You are on page 1of 1048

#REF!

ABSTRACT ESTIMATE FOR CIVIL WORKS

Total
Description of Work
Quantity
#REF! Earth work excavation for foundations (Mechanical Means) for Earth work excavation Earth work excavation
buildings in ordinary soils and depositing on bank for all lifts
and with an initial lead of 10m and up to 3m depth including all
operational,incidental, labour charges such as shoring,
sheeting, planking, strutting etc., and overheads & contractors
profit complete for finished item of work excluding dewatering
charges etc., as per SS 20 B(APSS 308)

11060 Earth work excavation for foundations (Mechanical Means) for Earth work excavation Earth work excavation
buildings in ordinary soils and depositing on bank for all lifts
and with an initial lead of 10m and 3m to 6m depth including
all operational,incidental, labour charges such as shoring,
sheeting, planking, strutting etc., and overheads & contractors
profit complete for finished item of work excluding dewatering
charges etc., as per SS 20 B(APSS 308)

2621 Earth work excavation for foundations (Mechanical Means) for Earth work excavation Earth work excavation
buildings in ordinary rock (not requiring blasting) and
depositing on bank for all lifts and with an initial lead of 10m and
up to 3m depth including all operational,incidental, labour
charges such as shoring, sheeting, planking, strutting etc., and
overheads & contractors profit complete for finished item of
work excluding dewatering charges etc., as per SS 20 B(APSS
308)
575 Earth work excavation for foundations for buildings in hard Earth work excavation Earth work excavation
rock (blasting prohibited) and depositing on bank for all lifts and
with an initial lead of 10m and up to 3m depth including all
operational,incidental, labour charges such as shoring,
sheeting, planking, strutting etc., and overheads & contractors
profit complete for finished item of work excluding dewatering
charges etc., as per SS 20 B(APSS 308)

1500 Plain Cement Concrete (1:4:8) (cement: fine aggregate: Plain Cement Concrete (1:4:8) Plain Cement Concrete (1:4:8)
Coarse aggregate) for foundations using coarse aggregate
40mm size hard , machine crushed granite from approved
quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
including cost and conveyance of all materials like cement,
sand, coarse aggregate, water etc. to site including all charges
for machine mixing and hire charges of concrete mixer, laying
concrete in foundations and under flooring bed, ramming in 15
cm layers finishing top surface to the required level curing
etc.,and overheads & contractors profit complete for finished
item of work. (APSS No. 402) For Foundation

#REF! Plain Cement Concrete (1:5:10) (cement: fine aggregate: Plain Cement Concrete (1:4:10) Plain Cement Concrete (1:4:10)
Coarse aggregate) for foundations and under flooring bed
using coarse aggregate 40mm size hard , machine crushed
granite from approved quarry using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, sand, coarse aggregate, water etc. to site
including all charges for machine mixing and hire charges of
concrete mixer, laying concrete in foundations and under
flooring bed, ramming in 15 cm layers finishing top surface to
the required level curing etc.,and overheads & contractors profit
complete for finished item of work. (APSS No. 402)
21736 Filling with useful available excavated earth (excluding rock) Filling with useful available Filling with useful available excavated
with a lead of 50 m in trenches, sides of foundations and excavated earth earth
basement with initial lead in layers not exceeding 15cm thick,
watering and ramming including cost and conveyance of water
to work site and all operaitonal, incidental, labour charges, hire
charges of T&P etc., and overheads & contractors profit
complete for fnished item of work (APSS NO.309&310)

3237 Pre construction Anti termite treatment is a process in which Pre construction Anti termite Pre construction Anti termite treatment
chemical toxic to subterrean tremites is apply/ inject into soil treatment
during early stage of building Construction 2. Treatement of soil
Beneath the building and around the foundations conduct and
chemical use as per BIS - IS 6313 (Part -2) 2013 code
specification & CIB RC registered termiticide which creates a
continuous chemical barrier beneath the building which kills or
repels terminates & impervious to tremite entry 3. Imidacloprid
30.5% SC (IS 63131) dissolve 2.1 Ml/1 liter of water and apply
emulsion/solution @ 7.5 Litres/Square meter (Sqm) of internal,
external vertical surface of the colums, plinth beams (Back
filling) walls and floor junction, external perimeters, along
reatining wall @ 5.0 Liters/Sqm of the horizontal surface of
basement top surface of the basement filling below flooring bed
(Plinth) & @ 2.0 Litres/ Line meter at expansion joints. The
substructure of a depth of 500mm around coulmns & 300mm
deep around plinth beams, basements & floor filling area
including excavation channel along the wall & rodding etc. cost
& Conveyance of all materials to the site, cost of labour for
sparying, rodding, overheads and contractor profit etc. complete
for furnished item of work as per the approval of the Engineer-
in-charge
#REF! Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of 15
cum per hour capacity with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970 and
IS 2386 Part 1 to Part 8) from approved quarry including cost
and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site, centering using
steel scaffolding pipes , jack props , wallers , foot plates ,
brackets , steel centering plates etc., including all operational,
incidental and labour charges, transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing etc., and overheads &
contractors profit complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402)
Footings

2796 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of 15
cum per hour capacity with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970 and
IS 2386 Part 1 to Part 8) from approved quarry including cost
and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site, centering using
steel scaffolding pipes , jack props , wallers , foot plates ,
brackets , steel centering plates etc., including all operational,
incidental and labour charges, transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing etc., and overheads &
contractors profit complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402)
Raft Concrete
119 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of 15
cum per hour capacity with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970 and
IS 2386 Part 1 to Part 8) from approved quarry including cost
and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site, centering using
steel scaffolding pipes , jack props , wallers , foot plates ,
brackets , steel centering plates etc., including all operational,
incidental and labour charges, transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing etc., and overheads &
contractors profit complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402)
Column Pedastals

#REF! Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of 15
cum per hour capacity with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970 and
IS 2386 Part 1 to Part 8) from approved quarry including cost
and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site, centering using
steel scaffolding pipes , jack props , wallers , foot plates ,
brackets , steel centering plates etc., including all operational,
incidental and labour charges, transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing etc., and overheads &
contractors profit complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402)
Plinth Beams
35 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of 15
cum per hour capacity with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970 and
IS 2386 Part 1 to Part 8) from approved quarry including cost
and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site, centering using
steel scaffolding pipes , jack props , wallers , foot plates ,
brackets , steel centering plates etc., including all operational,
incidental and labour charges, transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing etc., and overheads &
contractors profit complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402)
Tie Beam

246 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of 15
cum per hour capacity with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970 and
IS 2386 Part 1 to Part 8) from approved quarry including cost
and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site, centering using
steel scaffolding pipes , jack props , wallers , foot plates ,
brackets , steel centering plates etc., including all operational,
incidental and labour charges, transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing etc., and overheads &
contractors profit complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402)
STP Bottom Slab/Sump Bottom Slab
4.3 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of 15
cum per hour capacity with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970 and
IS 2386 Part 1 to Part 8) from approved quarry including cost
and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site, centering using
steel scaffolding pipes , jack props , wallers , foot plates ,
brackets , steel centering plates etc., including all operational,
incidental and labour charges, transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing etc., and overheads &
contractors profit complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402)
Haunch Concrete

145 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Columns :
Cellar :
251 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Columns :
Basement Floor

#REF! Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Columns :
First Floor :
214 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Columns :
Second Floor :

214 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Columns :
Fourth Floor :
45 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Columns :
Fifth Floor :

10 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Lintels
Cellar :
22 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Lintels
Basement Floor

12 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Lintels
First Floor :
21 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Lintels
Second Floor :

15 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Lintels
Third Floor :
21 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Lintels
Fourth Floor :

1 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Lintels
Fifth Floor :
810 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
100mm thick Drain side walls
Second Floor :

1 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
150mm thick Sump side walls
First Floor :
208 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
150mm thick Water Tank side walls
Fifth Floor :

1098 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402) 230mm thick
Retaining wall
Cellar :
1187 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402) 230mm thick
Retaining wall
Basement Floor

46 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
300mm thick STP Side walls
First Floor :
326 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
450mm thick STP/Sump side walls
First Floor :

98 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Beams : un supported height up to 3.66 m
Cellar :
161 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Beams : un supported height up to 3.66 m
Basement Floor

173.5 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Beams : un supported height up to 3.66 m
First Floor :
161 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Beams : un supported height up to 3.66 m
Second Floor :

161 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Beams : un supported height up to 3.66 m
Fourth Floor :
17 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Beams : un supported height up to 3.66 m
Fifth Floor :

283 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slabs : un supported height up to 3.66 m
Roof Slabs 125mm thick :
Cellar :
283 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slabs : un supported height up to 3.66 m
Roof Slabs 125mm thick :
Basement Floor

339 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slabs : un supported height up to 3.66 m
Roof Slabs 125mm thick :
First Floor :
284 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slabs : un supported height up to 3.66 m
Roof Slabs 125mm thick :
Second Floor :

283 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slabs : un supported height up to 3.66 m
Roof Slabs 125mm thick :
Fourth Floor :
181 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slabs : un supported height up to 3.66 m
Roof Slabs 125mm thick :
Fifth Floor :

762 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slabs : un supported height up to 3.66 m
Roof Slabs 150mm thick :
Cellar :
1786 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slabs : un supported height up to 3.66 m
Roof Slabs 150mm thick :
Basement Floor

2005 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slabs : un supported height up to 3.66 m
Roof Slabs 150mm thick :
First Floor :
1643 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slabs : un supported height up to 3.66 m
Roof Slabs 150mm thick :
Second Floor :

1647 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slabs : un supported height up to 3.66 m
Roof Slabs 150mm thick :
Fourth Floor :
195 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slabs : un supported height up to 3.66 m
Roof Slabs 150mm thick :
Fifth Floor :

831 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slabs : un supported height up to 3.66 m
Roof Slabs 175mm thick :
Cellar :
1170 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slabs : un supported height up to 3.66 m
Roof Slabs 175mm thick :
Basement Floor

1210 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slabs : un supported height up to 3.66 m
Roof Slabs 175mm thick :
First Floor :
1192 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slabs : un supported height up to 3.66 m
Roof Slabs 175mm thick :
Second Floor :

1170 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of
15 cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slabs : un supported height up to 3.66 m
Roof Slabs 175mm thick :
Fourth Floor :
585 Reinforced Cement Concrete M 20 nominal mix using 12mm Supply and placing of the Design Supply and placing of the Design Mix
size hard granite machine crushed graded metal (coarse Mix Concrete M 30 grade Concrete M 30 grade
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for 100mm thick precast
slabs
100mm thich Precast Slab
Second Floor :

251 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of 15
cum per hour capacity with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970 and
IS 2386 Part 1 to Part 8) from approved quarry including cost
and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site, centering using
steel scaffolding pipes , jack props , wallers , foot plates ,
brackets , steel centering plates etc.,including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Columns :
un supported height up to 4.27 m
Third Floor :
161 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of 15
cum per hour capacity with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970 and
IS 2386 Part 1 to Part 8) from approved quarry including cost
and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site, centering using
steel scaffolding pipes , jack props , wallers , foot plates ,
brackets , steel centering plates etc.,including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Beams
un supported height up to 4.27 m
Third Floor :
283 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of 15
cum per hour capacity with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970 and
IS 2386 Part 1 to Part 8) from approved quarry including cost
and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site, centering using
steel scaffolding pipes , jack props , wallers , foot plates ,
brackets , steel centering plates etc.,including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slab 125mm thick
un supported height up to 4.27 m
Third Floor :
1647 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of 15
cum per hour capacity with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970 and
IS 2386 Part 1 to Part 8) from approved quarry including cost
and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site, centering using
steel scaffolding pipes , jack props , wallers , foot plates ,
brackets , steel centering plates etc.,including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slab 150mm thick
un supported height up to 4.27 m
Third Floor :
1170 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using batching and mixing plant of 15
cum per hour capacity with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970 and
IS 2386 Part 1 to Part 8) from approved quarry including cost
and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site, centering using
steel scaffolding pipes , jack props , wallers , foot plates ,
brackets , steel centering plates etc.,including all operational,
incidental and labour charges ,transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)
Roof Slab 175mm thick
un supported height up to 4.27 m
Third Floor :

163 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using weigh batcher / mixer with
20mm size graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand), coarse aggregate,
water etc., to site, centering using casurina ballies , bamboos ,
wooden reapers , runners , wood posts , wall plates etc., for
60cm wide sun-shades 7.5cm thick at fixed end and 5cm thick
at free end with an average thickness of 6.25cm including all
operational, incidental and labour charges such as weigh
batching, machine mixing, lifting of concrete manually, laying
concrete, curing, overheads & contractors profit complete etc.,
but excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402, 403 & 903)
Cellar :
318 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using weigh batcher / mixer with
20mm size graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand), coarse aggregate,
water etc., to site, centering using casurina ballies , bamboos ,
wooden reapers , runners , wood posts , wall plates etc., for
60cm wide sun-shades 7.5cm thick at fixed end and 5cm thick
at free end with an average thickness of 6.25cm including all
operational, incidental and labour charges such as weigh
batching, machine mixing, lifting of concrete manually, laying
concrete, curing, overheads & contractors profit complete etc.,
but excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402, 403 & 903)
Basement Floor

154 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using weigh batcher / mixer with
20mm size graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand), coarse aggregate,
water etc., to site, centering using casurina ballies , bamboos ,
wooden reapers , runners , wood posts , wall plates etc., for
60cm wide sun-shades 7.5cm thick at fixed end and 5cm thick
at free end with an average thickness of 6.25cm including all
operational, incidental and labour charges such as weigh
batching, machine mixing, lifting of concrete manually, laying
concrete, curing, overheads & contractors profit complete etc.,
but excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402, 403 & 903)
First Floor :
231 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using weigh batcher / mixer with
20mm size graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand), coarse aggregate,
water etc., to site, centering using casurina ballies , bamboos ,
wooden reapers , runners , wood posts , wall plates etc., for
60cm wide sun-shades 7.5cm thick at fixed end and 5cm thick
at free end with an average thickness of 6.25cm including all
operational, incidental and labour charges such as weigh
batching, machine mixing, lifting of concrete manually, laying
concrete, curing, overheads & contractors profit complete etc.,
but excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402, 403 & 903)
Second Floor :

102 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using weigh batcher / mixer with
20mm size graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand), coarse aggregate,
water etc., to site, centering using casurina ballies , bamboos ,
wooden reapers , runners , wood posts , wall plates etc., for
60cm wide sun-shades 7.5cm thick at fixed end and 5cm thick
at free end with an average thickness of 6.25cm including all
operational, incidental and labour charges such as weigh
batching, machine mixing, lifting of concrete manually, laying
concrete, curing, overheads & contractors profit complete etc.,
but excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402, 403 & 903)
Third Floor :
221 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using weigh batcher / mixer with
20mm size graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand), coarse aggregate,
water etc., to site, centering using casurina ballies , bamboos ,
wooden reapers , runners , wood posts , wall plates etc., for
60cm wide sun-shades 7.5cm thick at fixed end and 5cm thick
at free end with an average thickness of 6.25cm including all
operational, incidental and labour charges such as weigh
batching, machine mixing, lifting of concrete manually, laying
concrete, curing, overheads & contractors profit complete etc.,
but excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402, 403 & 903)
Fourth Floor :

9 Supply and placing of the Design Mix Concrete M 30 grade Supply and placing of the Design Supply and placing of the Design Mix
corresponding to IS 456 with minimum cement content of 400 Mix Concrete M 30 grade Concrete M 30 grade
kgs per 1 cum of concrete using weigh batcher / mixer with
20mm size graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand), coarse aggregate,
water etc., to site, centering using casurina ballies , bamboos ,
wooden reapers , runners , wood posts , wall plates etc., for
60cm wide sun-shades 7.5cm thick at fixed end and 5cm thick
at free end with an average thickness of 6.25cm including all
operational, incidental and labour charges such as weigh
batching, machine mixing, lifting of concrete manually, laying
concrete, curing, overheads & contractors profit complete etc.,
but excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402, 403 & 903)
Fifth Floor :
19 Reinforced Cement Concrete M 20 nominal mix using 12mm Supply and placing of the Design Supply and placing of the Design Mix
size hard granite machine crushed graded metal (coarse Mix Concrete M 30 grade Concrete M 30 grade
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for platforms and shelves.
50mm thick platforms / lofts:
Cellar :

120 Reinforced Cement Concrete M 20 nominal mix using 12mm Supply and placing of the Design Supply and placing of the Design Mix
size hard granite machine crushed graded metal (coarse Mix Concrete M 30 grade Concrete M 30 grade
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for platforms and shelves.
50mm thick platforms / lofts:
Basement Floor
34 Reinforced Cement Concrete M 20 nominal mix using 12mm Supply and placing of the Design Supply and placing of the Design Mix
size hard granite machine crushed graded metal (coarse Mix Concrete M 30 grade Concrete M 30 grade
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for platforms and shelves.
50mm thick platforms / lofts:
First Floor :

39 Reinforced Cement Concrete M 20 nominal mix using 12mm Supply and placing of the Design Supply and placing of the Design Mix
size hard granite machine crushed graded metal (coarse Mix Concrete M 30 grade Concrete M 30 grade
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for platforms and shelves.
50mm thick platforms / lofts:
Second Floor :
29 Reinforced Cement Concrete M 20 nominal mix using 12mm Supply and placing of the Design Supply and placing of the Design Mix
size hard granite machine crushed graded metal (coarse Mix Concrete M 30 grade Concrete M 30 grade
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for platforms and shelves.
50mm thick platforms / lofts:
Third Floor :

192 Reinforced Cement Concrete M 20 nominal mix using 12mm Supply and placing of the Design Supply and placing of the Design Mix
size hard granite machine crushed graded metal (coarse Mix Concrete M 30 grade Concrete M 30 grade
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for platforms and shelves.
50mm thick platforms / lofts:
Fourth Floor :
3 Reinforced Cement Concrete M 20 nominal mix using 12mm Supply and placing of the Design Supply and placing of the Design Mix
size hard granite machine crushed graded metal (coarse Mix Concrete M 30 grade Concrete M 30 grade
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for platforms and shelves.
25mm thick shelves :
Cellar :

40 Reinforced Cement Concrete M 20 nominal mix using 12mm Supply and placing of the Design Supply and placing of the Design Mix
size hard granite machine crushed graded metal (coarse Mix Concrete M 30 grade Concrete M 30 grade
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for platforms and shelves.
25mm thick shelves :
Basement Floor
9 Reinforced Cement Concrete M 20 nominal mix using 12mm Supply and placing of the Design Supply and placing of the Design Mix
size hard granite machine crushed graded metal (coarse Mix Concrete M 30 grade Concrete M 30 grade
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for platforms and shelves.
25mm thick shelves :
First Floor :

17 Reinforced Cement Concrete M 20 nominal mix using 12mm Supply and placing of the Design Supply and placing of the Design Mix
size hard granite machine crushed graded metal (coarse Mix Concrete M 30 grade Concrete M 30 grade
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for platforms and shelves.
25mm thick shelves :
Second Floor :
71 Reinforced Cement Concrete M 20 nominal mix using 12mm Supply and placing of the Design Supply and placing of the Design Mix
size hard granite machine crushed graded metal (coarse Mix Concrete M 30 grade Concrete M 30 grade
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for platforms and shelves.
25mm thick shelves :
Third Floor :

108 Reinforced Cement Concrete M 20 nominal mix using 12mm Supply and placing of the Design Supply and placing of the Design Mix
size hard granite machine crushed graded metal (coarse Mix Concrete M 30 grade Concrete M 30 grade
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for platforms and shelves.
25mm thick shelves :
Fourth Floor :
4 Plain Cement Concrete M 20 nominal mix using 20mm size Plain Cement Concrete M 20 Plain Cement Concrete M 20 nominal
graded machine crushed hard granite metal (coarse aggregate - nominal mix mix
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity including cost and conveyance of all materials like
cement, fine aggregate(sand), coarse aggregate, water etc. to
site including all charges centering, labour charges such as
weigh batching, machine mixing, hire charges of concrete
mixer, laying concrete in position, curing etc., & lift charges ,
and overheads & contractors profit for steps for finished item of
work. (APSS No. 402)
Cellar :

6 Plain Cement Concrete M 20 nominal mix using 20mm size Plain Cement Concrete M 20 Plain Cement Concrete M 20 nominal
graded machine crushed hard granite metal (coarse aggregate - nominal mix mix
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity including cost and conveyance of all materials like
cement, fine aggregate(sand), coarse aggregate, water etc. to
site including all charges centering, labour charges such as
weigh batching, machine mixing, hire charges of concrete
mixer, laying concrete in position, curing etc., & lift charges ,
and overheads & contractors profit for steps for finished item of
work. (APSS No. 402)
Basement Floor

#REF! Plain Cement Concrete M 20 nominal mix using 20mm size Plain Cement Concrete M 20 Plain Cement Concrete M 20 nominal
graded machine crushed hard granite metal (coarse aggregate - nominal mix mix
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity including cost and conveyance of all materials like
cement, fine aggregate(sand), coarse aggregate, water etc. to
site including all charges centering, labour charges such as
weigh batching, machine mixing, hire charges of concrete
mixer, laying concrete in position, curing etc., & lift charges ,
and overheads & contractors profit for steps for finished item of
work. (APSS No. 402)
First Floor :
6 Plain Cement Concrete M 20 nominal mix using 20mm size Plain Cement Concrete M 20 Plain Cement Concrete M 20 nominal
graded machine crushed hard granite metal (coarse aggregate - nominal mix mix
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity including cost and conveyance of all materials like
cement, fine aggregate(sand), coarse aggregate, water etc. to
site including all charges centering, labour charges such as
weigh batching, machine mixing, hire charges of concrete
mixer, laying concrete in position, curing etc., & lift charges ,
and overheads & contractors profit for steps for finished item of
work. (APSS No. 402)
Second Floor :

6 Plain Cement Concrete M 20 nominal mix using 20mm size Plain Cement Concrete M 20 Plain Cement Concrete M 20 nominal
graded machine crushed hard granite metal (coarse aggregate - nominal mix mix
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity including cost and conveyance of all materials like
cement, fine aggregate(sand), coarse aggregate, water etc. to
site including all charges centering, labour charges such as
weigh batching, machine mixing, hire charges of concrete
mixer, laying concrete in position, curing etc., & lift charges ,
and overheads & contractors profit for steps for finished item of
work. (APSS No. 402)
Third Floor :

6 Plain Cement Concrete M 20 nominal mix using 20mm size Plain Cement Concrete M 20 Plain Cement Concrete M 20 nominal
graded machine crushed hard granite metal (coarse aggregate - nominal mix mix
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity including cost and conveyance of all materials like
cement, fine aggregate(sand), coarse aggregate, water etc. to
site including all charges centering, labour charges such as
weigh batching, machine mixing, hire charges of concrete
mixer, laying concrete in position, curing etc., & lift charges ,
and overheads & contractors profit for steps for finished item of
work. (APSS No. 402)
Fourth Floor :
1 Reinforced Cement Concrete M 20 nominal mix using 12mm Plain Cement Concrete M 20 Plain Cement Concrete M 20 nominal
size hard granite machine crushed graded metal (coarse nominal mix mix
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for sill slabs.
Cellar :

2 Reinforced Cement Concrete M 20 nominal mix using 12mm Plain Cement Concrete M 20 Plain Cement Concrete M 20 nominal
size hard granite machine crushed graded metal (coarse nominal mix mix
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for sill slabs.
Basement Floor
1.9 Reinforced Cement Concrete M 20 nominal mix using 12mm Plain Cement Concrete M 20 Plain Cement Concrete M 20 nominal
size hard granite machine crushed graded metal (coarse nominal mix mix
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for sill slabs.
First Floor :

3.9 Reinforced Cement Concrete M 20 nominal mix using 12mm Plain Cement Concrete M 20 Plain Cement Concrete M 20 nominal
size hard granite machine crushed graded metal (coarse nominal mix mix
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for sill slabs.
Second Floor :
2 Reinforced Cement Concrete M 20 nominal mix using 12mm Plain Cement Concrete M 20 Plain Cement Concrete M 20 nominal
size hard granite machine crushed graded metal (coarse nominal mix mix
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for sill slabs.
Third Floor :

3.3 Reinforced Cement Concrete M 20 nominal mix using 12mm Plain Cement Concrete M 20 Plain Cement Concrete M 20 nominal
size hard granite machine crushed graded metal (coarse nominal mix mix
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for sill slabs.
Fourth Floor :

245 Brick masonry for panel walls in superstructure with CM (1:8) Brick masonry for panel walls in Brick masonry for panel walls in
prop: (Cement : Sand) using common burnt clay bricks of class superstructure with CM (1:8) prop superstructure with CM (1:8) prop
as per Table- I of IS:1077-1992, Non- Modular or traditional size
23 x 11 x 7 cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and
conveyance of all materials like cement, screened sand, bricks,
water etc., to site, labour charges, like mixing cement mortar,
scaffolding charges, constructing masonry, lift charges, curing,
etc.,and overheads & contractors profit complete for finished
item of work. (APSS No. 501 & 504).
Cellar :
472 Brick masonry for panel walls in superstructure with CM (1:8) Brick masonry for panel walls in Brick masonry for panel walls in
prop: (Cement : Sand) using common burnt clay bricks of class superstructure with CM (1:8) prop superstructure with CM (1:8) prop
as per Table- I of IS:1077-1992, Non- Modular or traditional size
23 x 11 x 7 cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and
conveyance of all materials like cement, screened sand, bricks,
water etc., to site, labour charges, like mixing cement mortar,
scaffolding charges, constructing masonry, lift charges, curing,
etc.,and overheads & contractors profit complete for finished
item of work. (APSS No. 501 & 504).
Basement Floor

478 Brick masonry for panel walls in superstructure with CM (1:8) Brick masonry for panel walls in Brick masonry for panel walls in
prop: (Cement : Sand) using common burnt clay bricks of class superstructure with CM (1:8) prop superstructure with CM (1:8) prop
as per Table- I of IS:1077-1992, Non- Modular or traditional size
23 x 11 x 7 cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and
conveyance of all materials like cement, screened sand, bricks,
water etc., to site, labour charges, like mixing cement mortar,
scaffolding charges, constructing masonry, lift charges, curing,
etc.,and overheads & contractors profit complete for finished
item of work. (APSS No. 501 & 504).
First Floor :

368 Brick masonry for panel walls in superstructure with CM (1:8) Brick masonry for panel walls in Brick masonry for panel walls in
prop: (Cement : Sand) using common burnt clay bricks of class superstructure with CM (1:8) prop superstructure with CM (1:8) prop
as per Table- I of IS:1077-1992, Non- Modular or traditional size
23 x 11 x 7 cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and
conveyance of all materials like cement, screened sand, bricks,
water etc., to site, labour charges, like mixing cement mortar,
scaffolding charges, constructing masonry, lift charges, curing,
etc.,and overheads & contractors profit complete for finished
item of work. (APSS No. 501 & 504).
Second Floor :
580 Brick masonry for panel walls in superstructure with CM (1:8) Brick masonry for panel walls in Brick masonry for panel walls in
prop: (Cement : Sand) using common burnt clay bricks of class superstructure with CM (1:8) prop superstructure with CM (1:8) prop
as per Table- I of IS:1077-1992, Non- Modular or traditional size
23 x 11 x 7 cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and
conveyance of all materials like cement, screened sand, bricks,
water etc., to site, labour charges, like mixing cement mortar,
scaffolding charges, constructing masonry, lift charges, curing,
etc.,and overheads & contractors profit complete for finished
item of work. (APSS No. 501 & 504).
Third Floor :

388 Brick masonry for panel walls in superstructure with CM (1:8) Brick masonry for panel walls in Brick masonry for panel walls in
prop: (Cement : Sand) using common burnt clay bricks of class superstructure with CM (1:8) prop superstructure with CM (1:8) prop
as per Table- I of IS:1077-1992, Non- Modular or traditional size
23 x 11 x 7 cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and
conveyance of all materials like cement, screened sand, bricks,
water etc., to site, labour charges, like mixing cement mortar,
scaffolding charges, constructing masonry, lift charges, curing,
etc.,and overheads & contractors profit complete for finished
item of work. (APSS No. 501 & 504).
Fourth Floor :

86 Brick masonry for panel walls in superstructure with CM (1:8) Brick masonry for panel walls in Brick masonry for panel walls in
prop: (Cement : Sand) using common burnt clay bricks of class superstructure with CM (1:8) prop superstructure with CM (1:8) prop
as per Table- I of IS:1077-1992, Non- Modular or traditional size
23 x 11 x 7 cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and
conveyance of all materials like cement, screened sand, bricks,
water etc., to site, labour charges, like mixing cement mortar,
scaffolding charges, constructing masonry, lift charges, curing,
etc.,and overheads & contractors profit complete for finished
item of work. (APSS No. 501 & 504).
Fifth Floor :
#REF! Brick masonry for panel walls in superstructure with CM (1:8) Brick masonry for panel walls in Brick masonry for panel walls in
prop: (Cement : Sand) using common burnt clay bricks of class superstructure with CM (1:8) prop superstructure with CM (1:8) prop
as per Table- I of IS:1077-1992, Non- Modular or traditional size
23 x 11 x 7 cms from approved source having minimum
crushing strength of 40 Kg/Sqcm. including cost and
conveyance of all materials like cement, screened sand, bricks,
water etc., to site, labour charges, like mixing cement mortar,
scaffolding charges, constructing masonry, lift charges, curing,
etc.,and overheads & contractors profit complete for finished
item of work. (APSS No. 501 & 504).
For Compound wall :

238 Reinforced Brick Masonry for partition walls (11.0 cm thick) in Reinforced Brick Masonry for Reinforced Brick Masonry for partition
CM (1:4) prop. (Cement : Sand) using common burnt clay bricks partition walls (11.0 cm thick) in CM walls (11.0 cm thick) in CM (1:4) prop
of class as per Table- I of IS:1077-1992, Non- Modular or (1:4) prop
traditional size 23 x 11 x 7 cms from approved source having
minimum crushing strength of 40 Kg/Sq.cm and placing 2 Nos.
of 6mm M.S plain rods in every third layer with free ends of the
reinforcement pegged into mortar joints of main brick walls
where applicable including cost and conveyance of all materials
like cement, steel, sand, bricks, water etc., to site, all
operational, incidental charges such as labour charges for
mixing cement mortar, scaffolding charges, constructing
masonry, lift charges, curing, etc., and overheads & contractors
profit but excluding cost of steel and its fabrication charges
complete for finished item of work. (APSS No. of 501 & 509)
Cellar :
1262 Reinforced Brick Masonry for partition walls (11.0 cm thick) in Reinforced Brick Masonry for Reinforced Brick Masonry for partition
CM (1:4) prop. (Cement : Sand) using common burnt clay bricks partition walls (11.0 cm thick) in CM walls (11.0 cm thick) in CM (1:4) prop
of class as per Table- I of IS:1077-1992, Non- Modular or (1:4) prop
traditional size 23 x 11 x 7 cms from approved source having
minimum crushing strength of 40 Kg/Sq.cm and placing 2 Nos.
of 6mm M.S plain rods in every third layer with free ends of the
reinforcement pegged into mortar joints of main brick walls
where applicable including cost and conveyance of all materials
like cement, steel, sand, bricks, water etc., to site, all
operational, incidental charges such as labour charges for
mixing cement mortar, scaffolding charges, constructing
masonry, lift charges, curing, etc., and overheads & contractors
profit but excluding cost of steel and its fabrication charges
complete for finished item of work. (APSS No. of 501 & 509)
Basement Floor

1358 Reinforced Brick Masonry for partition walls (11.0 cm thick) in Reinforced Brick Masonry for Reinforced Brick Masonry for partition
CM (1:4) prop. (Cement : Sand) using common burnt clay bricks partition walls (11.0 cm thick) in CM walls (11.0 cm thick) in CM (1:4) prop
of class as per Table- I of IS:1077-1992, Non- Modular or (1:4) prop
traditional size 23 x 11 x 7 cms from approved source having
minimum crushing strength of 40 Kg/Sq.cm and placing 2 Nos.
of 6mm M.S plain rods in every third layer with free ends of the
reinforcement pegged into mortar joints of main brick walls
where applicable including cost and conveyance of all materials
like cement, steel, sand, bricks, water etc., to site, all
operational, incidental charges such as labour charges for
mixing cement mortar, scaffolding charges, constructing
masonry, lift charges, curing, etc., and overheads & contractors
profit but excluding cost of steel and its fabrication charges
complete for finished item of work. (APSS No. of 501 & 509)
First Floor :
1394 Reinforced Brick Masonry for partition walls (11.0 cm thick) in Reinforced Brick Masonry for Reinforced Brick Masonry for partition
CM (1:4) prop. (Cement : Sand) using common burnt clay bricks partition walls (11.0 cm thick) in CM walls (11.0 cm thick) in CM (1:4) prop
of class as per Table- I of IS:1077-1992, Non- Modular or (1:4) prop
traditional size 23 x 11 x 7 cms from approved source having
minimum crushing strength of 40 Kg/Sq.cm and placing 2 Nos.
of 6mm M.S plain rods in every third layer with free ends of the
reinforcement pegged into mortar joints of main brick walls
where applicable including cost and conveyance of all materials
like cement, steel, sand, bricks, water etc., to site, all
operational, incidental charges such as labour charges for
mixing cement mortar, scaffolding charges, constructing
masonry, lift charges, curing, etc., and overheads & contractors
profit but excluding cost of steel and its fabrication charges
complete for finished item of work. (APSS No. of 501 & 509)
Second Floor :

1726 Reinforced Brick Masonry for partition walls (11.0 cm thick) in Reinforced Brick Masonry for Reinforced Brick Masonry for partition
CM (1:4) prop. (Cement : Sand) using common burnt clay bricks partition walls (11.0 cm thick) in CM walls (11.0 cm thick) in CM (1:4) prop
of class as per Table- I of IS:1077-1992, Non- Modular or (1:4) prop
traditional size 23 x 11 x 7 cms from approved source having
minimum crushing strength of 40 Kg/Sq.cm and placing 2 Nos.
of 6mm M.S plain rods in every third layer with free ends of the
reinforcement pegged into mortar joints of main brick walls
where applicable including cost and conveyance of all materials
like cement, steel, sand, bricks, water etc., to site, all
operational, incidental charges such as labour charges for
mixing cement mortar, scaffolding charges, constructing
masonry, lift charges, curing, etc., and overheads & contractors
profit but excluding cost of steel and its fabrication charges
complete for finished item of work. (APSS No. of 501 & 509)
Third Floor :
1161 Reinforced Brick Masonry for partition walls (11.0 cm thick) in Reinforced Brick Masonry for Reinforced Brick Masonry for partition
CM (1:4) prop. (Cement : Sand) using common burnt clay bricks partition walls (11.0 cm thick) in CM walls (11.0 cm thick) in CM (1:4) prop
of class as per Table- I of IS:1077-1992, Non- Modular or (1:4) prop
traditional size 23 x 11 x 7 cms from approved source having
minimum crushing strength of 40 Kg/Sq.cm and placing 2 Nos.
of 6mm M.S plain rods in every third layer with free ends of the
reinforcement pegged into mortar joints of main brick walls
where applicable including cost and conveyance of all materials
like cement, steel, sand, bricks, water etc., to site, all
operational, incidental charges such as labour charges for
mixing cement mortar, scaffolding charges, constructing
masonry, lift charges, curing, etc., and overheads & contractors
profit but excluding cost of steel and its fabrication charges
complete for finished item of work. (APSS No. of 501 & 509)
Fourth Floor :

458 Reinforced Brick Masonry for partition walls (11.0 cm thick) in Reinforced Brick Masonry for Reinforced Brick Masonry for partition
CM (1:4) prop. (Cement : Sand) using common burnt clay bricks partition walls (11.0 cm thick) in CM walls (11.0 cm thick) in CM (1:4) prop
of class as per Table- I of IS:1077-1992, Non- Modular or (1:4) prop
traditional size 23 x 11 x 7 cms from approved source having
minimum crushing strength of 40 Kg/Sq.cm and placing 2 Nos.
of 6mm M.S plain rods in every third layer with free ends of the
reinforcement pegged into mortar joints of main brick walls
where applicable including cost and conveyance of all materials
like cement, steel, sand, bricks, water etc., to site, all
operational, incidental charges such as labour charges for
mixing cement mortar, scaffolding charges, constructing
masonry, lift charges, curing, etc., and overheads & contractors
profit but excluding cost of steel and its fabrication charges
complete for finished item of work. (APSS No. of 501 & 509)
Fifth Floor :
5.8 Plain Cement Concrete (1:3:6) nominal mix using 20mm size Plain Cement Concrete (1:3:6) Plain Cement Concrete (1:3:6)
graded machine crushed hard granite metal (coarse aggregate -
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity including cost and conveyance of all materials like
cement, fine aggregate(sand), coarse aggregate, water etc. to
site including all charges for machine mixing, hire charges of
concrete mixer, laying concrete in position, curing etc., & lift
charges , and overheads & contractors profit for bed blocks &
hold fasts for finished item of work. (APSS No. 402)
Cellar :

66.6 Plain Cement Concrete (1:3:6) nominal mix using 20mm size Plain Cement Concrete (1:3:6) Plain Cement Concrete (1:3:6)
graded machine crushed hard granite metal (coarse aggregate -
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity including cost and conveyance of all materials like
cement, fine aggregate(sand), coarse aggregate, water etc. to
site including all charges for machine mixing, hire charges of
concrete mixer, laying concrete in position, curing etc., & lift
charges , and overheads & contractors profit for bed blocks &
hold fasts for finished item of work. (APSS No. 402)
Basement Floor

14 Plain Cement Concrete (1:3:6) nominal mix using 20mm size Plain Cement Concrete (1:3:6) Plain Cement Concrete (1:3:6)
graded machine crushed hard granite metal (coarse aggregate -
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity including cost and conveyance of all materials like
cement, fine aggregate(sand), coarse aggregate, water etc. to
site including all charges for machine mixing, hire charges of
concrete mixer, laying concrete in position, curing etc., & lift
charges , and overheads & contractors profit for bed blocks &
hold fasts for finished item of work. (APSS No. 402)
First Floor :
18 Plain Cement Concrete (1:3:6) nominal mix using 20mm size Plain Cement Concrete (1:3:6) Plain Cement Concrete (1:3:6)
graded machine crushed hard granite metal (coarse aggregate -
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity including cost and conveyance of all materials like
cement, fine aggregate(sand), coarse aggregate, water etc. to
site including all charges for machine mixing, hire charges of
concrete mixer, laying concrete in position, curing etc., & lift
charges , and overheads & contractors profit for bed blocks &
hold fasts for finished item of work. (APSS No. 402)
Second Floor :

13 Plain Cement Concrete (1:3:6) nominal mix using 20mm size Plain Cement Concrete (1:3:6) Plain Cement Concrete (1:3:6)
graded machine crushed hard granite metal (coarse aggregate -
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity including cost and conveyance of all materials like
cement, fine aggregate(sand), coarse aggregate, water etc. to
site including all charges for machine mixing, hire charges of
concrete mixer, laying concrete in position, curing etc., & lift
charges , and overheads & contractors profit for bed blocks &
hold fasts for finished item of work. (APSS No. 402)
Third Floor :

17 Plain Cement Concrete (1:3:6) nominal mix using 20mm size Plain Cement Concrete (1:3:6) Plain Cement Concrete (1:3:6)
graded machine crushed hard granite metal (coarse aggregate -
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity including cost and conveyance of all materials like
cement, fine aggregate(sand), coarse aggregate, water etc. to
site including all charges for machine mixing, hire charges of
concrete mixer, laying concrete in position, curing etc., & lift
charges , and overheads & contractors profit for bed blocks &
hold fasts for finished item of work. (APSS No. 402)
Fourth Floor :
1 Plain Cement Concrete (1:3:6) nominal mix using 20mm size Plain Cement Concrete (1:3:6) Plain Cement Concrete (1:3:6)
graded machine crushed hard granite metal (coarse aggregate -
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity including cost and conveyance of all materials like
cement, fine aggregate(sand), coarse aggregate, water etc. to
site including all charges for machine mixing, hire charges of
concrete mixer, laying concrete in position, curing etc., & lift
charges , and overheads & contractors profit for bed blocks &
hold fasts for finished item of work. (APSS No. 402)
Fifth Floor :

360.721 Providing Thermo Mechanically Treated (TMT) (Fe 500 / Fe 500 Providing Thermo Mechanically Plain Cement Concrete (1:3:6)
D grade as per IS 1786-1979) of different diameters for RCC Treated (TMT) (Fe 500 / Fe 500 D
works including labour charges for straightening, cutting, grade)
bending to required sizes and shapes, placing in position with
cover blocks of approved materials and size and tying and lap-
splicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and drawings,
including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars
including cost and conveyance of binding wire, cover blocks and
all incidental, operational, labour charges such as cutting,
bending, placing in position, tying etc., and overheads &
contractors profit complete for finished item of work.( APSS
No.126)
Cellar :
152.4 Providing Thermo Mechanically Treated (TMT) (Fe 500 / Fe 500 Providing Thermo Mechanically Plain Cement Concrete (1:3:6)
D grade as per IS 1786-1979) of different diameters for RCC Treated (TMT) (Fe 500 / Fe 500 D
works including labour charges for straightening, cutting, grade)
bending to required sizes and shapes, placing in position with
cover blocks of approved materials and size and tying and lap-
splicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and drawings,
including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars
including cost and conveyance of binding wire, cover blocks and
all incidental, operational, labour charges such as cutting,
bending, placing in position, tying etc., and overheads &
contractors profit complete for finished item of work.( APSS
No.126)
Basement Floor

#REF! Providing Thermo Mechanically Treated (TMT) (Fe 500 / Fe 500 Providing Thermo Mechanically Plain Cement Concrete (1:3:6)
D grade as per IS 1786-1979) of different diameters for RCC Treated (TMT) (Fe 500 / Fe 500 D
works including labour charges for straightening, cutting, grade)
bending to required sizes and shapes, placing in position with
cover blocks of approved materials and size and tying and lap-
splicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and drawings,
including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars
including cost and conveyance of binding wire, cover blocks and
all incidental, operational, labour charges such as cutting,
bending, placing in position, tying etc., and overheads &
contractors profit complete for finished item of work.( APSS
No.126)
First Floor :
115.8 Providing Thermo Mechanically Treated (TMT) (Fe 500 / Fe 500 Providing Thermo Mechanically Plain Cement Concrete (1:3:6)
D grade as per IS 1786-1979) of different diameters for RCC Treated (TMT) (Fe 500 / Fe 500 D
works including labour charges for straightening, cutting, grade)
bending to required sizes and shapes, placing in position with
cover blocks of approved materials and size and tying and lap-
splicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and drawings,
including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars
including cost and conveyance of binding wire, cover blocks and
all incidental, operational, labour charges such as cutting,
bending, placing in position, tying etc., and overheads &
contractors profit complete for finished item of work.( APSS
No.126)
Second Floor :

122.5 Providing Thermo Mechanically Treated (TMT) (Fe 500 / Fe 500 Providing Thermo Mechanically Plain Cement Concrete (1:3:6)
D grade as per IS 1786-1979) of different diameters for RCC Treated (TMT) (Fe 500 / Fe 500 D
works including labour charges for straightening, cutting, grade)
bending to required sizes and shapes, placing in position with
cover blocks of approved materials and size and tying and lap-
splicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and drawings,
including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars
including cost and conveyance of binding wire, cover blocks and
all incidental, operational, labour charges such as cutting,
bending, placing in position, tying etc., and overheads &
contractors profit complete for finished item of work.( APSS
No.126)
Third Floor :
115.6 Providing Thermo Mechanically Treated (TMT) (Fe 500 / Fe 500 Providing Thermo Mechanically Plain Cement Concrete (1:3:6)
D grade as per IS 1786-1979) of different diameters for RCC Treated (TMT) (Fe 500 / Fe 500 D
works including labour charges for straightening, cutting, grade)
bending to required sizes and shapes, placing in position with
cover blocks of approved materials and size and tying and lap-
splicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and drawings,
including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars
including cost and conveyance of binding wire, cover blocks and
all incidental, operational, labour charges such as cutting,
bending, placing in position, tying etc., and overheads &
contractors profit complete for finished item of work.( APSS
No.126)
Fourth Floor :

29 Providing Thermo Mechanically Treated (TMT) (Fe 500 / Fe 500 Providing Thermo Mechanically Plain Cement Concrete (1:3:6)
D grade as per IS 1786-1979) of different diameters for RCC Treated (TMT) (Fe 500 / Fe 500 D
works including labour charges for straightening, cutting, grade)
bending to required sizes and shapes, placing in position with
cover blocks of approved materials and size and tying and lap-
splicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and drawings,
including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars
including cost and conveyance of binding wire, cover blocks and
all incidental, operational, labour charges such as cutting,
bending, placing in position, tying etc., and overheads &
contractors profit complete for finished item of work.( APSS
No.126)
Fifth Floor :
0.86 Providing Mild steel (MS) steel bars (Fe 250 grade as per IS Providing Mild steel (MS) steel bars Providing Mild steel (MS) steel bars
432) of different diameters including labour charges for (Fe 250 grade) (Fe 250 grade)
straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and
size and tying and lap-splicing with binding wire of 18 SWG,
forming grills for reinforcement work as per approved designs
and drawings, including cost and conveyance of steel bars,
including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire,
cover blocks and all incidental, operational, labour charges such
as cutting, bending, placing in position, tying etc., and
overheads & contractors profit complete for finished item of
work.( APSS No.126)
Cellar :

2.6 Providing Mild steel (MS) steel bars (Fe 250 grade as per IS Providing Mild steel (MS) steel bars Providing Mild steel (MS) steel bars
432) of different diameters including labour charges for (Fe 250 grade) (Fe 250 grade)
straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and
size and tying and lap-splicing with binding wire of 18 SWG,
forming grills for reinforcement work as per approved designs
and drawings, including cost and conveyance of steel bars,
including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire,
cover blocks and all incidental, operational, labour charges such
as cutting, bending, placing in position, tying etc., and
overheads & contractors profit complete for finished item of
work.( APSS No.126)
Basement Floor
0.86 Providing Mild steel (MS) steel bars (Fe 250 grade as per IS Providing Mild steel (MS) steel bars Providing Mild steel (MS) steel bars
432) of different diameters including labour charges for (Fe 250 grade) (Fe 250 grade)
straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and
size and tying and lap-splicing with binding wire of 18 SWG,
forming grills for reinforcement work as per approved designs
and drawings, including cost and conveyance of steel bars,
including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire,
cover blocks and all incidental, operational, labour charges such
as cutting, bending, placing in position, tying etc., and
overheads & contractors profit complete for finished item of
work.( APSS No.126)
First Floor :

1.86 Providing Mild steel (MS) steel bars (Fe 250 grade as per IS Providing Mild steel (MS) steel bars Providing Mild steel (MS) steel bars
432) of different diameters including labour charges for (Fe 250 grade) (Fe 250 grade)
straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and
size and tying and lap-splicing with binding wire of 18 SWG,
forming grills for reinforcement work as per approved designs
and drawings, including cost and conveyance of steel bars,
including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire,
cover blocks and all incidental, operational, labour charges such
as cutting, bending, placing in position, tying etc., and
overheads & contractors profit complete for finished item of
work.( APSS No.126)
Second Floor :
1.67 Providing Mild steel (MS) steel bars (Fe 250 grade as per IS Providing Mild steel (MS) steel bars Providing Mild steel (MS) steel bars
432) of different diameters including labour charges for (Fe 250 grade) (Fe 250 grade)
straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and
size and tying and lap-splicing with binding wire of 18 SWG,
forming grills for reinforcement work as per approved designs
and drawings, including cost and conveyance of steel bars,
including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire,
cover blocks and all incidental, operational, labour charges such
as cutting, bending, placing in position, tying etc., and
overheads & contractors profit complete for finished item of
work.( APSS No.126)
Third Floor :

3.03 Providing Mild steel (MS) steel bars (Fe 250 grade as per IS Providing Mild steel (MS) steel bars Providing Mild steel (MS) steel bars
432) of different diameters including labour charges for (Fe 250 grade) (Fe 250 grade)
straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and
size and tying and lap-splicing with binding wire of 18 SWG,
forming grills for reinforcement work as per approved designs
and drawings, including cost and conveyance of steel bars,
including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire,
cover blocks and all incidental, operational, labour charges such
as cutting, bending, placing in position, tying etc., and
overheads & contractors profit complete for finished item of
work.( APSS No.126)
Fourth Floor :
0.23 Providing Mild steel (MS) steel bars (Fe 250 grade as per IS Providing Mild steel (MS) steel bars Providing Mild steel (MS) steel bars
432) of different diameters including labour charges for (Fe 250 grade) (Fe 250 grade)
straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and
size and tying and lap-splicing with binding wire of 18 SWG,
forming grills for reinforcement work as per approved designs
and drawings, including cost and conveyance of steel bars,
including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire,
cover blocks and all incidental, operational, labour charges such
as cutting, bending, placing in position, tying etc., and
overheads & contractors profit complete for finished item of
work.( APSS No.126)
Fifth Floor :

1837 Ornamental ceiling plastering 12mm thick single coat in CM Ornamental ceiling plastering 12mm Ornamental ceiling plastering 12mm
(1:5) using screened sand including cost and conveyance of all thick single coat in CM (1:5) thick single coat in CM (1:5)
materials like cement, sand, water etc., to site and all
operational, incidental charges on materials and including cost
of all labour charges for mixing mortar, finishing, curing as
directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work.(SS
901,903 & 904)
Cellar :

2889 Ornamental ceiling plastering 12mm thick single coat in CM Ornamental ceiling plastering 12mm Ornamental ceiling plastering 12mm
(1:5) using screened sand including cost and conveyance of all thick single coat in CM (1:5) thick single coat in CM (1:5)
materials like cement, sand, water etc., to site and all
operational, incidental charges on materials and including cost
of all labour charges for mixing mortar, finishing, curing as
directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work.(SS
901,903 & 904)
Basement Floor
2683 Ornamental ceiling plastering 12mm thick single coat in CM Ornamental ceiling plastering 12mm Ornamental ceiling plastering 12mm
(1:5) using screened sand including cost and conveyance of all thick single coat in CM (1:5) thick single coat in CM (1:5)
materials like cement, sand, water etc., to site and all
operational, incidental charges on materials and including cost
of all labour charges for mixing mortar, finishing, curing as
directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work.(SS
901,903 & 904)
First Floor :

2746 Ornamental ceiling plastering 12mm thick single coat in CM Ornamental ceiling plastering 12mm Ornamental ceiling plastering 12mm
(1:5) using screened sand including cost and conveyance of all thick single coat in CM (1:5) thick single coat in CM (1:5)
materials like cement, sand, water etc., to site and all
operational, incidental charges on materials and including cost
of all labour charges for mixing mortar, finishing, curing as
directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work.(SS
901,903 & 904)
Second Floor :

2163 Ornamental ceiling plastering 12mm thick single coat in CM Ornamental ceiling plastering 12mm Ornamental ceiling plastering 12mm
(1:5) using screened sand including cost and conveyance of all thick single coat in CM (1:5) thick single coat in CM (1:5)
materials like cement, sand, water etc., to site and all
operational, incidental charges on materials and including cost
of all labour charges for mixing mortar, finishing, curing as
directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work.(SS
901,903 & 904)
Third Floor :

459 Ornamental ceiling plastering 12mm thick single coat in CM Ornamental ceiling plastering 12mm Ornamental ceiling plastering 12mm
(1:5) using screened sand including cost and conveyance of all thick single coat in CM (1:5) thick single coat in CM (1:5)
materials like cement, sand, water etc., to site and all
operational, incidental charges on materials and including cost
of all labour charges for mixing mortar, finishing, curing as
directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work.(SS
901,903 & 904)
Fourth Floor :
364 Ornamental ceiling plastering 12mm thick single coat in CM Ornamental ceiling plastering 12mm Ornamental ceiling plastering 12mm
(1:5) using screened sand including cost and conveyance of all thick single coat in CM (1:5) thick single coat in CM (1:5)
materials like cement, sand, water etc., to site and all
operational, incidental charges on materials and including cost
of all labour charges for mixing mortar, finishing, curing as
directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work.(SS
901,903 & 904)
Fifth Floor :

1294 Plastering 12mm thick in two coats using screened sand with Plastering 12mm thick in two coats Plastering 12mm thick in two coats
base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in
CM (1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site
and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer - in - charge etc., and overheads &
contractors profit complete for finished item of work. (SS
901,903 & 904) For Internal Walls
Cellar :

3816 Plastering 12mm thick in two coats using screened sand with Plastering 12mm thick in two coats Plastering 12mm thick in two coats
base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in
CM (1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site
and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer - in - charge etc., and overheads &
contractors profit complete for finished item of work. (SS
901,903 & 904) For Internal Walls
Basement Floor
3640 Plastering 12mm thick in two coats using screened sand with Plastering 12mm thick in two coats Plastering 12mm thick in two coats
base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in
CM (1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site
and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer - in - charge etc., and overheads &
contractors profit complete for finished item of work. (SS
901,903 & 904) For Internal Walls
First Floor :

3511 Plastering 12mm thick in two coats using screened sand with Plastering 12mm thick in two coats Plastering 12mm thick in two coats
base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in
CM (1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site
and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer - in - charge etc., and overheads &
contractors profit complete for finished item of work. (SS
901,903 & 904) For Internal Walls
Second Floor :

4193 Plastering 12mm thick in two coats using screened sand with Plastering 12mm thick in two coats Plastering 12mm thick in two coats
base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in
CM (1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site
and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer - in - charge etc., and overheads &
contractors profit complete for finished item of work. (SS
901,903 & 904) For Internal Walls
Third Floor :
2936 Plastering 12mm thick in two coats using screened sand with Plastering 12mm thick in two coats Plastering 12mm thick in two coats
base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in
CM (1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site
and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer - in - charge etc., and overheads &
contractors profit complete for finished item of work. (SS
901,903 & 904) For Internal Walls
Fourth Floor :

407 Plastering 12mm thick in two coats using screened sand with Plastering 12mm thick in two coats Plastering 12mm thick in two coats
base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in
CM (1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site
and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer - in - charge etc., and overheads &
contractors profit complete for finished item of work. (SS
901,903 & 904) For Internal Walls
Fifth Floor :

1658 Plastering 20mm thick in two coats using screened sand with Plastering 20mm thick in two coats Plastering 20mm thick in two coats
base coat of 16mm thick in CM(1:6) and top coat of 4mm thick
in CM(1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site
and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work .(SS
901,903 & 904)
For Internal Walls & External Walls
Cellar :
4082 Plastering 20mm thick in two coats using screened sand with Plastering 20mm thick in two coats Plastering 20mm thick in two coats
base coat of 16mm thick in CM(1:6) and top coat of 4mm thick
in CM(1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site
and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work .(SS
901,903 & 904)
For Internal Walls & External Walls
Basement Floor

4227 Plastering 20mm thick in two coats using screened sand with Plastering 20mm thick in two coats Plastering 20mm thick in two coats
base coat of 16mm thick in CM(1:6) and top coat of 4mm thick
in CM(1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site
and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work .(SS
901,903 & 904)
For Internal Walls & External Walls
First Floor :

3781 Plastering 20mm thick in two coats using screened sand with Plastering 20mm thick in two coats Plastering 20mm thick in two coats
base coat of 16mm thick in CM(1:6) and top coat of 4mm thick
in CM(1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site
and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work .(SS
901,903 & 904)
For Internal Walls & External Walls
Second Floor :
4956 Plastering 20mm thick in two coats using screened sand with Plastering 20mm thick in two coats Plastering 20mm thick in two coats
base coat of 16mm thick in CM(1:6) and top coat of 4mm thick
in CM(1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site
and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work .(SS
901,903 & 904)
For Internal Walls & External Walls
Third Floor :

4269 Plastering 20mm thick in two coats using screened sand with Plastering 20mm thick in two coats Plastering 20mm thick in two coats
base coat of 16mm thick in CM(1:6) and top coat of 4mm thick
in CM(1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site
and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work .(SS
901,903 & 904)
For Internal Walls & External Walls
Fourth Floor :

1419 Plastering 20mm thick in two coats using screened sand with Plastering 20mm thick in two coats Plastering 20mm thick in two coats
base coat of 16mm thick in CM(1:6) and top coat of 4mm thick
in CM(1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site
and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work .(SS
901,903 & 904)
For Internal Walls & External Walls
Fifth Floor :
#REF! Plastering 12mm thick single coat in CM(1:5) using Plastering 12mm thick single coat in Plastering 12mm thick single coat in
screened sand including cost and conveyance of all materials CM(1:5) CM(1:5)
like cement, sand, water etc., to site and all operational,
incidental charges on materials and including cost of all labour
charges for mixing mortar, finishing, curing as directed by
Engineer-in-charge etc., and overheads & contractors profit
complete for finished item of work.(SS 901,903 & 904)

78 Flooring with non-skid white full body Ceramic floor tiles of size Flooring with non-skid white full Flooring with non-skid white full body
300 mm x 300 mm and thickness between 7-8 mm 1st quality body Ceramic floor tiles of size 300 Ceramic floor tiles of size 300 mm x
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of mm x 300 mm 300 mm
any colour and finish in all shades and designs as approved by
Engineer-in-charge, set over base coat of cement mortar (1:8),
12mm thick using screened sand over CC bed already laid or
RCC roof slab, including neat cement slurry of honey like
consistency spread @ 3.3 Kgs per sqm & jointed neatly with
white cement paste to full depth mixed with pigment of matching
shade, including cost of all materials like cement, screened
sand , water and tiles etc., and overheads & contractors profit
complete for finished item of work. (APSS No.701 & 707) For
Toilets
Cellar :

249 Flooring with non-skid white full body Ceramic floor tiles of size Flooring with non-skid white full Flooring with non-skid white full body
300 mm x 300 mm and thickness between 7-8 mm 1st quality body Ceramic floor tiles of size 300 Ceramic floor tiles of size 300 mm x
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of mm x 300 mm 300 mm
any colour and finish in all shades and designs as approved by
Engineer-in-charge, set over base coat of cement mortar (1:8),
12mm thick using screened sand over CC bed already laid or
RCC roof slab, including neat cement slurry of honey like
consistency spread @ 3.3 Kgs per sqm & jointed neatly with
white cement paste to full depth mixed with pigment of matching
shade, including cost of all materials like cement, screened
sand , water and tiles etc., and overheads & contractors profit
complete for finished item of work. (APSS No.701 & 707) For
Toilets
Basement Floor
312 Flooring with non-skid white full body Ceramic floor tiles of size Flooring with non-skid white full Flooring with non-skid white full body
300 mm x 300 mm and thickness between 7-8 mm 1st quality body Ceramic floor tiles of size 300 Ceramic floor tiles of size 300 mm x
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of mm x 300 mm 300 mm
any colour and finish in all shades and designs as approved by
Engineer-in-charge, set over base coat of cement mortar (1:8),
12mm thick using screened sand over CC bed already laid or
RCC roof slab, including neat cement slurry of honey like
consistency spread @ 3.3 Kgs per sqm & jointed neatly with
white cement paste to full depth mixed with pigment of matching
shade, including cost of all materials like cement, screened
sand , water and tiles etc., and overheads & contractors profit
complete for finished item of work. (APSS No.701 & 707) For
Toilets
First Floor :

180 Flooring with non-skid white full body Ceramic floor tiles of size Flooring with non-skid white full Flooring with non-skid white full body
300 mm x 300 mm and thickness between 7-8 mm 1st quality body Ceramic floor tiles of size 300 Ceramic floor tiles of size 300 mm x
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of mm x 300 mm 300 mm
any colour and finish in all shades and designs as approved by
Engineer-in-charge, set over base coat of cement mortar (1:8),
12mm thick using screened sand over CC bed already laid or
RCC roof slab, including neat cement slurry of honey like
consistency spread @ 3.3 Kgs per sqm & jointed neatly with
white cement paste to full depth mixed with pigment of matching
shade, including cost of all materials like cement, screened
sand , water and tiles etc., and overheads & contractors profit
complete for finished item of work. (APSS No.701 & 707) For
Toilets
Second Floor :
100 Flooring with non-skid white full body Ceramic floor tiles of size Flooring with non-skid white full Flooring with non-skid white full body
300 mm x 300 mm and thickness between 7-8 mm 1st quality body Ceramic floor tiles of size 300 Ceramic floor tiles of size 300 mm x
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of mm x 300 mm 300 mm
any colour and finish in all shades and designs as approved by
Engineer-in-charge, set over base coat of cement mortar (1:8),
12mm thick using screened sand over CC bed already laid or
RCC roof slab, including neat cement slurry of honey like
consistency spread @ 3.3 Kgs per sqm & jointed neatly with
white cement paste to full depth mixed with pigment of matching
shade, including cost of all materials like cement, screened
sand , water and tiles etc., and overheads & contractors profit
complete for finished item of work. (APSS No.701 & 707) For
Toilets
Third Floor :

130 Flooring with non-skid white full body Ceramic floor tiles of size Flooring with non-skid white full Flooring with non-skid white full body
300 mm x 300 mm and thickness between 7-8 mm 1st quality body Ceramic floor tiles of size 300 Ceramic floor tiles of size 300 mm x
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of mm x 300 mm 300 mm
any colour and finish in all shades and designs as approved by
Engineer-in-charge, set over base coat of cement mortar (1:8),
12mm thick using screened sand over CC bed already laid or
RCC roof slab, including neat cement slurry of honey like
consistency spread @ 3.3 Kgs per sqm & jointed neatly with
white cement paste to full depth mixed with pigment of matching
shade, including cost of all materials like cement, screened
sand , water and tiles etc., and overheads & contractors profit
complete for finished item of work. (APSS No.701 & 707) For
Toilets
Fourth Floor :
369 Flooring with non-skid Double charged / multi charged stain free Flooring with non-skid Double Flooring with non-skid Double charged
full body porcelain vitrified tiles with double layer pigment of charged / multi charged stain free / multi charged stain free full body
Size 600 x 600 mm and thickness between 8-10 mm 1st quality full body porcelain vitrified tiles with porcelain vitrified tiles with double layer
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of double layer pigment of Size 600 x pigment of Size 600 x 600 mm
any colour and finish in all shades and designs with borders and 600 mm
design as per the approved flooring pattern as directed by the
Engineer-In -Charge, laying tiles using spacers of 2mm thick,
set over a base coat of CM (1:8) prop. 12mm thick using
screened sand over CC bed already laid or RCC roof slab ,
including neat cement slurry of honey like consistancy spread
@ 3.3 kgs per sqm. and jointed neately with white cement
paste to full depth mixed with pigment of matching shade
including cost and conveyance of all materials like cement,
sand, water, tiles, white cement etc., to site (excluding cost of
C.C. bed) including cost of base coat and all labour charges
for mixing of cement mortar, laying tiles to required slope as
directed by the Engineer- in-charge etc.,and overheads &
contractors profit complete for finished item of work. (APSS
No.701 & 707)
Cellar :
1444 Flooring with non-skid Double charged / multi charged stain free Flooring with non-skid Double Flooring with non-skid Double charged
full body porcelain vitrified tiles with double layer pigment of charged / multi charged stain free / multi charged stain free full body
Size 600 x 600 mm and thickness between 8-10 mm 1st quality full body porcelain vitrified tiles with porcelain vitrified tiles with double layer
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of double layer pigment of Size 600 x pigment of Size 600 x 600 mm
any colour and finish in all shades and designs with borders and 600 mm
design as per the approved flooring pattern as directed by the
Engineer-In -Charge, laying tiles using spacers of 2mm thick,
set over a base coat of CM (1:8) prop. 12mm thick using
screened sand over CC bed already laid or RCC roof slab ,
including neat cement slurry of honey like consistancy spread
@ 3.3 kgs per sqm. and jointed neately with white cement
paste to full depth mixed with pigment of matching shade
including cost and conveyance of all materials like cement,
sand, water, tiles, white cement etc., to site (excluding cost of
C.C. bed) including cost of base coat and all labour charges
for mixing of cement mortar, laying tiles to required slope as
directed by the Engineer- in-charge etc.,and overheads &
contractors profit complete for finished item of work. (APSS
No.701 & 707)
Basement Floor
900 Flooring with non-skid Double charged / multi charged stain free Flooring with non-skid Double Flooring with non-skid Double charged
full body porcelain vitrified tiles with double layer pigment of charged / multi charged stain free / multi charged stain free full body
Size 600 x 600 mm and thickness between 8-10 mm 1st quality full body porcelain vitrified tiles with porcelain vitrified tiles with double layer
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of double layer pigment of Size 600 x pigment of Size 600 x 600 mm
any colour and finish in all shades and designs with borders and 600 mm
design as per the approved flooring pattern as directed by the
Engineer-In -Charge, laying tiles using spacers of 2mm thick,
set over a base coat of CM (1:8) prop. 12mm thick using
screened sand over CC bed already laid or RCC roof slab ,
including neat cement slurry of honey like consistancy spread
@ 3.3 kgs per sqm. and jointed neately with white cement
paste to full depth mixed with pigment of matching shade
including cost and conveyance of all materials like cement,
sand, water, tiles, white cement etc., to site (excluding cost of
C.C. bed) including cost of base coat and all labour charges
for mixing of cement mortar, laying tiles to required slope as
directed by the Engineer- in-charge etc.,and overheads &
contractors profit complete for finished item of work. (APSS
No.701 & 707)
First Floor :
2352 Flooring with non-skid Double charged / multi charged stain free Flooring with non-skid Double Flooring with non-skid Double charged
full body porcelain vitrified tiles with double layer pigment of charged / multi charged stain free / multi charged stain free full body
Size 600 x 600 mm and thickness between 8-10 mm 1st quality full body porcelain vitrified tiles with porcelain vitrified tiles with double layer
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of double layer pigment of Size 600 x pigment of Size 600 x 600 mm
any colour and finish in all shades and designs with borders and 600 mm
design as per the approved flooring pattern as directed by the
Engineer-In -Charge, laying tiles using spacers of 2mm thick,
set over a base coat of CM (1:8) prop. 12mm thick using
screened sand over CC bed already laid or RCC roof slab ,
including neat cement slurry of honey like consistancy spread
@ 3.3 kgs per sqm. and jointed neately with white cement
paste to full depth mixed with pigment of matching shade
including cost and conveyance of all materials like cement,
sand, water, tiles, white cement etc., to site (excluding cost of
C.C. bed) including cost of base coat and all labour charges
for mixing of cement mortar, laying tiles to required slope as
directed by the Engineer- in-charge etc.,and overheads &
contractors profit complete for finished item of work. (APSS
No.701 & 707)
Second Floor :
2403 Flooring with non-skid Double charged / multi charged stain free Flooring with non-skid Double Flooring with non-skid Double charged
full body porcelain vitrified tiles with double layer pigment of charged / multi charged stain free / multi charged stain free full body
Size 600 x 600 mm and thickness between 8-10 mm 1st quality full body porcelain vitrified tiles with porcelain vitrified tiles with double layer
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of double layer pigment of Size 600 x pigment of Size 600 x 600 mm
any colour and finish in all shades and designs with borders and 600 mm
design as per the approved flooring pattern as directed by the
Engineer-In -Charge, laying tiles using spacers of 2mm thick,
set over a base coat of CM (1:8) prop. 12mm thick using
screened sand over CC bed already laid or RCC roof slab ,
including neat cement slurry of honey like consistancy spread
@ 3.3 kgs per sqm. and jointed neately with white cement
paste to full depth mixed with pigment of matching shade
including cost and conveyance of all materials like cement,
sand, water, tiles, white cement etc., to site (excluding cost of
C.C. bed) including cost of base coat and all labour charges
for mixing of cement mortar, laying tiles to required slope as
directed by the Engineer- in-charge etc.,and overheads &
contractors profit complete for finished item of work. (APSS
No.701 & 707)
Third Floor :
2463 Flooring with non-skid Double charged / multi charged stain free Flooring with non-skid Double Flooring with non-skid Double charged
full body porcelain vitrified tiles with double layer pigment of charged / multi charged stain free / multi charged stain free full body
Size 600 x 600 mm and thickness between 8-10 mm 1st quality full body porcelain vitrified tiles with porcelain vitrified tiles with double layer
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of double layer pigment of Size 600 x pigment of Size 600 x 600 mm
any colour and finish in all shades and designs with borders and 600 mm
design as per the approved flooring pattern as directed by the
Engineer-In -Charge, laying tiles using spacers of 2mm thick,
set over a base coat of CM (1:8) prop. 12mm thick using
screened sand over CC bed already laid or RCC roof slab ,
including neat cement slurry of honey like consistancy spread
@ 3.3 kgs per sqm. and jointed neately with white cement
paste to full depth mixed with pigment of matching shade
including cost and conveyance of all materials like cement,
sand, water, tiles, white cement etc., to site (excluding cost of
C.C. bed) including cost of base coat and all labour charges
for mixing of cement mortar, laying tiles to required slope as
directed by the Engineer- in-charge etc.,and overheads &
contractors profit complete for finished item of work. (APSS
No.701 & 707)
Fourth Floor :

144 Flooring with 16 mm to 18 mm thick high polished granite stone Flooring with 16 mm to 18 mm thick Flooring with 16 mm to 18 mm thick
slabs other than black and regular colours (i.e. of shades like high polished granite stone slabs high polished granite stone slabs other
paradiso / bala flower / copper silk / laka red / lavender blue) other than black than black
with borders and design as per the pattern approved by the
Engineer-in-Charge of length not less than 2.43 mts set over
base coat of cement mortar (1:8) , 20mm thick using screened
sand over CC bed already laid or RCC roof slab including neat
grey cement slurry of honey like consistency spread @ 3.3 Kg
per sqm and jointed neatly with white cement paste mixed with
pigment of matching shade to full depth including cost and
conveyance of all materials like cement , sand , water , granite
slabs etc., to work site and all operational, incidental labour & lift
charges, polishing charges, cost of base coat and overheads &
contractors profit complete for finished item of work (S.S.701 &
special)
Cellar :
986 Flooring with 16 mm to 18 mm thick high polished granite stone Flooring with 16 mm to 18 mm thick Flooring with 16 mm to 18 mm thick
slabs other than black and regular colours (i.e. of shades like high polished granite stone slabs high polished granite stone slabs other
paradiso / bala flower / copper silk / laka red / lavender blue) other than black than black
with borders and design as per the pattern approved by the
Engineer-in-Charge of length not less than 2.43 mts set over
base coat of cement mortar (1:8) , 20mm thick using screened
sand over CC bed already laid or RCC roof slab including neat
grey cement slurry of honey like consistency spread @ 3.3 Kg
per sqm and jointed neatly with white cement paste mixed with
pigment of matching shade to full depth including cost and
conveyance of all materials like cement , sand , water , granite
slabs etc., to work site and all operational, incidental labour & lift
charges, polishing charges, cost of base coat and overheads &
contractors profit complete for finished item of work (S.S.701 &
special)
Basement Floor

1367 Flooring with 16 mm to 18 mm thick high polished granite stone Flooring with 16 mm to 18 mm thick Flooring with 16 mm to 18 mm thick
slabs other than black and regular colours (i.e. of shades like high polished granite stone slabs high polished granite stone slabs other
paradiso / bala flower / copper silk / laka red / lavender blue) other than black than black
with borders and design as per the pattern approved by the
Engineer-in-Charge of length not less than 2.43 mts set over
base coat of cement mortar (1:8) , 20mm thick using screened
sand over CC bed already laid or RCC roof slab including neat
grey cement slurry of honey like consistency spread @ 3.3 Kg
per sqm and jointed neatly with white cement paste mixed with
pigment of matching shade to full depth including cost and
conveyance of all materials like cement , sand , water , granite
slabs etc., to work site and all operational, incidental labour & lift
charges, polishing charges, cost of base coat and overheads &
contractors profit complete for finished item of work (S.S.701 &
special)
First Floor :
112 Flooring with 16 mm to 18 mm thick high polished granite stone Flooring with 16 mm to 18 mm thick Flooring with 16 mm to 18 mm thick
slabs other than black and regular colours (i.e. of shades like high polished granite stone slabs high polished granite stone slabs other
paradiso / bala flower / copper silk / laka red / lavender blue) other than black than black
with borders and design as per the pattern approved by the
Engineer-in-Charge of length not less than 2.43 mts set over
base coat of cement mortar (1:8) , 20mm thick using screened
sand over CC bed already laid or RCC roof slab including neat
grey cement slurry of honey like consistency spread @ 3.3 Kg
per sqm and jointed neatly with white cement paste mixed with
pigment of matching shade to full depth including cost and
conveyance of all materials like cement , sand , water , granite
slabs etc., to work site and all operational, incidental labour & lift
charges, polishing charges, cost of base coat and overheads &
contractors profit complete for finished item of work (S.S.701 &
special)
Second Floor :

43 Flooring with 16 mm to 18 mm thick high polished granite stone Flooring with 16 mm to 18 mm thick Flooring with 16 mm to 18 mm thick
slabs other than black and regular colours (i.e. of shades like high polished granite stone slabs high polished granite stone slabs other
paradiso / bala flower / copper silk / laka red / lavender blue) other than black than black
with borders and design as per the pattern approved by the
Engineer-in-Charge of length not less than 2.43 mts set over
base coat of cement mortar (1:8) , 20mm thick using screened
sand over CC bed already laid or RCC roof slab including neat
grey cement slurry of honey like consistency spread @ 3.3 Kg
per sqm and jointed neatly with white cement paste mixed with
pigment of matching shade to full depth including cost and
conveyance of all materials like cement , sand , water , granite
slabs etc., to work site and all operational, incidental labour & lift
charges, polishing charges, cost of base coat and overheads &
contractors profit complete for finished item of work (S.S.701 &
special)
Third Floor :
43 Flooring with 16 mm to 18 mm thick high polished granite stone Flooring with 16 mm to 18 mm thick Flooring with 16 mm to 18 mm thick
slabs other than black and regular colours (i.e. of shades like high polished granite stone slabs high polished granite stone slabs other
paradiso / bala flower / copper silk / laka red / lavender blue) other than black than black
with borders and design as per the pattern approved by the
Engineer-in-Charge of length not less than 2.43 mts set over
base coat of cement mortar (1:8) , 20mm thick using screened
sand over CC bed already laid or RCC roof slab including neat
grey cement slurry of honey like consistency spread @ 3.3 Kg
per sqm and jointed neatly with white cement paste mixed with
pigment of matching shade to full depth including cost and
conveyance of all materials like cement , sand , water , granite
slabs etc., to work site and all operational, incidental labour & lift
charges, polishing charges, cost of base coat and overheads &
contractors profit complete for finished item of work (S.S.701 &
special)
Fourth Floor :

102 Flooring with chequered Cement Concrete heavy duty tiles Flooring with chequered Cement Flooring with chequered Cement
conforming to IS: 13801 using aggregates, cement, pigments of Concrete heavy duty tiles Concrete heavy duty tiles
size 300mm x 300 mm and thickness 25 mm of any shades as
approved by Engineer - In - Charge set over base coat of
cement mortar (1:6), 12 mm thick using screened sand over CC
bed alredy laid or RCC roof slab including neat cement slurry of
honey like consistency spread @ 3.3 kgs per sqm and jointed
with neat white cement to full depth mixed with pigment of
matching shade including cost and conveyance of all materials
like cement, sand, water and tiles etc.,and overheads &
contractors profit complete for finished item of work.
Cellar :
102 Flooring with chequered Cement Concrete heavy duty tiles Flooring with chequered Cement Flooring with chequered Cement
conforming to IS: 13801 using aggregates, cement, pigments of Concrete heavy duty tiles Concrete heavy duty tiles
size 300mm x 300 mm and thickness 25 mm of any shades as
approved by Engineer - In - Charge set over base coat of
cement mortar (1:6), 12 mm thick using screened sand over CC
bed alredy laid or RCC roof slab including neat cement slurry of
honey like consistency spread @ 3.3 kgs per sqm and jointed
with neat white cement to full depth mixed with pigment of
matching shade including cost and conveyance of all materials
like cement, sand, water and tiles etc.,and overheads &
contractors profit complete for finished item of work.
Basement Floor

277 Flooring with chequered Cement Concrete heavy duty tiles Flooring with chequered Cement Flooring with chequered Cement
conforming to IS: 13801 using aggregates, cement, pigments of Concrete heavy duty tiles Concrete heavy duty tiles
size 300mm x 300 mm and thickness 25 mm of any shades as
approved by Engineer - In - Charge set over base coat of
cement mortar (1:6), 12 mm thick using screened sand over CC
bed alredy laid or RCC roof slab including neat cement slurry of
honey like consistency spread @ 3.3 kgs per sqm and jointed
with neat white cement to full depth mixed with pigment of
matching shade including cost and conveyance of all materials
like cement, sand, water and tiles etc.,and overheads &
contractors profit complete for finished item of work.
First Floor :

102 Flooring with chequered Cement Concrete heavy duty tiles Flooring with chequered Cement Flooring with chequered Cement
conforming to IS: 13801 using aggregates, cement, pigments of Concrete heavy duty tiles Concrete heavy duty tiles
size 300mm x 300 mm and thickness 25 mm of any shades as
approved by Engineer - In - Charge set over base coat of
cement mortar (1:6), 12 mm thick using screened sand over CC
bed alredy laid or RCC roof slab including neat cement slurry of
honey like consistency spread @ 3.3 kgs per sqm and jointed
with neat white cement to full depth mixed with pigment of
matching shade including cost and conveyance of all materials
like cement, sand, water and tiles etc.,and overheads &
contractors profit complete for finished item of work.
Second Floor :
104 Flooring with chequered Cement Concrete heavy duty tiles Flooring with chequered Cement Flooring with chequered Cement
conforming to IS: 13801 using aggregates, cement, pigments of Concrete heavy duty tiles Concrete heavy duty tiles
size 300mm x 300 mm and thickness 25 mm of any shades as
approved by Engineer - In - Charge set over base coat of
cement mortar (1:6), 12 mm thick using screened sand over CC
bed alredy laid or RCC roof slab including neat cement slurry of
honey like consistency spread @ 3.3 kgs per sqm and jointed
with neat white cement to full depth mixed with pigment of
matching shade including cost and conveyance of all materials
like cement, sand, water and tiles etc.,and overheads &
contractors profit complete for finished item of work.
Third Floor :

