

Polished Marble Slabs of any


variety 16 to 20 mm thick
19
BMT-B.12
(size 0.457 x 0.457 M / 0.6 x
0.6 M)

18

LOCAL

1.00

0.50

2.00

0.29

729.00

0.00

0.00

0.00

0.00

High polished Granite 16 to


20 18 mm thick up to 8' 00"
(2.43M) black

17

LOCAL

5.00

0.50

5.00

0.00

2352.00

0.00

0.00

0.00

0.00

Local

0.50

0.00

5.00

0.00

77.00

0.00

0.00

0.00

0.00

CSSR-A.05

At Site

0.00

0.00

0.00

0.00

5760.00

0.00

0.00

0.00

50.25

M-126

At Site

0.00

0.00

0.00

0.00

34000.00

0.00

0.00

0.00

60.23

High Yield Strength


24 Deformed Bars (Fe 415) for
8mm to 40mm dia

CSSR-A.62

At Site

0.00

0.00

0.00

0.00

32000.00

0.00

0.00

0.00

60.23

Mild Steel, Structural steel,


25 I,e, Angles, Channels & ISections

CSSR-A.68

At Site

0.00

0.00

0.00

0.00

37000.00

0.00

0.00

0.00

60.23

26 M.S. Plates

CSSR-A.69

At Site

0.00

0.00

0.00

0.00

35000.00

0.00

0.00

0.00

60.23

BMT-B.11

21 water
22 Cement
23

Mild Steel Bars (Fe 250) for


6mm

CERTIFICATES:1

Certified that the above leads are true and correct to the best of my knowledge

Certified that the quarry requries blasting for RR, CRS, 6mm, 10mm, 12mm, 20mm & 40mm Metal

Certified that the 20mm, 12mm, 10mm, 6mm Metal requires Machine Crushing

Certified that the work site does not falls within 12 Kms belt of any Municipality/ Corporation. Hence no extra on labour charges is allowed

145 of 517

LEAD

Lead in KM
Sl.
No.

Description

Avg.
Thickn
SSR Sl.No.
ess in
mm

Source of Material
MR

CT

Total

Add
Convence
Initial Cost Differenc
Charges
1%
including
in
including
towards
Stacking SeignioStacking
storage
Charges
rage
Charges
Charges

Loading unloadin
charges g charges

Certified that the sand in notified sand reaches around Kuppam is completed and proposed a new notified reach at Koundinya river at Samudrapalli near Palamaner

Superintending Engineer

Executive Engineer

Dy. Executive Engineer

Asst.Exe.Engineer

APEWIDC, Kadapa

APEWIDC, Chittoor

APEWIDC, Madanapalli

APEWIDC, Kuppam

146 of 517

LEAD

LEAD CHART

e College at KUPPAM(V) of KUPPAM (M) CHITTOOR District

F 2015-2016 with cement and steel rates of November


Area
allowence
on loading
&
unloading
charges
@0%

Total

Unit per

(15)
0.00

(16)
1074.09

(17)
Cum.

0.00

1141.09

Cum.

0.00
0.00

924.09
159.41

Cum.
Cum.

0.00

363.01

Cum.

0.00

399.01

Cum.

0.00

1151.01

Cum.

0.00

956.01

Cum.

0.00

1910.99

Cum.

0.00

1642.99

Cum.

0.00

1480.99

Cum.

0.00

1280.99

Cum.

0.00

5427.01 1000 Nos

147 of 517

LEAD

Area
allowence
on loading
&
unloading
charges
@0%

Total

Unit per

0.00

11520.42 1000 Nos

0.00

25170.94 1000 Nos

0.00

534.55

148 of 517

1Sqm.

LEAD

Area
allowence
on loading
&
unloading
charges
@0%

Total

Unit per

0.00

197.99

1Sqm.

0.00

256.24

1Sqm.

0.00

729.29

1Sqm.

0.00

2352.00

1Sqm.

0.00

77.00

KL

0.00

5810.25

M.T

0.00

34060.23

M.T

0.00

32060.23

M.T

0.00

37060.23

M.T

0.00

35060.23

M.T

tal

Hence no extra on labour charges is allowed

149 of 517

LEAD

Area
allowence
on loading
&
unloading
charges
@0%

Total

Unit per

a new notified reach at Koundinya river at Samudrapalli near Palamaner

Asst.Exe.Engineer
APEWIDC, Kuppam

150 of 517

LEAD

DATA
1

Providing & Applying Synthetic Plaster Putty or


Plaster of Paris Putty or Lime punning of
average 1 to 2mm thick over plastered surface
to prepare the surface even and smooth after
thoroughly brushing the surface to remove all
dirt and remains of loose powdered materials,
applying emery paper, sand the surface, clean &
wipe off loose dust, applying knifing paste filler
by putty knife/muslin pad, air dry for 2-3 hours,
sand with 180 and 320 No, emery paper for the
surface preparation including cost and
conveyance of all materials to site, sales & other
taxes, all operational, incidental and labour
charges etc., complete for finished item of work
for internal walls.
Unit = 10 Sqm
Wall putty-BMT-J.40
Painter 1st class
Painter 2nd class
Mazdoor
Sundries for emery papers, fillers, knife etc., @
1%
Overheads&Contractors Profit @14%
Rate per 10 sqm
Rate per 1 sqm

23 Kgs
0.273 Nos.
0.637 Nos.
0.91 Nos.
0.01

0.14

875
480.00
375.00
320.00
1667.37

20 Kg
1 Each
1 Each
1 Each

1684.04

Say

151 of 517

C-Data

1006.25
131.04
238.88
291.2
16.67
1684.04
235.77
1919.81
191.981
192.00

152 of 517

C-Data

CC ROAD DATA
Name of Work ::- Construction of Govt. Degree College at KUPPAM(V) of KUPPAM
(M) CHITTOOR District
S.No.
Quantity
Description of Item
Rate
per
1 Forming embankment with Side earth by mechanical means upto SDR including prewatering of soil , removal of top soil, excavation of soils , depositing the soils on the
embankment, spreading soil, breaking clods, sectioning , grading and consolidation
with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet requirement of table 3002 of MoRT&H, including all hire and operational charges of T&P and , complete for
finished item of work as per MoRT&H specification 305 (4th revision) (Payment will
be made based on level for finished item of work).

Unit : Cum
Taking out put = 100 Cum
(A) Labour
0.02 day
Mate
Mazdoor unskilled
0.50 day

Amount

Page 70 of MoRT&H SDB

(B) Machinery
100.00 cum
Rate as per G.O. Ms No 10, Dt
26/7/2005
1.00 hr
Motor Grador for Grading @ 100 cum
per
hour
Water
tanker 6 KL
4.00 hr
Vibratory roller 8T
1.00 hr

400.00
320.00

day
day

8.00
160.00
168.00

86.43
2600.00
658.35
2678.30

cum
hr
hr
hr

8643.00
2600.00

0.00

cum

2633.40
2678.30
16554.70

(C)
100.00 Cum
(D) Over head charges @4% (10%-VAT) on (A) + (B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 100 cum (E) + (F)
Rate per Cum
Rate per 1 cum
2

Providing Plain Cement Concrete (1:4:8) mix using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
seigniorage conveyance of all materials to site and labour charges, centering,
machine mixing, laying, Vibrating, curing etc., including all other incidental and
operational charges of all T&P etc., complete for finished item of work as per
MoRT&H specification 1500,1700, 2100 (4th Revision) and as directed by the
Engineer-in-Charge for base coarse below CC Pavement.

CC Road - Data

153 of 517

0.00
668.91
17391.61
1739.16
19130.77
191.31
191.00
1 Cum

S.No.

Quantity

Description of Item

Rate

per

Amount

400.00
420.00
320.00

day
day
day

256.00
420.00
4800.00
5476.00

Cost of 40mm SS-5 HBG M/C metal


956.01
Sand at site
1074.09
Cement at site
5810.25
Total
Machinery
6.00
hr
Concrete mixer 0.4/0.28 cum
328.60
0.00
hr
Generator set 35 KVA
620.00
2.00
hr
Water tanker 6 KL
658.35
Total
(D) Over head charges @ 4% (10%-VAT)
4.00 %
Add for Over head charges @ 6% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)

cum
cum
MT

12906.14
7250.11
14118.91
34275.16

hr
hr
hr

1971.60
0.00
1316.70
3288.30

Unit = cum
Taking output = 15 cum
(A) Labour
0.64 nos
1.00 nos
15.00 nos

Mate
Mason
Mazdoor
Total

(B) Material
13.50 cum
6.75
cum
2.43
MT

1721.58
44761.04
4476.10
49237.14
3282.48
3282.00
1 Cum

Cost per 15 cum (E) + (F)


Rate for 1 cum
Rate to be adopted
3

Vibrated cement concrete M 35 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials
to site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including all other incidental and operational charges of all T&P etc., complete for
finished item of work as per MoRT&H specification 1500, 1700, 2100 & 2702 (4th
Revision) and as directed by the Engineer-in-Charge for C.C Pavement.

Page 345,346 of MoRT&H SDB


Unit = cum
Taking output = 15 cum
(A) Labour
0.86 nos
1.50 nos
20.00 nos

(B) Material
8.10 cum

CC Road - Data

Mate
Mason
Mazdoor
Total

400.00
420.00
320.00

day
day
day

344.00
630.00
6400.00
7374.00

Cost of 20mm SS-5 HBG M/C metal

1910.99

cum

15479.02

154 of 517

S.No.

Quantity

Description of Item
Cost of 10mm SS-5 HBG M/C metal
5.40 cum
6.75 cum
Sand at site
6.33 MT
Cement at site
Total
Machinery
6.00 hr
Concrete mixer 0.4/0.28 cum
0.00 hr
Generator set 35 KVA

Rate

per

Amount

1480.99
1074.09
5810.25

cum
cum
MT

7997.35
7250.11
36778.88
67505.36

328.60
620.00

hr
hr

1971.60
0.00
1971.60

76850.96

Cum

2689.78

(D) Form work


3.50 %
Form work @ 3.50% on (A)+(B)+( C)
(E) Over head charges @ 6% (10%-VAT)
4.00 %

Add for Over head charges @ 4% on (A)+(B)+( C)+(D)


(F) Total of (A) + (B)+( C)+(D)+(E)

3181.63
82722.37

(G) Add Contractors Profit at 10% on (F)

8272.24

Cost per 15 cum (F)+(G)

90994.61

Rate for 1 cum

6066.31

Rate to be adopted

6066.00
1 Cum

Construction of Gravel shoulders including cost, and conveyance of all materials to


work site and spreading in uniform layers by approved means, on prepared surface
and compacting with vibratory roller to achieve the desired density at OMC etc.,
complete for finished item of work as per MoRT&H Specification 401& 407 (4th
revision) and as directed by the Engineer-in-charge.
( Payment will be made based on levels for finished item of work ).
Unit = cum
Taking output = 300 cum
(A) Labour
0.40 day

Mate

400.00

day

160.00

2.00 day

Mazdoor skilled

320.00

day

640.00

8.00 day

Mazdoor unskilled

320.00

day

2560.00

Total

3360.00

(B) Machinery
6.00 hr

Vibratory roller 8T

2678.30

hr

16069.80

3.00 hr

Water tanker 6 KL

658.35

hr

1975.05

Total

18044.85

(C) Material
CC Road - Data

155 of 517

S.No.

Quantity
384.00 cum

Description of Item
Gravel

Rate
159.41

per

Amount
61213.44

(D) Over head charges @ 6% (10%-VAT)


4.00 %

Add for Over head charges @ 6% on (A)+(B)+( C)


(E) Total of (A) + (B)+( C)+(D)

3304.73
85923.02

(F) Add Contractors Profit at 10% on (E)

8592.30

Cost per 300 cum (E) + (F)

94515.32

Rate per 1 cum

315.05

Rate to be adopted

315.00
1 Cum

Vibrated cement concrete M.25 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials
to site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including all other incidental and operational charges of all T&P etc., complete for
finished item of work as per Approved drawing but excluding cost of steel and its
fabrication charges as per MoRT&H specification 1500, 1600,1700, & 2704 (4th
Revision) and as directed by the Engineer-in-Charge for CC Pavements.

0.86
1.50
20.00

Unit = cum
Taking output = 15 cum
(A)
Labour
nos
Mate
nos
Mason
nos
Mazdoor
Total

8.10
5.40
6.75
6.05

(B)
cum
cum
cum
MT

6.00
6.00

hr
hr

2.00
14.00

(D)
%
%

CC Road - Data

Page 340,501 of MoRT&H SDB


400.00
420.00
320.00

day
day
day

Material
Cost of 20mm HBG metal
1910.99
cum
Cost of 10mm HBG metal
1480.99
cum
Sand at site
1074.09
cum
Cement at site
5810.25
MT
Total
Machinery
Concrete mixer 0.4/0.28 cum
328.60
hr
Generator set 33 KVA
620.00
hr
Total
Form work
Form work @ 2% on (A)+(B)+( C)
78944.09
Cum
Add for Over head charges @ 14% on (A)+(B)+( C)+(D)

156 of 517

344.00
630.00
6400.00
7374.00

15479.02
7997.35
7250.11
35152.01
65878.49
1971.60
3720.00
5691.60
1578.88
11273.22

S.No.

Quantity

Description of Item
Cost per 15 cum
Rate for 1 cum M 25 Concrete
Rate to be adopted

Rate

per

Amount
91796.19
6119.75
6120.00
1 Cum

Asst. Exe.Engineer
APEWIDC, Kuppam

Dy. Executive Engineer


APEWIDC, Madanapalli

Executive Engineer
APEWIDC, Chittoor

Superintending Engineer
APEWIDC, Kadapa

CC Road - Data

157 of 517

DATAS FOR DOORS AND WINDOWS


Sno

Qty

Description of Item
Supply and Fixing of Door with Double leaf shutter, Door Size 1.52x2.13
mtrs with MediumTeak wood Frame of sections size 75mm x 100mm with
Flush Door Shutter Solid Bond Wood black board type with commercial ply
on both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 300mm long 2 Nos, Aluminium Handles 150mm long 2 Nos,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 6Nos,
300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to
site all Labour charges such as Fixing of Door Frame and shutter Fixing in
position , with Hardware fixtures etc., complete for finsihed utem of work.

Rate

Unit

Per

DOOR SIZE 1.52 x 2.13 mtrs : Area = 3.24 Sqm

1.52

2.13

Medium Teak Wood for Frame


Verticals 2 x 2.13 x 0.075 x 0.10

= 0.0319

0.03195

cum

Horizental 1 x 1.52 x 0.075 x 0.10

= 0.00864

0.01140

cum

0.04335

cum

2.89

sqm

Total

= 0.04054

35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
1x1.41x2.05 = 2.89 Sqm
ABSTRACT
a)MATERIAL
1

0.03195 Cost of medium Teak wood scantling of size 2.0 to 3.0 M ( BMT-E.02)

88994.00

Cum

0.01140 Cost of medium Teak wood scantling of size up to 2.0 M ( BMT-E.1)

80094.00

Cum

1488.00

Sqm

2.89

Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)

6.00

MS Hold Fasts

25.00

Each

1.00

Cost of 300mm Long Aluminium Aldrops(BMT-G.42)

425.00

Each

2.00

Cost of 300 long Aluminium Towerbolts (BMT-G.11)

198.00

Each

2.00

Cost of 150mm Long Aluminium Handles (BMT-G.34)

140.00

Each

6.00

Cost of 125mm long M.S. Powder Coated but hinges (BMT-G29)

34.00

Each

1.00

Cost of Flat latch Aluminium 300long (BMT-G.50)

188.00

Each

10

2.00

Cost of Door Stoper (BMT-G.53)

50.00

Each

685.00

Sqm

685.00

2.89
11
12

a)
LABOUR
Labour
charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)

0.00

Add munipal area allowance @ 0 %

13

Add overheads @

14%

Rate per / Each

158 of 517

D-W data

Sno

Qty

Description of Item

Rate

Unit

Per

2.13

0.03195
0.01500
0.04695

cum
cum
cum

3.87

sqm

88994.00
80094.00

1
1

Cum
Cum

1488.00
25.00
425.00
198.00
140.00
34.00
188.00
50.00

1
1
1
1
1
1
1
1

Sqm
Each
Each
Each
Each
Each
Each
Each

Sqm

Supply and Fixing of Door with Double leaf shutter, Door Size 2.0x2.13 mtrs
with MediumTeak wood Frame of sections size 75mm x 100mm with Flush
Door Shutter Solid Bond Wood black board type with commercial ply on
both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 300mm long 2 Nos, Aluminium Handles 150mm long 2 Nos,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 6Nos,
300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to
site all Labour charges such as Fixing of Door Frame and shutter Fixing in
position , with Hardware fixtures etc., complete for finsihed utem of work.

1
2

3
4
5
6
7
8
9
10

DOOR SIZE 2.0 x 2.13 mtrs : Area = 4.26 Sqm


Medium Teak Wood for Frame
Verticals 2 x 2.13 x 0.075 x 0.10
= 0.0319
Horizental 1 x 2.0 x 0.075 x 0.10
= 0.01500
Total
= 0.04695
35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
1x1.89x2.05 = 3.87 Sqm
ABSTRACT
a)MATERIAL
0.03195 Cost of medium Teak wood scantling of size 2.0 to 3.0 M
0.01500 Cost of medium Teak wood scantling of size up to 2.0 M

3.87
6.00
1.00
2.00
2.00
6.00
1.00
2.00
3.87

11
12

0.00

Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long Aluminium Aldrops(BMT-G.42)
Cost of 300 long Aluminium Towerbolts (BMT-G.11)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 300long (BMT-G.50)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 0 %

13

Add overheads @

685.00
685.00

14%

Rate per / Each

159 of 517

D-W data

Sno

1
2

3
4
5
6
7
8
9
10

Qty

DOOR SIZE 2.4 x 2.13 mtrs : Area = 5.11 Sqm


Medium Teak Wood for Frame
Verticals 2 x 2.13 x 0.075 x 0.10
= 0.0319
Horizental 1 x 2.4 x 0.075 x 0.10
= 0.01800
Total
= 0.04995
35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
1x2.3x2.05 = 4.9Sqm
ABSTRACT
a)MATERIAL
0.03195 Cost of medium Teak wood scantling of size 2.0 to 3.0 M
0.01800 Cost of medium Teak wood scantling of size up to 2.0 M

4.9
6.00
1.00
2.00
2.00
6.00
1.00
2.00
4.90

11
12

Description of Item
Supply and Fixing of Door with Double leaf shutter, Door Size 2.4x2.13 mtrs
with MediumTeak wood Frame of sections size 125mm x 100mm with Flush
Door Shutter Solid Bond Wood black board type with commercial ply on
both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 250mm long 2 Nos, Aluminium Handles 150mm long 2 Nos,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 6Nos,
300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to
site all Labour charges such as Fixing of Door Frame and shutter Fixing in
position , with Hardware fixtures etc., complete for finsihed utem of work.

0.00

Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long Aluminium Aldrops(BMT-G.42)
Cost of 250 long Aluminium Towerbolts (BMT-G.11)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 300long (BMT-G.50)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 0 %

13

Add overheads @

Rate

Unit

Per

2.4

2.13

0.03195
0.01800
0.04995

cum
cum
cum

4.9

sqm

88994.00
80094.00

1
1

Cum
Cum

1488.00
25.00
425.00
198.00
140.00
34.00
188.00
50.00

1
1
1
1
1
1
1
1

Sqm
Each
Each
Each
Each
Each
Each
Each

Sqm

685.00
685.00

14%

Rate per / Each

160 of 517

D-W data

Sno

Qty

Description of Item
Supply and Fixing of Door with Double leaf shutter, Door Size 1.22x2.13
mtrs with Medium teak wood Frame of sections size 75mm x 100mm with
Flush Door Shutter Solid Bond Wood black board type with commercial ply
on both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 300mm long 2 Nos, Alluminimum Handles 150mm long 2 Nos,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 6Nos,
300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to
site all Labour charges such as Fixing of Door Frame on shutter Fixing in
position , with Hardware fixtures etc., complete for finsihed utem of work.

Rate

Unit

Per

1.22

2.13

0.03195
0.00915
0.04110

cum
cum
cum

2.28

sqm

88994.00
80094.00

1
1

Cum
Cum

1488.00
25.00
425.00
198.00
140.00
34.00
188.00
50.00

1
1
1
1
1
1
1
1

Sqm
Each
Each
Each
Each
Each
Each
Each

685.00

Sqm

685.00

1
2

3
4
5
6
7
8
9
10

DOOR SIZE 1.22 x 2.13 mtrs : Area = 2.60 Sqm


Medium Teak Wood for Frame
Verticals 2 x 2.13 x 0.075 x 0.10
=
Horizental 1 x 1.22 x 0.075 x 0.10
=
Total
=
35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
1x1.11x2.05 = 2.45 Sqm
ABSTRACT
a)MATERIAL
0.03195 Cost of medium Teak wood scantling of size 2.0 to 3.0 M
0.00915 Cost of medium Teak wood scantling of size up to 2.0 M

2.28
6.00
1.00
2.00
2.00
6.00
1.00
2.00
2.28

12

0.00

Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long Aluminium Aldrops(BMT-G.42)
Cost of 300 long Aluminium Towerbolts (BMT-G.11)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 300long (BMT-G.50)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 0 %

14

Add overheads @

14%

Rate per / Each

161 of 517

D-W data

Sno
3

1
2

3
4
5
6
7
8
9
10

Qty

DOOR SIZE 0.90 x 2.13 mtrs : Area =


Medium Teak Wood for Frame
Verticals 2 x 2.13 x 0.075 x 0.10
=
Horizental 1 x 0.90 x 0.075 x 0.10
=
Total
=
35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
1x0.78x2.05 =
ABSTRACT
a)MATERIAL
0.03195 Cost of medium Teak wood scantling of size 2.0 to 3.0 M
0.00675 Cost of medium Teak wood scantling of size up to 2.0 M

1.6
6.00
1.00
2.00
1.00
3.00
1.00
1.00
1.60

12

Description of Item
Supply and Fixing of Door with Single leaf shutter, Door Size 0.90x2.13
mtrs with Medium Teak Wood Frame of sections size 75mm x 100mm with
Flush Door Shutter Solid Bond Wood black board type with commercial ply
on both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 300mm long 2 Nos, Aluminium Handels 150mm long 1 No,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 3 Nos,
300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to
site all Labour charges such as Fixing of Door Frame on shutter Fixing in
position , with Hardware fixtures etc., complete for finsihed utem of work.
D6

0.00

Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long Aluminium Aldrops(BMT-G.42)
Cost of 300 long Aluminium Towerbolts (BMT-G.11)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 300long (BMT-G.50)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 0 %

14

Add overheads @

Rate

Unit

Per

0.9

2.13

0.03195
0.00675
0.03870

cum
cum
cum

1.6

sqm

88994.00
80094.00

1
1

Cum
Cum

1488.00
25.00
425.00
198.00
140.00
34.00
188.00
50.00

1
1
1
1
1
1
1
1

Sqm
Each
Each
Each
Each
Each
Each
Each

685.00

Sqm

685.00

14%

Rate per / Each

162 of 517

D-W data

Sno

Qty

Description of Item
Supply and Fixing of Door with Single leaf shutter, Door Size 0.76x2.13
mtrs with Medium Teak Wood Frame of sections size 75mm x 100mm with
Flush Door Shutter Solid Bond Wood black board type with commercial ply
on both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 150mm long 1 Nos, Aluminium Handels 150mm long 1 No,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 3 Nos,
250 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Fixing in position of Aluminium Sheet 24 guage of full width of
shutter to a height of 0.60 mtrs for interior face and 0.15 mtrs to external
face , Sales and Other Taxes cost and convenyance of all materials to site
all Labour charges such as Fixing of Door Frame on shutter Fixing in
position , with Hardware fixtures etc., complte for finsihed item of work.

Rate

Unit

Per

0.76

2.13

0.03195
0.00570
0.03765

cum
cum
cum

1.29

sqm

88994.00
80094.00

1
1

Cum
Cum

1488.00
25.00
114.00
391.00
140.00
34.00
179.00
302.00

1
1
1
1
1
1
1
1

Sqm
Each
Each
Each
Each
Each
Each
Sqm

685.00

Sqm

685.00

4
1

1
2

3
4
5
6
7
8
9
10
11

DOOR SIZE 0.76 x 2.13 mtrs : Area =


Salwood Frame
Verticals 2 x 2.13 x 0.075 x 0.10
=
Horizental 1 x 0.76 x 0.075 x 0.10
=
Total
=
35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
1x0.63x2.05 = 1.30 Sqm
ABSTRACT
a)MATERIAL
0.03195 Cost of medium Teak wood scantling of size 2.0 to 3.0 M
0.00570 Cost of medium Teak wood scantling of size up to 2.0 M

1.29
6.00
1.00
1.00
2.00
3.00
1.00
0.48
1.29

0.00

Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 150 long Aluminium Towerbolts (BMT-G.08)
Cost of 250mm Long Aluminium Aldrops(BMT-G.41)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 250 MM long (BMT-G.49)
Cost of 24 guage Alluminium Sheet (BMS-W.18)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 0 %
Add overheads @

14%

Rate per / Each

163 of 517

D-W data

Sno
4

1
2

3
4
5
6
7
8
9
10

Qty

DOOR SIZE 1.05 x 2.13 mtrs : Area =


Medium Teak Wood for Frame
Verticals 2 x 2.13 x 0.075 x 0.10
=
Horizental 1 x 1.05 x 0.075 x 0.10
=
Total
=
35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
1x0.95x2.05 = 1.947 Sqm
ABSTRACT
a)MATERIAL
0.03195 Cost of medium Teak wood scantling of size 2.0 to 3.0 M
0.00788 Cost of medium Teak wood scantling of size up to 2.0 M

1.95
6.00
1.00
2.00
2.00
6.00
1.00
2.00
1.95

11
12
13
14

Description of Item
Supply and Fixing of Door with Double leaf shutter, Door Size 1.05x2.13
mtrs with Medium Teak Wood Frame of sections size 75mm x 100mm with
Flush Door Shutter Solid Bond Wood black board type with commercial ply
on both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 300mm long 2 Nos, MS Powder coated Handles 150mm long 2
Nos, 300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges
6Nos, 300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS
Hold fasts 6Nos, Sales and Other Taxes cost and convenyance of all
materials to site all Labour charges such as Fixing of Door Frame on
shutter Fixing in position , with Hardware fixtures etc., complete for finsihed
utem of work.

0.00

Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long Aluminium Aldrops(BMT-G.42)
Cost of 300 long Aluminium Towerbolts (BMT-G.11)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 300long (BMT-G.50)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 0 %
Add overheads @

Rate

Unit

Per

1.05

2.13

0.03195
0.00788
0.03983

cum
cum
cum

1.95

sqm

88994.00
80094.00

1
1

Cum
Cum

1488.00
25.00
425.00
198.00
140.00
34.00
188.00
50.00

1
1
1
1
1
1
1
1

Sqm
Each
Each
Each
Each
Each
Each
Each

685.00

Sqm

685.00

14%

Rate per / Each

164 of 517

D-W data

Sno
5

1
2

3
4
5
6
7
8
9
10

Qty

DOOR SIZE 1.00 x 2.13 mtrs : Area = 2.13 Sqm


Salwood Frame
Verticals 2 x 2.13 x 0.075 x 0.10
=
Horizental 1 x 1.00 x 0.075 x 0.10
= 0.0075
Total
= 0.0394
35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
1x0.875x2.05 = 1.79 Sqm
ABSTRACT
a)MATERIAL
0.03195 Cost of medium Teak wood scantling of size 2.0 to 3.0 M
0.00750 Cost of medium Teak wood scantling of size up to 2.0 M

1.79
6.00
1.00
2.00
1.00
3.00
1.00
1.00
1.79

12

Description of Item
Supply and Fixing of Door with Single leaf shutter, Door Size 1.00x2.13
mtrs with Medium teak Wood Frame of sections size 75mm x 100mm with
Flush Door Shutter Solid Bond Wood black board type with commercial ply
on both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 200mm long 2 Nos, Aluminium Handels 150mm long 1 No,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 3 Nos,
300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to
site all Labour charges such as Fixing of Door Frame on shutter Fixing in
position , with Hardware fixtures etc., complete for finsihed item of work.

0.00

Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long Aluminium Aldrops(BMT-G.42)
Cost of 200 long Aluminium Towerbolts (BMT-G.11)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 300long (BMT-G.50)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 0 %

14

Add overheads @

Rate

Unit

Per

0.9

2.13

0.03195
0.00750
0.03945

cum
cum
cum

1.79

sqm

88994.00
80094.00

1
1

Cum
Cum

1488.00
25.00
425.00
198.00
140.00
34.00
188.00
50.00

1
1
1
1
1
1
1
1

Sqm
Each
Each
Each
Each
Each
Each
Each

Sqm

685.00
685.00

14%

Rate per / Each


7

Providing and fixing factory made Polyvinyl chloride (PVC) Door Frame of
the size 50 x 47mm with a wall thickness of 5mm, made out of extruded
5mm rigid PVC foam sheet, mitre cut at two corners and joined with 2nos.
of 150mm long brackets of 15x15mm M.S. square tube. The two vertical
door profiles are to be reinforced with 19x19mm M.S. Square tube of 19
gauge. The door frame shall be fixed to the wall using 65/100mm long M.S.
Screws through the frame by using PVC fasteners. A minimum of 4nos. of
screws to be provided for each vertical member & minimum 2nos. for
horizontal member etc. complete as per manufacturers specification and
direction of Engineer-in-Charge for finished item of work

165 of 517

D-W data

Sno

Qty
1 rmt

Description of Item
cost of PVC door frame (BMT-N.01)
Add overheads @
Rate per / Each
Providing and fixing 30mm thick Solid panel PVC door shutter consisting of
frame made out of M.S. tubes of 19 gauge thickness and size of 19mm x
19mm for stiles, & 15mm x 15mm for top & bottom rails. M.S. frame shall
have a coat of steel primers of approved make and manufacture. M.S.
frame shall be covered with 5mm thick heat moulded PVC C channel of
size 30 x 50mm forming stiles, and 5mm thick, 75mm wide PVC sheets for
top rail, lock rail & bottom rail on either side, and 10mm (5mm x 2) thick,
20mm wide cross PVC sheet as gap insert for top rail & bottom rail.
Panelling of 5mm thick PVC sheet to be fitted in the M.S. frame welded /
sealed to the stiles & rails with 30mm wide x 5mm thick PVC sheet beading
on either side, and joined together with solvent cement adhesive etc. An
additional 5mm thick PVC strip of 20mm width is to be stuck on the interior
side of the C Channel using PVC solvent adhesive. Complete as per
direction of Engineer-in-charge, manufacturers specification & drawing for
finished item of work .

cost of PVC shutter (BMT-N.02)


Add overheads @

Rate
325.00
14%

Unit
1

Per
Rmt

2362.00
14%

sqm

7288
558

1
-1

SQM

Rate per 1 sqm

8
Providing & Fixing of Openable Windows with Fly-mesh made of
pre-painted steel (Base Steel as per IS 513 of 0.6mm thick
galvanized as per IS 277 with zinc of 150 GSM) primer coated
with epoxy primer of 5-7 microns thick, finish painted with a
polyester paint of 12-16 microns thick and back coated with 5-7
microns thick alkyd backer and the section for outer frame of 72 x
55mm, centre mullion of 72 x 50mm, section for fixed glass
beading section of 12 x 12 mm and section for shutters of 47 x 20
mm and outer frame & mullion sections with rebate for glazed
shutters, fly mesh and a 20 mm provision for guard bars/grills and
fly mesh shutter section of 20 x 40 mm and the sections cut to
length metre joined with corner bracket, centre mullions fixed with
mullion cap, stay, handles, latch 2 Nos of heavy duty stainless
steel pivot hinges per shutter and panelled with 5mm thick plain
float glass and S.S. Mesh for fly mesh shutter (304 grade), fitted
using rubber gaskets
including fixing the windows in the concrete/masonry wall by
means of self expanding screws, including 10mm Square guard
bars with 6 (152.4mm) pitch , complete for finished item of work
a)

Centre fixed both side openable shutter window 50x40


(1524mm x1219.2mm). Outer frame section size of 72x50mm.
Shutter frame section size of 47x20mm. Mullion section size of
72x50mm. Fixed beading section size of 12x12mm.
basic rate as per ssr item code BMT-P.31
Deduct 5 mm plain glass BMT-I.02

166 of 517

D-W data

Sno

Qty

Description of Item
Add 0.5 mm thick Galvalume corrugated sheet BMS-W.55
Add 14% overheads
Rate per sqmt.

b)

Double shutter Window with vertical mullion outer frame section


size of 72x50mm shutter frame section size of 47x20mm. Mullion
section size of 72x50mm.
basic rate as per ssr item code BMT-P.95 & 96
Deduct 5 mm plain glass BMT-I.02
Add 0.5 mm thick Galvalume corrugated sheet BMS-W.55
Add 14% overheads
Rate per sqmt.

Rate
456
Total
14%

Unit
1

Per
SQM

7069

SQM

456
Total
14%

SQM

4737
14%

SQM

Supply and fixing of Fixed Louvered Ventilators with sections


made of pre - painted steel (base steel as per IS 513 of 'D"
quality, galvanized as per IS 277 with zinc of 120 GSM) primer
coated with epoxy primer of 5-7 microns thick, finish painted with
a polyester paint of 12-16 microns thick and back coated with 5-7
microns thick alkyd backer with total coated thickness of 0.6mm.
Section for louvered ventilator frame should be of 33x57mm. All
the above closed and seamed sections should be made out of
single sheet and with stitch at a single place as per enclosed
drawings; The ventilators should be paneled with 4 mm pinhead
glass with Ethyl propylene Diamine monomer Gasket (EPDM). The
sections are to be cut to length mitre joined with corner bracket.
Gaskets are to be made of Ethyl propylene Diamine
monomer(EPDM). Corner brackets made of CRCA with Zinc
Phosphate. The above frames should be fixed to the concrete
/masonry wall by means of self expanding brackets & screws
including 10 mm square guard bars with 6" pitch and all taxes
complete for finished item of work.
Basic rate as per item code BMT-P.20
Add 14% overheads
Rate per sqmt.

167 of 517

D-W data

Sno
10

Qty

Description of Item
Rate
Unit
Providing and fixing Structural Glazing fabricated from Roll formed sections made of Pre-painted Steel /
Powder coated (Base steel as per IS 513 of D quality, galvanized as per IS 277 with Zinc of 120
Gm/Sqm) with total coated thickness of 0.72 mm and the glass holding section made of 304 grade
stainless steel of 0.58 mm thick galvanised steel section as stiffeners inside the colour coated steel powder
coated sections as per the design requirement & calculations to suit wind pressures as given in IS: 875, the
primer coat with epoxy primer of 5 7 microns thick, finish painted with a polyester paint of 12-16
microns thick and back coated with Alkyd backer of 5-7 microns or powder coated with pure polyester
powder up to 50-60 microns thick and the vertical section of 50 mm x 99 mm x 0.72 mm, 33 mm x 56
mm x 0.72 mm for frame horizontal section, stiffener section of 47 mm x 97 mm x 1 mm, cover profiles
sections of 20 mm x 58 mm x 0.58 mm, glass holding section of 37 mm x 37 mm & 37 mm x 18 mm
including fixing 5mm thick Ocean Blue reflective glass, brackets made of CRCA powder
coated/Electroplated to connect vertical to horizontal, vertical to slab, to fix verticals at top & bottom as
per site requirement and gasket made of Ethyl Propylene Diamine Monomer, U.V. resistant silicon sealant
including fixing in concrete/masonry wall with self-expanding cap & screws inclusive of cost and
conveyance of all materials to site, all labour charges, incidental charges, cost of all consumables etc. and
fixing

Basic rate as per item code BMT-Q.1


Add 14% overheads
Rate per sqmt.

7288
14%

Per

SQM

Supply and fixing of MS grill Window of 2.73X 1.35 mts by using 40 x40 x 6mm MS Angle section for
outer frame and 10 mm square safety bars @ 100 mm C/C both ways including cost & conveyance of
all materials and labour charges for finished item of work
Frame 40x40x6 mm (GW)
Verticals 2 x 1.35
Harizontal 2 x 2.73
10 mm SQ rod@ 100c/c
Verticals 14 x 1.32
Harizontal 26x 2.69
MS Aldrop,Tower Bolt and Holdfast
total weight
Rate analysis
cost of MS steel
Fabrication charges BMM -V-14
Fixing Charges BMM -V-15
Over Head Charges

2.7
5.46
8.16

3.5

28.56

18.48
69.94
88.42

0.78

68.968
0.55
98.078

98.08
98.08
98.08
5890.54

32.06
24.00
4.00
0.14

Say

Supply and fixing of MS grill Window of 3.23X 1.35 mts by using 40 x40 x 6mm MS Angle section for
outer frame and 10 mm square safety bars @ 100 mm C/C both ways including cost & conveyance of
all materials and labour charges for finished item of work
Frame 40x40x6 mm (GW)
Verticals 2 x 1.35
Harizontal 2 x 3.23
10 mm SQ rod@ 100c/c
Verticals 14 x 1.32
Harizontal 30x 2.93
MS Aldrop,Tower Bolt and Holdfast

168 of 517

2.7
6.46
9.16

3.5

32.06

18.48
87.9
106.38

0.78

82.976
0.55

D-W data

Sno

Qty

Description of Item
total weight
Rate analysis
cost of MS steel
Fabrication charges BMM -V-14

Rate

Unit

115.59
115.59

32.06
24.00

Fixing Charges BMM -V-15

115.59

4.00

Over Head Charges

6942.12

0.14

Per
115.59

Say

Supply and fixing of MS grill Window of 2.26 x1.35 mts by using 40 x40 x 6mm MS Angle section for
outer frame and 10 mm square safety bars @ 100 mm C/C both ways including cost & conveyance of
all materials and labour charges for finished item of work
Frame 40x40x6 mm (GW)
Verticals 2 x 1.35

2.7

Harizontal 2 x 2.26

4.52
7.22

3.5

25.27

0.78

46.332

10 mm SQ rod@ 100c/c
Verticals 14 x 1.32

18.48

Harizontal 22x 1.86

40.92
59.4

MS Aldrop,Tower Bolt and Holdfast

0.55

total weight

72.152

Rate analysis
cost of MS steel

72.15

32.06

Fabrication charges BMM -V-14

72.15

24.00

Fixing Charges BMM -V-15

72.15

4.00

Over Head Charges

4333.45

0.14

Say

Supply and fixing of MS grill Window of 3 x1.35 mts by using 40 x40 x 6mm MS Angle section for
outer frame and 10 mm square safety bars @ 100 mm C/C both ways including cost & conveyance of
all materials and labour charges for finished item of work
Frame 40x40x6 mm (GW)
Verticals 2 x 1.35

2.7

Harizontal 2 x 3

6
8.7

3.5

30.45

0.78

73.226

10 mm SQ rod@ 100c/c
Verticals 14 x 1.32

18.48

Harizontal 29x 2.6

75.4
93.88

169 of 517

D-W data

Sno

Qty

Description of Item

Rate

Unit

Per

MS Aldrop,Tower Bolt and Holdfast

0.55

total weight

104.23

Rate analysis
cost of MS steel

104.23

32.06

Fabrication charges BMM -V-14

104.23

24.00

Fixing Charges BMM -V-15

104.23

4.00

Over Head Charges

6259.84

0.14

Say

170 of 517

D-W data

Amount

3.24

2843.36
913.07

4300.32
150.00
425.00
396.00
280.00
204.00
188.00
100.00
1979.65

0.00
11779.40
1603.77
13383.20

171 of 517

D-W data

Amount

4.26

2843.36
1201.41

5758.56
150.00
425.00
396.00
280.00
204.00
188.00
100.00
2650.95

0.00
14197.28
1932.96
16130.25

172 of 517

D-W data

Amount

5.11

2843.36
1441.69

7291.20
150.00
425.00
396.00
280.00
204.00
188.00
100.00
3356.50

0.00
16675.75
2270.40
18946.20

173 of 517

D-W data

Amount

2.6

2843.36
732.86

3392.64
150.00
425.00
396.00
280.00
204.00
188.00
100.00
1561.80

0.00
10273.66
1398.76
11672.45

174 of 517

D-W data

Amount

1.92

2843.36
540.63

2380.80
150.00
425.00
396.00
140.00
102.00
188.00
50.00
1096.00

0.00
8311.79
1131.65
9443.45

175 of 517

D-W data

Amount

1.62

2843.36
456.54

1919.52
150.00
114.00
391.00
280.00
102.00
179.00
144.96
883.65

0.00
7464.03
1016.23
8480.30

176 of 517

D-W data

Amount

2.24

2843.36
630.74

2901.60
150.00
425.00
396.00
280.00
204.00
188.00
100.00
1335.75

0.00
9454.45
1287.22
10741.70

177 of 517

D-W data

Amount

1.92

2843.36
600.71

2663.52
150.00
425.00
396.00
140.00
102.00
188.00
50.00
1226.15

0.00
8784.74
1196.04
9980.80

178 of 517

D-W data

Amount
325.00
44.25
369.25

2362.00
321.59
2683.60

7288.00
-558.00

179 of 517

D-W data

Amount
456.00
7186.00
978.37
8164.40

7069.00
-558.00
456.00
6967.00
948.56
7915.60

4737.00
644.94
5381.95

180 of 517

D-W data

Amount

7288.00
992.26
8280.30

3144.37
2353.86
392.31
824.68
6715.22
6716.00

181 of 517

D-W data

Amount

3705.70
2774.07
462.35
971.90
7914.02
7915.00

2313.19
1731.65
288.61
606.68
4940.13
4941.00

182 of 517

D-W data

Amount

3341.50
2501.43
416.91
876.38
7136.21
7137.00

183 of 517

D-W data

1 Supplying & fixing of Medium Teak Wood Panneled Main Door of Size 4.00 Mts X 2.70 Mts made with outer frame of
section 4"x5"(100x125mm) two horizontal and four verticals fixed frame,Both sides fixed with Iron grill (size:1900 x
500mm) ,(1850x500mm)madeup of Vertical & Horizontal bars of 10mm Square welded to MS Flat 20x5mm alround
forming (100x125mm) grid and with 5mm thick pin headed glass panels (2Nos of 500mmX1900mm, 2'nos of 500mm
500mm,1 no of 2600mmx500mm), MT beading .The shutters should be made up of size 650mm x 1900mm (4nos) fra
with 2"thick(50mm) and scantlings(planks) should be 1" (25mm thick) including fixing all fixtures such as 350mm long
Brass Aldrops , 200mm Long Towetr bolts(4 nos), Brass fancy Door Handles 250mm long (2nos)out side, 250mm long
(2nos) inside, BrassHinges 150mm long (4x4=16Nos) including polishing with melamine finish including all labour cha
for wrought &put up all other charges stc., complete for finished item of work.
Nos

Qty

Rate

per

4.0

0.1

0.125

0.15

97894

cum

Verticals end
Verticals midle
BMT-E.02 (2 TO 3mt length)

2
2

2.7
2.1

0.1
0.1

0.125
0.125

88994

cum

Vertical at midle top grill


BMT-E.01 (up to 2 mt length)

0.07
0.05
0.120
cum
0.01
0.009
cum

80094

cum

80094

cum

160189

cum

I. Outer frame:Horizontals

BMT-E.03

II.Shutters:Top & Bottom rails


4x2
Middle
4x2
Verticals
4x2
SSR No.109 (up to 2 mt length)
Top & Middle planks
III.PLANKS:Bottom planks
BMT-E.04
Iron Grill(side) 10mm Sq.bars Ver.
Iron Grill(top)

Iron Grill

Horizontal
Horizontal
10mm Sq.bars Ver.

8
8
8

8
4

8
18
8
36

0.7

0.66
0.53
1.93

0.1

0.125
0.125
0.125

0.42
0.42

0.42
0.62

0.125

0.05
0.05
0.05

0.033
0.027
0.097
0.156
cum
0.035
0.026
0.061
cum
15.2
9
13.2
18
55.4
43.489

0.025
0.025

1.9
0.5
1.65
0.5

10 mm Sq.bars 0.785kg/rm ==
or say
Alround MS frame

(4*(0.5+1.9) +4*(0.5+1.85)) =

19

Wt of 20x5 mm MS flat @ 0.785Kg/Rm


or say
Labour charges for fabrication & fixing Grill in position
Rate as per BMM-V.14&15 (945,946)
Wrought & put up for Door

Total Qty.of
Wood

model door 4X2.7

Carpentor class I 5.31 420.00


Carpentor class II 12.39 375.00
M.M.
8.8 320.00
Qty.
0.15 + 0.12 + 0.00875 +
0.156+0.06132 = 0.49607 cum

184 of 517

43.5
Kgs

Rm
'
'
Rm
Rm
32.06

Kg

Rm

14.915
15
Kgs
58.5
Kgs
day
day
day
0.49607
cum

32.06

Kg

28

Kg

2230.2
4646.25
2816
9692.45

cum

Cost of 5mm thick pin headed glass panels 1x2x1.90m X


0.50m=1.90m2 + 2x1.85x0.5=1.85 (3.75sqm) as per BMT-I.14
FIXTURES:350mm Long Brass Aldrop
BMT-G.38
300mm long Brass Latch heavy
BMT-G.68
300mm Long Tower Bolts
BMT-G.05
200mm long Handles (Brass)
BMT-G.59
250mm long Handles (Brass)
BMT-G.60
150mm long Brass But Hinges
BMT-G.22
Brass Door Stoppers (BMT_G.46)
BMT-G.46
Screws
LS

3.75

430

sqm

2473

Each

644

Each

530

Each

454

Each

819

Each

16

16

383

Each

198

Each

90

each

Add 14 % Over head Charges


Total Rate/Each
ORSAY

Asst. Exe.Engineer
APEWIDC, Kuppam

Dy. Executive Engineer


APEWIDC, Madanapalli

Executive Engineer
APEWIDC, Chittoor

Superintending Engineer
APEWIDC, Kadapa

model door 4X2.7

185 of 517

made with outer frame of


h Iron grill (size:1900 x
MS Flat 20x5mm alround
1900mm, 2'nos of 500mm x
50mm x 1900mm (4nos) frame
ures such as 350mm long
2nos)out side, 250mm long
ish including all labour charges

Amount
14684.10

10679.28

700.82

12494.66

9822.79

1394.61

480.90
1638.00

4808.13

model door 4X2.7

186 of 517

1612.50
2473
644
2120
908
1638
6128
396
360
72982.79
10217.59
83200.38
83201

model door 4X2.7

187 of 517

Standard Data - Electrical Items SSR 2015-16


Index Specific
Description
Unit Quanti Rate Rs. Amount 3
1
-code
ation
ty
Rs.
No.
1
2
3
4
5
61
0
1.4.2
Supply and Fixing of 25mm dia 2.20 mm
thick PVC pipe (ISI MARK) concealed in
2
0
(C)
Roof Slabs with all required accessories
0
including masonary work
and labour
6
charges
etc.,
complete.
Make
:
Sudhakar/ Maco Plast / Modi
Taking Output = 100 M
a) Material
elec-1.2.4 25mm dia 2.20 mm thick PVC pipe
100 M
1
3200.00
3200.00
ele-1.2.39 25mm dia 1,2,3 & 4 way deep Junction Each
12
25.00
300.00
Box
elec-1.2.44 25mm PVC bends
Each
12
6.00
72.00
3572.00
Add contr profit @14% on material
0.00
0.00
Total material cost
3572.00
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
2
480.00
960.00
elec-8.1.75 Semi skilled Electrician
day
2
375.00
750.00
elec-8.1.81 Helpers
day
2
375.00
750.00
Add area allowence on labour 0%
0.00
charges
@
Add contr profit @14% on Labour
0%
2460.00
0.00
C) Cost for 100 RM
6032.00
Rate per Metre = C/100
60.35
Note : 1. If 25mm dia PVC / MS pipes are used
for light / fan point, add the cost of sheet metal /
1.4.2
(b)

Supply and Fixing of 25mm dia 1.80 mm


thick P.V.C. pipe (ISI MARK) concealed in
wall with all required accessories
including masonary work for light, fan
and separate plug point with well
seasoned TW box including all labour
charges etc., complete.
Make :
Sudhakar/ Maco Plast / Modi

Taking Output = 100 M


a) Material
elec-1.2.3 25mm dia 1.8mm thick PVC pipe
elec-8.1.7 U' Nails

100 M
100
Nos

elec-1.3.5 8"x10" Hot dip Galvanized Metal Boxes


Each
ele-1.2.39 25mm dia 1,2,3 & 4 way deep Junction Each
elec-1.2.44 Box
25mm PVC bends
Each
elec-8.1.50 Cement
kg
Add contr profit @14% on material

188 of 517

0.00

1
2

2800.00
44.00

2800.00
88.00

2
12
12
50

179.00
25.00
6.00
7.00

358.00
300.00
72.00
350.00
3968.00
0.00

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

Total material cost


b) Labour charges :
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi skilled Electrician
elec-8.1.81 Helpers
elec-8.1.76 Mason Ist class
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
C) Cost for 100 RM
Rate per Metre = C/100
2.1.1

day
day
day
day
0%
0%

3
1
3968.00 1
0
960.00 2
750.00 0
0
750.00 6

Quanti Rate Rs. Amount


ty
Rs.

2
2
2
2

480.00
375.00
375.00
420.00
3300.00

840.00
0.00
0.00
7268.00
72.70

1051.00

1051.00

6
6
100

18.00
21.00
0.61

Wiring with 2 runs of 14/0.3mm (1.0


Sq.mm) Fire Retardant Low Smoke
(FRLS) P.V.C. insulated flexible copper
cable (ISI MARK) in existing pipe with
6A switch, Ceiling rose and 3mm thick
hylam sheet covering to switch control
box including all labour charges etc.,
complete for light, bell, fan and exhaust
fan points in Non-Residential Buildings
Makes of Wires : Finolex / R.R.Cable
Makes of Switches :
Anchor Penta Cherry / Gold Madel
Olive / Million Zoom / Great white
omega

Taking Output = 6 Points

a) Material
elec-1.5.1 14/0.3mm (1.00 Sqmm)
FRLS PVC 100 M
insulated flexible copper wire
elec-1.7.1 6A Switch @18/- each
each
elec-1.7.13 6A 3 way Ceiling Rose@21/-each
each
elec-8.1.51 25 x 20 cms (10" x8") Hylam sheet 3mm Sq.in
thick
Add contr profit @14% on material
0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi skilled Electrician
day
elec-8.1.81 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
C) Cost for 6 Points

189 of 517

108.00
126.00
61.00
1346.00
0.00
1346.00

0.6
1.2
0.6

480.00
375.00
375.00
963.00

288.00
450.00
225.00
0.00
0.00
2309.00

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

3
1
384.85 1
0
2
0
0
6

Quanti Rate Rs. Amount


ty
Rs.

Rate per Point = C/6

2.1.1 (1) Wiring with 2 runs of 14/0.3mm (1.0


Sq.mm) Fire Retardant Low Smoke
(FRLS) P.V.C. insulated flexible copper
cable (ISI MARK) in existing pipe with
6A 2 way flush type switch, Ceiling rose
and 3mm thick hylam sheet covering to
switch control box including all labour
charges etc., complete for Stair case and
2 way light/ fan points in Residential
Buildings
Makes of Wires : Polycab / Havells /
SunCab / Fortune Art / Paragon /
HPL / L&T / Power flex / RPG /
Anchor / Bonton
Makes of Switches : Anchor
Penta Cherry / Gold Madel Olive /
Million Zoom
Rate as per light point in Non Residental
Building =338.4
For stair case
3.1.1

1.50

100

338.40

507.60

Supply and run of 2 of 14 /0.3mm (1.0


Sq.mm) FRLS P.V.C. insulated flexible
copper cable in existing pipe for earth
continuity including all labour charges
etc., complete.
Makes of Wires : Polycab / Havells /
SunCab / Fortune Art / Paragon /
HPL / L&T / Power flex / RPG /
Anchor / Bonton

Taking Output = 100 M


a) Material
elec-1.5.8 14/0.3 mm(1.00 sq.mm) FRLS Copper
wire

Add contr profit @14% on material


0.00
Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Cost per 100 Rmt

190 of 517

0.67
2
0.67

924.00

480.00
375.00
375.00
1322.85

1848.00
1848.00
0.00
1848.00
321.60
750.00
251.25
0.00
0.00
3170.85

Ele-Data

Index Specific
-code
ation
No.
3.1.2

Description

Unit

Rate per Meter= C/100


Supply and run of 1 of 14 /0.3mm (1.0
Sq.mm) FRLS P.V.C. insulated flexible
copper cable in existing pipe for earth
continuity including all labour charges
etc., complete.
Makes of Wires : Polycab / Havells /
SunCab / Fortune Art / Paragon /
HPL / L&T / Power flex / RPG /
Anchor / Bonton

Taking Output = 100 M


a) Material
elec-1.5.8 14/0.3 mm (1.00 sq.mm) FRLS Copper
wire

100

Add contr profit @14% on material


0.00
Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Cost per 100 Rmt
Rate per Meter= C/100
3.1.3

3
1
31.75 1
0
2
0
0
6

Quanti Rate Rs. Amount


ty
Rs.

924.00

924.00
0.00
924.00

0.34
1
0.34

480.00
375.00
375.00
665.70

163.20
375.00
127.50
0.00
0.00
1589.70
15.90

Supply and run of 2 of 2 /0.3mm (1.50


Sq.mm) FRLS P.V.C. insulated flexible
copper cable in existing pipe for phase
and neutral including all labour charges
etc., complete.
Makes of Wires : Polycab / Havells /
SunCab / Fortune Art / Paragon /
HPL / L&T / Power flex / RPG /
Anchor / Bonton

Taking Output = 100 M


a) Material
elec-1.5.9 22/0.3 mm (1.50 sq.mm) FRLS Copper
wire
Add contr profit @14% on material
Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi skilled Electrician
elec-8.1.82 Helpers
Add area
charges @

allowence

on

labour

191 of 517

100

1358.00

0.00

day
day
day
0%

0.67
2
0.67

480.00
375.00
375.00

2716.00
2716.00
0.00
2716.00
321.60
750.00
251.25
0.00

Ele-Data

Index Specific
-code
ation
No.

Description
Add contr profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100

Quanti Rate Rs. Amount


ty
Rs.

0%

1322.85

3.1.3(1) Supply and run of 1 of 22 /0.3mm (1.50


Sq.mm) FRLS P.V.C. insulated flexible
copper cable in existing pipe for earth
continuity including all labour charges
etc., complete.
Makes of Wires : Polycab / Havells /
SunCab / Fortune Art / Paragon /
HPL / L&T / Power flex / RPG /
Anchor / Bonton
Taking Output = 100 M
a) Material
elec-1.5.9 22/0.3 mm (1.50 sq.mm) FRLS Copper
wire

100

Add contr profit @14% on material


0.00
Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Cost per 100 Rmt
Rate per Meter= C/100
3.1.4

3
1
0.00 1
0
4038.85 40.40 2
0
0
6

Unit

0.34
1
0.34

1358.00

480.00
375.00
375.00
665.70

1358.00
1358.00
0.00
1358.00
163.20
375.00
127.50
0.00
0.00
2023.70
20.25

Supply and run of 2 of 36/0.3 mm ( 2.5


sq.mm) FRLS / HFFR PVC insulated 1100
V grade as per IS: 694 / 1990
specifications for flexible copper cable
and one run of 14/0.3mm (1.0 sq.mm)
flexible copper wire for earthing in
existing PVC conduit pipe for circuit
mains including labour charges (phase
neutral and earth) etc., complete as
required for switch board circuit mains.
Makes of Wires : Finolex / RR Cabel

elec-1.5.3 36/0.3mm (2.5 sq.mm ) FRLS copper


elec-1.5.1 wire
1 run of 1.00 sq.mm wire
Add contr profit @14% on material
Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician

192 of 517

100 M

2.00

2510.00

1.00

1051.00

1051.00

6071.00
0.00
6071.00

0.00

day

5020.00

1.01

480.00

484.80

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
elec-8.1.75 Semi skilled Electrician
day
elec-8.1.81 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Cost per 100 Rmt
Rate per Meter= C/100

Supply and run of 2 of 56/0.3 mm ( 4


sq.mm) FRLS PVC insulated flexible
copper cable in existing conduit pipe for
circuit mains including labour charges
(for phase and neutral ) etc., complete
as required for switch board circuit
mains.
Makes of Wires : Finolex / RR Cabel
elec-1.5.4 56/0.3mm ( 4 sq.mm ) FRLS copper wire 100 M

3
1
1125.00 1
0
378.75 0.00 2
0
0.00 0
8059.55 6

Quanti Rate Rs. Amount


ty
Rs.
3
1.01

375.00
375.00
1988.55

80.60
8059.55

3.1.5

elec-1.5.3

1 run of 2.50 sq.mm wire

Add contr profit @14% on material


0.00
Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi skilled Electrician
day
elec-8.1.81 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Cost per 100 Rmt
Rate per Meter= C/100
3.1.6

3833.00

1.00

2510.00

7666.00
2510.00

10176.00
0.00
10176.00
1.34
4
1.34

480.00
375.00
375.00
2645.70

643.20
1500.00
502.50
0.00
0.00
12821.70
128.25

Supply and run of 2 of 84/0.3 mm ( 6


sq.mm) FRLS PVC insulated flexible
copper cable in existing conduit pipe for
circuit mains including labour charges
(phase and neutral ) etc., complete as
required for switch board circuit mains.
Makes of Wires : Finolex / RR Cabel

elec-1.5.5 84/0.3mm ( 6 sq.mm ) FRLS copper wire


elec-1.5.3

2.00

1 run of 2.50 sq.mm wire

Add contr profit @14% on material


Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi skilled Electrician

193 of 517

100 M

2.00

5828.00

1.00

2510.00

2510.00

14166.00
0.00
14166.00

0.00

day
day

11656.00

1.34
4

480.00
375.00

643.20
1500.00

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Cost per 100 Rmt
Rate per Meter= C/100

3
1
502.50 1
0
0.00 0.00 2
0
16811.70 0
168.15 6

Quanti Rate Rs. Amount


ty
Rs.
1.34

375.00
2645.70

3.1.6 (1) Supply and run of 4 of 84/0.3 mm ( 6


sq.mm) FRLS PVC insulated flexible
copper cable in existing conduit pipe for
circuit mains including labour charges
(for earth) etc., complete as required for
switch board circuit mains.
Makes of Wires : Finolex / RR Cabel
elec-1.5.5 84/0.3mm ( 6 sq.mm ) FRLS copper wire
elec-1.5.3

1 run of 2.50 sq.mm wire

100 M

4.00

5828.00

23312.00

1.00

2510.00

2510.00

Add contr profit @14% on material


0.00
Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi skilled Electrician
day
elec-8.1.81 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Cost per 100 Rmt
Rate per Meter= C/100
3.1.7

25822.00
0.00
25822.00
2.34
7
2.34

480.00
375.00
375.00
4625.70

1123.20
2625.00
877.50
0.00
0.00
30447.70
304.48

Supply and run of 2 of 140/0.3 mm ( 10


sq.mm) FRLS PVC insulated flexible
copper cable in existing conduit pipe for
circuit mains including labour charges
(phase and neutral ) etc., complete as
required for switch board circuit mains.
Makes of Wires : Finolex / RR-Cable

elec-1.5.6 140/0.3mm ( 10 sq.mm ) FRLS copper


wire

100 M

Add contr profit @14% on material


0.00
Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges @

194 of 517

2.00

9030.00

18060.00
18060.00
0.00
18060.00

1
3
1

480.00
375.00
375.00

480.00
1125.00
375.00
0.00

Ele-Data

Index Specific
-code
ation
No.

Description
Add contr profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100

Quanti Rate Rs. Amount


ty
Rs.

0%

1980.00

3.1.7 (1) Supply and run of 1 of 140/0.3 mm ( 10


sq.mm) FRLS PVC insulated flexible
copper cable in existing conduit pipe for
circuit mains including labour charges
(for earth) etc., complete as required for
switch board circuit mains.
Makes of Wires : Finolex / RR Cable
elec-1.5.6 140/0.3mm ( 10 sq.mm ) FRLS copper
wire

3
1
0.00 1
0
20040.00 200.40 2
0
0
6

Unit

100 M

Add contr profit @14% on material


0.00
Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi skilled Electrician
day
elec-8.1.81 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Cost per 100 Rmt
Rate per Meter= C/100

1.00

9030.00

9030.00
9030.00
0.00
9030.00

0.5
1.5
0.5

480.00
375.00
375.00
990.00

240.00
562.50
187.50
0.00
0.00
10020.00
100.20

3.1.4 ( 1) Supply and run of 2 of 2.5 sq.mm FRLS


PVC insulated flexible copper cable and
one run of 1.0 sq.mm flexible copper
wire for earthing in existing PVC/ MS
conduit pipe for circuit mains including
labour charges (phase neutral and earth)
etc., complete as required for switch
board circuit mains.
Makes of Wires : Finolex / RR Cable

elec-1.5.3 2 run of 2.5 sq.mm wire


elec-1.5.1 1 run of 1 sq.mm wire

1
1

Add contr profit @14% on material


Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician (0.67 + 0.34)
elec-8.1.75 Semi skilled Electrician (2 + 1)
elec-8.1.81 Helpers (0.67 + 0.34)

195 of 517

2.00
1.00

2510.00
1051.00

5020.00
1051.00
6071.00
0.00
6071.00

1.005
3
1.005

480.00
375.00
375.00

482.40
1125.00
376.88

0.00

day
day
day

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

Add area allowence on labour


charges
Add contr@
profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100

0%
0%

3
1
0.00 1
0
0.00 8055.28 2
0
80.60 0
6

Quanti Rate Rs. Amount


ty
Rs.
1984.28

3.1.5 (2) Supply and run of 2 of 4 sq.mm FRLS


PVC insulated flexible copper cable and
one run of 2.5 sq.mm flexible copper
wire for earthing in existing PVC/ MS
conduit pipe for circuit mains including
labour charges (phase neutral and earth)
etc., complete as required for switch
board circuit mains.
Makes of Wires : Finolex / RR Cable
elec-1.5.14 2 run of 4.0 sq.mm wire
elec-1.5.3 1 run of 2.50 sq.mm wire

1
1

Add contr profit @14% on material


0.00
Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician (1.0 + 0.34)
day
elec-8.1.75 Semi skilled Electrician (3 + 1)
day
elec-8.1.81 Helpers (1.0 + 0.34)
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Cost per 100 Rmt
Rate per Meter= C/100

2.00
1.00

3833.00
2510.00

1.34
4
1.34

.
480.00
375.00
375.00
2645.70

7666.00
2510.00
10176.00
0.00
10176.00
643.20
1500.00
502.50
0.00
0.00
12821.70
128.25

3.1.6 (2) Supply & run of 2 of 6.0


Sqmm(84/0.3mm) PVC insulated flexible
copper cable and one run of 2.5 Sqmm
flexible PVC insulated copper cable for
earthing in the existing conduit pipe for
AC points & SDB's etc as required.
Makes of Wires :Finolex / RR Cable
elec-1.5.5 2 run of 6.0 sq.mm wire
elec-1.5.3 1 run of 2.50 sq.mm wire

1
1

Add contr profit @14% on material


0.00
Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician (1.0 + 0.34)
day
elec-8.1.75 Semi skilled Electrician (3 + 1)
day
elec-8.1.81 Helpers (1.0 + 0.34)
day
Add area allowence on labour 0%
charges @

196 of 517

2.00
1.00

5828.00
2510.00

1.34
4
1.34

480.00
375.00
375.00

11656.00
2510.00
14166.00
0.00
14166.00
643.20
1500.00
502.50
0.00

Ele-Data

Index Specific
-code
ation
No.

Description
Add contr profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100

Quanti Rate Rs. Amount


ty
Rs.

0%

2645.70

3.1.6 (3) Supply and run of 4 of 6 Sq mm PVC


insulated flexible copper cable and 1 run
of 2.5 Sq mm flexible PVC insulated
flexible copper cable in the existing
conduit pipe for run of mains from main
panel board to TPN DB'S with pin type
lugs and connections etc.,complete for
Lighting Distribution boards.
Makes of Wires : Finolex / RR Cable
elec-1.5.5 4 run of 6.0 sq.mm wire
elec-1.5.3 1 run of 2.50 sq.mm wire

1
1

Add contr profit @14% on material


Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician (2.0 + 0.34)
elec-8.1.75 Semi skilled Electrician (6 + 1)
elec-8.1.81 Helpers (2.0 + 0.34)

19

4.00
1.00

5828.00
2510.00

23312.00
2510.00
25822.00
0.00
25822.00

2.5
7.5
2.5

480.00
375.00
375.00

1200.00
2812.50
937.50
0.00
0.00
30772.00
307.75

0.00

Add area allowence on labour


charges
Add contr@
profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100

3
1
0.00 1
0
16811.70 168.15 2
0
0
6

Unit

day
day
day
0%
0%

4950.00

Supply and run of 4 of 10 Sq mm FRLS


PVC insulated flexible copper cable with
1 No 4.00 Sq.mm PVC insulated flexible
copper cable in the existing conduit pipe
for run of mains from main panel board
to TPN DB'S with pin type lugs and
connections etc.,complete for PDB's and
AC DBS
Makes of Wires :Finolex / RR Cable

Taking Output = 100 M


a) Material
elec-1.5.6 126/0.4mm (10 Sq.mm)
flexible copper cable

FRLS

PVC 100 M

9030.00

36120.00

elec-1.5.4 56/0.3mm 4.00 sqmm) FRLS PVC copper 100 M


cable

3383.00

3383.00

Add contr profit @14% on material


Total material cost

197 of 517

0.00

39503.00
0.00
39503.00

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

b) Labour charges :
elec-8.1.74 Skilled Electrician (2.0 + 0.5)
day
elec-8.1.75 Semi skilled Electrician (6 + 1.5)
day
elec-8.1.81 Helpers (2.0 + 0.5)
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 100 M / day
2.1.4

2
6
2

480.00
375.00
375.00
3960.00

0.00
43463.00
434.65

Supply and fixing of 6A 3/2 pin wall plug


socket with 6A switch control on a
common switch board with earth
continuity including wire leads, earth
connections along with all labour
charges etc., complete.
Makes : Anchor / Gold Medal
Olive /Million Zoom

Taking Output = each


a) Material
elec-1.7.4 6A 3 pin / 2 pin Socket
elec-1.7.1 6A 1 way flush type switch

each
each

1
1

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
0.067
elec-8.1.81 Helpers
day
0.067
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Rate per each
Note : Labour Charges proposed for 1point
considering 15 per day
2.1.4(a)

3
1
1
0
960.00 2250.00 2
750.00 0
0
0.00 6

Quanti Rate Rs. Amount


ty
Rs.

27.00
18.00

.
480.00
375.00
57.29

27.00
18.00
45.00
0.00
45.00
32.16
25.13
0.00
0.00
102.30

Supply and fixing of 3 Nos 6A 3 pin wall


plug socket with 3 Nos. 6A switch control
on a common switch board with earth
continuity including wire leads, earth
connections along with all labour
charges etc., complete.
Makes : Anchor Penta Cherry / Gold
Medal Olive / Million Zoom

Taking Output = each


a) Material
elec-1.7.4 6A 3 pin / 2 pin Socket
elec-1.7.1 6A 1 way flush type switch
elec-8.1.51 25 x 20 cms (10" x8") Hylam sheet 3mm thick

198 of 517

each
each

3
3

27.00
18.00

Sq.in

100

0.61

81.00
54.00
61.00

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
0.201
elec-8.1.81 Helpers
day
0.201
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Rate per each
Note : Labour Charges proposed for 1point
considering 15 per day
2.1.3

.
480.00
375.00
171.86

75.38
0.00
0.00
367.90

Wiring with 2 of 14/0.3mm (1.0 Sq.mm)


P.V.C. insulated F.R.L.S flexible copper
cable (ISI MARK) in existing pipe with
6A switch control and 3/2 pin sockets
fixing on separate board including all
labour charges etc., complete.
Makes of Wires : Finolex / RR Cable

Taking Output = 15 Points


a) Material
elec-1.5.1 14/0.3mm PVC FR flexible copper wire
elec-1.7.1 6Aswitches @18/- each
elec-1.7.4 6A 3 pin / 2 Pin Socket

100 M
each
each

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi skilled Electrician
day
elec-8.1.81 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
C) Cost for 15 Points
Rate per Points = C/15

12

3
1
196.00 1
0
0.00 196.00 2
0
0
96.48 6

Quanti Rate Rs. Amount


ty
Rs.

1
15
15

1051.00
18.00
27.00

1051.00
270.00
405.00
1726.00
0.00
1726.00

1.5
1.5
1.5

480.00
375.00
375.00

720.00
562.50
562.50
0.00
0.00
3571.00
238.10

1845.00

Supply and Fixing of 16A 3pin and 6A


3pin plug socket with and 16A switch
control duly recessed in wall with MS
switch deep box of 6" x8" x2 1/2" size
covered with hylam
sheet including
earth connections and all labour charges
etc., complete.
Makes : Anchor Penta Cherry / Gold
Medal /Million Zoom
Taking Output = each

199 of 517

Ele-Data

Index Specific
-code
ation
No.
elec-1.3.4

Description

Unit

6 Module Galvanized Metal Boxes Horizontal /


Verticle

each

137.00

Sq.in
each
each

50
1
1

0.61
102.00
65.00

a) Material

elec-8.1.51 25 x 20 cms (10" x8") Hylam sheet 3mm thick


elec-1.7.10 16A 3 pin / 6A 3pin plug socket (2 in 1)
Elec1-7-8 16A flush type switch
Add contr profit @14% on material
Total material cost

3
1
1
0
137.00 2
30.50 0
102.00 0
6
65.00
334.50

Quanti Rate Rs. Amount


ty
Rs.

0.00

0.00
334.50

b) Labour charges :
Skilled Electrician
elec-8.1.77 Semi Skilled Electrician
elec-8.1.81 Helpers

day
day
day

Add area allowence on labour


charges
Add contr@
profit @14% on Labour

0.1
0.1
0.1

480.00
375.00
375.00

48.00
37.50
37.50
0.00

123.00

0.00
457.50

0%
0%

Rate per each


Note : Labour Charges proposed for 10 jobs per
day
20

elec2.12.67

Supply and fixing Distribution board with


20A single phase plug and Socket, in
sheet steel enclosure with 10/16/20A SP
MCB including internal connection and
labour charges for flush mounting etc.,
complete
Makes : L&T Exora /Siemens / GE
/ABB /Standard / Havells / HPL / Indo
Asain / Toyoma
a) Material
1 Phase Distribution board with 20A plug
and socket.

ele-2.9.9 10/16/20A SP MCB

Nos

590.00

590.00

Nos

162.00

162.00
752.00
0.00
752.00

0.25
0.25
0.25

480.00
375.00
375.00

120.00
93.75
93.75
0.00
0.00
130.00

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
Nos
elec-8.1.75 Semi skilled Electrician
Nos
elec-8.1.81 Helpers
Nos
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as Cement, Sand, T.W. LS
Plugs, Screws etc.,
Rate per each
Note : 1. Labour Charges considered for 4 jobs /
day
2.
For concealing, add
the
following:
a
1No. Semi skilled mason
b
1/4 bag cement

200 of 517

307.50

1189.50

Ele-Data

Index Specific
-code
ation
No.
21

Description

Unit

Quanti Rate Rs. Amount


ty
Rs.

Supply and fixing 4 Way TPN Distribution


board with IP-43 protection (Metal Door)
suitable for 3 phase 40 A FP Isolator as
incomer and 12 Nos 6-32 A 10kA SP
MCBs as outing goings including internal
connection and labour charges for flush
mounting etc., complete.
Makes : L&T Exora /Siemens / GE
/ABB /Standard / Havells / HPL / Indo
Asain / Toyoma

40A FP Isolator - 1 No for incomer,


10kA-6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
elec.2.12.4 4way TPN, D.B with IP-43 Protection (MD) each
2
suitable for 3 phase ELCB / RCCB / FP
Isolator as incommer.

3
1
1
0
2
0
0
6

elec40A, 4 Pole Isolator


2.10.14 10kA - 6-32A range SP MCBs
elec-2.9.9

each
each

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as TW Plugs, Screws LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
A

2200.00

2200.00

1
12

678.00
162.00

678.00
1944.00
4822.00
0.00
4822.00

0.5
1
1

480.00
375.00
375.00

240.00
375.00
375.00
0.00
0.00
15.00

990.00
15.00

5827.00

Supply and fixing 4 Way TPN Distribution


board with IP-20 protection (Metal Door)
suitable for 3 phase 40 A FP Isolator as
incomer and 12 Nos 6-32 A 10kA SP
MCBs as outing goings including internal
connection and labour charges for flush
mounting etc., complete.
Makes : L&T Exora /Siemens / GE
/ABB /Standard / Havells / HPL / Indo
Asain / Toyoma
40A FP Isolator - 1 No for incomer,
10kA-6-32A SP MCBs - 12Nos for
outgoing.

201 of 517

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

Taking Output = each


a) Material
elec.2.12.3 4way TPN, D.B with IP-20 Protection (MD) each
9
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.
elec40A, 4 Pole Isolator
2.10.14
elec-2.9.9 10kA - 6-32A range SP MCBs

each
each

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as TW Plugs, Screws LS
Cement etc,

2491.00

1
12

890.00
201.00

0.5
1
1

480.00
375.00
375.00
990.00
15.00

Rate per each


Note : Labour Charges considered for 2 jobs / day
B

3
1
1
0
2491.00 2
0
0
6

Quanti Rate Rs. Amount


ty
Rs.

890.00
2412.00
5793.00
0.00
5793.00
240.00
375.00
375.00
0.00
0.00
15.00
6798.00

Supply and fixing 4 Way TPN Distribution


board with IP-43 protection (Metal Door)
suitable for 3 phase 63 A FP Isolator as
incomer and 12 Nos 6-32 A 10kA SP
MCBs as outing goings including internal
connection and labour charges for flush
mounting etc., complete.
Makes : L&T Exora /Siemens / GE
/ABB /Standard / Havells / HPL / Indo
Asain / Toyoma

63A FP Isolator - 1 No for incomer,


10kA-6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
elec.2.12.4 4way TPN, D.B with IP-43 Protection (MD) each
2
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.
elec63A, 4 Pole Isolator
2.10.15
elec-2.9.9 10kA - 6-32A range SP MCBs

each
each

Add contr profit @14% on material


Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi Skilled Electrician
elec-8.1.82 Helpers

202 of 517

2491.00

2491.00

1
12

890.00
201.00

890.00
2412.00
5793.00
0.00
5793.00

0.5
1
1

480.00
375.00
375.00

240.00
375.00
375.00

0.00

day
day
day

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

Add area allowence on labour


charges
Add contr@
profit @14% on Labour
Sundries such as TW Plugs, Screws
Cement etc,

0%
0%
LS

3
1
0.00 1
0
0.00 15.00 2
0
0
6798.00 6

Quanti Rate Rs. Amount


ty
Rs.
990.00
15.00

Rate per each


Note : Labour Charges considered for 2 jobs / day
Supply and fixing
4 Way TPN
Distribution board with IP-43 protection
(Metal Door) suitable for 3 phase 80 A FP
Isolator as incomer and 12 Nos 6-32 A
10kA SP MCBs as outing goings including
internal connection and labour charges
for flush mounting etc., complete.
Makes : L&T Exora /Siemens / GE
/ABB /Standard / Havells / HPL / Indo
Asain / Toyoma
B -2

80A FP Isolator - 1 No for incomer,


10kA-6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
elec.2.12.4 4way TPN, D.B with IP-43 Protection (MD) each
2
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.
elec80A, 4 Pole Isolator
2.10.17 10kA - 6-32A range SP MCBs
elec-2.9.9

each
each

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as TW Plugs, Screws LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day

203 of 517

2491.00

2491.00

1
12

956.00
201.00

956.00
2412.00
5859.00
0.00
5859.00

1
1
1

480.00
375.00
375.00

480.00
375.00
375.00
0.00
0.00
14.00

1230.00
14.00

7103.00

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
22
Supply and fixing 8 way SPN Distribution
board with IP-43 protection (Metal Door)
suitable for 1 No. 40A single phase DP
Isolator as incomer and 6 Nos 6-32 A
10kA SP MCBs as outing going including
internal connection and labour charges
for surface / flush mounting etc.,
complete.
Makes : L&T Exora /Siemens / GE
/ABB /Standard / Havells / HPL / Indo
Asain / Toyoma

elec2.12.11

Quanti Rate Rs. Amount


ty
Rs.

3
1
1
0
2
0
0
6

40A DP Isolator / RCCB / ELCB - 1 No


for incomer, 6-32A SP MCBs - 6Nos
for outgoing.
Taking Output = each
a) Material
SPN 8 way D.B with IP-43 Protection (MD) each
suitable for single phase ECCB / RCCB/
DP Isolator.

elec40A D.P.Isolator
2.10.10
elec-2.9.9 10 kA - 6-32A range SP MCBs

each
each

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as hardware, cement etc,
LS
Rate per each
Note : Labour Charges considered for 2 jobs / day
23

Supply and fixing 8 way TPN - Vertical


type Distribution board with IP -43
Protection
with 125A, 4 Pole 25 kA
MCCB as incomer with 8Nos 63A TP
MCBs as outgoing including internal
connection and labour charges for flush
mounting etc., complete.
Makes : L&T Exora /Siemens / GE
/ABB /Standard / Havells / HPL / Indo
Asain / Toyoma

8 way TPN Vertical DB


a) Material

204 of 517

1245.00

1245.00

1
6

367.00
201.00

367.00
1206.00
2818.00
0.00
2818.00

0.5
0.5
1

480.00
375.00
375.00

240.00
187.50
375.00
0.00
0.00
9.50
3630.00

802.50
9.50

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
elec.2.12.5 6 Way TPN Vertical DB with IP -43 (Metal Nos
0
door) protection suitable for 125A, 4
Pole, 25kA MCCB as incomer.
elec-2.8.13 125 Amps, 4 Pole , 25 kA MCCB
elec-2.9.14 10 kA, 63A TP MCBs:
elec-2.9.9 10kA, 6 to 32A SP MCBs:

Nos
Nos
Nos

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as T.W. Plugs, Screws, LS
Cement etc.,

9823.00

1
8
0

7194.00
1477.00
201.00

1
1
1

480.00
375.00
375.00
1230.00
19.00

Rate per each


Note : 1. Labour Charges considered for 1 jobs /
day
2. If the Distribution Boards from Item No. 4.4.1
to
proposed
concealing, add the
a 4.4.8
1No. Semi
skilledfor
mason
b
23

3
1
9823.00 1
0
2
7194.00 0
0
11816.00 6

Quanti Rate Rs. Amount


ty
Rs.

Say

0.00
28833.00
0.00
28833.00
480.00
375.00
375.00
0.00
0.00
19.00
30082.00
30082.00

1/4 bag cement

Supply and fixing 8 way TPN - Vertical


type Distribution board with IP -43
Protection
with 125A, 4 Pole 25 kA
MCCB as incomer with 4Nos 63A TP
MCBs and 12 Nos. 10 kA SPMCBs as
outgoing including internal connection
and labour charges for flush mounting
etc., complete.
Makes : L&T Exora /Siemens / GE
/ABB /Standard / Havells / HPL / Indo
Asain / Toyoma

8 way TPN Vertical DB


a) Material
elec.2.12.5 8 Way TPN Vertical DB with IP -43 (Metal
0
door) protection suitable for 125A, 4
Pole, 25kA MCCB as incomer.

Nos

9823.00

9823.00

elec-2.8.13 125 Amps, 4 Pole , 25 kA MCCB


elec-2.9.14 10 kA, 63A TP MCBs:
elec-2.9.9 10kA, 6 to 32A SP MCBs:

Nos
Nos
Nos

1
4
12

7194.00
1477.00
201.00

Add contr profit @14% on material


Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician

0.00

7194.00
5908.00
2412.00
25337.00
0.00
25337.00

480.00

205 of 517

day

480.00

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as T.W. Plugs, Screws, LS
Cement etc.,

1
1

375.00
375.00
1230.00
19.00

Rate per each


Note : 1. Labour Charges considered for 1 jobs /
day
2. If the Distribution Boards from Item No. 4.4.1
to
proposed
concealing, add the
a 4.4.8
1No. Semi
skilledfor
mason
b
1/4 bag cement
23

3
1
375.00 1
0
375.00 0.00 2
0.00 0
0
19.00 6

Quanti Rate Rs. Amount


ty
Rs.

Say

26586.00
26586.00

Supply and fixing 8 way TPN - Vertical


type Distribution board with IP -43
Protection with 1 No. 63A FP MCCB as
incomer with 24 Nos. 10 kA SPMCBs as
outgoing including internal connection
and labour charges for flush mounting
etc., complete.
Makes : L&T Exora /Siemens / GE
/ABB /Standard / Havells / HPL / Indo
Asain / Toyoma

8 way TPN Vertical DB


a) Material
elec.2.12.3 8 Way TPN Vertical DB with IP -43 (Metal
5
door) protection suitable for 125A, 4
Pole, 25kA MCCB as incomer.

Nos

9823.00

9823.00

elec-2.8.12 63 Amps, 4 Pole , 25 kA MCCB


elec-2.9.6 10 kA, 63A TP MCBs:
elec-2.9.9 10kA, 6 to 32A SP MCBs:

Nos
Nos
Nos

1
24

5668.00
1477.00
162.00

5668.00
0.00
3888.00
19379.00
0.00
19379.00

1
1
1

480.00
375.00
375.00

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as T.W. Plugs, Screws, LS
Cement etc.,
Rate per each
Note : 1. Labour Charges considered for 1 jobs /
day
2. If the Distribution Boards from Item No. 4.4.1
to
proposed
concealing, add the
a 4.4.8
1No. Semi
skilledfor
mason
b

1230.00
19.00

Say

480.00
375.00
375.00
0.00
0.00
19.00
20628.00
20628.00

1/4 bag cement

206 of 517

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

Quanti Rate Rs. Amount


ty
Rs.

24 Supply, installation, commissioning of


3Phases, neutral 415V, free standing
type cubical panel board made of 16
Gauge CRCA sheet steel, the panel shall
be painted after processing 7 tank
process with RAL 7032 siemens grey. The
panel shall be consisting of suitable
rating of allumunium bus bars ( At the
rating of 0.8 A/Sq.mm) supported with
DMC/SMC and colour coded with heat
shrinkable sleeves. The bus bars fault
level shall be 50 KA and shall be as per
requirement
of
local
CEIG,
fire
regulations, other authorities etc. Panel
shall be suitable for accomdating the
following switch gears including supply
of all components, hard wares etc
including all necessary civil works,
adequate reinforcement foundation bolts
suitable G.I earth strip , 100 x 50mm MS
base channel, earth bar,
door loop
earthings
.
Bus
bar
to
switch
interconnections,

3
1
1
0
2
0
0
6

All cables shall have proper cable


entry,gland plates, suitable size of
glands, earth tags for glands, lugs,
cadmium plated nuts , bolts, feeder
identification marks, shall be installed on
performed trench and consisting of the
following as required and as per IS
standards
and
panel
should
be
manufactures only from panel builds with
CPRI Test certificate.
250 A Aluminium Bus Bar with colour
code.
Internal wiring with approved make cable
Earthing: Providing 50x6 mm G.I flat
Incommer: .
elec-2.1.5 250A TPN switchs with fuse L&T make.- 1
No.
elec-2.5.4 250A HRC Fuse links
Metering Set:
elec-6.3.3 0- 250 A Digital Ammeter . - 1 No.
elec-6.3.8 Ammeter selector switch - 1 No.
elec-6.3.1 0-500V Digital Volt meter - 1 No.
elec-6.3.8 Voltmeter selector switch - 1 No.
elec-6.3.9 R, Y, B Indication lamps LED type, puse
buttons.
elec-6.3.10 250 /5A C.T coils : 2 sets

207 of 517

8740

8740

363

1089

1
1
1
1
3

2500
175
2500
175
135

2500
175
2500
175
405

450

2700

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
elec-2.6.1 32A 240 V Porcelain Rewirable fuse units
- 3 Nos.
elec-2.5.1 upto 32A HRC fuse link - 3 Nos:
Outgoing :
elec-2.1.2 63A TPN SFU -10 NOS - L&T Make

99
50

10

2329

Sub TOTAL:
Bus bars and insulators 25%
Cost of enclosure @ 45%

41871
10467.75
18841.95

Bus bars and insulators 10%

4187.10

Control wiring, Labour charges for Job


errection of switch gear, panel board
including all labour charges etc complete
with connections for finished item of
work
including
transportation
charges.5%
L.S Towards unforseen items and
rounding off
Add contr profit @14% on material
Total material cost
26

3
1
297 1
0
02
0
0
23290 6

Quanti Rate Rs. Amount


ty
Rs.

2093.55

628.07
78089.42
0.00
78089.45

0.00

Providing independent earthling by


excavating a trench to a depth of 2.1 M
in all soils, as per size specified in the
Data, using 40mm dia 'B' class GI pipe of
2.5
Mtrs
length
with
necessary
accessories with hume pipe ring duly
providing staggered holes
including
filling with equal proportion of Salt and
Charcoal in layers and all labour charges
etc., complete for small quarters.

a) Material
elec.8.1.52 Earth Work Excavation of Hard gravel
Soil with small boulder for trench 1st
step of size 1.5 x 0.6 x 0.9 m
Excavation of Hard disteggrated rocks
and boulders for trench 2nd Step of size
1.2 x 0.6 x 1.2 m (Civil SSR)

cum

0.85

0.00

0.00

cum

0.9

0.00

0.00

0.00

0.00

2.5
1

355.00
75.00

25% extra for narrow trench & pit and


back filling with Sand, Coke, Salt etc.,
and leveling
elec.8.1.58 40mm dia 'B' Class G.I pipe
Mtr
25 x 6 mm (1"X 1/4") G.I Flat duly Each
drilled 12mm holes (4 Nos) of 200 mm
(8") length

208 of 517

887.50
75.00

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
elec.8.1.59 Drilling of 16 Nos through holes of 12mm Each
dia to G.I pipe
elec-8.1.12 G.I Nuts, Bolts an Washers
elec.8.1.61 18" dia hume pipe ring
elec-8.1.13 Hard Coke
elec-8.1.14 Salt

Set
Each
Kg
Kg

16

6.00

4
1
40
20

13.00
220.00
9.00
4.00

0.5
0.5

375.00
375.00

Add contr profit @14% on material


0.00
Total material cost
b) labour charges for fixing pipe Each
ring and connections
elec-8.1.75 Semi skilled Electrician
elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Sundries
Rate per each

Nos
Nos
0%
0%

375.00

Say
27

3
1
96.00 1
0
52.00 2
220.00 0
0
360.00 6

Quanti Rate Rs. Amount


ty
Rs.

80.00
1770.50
0.00
1770.50

187.50
187.50
0.00
0.00
2145.50
2145.50

Supply and Run of No.8 SWG G.I wire


including cost of all accessories and
labour charges etc., complete.

a) Material
elec-8.1.45 No.8 SWG G.I wire 100 M Length (0.104
Kg / Mtr)
elec-8.1.07 U' Nails

Add contr profit @14% on material


Total for material
b) labour charges
elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
C) Cost for 100 M
Rate per mtr c/100

209 of 517

Kg

10.4

68.00

707.20

100No
s

1.5

44.00

66.00
773.20
0.00
773.20

0.00

day
0%
0%

375.00

750.00

750.00
0.00
0.00
1523.20
15.25

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
28
Supply, Transportation and fixing of 4' of
1x 36/ 40 Watt Box type Tube Light
luminaire powder coated CRCA sheet
steel housing with
electronic ballast
suitable for 40 Watt tube including all
labour charges for fixing fitting on
varnished teak wood round blocks with
flexible 3 core wire etc.,, complete with
all connections including cost of 40W
tube.
Makes:
Surya /
Havells / HPL /
Fortune Art
a) Material
elec-3.6.5 4' x 40 watts box type flourscent light
fitting.
elec-3.7.16 Lamp cost of 40W
elec-8.1.31 Tw Round blocks
Elec-1.4.34 screws with rawal plugs
Elec-1.6.8 23/0060 twin core flexible copper cable
Rate per each
Add contr profit @14% on material
Total for material

Quanti Rate Rs. Amount


ty
Rs.

each

each
each
each
M

1
2
2
1.5

1060.00
45.00
7.00
0.00
0.00

0.00

a) Labour charges
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Rate per each
Fixing of 40W tube light luminaire on wall
/ Ceiling with TW round blocks with
all
accessories
including
giving
connections and all labour charges etc.,
complete.
Rate per each
a) Material
Elec-1.6.8 23/0060 twin core flexible copper cable
M
Elec-1.4.34 screws with rawal plugs
each
Elec-8.1.35 T.W round blocks
each
Cement and sand etc.,
LS

0.1
0.1

480
375
85.50

3
1
1
0
2
0
0
6

1060.00
45.00
14.00
0
0
1119.00
0.00
1119.00
48.00
37.50
0.00
0.00
1204.50

7.9.3

Add contr profit @14% on material


0.00
Total for material
b) Labour charges :
elec-8.1.74 Skilled Electrician/carpenter
day
elec-8.1.75 Semi skilled Electrician / Helper
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%

210 of 517

1
2
2
5.6

0.1
0.1

1040.00
54.00
7.00

480
375
85.50

10.4
1.08
14
2.11
27.59
0.00
29.70
48
37.5
0.00
0.00

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

3
1
115.20 1
0
2
0
0
6

Quanti Rate Rs. Amount


ty
Rs.

Rate per each


Note : 1. The Cost of Ceiling Rose may
be deducted in view of holder.
Note : Labour Charges considered for 10 fixtures
/ day .