104 Flooring with chequered Cement Concrete heavy duty tiles Flooring with chequered Cement Flooring with chequered Cement
conforming to IS: 13801 using aggregates, cement, pigments of Concrete heavy duty tiles Concrete heavy duty tiles
size 300mm x 300 mm and thickness 25 mm of any shades as
approved by Engineer - In - Charge set over base coat of
cement mortar (1:6), 12 mm thick using screened sand over CC
bed alredy laid or RCC roof slab including neat cement slurry of
honey like consistency spread @ 3.3 kgs per sqm and jointed
with neat white cement to full depth mixed with pigment of
matching shade including cost and conveyance of all materials
like cement, sand, water and tiles etc.,and overheads &
contractors profit complete for finished item of work.
Fourth Floor :

298 Supply of precast concrete blocks for paving of M-40 grade and Supply of precast concrete blocks Supply of precast concrete blocks for
thickness not less than 80 mm for Medium traffic areas for paving of M-40 grade paving of M-40 grade
conforming to IS 15658:2006 in all shapes and designs as per
the manufacturer's specification including cost and conveyance
of all materials and all labour charges etc.
Cellar, Basement Floor & First Floors
1144 Vaccum dewatering cement concrete flooring 50mm thick using Vaccum dewatering cement Vaccum dewatering cement concrete
M 30 grade design mix corresponding to IS 456 with minimum concrete flooring 50mm thick flooring 50mm thick
cement content of 400 kgs per 1 cum of concrete and required
quantity of Chemical Admixtures per 1 cum of concrete using
WEIGH BATCHER / MIXER with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry in
panels as per drawing / design, laid to proper level and slope
including consolidating with power driven mechanical vibrators
(both needle & screed vibrators), dewatering by vacuum
process "Tremix" method, floated with neat cement and power
troweled to achieve smooth finishing, including MS Shuttering,
finishing, rounding of the edges, curing including cost and
conveyance of all materials like cement, coarse aggregate,
sand etc., to site, centering, shuttering, machine mixing, laying
concrete, vibrating, curing, hire charges of all tools and plants,
all other incidental and operational charges, labour charges and
all taxes etc., complete for finished item of work but excluding
cost of steel and its fabrication charges for finished item of work.
For Cellar
43 Providing 16 mm to 18 mm thick high polished leather finish Providing 16 mm to 18 mm thick Providing 16 mm to 18 mm thick high
granite stone slabs (steel grey or pearl black) with borders and high polished leather finish granite polished leather finish granite stone
design as per the pattern approved by the Engineer-in-Charge stone slabs for Treads & Risers slabs for Treads & Risers
of length not less than 2.43 mts set over base coat of cement
mortar (1:5) , 12mm thick using screened sand over CC bed
already laid or RCC roof slab including neat grey cement slurry
of honey like consistency spread @ 3.3 Kg per sqm and jointed
neatly with white cement paste mixed with pigment of matching
shade to full depth including cost and conveyance of all
materials like cement , sand , water , granite slabs etc., to work
site and all operational, incidental labour & lift charges, full
rounding the edges of treads , polishing charges, cost of base
coat and overheads & contractors profit complete for finished
item of work for treads and risers (S.S.701 & special)
Treads of 0.30m wide :
Cellar :

82 Providing 16 mm to 18 mm thick high polished leather finish Providing 16 mm to 18 mm thick Providing 16 mm to 18 mm thick high
granite stone slabs (steel grey or pearl black) with borders and high polished leather finish granite polished leather finish granite stone
design as per the pattern approved by the Engineer-in-Charge stone slabs for Treads & Risers slabs for Treads & Risers
of length not less than 2.43 mts set over base coat of cement
mortar (1:5) , 12mm thick using screened sand over CC bed
already laid or RCC roof slab including neat grey cement slurry
of honey like consistency spread @ 3.3 Kg per sqm and jointed
neatly with white cement paste mixed with pigment of matching
shade to full depth including cost and conveyance of all
materials like cement , sand , water , granite slabs etc., to work
site and all operational, incidental labour & lift charges, full
rounding the edges of treads , polishing charges, cost of base
coat and overheads & contractors profit complete for finished
item of work for treads and risers (S.S.701 & special)
Treads of 0.30m wide :
Basement Floor
77 Providing 16 mm to 18 mm thick high polished leather finish Providing 16 mm to 18 mm thick Providing 16 mm to 18 mm thick high
granite stone slabs (steel grey or pearl black) with borders and high polished leather finish granite polished leather finish granite stone
design as per the pattern approved by the Engineer-in-Charge stone slabs for Treads & Risers slabs for Treads & Risers
of length not less than 2.43 mts set over base coat of cement
mortar (1:5) , 12mm thick using screened sand over CC bed
already laid or RCC roof slab including neat grey cement slurry
of honey like consistency spread @ 3.3 Kg per sqm and jointed
neatly with white cement paste mixed with pigment of matching
shade to full depth including cost and conveyance of all
materials like cement , sand , water , granite slabs etc., to work
site and all operational, incidental labour & lift charges, full
rounding the edges of treads , polishing charges, cost of base
coat and overheads & contractors profit complete for finished
item of work for treads and risers (S.S.701 & special)
Treads of 0.30m wide :
First Floor :

82 Providing 16 mm to 18 mm thick high polished leather finish Providing 16 mm to 18 mm thick Providing 16 mm to 18 mm thick high
granite stone slabs (steel grey or pearl black) with borders and high polished leather finish granite polished leather finish granite stone
design as per the pattern approved by the Engineer-in-Charge stone slabs for Treads & Risers slabs for Treads & Risers
of length not less than 2.43 mts set over base coat of cement
mortar (1:5) , 12mm thick using screened sand over CC bed
already laid or RCC roof slab including neat grey cement slurry
of honey like consistency spread @ 3.3 Kg per sqm and jointed
neatly with white cement paste mixed with pigment of matching
shade to full depth including cost and conveyance of all
materials like cement , sand , water , granite slabs etc., to work
site and all operational, incidental labour & lift charges, full
rounding the edges of treads , polishing charges, cost of base
coat and overheads & contractors profit complete for finished
item of work for treads and risers (S.S.701 & special)
Treads of 0.30m wide :
Second Floor :
78 Providing 16 mm to 18 mm thick high polished leather finish Providing 16 mm to 18 mm thick Providing 16 mm to 18 mm thick high
granite stone slabs (steel grey or pearl black) with borders and high polished leather finish granite polished leather finish granite stone
design as per the pattern approved by the Engineer-in-Charge stone slabs for Treads & Risers slabs for Treads & Risers
of length not less than 2.43 mts set over base coat of cement
mortar (1:5) , 12mm thick using screened sand over CC bed
already laid or RCC roof slab including neat grey cement slurry
of honey like consistency spread @ 3.3 Kg per sqm and jointed
neatly with white cement paste mixed with pigment of matching
shade to full depth including cost and conveyance of all
materials like cement , sand , water , granite slabs etc., to work
site and all operational, incidental labour & lift charges, full
rounding the edges of treads , polishing charges, cost of base
coat and overheads & contractors profit complete for finished
item of work for treads and risers (S.S.701 & special)
Treads of 0.30m wide :
Third Floor :

66 Providing 16 mm to 18 mm thick high polished leather finish Providing 16 mm to 18 mm thick Providing 16 mm to 18 mm thick high
granite stone slabs (steel grey or pearl black) with borders and high polished leather finish granite polished leather finish granite stone
design as per the pattern approved by the Engineer-in-Charge stone slabs for Treads & Risers slabs for Treads & Risers
of length not less than 2.43 mts set over base coat of cement
mortar (1:5) , 12mm thick using screened sand over CC bed
already laid or RCC roof slab including neat grey cement slurry
of honey like consistency spread @ 3.3 Kg per sqm and jointed
neatly with white cement paste mixed with pigment of matching
shade to full depth including cost and conveyance of all
materials like cement , sand , water , granite slabs etc., to work
site and all operational, incidental labour & lift charges, full
rounding the edges of treads , polishing charges, cost of base
coat and overheads & contractors profit complete for finished
item of work for treads and risers (S.S.701 & special)
Treads of 0.30m wide :
Fourth Floor :
24 Providing 16 mm to 18 mm thick high polished leather finish Providing 16 mm to 18 mm thick Providing 16 mm to 18 mm thick high
granite stone slabs (steel grey or pearl black) with borders and high polished leather finish granite polished leather finish granite stone
design as per the pattern approved by the Engineer-in-Charge stone slabs for Treads & Risers slabs for Treads & Risers
of length not less than 2.43 mts set over base coat of cement
mortar (1:5) , 12mm thick using screened sand over CC bed
already laid or RCC roof slab including neat grey cement slurry
of honey like consistency spread @ 3.3 Kg per sqm and jointed
neatly with white cement paste mixed with pigment of matching
shade to full depth including cost and conveyance of all
materials like cement , sand , water , granite slabs etc., to work
site and all operational, incidental labour & lift charges, full
rounding the edges of treads , polishing charges, cost of base
coat and overheads & contractors profit complete for finished
item of work for treads and risers (S.S.701 & special)
Risers of 0.15m height :
Cellar :

44 Providing 16 mm to 18 mm thick high polished leather finish Providing 16 mm to 18 mm thick Providing 16 mm to 18 mm thick high
granite stone slabs (steel grey or pearl black) with borders and high polished leather finish granite polished leather finish granite stone
design as per the pattern approved by the Engineer-in-Charge stone slabs for Treads & Risers slabs for Treads & Risers
of length not less than 2.43 mts set over base coat of cement
mortar (1:5) , 12mm thick using screened sand over CC bed
already laid or RCC roof slab including neat grey cement slurry
of honey like consistency spread @ 3.3 Kg per sqm and jointed
neatly with white cement paste mixed with pigment of matching
shade to full depth including cost and conveyance of all
materials like cement , sand , water , granite slabs etc., to work
site and all operational, incidental labour & lift charges, full
rounding the edges of treads , polishing charges, cost of base
coat and overheads & contractors profit complete for finished
item of work for treads and risers (S.S.701 & special)
Risers of 0.15m height :
Basement Floor
43 Providing 16 mm to 18 mm thick high polished leather finish Providing 16 mm to 18 mm thick Providing 16 mm to 18 mm thick high
granite stone slabs (steel grey or pearl black) with borders and high polished leather finish granite polished leather finish granite stone
design as per the pattern approved by the Engineer-in-Charge stone slabs for Treads & Risers slabs for Treads & Risers
of length not less than 2.43 mts set over base coat of cement
mortar (1:5) , 12mm thick using screened sand over CC bed
already laid or RCC roof slab including neat grey cement slurry
of honey like consistency spread @ 3.3 Kg per sqm and jointed
neatly with white cement paste mixed with pigment of matching
shade to full depth including cost and conveyance of all
materials like cement , sand , water , granite slabs etc., to work
site and all operational, incidental labour & lift charges, full
rounding the edges of treads , polishing charges, cost of base
coat and overheads & contractors profit complete for finished
item of work for treads and risers (S.S.701 & special)
Risers of 0.15m height :
First Floor :

44 Providing 16 mm to 18 mm thick high polished leather finish Providing 16 mm to 18 mm thick Providing 16 mm to 18 mm thick high
granite stone slabs (steel grey or pearl black) with borders and high polished leather finish granite polished leather finish granite stone
design as per the pattern approved by the Engineer-in-Charge stone slabs for Treads & Risers slabs for Treads & Risers
of length not less than 2.43 mts set over base coat of cement
mortar (1:5) , 12mm thick using screened sand over CC bed
already laid or RCC roof slab including neat grey cement slurry
of honey like consistency spread @ 3.3 Kg per sqm and jointed
neatly with white cement paste mixed with pigment of matching
shade to full depth including cost and conveyance of all
materials like cement , sand , water , granite slabs etc., to work
site and all operational, incidental labour & lift charges, full
rounding the edges of treads , polishing charges, cost of base
coat and overheads & contractors profit complete for finished
item of work for treads and risers (S.S.701 & special)
Risers of 0.15m height :
Second Floor :
42 Providing 16 mm to 18 mm thick high polished leather finish Providing 16 mm to 18 mm thick Providing 16 mm to 18 mm thick high
granite stone slabs (steel grey or pearl black) with borders and high polished leather finish granite polished leather finish granite stone
design as per the pattern approved by the Engineer-in-Charge stone slabs for Treads & Risers slabs for Treads & Risers
of length not less than 2.43 mts set over base coat of cement
mortar (1:5) , 12mm thick using screened sand over CC bed
already laid or RCC roof slab including neat grey cement slurry
of honey like consistency spread @ 3.3 Kg per sqm and jointed
neatly with white cement paste mixed with pigment of matching
shade to full depth including cost and conveyance of all
materials like cement , sand , water , granite slabs etc., to work
site and all operational, incidental labour & lift charges, full
rounding the edges of treads , polishing charges, cost of base
coat and overheads & contractors profit complete for finished
item of work for treads and risers (S.S.701 & special)
Risers of 0.15m height :
Third Floor :

36 Providing 16 mm to 18 mm thick high polished leather finish Providing 16 mm to 18 mm thick Providing 16 mm to 18 mm thick high
granite stone slabs (steel grey or pearl black) with borders and high polished leather finish granite polished leather finish granite stone
design as per the pattern approved by the Engineer-in-Charge stone slabs for Treads & Risers slabs for Treads & Risers
of length not less than 2.43 mts set over base coat of cement
mortar (1:5) , 12mm thick using screened sand over CC bed
already laid or RCC roof slab including neat grey cement slurry
of honey like consistency spread @ 3.3 Kg per sqm and jointed
neatly with white cement paste mixed with pigment of matching
shade to full depth including cost and conveyance of all
materials like cement , sand , water , granite slabs etc., to work
site and all operational, incidental labour & lift charges, full
rounding the edges of treads , polishing charges, cost of base
coat and overheads & contractors profit complete for finished
item of work for treads and risers (S.S.701 & special)
Risers of 0.15m height :
Fourth Floor :
9 Flooring with 16 mm to 18 mm thick high polished granite Flooring with 16 mm to 18 mm Flooring with 16 mm to 18 mm thick
stone slabs black colour as approved by the Engineer-in- thick high polished granite stone high polished granite stone slabs black
Charge of length not less than 2.43 mts set over base coat of slabs black
cement mortar (1:8) , 20mm thick using screened sand over CC
bed already laid or RCC roof slab including neat grey cement
slurry of honey like consistency spread @ 3.3 Kg per sqm and
jointed neatly with white cement paste mixed with pigment of
matching shade to full depth including cost and conveyance of
all materials like cement , sand , water , granite slabs etc., to
work site and all operational, incidental labour & lift charges,
half rounding the edge , polishing charges, cost of base coat
and overheads & contractors profit complete for finished item of
work for platforms (S.S.701 & special)
Cellar :

72 Flooring with 16 mm to 18 mm thick high polished granite Flooring with 16 mm to 18 mm Flooring with 16 mm to 18 mm thick
stone slabs black colour as approved by the Engineer-in- thick high polished granite stone high polished granite stone slabs black
Charge of length not less than 2.43 mts set over base coat of slabs black
cement mortar (1:8) , 20mm thick using screened sand over CC
bed already laid or RCC roof slab including neat grey cement
slurry of honey like consistency spread @ 3.3 Kg per sqm and
jointed neatly with white cement paste mixed with pigment of
matching shade to full depth including cost and conveyance of
all materials like cement , sand , water , granite slabs etc., to
work site and all operational, incidental labour & lift charges,
half rounding the edge , polishing charges, cost of base coat
and overheads & contractors profit complete for finished item of
work for platforms (S.S.701 & special)
Basement Floor
25 Flooring with 16 mm to 18 mm thick high polished granite Flooring with 16 mm to 18 mm Flooring with 16 mm to 18 mm thick
stone slabs black colour as approved by the Engineer-in- thick high polished granite stone high polished granite stone slabs black
Charge of length not less than 2.43 mts set over base coat of slabs black
cement mortar (1:8) , 20mm thick using screened sand over CC
bed already laid or RCC roof slab including neat grey cement
slurry of honey like consistency spread @ 3.3 Kg per sqm and
jointed neatly with white cement paste mixed with pigment of
matching shade to full depth including cost and conveyance of
all materials like cement , sand , water , granite slabs etc., to
work site and all operational, incidental labour & lift charges,
half rounding the edge , polishing charges, cost of base coat
and overheads & contractors profit complete for finished item of
work for platforms (S.S.701 & special)
First Floor :

27 Flooring with 16 mm to 18 mm thick high polished granite Flooring with 16 mm to 18 mm Flooring with 16 mm to 18 mm thick
stone slabs black colour as approved by the Engineer-in- thick high polished granite stone high polished granite stone slabs black
Charge of length not less than 2.43 mts set over base coat of slabs black
cement mortar (1:8) , 20mm thick using screened sand over CC
bed already laid or RCC roof slab including neat grey cement
slurry of honey like consistency spread @ 3.3 Kg per sqm and
jointed neatly with white cement paste mixed with pigment of
matching shade to full depth including cost and conveyance of
all materials like cement , sand , water , granite slabs etc., to
work site and all operational, incidental labour & lift charges,
half rounding the edge , polishing charges, cost of base coat
and overheads & contractors profit complete for finished item of
work for platforms (S.S.701 & special)
Second Floor :
14 Flooring with 16 mm to 18 mm thick high polished granite Flooring with 16 mm to 18 mm Flooring with 16 mm to 18 mm thick
stone slabs black colour as approved by the Engineer-in- thick high polished granite stone high polished granite stone slabs black
Charge of length not less than 2.43 mts set over base coat of slabs black
cement mortar (1:8) , 20mm thick using screened sand over CC
bed already laid or RCC roof slab including neat grey cement
slurry of honey like consistency spread @ 3.3 Kg per sqm and
jointed neatly with white cement paste mixed with pigment of
matching shade to full depth including cost and conveyance of
all materials like cement , sand , water , granite slabs etc., to
work site and all operational, incidental labour & lift charges,
half rounding the edge , polishing charges, cost of base coat
and overheads & contractors profit complete for finished item of
work for platforms (S.S.701 & special)
Third Floor :

161 Flooring with 16 mm to 18 mm thick high polished granite Flooring with 16 mm to 18 mm Flooring with 16 mm to 18 mm thick
stone slabs black colour as approved by the Engineer-in- thick high polished granite stone high polished granite stone slabs black
Charge of length not less than 2.43 mts set over base coat of slabs black
cement mortar (1:8) , 20mm thick using screened sand over CC
bed already laid or RCC roof slab including neat grey cement
slurry of honey like consistency spread @ 3.3 Kg per sqm and
jointed neatly with white cement paste mixed with pigment of
matching shade to full depth including cost and conveyance of
all materials like cement , sand , water , granite slabs etc., to
work site and all operational, incidental labour & lift charges,
half rounding the edge , polishing charges, cost of base coat
and overheads & contractors profit complete for finished item of
work for platforms (S.S.701 & special)
Fourth Floor :
11 Providing window sills with 16 mm to 18 mm thick high polished Providing window sills with 16 mm to Providing window sills with 16 mm to
granite stone slabs black colour as approved by the Engineer- 18 mm thick high polished granite 18 mm thick high polished granite
in-Charge set over base coat of cement mortar (1:8) , 20mm stone slabs black stone slabs black
thick using screened sand over CC bed already laid including
neat grey cement slurry of honey like consistency spread @ 3.3
Kg per sqm and jointed neatly with white cement paste mixed
with pigment of matching shade to full depth including cost and
conveyance of all materials like cement , sand , water , granite
slabs etc., to work site and all operational, incidental labour & lift
charges, half rounding the edge , polishing charges, cost of
base coat and overheads & contractors profit complete for
finished item of work (S.S.701 & special)
Cellar :

31 Providing window sills with 16 mm to 18 mm thick high polished Providing window sills with 16 mm to Providing window sills with 16 mm to
granite stone slabs black colour as approved by the Engineer- 18 mm thick high polished granite 18 mm thick high polished granite
in-Charge set over base coat of cement mortar (1:8) , 20mm stone slabs black stone slabs black
thick using screened sand over CC bed already laid including
neat grey cement slurry of honey like consistency spread @ 3.3
Kg per sqm and jointed neatly with white cement paste mixed
with pigment of matching shade to full depth including cost and
conveyance of all materials like cement , sand , water , granite
slabs etc., to work site and all operational, incidental labour & lift
charges, half rounding the edge , polishing charges, cost of
base coat and overheads & contractors profit complete for
finished item of work (S.S.701 & special)
Basement Floor
38 Providing window sills with 16 mm to 18 mm thick high polished Providing window sills with 16 mm to Providing window sills with 16 mm to
granite stone slabs black colour as approved by the Engineer- 18 mm thick high polished granite 18 mm thick high polished granite
in-Charge set over base coat of cement mortar (1:8) , 20mm stone slabs black stone slabs black
thick using screened sand over CC bed already laid including
neat grey cement slurry of honey like consistency spread @ 3.3
Kg per sqm and jointed neatly with white cement paste mixed
with pigment of matching shade to full depth including cost and
conveyance of all materials like cement , sand , water , granite
slabs etc., to work site and all operational, incidental labour & lift
charges, half rounding the edge , polishing charges, cost of
base coat and overheads & contractors profit complete for
finished item of work (S.S.701 & special)
First Floor :

75 Providing window sills with 16 mm to 18 mm thick high polished Providing window sills with 16 mm to Providing window sills with 16 mm to
granite stone slabs black colour as approved by the Engineer- 18 mm thick high polished granite 18 mm thick high polished granite
in-Charge set over base coat of cement mortar (1:8) , 20mm stone slabs black stone slabs black
thick using screened sand over CC bed already laid including
neat grey cement slurry of honey like consistency spread @ 3.3
Kg per sqm and jointed neatly with white cement paste mixed
with pigment of matching shade to full depth including cost and
conveyance of all materials like cement , sand , water , granite
slabs etc., to work site and all operational, incidental labour & lift
charges, half rounding the edge , polishing charges, cost of
base coat and overheads & contractors profit complete for
finished item of work (S.S.701 & special)
Second Floor :
40 Providing window sills with 16 mm to 18 mm thick high polished Providing window sills with 16 mm to Providing window sills with 16 mm to
granite stone slabs black colour as approved by the Engineer- 18 mm thick high polished granite 18 mm thick high polished granite
in-Charge set over base coat of cement mortar (1:8) , 20mm stone slabs black stone slabs black
thick using screened sand over CC bed already laid including
neat grey cement slurry of honey like consistency spread @ 3.3
Kg per sqm and jointed neatly with white cement paste mixed
with pigment of matching shade to full depth including cost and
conveyance of all materials like cement , sand , water , granite
slabs etc., to work site and all operational, incidental labour & lift
charges, half rounding the edge , polishing charges, cost of
base coat and overheads & contractors profit complete for
finished item of work (S.S.701 & special)
Third Floor :

66 Providing window sills with 16 mm to 18 mm thick high polished Providing window sills with 16 mm to Providing window sills with 16 mm to
granite stone slabs black colour as approved by the Engineer- 18 mm thick high polished granite 18 mm thick high polished granite
in-Charge set over base coat of cement mortar (1:8) , 20mm stone slabs black stone slabs black
thick using screened sand over CC bed already laid including
neat grey cement slurry of honey like consistency spread @ 3.3
Kg per sqm and jointed neatly with white cement paste mixed
with pigment of matching shade to full depth including cost and
conveyance of all materials like cement , sand , water , granite
slabs etc., to work site and all operational, incidental labour & lift
charges, half rounding the edge , polishing charges, cost of
base coat and overheads & contractors profit complete for
finished item of work (S.S.701 & special)
Fourth Floor :
314 Providing skirting 10 cm height with Double charged / multi Providing skirting 10 cm height with Providing skirting 10 cm height with
charged stain free full body porcelain vitrified tiles with double Double charged / multi charged Double charged / multi charged stain
layer pigment of Size 600 x 600 mm and thickness between 8- stain free full body porcelain vitrified free full body porcelain vitrified tiles
10 mm of any colour and finish in all shades and designs, length tiles
equal to flooring tiles, flushed to wall surface to set over base
coat of CM(1:5) 12 mm thick using screened sand with cement
slurry of honey like consistency spread at the rate of 3.30 kgs
per sqm and jointing with white cement paste mixed with
pigment of matching shade to full depth, including cost of all
materials like tiles, cement, sand and water etc.,and overheads
& contractors profit complete for finished item of work.(APSS
No.701 &707)
Cellar :

1488 Providing skirting 10 cm height with Double charged / multi Providing skirting 10 cm height with Providing skirting 10 cm height with
charged stain free full body porcelain vitrified tiles with double Double charged / multi charged Double charged / multi charged stain
layer pigment of Size 600 x 600 mm and thickness between 8- stain free full body porcelain vitrified free full body porcelain vitrified tiles
10 mm of any colour and finish in all shades and designs, length tiles
equal to flooring tiles, flushed to wall surface to set over base
coat of CM(1:5) 12 mm thick using screened sand with cement
slurry of honey like consistency spread at the rate of 3.30 kgs
per sqm and jointing with white cement paste mixed with
pigment of matching shade to full depth, including cost of all
materials like tiles, cement, sand and water etc.,and overheads
& contractors profit complete for finished item of work.(APSS
No.701 &707)
Basement Floor
912 Providing skirting 10 cm height with Double charged / multi Providing skirting 10 cm height with Providing skirting 10 cm height with
charged stain free full body porcelain vitrified tiles with double Double charged / multi charged Double charged / multi charged stain
layer pigment of Size 600 x 600 mm and thickness between 8- stain free full body porcelain vitrified free full body porcelain vitrified tiles
10 mm of any colour and finish in all shades and designs, length tiles
equal to flooring tiles, flushed to wall surface to set over base
coat of CM(1:5) 12 mm thick using screened sand with cement
slurry of honey like consistency spread at the rate of 3.30 kgs
per sqm and jointing with white cement paste mixed with
pigment of matching shade to full depth, including cost of all
materials like tiles, cement, sand and water etc.,and overheads
& contractors profit complete for finished item of work.(APSS
No.701 &707)
First Floor :

1110 Providing skirting 10 cm height with Double charged / multi Providing skirting 10 cm height with Providing skirting 10 cm height with
charged stain free full body porcelain vitrified tiles with double Double charged / multi charged Double charged / multi charged stain
layer pigment of Size 600 x 600 mm and thickness between 8- stain free full body porcelain vitrified free full body porcelain vitrified tiles
10 mm of any colour and finish in all shades and designs, length tiles
equal to flooring tiles, flushed to wall surface to set over base
coat of CM(1:5) 12 mm thick using screened sand with cement
slurry of honey like consistency spread at the rate of 3.30 kgs
per sqm and jointing with white cement paste mixed with
pigment of matching shade to full depth, including cost of all
materials like tiles, cement, sand and water etc.,and overheads
& contractors profit complete for finished item of work.(APSS
No.701 &707)
Second Floor :
1191 Providing skirting 10 cm height with Double charged / multi Providing skirting 10 cm height with Providing skirting 10 cm height with
charged stain free full body porcelain vitrified tiles with double Double charged / multi charged Double charged / multi charged stain
layer pigment of Size 600 x 600 mm and thickness between 8- stain free full body porcelain vitrified free full body porcelain vitrified tiles
10 mm of any colour and finish in all shades and designs, length tiles
equal to flooring tiles, flushed to wall surface to set over base
coat of CM(1:5) 12 mm thick using screened sand with cement
slurry of honey like consistency spread at the rate of 3.30 kgs
per sqm and jointing with white cement paste mixed with
pigment of matching shade to full depth, including cost of all
materials like tiles, cement, sand and water etc.,and overheads
& contractors profit complete for finished item of work.(APSS
No.701 &707)
Third Floor :

783 Providing skirting 10 cm height with Double charged / multi Providing skirting 10 cm height with Providing skirting 10 cm height with
charged stain free full body porcelain vitrified tiles with double Double charged / multi charged Double charged / multi charged stain
layer pigment of Size 600 x 600 mm and thickness between 8- stain free full body porcelain vitrified free full body porcelain vitrified tiles
10 mm of any colour and finish in all shades and designs, length tiles
equal to flooring tiles, flushed to wall surface to set over base
coat of CM(1:5) 12 mm thick using screened sand with cement
slurry of honey like consistency spread at the rate of 3.30 kgs
per sqm and jointing with white cement paste mixed with
pigment of matching shade to full depth, including cost of all
materials like tiles, cement, sand and water etc.,and overheads
& contractors profit complete for finished item of work.(APSS
No.701 &707)
Fourth Floor :

120 Providing skirting to internal walls 10 cm height with High Providing skirting to internal walls 10 Providing skirting to internal walls 10
Polished Granite 16 mm to 18 mm thick up to 8'-00 (2.43 M) cm height with High Polished cm height with High Polished Granite
other than black and regular colours, length equal to flooring Granite 16 mm to 18 mm thick up to 16 mm to 18 mm thick up to 8'-00
slabs set over base coat of CM(1:5) 12 mm thick using 8'-00
screened sand with cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and jointing with white
cement paste mixed with pigment of matching shade to full
depth, including cost of all materials like tiles, cement, sand and
water etc., and overheads & contractors profit complete for
finished item of work.
Cellar :
121 Providing skirting to internal walls 10 cm height with High Providing skirting to internal walls 10 Providing skirting to internal walls 10
Polished Granite 16 mm to 18 mm thick up to 8'-00 (2.43 M) cm height with High Polished cm height with High Polished Granite
other than black and regular colours, length equal to flooring Granite 16 mm to 18 mm thick up to 16 mm to 18 mm thick up to 8'-00
slabs set over base coat of CM(1:5) 12 mm thick using 8'-00
screened sand with cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and jointing with white
cement paste mixed with pigment of matching shade to full
depth, including cost of all materials like tiles, cement, sand and
water etc., and overheads & contractors profit complete for
finished item of work.
Basement Floor

78 Providing skirting to internal walls 10 cm height with High Providing skirting to internal walls 10 Providing skirting to internal walls 10
Polished Granite 16 mm to 18 mm thick up to 8'-00 (2.43 M) cm height with High Polished cm height with High Polished Granite
other than black and regular colours, length equal to flooring Granite 16 mm to 18 mm thick up to 16 mm to 18 mm thick up to 8'-00
slabs set over base coat of CM(1:5) 12 mm thick using 8'-00
screened sand with cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and jointing with white
cement paste mixed with pigment of matching shade to full
depth, including cost of all materials like tiles, cement, sand and
water etc., and overheads & contractors profit complete for
finished item of work.
First Floor :

121 Providing skirting to internal walls 10 cm height with High Providing skirting to internal walls 10 Providing skirting to internal walls 10
Polished Granite 16 mm to 18 mm thick up to 8'-00 (2.43 M) cm height with High Polished cm height with High Polished Granite
other than black and regular colours, length equal to flooring Granite 16 mm to 18 mm thick up to 16 mm to 18 mm thick up to 8'-00
slabs set over base coat of CM(1:5) 12 mm thick using 8'-00
screened sand with cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and jointing with white
cement paste mixed with pigment of matching shade to full
depth, including cost of all materials like tiles, cement, sand and
water etc., and overheads & contractors profit complete for
finished item of work.
Second Floor :
78 Providing skirting to internal walls 10 cm height with High Providing skirting to internal walls 10 Providing skirting to internal walls 10
Polished Granite 16 mm to 18 mm thick up to 8'-00 (2.43 M) cm height with High Polished cm height with High Polished Granite
other than black and regular colours, length equal to flooring Granite 16 mm to 18 mm thick up to 16 mm to 18 mm thick up to 8'-00
slabs set over base coat of CM(1:5) 12 mm thick using 8'-00
screened sand with cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and jointing with white
cement paste mixed with pigment of matching shade to full
depth, including cost of all materials like tiles, cement, sand and
water etc., and overheads & contractors profit complete for
finished item of work.
Third Floor :

78 Providing skirting to internal walls 10 cm height with High Providing skirting to internal walls 10 Providing skirting to internal walls 10
Polished Granite 16 mm to 18 mm thick up to 8'-00 (2.43 M) cm height with High Polished cm height with High Polished Granite
other than black and regular colours, length equal to flooring Granite 16 mm to 18 mm thick up to 16 mm to 18 mm thick up to 8'-00
slabs set over base coat of CM(1:5) 12 mm thick using 8'-00
screened sand with cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and jointing with white
cement paste mixed with pigment of matching shade to full
depth, including cost of all materials like tiles, cement, sand and
water etc., and overheads & contractors profit complete for
finished item of work.
Fourth Floor :

233 Providing dadooing with glazed white full body ceramic wall tiles Providing dadooing with glazed Providing dadooing with glazed white
of size 200mm x 300 mm / 245 mm x 325 mm and thickness 6 white full body ceramic wall tiles of full body ceramic wall tiles of size
mm 1st quality conforming to IS:13711, IS:13712, IS:13630 size 200mm x 300 mm / 245 mm x 200mm x 300 mm / 245 mm x 325 mm
(Parts 1 to 15) of any colour and finish in all shades and designs 325 mm
with borders as approved by Engineer-in-Charge flushed to
wall surface set over base coat of CM(1:5) 12 mm thick using
screened sand with cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and jointing with white
cement paste mixed with pigment of matching shade to full
depth, including cost of all materials like tiles, cement, sand and
water etc., and overheads & contractors profit complete for
finished item of work.
Cellar :
525 Providing dadooing with glazed white full body ceramic wall tiles Providing dadooing with glazed Providing dadooing with glazed white
of size 200mm x 300 mm / 245 mm x 325 mm and thickness 6 white full body ceramic wall tiles of full body ceramic wall tiles of size
mm 1st quality conforming to IS:13711, IS:13712, IS:13630 size 200mm x 300 mm / 245 mm x 200mm x 300 mm / 245 mm x 325 mm
(Parts 1 to 15) of any colour and finish in all shades and designs 325 mm
with borders as approved by Engineer-in-Charge flushed to
wall surface set over base coat of CM(1:5) 12 mm thick using
screened sand with cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and jointing with white
cement paste mixed with pigment of matching shade to full
depth, including cost of all materials like tiles, cement, sand and
water etc., and overheads & contractors profit complete for
finished item of work.
Basement Floor

993 Providing dadooing with glazed white full body ceramic wall tiles Providing dadooing with glazed Providing dadooing with glazed white
of size 200mm x 300 mm / 245 mm x 325 mm and thickness 6 white full body ceramic wall tiles of full body ceramic wall tiles of size
mm 1st quality conforming to IS:13711, IS:13712, IS:13630 size 200mm x 300 mm / 245 mm x 200mm x 300 mm / 245 mm x 325 mm
(Parts 1 to 15) of any colour and finish in all shades and designs 325 mm
with borders as approved by Engineer-in-Charge flushed to
wall surface set over base coat of CM(1:5) 12 mm thick using
screened sand with cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and jointing with white
cement paste mixed with pigment of matching shade to full
depth, including cost of all materials like tiles, cement, sand and
water etc., and overheads & contractors profit complete for
finished item of work.
First Floor :
772 Providing dadooing with glazed white full body ceramic wall tiles Providing dadooing with glazed Providing dadooing with glazed white
of size 200mm x 300 mm / 245 mm x 325 mm and thickness 6 white full body ceramic wall tiles of full body ceramic wall tiles of size
mm 1st quality conforming to IS:13711, IS:13712, IS:13630 size 200mm x 300 mm / 245 mm x 200mm x 300 mm / 245 mm x 325 mm
(Parts 1 to 15) of any colour and finish in all shades and designs 325 mm
with borders as approved by Engineer-in-Charge flushed to
wall surface set over base coat of CM(1:5) 12 mm thick using
screened sand with cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and jointing with white
cement paste mixed with pigment of matching shade to full
depth, including cost of all materials like tiles, cement, sand and
water etc., and overheads & contractors profit complete for
finished item of work.
Second Floor :

454 Providing dadooing with glazed white full body ceramic wall tiles Providing dadooing with glazed Providing dadooing with glazed white
of size 200mm x 300 mm / 245 mm x 325 mm and thickness 6 white full body ceramic wall tiles of full body ceramic wall tiles of size
mm 1st quality conforming to IS:13711, IS:13712, IS:13630 size 200mm x 300 mm / 245 mm x 200mm x 300 mm / 245 mm x 325 mm
(Parts 1 to 15) of any colour and finish in all shades and designs 325 mm
with borders as approved by Engineer-in-Charge flushed to
wall surface set over base coat of CM(1:5) 12 mm thick using
screened sand with cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and jointing with white
cement paste mixed with pigment of matching shade to full
depth, including cost of all materials like tiles, cement, sand and
water etc., and overheads & contractors profit complete for
finished item of work.
Third Floor :
542 Providing dadooing with glazed white full body ceramic wall tiles Providing dadooing with glazed Providing dadooing with glazed white
of size 200mm x 300 mm / 245 mm x 325 mm and thickness 6 white full body ceramic wall tiles of full body ceramic wall tiles of size
mm 1st quality conforming to IS:13711, IS:13712, IS:13630 size 200mm x 300 mm / 245 mm x 200mm x 300 mm / 245 mm x 325 mm
(Parts 1 to 15) of any colour and finish in all shades and designs 325 mm
with borders as approved by Engineer-in-Charge flushed to
wall surface set over base coat of CM(1:5) 12 mm thick using
screened sand with cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and jointing with white
cement paste mixed with pigment of matching shade to full
depth, including cost of all materials like tiles, cement, sand and
water etc., and overheads & contractors profit complete for
finished item of work.
Fourth Floor :

6 Providing dadooing with glazed full body porcelain wall tiles of Providing dadooing with glazed full Providing dadooing with glazed full
size 300mm x 600 mm with any type of design texture such as body porcelain wall tiles of size body porcelain wall tiles of size 300mm
marble finish, wooden, bamboo, stone finishes etc., scratch 300mm x 600 mm x 600 mm
less, stain free and thickness between 6-8 mm 1st quality
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of
any colour and finish in all shades and designs with borders
and design as per the approved pattern as approved by
Engineer-in-Charge flushed to wall surface set over base coat
of CM(1:5) 12 mm thick using screened sand with cement slurry
of honey like consistency spread at the rate of 3.30 kgs per sqm
and jointing with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials like
tiles, cement, sand and water etc., and overheads & contractors
profit complete for finished item of work.
Cellar :
559 Providing dadooing with glazed full body porcelain wall tiles of Providing dadooing with glazed full Providing dadooing with glazed full
size 300mm x 600 mm with any type of design texture such as body porcelain wall tiles of size body porcelain wall tiles of size 300mm
marble finish, wooden, bamboo, stone finishes etc., scratch 300mm x 600 mm x 600 mm
less, stain free and thickness between 6-8 mm 1st quality
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of
any colour and finish in all shades and designs with borders
and design as per the approved pattern as approved by
Engineer-in-Charge flushed to wall surface set over base coat
of CM(1:5) 12 mm thick using screened sand with cement slurry
of honey like consistency spread at the rate of 3.30 kgs per sqm
and jointing with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials like
tiles, cement, sand and water etc., and overheads & contractors
profit complete for finished item of work.
Basement Floor

784 Providing dadooing with glazed full body porcelain wall tiles of Providing dadooing with glazed full Providing dadooing with glazed full
size 300mm x 600 mm with any type of design texture such as body porcelain wall tiles of size body porcelain wall tiles of size 300mm
marble finish, wooden, bamboo, stone finishes etc., scratch 300mm x 600 mm x 600 mm
less, stain free and thickness between 6-8 mm 1st quality
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of
any colour and finish in all shades and designs with borders
and design as per the approved pattern as approved by
Engineer-in-Charge flushed to wall surface set over base coat
of CM(1:5) 12 mm thick using screened sand with cement slurry
of honey like consistency spread at the rate of 3.30 kgs per sqm
and jointing with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials like
tiles, cement, sand and water etc., and overheads & contractors
profit complete for finished item of work.
First Floor :
1086 Providing dadooing with glazed full body porcelain wall tiles of Providing dadooing with glazed full Providing dadooing with glazed full
size 300mm x 600 mm with any type of design texture such as body porcelain wall tiles of size body porcelain wall tiles of size 300mm
marble finish, wooden, bamboo, stone finishes etc., scratch 300mm x 600 mm x 600 mm
less, stain free and thickness between 6-8 mm 1st quality
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of
any colour and finish in all shades and designs with borders
and design as per the approved pattern as approved by
Engineer-in-Charge flushed to wall surface set over base coat
of CM(1:5) 12 mm thick using screened sand with cement slurry
of honey like consistency spread at the rate of 3.30 kgs per sqm
and jointing with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials like
tiles, cement, sand and water etc., and overheads & contractors
profit complete for finished item of work.
Second Floor :

1341 Providing dadooing with glazed full body porcelain wall tiles of Providing dadooing with glazed full Providing dadooing with glazed full
size 300mm x 600 mm with any type of design texture such as body porcelain wall tiles of size body porcelain wall tiles of size 300mm
marble finish, wooden, bamboo, stone finishes etc., scratch 300mm x 600 mm x 600 mm
less, stain free and thickness between 6-8 mm 1st quality
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of
any colour and finish in all shades and designs with borders
and design as per the approved pattern as approved by
Engineer-in-Charge flushed to wall surface set over base coat
of CM(1:5) 12 mm thick using screened sand with cement slurry
of honey like consistency spread at the rate of 3.30 kgs per sqm
and jointing with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials like
tiles, cement, sand and water etc., and overheads & contractors
profit complete for finished item of work.
Third Floor :
1578 Providing dadooing with glazed full body porcelain wall tiles of Providing dadooing with glazed full Providing dadooing with glazed full
size 300mm x 600 mm with any type of design texture such as body porcelain wall tiles of size body porcelain wall tiles of size 300mm
marble finish, wooden, bamboo, stone finishes etc., scratch 300mm x 600 mm x 600 mm
less, stain free and thickness between 6-8 mm 1st quality
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of
any colour and finish in all shades and designs with borders
and design as per the approved pattern as approved by
Engineer-in-Charge flushed to wall surface set over base coat
of CM(1:5) 12 mm thick using screened sand with cement slurry
of honey like consistency spread at the rate of 3.30 kgs per sqm
and jointing with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials like
tiles, cement, sand and water etc., and overheads & contractors
profit complete for finished item of work.
Fourth Floor :

12 Providing cladding to walls with High Polished Granite 16 mm Providing cladding to walls with High Providing cladding to walls with High
to 18 mm thick up to 8'-00 (2.43 M) other than black and regular Polished Granite 16 mm to 18 mm Polished Granite 16 mm to 18 mm
colours, length equal to flooring slabs set over base coat of thick up to 8'-00 (2.43 M) other than thick up to 8'-00 (2.43 M) other than
CM(1:5) 12 mm thick using screened sand with cement slurry of black black
honey like consistency spread at the rate of 3.30 kgs per sqm
and jointing with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials like
tiles, cement, sand and water etc., and overheads & contractors
profit complete for finished item of work.
Cellar :

247 Providing cladding to walls with High Polished Granite 16 mm Providing cladding to walls with High Providing cladding to walls with High
to 18 mm thick up to 8'-00 (2.43 M) other than black and regular Polished Granite 16 mm to 18 mm Polished Granite 16 mm to 18 mm
colours, length equal to flooring slabs set over base coat of thick up to 8'-00 (2.43 M) other than thick up to 8'-00 (2.43 M) other than
CM(1:5) 12 mm thick using screened sand with cement slurry of black black
honey like consistency spread at the rate of 3.30 kgs per sqm
and jointing with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials like
tiles, cement, sand and water etc., and overheads & contractors
profit complete for finished item of work.
Basement Floor
27 Providing cladding to walls with High Polished Granite 16 mm Providing cladding to walls with High Providing cladding to walls with High
to 18 mm thick up to 8'-00 (2.43 M) other than black and regular Polished Granite 16 mm to 18 mm Polished Granite 16 mm to 18 mm
colours, length equal to flooring slabs set over base coat of thick up to 8'-00 (2.43 M) other than thick up to 8'-00 (2.43 M) other than
CM(1:5) 12 mm thick using screened sand with cement slurry of black black
honey like consistency spread at the rate of 3.30 kgs per sqm
and jointing with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials like
tiles, cement, sand and water etc., and overheads & contractors
profit complete for finished item of work.
First Floor :

13 Providing cladding to walls with High Polished Granite 16 mm Providing cladding to walls with High Providing cladding to walls with High
to 18 mm thick up to 8'-00 (2.43 M) other than black and regular Polished Granite 16 mm to 18 mm Polished Granite 16 mm to 18 mm
colours, length equal to flooring slabs set over base coat of thick up to 8'-00 (2.43 M) other than thick up to 8'-00 (2.43 M) other than
CM(1:5) 12 mm thick using screened sand with cement slurry of black black
honey like consistency spread at the rate of 3.30 kgs per sqm
and jointing with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials like
tiles, cement, sand and water etc., and overheads & contractors
profit complete for finished item of work.
Second Floor :

5 Providing cladding to walls with High Polished Granite 16 mm Providing cladding to walls with High Providing cladding to walls with High
to 18 mm thick up to 8'-00 (2.43 M) other than black and regular Polished Granite 16 mm to 18 mm Polished Granite 16 mm to 18 mm
colours, length equal to flooring slabs set over base coat of thick up to 8'-00 (2.43 M) other than thick up to 8'-00 (2.43 M) other than
CM(1:5) 12 mm thick using screened sand with cement slurry of black black
honey like consistency spread at the rate of 3.30 kgs per sqm
and jointing with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials like
tiles, cement, sand and water etc., and overheads & contractors
profit complete for finished item of work.
Third Floor :
5 Providing cladding to walls with High Polished Granite 16 mm Providing cladding to walls with High Providing cladding to walls with High
to 18 mm thick up to 8'-00 (2.43 M) other than black and regular Polished Granite 16 mm to 18 mm Polished Granite 16 mm to 18 mm
colours, length equal to flooring slabs set over base coat of thick up to 8'-00 (2.43 M) other than thick up to 8'-00 (2.43 M) other than
CM(1:5) 12 mm thick using screened sand with cement slurry of black black
honey like consistency spread at the rate of 3.30 kgs per sqm
and jointing with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials like
tiles, cement, sand and water etc., and overheads & contractors
profit complete for finished item of work.
Fourth Floor :

40 Filling with well burnt cinder aggregate as per IS:2686-1977 in Filling with well burnt cinder Filling with well burnt cinder
sunken slabs including cost and conveyance of cinder, labour
charges for filling, ramming, overheads and contractor profit
etc., complete for finished item of work
First Floor :
40 Filling with well burnt cinder aggregate as per IS:2686-1977 in Filling with well burnt cinder Filling with well burnt cinder
sunken slabs including cost and conveyance of cinder, labour
charges for filling, ramming, overheads and contractor profit
etc., complete for finished item of work
Second Floor :
41 Filling with well burnt cinder aggregate as per IS:2686-1977 in Filling with well burnt cinder Filling with well burnt cinder
sunken slabs including cost and conveyance of cinder, labour
charges for filling, ramming, overheads and contractor profit
etc., complete for finished item of work
Third Floor :
61 Filling with well burnt cinder aggregate as per IS:2686-1977 in Filling with well burnt cinder Filling with well burnt cinder
sunken slabs including cost and conveyance of cinder, labour
charges for filling, ramming, overheads and contractor profit
etc., complete for finished item of work
Fourth Floor :
40 Reinforced cement concrete (1:5:10) proportion (Cement: fine Reinforced cement concrete (1:5:10) Reinforced cement concrete (1:5:10)
aggregates: coarse aggregate) using 40mm size (SS5) hard proportion proportion
granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand), coarse aggregate, water etc., to site including
centering using Casurina Ballies , Bamboos , Wooden
Reapers , Runners , Wood Posts , Wall Plates etc., shuttering,
machine mixing, laying concrete, lifting concrete manually ,
vibrating, curing, etc., and overheads & contractors profit
complete as per drawings but excluding cost of steel and it's
fabrication charges for finished item of work (APSS NO. 402 &
403) for dummy columns.
Fifth Floor :

1326.00 Providing impervious coat to exposed RCC roof slab surfaces Providing impervious coat 12mm Providing impervious coat 12mm thick
of sump , sump side wall,sump bottom slab,in side of septic thick
tank , in sunken slabs etc. to required slopes with CM (1:3)
prop. using screened sand 12mm thick mixed with integral
cement water proofing liquid confirming to IS: 2645-2003
manufactured by reputed manufacturers as approved by
Engineer-in-charge at 200ml per one bag of cement, laid over
roof slab when it is green, finished smooth with a floating coat of
neat cement and thread lining at regular intervals of
45cmx45cm where ever necessary including cost and
conveyance of all materials like cement, sand, water proofing
compound, water etc., to site, operational, incidental, and labour
charges for mixing mortar, laying, lift charges, rendering smooth
and thread lining, curing including rounding off junctions of wall
and slab etc., and overheads & contractors profit complete for
finished item of work. (APSS No. 901 & 903).
First Floor :
465.00 Providing specialized high performance acrylic polymer modified Providing specialized high Providing specialized high
elastomeric cementitious waterproof coating to the bottom and performance acrylic polymer performance acrylic polymer modified
sides of sunken slabs of toilets duly cleaning of the surface from modified elastomeric cementitious elastomeric cementitious waterproof
dirt, dust and other contaminations, providing and application of waterproof coating coating
two coats of high performance Acrylic polymer modified
Elastomeric cementitious waterproof coating ( 1.8 Sq. Mtr. /
Kg /Each Coat ) including cost and conveyance of all materials
to site, operationals & incidental charges, lift charges etc., and
overheads & contractors profit complete for finished item of
work

0 Providing impervious coat to exposed RCC roof slab surfaces Providing impervious coat 12mm Providing impervious coat 12mm thick
of sump , sump side wall,sump bottom slab,in side of septic thick
tank , in sunken slabs etc. to required slopes with CM (1:3)
prop. using screened sand 12mm thick mixed with integral
cement water proofing liquid confirming to IS: 2645-2003
manufactured by reputed manufacturers as approved by
Engineer-in-charge at 200ml per one bag of cement, laid over
roof slab when it is green, finished smooth with a floating coat of
neat cement and thread lining at regular intervals of
45cmx45cm where ever necessary including cost and
conveyance of all materials like cement, sand, water proofing
compound, water etc., to site, operational, incidental, and labour
charges for mixing mortar, laying, lift charges, rendering smooth
and thread lining, curing including rounding off junctions of wall
and slab etc., and overheads & contractors profit complete for
finished item of work. (APSS No. 901 & 903).
Fifth Floor :
308 Providing impervious coat to exposed RCC roof slab surfaces to Providing impervious coat 20mm Providing impervious coat 20mm thick
required slopes with CM (1:3) prop. using screened sand 20mm thick
thick (average) mixed with integral cement water proofing liquid
confirming to IS: 2645-2003 manufactured by reputed
manufacturers as approved by Engineer-in-charge at 200ml per
one bag of cement, laid over roof slab when it is green, finished
smooth with a floating coat of neat cement and thread lining at
regular intervals of 45cmx45cm including cost and conveyance
of all materials like cement, sand, water proofing compound,
water etc., to site, operational, incidental, and labour charges for
mixing mortar, laying, lift charges, rendering smooth and thread
lining, curing including rounding off junctions of wall and slab
etc., and overheads & contractors profit complete for finished
item of work. (APSS No. 901 & 903).
First Floor :

298 Providing impervious coat to exposed RCC roof slab surfaces to Providing impervious coat 20mm Providing impervious coat 20mm thick
required slopes with CM (1:3) prop. using screened sand 20mm thick
thick (average) mixed with integral cement water proofing liquid
confirming to IS: 2645-2003 manufactured by reputed
manufacturers as approved by Engineer-in-charge at 200ml per
one bag of cement, laid over roof slab when it is green, finished
smooth with a floating coat of neat cement and thread lining at
regular intervals of 45cmx45cm including cost and conveyance
of all materials like cement, sand, water proofing compound,
water etc., to site, operational, incidental, and labour charges for
mixing mortar, laying, lift charges, rendering smooth and thread
lining, curing including rounding off junctions of wall and slab
etc., and overheads & contractors profit complete for finished
item of work. (APSS No. 901 & 903).
above First Floor :
2874 Providing impervious coat to exposed RCC roof slab surfaces to Providing impervious coat 20mm Providing impervious coat 20mm thick
required slopes with CM (1:3) prop. using screened sand 20mm thick
thick (average) mixed with integral cement water proofing liquid
confirming to IS: 2645-2003 manufactured by reputed
manufacturers as approved by Engineer-in-charge at 200ml per
one bag of cement, laid over roof slab when it is green, finished
smooth with a floating coat of neat cement and thread lining at
regular intervals of 45cmx45cm including cost and conveyance
of all materials like cement, sand, water proofing compound,
water etc., to site, operational, incidental, and labour charges for
mixing mortar, laying, lift charges, rendering smooth and thread
lining, curing including rounding off junctions of wall and slab
etc., and overheads & contractors profit complete for finished
item of work. (APSS No. 901 & 903).
Fifth Floor :

1110 Providing 110 mm Dia ISI marked PVC down water take Providing 110 mm Dia ISI marked Providing 110 mm Dia ISI marked PVC
pipes with socket , 2.5mm thick 4.0 kg/sq.cm pressure of ISI PVC down water take pipes down water take pipes
marked including cost of necessary PVC Bends, shoes, iron /
PVC clamps and all other accessories and fixing in position
including cost and conveyance of all materials, operational &
incidental charges including all labour charges for fixing at site
etc., and overheads & contractors profit complete for finished
item of work. (APSS No. 1328)

16 RCM facia 50mm thick in CM(1:3) using screened sand for drop RCM facia 50mm thick in CM(1:3) RCM facia 50mm thick in CM(1:3)
walls, fins with rabbit wire mesh & nomianl reinforcement as
directred by Engineer - In - Charge with dubara sponge
finishing,including cost and conveyance of all materials to site,
operationals &incidental,cost and conveyance of cement, wire
mesh water to work site, centering, scaffolding and form work,lift
charges etc., and overheads & contractors profit complete for
finished item of work but excluding cost of steel and its
fabrication charges for finished item of work(APSS
NO.403&903)
Basement Floor
21 RCM facia 50mm thick in CM(1:3) using screened sand for drop RCM facia 50mm thick in CM(1:3) RCM facia 50mm thick in CM(1:3)
walls, fins with rabbit wire mesh & nomianl reinforcement as
directred by Engineer - In - Charge with dubara sponge
finishing,including cost and conveyance of all materials to site,
operationals &incidental,cost and conveyance of cement, wire
mesh water to work site, centering, scaffolding and form work,lift
charges etc., and overheads & contractors profit complete for
finished item of work but excluding cost of steel and its
fabrication charges for finished item of work(APSS
NO.403&903)
First Floor :

6 RCM facia 50mm thick in CM(1:3) using screened sand for drop RCM facia 50mm thick in CM(1:3) RCM facia 50mm thick in CM(1:3)
walls, fins with rabbit wire mesh & nomianl reinforcement as
directred by Engineer - In - Charge with dubara sponge
finishing,including cost and conveyance of all materials to site,
operationals &incidental,cost and conveyance of cement, wire
mesh water to work site, centering, scaffolding and form work,lift
charges etc., and overheads & contractors profit complete for
finished item of work but excluding cost of steel and its
fabrication charges for finished item of work(APSS
NO.403&903)
Second Floor :

6 RCM facia 50mm thick in CM(1:3) using screened sand for drop RCM facia 50mm thick in CM(1:3) RCM facia 50mm thick in CM(1:3)
walls, fins with rabbit wire mesh & nomianl reinforcement as
directred by Engineer - In - Charge with dubara sponge
finishing,including cost and conveyance of all materials to site,
operationals &incidental,cost and conveyance of cement, wire
mesh water to work site, centering, scaffolding and form work,lift
charges etc., and overheads & contractors profit complete for
finished item of work but excluding cost of steel and its
fabrication charges for finished item of work(APSS
NO.403&903)
Third Floor :
6 RCM facia 50mm thick in CM(1:3) using screened sand for drop RCM facia 50mm thick in CM(1:3) RCM facia 50mm thick in CM(1:3)
walls, fins with rabbit wire mesh & nomianl reinforcement as
directred by Engineer - In - Charge with dubara sponge
finishing,including cost and conveyance of all materials to site,
operationals &incidental,cost and conveyance of cement, wire
mesh water to work site, centering, scaffolding and form work,lift
charges etc., and overheads & contractors profit complete for
finished item of work but excluding cost of steel and its
fabrication charges for finished item of work(APSS
NO.403&903)
Fourth Floor :

36.6 Supply and fixing of doors as per approved drawings with 1st Supply and fixing of doors as per Supply and fixing of doors as per
Grade Burma teak wood frame of section 250mm x 150 mm of approved drawings with 1st Grade approved drawings with 1st Grade
4 verticals of 2.85m height with one horizontal at the top of Burma teak wood (6100mm x Burma teak wood (6100mm x
6.10m of length with a section of 250mm x 150mm, and at the 2850mm) 2850mm)
bottom of frame 2 Nos of 1.25m length horizontals each of
section 250mm x 150mm and with 1st grade burma teak wood
door shutter of 150mmX35mm thick alround frame double
shutter on center and single shutter on either side and with
12mm thick plain float glass fixid to door shutter with teak wood
beeding of 12mmX12mm Supply and fixing of 8 Nos. MS hold
fasts of size (450 mm x 100 mm x 8mm) flat of 2 nos welded
together to fix with the help of anchor fasteners of 4 nos (Two
on either side) including cost of ISI marked Brass fixtures of 16
Nos. butt hinges of 250mm long, 3 No. brass aldrops (IS:2681)
of 450mm long, 3 Nos. brass tower bolts (IS:204) of 300 mm x
10 mm dia at top, 4 Nos. of 450mm long brass fanvy handless
(IS:208) at front side and 4 Nos of 300mm Brass handles on
back side, 4 Nos.of door stoppers, including fixing the fixtures
to door with required number of screws, bolt and nuts including
labour charges for fixing the frame in position, fixing the shutter
to the frame etc., including cost & conveyence, overheads &
contractors profit etc.. complete for finished item of work
(6100mm x 2850mm)
Basement Floor & First Floors
525.2 Supply and fixing powder coated aluminium fully glazed swing Supply and fixing powder coated Supply and fixing powder coated
door as per the approved drawing with fixed fan light of 500mm aluminium fully glazed swing door aluminium fully glazed swing door
height at top door using aluminium sections of 101.60 mmm x
44.45mm , 3.18 mm thick for frame and door shutter made of
styles , top and middle rail of 47.62mm x 44.45mm , 3.18 mm
thick and bottom rail of 114.30mm x 44.45 mm , 3.18mm
thick,powder coating of alluminium sections 25mm microns
thick, 5 mm thick plain float glass fitted with suitable aluminium
glazing clips and rubber beading in fan light portion, double
shutters fitted with 5mm thick frosted / ground glass in the top
half and MDF Board: interior-Both Side Laminated -12 mm thick
in the bottom half fitted with suitable aluminium glazing clips
and rubber beading,shutters mounted on double action
hydraulic floor spring of approved brand manufacture IS : 6315
marked , Hardwyn make M-3000 for doors including cost of
cutting floors as required , embedding in floors and SS cover
plates with brass pivot and sigle piece MS Sheet outer box with
slide plate etc.complete (Weight Capacity up to 130 Kgs)
as approved by Engineer-in-Charge including supply and fixing
ISI marked powder coated aluminium fixtures of 3 Nos. of butt
hinges (IS:205) of 150mm long(for each shutter), 4 Nos.tower
bolts 10mm bolt (IS:204) 300mm long , 4 Nos.alluminium
handles (IS:208) 150mm dia and 2 Nos. aldrops (IS:2681)
245.7 Supply and fixing of doors as per approved drawings with Supply and fixing of doors as per Supply and fixing of doors as per
medium teak wood frame of section 100mm x 65 mm with split approved drawings with medium approved drawings with medium teak
type fan light of 500mm at the top fixed with 4mm thick pin teak wood wood
headed glass using 12mm x 12mm Teak Wood beading and 2
Nos. of 10mm MS Square bars and ISI marked flush door
shutter of 30mm thick double shutters with bond wood solid
block board type core having cross bands and face veneers, hot
pressed bonded with water proof phenol formaldehyde synthetic
resin factory made conforming to IS 2202-1991 (Part-I) both
sides commercial ply with internal lipping on all sides, fixing
1mm thick mat finish laminated sheet to full width and height of
the flush shutter both sides including cost and conveyance to
site of teak wood frame, flush shutter, laminate sheet including
supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40
mm x 5mm including cost of ISI marked Alumimium fixtures of 6
Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681)
300mm long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm
dia at top, 2 Nos. 150mm long handles (IS:208), 2 Nos. door
stoppers and 2 Nos. Rubber / Nylon door stop bushes including
fixing the fixtures to door with required number of screws, bolt
and nuts including labour charges for fixing the frame in
position, fixing the shutter to the frame, fixing glass in fan light
portion etc., including overheads & contractors profit complete
149.76 Supply and fixing of doors as per approved drawings with Supply and fixing of doors as per Supply and fixing of doors as per
medium teak wood frame of section 100mm x 65 mm with split approved drawings with medium approved drawings with medium teak
type fan light of 500mm at the top fixed with 4mm thick pin teak wood wood
headed glass using 12mm x 12mm Teak Wood beading and 2
Nos. of 10mm MS Square bars and ISI marked flush door
shutter of 30mm thick double shutters with bond wood solid
block board type core having cross bands and face veneers, hot
pressed bonded with water proof phenol formaldehyde synthetic
resin factory made conforming to IS 2202-1991 (Part-I) both
sides commercial ply with internal lipping on all sides, fixing
1mm thick mat finish laminated sheet to full width and height of
the flush shutter both sides including cost and conveyance to
site of teak wood frame, flush shutter, laminate sheet including
supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40
mm x 5mm including cost of ISI marked Aluminium fixtures of 6
Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681)
300mm long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm
dia at top, 2 Nos. 150mm long handles (IS:208), 2 Nos. door
stoppers and 2 Nos. Rubber / Nylon door stop bushes including
fixing the fixtures to door with required number of screws, bolt
and nuts including labour charges for fixing the frame in
position, fixing the shutter to the frame, fixing glass in fan light
portion etc, including overheads & contractors profit complete
123.2 Supply and fixing of doors as per approved drawings with Supply and fixing of doors as per Supply and fixing of doors as per
medium teak wood frame of section 100mm x 65 mm with split approved drawings with medium approved drawings with medium teak
type fan light of 500mm at the top fixed with 4mm thick pin teak wood wood
headed glass using 12mm x 12mm Teak Wood beading and 2
Nos. of 10mm MS Square bars and ISI marked flush door
shutter of 30mm thick single shutter with bond wood solid block
board type core having cross bands and face veneers, hot
pressed bonded with water proof phenol formaldehyde synthetic
resin factory made conforming to IS 2202-1991 (Part-I) both
sides commercial ply with internal lipping on all sides fixing 1mm
thick mat finish laminated sheet to full width and height of the
flush shutter both sides including cost and conveyance to site of
teak wood frame, flush shutter, laminate sheet including supply
and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x
5mm including cost of ISI marked Aluminium fixtures of 3 Nos.
butt hinges (IS:205) 150mm long , 1 No. aldrop (IS:2681)
300mm long, 1 No. tower bolt (IS:204) of 200 mm x 10 mm dia
at top, 2 Nos. 150mm long handles (IS:208), 1 No. door stopper
and 1 No. Rubber / Nylon door stop bushes including fixing the
fixtures to door with required number of screws, bolt and nuts
including labour charges for fixing the frame in position, fixing
the shutter to the frame, fixing glass in fan light portion etc,
including overheads & contractors profit complete for finished
294.84 Supply and fixing doors as per drawings with medium teak Supply and fixing of doors as per Supply and fixing of doors as per
wood frame of section 100mm x 65 mm and ISI marked flush approved drawings with medium approved drawings with medium teak
door shutters of 30 mm thick single shutter with bond wood solid teak wood wood
block board type Core having cross bands and face veneers,
hot pressed bonded with water proof phenol formaldehyde
synthetic resin factory made conforming to IS 2202-1991 (Part-
I) both sides commercial ply with internal lipping on all sides,
fixing 1mm thick mat finish laminated sheet to full width and
height of the flush shutter both sides including cost and
conveyance to site of teak wood frame, flush shutter, laminate
sheet including supply and fixing 6 Nos. MS Z hold fasts of size
300 mm x 40 mm x 5mm including cost of ISI marked
Aluminium fixtures of 3 Nos. butt hinges (IS:205) 150mm long, 1
No. aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204) of
200 mm x 10 mm dia at top, 2 Nos. 150 mm long handles
(IS:208), 1 No. door stopper and 1 No. Rubber / Nylon door stop
bushes including fixing the fixtures to door with required
number of screws, bolt and nuts including labour charges for
fixing the frame in position, fixing the shutter to the frame etc,
including overheads & contractors profit complete for finished
item of work as per APSS 1001 & 1002 (The vertical frame of
door shall be embedded in flooring for a depth of not less than
10 mm) (900mm x 2100mm)
1265 Supplying and fixing single side prelam solid panel PVC Supplying and fixing single side Supplying and fixing single side prelam
door frame (Choukhat): Providing and fixing factory made Pac prelam solid panel PVC door frame solid panel PVC door frame
single side Prelam door frame of the size 50x7 mm with a wall (Choukhat) (Choukhat)
thickness of 5mm, made out of extruded 5mm rigid Pac single
side prelam sheet, meter cut at two corners and joined with 2
Nos. of 150mm long brackets of 15 x 15mm MS Square tube.
The two vertical door profiles are to be reinforced with 19 x
19mm MS. square tube of 19 guage. The door frame shall be
fixed to the wall using 65/100mm long MS. Screws through the
frame by using Pac fasteners. a minimum of 4 Nos. of screws to
be provided for each vertical member and minimum 2nos. for
horizontal member etc. complete as per manufacture
specification and direction of Engineer-incharge including
conveyance of all materials, labour charges for fixing,
overheads & contractors profit complete for finished item of
work.
Cellar to Fourth Floors
425.04 Providing and fixing 30mm thick factory made moulded Providing and fixing 30mm thick Providing and fixing 30mm thick
door shutter- wood free consisting of frame made out of MS. factory made moulded door shutter factory made moulded door shutter
tubes 19gauge thickness and size of 25mmX25mm for styles,
top and bottom rails. MS. Frame shall have a coat of steel
primers. The inner panel shall consist of 25mm thick high
density EPS conforming to IS 4671-1984 bounded with 2mm
thick termite proof, water proof and fire resistant moulded Pac
sheet with 2,4,6 raised panel design in different plain and / or
pre-lam colours after routing to the moulded design on one side
and 2mm plain and / or pre-lam Pac sheet on other side of the
EPS. The edge of panel to be sealed with lipping of 10mm wide
PVC sheet bottom (made by sticking 2 rigid foam sheet of 5mm
thickness using Pac solvent cement) and stiles sides
25mm(5mmX5) thick and 30mm width Pac sheet fitted along
MS tube for lock provision for lock height 5mm thick Pac sheet
of size 150mmX100mm fixed with upper and lower face of inner
side of EPS panel etc., complete as per direction of Engineer –
in-Charge, manufacture specification and drawing including ISI
marked Aluminium fixtures 3 Nos. butt hinges (IS:205) of
150mm long, 1 No. aldrop (IS:2681) 250 mm long, 1 No. tower
bolt (IS:204) of 150 mm x 10mm dia, 2 Nos. 125mm long
handles (IS:208),1 No. Rubber / Nylon door stop bushes
including labour charges for fixing the shutter to frame etc.,
including overheads & contractors profit complete for finished
1237.44 Providing and fixing factory made uPVC white colour sliding Providing and fixing factory made Providing and fixing factory made
glazed window comprising of uPVC multi-chambered frame with uPVC white colour sliding glazed uPVC white colour sliding glazed
in-built roller track and sash extruded profiles duly reinforced window comprising of uPVC window comprising of uPVC
with 1.60 ± 0.2 mm thick galvanized mild steel section made
from roll forming process of required length (shape & size
according to uPVC profile), appropriate dimension of uPVC
extruded glazing beads and uPVC extruded interlocks, EPDM
gasket, wool pile, zinc alloy (white powder coated) touch locks
with hook, zinc alloy body with single nylon rollers (weight
bearing capacity to be 40 kg), G.I fasteners 100 x 8 mm size for
fixing frame to finished wall and necessary stainless steel
screws etc. Profile of frame & sash shall be mitred cut and
fusion welded at all corners, including drilling of holes for fixing
hardware's and drainage of water etc. After fixing frame the gap
between frame and adjacent finished wall shall be filled with
weather proof silicon sealent over backer rod of required size
and of approved quality, all complete as per approved drawing
& direction of Engineer-in-Charge inclusive of cost of Single /
double glass panes of 4mm thick pin headed glass, wire mesh
and silicon sealent . Note: For uPVC frame and sash extruded
profiles minus 5% tolerancein dimension i.e. in depth & width of
profile shall be acceptable.Variation in profile dimension in
higher side shall be accepted. But no extra payment on this
account shall be made.
184.68 Providing and fixing factory made uPVC white colour sliding Providing and fixing factory made Providing and fixing factory made
glazed window comprising of uPVC multi-chambered frame with uPVC white colour sliding glazed uPVC white colour sliding glazed
in-built roller track and sash extruded profiles duly reinforced window comprising of uPVC window comprising of uPVC
with 1.60 ± 0.2 mm thick galvanized mild steel section made
from roll forming process of required length (shape & size
according to uPVC profile), appropriate dimension of uPVC
extruded glazing beads and uPVC extruded interlocks, EPDM
gasket, wool pile, zinc alloy (white powder coated) touch locks
with hook, zinc alloy body with single nylon rollers (weight
bearing capacity to be 40 kg), G.I fasteners 100 x 8 mm size for
fixing frame to finished wall and necessary stainless steel
screws etc. Profile of frame & sash shall be mitred cut and
fusion welded at all corners, including drilling of holes for fixing
hardware's and drainage of water etc. After fixing frame the gap
between frame and adjacent finished wall shall be filled with
weather proof silicon sealent over backer rod of required size
and of approved quality, all complete as per approved drawing
& direction of Engineer-in-Charge inclusive of cost of Single /
double glass panes of 4mm thick pin headed glass, wire mesh
and silicon sealent . Note: For uPVC frame and sash extruded
profiles minus 5% tolerancein dimension i.e. in depth & width of
profile shall be acceptable.Variation in profile dimension in
higher side shall be accepted. But no extra payment on this
account shall be made.
132.45 Providing and fixing factory made uPVC white colour fixed Providing and fixing factory made Providing and fixing factory made
glazed windows / Ventilators comprising of uPVC multi uPVC white colour fixed glazed uPVC white colour fixed glazed
chambered frame and mullion (where ever required) extruded windows / Ventilators windows / Ventilators
profiles duly reinforced with 1.60± 0.2 mm thick galvanized mild
steel section made from roll forming process of required length
(shape & size according to uPVC profile), uPVC extruded
glazing beads of appropriate dimension, EPDM gasket,G.I
fasteners 100 x 8 mm size for fixing frame to finished wall,
plastic packers, plastic caps and necessary stainless steel
screws etc. Profileof frame shall be mitred cut and fusion
welded at all corners, mullion (if required) shall be also fusion
welded including drilling of holes for fixing hardware and
drainage of water etc.
After fixing frame the gap between frame and adjacent finished
wall shall be filled with weather proof silicon sealant over backer
rod of required size and of approved quality, all complete as per
approved drawing & direction of Engineer-in-Charge inclusive of
cost of Single / double glass panes and silicon sealant. Note:
For uPVC frame, sash and mullion extruded profiles minus
5%tolerance in dimension i.e. in depth & width of profile shall be
acceptable.Variation in profile dimension in higher side shall be
accepted. But, no extra payment on this account shall be made.
Fixed windows / Ventilators made of (small series) frame 47 x
50mm & mullion 47 x 68 mm both having wall thickness of 1.9
#REF! Supplying and fixing of MS doors, grill to windows / in open Supplying and fixing of MS doors, Supplying and fixing of MS doors, grill
court yards using MS angles, flat, square bars including cost grill to windows / in open court yards to windows / in open court yards
and conveyance of all materials, cutting, bending, welding, all
operational charges, labour charges, overheads and contractor
profit etc., complete for finished item of work. For All Floors

39 Supply and fixing jallies ( cement concrete ) of 50mm thick as Supply and fixing jallies ( cement Supply and fixing jallies ( cement
per the design approved by the Engineer-in-Charge including concrete ) of 50mm thick concrete ) of 50mm thick
cost and conveyance of materials to site and labour charges
etc., overheads & contractors profit complete for finished item of
work.
Cellar :

78 Supply and fixing jallies ( cement concrete ) of 50mm thick as Supply and fixing jallies ( cement Supply and fixing jallies ( cement
per the design approved by the Engineer-in-Charge including concrete ) of 50mm thick concrete ) of 50mm thick
cost and conveyance of materials to site and labour charges
etc., overheads & contractors profit complete for finished item of
work.
Basement Floor
78 Supply and fixing jallies ( cement concrete ) of 50mm thick as Supply and fixing jallies ( cement Supply and fixing jallies ( cement
per the design approved by the Engineer-in-Charge including concrete ) of 50mm thick concrete ) of 50mm thick
cost and conveyance of materials to site and labour charges
etc., overheads & contractors profit complete for finished item of
work.
First Floor :

78 Supply and fixing jallies ( cement concrete ) of 50mm thick as Supply and fixing jallies ( cement Supply and fixing jallies ( cement
per the design approved by the Engineer-in-Charge including concrete ) of 50mm thick concrete ) of 50mm thick
cost and conveyance of materials to site and labour charges
etc., overheads & contractors profit complete for finished item of
work.
Second Floor :

52 Supply and fixing jallies ( cement concrete ) of 50mm thick as Supply and fixing jallies ( cement Supply and fixing jallies ( cement
per the design approved by the Engineer-in-Charge including concrete ) of 50mm thick concrete ) of 50mm thick
cost and conveyance of materials to site and labour charges
etc., overheads & contractors profit complete for finished item of
work.
Third Floor :

72 Supply and fixing jallies ( cement concrete ) of 50mm thick as Supply and fixing jallies ( cement Supply and fixing jallies ( cement
per the design approved by the Engineer-in-Charge including concrete ) of 50mm thick concrete ) of 50mm thick
cost and conveyance of materials to site and labour charges
etc., overheads & contractors profit complete for finished item of
work.
Fourth Floor :
246 Providing and Fixing Structural Glazing fabricated from Roll Providing and Fixing Structural Providing and Fixing Structural Glazing
formed sections made of Pre-painted Steel / Powder coated Glazing fabricated from Roll formed fabricated from Roll formed sections
(Base steel as per IS 513 of ‘D’ quality, galvanized as per IS sections
277 with Zinc of 120 Gm/sqm) with total coated thickness of
0.72mm. The glass holding section made of 304 grade stainless
steel of 0.6mm thick as per the design requirement &
calculations as given in IS: 875. Primer coat with epoxy primer
of 5 – 7 microns thick, finish painted with a polyester paint of 12-
16 microns thick and back coated with Alkyd backer of 5-7
microns or powder coated with pure polyester powder up to 50-
60 microns thick. The vertical section should be of 50mm
x100mm x 0.72mm, 33mm x 58mm x 0.72mm for frame
horizontal section, stiffener section should be 48mm x 98mm x
1mm, cover profiles sections should be of 20mm x 58mm x
0.58mm, Glass holding section should be of 37mm x 37mm &
37mm x 18mm. Including 5mm thick Ocean Blue reflective
glass. Brackets made of CRCA powder coated/Electroplated
should be used to connect vertical to horizontal, vertical to slab,
to fix verticals at top & bottom as per site requirement. Gasket
made of Ethyl Propylene Diamine Monomer. Natural cure, with
Good U.V. Resistance Silicon to be used. Wall fixing of sections
to concrete/masonry wall should be with self-expanding cap &
screws. The rate is inclusive of cost and conveyance of all
materials to site, all labour charges, incidental charges, cost of
all consumables etc. and scaffolding charges, form work ,
overheads & contractors profit etc., complete for finished item of
work in all floors.
53 Providing and Fixing Top Hung shutters in Structural Providing and Fixing Top Hung Providing and Fixing Top Hung
Glazing fabricated from Roll formed sections made of Pre- shutters in Structural Glazing shutters in Structural Glazing
painted Steel / Powder coated (Base steel as per IS 513 of ‘D’ fabricated from Roll formed sections fabricated from Roll formed sections
quality, galvanized as per IS 277 with Zinc of 120 Gm/sqm) with
total coated thickness of 0.72mm. The glass holding section
made of 304 grade stainless steel of 0.6mm thick. Galvanized
steel sections are to be used as stiffeners inside the colour
coated steel/powder coated sections as per the design
requirement. Design calculations are made to suit wind
pressures as given in IS 875. Primer coat with epoxy primer of
5-7 microns thick and back coated with Alkyd backer of 5-7
microns or powder coated with pure polyester powder up to 50-
60 microns thick. The outer frame should be of 20mm x 58mm
x 0.6mm, Shutter section should be of 58mm x 33mm x 0.72
mm, stiffener section should be 56mm x 31mm x 1mm. EARL
Bihari Hinges – 2 Nos for each shutter and Aluminium Stays – 2
Nos. for each shutter, Aluminium Handle – 1 no. for each
shutter. The rate is inclusive of cost and conveyance of all
materials to site, all labour charges,
incidental charges, cost of all consumables etc. and scaffolding
charges, form work, overheads & contractor profit etc. complete
for finished item of work in all floors.
368.1 Supplying and fixing of stainless steel (grade 304) hand Supplying and fixing of stainless Supplying and fixing of stainless steel
railing as per approved drawing with top rail of 50mm dia pipe steel (grade 304) hand railing (grade 304) hand railing
and 2mm thick medium class and vertical posts of 25mm dia
and 1.6mm thick medium class 1 No for each step fixed with
base plate of 75mm dia using bonding agent and anchor
fastner and welding, drilling of 25mm dia holes with pneumatic
compressor for fixing railing, buffing, polishing all members of
the railing thouroughly , lacquer finishing to present seamless
finish including cost and conveyance of all materials, electrodes,
welding charges, cost of all consumables, labour charges ,
overheads & contractors profit etc., complete for finished item of
work. for all floors
801 Supplying and fixing of stainless steel (grade 304) railing Supplying and fixing of stainless Supplying and fixing of stainless steel
for ramp as per approved drawing with top rail of 50mm dia steel (grade 304) railing for ramp (grade 304) railing for ramp
pipe and 2mm thick medium class fixed in to wall with 25mm dia
pipe of 0.30m length @ 1m centre to centre and welding,
buffing, polishing all members of the railing thouroughly ,
lacquer finishing to present seamless finish including cost and
conveyance of all materials, electrodes, welding charges, cost
of all consumables, labour charges , overheads & contractors
profit etc., complete for finished item of work.