29

Supply and fixing of batten holder /


slanting holder in lieu of ceiling rose of
light point complete with all connections
and all labour charges with 13w CFL
lights (for new installation).
Makes : Gold Medal Olive /Million Zoom /
Anchor Penta Cherry

Taking Output = each


a) Material
elec-1.7.15 PVC batten holder
elec-3.7.1 13w CFL lights
elec-1.7.13 Deduct Cost of Ceiling Rose

each
each
each

Add contr profit @14% on material


0.00
Total for material
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Rate per each
Note : 1. The Cost of Ceiling Rose may
be deducted in view of holder.

1
1
1

20.00
110.00
21.00

20.00
110.00
-21.00
109.00
0.00
109.00

0.05
0.05

480
345

24.00
17.25
0.00
0.00
150.25

39.25

2. Labour Charges proposed for 20 jobs per day

30

Supply and fixing of call bell on 6"x8"


decolam
block
including
giving
connections, cost of all accessories and
labour charges etc., complete. Make :
Anchor/Goldmedal/Million / Million /
Vimal / Maru

Taking Output = each


a) Material
elec-1.7.20 Call bell
elec-1.4.11 8"x6" decolam block

each
each

Add contr profit @14% on material


Total for material

211 of 517

0.00

1
1

102
44

102.00
44.00
146.00
0.00
146.00

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

b) Labour charges :
elec-8.1.74 Skilled Electrician
elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Rate per each

31

day
day
0%
0%

0.062
0.062

480
345
51.15

197.15

Supply and fixing of Ding dong on 6"x8"


decolam
block
including
giving
connections, cost of all accessories and
labour charges etc., complete. Make :
Anchor/Goldmedal/Million / Million /
Vimal / Maru

Taking Output = each


a) Material
elec-1.7.22 Ding dong bell
elec-1.4.11 6"x8" decolam block

each
each

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Rate per each
32

3
1
1
0
29.76 21.39 2
0
0.00 0
0.00 6

Quanti Rate Rs. Amount


ty
Rs.

1
1

102
39.6

102
39.6
141.6
0.00
141.6

0.062
0.062

480
345

29.76
21.39
0.00
0.00
192.75

51.15

Supply of 1200 mm (48") sweep ISI mark


ceiling Fan as per IS 374- 1979 and
operating on 230V, A.C 50 Hz.Ceiling fan
with 3 Blades and double ball bearings
with all standard accessories. Brown
color
Makes: Crompton / Bajaj Kassels 50
/ Usha Atom

a) Material
elec-5.1.1 1200 mm (48") Ceiling Fan
Transportation Charges on Unit Cost
Add contr profit @14% on material
Total material cost

212 of 517

each

0.00

1
1%

1600.00
16.00

1600
16.00
1616.00
0.00
1616.00

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
33
Supply and erecting Electronic
type
regulator for ceiling fans 1200 mm
sweep complete erected on existing
board.Make : Anchor Penta Cherry / Gold
Medal Olive / Million Zoom
a) Material
elec-1.7.12 Steeped type Electronics type Regulator
M
Add contr profit @14% on material
0.00
Total material cost
b) Labour charges.
elec-8.1.75 Semi skilled Electrician
day
Sundries.
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Rate per Each
Note : Labour is Considered for 10
jobs / day
34

220.00

220.00
0.00
220.00

0.1

375.00

37.50
21.20
0.00
0.00
278.70

58.70

3
1
1
0
2
0
0
6

Labour Charges
Labour charges for Fixing of Ceiling fan
and regulator including transportation
and giving connections with twin core
wire etc., complete.

a) Material
elec-1.6.8 23/0060 Twin Core wire
100 M
Unforseen item works, such as painting LS
to down rod, screws etc.,
Add contr profit @14% on material
0.00
Total for material
b) Labour charges.
elec-8.1.75 Skilled Electrician
day
elec-8.1.82 Helper
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Rate per Each
Note : Labour is Considered for 8
fans / day
35

Quanti Rate Rs. Amount


ty
Rs.

1
1

1040.00
3.00

1040.00
3.00
1043.00
0.00
1043.00

0.125
0.125

440.00
345.00
98.13

55.00
43.13
0.00
0.00
1141.13
142.64

Supply of fresh air exhaust fan of heavy


duty 250V A.C.50Hz.. 300mm size (12")
900 R.P.M etc., complete.
Makes: CG / Almounard / Havells Turbo
Force

213 of 517

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

a) Material
elec-5.1.11 300mm (12") 1350 RPM H.D. Exhaust each
Fan
Transportation Charges on Unit Cost
Rate per Each
Add contr profit @14% on material
0.00
Total for material
35

1
1%

2645.00
26.45

2671.45

Supply of fresh air exhaust fan of heavy


duty 250V A.C.50Hz.. 300mm size (12")
900 R.P.M etc., complete.
Makes: CG / Almounard / Havells
Turbo Force

a) Material
elec-5.1.13 300mm (12") 900 RPM H.D. Exhaust Fan 100 m
Transportation Charges on Unit Cost
Rate per Each
Add contr profit @14% on material
0.00
Total for material
36

3
1
1
0
2645.00 26.45 2
0
2671.45 0
0.00 6

Quanti Rate Rs. Amount


ty
Rs.

1
1%

2645.00
26.45

2645.00
26.45
2671.45
0.00
2671.45

1
1

1040.00
6.60

1040.00
6.60
1046.60
0.00
1046.60

0.25
0.25
0.25

440.00
345.00
385.00

292.50
24.34

110.00
86.25
96.25
0.00
0.00
24.34
1363.44
227.24

Labour charges for fixing of Exhaust fan


in wall with necessary connections and
masonary work of making hole, finishing
etc., complete

a) Material
elec-1.6.8 23/0060 Twin flat wire
elec-8.1.50 Cement

100 M
kg

Add contr profit @14% on material


0.00
Total for material
b) Labour charges.
elec-8.1.74 Skilled Electrician
day
elec-8.1.82 Helper
day
elec-8.1.76 Mason
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as Sand, Bolt, Nuts etc.,
LS
Rate per Each
Note :1. Labour is Considered for 6
jobs / day
2. Cost of louver shutter may be added if
required.
3. If hole is already made available,
labour charges of Mason
shall be
deleted.

214 of 517

Ele-Data

Index Specific
-code
ation
No.
37

Description

Unit

Supply
of
1x40W
weather
proof
flourescent streetlight fitting comprising
canopy of sheet Aluminium in stove
enamel finish with copper / VPIT ballast,
capacitor,
tube
and
starter
etc.,
complete.
Makes: Phillips / GE / Wipro

a) Material
elec-3.1.1 1x40W WP flourscent street light fitting.
elec-3.7.7 Lamp cost of 40W
Add contr profit @14% on material
Total for material
38

each
each

1
1

1400.00
45.00

1
10
1
1

226.00
10.40
25.00
35.00

226.00
104.00
25.00
35.00
390.00
0.00
390.00

0.2
0.2
0.2

440.00
385.00
345.00

88.00
77.00
69.00
0.00
0.00
624.00

0.00

3
1
1
0
2
0
0
6

1400.00
45.00
1445.00
0.00
1445.00

Fixing of 40W street light luminaire to


the wall with 1.0 Mtr., 25mm dia GI pipe
bracket and anti tilting MS flat etc.,
including giving connections and labour
charges etc., complete.

a) Material
elec-8.1.55 25mm dia G.I pipe light grade
elec-1.6.8 23/0060 twin core flexible copper cable
Pipe bending charges
M.S flat and welding charges

M
M
LS
LS

Add contr profit @14% on material


0.00
Total for material
b) Labour charges
elec-8.1.74 Skilled Electrician/carpenter
day
elec-8.1.76 Mason
day
elec-8.1.75 Semi skilled Electrician / Helper
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Rate per each
Note : Labour Charges considered for 5
fixtures / day .

39

Quanti Rate Rs. Amount


ty
Rs.

234.00

Supply of Integral street light luminaire


of 150W HPSV lamp fitting comprises of
single piece die cast Aluminium body
with copper wound ballast and capacitor,
Ignitor, with pot optics including 150W
HPSV lamp etc., complete.
Makes: Phillips / GE /Wipro / Bajaj /
Crompton

215 of 517

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

a) Material
elec-3.1.7 150W HPSV Lamp fitting single piece die each
cast Aluminium body with copper wound
ballast and capacitor, Ignitor, with pot
optics

elec-3.4.10 150W HPSV lamp

40

5327.00

710.00

1
4

355.00
25.10

LS

25.00

day
day
day
day
0%
0%

0.25
0.25
0.25
0.25

440.00
385.00
345.00
385.00

0.00

710.00
6037.00
0.00
6037.00
6037.00

Fixing of MV / SV/MH luminaire on wall


with 1.0mt 40mm dia GI pipe bracket
and anti-tilting MS flat, 2.5 Sq.mm
flexible copper cable etc.,including all
labour charges for mason work and
giving connections etc., complete.

a) Material
elec.8.1.57 40mm G.I pipe for Bracket
elec.1.5.3 2.5 Sq.mm flexible copper cable

M
M

Add contr profit @14% on material

0.00

Pipe bending charges


b) Labour charges for Antitiling MS
flat / welding charges & fixing
elec-8.1.74 Skilled Electrician
elec-8.1.83 Carpenter
elec-8.1.82 Helper
elec.8.1.78 Welder
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Rate per each
Note : Labour Charges considered for 4Nos

41

each

Add contr profit @14% on material


Total for material
Rate per each

3
1
1
0
5327.00 2
0
0
6

Quanti Rate Rs. Amount


ty
Rs.

278.75

MV / SV

Say

355.00
100.40
455.40
0.00
455.40
25.00

110.00
96.25
86.25
96.25
0.00
0.00
869.15
869.15

Supply and laying of 2 pair telephone


wire in the existing metallic/non metallic
conduit
pipe
with
connections
etc.,complete
Makes: Million / Finolex / Delton / Surabi
/ Polycab / Nakoda

Taking Output = 100 M


a) Material
elec-7.1.1 2 pair telephone wire
Add contr profit @14% on material

216 of 517

100 M
0.00

1010.00

1010.00
0.00

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

Total for material


b) Labour charges :
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi Skilled Electrician
elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Sundries

day
day
day
0%
0%

0.34
1
0.34

440.00
375.00
345.00
641.90

C) Cost for 100 RM


Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day

Supply and fixing of telephone jack type


socket with top on MS box with modular
plate cover with screws connections etc.,
Makes: Gold Medal Olive / Million
zoom
Taking Output = 100 M
a) Material
elec-1.7.16 telephone jack type socket
elec-1.3.1 MS box
elec-1.4.1 4x4 sunglass delux board

3
1
1010.00 1
0
149.60 2
375.00 0
0
117.30 6

Quanti Rate Rs. Amount


ty
Rs.

0.00
0.00

1651.90
16.55

42

Add contr profit @14% on material


0.00
Total for material
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries
C) Cost for each
42 (a)
elec-7.1.9 Supply of 3 feet length patch cords of
make D link make / Beldan / Krone
43

1
1
1

48.00
57.00
14.00

0.1
0.1
0.1

440.00
375.00
345.00
116.00

48.00
57.00
14.00
119.00
0.00
119.00
44.00
37.50
34.50
0.00
0.00
235.00

200.00

2580.00

200.00

Supply and laying of LAN cable Cat-6(A)


UTP CABLE in the existing metallic/non
metallic conduit pipe with connections
etc.,complete
Makes:D Link/ AMP /Molex

Taking Output = 100 M


a) Material
elec-7.1.3 cat-6 (A) UTP LAN cable

100 M

217 of 517

2580.00

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

Add contr profit @14% on material


0.00
Total for material
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
0.34
elec-8.1.75 Semi Skilled Electrician
day
1
elec-8.1.82 Helpers
day
0.34
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
44

440.00
375.00
345.00
641.90

117.30
0.00
0.00
3221.90
32.25

Supply and fixing of


cat-6 RJ45information outlets including dual face
plate with MS box with modular plate
cover with screws connections etc.,
Makes: Belden/D link/Legrand

a) Material
elec-7.1.4 cat-6 RJ 45 information oulet
elec-1.3.1 MS box

Add contr profit @14% on material


0.00
Total for material
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries
C) Cost for each
45

3
1
0.00 1
0
2580.00 2
0
149.60 0
375.00 6

Quanti Rate Rs. Amount


ty
Rs.

1
1

340.00
57.00

340.00
57.00
0.00
397.00
0.00
397.00

0.2
0.2
0.12

440.00
375.00
345.00

88.00
75.00
41.40
0.00
0.00

204.40

601.40

Supply and laying of lan cable cat-6 UTP


cable in the existing metallic/non
metallic conduit pipe with connections
etc.,complete
Makes:
AMP/D-LINK/MOLEX/LEGRAND/KRONE.
Taking Output = 100 M
a) Material

100 M
0.00

ELEC-7.1.3 RG6 lan cable cat-6 UTP cable


Add contr profit @14% on material
Total for material

218 of 517

2580.00

2580.00
0.00
2580.00

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

b) Labour charges :
elec-8.1.74 Skilled Electrician
day
0.34
elec-8.1.75 Semi Skilled Electrician
day
1
elec-8.1.82 Helpers
day
0.34
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
46

440.00
375.00
345.00
641.90

0.00
3221.90
32.25

Supply and fixing of TV antenna outlet


with MS box with cover with screws
connections etc., Makes: Goldmedal
olive/Million
zoom/Vimal
opel/Maru
montero/Anchor

a) Material
elec1.7.17 TV socket outlet
elec-1.3.1 MS box
elec-1.4.3 6" X 6" sunglass delux board
Add contr profit @14% on material
0.00
Total for material
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries
C) Cost for each
21

3
1
1
0
149.60 375.00 2
0
117.30 0
0.00 6

Quanti Rate Rs. Amount


ty
Rs.

1
1
1

26.00
63.00
25.00

0.04
0.04
0.04

440.00
375.00
345.00
46.40

26.00
63.00
25.00
114.00
0.00
114.00
17.60
15.00
13.80
0.00
0.00
160.40

Supply and fixing of 24 port switches of


D link/ AMP/ Krone make including
making connections and etc., complete

24 switch
Taking Output = each
a) Material
elec-7.1.5 24 port switch

each
each
each

Add contr profit @14% on material


Total material cost
b) Labour charges :

219 of 517

0.00

5200.00

5200.00
0.00
0.00
5200.00
0.00
5200.00

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as TW Plugs, Screws LS
Cement etc,

1
1
1

440.00
375.00
345.00
1160.00
14.00

Rate per each


Note : Labour Charges considered for 2 jobs / day
21

3
1
440.00 1
0
375.00 345.00 2
0.00 0
0
0.00 6

Quanti Rate Rs. Amount


ty
Rs.

14.00
6374.00

Supply of 17U floor mounting net work


rack with power spike including all
accessries of make HCL / Vall

24 switch
Taking Output = each
a) Material
elec-7.1.24 17U floor mounting rack

each
each
each

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as TW Plugs, Screws LS
Cement etc,

10125.00

1
1
1

440.00
375.00
345.00
1160.00
14.00

Rate per each


Note : Labour Charges considered for 2 jobs / day

10125.00
0.00
0.00
10125.00
0.00
10125.00
440.00
375.00
345.00
0.00
0.00
14.00
11299.00

Supply of 95 Sq. mm 3.5 Core XLPE


insulated 1100 Volts grade armoured
alluminium cable as per specification
confirming of IS 7098 (Part - I) conductor
complete
Make:
PolyCab / RPG / Finolex /
Havells / Paragon / V- Guard /
Fortune Art / Gloster / Suncab
elec-4.1.32 3.5 Core 95.00 Sq.mm.
Add contr profit @14% on material
Total for material

220 of 517

Rmt
0.00

547.00

547.00
0.00
547.00

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

Quanti Rate Rs. Amount


ty
Rs.

Supply of 50 Sq. mm 3.5 Core XLPE


insulated 1100 Volts grade armoured
alluminium cable as per specification
confirming of IS 7098 (Part - I) conductor
complete
Make:
PolyCab / RPG / Finolex /
Havells / Paragon / V- Guard /
Fortune Art / Gloster / Suncab

elec-4.1.26 3.5 Core 50.00 Sq.mm.


Add contr profit @14% on material
Total for material

Rmt
0.00

326.00

326.00
0.00
326.00

Rmt
0.00

347.00

347.00
0.00
347.00

Rmt
0.00

207.00

207.00
0.00
207.00

Rmt
0.00

162.00

162.00
0.00

3
1
1
0
2
0
0
6

Supply of 35 Sq. mm 3.5 Core XLPE


insulated 1100 Volts grade armoured
alluminium cable as per specification
confirming of IS 7098 (Part - I) conductor
complete
Make:
PolyCab / RPG / Finolex /
Havells / Paragon / V- Guard /
Fortune Art / Gloster / Suncab
elec-4.1.23 3.5 Core 35.00 Sq.mm.
Add contr profit @14% on material
Total for material
Supply of 25 Sq. mm 3.5 Core XLPE
insulated 1100 Volts grade armoured
alluminium cable as per specification
confirming of IS 7098 (Part - I) conductor
complete
Make:
PolyCab / RPG / Finolex /
Havells / Paragon / V- Guard /
Fortune Art / Gloster / Suncab
elec-4.1.20 3.5 Core 25.00 Sq.mm.
Add contr profit @14% on material
Total for material
Supply of 16 Sq. mm 4 Core XLPE
insulated 1100 Volts grade armoured
alluminium cable as per specification
confirming of IS 7098 (Part - I) conductor
complete
Make:
PolyCab / RPG / Finolex /
Havells / Paragon / V- Guard /
Fortune Art / Gloster / Suncab
elec-4.1.17 4.0 Core 16.00 Sq.mm.
Add contr profit @14% on material

221 of 517

Ele-Data

Index Specific
-code
ation
No.

48

3
1
Total for material
162.00 1
0
2
0
Earth work excavation of Trench in hard ground soil, laying of U.G cables from 70 0sqm to 400
6

Description

Unit

a) Material
elec-8.1.52 Excavation of earth 100 x 0.3 X 0.9 m
elec-8.1.54 Cost of bricks (Civil SSR)

Quanti Rate Rs. Amount


ty
Rs.

cum
1000
Nos

1
1

110.00
5427.01

110.00
5427.01

cum
Kg
each

1
25
12

924.09
5.81
83.00

924.09
145.25
996.00
7602.35
0.00
7602.35

2.5

320.00

800.00

elec-8.1.74 Skilled Electrician


day
1
480.00
elec-8.1.81 Helper
day
2
375.00
elec-8.1.84 Man Mazdoor for concreting and embeddingday
of cable 2
way indicators
320.00

480.00
750.00
640.00

elec-8.1.53 Cost of sand (Civil SSR)


elec-8.1.50 Cement (Civil SSR)
elec-8.1.27 Cost of cable route indicator

Add contr profit @14% on material


0.00
Total for material
b) Labour charges for laying cable.
elec-8.1.84 Man Mazdoor for spreading the sand and each
back filling the excavated soil.

Add area allowence on labour


charges
Add contr@
profit @14% on Labour
Sundires and Rounding off
Rate per 100mts
Rate per Mtr
48

0%
0%

1870.00

0.00
0.00
10272.35
102.75

Earth work excavation of Trench in hard ground soil, laying of U.G cables upto 50 Sq,mm on s

a) Material
elec-8.1.52 Excavation of earth 100 x 0.3 X 0.9 m
elec-8.1.54 Cost of bricks (Civil SSR)

222 of 517

cum
1000
Nos

1
1

110.00
5427.01

110.00
5427.01

Ele-Data

Index Specific
Description
-code
ation
No.
elec-8.1.53 Cost of sand (Civil SSR)
elec-8.1.50 Cement (Civil SSR)
elec-8.1.27 Cost of cable route indicator

Unit
cum
Kg
each

Add contr profit @14% on material


0.00
Total for material
b) Labour charges for laying cable.
elec-8.1.84 Man Mazdoor for spreading the sand and each
back filling the excavated soil.

3
1
924.09 1
0
145.25 996.00 2
0
7602.35 0
0.00 6

Quanti Rate Rs. Amount


ty
Rs.
1
25
12

924.09
5.81
83.00

7602.35
320.00

800.00

elec-8.1.74 Skilled Electrician


day
1
480.00
elec-8.1.81 Helper
day
2
375.00
elec-8.1.85 Man Mazdoor for concreting and embeddingday
of cable 2
way indicators
320.00

480.00
750.00
640.00

Add area allowence on labour


charges
Add contr@
profit @14% on Labour
Sundires and Rounding off
Rate per 100mts
Rate per Mtr

2.5

0%
0%

1870.00

0.00
0.00
10272.35
102.75

49

Labour charges for run of U.G cable on


wall / existing pipe with necessary fixing
arrangments
such
as
saddles,
clamps,wooden separators etc., (as
directed by departmental official) with
No.10 SWG G.I wire for eath connections
for the cables.
a) Material
elec-8.1.8 Wooden separators
each
elec-1.1.38 saddles of required size
100
nos
elec-1.4.34 12mm screws
elec-8.1.45 No.10 SWG GI wire

100
2

165.00
446.00

100
nos

59.00

236.00

kg

68.00

476.00
18104.00
0.00
18104.00

1
4

480.00
375.00

480.00
1500.00
0.00
0.00
21.00
20105.00
201.05

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges
elec-8.1.74 Skilled Electrician
day
elec-8.1.82 Helper
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundires such as Cement, Sand etc.,
Rate per Each
Note : Labour Charges Considered
for 100 Mts / day

223 of 517

1980.00

16500.00
892.00

Ele-Data

Index Specific
-code
ation
No.
50

Description

Unit

Quanti Rate Rs. Amount


ty
Rs.

Supply and Fixing of 3 phase meter Box,


3 Nos 100 A fuse units, Neutral link, on
T.W block with all accessaries etc.,
complete for finished items of work.

a) Material
elec-2.6.4 100 A Fuse units
100 A neutral links
elec-1.4.31 T.W blocks ( 12" x 15" )

each
each
each

Add contr profit @14% on material


0.00
Total for material
b) Labour charges
elec-8.1.74 Skilled Electrician
day
elec-8.1.82 Helper
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundires such as Cement, Sand etc.,
Rate per Each
52
Supply and erecting ISI Mark 25 Ltrs
Water heater with multiple safety
system, rust free ABS plastic body,
230V, 50Hz.., A.C. supply with inlet and
outlet connections with pvc/ nylon /
metallic hose pipe, thermostat control
and thermal cutoff with 3 core P.V.C.
flexible wire leads duly tested including
cost of all materials and all labour
charges etc., complete.
Make: VENUS / RACOLD / BAJAJ / USHA
a) Material
elec-5.2.2 25 ltr water heater
transportation charges on unit cost
elec-5.3.4 Hose pipe PVC/Nylon

each
nos

Add contr profit @14% on material


0.00
Total for material
b) Labour charges
elec-8.1.74 Skilled Electrician
day
elec-8.1.82 Helper
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundires such as anchor bolts ,gutties etc.,

224 of 517

3
1
1

484.00
118.00
109.00

1452.00
118.00
109.00
1679.00
0.00
1679.00

1
4

480.00
375.00

480.00
1500.00
0.00
0.00
50.00
3709.00

1980.00

1
2%
2

10438.00

0.25
0.25

480
375

158.00

213.75

3
1
1
0
2
0
0
6

10438.00
208.76
316.00
10962.76
0.00
10962.76
120.00
93.75
0.00
0.00
25.00
11201.55

Ele-Data

Index Specific
Description
-code
ation
No.
54
Supply and fixing of concealed box
PVC/MS with hook for fan

Unit

A.Material
elec-8.1.25 Fan hook box
each
Add contr profit @14% on material
0.00
Total for material
b) Labour charges
elecSkilled Electrician
day
8.1.74
elecHelper
day
8.1.82 Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Rate for each

3
1
1
0
2
0
0
88.00 6

Quanti Rate Rs. Amount


ty
Rs.

88.00

0.00
88.00
0.05
0.05

480.00
375.00
42.75

24.00
18.75
0.00
0.00
130.75

Standard Data - Electrical Items For External electrification


Specificat
ion No.

Description

Unit

Supply, fabrication of 175x85 ISMB RS


Joist for single pole (box type)structure
for
transformer
with
support
angles,mounting clamps,hardwares etc
with one coat of red-oxide primer with
two coats of aluminium enamel paint
complete for finished item
a.Material
Elec-6.5.15 175x85 RS joist (each 9.5mtr @19.6 kg
per mtr) 2 lengths for box type

Quanti Rate Rs. Amount


ty
Rs.

kg

372.4

50.00

18620.00

Elec8.1.29

Base
plate
600x600x8mm
plate(@62.80 kg /sq mtr)

MS

kg

37.68

61.00

2298.48

Elec8.1.29

100x50 ISMC cross arms for mounting


11KV insulators(@9.56kg/mtr-5mtr

kg

47.8

61.00

2915.80

Elec8.1.29
Elec8.1.29

Clamps of 50x6 ms flat(@3,85kg/mtr


Support cleets of35x35x6 L angle@3
kg /mtr

kg
kg

12
15

61.00
61.00

732.00
915.00

Elec8.1.29

Support angles of 50x 50x6 L angle@4.5


kg/mtr- 3mtr

kg

13.5

61.00

823.50

Total Ms items
Add wastage @ 3%
Total weight

Kg

61.00
61.00

kg

498.38
14.951
513.33

30401.18
912.04
57618.00

Fabrication charges
Total cost for ms items
Add contr profit @14% on material

LS

513.3

9.00

4619.70
62237.70
0.00

225 of 517

0.00

3
1
1
0
2
0
0
6

Ele-Data

Index Specific
-code
ation
No.

Elec8.1.74
Elec8.1.82
Elec8.1.76
Elec8.1.85

Description

Unit

Total cost for single pole(box type)


Total cost for single pole(box type)
B.Labour charges
Skilled Electrician
Helper
Mason for concreting and coping
Man mazdoor for concreting
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Rate for sinple pole structure

day
day
day
day
0%
0%

Supply and erecting porcelain disc type


insulatorsuitable for 11KV line with
suitable hardware in the existing cross
arm
elec- 6.5.2 11KV disc insulator
each
Add contr profit @14% on material
0.00
Total for disc insulator

3
1
62237.70 1
0
2
0
880.00 0
1380.00 6

Quanti Rate Rs. Amount


ty
Rs.

2
4
2
2

440.00
345.00
385.00
295.00
2740.00

770.00
590.00
0.00
0.00
65857.70

600.00

600.00
0.00
600.00

300.00

300.00
0.00
300.00

Each
0.00

1500.00

1500.00
0.00
1500.00

each
0.00

5900.00

5900.00
0.00
5900.00

Supply and erecting porcelain pin type


insulatorsuitable for 11KV line with
suitable hardware in the existing cross
arm
elec-6.5.3 11kv pin insulator
each
Add contr profit @14% on material
0.00
Total for pin insulator
4

Supply and erecting


approved make
11KV 5KA metal oxide lightning arrester
suitable for 11KV line with suitable
hardware in the existing cross arm

elec-6.5.1 lightning arrester


Add contr profit @14% on material
Total for lightning arrestor
5

Supply and erecting approved make


11KV 200A AB switch(tilting) with all
accessories etccomplete with cost and
conveyance of all materials

elec-6.5.9 200A AB switch


Add contr profit @14% on material
Total for AB switch
6

Supply and erecting approved make


11KV HG fuse set with all accessories
etccomplete with cost and conveyance
of all materials

226 of 517

Ele-Data

Index Specific
Description
-code
ation
No.
elec-6.5.10 HG fuse set
Add contr profit @14% on material
Total for AB switch

Unit
each
0.00

3
1
4000.00 1
0
0.00 4000.00 2
0
0
6

Quanti Rate Rs. Amount


ty
Rs.
1

4000.00

658.00

658.00
0.00
658.00

2.5

280.00

700.00

Skilled Electrician
day
1
400.00
Helper
day
2
320.00
Man Mazdoor for concreting and embeddingday
of cable 2
way indicators
280.00

400.00
640.00
560.00

Supply fixing of 150 sqmm 3.5core XLPE


PVC
armoured
alluminium
cable
including trench works as per standards
of Make:
PolyCab / RPG / Finolex /
Havells / Paragon / V- Guard / Fortune Art
/ Gloster / Suncab

a) Material
elec-4.1.38 3.5corex150 sqmm cable
Rmt
Add contr profit @14% on material
0.00
Total for 150 sqmm cable
b) Labour charges for laying cable.
Man Mazdoor for spreading the sand and each
back filling the excavated soil.

Add area allowence on labour


charges
Add contr@
profit @14% on Labour
Sundires and Rounding off
Rate per 100mts
Rate per Mtr
Total for supply and laying

227 of 517

0%
0%

1600.00

0.00
0.00
5.00
2305.00
23.05
681.05

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
8
Supply, installation,and commissioning
of 3Phases and neutral 415V,
free
standing type cubical panel board made
of 16 Gauge CRCA sheet steel, panel
shall be painted after processing 7 tank
process with RAL 7032 siemens grey. The
panel shall be consisting of suitable
rating of allumunium bus bars ( At the
rating of 0.8 A/Sq.mm) supported with
DMC/SMC and colour coded with heat
shrinkable sleeves. The bus bars fault
level shall be 50 KA and shall be as per
the requirement of local CEIG, fire
regulations, other authorities etc. The
panel shall be suitable for accomdating
the following switch gears including
supply of all components, hard wares etc
including all necessary civil works,
adequate reinforcement foundation bolts
suitable G.I earth strip , 100 x 50mm MS
base channel, earth bar,
door loop
earthings
.
Bus
bar
to
switch
interconnections,

Quanti Rate Rs. Amount


ty
Rs.

3
1
1
0
2
0
0
6

All cables shall have proper cable


entry,gland plates, suitable size of
glands, earth tags for glands, lugs,
cadmium plated nuts , bolts, feeder
identification marks,shall be installed on
performed trench consisting of the
following as required and as per IS
standards
and
panel
should
be
manufactures only from panel builds with
CPRI Test certificate.
400A Aluminium Bus Bar with colour
code.
Internal wiring with approved make cable
Earthing: Providing 50x6 mm G.I flat
Incommer: .
elec-2.8.15 400A TPN 50 KA MCCB Legrand make.- each
1 No.
elec-6.3.3
elec-6.3.8
elec-6.3.1
elec-6.3.8
elec-6.3.9
Elec6.3.10

Metering Set:
0- 400 A Digital Ammeter . - 1 No.
Ammeter selector switch - 1 No.
0-500V Digital Volt meter - 1 No.
Voltmeter selector switch - 1 No.
R, Y, B Indication lamps LED type, puse
buttons.
400 /5A C.T coils : 2 sets
20A Bakelite fuse fittings - 3 Nos.
2A HRC fuse link - 3 Nos:

228 of 517

each
each
each
each
each

22890.00

22890.00

1
1
1
1
3

2500.00
175.00
2500.00
175.00
135.00

2500.00
175.00
2500.00
175.00
405.00

6
3
3

450.00
130.00
45.00

2700.00
390.00
135.00

Ele-Data

Index Specific
Description
-code
ation
No.
ElecAPFC relay 8 stage.
6.3.13 Outgoing :
elec-2.8.14 250A 25KA MCCB-02 NOS -Legrand Make
elec-2.8.13 125A 25KA MCCB-02 NOS -Legrand Make
elec-2.8.12 63A 25KA MCCB -04 NOS - Legrand Make

Unit

13600.00

each
each

1
4

18010.00
6322.00

each

5668.00

Bus bars and insulators 10%


Cost of enclosure @ 45%
Control wiring, Labour charges for
errection of switch gear, panel board
including all labour charges etc complete
with connections for finished item of
work
including
transportation
charges.5%
Add contr profit @14% on material
0.00
Total cost of panel board
b)labour charges
elec-8.1.74 Skilled electrician
day
elec-8.1.75 semi skilled electrician
day
elec-8.1.82 helper
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Total
cost
of
panel
board(supply&erection)
9

3
1
13600.00 1
0
2
18010.00
0
25288.00 0
6

Quanti Rate Rs. Amount


ty
Rs.

22672.00
0.00
111440.00
11144.00
50148.00
5572.00

178304.00
0.00
178304.00
1
2
4

440.00
345.00
345.00
2510.00

440.00
690.00
1380.00
0.00
0.00
###

Providing independent earthling by


excavating a trench to a depth of 2.1 M
in all soils, as per size specified in the
Data, using 40mm dia 'B' class GI pipe of
2.5
Mtrs
length
with
necessary
accessories with hume pipe ring duly
providing staggered holes
including
filling with equal proportion of Salt and
Charcoal in layers and all labour charges
etc., complete for small quarters.

a) Material
elec.8.1.52 Earth Work Excavation of Hard gravel
Soil with small boulder for trench 1st
step of size 1.5 x 0.9 x 0.9 m
Excavation of Hard disteggrated rocks
and boulders for trench 2nd Step of size
1.2 x 0.6 x 1.2 m (Civil SSR)

229 of 517

cum

1.21

220.00

cum

0.9

0.00

266.20

0.00

Ele-Data

55.00

elec.8.1.58 40mm dia 'B' Class G.I pipe


Mtr
25 x 6 mm (1"X 1/4") G.I Flat duly Each
drilled 12mm holes (4 Nos) of 200 mm
length
elec.8.1.59 (8")
Drilling
of 16 Nos through holes of 12mm Each
dia to G.I pipe

2.5
1

381.00
75.00

3
1
55.00 1
0
2
952.50 0
0
75.00 6

18

5.00

90.00

elec-8.1.12 G.I Nuts, Bolts an Washers


elec.8.1.61 18" dia hume pipe ring
elec-8.1.13 Hard Coke
elec-8.1.14 Salt

4
1
20
20

13.00
275.00
9.00
4.00

52.00
275.00
180.00
80.00
2025.70
0.00
2025.70

0.5
0.5

345.00
345.00

172.50
172.50
0.00
0.00

Index Specific
-code
ation
No.

Description

Unit

25% extra for narrow trench & pit and


back filling with Sand, Coke, Salt etc.,
and leveling

Set
Each
Kg
Kg

Quanti Rate Rs. Amount


ty
Rs.

Add contr profit @14% on material


0.00
Total material cost
b) labour charges for fixing pipe Each
ring and connections
elec-8.1.75 Semi skilled Electrician
elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Sundries
Rate per each
10

day
day
0%
0%

345.00
Say

2370.70

Supply and laying of earth strip of size


50x6, 32x6 mm for transformer/
structure earthing

a)Material
elec-8.1.41 GI strip
kg
Add contr profit @14% on material
0.00
Total material cost
b) Labour charges
elec-8.1.75 Semi skilled electrician
day
elec-8.1.82 Helper
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
considered 50 mtr laying per day
Total for GI flat
Rmt

1.4

68.00

95.20
0.00
95.20

0.02
0.04

345.00
345.00

6.90
13.80
0.00
0.00

20.70

115.90

Street light poles

12

Cable termination
Supply and fixing of 3.5x150 sqmm
cable end termination
a)Material

230 of 517

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
elec-4.2.7 Heavy duty flange type brass cable each
gland for 3.5c x150 sqmm PVC armoured
elec-4.3.8 cable
Crimping type copper lugs of 150 sqmm each
with nut/bolt/washer and crimping
elec-4.3.5 Crimping type copper lugs of 70sqmm each
with nut/bolt/washer and crimping (for
neutral lead)
Add contr profit @14% on material
Total for 150 sqmm cable termination

13

264.00

104.00

55.00

631.00
0.00
631.00

Supply and fixing of 3.5x35 sqmm cable


end termination

elec-4.3.1 Crimping type copper lugs of 16sqmm each


with nut/bolt/washer and crimping (for
neutral lead)
Add contr profit @14% on material
Total for 35 sqmm cable termination

138.00

33.00

99.00

22.00

22.00

138.00

259.00
0.00
259.00

0.00

Supply and fixing of 3.5x50 sqmm cable


end termination

a)Material
elec-4.2.6 Heavy duty flange type brass cable each
gland for 3.5c x50 sqmm PVC armoured
cable
elec-4.3.4 Crimping
type copper lugs of 50 sqmm each
with nut/bolt/washer and crimping
elec-4.3.2 Crimping type copper lugs of 25sqmm each
with nut/bolt/washer and crimping (for
neutral lead)
Add contr profit @14% on material
Total for 50 sqmm cable termination
15

0.00

a)Material
elec-4.2.6 Heavy duty flange type brass cable each
gland for 3.5c x35 sqmm PVC armoured
elec-4.3.3 cable
Crimping type copper lugs of 35sqmm each
with nut/bolt/washer and crimping

14

3
1
264.00 1
0
312.00 2
0
0
55.00 6

Quanti Rate Rs. Amount


ty
Rs.

138.00

138.00

40.00

120.00

30.00

30.00

288.00
0.00
288.00

0.00

Supply and fixing of 4cx16 sqmm cable


end termination

a)Material
elec-4.2.5 Heavy duty flange type brass cable each
gland for 4cx16sqmm PVC armoured
cable

231 of 517

94.00

94.00

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
elec-4.3.1 Crimping type copper lugs of 16 sqmm each
with nut/bolt/washer and crimping

22.00

104.00

104.00
0.00
104.00

2.5

295.00

737.50

Skilled Electrician
day
1
440.00
Helper
day
2
345.00
Man Mazdoor for concreting and embeddingday
of cable 2
way indicators
295.00

440.00
690.00
590.00

Add contr profit @14% on material


Total for 16 sqmm cable termination
16

elec4.1.12

elec8.1.85
elec8.1.74
elec8.1.82
elec8.1.85

0.00

Supplyand laying of 6 sqmm 4core XLPE


PVC armoured alluminium cable of Make:
PolyCab / RPG / Finolex / Havells /
Paragon / V- Guard / Fortune Art / Gloster
/ Suncab
a) Material
4corex6 sqmm cable
Rmt
Add contr profit @14% on material
0.00
Total for 6 sqmm cable
b) Labour charges for laying cable.
Man Mazdoor for spreading the sand and each
back filling the excavated soil.

Add area allowence on labour


charges
Add contr@
profit @14% on Labour
Sundires and Rounding off
Rate per 100mts
Rate per Mtr
Total for supply and laying
17

3
1
88.00 1
0
182.00 2
0.00 0
0
182.00 6

Quanti Rate Rs. Amount


ty
Rs.

0%
0%

1720.00

0.00
0.00
5.00
2462.50
24.63
128.65

Supply and fixing of 4cx6 sqmm cable


end termination

a)Material
elec-4.2.5 Heavy duty flange type brass cable each
gland for 4cx6sqmm PVC armoured cable
elec-4.3.1 Crimping type copper lugs of 6 sqmm each
with nut/bolt/washer and crimping
Add contr profit @14% on material
Total for 6 sqmm cable termination

232 of 517

0.00

94.00

94.00

22.00

88.00
182.00
0.00
182.00

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
18
Supply erection testing commisioning of
250 KVA 11kv/433 volts outdoor type
transformer with ONAN cooling and first
filled oil ,bushings on HT side and cable
box on LT side with bidirectional rollers,
silica gel breather,off load tap changer
with locking arrangement complete as
per IS-SPECIFICATIONS
MR

250 KVA Transformer


Erection ,Testing and Commisioning
Total for supply and erection

6.2.1

each

###

0.00

LS

6500.00

0.00
0.00

, Executive
Engineer
Supply
and Run of Deputy
1 of 6Executive
Sq.mm WPTC
,A.P.E.W.I.D.Corporation
, Engineer
cable along
with No.10 SWG
. N EAluminium
LLORE
A.P.E.W.I.D.Corpor
G.I bearer wire through ,PVC
ation cleats with
all accessories including
labour
South
Sub- charges
, Division
etc., complete.
.N E L L O R E

a) Material
elec-1.6.5 6 Sq.mm (7/18) wptc Aluminium cable
elec-8.1.41 No.10 G.I wire. Length 100 RM
elec-8.1.18 Insulation tapes
elec-8.1.85 Aluminium link clips
b) labour charges
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi skilled
elec-8.1.82 Helper
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
6.1.3

Quanti Rate Rs. Amount


ty
Rs.

3
1
1
0
2
0
0
6

, Assistant Engineer
,A.P.E.W.I.D.Corporation
.NELLORE

100 M
kg
each
box

1
6.7
2
2

day
day
day

1
1
1

3017
68
17
55
440
345
345

3017
455.6
34
110
0
440
345
345
2
4748.6
47.49

Supply and Run of 2 of 10 Sq.mm WPSC


Aluminium cable along with No.10 SWG
G.I bearer wire through PVC cleats with
all accessories including labour charges
etc., complete for service mains.
a) Material
100 M
elec-1.6.3 10 Sq.mm WPSC Aluminium cable
No.10 SWG G.I wire. (0.026 Kg / Mtr ) kg
elec-8.1.41 Length 100 RM
PVC Cleats 2way

2
6.7
1

elec-8.1.15

100
Nos

b) labour charges
elec-8.1.74 Skilled Electrician

day

233 of 517

1611

3222

68

455.6

330

330

440

440

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
elec-8.1.75 Semi skilled
day
elec-8.1.82 Helper
day
Sundries such as insulation tapes and
rounding off

3
1
345 1
0
345 2
0
0
5137.6 6

Quanti Rate Rs. Amount


ty
Rs.
1
1

345
345

C) Cost for 100 M


Rate per mtr c/100

51.38

28

Supply, Transportation and fixing of 4' 40 Watt Patty type flourescent single
Tube Light fitting with Energy saving
electronic ballast suitable for 40 Watt
tube on varnished teak wood round
blocks with flexible 3 core wire etc.,,
complete with all connections including
cost of 40W tube. The fitting shall be
under warranty for three years.
Makes:
Crompton/Bajaj/Surya/Havells HPL
a) Material
elec-3.6.8 4' x 40 watts box type flourscent light each
elec-3.7.7 fitting.
Lamp cost of 40W
each
elec-8.1.31 Tw Round blocks
each
Rate per each
Add contr profit @14% on material
0.00
Total for material
a) Labour charges
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi Skilled Electrician
Labour for 1 No
20

elec2.12.36

day
day

Supply and fixing Distribution board with


20A single phase plug and Socket, in
sheet steel enclosure with 10/16/20A SP
MCB including internal connection and
labour charges for flush mounting etc.,
complete
Makes : Legrand / Schneider.
a) Material
1 Phase Distribution board with 20A plug
and socket.

ele-2.9.1 10/16/20A SP MCB


Add contr profit @14% on material
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi skilled Electrician

234 of 517

273.00

273.00

1
2

45.00
7.00

45.00
14.00
332.00
0.00
332.00

440
345

44.00
34.50
410.50

0.10
0.10

Nos

901.00

901.00

Nos

201.00

201.00
1102.00
0.00
1102.00

0.25
0.25

440.00
345.00

110.00
86.25

0.00

Nos
Nos

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
elec-8.1.82 Helpers
Nos
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as Cement, Sand, T.W. LS
Plugs, Screws etc.,

0.25

345.00
282.50

Rate per each


Note : 1. Labour Charges considered for 4 jobs /
day
2.
For concealing, add
the
following:
a
1No. Semi skilled mason
b
1/4 bag cement
21

3
1
86.25 1
0
0.00 0.00 2
0
130.00 0
6

Quanti Rate Rs. Amount


ty
Rs.

1514.50

Supply and fixing TPN Distribution board


with IP-43 protection (Metal Door)
suitable for 3 phase ELCB / RCCB / FP
Isolator as incomer and 10kA SP MCBs as
outing
going
including
internal
connection and labour charges for flush
mounting etc., complete.
Makes:
Gold Medal / Milltec /
Sputnik / Crystal / Bentec

;lk;

40A FP Isolator - 1 No for incomer,


10kA-6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
elec.2.12.5 4way TPN, D.B with IP-43 Protection (MD) each
7
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.
elec40A, 4 Pole Isolator
2.10.22
elec-2.9.17 10kA - 6-32A range SP MCBs

each
each

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as TW Plugs, Screws LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day

235 of 517

1650.00

1650.00

1
12

571.20
121.00

571.20
1452.00
3673.20
0.00
3673.20

0.5
1
1

440.00
345.00
345.00

220.00
345.00
345.00
0.00
0.00
14.00

910.00
14.00

4597.20

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
21
Supply and fixing TPN Distribution board
with IP-43 protection (Metal Door)
suitable for 3 phase ELCB / RCCB / FP
Isolator as incomer and 10kA SP MCBs as
outing
going
including
internal
connection and labour charges for flush
mounting etc., complete.
Makes: Legrand /Schneider.
40A FP Isolator - 1 No for incomer,
10kA-6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
elec.2.12.5 4way TPN, D.B with IP-43 Protection (MD) each
7
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.

Quanti Rate Rs. Amount


ty
Rs.

3
1
1
0
2
0
0
6

40A, 4 Pole Isolator


elec2.10.22
elec-2.9.17 10kA - 6-32A range SP MCBs

each
each

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as TW Plugs, Screws LS
Cement etc,

1650.00

1650.00

1
8

571.20
121.00

571.20
968.00
3189.20
0.00
3189.20

0.5
1
1

440.00
345.00
345.00

220.00
345.00
345.00
0.00
0.00
14.00

910.00
14.00

Rate per each


Note : Labour Charges considered for 2 jobs / day
63A FP Isolator - 1 No for incomer,
10kA-6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
elec.2.12.2 4way TPN, D.B with IP-43 Protection (MD) each
2
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.