4.6 Supply & fixing of Rolling shutter made of 80 x 1.25 mm Supply & fixing of Rolling shutter Supply & fixing of Rolling shutter made
machine rolled CRCA laths, interlocked together through their made of 80 x 1.25 mm of 80 x 1.25 mm
entire length and jointed together at the ends by end-locks,
mounted on specially designed pipe shaft of 50mm dia nominal
bore MS B class pipe with brackets, plates, guide channels,
stoppers, bottom locking plates and arrangements for inside &
outside locking with push-pull operations including cost of hood
cover and springs complete, painted with one coat of approved
steel primer, locks, ball bearings, all accessories etc.,
overheads & contractors profit complete for finished item of
work as per special spn: 1108

519 White washing two coats with white cement to ceiling to give White washing two coats with white White washing two coats with white
an even shade after thouroughly brushing the surface to remove cement to ceiling cement to ceiling
all dirt and remains of loose powdered materials including cost
of all materials , labour charges and incidental such as
scaffolding , lift charges etc., and overheads & contractors profit
complete for finished item of work in all floors.
First & Fifth Floors
47661 Providing and applying Wall putty of White Cement or Providing and applying Wall putty of Providing and applying Wall putty of
Polymer or Cement based of average 1 to 2 mm thickness over White Cement or Polymer or White Cement or Polymer or Cement
plastered surface to prepare the surface even and smooth after Cement based based
thoroughly brushing the surface to remove all dirt and remains
of loose powdered materials, applying emery paper, Sand the
surface, clean & wipe off loose dust, applying knifing paste filler
by putty knife / muslin pad, air dry for 2 - 3 hrs, sand with 180
and 320 No., emery paper for the surface preparation including
cost and conveyance of all materials to work site and all
operational, incidental, labour charges, over heads and
contractors profit etc., complete for finished item of work in all
floors for internal walls & Ceiling
Cellar to Fourth Floors

32534 Supply & application of one coat water based cement Supply & application of one coat Supply & application of one coat water
primer of interior grade I and two coats of synthetic water based cement primer of based cement primer of interior grade I
polymer luxury plastic emulsion paint of superior grade interior grade I and two coats of and two coats of synthetic polymer
having VOC (Volatile Organic Compound) content less than 50 synthetic polymer luxury plastic luxury plastic emulsion paint
grams/litre for internal walls including cost and conveyance of emulsion paint
all materials to site, incidental, operational and all labour
charges etc., and overheads & contractors profit complete for
finished item of work in all floors.
Cellar to Fifth Floors

#REF! Supply & application of one coat water based cement Supply & application of one coat Supply & application of one coat water
primer of exterior grade II and two coats of synthetic water based cement primer of based cement primer of exterior grade
polymer luxury plastic emulsion paint of superior grade exterior grade II and two coats of II and two coats of synthetic polymer
having VOC (Volatile Organic Compound) content less than 50 synthetic polymer luxury plastic luxury plastic emulsion paint
grams/litre for exterior walls including cost and conveyance of emulsion paint
all materials to site, incidental, operational and all labour
charges etc., and overheads & contractors profit complete for
finished item of work in all floors.
Cellar to Fifth Floors
4559 Providing and applying PMCC / Deco orient base or Providing and applying PMCC / Providing and applying PMCC / Deco
Equivalent exterior Texture of average 2 to 3 mm thickness Deco orient base or Equivalent orient base or Equivalent exterior
over plastered surface to prepare the surface even and smooth exterior Texture Texture
after thoroughly brushing the surface to remove all dirt and
remains of loose powdered materials, applying emery paper,
Sand the surface, clean & wipe off loose dust, applying putty/
texture paint filler by putty knife / muslin pad, air dry for 2-3
hrs for the surface preparation including cost and conveyance of
all materials to work site and all operational, incidental, labour
charges, scaffolding charges, overheads and contractors profit
etc., complete for finished item of work in all floors for external
walls
Cellar to Fifth Floors

84 Supply & applying Melamine Polish Glossy/ Matt finish to the Supply & applying Melamine Polish Supply & applying Melamine Polish
wood works duly cleaning the surface and applying emery Glossy/ Matt finish to the wood Glossy/ Matt finish to the wood works
paper, sand the wood with 180 No., emery paper and then with works
320 No., emery paper, clean & wipe off loose dust, applying
suitable knifing paste filler / wood filler by putty knife / muslin
pad, air dry for 2 - 3 hrs, sand with 180 and 320 No., emery
paper, apply two component wood sealer, air dry for 24 hrs,
sand with 320 No emery paper, applying one coat of approved
spraying thinner (for spraying)/ applying one coat of approved
brushing thinner or general purpose thinner (for brushing) and
apply (either with spray or brush) two coats of approved brand
melamine including cost & labour charges, emery papers, cost
of thinner & melamine polish, over heads and contractors profit
etc., complete for finished item of work
Basement Floor & First Floors

#REF! Painting two coats with synthetic enamel paint Grade-II Painting two coats with synthetic Painting two coats with synthetic
VOC (Volatile Organic Compound) content less than 50 enamel paint Grade-II VOC enamel paint Grade-II VOC
grams/litre over primer coat of red oxide to new iron work
including cost and conveyance of all materials to site, incidental,
operational and all labour charges etc., and overheads &
contractors profit complete for finished item of work in all floors.
(SS No. 1201, 1212 & 1207).
Cellar to Fifth Floors
347 Supplying and fixing of two shutter cupboards as per Supplying and fixing of two shutter Supplying and fixing of two shutter
drawing with medium teak wood frames of size 75mm x 40mm cupboards cupboards
and MDF Board Interior grade both sides laminated 18mm thick
for shutters with 18mm x 12mm teak wood beading alround
and supplying and fixing powder coated MS fixtures 3 Nos.
butt hinges of size 100mm long(for each shutter), tower bolt 2
Nos. of 100mm x 10mm, 2 Nos of handles 100mm long and
standard locking arrangements for shutters including cost and
conveyance of all materials to site, labour charges, over heads
and contractor profit etc., complete for finished item of work.
Cellar to Fourth Floors

2951 Supplying and fixing Gyp board Fine line Grid false ceiling Supplying and fixing Gyp board Supplying and fixing Gyp board Fine
(GS-FLC-4.6)using 12.5mm thick Gyp Board sheet tiles of Fine line Grid false ceiling line Grid false ceiling
size 595mm x 595mm conforming to IS 2095 - 1992 fixing to
Gyp steel precoated GI wall angle of size 25mm x 25mm x
0.70mm thick along the perimeter of ceiling screw fixed to brick
work / partition at 610mm center to center and suspending the
frame work using precoated GI Tee section (24mm x 38mm x
0.7mm) from soffit at 1220mm center to center fixed with GI
Soffit Cleat, rawl plugs and steel expansion fasteners &
connecting clip to the GI Tee section with 4mm dia GI rod with
galvanised spring steel level clip of PVC unversal holding clips
system at 1200mm center to center and fixing the 12.5mm
Gypboard sheet tiles of size 595mm x 595mm and finishing two
coats of drywall top coat, overheads and contractor profit
complete for finished item of work in all floors.
Third floor & Fourth Floors
1086 Suplying and fabricating, erecting and fixing in position Suplying and fabricating, erecting Suplying and fabricating, erecting and
tabular trusses of approved design with M.S tube conforming and fixing in position tabular trusses fixing in position tabular trusses
to I.S specifications including roof frame work consisting of
rafters,ties struts and purlins including cost of foundations bolts,
cleats, bearings plates,etc.,complete as per the sketch
enclosed and including cost of painting with enmel paint 2
coats over a primary coat with red oxide paint including cost and
conveyance of all materials, labour charges for fabrication and
fixing, hire charges of all tools and plants, all incidental charges,
overheads and contractor profit etc., complete for finished item
of work as directed by the Engineer-in-Charge
Fifth Floor :

170 Supplying and fixing 50mm dia nominal bore Medium Supplying and fixing 50mm dia Supplying and fixing 50mm dia
Grade properties & weight as per IS 1239 ISI mark MS Tube nominal bore Medium Grade nominal bore Medium Grade
for fixing of GI Sheet including cost and conveyance of all
materials to work site and all operational, incidental, labour
charges etc., complete for finished item of work in all floors for
stair case head room roof.
Fifth Floor :

191 Roofing with UV resistant multi-wall polycarbonate sheets of Roofing with UV resistant multi-wall Roofing with UV resistant multi-wall
any colour 6mm thick fixed with Aluminium Universal glazing polycarbonate sheets polycarbonate sheets
set 40mm wide and as per drawing etc., complete excluding the
cost of purlins, rafters,trusses,aluminium universal glazing set
40mm wide including cost and conveyance of all materials,
labour charges, overheads and contractors profit etc., complete
for finished item of work
Fifth Floor :

38 Supplying and fixing Aluminium Universal glazing set Supplying and fixing Aluminium Supplying and fixing Aluminium
40mm wide for jointing and fixing Polycarbonate sheets Universal glazing set Universal glazing set
including cost and conveyance of all materials, labour charges,
overheads and contractors profit etc., complete for finished item
of work
Fifth Floor :
#REF! Providing and fixing of Expansion joint filler board for Providing and fixing of Expansion Providing and fixing of Expansion joint
buildings, columns, beams and slabs 25 mm thick including cost joint filler board filler board
and conveyance of all materials to site, all incidental,
operational, labour charges etc.overheads & contractors profit
complete for finished item of work as per approved drawing for
all floors
Cellar to Fourth Floors

42 Providing and fixing of 24 gauge alluminium sheet over Providing and fixing of 24 gauge Providing and fixing of 24 gauge
expansion joint groove of width 15cm fixed to walls / columns alluminium sheet over expansion alluminium sheet over expansion joint
at one edge and resting over the other block walls/columns joint groove groove
concealing expansion joint with slotted holes for free edge of
aluminium sheet to facilitate free movement of aluminium sheet
over the finished surface of expansion joint and wall face using
sheet metal screws with nylon receiver complete including cost
and conveyance of all materials to site, all incidental,
operational, labour charges , overheads & contractors profit
etc., complete for finished item of work as per approved drawing
(for all floors for vertical joints and bottom of slab)
Cellar to Fourth Floors
42 Providing specialized polysulphide sealant treatment to the Providing specialized polysulphide Providing specialized polysulphide
expansion joints (Size : 25mm x 12mm) duly a). Chipping and sealant treatment to the expansion sealant treatment to the expansion
removing of existing covering on expansion joints b). Cleaning joints joints
of the surface from dirt, dust and other contaminations
c).Application of one coat of - High performance specially
designed SBR latex polymer based bonding agent d). Providing
and application of Acrylic Polymer modified reinstatement
concrete /mortar to the damaged edges of joint and making the
groove. e]. Providing and fixing of masking tape on top of the
joint both sides f). Providing and fixing of Back up support
material of Backer rod to leave the depth of 12mm on the joint
g). Providing and application of one coat of polysulphide primer
on inner edges of Joint. h). Providing and application of Two
part Polysulphide sealant to a width of 25mm and 12mm depth
with putty knife and neat finish i). Removing of masking tape
and providing and application of two coats of Acrylic elastomeric
cementitious coating including cost and conveyance of all
materials, labour charges, overheads & contractors profit etc.,
complete for finished item of work
Cellar to Fourth Floors

30 Supply and delivery of encapsulated plastic steps Supply and delivery of encapsulated Supply and delivery of encapsulated
manufactured as per companies standard specification plastic steps plastic steps
including cost of materials packing as per companiess
standards, loading, transportation, unloading and stacking at
site of work , etc.,as applicalble including labour charges for
fixing etc. complete for finished item of work.

2 Supplying & fixing 602 x 602 mm CI man hole frame and Supplying & fixing 602 x 602 mm CI Supplying & fixing 602 x 602 mm CI
cover (light weight) 30 Kgs including cost and conveyance man hole frame and cover (light man hole frame and cover (light
and labour charges for fixing, overheads and contractor profit weight) 30 Kgs weight) 30 Kgs
etc., complete for finished item of work
1814 Construction of Granular sub-base by providing HBG Construction of Granular sub-base Construction of Granular sub-base by
material confirming to Grading - III of MORT & H Table 400- by providing HBG material providing HBG material confirming to
2 including cost and conveyance of all material to woek site and confirming to Grading - III of MORT Grading - III of MORT & H Table 400-2
spreading in uniform layers with motor grader or by approved & H Table 400-2
means, on prepared surface mixing by mix place method with
Rotavator/ approved means, at OMC and compacting with
vibratory roller to achieve the desired density etc., complete for
finished item of work as per MoRT& H specification 401 (4th
revision) and as directed by the Engineer- in - charge (Payment
will be made based on levels for finished item of work)

1451 Construction of un-reinforced, dowel jointed at expansion Construction of un-reinforced, Construction of un-reinforced, dowel
and construction joint only, plain cement concrete dowel jointed at expansion and jointed at expansion and construction
pavement, thickness as per design, over a prepared sub base, construction joint only, plain cement joint only, plain cement concrete
with 43 grade cement or any other type as per Clause 1501.2.2 concrete pavement pavement
M30 (Grade), coarse and fine aggregates conforming to IS :
383, maximum in a concrete mixer of not less than 0.2 cum
capacity and appropeiate weigh batcher using approved mix
design, laid in approved fixed side formwork (steel channel,
laying and fixing of 125 mictron thick polythene film, wedges,
steel plates including levelling the formwork as per drawing),
spreading the concrete with sholvels, rakes, compacted using
needle, scareed and plate vibrators and finished in continuous
operation including provision of contraction and expansion,
construction joints, applying debonding strips, primer, sealant,
dowel bars, near approaches to bridge / culvert and
construction joints, admixtures as approved, curing of concrete
slabs for 14- days, curing compound (where specified) and
water finishing to lines and grade as per drawing and Technical
Specification Clause 1501 MORD.

Sub Total ::(Civil Works)


Amount
Rate Unit
(Rs.)
APSS 308 #REF! ONE CUM #REF!

APSS 308 #REF! ONE CUM #REF!

APSS 308 #REF! ONE CUM #REF!


APSS 308 #REF! ONE CUM #REF!

APSS 402 #REF! ONE CUM #REF!

APSS 402 #REF! ONE CUM #REF!


APSS NO.309&310 #REF! ONE CUM #REF!

NA #REF! ONE SQM #REF!


APSS NO 402 #REF! ONE CUM #REF!

APSS NO 402 #REF! ONE CUM #REF!


APSS NO 402 #REF! ONE CUM #REF!

APSS NO 402 #REF! ONE CUM #REF!


APSS NO 402 #REF! ONE CUM #REF!

APSS NO 402 #REF! ONE CUM #REF!


APSS NO 402 #REF! ONE CUM #REF!

APSS NO 402 #REF! ONE CUM #REF!


APSS NO 402 #REF! ONE CUM #REF!

APSS NO 402 #REF! ONE CUM #REF!


APSS NO 402 #REF! ONE CUM #REF!

APSS NO 402 #REF! ONE CUM #REF!


APSS NO 402 #REF! ONE CUM #REF!

APSS NO 402 #REF! ONE CUM #REF!


APSS NO 402 #REF! ONE CUM #REF!

APSS NO 402 #REF! ONE CUM #REF!


APSS NO 402 #REF! ONE CUM #REF!

APSS NO 402 #REF! ONE CUM #REF!


APSS NO 402 #REF! ONE CUM #REF!

APSS NO 402 #REF! ONE CUM #REF!


APSS NO 402 #REF! ONE SQM #REF!

APSS NO 402 #REF! ONE SQM #REF!


APSS NO 402 #REF! ONE SQM #REF!

APSS NO 402 #REF! ONE SQM #REF!


APSS NO 402 #REF! ONE CUM #REF!

APSS NO 402 #REF! ONE SQM #REF!


APSS NO 402 #REF! ONE SQM #REF!

APSS NO 402 #REF! ONE CUM #REF!


APSS NO 402 #REF! ONE CUM #REF!

APSS NO 402 #REF! ONE CUM #REF!


APSS NO 402 #REF! ONE CUM #REF!

APSS NO 402 #REF! ONE CUM #REF!


APSS NO 402 #REF! ONE CUM #REF!

APSS NO 402 #REF! ONE SQM #REF!


APSS NO 402 #REF! ONE SQM #REF!

APSS NO 402 #REF! ONE SQM #REF!


APSS NO 402 #REF! ONE SQM #REF!

APSS NO 402 #REF! ONE SQM #REF!


APSS NO 402 #REF! ONE SQM #REF!

APSS NO 402 #REF! ONE SQM #REF!


APSS NO 402 #REF! ONE SQM #REF!

APSS NO 402 #REF! ONE SQM #REF!


APSS NO 402 #REF! ONE SQM #REF!

APSS NO 402 #REF! ONE SQM #REF!


APSS NO 402 #REF! ONE SQM #REF!

APSS NO 402 #REF! ONE SQM #REF!


APSS NO 402 #REF! ONE SQM #REF!

APSS NO 402 #REF! ONE SQM #REF!


APSS NO 402 #REF! ONE SQM #REF!

APSS NO 402 #REF! ONE SQM #REF!


APSS NO 402 #REF! ONE SQM #REF!

APSS NO 402 #REF! ONE CUM #REF!


APSS NO 402 #REF! ONE CUM #REF!
APSS NO 402 #REF! ONE SQM #REF!
APSS NO 402 #REF! ONE SQM #REF!
APSS NO 402 #REF! ONE SQM #REF!

APSS No. 402, 403 & #REF! ONE RM #REF!


903
APSS No. 402, 403 & #REF! ONE RM #REF!
903

APSS No. 402, 403 & #REF! ONE RM #REF!


903
APSS No. 402, 403 & #REF! ONE RM #REF!
903

APSS No. 402, 403 & #REF! ONE RM #REF!


903
APSS No. 402, 403 & #REF! ONE RM #REF!
903

APSS No. 402, 403 & #REF! ONE RM #REF!


903
APSS No. 402 & 403 #REF! ONE SQM #REF!

APSS No. 402 & 403 #REF! ONE SQM #REF!


APSS No. 402 & 403 #REF! ONE SQM #REF!

APSS No. 402 & 403 #REF! ONE SQM #REF!


APSS No. 402 & 403 #REF! ONE SQM #REF!

APSS No. 402 & 403 #REF! ONE SQM #REF!


APSS No. 402 & 403 #REF! ONE SQM #REF!

APSS No. 402 & 403 #REF! ONE SQM #REF!


APSS No. 402 & 403 #REF! ONE SQM #REF!

APSS No. 402 & 403 #REF! ONE SQM #REF!


APSS No. 402 & 403 #REF! ONE SQM #REF!

APSS No. 402 & 403 #REF! ONE SQM #REF!


APSS No. 402 #REF! ONE CUM #REF!

APSS No. 402 #REF! ONE CUM #REF!

APSS No. 402 #REF! ONE CUM #REF!


APSS No. 402 #REF! ONE CUM #REF!

APSS No. 402 #REF! ONE CUM #REF!

APSS No. 402 #REF! ONE CUM #REF!


APSS No. 402 & 403 #REF! ONE CUM #REF!

APSS No. 402 #REF! ONE CUM #REF!


APSS No. 402 #REF! ONE CUM #REF!

APSS No. 402 #REF! ONE CUM #REF!


APSS No. 402 #REF! ONE CUM #REF!

APSS No. 402 #REF! ONE CUM #REF!

APSS No. 501 & 504 #REF! ONE CUM #REF!


APSS No. 501 & 504 #REF! ONE CUM #REF!

APSS No. 501 & 504 #REF! ONE CUM #REF!

APSS No. 501 & 504 #REF! ONE CUM #REF!


APSS No. 501 & 504 #REF! ONE CUM #REF!

APSS No. 501 & 504 #REF! ONE CUM #REF!

APSS No. 501 & 504 #REF! ONE CUM #REF!


APSS No. 501 & 504 #REF! ONE CUM #REF!

APSS No. 501 & 509 #REF! ONE SQM #REF!


APSS No. 501 & 509 #REF! ONE SQM #REF!

APSS No. 501 & 509 #REF! ONE SQM #REF!


APSS No. 501 & 509 #REF! ONE SQM #REF!

APSS No. 501 & 509 #REF! ONE SQM #REF!


APSS No. 501 & 509 #REF! ONE SQM #REF!

APSS No. 501 & 509 #REF! ONE SQM #REF!


APSS No. 402 #REF! ONE CUM #REF!

APSS No. 402 #REF! ONE CUM #REF!

APSS No. 402 #REF! ONE CUM #REF!


APSS No. 402 #REF! ONE CUM #REF!

APSS No. 402 #REF! ONE CUM #REF!

APSS No. 402 #REF! ONE CUM #REF!


APSS No. 402 #REF! ONE CUM #REF!

APSS No. 126 #REF! ONE MT #REF!


APSS No. 126 #REF! ONE MT #REF!

APSS No. 126 #REF! ONE MT #REF!


APSS No. 126 #REF! ONE MT #REF!

APSS No. 126 #REF! ONE MT #REF!


APSS No. 126 #REF! ONE MT #REF!

APSS No. 126 #REF! ONE MT #REF!


APSS No. 126 #REF! ONE MT #REF!

APSS No. 126 #REF! ONE MT #REF!


APSS No. 126 #REF! ONE MT #REF!

APSS No. 126 #REF! ONE MT #REF!


APSS No. 126 #REF! ONE MT #REF!

APSS No. 126 #REF! ONE MT #REF!


APSS No. 126 #REF! ONE MT #REF!

SS 901,903 & 904 #REF! ONE SQM #REF!

SS 901,903 & 904 #REF! ONE SQM #REF!


SS 901,903 & 904 #REF! ONE SQM #REF!

SS 901,903 & 904 #REF! ONE SQM #REF!

SS 901,903 & 904 #REF! ONE SQM #REF!

SS 901,903 & 904 #REF! ONE SQM #REF!


SS 901,903 & 904 #REF! ONE SQM #REF!

SS 901,903 & 904 #REF! ONE SQM #REF!

SS 901,903 & 904 #REF! ONE SQM #REF!


SS 901,903 & 904 #REF! ONE SQM #REF!

SS 901,903 & 904 #REF! ONE SQM #REF!

SS 901,903 & 904 #REF! ONE SQM #REF!


SS 901,903 & 904 #REF! ONE SQM #REF!

SS 901,903 & 904 #REF! ONE SQM #REF!

SS 901,903 & 904 #REF! ONE SQM #REF!


SS 901,903 & 904 #REF! ONE SQM #REF!

SS 901,903 & 904 #REF! ONE SQM #REF!

SS 901,903 & 904 #REF! ONE SQM #REF!


SS 901,903 & 904 #REF! ONE SQM #REF!

SS 901,903 & 904 #REF! ONE SQM #REF!

SS 901,903 & 904 #REF! ONE SQM #REF!


SS 901,903 & 904 #REF! ONE SQM #REF!

APSS No.701 & 707 #REF! ONE SQM #REF!

APSS No.701 & 707 #REF! ONE SQM #REF!


APSS No.701 & 707 #REF! ONE SQM #REF!

APSS No.701 & 707 #REF! ONE SQM #REF!


APSS No.701 & 707 #REF! ONE SQM #REF!

APSS No.701 & 707 #REF! ONE SQM #REF!


APSS No.701 & 707 #REF! ONE SQM #REF!
APSS No.701 & 707 #REF! ONE SQM #REF!
APSS No.701 & 707 #REF! ONE SQM #REF!
APSS No.701 & 707 #REF! ONE SQM #REF!
APSS No.701 & 707 #REF! ONE SQM #REF!
APSS No.701 & 707 #REF! ONE SQM #REF!

S.S.701 & special #REF! ONE SQM #REF!


S.S.701 & special #REF! ONE SQM #REF!

S.S.701 & special #REF! ONE SQM #REF!


S.S.701 & special #REF! ONE SQM #REF!

S.S.701 & special #REF! ONE SQM #REF!


S.S.701 & special #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!


NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!


NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!


NA #REF! ONE SQM #REF!
S.S.701 & special #REF! ONE SQM #REF!

S.S.701 & special #REF! ONE SQM #REF!


S.S.701 & special #REF! ONE SQM #REF!

S.S.701 & special #REF! ONE SQM #REF!


S.S.701 & special #REF! ONE SQM #REF!

S.S.701 & special #REF! ONE SQM #REF!


S.S.701 & special #REF! ONE SQM #REF!

S.S.701 & special #REF! ONE SQM #REF!


S.S.701 & special #REF! ONE SQM #REF!

S.S.701 & special #REF! ONE SQM #REF!


S.S.701 & special #REF! ONE SQM #REF!

S.S.701 & special #REF! ONE SQM #REF!


S.S.701 & special #REF! ONE SQM #REF!

S.S.701 & special #REF! ONE SQM #REF!


S.S.701 & special #REF! ONE SQM #REF!

S.S.701 & special #REF! ONE SQM #REF!


S.S.701 & special #REF! ONE SQM #REF!

S.S.701 & special #REF! ONE SQM #REF!


S.S.701 & special #REF! ONE SQM #REF!

S.S.701 & special #REF! ONE SQM #REF!


S.S.701 & special #REF! ONE SQM #REF!

S.S.701 & special #REF! ONE SQM #REF!


S.S.701 & special #REF! ONE SQM #REF!

S.S.701 & special #REF! ONE SQM #REF!


APSS No.701 &707 #REF! ONE RM #REF!

APSS No.701 &707 #REF! ONE RM #REF!


APSS No.701 &707 #REF! ONE RM #REF!

APSS No.701 &707 #REF! ONE RM #REF!


APSS No.701 &707 #REF! ONE RM #REF!

APSS No.701 &707 #REF! ONE RM #REF!

NA #REF! ONE RM #REF!


NA #REF! ONE RM #REF!

NA #REF! ONE RM #REF!

NA #REF! ONE RM #REF!


NA #REF! ONE RM #REF!

NA #REF! ONE RM #REF!

NA #REF! ONE SQM #REF!


NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!


NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!


NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!


NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!


NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!


NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!


NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!


NA #REF! ONE SQM #REF!

NA #REF! ONE CUM #REF!

NA #REF! ONE CUM #REF!

NA #REF! ONE CUM #REF!

NA #REF! ONE SQM #REF!


APSS NO. 402 & 403 #REF! ONE CUM #REF!

APSS No. 901 & 903 #REF! ONE SQM #REF!


NA #REF! ONE SQM #REF!

APSS No. 901 & 903 #REF! ONE SQM #REF!


APSS No. 901 & 903 #REF! ONE SQM #REF!

APSS No. 901 & 903 #REF! ONE SQM #REF!


APSS No. 901 & 903 #REF! ONE SQM #REF!

APSS No. 1328 #REF! ONE RM #REF!

APSS NO.403&903 #REF! ONE SQM #REF!


APSS NO.403&903 #REF! ONE SQM #REF!

APSS NO.403&903 #REF! ONE SQM #REF!

APSS NO.403&903 #REF! ONE SQM #REF!


APSS NO.403&903 #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!


NA #REF! ONE SQM #REF!
NA #REF! ONE SQM #REF!
NA #REF! ONE SQM #REF!
NA #REF! ONE SQM #REF!
NA #REF! ONE SQM #REF!

NA #REF! ONE RM #REF!


NA #REF! ONE SQM #REF!
NA #REF! ONE SQM #REF!
NA #REF! ONE SQM #REF!
NA #REF! ONE SQM #REF!

NA #REF! ONE KG #REF!

NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!


NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!


NA #REF! ONE SQM #REF!
NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!


NA #REF! ONE RM #REF!

spn: 1108 #REF! ONE RM #REF!

NA #REF! ONE SQM #REF!


NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!


NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!

SS No. 1201, 1212 & #REF! ONE SQM #REF!


1207
NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!


NA #REF! ONE KG #REF!

NA #REF! ONE SQM #REF!

NA #REF! ONE SQM #REF!

NA #REF! ONE RM #REF!


NA #REF! ONE SQM #REF!

NA #REF! ONE RM #REF!


NA #REF! ONE RM #REF!

NA #REF! EACH #REF!

NA #REF! EACH #REF!


MoRT& H #REF! ONE CUM #REF!
specification 401 (4th
revision)

Technical #REF! ONE CUM #REF!


Specification Clause
1501 MORD.

#REF!
#REF!

ABSTRACT ESTIMATE FOR CIVIL WORKS

A HOSPITAL BUILDING D
B 130 KLD SEWERAGE TREATMENT PLANT E
C 4 LAKH LITERS SUMP F

Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
1 Earth work excavation for foundations (Mechanical Means) for
buildings in ordinary soils and depositing on bank for all lifts
and with an initial lead of 10m and up to 3m depth including all
operational,incidental, labour charges such as shoring,
sheeting, planking, strutting etc., and overheads & contractors
profit complete for finished item of work excluding dewatering
charges etc., as per SS 20 B(APSS 308)

10482.00 #REF! #REF!

2 Earth work excavation for foundations (Mechanical Means) for


buildings in ordinary soils and depositing on bank for all lifts
and with an initial lead of 10m and 3m to 6m depth including
all operational,incidental, labour charges such as shoring,
sheeting, planking, strutting etc., and overheads & contractors
profit complete for finished item of work excluding dewatering
charges etc., as per SS 20 B(APSS 308)

10909.00 #REF! #REF!

3 Earth work excavation for foundations (Mechanical Means) for


buildings in ordinary rock (not requiring blasting) and
depositing on bank for all lifts and with an initial lead of 10m and
up to 3m depth including all operational,incidental, labour
charges such as shoring, sheeting, planking, strutting etc., and
overheads & contractors profit complete for finished item of
work excluding dewatering charges etc., as per SS 20 B(APSS
308)

2621.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 271 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)

4 Earth work excavation for foundations for buildings in hard


rock (blasting prohibited) and depositing on bank for all lifts and
with an initial lead of 10m and up to 3m depth including all
operational,incidental, labour charges such as shoring,
sheeting, planking, strutting etc., and overheads & contractors
profit complete for finished item of work excluding dewatering
charges etc., as per SS 20 B(APSS 308)

575.00 #REF! #REF!

5 Plain Cement Concrete (1:4:8) (cement: fine aggregate:


Coarse aggregate) for foundations using coarse aggregate
40mm size hard , machine crushed granite from approved
quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
including cost and conveyance of all materials like cement,
sand, coarse aggregate, water etc. to site including all charges
for machine mixing and hire charges of concrete mixer, laying
concrete in foundations and under flooring bed, ramming in 15
cm layers finishing top surface to the required level curing
etc.,and overheads & contractors profit complete for finished
item of work. (APSS No. 402) For Foundation

619.00 #REF! #REF!

6 Plain Cement Concrete (1:5:10) (cement: fine aggregate:


Coarse aggregate) for foundations and under flooring bed
using coarse aggregate 40mm size hard , machine crushed
granite from approved quarry using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, sand, coarse aggregate, water etc. to site
including all charges for machine mixing and hire charges of
concrete mixer, laying concrete in foundations and under
flooring bed, ramming in 15 cm layers finishing top surface to
the required level curing etc.,and overheads & contractors profit
complete for finished item of work. (APSS No. 402)

#REF! #REF!

APMSIDC-PALASA ABS-CIVIL 272 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
7 Filling with useful available excavated earth (excluding rock)
with a lead of 50 m in trenches, sides of foundations and
basement with initial lead in layers not exceeding 15cm thick,
watering and ramming including cost and conveyance of water
to work site and all operaitonal, incidental, labour charges, hire
charges of T&P etc., and overheads & contractors profit
complete for fnished item of work (APSS NO.309&310)

20897.00 #REF! #REF!

8 Pre construction Anti termite treatment is a process in which


chemical toxic to subterrean tremites is apply/ inject into soil
during early stage of building Construction 2. Treatement of soil
Beneath the building and around the foundations conduct and
chemical use as per BIS - IS 6313 (Part -2) 2013 code
specification & CIB RC registered termiticide which creates a
continuous chemical barrier beneath the building which kills or
repels terminates & impervious to tremite entry 3. Imidacloprid
30.5% SC (IS 63131) dissolve 2.1 Ml/1 liter of water and apply
emulsion/solution @ 7.5 Litres/Square meter (Sqm) of internal,
external vertical surface of the colums, plinth beams (Back
filling) walls and floor junction, external perimeters, along
reatining wall @ 5.0 Liters/Sqm of the horizontal surface of
basement top surface of the basement filling below flooring bed
(Plinth) & @ 2.0 Litres/ Line meter at expansion joints. The
substructure of a depth of 500mm around coulmns & 300mm
deep around plinth beams, basements & floor filling area
including excavation channel along the wall & rodding etc. cost
& Conveyance of all materials to the site, cost of labour for
sparying, rodding, overheads and contractor profit etc. complete
for furnished item of work as per the approval of the Engineer-
in-charge

3237.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 273 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
9 Supply and placing of the Design Mix Concrete M 30 grade
corresponding to IS 456 with minimum cement content of
400 kgs per 1 cum of concrete using batching and mixing
plant of 15 cum per hour capacity with 20mm size graded
machine crushed hard granite metal (coarse aggregate - as per
IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved
quarry including cost and conveyance of all materials like
cement, fine aggregate (sand) coarse aggregate, water etc., to
site, centering using steel scaffolding pipes , jack props ,
wallers , foot plates , brackets , steel centering plates etc.,
including all operational, incidental and labour charges,
transporting concrete using transit mixer, lifting concrete
mechnically, laying concrete using concrete pump, vibrating,
curing etc., and overheads & contractors profit complete but
excluding cost of steel and its fabrication charges for finished
item of work (APSS No. 402)

a) Footings 24.00 #REF! #REF!

b) Raft Concrete 2796.00 #REF! #REF!

c) Column Pedastals 119.00 #REF! #REF!

d) Plinth Beams 176.00 #REF! #REF!

e) Tie Beam 35.00 #REF! #REF!

f) STP/Sump base Slab #REF! #REF!

g) Haunch Concrete #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 274 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
10 Supply and placing of the Design Mix Concrete M 30 grade
corresponding to IS 456 with minimum cement content of
400 kgs per 1 cum of concrete using batching and mixing
plant of 15 cum per hour capacity with 20mm size graded
machine crushed hard granite metal (coarse aggregate - as per
IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved
quarry including cost and conveyance of all materials like
cement, fine aggregate (sand) coarse aggregate, water etc., to
site, centering using casurina ballies, bamboos, wooden
reapers, runners, wood posts, wall plates etc., including all
operational, incidental and labour charges ,transporting
concrete using transit mixer, lifting concrete mechnically, laying
concrete using concrete pump, vibrating, curing , overheads &
contractors profit etc., complete but excluding cost of steel and
its fabrication charges for finished item of work (APSS No. 402)

a) Columns :
Cellar : 145.00 #REF! #REF!

Basement Floor : 251.00 #REF! #REF!

First Floor : 214.00 #REF! #REF!

Second Floor : 214.00 #REF! #REF!

Fourth Floor : 214.00 #REF! #REF!

Fifth Floor : 45.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 275 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
b) Lintels
Cellar : 10.00 #REF! #REF!

Basement Floor : 22.00 #REF! #REF!

First Floor : 12.00 #REF! #REF!

Second Floor : 21.00 #REF! #REF!

Third Floor : 15.00 #REF! #REF!

Fourth Floor : 21.00 #REF! #REF!

Fifth Floor : 1.00 #REF! #REF!

c) 100mm thick Drain side walls


First Floor : #REF! #REF!

d) 150mm thick Water Tank side walls


First Floor : #REF! #REF!

Fifth Floor : 208.00 #REF! #REF!

e) 230mm thick Retaining wall


Cellar : 1098.00 #REF! #REF!

Basement Floor : 1098.00 #REF! #REF!

f) 300mm thick STP Side walls


First Floor : #REF! #REF!

g) 450mm thick STP/Sump side walls


First Floor : #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 276 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
h) Roof Beams :
un supported height up to 3.66 m
Cellar : 98.00 #REF! #REF!

Basement Floor : 161.00 #REF! #REF!

First Floor : 161.00 #REF! #REF!

Second Floor : 161.00 #REF! #REF!

Fourth Floor : 161.00 #REF! #REF!

Fifth Floor : 17.00 #REF! #REF!

i) ROOF SLABS :
i) Roof Slabs 125mm thick :
Cellar : 283.00 #REF! #REF!

Basement Floor : 283.00 #REF! #REF!

First Floor : 284.00 #REF! #REF!

Second Floor : 284.00 #REF! #REF!

Fourth Floor : 283.00 #REF! #REF!

Fifth Floor : 181.00 #REF! #REF!

ii) Roof Slabs 150mm thick :


Cellar : 762.00 #REF! #REF!

Basement Floor : 1786.00 #REF! #REF!

First Floor : 1652.00 #REF! #REF!

Second Floor : 1643.00 #REF! #REF!

Fourth Floor : 1647.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 277 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)

Fifth Floor : 195.00 #REF! #REF!

ii) Roof Slabs 175mm thick :


Cellar : 831.00 #REF! #REF!

Basement Floor : 1170.00 #REF! #REF!

First Floor : 1192.00 #REF! #REF!

Second Floor : 1192.00 #REF! #REF!

Fourth Floor : 1170.00 #REF! #REF!

11 Reinforced Cement Concrete M 20 nominal mix using


12mm size hard granite machine crushed graded metal
(coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to
Part 8) from approved quarry, using a minimum quantity of 350
kgs. of cement per 1 cum of concrete using concrete Mixer 10 /
7 cft (0.2 / 0.8 cum) capacity including cost and conveyance of
all materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for 100mm thick precast
slabs

First Floor : #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 278 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
12 Supply and placing of the Design Mix Concrete M 30 grade
corresponding to IS 456 with minimum cement content of
400 kgs per 1 cum of concrete using batching and mixing
plant of 15 cum per hour capacity with 20mm size graded
machine crushed hard granite metal (coarse aggregate - as per
IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved
quarry including cost and conveyance of all materials like
cement, fine aggregate (sand) coarse aggregate, water etc., to
site, centering using steel scaffolding pipes , jack props ,
wallers , foot plates , brackets , steel centering plates
etc.,including all operational, incidental and labour charges
,transporting concrete using transit mixer, lifting concrete
mechnically, laying concrete using concrete pump, vibrating,
curing , overheads & contractors profit etc., complete but
excluding cost of steel and its fabrication charges for finished
item of work (APSS No. 402)

a) Columns :
un supported height up to 4.27 m
Third Floor : 251.00 #REF! #REF!

b) Roof Beams
un supported height up to 4.27 m
Third Floor : 161.00 #REF! #REF!

c) Roof Slab 125mm thick


un supported height up to 4.27 m
Third Floor : 283.00 #REF! #REF!

d) Roof Slab 150mm thick


un supported height up to 4.27 m
Third Floor : 1647.00 #REF! #REF!

e) Roof Slab 175mm thick


un supported height up to 4.27 m
Third Floor : 1170.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 279 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)

13 Supply and placing of the Design Mix Concrete M 30 grade


corresponding to IS 456 with minimum cement content of 400
kgs per 1 cum of concrete using batching and mixing plant of 15
cum per hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand), coarse aggregate, water etc., to site,
centering using casurina ballies , bamboos , wooden reapers ,
runners , wood posts , wall plates etc., for 60cm wide sun-
shades 7.5cm thick at fixed end and 5cm thick at free end with
an average thickness of 6.25cm including all operational,
incidental and labour charges , transporting concrete using
transit mixer, lifting concrete mechnically, laying concrete using
concrete pump, curing, overheads & contractors profit complete
etc., but excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402, 403 & 903)

Cellar : 163.00 #REF! #REF!

Basement Floor : 318.00 #REF! #REF!

First Floor : 154.00 #REF! #REF!

Second Floor : 231.00 #REF! #REF!

Third Floor : 102.00 #REF! #REF!

Fourth Floor : 221.00 #REF! #REF!

Fifth Floor : 9.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 280 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
14 Reinforced Cement Concrete M 20 nominal mix using
12mm size hard granite machine crushed graded metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for platforms and
shelves.

a 50mm thick platforms / lofts:


Cellar : 19.00 #REF! #REF!

Basement Floor : 120.00 #REF! #REF!

First Floor : 34.00 #REF! #REF!

Second Floor : 39.00 #REF! #REF!

Third Floor : 29.00 #REF! #REF!

Fourth Floor : 192.00 #REF! #REF!

b 25mm thick shelves :


Cellar : 3.00 #REF! #REF!

Basement Floor : 40.00 #REF! #REF!

First Floor : 9.00 #REF! #REF!

Second Floor : 17.00 #REF! #REF!

Third Floor : 71.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 281 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)

Fourth Floor : 108.00 #REF! #REF!

15 Plain Cement Concrete M 20 nominal mix using 20mm size


graded machine crushed hard granite metal (coarse aggregate -
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity including cost and conveyance of all materials like
cement, fine aggregate(sand), coarse aggregate, water etc. to
site including all charges centering, labour charges such as
weigh batching, machine mixing, hire charges of concrete
mixer, laying concrete in position, curing etc., & lift charges ,
and overheads & contractors profit for steps for finished item of
work. (APSS No. 402)

Cellar : 4.00 #REF! #REF!

Basement Floor : 6.00 #REF! #REF!

First Floor : 6.00 #REF! #REF!

Second Floor : 6.00 #REF! #REF!

Third Floor : 6.00 #REF! #REF!

Fourth Floor : 6.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 282 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
16 Reinforced Cement Concrete M 20 nominal mix using
12mm size hard granite machine crushed graded metal
(coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to
Part 8) from approved quarry, using a minimum quantity of 350
kgs. of cement per 1 cum of concrete using concrete Mixer 10 /
7 cft (0.2 / 0.8 cum) capacity including cost and conveyance of
all materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for sill slabs.

Cellar : 1.00 #REF! #REF!

Basement Floor : 2.00 #REF! #REF!

First Floor : 1.90 #REF! #REF!

Second Floor : 3.90 #REF! #REF!

Third Floor : 2.00 #REF! #REF!

Fourth Floor : 3.30 #REF! #REF!

17 Brick masonry for panel walls in superstructure with CM


(1:8) prop: (Cement : Sand) using common burnt clay
bricks of class as per Table- I of IS:1077-1992, Non- Modular
or traditional size 23 x 11 x 7 cms from approved source having
minimum crushing strength of 40 Kg/Sqcm. including cost and
conveyance of all materials like cement, screened sand, bricks,
water etc., to site, labour charges, like mixing cement mortar,
scaffolding charges, constructing masonry, lift charges, curing,
etc.,and overheads & contractors profit complete for finished
item of work. (APSS No. 501 & 504).

Cellar : 245.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 283 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)

Basement Floor : 472.00 #REF! #REF!

First Floor : 445.00 #REF! #REF!

Second Floor : 368.00 #REF! #REF!

Third Floor : 580.00 #REF! #REF!

Fourth Floor : 388.00 #REF! #REF!

Fifth Floor : 86.00 #REF! #REF!

For Compound wall : #REF! #REF!

18 Reinforced Brick Masonry for partition walls (11.0 cm thick)


in CM (1:4) prop. (Cement : Sand) using common burnt clay
bricks of class as per Table- I of IS:1077-1992, Non- Modular
or traditional size 23 x 11 x 7 cms from approved source
having minimum crushing strength of 40 Kg/Sq.cm and placing
2 Nos. of 6mm M.S plain rods in every third layer with free ends
of the reinforcement pegged into mortar joints of main brick
walls where applicable including cost and conveyance of all
materials like cement, steel, sand, bricks, water etc., to site, all
operational, incidental charges such as labour charges for
mixing cement mortar, scaffolding charges, constructing
masonry, lift charges, curing, etc., and overheads & contractors
profit but excluding cost of steel and its fabrication charges
complete for finished item of work. (APSS No. of 501 & 509)

Cellar : 238.00 #REF! #REF!

Basement Floor : 1262.00 #REF! #REF!

First Floor : 1358.00 #REF! #REF!

Second Floor : 1394.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 284 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)

Third Floor : 1726.00 #REF! #REF!

Fourth Floor : 1161.00 #REF! #REF!

Fifth Floor : 458.00 #REF! #REF!

19 Plain Cement Concrete (1:3:6) nominal mix using 20mm


size graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8
cum) capacity including cost and conveyance of all materials
like cement, fine aggregate(sand), coarse aggregate, water etc.
to site including all charges for machine mixing, hire charges of
concrete mixer, laying concrete in position, curing etc., & lift
charges , and overheads & contractors profit for bed blocks &
hold fasts for finished item of work. (APSS No. 402)

Cellar : 5.80 #REF! #REF!

Basement Floor : 12.60 #REF! #REF!

First Floor : 14.00 #REF! #REF!

Second Floor : 18.00 #REF! #REF!

Third Floor : 13.00 #REF! #REF!

Fourth Floor : 17.00 #REF! #REF!

Fifth Floor : 1.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 285 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
20 Providing Thermo Mechanically Treated (TMT) (Fe 500 / Fe
500 D grade as per IS 1786-1979) of different diameters for
RCC works including labour charges for straightening, cutting,
bending to required sizes and shapes, placing in position with
cover blocks of approved materials and size and tying and lap-
splicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and drawings,
including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars
including cost and conveyance of binding wire, cover blocks and
all incidental, operational, labour charges such as cutting,
bending, placing in position, tying etc., and overheads &
contractors profit complete for finished item of work.( APSS
No.126)

Cellar : 360.72 #REF! #REF!

Basement Floor : 152.40 #REF! #REF!

First Floor : 114.20 #REF! #REF!

Second Floor : 115.80 #REF! #REF!

Third Floor : 122.50 #REF! #REF!

Fourth Floor : 115.60 #REF! #REF!

Fifth Floor : 29.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 286 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
21 Providing Mild steel (MS) steel bars (Fe 250 grade as per IS
432) of different diameters including labour charges for
straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and
size and tying and lap-splicing with binding wire of 18 SWG,
forming grills for reinforcement work as per approved designs
and drawings, including cost and conveyance of steel bars,
including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire,
cover blocks and all incidental, operational, labour charges such
as cutting, bending, placing in position, tying etc., and
overheads & contractors profit complete for finished item of
work.( APSS No.126)

Cellar : 0.86 #REF! #REF!

Basement Floor : 2.60 #REF! #REF!

First Floor : 0.86 #REF! #REF!

Second Floor : 1.86 #REF! #REF!

Third Floor : 1.67 #REF! #REF!

Fourth Floor : 3.03 #REF! #REF!

Fifth Floor : 0.23 #REF! #REF!

22 Ornamental ceiling plastering 12mm thick single coat in CM


(1:5) using screened sand including cost and conveyance of
all materials like cement, sand, water etc., to site and all
operational, incidental charges on materials and including cost
of all labour charges for mixing mortar, finishing, curing as
directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work.(SS
901,903 & 904)

Cellar : 1837.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 287 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)

Basement Floor : 2781.00 #REF! #REF!

First Floor : 2683.00 #REF! #REF!

Second Floor : 2746.00 #REF! #REF!

Third Floor : 2163.00 #REF! #REF!

Fourth Floor : 459.00 #REF! #REF!

Fifth Floor : 364.00 #REF! #REF!

23 Plastering 12mm thick in two coats using screened sand


with base coat of 8mm thick in CM (1:6) and top coat of 4mm
thick in CM (1:4) with dubara sponge finishing including cost
and conveyance of all materials like cement, sand, water etc., to
site and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer - in - charge etc., and overheads &
contractors profit complete for finished item of work. (SS
901,903 & 904) For Internal Walls

Cellar : 1294.00 #REF! #REF!

Basement Floor : 3650.00 #REF! #REF!

First Floor : 3640.00 #REF! #REF!

Second Floor : 3511.00 #REF! #REF!

Third Floor : 4193.00 #REF! #REF!

Fourth Floor : 2936.00 #REF! #REF!

Fifth Floor : 407.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 288 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
24 Plastering 20mm thick in two coats using screened sand
with base coat of 16mm thick in CM(1:6) and top coat of 4mm
thick in CM(1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site
and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work .(SS
901,903 & 904)
For Internal Walls & External Walls

Cellar : 1658.00 #REF! #REF!

Basement Floor : 3895.00 #REF! #REF!

First Floor : 4227.00 #REF! #REF!

Second Floor : 3781.00 #REF! #REF!

Third Floor : 4956.00 #REF! #REF!

Fourth Floor : 4269.00 #REF! #REF!

Fifth Floor : 1419.00 #REF! #REF!

25 Plastering 12mm thick single coat in CM(1:5) using


screened sand including cost and conveyance of all materials
like cement, sand, water etc., to site and all operational,
incidental charges on materials and including cost of all labour
charges for mixing mortar, finishing, curing as directed by
Engineer-in-charge etc., and overheads & contractors profit
complete for finished item of work.(SS 901,903 & 904)

#REF! #REF!

APMSIDC-PALASA ABS-CIVIL 289 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
26 Flooring with non-skid white full body Ceramic floor tiles of
size 300 mm x 300 mm and thickness between 7-8 mm 1st
quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to
15) of any colour and finish in all shades and designs as
approved by Engineer-in-charge, set over base coat of cement
mortar (1:8), 12mm thick using screened sand over CC bed
already laid or RCC roof slab, including neat cement slurry of
honey like consistency spread @ 3.3 Kgs per sqm & jointed
neatly with white cement paste to full depth mixed with pigment
of matching shade, including cost of all materials like cement,
screened sand , water and tiles etc., and overheads &
contractors profit complete for finished item of work. (APSS
No.701 & 707) For Toilets

Cellar : 78.00 #REF! #REF!

Basement Floor : 249.00 #REF! #REF!

First Floor : 312.00 #REF! #REF!

Second Floor : 180.00 #REF! #REF!

Third Floor : 100.00 #REF! #REF!

Fourth Floor : 130.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 290 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
27 Flooring with non-skid Double charged / multi charged
stain free full body porcelain vitrified tiles with double layer
pigment of Size 600 x 600 mm and thickness between 8-10
mm 1st quality conforming to IS:13711, IS:13712, IS:13630
(Parts 1 to 15) of any colour and finish in all shades and designs
with borders and design as per the approved flooring pattern as
directed by the Engineer-In -Charge, laying tiles using spacers
of 2mm thick, set over a base coat of CM (1:8) prop. 12mm
thick using screened sand over CC bed already laid or RCC
roof slab , including neat cement slurry of honey like
consistancy spread @ 3.3 kgs per sqm. and jointed neately
with white cement paste to full depth mixed with pigment of
matching shade including cost and conveyance of all
materials like cement, sand, water, tiles, white cement etc., to
site (excluding cost of C.C. bed) including cost of base coat
and all labour charges for mixing of cement mortar, laying tiles
to required slope as directed by the Engineer- in-charge
etc.,and overheads & contractors profit complete for finished
item of work. (APSS No.701 & 707)

Cellar : 369.00 #REF! #REF!

Basement Floor : 1444.00 #REF! #REF!

First Floor : 900.00 #REF! #REF!

Second Floor : 2352.00 #REF! #REF!

Third Floor : 2403.00 #REF! #REF!

Fourth Floor : 2463.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 291 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
28 Flooring with 16 mm to 18 mm thick high polished granite
stone slabs other than black and regular colours (i.e. of
shades like paradiso / bala flower / copper silk / laka red /
lavender blue) with borders and design as per the pattern
approved by the Engineer-in-Charge of length not less than
2.43 mts set over base coat of cement mortar (1:8) , 20mm thick
using screened sand over CC bed already laid or RCC roof slab
including neat grey cement slurry of honey like consistency
spread @ 3.3 Kg per sqm and jointed neatly with white cement
paste mixed with pigment of matching shade to full depth
including cost and conveyance of all materials like cement ,
sand , water , granite slabs etc., to work site and all operational,
incidental labour & lift charges, polishing charges, cost of base
coat and overheads & contractors profit complete for finished
item of work (S.S.701 & special)

Cellar : 144.00 #REF! #REF!

Basement Floor : 986.00 #REF! #REF!

First Floor : 1367.00 #REF! #REF!

Second Floor : 112.00 #REF! #REF!

Third Floor : 43.00 #REF! #REF!

Fourth Floor : 43.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 292 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
29 Flooring with chequered Cement Concrete heavy duty tiles
conforming to IS: 13801 using aggregates, cement, pigments of
size 300mm x 300 mm and thickness 25 mm of any shades as
approved by Engineer - In - Charge set over base coat of
cement mortar (1:6), 12 mm thick using screened sand over CC
bed alredy laid or RCC roof slab including neat cement slurry of
honey like consistency spread @ 3.3 kgs per sqm and jointed
with neat white cement to full depth mixed with pigment of
matching shade including cost and conveyance of all materials
like cement, sand, water and tiles etc.,and overheads &
contractors profit complete for finished item of work.

Cellar : 102.00 #REF! #REF!

Basement Floor : 102.00 #REF! #REF!

First Floor : 104.00 #REF! #REF!

Second Floor : 102.00 #REF! #REF!

Third Floor : 104.00 #REF! #REF!

Fourth Floor : 104.00 #REF! #REF!

30 Supply of precast concrete blocks for paving of M-40 grade


and thickness not less than 80 mm for Medium traffic areas
conforming to IS 15658:2006 in all shapes and designs as per
the manufacturer's specification including cost and conveyance
of all materials and all labour charges etc.

Cellar : 80.00

Basement Floor : 109.00

First Floor : 109.00


298.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 293 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)

31 Vaccum dewatering cement concrete flooring 50mm thick


using M 30 grade design mix corresponding to IS 456 with
minimum cement content of 400 kgs per 1 cum of concrete and
required quantity of Chemical Admixtures per 1 cum of concrete
using WEIGH BATCHER / MIXER with 20mm size graded
machine crushed hard granite metal (coarse aggregate - as per
IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved
quarry in panels as per drawing / design, laid to proper level and
slope including consolidating with power driven mechanical
vibrators (both needle & screed vibrators), dewatering by
vacuum process "Tremix" method, floated with neat cement and
power troweled to achieve smooth finishing, including MS
Shuttering, finishing, rounding of the edges, curing including
cost and conveyance of all materials like cement, coarse
aggregate, sand etc., to site, centering, shuttering, machine
mixing, laying concrete, vibrating, curing, hire charges of all
tools and plants, all other incidental and operational charges,
labour charges and all taxes etc., complete for finished item of
work but excluding cost of steel and its fabrication charges for
finished item of work. For Cellar Floor

1144.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 294 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
32 Providing 16 mm to 18 mm thick high polished leather
finish granite stone slabs (steel grey or pearl black) with
borders and design as per the pattern approved by the
Engineer-in-Charge of length not less than 2.43 mts set over
base coat of cement mortar (1:5) , 12mm thick using screened
sand over CC bed already laid or RCC roof slab including neat
grey cement slurry of honey like consistency spread @ 3.3 Kg
per sqm and jointed neatly with white cement paste mixed with
pigment of matching shade to full depth including cost and
conveyance of all materials like cement , sand , water , granite
slabs etc., to work site and all operational, incidental labour & lift
charges, full rounding the edges of treads , polishing charges,
cost of base coat and overheads & contractors profit complete
for finished item of work for treads and risers (S.S.701 &
special)

a Treads of 0.30m wide :


Cellar : 43.00 #REF! #REF!

Basement Floor : 82.00 #REF! #REF!

First Floor : 77.00 #REF! #REF!

Second Floor : 82.00 #REF! #REF!

Third Floor : 78.00 #REF! #REF!

Fourth Floor : 66.00 #REF! #REF!

b Risers of 0.15m height :


Cellar : 24.00 #REF! #REF!

Basement Floor : 44.00 #REF! #REF!

First Floor : 43.00 #REF! #REF!

Second Floor : 44.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 295 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
Third Floor : 42.00 #REF! #REF!

Fourth Floor : 36.00 #REF! #REF!

33 Flooring with 16 mm to 18 mm thick high polished granite


stone slabs black colour as approved by the Engineer-in-
Charge of length not less than 2.43 mts set over base coat of
cement mortar (1:8) , 20mm thick using screened sand over CC
bed already laid or RCC roof slab including neat grey cement
slurry of honey like consistency spread @ 3.3 Kg per sqm and
jointed neatly with white cement paste mixed with pigment of
matching shade to full depth including cost and conveyance of
all materials like cement , sand , water , granite slabs etc., to
work site and all operational, incidental labour & lift charges,
half rounding the edge , polishing charges, cost of base coat
and overheads & contractors profit complete for finished item of
work for platforms (S.S.701 & special)

Cellar : 9.00 #REF! #REF!

Basement Floor : 72.00 #REF! #REF!

First Floor : 25.00 #REF! #REF!

Second Floor : 27.00 #REF! #REF!

Third Floor : 14.00 #REF! #REF!

Fourth Floor : 161.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 296 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
34 Providing window sills with 16 mm to 18 mm thick high
polished granite stone slabs black colour as approved by
the Engineer-in-Charge set over base coat of cement mortar
(1:8) , 20mm thick using screened sand over CC bed already
laid including neat grey cement slurry of honey like consistency
spread @ 3.3 Kg per sqm and jointed neatly with white cement
paste mixed with pigment of matching shade to full depth
including cost and conveyance of all materials like cement ,
sand , water , granite slabs etc., to work site and all operational,
incidental labour & lift charges, half rounding the edge ,
polishing charges, cost of base coat and overheads &
contractors profit complete for finished item of work (S.S.701 &
special)

Cellar : 11.00 #REF! #REF!

Basement Floor : 31.00 #REF! #REF!

First Floor : 38.00 #REF! #REF!

Second Floor : 75.00 #REF! #REF!

Third Floor : 40.00 #REF! #REF!

Fourth Floor : 66.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 297 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
35 Providing skirting 10 cm height with Double charged / multi
charged stain free full body porcelain vitrified tiles with
double layer pigment of Size 600 x 600 mm and thickness
between 8-10 mm of any colour and finish in all shades and
designs, length equal to flooring tiles, flushed to wall surface to
set over base coat of CM(1:5) 12 mm thick using screened sand
with cement slurry of honey like consistency spread at the rate
of 3.30 kgs per sqm and jointing with white cement paste mixed
with pigment of matching shade to full depth, including cost of
all materials like tiles, cement, sand and water etc.,and
overheads & contractors profit complete for finished item of
work.(APSS No.701 &707)

Cellar : 314.00 #REF! #REF!

Basement Floor : 1488.00 #REF! #REF!

First Floor : 912.00 #REF! #REF!

Second Floor : 1110.00 #REF! #REF!

Third Floor : 1191.00 #REF! #REF!

Fourth Floor : 783.00 #REF! #REF!

36 Providing skirting to internal walls 10 cm height with High


Polished Granite 16 mm to 18 mm thick up to 8'-00 (2.43 M)
other than black and regular colours, length equal to flooring
slabs set over base coat of CM(1:5) 12 mm thick using
screened sand with cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and jointing with white
cement paste mixed with pigment of matching shade to full
depth, including cost of all materials like tiles, cement, sand and
water etc., and overheads & contractors profit complete for
finished item of work.

Cellar : 120.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 298 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)

Basement Floor : 121.00 #REF! #REF!

First Floor : 78.00 #REF! #REF!

Second Floor : 121.00 #REF! #REF!

Third Floor : 78.00 #REF! #REF!

Fourth Floor : 78.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 299 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
37 Providing dadooing with glazed white full body ceramic
wall tiles of size 200mm x 300 mm / 245 mm x 325 mm and
thickness 6 mm 1st quality conforming to IS:13711, IS:13712,
IS:13630 (Parts 1 to 15) of any colour and finish in all shades
and designs with borders as approved by Engineer-in-Charge
flushed to wall surface set over base coat of CM(1:5) 12 mm
thick using screened sand with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per sqm and jointing
with white cement paste mixed with pigment of matching shade
to full depth, including cost of all materials like tiles, cement,
sand and water etc., and overheads & contractors profit
complete for finished item of work.

Cellar : 233.00 #REF! #REF!

Basement Floor : 525.00 #REF! #REF!

First Floor : 993.00 #REF! #REF!

Second Floor : 772.00 #REF! #REF!

Third Floor : 454.00 #REF! #REF!

Fourth Floor : 542.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 300 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
38 Providing dadooing with glazed full body porcelain wall
tiles of size 300mm x 600 mm with any type of design texture
such as marble finish, wooden, bamboo, stone finishes etc.,
scratch less, stain free and thickness between 6-8 mm 1st
quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to
15) of any colour and finish in all shades and designs with
borders and design as per the approved pattern as approved by
Engineer-in-Charge flushed to wall surface set over base coat
of CM(1:5) 12 mm thick using screened sand with cement slurry
of honey like consistency spread at the rate of 3.30 kgs per sqm
and jointing with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials like
tiles, cement, sand and water etc., and overheads & contractors
profit complete for finished item of work.

Cellar : 6.00 #REF! #REF!

Basement Floor : 559.00 #REF! #REF!

First Floor : 784.00 #REF! #REF!

Second Floor : 1086.00 #REF! #REF!

Third Floor : 1341.00 #REF! #REF!

Fourth Floor : 1578.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 301 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
39 Providing cladding to walls with High Polished Granite 16
mm to 18 mm thick up to 8'-00 (2.43 M) other than black and
regular colours, length equal to flooring slabs set over base coat
of CM(1:5) 12 mm thick using screened sand with cement slurry
of honey like consistency spread at the rate of 3.30 kgs per sqm
and jointing with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials like
tiles, cement, sand and water etc., and overheads & contractors
profit complete for finished item of work.

Cellar : 12.00 #REF! #REF!

Basement Floor : 247.00 #REF! #REF!

First Floor : 27.00 #REF! #REF!

Second Floor : 13.00 #REF! #REF!

Third Floor : 5.00 #REF! #REF!

Fourth Floor : 5.00 #REF! #REF!

40 Filling with well burnt cinder aggregate as per IS:2686-1977


in sunken slabs including cost and conveyance of cinder,
labour charges for filling, ramming, overheads and contractor
profit etc., complete for finished item of work

First Floor : 40.00 #REF! #REF!

Second Floor : 40.00 #REF! #REF!

Third Floor : 41.00 #REF! #REF!

Fourth Floor : 61.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 302 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
41 Reinforced cement concrete (1:5:10) proportion (Cement:
fine aggregates: coarse aggregate) using 40mm size (SS5)
hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand), coarse aggregate, water etc., to site including
centering using Casurina Ballies , Bamboos , Wooden
Reapers , Runners , Wood Posts , Wall Plates etc., shuttering,
machine mixing, laying concrete, lifting concrete manually ,
vibrating, curing, etc., and overheads & contractors profit
complete as per drawings but excluding cost of steel and it's
fabrication charges for finished item of work (APSS NO. 402 &
403) for dummy columns.

Fifth Floor : 40.00 #REF! #REF!

42 Providing specialized high performance acrylic polymer modified


elastomeric cementitious waterproof coating to the bottom and
sides of sunken slabs of toilets duly cleaning of the surface from
dirt, dust and other contaminations, providing and application of
two coats of high performance Acrylic polymer modified
Elastomeric cementitious waterproof coating ( 1.8 Sq. Mtr. /
Kg /Each Coat ) including cost and conveyance of all materials
to site, operationals & incidental charges, lift charges etc., and
overheads & contractors profit complete for finished item of
work

First Floor : 28.00

Second Floor : 28.00

Third Floor : 29.00

Fourth Floor : 43.00

Fifth Floor : 337.00


465.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 303 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
43 Providing impervious coat to exposed RCC roof slab
surfaces of sump , sump side wall,sump bottom slab,in side of
septic tank , in sunken slabs etc. to required slopes with CM
(1:3) prop. using screened sand 12mm thick mixed with
integral cement water proofing liquid confirming to IS: 2645-
2003 manufactured by reputed manufacturers as approved by
Engineer-in-charge at 200ml per one bag of cement, laid over
roof slab when it is green, finished smooth with a floating coat of
neat cement and thread lining at regular intervals of
45cmx45cm where ever necessary including cost and
conveyance of all materials like cement, sand, water proofing
compound, water etc., to site, operational, incidental, and labour
charges for mixing mortar, laying, lift charges, rendering smooth
and thread lining, curing including rounding off junctions of wall
and slab etc., and overheads & contractors profit complete for
finished item of work. (APSS No. 901 & 903).

First Floor #REF! #REF!

44 Providing impervious coat to exposed RCC roof slab


surfaces to required slopes with CM (1:3) prop. using screened
sand 20mm thick (average) mixed with integral cement water
proofing liquid confirming to IS: 2645-2003 manufactured by
reputed manufacturers as approved by Engineer-in-charge at
200ml per one bag of cement, laid over roof slab when it is
green, finished smooth with a floating coat of neat cement and
thread lining at regular intervals of 45cmx45cm including cost
and conveyance of all materials like cement, sand, water
proofing compound, water etc., to site, operational, incidental,
and labour charges for mixing mortar, laying, lift charges,
rendering smooth and thread lining, curing including rounding
off junctions of wall and slab etc., and overheads & contractors
profit complete for finished item of work. (APSS No. 901 &
903).

First Floor : #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 304 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)

above First Floor : 298.00 #REF! #REF!

Fifth Floor : 2874.00 #REF! #REF!

45 Providing 110 mm Dia ISI marked PVC down water take


pipes with socket , 2.5mm thick 4.0 kg/sq.cm pressure of ISI
marked including cost of necessary PVC Bends, shoes, iron /
PVC clamps and all other accessories and fixing in position
including cost and conveyance of all materials, operational &
incidental charges including all labour charges for fixing at site
etc., and overheads & contractors profit complete for finished
item of work. (APSS No. 1328)

1107.00 #REF! #REF!

46 RCM facia 50mm thick in CM(1:3) using screened sand for


drop walls, fins with rabbit wire mesh & nomianl reinforcement
as directred by Engineer - In - Charge with dubara sponge
finishing,including cost and conveyance of all materials to site,
operationals &incidental,cost and conveyance of cement, wire
mesh water to work site, centering, scaffolding and form work,lift
charges etc., and overheads & contractors profit complete for
finished item of work but excluding cost of steel and its
fabrication charges for finished item of work(APSS
NO.403&903)

Basement Floor : 16.00 #REF! #REF!

First Floor : 21.00 #REF! #REF!

Second Floor : 6.00 #REF! #REF!

Third Floor : 6.00 #REF! #REF!

Fourth Floor : 6.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 305 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
47 Supply and fixing of doors as per approved drawings with
1st Grade Burma teak wood frame of section 250mm x 150
mm of 4 verticals of 2.85m height with one horizontal at the top
of 6.10m of length with a section of 250mm x 150mm, and at
the bottom of frame 2 Nos of 1.25m length horizontals each of
section 250mm x 150mm and with 1st grade burma teak wood
door shutter of 150mmX35mm thick alround frame double
shutter on center and single shutter on either side and with
12mm thick plain float glass fixid to door shutter with teak wood
beeding of 12mmX12mm

Supply and fixing of 8 Nos. MS hold fasts of size (450 mm x


100 mm x 8mm) flat of 2 nos welded together to fix with the help
of anchor fasteners of 4 nos (Two on either side) including cost
of ISI marked Brass fixtures of 16 Nos. butt hinges of 250mm
long, 3 No. brass aldrops (IS:2681) of 450mm long, 3 Nos.
brass tower bolts (IS:204) of 300 mm x 10 mm dia at top, 4 Nos.
of 450mm long brass fanvy handless (IS:208) at front side and 4
Nos of 300mm Brass handles on back side, 4 Nos.of door
stoppers, including fixing the fixtures to door with required
number of screws, bolt and nuts including labour charges for
fixing the frame in position, fixing the shutter to the frame etc.,
including cost & conveyence, overheads & contractors profit
etc.. complete for finished item of work (6100mm x 2850mm)

Basement Floor : 18.30

First Floor : 18.30


36.60 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 306 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
48 Supply and fixing powder coated aluminium fully glazed
swing door as per the approved drawing with fixed fan light of
500mm height at top door using aluminium sections of 101.60
mmm x 44.45mm , 3.18 mm thick for frame and door shutter
made of styles , top and middle rail of 47.62mm x 44.45mm ,
3.18 mm thick and bottom rail of 114.30mm x 44.45 mm ,
3.18mm thick,powder coating of alluminium sections 25mm
microns thick, 5 mm thick plain float glass fitted with suitable
aluminium glazing clips and rubber beading in fan light portion,
double shutters fitted with 5mm thick frosted / ground glass in
the top half and MDF Board: interior-Both Side Laminated -12
mm thick in the bottom half fitted with suitable aluminium
glazing clips and rubber beading,shutters mounted on double
action hydraulic floor spring of approved brand manufacture IS :
6315 marked , Hardwyn make M-3000 for doors including cost
of cutting floors as required , embedding in floors

and SS cover plates with brass pivot and sigle piece MS Sheet
outer box with slide plate etc.complete (Weight Capacity
up to 130 Kgs) as approved by Engineer-in-Charge including
supply and fixing ISI marked powder coated aluminium fixtures
of 3 Nos. of butt hinges (IS:205) of 150mm long(for each
shutter), 4 Nos.tower bolts 10mm bolt (IS:204) 300mm long , 4
Nos.alluminium handles (IS:208) 150mm dia and 2 Nos.
aldrops (IS:2681) 300mm long including labour charges for
manufacturing door , fixing the door with required No. of screws
etc., including overheads & contractors profit complete for
finished item of work. (The Aluminium section used shall be
standard make confirming to IS 1948 – 1961) and as approved
by the Engineer) (2000mm x 2600mm)

Cellar : 26.00

Basement Floor : 67.60

First Floor : 104.00

APMSIDC-PALASA ABS-CIVIL 307 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)

Second Floor : 104.00

Third Floor : 124.80

Fourth Floor : 98.80


525.20 #REF! #REF!

49 Supply and fixing of doors as per approved drawings with


medium teak wood frame of section 100mm x 65 mm with
split type fan light of 500mm at the top fixed with 4mm thick
pin headed glass using 12mm x 12mm Teak Wood beading and
2 Nos. of 10mm MS Square bars and ISI marked flush door
shutter of 30mm thick double shutters with bond wood solid
block board type core having cross bands and face veneers, hot
pressed bonded with water proof phenol formaldehyde synthetic
resin factory made conforming to IS 2202-1991 (Part-I) both
sides commercial ply with internal lipping on all sides, fixing
1mm thick mat finish laminated sheet to full width and
height of the flush shutter both sides

including cost and conveyance to site of teak wood frame, flush


shutter, laminate sheet including supply and fixing 6 Nos. MS Z
hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI
marked Alumimium fixtures of 6 Nos. butt hinges (IS:205)
150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower
bolts (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150mm
long handles (IS:208), 2 Nos. door stoppers and 2 Nos.
Rubber / Nylon door stop bushes including fixing the fixtures to
door with required number of screws, bolt and nuts including
labour charges for fixing the frame in position, fixing the shutter
to the frame, fixing glass in fan light portion etc., including
overheads & contractors profit complete for finished item of
work as per APSS 1001 & 1002 (The vertical frame of door shall
be embedded in flooring for a depth of not less than 10 mm)
(1500mm x 2600mm)

Cellar : 3.90

APMSIDC-PALASA ABS-CIVIL 308 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)

Basement Floor : 70.20

First Ground : 70.20

Second Ground : 7.80

Third Floor : 35.10

Fourth Floor : 58.50


245.70 #REF! #REF!

50 Supply and fixing of doors as per approved drawings with


medium teak wood frame of section 100mm x 65 mm with
split type fan light of 500mm at the top fixed with 4mm thick
pin headed glass using 12mm x 12mm Teak Wood beading and
2 Nos. of 10mm MS Square bars and ISI marked flush door
shutter of 30mm thick double shutters with bond wood solid
block board type core having cross bands and face veneers, hot
pressed bonded with water proof phenol formaldehyde synthetic
resin factory made conforming to IS 2202-1991 (Part-I) both
sides commercial ply with internal lipping on all sides, fixing
1mm thick mat finish laminated sheet to full width and
height of the flush shutter both sides

APMSIDC-PALASA ABS-CIVIL 309 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
including cost and conveyance to site of teak wood frame, flush
shutter, laminate sheet including supply and fixing 6 Nos. MS Z
hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI
marked Aluminium fixtures of 6 Nos. butt hinges (IS:205)
150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower
bolts (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150mm
long handles (IS:208), 2 Nos. door stoppers and 2 Nos.
Rubber / Nylon door stop bushes including fixing the fixtures to
door with required number of screws, bolt and nuts including
labour charges for fixing the frame in position, fixing the shutter
to the frame, fixing glass in fan light portion etc, including
overheads & contractors profit complete for finished item of
work as per APSS 1001 & 1002 (The vertical frame of door shall
be embedded in flooring for a depth of not less than 10 mm)
(1200mm x 2600mm)

Cellar : 6.24

Basement Floor : 28.08

First Floor : 28.08

Second Floor : 21.84


Third Floor : 34.32

Fourth Floor : 31.20

149.76 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 310 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
51 Supply and fixing of doors as per approved drawings with
medium teak wood frame of section 100mm x 65 mm with split
type fan light of 500mm at the top fixed with 4mm thick pin
headed glass using 12mm x 12mm Teak Wood beading and 2
Nos. of 10mm MS Square bars and ISI marked flush door
shutter of 30mm thick single shutter with bond wood solid block
board type core having cross bands and face veneers, hot
pressed bonded with water proof phenol formaldehyde synthetic
resin factory made conforming to IS 2202-1991 (Part-I) both
sides commercial ply with internal lipping on all sides fixing 1mm
thick mat finish laminated sheet to full width and height of the
flush shutter both sides including cost and conveyance to site of
teak wood frame, flush shutter, laminate sheet including supply
and fixing

6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm


including cost of ISI marked Aluminium fixtures of 3 Nos. butt
hinges (IS:205) 150mm long , 1 No. aldrop (IS:2681) 300mm
long, 1 No. tower bolt (IS:204) of 200 mm x 10 mm dia at top, 2
Nos. 150mm long handles (IS:208), 1 No. door stopper and 1
No. Rubber / Nylon door stop bushes including fixing the
fixtures to door with required number of screws, bolt and nuts
including labour charges for fixing the frame in position, fixing
the shutter to the frame, fixing glass in fan light portion etc,
including overheads & contractors profit complete for finished
item of work as per APSS 1001 & 1002 (The vertical frame of
door shall be embedded in flooring for a depth of not less than
10 mm) (1000mm x 2600mm)

First Floor : 67.60

Second Floor : 23.40

Third Floor : 26.00

117.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 311 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
52 Supply and fixing doors as per drawings with medium teak
wood frame of section 100mm x 65 mm and ISI marked flush
door shutters of 30 mm thick single shutter with bond wood solid
block board type Core having cross bands and face veneers,
hot pressed bonded with water proof phenol formaldehyde
synthetic resin factory made conforming to IS 2202-1991 (Part-
I) both sides commercial ply with internal lipping on all sides,
fixing 1mm thick mat finish laminated sheet to full width
and height of the flush shutter both sides including cost and
conveyance to site of teak wood frame, flush shutter, laminate
sheet including supply and

fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm


including cost of ISI marked Aluminium fixtures of 3 Nos. butt
hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm
long, 1 No. tower bolt (IS:204) of 200 mm x 10 mm dia at top, 2
Nos. 150 mm long handles (IS:208), 1 No. door stopper and 1
No. Rubber / Nylon door stop bushes including fixing the
fixtures to door with required number of screws, bolt and nuts
including labour charges for fixing the frame in position, fixing
the shutter to the frame etc, including overheads & contractors
profit complete for finished item of work as per APSS 1001 &
1002 (The vertical frame of door shall be embedded in flooring
for a depth of not less than 10 mm) (900mm x 2100mm)

Cellar : 22.68

Basement Floor : 51.03

First Floor : 52.92

Second Floor : 58.59

Third Floor : 54.81

Fourth Floor : 45.36

Fifth Floor : 9.45

APMSIDC-PALASA ABS-CIVIL 312 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
294.84 #REF! #REF!

53 Supplying and fixing single side prelam solid panel PVC


door frame (Choukhat): Providing and fixing factory made Pac
single side Prelam door frame of the size 50x7 mm with a wall
thickness of 5mm, made out of extruded 5mm rigid Pac single
side prelam sheet, meter cut at two corners and joined with 2
Nos. of 150mm long brackets of 15 x 15mm MS Square tube.
The two vertical door profiles are to be reinforced with 19 x
19mm MS. square tube of 19 guage. The door frame shall be
fixed to the wall using 65/100mm long MS. Screws through the
frame by using Pac fasteners. a minimum of 4 Nos. of screws to
be provided for each vertical member and minimum 2nos. for
horizontal member etc. complete as per manufacture
specification and direction of Engineer-incharge including
conveyance of all materials, labour charges for fixing,
overheads & contractors profit complete for finished item of
work.