4113.20

elec-2.10.7 63A, 4 Pole Isolator


elec-2.9.1 10kA - 6-32A range SP MCBs

each
each

Add contr profit @14% on material


Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi Skilled Electrician
elec-8.1.82 Helpers

0.00

236 of 517

day
day
day

2491.00

2491.00

1
8

890.00
201.00

890.00
1608.00
4989.00
0.00
4989.00

0.5
1
1

440.00
345.00
345.00

220.00
345.00
345.00

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

Add area allowence on labour


charges
Add contr@
profit @14% on Labour
Sundries such as TW Plugs, Screws
Cement etc,

0%
0%
LS

910.00
14.00

Rate per each


Note : Labour Charges considered for 2 jobs / day
80A FP Isolator - 1 No for incomer,
10kA-6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
elec.2.12.2 4way TPN, D.B with IP-43 Protection (MD) each
4
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.

3
1
0.00 1
0
0.00 14.00 2
0
0
5913.00 6

Quanti Rate Rs. Amount


ty
Rs.

B -2

elec-2.10.8 80A, 4 Pole Isolator


elec-2.9.1 10kA - 6-32A range SP MCBs

each
each

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as TW Plugs, Screws LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
22

Supply and fixing SPN Distribution board


with IP-43 protection (Metal Door)
suitable for single phase ELCB / RCCB/DP
Isolator as incomer and 10kA SP MCBs as
outing
going
including
internal
connection and labour charges for
surface / flush mounting etc., complete.
Makes: Legrand /Schneider.

40A DP Isolator / RCCB / ELCB - 1 No


for incomer, 6-32A SP MCBs - 6Nos
for outgoing.

2491.00

2491.00

1
12

571.20
201.00

571.20
2412.00
5474.20
0.00
5474.20

0.5
1
1

440.00
345.00
345.00

220.00
345.00
345.00
0.00
0.00
14.00

910.00
14.00

6398.20

Taking Output = each


a) Material

237 of 517

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
elec-2.12.5 SPN 8 way D.B with IP-43 Protection (MD) each
suitable for single phase ECCB / RCCB/
DP Isolator.
elec-2.10.2 40A D.P.Isolator
elec-2.9.1 10 kA - 6-32A range SP MCBs

each
each

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as hardware, cement etc,
LS
Rate per each
Note : Labour Charges considered for 2 jobs / day
23

Supply and fixing SPN Distribution board


with IP-43 protection (Metal Door)
suitable for single phase ELCB / RCCB/ 1
No. 40 A DP Isolator as incomer and 6
Nos 10kA SP MCBs as outing going
including internal connection and labour
charges for surface / flush mounting etc.,
complete.
Makes: Legrand /Schneider.

40A DP Isolator / RCCB / ELCB - 1 No


for incomer, 6-32A SP MCBs - 6Nos
for outgoing.

3
1
1245.00 1
0
2
367.00 0
0
1206.00 6

Quanti Rate Rs. Amount


ty
Rs.
1

1245.00

1
6

367.00
201.00

2818.00
0.00
2818.00
0.5
0.5
1

440.00
345.00
345.00
737.50
5.00

220.00
172.50
345.00
0.00
0.00
5.00
3560.50

Taking Output = each


a) Material
elec-2.12.5 SPN 8 way D.B with IP-43 Protection (MD) each
suitable for single phase ECCB / RCCB/
DP Isolator.

1245.00

1245.00

elec-2.10.2 40A D.P.Isolator


elec-2.9.1 10 kA - 6-32A range SP MCBs

1
6

367.00
201.00

367.00
1206.00
2818.00
0.00
2818.00

0.5
0.5
1

440.00
345.00
345.00

220.00
172.50
345.00
0.00
0.00

each
each

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%

238 of 517

737.50

Ele-Data

Index Specific
-code
ation
No.

23

Description

Unit

3
1
5.00 1
0
3560.50 2
0
0
6

Quanti Rate Rs. Amount


ty
Rs.

Sundries such as hardware, cement etc,


LS
Rate per each
Note : Labour Charges considered for 2 jobs / day

5.00

Supply and fixing TPN - Vertical type


Distribution board with IP -43 Protection
with 125A, 4 Pole 25 kA MCCB as
incomer with 4Nos 63A TP MCBs and 12
Nos. 10 kA SPMCBs as outgoing including
internal connection and labour charges
for flush mounting etc., complete.
Makes: Legrand /Schneider.

8 way TPN Vertical DB


a) Material
elec.2.12.3 8 Way TPN Vertical DB with IP -43 (Metal
5
door) protection suitable for 125A, 4
Pole, 25kA MCCB as incomer.

Nos

9823.00

9823.00

elec-2.8.6 125 Amps, 4 Pole , 25 kA MCCB


elec-2.9.6 10 kA, 63A TP MCBs:
elec-2.9.1 10kA, 6 to 32A SP MCBs: Rs.184 / Each

Nos
Nos
Nos

1
8
0

8700.00
1477.00
201.00

8700.00
11816.00
0.00
30339.00
0.00
30339.00

1
1
1

440.00
345.00
345.00

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as T.W. Plugs, Screws, LS
Cement etc.,
Rate per each
Note : 1. Labour Charges considered for 1 jobs /
day
2. If the Distribution Boards from Item No. 4.4.1
to
proposed
concealing, add the
a 4.4.8
1No. Semi
skilledfor
mason
b
1/4 bag cement
23

Supply and fixing TPN - Vertical type


Distribution board with IP -43 Protection
with 1 No. 63A TP MCB as incomer with
24 Nos. 10 kA SPMCBs as outgoing
including internal connection and labour
charges for
flush mounting etc.,
complete.
Makes: Legrand /Schneider.

8 way TPN Vertical DB

239 of 517

1130.00
19.00

Say

440.00
345.00
345.00
0.00
0.00
19.00
31488.00
31488.00

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

a) Material
elec.2.12.3 8 Way TPN Vertical DB with IP -43 (Metal
7
door) protection suitable for 125A, 4
Pole, 25kA MCCB as incomer.

Nos

9823.00

elec-2.8.2 125 Amps, 4 Pole , 25 kA MCCB


elec-2.9.6 10 kA, 63A TP MCBs:
elec-2.9.1 10kA, 6 to 32A SP MCBs: Rs.184 / Each

Nos
Nos
Nos

1
24

7194.00
1477.00
201.00

1
1
1

440.00
345.00
345.00

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour 0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as T.W. Plugs, Screws, LS
Cement etc.,

1130.00
19.00

Rate per each


Note : 1. Labour Charges considered for 1 jobs /
day
2. If the Distribution Boards from Item No. 4.4.1
to
proposed
concealing, add the
a 4.4.8
1No. Semi
skilledfor
mason
b

3
1
1
0
9823.00 2
0
0
0.00 6

Quanti Rate Rs. Amount


ty
Rs.

Say

1477.00
4824.00
16124.00
0.00
16124.00
440.00
345.00
345.00
0.00
0.00
19.00
17273.00
17273.00

1/4 bag cement

23

Supply and fixing TPN - Vertical type


Distribution board with IP -43 Protection
with 125A, 4 Pole 25 kA MCCB as
incomer with 4Nos 63A TP MCBs and 12
Nos. 10 kA SPMCBs as outgoing including
internal connection and labour charges
for flush mounting etc., complete.
Makes:
MDS/
L&T Hager
B
8 way TPN
Vertical
DB
a) Material
elec.2.12.3 8 Way TPN Vertical DB with IP -43 (Metal
7
door) protection suitable for 125A, 4
Pole, 25kA MCCB as incomer.
elec-2.8.2 125 Amps, 4 Pole , 25 kA MCCB
elec-2.9.6 10 kA, 63A TP MCBs:
elec-2.9.1 10kA, 6 to 32A SP MCBs: Rs.184 / Each
Add contr profit @14% on material
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi Skilled Electrician
elec-8.1.82 Helpers
Add area allowence on labour
charges @

240 of 517

Nos

9823.00

9823.00

Nos
Nos
Nos

1
4
12

7194.00
1477.00
201.00

7194.00
5908.00
2412.00
25337.00
0.00
25337.00

day
day
day

1
1
1

440.00
345.00
345.00

440.00
345.00
345.00
0.00

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

Add contr profit @14% on Labour


Sundries such as T.W. Plugs, Screws,
Cement
etc.,
Rate per
each
Note : 1. Labour Charges considered for
1 jobs
/ day
2.
If the
Distribution Boards from Item
No.
4.4.1
toskilled
4.4.8
proposed for
a
1No. Semi
mason
concealing, add the following:

3
1
0.00 1
0
19.00 26486.00 2
0
26486.00 0
6

Quanti Rate Rs. Amount


ty
Rs.
1130.00
19.00

LS

Say

Supply, installation,and commissioning


of 3Phases and neutral 415V,
free
standing type cubical panel board made
of 16 Gauge CRCA sheet steel, panel
shall be painted after processing 7 tank
process with RAL 7032 siemens grey. The
panel shall be consisting of suitable
rating of allumunium bus bars ( At the
rating of 0.8 A/Sq.mm) supported with
DMC/SMC and colour coded with heat
shrinkable sleeves. The bus bars fault
level shall be 50 KA and shall be as per
the requirement of local CEIG, fire
regulations, other authorities etc. The
panel shall be suitable for accomdating
the following switch gears including
supply of all components, hard wares etc
including all necessary civil works,
adequate reinforcement foundation bolts
suitable G.I earth strip , 100 x 50mm MS
base channel, earth bar,
door loop
earthings
.
Bus
bar
to
switch
interconnections,

All cables shall have proper cable


entry,gland plates, suitable size of
glands, earth tags for glands, lugs,
cadmium plated nuts , bolts, feeder
identification marks,shall be installed on
performed trench consisting of the
following as required and as per IS
standards
and
panel
should
be
manufactures only from panel builds with
CPRI Test certificate.

elec-2.8.8
elec-6.3.3
elec-6.3.8
elec-6.3.1

400A Aluminium Bus Bar with colour


code.
Internal wiring with approved make cable
Earthing: Providing 50x6 mm G.I flat
Incommer: .
400A TPN 50KA MCCB L&T make.- 1 No.
Metering Set:
0- 400 A Digital Ammeter . - 1 No.
Ammeter selector switch - 1 No.
0-500V Digital Volt meter - 1 No.

241 of 517

each

26208.00

each
each
each

1
1
1

2500.00
175.00
2500.00

26208.00
2500.00
175.00
2500.00

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
elec-6.3.8 Voltmeter selector switch - 1 No.
each
elec-6.3.9 R, Y, B Indication lamps LED type, puse each
buttons.
elec-6.3.10 400 /5A C.T coils : 2 sets
elec-2.6.2 32A Bakelite fuse fittings - 3 Nos.
elec-2.5.1 2A HRC fuse link - 3 Nos:
elec-6.3.13 APFC relay 8 stage.
Outgoing :
ele -2.8.7 250 A MCCB 2Nos- L &T Make
elec-2.8.6 125A 25KA MCCB-02 NOS -L&T Make
MR
100A 25KA MCCB-02 NOS -L&T Make
elec-2.8.5 63A 25KA MCCB -04 NOS - L&T Make

each
each
each

1
3

175.00
135.00

6
3
3
1

450.00
123.00
50.00
13600.00

2
2

20818.00
8700.00
6350.00
6813.00

Bus bars and insulators 10%


Cost of enclosure @ 45%
Control wiring, Labour charges for
errection of switch gear, panel board
including all labour charges etc complete
with connections for finished item of
work
including
transportation
charges.5%
Add contr profit @14% on material

Total cost of panel board


b)labour charges
elec-8.1.74 Skilled electrician
elec-8.1.75 semi skilled electrician
elec-8.1.82 helper
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Total
cost
of
panel
board(supply&erection)
13

SWAGED POLES
2713 / 1980).

3
1
175.00 1
0
405.00 2
2700.00 0
0
369.00 6

Quanti Rate Rs. Amount


ty
Rs.

150.00
13600.00

41636.00
17400.00
0.00
27252.00
0.00
135070.00
13507.00
60781.50
6753.50

216112.00
0.00

Overhe
ads
and
contra
ctors
profit
on
materi
als

216112.00
day
day
day
0%
0%

1
2
4

440.00
345.00
345.00
2930.00

440.00
690.00
1380.00
420.00
0.00
###

(Confirming to IS

242 of 517

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
13.1
Fabrication, supply and transportation of
swaged poles up to site confirming to IS
2713 / 1980 specifications. The pole
should be painted with primary coat of
red oxide and black bituminous paint and
Aluminuim paint up to ground level with
base plate, including cost of all materials
and transportation etc., complete. as per
specification 410 SP 27 of over length of
9.00 Mtrs in 3 sizes i.e. 5.00 Mtrs of
114.30 mm dai with 5.40 thick, 2.00 Mtrs
of 88.90 mm dai with 4.85 mm thick and
2.00 Mtrs of dai 76.10 mm with 3.25 mm
thick. the pole should be planted 1.50
Mtrs depth in the ground. The over all
wieght of the pole is 113 Kgs. as per
standard data 13.1.8 of Electrical SSR
2010-11
a) Material
Elec-6.1.1 Cost of swaged pole
13.2
13.2.1

113

Kg

24.8

71

8023

65

1612

65

2418

Rate per Each


Fabrication and Supply of M.S. Poles for
garden posts with 'B' class 6 mtrs long
60.25mm outer dia with base plate and
suitable pole cap including cost and
conveyance of all material including
fixing of luminaire and labour charges
etc., complete.

Elec-6.1.2 a) Material
6Mtrs 'B' Class M.S. pipe of 60.25mm
dia with base plate and suitable pole cap
13.3

Kg

3
1
1
0
2
0
0
6

Garden Posts
Fabrication and Supply of M.S. Poles for
garden posts with 'B' class 4mtrs long
60.25mm outer dia with base plate and
suitable pole cap including cost and
conveyance of all material including
fixing of luminaire and labour charges
etc., complete.

a) Material
Elec-6.1.2 4Mtrs 'B' Class M.S. pipe of 60.25mm dia
with base plate and suitable pole cap
13.2.2

Quanti Rate Rs. Amount


ty
Rs.

Kg

37.2

Rate per Each


Brackets

243 of 517

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
13.3.1 Supply and fixing of 50mm dia 0.5 mtrs
single arm M.S. pipe bracket with sleeve
and fasteners with necessary angle
including painting etc., complete on
existing
pole
including
fixing
of
luminaire.
a) Material
Elec-6.1.3 0.5Mtr length 50mm 'B' class pipe.
Kg
45cm length , 10cm dia and cap.
Kg
Painting with red oxid and enamel paint.
job
b) Labour charges for fixing with
Spl. T & P
elec-8.1.74 Skilled Electrician
elec-8.1.80 Fitter
Rate per Each
Note : Labour is Considered for 5
jobs / day
13.3.2

2.55
5.4
1

65.00
65.00
80.00

440.00
385.00

3
1
1
0
2
0
0
6

165.75
351
80.00

88.00
77.00
761.75

day
day

0.2
0.2

Kg
Kg
job

5.1
5.4
1

65.00
65.00
160.00

331.5
351
160.00

day
day

0.33
0.33

440.00
385.00

145.20
127.05

Kg
Kg
job

7.65
5.4
1

65.00
65.00
240.00

497.25
351
240.00

day
day

0.5
0.5

440.00
385.00

220.00
192.50

Supply and fixing of 50mm dia 0.5 mtrs


double arm M.S. pipe bracket with sleeve
and fasteners with necessary angle
including painting etc., complete on
existing pole including fixing of luminaire
a) Material
2 x 0.5Mtr length 50mm 'B' class pipe.
45cm length , 10cm dia and cap.
Painting with red oxid and enamel paint.
b) Labour charges for fixing with
Spl. T & P

elec-8.1.74 Skilled Electrician


elec-8.1.80 Fitter
Rate per Each
Note : Labour is Considered for 3
jobs / day
13.3.3

Quanti Rate Rs. Amount


ty
Rs.

Supply and fixing of 50mm dia 0.5 mtrs


triple arm M.S. pipe bracket with sleeve
and fasteners with necessary angle
including painting etc., complete on
existing
pole
including
fixing
of
luminaire.
a) Material
3 x 0.5Mtr length 50mm 'B' class pipe.
45cm length , 10cm dia and cap.
Painting with red oxid and enamel paint.
b) Labour charges for fixing with
Spl. T & P

elec-8.1.74 Skilled Electrician


elec-8.1.80 Fitter

244 of 517

Ele-Data

Index Specific
-code
ation
No.

13.3.4

Description

Unit

3
1
1500.75 1
0
2
0
0
6

Quanti Rate Rs. Amount


ty
Rs.

Rate per Each


Note : Labour is Considered for 2
jobs / day
Supply and fixing of 50mm dia 1 mtrs
single arm M.S. pipe bracket with sleeve
and fasteners with necessary angle
including painting etc., complete on
existing pole including fixing of luminaire
a) Material
1Mtr length 50mm 'B' class M.S pipe.
45cm length , 10cm dia and cap.
Painting with red oxid and anamel paint.
b) Labour charges for fixing with
Spl. T & P

elec-8.1.74 Skilled Electrician


elec-8.1.80 Fitter
Rate per Each
Note : Labour is Considered for 5
jobs / day

Kg
Kg
job

5.1
5.4
1

61.00
61.00
160.00

311.1
329.4
160.00

day
day

0.2
0.2

440.00
385.00

88.00
77.00
965.5

220
4238.36
4884.46
80
60

158.40
3051.62
263.76
668.00
60.00

480.00
375.00
420.00

158.4
1001.25
138.6

13.4.2(a) Erection charges for 9 mtrs to 11 mtrs


long swaged pole including excavation of
pit, coil earthing, hire charges of special
T&P painting
of Pole CC 1:3:6 upto
ground and 1:2:4 for Couping work,
including labour and transportation
charges etc., complete.
a) Material
Pit excavation 156 Cmx 60Cmx60cm.
cum
(Civil SSR)
cum
C.C.work for pit 1:3:6 (Civil SSR)
cum
Couping 1:2:4 (Civil SSR)
Painting with red oxid and enamel paint.
M
each
Coil earthing
b) Labour charges
elec-8.1.74 Skilled Electrician
day
elec-8.1.82 Helper
day
elec-8.1.76 Mason
day
Hire charges for Spl.T&P 40% on labour
cost
Rate per Each
Note : Labour is Considered for 3
jobs / day

245 of 517

0.72
0.72
0.054
8.35
1
0.33
2.67
0.33

519.30
6019.33

Ele-Data

Index Specific
Description
Unit
-code
ation
No.
5.1.2
Providing independent earthing for
Important equipment with 40mm dia 'B'
class 2.5m long G.I pipe and 19mm dia
'B' class G.I pipe of 0.3mtr. long
connected with reducer providing G.I
funnel
with
mesh
enclosed
in
C.C.Chamber of 400m x 400m x 400mm
with R.C.C. Slab cover duly providing
staggered holes filling with salt and
charcoal from the bottom of the pipe
giving earth connection from electrode
through G.I strip of 25 x 6mm x 200mm
length with all accessories and labour
charges
complete,
as
per
IS
specifications 732/1982 (Part II)

ELEC8.1.52

a) Material
Earth work excavation of hard gravel soil
with small boulders for trench 1st step of
size 1.5 x 0.9 x 0.9 m (5'x3'x3')

Quanti Rate Rs. Amount


ty
Rs.

cum

1.27

Earth work hard disintegrated rock and cum


boulders for trench 2nd Step of size 1.2 x
0.9 x 1.65 m (Civil SSR-16) (4'x3'x5.5')

1.87

25% extra for trenches and narrow Pit,


back filling and blending.

279.40

0.00

55.00

55.00

0.9

4884.46

4396.01

Masonary through with brick Masonry cum


with CM 1:3

0.23

4118.22

947.19

Cement plastering inside through with


1:3 Cement mortar, 12 mm thick (Civil
SSR).
40mm dia G.I pipe Class 'B' (Civil SSR)

sqm

2.09

247.21

516.66

Mtr

2.5

381.00

952.50

Mtr

0.3

226.00

67.80

Each
Each

1
1

40.00
83.00

40.00
83.00

25mm x 6mm x 200 mm length G.I Strip Each


(Flat) with 4 Nos. Holes of 12mm dia.

220.00

220.00

ELEC8.1.59

Drilling of staggered holes of 16mm dia Each


to G.I pipe.

16

6.00

96.00

ELEC8.1.60

G.I Bolts, Nuts and Washers.

Set

11.00

44.00

ELEC8.1.13

Hard Coke.

kg

9.00

36.00

Laying C.C bed in Cement mortar with 1:


2:4 with 20 mm HBG Stone Metal (Civil
SSR).

ELEC8.1.58

ELEC-8-1- 19/25 mm dia G.I pipe


55
ELEC8.1.32

40mm x 19mm reducer


G.I Funel covered with wire mesh

246 of 517

220.00

cum

3
1
1
0
2
0
0
6

Ele-Data

Index Specific
-code
ation
No.
ELEC- Salt.
8.1.14

DATA

Description

Unit

Cost Iron cover 400 mm x 400mm x


50mm.
b) labour charges for fixing pipe
Skilled Electrician
Sundries such as Lugs and Saddles
Rate per each
Supply, Transportaton, installation, testing and
commissioning of 2X 36 Watt CFL recessed
mounted mirror optic fitting with P5 Lowers,
suitable for 2 Nos 36W CFL lamps,energy saving
electronic ballast including all labour charges and
conveyance of all materials etc complete with wire
leads and connections required anchor hold
fasteners and GI wire. Wipro / G.E./ Phillips /
Thorn) ( as approve for Sainik School
Kalikiri)

3
1
80.00 1
0
2
380.00
0
0.00 0
440.00 6

Quanti Rate Rs. Amount


ty
Rs.

kg

20

4.00

L.S

380.00

Nos

1
1

440.00

15.50

15.5

8649.06

ELEC-3.6.39 Supply of 2 x 36W CFL Paralite louvre (P5)


Surface / Recessed low glare Mirror Optic
luminaire comprising bright anodised alluminium
reflector with Electronic Ballst of makes Wipro /
G.E./ Phillips / Thorn

4961.3

4961.3

ELEC-3.7.30 Cost of 36W CFL bulb


anchor fasteners
TOTAL
Fixing of mirror optic tube light luminaire in false
ceiling / pop with necessary arrangment including
giving connections and all labour charges etc.,
complete.

2
1

135
50

270
50
5281.3

0.05
0.05
0.05

297
284
260

14.85
14.2
13

8.1.77
8.1.86
8.1.84

b) Labour charges for cutting P.O.P / false ceiling


and Fixing MOT
Skilled Electrician
day
Skilled Carpenter
day
Semi skilled Electrician / Helper
day
Rate per each

42.05

Note : Labour Charges considered for 8 Nos MOT


lights in a day
2X 36 Watt CFL per each

5323.35

Asst. Exe.Engineer
APEWIDC, Kuppam

Dy. Executive Engineer


APEWIDC, Madanapalli

247 of 517

Ele-Data

Index Specific
-code
ation
No.

Description

Unit

Executive Engineer
APEWIDC, Chittoor

Quanti Rate Rs. Amount


ty
Rs.

3
1
1
0
2
0
0
Engineer
6

Superintending
APEWIDC, Kadapa

248 of 517

Ele-Data

3 Remarks 3
1
1
1
1
7
0
0
2
2
0
0
0
0
6
6

249 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

The
R&B
Department
Proposed
Labour, for
both piping
&
wiring
considering
40% Labour,
for
Wire
draw.
Keeping
this,
the
labour
is
proposed for
wiring 100
RM.
Million /
RPG/
paragon

250 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

251 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

252 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

253 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

254 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

255 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

256 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

257 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

258 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

259 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

260 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

261 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

262 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

263 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

264 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

265 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

266 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

267 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

268 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

269 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

270 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

271 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

272 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

273 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

274 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

275 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

276 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

277 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

278 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

279 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

280 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

281 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

282 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

283 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

284 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

285 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

ctrification
3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

286 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

287 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

288 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

289 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

290 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

291 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

292 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

293 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

294 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

295 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

296 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

L&T Hager

L&T Hager
L&T Hager

297 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

298 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

299 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

300 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

301 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

302 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

303 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

304 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

305 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

306 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

307 of 517

Ele-Data

3 Remarks 3
1
1
1
1
0
0
2
2
0
0
0
0
6
6

ecutive Engineer
DC, Madanapalli

308 of 517

Ele-Data

3 Remarks
1
1
0
2
0
0
Engineer
6

tending
WIDC, Kadapa

3
1
1
0
2
0
0
6

309 of 517

Ele-Data

WATER SUPPLY AND SANITARY DATAS

Sl.
No.
1

AREA ALLOWENCE
ADD 14% OVERHEADS

0%
14%

DESCRIPTION

ITEM
CODE

COEFFIC
UNIT
IENT

RATE

PER

Supplying and laying, filling, jointing and testing


SWG SP-1 pipes of ISI make confirming to IS 1651
& 4127 1st quality with air tight Cement joints in CM
(1.5:1)prop. including excavation of trenches and
socket pits in any soil (except rock requiring blasting)
and refilling with watering and tamping to the required
slope including cost and conveyance of all materials
to site and all labour charges for finished item of work
(APSS NO 1301 & 1318)

BMW-A.02
BMW-A.05

a) 101.60 mm dia SWG pipe upto 3' depth


Area allowence on labour charges

1.00
0%

Rmt

408.00
232.00

1.00
1.00

1.00
0%

Rmt

680.00
288.00

1.00
1.00

1.00
0%

Rmt

466.00
288.00

1.00
1.00

1.00
0%

Rmt

614.00
232.00

1.00
1.00

0.14

add overheads @
Total rate per 1 Rmt

BMW-A.03
BMW-A.06

b) 152.40mm dia SWG pipe upto 5' depth


Area allowence on labour charges

0.14

add overheads @
Total rate per 1 Rmt

BMW-A.01
BMW-A.06

c 101.60 mm dia SWG pipe upto 5' depth


Area allowence on labour charges

0.14

add overheads @
Total rate per 1 Rmt

BMW-A.04
BMW-A.05

152.40mm dia SWG pipe upto 3' depth


Area allowence on labour charges
add overheads @

0.14

Total rate per 1 Rmt

310 of 517

WS-Data

Sl.
No.
2

ITEM
CODE

DESCRIPTION

COEFFIC
UNIT
IENT

RATE

PER

Constructing 904.0 mm (30) dia brick masonry


inspection chamber as per IS - 4111: Part-1:1986
with cement mortar (1:6) prop using 2nd Class Clay
Bricks of 225 mm thick from approved source having
a minimum crushing strength of 5 N/sq.mm including
plastering with cement mortar 1:3 prop; thick both
inside and outside fitted with 20 dia RCC manhole
covers and frames including excavating pits up to
a depth of 904 mm (3'-0") in all sorts of soils
(exculding rock) and laying cement conrete (1:4:8)
150 mm thick using 40 mm HBG Metal and P.C.C.
1:2:4 benching and channel 100 mm thick as per
Standard specification and
including cost and
conveyance of all materials like cement, sand, bricks,
water etc., to site, cost of seigniorage charges on all
materials and all incidental and operational, labour
charges like mixing cement mortar, constructing
masonry, lift charges, curing etc., complete for
finished item of work as per Standard specification.

basic rate as per ssr item

BMW-B.03

Area allowence on labour charges


add overheads @

1.00
0%

Nos 6237.00
0.00

1.00
1.00

0.14

Total rate per 1 Nos

311 of 517

WS-Data

Sl.
No.
3

ITEM
CODE

DESCRIPTION

COEFFIC
UNIT
IENT

RATE

PER

Constructing 904.0 mm (30) dia brick masonry


inspection chamber as per IS - 4111: Part-1:1986
with cement mortar (1:6) prop using 2nd Class Clay
Bricks of 225 mm thick from approved source having
a minimum crushing strength of 5 N/sq.mm including
plastering with cement mortar 1:3 prop; thick both
inside and outside fitted with 20 dia RCC manhole
covers and frames including excavating pits up to
a depth of 1524 mm (5'-0") in all sorts of soils
(exculding rock) and laying cement conrete (1:4:8)
150 mm thick using 40 mm HBG Metal and P.C.C.
1:2:4 benching and channel 100 mm thick as per
Standard specification and
including cost and
conveyance of all materials like cement, sand, bricks,
water etc., to site, cost of seigniorage charges on all
materials and all incidental and operational, labour
charges like mixing cement mortar, constructing
masonry, lift charges, curing etc., complete for
finished item of work as per Standard specification.

BMW-B.04

basic rate as per ssr item


Area allowence on labour charges
add overheads @

1.00
0%

Nos 10181.00
0.00

1.00
1.00

0.14

Total rate per 1 Nos


4

Constructing 904.0 mm (30) dia solid block


masonry inspection chamber as per IS - 4111:
Part-1:1986 with cement mortar (1:6) prop using fly
ash blocks of 225mm thick from approved source
having a minimum crushing strength of 10 N/sq.mm
including plastering with cement mortar 1:3 prop;
thick both inside and outside fitted with 20 dia RCC
manhole covers and frames including excavating
pits up to a depth of 1524 mm (5'-0") in all sorts of
soils (exculding rock) and laying cement conrete
(1:4:8) 150 mm thick using 40 mm HBG Metal and
P.C.C. 1:2:4 benching and channel 100 mm thick as
per Standard specification and including cost and
conveyance of all materials like cement, sand, bricks,
water etc., to site, cost of seigniorage charges on all
materials and all incidental and operational, labour
charges like mixing cement mortar, constructing
masonry, lift charges, curing etc., complete for
finished item of work as per Standard specification.

312 of 517

WS-Data

Sl.
No.

ITEM
COEFFIC
UNIT
RATE
CODE IENT
BMW-B.02
1.00
Nos 10590.00
0.00
0%

DESCRIPTION
basic rate as per ssr item
Area allowence on labour charges

PER
1.00
1.00

0.14

add overheads @
Total rate per 1 Nos
5

Constructing 904.0 mm (30) dia solid block


masonry inspection chamber as per IS - 4111:
Part-1:1986 with cement mortar (1:6) prop using fly
ash blocks of 225mm thick from approved source
having a minimum crushing strength of 10 N/sq.mm
including plastering with cement mortar 1:3 prop;
thick both inside and outside fitted with 20 dia RCC
manhole covers and frames including excavating
pits up to a depth of 1524 mm (3'-0") in all sorts of
soils (exculding rock) and laying cement conrete
(1:4:8) 150 mm thick using 40 mm HBG Metal and
P.C.C. 1:2:4 benching and channel 100 mm thick as
per Standard specification and including cost and
conveyance of all materials like cement, sand, bricks,
water etc., to site, cost of seigniorage charges on all
materials and all incidental and operational, labour
charges like mixing cement mortar, constructing
masonry, lift charges, curing etc., complete for
finished item of work as per Standard specification.

BMW-B.01

basic rate as per ssr item


Area allowence on labour charges

1.00
0%

Nos 6730.00
0.00

1.00
1.00

1.00
0%

Nos

1.00
1.00

0.14

add overheads @
Total rate per 1 Nos

Supplying and fixing 150.00mmx100.00mm SWG


gully trap 1st class confirming to ISI 651 & 4127 with
CI grating and constructing single brick masonry wall
chamber of size 20" x 14" x 12 in CM (1:6) prop.
Over a CC (1:5:10)prop. bed, and fitted with 304.8
mm x 225.6 mm(12" x 9") CI frame and hinged cover
and plastering 12mm thk. in CM (1:4) prop. both
inside and outside surfaces and including cost and
conveyance of all materials to site, labour charges
etc., complete for finished item of work. SSR ITEM
NO.527
Basic rate as per ssr item
Area allowence on labour charges

BMW-A.72
BMW-A.74

313 of 517

568.00
30.00

WS-Data

Sl.
No.

ITEM
COEFFIC
UNIT
CODE IENT
0.14

DESCRIPTION
add overheads @

RATE

PER

Total rate per 1 Nos


7

Supplying and fixing Indian make Flat Back Wash


Hand Basin (HSW/Parryware/ Neycer) 1st quality
conforming to IS:2556-Part-4:1972 of size 550mm x
400mm with waste fittings like rubber plug, chain, 32
mm nominal size C.P. Fitting with parallel pipe thread
conforming to IS:2963-1979 and fitted with 15 mm
nominal bore Chromium Plated Pillar Tap of 1st
quality Indian make 400 grams Seiko/ Esso or
equivalent complete with standard CI brackets
including wooden block ,1 No.12.70mm PVC
connection with brass union nuts CP coated , 1
No.12.70mm NP bib tap 300 gms Seiko or equivalent
including cost and conveyance of all materials to site,
labour charges etc. complete for finished item of work

BMW-D24
BMW-D28

1.00
0%

Nos 1782.00
377.00

1.00
1.00

0.14
add overheads @
Total rate per 1 Nos
B Basic rate as per ssr item 12.7MM DIA PVC
conection with brass union nut CP coated
BMW-I48
BMW-I49
Area allowence on labour charges

1.00
0%

Nos

102.00
20.00

1.00
1.00

0.14
add overheads @
Total rate per 1 Nos
C Basic rate as per ssr item 12.7 MM ANGLE STOP
COCK first quality Indian make 400 gms Seiko
BMW-E 05
BMW-E 06
Area allowence on labour charges

1.00
0%

Nos

474.00
43.00

1.00
1.00

0.14
add overheads @
Total rate per 1 Nos
D Basic rate as per ssr item 38.1 MM CP WASTE
COUPLING half or full thread 1st quality indian make
paryware or equivalent
BMW-E31
BMW-E32
Area allowence on labour charges

1.00
0%

Nos

237.00
29.00

1.00
1.00

1.00
0%

Nos

26.00
0.00

1.00
1.00

A Basic rate as per ssr item


Area allowence on labour charges

0.14

add overheads @
Total rate per 1 Nos
E Basic rate as per ssr item 31.75 MM dia PVC fleible
waste pipe of 914.4 mm length of first quality

BMW-G05
Area allowence on labour charges
add overheads @

314 of 517

0.14

WS-Data

Sl.
No.

ITEM
CODE

DESCRIPTION

COEFFIC
UNIT
IENT

RATE

PER

Total rate per 1 Nos


TOTAL COST (A+B+C+D+E)
8

Supplying and fixing NP soap dish heavy type of


approved make ISI quality with NP screws etc.,
complete including cost and conveyance of all
materials, labour charges for fixing etc., complete for
finished item of work in all floors as per ssr item no
598
BMW-I28
BMW-I29

Basic rate as per ssr item


Area allowence on labour charges

1.00
0%

Nos

243.00
12.00

1.00
1.00

1.00
0%

Nos

513.00
116.00

1.00
1.00

1.00
0%

Nos

164.00
44.00

1.00
1.00

1.00
0%

Nos

258.00
29.00

1.00
1.00

0.14

add overheads @
Total rate per 1 Nos
9

Supplying and fixing TV shape mirror with plastic


frame of size 609.6mm x 457.2mm , plywood back
with NP screws 1st quality including cost and
conveyance of all materials, labour charges etc.,
complete for finished item of work in all floors.
BMW-I 105
BMW-I106

Basic rate as per ssr item


Area allowence on labour charges

0.14

add overheads @
Total rate per 1 Nos
10

Supplying and fixing of 25.4mm dia , 609.6mm


long aluminium anodized towel rods with brackets
and aluminium screws including cost and conveyance
of all materials, labour charges etc., complete for
finished item of work.
BMW-I 20
BMW-I 21

Basic rate as per ssr item


Area allowence on labour charges

0.14

add overheads @
Total rate per 1 Nos
11

Supplying and fixing NP bib taps of size 12.70mm


dia of Indian make Seiko or equivalent including
cost and conveyance of all materials, labour charges
etc., complete for finished item of work in all floors.
a) 300 grams
Basic rate as per ssr item
Area allowence on labour charges

BMW-E 09
BMW-E 10
add overheads @

315 of 517

0.14

WS-Data

Sl.
No.

ITEM
CODE

DESCRIPTION

COEFFIC
UNIT
IENT

RATE

PER

Total rate per 1 Nos


b) 400 gms
Basic rate as per ssr item
Area allowence on labour charges

BMW-E 07
BMW-E 08

1.00
0%

Nos

407.00
29.00

1.00
1.00

1.00 RM
0%

405.00
0.00

3.00
1.00

1.00 RM
RM
0%

484.00
0.00

3.00
1.00

1.00 RM
RM
0%

1153.00
0.00

3.00
1.00

0.14

add overheads @
Total rate per 1 Nos
12

Supplying and fixing of SWR/ PVC pipes (as per


ISI standards) 4 Kg/Sq.cm. Prince/sudhakar or any
ISI brand and fixing all special such as plain bends,
off sets, door bends, single junctions, double
junctions as per site requirement, fixing with PVC
clamps if necessary with required number of Bombay
nails including cost and conveyance of all materials to
site, labour charges etc.complete for finished item of
work at all floor levels. (APSS No. 1302 1319 &
1326)
(a) 90mm dia 3 Mts single socket
Basic rate as per ssr item
Area allowence on labour charges

BMW-G12
BMW
0.14

add overheads @
Total rate per 1 RMT
(b) 110mm dia 3 Mts single socket
Basic rate as per ssr item
Area allowence on labour charges

BMW-G13
BMW
0.14

add overheads @
Total rate per 1 RMT
(b) 160mm dia 3 Mts single socket
Basic rate as per ssr item
Area allowence on labour charges

BMW-G 32
BMW
add overheads @

0.14

Total rate per 1 RMT

316 of 517

WS-Data

Sl.
No.
13

ITEM
CODE

DESCRIPTION

COEFFIC
UNIT
IENT

RATE

PER

Supplying & fixing Ashirvad/Astral flow guard for


equivalent CPVC Pipes with fittings in ground or on
wall including cost of tees, elbows, bends, reducers,
couplings, running joints, union flanges, unions etc.
with necessary excavation in all types of soils except
rock requiring blasting, refilling, chiselling masonry
walls and making good the walls & floors to the
original surface and fixing MS clamps on TW blocks
on walls including cost and conveyance of all
materials and labour charges complete for finished
item of work.

a) 15.90 mm dia CPVC SDR 13.50


Basic rate as per ssr item
Area allowence on labour charges

BMW-I 220
BMW-I 415

1.00 Rmt
Rmt
0%

141.00
31.00

1.00
1.00

1.00 Rmt
Rmt
0%

160.00
31.00

1.00
1.00

1.00 Rmt
Rmt
0%

212.00
31.00

1.00
1.00

1.00 Rmt
Rmt
0%

360.00
31.00

1.00
1.00

1.00 Rmt
Rmt
0%

525.00
31.00

1.00
1.00

0.14

add overheads @
Total rate per 1 RMT
b) 22.20 mm dia CPVC SDR 13.50
Basic rate as per ssr item
Area allowence on labour charges

BMW-I 221
BMW-I 415
0.14

add overheads @
Total rate per 1 RMT
c) 28.60 mm dia CPVC SDR 13.50
Basic rate as per ssr item
Area allowence on labour charges

BMW-I 222
BMW-I 415
0.14

add overheads @
Total rate per 1 RMT

D 41.30 mm dia CPVC SDR 13.50


Basic rate as per ssr item
Area allowence on labour charges

BMW-I 224
BMW-I 415
0.14

add overheads @
Total rate per 1 RMT
E 54 mm dia CPVC SDR 13.50
Basic rate as per ssr item
Area allowence on labour charges

BMW-I 225
BMW-I 415
add overheads @

0.14

Total rate per 1 RMT

317 of 517

WS-Data

Sl.
No.

ITEM
CODE

DESCRIPTION
F 22.20 mm dia CPVC SDR 13.50
Basic rate as per ssr item
Area allowence on labour charges

BMW-I 227
BMW-I 415

COEFFIC
UNIT
IENT

1.00 Rmt
Rmt
0%

RATE

PER

189.00
31.00

1.00
1.00

0.14

add overheads @
Total rate per 1 RMT

14

Supplying and fixing Gunmetal Gate ( GM peet )


valve as per IS-778 Class - I , Indian make heavy
type including cost and conveyance of all materials ,
labour charges etc. complete for finished item of
work.
15 mm dia nominal bore
Basic rate as per ssr item
Area allowence on labour charges

BMW-F21
BMW-F22

1.00
0%

Nos

636.00
44.00

1.00
1.00

1.00
0%

Nos

186.00
44.00

1.00
1.00

1.00
0%

Nos

245.00
44.00

1.00
1.00

1.00
0%

Nos

526.00
67.00

1.00
1.00

0.14

add overheads @
Total rate per 1 No
15

Supplying and fixing PPR Ball valve as per ISI


Class - I , Indian make heavy type including cost and
conveyance of all materials , labour charges etc.
complete for finished item of work.
a) 20mm PPR Ball valve
Basic rate as per ssr item
Area allowence on labour charges

BMW-I 403
BMW-F20
0.14

add overheads @
Total rate per 1 No
b) 25mm PPR Ball valve
Basic rate as per ssr item
Area allowence on labour charges

BMW-I 404
BMW-F18
0.14

add overheads @
Total rate per 1 No

c) 40 mm PPR Ball valve


Basic rate as per ssr item
Area allowence on labour charges

BMW-I 406
BMW-F26
add overheads @

0.14

Total rate per 1 No

318 of 517

WS-Data

Sl.
No.

ITEM
CODE

DESCRIPTION

d) 50 mm PPR Ball valve


Basic rate as per ssr item
Area allowence on labour charges

BMW-I 407
BMW-F28

COEFFIC
UNIT
IENT

RATE

PER

1.00
0%

Nos

613.00
90.00

1.00
1.00

1.00
0%

Nos

992.00
112.00

1.00
1.00

1.00
0%

Nos

930.00
150.00

1.00
1.00

1.00
0%

Nos

76.00
22.00

1.00
1.00

0.14

add overheads @
Total rate per 1 No
e 63 mm PPR Ball valve
Basic rate as per ssr item
Area allowence on labour charges

BMW-I 408
BMW-F30
0.14

add overheads @
Total rate per 1 No
15

Supply and fixing of white glazed flat back bowl


urinals of size 440 mm x 265 mm x 315 mm with
internal rim flushing mm fixied with screws complete
inidan make (HS W/Parry/Neycer) conforming to IS
2556 -1995 as approved be Engineer - in - charge
12.7 mm PVC connection with brass plumber union
nuts CM Coated. including 12.70 mm push cock 1st
qulaity of approved make including supply & fixing
31.75 m dia PVC flexible waser pipe of 914.40 mm
lenght of 1st including cost and conveyance of all
materials to site labour charges etc., complete for
finished item of work for all floors

BMW-D33
BMW-D36

Basic rate as per ssr item


Area allowence on labour charges

0.14

add overheads @
Total rate per 1 No
16

Construction of brick masonry support for GI pipe


of size 304.80mm x 228.60mm x 228.60 mm in CM
(1:8) prop including plastering and finishing with
12mm thick in CM (1:5)
including cost and
conveyance of all materials and all labour charges
etc. complete
BMW-i63
BMW-i64

Basic rate as per ssr item


Area allowence on labour charges
add overheads @

0.14

Total rate per 1 No

319 of 517

WS-Data

Sl.
No.
17

ITEM
CODE

DESCRIPTION

COEFFIC
UNIT
IENT

RATE

PER

Supplying and fixing 150.00mmx100.00mm SWG


gully trap 1st class confirming to ISI 651 & 4127with
CI grating and constructing single brick masonry wall
chamber of size 20" x 14" x 12 in CM (1:6) prop.
Over a CC (1:5:10)prop. bed, and plastering 12mm
thk. in CM (1:4) prop. both inside and outside
surfaces and fitted with 304.8MM X 288.6 MM
(12"X9") CI frame and hinged cover as directed by
Engineer-in-charge including cost and conveyance of
all materials to site, labour charges etc., complete for
finished item of work.
BMW-A72
BMW-A74

Basic rate as per ssr item


Area allowence on labour charges

1.00
0%

Nos

568.00
30.00

1.00
1.00

1.00
0%

Nos

112.00
59.00

1.00
1.00

1.00
0%

Nos

24.00
19.00

1.00
1.00

0.14

add overheads @
Total rate per 1 No
18

Supplying and fixing CI Nahani traps 100 mm dia


Inlet- 75 mm (3") outlet pipe - 4 Kgs 1st quality ISI
marked conforming to IS:1729-1979 with C.P. Grating
fixing with white cement as per site requirements with
standard practice for all floors including cost and
conveyance of all materials to site, labour charges
etc., complete for finished item of work.