Cellar : 110.00

Basement Floor : 215.00

First Floor : 215.00

Second Floor : 300.00

Third Floor : 245.00

Fourth Floor : 180.00

1265.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 313 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
54 Providing and fixing 30mm thick factory made moulded
door shutter- wood free consisting of frame made out of MS.
tubes 19gauge thickness and size of 25mmX25mm for styles,
top and bottom rails. MS. Frame shall have a coat of steel
primers. The inner panel shall consist of 25mm thick high
density EPS conforming to IS 4671-1984 bounded with 2mm
thick termite proof, water proof and fire resistant moulded Pac
sheet with 2,4,6 raised panel design in different plain and / or
pre-lam colours after routing to the moulded design on one side
and 2mm plain and / or pre-lam Pac sheet on other side of the
EPS. The edge of panel to be sealed with lipping of 10mm wide
PVC sheet bottom (made by sticking 2 rigid foam sheet of 5mm
thickness using Pac solvent cement) and stiles sides
25mm(5mmX5) thick and 30mm width Pac sheet fitted along
MS tube for lock provision for lock height 5mm thick Pac sheet
of size 150mmX100mm fixed with upper and lower face of inner
side of EPS panel etc., complete as per direction of Engineer –
in-Charge, manufacture specification and drawing including ISI
marked Aluminium fixtures 3 Nos. butt hinges (IS:205) of
150mm long, 1 No. aldrop (IS:2681) 250 mm long, 1 No. tower
bolt (IS:204) of 150 mm x 10mm dia, 2 Nos. 125mm long
handles (IS:208),1 No. Rubber / Nylon door stop bushes
including labour charges for fixing the shutter to frame etc.,
including overheads & contractors profit complete for finished
item of work

Cellar : 36.96

Basement Floor : 72.24

First Floor : 72.24

Second Floor : 100.80

Third Floor : 82.32

APMSIDC-PALASA ABS-CIVIL 314 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
Fourth Floor : 60.48

425.04 #REF! #REF!

55 Providing and fixing factory made uPVC white colour


sliding glazed window comprising of uPVC multi-chambered
frame with in-built roller track and sash extruded profiles duly
reinforced with 1.60 ± 0.2 mm thick galvanized mild steel
section made from roll forming process of required length
(shape & size according to uPVC profile), appropriate
dimension of uPVC extruded glazing beads and uPVC extruded
interlocks, EPDM gasket, wool pile, zinc alloy (white powder
coated) touch locks with hook, zinc alloy body with single nylon
rollers (weight bearing capacity to be 40 kg), G.I fasteners 100 x
8 mm size for fixing frame to finished wall and necessary
stainless steel screws etc. Profile of frame & sash shall be
mitred cut and fusion

welded at all corners, including drilling of holes for fixing


hardware's and drainage of water etc. After fixing frame the gap
between frame and adjacent finished wall shall be filled with
weather proof silicon sealent over backer rod of required size
and of approved quality, all complete as per approved drawing
& direction of Engineer-in-Charge inclusive of cost of Single /
double glass panes of 4mm thick pin headed glass, wire mesh
and silicon sealent . Note: For uPVC frame and sash extruded
profiles minus 5% tolerancein dimension i.e. in depth & width of
profile shall be acceptable.Variation in profile dimension in
higher side shall be accepted. But no extra payment on this
account shall be made.

APMSIDC-PALASA ABS-CIVIL 315 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
a) Two track two panels sliding window made of frame 67 x 50
mm & sash 46 x 62 mm both having wall thickness of 2.3 ± 0.2
mm and single glazing bead / double glazing bead of
appropriate dimension .

Cellar : 72.36

Basement Floor : 181.98

First Floor : 318.06

Second Floor : 172.80

Third Floor : 147.96

Fourth Floor : 327.78

Fifth Floor : 13.50


1234.44 #REF! #REF!

b) Three track three panels sliding window with fly proof SS


wire mesh (Two nos. glazed & one no. wire mesh panels)
made of frame 92 x 44 mm & sash 32 x 60 mmboth having wall
thickness of 1.9 ± 0.2 mm and single glazing bead of
appropriate dimension

Basement Floor : 10.80

Second Floor : 167.40

Third Floor : 6.48

184.68 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 316 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
56 Providing and fixing factory made uPVC white colour fixed
glazed windows / Ventilators comprising of uPVC multi
chambered frame and mullion (where ever required) extruded
profiles duly reinforced with 1.60± 0.2 mm thick galvanized mild
steel section made from roll forming process of required length
(shape & size according to uPVC profile), uPVC extruded
glazing beads of appropriate dimension, EPDM gasket,G.I
fasteners 100 x 8 mm size for fixing frame to finished wall,
plastic packers, plastic caps and necessary stainless steel
screws etc. Profileof frame shall be mitred cut and fusion
welded at all corners, mullion (if required) shall be also fusion
welded including drilling of holes for fixing hardware and
drainage of water etc.

After fixing frame the gap between frame and adjacent finished
wall shall be filled with weather proof silicon sealant over backer
rod of required size and of approved quality, all complete as per
approved drawing & direction of Engineer-in-Charge inclusive of
cost of Single / double glass panes and silicon sealant. Note:
For uPVC frame, sash and mullion extruded profiles minus
5%tolerance in dimension i.e. in depth & width of profile shall be
acceptable.Variation in profile dimension in higher side shall be
accepted. But, no extra payment on this account shall be made.

APMSIDC-PALASA ABS-CIVIL 317 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
Fixed windows / Ventilators made of (small series) frame 47 x
50mm & mullion 47 x 68 mm both having wall thickness of 1.9
±0.2 mm and single glazing bead of appropriate dimension.

Cellar : 34.95

Basement Floor : 19.80

First Floor : 19.80

Second Floor : 22.20

Third Floor : 17.40

Fourth Floor : 18.30

132.45 #REF! #REF!

57 Supplying and fixing of MS doors, grill to windows / in open


court yards using MS angles, flat, square bars including cost
and conveyance of all materials, cutting, bending, welding, all
operational charges, labour charges, overheads and contractor
profit etc., complete for finished item of work. For All Floors

22710.00 #REF! #REF!

58 Supply and fixing jallies ( cement concrete ) of 50mm thick as


per the design approved by the Engineer-in-Charge including
cost and conveyance of materials to site and labour charges
etc., overheads & contractors profit complete for finished item of
work.

Cellar : 39.00 #REF! #REF!

Basement Floor : 78.00 #REF! #REF!

First Floor : 78.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 318 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)

Second Floor : 78.00 #REF! #REF!

Third Floor : 52.00 #REF! #REF!

Fourth Floor : 72.00 #REF! #REF!

59 Providing and Fixing Structural Glazing fabricated from Roll


formed sections made of Pre-painted Steel / Powder coated
(Base steel as per IS 513 of ‘D’ quality, galvanized as per IS
277 with Zinc of 120 Gm/sqm) with total coated thickness of
0.72mm. The glass holding section made of 304 grade stainless
steel of 0.6mm thick as per the design requirement &
calculations as given in IS: 875. Primer coat with epoxy primer
of 5 – 7 microns thick, finish painted with a polyester paint of 12-
16 microns thick and back coated with Alkyd backer of 5-7
microns or powder coated with pure polyester powder up to 50-
60 microns thick. The vertical section should be of 50mm
x100mm x 0.72mm, 33mm x 58mm x 0.72mm for frame
horizontal section, stiffener section should be 48mm x 98mm x
1mm, cover profiles sections should be of 20mm x 58mm x
0.58mm, Glass holding section should be of 37mm x 37mm &
37mm x 18mm. Including 5mm thick Ocean Blue reflective
glass. Brackets made of CRCA powder coated/Electroplated
should be used to connect vertical to horizontal, vertical to slab,
to fix verticals at top & bottom as per site requirement.

APMSIDC-PALASA ABS-CIVIL 319 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
Gasket made of Ethyl Propylene Diamine Monomer. Natural
cure, with Good U.V. Resistance Silicon to be used. Wall fixing
of sections to concrete/masonry wall should be with self-
expanding cap & screws. The rate is inclusive of cost and
conveyance of all materials to site, all labour charges, incidental
charges, cost of all consumables etc. and scaffolding charges,
form work , overheads & contractors profit etc., complete for
finished item of work in all floors.

246.00 #REF! #REF!

60 Providing and Fixing Top Hung shutters in Structural


Glazing fabricated from Roll formed sections made of Pre-
painted Steel / Powder coated (Base steel as per IS 513 of ‘D’
quality, galvanized as per IS 277 with Zinc of 120 Gm/sqm) with
total coated thickness of 0.72mm. The glass holding section
made of 304 grade stainless steel of 0.6mm thick. Galvanized
steel sections are to be used as stiffeners inside the colour
coated steel/powder coated sections as per the design
requirement. Design calculations are made to suit wind
pressures as given in IS 875. Primer coat with epoxy primer of
5-7 microns thick and back coated with Alkyd backer of 5-7
microns or powder coated with pure polyester powder up to 50-
60 microns thick. The outer frame should be of 20mm x 58mm
x 0.6mm, Shutter section should be of 58mm x 33mm x 0.72
mm, stiffener section should be 56mm x 31mm x 1mm. EARL
Bihari Hinges – 2 Nos for each shutter and Aluminium Stays – 2
Nos. for each shutter, Aluminium Handle – 1 no. for each
shutter. The rate is inclusive of cost and conveyance of all
materials to site, all labour charges,

incidental charges, cost of all consumables etc. and scaffolding


charges, form work, overheads & contractor profit etc. complete
for finished item of work in all floors.

53.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 320 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
61 Supplying and fixing of stainless steel (grade 304) hand
railing as per approved drawing with top rail of 50mm dia pipe
and 2mm thick medium class and vertical posts of 25mm dia
and 1.6mm thick medium class 1 No for each step fixed with
base plate of 75mm dia using bonding agent and anchor
fastner and welding, drilling of 25mm dia holes with pneumatic
compressor for fixing railing, buffing, polishing all members of
the railing thouroughly , lacquer finishing to present seamless
finish including cost and conveyance of all materials, electrodes,
welding charges, cost of all consumables, labour charges ,
overheads & contractors profit etc., complete for finished item of
work. for all floors

328.00 #REF! #REF!

62 Supplying and fixing of stainless steel (grade 304) railing


for ramp as per approved drawing with top rail of 50mm dia
pipe and 2mm thick medium class fixed in to wall with 25mm dia
pipe of 0.30m length @ 1m centre to centre and welding,
buffing, polishing all members of the railing thouroughly ,
lacquer finishing to present seamless finish including cost and
conveyance of all materials, electrodes, welding charges, cost
of all consumables, labour charges , overheads & contractors
profit etc., complete for finished item of work.

801.00 #REF! #REF!

63 Supply & fixing of Rolling shutter made of 80 x 1.25 mm


machine rolled CRCA laths, interlocked together through their
entire length and jointed together at the ends by end-locks,
mounted on specially designed pipe shaft of 50mm dia nominal
bore MS B class pipe with brackets, plates, guide channels,
stoppers, bottom locking plates and arrangements for inside &
outside locking with push-pull operations including cost of hood
cover and springs complete, painted with one coat of approved
steel primer, locks, ball bearings, all accessories etc.,
overheads & contractors profit complete for finished item of
work as per special spn: 1108

#REF! #REF!

APMSIDC-PALASA ABS-CIVIL 321 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
64 White washing two coats with white cement to ceiling to give
an even shade after thouroughly brushing the surface to remove
all dirt and remains of loose powdered materials including cost
of all materials , labour charges and incidental such as
scaffolding , lift charges etc., and overheads & contractors profit
complete for finished item of work in all floors.

First Ground :
Fifth Floor : 370.00
370.00 #REF! #REF!

65 Providing and applying Wall putty of White Cement or


Polymer or Cement based of average 1 to 2 mm thickness over
plastered surface to prepare the surface even and smooth after
thoroughly brushing the surface to remove all dirt and remains
of loose powdered materials, applying emery paper, Sand the
surface, clean & wipe off loose dust, applying knifing paste filler
by putty knife / muslin pad, air dry for 2 - 3 hrs, sand with 180
and 320 No., emery paper for the surface preparation including
cost and conveyance of all materials to work site and all
operational, incidental, labour charges, over heads and
contractors profit etc., complete for finished item of work in all
floors for internal walls & Ceiling

Cellar : 3993.00

Basement Floor : 8864.00

First Floor : 8750.00

Second Floor : 8598.00

Third Floor : 9640.00

Fourth Floor : 7816.00

47661.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 322 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)

APMSIDC-PALASA ABS-CIVIL 323 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
66 Supply & application of one coat water based cement
primer of interior grade I and two coats of synthetic
polymer luxury plastic emulsion paint of superior grade
having VOC (Volatile Organic Compound) content less than 50
grams/litre for internal walls including cost and conveyance of
all materials to site, incidental, operational and all labour
charges etc., and overheads & contractors profit complete for
finished item of work in all floors.

Cellar : 2156.00

Basement Floor : 6083.00

First Floor : 6067.00

Second Floor : 5852.00

Third Floor : 6989.00

Fourth Floor : 4894.00

Fifth Floor : 407.00

32448.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 324 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
67 Supply & application of one coat water based cement
primer of exterior grade II and two coats of synthetic
polymer luxury plastic emulsion paint of superior grade
having VOC (Volatile Organic Compound) content less than 50
grams/litre for exterior walls including cost and conveyance of
all materials to site, incidental, operational and all labour
charges etc., and overheads & contractors profit complete for
finished item of work in all floors.

Cellar : 478.00

Basement Floor : 878.00

First Floor : 1081.00

Second Floor : 865.00

Third Floor : 1296.00

Fourth Floor : 1388.00

Fifth Floor : 857.00

6843.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 325 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
68 Providing and applying PMCC / Deco orient base or
Equivalent exterior Texture of average 2 to 3 mm thickness
over plastered surface to prepare the surface even and smooth
after thoroughly brushing the surface to remove all dirt and
remains of loose powdered materials, applying emery paper,
Sand the surface, clean & wipe off loose dust, applying putty/
texture paint filler by putty knife / muslin pad, air dry for 2-3
hrs for the surface preparation including cost and conveyance of
all materials to work site and all operational, incidental, labour
charges, scaffolding charges, overheads and contractors profit
etc., complete for finished item of work in all floors for external
walls

Cellar : 319.00

Basement Floor : 585.00

First Floor : 721.00

Second Floor : 577.00

Third Floor : 864.00

Fourth Floor : 925.00

Fifth Floor : 568.00

4559.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 326 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
68 Supply & applying Melamine Polish Glossy/ Matt finish to
the wood works duly cleaning the surface and applying emery
paper, sand the wood with 180 No., emery paper and then with
320 No., emery paper, clean & wipe off loose dust, applying
suitable knifing paste filler / wood filler by putty knife / muslin
pad, air dry for 2 - 3 hrs, sand with 180 and 320 No., emery
paper, apply two component wood sealer, air dry for 24 hrs,
sand with 320 No emery paper, applying one coat of approved
spraying thinner (for spraying)/ applying one coat of approved
brushing thinner or general purpose thinner (for brushing) and
apply (either with spray or brush) two coats of approved brand
melamine including cost & labour charges, emery papers, cost
of thinner & melamine polish, over heads and contractors profit
etc., complete for finished item of work

Basement Floor : 42.00

First Floor : 42.00

84.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 327 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
69 Painting two coats with synthetic enamel paint Grade-II
VOC (Volatile Organic Compound) content less than 50
grams/litre over primer coat of red oxide to new iron work
including cost and conveyance of all materials to site, incidental,
operational and all labour charges etc., and overheads &
contractors profit complete for finished item of work in all floors.
(SS No. 1201, 1212 & 1207).

Cellar : 107.98

Basement Floor : 215.00

First Floor : 278.00

Second Floor : 371.00

Third Floor : 172.00

Fourth Floor : 356.00

Fifth Floor : 15.00

1514.98 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 328 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
70 Supplying and fixing of two shutter cupboards as per
drawing with medium teak wood frames of size 75mm x 40mm
and MDF Board Interior grade both sides laminated 18mm thick
for shutters with 18mm x 12mm teak wood beading alround
and supplying and fixing powder coated MS fixtures 3 Nos.
butt hinges of size 100mm long(for each shutter), tower bolt 2
Nos. of 100mm x 10mm, 2 Nos of handles 100mm long and
standard locking arrangements for shutters including cost and
conveyance of all materials to site, labour charges, over heads
and contractor profit etc., complete for finished item of work.

Cellar : 18.00

Basement Floor : 115.00

First Floor : 13.00

Second Floor : 53.00

Third Floor : 90.00

Fourth Floor : 58.00

347.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 329 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
71 Supplying and fixing Gyp board Fine line Grid false ceiling
(GS-FLC-4.6)using 12.5mm thick Gyp Board sheet tiles of
size 595mm x 595mm conforming to IS 2095 - 1992 fixing to
Gyp steel precoated GI wall angle of size 25mm x 25mm x
0.70mm thick along the perimeter of ceiling screw fixed to brick
work / partition at 610mm center to center and suspending the
frame work using precoated GI Tee section (24mm x 38mm x
0.7mm) from soffit at 1220mm center to center fixed with GI
Soffit Cleat, rawl plugs and steel expansion fasteners &
connecting clip to the GI Tee section with 4mm dia GI rod with
galvanised spring steel level clip of PVC unversal holding clips
system at 1200mm center to center and fixing the 12.5mm
Gypboard sheet tiles of size 595mm x 595mm and finishing two
coats of drywall top coat, overheads and contractor profit
complete for finished item of work in all floors.

Third Floor : 488.00

Fourth Floor : 2463.00

2951.00 #REF! #REF!

72 Suplying and fabricating, erecting and fixing in position


tabular trusses of approved design with M.S tube conforming
to I.S specifications including roof frame work consisting of
rafters,ties struts and purlins including cost of foundations bolts,
cleats, bearings plates,etc.,complete as per the sketch
enclosed and including cost of painting with enmel paint 2
coats over a primary coat with red oxide paint including cost and
conveyance of all materials, labour charges for fabrication and
fixing, hire charges of all tools and plants, all incidental charges,
overheads and contractor profit etc., complete for finished item
of work as directed by the Engineer-in-Charge

Fifth Floor : 1086.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 330 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)

73 Supplying and fixing 50mm dia nominal bore Medium


Grade properties & weight as per IS 1239 ISI mark MS Tube
for fixing of GI Sheet including cost and conveyance of all
materials to work site and all operational, incidental, labour
charges etc., complete for finished item of work in all floors for
stair case head room roof.

Fifth Floor : #REF! #REF!

74 Roofing with UV resistant multi-wall polycarbonate sheets of


any colour 6mm thick fixed with Aluminium Universal glazing
set 40mm wide and as per drawing etc., complete excluding the
cost of purlins, rafters,trusses,aluminium universal glazing set
40mm wide including cost and conveyance of all materials,
labour charges, overheads and contractors profit etc., complete
for finished item of work

Fifth Floor : 101.00 #REF! #REF!

75 Supplying and fixing Aluminium Universal glazing set


40mm wide for jointing and fixing Polycarbonate sheets
including cost and conveyance of all materials, labour charges,
overheads and contractors profit etc., complete for finished item
of work

Fifth Floor : 38.00 #REF! #REF!

APMSIDC-PALASA ABS-CIVIL 331 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
76 Providing and fixing of Expansion joint filler board for
buildings, columns, beams and slabs 25 mm thick including cost
and conveyance of all materials to site, all incidental,
operational, labour charges etc.overheads & contractors profit
complete for finished item of work as per approved drawing for
all floors

Cellar : 3.00

Basement Floor : 4.00

First Floor : 4.00

Second Floor : 4.00

Third Floor : 4.00

Fourth Floor : 4.00

23.00 #REF! #REF!

77 Providing and fixing of 24 gauge alluminium sheet over


expansion joint groove of width 15cm fixed to walls / columns
at one edge and resting over the other block walls/columns
concealing expansion joint with slotted holes for free edge of
aluminium sheet to facilitate free movement of aluminium sheet
over the finished surface of expansion joint and wall face using
sheet metal screws with nylon receiver complete including cost
and conveyance of all materials to site, all incidental,
operational, labour charges , overheads & contractors profit
etc., complete for finished item of work as per approved drawing
(for all floors for vertical joints and bottom of slab)

Cellar : 7.00

Basement Floor : 7.00

APMSIDC-PALASA ABS-CIVIL 332 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
First Floor : 7.00

Second Floor : 7.00

Third Floor : 7.00

Fourth Floor : 7.00

42.00 #REF! #REF!

78 Providing specialized polysulphide sealant treatment to the


expansion joints (Size : 25mm x 12mm) duly a). Chipping and
removing of existing covering on expansion joints b). Cleaning
of the surface from dirt, dust and other contaminations
c).Application of one coat of - High performance specially
designed SBR latex polymer based bonding agent d). Providing
and application of Acrylic Polymer modified reinstatement
concrete /mortar to the damaged edges of joint and making the
groove. e]. Providing and fixing of masking tape on top of the
joint both sides f). Providing and fixing of Back up support
material of Backer rod to leave the depth of 12mm on the joint
g). Providing and application of one coat of polysulphide primer
on inner edges of Joint. h). Providing and application of Two
part Polysulphide sealant to a width of 25mm and 12mm depth
with putty knife and neat finish i). Removing of masking tape
and providing and application of two coats of Acrylic elastomeric
cementitious coating including cost and conveyance of all
materials, labour charges, overheads & contractors profit etc.,
complete for finished item of work

Cellar : 7.00

Basement Floor : 7.00

First Floor : 7.00

APMSIDC-PALASA ABS-CIVIL 333 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
Second Floor : 7.00

Third Floor : 7.00

APMSIDC-PALASA ABS-CIVIL 334 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
Fourth Floor : 7.00

42.00 #REF! #REF!

79 Supply and delivery of encapsulated plastic steps


manufactured as per companies standard specification
including cost of materials packing as per companiess
standards, loading, transportation, unloading and stacking at
site of work , etc.,as applicalble including labour charges for
fixing etc. complete for finished item of work.

#REF! #REF!

80 Supplying & fixing 602 x 602 mm CI man hole frame and


cover (light weight) 30 Kgs including cost and conveyance
and labour charges for fixing, overheads and contractor profit
etc., complete for finished item of work
#REF! #REF!

81 Construction of Granular sub-base by providing HBG


material confirming to Grading - III of MORT & H Table 400-
2 including cost and conveyance of all material to woek site and
spreading in uniform layers with motor grader or by approved
means, on prepared surface mixing by mix place method with
Rotavator/ approved means, at OMC and compacting with
vibratory roller to achieve the desired density etc., complete for
finished item of work as per MoRT& H specification 401 (4th
revision) and as directed by the Engineer- in - charge (Payment
will be made based on levels for finished item of work)

#REF! #REF!

APMSIDC-PALASA ABS-CIVIL 335 of 1048


Quantity Amount
Sl. No. Description of Work
A Rate (Rs.)
82 Construction of un-reinforced, dowel jointed at expansion
and construction joint only, plain cement concrete
pavement, thickness as per design, over a prepared sub base,
with 43 grade cement or any other type as per Clause 1501.2.2
M30 (Grade), coarse and fine aggregates conforming to IS :
383, maximum in a concrete mixer of not less than 0.2 cum
capacity and appropeiate weigh batcher using approved mix
design, laid in approved fixed side formwork (steel channel,
laying and fixing of 125 mictron thick polythene film, wedges,
steel plates including levelling the formwork as per drawing),
spreading the concrete with sholvels, rakes, compacted using
needle, scareed and plate vibrators and finished in continuous
operation including provision of contraction and expansion,
construction joints, applying debonding strips, primer, sealant,
dowel bars, near approaches to bridge / culvert and
construction joints, admixtures as approved, curing of concrete
slabs for 14- days, curing compound (where specified) and
water finishing to lines and grade as per drawing and Technical
Specification Clause 1501 MORD.

#REF! #REF!
Cellar : #REF!

APMSIDC-PALASA ABS-CIVIL 336 of 1048


#REF!

ABSTRACT ESTIMATE FOR CIVIL WORKS

Unit Rate Amount


Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
1 Earth work excavation for foundations (Mechanical 10482.00 CUM ONE CUM #REF! #REF!
Means) for buildings in ordinary soils and depositing
on bank for all lifts and with an initial lead of 10m and
up to 3m depth including all operational,incidental,
labour charges such as shoring, sheeting, planking,
strutting etc., and overheads & contractors profit
complete for finished item of work excluding
dewatering charges etc., as per SS 20 B(APSS 308)

2 Earth work excavation for foundations (Mechanical 10909.00 CUM ONE CUM #REF! #REF!
Means) for buildings in ordinary soils and depositing
on bank for all lifts and with an initial lead of 10m and
3m to 6m depth including all operational,incidental,
labour charges such as shoring, sheeting, planking,
strutting etc., and overheads & contractors profit
complete for finished item of work excluding
dewatering charges etc., as per SS 20 B(APSS 308)

3 Earth work excavation for foundations (Mechanical 2621.00 CUM ONE CUM #REF! #REF!
Means) for buildings in ordinary rock (not requiring
blasting) and depositing on bank for all lifts and with an
initial lead of 10m and up to 3m depth including all
operational,incidental, labour charges such as shoring,
sheeting, planking, strutting etc., and overheads &
contractors profit complete for finished item of work
excluding dewatering charges etc., as per SS 20
B(APSS 308)

4 Earth work excavation for foundations for buildings in 575.00 CUM ONE CUM #REF! #REF!
hard rock (blasting prohibited) and depositing on bank
for all lifts and with an initial lead of 10m and up to 3m
depth including all operational,incidental, labour
charges such as shoring, sheeting, planking, strutting
etc., and overheads & contractors profit complete for
finished item of work excluding dewatering charges
etc., as per SS 20 B(APSS 308)

APMSIDC-PALASA Hospital Building - Civil Abs 337of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
5 Plain Cement Concrete (1:4:8) (cement: fine 619.00 CUM ONE CUM #REF! #REF!
aggregate: Coarse aggregate) for foundations using
coarse aggregate 40mm size hard , machine crushed
granite from approved quarry using concrete Mixer 10 /
7 cft (0.2 / 0.8 cum) capacity including cost and
conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site including all charges for
machine mixing and hire charges of concrete mixer,
laying concrete in foundations and under flooring bed,
ramming in 15 cm layers finishing top surface to the
required level curing etc.,and overheads & contractors
profit complete for finished item of work. (APSS No.
402)

6 Filling with useful available excavated earth (excluding 20897.00 CUM ONE CUM #REF! #REF!
rock) with a lead of 50 m in trenches, sides of
foundations and basement with initial lead in layers not
exceeding 15cm thick, watering and ramming including
cost and conveyance of water to work site and all
operaitonal, incidental, labour charges, hire charges of
T&P etc., and overheads & contractors profit complete
for fnished item of work (APSS NO.309&310)

7 Conveyance of un-useful excavated earth to a 3690.00 CUM ONE CUM #REF! #REF!
distance of 5 KM for disposal including hire charges of
T & P, labour charges etc., and overheads &
contractors profit complete for finished item of work.

APMSIDC-PALASA Hospital Building - Civil Abs 338of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
8 Pre construction Anti termite treatment is a process in 3237.00 SQM ONE SQM #REF! #REF!
which chemical toxic to subterrean tremites is apply/
inject into soil during early stage of building
Construction 2. Treatement of soil Beneath the
building and around the foundations conduct and
chemical use as per BIS - IS 6313 (Part -2) 2013 code
specification & CIB RC registered termiticide which
creates a continuous chemical barrier beneath the
building which kills or repels terminates & impervious
to tremite entry 3. Imidacloprid 30.5% SC (IS 63131)
dissolve 2.1 Ml/1 liter of water and apply
emulsion/solution @ 7.5 Litres/Square meter (Sqm) of
internal, external vertical surface of the colums, plinth
beams (Back filling) walls and floor junction, external
perimeters, along reatining wall @ 5.0 Liters/Sqm of
the horizontal surface of basement top surface of the
basement filling below flooring bed (Plinth) & @ 2.0
Litres/ Line meter at expansion joints. The substructure
of a depth of 500mm around coulmns & 300mm deep
around plinth beams, basements & floor filling area
including excavation channel along the wall & rodding
etc. cost & Conveyance of all materials to the site, cost
of labour for sparying, rodding, overheads and
contractor profit etc. complete for furnished item of
work as per the approval of the Engineer-in-charge

9 Supply and placing of the Design Mix Concrete M 30


grade corresponding to IS 456 with minimum cement
content of 400 kgs per 1 cum of concrete using
batching and mixing plant of 15 cum per hour capacity
with 20mm size graded machine crushed hard granite
metal (coarse aggregate - as per IS 383 - 1970 and IS
2386 Part 1 to Part 8) from approved quarry including
cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using steel scaffolding pipes , jack props ,
wallers , foot plates , brackets , steel centering plates
etc., including all operational, incidental and labour
charges, transporting concrete using transit mixer,
lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing etc., and overheads &
contractors profit complete but excluding cost of steel
and its fabrication charges for finished item of work
(APSS No. 402)

a) Footings 24.00 CUM ONE CUM #REF! #REF!

b) Column Pedastals 119.00 CUM ONE CUM #REF! #REF!

c) Plinth Beams 176.00 CUM ONE CUM #REF! #REF!

d) Tie Beam 35.00 CUM ONE CUM #REF! #REF!

e) Raft 2796.00 CUM ONE CUM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 339of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)

10 Supply and placing of the Design Mix Concrete M 30


grade corresponding to IS 456 with minimum cement
content of 400 kgs per 1 cum of concrete using
batching and mixing plant of 15 cum per hour capacity
with 20mm size graded machine crushed hard granite
metal (coarse aggregate - as per IS 383 - 1970 and IS
2386 Part 1 to Part 8) from approved quarry including
cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden
reapers, runners, wood posts, wall plates etc.,
including all operational, incidental and labour
charges ,transporting concrete using transit mixer,
lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads &
contractors profit etc., complete but excluding cost of
steel and its fabrication charges for finished item of
work (APSS No. 402)

a) Columns :
Cellar Floor : 145.00 CUM ONE CUM #REF! #REF!

Lower Ground Floor : 251.00 CUM ONE CUM #REF! #REF!

First Floor : 214.00 CUM ONE CUM #REF! #REF!

Second Floor : 214.00 CUM ONE CUM #REF! #REF!

Fourth Floor : 214.00 CUM ONE CUM #REF! #REF!

Fifth Floor : 45.00 CUM ONE CUM #REF! #REF!

b) Lintels
Cellar Floor : 10.00 CUM ONE CUM #REF! #REF!

Lower Ground Floor : 22.00 CUM ONE CUM #REF! #REF!

First Floor : 12.00 CUM ONE CUM #REF! #REF!

Second Floor : 21.00 CUM ONE CUM #REF! #REF!

Third Floor : 15.00 CUM ONE CUM #REF! #REF!

Fourth Floor : 21.00 CUM ONE CUM #REF! #REF!

Fifth Floor : 1.00 CUM ONE CUM #REF! #REF!

c) 150mm thick Water Tank side walls


Fifth Floor : 208.00 SQM ONE SQM #REF! #REF!

d) 230mm thick Retaining wall


Cellar Floor : 1098.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 1098.00 CUM ONE CUM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 340of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)

e) Roof Beams :
un supported height up to 3.66 m
Cellar Floor : 98.00 CUM ONE CUM #REF! #REF!

Lower Ground Floor : 161.00 CUM ONE CUM #REF! #REF!

First Floor : 161.00 CUM ONE CUM #REF! #REF!

Second Floor : 161.00 CUM ONE CUM #REF! #REF!

Fourth Floor : 161.00 CUM ONE CUM #REF! #REF!

Fifth Floor : 17.00 CUM ONE CUM #REF! #REF!

f) ROOF SLABS :
i) Roof Slabs 125mm thick :
Cellar Floor : 283.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 283.00 SQM ONE SQM #REF! #REF!

First Floor : 284.00 SQM ONE SQM #REF! #REF!

Second Floor : 284.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 283.00 SQM ONE SQM #REF! #REF!

Fifth Floor : 181.00 SQM ONE SQM #REF! #REF!

ii) Roof Slabs 150mm thick :


Cellar Floor : 762.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 1786.00 SQM ONE SQM #REF! #REF!

First Floor : 1652.00 SQM ONE SQM #REF! #REF!

Second Floor : 1643.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 1647.00 SQM ONE SQM #REF! #REF!

Fifth Floor : 195.00 SQM ONE SQM #REF! #REF!

ii) Roof Slabs 175mm thick :


Cellar Floor : 831.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 1170.00 SQM ONE SQM #REF! #REF!

First Floor : 1192.00 SQM ONE SQM #REF! #REF!

Second Floor : 1192.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 1170.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 341of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
11 Supply and placing of the Design Mix Concrete M
30 grade corresponding to IS 456 with minimum
cement content of 400 kgs per 1 cum of concrete
using batching and mixing plant of 15 cum per
hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per
IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site, centering using steel
scaffolding pipes , jack props , wallers , foot plates
, brackets , steel centering plates etc., including all
operational, incidental and labour
charges ,transporting concrete using transit mixer,
lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads &
contractors profit etc., complete but excluding cost of
steel and its fabrication charges for finished item of
work (APSS No. 402)

a) Columns :
un supported height up to 4.27 m
Third Floor : 251.00 CUM ONE CUM #REF! #REF!

b) Roof Beams
un supported height up to 4.27 m
Third Floor : 161.00 CUM ONE CUM #REF! #REF!

c) Roof Slab 125mm thick


un supported height up to 4.27 m
Third Floor : 283.00 SQM ONE SQM #REF! #REF!

d) Roof Slab 150mm thick


un supported height up to 4.27 m
Third Floor : 1647.00 SQM ONE SQM #REF! #REF!

e) Roof Slab 175mm thick


un supported height up to 4.27 m
Third Floor : 1170.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 342of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
11 Supply and placing of the Design Mix Concrete M30
grade corresponding to IS 456 with minimum cement
content of 400 kgs per 1 cum of concrete using
batching and mixing plant of 15 cum per hour capacity
with 20mm size graded machine crushed hard granite
metal (coarse aggregate - as per IS 383 - 1970 and IS
2386 Part 1 to Part 8) from approved quarry including
cost and conveyance of all materials like cement, fine
aggregate (sand), coarse aggregate, water etc., to site,
centering using casurina ballies , bamboos , wooden
reapers , runners , wood posts , wall plates etc., for
60cm wide sun-shades 7.5cm thick at fixed end and
5cm thick at free end with an average thickness of
6.25cm including all operational, incidental and labour
charges , transporting concrete using transit mixer,
lifting concrete mechnically, laying concrete using
concrete pump, curing, overheads & contractors profit
complete etc., but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No. 402, 403 & 903)

Cellar Floor : 163.00 RM ONE RM #REF! #REF!

Lower Ground Floor : 318.00 RM ONE RM #REF! #REF!

First Floor : 154.00 RM ONE RM #REF! #REF!

Second Floor : 231.00 RM ONE RM #REF! #REF!

Third Floor : 102.00 RM ONE RM #REF! #REF!

Fourth Floor : 221.00 RM ONE RM #REF! #REF!

Fifth Floor : 9.00 RM ONE RM #REF! #REF!

12 Reinforced Cement Concrete M 20 nominal mix using


12mm size hard granite machine crushed graded
metal (coarse aggregate - as per IS 383 - 1970 and IS
2386 Part 1 to Part 8) from approved quarry, using a
minimum quantity of 350 kgs. of cement per 1 cum of
concrete using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering,
shuttering, labour charges such as weigh batching,
machine mixing, hire charges of concrete mixer, laying
concrete, lift charges, curing etc., and overheads &
contractors profit complete for finished item of work
(APSS No. 402 & 403) for platforms and shelves.

a 50mm thick platforms / lofts:


Cellar Floor : 19.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 343of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
Lower Ground Floor : 120.00 SQM ONE SQM #REF! #REF!

First Floor : 34.00 SQM ONE SQM #REF! #REF!

Second Floor : 39.00 SQM ONE SQM #REF! #REF!

Third Floor : 29.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 192.00 SQM ONE SQM #REF! #REF!

b 25mm thick shelves :


Cellar Floor : 3.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 40.00 SQM ONE SQM #REF! #REF!

First Floor : 9.00 SQM ONE SQM #REF! #REF!

Second Floor : 17.00 SQM ONE SQM #REF! #REF!

Third Floor : 71.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 108.00 SQM ONE SQM #REF! #REF!

13 Plain Cement Concrete M 20 nominal mix using 20mm


size graded machine crushed hard granite metal
(coarse aggregate - as per IS 383 - 1970 and IS 2386
Part 1 to Part 8) from approved quarry using concrete
Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity including cost
and conveyance of all materials like cement, fine
aggregate(sand), coarse aggregate, water etc. to site
including all charges centering, labour charges such as
weigh batching, machine mixing, hire charges of
concrete mixer, laying concrete in position, curing etc.,
& lift charges , and overheads & contractors profit for
steps for finished item of work. (APSS No. 402)

Cellar Floor : 4.00 CUM ONE CUM #REF! #REF!

Lower Ground Floor : 6.00 CUM ONE CUM #REF! #REF!

First Floor : 6.00 CUM ONE CUM #REF! #REF!

Second Floor : 6.00 CUM ONE CUM #REF! #REF!

Third Floor : 6.00 CUM ONE CUM #REF! #REF!

Fourth Floor : 6.00 CUM ONE CUM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 344of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
14 Reinforced Cement Concrete M 20 nominal mix
using 12mm size hard granite machine crushed
graded metal (coarse aggregate - as per IS 383 - 1970
and IS 2386 Part 1 to Part 8) from approved quarry,
using a minimum quantity of 350 kgs. of cement per 1
cum of concrete using concrete Mixer 10 / 7 cft (0.2 /
0.8 cum) capacity including cost and conveyance of
all materials like cement, fine aggregate (Sand),
coarse aggregate, water etc., to site including
centering, shuttering, labour charges such as weigh
batching, machine mixing, hire charges of concrete
mixer, laying concrete, lift charges, curing etc., and
overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for sill slabs.

Cellar Floor : 1.00 CUM ONE CUM #REF! #REF!

Lower Ground Floor : 2.00 CUM ONE CUM #REF! #REF!

First Floor : 1.90 CUM ONE CUM #REF! #REF!

Second Floor : 3.90 CUM ONE CUM #REF! #REF!

Third Floor : 2.00 CUM ONE CUM #REF! #REF!

Fourth Floor : 3.30 CUM ONE CUM #REF! #REF!

15 Brick masonry for panel walls in superstructure with


CM (1:8) prop: (Cement : Sand) using common burnt
clay bricks of class as per Table- I of IS:1077-1992,
Non- Modular or traditional size 23 x 11 x 7 cms from
approved source having minimum crushing strength of
40 Kg/Sqcm. including cost and conveyance of all
materials like cement, screened sand, bricks, water
etc., to site, labour charges, like mixing cement mortar,
scaffolding charges, constructing masonry, lift charges,
curing, etc.,and overheads & contractors profit
complete for finished item of work. (APSS No. 501 &
504).

Cellar Floor : 245.00 CUM ONE CUM #REF! #REF!

Lower Ground Floor : 472.00 CUM ONE CUM #REF! #REF!

First Floor : 445.00 CUM ONE CUM #REF! #REF!

Second Floor : 368.00 CUM ONE CUM #REF! #REF!

Third Floor : 580.00 CUM ONE CUM #REF! #REF!

Fourth Floor : 388.00 CUM ONE CUM #REF! #REF!

Fifth Floor : 86.00 CUM ONE CUM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 345of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
16 Reinforced Brick Masonry for partition walls (11.0 cm
thick) in CM (1:4) prop. (Cement : Sand) using
common burnt clay bricks of class as per Table- I of
IS:1077-1992, Non- Modular or traditional size 23 x
11 x 7 cms from approved source having minimum
crushing strength of 40 Kg/Sq.cm and placing 2 Nos.
of 6mm M.S plain rods in every third layer with free
ends of the reinforcement pegged into mortar joints of
main brick walls where applicable including cost and
conveyance of all materials like cement, steel, sand,
bricks, water etc., to site, all operational, incidental
charges such as labour charges for mixing cement
mortar, scaffolding charges, constructing masonry, lift
charges, curing, etc., and overheads & contractors
profit but excluding cost of steel and its fabrication
charges complete for finished item of work. (APSS No.
of 501 & 509)

Cellar Floor : 238.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 1262.00 SQM ONE SQM #REF! #REF!

First Floor : 1358.00 SQM ONE SQM #REF! #REF!

Second Floor : 1394.00 SQM ONE SQM #REF! #REF!

Third Floor : 1726.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 1161.00 SQM ONE SQM #REF! #REF!

Fifth Floor : 458.00 SQM ONE SQM #REF! #REF!

17 Plain Cement Concrete (1:3:6) nominal mix using


20mm size graded machine crushed hard granite
metal (coarse aggregate - as per IS 383 - 1970 and IS
2386 Part 1 to Part 8) from approved quarry using
concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
including cost and conveyance of all materials like
cement, fine aggregate(sand), coarse aggregate,
water etc. to site including all charges for machine
mixing, hire charges of concrete mixer, laying concrete
in position, curing etc., & lift charges , and overheads
& contractors profit for bed blocks & hold fasts for
finished item of work. (APSS No. 402)

Cellar Floor : 5.80 CUM ONE CUM #REF! #REF!

Lower Ground Floor : 12.60 CUM ONE CUM #REF! #REF!

First Floor : 14.00 CUM ONE CUM #REF! #REF!

Second Floor : 18.00 CUM ONE CUM #REF! #REF!

Third Floor : 13.00 CUM ONE CUM #REF! #REF!

Fourth Floor : 17.00 CUM ONE CUM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 346of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)

Fifth Floor : 1.00 CUM ONE CUM #REF! #REF!

18 Providing Thermo Mechanically Treated (TMT) (Fe 500


/ Fe 500 D grade as per IS 1786-1979) of different
diameters for RCC works including labour charges for
straightening, cutting, bending to required sizes and
shapes, placing in position with cover blocks of
approved materials and size and tying and lap-splicing
with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and
drawings, including cost and conveyance of steel bars,
including all wastages such as overlaps, couplings,
chairs, spacer bars including cost and conveyance of
binding wire, cover blocks and all incidental,
operational, labour charges such as cutting, bending,
placing in position, tying etc., and overheads &
contractors profit complete for finished item of work.
( APSS No.126)

Cellar Floor : 360.72 MT ONE MT #REF! #REF!

Lower Ground Floor : 152.40 MT ONE MT #REF! #REF!

First Floor : 114.20 MT ONE MT #REF! #REF!

Second Floor : 115.80 MT ONE MT #REF! #REF!

Third Floor : 122.50 MT ONE MT #REF! #REF!

Fourth Floor : 115.60 MT ONE MT #REF! #REF!

Fifth Floor : 29.00 MT ONE MT #REF! #REF!

19 Providing Mild steel (MS) steel bars (Fe 250 grade as


per IS 432) of different diameters including labour
charges for straightening, cutting, bending to required
sizes and shapes, placing in position with cover blocks
of approved materials and size and tying and lap-
splicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and
drawings, including cost and conveyance of steel bars,
including all wastages such as overlaps, couplings,
chairs, spacer bars including cost and conveyance of
binding wire, cover blocks and all incidental,
operational, labour charges such as cutting, bending,
placing in position, tying etc., and overheads &
contractors profit complete for finished item of work.
( APSS No.126)

Cellar Floor : 0.86 MT ONE MT #REF! #REF!

Lower Ground Floor : 2.60 MT ONE MT #REF! #REF!

First Floor : 0.86 MT ONE MT #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 347of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)

Second Floor : 1.86 MT ONE MT #REF! #REF!

Third Floor : 1.67 MT ONE MT #REF! #REF!

Fourth Floor : 3.03 MT ONE MT #REF! #REF!

Fifth Floor : 0.23 MT ONE MT #REF! #REF!

20 Ornamental ceiling plastering 12mm thick single coat


in CM (1:5) using screened sand including cost and
conveyance of all materials like cement, sand, water
etc., to site and all operational, incidental charges on
materials and including cost of all labour charges for
mixing mortar, finishing, curing as directed by
Engineer-in-charge etc., and overheads & contractors
profit complete for finished item of work.(SS 901,903 &
904)

Cellar Floor : 1837.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 2781.00 SQM ONE SQM #REF! #REF!

First Floor : 2683.00 SQM ONE SQM #REF! #REF!

Second Floor : 2746.00 SQM ONE SQM #REF! #REF!

Third Floor : 2163.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 459.00 SQM ONE SQM #REF! #REF!

Fifth Floor : 364.00 SQM ONE SQM #REF! #REF!

21 Plastering 12mm thick in two coats using screened


sand with base coat of 8mm thick in CM (1:6) and top
coat of 4mm thick in CM (1:4) with dubara sponge
finishing including cost and conveyance of all materials
like cement, sand, water etc., to site and all
operational, incidental charges on materials and
including cost of all labour charges for mixing mortar,
finishing, scaffolding, lift charges, curing, including
cutting grooves as directed by Engineer - in - charge
etc., and overheads & contractors profit complete for
finished item of work. (SS 901,903 & 904)
For Interal Walls

Cellar Floor : 1294.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 3650.00 SQM ONE SQM #REF! #REF!

First Floor : 3640.00 SQM ONE SQM #REF! #REF!

Second Floor : 3511.00 SQM ONE SQM #REF! #REF!

Third Floor : 4193.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 2936.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 348of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)

Fifth Floor : 407.00 SQM ONE SQM #REF! #REF!

22 Plastering 20mm thick in two coats using screened


sand with base coat of 16mm thick in CM(1:6) and top
coat of 4mm thick in CM(1:4) with dubara sponge
finishing including cost and conveyance of all materials
like cement, sand, water etc., to site and all
operational, incidental charges on materials and
including cost of all labour charges for mixing mortar,
finishing, scaffolding, lift charges, curing, including
cutting grooves as directed by Engineer-in-charge etc.,
and overheads & contractors profit complete for
finished item of work .(SS 901,903 & 904)
For Internal Walls

Cellar Floor : 862.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 2433.00 SQM ONE SQM #REF! #REF!

First Floor : 2426.00 SQM ONE SQM #REF! #REF!

Second Floor : 2340.00 SQM ONE SQM #REF! #REF!

Third Floor : 2796.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 1957.00 SQM ONE SQM #REF! #REF!

23 Plastering 20mm thick in two coats using screened


sand with base coat of 16mm thick in CM(1:6) and top
coat of 4mm thick in CM(1:4) with dubara sponge
finishing including cost and conveyance of all materials
like cement, sand, water etc., to site and all
operational, incidental charges on materials and
including cost of all labour charges for mixing mortar,
finishing, scaffolding, lift charges, curing, including
cutting grooves as directed by Engineer-in-charge etc.,
and overheads & contractors profit complete for
finished item of work .(SS 901,903 & 904)
For External Walls

Cellar Floor : 796.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 1462.00 SQM ONE SQM #REF! #REF!

First Floor : 1801.00 SQM ONE SQM #REF! #REF!

Second Floor : 1441.00 SQM ONE SQM #REF! #REF!

Third Floor : 2160.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 2312.00 SQM ONE SQM #REF! #REF!

Fifth Floor : 1419.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 349of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
23 Flooring with non-skid red or white full body Ceramic
floor tiles of size 300 mm x 300 mm and thickness
between 7-8 mm 1st quality conforming to IS:13711,
IS:13712, IS:13630 (Parts 1 to 15) of any colour and
finish in all shades and designs as approved by
Engineer-in-charge, set over base coat of cement
mortar (1:8), 12mm thick using screened sand over CC
bed already laid or RCC roof slab, including neat
cement slurry of honey like consistency spread @ 3.3
Kgs per sqm & jointed neatly with white cement paste
to full depth mixed with pigment of matching shade,
including cost of all materials like cement, screened
sand , water and tiles etc., and overheads &
contractors profit complete for finished item of work.
(APSS No.701 & 707)

Cellar Floor : 78.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 249.00 SQM ONE SQM #REF! #REF!

First Floor : 312.00 SQM ONE SQM #REF! #REF!

Second Floor : 180.00 SQM ONE SQM #REF! #REF!

Third Floor : 100.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 130.00 SQM ONE SQM #REF! #REF!

24 Flooring with non-skid Double charged / multi charged


stain free full body porcelain vitrified tiles with double
layer pigment of Size 600 x 600 mm and thickness
between 8-10 mm 1st quality conforming to IS:13711,
IS:13712, IS:13630 (Parts 1 to 15) of any colour and
finish in all shades and designs with borders and
design as per the approved flooring pattern as directed
by the Engineer-In -Charge, laying tiles using spacers
of 2mm thick, set over a base coat of CM (1:8) prop.
12mm thick using screened sand over CC bed already
laid or RCC roof slab , including neat cement slurry of
honey like consistancy spread @ 3.3 kgs per sqm.
and jointed neately with white cement paste to full
depth mixed with pigment of matching shade
including cost and conveyance of all materials like
cement, sand, water, tiles, white cement etc., to site
(excluding cost of C.C. bed) including cost of base
coat and all labour charges for mixing of cement
mortar, laying tiles to required slope as directed by
the Engineer- in-charge etc.,and overheads &
contractors profit complete for finished item of work.
(APSS No.701 & 707)

Cellar Floor : 369.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 1444.00 SQM ONE SQM #REF! #REF!

First Floor : 900.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 350of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
Second Floor : 2352.00 SQM ONE SQM #REF! #REF!

Third Floor : 2403.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 2463.00 SQM ONE SQM #REF! #REF!

25 Supply and application of epoxy flooring of light green


or light blue colour in Operation Theatres and labour
rooms - SIKA Epoxy seamless joint free finish with
3mm thickness and anti slip & water washable
chemical resistance durable and non particle shedding
with attractive finishing including cost and conveyance
of all materials and all labour charges, overheads and
contractor profit etc., complete for finished item of
work.

Third Floor : #NAME? SQM ONE SQM #REF! #NAME?

25 Flooring with 16 mm to 18 mm thick high polished


granite stone slabs other than black and regular
colours (i.e. of shades like paradiso / bala flower /
copper silk / laka red / lavender blue) with borders and
design as per the pattern approved by the Engineer-in-
Charge of length not less than 2.43 mts set over base
coat of cement mortar (1:8) , 20mm thick using
screened sand over CC bed already laid or RCC roof
slab including neat grey cement slurry of honey like
consistency spread @ 3.3 Kg per sqm and jointed
neatly with white cement paste mixed with pigment of
matching shade to full depth including cost and
conveyance of all materials like cement , sand , water ,
granite slabs etc., to work site and all operational,
incidental labour & lift charges, polishing charges, cost
of base coat and overheads & contractors profit
complete for finished item of work (S.S.701 & special)

Cellar Floor : 144.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 986.00 SQM ONE SQM #REF! #REF!

First Floor : 1367.00 SQM ONE SQM #REF! #REF!

Second Floor : 112.00 SQM ONE SQM #REF! #REF!

Third Floor : 43.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 43.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 351of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
26 Flooring with chequered Cement Concrete heavy duty
tiles conforming to IS: 13801 using aggregates,
cement, pigments of size 300mm x 300 mm and
thickness 25 mm of any shades as approved by
Engineer - In - Charge set over base coat of cement
mortar (1:6), 12 mm thick using screened sand over
CC bed alredy laid or RCC roof slab including neat
cement slurry of honey like consistency spread @ 3.3
kgs per sqm and jointed with neat white cement to full
depth mixed with pigment of matching shade including
cost and conveyance of all materials like cement,
sand, water and tiles etc.,and overheads & contractors
profit complete for finished item of work.

Cellar Floor : 102.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 102.00 SQM ONE SQM #REF! #REF!

First Floor : 104.00 SQM ONE SQM #REF! #REF!

Second Floor : 102.00 SQM ONE SQM #REF! #REF!

Third Floor : 104.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 104.00 SQM ONE SQM #REF! #REF!

27 Supply of precast concrete blocks for paving of M-40


grade and thickness not less than 80 mm for Medium
traffic areas conforming to IS 15658:2006 in all shapes
and designs as per the manufacturer's specification
including cost and conveyance of all materials and all
labour charges etc.

Cellar Floor : 80.00

Lower Ground Floor : 109.00

First Floor : 109.00

298.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 352of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
27 Vaccum dewatering cement concrete flooring 50mm 1144.00 SQM ONE SQM #REF! #REF!
thick using M 30 grade design mix corresponding to
IS 456 with minimum cement content of 400 kgs per 1
cum of concrete and required quantity of Chemical
Admixtures per 1 cum of concrete using WEIGH
BATCHER / MIXER with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per
IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry in panels as per drawing / design, laid
to proper level and slope including consolidating with
power driven mechanical vibrators (both needle &
screed vibrators), dewatering by vacuum process
"Tremix" method, floated with neat cement and power
troweled to achieve smooth finishing, including MS
Shuttering, finishing, rounding of the edges, curing
including cost and conveyance of all materials like
cement, coarse aggregate, sand etc., to site,
centering, shuttering, machine mixing, laying concrete,
vibrating, curing, hire charges of all tools and plants, all
other incidental and operational charges, labour
charges and all taxes etc., complete for finished item
of work but excluding cost of steel and its fabrication
charges for finished item of work.

28 Providing 16 mm to 18 mm thick high polished leather


finish granite stone slabs (steel grey or pearl black)
with borders and design as per the pattern approved
by the Engineer-in-Charge of length not less than 2.43
mts set over base coat of cement mortar (1:5) , 12mm
thick using screened sand over CC bed already laid or
RCC roof slab including neat grey cement slurry of
honey like consistency spread @ 3.3 Kg per sqm and
jointed neatly with white cement paste mixed with
pigment of matching shade to full depth including cost
and conveyance of all materials like cement , sand ,
water , granite slabs etc., to work site and all
operational, incidental labour & lift charges, full
rounding the edges of treads , polishing charges, cost
of base coat and overheads & contractors profit
complete for finished item of work for treads and risers
(S.S.701 & special)

a Treads
Cellar Floor : 43.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 82.00 SQM ONE SQM #REF! #REF!

First Floor : 77.00 SQM ONE SQM #REF! #REF!

Second Floor : 82.00 SQM ONE SQM #REF! #REF!

Third Floor : 78.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 66.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 353of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
b Risers
Cellar Floor : 24.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 44.00 SQM ONE SQM #REF! #REF!

First Floor : 43.00 SQM ONE SQM #REF! #REF!

Second Floor : 44.00 SQM ONE SQM #REF! #REF!

Third Floor : 42.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 36.00 SQM ONE SQM #REF! #REF!

29 Flooring with 16 mm to 18 mm thick high polished


granite stone slabs black colour as approved by the
Engineer-in-Charge of length not less than 2.43 mts
set over base coat of cement mortar (1:8) , 20mm thick
using screened sand over CC bed already laid or RCC
roof slab including neat grey cement slurry of honey
like consistency spread @ 3.3 Kg per sqm and jointed
neatly with white cement paste mixed with pigment of
matching shade to full depth including cost and
conveyance of all materials like cement , sand , water ,
granite slabs etc., to work site and all operational,
incidental labour & lift charges, half rounding the
edge , polishing charges, cost of base coat and
overheads & contractors profit complete for finished
item of work for platforms (S.S.701 & special)

Cellar Floor : 9.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 72.00 SQM ONE SQM #REF! #REF!

First Floor : 25.00 SQM ONE SQM #REF! #REF!

Second Floor : 27.00 SQM ONE SQM #REF! #REF!

Third Floor : 14.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 161.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 354of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
30 Providing window sills with 16 mm to 18 mm thick high
polished granite stone slabs black colour as approved
by the Engineer-in-Charge set over base coat of
cement mortar (1:8) , 20mm thick using screened sand
over CC bed already laid including neat grey cement
slurry of honey like consistency spread @ 3.3 Kg per
sqm and jointed neatly with white cement paste mixed
with pigment of matching shade to full depth including
cost and conveyance of all materials like cement ,
sand , water , granite slabs etc., to work site and all
operational, incidental labour & lift charges, half
rounding the edge , polishing charges, cost of base
coat and overheads & contractors profit complete for
finished item of work (S.S.701 & special)

Cellar Floor : 11.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 31.00 SQM ONE SQM #REF! #REF!

First Floor : 38.00 SQM ONE SQM #REF! #REF!

Second Floor : 75.00 SQM ONE SQM #REF! #REF!

Third Floor : 40.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 66.00 SQM ONE SQM #REF! #REF!

31 Providing skirting 10 cm height with Double charged /


multi charged stain free full body porcelain vitrified tiles
with double layer pigment of Size 600 x 600 mm and
thickness between 8-10 mm of any colour and finish in
all shades and designs, length equal to flooring tiles,
flushed to wall surface to set over base coat of
CM(1:5) 12 mm thick using screened sand with
cement slurry of honey like consistency spread at the
rate of 3.30 kgs per sqm and jointing with white
cement paste mixed with pigment of matching shade
to full depth, including cost of all materials like tiles,
cement, sand and water etc.,and overheads &
contractors profit complete for finished item of work.
(APSS No.701 &707)

Cellar Floor : 314.00 RM ONE RM #REF! #REF!

Lower Ground Floor : 1488.00 RM ONE RM #REF! #REF!

First Floor : 912.00 RM ONE RM #REF! #REF!

Second Floor : 1110.00 RM ONE RM #REF! #REF!

Third Floor : 1191.00 RM ONE RM #REF! #REF!

Fourth Floor : 783.00 RM ONE RM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 355of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
32 Providing skirting to internal walls 10 cm height with
High Polished Granite 16 mm to 18 mm thick up to 8'-
00 (2.43 M) other than black and regular colours,
length equal to flooring slabs set over base coat of
CM(1:5) 12 mm thick using screened sand with
cement slurry of honey like consistency spread at the
rate of 3.30 kgs per sqm and jointing with white
cement paste mixed with pigment of matching shade
to full depth, including cost of all materials like tiles,
cement, sand and water etc., and overheads &
contractors profit complete for finished item of work.

Cellar Floor : 120.00 RM ONE RM #REF! #REF!

Lower Ground Floor : 121.00 RM ONE RM #REF! #REF!

First Floor : 78.00 RM ONE RM #REF! #REF!

Second Floor : 121.00 RM ONE RM #REF! #REF!

Third Floor : 78.00 RM ONE RM #REF! #REF!

Fourth Floor : 78.00 RM ONE RM #REF! #REF!

33 Supply and application of epoxy coving with SIKA


brand with 50mmx50mm width at the corners of the all
walls in Operation Theatres, labour rooms including
cost and conveyance of all materials and labour
charges, overheads and contractor profit etc.,
complete for finished item of work .

Fourth Floor : 97.00 RM ONE RM #REF! #REF!

34 Providing dadooing with glazed red or white full body


ceramic wall tiles of size 200mm x 300 mm / 245 mm x
325 mm and thickness 6 mm 1st quality conforming to
IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any
colour and finish in all shades and designs with
borders as approved by Engineer-in-Charge flushed
to wall surface set over base coat of CM(1:5) 12 mm
thick using screened sand with cement slurry of honey
like consistency spread at the rate of 3.30 kgs per sqm
and jointing with white cement paste mixed with
pigment of matching shade to full depth, including cost
of all materials like tiles, cement, sand and water etc.,
and overheads & contractors profit complete for
finished item of work.

Cellar Floor : 233.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 525.00 SQM ONE SQM #REF! #REF!

First Floor : 993.00 SQM ONE SQM #REF! #REF!

Second Floor : 772.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 356of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)

Third Floor : 454.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 542.00 SQM ONE SQM #REF! #REF!

35 Providing dadooing with glazed full body porcelain


wall tiles of size 300mm x 600 mm with any type of
design texture such as marble finish, wooden,
bamboo, stone finishes etc., scratch less, stain free
and thickness between 6-8 mm 1st quality conforming
to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any
colour and finish in all shades and designs with
borders and design as per the approved pattern as
approved by Engineer-in-Charge flushed to wall
surface set over base coat of CM(1:5) 12 mm thick
using screened sand with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per sqm and
jointing with white cement paste mixed with pigment of
matching shade to full depth, including cost of all
materials like tiles, cement, sand and water etc., and
overheads & contractors profit complete for finished
item of work.

Cellar Floor : 6.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 559.00 SQM ONE SQM #REF! #REF!

First Floor : 784.00 SQM ONE SQM #REF! #REF!

Second Floor : 1086.00 SQM ONE SQM #REF! #REF!

Third Floor : 1341.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 1578.00 SQM ONE SQM #REF! #REF!

36 Providing cladding to walls with High Polished


Granite 16 mm to 18 mm thick up to 8'-00 (2.43 M)
other than black and regular colours, length equal to
flooring slabs set over base coat of CM(1:5) 12 mm
thick using screened sand with cement slurry of honey
like consistency spread at the rate of 3.30 kgs per sqm
and jointing with white cement paste mixed with
pigment of matching shade to full depth, including cost
of all materials like tiles, cement, sand and water etc.,
and overheads & contractors profit complete for
finished item of work.

Cellar Floor : 12.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 247.00 SQM ONE SQM #REF! #REF!

First Floor : 27.00 SQM ONE SQM #REF! #REF!

Second Floor : 13.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 357of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
Third Floor : 5.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 5.00 SQM ONE SQM #REF! #REF!

37 Filling with well burnt cinder aggregate as per IS:2686-


1977 in sunken slabs including cost and conveyance
of cinder, labour charges for filling, ramming,
overheads and contractor profit etc., complete for
finished item of work
First Floor : 40.00 CUM ONE CUM #REF! #REF!

Second Floor : 40.00 CUM ONE CUM #REF! #REF!

Third Floor : 41.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 61.00 SQM ONE SQM #REF! #REF!

38 Reinforced cement concrete (1:5:10) proportion


(Cement: fine aggregates: coarse aggregate) using
40mm size (SS5) hard granite metal (coarse
aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate
(sand), coarse aggregate, water etc., to site including
centering using Casurina Ballies , Bamboos , Wooden
Reapers , Runners , Wood Posts , Wall Plates etc.,
shuttering, machine mixing, laying concrete, lifting
concrete manually , vibrating, curing, etc., and
overheads & contractors profit complete as per
drawings but excluding cost of steel and it's fabrication
charges for finished item of work (APSS NO. 402 &
403) for dummy columns.

Fifth Floor : 40.00 CUM ONE CUM #REF! #REF!

39 Providing impervious coat to exposed RCC roof slab


surfaces of sump , sump side wall,sump bottom
slab,in side of septic tank , in sunken slabs etc. to
required slopes with CM (1:3) prop. using screened
sand 12mm thick mixed with integral cement water
proofing liquid confirming to IS: 2645-2003
manufactured by reputed manufacturers as approved
by Engineer-in-charge at 200ml per one bag of
cement, laid over roof slab when it is green, finished
smooth with a floating coat of neat cement and thread
lining at regular intervals of 45cmx45cm where ever
necessary including cost and conveyance of all
materials like cement, sand, water proofing compound,
water etc., to site, operational, incidental, and labour
charges for mixing mortar, laying, lift charges,
rendering smooth and thread lining, curing including
rounding off junctions of wall and slab etc., and
overheads & contractors profit complete for finished
item of work. (APSS No. 901 & 903).

First Floor : 28.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 358of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)

Second Floor : 28.00 SQM ONE SQM #REF! #REF!

Third Floor : 29.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 43.00 SQM ONE SQM #REF! #REF!

Fifth Floor : 337.00 SQM ONE SQM #REF! #REF!

40 Providing impervious coat to exposed RCC roof slab


surfaces to required slopes with CM (1:3) prop. using
screened sand 20mm thick (average) mixed with
integral cement water proofing liquid confirming to IS:
2645-2003 manufactured by reputed manufacturers as
approved by Engineer-in-charge at 200ml per one bag
of cement, laid over roof slab when it is green, finished
smooth with a floating coat of neat cement and thread
lining at regular intervals of 45cmx45cm including cost
and conveyance of all materials like cement, sand,
water proofing compound, water etc., to site,
operational, incidental, and labour charges for mixing
mortar, laying, lift charges, rendering smooth and
thread lining, curing including rounding off junctions of
wall and slab etc., and overheads & contractors profit
complete for finished item of work. (APSS No. 901 &
903).

above First Floor : 298.00 SQM ONE SQM #REF! #REF!

Fifth Floor : 2874.00 SQM ONE SQM #REF! #REF!

41 Providing 110 mm Dia ISI marked PVC down water 1107.00 RM ONE RM #REF! #REF!
take pipes with socket , 2.5mm thick 4.0 kg/sq.cm
pressure of ISI marked including cost of necessary
PVC Bends, shoes, iron / PVC clamps and all other
accessories and fixing in position including cost and
conveyance of all materials, operational & incidental
charges including all labour charges for fixing at site
etc., and overheads & contractors profit complete for
finished item of work. (APSS No. 1328)

42 RCM facia 50mm thick in CM(1:3) using screened


sand for drop walls, fins with rabbit wire mesh &
nomianl reinforcement as directred by Engineer - In -
Charge with dubara sponge finishing,including cost
and conveyance of all materials to site, operationals
&incidental,cost and conveyance of cement, wire mesh
water to work site, centering, scaffolding and form
work,lift charges etc., and overheads & contractors
profit complete for finished item of work but excluding
cost of steel and its fabrication charges for finished
item of work(APSS NO.403&903)

Lower Ground Floor : 16.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 359of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)

First Floor : 21.00 SQM ONE SQM #REF! #REF!

Second Floor : 6.00 SQM ONE SQM #REF! #REF!

Third Floor : 6.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 6.00 SQM ONE SQM #REF! #REF!

43 Supply and fixing of two shutter main door cum fixed


window as per approved drawing with best teak wood
frame of section 150mm x 100 mm with fixed fan light
of 500mm at top and fixed panels of 600mm width at
sides fixed with 12mm thick Tinted - Bronze/Green
glass using 12mm x 12mm teak wood beading and
fixing ornamental grill made of 25mm x 5mm MS flats
as per the approved drawing in fan light portion and
fixed panels and 1st class teak wood top and middle
rails & styles of section 120mm x 35mm, bottom rail of
size 150mm x 35mm and 12mm thick plain float glass
for shutter with ornamental etching including cost and

conveyance to site of teak wood frame, shutters,


glass including supply and fixing 6 Nos MS Zhold
fasts of size 300 mm x 40 mm x 5mm including cost of
ISI marked brass fixtures of 8 Nos butt hinges(IS:205)
250mm long , 1 No. aldrop (IS:2681) 450mm long, 3
Nos tower bolts- 10mm (IS:204) of 200 mm long , 2
Nos 450 mm long fancy handles, 2 Nos door stoppers,
2 Nos. Rubber / Nylon door stop bushes including
fixing the fixtures to door with required number of
screws, bolt and nuts including labour charges for
fixing the frame in position, fixing the shutters to the
frame, fixing glass in fan light portion etc., including
overheads & contractors profit complete for finished
item of work as per APSS 1001 & 1002 (The vertical
frame of door shall be embedded in flooring for a depth
of not less than 40 mm) (3000mm x 2600mm)

Lower Ground Floor : 18.30

First Floor : 18.30


36.60 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 360of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
44 Providing & Fixing of Scientific Doors with metal door
frames and door shutters made of galvanize steel
(base steel as per IS 513 of 0.58 mm thick D quality,
galvanized as per IS 277 with Zinc of 120 GSM).
coated with Zinc Phosphate Primer to receive any
paint on site or finished with Thermosetting
Polyurethane paint of Aliphatic Grade providing high
levels of scratch resistance and durability/Epoxy
polyester powder for powder coating paint thickness
50-60 microns (Dry film thickness) outer frame section
of 100 x 58 mm x 1.2 mm thick, shutter section of 0.80
mm thick galvanized steel sheet pressed (roll formed)
for 46mm thick fully flush, double skin door shell seam
joints at stile edges, in-fill of honeycomb Kraft paper
used to give the required rigidity and effective acoustic
insulation with 6” Tower bolt – 2 Nos., 6” D handles – 2
Nos., 10” Aldrops – 1 No., Butt Hinges – 6 Nos,
Mortise Lock of approved quality – 1 No, frames fixed
to the concrete/masonry wall by means of self
expanding screws including overheads and contractor
profit etc., complete for finished item of work for
Double leaf Door

Fourth Floor : 20.90 SQM


20.90 SQM ONE SQM #REF! #REF!

45 Supply and fixing powder coated aluminium fully


glazed swing door as per the approved drawing with
fixed fan light of 500mm height at top door using
aluminium sections of 101.60 mmm x 44.45mm , 3.18
mm thick for frame and door shutter made of styles ,
top and middle rail of 47.62mm x 44.45mm , 3.18 mm
thick and bottom rail of 114.30mm x 44.45 mm ,
3.18mm thick,powder coating of alluminium sections
25mm microns thick, 5 mm thick plain float glass fitted
with suitable aluminium glazing clips and rubber
beading in fan light portion, double shutters fitted with
5mm thick frosted / ground glass in the top half and
MDF Board: interior-Both Side Laminated -12 mm thick
in the bottom half fitted with suitable aluminium
glazing clips and rubber beading,shutters mounted on
double action hydraulic floor spring of approved brand
manufacture IS : 6315 marked , Hardwyn make M-
3000 for doors including cost of cutting floors as
required , embedding in floors

APMSIDC-PALASA Hospital Building - Civil Abs 361of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
and SS cover plates with brass pivot and sigle piece
MS Sheet outer box with slide plate etc.complete
(Weight Capacity up to 130 Kgs) as approved by
Engineer-in-Charge including supply and fixing ISI
marked powder coated aluminium fixtures of 3 Nos.
of butt hinges (IS:205) of 150mm long(for each
shutter), 4 Nos.tower bolts 10mm bolt (IS:204) 300mm
long , 4 Nos.alluminium handles (IS:208) 150mm dia
and 2 Nos. aldrops (IS:2681) 300mm long including
labour charges for manufacturing door , fixing the door
with required No. of screws etc., including overheads
& contractors profit complete for finished item of
work. (The Aluminium section used shall be standard
make confirming to IS 1948 – 1961) and as approved
by the Engineer) (2000mm x 2600mm)

Cellar Floor : 26.00 SQM

Lower Ground Floor : 67.60 SQM

First Floor : 104.00 SQM

Second Floor : 104.00 SQM

Third Floor : 124.80 SQM

Fourth Floor : 98.80 SQM


525.20 SQM ONE SQM #REF! #REF!

46 Supply and fixing of doors as per approved drawings


with medium teak wood frame of section 100mm x 65
mm with split type fan light of 500mm at the top
fixed with 4mm thick pin headed glass using 12mm x
12mm Teak Wood beading and 2 Nos. of 10mm MS
Square bars and ISI marked flush door shutter of
30mm thick double shutters with bond wood solid
block board type core having cross bands and face
veneers, hot pressed bonded with water proof phenol
formaldehyde synthetic resin factory made conforming
to IS 2202-1991 (Part-I) both sides commercial ply with
internal lipping on all sides, fixing 1mm thick mat
finish laminated sheet to full width and height of
the flush shutter both sides

APMSIDC-PALASA Hospital Building - Civil Abs 362of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
including cost and conveyance to site of teak wood
frame, flush shutter, laminate sheet including supply
and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40
mm x 5mm including cost of ISI marked Alumimium
fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1
No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts
(IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150mm
long handles (IS:208), 2 Nos. door stoppers and 2
Nos. Rubber / Nylon door stop bushes including fixing
the fixtures to door with required number of screws,
bolt and nuts including labour charges for fixing the
frame in position, fixing the shutter to the frame, fixing
glass in fan light portion etc., including overheads &
contractors profit complete for finished item of work as
per APSS 1001 & 1002 (The vertical frame of door
shall be embedded in flooring for a depth of not less
than 10 mm) (1500mm x 2600mm)

Cellar Floor : 3.90 SQM

Lower Ground Floor : 70.20 SQM

First Floor : 70.20 SQM

Second Floor : 7.80 SQM

Third Floor : 35.10 SQM

Fourth Floor : 58.50 SQM


245.70 SQM ONE SQM #REF! #REF!

47 Supply and fixing of doors as per approved drawings


with medium teak wood frame of section 100mm x
65 mm with split type fan light of 500mm at the top
fixed with 4mm thick pin headed glass using 12mm x
12mm Teak Wood beading and 2 Nos. of 10mm MS
Square bars and ISI marked flush door shutter of
30mm thick double shutters with bond wood solid
block board type core having cross bands and face
veneers, hot pressed bonded with water proof phenol
formaldehyde synthetic resin factory made conforming
to IS 2202-1991 (Part-I) both sides commercial ply with
internal lipping on all sides, fixing 1mm thick mat
finish laminated sheet to full width and height of
the flush shutter both sides

APMSIDC-PALASA Hospital Building - Civil Abs 363of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
including cost and conveyance to site of teak wood
frame, flush shutter, laminate sheet including supply
and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40
mm x 5mm including cost of ISI marked Aluminium
fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1
No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts
(IS:204) of 200 mm x 10 mm dia at top, 2 Nos.
150mm long handles (IS:208), 2 Nos. door stoppers
and 2 Nos. Rubber / Nylon door stop bushes including
fixing the fixtures to door with required number of
screws, bolt and nuts including labour charges for
fixing the frame in position, fixing the shutter to the
frame, fixing glass in fan light portion etc, including
overheads & contractors profit complete for finished
item of work as per APSS 1001 & 1002 (The vertical
frame of door shall be embedded in flooring for a depth
of not less than 10 mm) (1200mm x 2600mm)

Cellar Floor : 6.24 SQM

Lower Ground Floor : 28.08 SQM

First Floor : 28.08 SQM

Second Floor : 21.84 SQM

Third Floor : 34.32 SQM

Fourth Floor : 31.20 SQM

149.76 SQM ONE SQM #REF! #REF!

48 Supply and fixing doors as per drawings with


medium teak wood frame of section 100mm x 65 mm
and ISI marked flush door shutters of 30 mm thick
single shutter with bond wood solid block board type
Core having cross bands and face veneers, hot
pressed bonded with water proof phenol formaldehyde
synthetic resin factory made conforming to IS 2202-
1991 (Part-I) both sides commercial ply with internal
lipping on all sides, fixing 1mm thick mat finish
laminated sheet to full width and height of the
flush shutter both sides including cost and
conveyance to site of teak wood frame, flush shutter,
laminated sheet including supply and

APMSIDC-PALASA Hospital Building - Civil Abs 364of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm
x 5mm including cost of ISI marked Aluminium fixtures
of 3 Nos. butt hinges (IS:205) 150mm long, 1 No.
aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204)
of 200 mm x 10 mm dia at top , 2 Nos. 150 mm long
handles (IS:208), 1 No. door stopper and 1 No. Rubber
/ Nylon door stop bushes including fixing the fixtures
to door with required number of screws, bolt and nuts
including labour charges for fixing the frame in
position, fixing the shutter to the frame etc., including
overheads & contractors profit complete for finished
item of work as per APSS 1001 & 1002 (The vertical
frame of door shall be embedded in flooring for a depth
of not less than 10 mm) (1000mm x 2100mm)

First Floor : 67.60

Second Floor : 23.40

Third Floor : 26.00


117.00 SQM ONE SQM #REF! #REF!

48 Supply and fixing doors as per drawings with


medium teak wood frame of section 100mm x 65 mm
and ISI marked flush door shutters of 30 mm thick
single shutter with bond wood solid block board type
Core having cross bands and face veneers, hot
pressed bonded with water proof phenol formaldehyde
synthetic resin factory made conforming to IS 2202-
1991 (Part-I) both sides commercial ply with internal
lipping on all sides, fixing 1mm thick mat finish
laminated sheet to full width and height of the
flush shutter both sides including cost and
conveyance to site of teak wood frame, flush shutter,
laminate sheet including supply and

fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm


x 5mm including cost of ISI marked Aluminium fixtures
of 3 Nos. butt hinges (IS:205) 150mm long, 1 No.
aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204)
of 200 mm x 10 mm dia at top, 2 Nos. 150 mm long
handles (IS:208), 1 No. door stopper and 1 No. Rubber
/ Nylon door stop bushes including fixing the fixtures
to door with required number of screws, bolt and nuts
including labour charges for fixing the frame in
position, fixing the shutter to the frame etc, including
overheads & contractors profit complete for finished
item of work as per APSS 1001 & 1002 (The vertical
frame of door shall be embedded in flooring for a depth
of not less than 10 mm) (900mm x 2100mm)

Cellar Floor : 22.68 SQM

Lower Ground Floor : 51.03 SQM

APMSIDC-PALASA Hospital Building - Civil Abs 365of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
First Floor : 52.92 SQM

Second Floor : 58.59 SQM

Third Floor : 54.81 SQM

Fourth Floor : 45.36 SQM

Fifth Floor : 9.45 SQM


294.84 SQM ONE SQM #REF! #REF!

49 Supplying and fixing single side prelam solid panel


PVC door frame (Choukhat): Providing and fixing
factory made Pac single side Prelam door frame of the
size 50x7 mm with a wall thickness of 5mm, made out
of extruded 5mm rigid Pac single side prelam sheet,
meter cut at two corners and joined with 2 Nos. of
150mm long brackets of 15 x 15mm MS Square tube.
The two vertical door profiles are to be reinforced with
19 x 19mm MS. square tube of 19 guage. The door
frame shall be fixed to the wall using 65/100mm long
MS. Screws through the frame by using Pac fasteners.
a minimum of 4 Nos. of screws to be provided for each
vertical member and minimum 2nos. for horizontal
member etc. complete as per manufacture
specification and direction of Engineer-incharge
including conveyance of all materials, labour charges
for fixing, overheads & contractors profit complete for
finished item of work.