Basic rate as per ssr item Nahany trap

BMW-G
114
BMW-C42

Area allowence on labour charges

0.14
add overheads @
Total rate per 1 No
Basic rate as per ssr item Nahany trap cover
BMW-G
121
BMW-I13
Area allowence on labour charges
add overheads @

0.14

Total rate per 1 No


Total cost (A +B)

320 of 517

WS-Data

Sl.
No.
19

ITEM
CODE

DESCRIPTION

COEFFIC
UNIT
IENT

RATE

PER

Supplying and fixing 580 mm x 440 mm long Orissa


pan white glazed Water Closet 1st qualityISI marked
confirming to IS:2556-Part-3-1981 with "P" or "S" trap
Hindware / Parryware / Neycer with brick masonry
seat, CC squatting plate and fixing 12.70mm dia NP
Push cock 1st quality , P trap or S trap of Indian W.C.
shall be encased on CC (1:2:4) 150mm alround well
above the joint to stop leakage at the joint etc.,
complete including cost and conveyance of all
materials to site, cost of CC bed, labour charges and
seigniorage charges etc., complete for finished item
of work.
BMW-d04
BMW-d06

Basic rate as per ssr item


Area allowence on labour charges
add overheads @

0.14

add overheads @

BMW-d09
0.14

Total rate per 1 No


Providing brick masonry seat

1.00
0%

Nos 1584.00
377.00

1.00
1.00

Nos

328.00

1.00

1.00
0%

Nos 1584.00
377.00

1.00
1.00

1.00
0%

Nos 1455.00
0.00

1.00
1.00

1.00

Total cost (A +B)


20

Supplying and fixing 584.2mm long Orissa pan white


glazed Water Closet 1st qualityISI marked confirming
to IS:2556-Part-3-1981 with "P" or "S" trap Hindware /
Parryware / Neycer with brick masonry seat, CC
squatting plate and 10 litres capacity single flu
BMW-d04
Basic rate as per ssr item
BMW-d06
Area allowence on labour charges
Supply and Fixing 10 Litres capacity Single Flush
white PVC low level flushing system parryware,
slimline with internal components and short bend
including cost and conveyance of all materials to site,
all labour charges, sales and other taxes on all
materials etc., complete for finished item of work for
all floors.
Initial cost SSR item No 319
BMW-G08
Area allowence on labour charges
add overheads @
Total rate per 1 No including flush tank 10 Ltrs

321 of 517

0.14

WS-Data

Sl.
No.
20

ITEM
CODE

DESCRIPTION

COEFFIC
UNIT
IENT

RATE

PER

Providing and placing on terrace (at all floor


levels)polyetheylene water storage tank with double
layer approved brand and manufacture with cover
and suitable locking arrangement and making
necessary holes for inlet and outlets and over flow
pipes but without fittings and base support for tanks

BMW-g01
BMW-g02

Basic rate as per ssr item


Area allowence on labour charges

1.00
0%

Lit

6.00
1.00

1.00
1.00

1.00
0%

Nos

791.00
255.00

1.00
1.00

1.00
0%

Nos 7552.00
506.00

1.00
1.00

0.14

add overheads @
Total rate per 1 Ltr
21

Supplying and fixing 609.6 mm x 457.2 mm x 254 mm


RCC terrazo finished sink (or constructed at site with
50.80 mm thick) brass plug and chain incluiding CI
cantilever brackets, 31.75 mm dia PVC flexible waste
pipe 914.4 mmm length of 1st quality including cost
and conveyance fo all materials labour charges etc.,
complete for finished item of work

BMW-D40
BMW-D41

Basic rate as per ssr item


Area allowence on labour charges

0.14

add overheads @
Total rate per 1 No
22

Supply and fixing of stainless steel sink with drain


board of size 914.4 mm x 457.2 mm 1 mm thick of
indian make on cantilever barackets with including 32
mm cP waste coupling supply & fixing 31.75 mm dia
PVC flexible waste pipe of 914.4 mm longth of 1st
quality incluidng chasing brick masonry wall and
making good restoring to original srufaces etc.,
complete for finished item of work in all floors SSR
No.692
BMW-I119
BMW-I120

Basic rate as per ssr item


Area allowence on labour charges
add overheads @

0.14

Total rate per 1 No


23

Supply & Fixing of 22" dia RCC Cover for manhole


with nominal reinforecement 3" thick with hookcs for
lfifting including cost and conveyance of all materials,
labour charges etc., complete for finished tiem of
work

322 of 517

WS-Data

Sl.
No.

ITEM
COEFFIC
UNIT
CODE IENT
BMW-I130
1.00
Nos
BMW-I120
0%

DESCRIPTION
Basic rate as per ssr item
Area allowence on labour charges
add overheads @

RATE
734.00
506.00

PER
1.00
1.00

0.14

Total rate per 1 No

41

Construction of Perforated Dry Brick Masonry without


using CM and keeping vertical dry joints of 15 to
20mm as directed by the Engineer in Charge
including cost and conveyance of all amterials to site
seignorage charges, sales and other taxes, all labour
charges etc., complete item of work for Soak Pit.

Cost of Bricks
Deduct 15% for perforation
Ist class Brick layer
Man Mazdoor
Women Mazdoor
26

Rate per Cum


Supply and fixing of PVC pipes 110 mm Single
socket ISI marked confirming to IS: 1729 - 1979
of reputed make with cement caulked joints
and paintaed black with japan paint and fixing
with necessary woden blocks fixed in the
masoery walls in CM (1.5:1) including fixing of
MS clamps of necessary size and required no
of Bombay nails etc., complete including cost
and conveyance of all materials to site all
labour charges sales and other taxes on all
materials etc.,, complete for finished item of
a work all Floors
BMW-G 13
Basic rate as per ssr item
BMW-CO7
Area allowence on labour charges
add overheads @

654 Nos.

5427.01

1000

98.10 Nos.
1.28 Each
0.64 Each
1.93 Each

5427.01
420.00
320.00
320.00

-1000
1
1
1

1.00
0%

Nos

484.00
227.00

1.00
1.00

0.14

Total rate per 1 No

323 of 517

WS-Data

Sl.
No.
27

ITEM
CODE

DESCRIPTION

Supply and fixing of PVC pipes 75 mm Single


socket ISI marked confirming to IS: 1729 - 1979
of reputed make with cement caulked joints
and paintaed black with japan paint and fixing
with necessary woden blocks fixed in the
masoery walls in CM (1.5:1) including fixing of
MS clamps of necessary size and required no
of Bombay nails etc., complete including cost
and conveyance of all materials to site all
labour charges sales and other taxes on all
materials etc.,, complete for finished item of
b work all Floors
BMW-G11
Basic rate as per ssr item
BMW-CO7
Area allowence on labour charges

COEFFIC
UNIT
IENT

RATE

PER

1.00
0%

Nos

255.00
227.00

1.00
1.00

1.00
0%

Nos 3825.00
0.00

1.00
1.00

1.00
0%

Nos 2247.00
0.00

1.00
1.00

1.00
0%

Nos

1.00
1.00

0.14

add overheads @
Total rate per 1 No
28

Constructing 457.2mm x 457.2mm (1'-6" x 1'6") brick in CM (1:6) prop. Masonry inspection
chamber upto 914.4mm (3'-0") and fitted with
light weight 457.2mm x 457.2mm (1'-6" x 1"6") frame and cover of 20kg., including cost
and convenyance of all materials to site, all
labour charges, sales and otehr taxes on all
materials etc., complete for finished item of
BMW-B06
Basic rate as per ssr item
work
Area allowence on labour charges
0.14

add overheads @
Total rate per 1 No
24

Supply and fixing of 100 mm dia CI Vent pipe of 3 mts


lenth fitted with AC cowl and mosquito proof wire
mesh including cost and conveyance of all materials
to site complete for finished item of work.
BMW-H05
BMW-

Basic rate as per ssr item


Area allowence on labour charges
add overheads @
29

0.14

Total rate per 1 No


Supply and Fixing of Vent Cowls 90 mn dia with
all
necessary requirements including all
operational , incidental sales and other taxes
and all labour charges etc., complete including
cost and convenyance of all materials complete
for finished item of work for all Floors.
BMW-G 99
Basic rate as per ssr item
BMW-I37
Area allowence on labour charges

324 of 517

17.00
14.00

WS-Data

Sl.
No.

ITEM
CODE

DESCRIPTION
add overheads @

COEFFIC
UNIT
IENT

RATE

PER

0.14

Total rate per 1 No


30

Supply and Fixing of vent Cowls 63 mn dia with


all
necessary requirements including all
operational , incidental sales and other taxes
and all labour charges etc., complete including
cost and convenyance of all materials complete
for finished item of work for all Floors.
BMW-G 97
Basic rate as per ssr item
BMW-I39
Area allowence on labour charges
add overheads @

1.00
0%

Nos

9.00
11.00

1.00
1.00

1.00
0%

Nos

251.00
44.00

1.00
1.00

1.00
0%
1.00
0%

Nos 2247.00
0.00
Nos 71.00
14.00

1.00
1.00
1.00
1.00

0.14

Total rate per 1 No


31

Construction of 50.8mm thick RCM Baffle wall


with 2.267 Kg steel and rabit wire mesh in CM
(1:3) prop: with fine rendering in neat cement
in septic tank including cost and convenyance
of all materials to site, seigonarage charges
sales and othe taxes on all materials , and all
labour charges etc., complete for finished item
of work.
BMW-I95
Basic rate as per ssr item
BMW-I97
Area allowence on labour charges
add overheads @

0.14

Total rate per 1 No


32

Supply and Fixing of C.I. (Spun ) Soil waste and


ventilating pipe of 3.00 Mt length of 100mm
dia with double socket for vent over septic tank
including cost and convenyance of all materials
to site, all labour charges sales and all other
taxes on all materials etc., complete for
finished item of work.
BMW-H05
Basic rate as per ssr item
Area allowence on labour charges
BMW-I36
Basic rate as per ssr item
BMW-I37
Area allowence on labour charges
add overheads @

0.14

Total rate per 1 No

325 of 517

WS-Data

Sl.
No.
33

ITEM
CODE

DESCRIPTION

Supply and Fixing of 914.4mm x 457.2mm


Light Weight CI Manhole Frame and Cover (30
Kgs) complete for finished item of work
including cost and conveyance of all materials
to site, all labour charges, sales and other
taxes on
all materials etc., complete for
finished item of work.
Initial cost SSR item No 656
BMW-I86
Basic rate as per ssr item
BMW-I88
Area allowence on labour charges

COEFFIC
UNIT
IENT

RATE

PER

1.00
0%

Nos 2020.00
140.00

1.00
1.00

1.00
0%

Nos

1.00
1.00

1.00
0%

Nos 1455.00
0.00

0.14

add overheads @
Total rate per 1 No
34

Supply and Fixing of CI Steps for Septic Tank /


Manhole complete for finished item of work
including cost and conveyance of all materials
to site, all labour charges, sales and other
taxes on all materials etc., complete for
finished item of work.
BMW-I89
BMW-I90

Basic rate as per ssr item


Area allowence on labour charges
add overheads @

65.00
11.00

0.14

Total rate per 1 No


35

Supply and Fixing 10 Litres capacity Single


Flush white PVC low level flushing system
parryware, slimline with internal components
and short bend including cost and conveyance
of all materials to site, all labour charges, sales
and other taxes on all materials etc., complete
for finished item of work for all floors.
Initial cost SSR item No 342
BMW-G08
Basic rate as per ssr item
Area allowence on labour charges
add overheads @

1.00
1.00

0.14

Total rate per 1 No

326 of 517

WS-Data

Sl.
No.
36

ITEM
CODE

DESCRIPTION

COEFFIC
UNIT
IENT

Supply & Fixing 4" dia (110 mm) UPVC Plug


(Door) bends 1st quality ISI marked conforming
to IS : 1729-1979 with cement caulked joints
and fixing as per site requirements with
standard
practice
including
cost
and
conveyance of all materials to site, all labour
charges, sales and other taxes on all materials
etc., complete for finished item of work for all
floors
281
Initial cost SSR item No 74
BMW-G 60
Basic rate as per ssr item
BMW-C14
Area allowence on labour charges

RATE

PER

1.00
0%

Nos

107.00
72.00

1.00
1.00

1.00
0%

Nos

367.00
72.00

1.00
1.00

67.00
31.00
31.00

1.00
1

0.14

add overheads @
Total rate per 1 No
37

Supply & Fixing 3" dia (75 mm) UPVC Plug


(Door) bends 1st quality ISI marked conforming
to IS with cement caulked joints and fixing as
per site requirements with standard practice
including cost and conveyance of all materials
to site, all labour charges, sales and other
taxes on
all materials etc., complete for
finished item of work for all floors
Initial cost SSR item No 73
240
BMW-C11
Basic rate as per ssr item
BMW-C14
Area allowence on labour charges
0.14

add overheads @
Total rate per 1 No
38

Manufacture, supply, & delivery of 50mm outer


dia HDPE pipes conforming to IS 4984 - 1995
at 6Kg/Sqcm. including cost and conveyance of
all materials to site, all labour charges, sales
and other taxes on all materials etc., complete
for finished item of and ,Laying jointing of
HDPE pipes as per BIS No. 7634 part -II/75 and
specials /fittings including excavation of
trenches up to 0.5 mts depth in all soils except
rock requires blasting and refilling trenches
after laying and jointing of pipes as per ssr ite

Basic rate as per ssr item

labour charges for laying and jointing


Area allowence on labour charges

TABLE
16(1) page
52
12 (b) page 5

327 of 517

1.00
RMT
1 RMT
0%

WS-Data

Sl.
No.

ITEM
COEFFIC
UNIT
CODE IENT
0.14

DESCRIPTION
add overheads @

RATE

PER

Total rate per 1Rmt


39

Construction
of
60,000
liters
capacity
OHSR(VRCC) with 15.0 mts staging without
seismic analysis including fixtures OF rcc OR
ALLUMINIUM LADDER INSIDE 0.45 Mtrs wide,
MS ladder on the outside . Lighting including
condutor & earthing etc., RCC ventilators with
copper or stainless steel skyproof mesh,
Manhole frame and cover 0.75x0.75mts with
frame as per IS specifications (light duty - 2
Nos), Ralling with 32mm dia GI pipes (A class in
2 nos alround OHSR fixed in RCC (1:2:4) poles
of size 100x75x75mm with 1.50mts intervals
alround periphery on top of the OHSR for smaller
capacities,Water level indicator of good quality
with ebonite /copper float approved pattern - 1 no

a . RCC or allumininum ladder inside 0.45mts


wide
b. MS ladder on the outside
c. Lighting including condutor & earthing etc.,
d. RCC ventilators with copper or stainless steel
skyproof mesh
e. Manhole frame and cover 0.75x0.75mts with
frame as per IS specifications (light duty - 2 Nos)
f. Ralling with 32mm dia GI pipes (A class in 2
nos alround OHSR fixed in RCC (1:2:4) poles of
size 100x75x75mm with 1.50mts intervals
alround periphery on top of the OHSR for smaller
capacities
g. Water level indicator of good quality with
ebonite /copper float approved pattern - 1 no
1.00

Add for difference in cost of cement

Lt

30.26

1.00

30.26*(5760-6400)*0.00007 =
328 of 517

WS-Data

Sl.
No.

ITEM
CODE

DESCRIPTION

Add for difference in cost of steel

COEFFIC
UNIT
IENT

RATE

PER

30.26*(32000-42000)*0.00002=

Add 10% extra for rural area allowence


0.13615

add overheads @
Total rate per 1 Lt
40 a) Supply and fixing of the following fixtures

a. 80mm dia x 2.00 mts CI D/F pipes


Page 380
table 26
add overheads @
0.13615

1.00

Kg

1.00

Kg

1.00

Kg

73.7

1.00

Total rate per 1 Kg


b) b. 80mm dia x 1.00 CI D/F pipes initiate cost only
Page 380
table 26
add overheads @
0.14

73.70

1.00

Total rate per 1 Kg

c. 80mm dia x flonged spigot CI tail pieces


Page 380
table 26
add overheads @
0.14

73.70

1.00

Total rate per 1 Kg

d. 80mm dia CI sluice valves


page 380
add overheads @
0.14

1.00

nos 10500.00

1.00

Total rate per 1 Nos

e. 80mm dia CI duct foot bends


Page 380
table 26
add overheads @
0.14

73.70

1.00

Kg

1.00

table 31
add overheads @
0.14

1.00

kg

103.00

1.00

table 31
0.14

1.00

Kg

123.00

1.00

Total rate per 1 Kg

f. Rubber packing 3/6mm thick

Total rate per 1 Kg

g. Bolts & nuts


add overheads @
Total rate per 1 Kg

329 of 517

WS-Data

Sl.
No.

ITEM
CODE

DESCRIPTION

COEFFIC
UNIT
IENT

RATE

PER

Supplying and fixing of European Water Closet of 1st


quality confirming to IS: 2556-Part-2-1973 of
Hindustan / Neycer or Parryware make white gllazed
with 'S' trap lying and fixing best Indian make plastic
seal and lid for European water closets with rubb
Basic rate as per ssr item
Plastic seat & lid as per IS 2548-1996
Supply and Fixing 10 Litres capacity Single Flush
white PVC low level flushing system parryware,
slimline with internal components and short bend
including cost and conveyance of all materials to site,
all labour charges, sales and other taxes on all
materials etc., complete for finished item of work for
all floors.

BMW-d14

1.00

Nos 1964.00

1.00

BMW-d 16

1.00

Nos

981.00

1.00

BMW-G08

1.00

Nos 1455.00

1.00

1.00

Nos

271.00

1.00

1.00

Nos

474.00

1.00

1.00

Nos

50.00

1.00

0.14

add overheads @
Total cost (A +B)
Supply and Fixing 12.7 mm dia NP push cock Ist
quality including cost and conveyance of all materials
to site, all labour charges, sales and other taxes on
all materials etc., complete for finished item of work
for all floors.

BMW-E 29
0.14

add overheads @
Total cost (A +B)
Supply and Fixing angle stop cock 12.7 mm dia first
quality Indian Make heavy duty Seiko/ Senior/ Nice or
equivalent including cost and conveyance of all
materials to site, labour charges etc., complete for
finished item of work. 178 - BMW E.05

BMW-E 01
0.14

add overheads @
Total cost (A +B)
Supply and FixingSupplying and fixing CP Jollys of
approved make with complete including cost and
conveyance of all materials, labour charges for fixing
etc., complete for finished item of work in all floors
663 - BMW I.69

BMW-I 69

add overheads @

330 of 517

0.14

WS-Data

Sl.
No.

ITEM
CODE

DESCRIPTION

COEFFIC
UNIT
IENT

RATE

PER

Total cost (A +B)


41

Supplying & fixing GI pipe Medium Grade properties & weight as per IS 1239 ISI mark with GI fittings in ground or on wall including cost of te
reducers, couplings, running joints, union flanges, unions etc. with necessary excavation in all types of soils except rock requiring blasting, refillin
masonry walls and making good the walls & floors to the original surface and fixing MS clamps on TW blocks on walls including cost and conveya
and labour charges complete for finished item of work.
a) 15mm Nominal bore
Basic rate as per ssr item

BMW-F79

Area allowence on labour charges

BMW-F80
add overheads @

1.00 Rmt

204.00

1.00

Rmt

41.00

1.00

1.00 Rmt

227.00

1.00

Rmt

41.00

1.00

1.00 Rmt

297.00

1.00

Rmt

41.00

1.00

1.00 Rmt

466.00

1.00

Rmt

44.00

1.00

1.00 Rmt

466.00

1.00

Rmt

44.00

1.00

1.00 Rmt

503.00

1.00

Rmt

67.00

1.00

1.00 Rmt

892.00

1.00

Rmt

67.00

1.00

0%
14.00%

Total rate per 1 RMT


b) 20mm Nominal bore
Basic rate as per ssr item

BMW-F81

Area allowence on labour charges

BMW-F82
add overheads @

0%
14.00%

Total rate per 1 RMT


c) 25mm Nominal bore
Basic rate as per ssr item

BMW-F83

Area allowence on labour charges

BMW-F84
add overheads @

0%
14.00%

Total rate per 1 RMT


D 32mm Nominal bore
Basic rate as per ssr item

BMW-F87

Area allowence on labour charges

BMW-F88
add overheads @

0%
14.00%

Total rate per 1 RMT


D 40mm Nominal bore
Basic rate as per ssr item

BMW-F87

Area allowence on labour charges

BMW-F88
add overheads @

0%
14.00%

Total rate per 1 RMT


E 50mm Nominal bore
Basic rate as per ssr item

BMW-F89

Area allowence on labour charges

BMW-F90
add overheads @

0%
14.00%

Total rate per 1 RMT


F 65mm Nominal bore
Basic rate as per ssr item

BMW-F91

Area allowence on labour charges

BMW-F90
add overheads @

0%
14.00%

Total rate per 1 RMT

331 of 517

WS-Data

Sl.
No.
1

ITEM
CODE

DESCRIPTION

COEFFIC
UNIT
IENT

RATE

PER

Supplying and fixing Gunmetal Gate ( GM peet )


valve as per IS-778 Class - I , Indian make heavy
type including cost and conveyance of all materials ,
labour charges etc. complete for finished item of
work.
15 mm dia nominal bore
Basic rate as per ssr item
Area allowence on labour charges

BMW-F21
BMW-F22

1.00

Nos

0%

636.00

1.00

44.00

1.00

858.00

1.00

44.00

1.00

1233.00

1.00

44.00

1.00

2533.00

1.00

67.00

1.00

3711.00

1.00

90.00

1.00

0.14

add overheads @
Total rate per 1 No
15

Supplying and fixing Gunmetal Gate ( GM peet )


valve as per IS-778 Class - I , Indian make heavy
type including cost and conveyance of all materials ,
labour charges etc. complete for finished item of
work.
a) 20mm GM peet valve
Basic rate as per ssr item
Area allowence on labour charges

BMW-F19
BMW-F20

1.00

Nos

0%

0.14

add overheads @
Total rate per 1 No
b) 25mm GM peet valve
Basic rate as per ssr item
Area allowence on labour charges

BMW-F17
BMW-F18

1.00

Nos

0%

0.14

add overheads @
Total rate per 1 No

c) 40mm GM peet valve


Basic rate as per ssr item
Area allowence on labour charges

BMW-F25
BMW-F26

1.00

Nos

0%

0.14

add overheads @
Total rate per 1 No

d) 50mm GM peet valve


Basic rate as per ssr item
Area allowence on labour charges

BMW-F27
BMW-F28

add overheads @

1.00

0%

Nos

0.14

Total rate per 1 No

332 of 517

WS-Data

Sl.
No.

ITEM
CODE

DESCRIPTION
e 65 mm GM peet valve
Basic rate as per ssr item
Area allowence on labour charges

COEFFIC
UNIT
IENT

BMW-F29
BMW-F30

1.00

RATE
Nos

0%

PER

5730.00

1.00

112.00

1.00

891.00
76.00

1.00
1.00

0.14

add overheads @
Total rate per 1 No

21

Supply and fixing of European Water Closet of 1st


quality conforming to IS: 2556-Part-2-1973 of
Hindustan/Neycer of Parryware make white glazed
with 'P' trap.
BMW-D16
BMW-D17

Basic rate as per ssr item


Area allowence on labour charges
add overheads @

1.00
0%

Nos

0.14

Total rate per 1 No

Asst. Exe.Engineer
APEWIDC, Kuppam

Dy. Executive Engineer


APEWIDC, Madanapalli

Executive Engineer
APEWIDC, Chittoor

Superintending Engineer
APEWIDC, Kadapa

333 of 517

WS-Data

UNIT

Rmt
0.00

Rmt
0.00

Rmt
0.00

Rmt
0.00

Amount
(Rs.)

408.00
0.00
408.00
55.55
463.55
680.00
0.00
680.00
92.58
772.60
466.00
0.00
466.00
63.45
529.45
614.00
0.00
614.00
83.60
697.60

334 of 517

WS-Data

UNIT

Nos

Amount
(Rs.)

6237.00
0.00

0.00
6237.00
849.17
7086.20

335 of 517

WS-Data

UNIT

Nos
0.00

Amount
(Rs.)

10181.00
0.00
10181.00
1386.14
11567.15

336 of 517

WS-Data

UNIT
Nos
0.00

Nos
0.00

Nos
0.00

Amount
(Rs.)
10590.00
0.00
10590.00
1441.83
12031.85

6730.00
0.00
6730.00
916.29
7646.30

568.00
0.00
568.00

337 of 517

WS-Data

UNIT

Nos
0.00

Nos
0.00

Nos
0.00

Nos
0.00

Nos
0.00

Amount
(Rs.)
77.33
645.35

1782.00
0.00
1782.00
242.62
2024.65
102.00
0.00
102.00
13.89
115.90
474.00
0.00
474.00
64.54
538.55

237.00
0.00
237.00
32.27
269.30

26.00
0.00
26.00
3.54

338 of 517

WS-Data

UNIT
Rs

Nos
0.00

Nos
0.00

Nos
0.00

Nos
0.00

Amount
(Rs.)
29.55
2977.95

243.00
0.00
243.00
33.08
276.10

513.00
0.00
513.00
69.84
582.85

164.00
0.00
164.00
22.33
186.35

258.00
0.00
258.00
35.13

339 of 517

WS-Data

UNIT

Nos
0.00

RMT
0.00

Amount
(Rs.)
293.15

407.00
0.00
407.00
55.41
462.45

135.00
0.00
135.00
18.38
153.40

RMT
RM

161.33
0.00
161.33
21.97
183.35

RMT
RM

384.33
0.00
384.33
52.33
436.70

340 of 517

WS-Data

UNIT

Amount
(Rs.)

Rmt

141.00
0.00
141.00
19.20
160.20

Rmt
Rmt

160.00
0.00
160.00
21.78
181.80

RMT
Rmt

212.00
0.00
212.00
28.86
240.90

RMT
Rmt

360.00
0.00
360.00
49.01
409.05

RMT
Rmt

525.00
0.00
525.00
71.48
596.50

341 of 517

WS-Data

UNIT

RMT
Rmt

Amount
(Rs.)

189.00
0.00
189.00
25.73
214.75

Nos
0.00

Nos
0.00

Nos
0.00

Nos
0.00

636.00
0.00
636.00
86.59
722.60

186.00
0.00
186.00
25.32
211.35

245.00
0.00
245.00
33.36
278.40

526.00
0.00
526.00
71.61
597.65

342 of 517

WS-Data

UNIT

Nos
0.00

Nos
0.00

Nos
0.00

Nos
0.00

Amount
(Rs.)

613.00
0.00
613.00
83.46
696.50

992.00
0.00
992.00
135.06
1127.10

930.00
0.00
930.00
126.62
1056.65

76.00
0.00
76.00
10.35
86.35

343 of 517

WS-Data

UNIT

Nos
0.00

Nos
0.00

Nos
0.00

Amount
(Rs.)

568.00
0.00
568.00
77.33
645.35

112.00
0.00
112.00
15.25
127.25
24.00
0.00
24.00
3.27
27.30

154.55

344 of 517

WS-Data

UNIT

Nos
0.00

Nos

Amount
(Rs.)

1584.00
0.00
1584.00
215.66
1799.70
328.00
44.66

2172.36

Nos
0.00

Nos
0.00

1584.00
0.00

1455.00
0.00
3039.00
413.76
3452.80

345 of 517

WS-Data

UNIT

Lit
0.00

Nos
0.00

Nos
0.00

Amount
(Rs.)

6.00
0.00
6.00
0.82
6.85

791.00
0.00
791.00
107.69
898.70

7552.00
0.00
7552.00
1028.20
8580.20

346 of 517

WS-Data

UNIT
Nos
0.00

Amount
(Rs.)
734.00
0.00
734.00
99.93
833.95

Nos.

3549.26

Nos.
Each
Each
Each

-532.39
537.60
204.80
617.60
4376.87

Nos
0.00

484.00
0.00
484.00
65.90
549.90

347 of 517

WS-Data

UNIT

Nos
0.00

Nos
0.00

Nos
0.00

Nos
0.00

Amount
(Rs.)

255.00
0.00
255.00
34.72
289.75

3825.00
0.00
3825.00
520.77
4345.80

2247.00
0.00
2247.00
305.93
2552.95

17.00
0.00

348 of 517

WS-Data

UNIT

Nos
0.00

Nos
0.00

Nos
0.00
Nos
0.00

Amount
(Rs.)
17.00
2.31
19.35

9.00
0.00
9.00
1.23
10.25

251.00
0.00
251.00
34.17
285.20

2247.00
0.00
71.00
0.00
2318.00
315.60
2633.60

349 of 517

WS-Data

UNIT

Nos
0.00

Nos
0.00

Nos
0.00

Amount
(Rs.)

2020.00
0.00
2020.00
275.02
2295.05

65.00
0.00
65.00
8.85
73.85

1455.00
0.00
1455.00
198.10
1653.10

350 of 517

WS-Data

UNIT

Nos
0.00

Nos
0.00

RMT
RMT

Amount
(Rs.)

107.00
0.00
107.00
14.57
121.60

367.00
0.00
367.00
49.97
417.00

67.00
31.00
0.00
98.00

351 of 517

WS-Data

UNIT

Amount
(Rs.)
13.34
111.35

0.104

Lt

30.26

-1.36
352 of 517

WS-Data

UNIT

Amount
(Rs.)

-6.05
22.85
0.00
22.85
3.11
26.00

Kg

73.70
10.03
83.75

Kg

73.70
10.03
83.75

Kg

73.70
10.03
83.75

nos

10500.00
1429.58
11929.60

Kg

73.70
10.03
83.75

kg

103.00
14.02
117.05

Kg

123.00
16.75
139.75

353 of 517

WS-Data

UNIT

Amount
(Rs.)

Nos

1964.00

Nos

981.00

Nos

1455.00
4400.00
599.06

4999.06

Nos

271.00
36.90

307.90

Nos

474.00
64.54

538.54

Nos

50.00
6.81

354 of 517

WS-Data

UNIT

Amount
(Rs.)

56.81

n wall including cost of tees, elbows, bends,


k requiring blasting, refilling, chiselling
ncluding cost and conveyance of all materials

Rmt

204.00
0.00
204.00
28.56
232.60

Rmt
Rmt

227.00
0.00
227.00
31.78
258.80

RMT
Rmt

297.00
0.00
297.00
41.58
338.60

RMT
Rmt

466.00
0.00
466.00
65.24
531.25

RMT
Rmt

466.00
0.00
466.00
65.24
531.25

RMT
Rmt

503.00
0.00
503.00
70.42
573.45

RMT
Rmt

892.00
0.00
892.00
124.88
1016.90

355 of 517

WS-Data

UNIT

Nos

Amount
(Rs.)

636.00
0.00

0.00

636.00
86.59
722.60

Nos

858.00
0.00

0.00

858.00
116.82
974.85

Nos

1233.00
0.00

0.00

1233.00
167.87
1400.90

Nos

2533.00
0.00

0.00

2533.00
344.87
2877.90

Nos

3711.00
0.00

0.00

3711.00
505.25
4216.25

356 of 517

WS-Data

UNIT
Nos

Amount
(Rs.)
5730.00

0.00

0.00

5730.00
780.14
6510.15

Nos
0.00

891.00
0.00
891.00
121.31
1012.35

utive Engineer
C, Madanapalli

nding Engineer
DC, Kadapa

357 of 517

WS-Data

Sl.No

###

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51

CONVEYANCE CHARGES AS PER COMMON SSR 2013-14


Lead in Earth/Sand/G Rubble/Size Cement/Steel/R
PCC
Water
Kms ravel/Murrum/
Stone/Cut
CC poles/A.C & Slabs/Shabad
Lime/Surki
Stone/Coarse
G.I
Slabs/CC &
aggregates
Sheets/Packed
Laterite
materials
Blocks/Wood
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
22.00
23.00
24.00
25.00
26.00
27.00
28.00
29.00
30.00
31.00
32.00
33.00
34.00
35.00
36.00
37.00
38.00
39.00
40.00
41.00
42.00
43.00
44.00
45.00
46.00
47.00
48.00
49.00
50.00
51.00

0.00
10.92
23.65
34.57
45.49
56.41
67.33
78.25
89.17
100.09
111.01
121.93
132.85
143.77
154.69
165.61
176.53
187.45
198.37
209.29
220.21
231.13
242.05
252.97
263.89
274.81
285.73
296.65
307.57
318.49
327.59
336.69
345.79
354.89
363.99
373.09
382.19
391.29
400.39
409.49
418.59
427.69
436.79
445.89
454.99
464.09
473.19
482.29
491.39
500.49
509.59

0.00
10.92
23.65
34.57
45.49
56.41
67.33
78.25
89.17
100.09
111.01
121.93
132.85
143.77
154.69
165.61
176.53
187.45
198.37
209.29
220.21
231.13
242.05
252.97
263.89
274.81
285.73
296.65
307.57
318.49
327.59
336.69
345.79
354.89
363.99
373.09
382.19
391.29
400.39
409.49
418.59
427.69
436.79
445.89
454.99
464.09
473.19
482.29
491.39
500.49
509.59

0.00
6.82
14.78
21.60
28.43
35.25
42.07
48.89
55.71
62.53
69.35
76.17
82.99
89.81
96.63
103.45
110.27
117.09
123.91
130.73
137.55
144.37
151.19
158.01
164.83
171.65
178.47
185.29
192.11
198.93
204.62
210.31
216.00
221.69
227.38
233.07
238.76
244.45
250.14
255.83
261.52
267.21
272.90
278.59
284.28
289.97
295.66
301.35
307.04
312.73
318.42

0.00
16.05
34.78
50.83
66.88
82.93
98.98
115.03
131.08
147.13
163.18
179.23
195.28
211.33
227.38
243.43
259.48
275.53
291.58
307.63
323.68
339.73
355.78
371.83
387.88
403.93
419.98
436.03
452.08
468.13
481.51
494.89
508.27
521.65
535.03
548.41
561.79
575.17
588.55
601.93
615.31
628.69
642.07
655.45
668.83
682.21
695.59
708.97
722.35
735.73
749.11

0.00
6.49
14.06
20.55
27.05
33.54
40.03
46.52
53.01
59.50
65.99
72.48
78.97
85.46
91.95
98.44
104.93
111.42
117.91
124.40
130.89
137.38
143.87
150.36
156.85
163.34
169.83
176.32
182.81
189.30
194.71
200.12
205.53
210.94
216.35
221.76
227.17
232.58
237.99
243.40
248.81
254.22
259.63
265.04
270.45
275.86
281.27
286.68
292.09
297.50
302.91

Bricks

0.00
17.54
38.00
55.54
73.09
90.63
108.17
125.71
143.25
160.79
178.33
195.87
213.41
230.95
248.49
266.03
283.57
301.11
318.65
336.19
353.73
371.27
388.81
406.35
423.89
441.43
458.97
476.51
494.05
511.59
526.21
540.83
555.45
570.07
584.69
599.31
613.93
628.55
643.17
657.79
672.41
687.03
701.65
716.27
730.89
745.51
760.13
774.75
789.37
803.99
818.61

52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108

52.00
53.00
54.00
55.00
56.00
57.00
58.00
59.00
60.00
61.00
62.00
63.00
64.00
65.00
66.00
67.00
68.00
69.00
70.00
71.00
72.00
73.00
74.00
75.00
76.00
77.00
78.00
79.00
80.00
81.00
82.00
83.00
84.00
85.00
86.00
87.00
88.00
89.00
90.00
91.00
92.00
93.00
94.00
95.00
96.00
97.00
98.00
99.00
100.00
101.00
102.00
103.00
104.00
105.00
106.00
107.00
108.00

518.69
527.79
536.89
545.99
555.09
564.19
573.29
582.39
591.49
600.59
609.69
618.79
627.89
636.99
646.09
655.19
664.29
673.39
682.49
691.59
700.69
709.79
718.89
727.99
737.09
746.19
755.29
764.39
773.49
782.59
791.69
800.79
809.89
818.99
828.09
837.19
846.29
855.39
864.49
873.59
882.69
891.79
900.89
909.99
919.09
928.19
937.29
946.39
955.49
964.59
973.69
982.79
991.89
1000.99
1010.09
1019.19
1028.29

518.69
527.79
536.89
545.99
555.09
564.19
573.29
582.39
591.49
600.59
609.69
618.79
627.89
636.99
646.09
655.19
664.29
673.39
682.49
691.59
700.69
709.79
718.89
727.99
737.09
746.19
755.29
764.39
773.49
782.59
791.69
800.79
809.89
818.99
828.09
837.19
846.29
855.39
864.49
873.59
882.69
891.79
900.89
909.99
919.09
928.19
937.29
946.39
955.49
964.59
973.69
982.79
991.89
1000.99
1010.09
1019.19
1028.29

324.11
329.80
335.49
341.18
346.87
352.56
358.25
363.94
369.63
375.32
381.01
386.70
392.39
398.08
403.77
409.46
415.15
420.84
426.53
432.22
437.91
443.60
449.29
454.98
460.67
466.36
472.05
477.74
483.43
489.12
494.81
500.50
506.19
511.88
517.57
523.26
528.95
534.64
540.33
546.02
551.71
557.40
563.09
568.78
574.47
580.16
585.85
591.54
597.23
602.92
608.61
614.30
619.99
625.68
631.37
637.06
642.75

762.49
775.87
789.25
802.63
816.01
829.39
842.77
856.15
869.53
882.91
896.29
909.67
923.05
936.43
949.81
963.19
976.57
989.95
1003.33
1016.71
1030.09
1043.47
1056.85
1070.23
1083.61
1096.99
1110.37
1123.75
1137.13
1150.51
1163.89
1177.27
1190.65
1204.03
1217.41
1230.79
1244.17
1257.55
1270.93
1284.31
1297.69
1311.07
1324.45
1337.83
1351.21
1364.59
1377.97
1391.35
1404.73
1418.11
1431.49
1444.87
1458.25
1471.63
1485.01
1498.39
1511.77

308.32
313.73
319.14
324.55
329.96
335.37
340.78
346.19
351.60
357.01
362.42
367.83
373.24
378.65
384.06
389.47
394.88
400.29
405.70
411.11
416.52
421.93
427.34
432.75
438.16
443.57
448.98
454.39
459.80
465.21
470.62
476.03
481.44
486.85
492.26
497.67
503.08
508.49
513.90
519.31
524.72
530.13
535.54
540.95
546.36
551.77
557.18
562.59
568.00
573.41
578.82
584.23
589.64
595.05
600.46
605.87
611.28

833.23
847.85
862.47
877.09
891.71
906.33
920.95
935.57
950.19
964.81
979.43
994.05
1008.67
1023.29
1037.91
1052.53
1067.15
1081.77
1096.39
1111.01
1125.63
1140.25
1154.87
1169.49
1184.11
1198.73
1213.35
1227.97
1242.59
1257.21
1271.83
1286.45
1301.07
1315.69
1330.31
1344.93
1359.55
1374.17
1388.79
1403.41
1418.03
1432.65
1447.27
1461.89
1476.51
1491.13
1505.75
1520.37
1534.99
1549.61
1564.23
1578.85
1593.47
1608.09
1622.71
1637.33
1651.95

109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165

109.00
110.00
111.00
112.00
113.00
114.00
115.00
116.00
117.00
118.00
119.00
120.00
121.00
122.00
123.00
124.00
125.00
126.00
127.00
128.00
129.00
130.00
131.00
132.00
133.00
134.00
135.00
136.00
137.00
138.00
139.00
140.00
141.00
142.00
143.00
144.00
145.00
146.00
147.00
148.00
149.00
150.00
151.00
152.00
153.00
154.00
155.00
156.00
157.00
158.00
159.00
160.00
161.00
162.00
163.00
164.00
165.00

1037.39
1046.49
1055.59
1064.69
1073.79
1082.89
1091.99
1101.09
1110.19
1119.29
1128.39
1137.49
1146.59
1155.69
1164.79
1173.89
1182.99
1192.09
1201.19
1210.29
1219.39
1228.49
1237.59
1246.69
1255.79
1264.89
1273.99
1283.09
1292.19
1301.29
1310.39
1319.49
1328.59
1337.69
1346.79
1355.89
1364.99
1374.09
1383.19
1392.29
1401.39
1410.49
1419.59
1428.69
1437.79
1446.89
1455.99
1465.09
1474.19
1483.29
1492.39
1501.49
1510.59
1519.69
1528.79
1537.89
1546.99

1037.39
1046.49
1055.59
1064.69
1073.79
1082.89
1091.99
1101.09
1110.19
1119.29
1128.39
1137.49
1146.59
1155.69
1164.79
1173.89
1182.99
1192.09
1201.19
1210.29
1219.39
1228.49
1237.59
1246.69
1255.79
1264.89
1273.99
1283.09
1292.19
1301.29
1310.39
1319.49
1328.59
1337.69
1346.79
1355.89
1364.99
1374.09
1383.19
1392.29
1401.39
1410.49
1419.59
1428.69
1437.79
1446.89
1455.99
1465.09
1474.19
1483.29
1492.39
1501.49
1510.59
1519.69
1528.79
1537.89
1546.99

648.44
654.13
659.82
665.51
671.20
676.89
682.58
688.27
693.96
699.65
705.34
711.03
716.72
722.41
728.10
733.79
739.48
745.17
750.86
756.55
762.24
767.93
773.62
779.31
785.00
790.69
796.38
802.07
807.76
813.45
819.14
824.83
830.52
836.21
841.90
847.59
853.28
858.97
864.66
870.35
876.04
881.73
887.42
893.11
898.80
904.49
910.18
915.87
921.56
927.25
932.94
938.63
944.32
950.01
955.70
961.39
967.08

1525.15
1538.53
1551.91
1565.29
1578.67
1592.05
1605.43
1618.81
1632.19
1645.57
1658.95
1672.33
1685.71
1699.09
1712.47
1725.85
1739.23
1752.61
1765.99
1779.37
1792.75
1806.13
1819.51
1832.89
1846.27
1859.65
1873.03
1886.41
1899.79
1913.17
1926.55
1939.93
1953.31
1966.69
1980.07
1993.45
2006.83
2020.21
2033.59
2046.97
2060.35
2073.73
2087.11
2100.49
2113.87
2127.25
2140.63
2154.01
2167.39
2180.77
2194.15
2207.53
2220.91
2234.29
2247.67
2261.05
2274.43

616.69
622.10
627.51
632.92
638.33
643.74
649.15
654.56
659.97
665.38
670.79
676.20
681.61
687.02
692.43
697.84
703.25
708.66
714.07
719.48
724.89
730.30
735.71
741.12
746.53
751.94
757.35
762.76
768.17
773.58
778.99
784.40
789.81
795.22
800.63
806.04
811.45
816.86
822.27
827.68
833.09
838.50
843.91
849.32
854.73
860.14
865.55
870.96
876.37
881.78
887.19
892.60
898.01
903.42
908.83
914.24
919.65

1666.57
1681.19
1695.81
1710.43
1725.05
1739.67
1754.29
1768.91
1783.53
1798.15
1812.77
1827.39
1842.01
1856.63
1871.25
1885.87
1900.49
1915.11
1929.73
1944.35
1958.97
1973.59
1988.21
2002.83
2017.45
2032.07
2046.69
2061.31
2075.93
2090.55
2105.17
2119.79
2134.41
2149.03
2163.65
2178.27
2192.89
2207.51
2222.13
2236.75
2251.37
2265.99
2280.61
2295.23
2309.85
2324.47
2339.09
2353.71
2368.33
2382.95
2397.57
2412.19
2426.81
2441.43
2456.05
2470.67
2485.29

166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222

166.00
167.00
168.00
169.00
170.00
171.00
172.00
173.00
174.00
175.00
176.00
177.00
178.00
179.00
180.00
181.00
182.00
183.00
184.00
185.00
186.00
187.00
188.00
189.00
190.00
191.00
192.00
193.00
194.00
195.00
196.00
197.00
198.00
199.00
200.00
201.00
202.00
203.00
204.00
205.00
206.00
207.00
208.00
209.00
210.00
211.00
212.00
213.00
214.00
215.00
216.00
217.00
218.00
219.00
220.00
221.00
222.00

1556.09
1565.19
1574.29
1583.39
1592.49
1601.59
1610.69
1619.79
1628.89
1637.99
1647.09
1656.19
1665.29
1674.39
1683.49
1692.59
1701.69
1710.79
1719.89
1728.99
1738.09
1747.19
1756.29
1765.39
1774.49
1783.59
1792.69
1801.79
1810.89
1819.99
1829.09
1838.19
1847.29
1856.39
1865.49
1874.59
1883.69
1892.79
1901.89
1910.99
1920.09
1929.19
1938.29
1947.39
1956.49
1965.59
1974.69
1983.79
1992.89
2001.99
2011.09
2020.19
2029.29
2038.39
2047.49
2056.59
2065.69

1556.09
1565.19
1574.29
1583.39
1592.49
1601.59
1610.69
1619.79
1628.89
1637.99
1647.09
1656.19
1665.29
1674.39
1683.49
1692.59
1701.69
1710.79
1719.89
1728.99
1738.09
1747.19
1756.29
1765.39
1774.49
1783.59
1792.69
1801.79
1810.89
1819.99
1829.09
1838.19
1847.29
1856.39
1865.49
1874.59
1883.69
1892.79
1901.89
1910.99
1920.09
1929.19
1938.29
1947.39
1956.49
1965.59
1974.69
1983.79
1992.89
2001.99
2011.09
2020.19
2029.29
2038.39
2047.49
2056.59
2065.69