Cellar Floor : 110.00 RM

Lower Ground Floor : 215.00 RM

First Floor : 215.00 RM

Second Floor : 300.00 RM

Third Floor : 245.00 RM

Fourth Floor : 180.00 RM

1265.00 RM ONE RM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 366of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
50 Providing and fixing 30mm thick factory made moulded
door shutter- wood free consisting of frame made out
of MS. tubes 19gauge thickness and size of
25mmX25mm for styles, top and bottom rails. MS.
Frame shall have a coat of steel primers. The inner
panel shall consist of 25mm thick high density EPS
conforming to IS 4671-1984 bounded with 2mm thick
termite proof, water proof and fire resistant moulded
Pac sheet with 2,4,6 raised panel design in different
plain and / or pre-lam colours after routing to the
moulded design on one side and 2mm plain and / or
pre-lam Pac sheet on other side of the EPS. The edge
of panel to be sealed with lipping of 10mm wide PVC
sheet bottom (made by sticking 2 rigid foam sheet of
5mm thickness using Pac solvent cement) and stiles
sides 25mm(5mmX5) thick and 30mm width Pac sheet
fitted along MS tube for lock provision for lock height
5mm thick Pac sheet of size 150mmX100mm fixed
with upper and lower face of inner side of EPS panel
etc., complete as per direction of Engineer – in-
Charge, manufacture specification and drawing
including ISI marked Aluminium fixtures 3 Nos. butt
hinges (IS:205) of 150mm long, 1 No. aldrop (IS:2681)
250 mm long, 1 No. tower bolt (IS:204) of 150 mm x
10mm dia, 2 Nos. 125mm long handles (IS:208),1 No.
Rubber / Nylon door stop bushes including labour
charges for fixing the shutter to frame etc., including
overheads & contractors profit complete for finished
item of work

Cellar Floor : 36.96 SQM

Lower Ground Floor : 72.24 SQM

First Floor : 72.24 SQM

Second Floor : 100.80 SQM

Third Floor : 82.32 SQM

Fourth Floor : 60.48 SQM

425.04 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 367of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
51 Providing and fixing factory made uPVC white colour
sliding glazed window comprising of uPVC multi-
chambered frame with in-built roller track and sash
extruded profiles duly reinforced with 1.60 ± 0.2 mm
thick galvanized mild steel section made from roll
forming process of required length (shape & size
according to uPVC profile), appropriate dimension of
uPVC extruded glazing beads and uPVC extruded
interlocks, EPDM gasket, wool pile, zinc alloy (white
powder coated) touch locks with hook, zinc alloy body
with single nylon rollers (weight bearing capacity to be
40 kg), G.I fasteners 100 x 8 mm size for fixing frame
to finished wall and necessary stainless steel screws
etc. Profile of frame & sash shall be mitred cut and
fusion

welded at all corners, including drilling of holes for


fixing hardware's and drainage of water etc. After fixing
frame the gap between frame and adjacent finished
wall shall be filled with weather proof silicon sealent
over backer rod of required size and of approved
quality, all complete as per approved drawing &
direction of Engineer-in-Charge inclusive of cost of
Single / double glass panes of 4mm thick pin headed
glass, wire mesh and silicon sealent . Note: For uPVC
frame and sash extruded profiles minus 5%
tolerancein dimension i.e. in depth & width of profile
shall be acceptable.Variation in profile dimension in
higher side shall be accepted. But no extra payment
on this account shall be made.

a) Two track two panels sliding window made of frame 67


x 50 mm & sash 46 x 62 mm both having wall
thickness of 2.3 ± 0.2 mm and single glazing bead /
double glazing bead of appropriate dimension .

Cellar Floor : 72.36 SQM

Lower Ground Floor : 181.98 SQM

First Floor : 318.06 SQM

Second Floor : 172.80 SQM

Third Floor : 147.96 SQM

Fourth Floor : 327.78 SQM

Fifth Floor : 13.50 SQM


1234.44 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 368of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
b) Three track three panels sliding window with fly proof
SS wire mesh (Two nos. glazed & one no. wire mesh
panels) made of frame 92 x 44 mm & sash 32 x 60
mmboth having wall thickness of 1.9 ± 0.2 mm and
single glazing bead of appropriate dimension

Lower Ground Floor : 10.80 SQM

Second Floor : 167.40 SQM

Third Floor : 6.48 SQM

184.68 SQM ONE SQM #REF! #REF!

52 Providing and fixing factory made uPVC white colour


fixed glazed windows / Ventilators comprising of uPVC
multi chambered frame and mullion (where ever
required) extruded profiles duly reinforced with 1.60±
0.2 mm thick galvanized mild steel section made from
roll forming process of required length (shape & size
according to uPVC profile), uPVC extruded glazing
beads of appropriate dimension, EPDM gasket,G.I
fasteners 100 x 8 mm size for fixing frame to finished
wall, plastic packers, plastic caps and necessary
stainless steel screws etc. Profileof frame shall be
mitred cut and fusion welded at all corners, mullion (if
required) shall be also fusion welded including drilling
of holes for fixing hardware and drainage of water etc.

After fixing frame the gap between frame and adjacent


finished wall shall be filled with weather proof silicon
sealant over backer rod of required size and of
approved quality, all complete as per approved
drawing & direction of Engineer-in-Charge inclusive of
cost of Single / double glass panes and silicon sealant.
Note: For uPVC frame, sash and mullion extruded
profiles minus 5%tolerance in dimension i.e. in depth &
width of profile shall be acceptable.Variation in profile
dimension in higher side shall be accepted. But, no
extra payment on this account shall be made.

Fixed windows / Ventilators made of (small series)


frame 47 x 50mm & mullion 47 x 68 mm both having
wall thickness of 1.9 ±0.2 mm and single glazing bead
of appropriate dimension.
Cellar Floor : 34.95 SQM

Lower Ground Floor : 19.80 SQM

First Floor : 19.80 SQM

Second Floor : 22.20 SQM

Third Floor : 17.40 SQM

APMSIDC-PALASA Hospital Building - Civil Abs 369of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
Fourth Floor : 18.30 SQM

132.45 SQM ONE SQM #REF! #REF!

53 Supplying and fixing of MS doors, grill to windows / in


open court yards using MS angles, flat, square bars
including cost and conveyance of all materials, cutting,
bending, welding, all operational charges, labour
charges, overheads and contractor profit etc.,
complete for finished item of work.

Cellar Floor : 1620.00 Kgs

Lower Ground Floor : 3225.00 Kgs

First Floor : 4170.00 Kgs

Second Floor : 5565.00 Kgs

Third Floor : 2580.00 Kgs

Fourth Floor : 5340.00 Kgs

Fifth Floor : 210.00 Kgs


22710.00 Kgs ONE Kgs #REF! #REF!

54 Supply and fixing jallies ( cement concrete ) of 50mm


thick as per the design approved by the Engineer-in-
Charge including cost and conveyance of materials to
site and labour charges etc., overheads & contractors
profit complete for finished item of work.

Cellar Floor : 39.00 SQM ONE SQM #REF! #REF!

Lower Ground Floor : 78.00 SQM ONE SQM #REF! #REF!

First Floor : 78.00 SQM ONE SQM #REF! #REF!

Second Floor : 78.00 SQM ONE SQM #REF! #REF!

Third Floor : 52.00 SQM ONE SQM #REF! #REF!

Fourth Floor : 72.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 370of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
55 Providing and Fixing Structural Glazing fabricated from
Roll formed sections made of Pre-painted Steel /
Powder coated (Base steel as per IS 513 of ‘D’ quality,
galvanized as per IS 277 with Zinc of 120 Gm/sqm)
with total coated thickness of 0.72mm. The glass
holding section made of 304 grade stainless steel of
0.6mm thick as per the design requirement &
calculations as given in IS: 875. Primer coat with
epoxy primer of 5 – 7 microns thick, finish painted with
a polyester paint of 12-16 microns thick and back
coated with Alkyd backer of 5-7 microns or powder
coated with pure polyester powder up to 50-60 microns
thick. The vertical section should be of 50mm x100mm
x 0.72mm, 33mm x 58mm x 0.72mm for frame
horizontal section, stiffener section should be 48mm x
98mm x 1mm, cover profiles sections should be of
20mm x 58mm x 0.58mm, Glass holding section
should be of 37mm x 37mm & 37mm x 18mm.
Including 5mm thick Ocean Blue reflective glass.
Brackets made of CRCA powder coated/Electroplated
should be used to connect vertical to horizontal,
vertical to slab, to fix verticals at top & bottom as per
site requirement.

Gasket made of Ethyl Propylene Diamine Monomer.


Natural cure, with Good U.V. Resistance Silicon to be
used. Wall fixing of sections to concrete/masonry wall
should be with self-expanding cap & screws. The rate
is inclusive of cost and conveyance of all materials to
site, all labour charges, incidental charges, cost of all
consumables etc. and scaffolding charges, form work ,
overheads & contractors profit etc., complete for
finished item of work in all floors.

Cellar Floor : 11.00 SQM

Lower Ground Floor : 11.00 SQM

First Floor : 56.00 SQM

Second Floor : 16.00 SQM

Third Floor : 70.00 SQM

Fourth Floor : 82.00 SQM

246.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 371of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
56 Providing and Fixing Top Hung shutters in Structural
Glazing fabricated from Roll formed sections made of
Pre-painted Steel / Powder coated (Base steel as per
IS 513 of ‘D’ quality, galvanized as per IS 277 with
Zinc of 120 Gm/sqm) with total coated thickness of
0.72mm. The glass holding section made of 304
grade stainless steel of 0.6mm thick. Galvanized steel
sections are to be used as stiffeners inside the colour
coated steel/powder coated sections as per the design
requirement. Design calculations are made to suit
wind pressures as given in IS 875. Primer coat with
epoxy primer of 5-7 microns thick and back coated
with Alkyd backer of 5-7 microns or powder coated
with pure polyester powder up to 50-60 microns thick.
The outer frame should be of 20mm x 58mm x
0.6mm, Shutter section should be of 58mm x 33mm x
0.72 mm, stiffener section should be 56mm x 31mm x
1mm. EARL Bihari Hinges – 2 Nos for each shutter
and Aluminium Stays – 2 Nos. for each shutter,
Aluminium Handle – 1 no. for each shutter. The rate is
inclusive of cost and conveyance of all materials to
site, all labour charges,

incidental charges, cost of all consumables etc. and


scaffolding charges, form work, overheads &
contractor profit etc. complete for finished item of work
in all floors.
Cellar Floor : 3.00 SQM

Lower Ground Floor : 3.00 SQM

First Floor : 12.00 SQM

Second Floor : 4.00 SQM

Third Floor : 14.00 SQM

Fourth Floor : 17.00 SQM

53.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 372of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
57 Supplying and fixing of stainless steel (grade 304)
hand railing as per approved drawing with top rail of
50mm dia pipe and 2mm thick medium class and
vertical posts of 25mm dia and 1.6mm thick medium
class 1 No for each step fixed with base plate of
75mm dia using bonding agent and anchor fastner and
welding, drilling of 25mm dia holes with pneumatic
compressor for fixing railing, buffing, polishing all
members of the railing thouroughly , lacquer finishing
to present seamless finish including cost and
conveyance of all materials, electrodes, welding
charges, cost of all consumables, labour charges ,
overheads & contractors profit etc., complete for
finished item of work.

Cellar Floor : 53.00 SQM

Lower Ground Floor : 66.00 SQM

First Floor : 57.00 SQM

Second Floor : 66.00 SQM

Third Floor : 43.00 SQM

Fourth Floor : 43.00 SQM

328.00 SQM ONE SQM #REF! #REF!

58 Supplying and fixing of stainless steel (grade 304)


railing for ramp as per approved drawing with top rail
of 50mm dia pipe and 2mm thick medium class fixed in
to wall with 25mm dia pipe of 0.30m length @ 1m
centre to centre and welding, buffing, polishing all
members of the railing thouroughly , lacquer finishing
to present seamless finish including cost and
conveyance of all materials, electrodes, welding
charges, cost of all consumables, labour charges ,
overheads & contractors profit etc., complete for
finished item of work.

Cellar Floor : 117.00 RM

Lower Ground Floor : 166.00 RM

First Floor : 122.00 RM

Second Floor : 152.00 RM

Third Floor : 122.00 RM

Fourth Floor : 122.00 RM

801.00 RM ONE RM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 373of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
59 White washing two coats with white cement to ceiling
to give an even shade after thouroughly brushing the
surface to remove all dirt and remains of loose
powdered materials including cost of all materials ,
labour charges and incidental such as scaffolding , lift
charges etc., and overheads & contractors profit
complete for finished item of work in all floors.

Cellar Floor : 1837.00 SQM

Lower Ground Floor : 2781.00 SQM

First Floor : 2683.00 SQM

Second Floor : 2746.00 SQM

Third Floor : 2163.00 SQM

Fourth Floor : 459.00 SQM

Fifth Floor : 370.00 SQM


13039.00 SQM ONE SQM #REF! #REF!

60 Providing and applying Wall putty of White Cement or


Polymer or Cement based of average 1 to 2 mm
thickness over plastered surface to prepare the
surface even and smooth after thoroughly brushing the
surface to remove all dirt and remains of loose
powdered materials, applying emery paper, Sand the
surface, clean & wipe off loose dust, applying knifing
paste filler by putty knife / muslin pad, air dry for 2 - 3
hrs, sand with 180 and 320 No., emery paper for the
surface preparation including cost and conveyance of
all materials to work site and all operational, incidental,
labour charges, over heads and contractors profit etc.,
complete for finished item of work in all floors for
internal walls

Cellar Floor : 2156.00 SQM

Lower Ground Floor : 6083.00 SQM

First Floor : 6067.00 SQM

Second Floor : 5852.00 SQM

Third Floor : 7477.00 SQM

Fourth Floor : 7357.00 SQM

34992.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 374of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
61 Supply & application of one coat water based cement
primer of interior grade I and two coats of synthetic
polymer luxury plastic emulsion paint of superior grade
having VOC (Volatile Organic Compound) content less
than 50 grams/litre for internal walls including cost and
conveyance of all materials to site, incidental,
operational and all labour charges etc., and overheads
& contractors profit complete for finished item of work
in all floors.

Cellar Floor : 2156.00 SQM

Lower Ground Floor : 6083.00 SQM

First Floor : 6067.00 SQM

Second Floor : 5852.00 SQM

Third Floor : 6989.00 SQM

Fourth Floor : 4894.00 SQM

Fifth Floor : 407.00 SQM

32448.00 SQM ONE SQM #REF! #REF!

62 Supply & application of one coat water based cement


primer of exterior grade II and two coats of synthetic
polymer luxury plastic emulsion paint of superior grade
having VOC (Volatile Organic Compound) content less
than 50 grams/litre for exterior walls including cost and
conveyance of all materials to site, incidental,
operational and all labour charges etc., and overheads
& contractors profit complete for finished item of work
in all floors.

Cellar Floor : 478.00 SQM

Lower Ground Floor : 878.00 SQM

First Floor : 1081.00 SQM

Second Floor : 865.00 SQM

Third Floor : 1296.00 SQM

Fourth Floor : 1388.00 SQM

Fifth Floor : 857.00 SQM

6843.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 375of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
63 Providing and applying PMCC / Deco orient base or
Equivalent exterior Texture of average 2 to 3 mm
thickness over plastered surface to prepare the
surface even and smooth after thoroughly brushing the
surface to remove all dirt and remains of loose
powdered materials, applying emery paper, Sand the
surface, clean & wipe off loose dust, applying putty/
texture paint filler by putty knife / muslin pad, air dry for
2 - 3 hrs for the surface preparation including cost
and conveyance of all materials to work site and all
operational, incidental, labour charges, scaffolding
charges, overheads and contractors profit etc.,
complete for finished item of work in all floors for
external walls

Cellar Floor : 319.00 SQM

Lower Ground Floor : 585.00 SQM

First Floor : 721.00 SQM

Second Floor : 577.00 SQM

Third Floor : 864.00 SQM

Fourth Floor : 925.00 SQM

Fifth Floor : 568.00 SQM

4559.00 SQM ONE SQM #REF! #REF!

64 Providing and applying water proof wall putty of white


cement or polymer or cement based of average 1 to 2
mm thickness over plastered surface to prepare the
surface even and smooth after thoroughly brushing the
surface to remove all dirt and remains of loose
powdered materials, applying emery paper, Sand the
surface, clean & wipe off loose dust, applying knifing
paste filler by putty knife / muslin pad, air dry for 2 - 3
hrs, sand with 180 and 320 No., emery paper for the
surface preparation, applying one coat of cement
primer of interior grade-1 and two coats of poy-
urethane paint (MRF) of light green or light blue colour
with 1mm thickness with anti fungal and anti bacterial
chemical resistance durable and non particle shedding
including cost and conveyance of all materials to work
site and all operational, incidental, labour charges,
over heads and contractors profit etc., complete for
finished item of work in all floors for internal walls and
ceiling of Operation Theatre and labour rooms.

Third Floor : #NAME? SQM ONE SQM #REF! #NAME?

APMSIDC-PALASA Hospital Building - Civil Abs 376of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
63 Supply & applying Melamine Polish Glossy/ Matt finish
to the wood works duly cleaning the surface and
applying emery paper, sand the wood with 180 No.,
emery paper and then with 320 No., emery paper,
clean & wipe off loose dust, applying suitable knifing
paste filler / wood filler by putty knife / muslin pad, air
dry for 2 - 3 hrs, sand with 180 and 320 No., emery
paper, apply two component wood sealer, air dry for
24 hrs, sand with 320 No emery paper, applying one
coat of approved spraying thinner (for spraying)/
applying one coat of approved brushing thinner or
general purpose thinner (for brushing) and apply
(either with spray or brush) two coats of approved
brand melamine including cost & labour charges,
emery papers, cost of thinner & melamine polish, over
heads and contractors profit etc., complete for finished
item of work

Lower Ground Floor : 42.00 SQM

First Floor : 42.00 SQM

84.00 SQM ONE SQM #REF! #REF!

64 Painting two coats with synthetic enamel paint Grade-II


VOC (Volatile Organic Compound) content less than
50 grams/litre over primer coat of red oxide to new iron
work including cost and conveyance of all materials to
site, incidental, operational and all labour charges etc.,
and overheads & contractors profit complete for
finished item of work in all floors. (SS No. 1201, 1212
& 1207).

Cellar Floor : 108.00 SQM

Lower Ground Floor : 215.00 SQM

First Floor : 278.00 SQM

Second Floor : 371.00 SQM

Third Floor : 172.00 SQM

Fourth Floor : 356.00 SQM

Fifth Floor : 15.00 SQM

1515.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 377of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
65 Supplying and fixing of two shutter cupboards as per
drawing with medium teak wood frames of size 75mm
x 40mm and MDF Board Interior grade both sides
laminated 18mm thick for shutters with 18mm x 12mm
teak wood beading alround and supplying and fixing
powder coated MS fixtures 3 Nos. butt hinges of size
100mm long(for each shutter), tower bolt 2 Nos. of
100mm x 10mm, 2 Nos of handles 100mm long and
standard locking arrangements for shutters including
cost and conveyance of all materials to site, labour
charges, over heads and contractor profit etc.,
complete for finished item of work.

Cellar Floor : 18.00 SQM

Lower Ground Floor : 115.00 SQM

First Floor : 13.00 SQM

Second Floor : 53.00 SQM

Third Floor : 90.00 SQM

Fourth Floor : 58.00 SQM

347.00 SQM ONE SQM #REF! #REF!

66 Supplying and fixing Gyp board Fine line Grid false


ceiling (GS-FLC-4.6)using 12.5mm thick Gyp Board
sheet tiles of size 595mm x 595mm conforming to IS
2095 - 1992 fixing to Gyp steel precoated GI wall angle
of size 25mm x 25mm x 0.70mm thick along the
perimeter of ceiling screw fixed to brick work / partition
at 610mm center to center and suspending the frame
work using precoated GI Tee section (24mm x 38mm x
0.7mm) from soffit at 1220mm center to center fixed
with GI Soffit Cleat, rawl plugs and steel expansion
fasteners & connecting clip to the GI Tee section with
4mm dia GI rod with galvanised spring steel level clip
of PVC unversal holding clips system at 1200mm
center to center and fixing the 12.5mm Gypboard
sheet tiles of size 595mm x 595mm and finishing two
coats of drywall top coat, overheads and contractor
profit complete for finished item of work in all floors.

Third Floor : 488.00 SQM

Fourth Floor : 2463.00 SQM

2951.00 SQM ONE SQM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 378of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
67 Suplying and fabricating, erecting and fixing in position
tabular trusses of approved design with M.S tube
conforming to I.S specifications including roof frame
work consisting of rafters,ties struts and purlins
including cost of foundations bolts, cleats, bearings
plates,etc.,complete as per the sketch enclosed and
including cost of painting with enmel paint 2 coats
over a primary coat with red oxide paint including cost
and conveyance of all materials, labour charges for
fabrication and fixing, hire charges of all tools and
plants, all incidental charges, overheads and
contractor profit etc., complete for finished item of work
as directed by the Engineer-in-Charge

Fifth Floor : 1086.00 KGS ONE KGS #REF! #REF!

68 Roofing with UV resistant multi-wall polycarbonate


sheets of any colour 6mm thick fixed with Aluminium
Universal glazing set 40mm wide and as per drawing
etc., complete excluding the cost of
purlins,rafters,trusses,aluminium universal glazing set
40mm wide including cost and conveyance of all
materials, labour charges, overheads and contractors
profit etc., complete for finished item of work

Fifth Floor : 101.00 SQM ONE SQM #REF! #REF!

69 Supplying and fixing Aluminium Universal glazing set


40mm wide for jointing and fixing Polycarbonate
sheets including cost and conveyance of all materials,
labour charges, overheads and contractors profit etc.,
complete for finished item of work

Fifth Floor : 38.00 RM ONE RM #REF! #REF!

70 Providing and fixing of Expansion joint filler board for


buildings, columns, beams and slabs 25 mm thick
including cost and conveyance of all materials to site,
all incidental, operational, labour charges
etc.overheads & contractors profit complete for
finished item of work as per approved drawing for all
floors

Cellar Floor : 3.00 SQM

Lower Ground Floor : 4.00 SQM

First Floor : 4.00 SQM

Second Floor : 4.00 SQM

Third Floor : 4.00 SQM

APMSIDC-PALASA Hospital Building - Civil Abs 379of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
Fourth Floor : 4.00 SQM

23.00 SQM ONE SQM #REF! #REF!

71 Providing and fixing of 24 gauge alluminium sheet over


expansion joint groove of width 15cm fixed to walls /
columns at one edge and resting over the other block
walls/columns concealing expansion joint with slotted
holes for free edge of aluminium sheet to facilitate free
movement of aluminium sheet over the finished
surface of expansion joint and wall face using sheet
metal screws with nylon receiver complete including
cost and conveyance of all materials to site, all
incidental, operational, labour charges , overheads &
contractors profit etc., complete for finished item of
work as per approved drawing (for all floors for vertical
joints and bottom of slab)

Cellar Floor : 7.00 RM

Lower Ground Floor : 7.00 RM

First Floor : 7.00 RM

Second Floor : 7.00 RM

Third Floor : 7.00 RM

Fourth Floor : 7.00 RM

42.00 RM ONE RM #REF! #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 380of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
72 Providing specialized polysulphide sealant treatment to
the expansion joints (Size : 25mm x 12mm) duly a).
Chipping and removing of existing covering on
expansion joints b). Cleaning of the surface from dirt,
dust and other contaminations c).Application of one
coat of - High performance specially designed SBR
latex polymer based bonding agent d). Providing and
application of Acrylic Polymer modified reinstatement
concrete /mortar to the damaged edges of joint and
making the groove. e]. Providing and fixing of masking
tape on top of the joint both sides f). Providing and
fixing of Back up support material of Backer rod to
leave the depth of 12mm on the joint g). Providing and
application of one coat of polysulphide primer on inner
edges of Joint. h). Providing and application of Two
part Polysulphide sealant to a width of 25mm and
12mm depth with putty knife and neat finish i).
Removing of masking tape and providing and
application of two coats of Acrylic elastomeric
cementitious coating including cost and conveyance of
all materials, labour charges, overheads & contractors
profit etc., complete for finished item of work

Cellar Floor : 7.00 RM

Lower Ground Floor : 7.00 RM

First Floor : 7.00 RM

Second Floor : 7.00 RM

Third Floor : 7.00 RM

Fourth Floor : 7.00 RM

42.00 RM ONE RM #REF! #REF!

Sub Total ::(Civil Works) #REF!

APMSIDC-PALASA Hospital Building - Civil Abs 381of 1048


#REF!

Detailed Estimate - Cellar Floor


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
1 Earth work excavation by Machinary up
to 3.0m
Cellar Excavation 1 19.270 25.620 3.000 1481.09
Cellar Excavation 1 41.600 45.120 3.000 5630.98
Cellar Excavation 1 9.280 14.290 3.000 397.83
Lower Ground Floor Excavation 1 41.450 44.970 3.000 5592.02
13101.92
Say 13102.00

a 80% of ordinary soil 0.800 13102.0 10481.60


Say 10482.00

b 20% of ordinary rock 0.200 13102.0 2620.40


Say 2621.00

2 Earth work excavation 3.0mt to 6.0mt


Level
For Foundation
F6 2 2.650 2.650 2.000 28.09
F7 2 2.950 2.950 2.000 34.81
Cellar Excavation 1 19.270 25.620 2.600 1283.61
Cellar Excavation 1 41.600 45.120 2.600 4880.18
Cellar Excavation 1 9.290 14.290 2.600 345.16
Lower Ground Floor Foundation
F6 2 2.670 2.670 2.000 28.52
F7 2 2.970 2.970 2.000 35.28
Raft-2 1 41.450 44.970 2.600 4846.42
11482.07
Say 11483.00

a 95% of ordinary soil 0.950 11483.00 10908.85


Say 10909.00

b 5% of hard rock 0.050 11483.000 574.15


Say 575.00

3 PCC (1:4:8) for column footings


For Column Footings
F6 2 2.650 2.650 0.150 2.11
F7 2 2.950 2.950 0.150 2.61
Raft-1 1 19.320 25.670 0.150 74.39
Raft-1 1 41.650 45.120 0.150 281.89
Raft-1 1 9.290 14.290 0.150 19.91
Ded Of Duct -2 5.270 21.100 0.150 -33.36
Ded Of Duct -1 25.810 3.540 0.150 -13.71
For Lower Ground Floor
F6 2 2.650 2.650 0.150 2.11
F7 2 2.950 2.950 0.150 2.61
Raft-2 1 41.450 44.970 0.150 279.60
7 618.16
Say 619.00

APMSIDC-PALASA DET-Hospital Building 382 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
4 Earth filling with available earth
Qty as per excavation 11483.00 11483.000
Deductions
a Qty as per PCC (1:4:8) -618.164
b Qty as per footing -2795.133
c Qty as per pedestals -118.409
d Qty as per 230mm thick Retaining wall
upto GL -252.348
e Qty as per columns upto Ground level -18.643
7680.30 -3802.70
7680.30
Say 7681.00

5 Filling with Available Earth 85% 24583.991 20896.39


Say 20897.00

6 Disposal of earth
Qty as per excavation 24583.99
Ded for Filling with Available Earth -20896.39
3689.60
Say 3690.00

7 VRCC M30 grade


a) Footings
F6 2 2.500 2.500 0.375 4.69
F7 2 2.900 2.900 0.425 7.15
Lower Ground Floor
F6 2 2.500 2.500 0.375 4.69
F7 2 2.900 2.900 0.425 7.15
23.67
Say 24.00

b) RAFT
Raft-1 1 19.270 25.620 0.750 370.27
Raft-1 1 41.600 45.120 0.750 1407.74
Raft-1 1 9.280 14.290 0.750 99.46
Ded Of Duct -2 5.270 21.100 0.750 -166.80
Ded Of Duct -1 25.810 3.540 0.750 -68.53
For Lower Ground Floor
Raft-2 1 41.300 44.820 0.750 1388.30
Ded Of Duct -2 5.270 21.100 0.750 -166.80
Ded Of Duct -1 25.810 3.540 0.750 -68.53
2795.13
Say 2796.00

c) Pedestals
C1 13 1.050 1.050 0.600 8.60
C2 20 1.050 1.050 0.600 13.23
C3 12 1.050 1.050 0.600 7.94
C4 5 1.050 1.050 0.600 3.31
C5 10 1.050 1.050 0.600 6.62
C6 6 1.050 1.050 0.600 3.97
C7 4 1.050 1.050 0.600 2.65
C8 2 1.050 1.050 0.600 1.32
C9 2 1.050 1.050 0.600 1.32
C10 2 1.050 1.050 0.600 1.32
C11 7 1.050 1.050 0.600 4.63

APMSIDC-PALASA DET-Hospital Building 383 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
C12 19 1.050 1.050 0.600 12.57
C13 11 1.050 1.050 0.600 7.28
Lower Ground Floors
C4 5 1.050 1.050 0.600 3.31
C5 8 1.050 1.050 0.600 5.29
C6 6 1.050 1.050 0.600 3.97
C7 4 1.050 1.050 0.600 2.65
C8 2 1.050 1.050 0.600 1.32
C9 2 1.050 1.050 0.600 1.32
C10 2 1.050 1.050 0.600 1.32
C11 7 1.050 1.050 0.600 4.63
C12 19 1.050 1.050 0.600 12.57
C13 11 1.050 1.050 0.600 7.28
113 118.41
Say 119.00

c) Plinth Beams
Horizontal
Block-(-A)
T1-T7 1 13.810 0.300 0.400 1.66
Deduction of Columns -4 0.750 0.300 0.400 -0.36
T7-T10 2 7.700 0.300 0.600 2.77
T10-T16 2 13.810 0.300 0.400 3.31
Deduction of Columns -8 0.750 0.300 0.400 -0.72
Secondary Beam 1 6.850 0.300 0.400 0.82
Deduction of Columns -1 0.300 0.300 0.400 -0.04
Secondary Beam 1 6.820 0.300 0.400 0.82
Deduction of Columns -1 0.300 0.300 0.400 -0.04
Q1-Q5 1 9.520 0.300 0.400 1.14
Deduction of Columns -2 0.750 0.300 0.400 -0.18
Q5-Q10 1 11.250 0.300 0.600 2.03
O1-O5 4 9.520 0.300 0.600 6.85
O5-O12 4 16.290 0.300 0.400 7.82

APMSIDC-PALASA DET-Hospital Building 384 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Deduction of Columns -16 0.750 0.300 0.400 -1.44
O12-O16 4 9.520 0.300 0.600 6.85
Secondary Beam 2 4.300 0.300 0.400 1.03
G1-G16 2 35.320 0.300 0.400 8.48
Deduction of Columns -4 0.450 0.300 0.400 -0.22
Deduction of Columns -8 0.600 0.300 0.400 -0.58
E1-E3 1 4.300 0.300 0.400 0.52
Cantilever Beams 2 1.000 0.300 0.400 0.24
A6-A11 1 14.830 0.300 0.400 1.78
Deduction of Columns -4 0.600 0.300 0.400 -0.29
Ramp Block
R19-R21 5 5.100 0.230 0.300 1.76
Deduction of Columns -4 0.380 0.230 0.300 -0.10
K17-K19 4 5.860 0.230 0.300 1.62
Deduction of Columns -8 0.380 0.230 0.300 -0.21
I17-I23 1 16.820 0.230 0.300 1.16
Deduction of Columns -5 0.380 0.230 0.300 -0.13
H17-H18 2 5.080 0.230 0.300 0.70
Deduction of Columns -4 0.380 0.230 0.300 -0.10
H18-H22 1 10.360 0.230 0.400 0.95
Deduction of Columns -2 0.230 0.230 0.300 -0.03
G17-G19 2 7.480 0.230 0.300 1.03
Deduction of Columns -4 0.380 0.230 0.300 -0.10
G19-G21 4 4.800 0.230 0.350 1.55
F18-F19 2 2.180 0.230 0.300 0.30
Vertical
Block-(-A)
B1-E1 2 1.360 0.300 0.300 0.24
E1-G1 2 5.330 0.300 0.400 1.28
G1-H1 8 3.000 0.300 0.300 2.16
H1-O1 6 19.040 0.300 0.400 13.71
Deduction of Columns -24 0.600 0.230 0.400 -1.32
O1-Q1 4 3.000 0.300 0.300 1.08
Q1-T1 10 5.720 0.300 0.400 6.86
Deduction of Columns -1 0.600 0.300 0.400 -0.07
Secondary Beam 1 1.400 0.300 0.300 0.13
Secondary Beam 1 4.330 0.300 0.300 0.39
B5-G5 6 8.940 0.300 0.600 9.66
Deduction of Columns -10 0.750 0.300 0.600 -1.35
Deduction of Columns -2 0.600 0.300 0.600 -0.22
A6-B6 4 4.580 0.300 0.400 2.20
Ramp Block
D17-G17 2 5.860 0.230 0.400 1.08
G17-H17 4 3.000 0.230 0.300 0.83
H17-J17 2 5.750 0.230 0.400 1.06
J17-K17 2 2.560 0.230 0.300 0.35
D18-I18 2 12.920 0.230 0.300 1.78
Deduction of Columns -8 0.750 0.230 0.300 -0.41
I18-K18 2 6.050 0.230 0.400 1.11
C19-G19 2 8.640 0.230 0.300 1.19
Deduction of Columns -8 0.750 0.230 0.300 -0.41
G19-I19 2 5.860 0.230 0.400 1.08
I19-J19 3 2.890 0.230 0.300 0.60
J19-L19 3 4.930 0.230 0.400 1.36
L19-N19 3 3.490 0.230 0.350 0.84
N19-P19 3 3.850 0.230 0.350 0.93
P19-R19 2 2.760 0.230 0.300 0.38

APMSIDC-PALASA DET-Hospital Building 385 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
For Lower Ground Floor
Horizontal
Block-(-B)
T24-T30 1 13.810 0.300 0.400 1.66
Deduction of Columns -4 0.750 0.300 0.400 -0.36
T30-T33 2 7.700 0.300 0.600 2.77
T33-T39 2 13.810 0.300 0.400 3.31
Deduction of Columns -8 0.750 0.300 0.400 -0.72
Secondary Beam 2 9.520 0.300 0.400 2.28
Deduction of Columns -4 0.230 0.300 0.400 -0.11
Q24-Q28 2 9.520 0.300 0.400 2.28
Deduction of Columns -4 0.750 0.300 0.400 -0.36
Q28-Q30 1 2.800 0.300 0.400 0.34
Q30-Q35 1 11.250 0.300 0.600 2.03
O24-O28 4 9.520 0.300 0.600 6.85
O28-O35 4 16.290 0.300 0.400 7.82
Deduction of Columns -16 0.750 0.300 0.400 -1.44
O35-O39 4 9.520 0.300 0.600 6.85
G24-G39 2 35.320 0.300 0.400 8.48
Deduction of Columns -4 0.450 0.300 0.400 -0.22
Deduction of Columns -8 0.600 0.300 0.400 -0.58
Cantilever Beams 2 1.000 0.300 0.400 0.24
A29-A34 1 14.830 0.300 0.400 1.78
Deduction of Columns -4 0.600 0.300 0.400 -0.29
E39-E38 1 4.300 0.300 0.400 0.52
Vertical
Block-(-B)
B39-E39 2 1.360 0.300 0.300 0.24
E39-G39 2 5.330 0.300 0.400 1.28
G39-H39 8 3.000 0.300 0.300 2.16
H39-O39 6 19.040 0.300 0.400 13.71
Deduction of Columns -24 0.600 0.230 0.400 -1.32
O39-Q39 4 3.000 0.300 0.300 1.08
Q39-T39 10 5.720 0.300 0.400 6.86
Deduction of Columns -1 0.600 0.300 0.400 -0.07
Secondary Beam 1 1.400 0.300 0.300 0.13
Secondary Beam 1 4.330 0.300 0.300 0.39
B35-G35 6 8.940 0.300 0.600 9.66
Deduction of Columns -10 0.750 0.300 0.600 -1.35
Deduction of Columns -2 0.600 0.300 0.600 -0.22
A34-B34 4 4.580 0.300 0.400 2.20
175.05
Say 176.00

APMSIDC-PALASA DET-Hospital Building 386 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
d) 230Thk Retaining Wall
Upto Cellar Floor Lvl 1 255.155 4.300 1097.17
1097.17
Say 1098.00

8 VRCC
i Columns Upto GL
C1/RAFT-1 13 0.380 0.600 0.500 1.48
C2/RAFT-1 20 0.380 0.600 0.500 2.28
C3/RAFT-1 12 0.380 0.600 0.500 1.37
C4/RAFT-1 5 0.450 0.750 0.500 0.84
C5/RAFT-1 10 0.460 0.600 0.500 1.38
C6/RAFT-1 6 0.460 0.600 0.500 0.83
C7/RAFT-1 4 0.460 0.600 0.500 0.55
C8/F6 2 0.600 0.600 0.825 0.59
C9/F7 2 0.600 0.600 0.875 0.63
C10/RAFT-1 2 0.600 0.600 0.500 0.36
C11/RAFT-1 7 0.600 0.750 0.500 1.58
C12/RAFT-1 19 0.600 0.750 0.500 4.28
C13/RAFT-1 11 0.600 0.750 0.500 2.48
113 18.64
Say 19.00

iii
Columns Raft Top to Roof slab bottom
C1 13 0.380 0.600 3.475 10.30
C2 20 0.380 0.600 3.475 15.85
C3 12 0.380 0.600 3.475 9.51
C4 5 0.450 0.750 3.475 5.86
C5 10 0.460 0.600 3.475 9.59
C6 6 0.460 0.600 3.475 5.75
C7 4 0.460 0.600 3.475 3.84
C8 2 0.600 0.600 3.475 2.50
C9 2 0.600 0.600 3.475 2.50
C10 2 0.600 0.600 3.475 2.50
C11 7 0.600 0.750 3.475 10.95
C12 19 0.600 0.750 3.475 29.71
C13 11 0.600 0.750 3.475 17.20
113 126.06
Say 127.00
Total Qty of Columns
i Upto G.L 18.64
ii Above plinth 126.06
144.71
Say 145.00

9 Roof Beams
Horizontal
Block-(-A)
T1-T4 1 7.120 0.300 0.300 0.64
Deduction of Columns -2 0.750 0.300 0.300 -0.14
T4-T5 1 2.400 0.380 0.275 0.25
T5-T7 1 2.800 0.300 0.300 0.25
T7-T10 2 7.700 0.230 0.450 1.59
T10-T16 2 13.810 0.300 0.300 2.49
Deduction of Columns -8 0.750 0.300 0.300 -0.54
Secondary Beam 2 9.520 0.300 0.300 1.71

APMSIDC-PALASA DET-Hospital Building 387 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Deduction of Columns -2 0.230 0.300 0.300 -0.04

APMSIDC-PALASA DET-Hospital Building 388 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Q1-Q2 1 3.310 0.300 0.300 0.30
Q2-Q4 1 2.310 0.380 0.300 0.26
Q4-Q5 1 2.400 0.380 0.275 0.25
Q5-Q10 1 11.250 0.230 0.450 1.16
Q10-Q12 1 2.800 0.300 0.300 0.25
Q12-Q13 1 2.400 0.380 0.275 0.25
Q13-Q16 1 7.120 0.300 0.300 0.64
O1-O5 4 9.520 0.450 0.575 9.85
O5-O12 4 16.290 0.300 0.275 5.38
Deduction of Columns -16 0.750 0.300 0.275 -0.99
O12-O16 4 9.520 0.450 0.575 9.85
G1-G16 2 35.320 0.300 0.300 6.36
Deduction of Columns -4 0.450 0.300 0.300 -0.16
Deduction of Columns -8 0.600 0.300 0.300 -0.43
E1-E3 1 4.300 0.300 0.400 0.52
Cantilever Beams 2 1.000 0.300 0.300 0.18
Ramp Block
R19-R21 5 5.100 0.230 0.355 2.08
Deduction of Columns -4 0.380 0.230 0.355 -0.12
K17-K19 4 5.860 0.230 0.275 1.48
Deduction of Columns -8 0.380 0.230 0.275 -0.19
I17-I23 1 16.820 0.230 0.275 1.06
Deduction of Columns -5 0.380 0.230 0.275 -0.12
H17-H18 2 5.080 0.230 0.300 0.70
Deduction of Columns -4 0.380 0.230 0.300 -0.10
H18-H22 1 10.360 0.230 0.450 1.07
Deduction of Columns -2 0.230 0.230 0.450 -0.05
G17-G19 2 7.480 0.230 0.300 1.03
Deduction of Columns -4 0.380 0.230 0.300 -0.10
G19-G21 3 4.800 0.230 0.380 1.26
F18-F19 2 2.180 0.230 0.300 0.30
Vertical
Block-(-A)
B1-E1 2 1.360 0.300 0.300 0.24
E1-G1 2 5.330 0.300 0.450 1.44
G1-H1 8 3.000 0.300 0.300 2.16
H1-O1 8 19.040 0.300 0.425 19.42
Deduction of Columns -32 0.600 0.300 0.425 -2.45
O1-Q1 2 3.000 0.230 0.300 0.41
O2-Q2 4 3.000 0.300 0.300 1.08
Q1-T1 6 5.720 0.230 0.450 3.55
Q5-T5 4 5.720 0.230 0.475 2.50
Deduction of Columns -1 0.600 0.230 0.475 -0.07
Secondary Beam 1 1.400 0.300 0.325 0.14
Secondary Beam 1 4.330 0.300 0.325 0.42
B5-G5 6 8.940 0.380 0.475 9.68
Deduction of Columns -10 0.750 0.380 0.475 -1.35
Deduction of Columns -2 0.600 0.380 0.475 -0.22
Ramp Block
D17-G17 2 5.860 0.230 0.450 1.21
G17-H17 4 3.000 0.230 0.300 0.83
H17-J17 2 5.750 0.230 0.450 1.19
J17-K17 2 2.560 0.230 0.300 0.35
D18-I18 2 12.920 0.230 0.300 1.78
Deduction of Columns -8 0.750 0.230 0.300 -0.41
I18-K18 2 6.050 0.230 0.380 1.06
C19-G19 2 8.640 0.230 0.300 1.19

APMSIDC-PALASA DET-Hospital Building 389 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Deduction of Columns -8 0.750 0.230 0.300 -0.41

APMSIDC-PALASA DET-Hospital Building 390 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
G19-I19 2 5.860 0.230 0.450 1.21
I19-J19 3 2.890 0.230 0.275 0.55
J19-L19 3 4.930 0.230 0.425 1.45
L19-N19 3 3.490 0.230 0.355 0.85
N19-P19 3 3.850 0.230 0.355 0.94
P19-R19 2 2.760 0.230 0.275 0.35
97.30
Say 98.00

10 Roof slab
i) Roof Slab 125mm thick
Ramp Block 1 432.775 432.78
Ded Of Staircase -1 5.100 5.700 -29.07
Ded Of Lift -2 2.400 3.000 -14.40
Deduction of Ramp -1 5.100 21.000 -107.10
282.21
Say 283.00

ii) Roof Slab 150mm thick


Block-(-A) 1 1458.644 1458.64
Ded Of Staircase -1 5.300 4.430 -23.48
Ded Of Staircase -1 4.300 5.300 -22.79
Deduction of 175mm Thick Slab -650.48
761.89
Say 762.00

iii) Roof Slab 175mm thick


H1-H4 x H1-O1 2 7.350 19.040 279.89
H5-H12 x H5-O5 1 16.290 19.040 310.16
B8-B9 x B8-G8 1 6.760 8.940 60.43
650.48
Say 651.00
v) Waist slab (175mm thick)
Staircase (Flight -1& Flight-2) 2 3.600 2.000 14.40
Mid landing 1 2.000 4.430 8.86
Staircase (Flight -1& Flight-2) 2 3.600 2.000 14.40
Mid landing 1 2.000 4.300 8.60
Staircase (Flight -1& Flight-2) 2 3.600 2.400 17.28
Mid landing 1 5.100 2.400 12.24
Ramp 2 18.000 2.460 88.56
Mid landing 1 5.100 3.000 15.30
179.64
Say 180.00

11 Lintels
D2 1 1.960 0.225 0.175 0.08
D3 2 1.660 0.225 0.175 0.13
D5 11 1.360 0.225 0.175 0.59
D6 22 1.260 0.225 0.175 1.09
ALD1 2 2.460 0.225 0.175 0.19
FD1 3 2.460 0.225 0.175 0.29
FD2 2 1.960 0.225 0.175 0.15
W1 11 2.260 0.225 0.175 0.98
W2 12 1.960 0.225 0.175 0.93
W3 2 1.660 0.225 0.175 0.13
V1 12 2.260 0.225 0.175 1.07
V2 17 1.960 0.225 0.175 1.31

APMSIDC-PALASA DET-Hospital Building 391 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
V5 38 1.060 0.225 0.175 1.59
JW 12 2.260 0.225 0.175 1.07
Lift 2 1.460 0.225 0.175 0.11
135 9.71
Say 10.00

12 Sunshades
W1 11 2.100 23.10
W2 12 1.800 21.60
W3 2 1.500 3.00
JW 12 2.100 25.20
V1 12 2.100 25.20
V2 17 1.800 30.60
V5 38 0.900 34.20
162.90
Say 163.00

a Platforms
G toilets Wash Basins Platform 1 2.940 0.600 1.76
Store 1 2.895 0.600 1.74
Cold Store 1 2.895 0.600 1.74
L toilets Wash Basins Platform 1 2.940 0.600 1.76
Laboratory 1 2.500 0.600 1.50
8.50
Say 9.00

b Lofts
Store 1 2.895 0.600 1.74
Cold Store 1 2.895 0.600 1.74
Laboratory 1 3.000 0.600 1.80
House Keeping 1 6.230 0.600 3.74
9.01
Say 10.00

Total Platforms & Lofts 19.00


Say 19.00

c Racks and shelves 25mm


Store 1 2.000 0.450 0.90
Cold Store 1 2.500 0.450 1.13
Laboratory 1 2.000 0.450 0.90
2.93
Say 3.00
d sill slabs
W1 11 2.100 0.230 0.050 0.27
W2 12 1.800 0.230 0.050 0.25
W3 2 1.500 0.230 0.050 0.03
0.55
Say 1.00

13 230 mm thick brick masonary


Horizontal
Block-(-A)
Service Corridor 1 7.120 0.230 3.150 5.16
Deduction of columns -2 0.750 0.230 3.150 -1.09
Corridor 1 2.400 0.230 3.150 1.74
Store 1 2.800 0.230 3.150 2.03

APMSIDC-PALASA DET-Hospital Building 392 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Staircase 1 7.700 0.230 3.150 5.58
Cold Store To Service Corridor 1 13.060 0.230 3.150 9.46
Deduction of columns -3 0.750 0.230 3.150 -1.63
WC To PHC 2 6.060 0.230 3.150 8.78
WC 2 6.360 0.230 3.150 9.22
Deduction of columns -2 0.750 0.230 3.150 -1.09
Electrical Room 1 4.970 0.230 3.000 3.43

APMSIDC-PALASA DET-Hospital Building 393 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Staircase 1 5.300 0.230 3.000 3.66
Cold Store 1 2.800 0.230 3.150 2.03
Ramp Wall 1 5.160 0.230 3.600 4.27
Staircase 2 4.300 0.230 3.150 6.23
Drivers Rest To Parking 1 35.320 0.230 3.150 25.59
Deduction of columns -6 0.600 0.230 3.150 -2.61
Ramp Block
Ramp Wall 1 5.100 0.230 3.175 3.72
Attendents Waiting Room 2 5.860 0.230 3.175 8.56
Deduction of columns -4 0.380 0.230 3.175 -1.11
Laboratory 2 5.860 0.230 3.175 8.56
Deduction of columns -4 0.380 0.230 3.175 -1.11
Corridor 1 5.940 0.230 3.175 4.34
Security 1 2.700 0.230 3.175 1.97
Corridor To Staircase Entrance 1 8.490 0.230 3.175 6.20
Deduction of columns -2 0.380 0.230 3.175 -0.55
Staircase 1 4.800 0.230 3.175 3.51
Staircase Entrance To Admin 1 5.860 0.230 3.175 4.28
Deduction of columns -1 0.380 0.230 3.175 -0.28
Lift 2 2.400 0.230 3.175 3.51
House Keeping To Lift 2 5.330 0.230 3.175 7.78
Deduction of columns -2 0.380 0.230 3.175 -0.55
Staircase 1 4.800 0.230 3.175 3.51
Vertical
Block-(-A)
Drivers Rest 1 1.360 0.230 3.150 0.99
Drivers Rest 1 1.360 0.230 3.150 0.99
Staircase 1 5.330 0.230 3.150 3.86
Staircase 1 5.330 0.230 3.150 3.86
Lobby 1 1.900 0.230 3.150 1.38
Lobby 1 1.900 0.230 3.150 1.38
Parking 1 19.530 0.230 3.150 14.15
Deduction of columns -3 0.750 0.230 3.150 -1.63
Parking 1 3.000 0.230 3.150 2.17
Toilets 2 5.720 0.230 3.150 8.29
PHC 2 1.500 0.230 3.150 2.17
Toilets 2 3.115 0.230 3.150 4.51
Electrical Room To Store 2 6.620 0.230 3.150 9.59
Deduction of columns -4 0.600 0.230 3.150 -1.74
Water 2 1.750 0.230 3.600 2.90
Parking 1 7.440 0.230 3.150 5.39
Corridor 1 3.000 0.230 3.150 2.17
Parking 1 12.690 0.230 3.150 9.19
Deduction of columns -3 0.600 0.230 3.150 -1.30
Parking 1 4.350 0.230 3.150 3.15
Deduction of columns -1 0.600 0.230 3.150 -0.43
Ramp Wall 1 16.200 0.230 3.600 13.41
Ramp Block
House Keeping 2 5.860 0.230 3.150 8.49
Lab To Attendents 2 9.510 0.230 3.150 13.78
Deduction of columns -2 0.600 0.230 3.150 -0.87
House Keeping 2 6.460 0.230 3.175 9.43
Lab 2 2.260 0.230 3.175 3.30
Staircase 2 8.640 0.230 3.175 12.62
Deduction of columns -8 0.600 0.230 3.175 -3.51
Ramp Walls 3 2.890 0.230 3.175 6.33
Ramp Walls 2 4.930 0.230 3.175 7.20

APMSIDC-PALASA DET-Hospital Building 394 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Ramp Middle Wall 1 4.930 0.230 3.175 3.60

APMSIDC-PALASA DET-Hospital Building 395 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Ramp Walls 2 8.530 0.230 3.175 12.46
Deduction of columns -4 0.600 0.230 3.175 -1.75
Ramp Walls 1 8.530 0.230 3.175 6.23
Deduction of columns -2 0.600 0.230 3.175 -0.88
Ramp Walls 2 2.630 0.230 3.175 3.84
Deduction
D2 -1 1.500 0.230 2.600 -0.90
D3 -2 1.200 0.230 2.600 -1.44
D5 -11 0.900 0.230 2.100 -4.78
W1 -11 1.800 0.230 1.800 -8.20
W2 -12 1.500 0.230 1.800 -7.45
W3 -2 1.200 0.230 1.800 -0.99
FD1 -2 2.000 0.230 2.100 -1.93
FD2 -2 1.500 0.230 2.100 -1.45
V1 -12 1.800 0.230 0.500 -2.48
V2 -17 1.500 0.230 0.500 -2.93
V5 -38 0.600 0.230 0.500 -2.62
JW -12 1.800 0.230 1.800 -8.94
Lift -2 1.000 0.230 2.100 -0.97
Lintels Deduction
D2 -1 1.960 0.230 0.175 -0.08
D3 -2 1.660 0.230 0.175 -0.13
D5 -11 1.360 0.230 0.175 -0.60
W1 -11 2.260 0.230 0.175 -1.00
W2 -12 1.960 0.230 0.175 -0.95
W3 -2 1.660 0.230 0.175 -0.13
FD1 -2 2.460 0.230 0.175 -0.20
FD2 -2 1.960 0.230 0.175 -0.16
V1 -12 2.260 0.230 0.175 -1.09
V2 -17 1.960 0.230 0.175 -1.34
V5 -38 1.060 0.230 0.175 -1.62
JW -12 2.260 0.230 0.175 -1.09
Lift -2 1.460 0.230 0.175 -0.12
244.21
Say 245.00
14 100 mm thick brick masonry walls
Horizontals
Block-(-A)
WC 2 2.630 3.450 18.15
PHC 1 3.280 3.450 11.32
Staff Toilet 1 1.200 3.450 4.14
Electrical Room 1 4.070 3.450 14.04
Corridor 2 2.400 3.450 16.56
PHC To WC 1 3.830 3.450 13.21
WC 1 3.940 3.450 13.59
Ramp Block
Attendents Attached Toilets 6 1.315 3.450 27.22
House Keeping Attached Toilets 2 1.915 3.450 13.21
Verticals
Block-(-A)
WC 12 1.500 3.450 62.10
Service Corridor 2 1.200 3.450 8.28
Staff Toilet 1 1.800 3.450 6.21
Store 1 3.045 3.450 10.51
Electrical Room 1 2.780 3.450 9.59
Cold Store 1 5.720 3.000 17.16
Ramp Block

APMSIDC-PALASA DET-Hospital Building 396 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Attendents Attached Toilets 2 6.045 3.450 41.71
House Keeping Attached Toilets 2 1.200 3.450 8.28

APMSIDC-PALASA DET-Hospital Building 397 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Deduction
D6 -22 0.800 2.100 -36.96
ALD1 -2 2.000 2.600 -10.40
FD1 -1 2.000 2.100 -4.20
Lintels Deduction
D6 -22 1.260 0.175 -4.85
ALD1 -2 2.460 0.175 -0.86
FD1 -1 2.460 0.175 -0.43
237.58
Say 238.00
15 PCC for Steps
Staircase 0.5 24 2.000 0.300 0.150 1.08
Staircase 0.5 24 2.000 0.300 0.150 1.08
Staircase 0.5 24 2.400 0.300 0.150 1.30
3.46
Say 4.00

16 PCC (1:3:6) for Bedblocks


under lintels
D2 2 1 0.300 0.225 0.150 0.02
D3 2 2 0.300 0.225 0.150 0.04
D5 2 11 0.300 0.225 0.150 0.22
D6 2 22 0.300 0.100 0.150 0.20
ALD1 2 2 0.300 0.100 0.150 0.02
FD1 2 2 0.300 0.225 0.150 0.04
FD1 2 1 0.300 0.100 0.150 0.01
FD2 2 2 0.300 0.225 0.150 0.04
W1 2 11 0.300 0.225 0.150 0.22
W2 2 12 0.300 0.225 0.150 0.24
W3 2 2 0.300 0.225 0.150 0.04
V1 2 12 0.300 0.225 0.150 0.24
V2 2 17 0.300 0.225 0.150 0.34
V5 2 38 0.300 0.225 0.150 0.77
Lift 2 2 0.300 0.225 0.150 0.04
Hold fasts
D2 6 1 0.230 0.225 0.150 0.05
D3 6 2 0.230 0.225 0.150 0.09
D5 6 11 0.230 0.225 0.150 0.51
D6 6 22 0.230 0.100 0.150 0.46
ALD1 6 2 0.230 0.100 0.150 0.04
FD1 6 2 0.230 0.225 0.150 0.09
FD1 6 1 0.230 0.100 0.150 0.02
FD2 6 2 0.230 0.225 0.150 0.09
W1 4 11 0.230 0.225 0.150 0.34
W2 4 12 0.230 0.225 0.150 0.37
W3 4 2 0.230 0.225 0.150 0.06
V1 2 12 0.230 0.225 0.150 0.19
V2 2 17 0.230 0.225 0.150 0.26
V5 2 38 0.230 0.225 0.150 0.59
Lift 6 2 0.230 0.225 0.150 0.09
5.76
Say 5.80

17 TMT STEEL
Columns Footings 23.67 90.000 Kgs/Cum 2130.48
Raft 2796.00 80.000 Kgs/Cum 223680.00
Pedestals 118.41 100.000 Kgs/Cum 11840.85

APMSIDC-PALASA DET-Hospital Building 398 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Plinth beams 176.00 150.000 Kgs/Cum 26400.00
230mm thick Retaining wall 1097.17 22.000 Kgs/Sqm 24137.66
Columns upto 3.60 mts levael 145.00 200.000 Kgs/Cum 29000.00
Roof beams 98.00 200.000 Kgs/Cum 19600.00
125mm thick Roof slab 283.0 10.000 Kgs/Sqm 2830.00
150mm thick Roof slab 762.00 12.000 Kgs/Sqm 9144.00
175mm thick Roof slab 651.00 14.000 Kgs/Sqm 9114.00
175mm thick waist slab 180.00 14.000 Kgs/Sqm 2520.00
Lintels 10 80.000 Kgs/Cum 800.00
361196.99
Say 360.72

18 Mild Steel
Sunshades 162.90 4.000 Kgs/RM 651.60
Lofts & Platforms 19 4.000 Kgs/Sqm 76.00
Shelves 3.00 4.000 Kgs/Sqm 12.00
RBM 238.0 0.500 Kgs/Sqm 119.00
858.60
Say 0.86

19 External plastering
All round the Building Block-(-A) 1 155.450 3.600 559.62
All round the Building Ramp Block 1 106.113 3.600 382.01
Deductions
W1 -11 1.800 1.800 -35.64
W2 -12 1.500 1.800 -32.40
W3 -2 1.200 1.800 -4.32
JW -12 1.800 1.800 -38.88
V1 -12 1.800 0.500 -10.80
V2 -17 1.500 0.500 -12.75
V5 -38 0.600 0.500 -11.40
795.44
Say 796.00

20 Ceiling plastering
Qty Same as Ceramic tile flooring 78.00
Qty Same as Vitrified flooring 369.00
Qty Same as Chequered flooring 102.00
Qty Same as Granite flooring 143.29
Qty Same as VDF flooring 1144.00
1836.29
Say 1837.00

21 Internal plastering 12 mm thick


Electrical Room 1 14.220 3.450 49.06
Store 1 11.360 3.450 39.19
Lobby 1 2.630 3.450 9.07
Lobby 2 19.230 3.450 132.69
Service Corridor 2 14.520 3.450 100.19
Cold Store 1 20.220 3.450 69.76
Drivers Rest 1 13.400 3.450 46.23
Corridor 1 52.560 3.450 181.33
Laboratory & Security 2 12.000 3.450 82.80
Attendents Waiting 2 20.720 3.450 142.97
House Keeping & Admin 2 18.920 3.450 130.55
Infront Lift 2 10.800 3.450 74.52
Ramp 1 52.200 3.450 180.09

APMSIDC-PALASA DET-Hospital Building 399 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Toilets Entrance 2 12.110 3.450 83.56
Toilets Lobby 1 3.530 3.450 12.18
Toilets Corridor 1 5.260 3.450 18.15
Toilets Corridor 1 7.660 3.450 26.43
WC 10 5.400 3.450 186.30

APMSIDC-PALASA DET-Hospital Building 400 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
PHC Toilet 2 7.000 3.450 48.30
Staff Toilet 1 6.000 3.450 20.70
Laboratory & Security Toilet 2 5.400 3.450 37.26
Attendents Waiting Toilet 4 5.400 3.450 74.52
Attendents Waiting Toilet Lobby 2 2.400 3.450 16.56
House Keeping & Admin Toilet 2 6.000 3.450 41.40
Staircase 1 24.260 3.450 83.70
Staircase 1 24.100 3.450 83.15
Staircase 1 26.560 3.450 91.63
Parking 1 138.120 3.450 476.51
Entrance Corridor 1 21.080 3.450 72.73
Water Dumb 1 5.400 3.450 18.63
Duct 1 3.000 3.450 10.35
Deductions
D2 -1 1.500 2.600 -3.90
D3 -2 1.200 2.600 -6.24
D5 -11 0.900 2.100 -20.79
D6 -22 0.800 2.100 -36.96
ALD1 -2 2.000 2.600 -10.40
FD1 -3 2.000 2.100 -12.60
FD2 -2 1.500 2.100 -6.30
W1 -11 1.800 1.800 -35.64
W2 -12 1.500 1.800 -32.40
W3 -2 1.200 1.800 -4.32
V1 -2 1.800 0.500 -1.80
V2 -17 1.500 0.500 -12.75
V5 -38 0.600 0.500 -11.40
JW -12 1.800 1.800 -38.88
Ded for Dadooing with ceramic tiles for
Toilets -232.80
Ded for Dadooing in corridor -5.84
Cladding with Granite Slab -11.52
2155.96
Say 2156.00
a 12 mm thick internal plastering
60% of above quantity 1293.57
Say 1294.00
b 20 mm thick Internal plastering
40% of above quantity 862.38
Say 862.00
22 Flooring
a) Ceramic Tile Flooring
Toilets Entrance 2 2.940 3.115 18.32
Toilets Lobby 1 1.200 4.730 5.68
Toilets Corridor 1 2.630 1.500 3.95
Toilets Corridor 1 3.830 1.500 5.75
WC 10 1.200 1.500 18.00
PHC Toilet 2 2.000 1.500 6.00
Staff Toilet 1 1.200 1.800 2.16
Laboratory & Security Toilet 2 1.200 1.500 3.60
Attendents Waiting Toilet 4 1.200 1.500 7.20
Attendents Waiting Toilet Lobby 2 1.200 1.200 2.88
House Keeping & Admin Toilet 2 1.200 1.800 4.32
77.84
Say 78.00

APMSIDC-PALASA DET-Hospital Building 401 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
b) Vitrified Tile Flooring
Electrical Room 1 3.995 3.115 12.44
Store 1 2.635 3.045 8.02
Lobby 1 1.130 1.315 1.49
Lobby 2 2.400 3.345 16.06
Lobby 2 3.340 2.930 19.57
Service Corridor 2 6.060 1.200 14.54
Ded Of Ducts -6 0.750 0.600 -2.70
Cold Store 1 3.950 6.160 24.33
Drivers Rest 1 4.300 2.400 10.32
Corridor 1 20.050 3.000 60.15
Infront Ramp 1 10.360 3.230 33.46
Laboratory & Security 2 3.000 3.000 18.00
Attendents Waiting 2 4.315 6.045 52.17
House Keeping & Admin 2 3.000 4.915 29.49
Lobby 2 1.085 1.315 2.85
Infront Lift 2 2.400 3.000 14.40
Under Ramp 1 21.000 2.550 53.55
368.15
Say 369.00

d) Granite Slabs
Infront Staircase-1 1 2.400 6.280 15.07
Staircase Midlanding 1 2.000 4.430 8.86
Under Staircase 1 5.300 4.430 23.48
Infront Staircase-2 1 4.300 2.450 10.54
Staircase Midlanding 1 2.000 4.300 8.60
Under Staircase 1 4.300 5.300 22.79
Infront Staircase-3 1 5.100 2.480 12.65
Staircase Midlanding 1 5.100 2.400 12.24
Under Staircase 1 5.100 5.700 29.07
143.29
Say 144.00

e) Chequered tiles
Ramp 2 2.400 18.000 86.40
Ramp Mid Landing 1 5.100 3.000 15.30
101.70
Say 102.00

e) Intenrlocking Tiles
Entrance Ramp 1 5.000 15.965 79.83
79.83
Say 80.00

f) VDF Flooring
Parking 1 35.320 33.740 1191.70
Ded Of Toilet -1 4.530 10.610 -48.06
1143.63
Say 1144.00

23 Skirting
a) Skirting with Vitrified Tiles
Electrical Room 1 11.105 11.11
Store 1 8.315 8.32
Lobby 1 3.575 3.58
Lobby 2 8.145 16.29

APMSIDC-PALASA DET-Hospital Building 402 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Lobby 2 9.610 19.22
Service Corridor 2 13.320 26.64
Cold Store 1 14.060 14.06
Drivers Rest 1 11.000 11.00
Corridor 1 43.100 43.10
Infront Ramp 1 23.950 23.95
Laboratory & Security 2 9.000 18.00
Attendents Waiting 2 14.675 29.35
House Keeping & Admin 2 10.915 21.83
Lobby 2 3.485 6.97
Infront Lift 2 7.800 15.60
Under Ramp 1 44.550 44.55
313.56
Say 314.00

c) Skirting with Granite


Infront Staircase-1 1 17.360 17.36
Staircase Midlanding 1 8.430 8.43
Under Staircase 1 15.030 15.03
Infront Staircase-2 1 13.500 13.50
Staircase Midlanding 1 8.300 8.30
Under Staircase 1 14.900 14.90
Infront Staircase-3 1 15.160 15.16
Staircase Midlanding 1 9.900 9.90
Under Staircase 1 16.500 16.50
119.08
Say 120.00

24 Dadooing with Ceramic Tiles


Toilets Entrance 2 12.110 1.500 36.33
Toilets Lobby 2 4.430 1.500 13.29
Toilets Corridor 1 5.260 1.500 7.89
Toilets Corridor 1 7.660 1.500 11.49
WC 10 5.400 1.500 81.00
PHC Toilet 2 7.000 1.500 21.00
Staff Toilet 1 6.000 1.500 9.00
Laboratory & Security Toilet 2 5.400 1.500 16.20
Attendents Waiting Toilet 4 5.400 1.500 32.40
Attendents Waiting Toilet Lobby 2 4.800 1.500 14.40
House Keeping & Admin Toilet 2 6.000 1.500 18.00
Deductions
D5 -4 0.900 1.500 -5.40
D6 -19 0.800 1.500 -22.80
232.80
Say 233.00

25 Dadooing in corridor
3.0 m wide corridor 1 9.690 1.500 14.54
Deductions
D5 -2 0.900 1.500 -2.70
FD1 -2 2.000 1.500 -6.00
5.84
Say 6.00

25 Polished Granite slab


i Treads

APMSIDC-PALASA DET-Hospital Building 403 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Staircase-1&2 2 22 2.000 0.300 26.40
Staircase-3 1 22 2.400 0.300 15.84
42.24
Say 43.00

ii Risers
Staircase-1&2 2 24 2.000 0.150 14.40
Staircase-3 1 24 2.400 0.150 8.64
23.04
Say 24.00
26 High polished granite platforms
Qty same as Platforms 9.00
9.00
Say 9.00

27 High polished granite for sill slabs


W1 11 2.100 0.225 5.20
W2 12 1.800 0.225 4.86
W3 2 1.500 0.225 0.68
10.73
Say 11.00
28 Cladding With Granite Slabs
Block-A
Lifts 2 2.400 3.450 16.56
Deductions
Lift opening -2 1.200 2.100 -5.04
11.52
Say 12.00

29 Whiting for ceiling


Same as ceiling plastering 1837.00
1837.00
Say 1837.00

30 Wall putty
Same as internal plastering 2156.00
2156.00
Say 2156.00

31 Plastic Emulsion Paint for interior


faces of walls
Same as internal plastering 2156.00
2156.00
Say 2156.00

32
Emulsion paint for external plastering
Same as of external plastering @ 60% 477.60
477.60
Say 478.00

33
Emulsion paint for external plastering
Same as of external plastering @ 40% 318.40
318.40
Say 319.00

APMSIDC-PALASA DET-Hospital Building 404 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
34 Doors
Wooden Doors
D2 (1.5X 2.60) 1 1.500 2.600 3.90
Say 3.90

D3 (1.2 X 2.60) 2 1.200 2.600 6.24


Say 6.24

D5 (0.9 x 2.10) 12 0.900 2.100 22.68


Say 22.68

APMSIDC-PALASA DET-Hospital Building 405 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
D6 (0.8 X 2.10) - Frame 22 5.000 110.00
Say 110.00

D6 (0.8 X 2.10) 22 0.800 2.100 36.96


Say 36.96

35 Doors
ALD Doors
ALD1 (2.0X 2.60) 5 2.000 2.600 26.00
Say 26.00

36 Windows
W1 11 1.800 1.800 35.64
W2 12 1.500 1.800 32.40
W3 2 1.200 1.800 4.32
Total Quantity 72.36

37 MS Grill for Windows @ 15 Kg/Sqm


W1 11 1.800 1.800 35.64
W2 12 1.500 1.800 32.40
W3 2 1.200 1.800 4.32
Ventilators
V1 12 1.800 0.500 10.80
V2 17 1.500 0.500 12.75
V5 38 0.600 0.500 11.40
107.31
Say 108.00
1620.00
38 RCC Jally Windows
JW 12 1.800 1.800 38.88
38.88
Say 39.00

39 Painting to iron Work


Quantity Same as MS Grill 107.31
107.31
Say 108.00

40 Ventilators
V1 12 1.800 0.500 10.80
V2 17 1.500 0.500 12.75
V5 38 0.600 0.500 11.40
34.95
41 Structural Glazing
staire case at Ramp 2 1.800 3.000 10.80
10.80
Say 11.00
42 Structural Glazing with top hung
shutters
20% of above quantity 2.16
2.16
Say 3.00

43 Railing
All round the staircase 1 7.350 0.900 6.62

APMSIDC-PALASA DET-Hospital Building 406 OF1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
All round the staircase 1 7.350 0.900 6.62
All round the staircase 1 7.350 0.900 6.62
All round the ramp 1 36.000 0.900 32.40
52.25
Say 53.00
44 Grip bar
Staircase 1 15.030 15.03
Staircase 1 14.900 14.90
Staircase 1 16.500 16.50
Ramp 1 47.100 47.10
PHC Toilet 2 6.000 12.00
Entrance Ramp 1 10.600 10.60
116.13
Say 117.00

45 Cupboards
Store 1 2.000 2.100 4.20
Cold Store 2 2.000 2.100 8.40
House Keeping 1 2.500 2.100 5.25
17.85
Say 18.00

46 Mastic pad
Roof beams
Horizontal 1 3.460 0.450 1.56
PB 1 3.460 0.300 1.04
2.60
Say 3.00

47 Expansion joint treatment


Roof beams
Horizontal 1 3.460 3.46
PB 1 3.460 3.46
6.92
Say 7.00

48 Aluminium sheet
Roof beams
Horizontal 1 3.460 3.46
PB 1 3.460 3.46
6.92
Say 7.00

APMSIDC-PALASA DET-Hospital Building 407 OF1048


#REF!

ed Estimate - Cellar Floor


QUANTITY

Cum

Cum

Cum

Cum

Cum

Cum

Cum

APMSIDC-PALASA DET-Hospital Building 408 OF1048


QUANTITY

Cum

Cum

Cum
Cum
Cum
Cum

Cum

Cum

APMSIDC-PALASA DET-Hospital Building 409 OF1048


QUANTITY

Cum

APMSIDC-PALASA DET-Hospital Building 410 OF1048


QUANTITY

APMSIDC-PALASA DET-Hospital Building 411 OF1048


QUANTITY

Cum

APMSIDC-PALASA DET-Hospital Building 412 OF1048


QUANTITY

Sqm

Cum

Cum

Cum

APMSIDC-PALASA DET-Hospital Building 413 OF1048


QUANTITY

APMSIDC-PALASA DET-Hospital Building 414 OF1048


QUANTITY

APMSIDC-PALASA DET-Hospital Building 415 OF1048


QUANTITY

APMSIDC-PALASA DET-Hospital Building 416 OF1048


QUANTITY

Cum

Sqm

Sqm

Sqm

Sqm

APMSIDC-PALASA DET-Hospital Building 417 OF1048


QUANTITY

Cum

RM

Sqm

Sqm

Sqm

Sqm

cum

APMSIDC-PALASA DET-Hospital Building 418 OF1048


QUANTITY

APMSIDC-PALASA DET-Hospital Building 419 OF1048


QUANTITY

APMSIDC-PALASA DET-Hospital Building 420 OF1048


QUANTITY

APMSIDC-PALASA DET-Hospital Building 421 OF1048


QUANTITY

Cum

APMSIDC-PALASA DET-Hospital Building 422 OF1048


QUANTITY

APMSIDC-PALASA DET-Hospital Building 423 OF1048


QUANTITY

sqm

cum

Cum

APMSIDC-PALASA DET-Hospital Building 424 OF1048


QUANTITY

MT

MT

Sqm

Sqm

APMSIDC-PALASA DET-Hospital Building 425 OF1048


QUANTITY

APMSIDC-PALASA DET-Hospital Building 426 OF1048


QUANTITY

Sqm

Sqm

Sqm

Sqm

APMSIDC-PALASA DET-Hospital Building 427 OF1048


QUANTITY

Sqm

Sqm

Sqm

Sqm

Sqm

APMSIDC-PALASA DET-Hospital Building 428 OF1048


QUANTITY

Rmt

Rmt

Sqm

Sqm

APMSIDC-PALASA DET-Hospital Building 429 OF1048


QUANTITY

Sqm

Sqm

Sqm

Sqm

Sqm

Sqm

Sqm

Sqm

Sqm

Sqm

APMSIDC-PALASA DET-Hospital Building 430 OF1048


QUANTITY

Sqm

Sqm

Sqm

APMSIDC-PALASA DET-Hospital Building 431 OF1048


QUANTITY

RM

Sqm

Sqm

Sqm

Sqm
Kgs

Sqm

Sqm
Sqm

Sqm

Sqm

Sqm

APMSIDC-PALASA DET-Hospital Building 432 OF1048


QUANTITY

Sqm

Rmt

Sqm

Sqm

Rmt

Rmt

APMSIDC-PALASA DET-Hospital Building 433 OF1048


#REF!