972.77
978.46
984.15
989.84
995.53
1001.22
1006.91
1012.60
1018.29
1023.98
1029.67
1035.36
1041.05
1046.74
1052.43
1058.12
1063.81
1069.50
1075.19
1080.88
1086.57
1092.26
1097.95
1103.64
1109.33
1115.02
1120.71
1126.40
1132.09
1137.78
1143.47
1149.16
1154.85
1160.54
1166.23
1171.92
1177.61
1183.30
1188.99
1194.68
1200.37
1206.06
1211.75
1217.44
1223.13
1228.82
1234.51
1240.20
1245.89
1251.58
1257.27
1262.96
1268.65
1274.34
1280.03
1285.72
1291.41

2287.81
2301.19
2314.57
2327.95
2341.33
2354.71
2368.09
2381.47
2394.85
2408.23
2421.61
2434.99
2448.37
2461.75
2475.13
2488.51
2501.89
2515.27
2528.65
2542.03
2555.41
2568.79
2582.17
2595.55
2608.93
2622.31
2635.69
2649.07
2662.45
2675.83
2689.21
2702.59
2715.97
2729.35
2742.73
2756.11
2769.49
2782.87
2796.25
2809.63
2823.01
2836.39
2849.77
2863.15
2876.53
2889.91
2903.29
2916.67
2930.05
2943.43
2956.81
2970.19
2983.57
2996.95
3010.33
3023.71
3037.09

925.06
930.47
935.88
941.29
946.70
952.11
957.52
962.93
968.34
973.75
979.16
984.57
989.98
995.39
1000.80
1006.21
1011.62
1017.03
1022.44
1027.85
1033.26
1038.67
1044.08
1049.49
1054.90
1060.31
1065.72
1071.13
1076.54
1081.95
1087.36
1092.77
1098.18
1103.59
1109.00
1114.41
1119.82
1125.23
1130.64
1136.05
1141.46
1146.87
1152.28
1157.69
1163.10
1168.51
1173.92
1179.33
1184.74
1190.15
1195.56
1200.97
1206.38
1211.79
1217.20
1222.61
1228.02

2499.91
2514.53
2529.15
2543.77
2558.39
2573.01
2587.63
2602.25
2616.87
2631.49
2646.11
2660.73
2675.35
2689.97
2704.59
2719.21
2733.83
2748.45
2763.07
2777.69
2792.31
2806.93
2821.55
2836.17
2850.79
2865.41
2880.03
2894.65
2909.27
2923.89
2938.51
2953.13
2967.75
2982.37
2996.99
3011.61
3026.23
3040.85
3055.47
3070.09
3084.71
3099.33
3113.95
3128.57
3143.19
3157.81
3172.43
3187.05
3201.67
3216.29
3230.91
3245.53
3260.15
3274.77
3289.39
3304.01
3318.63

223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279

223.00
224.00
225.00
226.00
227.00
228.00
229.00
230.00
231.00
232.00
233.00
234.00
235.00
236.00
237.00
238.00
239.00
240.00
241.00
242.00
243.00
244.00
245.00
246.00
247.00
248.00
249.00
250.00
251.00
252.00
253.00
254.00
255.00
256.00
257.00
258.00
259.00
260.00
261.00
262.00
263.00
264.00
265.00
266.00
267.00
268.00
269.00
270.00
271.00
272.00
273.00
274.00
275.00
276.00
277.00
278.00
279.00

2074.79
2083.89
2092.99
2102.09
2111.19
2120.29
2129.39
2138.49
2147.59
2156.69
2165.79
2174.89
2183.99
2193.09
2202.19
2211.29
2220.39
2229.49
2238.59
2247.69
2256.79
2265.89
2274.99
2284.09
2293.19
2302.29
2311.39
2320.49
2329.59
2338.69
2347.79
2356.89
2365.99
2375.09
2384.19
2393.29
2402.39
2411.49
2420.59
2429.69
2438.79
2447.89
2456.99
2466.09
2475.19
2484.29
2493.39
2502.49
2511.59
2520.69
2529.79
2538.89
2547.99
2557.09
2566.19
2575.29
2584.39

2074.79
2083.89
2092.99
2102.09
2111.19
2120.29
2129.39
2138.49
2147.59
2156.69
2165.79
2174.89
2183.99
2193.09
2202.19
2211.29
2220.39
2229.49
2238.59
2247.69
2256.79
2265.89
2274.99
2284.09
2293.19
2302.29
2311.39
2320.49
2329.59
2338.69
2347.79
2356.89
2365.99
2375.09
2384.19
2393.29
2402.39
2411.49
2420.59
2429.69
2438.79
2447.89
2456.99
2466.09
2475.19
2484.29
2493.39
2502.49
2511.59
2520.69
2529.79
2538.89
2547.99
2557.09
2566.19
2575.29
2584.39

1297.10
1302.79
1308.48
1314.17
1319.86
1325.55
1331.24
1336.93
1342.62
1348.31
1354.00
1359.69
1365.38
1371.07
1376.76
1382.45
1388.14
1393.83
1399.52
1405.21
1410.90
1416.59
1422.28
1427.97
1433.66
1439.35
1445.04
1450.73
1456.42
1462.11
1467.80
1473.49
1479.18
1484.87
1490.56
1496.25
1501.94
1507.63
1513.32
1519.01
1524.70
1530.39
1536.08
1541.77
1547.46
1553.15
1558.84
1564.53
1570.22
1575.91
1581.60
1587.29
1592.98
1598.67
1604.36
1610.05
1615.74

3050.47
3063.85
3077.23
3090.61
3103.99
3117.37
3130.75
3144.13
3157.51
3170.89
3184.27
3197.65
3211.03
3224.41
3237.79
3251.17
3264.55
3277.93
3291.31
3304.69
3318.07
3331.45
3344.83
3358.21
3371.59
3384.97
3398.35
3411.73
3425.11
3438.49
3451.87
3465.25
3478.63
3492.01
3505.39
3518.77
3532.15
3545.53
3558.91
3572.29
3585.67
3599.05
3612.43
3625.81
3639.19
3652.57
3665.95
3679.33
3692.71
3706.09
3719.47
3732.85
3746.23
3759.61
3772.99
3786.37
3799.75

1233.43
1238.84
1244.25
1249.66
1255.07
1260.48
1265.89
1271.30
1276.71
1282.12
1287.53
1292.94
1298.35
1303.76
1309.17
1314.58
1319.99
1325.40
1330.81
1336.22
1341.63
1347.04
1352.45
1357.86
1363.27
1368.68
1374.09
1379.50
1384.91
1390.32
1395.73
1401.14
1406.55
1411.96
1417.37
1422.78
1428.19
1433.60
1439.01
1444.42
1449.83
1455.24
1460.65
1466.06
1471.47
1476.88
1482.29
1487.70
1493.11
1498.52
1503.93
1509.34
1514.75
1520.16
1525.57
1530.98
1536.39

3333.25
3347.87
3362.49
3377.11
3391.73
3406.35
3420.97
3435.59
3450.21
3464.83
3479.45
3494.07
3508.69
3523.31
3537.93
3552.55
3567.17
3581.79
3596.41
3611.03
3625.65
3640.27
3654.89
3669.51
3684.13
3698.75
3713.37
3727.99
3742.61
3757.23
3771.85
3786.47
3801.09
3815.71
3830.33
3844.95
3859.57
3874.19
3888.81
3903.43
3918.05
3932.67
3947.29
3961.91
3976.53
3991.15
4005.77
4020.39
4035.01
4049.63
4064.25
4078.87
4093.49
4108.11
4122.73
4137.35
4151.97

280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336

280.00
281.00
282.00
283.00
284.00
285.00
286.00
287.00
288.00
289.00
290.00
291.00
292.00
293.00
294.00
295.00
296.00
297.00
298.00
299.00
300.00
301.00
302.00
303.00
304.00
305.00
306.00
307.00
308.00
309.00
310.00
311.00
312.00
313.00
314.00
315.00
316.00
317.00
318.00
319.00
320.00
321.00
322.00
323.00
324.00
325.00
326.00
327.00
328.00
329.00
330.00
331.00
332.00
333.00
334.00
335.00
336.00

2593.49
2602.59
2611.69
2620.79
2629.89
2638.99
2648.09
2657.19
2666.29
2675.39
2684.49
2693.59
2702.69
2711.79
2720.89
2729.99
2739.09
2748.19
2757.29
2766.39
2775.49
2784.59
2793.69
2802.79
2811.89
2820.99
2830.09
2839.19
2848.29
2857.39
2866.49
2875.59
2884.69
2893.79
2902.89
2911.99
2921.09
2930.19
2939.29
2948.39
2957.49
2966.59
2975.69
2984.79
2993.89
3002.99
3012.09
3021.19
3030.29
3039.39
3048.49
3057.59
3066.69
3075.79
3084.89
3093.99
3103.09

2593.49
2602.59
2611.69
2620.79
2629.89
2638.99
2648.09
2657.19
2666.29
2675.39
2684.49
2693.59
2702.69
2711.79
2720.89
2729.99
2739.09
2748.19
2757.29
2766.39
2775.49
2784.59
2793.69
2802.79
2811.89
2820.99
2830.09
2839.19
2848.29
2857.39
2866.49
2875.59
2884.69
2893.79
2902.89
2911.99
2921.09
2930.19
2939.29
2948.39
2957.49
2966.59
2975.69
2984.79
2993.89
3002.99
3012.09
3021.19
3030.29
3039.39
3048.49
3057.59
3066.69
3075.79
3084.89
3093.99
3103.09

1621.43
1627.12
1632.81
1638.50
1644.19
1649.88
1655.57
1661.26
1666.95
1672.64
1678.33
1684.02
1689.71
1695.40
1701.09
1706.78
1712.47
1718.16
1723.85
1729.54
1735.23
1740.92
1746.61
1752.30
1757.99
1763.68
1769.37
1775.06
1780.75
1786.44
1792.13
1797.82
1803.51
1809.20
1814.89
1820.58
1826.27
1831.96
1837.65
1843.34
1849.03
1854.72
1860.41
1866.10
1871.79
1877.48
1883.17
1888.86
1894.55
1900.24
1905.93
1911.62
1917.31
1923.00
1928.69
1934.38
1940.07

3813.13
3826.51
3839.89
3853.27
3866.65
3880.03
3893.41
3906.79
3920.17
3933.55
3946.93
3960.31
3973.69
3987.07
4000.45
4013.83
4027.21
4040.59
4053.97
4067.35
4080.73
4094.11
4107.49
4120.87
4134.25
4147.63
4161.01
4174.39
4187.77
4201.15
4214.53
4227.91
4241.29
4254.67
4268.05
4281.43
4294.81
4308.19
4321.57
4334.95
4348.33
4361.71
4375.09
4388.47
4401.85
4415.23
4428.61
4441.99
4455.37
4468.75
4482.13
4495.51
4508.89
4522.27
4535.65
4549.03
4562.41

1541.80
1547.21
1552.62
1558.03
1563.44
1568.85
1574.26
1579.67
1585.08
1590.49
1595.90
1601.31
1606.72
1612.13
1617.54
1622.95
1628.36
1633.77
1639.18
1644.59
1650.00
1655.41
1660.82
1666.23
1671.64
1677.05
1682.46
1687.87
1693.28
1698.69
1704.10
1709.51
1714.92
1720.33
1725.74
1731.15
1736.56
1741.97
1747.38
1752.79
1758.20
1763.61
1769.02
1774.43
1779.84
1785.25
1790.66
1796.07
1801.48
1806.89
1812.30
1817.71
1823.12
1828.53
1833.94
1839.35
1844.76

4166.59
4181.21
4195.83
4210.45
4225.07
4239.69
4254.31
4268.93
4283.55
4298.17
4312.79
4327.41
4342.03
4356.65
4371.27
4385.89
4400.51
4415.13
4429.75
4444.37
4458.99
4473.61
4488.23
4502.85
4517.47
4532.09
4546.71
4561.33
4575.95
4590.57
4605.19
4619.81
4634.43
4649.05
4663.67
4678.29
4692.91
4707.53
4722.15
4736.77
4751.39
4766.01
4780.63
4795.25
4809.87
4824.49
4839.11
4853.73
4868.35
4882.97
4897.59
4912.21
4926.83
4941.45
4956.07
4970.69
4985.31

337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
354
355
356
357
358
359
360
361
362
363
364
365
366
367
368
369
370
371
372
373
374
375
376
377
378
379
380
381
382
383
384
385
386
387
388
389
390
391
392
393

337.00
338.00
339.00
340.00
341.00
342.00
343.00
344.00
345.00
346.00
347.00
348.00
349.00
350.00
351.00
352.00
353.00
354.00
355.00
356.00
357.00
358.00
359.00
360.00
361.00
362.00
363.00
364.00
365.00
366.00
367.00
368.00
369.00
370.00
371.00
372.00
373.00
374.00
375.00
376.00
377.00
378.00
379.00
380.00
381.00
382.00
383.00
384.00
385.00
386.00
387.00
388.00
389.00
390.00
391.00
392.00
393.00

3112.19
3121.29
3130.39
3139.49
3148.59
3157.69
3166.79
3175.89
3184.99
3194.09
3203.19
3212.29
3221.39
3230.49
3239.59
3248.69
3257.79
3266.89
3275.99
3285.09
3294.19
3303.29
3312.39
3321.49
3330.59
3339.69
3348.79
3357.89
3366.99
3376.09
3385.19
3394.29
3403.39
3412.49
3421.59
3430.69
3439.79
3448.89
3457.99
3467.09
3476.19
3485.29
3494.39
3503.49
3512.59
3521.69
3530.79
3539.89
3548.99
3558.09
3567.19
3576.29
3585.39
3594.49
3603.59
3612.69
3621.79

3112.19
3121.29
3130.39
3139.49
3148.59
3157.69
3166.79
3175.89
3184.99
3194.09
3203.19
3212.29
3221.39
3230.49
3239.59
3248.69
3257.79
3266.89
3275.99
3285.09
3294.19
3303.29
3312.39
3321.49
3330.59
3339.69
3348.79
3357.89
3366.99
3376.09
3385.19
3394.29
3403.39
3412.49
3421.59
3430.69
3439.79
3448.89
3457.99
3467.09
3476.19
3485.29
3494.39
3503.49
3512.59
3521.69
3530.79
3539.89
3548.99
3558.09
3567.19
3576.29
3585.39
3594.49
3603.59
3612.69
3621.79

1945.76
1951.45
1957.14
1962.83
1968.52
1974.21
1979.90
1985.59
1991.28
1996.97
2002.66
2008.35
2014.04
2019.73
2025.42
2031.11
2036.80
2042.49
2048.18
2053.87
2059.56
2065.25
2070.94
2076.63
2082.32
2088.01
2093.70
2099.39
2105.08
2110.77
2116.46
2122.15
2127.84
2133.53
2139.22
2144.91
2150.60
2156.29
2161.98
2167.67
2173.36
2179.05
2184.74
2190.43
2196.12
2201.81
2207.50
2213.19
2218.88
2224.57
2230.26
2235.95
2241.64
2247.33
2253.02
2258.71
2264.40

4575.79
4589.17
4602.55
4615.93
4629.31
4642.69
4656.07
4669.45
4682.83
4696.21
4709.59
4722.97
4736.35
4749.73
4763.11
4776.49
4789.87
4803.25
4816.63
4830.01
4843.39
4856.77
4870.15
4883.53
4896.91
4910.29
4923.67
4937.05
4950.43
4963.81
4977.19
4990.57
5003.95
5017.33
5030.71
5044.09
5057.47
5070.85
5084.23
5097.61
5110.99
5124.37
5137.75
5151.13
5164.51
5177.89
5191.27
5204.65
5218.03
5231.41
5244.79
5258.17
5271.55
5284.93
5298.31
5311.69
5325.07

1850.17
1855.58
1860.99
1866.40
1871.81
1877.22
1882.63
1888.04
1893.45
1898.86
1904.27
1909.68
1915.09
1920.50
1925.91
1931.32
1936.73
1942.14
1947.55
1952.96
1958.37
1963.78
1969.19
1974.60
1980.01
1985.42
1990.83
1996.24
2001.65
2007.06
2012.47
2017.88
2023.29
2028.70
2034.11
2039.52
2044.93
2050.34
2055.75
2061.16
2066.57
2071.98
2077.39
2082.80
2088.21
2093.62
2099.03
2104.44
2109.85
2115.26
2120.67
2126.08
2131.49
2136.90
2142.31
2147.72
2153.13

4999.93
5014.55
5029.17
5043.79
5058.41
5073.03
5087.65
5102.27
5116.89
5131.51
5146.13
5160.75
5175.37
5189.99
5204.61
5219.23
5233.85
5248.47
5263.09
5277.71
5292.33
5306.95
5321.57
5336.19
5350.81
5365.43
5380.05
5394.67
5409.29
5423.91
5438.53
5453.15
5467.77
5482.39
5497.01
5511.63
5526.25
5540.87
5555.49
5570.11
5584.73
5599.35
5613.97
5628.59
5643.21
5657.83
5672.45
5687.07
5701.69
5716.31
5730.93
5745.55
5760.17
5774.79
5789.41
5804.03
5818.65

394
395
396
397
398
399
400
401
402
403
404
405
406
407
408
409
410
411
412
413
414
415
416
417
418
419
420
421
422
423
424
425
426
427
428
429
430
431
432
433
434
435
436
437
438
439
440
441
442
443
444
445
446
447
448
449
450

394.00
395.00
396.00
397.00
398.00
399.00
400.00
401.00
402.00
403.00
404.00
405.00
406.00
407.00
408.00
409.00
410.00
411.00
412.00
413.00
414.00
415.00
416.00
417.00
418.00
419.00
420.00
421.00
422.00
423.00
424.00
425.00
426.00
427.00
428.00
429.00
430.00
431.00
432.00
433.00
434.00
435.00
436.00
437.00
438.00
439.00
440.00
441.00
442.00
443.00
444.00
445.00
446.00
447.00
448.00
449.00
450.00

3630.89
3639.99
3649.09
3658.19
3667.29
3676.39
3685.49
3694.59
3703.69
3712.79
3721.89
3730.99
3740.09
3749.19
3758.29
3767.39
3776.49
3785.59
3794.69
3803.79
3812.89
3821.99
3831.09
3840.19
3849.29
3858.39
3867.49
3876.59
3885.69
3894.79
3903.89
3912.99
3922.09
3931.19
3940.29
3949.39
3958.49
3967.59
3976.69
3985.79
3994.89
4003.99
4013.09
4022.19
4031.29
4040.39
4049.49
4058.59
4067.69
4076.79
4085.89
4094.99
4104.09
4113.19
4122.29
4131.39
4140.49

3630.89
3639.99
3649.09
3658.19
3667.29
3676.39
3685.49
3694.59
3703.69
3712.79
3721.89
3730.99
3740.09
3749.19
3758.29
3767.39
3776.49
3785.59
3794.69
3803.79
3812.89
3821.99
3831.09
3840.19
3849.29
3858.39
3867.49
3876.59
3885.69
3894.79
3903.89
3912.99
3922.09
3931.19
3940.29
3949.39
3958.49
3967.59
3976.69
3985.79
3994.89
4003.99
4013.09
4022.19
4031.29
4040.39
4049.49
4058.59
4067.69
4076.79
4085.89
4094.99
4104.09
4113.19
4122.29
4131.39
4140.49

2270.09
2275.78
2281.47
2287.16
2292.85
2298.54
2304.23
2309.92
2315.61
2321.30
2326.99
2332.68
2338.37
2344.06
2349.75
2355.44
2361.13
2366.82
2372.51
2378.20
2383.89
2389.58
2395.27
2400.96
2406.65
2412.34
2418.03
2423.72
2429.41
2435.10
2440.79
2446.48
2452.17
2457.86
2463.55
2469.24
2474.93
2480.62
2486.31
2492.00
2497.69
2503.38
2509.07
2514.76
2520.45
2526.14
2531.83
2537.52
2543.21
2548.90
2554.59
2560.28
2565.97
2571.66
2577.35
2583.04
2588.73

5338.45
5351.83
5365.21
5378.59
5391.97
5405.35
5418.73
5432.11
5445.49
5458.87
5472.25
5485.63
5499.01
5512.39
5525.77
5539.15
5552.53
5565.91
5579.29
5592.67
5606.05
5619.43
5632.81
5646.19
5659.57
5672.95
5686.33
5699.71
5713.09
5726.47
5739.85
5753.23
5766.61
5779.99
5793.37
5806.75
5820.13
5833.51
5846.89
5860.27
5873.65
5887.03
5900.41
5913.79
5927.17
5940.55
5953.93
5967.31
5980.69
5994.07
6007.45
6020.83
6034.21
6047.59
6060.97
6074.35
6087.73

2158.54
2163.95
2169.36
2174.77
2180.18
2185.59
2191.00
2196.41
2201.82
2207.23
2212.64
2218.05
2223.46
2228.87
2234.28
2239.69
2245.10
2250.51
2255.92
2261.33
2266.74
2272.15
2277.56
2282.97
2288.38
2293.79
2299.20
2304.61
2310.02
2315.43
2320.84
2326.25
2331.66
2337.07
2342.48
2347.89
2353.30
2358.71
2364.12
2369.53
2374.94
2380.35
2385.76
2391.17
2396.58
2401.99
2407.40
2412.81
2418.22
2423.63
2429.04
2434.45
2439.86
2445.27
2450.68
2456.09
2461.50

5833.27
5847.89
5862.51
5877.13
5891.75
5906.37
5920.99
5935.61
5950.23
5964.85
5979.47
5994.09
6008.71
6023.33
6037.95
6052.57
6067.19
6081.81
6096.43
6111.05
6125.67
6140.29
6154.91
6169.53
6184.15
6198.77
6213.39
6228.01
6242.63
6257.25
6271.87
6286.49
6301.11
6315.73
6330.35
6344.97
6359.59
6374.21
6388.83
6403.45
6418.07
6432.69
6447.31
6461.93
6476.55
6491.17
6505.79
6520.41
6535.03
6549.65
6564.27
6578.89
6593.51
6608.13
6622.75
6637.37
6651.99

451
452
453
454
455
456
457
458
459
460
461
462
463
464
465
466
467
468
469
470
471
472
473
474
475
476
477
478
479
480
481
482
483
484
485
486
487
488
489
490
491
492
493
494
495
496
497
498
499
500
501
502
503
504
505
506
507

451.00
452.00
453.00
454.00
455.00
456.00
457.00
458.00
459.00
460.00
461.00
462.00
463.00
464.00
465.00
466.00
467.00
468.00
469.00
470.00
471.00
472.00
473.00
474.00
475.00
476.00
477.00
478.00
479.00
480.00
481.00
482.00
483.00
484.00
485.00
486.00
487.00
488.00
489.00
490.00
491.00
492.00
493.00
494.00
495.00
496.00
497.00
498.00
499.00
500.00
501.00
502.00
503.00
504.00
505.00
506.00
507.00

4149.59
4158.69
4167.79
4176.89
4185.99
4195.09
4204.19
4213.29
4222.39
4231.49
4240.59
4249.69
4258.79
4267.89
4276.99
4286.09
4295.19
4304.29
4313.39
4322.49
4331.59
4340.69
4349.79
4358.89
4367.99
4377.09
4386.19
4395.29
4404.39
4413.49
4422.59
4431.69
4440.79
4449.89
4458.99
4468.09
4477.19
4486.29
4495.39
4504.49
4513.59
4522.69
4531.79
4540.89
4549.99
4559.09
4568.19
4577.29
4586.39
4595.49
4604.59
4613.69
4622.79
4631.89
4640.99
4650.09
4659.19

4149.59
4158.69
4167.79
4176.89
4185.99
4195.09
4204.19
4213.29
4222.39
4231.49
4240.59
4249.69
4258.79
4267.89
4276.99
4286.09
4295.19
4304.29
4313.39
4322.49
4331.59
4340.69
4349.79
4358.89
4367.99
4377.09
4386.19
4395.29
4404.39
4413.49
4422.59
4431.69
4440.79
4449.89
4458.99
4468.09
4477.19
4486.29
4495.39
4504.49
4513.59
4522.69
4531.79
4540.89
4549.99
4559.09
4568.19
4577.29
4586.39
4595.49
4604.59
4613.69
4622.79
4631.89
4640.99
4650.09
4659.19

2594.42
2600.11
2605.80
2611.49
2617.18
2622.87
2628.56
2634.25
2639.94
2645.63
2651.32
2657.01
2662.70
2668.39
2674.08
2679.77
2685.46
2691.15
2696.84
2702.53
2708.22
2713.91
2719.60
2725.29
2730.98
2736.67
2742.36
2748.05
2753.74
2759.43
2765.12
2770.81
2776.50
2782.19
2787.88
2793.57
2799.26
2804.95
2810.64
2816.33
2822.02
2827.71
2833.40
2839.09
2844.78
2850.47
2856.16
2861.85
2867.54
2873.23
2878.92
2884.61
2890.30
2895.99
2901.68
2907.37
2913.06

6101.11
6114.49
6127.87
6141.25
6154.63
6168.01
6181.39
6194.77
6208.15
6221.53
6234.91
6248.29
6261.67
6275.05
6288.43
6301.81
6315.19
6328.57
6341.95
6355.33
6368.71
6382.09
6395.47
6408.85
6422.23
6435.61
6448.99
6462.37
6475.75
6489.13
6502.51
6515.89
6529.27
6542.65
6556.03
6569.41
6582.79
6596.17
6609.55
6622.93
6636.31
6649.69
6663.07
6676.45
6689.83
6703.21
6716.59
6729.97
6743.35
6756.73
6770.11
6783.49
6796.87
6810.25
6823.63
6837.01
6850.39

2466.91
2472.32
2477.73
2483.14
2488.55
2493.96
2499.37
2504.78
2510.19
2515.60
2521.01
2526.42
2531.83
2537.24
2542.65
2548.06
2553.47
2558.88
2564.29
2569.70
2575.11
2580.52
2585.93
2591.34
2596.75
2602.16
2607.57
2612.98
2618.39
2623.80
2629.21
2634.62
2640.03
2645.44
2650.85
2656.26
2661.67
2667.08
2672.49
2677.90
2683.31
2688.72
2694.13
2699.54
2704.95
2710.36
2715.77
2721.18
2726.59
2732.00
2737.41
2742.82
2748.23
2753.64
2759.05
2764.46
2769.87

6666.61
6681.23
6695.85
6710.47
6725.09
6739.71
6754.33
6768.95
6783.57
6798.19
6812.81
6827.43
6842.05
6856.67
6871.29
6885.91
6900.53
6915.15
6929.77
6944.39
6959.01
6973.63
6988.25
7002.87
7017.49
7032.11
7046.73
7061.35
7075.97
7090.59
7105.21
7119.83
7134.45
7149.07
7163.69
7178.31
7192.93
7207.55
7222.17
7236.79
7251.41
7266.03
7280.65
7295.27
7309.89
7324.51
7339.13
7353.75
7368.37
7382.99
7397.61
7412.23
7426.85
7441.47
7456.09
7470.71
7485.33

508
509
510
511
512
513
514
515

508.00
509.00
510.00
511.00
512.00
513.00
514.00
515.00

4668.29
4677.39
4686.49
4695.59
4704.69
4713.79
4722.89
4731.99

4668.29
4677.39
4686.49
4695.59
4704.69
4713.79
4722.89
4731.99

2918.75
2924.44
2930.13
2935.82
2941.51
2947.20
2952.89
2958.58

6863.77
6877.15
6890.53
6903.91
6917.29
6930.67
6944.05
6957.43

2775.28
2780.69
2786.10
2791.51
2796.92
2802.33
2807.74
2813.15

7499.95
7514.57
7529.19
7543.81
7558.43
7573.05
7587.67
7602.29

HIRE CHARGES OF MACHINERY


Hire
Fuel
Crew
Charges
Charges
Charges

Total

Per

a) Hire charges of Tipper 5.00


Cum capacity

446.70

296.30

166.70

909.70

Hour

b) Hire charges of Tipper 10


Tonnes capacity

414.10

296.30

166.70

877.10

Hour

c) Hire charges of Water Tanker


8000 Ltrs capacity

402.50

296.30

166.70

865.50

Hour

d) Hire charges of Truck 10


Tonnes capacity

414.10

296.30

166.70

877.10

Hour

e) Hire charges of FE loader


1.00 Cum bucket capacity @
45 Cum

414.10

296.30

166.70

877.10

Hour

1
2
3
4
5
A)
1

RATES FOR CONVEYANCE BY MACHINERY


Mincipal area allowance
Industrial area allowance
Agency area allowance
Allowable allowance
Add Overhead Charges & Contractor's Profit
For Earth/Gravel/Sand/Morrum/Lime/Surki (per Cum):
Lead up to 1 Km:
Out put
=
5.00 Cum
Rate
0.15 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
446.70
0.15 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
296.30
0.15 Hrs. crew charges of Tipper 5.00 Cum @ Rs. 166.70
0.00 add area allowance at 0% on Rs.
25.01
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0% 27.29
on Rs.
Total rate for
1.00 Cum

2 Lead up to 2 Km:
Out put
=
5.00 Cum
0.21 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

0.00%
0.00%
0.00%
0.00%
0.00%

Per
Hour
Hour
Hour

Rate
446.70
296.30
166.70
35.01

Per
Hour
Hour
Hour

38.21

Hour

1.00 Cum

3 Lead up to 3 Km:
Out put
=
5.00 Cum
0.28 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.

Rate
446.70
296.30

Per
Hour
Hour

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
67.01
44.45
25.01
0.00
136.47
27.29
0.00

Rs.

27.29

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
93.81
62.22
35.01
0.00
191.04
38.21
0.00

Rs.

38.21

Rs.
Rs.

Amount
125.08
82.96

0.28 Hrs. crew charges of Tipper 5.00 Cum @ Rs.


0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Hour

Rate
446.70
296.30
166.70
56.68

Per
Hour
Hour
Hour

61.86

Hour

Rate
446.70
296.30
166.70
66.68

Per
Hour
Hour
Hour

72.78

Hour

1.00 Cum

6 Lead for every Km from 5 to 30 Km:


Out put
=
5.00 Cum
0.06 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.06 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.06 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

50.94

1.00 Cum

5 Lead up to 5 Km:
Out put
=
5.00 Cum
0.40 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Hour

1.00 Cum

4 Lead up to 4 Km:
Out put
=
5.00 Cum
0.34 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

166.70
46.68

Rate
446.70
296.30
166.70
10.00

Per
Hour
Hour
Hour

10.92

Hour

1.00 Cum

7 Lead for every Km beyond 30 Km:


Out put
=
5.00 Cum
0.05 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.05 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.05 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.

Rate
446.70
296.30
166.70
8.34

Per
Hour
Hour
Hour

Rs.
Rs.
Rs.
Rs.
Rs.

46.68
0.00
254.72
50.94
0.00

Rs.

50.94

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
151.88
100.74
56.68
0.00
309.30
61.86
0.00

Rs.

61.86

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
178.68
118.52
66.68
0.00
363.88
72.78
0.00

Rs.

72.78

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
26.80
17.78
10.00
0.00
54.58
10.92
0.00

Rs.

10.92

Rs.
Rs.
Rs.
Rs.

Amount
22.34
14.82
8.34
0.00

Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

9.10

1.00 Cum

Rs.
Rs.
Rs.

45.50
9.1
0.00

Rs.

9.10

B) For Rubble/Size stones/Cut stones/Coarse aggregates (per Cum):


1 Lead up to 1 Km:
Out put
=
5.00 Cum
0.15 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.15 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.15 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum
2 Lead up to 2 Km:
Out put
=
5.00 Cum
0.21 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Per
Hour
Hour
Hour

27.29

Rate
446.70
296.30
166.70
35.01

Per
Hour
Hour
Hour

38.21

Hour

1.00 Cum

3 Lead up to 3 Km:
Out put
=
5.00 Cum
0.28 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Rate
446.70
296.30
166.70
25.01

Rate
446.70
296.30
166.70
46.68

Per
Hour
Hour
Hour

50.94

Hour

1.00 Cum

4 Lead up to 4 Km:
Out put
=
5.00 Cum
0.34 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum

Rate
446.70
296.30
166.70
56.68

Per
Hour
Hour
Hour

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
67.01
44.45
25.01
0.00
136.47
27.29
0.00

Rs.

27.29

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
93.81
62.22
35.01
0.00
191.04
38.21
0.00

Rs.

38.21

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
125.08
82.96
46.68
0.00
254.72
50.94
0.00

Rs.

50.94

Rs.
Rs.
Rs.
Rs.
Rs.

Amount
151.88
100.74
56.68
0.00
309.30

Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Per
Hour
Hour
Hour

72.78

Hour

Rate
446.70
296.30
166.70
10.00

Per
Hour
Hour
Hour

10.92

Hour

1.00 Cum

7 Lead for every Km beyond 30 Km:


Out put
=
5.00 Cum
0.05 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.05 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.05 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Rate
446.70
296.30
166.70
66.68

1.00 Cum

6 Lead for every Km from 5 to 30 Km:


Out put
=
5.00 Cum
0.06 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.06 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.06 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Hour

1.00 Cum

5 Lead up to 5 Km:
Out put
=
5.00 Cum
0.40 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

61.86

Rate
446.70
296.30
166.70
8.34

Per
Hour
Hour
Hour

9.10

1.00 Cum

Rs.
Rs.

61.86
0.00

Rs.

61.86

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
178.68
118.52
66.68
0.00
363.88
72.78
0.00

Rs.

72.78

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
26.80
17.78
10.00
0.00
54.58
10.92
0.00

Rs.

10.92

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
22.34
14.82
8.34
0.00
45.50
9.1
0.00

Rs.

9.10

C) For Cement/Steel/RCC poles/A.C & G.I sheets/Packed materials (per Tonne):


1 Lead up to 1 Km:
Out put
=
8.00 MT
0.15 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.15 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.15 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT

Rate
446.70
296.30
166.70
25.01

Per
Hour
Hour
Hour

Rs.
Rs.
Rs.
Rs.
Rs.

Amount
67.01
44.45
25.01
0.00
136.47

Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 MT
2 Lead up to 2 Km:
Out put
=
8.00 MT
0.21 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Per
Hour
Hour
Hour

23.88

Hour

Rate
446.70
296.30
166.70
46.68

Per
Hour
Hour
Hour

31.84

Hour

1.00 MT

4 Lead up to 4 Km:
Out put
=
8.00 MT
0.34 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Rate
446.70
296.30
166.70
35.01

1.00 MT

3 Lead up to 3 Km:
Out put
=
8.00 MT
0.28 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

17.06

Rate
446.70
296.30
166.70
56.68

Per
Hour
Hour
Hour

38.66

Hour

1.00 MT

5 Lead up to 5 Km:
Out put
=
8.00 MT
0.40 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT
Rate for
1.00 MT

Rate
446.70
296.30
166.70
66.68

Per
Hour
Hour
Hour

Rs.
Rs.

17.06
0.00

Rs.

17.06

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
93.81
62.22
35.01
0.00
191.04
23.88
0.00

Rs.

23.88

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
125.08
82.96
46.68
0.00
254.72
31.84
0.00

Rs.

31.84

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
151.88
100.74
56.68
0.00
309.30
38.66
0.00

Rs.

38.66

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
178.68
118.52
66.68
0.00
363.88
45.49

0.00 add overheads and contractors profit at 0%


on Rs.
Total rate for

Rate
446.70
296.30
166.70
10.00

Per
Hour
Hour
Hour

6.82

Hour

1.00 MT

7 Lead for every Km beyond 30 Km:


Out put
=
8.00 MT
0.05 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.05 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.05 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Hour

1.00 MT

6 Lead for every Km from 5 to 30 Km:


Out put
=
8.00 MT
0.06 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.06 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.06 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

45.49

Rate
446.70
296.30
166.70
8.34

Per
Hour
Hour
Hour

5.69

1.00 MT

Rs.

0.00

Rs.

45.49

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
26.80
17.78
10.00
0.00
54.58
6.82
0.00

Rs.

6.82

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
22.34
14.82
8.34
0.00
45.50
5.69
0.00

Rs.

5.69

D) For PCC Slabs/Shabad Slabs/CC & Laterite Blocks/Wood (per Cum):


1 Lead up to 1 Km:
Out put
=
3.40 Cum
0.15 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.15 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.15 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum
2 Lead up to 2 Km:
Out put
=
3.40 Cum
0.21 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum

Rate
446.70
296.30
166.70
25.01

Per
Hour
Hour
Hour

40.14

Rate
446.70
296.30
166.70
35.01

Per
Hour
Hour
Hour

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
67.01
44.45
25.01
0.00
136.47
40.14
0.00

Rs.

40.14

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
93.81
62.22
35.01
0.00
191.04
56.19

0.00 add overheads and contractors profit at 0%


on Rs.
Total rate for

Per
Hour
Hour
Hour

74.92

Hour

Rate
446.70
296.30
166.70
56.68

Per
Hour
Hour
Hour

90.97

Hour

1.00 Cum

5 Lead up to 5 Km:
Out put
=
3.40 Cum
0.40 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Rate
446.70
296.30
166.70
46.68

1.00 Cum

4 Lead up to 4 Km:
Out put
=
3.40 Cum
0.34 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Hour

1.00 Cum

3 Lead up to 3 Km:
Out put
=
3.40 Cum
0.28 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

56.19

Rate
446.70
296.30
166.70
66.68

Per
Hour
Hour
Hour

107.02

Hour

1.00 Cum

6 Lead for every Km from 5 to 30 Km:


Out put
=
3.40 Cum
0.06 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.06 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.06 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum

Rate
446.70
296.30
166.70
10.00

Per
Hour
Hour
Hour

Rs.

0.00

Rs.

56.19

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
125.08
82.96
46.68
0.00
254.72
74.92
0.00

Rs.

74.92

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
151.88
100.74
56.68
0.00
309.30
90.97
0.00

Rs.

90.97

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
178.68
118.52
66.68
0.00
363.88
107.02
0.00

Rs.

107.02

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
26.80
17.78
10.00
0.00
54.58
16.05

0.00 add overheads and contractors profit at 0%


on Rs.
Total rate for

16.05

Hour

1.00 Cum

7 Lead for every Km beyond 30 Km:


Out put
=
3.40 Cum
0.05 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.05 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.05 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Rate
446.70
296.30
166.70
8.34

Per
Hour
Hour
Hour

13.38

1.00 Cum

E) For Water (per 1000 Ltrs):


1 Lead up to 1 Km:
Out put
=
8000 Ltrs
0.15 Hrs. hire charges of water tanker 8000 ltrs
capacity @ Rs.

Rs.

0.00

Rs.

16.05

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
22.34
14.82
8.34
0.00
45.50
13.38
0.00

Rs.

13.38

Rate
402.50

Per
Hour

Rs.

Amount
60.38

0.15 Hrs. fuel charges of water tanker 8000 ltrs


capacity @ Rs.

296.30

Hour

Rs.

44.45

0.15 Hrs. crew charges of water tanker 8000 ltrs


capacity @ Rs.

166.70

Hour

Rs.

25.01

0.00 add area allowance at 0% on Rs.


Rate for
8000 Ltrs
Rate for
1000 Ltrs
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Ltrs

25.01

Rs.
Rs.
Rs.
Rs.

0.00
129.84
16.23
0.00

Rs.

16.23

2 Lead up to 2 Km:
Out put
=
8000 Ltrs
0.21 Hrs. hire charges of water tanker 8000 ltrs
capacity @ Rs.

16.23

Rate
402.50

Per
Hour

Rs.

Amount
84.53

0.21 Hrs. fuel charges of water tanker 8000 ltrs


capacity @ Rs.

296.30

Hour

Rs.

62.22

0.21 Hrs. crew charges of water tanker 8000 ltrs


capacity @ Rs.

166.70

Hour

Rs.

35.01

0.00 add area allowance at 0% on Rs.


Rate for
8000 Ltrs
Rate for
1000 Ltrs
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Ltrs

35.01

Rs.
Rs.
Rs.
Rs.

0.00
181.76
22.72
0.00

Rs.

22.72

3 Lead up to 3 Km:
Out put
=

8000 Ltrs

22.72

Rate

Per

Amount

0.28 Hrs. hire charges of water tanker 8000 ltrs


capacity @ Rs.

402.50

Hour

Rs.

112.70

0.28 Hrs. fuel charges of water tanker 8000 ltrs


capacity @ Rs.

296.30

Hour

Rs.

82.96

0.28 Hrs. crew charges of water tanker 8000 ltrs


capacity @ Rs.

166.70

Hour

Rs.

46.68

0.00 add area allowance at 0% on Rs.


Rate for
8000 Ltrs
Rate for
1000 Ltrs
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Ltrs

46.68

Rs.
Rs.
Rs.
Rs.

0.00
242.34
30.29
0.00

Rs.

30.29

4 Lead up to 4 Km:
Out put
=
8000 Ltrs
0.34 Hrs. hire charges of water tanker 8000 ltrs
capacity @ Rs.

30.29

Rate
402.50

Per
Hour

Rs.

Amount
136.85

0.34 Hrs. fuel charges of water tanker 8000 ltrs


capacity @ Rs.

296.30

Hour

Rs.

100.74

0.34 Hrs. crew charges of water tanker 8000 ltrs


capacity @ Rs.

166.70

Hour

Rs.

56.68

0.00 add area allowance at 0% on Rs.


Rate for
8000 Ltrs
Rate for
1000 Ltrs
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Ltrs

56.68

Rs.
Rs.
Rs.
Rs.

0.00
294.27
36.78
0.00

Rs.

36.78

5 Lead up to 5 Km:
Out put
=
8000 Ltrs
0.40 Hrs. hire charges of water tanker 8000 ltrs
capacity @ Rs.

36.78

Rate
402.50

Per
Hour

Rs.

Amount
161.00

0.40 Hrs. fuel charges of water tanker 8000 ltrs


capacity @ Rs.

296.30

Hour

Rs.

118.52

0.40 Hrs. crew charges of water tanker 8000 ltrs


capacity @ Rs.

166.70

Hour

Rs.

66.68

0.00 add area allowance at 0% on Rs.


Rate for
8000 Ltrs
Rate for
1000 Ltrs
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Ltrs

66.68

Rs.
Rs.
Rs.
Rs.

0.00
346.20
43.28
0.00

Rs.

43.28

6 Lead for every Km from 5 to 30 Km:


Out put
=
8000 Ltrs
0.06 Hrs. hire charges of water tanker 8000 ltrs
capacity @ Rs.
0.06 Hrs. fuel charges of water tanker 8000 ltrs
capacity @ Rs.

43.28

Rate
402.50

Per
Hour

Rs.

Amount
24.15

296.30

Hour

Rs.

17.78

0.06 Hrs. crew charges of water tanker 8000 ltrs


capacity @ Rs.

166.70

0.00 add area allowance at 0% on Rs.


Rate for
8000 Ltrs
Rate for
1000 Ltrs
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Ltrs

10.00

7 Lead for every Km beyond 30 Km:


Out put
=
8000 Ltrs
0.05 Hrs. hire charges of water tanker 8000 ltrs
capacity @ Rs.

Hour

6.49

Rs.

10.00

Rs.
Rs.
Rs.
Rs.

0.00
51.93
6.49
0.00

Rs.

6.49

Rate
402.50

Per
Hour

Rs.

Amount
20.13

0.05 Hrs. fuel charges of water tanker 8000 ltrs


capacity @ Rs.

296.30

Hour

Rs.

14.82

0.05 Hrs. crew charges of water tanker 8000 ltrs


capacity @ Rs.

166.70

Hour

Rs.

8.34

0.00 add area allowance at 0% on Rs.


Rate for
8000 Ltrs
Rate for
1000 Ltrs
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Ltrs

8.34

Rs.
Rs.
Rs.
Rs.

0.00
43.29
5.41
0.00

Rs.

5.41

F) For Bricks (per 1000 Nos):


1 Lead up to 1 Km:
Out put
=
3000 Nos
0.15 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

5.41

Rate
414.10

Per
Hour

Rs.

Amount
62.12

0.15 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

44.45

0.15 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

25.01

0.00 add area allowance at 0% on Rs.


Rate for
3000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos

25.01

Rs.
Rs.
Rs.
Rs.

0.00
131.58
43.86
0.00

Rs.

43.86

2 Lead up to 2 Km:
Out put
=
3000 Nos
0.21 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

43.86

Rate
414.10

Per
Hour

Rs.

Amount
86.96

0.21 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

62.22

0.21 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

35.01

0.00 add area allowance at 0% on Rs.

35.01

Rs.

0.00

Rate for
3000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos

Rs.
Rs.
Rs.

184.19
61.40
0.00

61.40

Rs.

61.40

3 Lead up to 3 Km:
Out put
=
3000 Nos
0.28 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

Rate
414.10

Per
Hour

Rs.

Amount
115.95

0.28 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

82.96

0.28 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

46.68

0.00 add area allowance at 0% on Rs.


Rate for
3000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos

46.68

Rs.
Rs.
Rs.
Rs.

0.00
245.59
81.86
0.00

Rs.

81.86

4 Lead up to 4 Km:
Out put
=
3000 Nos
0.34 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

81.86

Rate
414.10

Per
Hour

Rs.

Amount
140.79

0.34 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

100.74

0.34 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

56.68

0.00 add area allowance at 0% on Rs.


Rate for
3000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos

56.68

Rs.
Rs.
Rs.
Rs.

0.00
298.21
99.40
0.00

Rs.

99.40

5 Lead up to 5 Km:
Out put
=
3000 Nos
0.40 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

99.40

Rate
414.10

Per
Hour

Rs.

Amount
165.64

0.40 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

118.52

0.40 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

66.68

0.00 add area allowance at 0% on Rs.


Rate for
3000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.

66.68

Rs.
Rs.
Rs.
Rs.

0.00
350.84
116.95
0.00

116.95

Total rate for

1000 Nos

6 Lead for every Km beyond 5 Kms up to 30 Kms:


Out put
=
3000 Nos
0.06 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

Rs.

116.95

Rate
414.10

Per
Hour

Rs.

Amount
24.85

0.06 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

17.78

0.06 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

10.00

0.00 add area allowance at 0% on Rs.


Rate for
3000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos

10.00

Rs.
Rs.
Rs.
Rs.

0.00
52.63
17.54
0.00

Rs.

17.54

7 Lead for every Km beyond 30 Kms:


Out put
=
3000 Nos
0.05 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

17.54

Rate
414.10

Per
Hour

Rs.

Amount
20.71

0.05 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

14.82

0.05 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

8.34

0.00 add area allowance at 0% on Rs.


Rate for
3000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos

8.34

Rs.
Rs.
Rs.
Rs.

0.00
43.87
14.62
0.00

Rs.

14.62

14.62

LOADING & UNLOADING CHARGES BY MANUAL MEANS (EXCLUDING IDLE HIRE CHARGES
OF TRUCKS)
A) For Earth, Sand, Morrum, Manure, Fly Ash (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
Rate
a) Labour:
0.01 day Head mazdoor
375.00
0.25 day Mazdoor
320.00
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum

83.75

15.23

Per
day
day

Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

3.75
80.00
83.75
0.00
83.75
83.75
15.23
0.00

Rs.

15.23

(ii) Unloading charges:


Out put
=
5.50 Cum
a) Labour:
0.005 day Head mazdoor
0.125 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum

Rate

Per

375.00
320.00

day
day

41.88

7.61

Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

1.88
40.00
41.88
0.00
41.88
41.88
7.61
0.00

Rs.

7.61

B) For Lime, Agrregate, Stone Boulder, Brick aggregate, Kankar, Building rubbish, Crushed
slag, Stone for masonry work (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
a) Labour:
0.02 day Head mazdoor
0.50 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum
(ii) Unloading charges:
Out put
=
5.50 Cum
a) Labour:
0.01 day Head mazdoor
0.25 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum
C) For Cement (per Tonne):
(i) Loading charges:
Out put
=
10.00 MT
a) Labour:
0.06 day Head mazdoor
1.50 day Mazdoor

Rate

Per

375.00
320.00

day
day

167.50

30.45

Rate

Per

375.00
320.00

day
day

83.75

15.23

Rate

Per

375.00
320.00

day
day

Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

7.50
160.00
167.50
0.00
167.50
167.50
30.45
0.00

Rs.

30.45

Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

3.75
80.00
83.75
0.00
83.75
83.75
15.23
0.00

Rs.

15.23

Amount
Rs.
Rs.

22.50
480.00

0.00 add area allowance at 0% on Rs.


Total labour charges
Rate for
10.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 MT
(ii) Unloading & Stacking charges:
Out put
=
10.00 MT
a) Labour:
0.06 day Head mazdoor
1.50 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
10.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 MT
D) For Structural steel, Steel bars (per Tonne):
(i) Loading charges:
Out put
=
10.00 MT
a) Labour:
0.07 day Head mazdoor
1.80 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
10.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 MT
(ii) Unloading & Stacking charges:
Out put
=
10.00 MT
a) Labour:
0.07 day Head mazdoor
1.80 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
10.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.

502.50

50.25

Rate

Per

375.00
320.00

day
day

502.50

50.25

Rate

Per

375.00
320.00

day
day

602.25

60.23

Rate

Per

375.00
320.00

day
day

602.25

60.23

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

502.50
0.00
502.50
502.50
50.25
0.00

Rs.

50.25

Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

22.50
480.00
502.50
0.00
502.50
502.50
50.25
0.00

Rs.

50.25

Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

26.25
576.00
602.25
0.00
602.25
602.25
60.23
0.00

Rs.

60.23

Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

26.25
576.00
602.25
0.00
602.25
602.25
60.23
0.00

Total rate for

1.00 MT

E) For Bricks of size 225 x 140 x 70mm (per 1000 Nos):


(i) Loading charges:
Out put
=
2000.00 Nos
a) Labour:
0.01 day Head mazdoor
0.25 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
2000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos
(ii) Unloading & Stacking charges:
Out put
=
2000.00 Nos
a) Labour:
0.01 day Head mazdoor
0.25 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
2000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos

Rs.

Rate

Per

375.00
320.00

day
day

83.75

41.88

Rate

Per

375.00
320.00

day
day

83.75

41.88

60.23

Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

3.75
80.00
83.75
0.00
83.75
83.75
41.88
0.00

Rs.

41.88

Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

3.75
80.00
83.75
0.00
83.75
83.75
41.88
0.00

Rs.

41.88

LOADING & UNLOADING CHARGES BY MANUAL MEANS (INCLUDING IDLE HIRE CHARGES
OF TRUCKS)
A) For Earth, Sand, Morrum, Manure, Fly Ash (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
Rate
a) Labour:
0.01 day Head mazdoor
375.00
0.25 day Mazdoor
320.00

Per

Amount

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

3.75
80.00
83.75
0.00
83.75

414.10

Hour

Rs.

207.05

0.50 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

148.15

0.50 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

83.35

0.00 add area allowance at 0% on Rs.


Total labour charges
b) Machinery:
0.50 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

83.75

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum
(ii) Unloading charges:
Out put
=
5.50 Cum
a) Labour:
0.005 day Head mazdoor
0.125 day Mazdoor

83.35

94.96

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
438.55
522.30
522.30
94.96
0.00

Rs.

94.96

Rate

Per

375.00
320.00

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

1.88
40.00
41.88
0.00
41.88

414.10

Hour

Rs.

68.74

0.166 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

49.19

0.166 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

27.67

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum

27.67

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
145.60
187.48
187.48
34.09
0.00

Rs.

34.09

0.00 add area allowance at 0% on Rs.


Total labour charges
b) Machinery:
0.166 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

41.88

34.09

Amount

B) For Lime, Agrregate, Stone Boulder, Brick aggregate, Kankar, Building rubbish, Crushed
slag, Stone for machinery work (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
a) Labour:
0.02 day Head mazdoor
0.50 day Mazdoor

Rate

Per

Amount

375.00
320.00

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

7.50
160.00
167.50
0.00
167.50

0.00 add area allowance at 0% on Rs.


Total labour charges
b) Machinery:
0.50 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

167.50

414.10

Hour

Rs.

207.05

0.50 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

148.15

0.50 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum

83.35

(ii) Unloading charges:


Out put
=
5.50 Cum
a) Labour:
0.01 day Head mazdoor
0.25 day Mazdoor

Hour

110.19

Rs.

83.35

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
438.55
606.05
606.05
110.19
0.00

Rs.

110.19

Rate

Per

375.00
320.00

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

3.75
80.00
83.75
0.00
83.75

414.10

Hour

Rs.

103.53

0.25 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

74.08

0.25 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

41.68

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum

41.68

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
219.29
303.04
303.04
55.1
0.00

Rs.

55.10

0.00 add area allowance at 0% on Rs.


Total labour charges
b) Machinery:
0.25 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

C) For Cement (per Tonne):


(i) Loading charges:
Out put
=
10.00 MT
a) Labour:
0.06 day Head mazdoor
1.50 day Mazdoor

83.75

55.10

Amount

Rate

Per

Amount

375.00
320.00

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

22.50
480.00
502.50
0.00
502.50

0.00 add area allowance at 0% on Rs.


Total labour charges
b) Machinery:
1.00 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

502.50

414.10

Hour

Rs.

414.10

1.00 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

296.30

1.00 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
10.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 MT

166.70

(ii) Unloading & Stacking charges:


Out put
=
10.00 MT
a) Labour:
0.07 day Head mazdoor
1.80 day Mazdoor

Hour

137.96

Rs.

166.70

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
877.10
1379.60
1379.60
137.96
0.00

Rs.

137.96

Rate

Per

Amount

375.00
320.00

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

26.25
576.00
602.25
0.00
602.25

0.00 add area allowance at 0% on Rs.


Total labour charges
b) Machinery:
1.00 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

602.25

414.10

Hour

Rs.

414.10

1.00 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

296.30

1.00 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

166.70

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
10.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 MT

166.70

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
877.10
1479.35
1479.35
147.94
0.00

Rs.

147.94

D) For Structural steel, Steel bars (per Tonne):


(i) Loading charges:
Out put
=
10.00 MT
a) Labour:
0.07 day Head mazdoor
1.80 day Mazdoor

147.94

Rate

Per

Amount

375.00
320.00

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

26.25
576.00
602.25
0.00
602.25

0.00 add area allowance at 0% on Rs.


Total labour charges
b) Machinery:
1.00 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

602.25

414.10

Hour

Rs.

414.10

1.00 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

296.30

1.00 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
10.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 MT

166.70

(ii) Unloading & Stacking charges:


Out put
=
10.00 MT
a) Labour:
0.07 day Head mazdoor
1.80 day Mazdoor

Hour

147.94

Rs.

166.70

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
877.10
1479.35
1479.35
147.94
0.00

Rs.

147.94

Rate

Per

Amount

375.00
320.00

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

26.25
576.00
602.25
0.00
602.25

0.00 add area allowance at 0% on Rs.


Total labour charges
b) Machinery:
1.00 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

602.25

414.10

Hour

Rs.

414.10

1.00 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

296.30

1.00 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

166.70

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
10.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 MT

166.70

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
877.10
1479.35
1479.35
147.94
0.00

Rs.

147.94

E) For Bricks of size 225 x 140 x 70mm (per 1000 Nos):


(i) Loading charges:
Out put
=
2000.00 Nos
a) Labour:
0.01 day Head mazdoor
0.25 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
b) Machinery:
0.33 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.
0.33 Hrs. fuel charges of Truck 10 Tonnes
capacity @ Rs.

147.94

Rate

Per

375.00
320.00

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

3.75
80.00
83.75
0.00
83.75

414.10

Hour

Rs.

136.65

296.30

Hour

Rs.

97.78

83.75

Amount

0.33 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
2000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos

55.01

(ii) Unloading & Stacking charges:


Out put
=
2000.00 Nos
a) Labour:
0.06 day Head mazdoor
1.50 day Mazdoor

Hour

186.60

Rs.

55.01

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
289.44
373.19
373.19
186.60
0.00

Rs.

186.60

Rate

Per

Amount

375.00
320.00

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

22.50
480.00
502.50
0.00
502.50

0.00 add area allowance at 0% on Rs.


Total labour charges
b) Machinery:
1.00 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

502.50

414.10

Hour

Rs.

414.10

1.00 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

296.30

1.00 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

166.70

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
2000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos

166.70

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
877.10
1379.60
1379.60
689.8
0.00

Rs.

689.80

689.80

LOADING & UNLOADING CHARGES BY MECHANICAL MEANS (INCLUDING IDLE HIRE


CHARGES OF TRUCKS)
A) For Earth, Sand, Morrum, Manure, Fly Ash (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
Rate
a) Machinery:
0.11 Hrs. hire charges of Tipper 10 Tonnes 414.10
capacity @ Rs.

Per

Amount

Hour

Rs.

45.55

0.11 Hrs. fuel charges of Tipper 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

32.59

0.11 Hrs. crew charges of Tipper 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

18.34

0.06 Hrs. hire charges of FE loader 1.00 Cum


bucket capacity @ 45 Cum @ Rs.

414.10

Hour

Rs.

24.85

0.06 Hrs. fuel charges of FE loader 1.00 Cum


bucket capacity @ 45 Cum @ Rs.

296.30

Hour

Rs.

17.78

0.06 Hrs. crew charges of FE loader 1.00 Cum


bucket capacity @ 45 Cum @ Rs.

166.70

Hour

Rs.

10.00

0.00 add area allowance at 0% on Rs.


Total machinery charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum

28.34

Rs.
Rs.
Rs.
Rs.
Rs.

0.00
149.11
149.11
27.11
0.00

Rs.

27.11

(ii) Unloading charges:


Out put
=
5.50 Cum
a) Machinery:
0.08 Hrs. hire charges of Tipper 10 Tonnes
capacity @ Rs.

27.11

Rate

Per

414.10

Hour

Rs.

33.13

0.08 Hrs. fuel charges of Tipper 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

23.70

0.08 Hrs. crew charges of Tipper 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

13.34

0.00 add area allowance at 0% on Rs.


Total machinery charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum

13.34

Rs.
Rs.
Rs.
Rs.
Rs.

0.00
70.17
70.17
12.76
0.00

Rs.

12.76

12.76

Amount

B) For Lime, Agrregate, Stone Boulder, Brick aggregate, Kankar, Building rubbish, Crushed
slag, Stone for machinery work (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
a) Machinery:
0.17 Hrs. hire charges of Tipper 10 Tonnes
capacity @ Rs.

Rate

Per

Amount

414.10

Hour

Rs.

70.40

0.17 Hrs. fuel charges of Tipper 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

50.37

0.17 Hrs. crew charges of Tipper 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

28.34

0.12 Hrs. hire charges of FE loader 1.00 Cum


bucket capacity @ 45 Cum @ Rs.

414.10

Hour

Rs.

49.69

0.12 Hrs. fuel charges of FE loader 1.00 Cum


bucket capacity @ 45 Cum @ Rs.

296.30

Hour

Rs.

35.56

0.12 Hrs. crew charges of FE loader 1.00 Cum


bucket capacity @ 45 Cum @ Rs.

166.70

Hour

Rs.

20.00

0.00 add area allowance at 0% on Rs.


Total machinery charges
Rate for
5.50 Cum

48.34

Rs.
Rs.
Rs.

0.00
254.36
254.36

Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum

46.25

Rs.
Rs.

46.25
0.00

Rs.

46.25

315806963.xlsx

E- DATA
Standard Data - Electrical Items SSR 09-10

3
Name of the Work :- Construction of Govt. Degree College at KUPPAM(V) of KUPPAM (M) CHITTOOR District
1
Area allowence
20%
1
Overheads and contractors profit on materials
0%
0
Overheads and contractors profit on labour
0%
2
Specification No.
Description
Unit
Quantity Rate Rs. Amount Rs. 0 Remarks
0
1
2
3
4
5
66
7
1

Supply and Fixing of 25mm dia 2mm thick PVC pipe (ISI
MARK) concealed in Roof Slabs with all required
accessories including masonary work and labour charges
etc., complete. Make : Sudhakar/Maru plast/Avon plast

Taking Output = 100 M


a) Material
elec-1.2.4

25mm dia 2mm thick PVC pipe

100 M

2500.00

2500.00

ele-1.2.39

25mm dia 1,2,3 & 4 way deep Junction Box

Each

12

20.00

240.00

elec-1.2.44

25mm PVC bends

Each

12

4.50

54.00

Add contr profit @14% on material

0.00

2794.00
0.00

Total material cost

2794.00

b) Labour charges :
Skilled Electrician

day

224.00

448.00

Semi skilled Electrician

day

206.00

412.00

Helpers

day

206.00

412.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

254.40
1526.40

C) Cost for 100 RM

0.00
4320.40

Rate per Metre = C/100

43.25

Note : 1. If 25mm dia PVC / MS pipes are used for light / fan point,
add the cost of sheet metal / well seasoned wooden board / box.

Supply and Fixing of 25mm dia 1.5mm thick P.V.C. pipe (ISI
MARK) concealed in wall with all required accessories
including masonary work for light, fan and separate plug
point with well seasoned TW box including all labour
charges etc., complete.
Make : Sudhakar/Maru
plast/Avon plast
Taking Output = 100 M
a) Material

elec-1.2.3

25mm dia 1.5mm thick PVC pipe

100 M

1950.00

elec-8.1.10

U' Links

elec-1.4.12

8"x10" TW deep boxes

ele-1.2.39
elec-1.2.44

100 Nos

40.00

80.00

Each

40.00

80.00

25mm dia 1,2,3 & 4 way deep Junction Box

Each

12

20.00

240.00

25mm PVC bends

Each

12

4.50

54.00

kg

50

5.81

290.50

Cement

1950.00

2694.50
Add contr profit @14% on material

0.00

0.00

Total material cost

2694.50

b) Labour charges :
Skilled Electrician

day

224.00

448.00

Semi skilled Electrician

day

206.00

412.00

Helpers

day

206.00

412.00

Mason Ist class

day

224.00

448.00

Add area allowence on labour charges @

20%

Page 1 of 517

344.00

315806963.xlsx
Specification No.

Description

Unit

Quantity

Add contr profit @14% on Labour

0%

1
0
2
Rate Rs. Amount Rs. 0
0
5
66
2064.00

C) Cost for 100 RM

0.00
47.60

Wiring with 2 runs of 14/0.3mm (1.0 Sq.mm) Fire Retardant


(FR) P.V.C. insulated flexible copper cable (ISI MARK) in
existing pipe with 6A switch, Ceiling rose and 3mm thick
hylam sheet covering to switch control box including all
labour charges etc., complete for light, bell, fan and exhaust
fan points in Non-Residential Buildings
Makes : Finolex / L&T/

The
R&B
Department
Proposed
Labour, for both
piping & wiring
considering
40% Labour, for
Wire
draw.
Keeping
this,
the labour is
proposed
for
wiring 100 RM.

Taking Output = 6 Points

Million / RPG/
paragon

a) Material
elec-1.5.1

14/0.3mm PVC FR flexible copper wire

100 M

893.00

893.00

elec-1.7.1

6A Switch @17.50/each (olive model)

each

17.50

105.00

elec-1.7.15

6A 3 way Ceiling Rose@19/each

each

19.00

114.00

elec-1.4.19

25 x 20 cms (10" x8") Hylam sheet 3mm thick

no

40.00

40.00
1152.00

Add contr profit @14% on material

0.00

0.00

Total material cost

1152.00

b) Labour charges :

Skilled Electrician

day

0.6

224.00

134.40

Semi skilled Electrician

day

1.2

206.00

247.20

Helpers

day

0.6

206.00

123.60

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

101.04
606.24

0.00

C) Cost for 6 Points

1657.20

Rate per Point = C/6

276.20

Wiring with 2 runs of 1.0 Sqmm PVC insulated flexible


copper cable, (phase,neutral) in the existing metalic/non
metalic conduit pipe with 6A flush type two way switch
control,ceiling rose and 3mm thick hylam sheet covering to
MS Switch control box including all labour charges etc., for
stir case as required
Make: Finolex / L &T

Rate as per light point in Non Residental Building =276.2


For stair case
5

4758.50

Rate per Metre = C/100


3

E- DATA
Remarks

Supply and run of 2 of 2.5 sq.mm PVC insulated flexible


copper cable and one run of 1.0 sq.mm flexible copper wire
for earthing in existing MS conduit pipe for circuits including
labour charges (phase neutral and earth) etc., complete as
required for switch board circuit mains.
Make:Finolex / L&T.

Page 2 of 517

1.50

276.20

414.30

315806963.xlsx
Specification No.

Description

Unit

Quantity

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

elec-1.5.3

2 run of 2.5 sq.mm wire

2.00

2130.00

4260.00

elec-1.5.1

1 run of 1.00 sq.mm wire

1.00

893.00

893.00
5153.00

Add contr profit @14% on material

0.00

0.00

Total material cost

5153.00

Labour Charges
Skilled Electrician (0.67 + 0.34)

day

1.01

224.00

226.24

Semi skilled Electrician (2 + 1)

day

206.00

618.00

Helpers (0.67 + 0.34)

day

1.01

206.00

208.06

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

210.46
1262.76

Cost per 100 Rmt


Rate per Meter= C/100
6

0.00
6415.76
64.20

Supply and 2 runs of 4.0 sq mm PVC insulated flexible


copper cable and 1 run of 2.5 sq.mm flexible PVC insulated
copper cable for earthing in the existing conduit pipe for
power point including labour charges for 16A sockets.
Make:Finolex / L&T.

elec-1.5.4

2 run of 4.0 sq.mm wire

2.00

3100.00

6200.00

elec-1.5.3

1 run of 2.50 sq.mm wire

1.00

2130.00

2130.00
8330.00

Add contr profit @14% on material

0.00

0.00

Total material cost

8330.00

Labour Charges

Skilled Electrician (1.0 + 0.34)

day

1.34

224.00

300.16

Semi skilled Electrician (3 + 1)


Helpers (1.0 + 0.34)

day

206.00

824.00

day

1.34

206.00

276.04

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

280.04
1680.24

Cost per 100 Rmt

10010.24

Rate per Meter= C/100


7

0.00
100.15

Supply & run of 2 of 6.0 Sqmm(84/0.3mm) PVC insulated


flexible copper cable and one run of 2.5 Sqmm flexible PVC
insulated copper cable for earthing in the existing conduit
pipe for AC points & SDB's etc as required.
Make:Finolex / L&T.

elec-1.5.5

2 run of 6.0 sq.mm wire

2.00

4715.00

elec-1.5.3

1 run of 2.50 sq.mm wire

1.00

2130.00

9430.00
2130.00
11560.00

Add contr profit @14% on material

0.00

0.00

Total material cost

11560.00

Labour Charges
Skilled Electrician (1.0 + 0.34)

day

1.34

224.00

300.16

Semi skilled Electrician (3 + 1)

day

206.00

824.00

Helpers (1.0 + 0.34)

day

1.34

206.00

276.04

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

Cost per 100 Rmt

280.04
1680.24

0.00
13240.24

Page 3 of 517

E- DATA
Remarks
7

315806963.xlsx
Specification No.

Description

Unit

Quantity

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

Rate per Meter= C/100


8

132.45

Supply and run of 4 of 6 Sq mm PVC insulated flexible


copper cable and 1 run of 2.5 Sq mm flexible PVC insulated
flexible copper cable in the existing conduit pipe for run of
mains from main panel board to TPN DB'S with pin type
lugs and connections etc.,complete for Lighting Distribution
boards.
Make:Finolex / L&T.

elec-1.5.5

4 run of 6.0 sq.mm wire

4.00

4715.00

elec-1.5.3

1 run of 2.50 sq.mm wire

1.00

2130.00

18860.00
2130.00
20990.00

Add contr profit @14% on material

0.00

0.00

Total material cost

20990.00

Labour Charges
Skilled Electrician (2.0 + 0.34)

day

2.34

224.00

524.16

Semi skilled Electrician (6 + 1)

day

206.00

1442.00

Helpers (2.0 + 0.34)

day

2.34

206.00

482.04

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

489.64
2937.84

Cost per 100 Rmt

23927.84

Rate per Meter= C/100


9

0.00
239.30

Wiring with 2 runs of 14/0.3mm (1.0 Sq.mm) P.V.C.


insulated F.R flexible copper cable (ISI MARK) in existing
pipe with 6A switch, Ceiling rose and 3mm thick hylam sheet
covering to switch control box including all labour charges
etc., complete for light, bell, fan and exhaust fan points in
Residential Buildings.
Makes : Finolex / L&T.

Taking Output = 7 Points


a) Material
elec-1.5.1

14/0.3mm PVC FR flexible copper wire

100 M

893.00

893.00

elec-1.7.1

6A Switch @17.50/each(olive mode)

each

17.50

122.50

elec-1.7.15

6A 3 way Ceiling Rose@19/each

each

19.00

133.00

elec-1.4.19

25 x 20 cms (10" x8") Hylam sheet 3mm thick

No

40.00

40.00
1188.50

Add contr profit @14% on material

0.00

0.00

Total material cost

1188.50

b) Labour charges :
Skilled Electrician

day

0.7

224.00

156.80

Semi skilled Electrician

day

1.4

206.00

288.40

Helpers

day

0.7

206.00

144.20

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

C) Cost for 7 Points

117.88
707.28

0.00
1895.78

Rate per Points = C/7

270.85

Page 4 of 517

E- DATA
Remarks
7

315806963.xlsx

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

Specification No.

Description

Unit

Quantity

1.50

270.85

406.30

Wiring with 2 runs of 1.0 Sqmm PVC insulated flexible


copper cable, (phase,neutral) in the existing metalic/non
metalic conduit pipe with 6A flush type two way switch
control,ceiling rose and 3mm thick hylam sheet covering to
MS Switch control box including all labour charges etc., for
stir case in residential building as required
Make: Finolex / L &T

Rate as per light point in Non Residental Building =270.85


For stair case
10

Supply and fixing of 6A 3 pin wall plug socket with 6A switch


control on a common switch board with earth continuity
including wire leads, earth connections along with all labour
charges etc., complete.
Makes : Gold Medal Olive /Million, Zoom / Vimal Opel
Taking Output = each
a) Material

elec-1.7.4

6A 3 pin / 2 pin Socket

each

25.00

25.00

elec-1.7.1

6A switch ( olive model)]

each

17.50

17.50

Add contr profit @14% on material

0.00

42.50
0.00

Total material cost

42.50

b) Labour charges :

Skilled Electrician

day

0.067

224.00

15.01

Helpers

day

0.067

206.00

13.80

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

5.76
34.57

Rate per each

0.00
77.10

Note : Labour Charges proposed for 1point considering 15 per day

11

Wiring with 2 of 14/0.3mm (1.0 Sq.mm) P.V.C. insulated F.R.


flexible copper cable (ISI MARK) in existing pipe with 6A
switch control and 3/2 pin sockets fixing on separate board
including all labour charges etc., complete.
Makes : Gold Medal /Million / Vimal /
Taking Output = 15 Points
a) Material

elec-1.5.1

14/0.3mm PVC FR flexible copper wire

100 M

893.00

893.00

elec-1.7.1

6Aswitches @17.50/each(olive model)

each

15

17.50

262.50

elec-1.7.4

6A 3 pin / 2 Pin Socket

each

15

25.00

375.00
1530.50

Add contr profit @14% on material

0.00

0.00

Total material cost

1530.50

b) Labour charges :
Skilled Electrician

day

1.5

224.00

336.00

Semi skilled Electrician

day

1.5

206.00

309.00

Helpers

day

1.5

206.00

309.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

C) Cost for 15 Points

190.80
1144.80

0.00
2675.30

Rate per Points = C/15

178.40

Page 5 of 517

E- DATA
Remarks
7

315806963.xlsx
Specification No.

Description

Unit

Quantity

12

Supply and Fixing of 16A 3pin and 6A 3pin plug socket with
and 16A switch control duly recessed in wall with MS switch
deep box of 6" x8" x2 1/2" size covered with hylam sheet
including earth connections and all labour charges etc.,
complete.
Makes : Gold Medal /Million / Vimal

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

Taking Output = each


a) Material
elec-1.3.5

20 x 15 cms (8" x6") MS switch deep box

each

150.00

150.00

elec-1.4.18

21.6 x 16.6 cms (8.5 x 6.5") 3mm thick hylam sheet

each

24.00

24.00

elec-1.7.11

16A 3 pin / 6A 3pin plug socket (5 in 1)

each

130.00

130.00
304.00

Add contr profit @14% on material

0.00

0.00

Total material cost

304.00

b) Labour charges :
Skilled Electrician

day

0.1

224.00

22.40

Semi Skilled Electrician

day

0.1

206.00

20.60

Helpers

day

0.1

206.00

20.60

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

12.72
76.32

Rate per each

0.00
380.35

Note : Labour Charges proposed for 10 jobs per day

13

Supply and run of 1 of 14 /0.3mm (1.0 Sq.mm) FR P.V.C.


insulated flexible copper cable in existing pipe for earth
continuity including all labour charges etc., complete.
Makes : Finolex / L&T.
Taking Output = 100 M
a) Material

elec-1.5.1

14/0.3mm FR PVC copper cable

100 M

Add contr profit @14% on material

893.00

0.00

893.00
0.00

Total material cost

893.00

b) Labour charges :
Skilled Electrician

day

0.34

224.00

76.16

Semi Skilled Electrician

day

206.00

206.00

Helpers

day

0.34

206.00

70.04

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

70.44
422.64

C) Cost for 100 RM

0.00
1315.64

Rate per Metre = C/100

13.20

Note : Labour Charges considered for 150 M / day


14

Supply and run of 2 of 36/0.3mm (2.5 Sq.mm) F.R P.V.C.


insulated flexible copper cable in existing pipe for mains
inlcuding all labour charges etc., complete.
Makes : Finolex / L&T.
Taking Output = 100 M
a) Material

elec-1.5.3

36/0.3mm (2.5 sqmm) FR PVC copper cable

100 M

Add contr profit @14% on material

0.00

Page 6 of 517

2130.00

4260.00
0.00

E- DATA
Remarks
7

315806963.xlsx
Specification No.

Description

Unit

Quantity

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

Total material cost

4260.00

b) Labour charges :
Skilled Electrician

day

0.67

224.00

150.08

Semi Skilled Electrician

day

206.00

412.00

Helpers

day

0.67

206.00

138.02

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

140.02
840.12

C) Cost for 100 RM

0.00
5100.12

Rate per Metre = C/100

51.05

Note : Labour Charges considered for 150 M / day


15

Supply and run of 2 of 56/0.3mm (4 Sq.mm) FR P.V.C.


insulated flexible copper cable in existing pipe for mains
inlcuding all labour charges etc., complete.
Makes : Finolex / L&T.
Taking Output = 100 M
a) Material

elec-1.5.4

56 /0.3mm (4 sqmm)FR PVC flexible copper cable


Add contr profit @14% on material

100 M

3100.00

0.00

6200.00
0.00

Total material cost

6200.00

b) Labour charges :
Skilled Electrician

day

224.00

224.00

Semi Skilled Electrician

day

206.00

618.00

Helpers

day

206.00

206.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

209.60
1257.60

C) Cost for 100 RM

0.00
7457.60

Rate per Metre = C/100

74.60

Note : Labour Charges considered for 100 M / day


16

Supply and run of 2 of 84/0.3mm (6.0 Sq.mm) FR P.V.C.


insulated flexible copper cable in existing pipe for mains
inlcuding all labour charges etc., complete.
Makes : Finolex / L&T.
Taking Output = 100 M
a) Material

elec-1.5.5

84 /0.3mm (6 Sq.mm) FR PVC flexible copper cable.


Add contr profit @14% on material

100 M

4715.00

0.00

9430.00
0.00

Total material cost

9430.00

b) Labour charges :
Skilled Electrician

day

224.00

224.00

Semi Skilled Electrician

day

206.00

618.00

Helpers

day

206.00

206.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

209.60
1257.60

C) Cost for 100 RM

0.00
10687.60

Rate per Metre = C/100

106.90

Note : Labour Charges considered for 100 M / day


17

Supply and run of 2 of 140 /0.3mm (10 Sq.mm) F.R PVC


insulated flexible copper cable in existing pipe for mains
including all labour charges etc., complete.
Makes : Finolex / L&T.
Taking Output = 100 M
a) Material

elec-1.5.6

140/0.3 (10 Sq.mm) FR PVC flexible copper cable

Page 7 of 517

100 M

7330.00

14660.00

E- DATA
Remarks
7

315806963.xlsx
Specification No.

Description

Unit

Quantity

Add contr profit @14% on material

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

0.00

0.00

Total material cost

14660.00

b) Labour charges :
Skilled Electrician

day

224.00

224.00

Semi Skilled Electrician

day

206.00

618.00

Helpers

day

206.00

206.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

209.60
1257.60

C) Cost for 100 RM

0.00
15917.60

Rate per Metre = C/100

159.20

Note : Labour Charges considered for 100 M / day


18

Supply and run of 2 of 126 /0.4mm (16 Sq.mm) F.R PVC


insulated flexible copper cable in existing pipe for mains
including all labour charges etc., complete.
Makes : Finolex / L&T.
Taking Output = 100 M
a) Material

elec-1.5.7

126/0.4mm (16 Sq.mm) FR PVC flexible copper cable


Add contr profit @14% on material

100 M

11725.00

0.00

23450.00
0.00

Total material cost

23450.00

b) Labour charges :
Skilled Electrician

day

224.00

224.00

Semi Skilled Electrician

day

206.00

618.00

Helpers

day

206.00

206.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

209.60
1257.60

C) Cost for 100 RM

0.00
24707.60

Rate per Metre = C/100

247.10

Note : Labour Charges considered for 100 M / day

19

Supply and run of 4 of 10 Sq mm PVC insulated flexible


copper cable and 1 run of 4.00 Sq mm flexible PVC
insulated flexible copper cable in the existing conduit pipe
for run of mains from main panel board to TPN DB'S with
pin type lugs and connections etc.,complete for PDB's and
AC DBS
Make:Finolex / L&T.
Taking Output = 100 M
a) Material

elec-1.5.6

126/0.4mm (10 Sq.mm) FR PVC flexible copper cable

elec-1.5.4

1 run of 4.0 sq.mm wire

100 M

7330.00

100

1.00

3100.00

29320.00
3100.00
32420.00

Add contr profit @14% on material

0.00

0.00

Total material cost

32420.00

b) Labour charges :
Skilled Electrician (2.0 + 0.5)

day

2.5

224.00

560.00

Semi skilled Electrician (6 + 1.5)

day

7.5

206.00

1545.00

Helpers (2.0 + 0.5)

day

2.5

206.00

515.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

524.00
3144.00

0.00

Sundries
C) Cost for 100 RM

35564.00

Rate per Metre = C/100

355.65

Page 8 of 517

E- DATA
Remarks
7

315806963.xlsx

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

Specification No.

Description

Unit

Quantity

1 Phase Distribution board with 20A plug and socket.

Nos

818.00

818.00

10/16/20A SP MCB

Nos

184.00

184.00

Add contr profit @14% on material

0.00

Note : Labour Charges considered for 100 M / day


20

Supply and fixing Distribution board with 20A single phase


plug and Socket, in sheet steel enclosure with 10/16/20A SP
MCB including internal connection and labour charges for
flush mounting etc., complete
Makes : MDS / GE/ L&T Hager / Seimens/Schneider.
a) Material

elec-2.93.36
ele-2.9.1

1002.00
0.00

Total material cost

1002.00

b) Labour charges :
Skilled Electrician

Nos

0.25

224.00

56.00

Semi skilled Electrician

Nos

0.25

206.00

51.50

Helpers

Nos

0.25

206.00

51.50

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

Sundries such as Cement, Sand, T.W. Plugs, Screws etc.,

LS

31.80
190.80

0.00
130.00

Rate per each

1322.80

Note : 1. Labour Charges considered for 4 jobs / day


2. For concealing, add the following:
a

1No. Semi skilled mason

1/4 bag cement

21

Supply and fixing TPN Distribution board with IP-43


protection (Metal Door) suitable for 3 phase ELCB / RCCB /
FP Isolator as incomer and 10kA SP MCBs as outing going
including internal connection and labour charges for flush
mounting etc., complete.
Makes: MDS / GE/ L&T Hager / Seimens/Schneider.

40A FP Isolator - 1 No for incomer,


MCBs - 12Nos for outgoing.

10kA-6-32A SP

Taking Output = each


a) Material
elec-2.93.22

4way TPN, D.B with IP-43 Protection (MD) suitable for 3


phase ELCB / RCCB/ FP Isolator as incommer.

each

elec-2.91.6

40A, 4 Pole Isolator

elec-2.9.1

10kA - 6-32A range SP MCBs


Add contr profit @14% on material

0.00

2261.00

2261.00

each

731.00

731.00

each

12

184.00

2208.00
5200.00
0.00

Total material cost

5200.00

b) Labour charges :
Skilled Electrician

day

0.5

224.00

112.00

Semi Skilled Electrician

day

206.00

206.00

Helpers

day

206.00

206.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

628.80

0.00

Sundries such as TW Plugs, Screws Cement etc,

LS

14.00

14.00

Rate per each

5842.80

Note : Labour Charges considered for 2 jobs / day


B

63A FP Isolator - 1 No for incomer,


MCBs - 12Nos for outgoing.

104.80

10kA-6-32A SP

Page 9 of 517

E- DATA
Remarks
7

Specification No.

Description

Unit

Quantity

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

elec-2.93.22

4way TPN, D.B with IP-43 Protection (MD) suitable for 3


phase ELCB / RCCB/ FP Isolator as incommer.

each

2261.00

2261.00 L&T Hager

elec-2.91.7

63A, 4 Pole Isolator

each

800.00

800.00 L&T Hager

elec-2.9.1

10kA - 6-32A range SP MCBs

each

12

184.00

2208.00 L&T Hager

315806963.xlsx

E- DATA
Remarks
7

Taking Output = each


a) Material

5269.00
Add contr profit @14% on material

0.00

0.00

Total material cost

5269.00

b) Labour charges :
Skilled Electrician

day

0.5

224.00

112.00

Semi Skilled Electrician

day

206.00

206.00

Helpers

day

206.00

206.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

628.80

0.00

Sundries such as TW Plugs, Screws Cement etc,

LS

14.00

14.00

104.80

Rate per each

5911.80

Note : Labour Charges considered for 2 jobs / day


B -2

80A FP Isolator - 1 No for incomer,


MCBs - 12Nos for outgoing.

10kA-6-32A SP

Taking Output = each


a) Material
elec-2.93.22

4way TPN, D.B with IP-43 Protection (MD) suitable for 3


phase ELCB / RCCB/ FP Isolator as incommer.

each

2261.00

2261.00

elec-2.91.8

80A, 4 Pole Isolator

each

846.00

846.00

elec-2.9.1

10kA - 6-32A range SP MCBs

each

12

184.00

2208.00

Add contr profit @14% on material

0.00

5315.00
0.00

Total material cost

5315.00

b) Labour charges :
Skilled Electrician

day

0.5

224.00

112.00

Semi Skilled Electrician

day

206.00

206.00

Helpers

day

206.00

206.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

628.80

Sundries such as TW Plugs, Screws Cement etc,

LS

14.00

104.80

Rate per each

0.00
14.00
5957.80

Note : Labour Charges considered for 2 jobs / day


22

Supply and fixing SPN Distribution board with IP-43


protection (Metal Door) suitable for single phase ELCB /
RCCB/DP Isolator as incomer and 10kA SP MCBs as outing
going including internal connection and labour charges for
surface / flush mounting etc., complete.
Makes: MDS /L&T Hager / Havells

40A DP Isolator / RCCB / ELCB - 1 No for incomer,


32A SP MCBs - 6Nos for outgoing.

6-

Taking Output = each


a) Material
elec-2.93.5

SPN 8 way D.B with IP-43 Protection (MD) suitable for


single phase ECCB / RCCB/ DP Isolator.

each

1113.00

1113.00 L&T Hager

elec-2.91.2

40A D.P.Isolator

each

329.00

329.00 L&T Hager

Page 10 of 517

315806963.xlsx
Specification No.

Description

Unit

Quantity

each

elec-2.9.1

10 kA - 6-32A range SP MCBs

1
0
2
Rate Rs. Amount Rs. 0
0
5
66
184.00

0.00

0.00

Total material cost

2546.00

b) Labour charges :
Skilled Electrician

day

0.5

224.00

112.00

Semi Skilled Electrician

day

0.5

206.00

103.00

Helpers

day

206.00

206.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

505.20

Sundries such as hardware, cement etc,

LS

5.00

84.20

Rate per each

0.00
5.00
3056.20

Note : Labour Charges considered for 2 jobs / day

23

Supply and fixing TPN - Vertical type Distribution board


with IP -43 Protection with 125A, 4 Pole 25 kA MCCB as
incomer with 4Nos 63A TP MCBs and 12 Nos. 10 kA
SPMCBs as outgoing including internal connection and
labour charges for flush mounting etc., complete.
Makes: MDS/ L&T Hager

8 way TPN Vertical DB


a) Material

elec-2.93.35

8 Way TPN Vertical DB with IP -43 (Metal door) protection


suitable for 125A, 4 Pole, 25kA MCCB as incomer.

Nos

8917.00

elec-2.8.2

125 Amps, 4 Pole , 25 kA MCCB

Nos

6750.00

6750.00

elec-2.9.6

10 kA, 63A TP MCBs:

Nos

1328.00

10624.00

elec-2.9.1

10kA, 6 to 32A SP MCBs: Rs.184 / Each

Nos

184.00

0.00

Add contr profit @14% on material

0.00

8917.00

26291.00
0.00

Total material cost

26291.00

b) Labour charges :
Skilled Electrician

day

224.00

224.00

Semi Skilled Electrician

day

206.00

206.00

Helpers

day

206.00

206.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

763.20

Sundries such as T.W. Plugs, Screws, Cement etc.,

LS

19.00

127.20

Rate per each


2. If the Distribution Boards from Item No. 4.4.1 to 4.4.8 proposed for
concealing,
add skilled
the following:
a
1No. Semi
mason
b

0.00
19.00
27073.20

Note : 1. Labour Charges considered for 1 jobs / day

1/4 bag cement

Page 11 of 517

Say

1104.00 L&T Hager


2546.00

Add contr profit @14% on material

E- DATA
Remarks

27073.20

315806963.xlsx
Specification No.

Description

Unit

Quantity

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

24 Supply, installation, commissioning of 3Phases, neutral


415V, free standing type cubical panel board made of 16
Gauge CRCA sheet steel, the panel shall be painted after
processing 7 tank process with RAL 7032 siemens grey. The
panel shall be consisting of suitable rating of allumunium
bus bars ( At the rating of 0.8 A/Sq.mm) supported with
DMC/SMC and colour coded with heat shrinkable sleeves.
The bus bars fault level shall be 50 KA and shall be as per
requirement of local CEIG, fire regulations, other authorities
etc. Panel shall be suitable for accomdating the following
switch gears including supply of all components, hard wares
etc including all necessary civil works, adequate
reinforcement foundation bolts suitable G.I earth strip , 100
x 50mm MS base channel, earth bar, door loop earthings .
Bus bar to switch interconnections,

All cables shall have proper cable entry,gland plates,


suitable size of glands, earth tags for glands, lugs, cadmium
plated nuts , bolts, feeder identification marks, shall be
installed on performed trench and consisting of the
following as required and as per IS standards and panel
should be manufactures only from panel builds with CPRI
Test certificate.
250 A Aluminium Bus Bar with colour code.
Internal wiring with approved make cable
Earthing: Providing 50x6 mm G.I flat
Incommer: .
elec-2.1.5 250A TPN switchs with fuse L&T make.- 1 No.

7600

7600

elec-2.5.4 250A HRC Fuse links

330

990

elec-6.3.3 0- 250 A Digital Ammeter . - 1 No.

2500

2500

elec-6.3.8 Ammeter selector switch - 1 No.

175

175

elec-6.3.1 0-500V Digital Volt meter - 1 No.

2500

2500

elec-6.3.8 Voltmeter selector switch - 1 No.

175

175

elec-6.3.9 R, Y, B Indication lamps LED type, puse buttons.

135

405

450

2700

83

249

45

135

2025

20250

Metering Set:

elec-6.3.10 250 /5A C.T coils : 2 sets


216 20A Bakelite fuse fittings - 3 Nos.
elec-2.5.1 2A HRC fuse link - 3 Nos:
Outgoing :

10

elec-2.1.2 63A TPN SFU -10 NOS - L&T Make

37679

Sub TOTAL:

9419.75

Bus bars and insulators 25%

16955.55

Cost of enclosure @ 45%

3767.90

Bus bars and insulators 10%


Control wiring, Labour charges for errection of switch gear, Job
panel board including all labour charges etc complete with
connections for finished item of work including transportation
charges.5%

1883.95

565.19

L.S Towards unforseen items and rounding off

70271.34
Add contr profit @14% on material

0.00

Page 12 of 517

0.00

E- DATA
Remarks
7

315806963.xlsx
Specification No.

Description

Unit

Quantity

1
0
2
Rate Rs. Amount Rs. 0
0
5
66
70271.35

Total material cost


26

Providing independent earthling by excavating a trench to a


depth of 2.1 M in all soils, as per size specified in the Data,
using 40mm dia 'B' class GI pipe of 2.5 Mtrs length with
necessary accessories with hume pipe ring duly providing
staggered holes including filling with equal proportion of
Salt and Charcoal in layers and all labour charges etc.,
complete for small quarters.

a) Material
Earth Work Excavation of Hard gravel Soil with small
boulder for trench 1st step of size 1.5 x 0.6 x 0.9 m

cum

0.85

203.84

173.26

Excavation of Hard disteggrated rocks and boulders for


trench 2nd Step of size 1.2 x 0.6 x 1.2 m (Civil SSR)

cum

0.9

203.84

183.46

25.00

25.00

25% extra for narrow trench & pit and back filling with Sand,
Coke, Salt etc., and leveling
40mm dia 'B' Class G.I pipe

elec-8.1.12

Mtr

2.5

360.00

900.00

25 x 6 mm (1"X 1/4") G.I Flat duly drilled 12mm holes (4


Nos) of 200 mm (8") length

Each

75.00

75.00

Drilling of 16 Nos through holes of 12mm dia to G.I pipe

Each

16

5.00

80.00

G.I Nuts, Bolts an Washers


18" dia hume pipe ring

Set

12.00

48.00

Each

100.00

100.00
320.00

elec-8.1.16

Hard Coke

Kg

40

8.00

elec-8.1.17

Salt

Kg

20

4.00

80.00
1984.72

Add contr profit @14% on material

0.00

0.00

Total material cost

1984.72

b) labour charges for fixing pipe ring and connections

Each

Semi skilled Electrician

Nos

0.5

206.00

103.00

Helpers

Nos

0.5

206.00

103.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

41.20
247.20

0.00

Sundries
Rate per each

27

2231.92
Say

2231.95

Supply and Run of No.8 SWG G.I wire including cost of all
accessories and labour charges etc., complete.
a) Material

elec-8.1.45

No.8 SWG G.I wire 100 M Length (0.104 Kg / Mtr)

elec-8.1.10

U' Nails

Kg

10.4

55.00

572.00

100Nos

1.5

40.00

60.00
632.00

Add contr profit @14% on material

0.00

0.00

Total for material

632.00

b) labour charges
Helpers

day

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

C) Cost for 100 M

206.00

412.00
82.40

494.40

0.00
1126.40

Rate per mtr c/100

11.30

Page 13 of 517

E- DATA
Remarks
7

Specification No.