Detailed Estimate - Lower Ground Floor


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
1 Antitermite treatment
Qty same as 125mm thick Slab 1 282.205 282.21
Qty same as 150mm thick Slab 1 1785.326 1785.33
Qty same as 175mm thick Slab 1 943.510 943.51

Qty same as 175mm thick Waist Slab 1 225.900 225.90


3236.94
Say 3237.00 Sqm

2 Tie Beam
Add extra Quantity for level difference 1 290.000 0.300 0.400 34.80
Say 35.00 Cum

3 230Thk Retaining Wall


Upto Lower Ground Floor Lvl 1 255.155 4.300 1097.17
1097.17
Say 1098.00 Sqm

4 VRCC
i Columns Upto GL
C4/RAFT-1 5 0.450 0.750 0.500 0.84
C5/RAFT-1 8 0.460 0.600 0.500 1.10
C6/RAFT-1 6 0.460 0.600 0.500 0.83
C7/RAFT-1 4 0.460 0.600 0.500 0.55
C8/F6 2 0.600 0.600 0.825 0.59
C9/F7 2 0.600 0.600 0.875 0.63
C10/RAFT-1 2 0.600 0.600 0.500 0.36
C11/RAFT-1 7 0.600 0.750 0.500 1.58
C12/RAFT-1 19 0.600 0.750 0.500 4.28
C13/RAFT-1 11 0.600 0.750 0.500 2.48

Add extra Quantity for level difference 33 0.450 0.750 2.000 22.28
99 35.51
Say 36.00 Cum

ii Columns Cellar Roof Top to Lower


Ground Roof slab bottom
Block-A & Ramp Block
C1 13 0.380 0.600 3.475 10.30
C2 20 0.380 0.600 3.475 15.85
C3 12 0.380 0.600 3.475 9.51
C4 5 0.450 0.750 3.475 5.86
C5 10 0.460 0.600 3.475 9.59
C6 6 0.460 0.600 3.475 5.75
C7 4 0.460 0.600 3.475 3.84
C8 2 0.600 0.600 3.475 2.50
C9 2 0.600 0.600 3.475 2.50
C10 2 0.600 0.600 3.475 2.50
C11 7 0.600 0.750 3.475 10.95
C12 19 0.600 0.750 3.475 29.71
C13 11 0.600 0.750 3.475 17.20

APMSIDC-PALASA DET-Lower Ground Floor 434 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Columns P.B Top to Roof slab
bottom
Block-(-B)
C4 5 0.450 0.750 3.475 5.86
C5 8 0.460 0.600 3.475 7.67
C6 6 0.460 0.600 3.475 5.75
C7 4 0.460 0.600 3.475 3.84
C8 2 0.600 0.600 3.475 2.50
C9 2 0.600 0.600 3.475 2.50
C10 2 0.600 0.600 3.475 2.50
C11 7 0.600 0.750 3.475 10.95
C12 19 0.600 0.750 3.475 29.71
C13 11 0.600 0.750 3.475 17.20
179 214.56
Say 215.00 Cum
Total Qty of Columns
i Upto G.L 35.51
iii Above plinth 214.56
250.07
Say 251.00 Cum

5 Roof Beams
Horizontal
Block-A
T1-T4 1 7.120 0.300 0.300 0.64
Deduction of Columns -2 0.750 0.300 0.300 -0.14
T4-T5 1 2.400 0.380 0.275 0.25
T5-T7 1 2.800 0.300 0.300 0.25
T7-T10 2 7.700 0.230 0.450 1.59
T10-T16 2 13.810 0.300 0.300 2.49
Deduction of Columns -8 0.750 0.300 0.300 -0.54
Secondary Beam 2 9.520 0.300 0.300 1.71
Deduction of Columns -2 0.230 0.300 0.300 -0.04
Q1-Q2 1 3.310 0.300 0.300 0.30
Q2-Q4 1 2.310 0.380 0.300 0.26
Q4-Q5 1 2.400 0.380 0.275 0.25
Q5-Q10 1 11.250 0.230 0.450 1.16
Q10-Q12 1 2.800 0.300 0.300 0.25
Q12-Q13 1 2.400 0.380 0.275 0.25
Q13-Q16 1 7.120 0.300 0.300 0.64
O1-O5 4 9.520 0.450 0.575 9.85
O5-O12 2 16.290 0.300 0.275 2.69
Deduction of Columns -8 0.750 0.300 0.275 -0.50
M5-M8 4 4.170 0.300 0.275 1.38
O12-O16 4 9.520 0.450 0.575 9.85
G1-G16 2 35.320 0.300 0.300 6.36
Deduction of Columns -4 0.450 0.300 0.300 -0.16
Deduction of Columns -8 0.600 0.300 0.300 -0.43
E1-E3 1 4.300 0.300 0.400 0.52
Cantilever Beams 2 1.000 0.300 0.300 0.18
Ramp Block
R19-R21 5 5.100 0.230 0.355 2.08
Deduction of Columns -4 0.380 0.230 0.355 -0.12
K17-K19 4 5.860 0.230 0.275 1.48
Deduction of Columns -8 0.380 0.230 0.275 -0.19
I17-I23 1 16.820 0.230 0.275 1.06

APMSIDC-PALASA DET-Lower Ground Floor 435 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Deduction of Columns -5 0.380 0.230 0.275 -0.12
H17-H18 2 5.080 0.230 0.300 0.70
Deduction of Columns -4 0.380 0.230 0.300 -0.10
H18-H22 1 10.360 0.230 0.450 1.07
Deduction of Columns -2 0.230 0.230 0.450 -0.05
G17-G19 2 7.480 0.230 0.300 1.03
Deduction of Columns -4 0.380 0.230 0.300 -0.10
G19-G21 3 4.800 0.230 0.380 1.26
F18-F19 2 2.180 0.230 0.300 0.30
Block-(-B)
T39-T33 3 13.060 0.300 0.300 3.53
Deduction of Columns -9 0.750 0.300 0.300 -0.61
T33-T30 2 7.700 0.230 0.450 1.59
Secondary Beam 2 9.520 0.300 0.300 1.71
Deduction of Columns -2 0.230 0.300 0.300 -0.04
Q1-Q38 1 3.310 0.300 0.300 0.30
Q38-Q36 1 2.310 0.380 0.300 0.26
Q36-Q35 1 2.400 0.380 0.275 0.25
Q35-Q30 1 11.250 0.230 0.450 1.16
O39-O35 4 9.520 0.450 0.575 9.85
O35-O28 4 16.290 0.300 0.275 5.38
Deduction of Columns -16 0.750 0.300 0.275 -0.99
O28-O24 4 9.520 0.450 0.575 9.85
G39-G24 2 35.320 0.300 0.300 6.36
Deduction of Columns -4 0.450 0.300 0.300 -0.16
Deduction of Columns -8 0.600 0.300 0.300 -0.43
E39-E38 1 4.300 0.300 0.400 0.52
Cantilever Beams 2 1.000 0.300 0.300 0.18
Vertical
Block-A
B1-E1 2 1.360 0.300 0.300 0.24
E1-G1 2 5.330 0.300 0.450 1.44
G1-H1 8 3.000 0.300 0.300 2.16
H1-O1 6 19.040 0.300 0.425 14.57
Deduction of Columns -24 0.600 0.300 0.425 -1.84
O1-Q1 2 3.000 0.230 0.300 0.41
O2-Q2 4 3.000 0.300 0.300 1.08
Q1-T1 6 5.720 0.230 0.450 3.55
Q5-T5 4 5.720 0.230 0.475 2.50
Deduction of Columns -1 0.600 0.230 0.475 -0.07
Secondary Beam 1 1.400 0.300 0.325 0.14
Secondary Beam 1 4.330 0.300 0.325 0.42
B5-G5 4 8.940 0.380 0.475 6.45
Deduction of Columns -8 0.750 0.380 0.475 -1.08
Ramp Block
D17-G17 2 5.860 0.230 0.450 1.21
G17-H17 4 3.000 0.230 0.300 0.83
H17-J17 2 5.750 0.230 0.450 1.19
J17-K17 2 2.560 0.230 0.300 0.35
D18-I18 2 12.920 0.230 0.300 1.78
Deduction of Columns -8 0.750 0.230 0.300 -0.41
I18-K18 2 6.050 0.230 0.380 1.06
C19-G19 2 8.640 0.230 0.300 1.19
Deduction of Columns -8 0.750 0.230 0.300 -0.41
G19-I19 2 5.860 0.230 0.450 1.21
I19-J19 3 2.890 0.230 0.275 0.55

APMSIDC-PALASA DET-Lower Ground Floor 436 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
J19-L19 3 4.930 0.230 0.425 1.45
L19-N19 3 3.490 0.230 0.355 0.85
N19-P19 3 3.850 0.230 0.355 0.94
P19-R19 2 2.760 0.230 0.275 0.35
Block-B
B39-E39 2 1.360 0.300 0.300 0.24
E39-G39 2 5.330 0.300 0.450 1.44
G39-H39 8 3.000 0.300 0.300 2.16
H39-O39 6 19.040 0.300 0.425 14.57
Deduction of Columns -24 0.600 0.300 0.425 -1.84
O39-Q39 6 3.000 0.230 0.300 1.24
Q39-T39 6 5.720 0.230 0.450 3.55
Q35-T35 4 5.720 0.230 0.475 2.50
Deduction of Columns -1 0.600 0.230 0.475 -0.07
Secondary Beam 1 1.400 0.300 0.325 0.14
Secondary Beam 1 4.330 0.300 0.325 0.42
B35-G35 6 8.940 0.380 0.475 9.68
Deduction of Columns -10 0.750 0.380 0.475 -1.35
Deduction of Columns -2 0.600 0.380 0.475 -0.22
160.69
Say 161.00 Cum

6 Roof slab
i) Roof Slab 125mm thick
Ramp Block 1 432.775 432.78
Ded Of Staircase -1 5.100 5.700 -29.07
Ded Of Lift -2 2.400 3.000 -14.40
Deduction of Ramp -1 5.100 21.000 -107.10
282.21
Say 283.00 Sqm

ii) Roof Slab 150mm thick


Block-(A) 1 40.600 35.780 1452.67
Ded Of Staircase -1 5.300 4.430 -23.48
Ded Of Staircase -1 4.300 5.300 -22.79
Ded Of Duct -1 6.000 18.575 -111.45
Block-(-B) 1 40.600 35.780 1452.67
Ded Of Staircase -1 5.300 4.430 -23.48
Ded Of Staircase -1 4.300 5.300 -22.79
Ded Of Duct -1 6.000 18.575 -111.45
Portico Slab 1 14.250 9.750 138.94
Deduction of 175mm Thick Slab -943.51
1785.33
Say 1786.00 Sqm

iii) Roof Slab 175mm thick


H1-H5 x H1-O1 2 2 9.980 19.040 760.08
H31-H32 x H31-O31 1 1 6.460 19.040 123.00
B31-B32 x B31-G31 1 1 6.760 8.940 60.43
943.51
Say 944.00 Sqm
v) Waist slab (175mm thick)
Staircase (Flight -1& Flight-2) 2 2 3.600 2.000 28.80
Mid landing 2 1 2.000 4.430 17.72
Staircase (Flight -1& Flight-2) 2 2 3.600 2.000 28.80
Mid landing 2 1 2.000 4.300 17.20

APMSIDC-PALASA DET-Lower Ground Floor 437 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Staircase (Flight -1& Flight-2) 1 2 3.600 2.400 17.28
Mid landing 1 1 5.100 2.400 12.24
Ramp 1 2 18.000 2.460 88.56
Mid landing 1 1 5.100 3.000 15.30
225.90
Say 226.00 Sqm

7 Lintels
MD1 1 3.460 0.225 0.175 0.14
D2 19 1.960 0.225 0.175 1.47
D3 9 1.660 0.225 0.175 0.59
D5 28 1.360 0.225 0.175 1.50
D6 43 1.260 0.225 0.175 2.13
ALD1 5 2.460 0.225 0.175 0.48
FD1 8 2.460 0.225 0.175 0.77
FD2 2 1.960 0.225 0.175 0.15
W1 43 2.260 0.225 0.175 3.83
W2 23 1.960 0.225 0.175 1.78
W3 2 1.660 0.225 0.175 0.13
V1 16 2.260 0.225 0.175 1.42
V2 22 1.960 0.225 0.175 1.70
V5 68 1.060 0.225 0.175 2.84
JW 23 2.260 0.225 0.175 2.05
Lift 2 1.460 0.225 0.175 0.11
21.09
Say 22.00 Cum

8 Sunshades
W1 43 2.100 90.30
W2 23 1.800 41.40
W2 2 1.800 3.60
JW 23 2.100 48.30
V1 16 2.100 33.60
V2 22 1.800 39.60
V5 68 0.900 61.20
318.00
Say 318.00 RM
a Platforms
Block-A
G toilets Wash Basins Platform 1 2.940 0.600 1.76
Store 1 3.045 0.600 1.83
Store 1 4.800 0.600 2.88
Clean Linen 1 4.800 0.600 2.88
Pharmacy 1 5.965 0.600 3.58
Police Out Post 1 2.515 0.600 1.51
Rec 1 5.780 0.600 3.47
Rec 1 3.780 0.600 2.27
Nurse Station 1 3.000 0.600 1.80
Console 1 3.385 0.600 2.03
Block-(-B)
G toilets Wash Basins Platform 2 1.620 0.600 1.94
Store 1 3.045 0.600 1.83
Issueing 1 4.800 0.600 2.88
Bio Chemistry Lab 1 22.855 0.600 13.71
Pathology Lab 1 23.620 0.600 14.17
Micro Biology Lab 1 21.455 0.600 12.87

APMSIDC-PALASA DET-Lower Ground Floor 438 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
71.42
Say 72.00 Sqm

b Lofts
Block-A
Store 1 3.045 0.600 1.83
Store 1 4.800 0.600 2.88
Clean Linen 1 4.800 0.600 2.88
Nurse Station 1 3.000 0.600 1.80
Console 1 3.385 0.600 2.03
Ramp Block
Laboratory 1 3.000 0.600 1.80
House Keeping 1 6.230 0.600 3.74
Block-(-B)
Store 2 3.000 0.600 3.60
Chemical Store 1 6.160 0.600 3.70
Drug Store 1 7.000 0.600 4.20
Medico Legal Store 1 7.000 0.600 4.20
Medical Store 1 4.800 0.600 2.88
Surgical Store 1 4.800 0.600 2.88
Celan Store 1 4.800 0.600 2.88
Office 1 4.800 0.600 2.88
Tailoring 1 4.800 0.600 2.88
47.05
Say 48.00 Sqm

Total Platforms & Lofts 120.00


Say 120.00 Sqm

c Racks and shelves 25mm


Block-(A)
Store 1 2.000 0.450 0.90
Console 1 2.500 0.450 1.13
Clean Linen Store 1 2.500 0.450 1.13
Store 1 2.500 0.450 1.13
Nurse Station 1 2.500 0.450 1.13
Pharmacy 2 2.000 0.450 1.80
Rec 1 2.500 0.450 1.13
Store 1 2.500 0.450 1.13
Rec 1 2.500 0.450 1.13
Ramp Block
Laboratory 1 2.000 0.450 0.90
Block-(-B)
Store 2 2.000 0.450 1.80
Chemical Store 1 2.000 0.450 0.90
Medico Legal Store 1 2.500 0.450 1.13
Drug Pharmacy 4 3.000 0.450 5.40
Surgical Store 4 3.000 0.450 5.40
Medical Store 4 3.000 0.450 5.40
Office 1 2.000 0.450 0.90
Tailoring 2 2.000 0.450 1.80
Bio Chemistry Lab 2 2.000 0.450 1.80
Pathology Lab 2 2.000 0.450 1.80
Micro Biology Lab 2 2.000 0.450 1.80
39.60
Say 40.00 Sqm

APMSIDC-PALASA DET-Lower Ground Floor 439 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
d sill slabs
W1 43 2.100 0.230 0.050 1.04
W2 23 1.800 0.230 0.050 0.48
W3 2 1.500 0.230 0.050 0.03
1.55
Say 2.00 cum

9 230 mm thick brick masonary


Horizontal
Block-(A)
Service Corridor to Store 1 13.810 0.230 3.150 10.01
Deduction of columns -4 0.750 0.230 3.150 -2.17
Staircase 1 7.700 0.230 3.000 5.31
Ultra Sound To Service Corridor 1 13.810 0.230 3.150 10.01
Deduction of columns -4 0.750 0.230 3.150 -2.17
WC To PHC 2 9.520 0.230 3.150 13.79
Electrical Room 1 5.720 0.230 3.000 3.95
Staircase 1 5.300 0.230 3.000 3.66
Ultra Sound 1 2.800 0.230 3.150 2.03
Console 1 7.110 0.230 3.450 5.64
Examination 8 7.110 0.230 2.850 37.28
Clean Linen 4 3.650 0.230 3.150 10.58
Rest Room 1 4.300 0.230 3.150 3.12
Rest Room To Rec 1 35.320 0.230 3.150 25.59
Deduction of columns -6 0.600 0.230 3.150 -2.61
Entrance Portico Steps 5 5.320 0.300 0.150 1.20
Ramp Block
Ramp Wall 1 5.100 0.230 3.095 3.63
Attendents Waiting Room 2 5.860 0.230 3.175 8.56
Deduction of columns -4 0.380 0.230 3.175 -1.11
Laboratory 2 5.860 0.230 3.175 8.56
Deduction of columns -4 0.380 0.230 3.175 -1.11
Corridor 1 5.940 0.230 3.025 4.13
Security 1 2.700 0.230 3.175 1.97
Corridor To Staircase Entrance 1 8.490 0.230 3.175 6.20
Deduction of columns -2 0.380 0.230 3.175 -0.55
Staircase 2 4.800 0.230 3.095 6.83
Staircase Entrance To Admin 1 5.860 0.230 3.175 18.61
Deduction of columns -1 0.380 0.230 3.175 -0.28
Lift 2 2.400 0.230 3.175 15.24
House Keeping To Lift 2 5.330 0.230 3.175 33.85
Deduction of columns -2 0.380 0.230 3.175 -0.55
Block-(-B)
Service Corridor to Store 1 13.810 0.230 1.950 6.19
Deduction of columns -4 0.750 0.230 1.950 -1.35
Staircase 1 7.700 0.230 1.800 3.19
Chemical Store To Service Corridor 1 13.810 0.230 1.950 6.19
Deduction of columns -4 0.750 0.230 1.950 -1.35
L ToileT To G Toilet 1 8.050 0.230 3.150 5.83
Calendering Machine 1 7.110 0.230 3.150 5.15
Electrical Room 1 2.820 0.230 3.150 2.04
Staircase 1 5.300 0.230 3.000 3.66
Water To Chemical Store 1 4.980 0.230 3.150 3.61
Calendering Machine 1 7.110 0.230 3.150 5.15
Deduction of columns -2 0.750 0.230 3.150 -1.09
Connecting Corridor 2 2.500 0.230 3.150 3.62

APMSIDC-PALASA DET-Lower Ground Floor 440 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Pthology Lab 1 12.090 0.230 3.150 8.76
Store 1 4.300 0.230 3.150 3.12
Wah Area To Store 1 35.320 0.230 1.950 15.84
Deduction of columns -6 0.600 0.230 1.950 -1.61
Vertical
Block-(A)
Toilet 2 1.360 0.230 3.150 1.97
Staircase 2 5.330 0.230 3.000 7.36
Lobby 1 1.900 0.230 3.150 1.38
Ward To Examination 1 19.040 0.230 3.000 13.14
Deduction of columns -4 0.600 0.230 3.000 -1.66
AHU Room 2 3.000 0.230 3.150 4.35
Toilets & Console 2 5.720 0.230 3.000 7.89
Toilets 1 4.510 0.230 3.000 3.11
Toilets 1 3.230 0.230 3.000 2.23
Electrical Room To Store 2 6.620 0.230 3.000 9.14
Deduction of columns -4 0.600 0.230 3.000 -1.66
Water 2 1.750 0.230 3.450 2.78
Ultra Sound 1 5.420 0.230 3.000 3.74
Administrator To Clean Linen 2 19.035 0.230 3.000 26.27
Deduction of columns -3 0.450 0.230 3.000 -0.93
Deduction of columns -5 0.600 0.230 3.000 -2.07
L Topilet To CT Scan 1 22.930 0.230 3.425 18.06
Rec To PHC Toilet 1 7.440 0.230 3.000 5.13
L Toilet To Console 1 28.660 0.230 3.000 19.78
Deduction of columns -4 0.600 0.230 3.000 -1.66
Deduction of columns -2 0.450 0.230 3.000 -0.62
Ramp Block
House Keeping 2 5.860 0.230 3.025 8.15
Lab To Attendents 2 9.510 0.230 3.025 13.23
Deduction of columns -2 0.600 0.230 3.025 -0.83
House Keeping 2 6.460 0.230 3.175 9.43
Lab 2 2.260 0.230 3.175 3.30
Staircase 2 8.640 0.230 3.175 12.62
Deduction of columns -8 0.600 0.230 3.175 -3.51
Ramp Walls 3 2.890 0.230 3.175 6.33
Ramp Walls 3 4.930 0.230 3.025 10.29
Ramp Walls 3 8.530 0.230 3.095 18.22
Deduction of columns -6 0.600 0.230 3.095 -2.56
Ramp Walls 2 2.630 0.230 3.175 3.84
Block-(-B)
Toilet 1 1.360 0.230 1.950 0.61
Toilet 1 1.360 0.230 3.150 0.99
Staircase 1 5.330 0.230 1.800 2.21
Staircase 1 5.330 0.230 3.000 3.68
Lobby 1 1.900 0.230 1.950 0.85
Lobby 1 1.900 0.230 3.150 1.38
Recieving To Calendering Machine 1 28.660 0.230 1.800 11.87
Deduction of columns -4 0.600 0.230 1.800 -0.99
Deduction of columns -2 0.450 0.230 1.800 -0.37
Calendering Machine 1 4.740 0.230 3.000 3.27
Pathology Lab 2 8.825 0.230 3.000 12.18
Deduction of columns -2 0.600 0.230 3.000 -0.83
Waiting To Tailoring 2 19.035 0.230 3.000 26.27
Deduction of columns -4 0.450 0.230 3.000 -1.24
Deduction of columns -4 0.600 0.230 3.000 -1.66

APMSIDC-PALASA DET-Lower Ground Floor 441 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Corridor To Chemical Store 1 9.620 0.230 3.000 6.64
Deduction of columns -2 0.600 0.230 3.000 -0.83
Water 2 1.750 0.230 3.450 2.78
Electrical Room To Store 1 6.620 0.230 3.000 4.57
Deduction of columns -2 0.600 0.230 3.000 -0.83
Toilets 1 4.660 0.230 3.450 3.70
Toilets 1 3.120 0.230 3.450 2.48
Bio Chemistry Lab 1 7.440 0.230 1.800 3.08
Corridor 1 3.000 0.230 3.150 2.17
Medico Legal To Drug Store 1 22.035 0.230 1.800 9.12
Deduction of columns -4 0.600 0.230 1.800 -0.99
Toilets 1 5.720 0.230 1.800 2.37
Deduction
MD1 -1 3.000 0.230 2.600 -1.79
D2 -8 1.500 0.230 2.600 -7.18
D3 -6 1.200 0.230 2.600 -4.31
D5 -14 0.900 0.230 2.100 -6.09
D6 -2 0.800 0.230 2.100 -0.77
W1 -43 1.800 0.230 1.800 -32.04
W2 -23 1.500 0.230 1.800 -14.28
W3 -2 1.200 0.230 1.800 -0.99
V1 -16 1.800 0.230 0.500 -3.31
V2 -22 1.500 0.230 0.500 -3.80
V5 -68 0.600 0.230 0.500 -4.69
JW -23 1.800 0.230 1.800 -17.14
Lift -2 1.000 0.230 2.100 -0.97
Lintels Deduction
MD1 -1 3.460 0.230 0.175 -0.14
D2 -8 1.960 0.230 0.175 -0.63
D3 -6 1.660 0.230 0.175 -0.40
D5 -14 1.360 0.230 0.175 -0.77
D6 -2 1.260 0.230 0.175 -0.10
W1 -43 2.260 0.230 0.175 -3.91
W2 -23 1.960 0.230 0.175 -1.81
W3 -2 1.660 0.230 0.175 -0.13
V1 -16 2.260 0.230 0.175 -1.46
V2 -22 1.960 0.230 0.175 -1.74
V5 -68 1.060 0.230 0.175 -2.90
JW -23 2.260 0.230 0.175 -2.09
Lift -2 1.460 0.230 0.175 -0.12
471.27
Say 472.00 Cum
10 100 mm thick brick masonry walls
Horizontals
Block-(A)
WC 4 1.200 3.450 16.56
G Toilet 1 2.630 3.450 9.07
G Toilet 1 3.990 3.450 13.77
Staff Toilet 1 1.200 3.450 4.14
Electrical Room 1 4.070 3.450 14.04
Ultra Sound Attached Toilet 1 1.315 3.450 4.54
ECG 1 3.385 3.450 11.68
AHU To Corridor 1 9.510 3.150 29.96
Staircase 1 2.400 3.000 7.20
Duct Walls 2 6.000 1.000 12.00
Clean Linen Store (Typ) 8 4.800 3.150 120.96

APMSIDC-PALASA DET-Lower Ground Floor 442 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Attached Toil 2 1.200 3.450 8.28
Electrical Room 1 4.070 3.450 14.04
Wards Attached Toilets 3 1.500 3.450 15.53
G Toilet 1 2.630 3.450 9.07
L Toilet 1 3.830 3.150 12.06
Pharmacy 1 4.770 3.150 15.03
PHC Toilet 1 2.100 3.450 7.25
Rec 1 4.680 3.450 16.15
Ward Partition 1 4.480 1.500 6.72
Ward Partition 1 2.250 1.500 3.38
Ward Partition 1 4.620 1.500 6.93
Ramp Block
Attendents Attached Toilets 6 1.315 3.450 27.22
House Keeping Attached Toilets 2 1.915 3.450 13.21
Block-(-B)
L Toilet 2 1.200 3.450 8.28
G Toilet 1 2.630 3.450 9.07
L Toilet To G Toilet 1 8.280 3.450 28.57
PHC Toilet 1 2.545 3.450 8.78
Electrical Room 1 4.070 3.450 14.04
Drug Pharmacy To Corridor 1 9.515 3.150 29.97
Ded Of Columns -2 0.750 3.150 -4.73
Corridor To Surgical Store 2 7.545 3.150 47.53
Ded Of Columns -4 0.750 3.150 -9.45
Surgical Store 1 4.800 3.450 16.56
Corridor 1 2.400 3.450 8.28
MRD 2 7.000 3.450 48.30
Duct Walls 2 6.000 1.000 12.00
Tailoring 1 3.645 3.150 11.48
Office 1 4.800 3.150 15.12
Celan Store 2 4.165 3.150 26.24
Segregation 2 7.000 3.000 42.00
Medico Legal Store To Corridor 1 9.515 3.000 28.55
Medical Store 1 3.645 3.150 11.48
Waiting 1 3.645 3.150 11.48
Corridor To Receiving 1 9.515 3.000 28.55
Bio Chemistry Lab To Microbiology
Lab 1 31.020 3.150 97.71
Ded Of Columns -2 0.450 3.150 -2.84
Ded Of Columns -4 0.600 3.150 -7.56
Verticals
Block-(A)
Rest Room 1 2.400 3.450 8.28
Staircase Lobby 1 3.000 3.450 10.35
Ward Attached Toilet 1 3.950 3.450 13.63
Ward 1 2.140 3.425 7.33
L Toilet 2 3.230 3.450 22.29
G Toilet 2 1.500 3.450 10.35
Staff Toilet 1 1.580 3.450 5.45
Store 1 3.045 3.450 10.51
Electrical Room 1 2.780 3.450 9.59
Admin To Clean Linen 1 19.040 3.000 57.12
Ded Of Columns -4 0.600 3.000 -7.20
Nurse Station 1 3.000 3.450 10.35
Admin Attached Toilet 1 1.610 3.450 5.55
Store To Rec 1 5.750 3.000 17.25

APMSIDC-PALASA DET-Lower Ground Floor 443 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Reporting To X ray 1 5.720 3.000 17.16
Service Corridor 1 1.200 3.450 4.14
Console 1 4.070 3.450 14.04
L Toilet 2 2.940 3.450 20.29
WC 4 1.500 3.450 20.70
Ramp Block
Attendents Attached Toilets 2 6.045 3.475 42.01
House Keeping Attached Toilets 2 1.200 3.475 8.34
Block-(-B)
Store 1 2.400 3.450 8.28
Service Corridor 1 1.200 3.450 4.14
Segregation To Washig 1 18.730 3.425 64.15
Issuing To Tailoring 1 15.730 3.000 47.19
Ded Of Columns -3 0.600 3.000 -5.40
Chemical Store 1 5.720 3.000 17.16
Medical Store To Surgical Store 1 19.040 3.000 57.12
Ded Of Columns -4 0.600 3.000 -7.20
Medico Legal Store To Drug Store 1 21.920 3.425 75.08
PHC Toilet 1 1.650 3.450 5.69
Electrical Room 1 2.780 3.450 9.59
Store 1 3.045 3.450 10.51
WC 3 1.500 3.450 15.53
WC 1 3.115 3.450 10.75
Deduction
D2 -11 1.500 2.600 -42.90
D3 -3 1.200 2.600 -9.36
D5 -14 0.900 2.100 -26.46
D6 -41 0.800 2.100 -68.88
ALD1 -5 2.000 2.600 -26.00
FD1 -8 2.000 2.100 -33.60
FD2 -2 1.500 2.100 -6.30
Lintels Deduction
D2 -11 1.960 0.175 -3.77
D3 -3 1.660 0.175 -0.87
D5 -14 1.360 0.175 -3.33
D6 -41 1.260 0.175 -9.04
ALD1 -5 2.460 0.175 -2.15
FD1 -8 2.460 0.175 -3.44
FD2 -2 1.960 0.175 -0.69
1261.50
Say 1262.00 sqm

11 PCC for Steps


Staircase 0.5 44 2.000 0.300 0.150 1.98
Staircase 0.5 44 2.000 0.300 0.150 1.98
Staircase 0.5 22 2.400 0.300 0.150 1.19
Entrance Portico Steps 0.5 5 5.320 0.300 0.150 0.60
5.75
Say 6.00 cum

12 PCC (1:3:6) for Bedblocks


under lintels
MD1 2 1 0.300 0.230 0.150 0.02
D2 2 8 0.300 0.230 0.150 0.17
D3 2 6 0.300 0.230 0.150 0.12
D5 2 14 0.300 0.230 0.150 0.29

APMSIDC-PALASA DET-Lower Ground Floor 444 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
D6 2 2 0.300 0.230 0.150 0.04
W1 2 43 0.300 0.230 0.150 0.89
W2 2 23 0.300 0.230 0.150 0.48
W3 2 2 0.300 0.230 0.150 0.04
V1 2 16 0.300 0.230 0.150 0.33
V2 2 22 0.300 0.230 0.150 0.46
V5 2 68 0.300 0.230 0.150 1.41
D2 2 11 0.300 0.115 0.150 0.11
D3 2 3 0.300 0.115 0.150 0.03
D5 2 14 0.300 0.115 0.150 0.14
D6 2 41 0.300 0.115 0.150 0.42
ALD1 2 5 0.300 0.115 0.150 0.05
FD1 2 8 0.300 0.115 0.150 0.08
FD2 2 2 0.300 0.115 0.150 0.02
Lift 2 2 0.300 0.230 0.150 0.04
Hold fasts
MD1 6 1 0.230 0.230 0.150 0.05
D2 6 8 0.230 0.230 0.150 0.38
D3 6 6 0.230 0.230 0.150 0.29
D5 6 14 0.230 0.230 0.150 0.67
D6 6 2 0.230 0.230 0.150 0.10
W1 4 43 0.230 0.230 0.150 1.36
W2 4 23 0.230 0.230 0.150 0.73
W3 4 2 0.230 0.230 0.150 0.06
V1 2 16 0.230 0.230 0.150 0.25
V2 2 22 0.230 0.230 0.150 0.35
V5 2 68 0.230 0.230 0.150 1.08
D2 6 11 0.230 0.115 0.150 0.26
D3 6 3 0.230 0.115 0.150 0.07
D5 6 14 0.230 0.115 0.150 0.33
D6 6 41 0.230 0.115 0.150 0.98
ALD1 6 5 0.230 0.115 0.150 0.12
FD1 6 8 0.230 0.115 0.150 0.19
FD2 6 2 0.230 0.115 0.150 0.05
Lift 6 2 0.230 0.230 0.150 0.10
12.57
Say 12.60 Cum

13 TMT STEEL
Tie beams 34.80 100.000 Kgs/Cum 3480.00
230mm thick Retaining wall 1097.2 22.000 Kgs/Sqm 24137.66
Columns upto 3.60 mts levael 251.00 200.000 Kgs/Cum 50200.00
Roof beams 161.00 200.000 Kgs/Cum 32200.00
125mm thick Roof slab 283.0 10.000 Kgs/Sqm 2830.00
150mm thick Roof slab 1786.00 12.000 Kgs/Sqm 21432.00
175mm thick Roof slab 944.00 14.000 Kgs/Sqm 13216.00
175mm thick waist slab 226.00 14.000 Kgs/Sqm 3164.00
Lintels 22 80.000 Kgs/Cum 1760.00
152419.66
Say 152.40 MT

14 Mild Steel
Sunshades 318.00 4.000 Kgs/Rm 1272.00
Lofts & Platforms 120 4.000 Kgs/Sqm 480.00
Shelves 40.00 4.000 Kgs/Sqm 160.00
Sillslab 1.549 4.000 Kgs/Sqm 6.20

APMSIDC-PALASA DET-Lower Ground Floor 445 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
RBM 1262.0 0.500 Kgs/Sqm 631.00
RCM facia 16.00 3.000 Kgs/Sqm 48.00
2597.20
Say 2.60 MT

15 External plastering
All round the Building Block-(A) 1 155.450 3.600 559.62
Duct Shorter Side 2 6.000 1.000 12.00
Duct Shorter Side 2 18.575 3.600 133.74
All round the Building Ramp Block 1 106.113 3.600 382.01
All round the Building Block-(-B) 1 155.450 3.600 559.62
Duct Shorter Side 2 6.000 1.000 12.00
Duct Shorter Side 2 18.575 3.600 133.74
Deductions
W1 -43 1.800 1.800 -139.32
W2 -23 1.500 1.800 -62.10
W3 -2 1.200 1.800 -4.32
JW -23 1.800 1.800 -74.52
V1 -16 1.800 0.500 -14.40
V2 -22 1.500 0.500 -16.50
V5 -68 0.600 0.500 -20.40
1461.17
Say 1462.00 Sqm

16 Ceiling plastering
Qty Same as Ceramic tile flooring 249.00
Qty Same as Vitrified flooring 1444.00
Qty Same as Chequered flooring 102.00
Qty Same as Granite flooring 985.85
2780.85
Say 2781.00 Sqm

17 Internal plastering 12 mm thick


Block-A
L Toilet 1 10.900 3.450 37.61
L Toilet Corridor 1 6.460 3.450 22.29
WC 4 5.400 3.450 74.52
G Toilet 1 10.990 3.450 37.92
G Toilet Lobby 1 3.240 3.450 11.18
WC 2 5.400 3.450 37.26
Staff Toilet 1 6.000 3.450 20.70
Ward Attached Toilets 2 6.600 3.450 45.54

Duty Nurse & Doctor Attached Toilets 2 5.400 3.450 37.26


Admin Attached Toilet 1 5.400 3.450 18.63
Ultra Sound Attached Toilet 1 6.000 3.450 20.70
Toilets Lobby 2 11.760 3.425 80.56
Toilets 2 10.320 3.425 70.69
Toilet Lobby 1 3.240 3.425 11.10
WC 5 5.400 3.450 93.15
PHC Toilet 1 7.800 3.450 26.91
Rest Room Toilet 1 7.200 3.450 24.84
Service Corridor 2 21.420 3.450 147.80
Infront Toilets 1 6.460 3.450 22.29
1 14.120 3.450 48.71
1 2.620 3.450 9.04

APMSIDC-PALASA DET-Lower Ground Floor 446 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Store 1 11.360 3.450 39.19
Electrical Room 1 14.220 3.450 49.06
AHU Room 1 14.170 3.450 48.89
Corridor 1 49.500 3.450 170.78
Water & lobby 1 13.600 3.450 46.92
Staircase 1 10.600 3.450 36.57
Ultra Sound 1 20.220 3.450 69.76
Ded Of Toilet -1 6.000 3.450 -20.70
Console 1 14.910 3.450 51.44
ECG 1 11.420 3.450 39.40
Lobby 1 10.500 3.450 36.23
Corridor 1 61.660 3.450 212.73
CT Scan 1 24.210 3.450 83.52
X Ray 2 24.210 3.425 165.84
X Ray Processing 1 15.600 3.450 53.82
Reporting 1 15.600 3.450 53.82
Waiting 1 21.610 3.450 74.55
Rec 1 16.360 3.450 56.44
Store 1 15.600 3.450 53.82
Clean Linen 1 15.600 3.450 53.82
Store 1 15.600 3.450 53.82
Duty Nurse 1 15.600 3.450 53.82
Nurse Station 1 13.200 3.450 45.54
Duty Doctor 1 15.600 3.450 53.82
Admin 1 15.600 3.450 53.82
Corridor 1 42.420 3.450 146.35
Examination 1 26.000 3.425 89.05
Ward 1 38.460 3.425 131.73
Corridor 1 67.800 3.450 233.91
Staircase 1 12.160 3.450 41.95
Pharmacy 1 22.360 3.450 77.14
Police Out Post 1 15.460 3.450 53.34
Rest Room 1 10.770 3.450 37.16
Rec 1 20.920 3.450 72.17
Lobby 1 10.320 3.450 35.60
Entrance Foyer 1 59.220 3.450 204.31
Ramp Block
Laboratory & Security Toilet 2 5.400 3.475 37.53
Attendents Waiting Toilet 4 5.400 3.475 75.06
Attendents Waiting Toilet Lobby 2 4.800 3.475 33.36
House Keeping & Admin Toilet 2 6.000 3.475 41.70
Laboratory & Security 2 12.000 3.475 83.40
Attendents Waiting 2 20.720 3.475 144.00
House Keeping & Admin 2 15.830 3.475 110.02
Lobby 2 4.800 3.475 33.36
Infront Lift 2 10.800 3.475 75.06
Corridor 1 59.240 3.475 205.86
Staircase 1 11.400 3.475 39.62
Ramp 1 42.000 3.475 145.95
Ramp 1 36.000 3.475 125.10
Block-(-B)
L Toilet 1 8.020 3.450 27.67
L Toilet Corridor 1 3.240 3.450 11.18
WC 3 5.400 3.450 55.89
G Toilet 1 10.990 3.450 37.92
G Toilet Lobby 1 3.240 3.450 11.18

APMSIDC-PALASA DET-Lower Ground Floor 447 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
WC 2 5.400 3.450 37.26
PHC Toilet 1 7.500 3.450 25.88
PHC Toilet 1 8.690 3.450 29.98
Washing & Drying Area 1 44.620 3.425 152.82
Store Attached Toilet 1 7.200 3.450 24.84
Service Corridor 2 18.500 3.450 127.65
Store 1 11.360 3.450 39.19
Electrical Room 1 14.220 3.450 49.06
Lobby 1 7.340 3.450 25.32
Lobby 1 6.460 3.450 22.29
Lobby 1 12.140 3.450 41.88
Corridor 1 34.800 3.450 120.06
Corridor Lobby 1 3.460 3.450 11.94
Staircase 1 10.600 3.450 36.57
Staircase Lobby 1 17.360 3.450 59.89
Chemical Store 1 20.300 3.450 70.04
Corridor 1 14.140 3.450 48.78
Calendering Machine 1 23.230 3.450 80.14
Segregation 1 20.380 3.425 69.80
Receiving 1 20.610 3.425 70.59
Waiting 1 21.010 3.450 72.48
Issuing 1 16.210 3.450 55.92
Corridor 1 55.060 3.450 189.96
Celen Store 1 21.300 3.450 73.49
Office 1 15.830 3.450 54.61
Tailoring 1 15.600 3.450 53.82
Medical Store 1 28.290 3.450 97.60
Surgical Store 1 28.290 3.450 97.60
Corridor 1 42.420 3.450 146.35
Medico Legal Store 1 18.800 3.425 64.39
MRD 1 33.890 3.425 116.07
Drug Store 1 32.690 3.425 111.96
Corridor 1 67.580 3.450 233.15
Bio Chemistry Lab 1 34.910 3.450 120.44
Pathology Lab 1 36.910 3.450 127.34
Micro Biology Lab 1 35.950 3.450 124.03
Corridor 1 28.180 3.450 97.22
Store 1 10.770 3.450 37.16
Staircase 1 26.760 3.450 92.32
Deductions
MD1 -1 3.000 2.600 -7.80
D2 -19 1.500 2.600 -74.10
D3 -9 1.200 2.600 -28.08
D5 -28 0.900 2.100 -52.92
D6 -43 0.800 2.100 -72.24
ALD1 -5 2.000 2.600 -26.00
FD1 -8 2.000 2.100 -33.60
FD2 -2 1.500 2.100 -6.30
W1 -43 1.800 1.800 -139.32
W2 -23 1.500 1.800 -62.10
W3 -2 1.200 1.800 -4.32
V1 -16 1.800 0.500 -14.40
V2 -22 1.500 0.500 -16.50
V5 -68 0.600 0.500 -20.40
JW -23 1.800 1.800 -74.52
Strl Glazing -4 2.400 1.800 -17.28

APMSIDC-PALASA DET-Lower Ground Floor 448 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Ded for Dadooing with ceramic tiles
for Toilets -524.30
Ded for Dadooing in corridor -558.50

Deduct Gladding with Granite Slabs -246.41


6082.77
Say 6083.00 Sqm
a 12 mm thick internal plastering
60% of above quantity (internal) 3649.66
Say 3650.00 Sqm
b 20 mm thick Internal plastering
40% of above quantity (external) 2433.11
Say 2433.00 Sqm

18 Flooring
a) Ceramic Tile Flooring
Block-A
L Toilet 1 3.830 1.620 6.20
L Toilet Corridor 1 3.230 1.200 3.88
WC 4 1.200 1.500 7.20
G Toilet 1 3.995 1.500 5.99
G Toilet Lobby 1 1.360 1.620 2.20
WC 2 1.200 1.500 3.60
Staff Toilet 1 1.200 1.800 2.16
Ward Attached Toilets 2 1.500 1.800 5.40

Duty Nurse & Doctor Attached Toilets 2 1.200 1.500 3.60


Admin Attached Toilet 1 1.200 1.500 1.80
Ultra Sound Attached Toilet 1 1.200 1.800 2.16
Toilets Lobby 2 2.940 2.940 17.29
Toilets 2 3.830 1.330 10.19
Toilet Lobby 1 1.200 1.620 1.94
WC 5 1.200 1.500 9.00
PHC Toilet 1 2.100 1.800 3.78
Rest Room Toilet 1 1.200 2.400 2.88
Ramp Block
Laboratory & Security Toilet 2 1.200 1.500 3.60
Attendents Waiting Toilet 4 1.200 1.500 7.20
Attendents Waiting Toilet Lobby 2 1.200 1.200 2.88
House Keeping & Admin Toilet 2 1.200 1.800 4.32
Block-(-B)
L Toilet 1 2.510 1.500 3.77
L Toilet Corridor 1 1.200 1.620 1.94
WC 3 1.200 1.500 5.40
G Toilet 1 3.995 1.500 5.99
G Toilet Lobby 1 1.360 1.620 2.20
WC 2 1.200 1.500 3.60
PHC Toilet 1 2.100 1.650 3.47
PHC Toilet 1 2.545 1.800 4.58
Washing & Drying Area 1 7.000 15.310 107.17
Store Attached Toilet 1 1.200 2.400 2.88
248.28
Say 249.00 Sqm

b) Vitrified Tile Flooring


Block-A

APMSIDC-PALASA DET-Lower Ground Floor 449 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Service Corridor 2 9.510 1.200 22.82
Ded Of Ducts -6 0.750 0.600 -2.70
Infront Toilets 1 1.230 3.230 3.97
1 5.450 1.610 8.77
1 1.310 1.130 1.48
Store 1 2.635 3.045 8.02
Electrical Room 1 3.995 3.115 12.44
AHU Room 1 4.085 3.000 12.26
Water & lobby 1 5.070 1.730 8.77
Ultra Sound 1 3.950 6.160 24.33
Ded Of Toilet -1 1.200 1.800 -2.16
Console 1 3.385 4.070 13.78
ECG 1 3.385 2.325 7.87
Lobby 1 3.620 1.630 5.90
CT Scan 1 6.885 5.220 35.94
X Ray 2 6.885 5.220 71.88
X Ray Processing 1 4.800 3.000 14.40
Reporting 1 4.800 3.000 14.40
Waiting 1 4.920 5.885 28.95
Rec 1 4.800 3.380 16.22
Store 1 4.800 3.000 14.40
Clean Linen 1 4.800 3.000 14.40
Store 1 4.800 3.000 14.40
Duty Nurse 1 4.800 3.000 14.40
Nurse Station 1 3.600 3.000 10.80
Duty Doctor 1 4.800 3.000 14.40
Admin 1 4.800 3.000 14.40
Ded Of Toilet -1 1.200 1.500 -1.80
Examination 1 6.885 6.115 42.10
Ward 1 7.000 12.230 85.61
Ded Of Toilet -2 1.500 1.800 -5.40
Pharmacy 1 5.215 5.965 31.11
Police Out Post 1 5.215 2.515 13.12
Rest Room 1 2.985 2.400 7.16
Rec 1 4.680 5.780 27.05
Ramp Block
Laboratory & Security 2 3.000 3.000 18.00
Attendents Waiting 2 4.315 6.045 52.17
House Keeping & Admin 2 3.000 4.915 29.49
Lobby 2 1.085 1.315 2.85
Block-(-B)
Service Corridor 2 8.050 1.200 19.32
Store 1 2.635 3.045 8.02
Electrical Room 1 3.995 3.115 12.44
Lobby 1 2.540 1.130 2.87
Lobby 1 1.230 3.230 3.97
Lobby 1 6.070 1.610 9.77
Chemical Store 1 3.990 6.160 24.58
Calendering Machine 1 6.885 4.730 32.57
Segregation 1 7.000 3.190 22.33
Receiving 1 7.115 3.190 22.70
Waiting 1 7.315 3.190 23.33
Issuing 1 4.800 3.305 15.86
Celen Store 1 4.800 5.850 28.08
Office 1 4.800 3.115 14.95
Tailoring 1 4.800 3.000 14.40

APMSIDC-PALASA DET-Lower Ground Floor 450 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Medical Store 1 4.800 9.345 44.86
Surgical Store 1 4.800 9.345 44.86
Medico Legal Store 1 7.000 2.400 16.80
MRD 1 7.000 9.945 69.62
Drug Store 1 7.000 9.345 65.42
Bio Chemistry Lab 1 8.860 8.595 76.15
Pathology Lab 1 12.090 6.365 76.95
Micro Biology Lab 1 9.380 8.595 80.62
Store 1 2.985 2.400 7.16
1443.66
Say 1444.00 Sqm

d) Granite Slabs
Entrance Portico 1 1 5.320 2.000 10.64
Infront Staircase-1 2 1 2.400 6.280 30.14
Staircase Midlanding 2 1 2.000 4.430 17.72
Infront Staircase-2 2 1 4.300 2.450 21.07
Staircase Midlanding 2 1 2.000 4.300 17.20
Infront Staircase-3 1 1 5.100 2.480 12.65
Staircase Midlanding 1 1 5.100 2.400 12.24
Lobby 1 2.350 2.810 6.60
Entrance Foyer 1 20.900 8.710 182.04
Corridor 1 21.750 3.000 65.25
Corridor 1 2.400 28.430 68.23
Corridor 1 2.400 18.810 45.14
Corridor 1 30.900 3.000 92.70
Infront Lift 2 2.400 3.000 14.40
Corridor 1 23.390 3.000 70.17
Corridor Lobby 1 10.360 3.230 33.46
Corridor 1 14.400 3.000 43.20
Corridor Lobby 1 5.070 1.730 8.77
Corridor 1 4.070 3.000 12.21
Corridor 1 2.400 25.130 60.31
Corridor 1 2.400 18.810 45.14
Corridor 1 30.790 3.000 92.37
Corridor 1 12.090 2.000 24.18
985.85
Say 986.00 Sqm

e) Chequered tiles
Ramp 2 2.400 18.000 86.40
Ramp Mid Landing 1 5.100 3.000 15.30
101.70
Say 102.00 Sqm

f) Interlocking Tiles
Entrance Ramp At Portico 2 5.000 2.000 20.00
Portico 1 14.250 6.240 88.92
108.92
Say 109.00 Sqm

19 Skirting
a) Skirting with Vitrified Tiles
Block-A
Service Corridor 2 21.420 42.84
Infront Toilets 1 8.920 8.92

APMSIDC-PALASA DET-Lower Ground Floor 451 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
1 14.120 14.12
1 4.880 4.88
Store 1 11.360 11.36
Electrical Room 1 14.220 14.22
AHU Room 1 14.170 14.17
Water & lobby 1 13.600 13.60
Ultra Sound 1 20.220 20.22
Console 1 14.910 14.91
ECG 1 11.420 11.42
Lobby 1 10.500 10.50
CT Scan 1 24.210 24.21
X Ray 2 24.210 48.42
X Ray Processing 1 15.600 15.60
Reporting 1 15.600 15.60
Waiting 1 21.610 21.61
Rec 1 16.360 16.36
Store 1 15.600 15.60
Clean Linen 1 15.600 15.60
Store 1 15.600 15.60
Duty Nurse 1 15.600 15.60
Nurse Station 1 13.200 13.20
Duty Doctor 1 15.600 15.60
Admin 1 15.600 15.60
Examination 1 26.000 26.00
Ward 1 38.460 38.46
Pharmacy 1 22.360 22.36
Police Out Post 1 15.460 15.46
Rest Room 1 10.770 10.77
Rec 1 20.920 20.92
Lobby 1 10.320 10.32
Ramp Block
Laboratory & Security 2 12.000 24.00
Attendents Waiting 2 20.720 41.44
House Keeping & Admin 2 15.830 31.66
Lobby 2 4.800 9.60
Infront Lift 2 10.800 21.60
Block-(-B)
Service Corridor 2 18.500 37.00
Store 1 11.360 11.36
Electrical Room 1 14.220 14.22
Lobby 1 7.340 7.34
Lobby 1 8.920 8.92
Lobby 1 15.360 15.36
Corridor 1 34.800 34.80
Corridor Lobby 1 13.600 13.60
Chemical Store 1 20.300 20.30
Corridor 1 14.140 14.14
Calendering Machine 1 23.230 23.23
Segregation 1 20.380 20.38
Receiving 1 20.610 20.61
Waiting 1 21.010 21.01
Issuing 1 16.210 16.21
Corridor 1 55.060 55.06
Celen Store 1 21.300 21.30
Office 1 15.830 15.83
Tailoring 1 15.600 15.60

APMSIDC-PALASA DET-Lower Ground Floor 452 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Medical Store 1 28.290 28.29
Surgical Store 1 28.290 28.29
Corridor 1 42.420 42.42
Medico Legal Store 1 18.800 18.80
MRD 1 33.890 33.89
Drug Store 1 32.690 32.69
Corridor 1 67.580 67.58
Bio Chemistry Lab 1 34.910 34.91
Pathology Lab 1 36.910 36.91
Micro Biology Lab 1 35.950 35.95
Corridor 1 28.180 28.18
Store 1 10.770 10.77
1487.30
Say 1488.00 Rmt

c) Skirting with Granite


Infront Staircase-1 2 1 17.360 34.72
Staircase Midlanding 2 1 8.430 16.86
Infront Staircase-2 2 1 13.500 27.00
Staircase Midlanding 2 1 8.300 16.60
Infront Staircase-3 1 1 15.160 15.16
Staircase Midlanding 1 1 9.900 9.90
120.24
Say 121.00 Rmt

20 Dadooing with Ceramic Tiles


Block-A
L Toilet 1 10.900 1.500 16.35
L Toilet Corridor 1 8.860 1.500 13.29
WC 4 5.400 1.500 32.40
G Toilet 1 10.990 1.500 16.49
G Toilet Lobby 1 5.960 1.500 8.94
WC 2 5.400 1.500 16.20
Staff Toilet 1 6.000 1.500 9.00
Ward Attached Toilets 2 6.600 1.500 19.80
Duty Nurse & Doctor Attached Toilets 2 5.400 1.500 16.20
Admin Attached Toilet 1 5.400 1.500 8.10
Ultra Sound Attached Toilet 1 6.000 1.500 9.00
Toilets Lobby 2 11.760 1.500 35.28
Toilets 2 10.320 1.500 30.96
Toilet Lobby 1 5.640 1.500 8.46
WC 5 5.400 1.500 40.50
PHC Toilet 1 7.800 1.500 11.70
Rest Room Toilet 1 7.200 1.500 10.80
Ramp Block
Laboratory & Security Toilet 2 5.400 1.500 16.20
Attendents Waiting Toilet 4 5.400 1.500 32.40
Attendents Waiting Toilet Lobby 2 4.800 1.500 14.40
House Keeping & Admin Toilet 2 6.000 1.500 18.00
Block-(-B)
L Toilet 1 8.020 1.500 12.03
L Toilet Corridor 1 5.640 1.500 8.46
WC 3 5.400 1.500 24.30
G Toilet 1 10.990 1.500 16.49
G Toilet Lobby 1 5.960 1.500 8.94
WC 2 5.400 1.500 16.20

APMSIDC-PALASA DET-Lower Ground Floor 453 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
PHC Toilet 1 7.500 1.500 11.25
PHC Toilet 1 8.690 1.500 13.04
Washing & Drying Area 1 44.620 1.500 66.93
Store Attached Toilet 1 7.200 1.500 10.80
Deductions
D5 -4 0.900 1.500 -5.40
D6 -36 0.800 1.500 -43.20
524.30
Say 525.00 Sqm

21 Dadooing in corridor
Block-A
Corridor 1 43.500 1.500 65.25
Entrance Corridor 1 61.800 1.500 92.70
Corridor 1 38.080 1.500 57.12
Corridor 1 56.860 1.500 85.29
Ramp Block
3.0 m wide corridor 1 13.160 1.500 19.74
3.0 m wide corridor 1 23.390 1.500 35.09
Block-(-B)
Corridor 1 37.420 1.500 56.13
Corridor 1 61.580 1.500 92.37
Corridor 1 38.080 1.500 57.12
Corridor 1 56.860 1.500 85.29
Deductions
ALD1 -2 2.000 1.500 -6.00
FD1 -6 2.000 1.500 -18.00
MD1 -1 3.000 1.500 -4.50
D2 -15 1.500 1.500 -33.75
D3 -3 1.200 1.500 -5.40
D5 -13 0.900 1.500 -17.55
D6 -2 0.800 1.500 -2.40
558.50
Say 559.00 Sqm

22 Cladding With Granite Slabs


Block-A
Entrance Portico 1 14.250 3.460 49.31
Entrance Foyer 1 59.220 3.460 204.90
Deductions
MD1 -1 3.000 2.600 -7.80
246.41
Say 247.00 Sqm

23 Polished Granite slab


i Treads
Staircase-1&2 4 26 2.000 0.300 62.40
Staircase-3 1 26 2.400 0.300 18.72
81.12
Say 82.00 Sqm

ii Risers
Staircase-1&2 4 28 2.000 0.150 33.60
Staircase-3 1 28 2.400 0.150 10.08
43.68

APMSIDC-PALASA DET-Lower Ground Floor 454 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Say 44.00 Sqm
24 High polished granite platforms
Qty same as Platforms 72.00
72.00
Say 72.00 Sqm

25 High polished granite for sill slabs


W1 43 2.100 0.225 20.32
W2 23 1.800 0.225 9.32
W3 2 1.500 0.225 0.68
30.31
Say 31.00 Sqm

26 Whiting for ceiling


Same as ceiling plastering 2781.00
2781.00
Say 2781.00 Sqm

27 Wall putty
Same as internal plastering 6083.00
6083.00
Say 6083.00 Sqm

28 Plastic Emulsion Paint for interior


faces of walls
Same as internal plastering 6083.00
6083.00
Say 6083.00 Sqm

29 Emulsion paint for external


plastering
Same as of external plastering @
60% 877.20
877.20
Say 878.00 Sqm

30 Emulsion paint for external


plastering
Same as of external plastering @
40% 584.80
584.80
Say 585.00 Sqm

31 Painting to wood woork


MD1 2.25 1 6.100 3.000 41.18
41.18
Say 42.00 Sqm
32 Doors
Wooden Doors
MD1 (3.0X 2.60) 1 6.100 3.000 18.30
Say 18.30 Sqm

D2 (1.5X 2.60) 18 1.500 2.600 70.20


Say 70.20 Sqm

D3 (1.2 X 2.60) 9 1.200 2.600 28.08

APMSIDC-PALASA DET-Lower Ground Floor 455 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Say 28.08 Sqm

D5 (0.9 x 2.10) 27 0.900 2.100 51.03


Say 51.03 Sqm

D6 (0.8 X 2.10) - Frame 43 5.000 215.00


Say 215.00 RM

D6 (0.8 X 2.10) 43 0.800 2.100 72.24


Say 72.24 Sqm

33 Doors
ALD Doors
ALD1 (2.0X 2.60) 13 2.000 2.600 67.60
Say 67.60 Sqm

34 Windows
2 Track Sliding Windows
W1 40 1.800 1.800 129.60
W2 17 1.500 1.800 45.90
W3 3 1.200 1.800 6.48
Total Quantity 181.98 Sqm

3 Track Sliding Windows


W2 4 1.500 1.800 10.80
10.80 Sqm

35
MS Grill for Windows @ 15 Kg/Sqm
W1 44 1.800 1.800 142.56
W2 17 1.500 1.800 45.90
W3 3 1.200 1.800 6.48
Ventilators
V5 66 0.600 0.500 19.80
214.74
Say 215.00 Sqm
3225.00 Kgs
36 RCC Jally Windows
JW 24 1.800 1.800 77.76
77.76
Say 78.00 Sqm

37 Painting to iron Work


Quantity Same as MS Grill 214.74
214.74 Sqm
Say 215.00 Sqm

38 Ventilators
V5 66 0.600 0.500 19.80
Say 19.80 Sqm

39 Structural Glazing
staire case at Ramp 2 1.800 3.000 10.80
10.80
Say 11.00 Sqm

APMSIDC-PALASA DET-Lower Ground Floor 456 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
40 Structural Glazing with top hung
shutters
20% of above quantity 2.16
2.16
Say 3.00 Sqm

40 Railing
All round the staircase 2 1 7.350 0.900 13.23
All round the staircase 2 1 7.350 0.900 13.23
All round the staircase 1 1 7.350 0.900 6.62
All round the ramp 1 1 36.000 0.900 32.40
65.48
Say 66.00 Sqm
41 Grip bar
Staircase 2 1 15.030 30.06
Staircase 2 1 14.900 29.80
Staircase 1 1 16.500 16.50
Ramp 1 1 47.100 47.10
PHC Toilet 1 1 7.800 7.80
PHC Toilet 1 1 7.500 7.50
PHC Toilet 1 1 8.690 8.69
Entrance Ramp 1 2 9.000 18.00
165.45
Say 166.00 Rmt

42 Cupboards
Pharmacy Issue 1 2.000 2.100 4.20
Nurse Station 1 2.000 2.100 4.20
Store 3 2.500 2.100 15.75
Clean Linen Store 1 2.500 2.100 5.25
Rec 1 2.500 2.100 5.25
Lab 1 2.500 2.100 5.25
Store 1 2.500 2.100 5.25
Drug Store 2 2.500 2.100 10.50
Surgical Store 2 2.500 2.100 10.50
Medical Store 2 2.500 2.100 10.50
Tailoring 1 2.000 2.100 4.20
Celen Store 1 2.000 2.100 4.20
Chemical Store 1 2.000 2.100 4.20
Bio Chemistry Lab 2 2.000 2.100 8.40
Pathology Lab 2 2.000 2.100 8.40
Micro Biology Lab 2 2.000 2.100 8.40
114.45
Say 115.00 Sqm

43 RCM Drop
Entrance Portico 1 33.730 0.450 15.18
15.18
Say 16.00 Sqm
44 False ceiling
Qty Same as Vitrified flooring 1 1444.00 1444.00
Qty Same as Granite flooring 1 985.85 985.85
2429.85
Say 2430.00 Sqm
45 Mastic pad
Roof beams

APMSIDC-PALASA DET-Lower Ground Floor 457 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Horizontal 2 3.460 0.450 3.11
3.11
Say 4.00 Sqm

46 Expansion joint treatment


Roof beams
Horizontal 2 3.460 6.92
6.92
Say 7.00 Rmt

47 Aluminium sheet
Roof beams
Horizontal 2 3.460 6.92
6.92
Say 7.00 Rmt
48 Impervious coat for terrace
Portico 1 14.830 9.980 148.00
148.00
Say 149.00 Sqm

APMSIDC-PALASA DET-Lower Ground Floor 458 of 1048


#REF!

DETAILED ESTIMATE - Upper Ground FLOOR


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
1
Columns P.B Top to Roof slab bottom
Block-A & Ramp Block
C1 13 0.380 0.600 3.475 10.30
C2 20 0.380 0.600 3.475 15.85
C3 12 0.380 0.600 3.475 9.51
C4 5 0.450 0.750 3.475 5.86
C5 10 0.460 0.600 3.475 9.59
C6 6 0.460 0.600 3.475 5.75
C7 4 0.460 0.600 3.475 3.84
C8 2 0.600 0.600 3.475 2.50
C9 2 0.600 0.600 3.475 2.50
C10 2 0.600 0.600 3.475 2.50
C11 7 0.600 0.750 3.475 10.95
C12 19 0.600 0.750 3.475 29.71
C13 11 0.600 0.750 3.475 17.20

Columns P.B Top to Roof slab bottom


Block-(-B)
C4 5 0.450 0.750 3.450 5.82
C5 8 0.460 0.600 3.450 7.62
C6 6 0.460 0.600 3.450 5.71
C7 4 0.460 0.600 3.450 3.81
C8 2 0.600 0.600 3.450 2.48
C9 2 0.600 0.600 3.450 2.48
C10 2 0.600 0.600 3.450 2.48
C11 7 0.600 0.750 3.450 10.87
C12 19 0.600 0.750 3.450 29.50
C13 11 0.600 0.750 3.450 17.08
213.92
Say 214.00 Cum

2 Roof Beams
Horizontal
Block-A
T1-T4 1 7.120 0.300 0.300 0.64
Deduction of Columns -2 0.750 0.300 0.300 -0.14
T4-T5 1 2.400 0.380 0.275 0.25
T5-T7 1 2.800 0.300 0.300 0.25
T7-T10 2 7.700 0.230 0.450 1.59
T10-T16 2 13.810 0.300 0.300 2.49
Deduction of Columns -8 0.750 0.300 0.300 -0.54
Secondary Beam 2 9.520 0.300 0.300 1.71
Deduction of Columns -2 0.230 0.300 0.300 -0.04
Q1-Q2 1 3.310 0.300 0.300 0.30
Q2-Q4 1 2.310 0.380 0.300 0.26
Q4-Q5 1 2.400 0.380 0.275 0.25
Q5-Q10 1 11.250 0.230 0.450 1.16
Q10-Q12 1 2.800 0.300 0.300 0.25
Q12-Q13 1 2.400 0.380 0.275 0.25
Q13-Q16 1 7.120 0.300 0.300 0.64
O1-O5 4 9.520 0.450 0.575 9.85

APMSIDC-PALASA DET-Upper Ground Floor 459 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
O5-O12 2 16.290 0.300 0.275 2.69
Deduction of Columns -8 0.750 0.300 0.275 -0.50
M5-M8 4 4.170 0.300 0.275 1.38
O12-O16 4 9.520 0.450 0.575 9.85
G1-G16 2 35.320 0.300 0.300 6.36
Deduction of Columns -4 0.450 0.300 0.300 -0.16
Deduction of Columns -8 0.600 0.300 0.300 -0.43
E1-E3 1 4.300 0.300 0.400 0.52
Cantilever Beams 2 1.000 0.300 0.300 0.18
Ramp Block
R19-R21 5 5.100 0.230 0.355 2.08
Deduction of Columns -4 0.380 0.230 0.355 -0.12
K17-K19 4 5.860 0.230 0.275 1.48
Deduction of Columns -8 0.380 0.230 0.275 -0.19
I17-I23 1 16.820 0.230 0.275 1.06
Deduction of Columns -5 0.380 0.230 0.275 -0.12
H17-H18 2 5.080 0.230 0.300 0.70
Deduction of Columns -4 0.380 0.230 0.300 -0.10
H18-H22 1 10.360 0.230 0.450 1.07
Deduction of Columns -2 0.230 0.230 0.450 -0.05
G17-G19 2 7.480 0.230 0.300 1.03
Deduction of Columns -4 0.380 0.230 0.300 -0.10
G19-G21 3 4.800 0.230 0.380 1.26
F18-F19 2 2.180 0.230 0.300 0.30
Block-(-B)
T39-T33 3 13.060 0.300 0.300 3.53
Deduction of Columns -9 0.750 0.300 0.300 -0.61
T33-T30 2 7.700 0.230 0.450 1.59
Secondary Beam 2 9.520 0.300 0.300 1.71
Deduction of Columns -2 0.230 0.300 0.300 -0.04
Q1-Q38 1 3.310 0.300 0.300 0.30
Q38-Q36 1 2.310 0.380 0.300 0.26
Q36-Q35 1 2.400 0.380 0.275 0.25
Q35-Q30 1 11.250 0.230 0.450 1.16
O39-O35 4 9.520 0.450 0.575 9.85
O35-O28 4 16.290 0.300 0.275 5.38
Deduction of Columns -16 0.750 0.300 0.275 -0.99
O28-O24 4 9.520 0.450 0.575 9.85
G39-G24 2 35.320 0.300 0.300 6.36
Deduction of Columns -4 0.450 0.300 0.300 -0.16
Deduction of Columns -8 0.600 0.300 0.300 -0.43
E39-E38 1 4.300 0.300 0.400 0.52
Cantilever Beams 2 1.000 0.300 0.300 0.18
Vertical
Block-A
B1-E1 2 1.360 0.300 0.300 0.24
E1-G1 2 5.330 0.300 0.450 1.44
G1-H1 8 3.000 0.300 0.300 2.16
H1-O1 6 19.040 0.300 0.425 14.57
Deduction of Columns -24 0.600 0.300 0.425 -1.84
O1-Q1 2 3.000 0.230 0.300 0.41
O2-Q2 4 3.000 0.300 0.300 1.08
Q1-T1 6 5.720 0.230 0.450 3.55
Q5-T5 4 5.720 0.230 0.475 2.50
Deduction of Columns -1 0.600 0.230 0.475 -0.07
Secondary Beam 1 1.400 0.300 0.325 0.14

APMSIDC-PALASA DET-Upper Ground Floor 460 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Secondary Beam 1 4.330 0.300 0.325 0.42
B5-G5 4 8.940 0.380 0.475 6.45
Deduction of Columns -8 0.750 0.380 0.475 -1.08
Ramp Block
D17-G17 2 5.860 0.230 0.450 1.21
G17-H17 4 3.000 0.230 0.300 0.83
H17-J17 2 5.750 0.230 0.450 1.19
J17-K17 2 2.560 0.230 0.300 0.35
D18-I18 2 12.920 0.230 0.300 1.78
Deduction of Columns -8 0.750 0.230 0.300 -0.41
I18-K18 2 6.050 0.230 0.380 1.06
C19-G19 2 8.640 0.230 0.300 1.19
Deduction of Columns -8 0.750 0.230 0.300 -0.41
G19-I19 2 5.860 0.230 0.450 1.21
I19-J19 3 2.890 0.230 0.275 0.55
J19-L19 3 4.930 0.230 0.425 1.45
L19-N19 3 3.490 0.230 0.355 0.85
N19-P19 3 3.850 0.230 0.355 0.94
P19-R19 2 2.760 0.230 0.275 0.35
Block-B
B39-E39 2 1.360 0.300 0.300 0.24
E39-G39 2 5.330 0.300 0.450 1.44
G39-H39 8 3.000 0.300 0.300 2.16
H39-O39 6 19.040 0.300 0.425 14.57
Deduction of Columns -24 0.600 0.300 0.425 -1.84
O39-Q39 6 3.000 0.230 0.300 1.24
Q39-T39 6 5.720 0.230 0.450 3.55
Q35-T35 4 5.720 0.230 0.475 2.50
Deduction of Columns -1 0.600 0.230 0.475 -0.07
Secondary Beam 1 1.400 0.300 0.325 0.14
Secondary Beam 1 4.330 0.300 0.325 0.42
B35-G35 6 8.940 0.380 0.475 9.68
Deduction of Columns -10 0.750 0.380 0.475 -1.35
Deduction of Columns -2 0.600 0.380 0.475 -0.22
160.69
Say 161.00 Cum

3 Roof slab
iii) Roof Slab 175mm thick
H1-H5 x H1-O1 2 2 9.980 19.040 760.08
H31-H32 x H31-O31 1 1 6.460 19.040 123.00
B31-B32 x B31-G31 1 1 6.760 8.940 60.43
943.51
Say 944.00 Sqm
i) Roof Slab 150mm thick
Block-(A) 1 40.600 35.780 1452.67
Block-(B) 1 40.600 35.780 1452.67
Ded Of Staircase -2 5.300 4.430 -46.96
Ded Of Staircase -2 4.300 5.300 -45.58
Ded Of Duct -2 6.000 18.575 -222.90
Deduct Double Height Portion -1 15.830 8.480 -134.24
Portico Slab 1 14.250 9.750 138.94
Deduction of 175mm Thick Slab -943.51
1651.09
Say 1652.00 Sqm
ii) Roof Slab 125mm thick

APMSIDC-PALASA DET-Upper Ground Floor 461 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Ramp Block 1 432.775 432.78
Ded Of Staircase -1 5.830 5.100 -29.73
Ded Of Lift -2 2.400 3.000 -14.40
Deduction of Ramp -1 20.550 5.100 -104.81
283.84
Say 284.00 Sqm

v) Waist slab (175mm thick)


Staircase (Flight -1& Flight-2) 5 2 3.600 2.000 72.00
Mid landing 5 1 4.460 2.000 44.60
Ramp 1 2 21.500 2.000 86.00
Mid landing 5 1 4.460 2.000 44.60
247.20
Say 248.00 Sqm

4 RCC M20 grade mix


a Platforms
Receiptions 2 4.915 0.600 5.90
Sample collection 1 7.185 0.600 4.31
Renal Lab 1 7.200 0.600 4.32
Uro dynamic lab 1 4.800 0.600 2.88
Hand wash in toilet 4 3.000 0.600 7.20
24.61
Say 25.00 Sqm
b Loft
Injection room(male) 3 1 3.140 0.450 4.24
Injection room(female) 3 1 3.140 0.450 4.24
8.48
Say 9.00 Sqm

c Racks
Injection room(male) 3 1 3.140 0.450 4.24
Injection room(female) 3 1 3.140 0.450 4.24
8.48
Say 9.00 Sqm

5 230mm thick brick masonary


Horizontal
Block-A1
Service Corridor to Dirty Utility 1 13.810 0.225 3.150 9.79
Deduction of columns -4 0.750 0.225 3.150 -2.13
Staircase 1 7.700 0.225 3.150 5.46
Stores To Service Corridor 1 13.810 0.225 3.150 9.79
Deduction of columns -4 0.750 0.225 3.150 -2.13
WC To PHC 2 6.060 0.225 3.150 8.59
G Toilet 2 6.430 0.225 3.150 9.11
Electrical Room 1 5.720 0.225 3.000 3.86
Staircase 1 5.300 0.225 3.000 3.58
Class IV 1 2.800 0.225 3.150 1.98
RenaL Lab 4 7.110 0.225 3.450 22.08
Technician 4 3.650 0.225 3.150 10.35
Dept Seminar Room 1 4.770 0.225 3.150 3.38
Dept Seminar Room 1 4.830 0.225 3.150 3.42
Server Room 1 4.230 0.225 3.150 3.00
Store 1 4.300 0.225 3.450 3.34
Store To Store 1 35.320 0.225 3.150 25.03

APMSIDC-PALASA DET-Upper Ground Floor 462 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Deduction of columns -6 0.600 0.225 3.150 -2.55
Ramp Block
Ramp Wall 1 5.100 0.225 3.095 3.55
Attendents Waiting Room 2 5.860 0.225 3.175 8.37
Deduction of columns -4 0.380 0.225 3.175 -1.09
Laboratory 2 5.860 0.225 3.175 8.37
Deduction of columns -4 0.380 0.225 3.175 -1.09
Corridor 1 5.940 0.225 3.025 4.04
Security 1 2.700 0.225 3.175 1.93
Corridor To Staircase Entrance 1 8.490 0.225 3.175 6.07
Deduction of columns -2 0.380 0.225 3.175 -0.54
Staircase 2 4.800 0.225 3.095 6.69
Staircase Entrance To Admin 1 5.860 0.225 3.175 4.19
Deduction of columns -1 0.380 0.225 3.175 -0.27
Lift 2 2.400 0.225 3.175 3.43
House Keeping To Lift 2 5.330 0.225 3.175 7.62
Deduction of columns -2 0.380 0.225 3.175 -0.54
Block-B
Service Corridor to Store 1 13.810 0.225 3.150 9.79
Deduction of columns -4 0.750 0.225 3.150 -2.13
Staircase 1 7.700 0.225 3.000 5.20
Store To Service Corridor 1 13.810 0.225 3.150 9.79
Deduction of columns -4 0.750 0.225 3.150 -2.13
WC To PHC 2 6.060 0.225 3.150 8.59
G Toilet 2 6.430 0.225 3.150 9.11
Class IV 1 5.720 0.225 3.000 3.86
Staircase 1 5.300 0.225 3.000 3.58
Electrical Room 1 2.800 0.225 3.150 1.98
Injection 4 7.110 0.225 3.450 22.08
Stress Test 4 3.650 0.225 3.150 10.35
Security 1 4.300 0.225 3.450 3.34
Rec To Security 1 35.320 0.225 3.150 25.03
Deduction of columns -6 0.600 0.225 3.150 -2.55
Entrance Portico Steps 5 5.320 0.300 0.150 1.20
Vertical
Block-(A)
Store 2 1.360 0.225 3.150 1.93
Staircase 2 5.330 0.225 3.000 7.20
Lobby 1 1.900 0.225 3.150 1.35
Rec To Renal Lab 4 19.040 0.225 3.000 51.41
Deduction of columns -3 0.450 0.225 3.000 -0.91
Deduction of columns -9 0.600 0.225 3.000 -3.65
Store 4 3.000 0.225 3.150 8.51
Toilets 2 5.720 0.225 3.000 7.72
Toilets 2 3.010 0.225 3.450 4.67
PHC 2 1.730 0.225 3.450 2.69
Electrical Room To Dirty Utility 2 6.620 0.225 3.000 8.94
Deduction of columns -4 0.600 0.225 3.000 -1.62
Water 2 1.750 0.225 3.450 2.72
Seminar Room 1 8.940 0.225 3.000 6.03
Deduction of columns -6 0.750 0.225 3.000 -3.04
Ramp Block
House Keeping 2 5.860 0.225 3.025 7.98
Lab To Attendents 2 9.510 0.225 3.025 12.95
Deduction of columns -2 0.600 0.225 3.025 -0.82
House Keeping 2 6.460 0.225 3.175 9.23

APMSIDC-PALASA DET-Upper Ground Floor 463 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Lab 2 2.260 0.225 3.175 3.23
Staircase 2 8.640 0.225 3.175 12.34
Deduction of columns -8 0.600 0.225 3.175 -3.43
Ramp Walls 3 2.890 0.225 3.175 6.19
Ramp Walls 3 4.930 0.225 3.025 10.07
Ramp Walls 3 8.530 0.225 3.095 17.82
Deduction of columns -6 0.600 0.225 3.095 -2.51
Ramp Walls 2 2.630 0.225 3.175 3.76
Block-(-B)
Security 2 1.360 0.225 3.150 1.93
Staircase 2 5.330 0.225 3.000 7.20
Lobby 1 1.900 0.225 3.150 1.35
Dressing Male To Female 4 19.040 0.225 3.000 51.41
Deduction of columns -3 0.450 0.225 3.000 -0.91
Deduction of columns -9 0.600 0.225 3.000 -3.65
Store 4 3.000 0.225 3.150 8.51
Toilets 4 6.620 0.225 3.000 17.87
Deduction of columns -4 0.450 0.225 3.000 -1.22
Deduction of columns -4 0.600 0.225 3.000 -1.62
PHC 2 1.730 0.225 3.450 2.69
Toilets 2 3.080 0.225 3.000 4.16
Water 2 1.750 0.225 3.450 2.72
Rec 1 7.440 0.225 3.000 5.02
Deduction
MD1 -1 3.000 0.225 2.600 -1.76
D3 -9 1.200 0.225 2.600 -6.32
D5 -12 0.900 0.225 2.100 -5.10
W1 -68 1.800 0.225 1.800 -49.57
W2 -5 1.500 0.225 1.800 -3.04
W3 -1 1.200 0.225 1.800 -0.49
V5 -66 0.600 0.225 0.500 -4.46
JW -16 1.800 0.225 1.800 -11.66
Lift -2 1.000 0.225 2.100 -0.95
Lintels Deduction
MD1 -1 3.460 0.225 0.175 -0.14
D3 -9 1.660 0.225 0.175 -0.59
D5 -12 1.360 0.225 0.175 -0.64
W1 -68 2.260 0.225 0.175 -6.05
W2 -5 1.960 0.225 0.175 -0.39
W3 -1 1.660 0.225 0.175 -0.07
V5 -66 1.060 0.225 0.175 -2.75
JW -16 2.260 0.225 0.175 -1.42
Lift -2 1.460 0.225 0.175 -0.11
444.46
Say 445.00 Cum
6 115 mm thick Brick masonry walls
Horizontal
Block-A1
G Toilet 2 2.630 3.450 18.15
PHC 2 3.280 3.450 22.63
Staff Toilet 2 1.200 3.450 8.28
Electrical Room 2 4.070 3.450 28.08
L Toilet 2 3.830 3.450 26.43
URO Dynamic Lab Attached Toilet 1 1.200 3.450 4.14
Duct Walls 2 6.000 3.450 41.40
Corridor Walls 4 2.400 3.150 30.24

APMSIDC-PALASA DET-Upper Ground Floor 464 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Double Height Eall 1 15.090 3.150 47.53
Store 1 5.465 3.450 18.85
Partitions 12 4.800 3.450 198.72
Ramp Block
Attendents Attached Toilets 6 1.315 3.450 27.22
House Keeping Attached Toilets 2 1.915 3.450 13.21
Block-B
L Toilet 2 3.830 3.450 26.43
G Toilet 2 2.630 3.450 18.15
PHC Toilet 2 3.050 3.450 21.05
Staff Toilet 2 1.200 3.450 8.28
Electrical Room 2 4.070 3.450 28.08
Duct Walls 2 6.000 3.450 41.40
Corridor Walls 4 2.400 3.150 30.24
Sample Collection 1 6.510 3.425 22.30
WC 1 1.445 3.425 4.95
Rec 2 4.230 3.150 26.65
Injection Partition 1 6.510 3.150 20.51
Stress Test Partitions 12 4.800 3.150 181.44
Verticals
Block-A1
Corridor Walls 2 3.000 3.450 20.70
WC 12 1.500 3.450 62.10
Service Corridor 2 1.200 3.450 8.28
Staff Toilet 2 1.580 3.450 10.90
Dirty Utility 2 3.045 3.450 21.01
Electrical Room 2 2.780 3.450 19.18
URO Dynamic Lab Attached Toilet 1 1.500 3.425 5.14
Store To Server Room 1 7.440 3.425 25.48
Partitions 4 3.115 3.000 37.38
Partitions 2 17.840 3.000 107.04
Ramp Block
Attendents Attached Toilets 2 6.045 3.450 41.71
House Keeping Attached Toilets 2 1.200 3.450 8.28
Block-B
Corridor Walls 2 3.000 3.450 20.70
WC 12 1.500 3.450 62.10
Service Corridor 2 1.200 3.450 8.28
Staff Toilet 2 1.580 3.450 10.90
Store 2 3.045 3.450 21.01
Electrical Room 2 2.780 3.450 19.18
Sample Collection 1 3.115 3.425 10.67
WC 1 3.000 3.425 10.28
Partitions 4 3.000 3.425 41.10
Partitions 2 17.840 3.425 122.20
Deduction
D5 -36 0.900 2.100 -68.04
D6 -35 0.800 2.100 -58.80
ALD1 -8 2.000 2.600 -41.60
FD1 -12 2.000 2.100 -50.40
FD2 -2 1.500 2.100 -6.30
Lintels Deduction
D5 -36 1.360 0.175 -8.57
D6 -35 1.260 0.175 -7.72
ALD1 -8 2.460 0.175 -3.44
FD1 -12 2.460 0.175 -5.17

APMSIDC-PALASA DET-Upper Ground Floor 465 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
FD2 -2 1.960 0.175 -0.69
1357.26
Say 1358.00 Sqm

7 PCC for Steps


Staircase 0.5 88 2.000 0.300 0.150 3.96
Staircase 0.5 22 2.415 0.300 0.150 1.20
Entrance 0.5 5 5.300 0.300 0.150 0.60
5.75
Say 6.00 cum
8 PCC (1:3:6) for Bedblocks
under lintels
W1 2 68 0.300 0.225 0.150 1.38
W2 2 5 0.300 0.225 0.150 0.10
W3 2 1 0.300 0.225 0.150 0.02
MD1 2 1 0.300 0.225 0.150 0.02
ALD1 2 8 0.300 0.225 0.150 0.16
D3 2 9 0.300 0.225 0.150 0.18
D5 2 48 0.300 0.225 0.150 0.97
FD1 2 12 0.300 0.225 0.150 0.24
V5 2 54 0.300 0.225 0.150 1.09
JW 2 16 0.300 0.225 0.150 0.32
D6 2 35 0.300 0.100 0.150 0.32
Hold fasts
W1 4 68 0.230 0.225 0.150 2.11
W2 4 5 0.230 0.225 0.150 0.16
W3 4 1 0.230 0.225 0.150 0.03
MD1 6 1 0.230 0.225 0.150 0.05
ALD1 6 8 0.230 0.225 0.150 0.37
D3 6 9 0.230 0.225 0.150 0.42
D5 6 48 0.230 0.225 0.150 2.24
FD1 6 12 0.230 0.225 0.150 0.56
V5 6 54 0.230 0.225 0.150 2.52
JW 0 16 0.230 0.225 0.150 0.00
D6 6 35 0.230 0.100 0.150 0.72
13.98
Say 14.00 Cum
9 Lintels
W1 68 2.260 0.225 0.175 6.05
W2 5 1.960 0.225 0.175 0.39
W3 1 1.660 0.225 0.175 0.07
ALD1 8 2.460 0.225 0.175 0.77
D3 9 1.360 0.225 0.175 0.48
V5 54 1.060 0.225 0.175 2.25
D5 48 1.360 0.100 0.175 1.14
D6 35 1.260 0.100 0.175 0.77
11.93
Say 12.00 Cum

10 Sunshades
W1 68 2.100 142.80
W2 5 1.800 9.00
W3 1 1.500 1.50
153.30
Say 154.00 Rmt

APMSIDC-PALASA DET-Upper Ground Floor 466 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
11 Sill slabs
W1 68 2.260 0.230 0.050 1.77
W2 5 1.960 0.230 0.050 0.11
W3 1 1.660 0.230 0.050 0.02
1.90
Say 1.90 cum
12 TMT STEEL
Columns upto 3.60 mts levael 213.92 200.000 Kgs/Cum 42784.06
Roof beams 160.69 200.000 Kgs/Cum 32137.52
125mm thick Roof slab 283.84 10.000 Kgs/Sqm 2838.37
150mm thick Roof slab 1651.09 12.000 Kgs/Sqm 19813.05
175mm thick Roof slab 943.51 14.000 Kgs/Sqm 13209.13
175mm thick waist slab 247.20 14.000 Kgs/Sqm 3460.80
114242.930
Say 114.20 MT