Description

Unit

Quantity

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

28

Supply, Transportation and fixing of 4' - 40 Watt box type


flourescent single Tube Light fitting with Energy saving
electronic ballast suitable for 40 Watt tube on varnished
teak wood round blocks with flexible 3 core wire etc.,,
complete with all connections including cost of 40W tube.
The fitting shall be under warranty for three years.
Makes: Crompton/Bajaj/Surya/Havells.

a) Material
4' x 40 watts box type flourscent light fitting.
Lamp cost of 40W
Tw Round blocks
Rate per each

each
each
each

1
1
2

810.00
45.00
6.00

Add contr profit @14% on material

0.00

315806963.xlsx

elec-3.6.8
elec-3.7.16
elec-8.1.35

0.00

Total for material


29

810.00
45.00
12.00
867.00
867.00

Supply and fixing of batten holder / slanting holder in lieu of


ceiling rose of light point complete with all connections and
all labour charges with 40W bulb (for new installation).
Makes : Gold Medal /Million / Vimal
Taking Output = each
a) Material

elec-1.7.16

PVC batten holder

each

19.00

elec-3.7.1

40W bulb

each

12.00

elec-1.7.15

Deduct Cost of Ceiling Rose

each

-19.00
12.00

Add contr profit @14% on material

0.00

0.00

Total for material

12.00

b) Labour charges :
Skilled Electrician

day

0.05

224.00

11.20

Helpers

day

0.05

206.00

10.30

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

4.30
25.80

Rate per each

0.00
37.80

Note : 1. The Cost of Ceiling Rose may be deducted in view


of holder.
2. Labour Charges proposed for 20 jobs per day

30

Supply and fixing of call bell of Anchor/Goldmedal/Million


make on 6"x8" decolam block including giving connections,
cost of all accessories and labour charges etc., complete.
Taking Output = each
a) Material

elec-1.7.22

Call bell

each

50

50.00

elec-1.4.25

8"x6" decolam block

each

36

36.00
86.00

Add contr profit @14% on material

0.00

0.00

Total for material

86.00

b) Labour charges :
Skilled Electrician

day

0.062

224

13.89

Helpers

day

0.062

206

12.77

Page 14 of 517

E- DATA
Remarks
7

315806963.xlsx
Specification No.

Description

Unit

Quantity

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

1
0
2
Rate Rs. Amount Rs. 0
0
5
66
5.33
31.99

Rate per each

31

0.00
118.00

Supply and fixing of Ding dong of Anchor/Goldmedal/Million


make on 6"x8" decolam block including giving connections,
cost of all accessories and labour charges etc., complete.
Taking Output = each
a) Material

elec-1.7.24 Ding dong bell

each

90

90

elec-1.4.25 6"x8" decolam block

each

36

36
126

Add contr profit @14% on material

0.00

0.00

Total material cost

126

b) Labour charges :
Skilled Electrician

day

0.062

224

13.89

Helpers

day

0.062

206

12.77

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

5.33
31.99

Rate per each


32

elec-5.1.3

158.00

Supply of 1200 mm (48") sweep 230V, A.C 50 Hz.Ceiling fan


with 3 Blades and double ball bearings with all standard
accessories.
Makes: Crompton Aura / Bajaj R Gold / Havells Festiva /
Usha Premium.
a) Material
1200 mm (48") Ceiling Fan
Transportation Charges on Unit Cost

each

Add contr profit @14% on material


Total material cost
33

0.00

1
1%

1600.00
16.00

1600
16.00
1616.00
0.00
1616.00

156.00

156.00

0.00

Supply and erecting Electronic type regulator for ceiling


fans 1200 mm sweep complete erected on existing board.
a) Material

elec-1.7.13

Electronics type Regulator

Add contr profit @14% on material

0.00

0.00
156.00

Total material cost


b) Labour charges.
Semi skilled Electrician

day

0.1

206.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

Rate per Each

8.36
50.16

0.00
206.20

Note : Labour is Considered for 10 jobs / day


34

20.60
21.20

Sundries.

Labour Charges

Page 15 of 517

E- DATA
Remarks
7

315806963.xlsx

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

Specification No.

Description

Unit

Quantity

23/0060 Twin Core wire

9.00

9.00

Unforseen item works, such as painting to down rod, screws


etc.,

LS

3.00

3.00

Labour charges for Fixing of Ceiling fan and regulator


including transportation and giving connections with twin
core wire etc., complete.
a) Material
elec-1.6.8

12.00
Add contr profit @14% on material

0.00

0.00
12.00

Total for material


b) Labour charges.
Skilled Electrician

day

0.125

224.00

28.00

Helper

day

0.125

206.00

25.75

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

10.75
64.50

Rate per Each

0.00
76.50

Note : Labour is Considered for 8 fans / day

35

Supply of fresh air exhaust fan of heavy duty 250V


A.C.50Hz.. 300mm size (12") 900 R.P.M etc., complete.
Makes: CG / Bajaj / Havells/ Orient.
a) Material

elec-5.1.14

300mm (12") H.D. Exhaust Fan

each

Transportation Charges on Unit Cost

2300.00

1%

23.00

Rate per Each

23.00
2323.00

Add contr profit @14% on material

0.00

0.00

Total for material


36

2300.00

2323.00

Labour charges for fixing of Exhaust fan in wall with


necessary connections and masonary work of making hole,
finishing etc., complete
a) Material

elec-1.6.8

23/0060 Twin flat wire

9.00

9.00

Cement

kg

25

4.40

110.00
119.00

Add contr profit @14% on material

0.00

0.00

Total for material

119.00

b) Labour charges.
Skilled Electrician

day

0.25

224.00

56.00

Helper

day

0.25

206.00

51.50

Mason

day

0.25

206.00

51.50

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

Sundries such as Sand, Bolt, Nuts etc.,

LS

Rate per Each

31.80
1

190.80

0.00

24.34

24.34
334.15

Note :1. Labour is Considered for 6 jobs / day


2. Cost of louver shutter may be added if required.
3. If hole is already made available, labour charges of
Mason shall be deleted.

Page 16 of 517

E- DATA
Remarks
7

Specification No.

Description

Unit

Quantity

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

37

Supply of 1x40W weather proof flourescent streetlight fitting


comprising canopy of sheet Aluminium in stove enamel
finish with copper / VPIT ballast, capacitor, tube and starter
etc., complete.
Makes: Phillips / GE / Wipro

315806963.xlsx

a) Material
elec-3.1.1

1x40W WP flourscent street light fitting.

each

1390.00

elec-3.7.16

Lamp cost of 40W

each

45.00

1390.00
45.00
1435.00

Add contr profit @14% on material

0.00

0.00

Total for material


38

1435.00

Fixing of 40W street light luminaire to the wall with 1.0 Mtr.,
25mm dia GI pipe bracket and anti tilting MS flat etc.,
including giving connections and labour charges etc.,
complete.
a) Material

BMW-F.83

25mm dia G.I pipe (Civil SSR 282)

212.00

212.00

elec-1.6.8

23/0060 twin core flexible copper cable

9.00

18.00

Pipe bending charges

LS

25.00

25.00

M.S flat and welding charges

LS

35.00

35.00
290.00

Add contr profit @14% on material

0.00

0.00

Total for material

290.00

b) Labour charges
Skilled Electrician/carpenter

day

0.2

224.00

44.80

Mason

day

0.2

224.00

44.80

Semi skilled Electrician / Helper

day

0.2

206.00

41.20

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

26.16
156.96

Rate per each

0.00
447.00

Note : Labour Charges considered for 5 fixtures / day .


Total cost including fixing
1635.90+503.58
39

1882.00

Supply of Integral street light luminaire of 150W HPSV lamp


fitting comprises of single piece die cast Aluminium body
with copper wound ballast and capacitor, Ignitor, with pot
optics including 150W HPSV lamp etc., complete.
Makes: Phillips / GE.
a) Material

elec-3.1.13

150W HPSV Lamp fitting single piece die cast Aluminium


body with copper wound ballast and capacitor, Ignitor, with
pot optics

each

5484.00

elec-3.4.10

150W HPSV lamp

each

710.00

5484.00

710.00
6194.00

Add contr profit @14% on material

0.00

0.00

Total for material

6194.00

Rate per each

6194.00

Page 17 of 517

E- DATA
Remarks
7

315806963.xlsx

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

Specification No.

Description

Unit

Quantity

40

Fixing of MV / SV/MH luminaire on wall with 1.0mt 40mm


dia GI pipe bracket and anti-tilting MS flat, 2.5 Sq.mm
flexible copper cable etc.,including all labour charges for
mason work and giving connections etc., complete.

40mm G.I pipe for Bracket (Civil SSR 286)

360.00

2.5 Sq.mm flexible copper cable

21.30

a) Material
BMW-F.87

360.00
85.20
445.20

Add contr profit @14% on material

0.00

0.00
445.20

Pipe bending charges

LS

25.00

25.00

Skilled Electrician

day

0.25

224.00

56.00

Carpenter

day

0.25

224.00

56.00

Helper

day

0.25

206.00

51.50

Welder

day

0.25

224.00

56.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

b) Labour charges for Antitiling MS flat / welding


charges & fixing

43.90
207.40

Rate per each


Note : Labour Charges considered for 4Nos MV / SV / MH in a day

41

0.00
733.60

Say

733.60

1010.00

1010.00

Supply and laying of 2 pair telephone wire in the existing


metallic/non metallic conduit pipe with connections
etc.,complete
Makes: million/payal/goldmedal/powerflex
Taking Output = 100 M
a) Material

elec-7.1.1

2 pair telephone wire

100 M

Add contr profit @14% on material

0.00

0.00

Total for material

1010.00

b) Labour charges :
Skilled Electrician

day

0.34

224.00

76.16

Semi Skilled Electrician


Helpers

day

206.00

206.00

day

0.34

206.00

70.04

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

70.44
422.64

0.00

Sundries
C) Cost for 100 RM

1432.64

Rate per Metre = C/100

14.35

Note : Labour Charges considered for 150 M / day

42

Supply and fixing of telephone jack type socket with top on


MS box with modular plate cover with screws connections
etc., Makes: Gold Medal Olive / Million zoom
Taking Output = 100 M
a) Material

elec-1.7.18

telephone jack type socket

44.00

44.00

elec-1.3.1

MS box

50.00

50.00

Page 18 of 517

E- DATA
Remarks
7

315806963.xlsx
Specification No.

Description

Unit

Quantity

elec-1.4.22

4x4 sunglass delux board

1
0
2
Rate Rs. Amount Rs. 0
0
5
66
12.00

12.00
106.00

Add contr profit @14% on material

0.00

0.00

Total for material

106.00

b) Labour charges :
Skilled Electrician

day

0.1

224.00

22.40

Semi Skilled Electrician

day

0.1

206.00

20.60

Helpers

day

0.1

206.00

20.60

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

12.72
76.32

0.00

Sundries
C) Cost for each
43

182.35

Supply and laying of LAN cable Cat-6(A) UTP CABLE in the


existing metallic/non metallic conduit pipe with connections
etc.,complete
Makes:D Link/Finolex
Taking Output = 100 M
a) Material

elec-7.1.4

cat-6 UTP LAN cable

100 M

Add contr profit @14% on material

2580.00

0.00

2580.00
0.00

Total for material

2580.00

b) Labour charges :
Skilled Electrician

day

0.34

224.00

76.16

Semi Skilled Electrician

day

206.00

206.00

Helpers

day

0.34

206.00

70.04

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

70.44
422.64

0.00

Sundries
C) Cost for 100 RM

3002.64

Rate per Metre = C/100

30.05

Note : Labour Charges considered for 150 M / day


44

Supply and fixing of


cat-6 RJ-45information outlets
including dual face plate with MS box with modular plate
cover with screws connections etc., Makes: Belden/D
link/Legrand
a) Material

elec-7.1.5

cat-6 RJ 45 information oulet

340.00

340.00

elec-1.3.1

MS box

50.00

50.00
0.00
390.00

Add contr profit @14% on material

0.00

0.00

Total for material

390.00

b) Labour charges :
Skilled Electrician

day

0.2

224.00

44.80

Semi Skilled Electrician

day

0.2

206.00

41.20

Helpers

day

0.12

206.00

24.72

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

22.14
132.86

0.00

Sundries
C) Cost for each

522.90

Page 19 of 517

E- DATA
Remarks
7

Specification No.

Description

Unit

Quantity

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

45

Supply and laying of RG 6 Co-axil cable in the existing


metallic/non metallic conduit pipe with connections
etc.,complete
Makes: Million/Gold medal/payal/power flex/sunlight

100 M

1700.00

315806963.xlsx

Taking Output = 100 M


a) Material
ELEC-7.1.3

RG6 CO-AXIL CABLE


Add contr profit @14% on material

0.00

1700.00
0.00

Total for material

1700.00

b) Labour charges :
Skilled Electrician

day

0.34

224.00

76.16

Semi Skilled Electrician

day

206.00

206.00

Helpers

day

0.34

206.00

70.04

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

70.44
422.64

0.00

Sundries
C) Cost for 100 RM

2122.64

Rate per Metre = C/100

21.25

Note : Labour Charges considered for 150 M / day


46

Supply and fixing of TV antenna outlet with MS box with


cover with screws connections etc., Makes: Goldmedal
olive/Million zoom/Vimal opel/Maru montero/Anchor
a) Material

elec1.7.19

TV socket outlet

26.00

26.00

elec-1.3.1

MS box

50.00

50.00

elec-1.4.22

sunglass delux board

12.00

12.00
88.00

Add contr profit @14% on material

0.00

0.00

Total for material

88.00

b) Labour charges :
Skilled Electrician

day

0.04

224.00

8.96

Semi Skilled Electrician

day

0.04

206.00

8.24

Helpers

day

0.04

206.00

8.24

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

5.09
30.53

0.00

Sundries
C) Cost for each
47

elec-4.1.28

118.55

Supply of the following PVC XLPE armoured cable 1100 V.


Grade with ISI mark stranded / solid, aluminimum conductor
complete
Make: Universal / NICCO/ TORRENT/CCI.
3.5 Core 50.00 Sq.mm.

Rmt

Add contr profit @14% on material

0.00

274.00

0.00

Total for material


elec-4.1.25

274.00
274.00

3.5 Core 35.00 Sq.mm.

Rmt

Add contr profit @14% on material

0.00

Total for material

207.00

207.00
0.00
207.00

Page 20 of 517

E- DATA
Remarks
7

315806963.xlsx
Specification No.

Description

Unit

Quantity

3.5 Core 25.00 Sq.mm.

Rmt

Add contr profit @14% on material

0.00

elec-4.1.22

1
0
2
Rate Rs. Amount Rs. 0
0
5
66
174.00

174.00
174.00

4.0 Core 16.00 Sq.mm.

Rmt

Add contr profit @14% on material

0.00

136.00

136.00
0.00

Total for material


48

136.00

Earth work excavation of Trench in hard ground soil, laying of U.G cables upto 50 Sq,mm on sand cushion covering the cable with br

a) Material
cum

27

203.84

5503.68

Cost of bricks (Civil SSR)

1000 Nos

0.92

5427.01

4992.85

Cost of sand (Civil SSR)

cum

1074.09

6444.54

Kg

25

5810.25

145.26

each

12

75.00

Excavation of earth 100 x 0.3 X 0.9 m

Cement (Civil SSR)


elec-8.1.30

Cost of cable route indicator

900.00
17986.33

Add contr profit @14% on material

0.00

0.00

Total for material

17986.33

b) Labour charges for laying cable.


Man Mazdoor for spreading the sand and back filling the
excavated soil.

each

2.5

206.00

515.00

Skilled Electrician

day

224.00

224.00

Helper

day

206.00

412.00

Man Mazdoor for concreting and embedding of cable way indicators


day

206.00

412.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

312.60
1360.60

19866.93

Rate per 100mts

198.70

Rate per Mtr


Labour charges for run of U.G cable on wall
with necessary fixing arrangments such
clamps,wooden separators etc., (as
departmental official) with No.10 SWG G.I
connections for the cables.

0.00
5.00

Sundires and Rounding off

49

0.00

Total for material


elec-4.1.19

E- DATA
Remarks

/ existing pipe
as saddles,
directed by
wire for eath

a) Material
elec-8.1.8

Wooden separators

each

200

1.50

300.00

elec-1.1.38

saddles of required size

100 nos

375.00

750.00

elec-1.4.34

12mm screws

100 nos

50.00

200.00

elec-8.1.45

No.10 SWG GI wire

kg

55.00

385.00
1635.00

Add contr profit @14% on material

0.00

0.00

Total material cost

1635.00

b) Labour charges
Skilled Electrician

day

Page 21 of 517

224.00

224.00

315806963.xlsx
Specification No.

Description

Unit

Quantity

Helper

day

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

1
0
2
Rate Rs. Amount Rs. 0
0
5
66
206.00

209.60
1257.60

Sundires such as Cement, Sand etc.,

0.00
21.00
2913.60

Rate per Each

29.15

Note : Labour Charges Considered for 100 Mts / day

50

824.00

Supply and Fixing of 3 phase meter Box, 3 Nos 100 A fuse


units, Neutral link, on T.W block with all accessaries etc.,
complete for finished items of work.
a) Material

elec-2.6.4
elec-1.4.7

100 A Fuse units

each

405.00

1215.00

100 A neutral links

each

118.00

118.00

T.W blocks ( 12" x 15" )

each

90.00

90.00

Add contr profit @14% on material

0.00

1423.00
0.00

Total for material

1423.00

b) Labour charges
Skilled Electrician

day

224.00

224.00

Helper

day

206.00

824.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

209.60
1257.60

Sundires such as Cement, Sand etc.,


Rate per Each

51

0.00
50.00
2730.60

Supply and Fixing of Single phase energy meterof 20A


rating in a M.S Box,including 1 No 32 A fuse units, Neutral
link etc. on T.W block with all accessaries etc., complete for
finished items of work. Make: Hpl/Conzeru/AE makes
a) Material

elec-6.3.11

Single phase energy meterof 20A rating

each

1012.00

elec-2.6.1

32 A Fuse units

each

80.00

1012.00
80.00

MS box 300mmx450mm

each

218.00

218.00

Add contr profit @14% on material

0.00

1310.00
0.00

Total for material

1310.00

b) Labour charges
Skilled Electrician

day

224.00

224.00

Helper

day

0.33

206.00

67.98

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

Sundires such as Cement, Sand etc.,

58.40
350.38

0.00
50.00
1710.40

Rate per Each

Page 22 of 517

E- DATA
Remarks
7

Specification No.

Description

Unit

Quantity

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

52

Supply and erecting ISI Mark 25 Ltrs Water heater with


multiple safety system, rust free ABS plastic body, 230V,
50Hz.., A.C. supply with inlet and outlet connections with
pvc/ nylon / metallic hose pipe, thermostat control and
thermal cutoff with 3 core P.V.C. flexible wire leads duly
tested including cost of all materials and all labour charges
etc., complete.
Make: VENUS / RACOLD / BAJAJ / V-GUARD /
CROMPTON.

each

8050.00

315806963.xlsx

a) Material
elec-5.2.3

25 ltr water heater


transportation charges on unit cost

elec-5.3.4

161.00

2%

Hose pipe PVC/Nylon

nos

8050.00

110.00

220.00
8431.00

Add contr profit @14% on material

0.00

0.00
8431.00

Total for material


b) Labour charges
Skilled Electrician

day

0.25

224.00

56.00

Helper

day

0.25

206.00

51.50

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

21.50
129.00

Sundires such as anchor bolts ,gutties etc.,

0.00
25.00
8585.00

53

Supply,Transportation and erection of self contained drinking


Water Cooler partial stainless steel confirming to IS : 1475 /
78 with amendment No. 1 to 7 with 40 Lts cooling capacity
and 80 Lts of storage capacity for operation on 230V +
10%, 50 Hz.. single Phase A.C. Supply.
(Make: USHA/VOLTAS/BLUE STAR)

a) Material
As per MR

34325.00

Rate per Each

54

34325.00
34325.00

Supply and fixing of concealed box PVC/MS with hook for


fan
A.Material

elec-8.1.28

Fan hook box

each

Add contr profit @14% on material

0.00

100.00

100.00
0.00

Total for material

100.00

b) Labour charges
Skilled Electrician

day

0.05

224.00

11.20

Helper

day

0.05

206.00

10.30

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

Rate for each

4.30
25.80

0.00
125.80

Page 23 of 517

E- DATA
Remarks
7

315806963.xlsx
Specification No.

Description

Unit

Quantity

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

E- DATA
Remarks
7

Standard Data - Electrical Items For External electrification


Specification No.

Description

Unit

Quantity

Supply, fabrication of 175x85 ISMB RS Joist for single pole


(box type)structure for transformer with support
angles,mounting clamps,hardwares etc with one coat of redoxide primer with two coats of aluminium enamel paint
complete for finished item

Rate Rs. Amount Rs.

175x85 RS joist (each9.5mtr@19.6 kg per mtr) 2lengths for


box type

kg

372.4

36.40

13555.36

Base plate 600x600x8mm MS plate(@62.80 kg /sq mtr)

kg

37.68

35.06

1321.07

100x50 ISMC cross arms


insulators(@9.56kg/mtr-5mtr

kg

47.8

37.06

1771.48

Clamps of 50x6 ms flat(@3,85kg/mtr

kg

12

37.06

444.72

Support cleets of35x35x6 L angle@3 kg /mtr

kg

15

37.06

555.90

Support angles of 50x 50x6 L angle@4.5 kg/mtr- 3mtr

kg

13.5

37.06

500.31

Total Ms items

Kg

37.06

554.10

a.Material
Elec-6.5.15

for

mounting

11KV

Add wastage @ 3%

498.38
14.9514

Total weight

kg

513.3314

Fabrication charges

LS

513.3

0.00
18702.95
9.00

Total cost for ms items

4619.70
23322.65

Add contr profit @14% on material

0.00

0.00

Total cost for single pole(box type)

23322.65

Total cost for single pole(box type)


B.Labour charges
Skilled Electrician

day

224.00

448.00

Helper

day

206.00

824.00

Mason for concreting and coping

day

224.00

448.00

Man mazdoor for concreting

day

206.00

412.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

426.40
2110.40

Rate for sinple pole structure


2

elec- 6.5.2

Supply and erecting porcelain disc type insulatorsuitable for


11KV line with suitable hardware in the existing cross arm
11KV disc insulator

each

Add contr profit @14% on material

0.00

600.00

elec-6.5.3

1800.00

Supply and erecting porcelain pin type insulatorsuitable for


11KV line with suitable hardware in the existing cross arm
11kv pin insulator

each

Add contr profit @14% on material

0.00

300.00

elec-6.5.1

900.00
0.00

Total for pin insulator


4

1800.00
0.00

Total for disc insulator


3

0.00
25881.10

900.00

Supply and erecting approved make 11KV 5KA metal oxide


lightning arrester suitable for 11KV line with suitable
hardware in the existing cross arm
lightning arrester

Each

Add contr profit @14% on material

0.00

Page 24 of 517

1500.00

4500.00
0.00

3
1
1
0
2
0
0
6

Remarks

315806963.xlsx
Specification No.

Description

Unit

Quantity

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

Total for lightning arrestor


5

elec-6.5.9

4500.00

Supply and erecting approved make 11KV 200A AB


switch(tilting) with all accessories etccomplete with cost and
conveyance of all materials
200A AB switch

each

Add contr profit @14% on material

0.00

5900.00

0.00

Total for AB switch


6

elec-6.5.10

5900.00

Supply and erecting approved make 11KV HG fuse set with


all accessories etccomplete with cost and conveyance of all
materials
HG fuse set

each

Add contr profit @14% on material

0.00

4000.00

4000.00
0.00

Total for AB switch

5900.00

4000.00

Supply of 150 sqmm 3.5core XLPE PVC armoured


alluminium cable of makes Torrent/Nicco/Universal/CCI
a) Material

elec-4.1.40

3.5corex150 sqmm cable

Rmt

Add contr profit @14% on material

0.00

641.00

641.00
0.00

Total for 150 sqmm cable

641.00

b) Labour charges for laying cable.


Man Mazdoor for spreading the sand and back filling the
excavated soil.

each

2.5

206.00

515.00

Skilled Electrician

day

224.00

224.00

Helper

day

206.00

412.00

Man Mazdoor for concreting and embedding of cable way indicators


day

206.00

412.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

Sundires and Rounding off

0.00
5.00
1880.60

Rate per 100mts

312.60
1360.60

Rate per Mtr

18.81

Total for supply and laying

659.85

Supply, installation,and commissioning of 3Phases and


neutral 415V, free standing type cubical panel board made
of 16 Gauge CRCA sheet steel, panel shall be painted after
processing 7 tank process with RAL 7032 siemens grey. The
panel shall be consisting of suitable rating of allumunium
bus bars ( At the rating of 0.8 A/Sq.mm) supported with
DMC/SMC and colour coded with heat shrinkable sleeves.
The bus bars fault level shall be 50 KA and shall be as per
the requirement of local CEIG, fire regulations, other
authorities etc. The panel shall be suitable for accomdating
the following switch gears including supply of all
components, hard wares etc including all necessary civil
works, adequate reinforcement foundation bolts suitable G.I
earth strip , 100 x 50mm MS base channel, earth bar, door
loop earthings . Bus bar to switch interconnections,

Page 25 of 517

E- DATA
Remarks
7

Specification No.

Description

Unit

Quantity

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

each

25350.00

25350.00

2500.00

2500.00

315806963.xlsx

All cables shall have proper cable entry,gland plates,


suitable size of glands, earth tags for glands, lugs, cadmium
plated nuts , bolts, feeder identification marks,shall be
installed on performed trench consisting of the following as
required and as per IS standards and panel should be
manufactures only from panel builds with CPRI Test
certificate.
400A Aluminium Bus Bar with colour code.
Internal wiring with approved make cable
Earthing: Providing 50x6 mm G.I flat
Incommer: .
elec-2.8.8

400A TPN 35KA MCCB L&T make.- 1 No.


Metering Set:

elec-6.3.3

0- 400 A Digital Ammeter . - 1 No.

each

elec-6.3.8

Ammeter selector switch - 1 No.

each

175.00

175.00

elec-6.3.1

0-500V Digital Volt meter - 1 No.

each

2500.00

2500.00

elec-6.3.8

Voltmeter selector switch - 1 No.

each

175.00

175.00

elec-6.3.9

R, Y, B Indication lamps LED type, puse buttons.

each

135.00

405.00

400 /5A C.T coils : 2 sets

450.00

2700.00

20A Bakelite fuse fittings - 3 Nos.

130.00

390.00

2A HRC fuse link - 3 Nos:

45.00

135.00

APFC relay 8 stage.

12450.00

12450.00

Outgoing :
elec-2.8.6

125A 25KA MCCB-02 NOS -L&T Make

each

7900.00

15800.00

MR

100A 25KA MCCB-02 NOS -L&T Make

each

6350.00

12700.00

elec-2.8.5

63A 25KA MCCB -04 NOS - L&T Make

each

5750.00

23000.00
0.00
98280.00

Bus bars and insulators 10%

9828.00

Cost of enclosure @ 45%

44226.00

Control wiring, Labour charges for errection of switch gear,


panel board including all labour charges etc complete with
connections for finished item of work including transportation
charges.5%

4914.00

157248.00
Add contr profit @14% on material

0.00

0.00

Total cost of panel board

157248.00

b)labour charges
Skilled electrician

day

224.00

224.00

semi skilled electrician

day

206.00

412.00

helper

day

206.00

824.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

Total cost of panel board(supply&erection)

292.00
1752.00

0.00
159000.00

Providing independent earthling by excavating a trench to a


depth of 2.1 M in all soils, as per size specified in the Data,
using 40mm dia 'B' class GI pipe of 2.5 Mtrs length with
necessary accessories with hume pipe ring duly providing
staggered holes including filling with equal proportion of
Salt and Charcoal in layers and all labour charges etc.,
complete for small quarters.

a) Material

Page 26 of 517

E- DATA
Remarks
7

315806963.xlsx

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

Specification No.

Description

Unit

Quantity

Earth Work Excavation of Hard gravel Soil with small


boulder for trench 1st step of size 1.5 x 0.9 x 0.9 m

cum

1.21

122.11

147.75

Excavation of Hard disteggrated rocks and boulders for


trench 2nd Step of size 1.2 x 0.6 x 1.2 m (Civil SSR)

cum

0.9

150.00

135.00

25.00

25.00

Mtr

2.5

301.00

752.50

25 x 6 mm (1"X 1/4") G.I Flat duly drilled 12mm holes (4


Nos) of 200 mm (8") length

Each

75.00

75.00

Drilling of 16 Nos through holes of 12mm dia to G.I pipe

Each

16

5.00

80.00

25% extra for narrow trench & pit and back filling with Sand,
Coke, Salt etc., and leveling
40mm dia 'B' Class G.I pipe

elec-8.1.12

G.I Nuts, Bolts an Washers


18" dia hume pipe ring

Set

12.00

48.00

Each

100.00

100.00

elec-8.1.16

Hard Coke

Kg

20

8.00

160.00

elec-8.1.17

Salt

Kg

20

4.00

80.00
1603.25

Add contr profit @14% on material

0.00

0.00

Total material cost

1603.25

b) labour charges for fixing pipe ring and connections

Each

Semi skilled Electrician

day

0.5

206.00

103.00

Helpers

day

0.5

206.00

103.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

41.20
247.20

0.00

Sundries
Rate per each
10

Say

1850.50

Supply and laying of earth strip of size 50x6, 32x6 mm for


transformer/ structure earthing
a)Material

elec-8.1.45

GI strip

kg

Add contr profit @14% on material

1.4

55.00

0.00

77.00
0.00

Total material cost

77.00

b) Labour charges
Semi skilled electrician

day

0.02

206.00

4.12

Helper

day

0.04

206.00

8.24

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

2.47
14.83

0.00

considered 50 mtr laying per day


Total for GI flat

Rmt

91.85

Street light poles


11

elec-6.1.1
MR

Fabrication supply transportation of all sizes swaged poles


to site confirming to IS2713/1980 specifications. The pole
should be painted with primary coat of red oxide and black
bituminous paint up to ground level with base plate,
including cost of all materials etc., complete.
9 mtr ms swaged pole with painting
loop in-out box with fuse unit and terminal block outdoor
type

kg

135

65.00

8775.00

each

540.00

540.00
396.00

elec-1.5.2

pole wiring with 3runsx1.5 sqmm copper wire

rmt

30

13.20

elec-6.1.3

1.5 mtr 40mmdia pipe bracket with pole cap

kg

8.41

60.00

504.60
10215.60

Add contr profit @14% on material

0.00

Total pole cost

0.00
10215.60

Page 27 of 517

E- DATA
Remarks
7

315806963.xlsx

1
0
2
Rate Rs. Amount Rs. 0
0
5
66

Specification No.

Description

Unit

Quantity

Skilled electrician

day

0.5

224.00

112.00

semi skilled electrician

day

0.5

206.00

103.00

helper

day

206.00

206.00

mason for concreting

day

0.5

224.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

b)Labour charges

112.00
106.60

527.60

Total pole cost(supply&erection)

0.00
10855.20

Cable termination
12

Supply and fixing of 3.5x150 sqmm cable end termination


a)Material

elec-4.2.9

Heavy duty flange type brass cable gland for 3.5c x150
sqmm PVC armoured cable

each

200.00

200.00

elec-4.3.8

Crimping type copper lugs of 150 sqmm with nut/bolt/washer


and crimping

each

94.00

282.00

elec-4.3.5

Crimping type copper lugs of 70sqmm with nut/bolt/washer


and crimping (for neutral lead)

each

50.00

50.00
532.00

Add contr profit @14% on material

0.00

0.00

Total for 150 sqmm cable termination

13

532.00

Supply and fixing of 3.5x35 sqmm cable end termination


a)Material

elec-4.2.4

Heavy duty flange type brass cable gland for 3.5c x35 sqmm
PVC armoured cable

each

100.00

100.00

elec-4.3.3

Crimping type copper lugs of 35sqmm with nut/bolt/washer


and crimping

each

30.00

90.00

elec-4.3.1

Crimping type copper lugs of 16sqmm with nut/bolt/washer


and crimping (for neutral lead)

each

20.00

20.00

Add contr profit @14% on material

0.00

210.00
0.00

Total for 35 sqmm cable termination

14

210.00

Supply and fixing of 3.5x50 sqmm cable end termination


a)Material

elec-4.2.5

Heavy duty flange type brass cable gland for 3.5c x50 sqmm
PVC armoured cable

each

115.00

115.00

elec-4.3.4

Crimping type copper lugs of 50 sqmm with nut/bolt/washer


and crimping

each

35.50

106.50

elec-4.3.2

Crimping type copper lugs of 25sqmm with nut/bolt/washer


and crimping (for neutral lead)

each

27.00

27.00
248.50

Add contr profit @14% on material

0.00

0.00

Total for 50 sqmm cable termination


15

248.50

Supply and fixing of 4cx16 sqmm cable end termination


a)Material

elec-4.2.3

Heavy duty flange type brass cable gland for 4cx16sqmm


PVC armoured cable

Page 28 of 517

each

95.00

95.00

E- DATA
Remarks
7

315806963.xlsx
Specification No.

Description

Unit

Quantity

elec-4.3.1

Crimping type copper lugs of 16 sqmm with nut/bolt/washer


and crimping

each

Add contr profit @14% on material

0.00

1
0
2
Rate Rs. Amount Rs. 0
0
5
66
20.00

80.00
175.00
0.00

Total for 16 sqmm cable termination


16

175.00

Supplyand laying of 6 sqmm 4core XLPE PVC armoured


alluminium cable of makes Torrent/Nicco/Universal/CCI
a) Material

elec-4.1.14

4corex6 sqmm cable

Rmt

Add contr profit @14% on material

0.00

98.00

98.00
0.00

Total for 6 sqmm cable

98.00

b) Labour charges for laying cable.


Man Mazdoor for spreading the sand and back filling the
excavated soil.

each

2.5

206.00

515.00

Skilled Electrician

day

224.00

224.00

Helper

day

206.00

412.00

Man Mazdoor for concreting and embedding of cable way indicators


day

206.00

412.00

Add area allowence on labour charges @

20%

Add contr profit @14% on Labour

0%

312.60
1360.60

1880.60

Rate per 100mts

17

0.00
5.00

Sundires and Rounding off


Rate per Mtr

18.81

Total for supply and laying

116.85

Supply and fixing of 4cx6 sqmm cable end termination


a)Material

elec-4.2.1

Heavy duty flange type brass cable gland for 4cx6sqmm


PVC armoured cable

each

45.00

45.00

elec-4.3.1

Crimping type copper lugs of 6 sqmm with nut/bolt/washer


and crimping

each

20.00

80.00

Add contr profit @14% on material

0.00

125.00
0.00

Total for 6 sqmm cable termination

125.00

18

Supply erection testing commisioning of 250 KVA 11kv/433


volts outdoor type transformer with ONAN cooling and first
filled oil ,bushings on HT side and cable box on LT side with
bidirectional rollers, silica gel breather,off load tap changer
with locking arrangement complete as per ISSPECIFICATIONS

MR

250 KVA Transformer


Erection ,Testing and Commisioning
Total for supply and erection

each

340628.00

LS

6500.00

340628.00
6500.00
347128.00

Page 29 of 517

E- DATA
Remarks
7

P
NIT
No

Name of work

for execution

Lr no from SE

Name of circle Name of District

NIT No

ECV

Eleshwaram & Gannavaram of East Godavari


District and Pamuru of Krishna District
4 ### #REF!

KADAPA
978/SE/D3/Model School/
/2011-12, Dt.21.02.2012

CHITTOOR

#REF!

#REF!

ECV in words

BidProcessingFee

#NAME?

Bid processing fee


Bid processing fee
to be handed over
in favour of
to

Superintending
Engineer,
O/o.Managing
Managing Director, Director,
APEWIDC,
APEWIDC,
20000 Hyderabad
Hyderabad

EMD

Bank
Gurantee in
favour of

Managing
Director,
APEWIDC,
#REF! Hyderabad

Period of
completion

#REF!

BGValidity for BalanceEMD Class of contractor

#REF!

DownloadingOfBid

20/09/2012 at 3.00 PM to
#REF! 6/010/2012 up to 3:30 PM

DateOfBidReceipt

20/09/2012 at 3.30 PM to
6/10/2012 up to 4:00 PM

TechnicalBid

06/09/2012 at 4.30 PM

PriceBid

10/10/2012 at
4.00 PM

SimilarNatureOfWork RRMasonry PCCRCC

#REF!

#REF!

#REF!

Plasterin
SteelCent
Flooring
PinVibrators PanVibrators WeighBatchers ConcreteMixers
g
ering

#REF!

#REF!

1000

QCLabs

GraduateEngineers DiplomaEngineers Solvency IssuedEarlier

#REF! 03/02/2011

TransactionFee APTSServiceChrg APEWIDCSerChrg

#REF!

#REF!

SSR

Building SSR 2011-2012 adopting rates of


Cement & Steel for the month of August
#REF! 2012 ( 3rd month of 1st Quarter)

SSRCement SSRHYSDBars

5000.00

47500.00

SSRMildSteel SEArbitration Penality for as built drawings

44500.00 Guntur

L1

20000 S.S Constructions.

Tender
discount

8.19% Less

LrNo

TCV

L2

M/s Deepak
22326965.42 Constructions

Tender
discount

5.60% Less

L3

G.Madhusudhan
Reddy.

Tender
discount

5.49% Less

L4

Ch.Marthanda
Rao & Co.

Tender
discount

4.50% Less

L5

M/s VCR
Associates.

Tender
discount

3.86% Less

L6

B.Sanjeeva
Reddy.

Tender
discount

3.69% Less

L7

Tender
discount

L8

Tender
discount

L9

Tender
discount

L10

Tender
discount

Srico Projects
Pvt. Ltd.
3.29% Less

Aditya
Housing &
Infrastructure
Dev. Corp. P. 3.10%
Ltd.
Less

3.06%
Murali. M Less

M/s
Sripathi
Constructi 0.69%
ons.
Less

L11

Tender
discount

DATAS WITH ZERO LEADS


Name of Work ::- Name of the work : CONSTRUCTION OF GOVT.JUNIOR
COLLEGE AT GUDIPALLI(V), GUDIPALLI(M), IN CHITOOR DIST.
S.No.
Quantity
Description of Item
Rate
per
Amount
1 Forming embankment with Side earth by mechanical means upto SDR including prewatering of soil , removal of top soil, excavation of soils , depositing the soils on the
embankment, spreading soil, breaking clods, sectioning , grading and consolidation with 8
to 10 Tonnes Vibratory Road Roller @ OMC to meet requirement of table 300-2 of
MoRT&H, including all hire and operational charges of T&P and , complete for finished
item of work as per MoRT&H specification 305 (4th revision) (Payment will be made
based on level for finished item of work).
Unit : Cum
Taking out put = 100 Cum
(A) Labour
0.02 day
Mate
Mazdoor unskilled
0.50 day

Page 70 of MoRT&H SDB

(B) Machinery
Rate as per G.O. Ms No 10, Dt 26/7/2005
100.00 cum
Motor Grador for Grading @ 100 cum per
1.00 hr
hour
Water tanker 6 KL
4.00 hr
Vibratory roller 8T
1.00 hr
(C)
100.00 Cum

385.00
295.00

day
day

7.70
147.50
155.20

81.44
2600.00
658.35
2678.30

cum
hr
hr
hr

8144.00

0.00

cum

2600.00

2633.40
2678.30
16055.70
0.00

(D) Over head charges @4% (10%-VAT) on (A) + (B)+( C)


(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 100 cum (E) + (F)
Rate per Cum
Rate per 1 cum

648.44
16859.34
1685.93
18545.27
185.45
185.00
1 Cum
Providing Plain Cement Concrete (1:4:8) mix using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine
mixing, laying, Vibrating, curing etc., including all other incidental and operational charges
of all T&P etc., complete for finished item of work as per MoRT&H specification
1500,1700, 2100 (4th Revision) and as directed by the Engineer-in-Charge for base
coarse below CC Pavement.
Unit = cum
Taking output = 15 cum

36 of 517

CC Road data

(A) Labour
0.64 nos
1.00 nos
15.00 nos

385.00
345.00
295.00

Mate
Mason
Mazdoor
Total

(B) Material
Cost of 40mm SS-5 HBG M/C metal
13.50 cum
946.40
6.75 cum
Sand at site
922.90
2.43 MT
Cement at site
6446.32
Total
Machinery
6.00 hr
Concrete mixer 0.4/0.28 cum
328.60
0.00 hr
Generator set 35 KVA
620.00
2.00 hr
Water tanker 6 KL
658.35
Total
(D) Over head charges @ 4% (10%-VAT)
4.00 %
Add for Over head charges @ 6% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 15 cum (E) + (F)
Rate for 1 cum
Rate to be adopted

day
day
day

246.40
345.00
4425.00
5016.40

cum
cum
MT

12776.40
6229.58
15664.55
34670.53

hr
hr
hr

1971.60
0.00
1316.70
3288.30

1719.01
44694.24
4469.42
49163.66
3277.58
3278.00
1 Cum
Construction of Gravel shoulders including cost, and conveyance of all materials to work
site and spreading in uniform layers by approved means, on prepared surface and
compacting with vibratory roller to achieve the desired density at OMC etc., complete for
finished item of work as per MoRT&H Specification 401& 407 (4th revision) and as
directed by the Engineer-in-charge.
( Payment will be made based on levels for finished item of work ).
Unit = cum
Taking output = 300 cum
(A) Labour
0.40 day
Mate
385.00
2.00 day
Mazdoor skilled
345.00
Mazdoor unskilled
295.00
8.00 day
Total
(B) Machinery
Vibratory roller 8T
2678.30
6.00 hr
Water tanker 6 KL
658.35
3.00 hr
Total
(C) Material
Gravel
149.10
384.00 cum
(D) Over head charges @ 6% (10%-VAT)
4.00 %
Add for Over head charges @ 6% on (A)+(B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
37 of 517

day
day
day

154.00
690.00
2360.00
3204.00

hr
hr

16069.80
1975.05
18044.85
57254.40

3140.13
81643.38
8164.34
CC Road data

Cost per 300 cum (E) + (F)


Rate per 1 cum
Rate to be adopted

89807.72

299.36
299.00
1 Cum

Vibrated cement concrete M.25 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming
to table 1000-2) including cost, seigniorage conveyance of all materials to site and labour
charges, centering, machine mixing, laying, vibrating, curing etc., including all other
incidental and operational charges of all T&P etc., complete for finished item of work as
per Approved drawing but excluding cost of steel and its fabrication charges as per
MoRT&H specification 1500, 1600,1700, & 2704 (4 th Revision) and as directed by the
Engineer-in-Charge for CC Pavements.

0.86
1.50
20.00

Unit = cum
Taking output = 15 cum
(A)
Labour
nos
Mate
nos
Mason
nos
Mazdoor
Total

8.10
5.40
6.75
6.05

(B)
cum
cum
cum
MT

6.00
6.00

hr
hr

2.00
14.00

(D)
%
%

Page 340,501 of MoRT&H SDB

Material
Cost of 20mm HBG metal
Cost of 10mm HBG metal
Sand at site
Cement at site
Total
Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
Total
Form work
Form work @ 2% on (A)+(B)+( C)

385.00
345.00
295.00

day
day
day

331.10
517.50
5900.00
6748.60

1908.88
1478.88
922.90
6446.32

cum
cum
cum
MT

15461.93
7985.95
6229.58
39000.21
68677.67

328.60
620.00

hr
hr

1971.60
3720.00
5691.60

81117.87

Cum

1622.36
11583.63
94323.86
6288.26
6288.00
1 Cum

Add for Over head charges @ 14% on (A)+(B)+( C)+(D)

Cost per 15 cum


Rate for 1 cum M 25 Concrete
Rate to be adopted

Executive Engineer
APEWIDC, CHITTOOR

Dy. Executive Engineer


Asst. Executive Engineer
APEWIDC, MADANAPALLI APEWIDC, KUPPAM

38 of 517

CC Road data

Superintending Engineer
APEWIDC, KADAPA

39 of 517

CC Road data

You might also like