13 Mild Steel
Sunshades 153.30 4.000 Kgs/RM 613.20
Platforms & Lofts 33.087 4.000 Kgs/Sqm 132.35
Shelves 9.000 4.000 Kgs/Sqm 36.00
Sillslab 1.899 4.000 Kgs/Sqm 7.60
RBM 1357.3 0.050 Kgs/Sqm 67.86
857.01
Say 0.86 MT

14 External plastering
All round the Building 1 411.000 3.600 1479.60
All round the Open Courtyard 2 49.150 2.230 219.21
Open court yard wall 2 49.150 3.600 353.88
Deductions
W1 -68 1.800 1.800 -220.32
W2 -5 1.500 1.800 -13.50
W3 -1 1.200 1.800 -2.16
V5 -54 0.600 0.500 -16.20
1800.51
Say 1801.00 Sqm

15 Ceiling plastering
Qty Same as Vitrified flooring 900.00
Qty Same as Ceramic flooring 312.00
Qty Same as Granite Slab Flooring 1367.00

Qty Same as Cheqquured tiles Flooring 104.00


2683.00
Say 2683.00 Sqm

16 Internal plastering 12 mm thick


Receiption at Nephrology & Urology 2 15.830 3.475 110.02
Renal Lab 1 15.600 3.475 54.21
Stores at Toilets 2 14.170 3.475 98.48
Electrical Room 1 14.220 3.475 49.41
Class IV Room 1 14.220 3.475 49.41
Uro dynamic Lab 1 15.600 3.475 54.21
Deduct Toilet 1 5.860 3.475 20.36
Uro flowmetry room 1 15.600 3.475 54.21

APMSIDC-PALASA DET-Upper Ground Floor 467 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Urology -OP 1,2,3,4 4 15.600 3.475 216.84
Technician Room 1 15.600 3.475 54.21
Nephrology-OP 1,2,3,4 4 15.600 3.475 216.84
Procedure Room 2 15.600 3.475 108.42
Store at Dept.Seminar Room 1 13.400 3.475 46.57
Dept.Seminar Room 2 26.630 3.475 185.08
Attenders waiting rooms 2 20.720 3.475 144.00
Laboratory & Security 2 12.000 3.475 83.40
House keeping & Floor Administration 2 18.460 3.475 128.30
Dedct Toilet -2 6.460 3.475 -44.90
Server Room 1 21.060 3.475 73.18
Store at Dept.Seminar Room 1 13.930 3.475 48.41
Block-B
Reception & Registration 1 26.550 3.475 92.26
Pharmacy issue counter 1 26.550 3.475 92.26
Security 1 13.400 3.475 46.57
Sample collection 1 15.570 3.475 54.11
Injection Rooms Male & Female 2 12.280 3.475 85.35
Stores at Toilets 2 15.600 3.475 108.42
Class IV Room 1 14.220 3.475 49.41
Electrical Room 1 14.220 3.475 49.41
Stores 2 11.360 3.475 78.95
Dressing Male &Female 2 15.600 3.475 108.42
Plaster room 1 15.600 3.475 54.21
G.Surgery-OP 1,2,3,4 4 15.600 3.475 216.84
Minor OT 1 15.600 3.475 54.21
ECG Room 1 15.600 3.475 54.21
General Medicine-OP 1,2,3,4 4 15.600 3.475 216.84
Stress test 1 15.600 3.475 54.21
Passage in Gents toilet 1 17.580 3.475 61.09
Dirty Utility 1 11.360 3.475 39.48
Staff toilet 1 6.000 3.475 20.85
Entry to Dirty Utility 2 1.315 3.475 9.14
PHC 1 7.000 3.475 24.33
offsets of PHC 1 0.950 3.475 3.30
Service corridor 1 14.520 3.475 50.46
Lobby at wash 1 12.130 3.475 42.15
Passage 2 2.630 3.475 18.28
Passage 1 11.860 3.475 41.21
WCs 4 5.400 3.475 75.06
Ladies toilet
Passage in Ladies toilet 1 17.580 3.475 61.09
Staff toilet 1 6.000 3.475 20.85
Entry to Dirty Utility 2 1.315 3.475 9.14
PHC 1 7.000 3.475 24.33
offsets of PHC 1 0.950 3.475 3.30
Service corridor 1 14.520 3.475 50.46
Lobby at wash 1 12.130 3.475 42.15
Entry to stores 2 1.315 3.475 9.14
Passage 2 3.945 3.475 27.42
WCs 6 5.400 3.475 112.59
Store at class IV 1 11.360 3.475 39.48
Toilet in Uro Dynamic Lab 1 5.400 3.475 18.77
WC & Baths in Attendants Male &
Female 6 5.400 3.475 112.59
Wash area Male & Female 2 5.030 3.475 34.96

APMSIDC-PALASA DET-Upper Ground Floor 468 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Toilet in House keeping 1 6.000 3.475 20.85
Toilet in Floor Admin 1 6.000 3.475 20.85
Block-B
Passage in Gents toilet 1 17.580 3.475 61.09
Dirty Utility 1 11.360 3.475 39.48
Staff toilet 1 6.000 3.475 20.85
Entry to Dirty Utility 2 1.315 3.475 9.14
PHC 1 7.000 3.475 24.33
offsets of PHC 1 0.950 3.475 3.30
Service corridor 1 14.520 3.475 50.46
Lobby at wash 1 12.130 3.475 42.15
Passage 2 2.630 3.475 18.28
Passage 1 11.860 3.475 41.21
WCs 4 5.400 3.475 75.06
Ladies toilet
Passage in Ladies toilet 1 17.580 3.475 61.09
Staff toilet 1 6.000 3.475 20.85
Entry to Dirty Utility 2 1.315 3.475 9.14
PHC 1 7.000 3.475 24.33
offsets of PHC 1 0.950 3.475 3.30
Service corridor 1 14.520 3.475 50.46
Lobby at wash 1 12.130 3.475 42.15
Entry to stores 2 1.315 3.475 9.14
Passage 2 3.945 3.475 27.42
WCs 6 5.400 3.475 112.59
Store at class IV 1 11.360 3.475 39.48
Toilets in sample collection 2 5.890 3.475 40.94
Corridors
Block -A1
From Reception to Pharmacy 1 76.640 3.475 266.32
Waiting hall area 2 43.720 3.475 303.85
corridor Area 4 15.430 3.475 214.48
Store to store 1 60.400 3.475 209.89
Infron of Dump 1 10.740 3.475 37.32
Infront of back side stairecase 1 17.580 3.475 61.09
Block -B
Entrance Foyer 1 59.980 3.475 208.43
From staire case to Reception 1 76.640 3.475 266.32
Waiting hall area 2 43.720 3.475 303.85
corridor Area 4 15.430 3.475 214.48
Store to store 1 60.400 3.475 209.89
Infron of Dump 1 10.740 3.475 37.32
Infront of back side stairecase 1 17.580 3.475 61.09
Ramp & Stairecase
Infront of Ramp 1 26.920 3.475 93.55
Infront of Stairecase 1 15.200 3.475 52.82
Connecting corridor 1 53.020 3.475 184.24
Presserisation 2 10.800 3.475 75.06
All round the staircase 4 15.108 3.475 210.00
All round the staircase 1 15.878 3.475 55.18
All round the Lifts 2 10.800 3.600 77.76
Deductions
ALD1 -8 1.800 2.600 -37.44
D3 -9 1.200 2.100 -22.68
D6 -35 0.800 2.100 -58.80
D5 -48 0.900 2.100 -90.72

APMSIDC-PALASA DET-Upper Ground Floor 469 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
JW -8 1.800 1.800 -25.92
Structural Glazing -2 1.800 3.000 -10.80
Structural Glazing -2 2.400 3.000 -14.40
Ded for Dadooing with glazed tiles for
Toilets -992.16
Ded for Dadooing in wards & corridor -783.75
Deduct Cladding with Granite Slabs -26.00
6066.14
Say 6067.00 Sqm
a 12 mm thick internal plastering
60% of above quantity (internal) 3639.68
Say 3640.00 Sqm
b 20 mm thick Internal plastering
40% of above quantity (external) 2426.46
Say 2426.00 Sqm

17 Flooring
a) Vitrified flooring
BLOCK-A1
Receiption at Nephrology & Urology 2 4.915 3.000 29.49
Renal Lab 1 4.800 3.000 14.40
Stores at Toilets 2 4.085 3.000 24.51
Electrical Room 1 3.995 3.115 12.44
Class IV Room 1 3.995 3.115 12.44
Uro dynamic Lab 1 4.800 3.000 14.40
Deduct Toilet -1 1.315 1.615 -2.12
Uro flowmetry room 1 4.800 3.000 14.40
Urology -OP 1,2,3,4 4 4.800 3.000 57.60
Technician Room 1 4.800 3.000 14.40
Nephrology-OP 1,2,3,4 4 4.800 3.000 57.60
Procedure Room 2 4.800 3.000 28.80
Store at Dept.Seminar Room 1 4.300 2.400 10.32
Dept.Seminar Room 2 4.835 8.480 82.00
Attendants waiting rooms 2 4.315 6.045 52.17
Laboratory & Security 2 3.000 3.000 18.00
House keeping & Floor Administration 2 3.000 6.230 37.38
Dedct Toilet -2 1.315 1.915 -5.04
Server Room 1 4.565 5.965 27.23
Store at Dept.Seminar Room 1 4.565 2.400 10.96
Block-B
Reception & Registration 1 4.680 8.595 40.22
Pharmacy issue counter 1 4.680 8.595 40.22
Security 1 4.300 2.400 10.32
Sample collection 1 4.785 3.000 14.36
Injection Rooms Male & Female 2 3.140 3.000 18.84
Stores at Toilets 2 3.830 3.000 22.98
Class IV Room 1 3.950 3.000 11.85
Electrical Room 1 3.950 3.000 11.85
Stores 2 2.635 3.045 16.05
Dressing Male &Female 2 4.800 3.000 28.80
Plaster room 1 4.800 3.000 14.40
G.Surgery-OP 1,2,3,4 4 4.800 3.000 57.60
Minor OT 1 4.800 3.000 14.40
ECG Room 1 4.800 3.000 14.40
General Medicine-OP 1,2,3,4 4 4.800 3.000 57.60
Stress test 1 4.800 3.000 14.40

APMSIDC-PALASA DET-Upper Ground Floor 470 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
899.68
Say 900.00 Sqm
b) Granite flooring
i Treads
Staircase 4 22 2.000 0.300 52.80
Staircase 1 22 2.415 0.300 15.94
Entrance 1 5 5.315 0.300 7.97
76.71
Say 77.00 Sqm

ii Risers
Staircase 4 24 2.000 0.150 28.80
Staircase 1 24 2.415 0.150 8.69
Entrance 1 6 5.315 0.150 4.78
42.28
Say 43.00 Sqm

iii Polished Granite Slabs Flooring


Staircase Midlanding 4 1 4.230 2.000 33.84
Staircase Midlanding 1 1 5.085 2.630 13.37
Corridors
Block -A1
From Reception to Reception 1 35.320 3.000 105.96
Waiting hall area 2 9.515 12.345 234.93
corridor Area 4 4.600 3.115 57.32
Store to store 1 27.200 3.000 81.60
Infron of Dump 1 3.640 1.730 6.30
Infront of back side stairecase 1 6.390 2.400 15.34
Block -B
Entrance Foyer 1 21.280 8.710 185.35
From staire case to Reception 1 35.320 3.000 105.96
Waiting hall area 2 9.515 12.345 234.93
corridor Area 4 4.600 3.115 57.32
Store to store 1 27.200 3.000 81.60
Infron of Dump 1 3.640 1.730 6.30
Infront of back side stairecase 1 6.390 2.400 15.34
Ramp & Stairecase 0.00
Infront of Ramp 1 10.230 3.230 33.04
Infront of Stairecase 1 5.100 2.500 12.75
Connecting corridor 1 23.510 3.000 70.53
Presserisation 2 2.400 3.000 14.40
1366.15
Say 1367.00 Sqm
d) Non skid ceramic flooring
Block-A1
Passage in Gents toilet 1 6.390 2.400 15.34
Dirty Utility 1 2.635 3.045 8.02
Staff toilet 1 1.200 1.800 2.16
Entry to Dirty Utility 1 1.315 1.130 1.49
PHC 1 2.000 1.500 3.00
Infront of PHC 1 2.750 0.950 2.61
Service corridor 1 6.060 1.200 7.27
Lobby at wash 1 2.950 3.115 9.19
Passage 1 2.630 1.500 3.95
Passage 1 4.730 1.200 5.68
WCs 4 1.200 1.500 7.20

APMSIDC-PALASA DET-Upper Ground Floor 471 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Ladies toilet
Passage in Ladies toilet 1 6.390 2.400 15.34
Dirty Utility 1 2.635 3.045 8.02
Staff toilet 1 1.200 1.800 2.16
Entry to Dirty Utility 1 1.315 1.130 1.49
PHC 1 2.000 1.500 3.00
Infront of PHC 1 2.750 0.950 2.61
Service corridor 1 6.060 1.200 7.27
Lobby at wash 1 2.950 3.115 9.19
Passage 1 2.630 1.500 3.95
Passage 1 4.730 1.200 5.68
WCs 6 1.200 1.500 10.80
Store at class IV 1 2.635 3.045 8.02
Toilet in Uro Dynamic Lab 1 1.200 1.500 1.80
WC & Baths in Attendants Male &
Female 6 1.200 1.500 10.80
Wash area Male & Female 2 1.200 1.315 3.16
Toilet in House keeping 1 1.200 1.800 2.16
Toilet in Floor Admin 1 1.200 1.800 2.16
Block-B
Passage in Gents toilet 1 6.390 2.400 15.34
Dirty Utility 1 2.635 3.045 8.02
Staff toilet 1 1.200 1.800 2.16
Entry to Dirty Utility 1 1.315 1.130 1.49
PHC 1 2.000 1.500 3.00
Infront of PHC 1 2.750 0.950 2.61
Service corridor 1 6.060 1.200 7.27
Lobby at wash 1 2.950 3.115 9.19
Passage 1 2.630 1.500 3.95
Passage 1 4.730 1.200 5.68
WCs 4 1.200 1.500 7.20
Ladies toilet
Passage in Ladies toilet 1 6.390 2.400 15.34
Dirty Utility 1 2.635 3.045 8.02
Staff toilet 1 1.200 1.800 2.16
Entry to Dirty Utility 1 1.315 1.130 1.49
PHC 1 2.000 1.500 3.00
Infront of PHC 1 2.750 0.950 2.61
Service corridor 1 6.060 1.200 7.27
Lobby at wash 1 2.950 3.115 9.19
Passage 1 2.630 1.500 3.95
Passage 1 4.730 1.200 5.68
WCs 6 1.200 1.500 10.80
Store at class IV 1 2.635 3.045 8.02
Toilets in sample collection 2 1.445 1.500 4.34
311.26
Say 312.00 Sqm
d) Cheq. Tiles flooring
Ramp 2 1 18.300 2.400 87.84
Midlanding 1 1 5.100 3.000 15.30
103.14
Say 104.00 Sqm

f) Interlocking Tiles
Entrance Ramp At Portico 2 5.000 2.000 20.00
Portico 1 14.250 6.240 88.92

APMSIDC-PALASA DET-Upper Ground Floor 472 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
108.92
Say 109.00 Sqm
18 High polished granite platforms
Qty same as Platforms 24.61
24.61
Say 25.00 Sqm

19 High Polished granite stone for Sill


slabs
W1 68 2.260 0.230 35.35
W2 5 1.960 0.230 2.25
W3 1 1.660 0.230 0.38
37.98
Say 38.00 Sqm
20 Skirting
a) Skirting with Vitrified
Receiption at Nephrology & Urology 2 15.830 31.66
Renal Lab 1 15.600 15.60
Stores at Toilets 2 14.170 28.34
Electrical Room 1 14.220 14.22
Class IV Room 1 14.220 14.22
Uro dynamic Lab 1 15.600 15.60
Deduct Toilet 1 5.860 5.86
Uro flowmetry room 1 15.600 15.60
Urology -OP 1,2,3,4 4 15.600 62.40
Technician Room 1 15.600 15.60
Nephrology-OP 1,2,3,4 4 15.600 62.40
Procedure Room 2 15.600 31.20
Store at Dept.Seminar Room 1 13.400 13.40
Dept.Seminar Room 2 26.630 53.26
Attenders waiting rooms 2 20.720 41.44
Laboratory & Security 2 12.000 24.00
House keeping & Floor Administration 2 18.460 36.92
Dedct Toilet -2 6.460 -12.92
Server Room 1 21.060 21.06
Store at Dept.Seminar Room 1 13.930 13.93
Block-B
Reception & Registration 1 26.550 26.55
Pharmacy issue counter 1 26.550 26.55
Security 1 13.400 13.40
Sample collection 1 15.570 15.57
Injection Rooms Male & Female 2 12.280 24.56
Stores at Toilets 2 15.600 31.20
Class IV Room 1 14.220 14.22
Electrical Room 1 14.220 14.22
Stores 2 11.360 22.72
Dressing Male &Female 2 15.600 31.20
Plaster room 1 15.600 15.60
G.Surgery-OP 1,2,3,4 4 15.600 62.40
Minor OT 1 15.600 15.60
ECG Room 1 15.600 15.60
General Medicine-OP 1,2,3,4 4 15.600 62.40
Stress test 1 15.600 15.60
911.18
Say 912.00 Rmt
c) Skirting with Granite

APMSIDC-PALASA DET-Upper Ground Floor 473 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
All round the staircase 5 15.568 77.84
77.84
Say 78.00 Rmt

21 Dadooing with Ceramic Tiles


Block-A1
Passage in Gents toilet 1 17.580 2.100 36.92
Dirty Utility 1 11.360 2.100 23.86
Staff toilet 1 6.000 2.100 12.60
Entry to Dirty Utility 2 1.315 2.100 5.52
PHC 1 7.000 2.100 14.70
offsets of PHC 1 0.950 2.100 2.00
Service corridor 1 14.520 2.100 30.49
Lobby at wash 1 12.130 2.100 25.47
Passage 2 2.630 2.100 11.05
Passage 1 11.860 2.100 24.91
WCs 4 5.400 2.100 45.36
Ladies toilet
Passage in Ladies toilet 1 17.580 2.100 36.92
Staff toilet 1 6.000 2.100 12.60
Entry to Dirty Utility 2 1.315 2.100 5.52
PHC 1 7.000 2.100 14.70
offsets of PHC 1 0.950 2.100 2.00
Service corridor 1 14.520 2.100 30.49
Lobby at wash 1 12.130 2.100 25.47
Entry to stores 2 1.315 2.100 5.52
Passage 2 3.945 2.100 16.57
WCs 6 5.400 2.100 68.04
Store at class IV 1 11.360 2.100 23.86
Toilet in Uro Dynamic Lab 1 5.400 2.100 11.34
WC & Baths in Attendants Male &
Female 6 5.400 2.100 68.04
Wash area Male & Female 2 5.030 2.100 21.13
Toilet in House keeping 1 6.000 2.100 12.60
Toilet in Floor Admin 1 6.000 2.100 12.60
Block-B 0.000 2.100 0.00
Passage in Gents toilet 1 17.580 2.100 36.92
Dirty Utility 1 11.360 2.100 23.86
Staff toilet 1 6.000 2.100 12.60
Entry to Dirty Utility 2 1.315 2.100 5.52
PHC 1 7.000 2.100 14.70
offsets of PHC 1 0.950 2.100 2.00
Service corridor 1 14.520 2.100 30.49
Lobby at wash 1 12.130 2.100 25.47
Passage 2 2.630 2.100 11.05
Passage 1 11.860 2.100 24.91
WCs 4 5.400 2.100 45.36
Ladies toilet
Passage in Ladies toilet 1 17.580 2.100 36.92
Staff toilet 1 6.000 2.100 12.60
Entry to Dirty Utility 2 1.315 2.100 5.52
PHC 1 7.000 2.100 14.70
offsets of PHC 1 0.950 2.100 2.00
Service corridor 1 14.520 2.100 30.49
Lobby at wash 1 12.130 2.100 25.47
Entry to stores 2 1.315 2.100 5.52

APMSIDC-PALASA DET-Upper Ground Floor 474 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Passage 2 3.945 2.100 16.57
WCs 6 5.400 2.100 68.04
Store at class IV 1 11.360 2.100 23.86
Toilets in sample collection 2 5.890 2.100 24.74
Deductions
D5 -4 0.900 2.100 -7.56
D6 -35 0.800 2.100 -58.80
ALD1 -4 1.800 2.100 -15.12
JW -8 1.800 1.800 -25.92
992.16
Say 993.00 Sqm
22 Dadooing in wards & corridor
Block -A1
From staire case to Reception 1 76.640 1.500 114.96
Waiting hall area 2 43.720 1.500 131.16
corridor Area 4 3.115 1.500 18.69
Store to store 1 60.400 1.500 90.60
Infron of Dump 2 1.730 1.500 5.19
Infront of back side stairecase 1 11.100 1.500 16.65
Block -B
sides of Receiption and Pharmacy 2 8.710 1.500 26.13
corridor From Reception to Pharmacy 1 76.640 1.500 114.96
Waiting hall area 2 43.720 1.500 131.16
corridor Area 4 3.115 1.500 18.69
Store to store 1 60.400 1.500 90.60
Infron of Dump 2 1.730 1.500 5.19
Infront of back side stairecase 1 11.100 1.500 16.65
Ramp & Stairecase 1.500 0.00
off sets at Ramp 2 3.230 1.500 9.69
Infront of Stairecase 1 15.200 1.500 22.80
Connecting corridor 1 53.020 1.500 79.53
Presserisation 2 10.800 1.500 32.40
Deductions
ALD1 -8 1.800 1.500 -21.60
FD1 -12 2.000 1.500 -36.00
D3 -9 1.200 1.500 -16.20
D5 -42 0.900 1.500 -56.70
JW -4 1.800 0.300 -2.16
W1 -16 1.800 0.300 -8.64
783.75
Say 784.00 Sqm

23 Cladding with Granite


Entrance 1 14.250 3.450 49.16
Lifts 2 2.400 3.450 16.56
Deductions
MD -1 3.000 2.600 -7.80
W -2 2.400 2.600 -12.48
Strl.Glazing -2 2.400 3.000 -14.40
Lift opening -2 1.200 2.100 -5.04
26.00
Say 27.00 Sqm

24 Cinder Filling 4 6.880 4.730 0.300 39.05


Say 40.00 cum

APMSIDC-PALASA DET-Upper Ground Floor 475 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
25 Impervious coat 4 23.220 0.300 27.86
Say 28.00 Sqm

26 Whiting for ceiling


Same as ceiling plastering 2683.00
2683.00
Say 2683.00 Sqm

27 Wall putty
Same as internal plastering 6067.00
6067.00
Say 6067.00 Sqm

28 Plastic Emulsion Paint for interior


faces of walls
Same as internal plastering 6067.00
6067.00
Say 6067.00 Sqm

29
Emulsion paint for external plastering
Same external plastering @ 60% 1080.60
1080.60
Say 1081.00 Sqm

30 Texture Paint for Exterrnal Walls

Same as of external plastering @ 40% 720.40


720.40
Say 721.00 Sqm

30 Painting to wood woork


MD1 2.25 1 6.100 3.000 41.18
41.18
Say 42.00 Sqm

31 Doors
MD1 1 6.100 3.000 18.30
18.30
Say 18.30 Sqm

D2 18 1.500 2.600 70.20


70.20
Say 70.20 Sqm

D3 9 1.200 2.600 28.08


28.08
Say 29.00 Sqm

D4 26 1.000 2.600 67.60


67.60
Say 67.60 Sqm

D5 28 0.900 2.100 52.92


52.92
Say 52.92 Sqm

APMSIDC-PALASA DET-Upper Ground Floor 476 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY

D6 (0.8 X 2.10) - Frame 43 5.000 215.00


215.00
Say 215.00 RM

D6 43 0.800 2.100 72.24


72.24
Say 72.24 Sqm

ALD1 20 2.000 2.600 104.00


104.00
Say 104.00 Sqm
32 Windows
W1 82 1.800 1.800 265.68

W2 17 1.500 1.800 45.90

W3 3 1.200 1.800 6.48

Total Quantity 318.06 Sqm

33 Ventilators
V5 66 0.600 0.500 19.80
19.80
Say 19.80 Sqm

34
MS Grill for Windows @ 15 Kg/Sqm
W1 68 1.800 1.800 220.32
W2 5 1.500 1.800 13.50
W3 1 1.200 1.800 2.16
staire case at Ramp 2 1.856 3.000 11.14
At Entrance 2 2.400 3.000 14.40
V5 54 0.600 0.500 16.20
277.72 Sqm
Say 278.00 Sqm
4170.00 Kgs

35 Painting to iron Work


Quantity Same as MS Grill 278.00
Say 278.00 Sqm

36 Structural Glazing
staire case at Ramp 2 1.856 3.000 11.14
At Entrance 2 2.400 3.000 14.40
At Double height 2 2.400 3.000 14.40
At Double height 1 5.165 3.000 15.50
55.43
Say 56.00 Sqm
37 Structural Glazing with top hung
shutters
20% of above quantity 11.09
11.09
Say 12.00 Sqm
38 Jali wall

APMSIDC-PALASA DET-Upper Ground Floor 477 of 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Jali wall 24 1.800 1.800 77.76
77.76
Say 78.00 Sqm
39 Railing
Staircase
Staircase 2 5 3.500 0.900 31.50
Duct 2 1 6.000 0.900 10.80
at Double height 1 1 15.830 0.900 14.25
56.55
Say 57.00 Sqm
b cupboards
Injection room(male) 1 1 3.000 2.100 6.30
Injection room(female) 1 1 3.000 2.100 6.30
12.60
Say 13.00 Sqm

40 Grip bar
Staircase 5 14.830 74.15
Ramp 1 47.100 47.10
121.25
Say 122.00 Rmt
38 RCM Drop
Entrance Portico 1 33.730 0.450 15.18
Duct 2 1 6.000 0.450 5.40
20.58
Say 21.00 Sqm

41 False ceiling
Qty Same as Vitrified flooring 899.68
899.68
Say 900.00 Sqm

42 Mastic pad
Roof beams
Horizontal 2 3.460 0.450 3.11
3.11
Say 4.00 Sqm

43 Expansion joint treatment


Roof beams
Horizontal 2 3.460 6.92
6.92
Say 7.00 Rmt

44 Aluminium sheet
Roof beams
Horizontal 2 3.460 6.92
6.92
Say 7.00 Rmt

45 Impervious coat for terrace


Portico 1 14.830 9.980 148.00
148.00
Say 149.00 Sqm

APMSIDC-PALASA DET-Upper Ground Floor 478 of 1048


#REF!

DETAILED ESTIMATE - FIRST FLOOR


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
1 Columns P.B Top to Roof slab
bottom
Block-A & Ramp Block
C1 13 0.380 0.600 3.475 10.30
C2 20 0.380 0.600 3.475 15.85
C3 12 0.380 0.600 3.475 9.51
C4 5 0.450 0.750 3.475 5.86
C5 10 0.460 0.600 3.475 9.59
C6 6 0.460 0.600 3.475 5.75
C7 4 0.460 0.600 3.475 3.84
C8 2 0.600 0.600 3.475 2.50
C9 2 0.600 0.600 3.475 2.50
C10 2 0.600 0.600 3.475 2.50
C11 7 0.600 0.750 3.475 10.95
C12 19 0.600 0.750 3.475 29.71
C13 11 0.600 0.750 3.475 17.20
Columns P.B Top to Roof slab
bottom
Block-(-B)
C4 5 0.450 0.750 3.450 5.82
C5 8 0.460 0.600 3.450 7.62
C6 6 0.460 0.600 3.450 5.71
C7 4 0.460 0.600 3.450 3.81
C8 2 0.600 0.600 3.450 2.48
C9 2 0.600 0.600 3.450 2.48
C10 2 0.600 0.600 3.450 2.48
C11 7 0.600 0.750 3.450 10.87
C12 19 0.600 0.750 3.450 29.50
C13 11 0.600 0.750 3.450 17.08
213.92
Say 214.00 Cum

2 Roof Beams
Horizontal
Block-A
T1-T4 1 7.120 0.300 0.300 0.64
Deduction of Columns -2 0.750 0.300 0.300 -0.14
T4-T5 1 2.400 0.380 0.275 0.25
T5-T7 1 2.800 0.300 0.300 0.25
T7-T10 2 7.700 0.230 0.450 1.59
T10-T16 2 13.810 0.300 0.300 2.49
Deduction of Columns -8 0.750 0.300 0.300 -0.54
Secondary Beam 2 9.520 0.300 0.300 1.71
Deduction of Columns -2 0.230 0.300 0.300 -0.04
Q1-Q2 1 3.310 0.300 0.300 0.30
Q2-Q4 1 2.310 0.380 0.300 0.26
Q4-Q5 1 2.400 0.380 0.275 0.25
Q5-Q10 1 11.250 0.230 0.450 1.16
Q10-Q12 1 2.800 0.300 0.300 0.25
Q12-Q13 1 2.400 0.380 0.275 0.25
Q13-Q16 1 7.120 0.300 0.300 0.64

APMSDIC-PALASA DET-FIRST FLOOR 479 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
O1-O5 4 9.520 0.450 0.575 9.85
O5-O12 2 16.290 0.300 0.275 2.69
Deduction of Columns -8 0.750 0.300 0.275 -0.50
M5-M8 4 4.170 0.300 0.275 1.38
O12-O16 4 9.520 0.450 0.575 9.85
G1-G16 2 35.320 0.300 0.300 6.36
Deduction of Columns -4 0.450 0.300 0.300 -0.16
Deduction of Columns -8 0.600 0.300 0.300 -0.43
E1-E3 1 4.300 0.300 0.400 0.52
Cantilever Beams 2 1.000 0.300 0.300 0.18
Ramp Block
R19-R21 5 5.100 0.230 0.355 2.08
Deduction of Columns -4 0.380 0.230 0.355 -0.12
K17-K19 4 5.860 0.230 0.275 1.48
Deduction of Columns -8 0.380 0.230 0.275 -0.19
I17-I23 1 16.820 0.230 0.275 1.06
Deduction of Columns -5 0.380 0.230 0.275 -0.12
H17-H18 2 5.080 0.230 0.300 0.70
Deduction of Columns -4 0.380 0.230 0.300 -0.10
H18-H22 1 10.360 0.230 0.450 1.07
Deduction of Columns -2 0.230 0.230 0.450 -0.05
G17-G19 2 7.480 0.230 0.300 1.03
Deduction of Columns -4 0.380 0.230 0.300 -0.10
G19-G21 3 4.800 0.230 0.380 1.26
F18-F19 2 2.180 0.230 0.300 0.30
Block-(-B)
T39-T33 3 13.060 0.300 0.300 3.53
Deduction of Columns -9 0.750 0.300 0.300 -0.61
T33-T30 2 7.700 0.230 0.450 1.59
Secondary Beam 2 9.520 0.300 0.300 1.71
Deduction of Columns -2 0.230 0.300 0.300 -0.04
Q1-Q38 1 3.310 0.300 0.300 0.30
Q38-Q36 1 2.310 0.380 0.300 0.26
Q36-Q35 1 2.400 0.380 0.275 0.25
Q35-Q30 1 11.250 0.230 0.450 1.16
O39-O35 4 9.520 0.450 0.575 9.85
O35-O28 4 16.290 0.300 0.275 5.38
Deduction of Columns -16 0.750 0.300 0.275 -0.99
O28-O24 4 9.520 0.450 0.575 9.85
G39-G24 2 35.320 0.300 0.300 6.36
Deduction of Columns -4 0.450 0.300 0.300 -0.16
Deduction of Columns -8 0.600 0.300 0.300 -0.43
E39-E38 1 4.300 0.300 0.400 0.52
Cantilever Beams 2 1.000 0.300 0.300 0.18
Vertical
Block-A
B1-E1 2 1.360 0.300 0.300 0.24
E1-G1 2 5.330 0.300 0.450 1.44
G1-H1 8 3.000 0.300 0.300 2.16
H1-O1 6 19.040 0.300 0.425 14.57
Deduction of Columns -24 0.600 0.300 0.425 -1.84
O1-Q1 2 3.000 0.230 0.300 0.41
O2-Q2 4 3.000 0.300 0.300 1.08
Q1-T1 6 5.720 0.230 0.450 3.55
Q5-T5 4 5.720 0.230 0.475 2.50

APMSDIC-PALASA DET-FIRST FLOOR 480 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Deduction of Columns -1 0.600 0.230 0.475 -0.07
Secondary Beam 1 1.400 0.300 0.325 0.14
Secondary Beam 1 4.330 0.300 0.325 0.42
B5-G5 4 8.940 0.380 0.475 6.45
Deduction of Columns -8 0.750 0.380 0.475 -1.08
Ramp Block
D17-G17 2 5.860 0.230 0.450 1.21
G17-H17 4 3.000 0.230 0.300 0.83
H17-J17 2 5.750 0.230 0.450 1.19
J17-K17 2 2.560 0.230 0.300 0.35
D18-I18 2 12.920 0.230 0.300 1.78
Deduction of Columns -8 0.750 0.230 0.300 -0.41
I18-K18 2 6.050 0.230 0.380 1.06
C19-G19 2 8.640 0.230 0.300 1.19
Deduction of Columns -8 0.750 0.230 0.300 -0.41
G19-I19 2 5.860 0.230 0.450 1.21
I19-J19 3 2.890 0.230 0.275 0.55
J19-L19 3 4.930 0.230 0.425 1.45
L19-N19 3 3.490 0.230 0.355 0.85
N19-P19 3 3.850 0.230 0.355 0.94
P19-R19 2 2.760 0.230 0.275 0.35
Block-B
B39-E39 2 1.360 0.300 0.300 0.24
E39-G39 2 5.330 0.300 0.450 1.44
G39-H39 8 3.000 0.300 0.300 2.16
H39-O39 6 19.040 0.300 0.425 14.57
Deduction of Columns -24 0.600 0.300 0.425 -1.84
O39-Q39 6 3.000 0.230 0.300 1.24
Q39-T39 6 5.720 0.230 0.450 3.55
Q35-T35 4 5.720 0.230 0.475 2.50
Deduction of Columns -1 0.600 0.230 0.475 -0.07
Secondary Beam 1 1.400 0.300 0.325 0.14
Secondary Beam 1 4.330 0.300 0.325 0.42
B35-G35 6 8.940 0.380 0.475 9.68
Deduction of Columns -10 0.750 0.380 0.475 -1.35
Deduction of Columns -2 0.600 0.380 0.475 -0.22
160.69
Say 161.00 Cum

3 Roof slab
iii) Roof Slab 175mm thick
H1-H5 x H1-O1 2 2 9.980 19.040 760.08
H31-H32 x H31-O31 1 1 6.460 19.040 123.00
B31-B32 x B31-G31 1 1 6.760 8.940 60.43
943.51
Say 944.00 Sqm
i) Roof Slab 150mm thick
Block-(A) 1 40.600 35.780 1452.67
Block-(B) 1 40.600 35.780 1452.67
Ded Of Staircase -2 5.780 4.300 -49.71
Ded Of Staircase -2 5.170 4.300 -44.46
Ded Of Duct -2 6.000 18.440 -221.28
Ded Of Dumb Waiter -2 1.500 1.200 -3.60
Deduction of 175mm Thick Slab -943.51
1642.78

APMSDIC-PALASA DET-FIRST FLOOR 481 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Say 1643.00 Sqm

ii) Roof Slab 125mm thick


Ramp Block 1 432.775 432.78
Ded Of Staircase -1 5.830 5.100 -29.73
Ded Of Lift -2 2.400 3.000 -14.40
Deduction of Ramp -1 20.550 5.100 -104.81
283.84
Say 284.00 Sqm

v) Waist slab (175mm thick)


Staircase (Flight -1& Flight-2) 5 2 3.600 2.000 72.00
Mid landing 5 1 4.460 2.000 44.60
Ramp 1 2 21.500 2.000 86.00
Mid landing 5 1 4.460 2.000 44.60
247.20
Say 248.00 Sqm

4 RCC M20 grade mix


a Platforms
Hand wash in toilet 4 1 3.000 0.600 7.20
Hand wash in toilet 2 1 1.200 0.600 1.44
Dirty Utility 2 1 3.000 0.600 3.60
Store 2 1 3.000 0.600 3.60
Reception 1 1 4.680 0.600 2.81
Lab 1 1 3.000 0.600 1.80
Pantry 1 2 4.800 0.600 5.76
26.21
Say 27.00 Sqm
b Loft
Reception 1 1 4.680 0.450 2.11
Laboratory 1 1 3.000 0.600 1.80
House Keeping 1 1 6.230 0.600 3.74
Class IV 2 1 3.995 0.450 3.60
11.24
Say 12.00 Sqm

c Racks
Reception 1 2 2.000 0.450 1.80
Stores 2 1 2.500 0.450 2.25
Dialyzer Storage 1 1 2.500 0.450 1.13
Laboratory 1 1 2.000 0.450 0.90
Pay Rooms 1 9 2.000 0.450 8.10
Pantry 2 1 2.500 0.450 2.25
16.43
Say 17.00 Sqm
5 230mm thick brick masonary
Horizontal
Block A2
Toilet Block to Dirty Utility 2 13.810 0.225 3.150 19.58
Deduction of columns -8 0.750 0.225 3.000 -4.05
Staircase 2 7.700 0.225 3.000 10.40
Toilet Block to Store 2 13.810 0.225 3.150 19.58
Deduction of columns -8 0.750 0.225 3.000 -4.05
Passage Beside Toilet Block 2 6.400 0.225 3.450 9.94

APMSDIC-PALASA DET-FIRST FLOOR 482 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Deduction of columns -2 0.750 0.225 3.000 -1.01
Dialysis 4 9.510 0.225 2.850 24.39
Deduction of columns -2 0.750 0.225 2.850 -0.96
Dialysis 4 5.140 0.225 3.150 14.57
Deduction of columns -4 0.750 0.225 3.150 -2.13
RO Plant 1 4.680 0.225 3.150 3.32
Deduction of columns -1 0.450 0.225 3.150 -0.32
Staircase 1 4.300 0.225 3.150 3.05
Staircase to RO Plant 1 35.320 0.225 3.150 25.03
Deduction of columns -6 0.600 0.225 3.150 -2.55
Dumb waiter 1 1.200 0.225 3.000 0.81
Ramp Block
Staircase to Attached Toilet 2 6.090 0.225 3.175 8.70
Deduction of columns -6 0.380 0.225 3.175 -1.63
Staircase 2 5.100 0.225 3.095 7.10
House Keeping 2 3.460 0.225 3.175 4.94
Deduction of columns -4 0.380 0.225 3.175 -1.09
Lift 2 2.630 0.225 3.175 3.76
Deduction of columns -2 0.380 0.225 3.175 -0.54
Between Open to Sky 4 3.000 0.225 3.175 8.57
Security 2 3.460 0.225 3.175 4.94
Deduction of columns -4 0.380 0.225 3.175 -1.09
Attandent waiting 4 6.090 0.225 3.175 17.40
Deduction of columns -8 0.380 0.225 3.175 -2.17
Ramp 1 5.100 0.225 3.095 3.55
Block B
Service Corridor to Store 1 13.810 0.230 3.150 10.01
Deduction of columns -4 0.750 0.230 3.150 -2.17
Staircase 1 7.700 0.230 3.000 5.31
Dirty Utility To Service Corridor 1 13.810 0.230 3.150 10.01
Deduction of columns -4 0.750 0.230 3.150 -2.17
Toilet 2 6.060 0.230 3.450 9.62
Toilet 2 7.115 0.230 3.150 10.31
Deduction of columns -4 0.750 0.230 3.150 -2.17
Electrical Room 1 2.820 0.230 3.150 2.04
Staircase 1 5.300 0.230 3.000 3.66
Water To ClassIV 1 4.980 0.230 3.150 3.61
Ward 4 7.115 0.230 3.000 19.64
Clean Linen 4 3.645 0.230 3.150 10.56
Room 1 4.300 0.230 3.150 3.12
Pay Room-1 to Room 1 35.320 0.230 3.150 25.59
Deduction of columns -6 0.600 0.230 3.150 -2.61
Vertical
Block A2
Change Room to Toilet Block 1 40.600 0.225 3.150 28.78
Deduction of columns -5 0.750 0.225 3.150 -2.66
Deduction of columns -12 0.450 0.225 3.150 -3.83
Change Room to Staircase 1 8.940 0.225 3.150 6.34
Deduction of columns -3 0.750 0.225 3.150 -1.59
Chemical Mixing 2 6.460 0.225 3.000 8.72
Deduction of columns -2 0.750 0.225 3.000 -1.01
RO Plant 1 2.600 0.225 3.000 1.76
Deduction of columns -1 0.750 0.225 3.000 -0.51
Open court yard walls 2 19.040 0.225 3.000 25.70
Deduction of columns -8 0.450 0.225 3.000 -2.43

APMSDIC-PALASA DET-FIRST FLOOR 483 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Dumb waiter to Staircase 2 6.640 0.225 3.000 8.96
Deduction of columns -4 0.450 0.225 3.000 -1.22
Toilet Block 2 6.640 0.225 3.000 8.96
Deduction of columns -4 0.450 0.225 3.000 -1.22
Dumb waiter 2 1.730 0.225 3.000 2.34
AHU 2 3.000 0.225 3.150 4.25
Ramp Block
House Keeping 2 6.640 0.225 3.095 9.25
Deduction of columns -2 0.450 0.225 3.095 -0.63
House Keeping 2 6.640 0.225 3.175 9.49
Deduction of columns -4 0.450 0.225 3.175 -1.29
Staircase side walls 2 8.640 0.225 3.175 12.34
Deduction of columns -6 0.600 0.225 3.175 -2.57
Security 2 3.460 0.225 3.175 4.94
Deduction of columns -4 0.600 0.225 3.175 -1.71
Attandent waiting to Security 2 9.510 0.225 3.175 13.59
Deduction of columns -4 0.750 0.225 3.175 -2.14
Attandent waiting 2 6.510 0.225 3.175 9.30
Deduction of columns -2 0.750 0.225 3.175 -1.07
Ramp walls 2 14.510 0.225 3.175 20.73
Deduction of columns -8 0.600 0.225 3.175 -3.43
Block B
Pay Room-1 1 7.410 0.225 3.000 5.00
Room To Staircase 2 8.940 0.225 3.150 12.67
Deduction of columns -16 0.750 0.225 3.150 -8.51
Lobby 1 3.000 0.225 3.150 2.13
Ward To Ward 4 19.035 0.225 3.000 51.39
Deduction of columns -16 0.600 0.225 3.000 -6.48
Deduction of columns -12 0.450 0.225 3.150 -3.83
AHU Room 4 3.000 0.225 3.150 8.51
Toilets 2 5.720 0.225 3.000 7.72
Toilets 2 3.010 0.225 3.450 4.67
Electrical To Store 2 5.420 0.225 3.000 7.32
Water 2 1.730 0.225 3.450 2.69
Deductions
W1 -33 1.800 0.225 1.800 -24.06
W2 -78 1.500 0.225 1.800 -47.39
W3 -10 1.200 0.225 1.800 -4.86
W4 -5 0.900 0.225 1.800 -1.82
V5 -54 0.600 0.225 0.500 -3.65
JW -24 1.800 0.225 1.800 -17.50
D3 -7 1.200 0.225 2.600 -4.91
D5 -17 0.900 0.225 2.100 -7.23
FD-1 -6 2.000 0.225 2.100 -5.67
FD-2 -2 1.500 0.225 2.100 -1.42
Strucural Glazing
SG -2 1.800 0.225 2.100 -1.70
Lintels
W1 -33 2.260 0.225 0.175 -2.94
W2 -78 1.960 0.225 0.175 -6.02
W3 -10 1.660 0.225 0.175 -0.65
W3 -5 1.360 0.225 0.175 -0.27
V5 -54 1.060 0.225 0.175 -2.25
JW -24 2.260 0.225 0.175 -2.14
D3 -7 1.660 0.225 0.175 -0.46

APMSDIC-PALASA DET-FIRST FLOOR 484 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
D5 -17 1.360 0.225 0.175 -0.91
FD-1 -6 2.460 0.225 0.175 -0.58
FD-2 -2 1.960 0.225 0.175 -0.15
367.25
Say 368.00 Cum
6 115 mm thick Brick masonry
walls
Horizontal
Block A1
Electrical Room 2 3.995 3.475 27.77
Staff Toilet 2 1.200 3.475 8.34
Toilet block 2 3.050 3.475 21.20
WC to Wc 4 3.830 2.100 32.17
Dialysis 8 6.010 1.500 72.12
Duty nurses to RO Plant 1 26.110 3.475 90.73
Ramp Block
Attendents Attached Toilets 6 1.315 3.450 27.22
House Keeping Attached Toilets 2 1.915 3.450 13.21
Block B
WC To PHC 2 6.885 3.450 47.51
Bath 2 3.945 3.450 27.22
Staff Toilet 2 1.315 3.450 9.07
Electrical Room 2 3.950 3.450 27.26
Corridor Walls 7 2.400 3.450 57.96
Duct Walls 2 6.000 1.000 12.00
Clean Linen 4 4.800 3.450 66.24
Duty Doctor 6 4.500 3.425 92.48
Attached Toilet 4 1.200 3.425 16.44
Partition Walls 4 2.500 2.100 21.00
Partition Walls 4 4.165 2.100 34.99
Pay Room-1 To 9 1 30.790 3.450 106.23
Attached Toilet 9 1.915 3.450 59.46
Vertical
Block A1
Electrical Room 2 3.530 3.000 21.18
Deduction of columns -2 0.380 3.000 -2.28
Staff Toilet 2 2.140 3.475 14.87
Deduction of columns -2 0.380 3.475 -2.64
Dirty Utility 2 3.045 3.475 21.16
PHC toilet 2 1.500 3.475 10.43
Bath 2 1.850 3.000 11.10
Deduction of columns -2 0.380 3.000 -2.28
WC 8 1.500 2.100 25.20
Change Room 1 2.400 3.475 8.34
Duty Doctore Room 4 6.120 3.475 85.07
Attached Toilet 1 2.815 3.475 9.78
Central Block
Attendents Attached Toilets 2 6.045 3.475 42.01
House Keeping Attached Toilets 2 1.200 3.475 8.34
Block B
Pay Rooms 8 6.500 3.450 179.40
Attached Toilet 9 2.065 3.450 64.12
Corridor Walls 2 3.000 3.150 18.90
Duty Nurse 2 6.115 3.425 41.89
Attached Toilet -4 1.500 3.425 -20.55

APMSDIC-PALASA DET-FIRST FLOOR 485 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Pantry 4 2.145 3.000 25.74
Partition Walls 16 2.250 2.100 75.60
Toilet block 12 1.500 3.450 62.10
Service Corridor 2 1.200 3.450 8.28
Staff Toilet 2 1.695 3.450 11.70
Electrical Room 2 2.895 3.450 19.98
Store 2 3.045 3.450 21.01
Deductions
D5 -23 0.900 2.100 -43.47
D6 -60 0.800 2.100 -100.80
ALD-1 -8 2.000 2.600 -41.60
FD1 -6 2.000 2.100 -25.20
Lintels
D5 -23 1.360 0.175 -5.47
D6 -60 1.260 0.175 -13.23
ALD-1 -8 2.460 0.175 -3.44
FD1 -6 2.460 0.175 -2.58
1393.24
Say 1394.00 Sqm

7 PCC for Steps


Staircase 0.5 44 2.000 0.300 0.150 1.98
Staircase 0.5 44 2.000 0.300 0.150 1.98
Staircase 0.5 22 2.400 0.300 0.150 1.19
5.15
Say 6.00 cum
8 PCC (1:3:6) for Bedblocks
under lintels
W1 2 33 0.300 0.225 0.150 0.67
W2 2 78 0.300 0.225 0.150 1.58
W3 2 10 0.300 0.225 0.150 0.20
W4 2 5 0.300 0.225 0.150 0.10
V5 2 76 0.300 0.225 0.150 1.54
JW 2 24 0.300 0.225 0.150 0.49
D3 2 7 0.300 0.225 0.150 0.14
D5 2 17 0.300 0.225 0.150 0.34
FD-1 2 6 0.300 0.225 0.150 0.12
FD-2 2 2 0.300 0.225 0.150 0.04
FD-1 2 6 0.300 0.115 0.150 0.06
D5 2 40 0.300 0.115 0.150 0.41
D6 2 60 0.300 0.115 0.150 0.62
ALD-1 2 8 0.300 0.115 0.150 0.08
Hold fasts
W1 4 33 0.230 0.225 0.150 1.02
W2 4 78 0.230 0.225 0.150 2.42
W3 4 10 0.230 0.225 0.150 0.31
W4 4 5 0.230 0.225 0.150 0.16
V5 4 76 0.230 0.225 0.150 2.36
JW 4 24 0.230 0.225 0.150 0.75
D3 6 7 0.230 0.225 0.150 0.33
D5 6 17 0.230 0.225 0.150 0.79
FD-1 6 6 0.230 0.225 0.150 0.28
FD-2 6 2 0.230 0.225 0.150 0.09
FD-1 6 6 0.230 0.115 0.150 0.14
D5 6 40 0.230 0.115 0.150 0.95

APMSDIC-PALASA DET-FIRST FLOOR 486 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
D6 6 60 0.230 0.115 0.150 1.43
ALD-1 6 8 0.230 0.115 0.150 0.19
17.63
Say 18.00 Cum

9 Lintels
W1 33 2.260 0.225 0.175 2.94
W2 78 1.960 0.225 0.175 6.02
W3 10 1.660 0.225 0.175 0.65
W4 5 1.360 0.225 0.175 0.27
V5 76 1.060 0.225 0.175 3.17
JW 24 2.260 0.225 0.175 2.14
D3 7 1.660 0.225 0.175 0.46
D5 40 1.260 0.225 0.175 1.98
D6 60 1.060 0.115 0.175 1.28
FD-1 12 2.460 0.225 0.175 1.16
FD-2 2 1.960 0.225 0.175 0.15
Strucural Glazing
SG 2 2.260 0.225 0.175 0.18
ALD-1 8 2.460 0.115 0.175 0.40
20.80
Say 21.00 Cum

10 Sunshades
W1 33 2.100 69.30
W2 78 1.800 140.40
W3 10 1.500 15.00
W4 5 1.200 6.00
230.70
Say 231.00 Rmt

11 Sill slabs
W1 33 2.260 0.230 0.050 0.86
W2 78 1.960 0.230 0.050 1.76
W3 10 1.660 0.230 0.050 0.19
W4 5 1.360 0.230 0.050 0.08
V5 76 1.060 0.230 0.050 0.93
3.81
Say 3.90 cum

12 TMT STEEL
Columns upto 3.60 mts levael 213.92 200.000 Kgs/Cum 42784.06
Roof beams 160.69 200.000 Kgs/Cum 32137.52
125mm thick Roof slab 283.84 10.000 Kgs/Sqm 2838.37
150mm thick Roof slab 1642.8 12.000 Kgs/Sqm 19713.32
175mm thick Roof slab 943.5 14.000 Kgs/Sqm 13209.13
175mm thick waist slab 247.20 14.000 Kgs/Sqm 3460.80
Lintels 20.80 80.000 Kgs/Cum 1663.85
115807.04
Say 115.80 MT

13 Mild Steel
Sunshades 230.70 4.000 Kgs/RM 922.80
Platforms & Lofts 39.000 4.000 Kgs/Sqm 156.00
Shelves 16.425 4.000 Kgs/Sqm 65.70
Sillslab 3.811 4.000 Kgs/Sqm 15.25

APMSDIC-PALASA DET-FIRST FLOOR 487 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
RBM 1393.2 0.500 Kgs/Sqm 696.62
1856.37
Say 1.86 MT

14 External plastering
All round the Building 1 421.977 3.600 1519.12
Duct Shorter Side 4 6.000 1.000 24.00
Duct Shorter Side 4 18.575 3.600 267.48
Deductions
W1 -33 1.800 1.800 -106.92
W2 -78 1.500 1.800 -210.60
W3 -10 1.200 1.800 -21.60
w4 -5 0.900 1.800 -8.10
V5 -76 0.600 0.500 -22.80
1440.58
Say 1441.00 Sqm

15 Ceiling plastering
Qty Same as Vitrified flooring 2352.00
Qty Same as Ceramic flooring 180.00
Qty Same as Cheqqured Tiles
flooring 102.00

Qty Same as Granite Slabs flooring 112.00


2746.00
Say 2746.00 Sqm

16 Internal plastering 12 mm thick


Block-A
Dialysis 2 66.010 3.475 458.77
Change Room 1 10.770 3.475 37.43
Duty Nurse Room 2 18.870 3.475 131.15
Dialyzer Storage 2 18.520 3.475 128.71
Chemical Mixing 1 18.750 3.475 65.16
Reception 1 15.590 3.475 54.18
Arogya Sree 1 15.360 3.475 53.38
RO Plant 1 30.230 3.475 105.05
RO Plant 1 13.630 3.475 47.36
AHU 2 14.170 3.475 98.48
Class IV 1 14.220 3.475 49.41
Electrical 1 14.220 3.475 49.41
Store/pantry 1 11.480 3.475 39.89
3.0 m wide corridor 1 67.810 3.475 235.64
infront of Reception 3.0 m wide
corridor 1 31.070 3.475 107.97
infront of Staircase 1 16.160 3.475 56.16
3.0 m wide corridor near AHU 1 60.400 3.475 209.89
Near Dumb 1 12.594 3.475 43.77
infront of Staircase 1 17.340 3.475 60.26
infront of PHC 2 17.340 3.475 120.51
infront of PHC 2 1.880 3.475 13.07
infront of Utility 2 2.260 3.475 15.71
L.toilet Entrance area 2 1 12.110 3.475 84.16
Space between WC 2 1 6.900 3.475 47.96
WC 2 4 5.400 2.100 90.72

APMSDIC-PALASA DET-FIRST FLOOR 488 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
BATH 2 4 5.400 2.100 90.72
P.H.C toilet 2 1 7.000 3.475 48.65
Dirty Utility 1 1 11.360 3.475 39.48
Attache Toilet 1 5 6.000 3.475 104.25
Attache Toilet 1 1 7.200 3.475 25.02
Ramp Block
Laboratory & Security Toilet 2 5.400 3.475 37.53
Attendents Waiting Toilet 4 5.400 3.475 75.06
Attendents Waiting Toilet Lobby 2 4.800 3.475 33.36
House Keeping & Admin Toilet 2 6.000 3.475 41.70
Laboratory & Security 2 12.000 3.475 83.40
Attendents Waiting 2 20.720 3.475 144.00
House Keeping & Admin 2 15.830 3.475 110.02
Lobby 2 4.800 3.475 33.36
Infront Lift 2 10.800 3.475 75.06
Corridor 1 59.240 3.475 205.86
Staircase 1 11.400 3.475 39.62
Ramp 1 42.000 3.475 145.95
Ramp 1 36.000 3.475 125.10
Block-B
Service Corridor 2 18.500 3.450 127.65
Store 2 11.360 3.450 78.38
Electrical Room 2 14.220 3.450 98.12
Lobby 2 7.340 3.450 50.65
Lobby 2 8.920 3.450 61.55
Lobby 2 15.360 3.450 105.98
Corridor 1 34.800 3.450 120.06
Corridor Lobby 1 13.600 3.450 46.92
AHU 2 14.170 3.450 97.77
Ward 4 26.230 3.450 361.97
Nurse Station 2 17.230 3.450 118.89
Duty Doctor 4 15.000 3.450 207.00
Corridor 2 42.870 3.450 295.80
Clean Linen 4 14.400 3.450 198.72
Ward 4 16.800 3.450 231.84
Ward 2 21.830 3.450 150.63
Corridor 1 72.000 3.450 248.40
Pay Rooms 9 19.640 3.450 609.82
Room 1 13.400 3.450 46.23
Toilet 2 12.110 3.450 83.56
Toilet Corridor 2 7.890 3.450 54.44
WC 12 5.400 3.450 223.56
PHC Toilet 2 7.000 3.450 48.30
Staff Toilet 2 6.000 3.450 41.40
Duty Doctor Attached Toi 4 5.400 3.450 74.52
Pay Rooms Attached Toilet 9 6.600 3.450 204.93
Staircase 1 27.960 3.450 96.46
Staircase 1 26.730 3.450 92.22
Deductions
ALD1 -12 2.000 2.600 -62.40
FD1 -12 2.000 2.100 -50.40
FD2 -2 1.500 2.100 -6.30
D3 -7 1.200 2.600 -21.84
D5 -40 0.900 2.100 -75.60
D6 -60 0.800 2.100 -100.80

APMSDIC-PALASA DET-FIRST FLOOR 489 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Ded for Dadooing with glazed tiles
for Toilets -771.96
Ded for Dadooing in wards &
corridor -1085.42
Deduct for Cladding with Granite
Slabs -12.36
5851.02
Say 5852.00 Sqm
a 12 mm thick internal plastering
60% of above quantity (internal) 3510.61
Say 3511.00 Sqm
b 20 mm thick Internal plastering
40% of above quantity (external) 2340.41
Say 2340.00 Sqm

17 Flooring
a) Vitrified flooring
Block-A
Dialysis 2 18.575 14.430 536.07
Change Room 1 2.985 2.400 7.16
Duty Nurse Room 2 3.320 6.115 40.60
Dialyzer Storage 2 3.145 6.115 38.46
Chemical Mixing 1 3.260 6.115 19.93
Reception 1 4.680 3.115 14.58
Arogya Sree 1 4.680 3.000 14.04
RO Plant 1 9.000 6.115 55.04
RO Plant 1 4.450 2.365 10.52
AHU 2 4.085 3.000 24.51
Class IV 1 3.995 3.115 12.44
Electrical 1 3.995 3.115 12.44
Store/pantry 1 2.695 3.045 8.21
3.0 m wide corridor 1 30.905 3.000 92.72
infront of Reception 3.0 m wide
corridor 1 26.110 2.480 64.75
infront of Staircase 1 4.300 3.780 16.25
3.0 m wide corridor near AHU 1 27.200 3.000 81.60
Near Dumb 1 3.640 1.730 6.30
infront of Staircase 1 6.270 2.400 15.05
infront of PHC 2 6.270 2.400 30.10
infront of PHC 2 2.930 0.940 5.51
infront of Utility 2 1.315 1.130 2.97
Ramp Block
Laboratory & Security 2 3.000 3.000 18.00
Attendents Waiting 2 4.315 6.045 52.17
House Keeping & Admin 2 3.000 4.915 29.49
Lobby 2 1.085 1.315 2.85
Infront Lift 2 2.400 3.000 14.40
Corridor 1 23.390 3.000 70.17
Corridor Lobby 1 10.360 3.230 33.46
Block-B
Service Corridor 2 8.050 1.200 19.32
Store 2 2.635 3.045 16.05
Electrical Room 2 3.995 3.115 24.89
Lobby 2 2.540 1.130 5.74
Lobby 2 1.230 3.230 7.95

APMSDIC-PALASA DET-FIRST FLOOR 490 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Lobby 2 6.070 1.610 19.55
Corridor 1 14.400 3.000 43.20
Corridor Lobby 1 5.070 1.730 8.77
AHU 2 4.085 3.000 24.51
Ward 4 7.000 6.115 171.22
Nurse Station 2 2.500 6.115 30.58
Duty Doctor 4 4.500 3.000 54.00
Ded Of Toi -4 1.200 1.500 -7.20
Corridor 2 2.400 19.035 91.37
Clean Linen 4 4.800 2.400 46.08
Ward 4 4.800 3.600 69.12
Ward 2 4.800 6.115 58.70
Corridor 1 30.905 5.095 157.46
Pay Rooms 9 3.320 6.500 194.22
Ded Of Toi -9 1.800 1.500 -24.30
Room 1 4.300 2.400 10.32
2351.35
Say 2352.00 Sqm
b) Granite flooring
i Treads
Staircase-1&2 4 26 2.000 0.300 62.40
Staircase-3 1 26 2.400 0.300 18.72
81.12
Say 82.00 Sqm

ii Risers
Staircase-1&2 4 28 2.000 0.150 33.60
Staircase-3 1 28 2.400 0.150 10.08
43.68
Say 44.00 Sqm

iii Staircase Midlanding


Infront Staircase-1 2 1 2.400 6.280 30.14
Staircase Midlanding 2 1 2.000 4.430 17.72
Infront Staircase-2 2 1 4.300 2.450 21.07
Staircase Midlanding 2 1 2.000 4.300 17.20
Infront Staircase-3 1 1 5.100 2.480 12.65
Staircase Midlanding 1 1 5.100 2.400 12.24
111.02
Say 112.00 Sqm

d) Non skid ceramic flooring


Block-A
Toilet 2 2.940 3.115 18.32
Toilet Corridor 2 3.945 1.500 11.84
WC 12 1.200 1.500 21.60
PHC Toilet 2 2.000 1.500 6.00
Staff Toilet 2 1.200 1.800 4.32
Duty Doctor Attached Toi 1 2.000 1.500 3.00
Change Room Attached Toi 1 1.200 2.400 2.88
Ramp Block
Laboratory & Security Toilet 2 1.200 1.500 3.60
Attendents Waiting Toilet 4 1.200 1.500 7.20
Attendents Waiting Toilet Lobby 2 1.200 1.200 2.88
House Keeping & Admin Toilet 2 1.200 1.800 4.32

APMSDIC-PALASA DET-FIRST FLOOR 491 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Block-(B)
Toilet 2 2.940 3.115 18.32
Toilet Corridor 2 3.945 1.500 11.84
WC 12 1.200 1.500 21.60
PHC Toilet 2 2.000 1.500 6.00
Staff Toilet 2 1.200 1.800 4.32
Duty Doctor Attached Toi 4 1.200 1.500 7.20
Pay Rooms Attached Toilet 9 1.800 1.500 24.30
179.52
Say 180.00 Sqm

d) Cheq. Tiles flooring


Ramp 2 2.400 18.000 86.40
Ramp Mid Landing 1 5.100 3.000 15.30
101.70
Say 102.00 Sqm
18
High polished granite platforms
Qty same as Platforms 26.21
26.21
Say 27.00 Sqm

19 High Polished granite stone for


Sill slabs
W1 33 2.260 0.225 16.78
W2 78 1.960 0.225 34.40
W3 10 1.660 0.225 3.74
W4 5 1.360 0.225 1.53
V5 76 1.060 0.225 18.13
74.57
Say 75.00 Sqm
20 Skirting
a) Skirting with Vitrified
Block-A
Dialysis 2 66.010 132.02
Change Room 1 10.770 10.77
Duty Nurse Room 2 18.870 37.74
Dialyzer Storage 2 18.520 37.04
Chemical Mixing 1 18.750 18.75
Reception 1 15.590 15.59
Arogya Sree 1 15.360 15.36
RO Plant 1 30.230 30.23
RO Plant 1 13.630 13.63
AHU 2 14.170 28.34
Class IV 1 14.220 14.22
Electrical 1 14.220 14.22
Store/pantry 1 11.480 11.48
Ramp Block 0.000 0.00
Laboratory & Security 2 12.000 24.00
Attendents Waiting 2 20.720 41.44
House Keeping & Admin 2 15.830 31.66
Lobby 2 4.800 9.60
Infront Lift 2 10.800 21.60
Corridor 1 52.780 52.78
Corridor Lobby 1 27.180 27.18

APMSDIC-PALASA DET-FIRST FLOOR 492 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Block-B 0.000 0.00
Service Corridor 2 18.500 37.00
Store 2 11.360 22.72
Electrical Room 2 14.220 28.44
Lobby 2 7.340 14.68
Lobby 2 8.920 17.84
Lobby 2 15.360 30.72
AHU 2 14.170 28.34
Nurse Station 2 17.230 34.46
Duty Doctor 4 15.000 60.00
Clean Linen 4 14.400 57.60
Pay Rooms 9 19.640 176.76
Room 1 13.400 13.40
1109.61
Say 1110.00 Rmt
c) Skirting with Granite
Infront Staircase-1 2 1 17.360 34.72
Staircase Midlanding 2 1 8.430 16.86
Infront Staircase-2 2 1 13.500 27.00
Staircase Midlanding 2 1 8.300 16.60
Infront Staircase-3 1 1 15.160 15.16
Staircase Midlanding 1 1 9.900 9.90
120.24
Say 121.00 Rmt

21 Dadooing with Ceramic Tiles


Block-A
Toilet 2 12.110 2.100 50.86
Toilet Corridor 2 10.890 2.100 45.74
WC 12 5.400 2.100 136.08
PHC Toilet 2 7.000 2.100 29.40
Staff Toilet 2 6.000 2.100 25.20
Duty Doctor Attached Toi 1 7.000 2.100 14.70
Change Room Attached Toi 1 7.200 2.100 15.12
Ramp Block
Laboratory & Security Toilet 2 5.400 2.100 22.68
Attendents Waiting Toilet 4 5.400 2.100 45.36
Attendents Waiting Toilet Lobby 2 4.800 2.100 20.16
House Keeping & Admin Toilet 2 6.000 2.100 25.20
Block-(B)
Toilet 2 12.110 2.100 50.86
Toilet Corridor 2 10.890 2.100 45.74
WC 12 5.400 2.100 136.08
PHC Toilet 2 7.000 2.100 29.40
Staff Toilet 2 6.000 2.100 25.20
Duty Doctor Attached Toi 4 5.400 2.100 45.36
Pay Rooms Attached Toilet 9 6.600 2.100 124.74
Deductions
D5 -8 0.900 2.100 -15.12
D6 -60 0.800 2.100 -100.80
771.96
Say 772.00 Sqm

22 Dadooing in wards & corridor


Block-A

APMSDIC-PALASA DET-FIRST FLOOR 493 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Dialysis 2 66.010 1.500 198.03
Duty Nurse Room 2 18.870 1.500 56.61
Dialyzer Storage 2 18.520 1.500 55.56
Chemical Mixing 1 18.750 1.500 28.13
Reception 1 15.590 1.500 23.39
RO Plant 1 30.230 1.500 45.35
RO Plant 1 13.630 1.500 20.45
AHU 2 14.170 1.500 42.51
Store/pantry 1 11.480 1.500 17.22
Ramp Block
3.0 m wide corridor 1 13.160 1.500 19.74
3.0 m wide corridor 1 23.390 1.500 35.09
Right
Corridor 1 60.400 1.500 90.60
Corridor 1 72.000 1.500 108.00
Corridor 2 42.870 1.500 128.61
Ward 4 26.230 1.500 157.38
Ward 4 16.800 1.500 100.80
Ward 2 21.830 1.500 65.49
Deductions
ALD1 -8 2.000 1.500 -24.00
FD1 -6 2.000 1.500 -18.00
D3 -7 1.200 1.500 -12.60
D5 -20 0.900 1.500 -27.00
JW -8 1.800 1.800 -25.92
1085.42
Say 1086.00 Sqm

23 Cladding with Granite


Lifts 2 2.400 3.450 16.56
Deductions
Lift Doors -2 1.000 2.100 -4.20
12.36
Say 13.00 Sqm

24 Cinder Filling 4 6.880 4.730 0.300 39.05


Say 40.00 cum

25 Impervious coat 4 23.220 0.300 27.86


Say 28.00 Sqm

23 Whiting for ceiling


Same as ceiling plastering 2746.00
2746.00
Say 2746.00 Sqm

24 Wall putty
Same as internal plastering 5852.00
5852.00
Say 5852.00 Sqm

25 Plastic Emulsion Paint for interior


faces of walls
Same as internal plastering 5852.00

APMSDIC-PALASA DET-FIRST FLOOR 494 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
5852.00
Say 5852.00 Sqm

26 Emulsion paint for external


plastering
Same external plastering @ 60% 864.60
864.60
Say 865.00 Sqm

27
Texture Paint for Exterrnal Walls
Same as of external plastering @
40% 576.40
576.40
Say 577.00 Sqm

28 Doors
D2 2 1.500 2.600 7.80
7.80
Say 7.80 Sqm

D3 7 1.200 2.600 21.84


21.84
Say 22.00 Sqm

D4 9 1.000 2.600 23.40


23.40
Say 23.40 Sqm

D5 31 0.900 2.100 58.59


58.59
Say 58.59 Sqm

D6 (0.8 X 2.10) - Frame 60 5.000 300.00


300.00
Say 300.00 RM

D6 60 0.800 2.100 100.80


100.80
Say 100.80 Sqm

ALD
ALD1 20 2.000 2.600 104.00
104.00
Say 104.00 Sqm

29 Windows without mesh


W1 31 1.800 1.800 100.44
W2 19 1.500 1.800 51.30
W3 6 1.200 1.800 12.96
W4 5 0.900 1.800 8.10
Total Quantity Say 172.80 Sqm

30 Windows withmesh
W2 62 1.500 1.800 167.40

APMSDIC-PALASA DET-FIRST FLOOR 495 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Total Quantity 167.40 Sqm

31 Ventilators
V5 74 0.600 0.500 22.20
22.20
Say 22.20 Sqm
32 Jali wall
Jali wall 24 1.800 1.800 77.76
77.76
Say 78.00 Sqm

33 MS Grill for Windows @ 15


Kg/Sqm
W1 33 1.800 1.800 106.92
W2 78 1.500 1.800 210.60
W3 10 1.200 1.800 21.60
W4 5 0.900 1.800 8.10
V5 76 0.600 0.500 22.80
370.02 Sqm
Say 371.00 Sqm
5565.00 Kgs

34 Painting to iron Work


Quantity Same as MS Grill 371.00
Say 371.00 Sqm

35 Railing
Staircase
All round the staircase 2 1 7.350 0.900 13.23
All round the staircase 2 1 7.350 0.900 13.23
All round the staircase 1 1 7.350 0.900 6.62
All round the ramp 1 1 36.000 0.900 32.40
65.48
Say 66.00 Sqm

36 Strucural Glazing
SG 4 1.800 2.100 15.12
15.12
Say 16.00 Sqm

37 Structural Glazing with top hung


shutters
20% of above quantity 3.02
3.02
Say 4.00 Sqm

38 cupboards
Reception 1 1 2.500 2.100 5.25
Dialyzer Store 1 1 2.500 2.100 5.25
Store 1 1 2.000 2.100 4.20
Pay Rooms 1 9 2.000 2.100 37.80
52.50
Say 53.00 Sqm

36 Grip bar

APMSDIC-PALASA DET-FIRST FLOOR 496 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Staircase 2 1 15.030 30.06
Staircase 2 1 14.900 29.80
Staircase 1 1 16.500 16.50
Ramp 1 1 47.100 47.10
PHC Toilet 2 2 7.000 28.00
151.46
Say 152.00 Rmt

37 RCM Drop
Duct 2 1 6.000 0.450 5.40
5.40
Say 6.00 Sqm
38 False ceiling
Qty Same as Vitrified flooring 2351.35
2351.35
Say 2352.00 Sqm

49 PVC down take pipe 2 7.800 15.60


15.60
Say 16.00 Rmt
50 Mastic pad
Roof beams
Horizontal 2 3.460 0.450 3.11
3.11
Say 4.00 Sqm

51 Expansion joint treatment


Roof beams
Horizontal 2 3.460 6.92
6.92
Say 7.00 Rmt

52 Aluminium sheet
Roof beams
Horizontal 2 3.460 6.92
6.92
Say 7.00 Rmt

APMSDIC-PALASA DET-FIRST FLOOR 497 OF 1048


#REF!

DETAILED ESTIMATE - SECOND FLOOR


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
1 Columns Second Top to Roof slab
bottom
Block-A & Ramp Block
C1 13 0.380 0.600 4.075 12.08
C2 20 0.380 0.600 4.075 18.58
C3 12 0.380 0.600 4.075 11.15
C4 5 0.450 0.750 4.075 6.88
C5 10 0.460 0.600 4.075 11.25
C6 6 0.460 0.600 4.075 6.75
C7 4 0.460 0.600 4.075 4.50
C8 2 0.600 0.600 4.075 2.93
C9 2 0.600 0.600 4.075 2.93
C10 2 0.600 0.600 4.075 2.93
C11 7 0.600 0.750 4.075 12.84
C12 19 0.600 0.750 4.075 34.84
C13 11 0.600 0.750 4.075 20.17
Block-(-B)
C4 5 0.450 0.750 4.050 6.83
C5 8 0.460 0.600 4.050 8.94
C6 6 0.460 0.600 4.050 6.71
C7 4 0.460 0.600 4.050 4.47
C8 2 0.600 0.600 4.050 2.92
C9 2 0.600 0.600 4.050 2.92
C10 2 0.600 0.600 4.050 2.92
C11 7 0.600 0.750 4.050 12.76
C12 19 0.600 0.750 4.050 34.63
C13 11 0.600 0.750 4.050 20.05
250.97
Say 251.00 Cum
2 Roof Beams
Horizontal
Block-A
T1-T4 1 7.120 0.300 0.300 0.64
Deduction of Columns -2 0.750 0.300 0.300 -0.14
T4-T5 1 2.400 0.380 0.275 0.25
T5-T7 1 2.800 0.300 0.300 0.25
T7-T10 2 7.700 0.230 0.450 1.59
T10-T16 2 13.810 0.300 0.300 2.49
Deduction of Columns -8 0.750 0.300 0.300 -0.54
Secondary Beam 2 9.520 0.300 0.300 1.71
Deduction of Columns -2 0.230 0.300 0.300 -0.04
Q1-Q2 1 3.310 0.300 0.300 0.30
Q2-Q4 1 2.310 0.380 0.300 0.26
Q4-Q5 1 2.400 0.380 0.275 0.25
Q5-Q10 1 11.250 0.230 0.450 1.16
Q10-Q12 1 2.800 0.300 0.300 0.25
Q12-Q13 1 2.400 0.380 0.275 0.25
Q13-Q16 1 7.120 0.300 0.300 0.64
O1-O5 4 9.520 0.450 0.575 9.85
O5-O12 2 16.290 0.300 0.275 2.69
Deduction of Columns -8 0.750 0.300 0.275 -0.50

APMSIDC-PALASA DET-THIRD FLOOR 498 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
M5-M8 4 4.170 0.300 0.275 1.38
O12-O16 4 9.520 0.450 0.575 9.85
G1-G16 2 35.320 0.300 0.300 6.36
Deduction of Columns -4 0.450 0.300 0.300 -0.16
Deduction of Columns -8 0.600 0.300 0.300 -0.43
E1-E3 1 4.300 0.300 0.400 0.52
Cantilever Beams 2 1.000 0.300 0.300 0.18
Ramp Block
R19-R21 5 5.100 0.230 0.355 2.08
Deduction of Columns -4 0.380 0.230 0.355 -0.12
K17-K19 4 5.860 0.230 0.275 1.48
Deduction of Columns -8 0.380 0.230 0.275 -0.19
I17-I23 1 16.820 0.230 0.275 1.06
Deduction of Columns -5 0.380 0.230 0.275 -0.12
H17-H18 2 5.080 0.230 0.300 0.70
Deduction of Columns -4 0.380 0.230 0.300 -0.10
H18-H22 1 10.360 0.230 0.450 1.07
Deduction of Columns -2 0.230 0.230 0.450 -0.05
G17-G19 2 7.480 0.230 0.300 1.03
Deduction of Columns -4 0.380 0.230 0.300 -0.10
G19-G21 3 4.800 0.230 0.380 1.26
F18-F19 2 2.180 0.230 0.300 0.30
Block-(-B)
T39-T33 3 13.060 0.300 0.300 3.53
Deduction of Columns -9 0.750 0.300 0.300 -0.61
T33-T30 2 7.700 0.230 0.450 1.59
Secondary Beam 2 9.520 0.300 0.300 1.71
Deduction of Columns -2 0.230 0.300 0.300 -0.04
Q1-Q38 1 3.310 0.300 0.300 0.30
Q38-Q36 1 2.310 0.380 0.300 0.26
Q36-Q35 1 2.400 0.380 0.275 0.25
Q35-Q30 1 11.250 0.230 0.450 1.16
O39-O35 4 9.520 0.450 0.575 9.85
O35-O28 4 16.290 0.300 0.275 5.38
Deduction of Columns -16 0.750 0.300 0.275 -0.99
O28-O24 4 9.520 0.450 0.575 9.85
G39-G24 2 35.320 0.300 0.300 6.36
Deduction of Columns -4 0.450 0.300 0.300 -0.16
Deduction of Columns -8 0.600 0.300 0.300 -0.43
E39-E38 1 4.300 0.300 0.400 0.52
Cantilever Beams 2 1.000 0.300 0.300 0.18
Vertical
Block-A
B1-E1 2 1.360 0.300 0.300 0.24
E1-G1 2 5.330 0.300 0.450 1.44
G1-H1 8 3.000 0.300 0.300 2.16
H1-O1 6 19.040 0.300 0.425 14.57
Deduction of Columns -24 0.600 0.300 0.425 -1.84
O1-Q1 2 3.000 0.230 0.300 0.41
O2-Q2 4 3.000 0.300 0.300 1.08
Q1-T1 6 5.720 0.230 0.450 3.55
Q5-T5 4 5.720 0.230 0.475 2.50
Deduction of Columns -1 0.600 0.230 0.475 -0.07
Secondary Beam 1 1.400 0.300 0.325 0.14
Secondary Beam 1 4.330 0.300 0.325 0.42
B5-G5 4 8.940 0.380 0.475 6.45

APMSIDC-PALASA DET-THIRD FLOOR 499 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Deduction of Columns -8 0.750 0.380 0.475 -1.08
Ramp Block
D17-G17 2 5.860 0.230 0.450 1.21
G17-H17 4 3.000 0.230 0.300 0.83
H17-J17 2 5.750 0.230 0.450 1.19
J17-K17 2 2.560 0.230 0.300 0.35
D18-I18 2 12.920 0.230 0.300 1.78
Deduction of Columns -8 0.750 0.230 0.300 -0.41
I18-K18 2 6.050 0.230 0.380 1.06
C19-G19 2 8.640 0.230 0.300 1.19
Deduction of Columns -8 0.750 0.230 0.300 -0.41
G19-I19 2 5.860 0.230 0.450 1.21
I19-J19 3 2.890 0.230 0.275 0.55
J19-L19 3 4.930 0.230 0.425 1.45
L19-N19 3 3.490 0.230 0.355 0.85
N19-P19 3 3.850 0.230 0.355 0.94
P19-R19 2 2.760 0.230 0.275 0.35
Block-B
B39-E39 2 1.360 0.300 0.300 0.24
E39-G39 2 5.330 0.300 0.450 1.44
G39-H39 8 3.000 0.300 0.300 2.16
H39-O39 6 19.040 0.300 0.425 14.57
Deduction of Columns -24 0.600 0.300 0.425 -1.84
O39-Q39 6 3.000 0.230 0.300 1.24
Q39-T39 6 5.720 0.230 0.450 3.55
Q35-T35 4 5.720 0.230 0.475 2.50
Deduction of Columns -1 0.600 0.230 0.475 -0.07
Secondary Beam 1 1.400 0.300 0.325 0.14
Secondary Beam 1 4.330 0.300 0.325 0.42
B35-G35 6 8.940 0.380 0.475 9.68
Deduction of Columns -10 0.750 0.380 0.475 -1.35
Deduction of Columns -2 0.600 0.380 0.475 -0.22
160.69
Say 161.00 Cum

3 Roof slab
i) Roof Slab 125mm thick
Ramp Block (as per CAD) 1 432.775 432.78
Ded Of Staircase -1 5.100 5.700 -29.07
Ded Of Lift -2 2.400 3.000 -14.40
Deduction of Ramp -1 5.100 21.000 -107.10
282.21
Say 283.00 Sqm

ii) Roof Slab 150mm thick


Block-(A) 1 40.600 35.780 1452.67
Ded Of Staircase -1 5.300 4.430 -23.48
Ded Of Staircase -1 4.300 5.300 -22.79
Ded Of Duct -1 6.000 18.575 -111.45
Block-(-B) 1 40.600 35.780 1452.67
Ded Of Staircase -1 5.300 4.430 -23.48
Ded Of Staircase -1 4.300 5.300 -22.79
Ded Of Duct -1 6.000 18.575 -111.45
Deduction of 175mm Thick Slab -943.51
1646.39
Say 1647.00 Sqm

APMSIDC-PALASA DET-THIRD FLOOR 500 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY

iii) Roof Slab 175mm thick


H1-H5 x H1-O1 2 2 9.980 19.040 760.08
H31-H32 x H31-O31 1 1 6.460 19.040 123.00
B31-B32 x B31-G31 1 1 6.760 8.940 60.43
943.51
Say 944.00 Sqm
v) Waist slab (175mm thick)
Staircase (Flight -1& Flight-2) 2 2 3.600 2.000 28.80
Mid landing 2 1 2.000 4.430 17.72
Staircase (Flight -1& Flight-2) 2 2 3.600 2.000 28.80
Mid landing 2 1 2.000 4.300 17.20
Staircase (Flight -1& Flight-2) 1 2 3.600 2.400 17.28
Mid landing 1 1 5.100 2.400 12.24
Ramp 1 2 18.000 2.460 88.56
Mid landing 1 1 5.100 3.000 15.30
225.90
Say 226.00 Sqm

4 RCC M20 grade mix


a Platforms
Block-A
Store 1 3.045 0.600 1.83
Store 1 4.800 0.600 2.88
Pharmacy 1 5.965 0.600 3.58
Class IV Room 1 3.995 0.600 2.40
Block-(-B)
Class IV Room 1 3.995 0.600 2.40
13.08
Say 14.00 Sqm
b Loft
Block-A
Store 1 3.045 0.600 1.83
Store 1 4.800 0.600 2.88
Class IV Room 1 3.995 0.600 2.40
Ramp Block
Laboratory 1 3.000 0.600 1.80
House Keeping 1 6.230 0.600 3.74
Block-(-B)
Store 1 3.045 0.600 1.83
14.47
Say 15.00 Sqm

Total Platforms & Lofts 28.08


Say 29.00 Sqm

c Racks and shelves 25mm


Block-(A)
Store 3 1 2.000 0.450 2.70
Store 3 1 2.000 0.450 2.70
Instruments Store 3 1 2.500 0.450 3.38
Pharmacy 3 2 2.000 0.450 5.40
Ramp Block
Laboratory 3 1 2.000 0.450 2.70
Block-(-B)

APMSIDC-PALASA DET-THIRD FLOOR 501 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Rooms 3 20 2.000 0.450 54.00
70.88
Say 71.00 Sqm
d sill slabs
W1 35 2.100 0.230 0.050 0.85
W2 4 1.800 0.230 0.050 0.08
W3 14 1.500 0.230 0.050 0.24
1.17
Say 2.00 cum

5 230mm thick brick masonary


BLOCK A4
Horizontal
From AHU to Stores 1 14.040 0.225 3.750 11.85
Deduction of columns -5 0.750 0.225 3.775 -3.19
Staircase walls 1 9.060 0.225 3.600 7.34
Deduction of columns -2 0.750 0.225 3.600 -1.22
Store to equipment room wall 1 14.490 0.225 3.750 12.23
Staircase walls 1 5.530 0.225 3.600 4.48
Electrical Room & dumb waiter wall 1 5.730 0.225 3.600 4.64
Deduction of columns -2 0.680 0.225 3.600 -1.10
Class IV wall 1 4.300 0.225 3.750 3.63
Deduction of columns -1 0.680 0.225 3.750 -0.57
Operation Theatre 4 7.790 0.225 3.450 24.19
Deduction of columns -4 0.750 0.225 3.450 -2.33
OT Instruments Store 1 5.150 0.225 3.750 4.35
Deduction of columns -2 0.750 0.225 3.450 -1.16
Threater Pack Preparation 1 5.150 0.225 3.750 4.35
Deduction of columns -2 0.750 0.225 3.450 -1.16
Post Operative Ward 1 13.980 0.225 3.450 10.85
CSSD 1 13.980 0.225 3.450 10.85
Store To Doctor Room 1 10.830 0.225 3.750 9.14
Deduction of columns -4 0.600 0.225 3.450 -1.86
Duty Nurse To Officers Incharge 1 10.200 0.225 3.750 8.61
Deduction of columns -3 0.600 0.225 3.450 -1.40
Vertical
AHU TO OT 2 28.660 0.225 3.775 48.69
Deduction of columns -6 0.600 0.225 3.450 -2.79
Staircase wall 2 8.190 0.225 3.600 13.27
Deduction of columns -3 0.600 0.225 3.450 -1.40
OT Instruments to sterilization 1 10.000 0.225 3.775 8.49
Deduction of columns -2 0.450 0.225 3.775 -0.76
Staircase side walls 1 4.060 0.225 3.600 3.29
Dumb Waiter 2 1.960 0.225 3.600 3.18
Deduction of columns -1 0.600 0.225 3.775 -0.51
Deduction of columns -1 0.380 0.225 3.775 -0.32
In Front of staircase 1 5.420 0.225 3.600 4.39
Equipment Room Side Walls 2 5.720 0.225 3.600 9.27
Post operative Side Walls 2 8.940 0.225 3.600 14.48
Deduction of columns -2 0.450 0.225 3.775 -0.76
Threater Pack Preparation Side Wall 1 5.750 0.225 3.600 4.66
C.S.S.D Side Wall 1 10.210 0.225 3.600 8.27
Deduction of columns -1 0.450 0.225 3.600 -0.36
Deduction of columns -1 0.600 0.225 3.600 -0.49
Corridor Side Wall 1 10.100 0.225 3.600 8.18
Deduction of columns -2 0.600 0.225 3.600 -0.97

APMSIDC-PALASA DET-THIRD FLOOR 502 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Officers Incharge To Toilet Side Walls 1 7.440 0.225 3.600 6.03
BLOCK B3
Vertical
Equipment Room Side Walls 2 6.620 0.225 3.600 10.72
Deduction of columns -4 0.450 0.225 3.600 -1.46
A.H.U. Room Side Walls 2 3.000 0.225 3.600 4.86
Deduction of columns -4 0.450 0.225 3.600 -1.46
Infornt of Staircase SideWalls 1 5.420 0.225 3.600 4.39
Staircase Midlanding Wall 1 5.260 0.225 3.600 4.26
Deduction of columns -4 0.450 0.225 3.600 -1.46
Dumb Waiter Walls 2 1.960 0.225 3.600 3.18
Deduction of columns -1 0.450 0.225 3.600 -0.36
Deduction of columns -1 0.380 0.225 3.600 -0.31
Equipment Room Side Walls 2 6.620 0.225 3.600 10.72
Deduction of columns -4 0.450 0.225 3.600 -1.46
A.H.U. Room Side Walls 2 3.000 0.225 3.600 4.86
Deduction of columns -4 0.450 0.225 3.600 -1.46
Room -1 to Room-5 2 19.040 0.225 3.600 30.84
Deduction of columns -8 0.450 0.225 3.600 -2.92
Room-6 to Clean Utility 2 19.040 0.225 3.600 30.84
Deduction of columns -8 0.450 0.225 3.600 -2.92
Dirty Utility to Duty Doctor 2 8.940 0.225 3.600 14.48
Deduction of columns -2 0.750 0.225 3.600 -1.22
Stair case Side Walls 2 6.830 0.225 3.600 11.06
Deduction of columns -4 0.750 0.225 3.600 -2.43
Clean Utility Side Walls 2 2.860 0.225 3.600 4.63
Deduction of columns -4 0.750 0.225 3.600 -2.43
Horizontal
Equipment Room to Diurty Utility 1 14.560 0.225 3.750 12.29
Deduction of columns -5 0.600 0.225 3.750 -2.53
Staircase Walls 1 9.200 0.225 3.600 7.45
Deduction of columns -2 0.750 0.225 3.600 -1.22
Diurty Utility to Equipment Room 1 14.560 0.225 3.750 12.29
Deduction of columns -5 0.600 0.225 3.750 -2.53
Equipment Room Walls 1 7.870 0.225 3.750 6.64
Deduction of columns -3 0.750 0.225 3.775 -1.91
Electrical Room Wall 1 4.290 0.225 3.750 3.62
Deduction of columns -2 0.750 0.225 3.750 -1.27
Staircase side walls 2 10.260 0.225 3.750 17.31
Deduction of columns -4 0.750 0.225 3.750 -2.53
Dumb Waiter to Class IV Room 1 5.720 0.225 3.750 4.83
Deduction of columns -4 0.750 0.225 3.750 -2.53
Equipment Room 1 4.810 0.225 3.750 4.06
Deduction of columns -2 0.750 0.225 3.750 -1.27
Room 5 Wall 2 6.770 0.225 3.750 11.42
Deduction of columns -2 0.750 0.225 3.750 -1.27
Room 6 Wall 2 6.240 0.225 3.750 10.53
Deduction of columns -4 0.750 0.225 3.750 -2.53
Room 1 Wall 2 6.770 0.225 3.750 11.42
Deduction of columns -2 0.750 0.225 3.750 -1.27
Nurses Station To clean Room 2 6.240 0.225 3.750 10.53
Deduction of columns -4 0.750 0.225 3.750 -2.53
Dirty Utility to Post OP I.C.U Ward 1 31.620 0.225 3.750 26.68
Deduction of columns -7 0.600 0.225 3.750 -3.54
Duty Doctor to Post OP I.C.U Ward 1 31.620 0.225 3.750 26.68
Deduction of columns -7 0.600 0.225 3.750 -3.54

APMSIDC-PALASA DET-THIRD FLOOR 503 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Ramp Block(horizontal)
Ramp Wall 1 5.100 0.225 3.695 4.24
Attendents Waiting Room 2 5.860 0.225 3.775 9.95
Deduction of columns -4 0.380 0.225 3.775 -1.29
Laboratory 2 5.860 0.225 3.775 9.95
Deduction of columns -4 0.380 0.225 3.775 -1.29
Corridor 1 5.940 0.225 3.625 4.84
Security 1 2.700 0.225 3.775 2.29
Corridor To Staircase Entrance 1 8.490 0.225 3.775 7.21
Deduction of columns -2 0.380 0.225 3.775 -0.65
Staircase 2 4.800 0.225 3.695 7.98
Staircase Entrance To Admin 1 5.860 0.225 3.775 4.98
Deduction of columns -1 0.380 0.225 3.775 -0.32
Lift 2 2.400 0.225 3.775 4.08
House Keeping To Lift 2 5.330 0.225 3.775 9.05
Deduction of columns -2 0.380 0.225 3.775 -0.65
Ramp Block( vertical)
House Keeping 2 5.860 0.225 3.625 9.56
Lab To Attendents 2 9.510 0.225 3.625 15.51
Deduction of columns -2 0.600 0.225 3.625 -0.98
House Keeping 2 6.460 0.225 3.775 10.97
Lab 2 2.260 0.225 3.775 3.84
Staircase 2 8.640 0.225 3.775 14.68
Deduction of columns -8 0.600 0.225 3.775 -4.08
Ramp Walls 3 2.890 0.225 3.775 7.36
Ramp Walls 3 4.930 0.225 3.625 12.06
Ramp Walls 3 8.530 0.225 3.695 21.27
Deduction of columns -6 0.600 0.225 3.695 -2.99
Ramp Walls 2 2.630 0.225 3.775 4.47
Deductions
W1 -32 1.800 0.225 1.800 -23.33
W2 -14 1.500 0.225 1.800 -8.51
W3 -10 1.200 0.225 1.800 -4.86
ALD1 -2 1.800 0.225 2.600 -2.11
OTD-1 -3 1.800 0.225 2.600 -3.16
D2 -4 1.200 0.225 2.100 -2.27
D3 -2 1.200 0.225 2.100 -1.13
V5 -58 0.600 0.225 0.500 -3.92
579.38
Say 580.00 Cum
6 115 mm thick Brick masonry walls
1 BLOCK A4
Horizontal
Staff Toilet 2 1.320 3.625 9.57
Electrical Room & Class IV Room 2 4.070 4.075 33.17
Equipment Room 1 3.390 4.075 13.81
OT Instruments Store 1 4.920 4.075 20.05
Otpharmacy 1 4.920 4.075 20.05
Threater pack Preparation 1 5.170 4.075 21.07
Post Operative Ward 1 14.660 4.075 59.74
Anesthetia Room & Doctor Room 2 4.580 4.075 37.33
Post Operative Ward 1 9.140 4.075 37.25
Change Room 1 5.150 3.750 19.31
Change Room 3 2.630 4.075 32.15
OT Records Room 1 3.780 4.075 15.40
Duty nurse to officers incharge 1 9.860 4.075 40.18

APMSIDC-PALASA DET-THIRD FLOOR 504 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Toilet in OT Reception 1 1.620 4.075 6.60
Toilet in Officer Incharge 1 1.320 4.075 5.38
Vertical
Store wall 2 3.050 3.625 22.11
Staff toilet wall 2 2.140 3.625 15.52
Electrical & Class IV room wall 2 3.350 3.625 24.29
OT Intruments & Pharmacy Store wall 1 6.950 3.625 25.19
Sterilization wall 1 6.350 4.075 25.88
Threater Pack Preparation wall 1 5.750 3.600 20.70
C.S.S.D 1 10.190 4.075 41.52
Anesthetia Room & Doctor Room 1 8.730 4.075 35.57
Pre Operative Ward 2 8.710 4.075 70.99
Change Room 2 8.940 4.075 72.86
OT Reception & Duty Nurse 1 7.440 3.600 26.78
Offecers Incharge 1 2.600 3.600 9.36
OT Reception 1 5.480 3.600 19.73
2 BLOCK B3
Horizontal
Staff Toilet 2 1.320 3.625 9.57
Electrical Room & Class IV Room 2 4.070 4.075 33.17
Equipment Room 1 3.390 4.075 13.81
Room 1-5 Walls 8 6.240 4.075 203.42
Room 6-Clean Utilty 8 6.240 4.075 203.42
Dirty Utility & Pantry 1 9.020 4.075 36.76
Duty Doctor to nurse 1 9.020 4.075 36.76
Vertical
Store wall 2 3.050 3.625 22.11
Staff toilet wall 2 2.140 3.625 15.52
Electrical & Class IV room wall 2 3.350 3.625 24.29
Rooms Walls 4 19.040 3.625 276.08
Dirty Utility & Nurse 2 8.940 3.625 64.82
Ramp Block(horizontal)
Attendents Attached Toilets 6 1.315 4.050 31.95
House Keeping Attached Toilets 2 1.915 4.050 15.51
Ramp Block(Vertical)
Attendents Attached Toilets 2 6.045 4.050 48.96
House Keeping Attached Toilets 2 1.200 4.050 9.72
Deductions
Columns -8 0.600 1.000 -4.80
Columns -8 0.300 1.000 -2.40
Deductions
D5 -20 1.000 2.100 -42.00
D5 -12 0.900 2.100 -22.68
D6 -18 0.800 2.100 -30.24
1725.32
Say 1726.00 Sqm

7 PCC for Steps


Staircase 0.5 44 2.000 0.300 0.150 1.98
Staircase 0.5 44 2.000 0.300 0.150 1.98
Staircase 0.5 22 2.400 0.300 0.150 1.19
5.15
Say 6.00 cum
8 PCC (1:3:6) for Bedblocks
under lintels
SW1 2 35 0.300 0.225 0.150 0.71

APMSIDC-PALASA DET-THIRD FLOOR 505 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
SW2 2 4 0.300 0.225 0.150 0.08
SW3 2 14 0.300 0.225 0.150 0.28
ALD1 2 12 0.300 0.225 0.150 0.24
OTD1 2 4 0.300 0.225 0.150 0.08
FD1 2 8 0.300 0.225 0.150 0.16
D2 2 7 0.300 0.225 0.150 0.14
D3 2 7 0.300 0.225 0.150 0.14
D4 2 20 0.300 0.225 0.150 0.41
D5 2 21 0.300 0.225 0.150 0.43
D6 2 42 0.300 0.225 0.150 0.85
V5 2 58 0.300 0.225 0.150 1.17
Hold fasts
SW1 4 35 0.230 0.225 0.150 1.09
SW2 4 4 0.230 0.225 0.150 0.12
SW3 4 14 0.230 0.225 0.150 0.43
ALD1 6 12 0.230 0.225 0.150 0.56
OTD1 6 4 0.230 0.225 0.150 0.19
D2 6 7 0.230 0.225 0.150 0.33
D3 6 7 0.230 0.225 0.150 0.33
D4 6 20 0.230 0.225 0.150 0.93
D5 6 21 0.230 0.225 0.150 0.98
D6 6 42 0.230 0.225 0.150 1.96
FD1 6 8 0.230 0.225 0.150 0.37
V5 2 58 0.230 0.225 0.150 0.90
12.88
Say 13.00 Cum
9 Lintels
SW1 35 2.260 0.225 0.175 3.11
SW2 4 1.960 0.225 0.175 0.31
SW3 14 1.660 0.225 0.175 0.92
ALD1 12 2.460 0.225 0.175 1.16
OTD1 4 2.470 0.225 0.175 0.39
D2 7 1.960 0.225 0.175 0.54
D3 7 1.660 0.225 0.175 0.46
D4 20 1.710 0.225 0.175 1.35
D6 42 1.260 0.225 0.175 2.08
FD1 8 2.460 0.225 0.175 0.77
V5 58 1.060 0.225 0.175 2.42
D5 21 1.360 0.100 0.175 0.50
14.01
Say 15.00 Cum

10 Sunshades
W1 35 2.100 73.50
W2 4 1.800 7.20
W3 14 1.500 21.00
101.70
Say 102.00 Rmt

11 TMT STEEL
Columns upto 3.60 mts levael 250.97 200.000 Kgs/Cum 50193.22
Roof beams 160.69 200.000 Kgs/Cum 32137.52
125mm thick Roof slab 283.00 10.000 Kgs/Sqm 2830.00
150mm thick Roof slab 1647.00 12.000 Kgs/Sqm 19764.00
175mm thick Roof slab 943.51 14.000 Kgs/Sqm 13209.13
175mm thick waist slab 225.90 14.000 Kgs/Sqm 3162.60

APMSIDC-PALASA DET-THIRD FLOOR 506 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Lintels 15.00 80.000 Kgs/Cum 1200.00
122496.47
Say 122.50 MT

12 Mild Steel
Sunshades 101.70 4.000 Kgs/RM 406.80
Sillslab 1.170 4.000 Kgs/Sqm 4.68
Platforms & Lofts 29.000 4.000 Kgs/Sqm 116.00
Shelves 71.000 4.000 Kgs/Sqm 284.00
RBM 1725.3 0.500 Kgs/Sqm 862.66
1674.14
Say 1.67 MT

13 External plastering
All round the Building 1 415.736 4.200 1746.09
Duuct at A4 1 32.000 4.200 134.40
Duuct at A4 1 24.230 4.200 101.77
Duuct at B3 1 49.150 4.200 206.43
Ramp offset walls 2 18.000 4.200 151.20
Deductions
W1 -32 1.800 1.800 -103.68
W2 -14 1.500 1.800 -37.80
W3 -10 1.200 1.800 -21.60
V5 -58 0.600 0.500 -17.40
2159.41
Say 2160.00 Sqm

14 Ceiling plastering
Qty Same as Vitrified flooring 2403.00
Qty Same as Ceramic flooring 100.00
Qty Same as Chqqured tiles flooring 104.00
Qty Same as Granite Slabs flooring 43.00
Deduct
Pre operative Ward -1 8.920 8.590 -76.62
Post Operative Ward -1 14.430 8.590 -123.95
ICU -1 11.200 12.800 -143.36
Pay Rooms -1 11.200 12.800 -143.36
2162.70
Say 2163.00 Sqm

15 Internal plastering 12 mm thick


BLOCK - A4
Store Room 1 16.960 4.075 69.11
Doctor Room 1 16.960 4.075 69.11
Anesthetia Room 1 16.960 4.075 69.11
Pre operative Ward 1 35.020 4.075 142.71
Deduction of toilet 1 8.620 4.075 35.13
Change Room 4 8.930 4.075 145.56
Duty nurse 1 15.670 4.075 63.86
Deduction of toilet 1 5.400 4.075 22.01
Officer Incharge 1 15.130 4.075 61.65
Deduction of toilet 1 5.400 4.075 22.01
O.T.Records Room 1 12.340 4.075 50.29
O.T.Reception 1 23.120 4.075 94.21
Operation Theatre 3 26.000 4.075 317.85
A.H.U 1 32.550 4.075 132.64

APMSIDC-PALASA DET-THIRD FLOOR 507 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Theatre Pack Preparation 1 21.830 4.075 88.96
Sterilization 1 18.230 4.075 74.29
OT pharmacy Store 1 15.600 4.075 63.57
OT instruments Store 1 15.600 4.075 63.57
Electrical Room 1 14.220 4.075 57.95
Stores 1 11.360 4.075 46.29
Stores 1 11.360 4.075 46.29
Class IV Room 1 14.220 4.075 57.95
Equipment Room 1 20.000 4.075 81.50
A.H.U. Room 1 14.170 4.075 57.74
Post Operative Ward 1 46.050 4.075 187.65
Deduction of toilet 1 9.670 4.075 39.41
C.S.S.D 1 39.160 4.075 159.58
2.4 m wide corridor(v) 1 22.220 4.075 90.55
2.4 m wide corridor(v) 1 61.650 4.075 251.22
corridor(v) near scrubs 1 15.830 4.075 64.51
corridor(v) b/w stores 1 19.580 4.075 79.79
corridor(v) b/w stores 1 19.580 4.075 79.79
corridor(v) near c.s.s.d 1 29.390 4.075 119.76
3.0 m wide corridor(H) 1 76.640 4.075 312.31
2.0 m wide corridor(H) 1 16.920 4.075 68.95
3.0 m wide corridor(H) Near class IV
room 1 47.490 4.075 193.52
Near Dumb Water 1 10.740 4.075 43.77
MIDDLE
Attendants Waiting Room(Female) 1 20.720 4.075 84.43
Laboratory 1 12.000 4.075 48.90
Attendants Waiting Room(male) 1 20.720 4.075 84.43
Security 1 12.000 4.075 48.90
House Keeping 1 15.830 4.075 64.51
Floor Administrator 1 15.830 4.075 64.51
3.0 m wide corridor(H) 1 53.480 4.075 217.93
corridor(H) b/w Corridor & Security 1 26.740 4.075 108.97
Pressurization 2 10.800 4.075 88.02
BLOCK - B3
Equipment Room 2 26.090 4.075 212.63
A.H.U. ROOM 2 14.170 4.075 115.49
Dirty utility 2 11.360 4.075 92.58
Electrical Room 1 14.220 4.075 57.95
Class IV Room 1 14.220 4.075 57.95
Room-1 2 19.050 4.075 155.26
Deduction of toilet 2 6.600 4.075 53.79
Room-2 2 19.050 4.075 155.26
Deduction of toilet 2 6.600 4.075 53.79
Room-3 2 19.050 4.075 155.26
Deduction of toilet 2 6.600 4.075 53.79
Room-4 2 19.050 4.075 155.26
Deduction of toilet 2 6.600 4.075 53.79
Room-5 2 19.050 4.075 155.26
Deduction of toilet 2 6.600 4.075 53.79
Room-6 2 19.050 4.075 155.26
Deduction of toilet 2 6.600 4.075 53.79
Room-7 2 19.050 4.075 155.26
Deduction of toilet 2 6.600 4.075 53.79
Room-8 2 19.050 4.075 155.26
Deduction of toilet 2 6.600 4.075 53.79

APMSIDC-PALASA DET-THIRD FLOOR 508 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Room-9 2 19.050 4.075 155.26
Nurses Station 2 14.050 4.075 114.51
Clean Utility 2 12.250 4.075 99.84
Dirty Utility 1 14.600 4.075 59.50
Pantry 1 13.470 4.075 54.89
Duty Doctor 1 18.130 4.075 73.88
Deduction of toilet 1 6.600 4.075 26.90
Duty nurse 1 16.030 4.075 65.32
Deduction of toilet 1 6.600 4.075 26.90
POST OP I.C.U. WARD 1 60.950 4.075 248.37
Clean Utility 1 13.400 4.075 54.61
3.0 m wide corridor(H) 1 76.870 4.075 313.25
3.0 m wide corridor(H) 1 60.400 4.075 246.13
2.4 m wide corridor(V) 2 42.870 4.075 349.39
2.4 m wide corridor(V) 2 42.870 4.075 349.39
2.4 m wide corridor(V) near equipment
room 3 17.576 4.075 214.87
Deductions
ALD1 -4 1.800 2.600 -18.72
OTD1 -4 1.800 2.600 -18.72
D2 -7 1.500 2.100 -22.05
D3 -7 1.200 2.100 -17.64
D4 -20 1.250 2.100 -52.50
D6 -42 0.800 2.100 -70.56
D5 -21 0.900 2.100 -39.69
D6 -42 0.800 2.100 -70.56
Ded for Dadooing with glazed tiles for
Toilets -453.21
Ded for Dadooing in wards & corridor -1340.04
Deduct Cladding with Granite Slabs -4.08
6988.93
Say 6989.00 Sqm
a 12 mm thick internal plastering
60% of above quantity (internal) 4193.36
Say 4193.00 Sqm
b 20 mm thick Internal plastering
40% of above quantity (external) 2795.57
Say 2796.00 Sqm

16 Flooring
a) Vitrified flooring
BLOCK - A4
Store Room 1 4.240 4.240 17.98
Doctor Room 1 4.240 4.240 17.98
Anesthetia Room 1 4.240 4.240 17.98
Pre operative Ward 1 8.915 8.595 76.62
Deduction of toilet -1 2.510 1.800 -4.52
Change Room 4 2.400 2.065 19.82
Duty nurse 1 4.835 3.000 14.51
Deduction of toilet -1 1.200 1.500 -1.80
Officer Incharge 1 4.565 3.000 13.70
Deduction of toilet -1 1.200 1.500 -1.80
O.T.Records Room 1 3.435 2.735 9.39
O.T.Reception 1 5.965 5.595 33.37
A.H.U 1 6.885 9.390 64.65
Theatre Pack Preparation 1 4.800 6.115 29.35

APMSIDC-PALASA DET-THIRD FLOOR 509 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
OT pharmacy Store 1 4.800 3.000 14.40
OT instruments Store 1 4.800 3.000 14.40
Electrical Room 1 3.995 3.115 12.44
Stores 1 2.635 3.045 8.02
Stores 1 2.635 3.045 8.02
Class IV Room 1 3.995 3.115 12.44
Equipment Room 1 6.885 3.115 21.45
A.H.U. Room 1 4.085 3.000 12.26
Post Operative Ward 1 14.430 8.595 124.03
Deduction of toilet -1 2.085 2.750 -5.73
C.S.S.D 1 9.715 9.865 95.84
2.4 m wide corridor(v) 1 8.710 2.400 20.90
2.4 m wide corridor(v) 1 28.425 2.400 68.22
corridor(v) near scrubs 1 6.115 1.800 11.01
corridor(v) b/w stores 1 6.390 3.400 21.73
corridor(v) b/w stores 1 6.390 3.400 21.73
corridor(v) near c.s.s.d 1 4.600 10.095 46.44
3.0 m wide corridor(H) 1 35.320 3.000 105.96
2.0 m wide corridor(H) 1 6.460 2.000 12.92
3.0 m wide corridor(H) Near class IV
room 1 21.745 2.000 43.49
Near Dumb Water 1 3.640 1.730 6.30
MIDDLE
Attendants Waiting Room(Female) 1 4.315 6.045 26.08
Laboratory 1 3.000 3.000 9.00
Attendants Waiting Room(male) 1 4.315 6.045 26.08
Security 1 3.000 3.000 9.00
House Keeping 1 3.000 4.915 14.75
Floor Administrator 1 3.000 4.915 14.75
3.0 m wide corridor(H) 1 23.740 3.000 71.22
corridor(H) b/w Corridor & Security 1 10.360 3.010 31.18
Pressurization 2 2.400 3.000 14.40
BLOCK - B3
Equipment Room 2 6.885 6.160 84.82
A.H.U. ROOM 2 4.085 3.000 24.51
Dirty utility 2 2.635 3.045 16.05
Electrical Room 1 3.995 3.115 12.44
Class IV Room 1 3.995 3.115 12.44
Room-1 2 5.900 3.625 42.78
Deduction of toilet -2 1.500 1.800 -5.40
Room-2 2 5.900 3.625 42.78
Deduction of toilet -2 1.500 1.800 -5.40
Room-3 2 5.900 3.625 42.78
Deduction of toilet -2 1.500 1.800 -5.40
Room-4 2 5.900 3.625 42.78
Deduction of toilet -2 1.500 1.800 -5.40
Room-5 2 5.900 3.625 42.78
Deduction of toilet -2 1.500 1.800 -5.40
Room-6 2 5.900 3.625 42.78
Deduction of toilet -2 1.500 1.800 -5.40
Room-7 2 5.900 3.625 42.78
Deduction of toilet -2 1.500 1.800 -5.40
Room-8 2 5.900 3.625 42.78
Deduction of toilet -2 1.500 1.800 -5.40
Room-9 2 5.900 3.625 42.78
Nurses Station 2 3.400 3.625 24.65

APMSIDC-PALASA DET-THIRD FLOOR 510 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Clean Utility 2 2.500 3.625 18.13
Dirty Utility 1 4.565 2.735 12.49
Pantry 1 4.000 2.735 10.94
Duty Doctor 1 4.565 4.500 20.54
Deduction of toilet -1 1.500 1.800 -2.70
Duty nurse 1 4.000 4.015 16.06
Deduction of toilet -1 1.500 1.800 -2.70
POST OP I.C.U. WARD 1 21.995 8.480 186.52
Clean Utility 1 4.300 2.400 10.32
3.0 m wide corridor(H) 1 35.435 3.000 106.31
3.0 m wide corridor(H) 1 27.200 3.000 81.60
2.4 m wide corridor(V) 2 19.035 2.400 91.37
2.4 m wide corridor(V) 2 19.035 2.400 91.37
2.4 m wide corridor(V) near equipment
room 3 6.388 2.400 45.99
2402.87
Say 2403.00 Sqm
b) Granite flooring
i Treads
Staircase 5 26 2.000 0.300 78.00
78.00
Say 78.00 Sqm

ii Risers
Staircase 5 28 2.000 0.150 42.00
42.00
Say 42.00 Sqm

iii Staircase Midlanding 5 4.230 2.000 42.30


42.30
Say 43.00 Sqm
d) Non skid ceramic flooring
BLOCK - A4
Toilet near nurse station 1 2.510 1.800 4.52
Toilet near duty nurse 1 1.200 1.500 1.80
Toilet near officer incharge 1 1.200 1.500 1.80
Toilet near O.T Reception 1 3.516 2.516 8.85
Toilet near stores 2 1.200 1.800 4.32
Toilet at post operative ward 1 2.085 2.750 5.73
MIDDLE
Toilet at House Keeping 1 1.200 1.800 2.16
Toilet at Floor Admin 1 1.200 1.800 2.16
Toilet at Floor Admin 1 1.200 1.800 2.16
WC 2 1.515 1.200 3.64
WC bath 2 1.515 1.200 3.64
toilet at lab 1 1.200 1.500 1.80
toilet at security 1 1.200 1.500 1.80
Space between WC 1 1.320 1.200 1.58
BLOCK - B3
Toilets in duty doctor 1 1.500 1.800 2.70
Toilets in duty nurse 1 1.500 1.800 2.70
Toilet in rooms 18 1.800 1.500 48.60
99.95
Say 100.00 Sqm
17 High polished granite platforms
Qty same as Platforms 13.08

APMSIDC-PALASA DET-THIRD FLOOR 511 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
13.08
Say 14.00 Sqm
d) Cheq. Tiles flooring
Ramp 2 1 18.300 2.400 87.84
Midlanding 1 1 5.100 3.000 15.30
103.14
Say 104.00 Sqm

18 High Polished granite stone for Sill


slabs
W1 35 2.260 0.230 18.19
W2 4 1.960 0.230 1.80
W3 14 1.660 0.230 5.35
V5 58 1.060 0.230 14.14
39.48
Say 40.00 Sqm
19 Skirting
a) Skirting with Vitrified
BLOCK - A4
Store Room 1 16.960 16.96
Doctor Room 1 16.960 16.96
Anesthetia Room 1 16.960 16.96
Change Room 4 8.930 35.72
Duty nurse 1 15.670 15.67
Officer Incharge 1 15.130 15.13
Deduction of toilet -1 5.400 -5.40
O.T.Records Room 1 12.340 12.34
O.T.Reception 1 23.120 23.12
Operation Theatre 3 26.000 78.00
A.H.U 1 32.550 32.55
Theatre Pack Preparation 1 21.830 21.83
Sterilization 1 18.230 18.23
OT pharmacy Store 1 15.600 15.60
OT instruments Store 1 15.600 15.60
Electrical Room 1 14.220 14.22
Stores 1 11.360 11.36
Stores 1 11.360 11.36
Class IV Room 1 14.220 14.22
Equipment Room 1 20.000 20.00
A.H.U. Room 1 14.170 14.17
Post Operative Ward 1 46.050 46.05
Deduction of toilet -1 9.670 -9.67
C.S.S.D 1 39.160 39.16
MIDDLE
Attendants Waiting Room(Female) 1 20.720 20.72
Laboratory 1 12.000 12.00
Attendants Waiting Room(male) 1 20.720 20.72
Security 1 12.000 12.00
House Keeping 1 15.830 15.83
Floor Administrator 1 15.830 15.83
BLOCK - B3
Equipment Room 2 26.090 52.18
A.H.U. ROOM 2 14.170 28.34
Dirty utility 2 11.360 22.72
Electrical Room 1 14.220 14.22
Class IV Room 1 14.220 14.22

APMSIDC-PALASA DET-THIRD FLOOR 512 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Room-1 2 19.050 38.10
Room-2 2 19.050 38.10
Room-3 2 19.050 38.10
Room-4 2 19.050 38.10
Room-5 2 19.050 38.10
Room-6 2 19.050 38.10
Room-7 2 19.050 38.10
Room-8 2 19.050 38.10
Room-9 2 19.050 38.10
Nurses Station 2 14.050 28.10
Clean Utility 2 12.250 24.50
Dirty Utility 1 14.600 14.60
Pantry 1 13.470 13.47
Duty Doctor 1 18.130 18.13
Duty nurse 1 16.030 16.03
Clean Utility 1 13.400 13.40
1190.05
Say 1191.00 Rmt
c) Skirting with Granite
All round the staircase 5 15.568 77.84
77.84
Say 78.00 Rmt

b) Epoxy coving
BLOCK - A4
Operation Theatre 3 26.000 78.00
Sterilization 1 18.230 18.23
96.23
Say 97.00 RM

20 Dadooing with Ceramic Tiles


BLOCK - A4
Toilet near nurse station 1 8.620 2.100 18.10
Toilet near duty nurse 1 5.400 2.100 11.34
Toilet near officer incharge 1 5.400 2.100 11.34
Toilet near O.T Reception 1 12.064 2.100 25.33
Toilet near stores 2 6.000 2.100 25.20
Toilet at post operative ward 1 9.670 2.100 20.31
MIDDLE
Toilet at House Keeping 1 6.000 2.100 12.60
Toilet at Floor Admin 1 6.000 2.100 12.60
Toilet at Floor Admin 1 6.000 2.100 12.60
WC 2 5.430 2.100 22.81
WC bath 2 5.430 2.100 22.81
toilet at lab 1 5.400 2.100 11.34
toilet at security 1 5.400 2.100 11.34
Space between WC 1 5.040 2.100 10.58
BLOCK - B3
Toilets in duty doctor 1 6.600 2.100 13.86
Toilets in duty nurse 1 6.600 2.100 13.86
Toilet in rooms 18 6.600 2.100 249.48
Deductions
D5 -1 0.900 2.100 -1.89
D6 -30 0.800 2.100 -50.40
453.21
Say 454.00 Sqm

APMSIDC-PALASA DET-THIRD FLOOR 513 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
21 Dadooing in wards & corridor
Pre operative Ward 1 35.020 1.500 52.53
post operative Ward 1 45.450 1.500 68.18
POST OP I.C.U. WARD 1 60.950 1.500 91.43
BLOCK - A4
2.4 m wide corridor(v) 1 22.220 1.500 33.33
2.4 m wide corridor(v) 1 61.650 1.500 92.48
corridor(v) near scrubs 1 15.830 1.500 23.75
corridor(v) b/w stores 1 19.580 1.500 29.37
corridor(v) b/w stores 1 19.580 1.500 29.37
corridor(v) near c.s.s.d 1 29.390 1.500 44.09
3.0 m wide corridor(H) 1 76.640 1.500 114.96
2.0 m wide corridor(H) 1 16.920 1.500 25.38
3.0 m wide corridor(H) Near class IV
room 1 47.490 1.500 71.24
Near Dumb Water 1 10.740 1.500 16.11
MIDDLE
3.0 m wide corridor(H) 1 53.480 1.500 80.22
corridor(H) b/w Corridor & Security 1 26.740 1.500 40.11
BLOCK - B3
3.0 m wide corridor(H) 1 76.870 1.500 115.31
3.0 m wide corridor(H) 1 60.400 1.500 90.60
2.4 m wide corridor(V) 2 42.870 1.500 128.61
2.4 m wide corridor(V) 2 42.870 1.500 128.61
2.4 m wide corridor(V) near equipment
room 3 17.576 1.500 79.09
Deductions
ALD1 -4 1.800 1.500 -10.80
D6 -1 0.800 1.500 -1.20
D5 -2 0.900 1.500 -2.70
1340.04
Say 1341.00 Sqm

22 Whiting for ceiling


Same as ceiling plastering 2163.00
2163.00
Say 2163.00 Sqm

23 Wall putty
Same as internal plastering 6989.00
Pre operative Ward 1 8.920 8.590 76.62
Post Operative Ward 1 14.430 8.590 123.95
ICU 1 11.200 12.800 143.36
Pay Rooms 1 11.200 12.800 143.36
7476.30
Say 7477.00 Sqm

24 Plastic Emulsion Paint for interior


faces of walls
Same as internal plastering 6989.00
6989.00
Say 6989.00 Sqm

25
Emulsion paint for external plastering
Same external plastering @ 60% 1296.00

APMSIDC-PALASA DET-THIRD FLOOR 514 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
1296.00
Say 1296.00 Sqm

26 Texture Paint for Exterrnal Walls

Same as of external plastering @ 40% 864.00


864.00
Say 864.00 Sqm

27 Cinder Filling
Toilet Blocks 4 7.085 4.730 0.300 40.21
40.21
Say 41.00 cum

28 Impervious coat 4 23.630 0.300 28.36


Say 29.00 Sqm

24 Cladding with Granite


Lifts 2 2.400 3.450 16.56
Deductions
W -2 2.400 2.600 -12.48
4.08
Say 5.00 Sqm
27 Doors
D2 9 1.500 2.600 35.10
35.10
Say 36.00 Sqm

D3 11 1.200 2.600 34.32


34.32
Say 35.00 Sqm

D4 10 1.000 2.600 26.00


26.00
Say 26.00 Sqm

D5 29 0.900 2.100 54.81


54.81
Say 54.81 Sqm

D6 (0.8 X 2.10) - Frame 49 5.000 245.00


245.00
Say 245.00 RM

D6 49 0.800 2.100 82.32


82.32
Say 82.32 Sqm

OT 4 2.010 2.600 20.90


Say 20.91 Sqm

ALD1 24 2.000 2.600 124.80


124.80
Say 125.00 Sqm
28 UPVC Sliding Windows(Without
Mess)

APMSIDC-PALASA DET-THIRD FLOOR 515 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
W1 33 1.800 1.800 106.92

W2 4 1.500 1.800 10.80

W3 14 1.200 1.800 30.24

Total Quantity 147.96 Sqm

29 UPVC Sliding Windows(With Mess)


W1 2 1.800 1.800 6.48

Total Quantity 6.48 Sqm

30 Ventilators
V5 58 0.600 0.500 17.40
17.40
Say 17.40 Sqm

31 MS Grill for Windows @ 15 Kg/Sqm


W1 35 1.800 1.800 113.40
W2 4 1.500 1.800 10.80
W3 14 1.200 1.800 30.24
V5 58 0.600 0.500 17.40
171.84 Sqm
Say 172.00 Sqm
2580.00 Kgs
32 RCC Jally Windows
JW 16 1.800 1.800 51.84
51.84
Say 52.00 Sqm

1 RCM Drop
Duct 2 1 6.000 0.450 5.40
5.40
Say 6.00 Sqm
33 Painting to iron Work
Quantity Same as MS Grill 172.00
Say 172.00 Sqm

34 Railing
Staircase
Staircase 5 7.000 0.900 31.50
Duct 2 1 6.000 0.900 10.80
42.30
Say 43.00 Sqm
b cupboards
Change Room 1 4 2.400 2.100 20.16
OT records Room 1 1 3.780 2.100 7.94
OT pharmacy Store 1 2 4.800 2.100 20.16
Store 1 2 2.890 2.100 12.14
Class IV Room 1 2 4.070 2.100 17.09
Dirty Utility 1 2 2.890 2.100 12.14
89.63
Say 90.00 Sqm

35 Grip bar

APMSIDC-PALASA DET-THIRD FLOOR 516 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Staircase 5 14.830 74.15
Ramp 1 47.100 47.10
121.25
Say 122.00 Rmt

36 False ceiling
Pre operative Ward 1 8.920 8.590 76.62
Post Operative Ward 1 14.430 8.590 123.95
ICU 1 11.200 12.800 143.36
Pay Rooms 1 11.200 12.800 143.36
487.30
Say 488.00 Sqm

37 Structural glazing
Pre Operative Ward 1 2.400 3.000 7.20
Change Room 1 2.400 3.000 7.20
Post OP I.C.U WARD 2 2.400 3.000 14.40
2 5.020 3.000 30.12
Staircase 2 1.800 3.000 10.80
69.72
Say 70.00 SQM

38 Structural Glazing with top hung


shutters
20% of above quantity 13.94
13.94
Say 14.00 Sqm

39 Mastic pad
Roof beams
Horizontal 2 3.460 0.450 3.11
3.11
Say 4.00 Sqm

40 Expansion joint treatment


Roof beams
Horizontal 2 3.460 6.92
6.92
Say 7.00 Rmt

41 Aluminium sheet
Roof beams
Horizontal 2 3.460 6.92
6.92
Say 7.00 Rmt

APMSIDC-PALASA DET-THIRD FLOOR 517 OF 1048


#REF!

DETAILED ESTIMATE - THIRD FLOOR


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
1 Columns Second Top to Roof slab
bottom
Block-A & Ramp Block
C1 13 0.380 0.600 3.475 10.30
C2 20 0.380 0.600 3.475 15.85
C3 12 0.380 0.600 3.475 9.51
C4 5 0.450 0.750 3.475 5.86
C5 10 0.460 0.600 3.475 9.59
C6 6 0.460 0.600 3.475 5.75
C7 4 0.460 0.600 3.475 3.84
C8 2 0.600 0.600 3.475 2.50
C9 2 0.600 0.600 3.475 2.50
C10 2 0.600 0.600 3.475 2.50
C11 7 0.600 0.750 3.475 10.95
C12 19 0.600 0.750 3.475 29.71
C13 11 0.600 0.750 3.475 17.20
Block-(-B)
C4 5 0.450 0.750 3.450 5.82
C5 8 0.460 0.600 3.450 7.62
C6 6 0.460 0.600 3.450 5.71
C7 4 0.460 0.600 3.450 3.81
C8 2 0.600 0.600 3.450 2.48
C9 2 0.600 0.600 3.450 2.48
C10 2 0.600 0.600 3.450 2.48
C11 7 0.600 0.750 3.450 10.87
C12 19 0.600 0.750 3.450 29.50
C13 11 0.600 0.750 3.450 17.08
213.92
Say 214.00 Cum

2 Roof Beams
Horizontal
Block-A
T1-T4 1 7.120 0.300 0.300 0.64
Deduction of Columns -2 0.750 0.300 0.300 -0.14
T4-T5 1 2.400 0.380 0.275 0.25
T5-T7 1 2.800 0.300 0.300 0.25
T7-T10 2 7.700 0.230 0.450 1.59
T10-T16 2 13.810 0.300 0.300 2.49
Deduction of Columns -8 0.750 0.300 0.300 -0.54
Secondary Beam 2 9.520 0.300 0.300 1.71
Deduction of Columns -2 0.230 0.300 0.300 -0.04
Q1-Q2 1 3.310 0.300 0.300 0.30
Q2-Q4 1 2.310 0.380 0.300 0.26
Q4-Q5 1 2.400 0.380 0.275 0.25
Q5-Q10 1 11.250 0.230 0.450 1.16
Q10-Q12 1 2.800 0.300 0.300 0.25
Q12-Q13 1 2.400 0.380 0.275 0.25
Q13-Q16 1 7.120 0.300 0.300 0.64
O1-O5 4 9.520 0.450 0.575 9.85
O5-O12 2 16.290 0.300 0.275 2.69

APMSIDC-PALASA DET-SECOND FLOOR 518 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Deduction of Columns -8 0.750 0.300 0.275 -0.50
M5-M8 4 4.170 0.300 0.275 1.38
O12-O16 4 9.520 0.450 0.575 9.85
G1-G16 2 35.320 0.300 0.300 6.36
Deduction of Columns -4 0.450 0.300 0.300 -0.16
Deduction of Columns -8 0.600 0.300 0.300 -0.43
E1-E3 1 4.300 0.300 0.400 0.52
Cantilever Beams 2 1.000 0.300 0.300 0.18
Ramp Block
R19-R21 5 5.100 0.230 0.355 2.08
Deduction of Columns -4 0.380 0.230 0.355 -0.12
K17-K19 4 5.860 0.230 0.275 1.48
Deduction of Columns -8 0.380 0.230 0.275 -0.19
I17-I23 1 16.820 0.230 0.275 1.06
Deduction of Columns -5 0.380 0.230 0.275 -0.12
H17-H18 2 5.080 0.230 0.300 0.70
Deduction of Columns -4 0.380 0.230 0.300 -0.10
H18-H22 1 10.360 0.230 0.450 1.07
Deduction of Columns -2 0.230 0.230 0.450 -0.05
G17-G19 2 7.480 0.230 0.300 1.03
Deduction of Columns -4 0.380 0.230 0.300 -0.10
G19-G21 3 4.800 0.230 0.380 1.26
F18-F19 2 2.180 0.230 0.300 0.30
Block-(-B)
T39-T33 3 13.060 0.300 0.300 3.53
Deduction of Columns -9 0.750 0.300 0.300 -0.61
T33-T30 2 7.700 0.230 0.450 1.59
Secondary Beam 2 9.520 0.300 0.300 1.71
Deduction of Columns -2 0.230 0.300 0.300 -0.04
Q1-Q38 1 3.310 0.300 0.300 0.30
Q38-Q36 1 2.310 0.380 0.300 0.26
Q36-Q35 1 2.400 0.380 0.275 0.25
Q35-Q30 1 11.250 0.230 0.450 1.16
O39-O35 4 9.520 0.450 0.575 9.85
O35-O28 4 16.290 0.300 0.275 5.38
Deduction of Columns -16 0.750 0.300 0.275 -0.99
O28-O24 4 9.520 0.450 0.575 9.85
G39-G24 2 35.320 0.300 0.300 6.36
Deduction of Columns -4 0.450 0.300 0.300 -0.16
Deduction of Columns -8 0.600 0.300 0.300 -0.43
E39-E38 1 4.300 0.300 0.400 0.52
Cantilever Beams 2 1.000 0.300 0.300 0.18
Vertical
Block-A
B1-E1 2 1.360 0.300 0.300 0.24
E1-G1 2 5.330 0.300 0.450 1.44
G1-H1 8 3.000 0.300 0.300 2.16
H1-O1 6 19.040 0.300 0.425 14.57
Deduction of Columns -24 0.600 0.300 0.425 -1.84
O1-Q1 2 3.000 0.230 0.300 0.41
O2-Q2 4 3.000 0.300 0.300 1.08
Q1-T1 6 5.720 0.230 0.450 3.55
Q5-T5 4 5.720 0.230 0.475 2.50
Deduction of Columns -1 0.600 0.230 0.475 -0.07
Secondary Beam 1 1.400 0.300 0.325 0.14
Secondary Beam 1 4.330 0.300 0.325 0.42

APMSIDC-PALASA DET-SECOND FLOOR 519 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
B5-G5 4 8.940 0.380 0.475 6.45
Deduction of Columns -8 0.750 0.380 0.475 -1.08
Ramp Block
D17-G17 2 5.860 0.230 0.450 1.21
G17-H17 4 3.000 0.230 0.300 0.83
H17-J17 2 5.750 0.230 0.450 1.19
J17-K17 2 2.560 0.230 0.300 0.35
D18-I18 2 12.920 0.230 0.300 1.78
Deduction of Columns -8 0.750 0.230 0.300 -0.41
I18-K18 2 6.050 0.230 0.380 1.06
C19-G19 2 8.640 0.230 0.300 1.19
Deduction of Columns -8 0.750 0.230 0.300 -0.41
G19-I19 2 5.860 0.230 0.450 1.21
I19-J19 3 2.890 0.230 0.275 0.55
J19-L19 3 4.930 0.230 0.425 1.45
L19-N19 3 3.490 0.230 0.355 0.85
N19-P19 3 3.850 0.230 0.355 0.94
P19-R19 2 2.760 0.230 0.275 0.35
Block-B
B39-E39 2 1.360 0.300 0.300 0.24
E39-G39 2 5.330 0.300 0.450 1.44
G39-H39 8 3.000 0.300 0.300 2.16
H39-O39 6 19.040 0.300 0.425 14.57
Deduction of Columns -24 0.600 0.300 0.425 -1.84
O39-Q39 6 3.000 0.230 0.300 1.24
Q39-T39 6 5.720 0.230 0.450 3.55
Q35-T35 4 5.720 0.230 0.475 2.50
Deduction of Columns -1 0.600 0.230 0.475 -0.07
Secondary Beam 1 1.400 0.300 0.325 0.14
Secondary Beam 1 4.330 0.300 0.325 0.42
B35-G35 6 8.940 0.380 0.475 9.68
Deduction of Columns -10 0.750 0.380 0.475 -1.35
Deduction of Columns -2 0.600 0.380 0.475 -0.22
160.69
Say 161.00 Cum

3 Roof slab
i) Roof Slab 125mm thick
Ramp Block 1 432.775 432.78
Ded Of Staircase -1 5.100 5.700 -29.07
Ded Of Lift -2 2.400 3.000 -14.40
Deduction of Ramp -1 5.100 21.000 -107.10
282.21
Say 283.00 Sqm

ii) Roof Slab 150mm thick


Block-(A) 1 40.600 35.780 1452.67
Ded Of Staircase -1 5.300 4.430 -23.48
Ded Of Staircase -1 4.300 5.300 -22.79
Ded Of Duct -1 6.000 18.575 -111.45
Block-(-B) 1 40.600 35.780 1452.67
Ded Of Staircase -1 5.300 4.430 -23.48
Ded Of Staircase -1 4.300 5.300 -22.79
Ded Of Duct -1 6.000 18.575 -111.45
Deduction of 175mm Thick Slab -943.51
1646.39

APMSIDC-PALASA DET-SECOND FLOOR 520 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Say 1647.00 Sqm

iii) Roof Slab 175mm thick


H1-H5 x H1-O1 2 2 9.980 19.040 760.08
H31-H32 x H31-O31 1 1 6.460 19.040 123.00
B31-B32 x B31-G31 1 1 6.760 8.940 60.43
943.51
Say 944.00 Sqm
v) Waist slab (175mm thick)
Staircase (Flight -1& Flight-2) 2 2 3.600 2.000 28.80
Mid landing 2 1 2.000 4.430 17.72
Staircase (Flight -1& Flight-2) 2 2 3.600 2.000 28.80
Mid landing 2 1 2.000 4.300 17.20
Staircase (Flight -1& Flight-2) 1 2 3.600 2.400 17.28
Mid landing 1 1 5.100 2.400 12.24
Ramp 1 2 18.000 2.460 88.56
Mid landing 1 1 5.100 3.000 15.30
225.90
Say 226.00 Sqm

4 RCC M20 grade mix


a Platforms
Block-A
Store 1 3.045 0.600 1.83
Store 1 4.800 0.600 2.88
Pharmacy 1 5.965 0.600 3.58
Class IV Room 1 3.995 0.600 2.40
Block-(-B)
Store 1 3.045 0.600 1.83
IPM Labs 1 57.293 0.600 34.38
Standard LAB 4 18.802 0.600 45.12
Diffrerent Research lab 3 19.530 0.600 35.15
LAB 3 17.300 0.600 31.14
Class IV Room 1 3.995 0.600 2.40
160.70
Say 161.00 Sqm
b Loft
Block-A
Store 1 3.045 0.600 1.83
Store 1 4.800 0.600 2.88
Class IV Room 1 3.995 0.600 2.40
Ramp Block
Laboratory 1 3.000 0.600 1.80
House Keeping 1 6.230 0.600 3.74
Block-(-B)
Store 1 3.045 0.600 1.83
Pay Room 1 18 1.200 0.600 12.96
Dirty Utility 1 2 2.890 0.600 3.47
30.90
Say 31.00 Sqm

Total Platforms & Lofts 191.70


Say 192.00 Sqm

c Racks and shelves 25mm

APMSIDC-PALASA DET-SECOND FLOOR 521 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Block-(A)
Store 3 1 2.000 0.450 2.70
Store 3 1 2.000 0.450 2.70
Instruments Store 3 1 2.500 0.450 3.38
Pharmacy 3 2 2.000 0.450 5.40
Ramp Block
Laboratory 3 1 2.000 0.450 2.70
Block-(-B)
Rooms 3 20 2.000 0.450 54.00
Pay Room 3 18 1.200 0.450 29.16
Dirty Utility 3 2 2.890 0.450 7.80
107.84
Say 108.00 Sqm

d sill slabs
W1 75 2.260 0.230 0.050 8.48
W2 26 1.960 0.230 0.050 2.55
11.02
Say 12.00 cum

5 230mm thick brick masonary


Horizontal
Block A
Toilet Block to Dirty Utility 2 13.810 0.225 3.150 19.58
Deduction of columns -8 0.750 0.225 3.150 -4.25
Staircase 2 7.700 0.225 3.000 10.40
Toilet Block to Store 2 13.810 0.225 3.150 19.58
Deduction of columns -8 0.750 0.225 3.150 -4.25
Passage Beside Toilet Block 2 6.060 0.225 3.450 9.41
Toilet 2 7.115 0.225 3.150 10.09
Deduction of columns -4 0.750 0.225 3.150 -2.13
Electrical Room 1 4.975 0.225 3.150 3.53
Class IV 1 3.000 0.225 3.150 2.13
Superintendent 5 6.885 0.225 3.000 23.24
Cabins 4 3.645 0.225 3.150 10.33
Store 1 4.300 0.225 3.150 3.05
Store To Waiting 1 35.320 0.225 3.150 25.03
Deduction of columns -6 0.600 0.225 3.150 -2.55
Ramp Block
Staircase to Attached Toilet 2 6.090 0.225 3.175 8.70
Deduction of columns -6 0.380 0.225 3.175 -1.63
Staircase 2 5.100 0.225 3.095 7.10
House Keeping 2 3.460 0.225 3.175 4.94
Deduction of columns -4 0.380 0.225 3.175 -1.09
Lift 2 2.630 0.225 3.175 3.76
Deduction of columns -2 0.380 0.225 3.175 -0.54
Between Open to Sky 4 3.000 0.225 3.175 8.57
Security 2 3.460 0.225 3.175 4.94
Deduction of columns -4 0.380 0.225 3.175 -1.09
Attandent waiting 4 6.090 0.225 3.175 17.40
Deduction of columns -8 0.380 0.225 3.175 -2.17
Ramp 1 5.100 0.225 3.095 3.55
Block B
Service Corridor to Store 1 13.810 0.225 3.150 9.79
Deduction of columns -4 0.750 0.225 3.150 -2.13
Staircase 1 7.700 0.225 3.000 5.20

APMSIDC-PALASA DET-SECOND FLOOR 522 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Research Lab 1 13.810 0.225 3.150 9.79
Electrical Room 1 2.820 0.225 3.150 2.00
Staircase 1 5.300 0.225 3.000 3.58
Water 1 1.430 0.225 3.000 0.97
Research Lab 4 7.115 0.225 3.000 19.21
Lab 4 3.645 0.225 3.150 10.33
IPM To Standard Lab 1 31.020 0.225 3.150 21.99
Deduction of columns -2 0.450 0.225 3.150 -0.64
Deduction of columns -4 0.600 0.225 3.150 -1.70
IPM To Store 1 35.320 0.225 3.150 25.03
Deduction of columns -6 0.600 0.225 3.150 -2.55
Vertical
Block A2
Store 2 1.360 0.225 3.150 1.93
Staircase 2 5.330 0.225 3.000 7.20
Lobby 1 3.000 0.225 3.150 2.13
Meeting Hall To Chamber 4 19.035 0.225 3.000 51.39
Deduction of columns -16 0.600 0.225 3.000 -6.48
AHU Room 4 3.000 0.225 3.150 8.51
Toilet 2 5.720 0.225 3.000 7.72
PHC 2 1.500 0.225 3.450 2.33
Toilet 2 3.010 0.225 3.450 4.67
Water 2 1.730 0.225 3.450 2.69
Meeting Hall 1 9.190 0.225 3.425 7.08
Chamber 1 6.575 0.225 3.425 5.07
Waiting 1 7.440 0.225 3.000 5.02
Ramp Block
House Keeping 2 6.640 0.225 3.095 9.25
Deduction of columns -2 0.450 0.225 3.095 -0.63
House Keeping 2 6.640 0.225 3.175 9.49
Deduction of columns -4 0.450 0.225 3.175 -1.29
Staircase side walls 2 8.640 0.225 3.175 12.34
Deduction of columns -6 0.600 0.225 3.175 -2.57
Security 2 3.460 0.225 3.175 4.94
Deduction of columns -4 0.600 0.225 3.175 -1.71
Attandent waiting to Security 2 9.510 0.225 3.175 13.59
Deduction of columns -4 0.750 0.225 3.175 -2.14
Attandent waiting 2 6.510 0.225 3.175 9.30
Deduction of columns -2 0.750 0.225 3.175 -1.07
Ramp walls 2 14.510 0.225 3.175 20.73
Deduction of columns -8 0.600 0.225 3.175 -3.43
Block B
IPM Labs 1 7.410 0.225 3.000 5.00
Standard Lab 1 8.480 0.225 3.450 6.58
Store 2 1.360 0.225 3.150 1.93
Staircase 2 5.330 0.225 3.000 7.20
Lobby 1 3.000 0.225 3.150 2.13
Research Lab 1 To 2 4 19.035 0.225 3.000 51.39
Deduction of columns -16 0.600 0.225 3.000 -6.48
AHU Room 3 3.000 0.225 3.150 6.38
Toilets 2 5.720 0.225 3.000 7.72
Toilets 1 3.115 0.225 3.450 2.42
Toilets 1 4.660 0.225 3.450 3.62
Staircase 2 5.420 0.225 3.000 7.32
Water 2 1.730 0.225 3.450 2.69
Deductions

APMSIDC-PALASA DET-SECOND FLOOR 523 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
D2 -3 1.500 0.225 2.600 -2.63
D3 -5 1.200 0.225 2.600 -3.51
D5 -12 0.900 0.225 2.100 -5.10
ALD1 -1 2.000 0.225 2.600 -1.17
FD1 -2 2.000 0.225 2.100 -1.89
FD2 -2 1.500 0.225 2.100 -1.42
W1 -75 1.800 0.225 1.800 -54.68
W2 -26 1.500 0.225 1.800 -15.80
V5 -60 0.600 0.225 0.500 -4.05
JW -60 1.800 0.225 1.800 -43.74
Lift -2 1.000 0.225 2.100 -0.95
Lintels
D2 -3 1.960 0.225 0.175 -0.23
D3 -5 1.660 0.225 0.175 -0.33
D5 -12 1.360 0.225 0.175 -0.64
ALD1 -1 2.460 0.225 0.175 -0.10
FD1 -2 2.460 0.225 0.175 -0.19
FD2 -2 1.960 0.225 0.175 -0.15
W1 -75 2.260 0.225 0.175 -6.67
W2 -26 1.960 0.225 0.175 -2.01
V5 -60 1.060 0.225 0.175 -2.50
JW -60 2.260 0.225 0.175 -5.34
Lift -2 1.460 0.225 0.175 -0.11
387.20
Say 388.00 Cum
6
115 mm thick Brick masonry walls
BLOCK A3
Horizontal
BLOCK A
WC 2 2.630 3.450 18.15
WC 2 3.945 3.450 27.22
PHC 2 3.055 3.450 21.08
Staff Toilet 2 1.315 3.450 9.07
Electrical Room 2 3.950 3.450 27.26
Corridor Walls 6 3.000 3.450 62.10
PA 1 3.470 3.425 11.88
Attached Toi 1 1.915 3.425 6.56
Cabins 7 4.800 3.450 115.92
Education Hall 2 7.000 3.425 47.95
Seminar Hall To Lecture Hall 1 26.790 3.150 84.39
Store 2 3.145 3.450 21.70
Vertical
Attendents Attached Toilets 6 1.315 3.450 27.22
House Keeping Attached Toilets 2 1.915 3.450 13.21
BLOCK B
WC 2 1.200 3.450 8.28
WC 1 2.630 3.450 9.07
Toilet 1 8.285 3.450 28.58
PHC Toi 1 2.545 3.450 8.78
Electrical Room 1 3.995 3.450 13.78
Corridor Walls 5 2.400 3.450 41.40
Research Lab 1 6.015 3.150 18.95
Duct Walls 2 6.000 1.000 12.00
Research Lab 2 7.000 3.425 47.95
Lab 2 4.800 2.100 20.16

APMSIDC-PALASA DET-SECOND FLOOR 524 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Vertical
Block-A
WC 12 1.500 3.450 62.10
Service Corridor 2 1.200 3.450 8.28
Electrical Room 2 2.895 3.000 17.37
Staff Toilet 2 1.695 3.450 11.70
Store 2 3.045 3.450 21.01
Ante Room Attached Toi 1 1.615 3.425 5.53
PA 1 5.885 3.425 20.16
Head Nurse To Cabin 1 19.035 3.000 57.11
Cabin 1 3.715 3.450 12.82
Stores Wall 1 3.000 3.475 10.43
Lecture Hall 3 8.595 3.450 88.96
Central Block
Attendents Attached Toilets 2 6.045 3.475 42.01
House Keeping Attached Toilets 2 1.200 3.475 8.34
Block-B
WC 1 3.115 3.450 10.75
WC 3 1.500 3.450 15.53
Store 1 3.045 3.450 10.51
Electrical Room 1 2.895 3.000 8.69
Research Lab 4 19.035 3.425 260.78
Deductions
D2 -13 1.500 2.600 -50.70
D3 -5 1.200 2.600 -15.60
D5 -12 0.900 2.100 -22.68
D6 -36 0.800 2.100 -60.48
ALD1 -6 2.000 2.600 -31.20
FD1 -8 2.000 2.100 -33.60
1160.45
Say 1161.00 Sqm

7 PCC for Steps


Staircase 0.5 44 2.000 0.300 0.150 1.98
Staircase 0.5 44 2.000 0.300 0.150 1.98
Staircase 0.5 22 2.400 0.300 0.150 1.19
5.15
Say 6.00 cum
8 PCC (1:3:6) for Bedblocks
under lintels
D2 2 3 0.300 0.225 0.150 0.06
D3 2 5 0.300 0.225 0.150 0.10
D5 2 12 0.300 0.225 0.150 0.24
ALD1 2 1 0.300 0.225 0.150 0.02
FD1 2 2 0.300 0.225 0.150 0.04
FD2 2 2 0.300 0.225 0.150 0.04
W1 2 75 0.300 0.225 0.150 1.52
W2 2 26 0.300 0.225 0.150 0.53
V5 2 60 0.300 0.225 0.150 1.22
JW 2 60 0.300 0.225 0.150 1.22
Lift 2 2 0.300 0.225 0.150 0.04
D2 2 13 0.300 0.115 0.150 0.13
D3 2 5 0.300 0.115 0.150 0.05
D5 2 12 0.300 0.115 0.150 0.12
D6 2 36 0.300 0.115 0.150 0.37
ALD1 2 6 0.300 0.115 0.150 0.06

APMSIDC-PALASA DET-SECOND FLOOR 525 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
FD1 2 8 0.300 0.115 0.150 0.08
Hold fasts
W1 4 15 0.230 0.225 0.150 0.47
D2 6 3 0.300 0.225 0.150 0.18
D3 6 5 0.300 0.225 0.150 0.30
D5 6 12 0.300 0.225 0.150 0.73
ALD1 6 1 0.300 0.225 0.150 0.06
FD1 6 2 0.300 0.225 0.150 0.12
FD2 6 2 0.300 0.225 0.150 0.12
W1 4 75 0.300 0.225 0.150 3.04
W2 4 26 0.300 0.225 0.150 1.05
V5 2 60 0.300 0.225 0.150 1.22
JW 2 60 0.300 0.225 0.150 1.22
Lift 2 2 0.300 0.225 0.150 0.04
D2 6 13 0.300 0.115 0.150 0.40
D3 6 5 0.300 0.115 0.150 0.16
D5 6 12 0.300 0.115 0.150 0.37
D6 6 36 0.300 0.115 0.150 1.12
ALD1 6 6 0.300 0.115 0.150 0.19
FD1 6 8 0.300 0.115 0.150 0.25
16.88
Say 17.00 Cum

9 Lintels
D2 3 1.960 0.225 0.175 0.23
D3 5 1.660 0.225 0.175 0.33
D5 12 1.360 0.225 0.175 0.64
ALD1 1 2.460 0.225 0.175 0.10
FD1 2 2.460 0.225 0.175 0.19
FD2 2 1.960 0.225 0.175 0.15
W1 75 2.260 0.225 0.175 6.67
W2 26 1.960 0.225 0.175 2.01
V5 60 1.060 0.225 0.175 2.50
JW 60 2.260 0.225 0.175 5.34
Lift 2 1.460 0.225 0.175 0.11
D2 13 1.500 0.115 0.175 0.39
D3 5 1.200 0.115 0.175 0.12
D5 12 0.900 0.115 0.175 0.22
D6 36 0.800 0.115 0.175 0.58
ALD1 6 2.000 0.115 0.175 0.24
FD1 8 2.000 0.115 0.175 0.32
20.16
Say 21.00 Cum

10 Sunshades
W1 75 2.260 169.50
W2 26 1.960 50.96
220.46
Say 221.00 Rmt

11 Sill slabs
W1 75 2.260 0.230 0.050 1.95
W2 26 1.960 0.230 0.050 0.59
V5 60 1.060 0.230 0.050 0.73
3.27
Say 3.30 cum

APMSIDC-PALASA DET-SECOND FLOOR 526 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
12 TMT STEEL
Columns upto 3.60 mts levael 213.92 200.000 Kgs/Cum 42784.06
Roof beams 160.69 200.000 Kgs/Cum 32137.52
125mm thick Roof slab 283.00 10.000 Kgs/Sqm 2830.00
150mm thick Roof slab 1647.00 12.000 Kgs/Sqm 19764.00
175mm thick Roof slab 944.00 14.000 Kgs/Sqm 13216.00
175mm thick waist slab 226.00 14.000 Kgs/Sqm 3164.00
Lintels 21.00 80.000 Kgs/Cum 1680.00
115575.58
Say 115.60 MT

13 Mild Steel
Sunshades 220.46 4.000 Kgs/RM 881.84
Platforms & Lofts 280.560 4.000 Kgs/Sqm 1122.24
Shelves 108.000 4.000 Kgs/Sqm 432.00
Sillslab 3.267 4.000 Kgs/Sqm 13.07
RBM 1160.5 0.500 Kgs/Sqm 580.23
3029.37
Say 3.03 MT

14 External plastering
All round the Building 1 415.736 3.600 1496.65
Duct at A4 1 49.150 3.600 176.94
Duct at B3 1 49.150 3.600 176.94
Ramp offset walls 2 18.000 3.600 129.60
Deductions
W1 75 1.800 1.800 243.00
W2 26 1.500 1.800 70.20
V5 60 0.600 0.500 18.00
2311.33
Say 2312.00 Sqm

15 Ceiling plastering
Qty Same as Waist slab 226.00
Qty Same as Ceramic flooring 129.13

Qty Same as Cheqqured tiles flooring 103.14


458.27
Say 459.00 Sqm

16
Internal plastering 12 mm thick
BLOCK - A4
Seminar Hal 1 30.330 3.475 105.40
Lecture Hall 1 50.050 3.475 173.92
Stores 1 13.270 3.475 46.11
Pantry 1 13.270 3.475 46.11
Meeting Hall 1 26.000 3.475 90.35
PA Room 1 11.940 3.475 41.49
Ante Room 1 18.370 3.475 63.84
Superintendent Chamber 1 26.000 3.475 90.35
Cabins1-6 6 10.690 3.475 222.89
RMO Room 1 15.600 3.475 54.21
Pantry 1 15.600 3.475 54.21
Head Nurse Room 1 15.600 3.475 54.21
AHU Room 2 14.170 3.475 98.48

APMSIDC-PALASA DET-SECOND FLOOR 527 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Electrical Room 1 14.220 3.475 49.41
Store Rooms 2 11.360 3.475 78.95
Before Staircase 1 17.580 3.475 61.09
Class IV Room 1 14.220 3.475 49.41
Maintainance Section 1 21.830 3.475 75.86
Establishment Section 1 21.830 3.475 75.86
Command Control Section 1 21.830 3.475 75.86
Infront OF staircase 1 16.100 3.475 55.95
Communication Center 1 32.580 3.475 113.22
InformationEducation Hall 1 32.580 3.475 113.22
Lobby & Waiting Area 1 27.180 3.475 94.45
3.0mt wide Corridor 1 67.810 3.475 235.64
3.0mt wide Corridor 1 60.400 3.475 209.89
Beside Staircase 1 10.740 3.475 37.32
2.40mt wide Corridor 2 42.870 3.475 297.95
2.40mt wide Corridor 2 17.350 3.475 120.58
Before Staircase 1 16.160 3.475 56.16
MIDDLE
Attendants Waiting Room(Female) 1 20.720 3.475 72.00
Laboratory 1 12.000 3.475 41.70
Attendants Waiting Room(male) 1 20.720 3.475 72.00
Security 1 12.000 3.475 41.70
House Keeping 1 15.830 3.475 55.01
Floor Administrator 1 15.830 3.475 55.01
3.0 m wide corridor(H) 1 53.480 3.475 185.84
corridor(H) b/w Corridor & Security 1 26.740 3.475 92.92
Pressurization 2 10.800 3.475 75.06
BLOCK - B4
IPM Lab 1 64.800 3.475 225.18
Standard Lab 1 30.240 3.475 105.08
Store Room 1 13.400 3.475 46.57
Research Labs 2 & 3 2 32.460 3.475 225.60
Standard Lab 2 & 3 2 28.060 3.475 195.02
Research Labs-1 1 39.710 3.475 137.99
1 20.230 3.475 70.30
Electrical Room 1 14.220 3.475 49.41
Stores 1 11.360 3.475 39.48
A.H.U. Room 1 14.170 3.475 49.24
Different Research Labs 2 & 3 2 32.460 3.475 225.60
Standard Lab 2 28.060 3.475 195.02
3.0mt wide Corridor 1 67.810 3.475 235.64
3.0mt wide Corridor 1 54.290 3.475 188.66
Beside Staircase 1 10.740 3.475 37.32
Before Staircase 1 17.580 3.475 61.09
Beside Toilets 1 19.800 3.475 68.81
Before PHC Toilet 1 8.920 3.475 31.00
1 7.350 3.475 25.54
2.40mt wide Corridor 2 41.170 3.475 286.13
Before Staircase 1 16.160 3.475 56.16
BLOCK - A4
Toilet in Ante Room 1 6.600 3.475 22.94
Gents & ladies Toilet 2 12.110 3.475 84.16
2 10.660 3.475 74.09
WCs 8 5.400 3.475 150.12
Urinals Area 4 5.630 3.475 78.26
PHC Toilet 2 7.000 3.475 48.65

APMSIDC-PALASA DET-SECOND FLOOR 528 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
1.20mt wide Service Corridor 2 14.520 3.475 100.91
MIDDLE
Toilet at House Keeping 1 6.000 3.475 20.85
Toilet at Floor Admin 1 6.000 3.475 20.85
WC 2 5.430 3.475 37.74
WC bath 2 5.430 3.475 37.74
toilet at lab 1 5.400 3.475 18.77
toilet at security 1 5.400 3.475 18.77
Space between WC 1 5.040 3.475 17.51
BLOCK - B3
Ladies Toilet 1 8.030 3.475 27.90
1 5.630 3.475 19.56
WCs 3 5.400 3.475 56.30
Gents Toilet 1 8.260 3.475 28.70
1 8.960 3.475 31.14
WCs 2 5.400 3.475 37.53
PHC Toilet 1 8.690 3.475 30.20
1.20mt wide Service Corridor 1 18.510 3.475 64.32
Deductions
ALD1 -7 1.800 2.600 -32.76
D2 -16 1.500 2.600 -62.40
D3 -10 1.200 2.100 -25.20
D5 -12 0.900 2.100 -22.68
D6 -36 0.800 2.100 -60.48
Ded for Dadooing with glazed tiles for
Toilets -541.25
Ded for Dadooing in wards & corridor -1577.10
4893.58
Say 4894.00 Sqm
a 12 mm thick internal plastering
60% of above quantity (internal) 2936.15
Say 2936.00 Sqm
b 20 mm thick Internal plastering
40% of above quantity (external) 1957.43
Say 1957.00 Sqm

17 Flooring
a) Vitrified flooring
BLOCK - A4
Seminar Hal 1 6.570 8.595 56.47
Lecture Hall 1 16.430 8.595 141.22
Stores 1 3.145 3.490 10.98
Pantry 1 3.145 3.490 10.98
Meeting Hall 1 6.885 6.115 42.10
PA Room 1 3.470 2.500 8.68
Ante Room 1 3.300 5.885 19.42
Superintendent Chamber 1 6.885 6.115 42.10
Cabins1-6 6 2.345 3.000 42.21
RMO Room 1 4.800 3.000 14.40
Pantry 1 4.800 3.000 14.40
Head Nurse Room 1 4.800 3.000 14.40
AHU Room 2 4.085 3.000 24.51
Electrical Room 1 3.995 3.115 12.44
Store Rooms 2 2.635 3.045 16.05
Before Staircase 1 2.400 6.390 15.34
Class IV Room 1 3.995 3.115 12.44

APMSIDC-PALASA DET-SECOND FLOOR 529 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Maintainance Section 1 4.800 6.115 29.35
Establishment Section 1 4.800 6.115 29.35
Command Control Section 1 4.800 6.115 29.35
Infront OF staircase 1 4.300 3.750 16.13
Communication Center 1 7.000 9.290 65.03
InformationEducation Hall 1 7.000 9.290 65.03
Lobby & Waiting Area 1 4.300 9.290 39.95
3.0mt wide Corridor 1 30.905 3.000 92.72
3.0mt wide Corridor 1 27.200 3.000 81.60
Beside Staircase 1 3.640 1.730 6.30
2.40mt wide Corridor 2 2.400 19.035 91.37
2.40mt wide Corridor 2 2.400 6.275 30.12
Before Staircase 1 4.300 3.780 16.25
MIDDLE
Attendants Waiting Room(Female) 1 4.315 6.045 26.08
Laboratory 1 3.000 3.000 9.00
Attendants Waiting Room(male) 1 4.315 6.045 26.08
Security 1 3.000 3.000 9.00
House Keeping 1 3.000 4.915 14.75
Floor Administrator 1 3.000 4.915 14.75
3.0 m wide corridor(H) 1 23.740 3.000 71.22
corridor(H) b/w Corridor & Security 1 10.360 3.010 31.18
Pressurization 2 2.400 3.000 14.40
BLOCK - B4
IPM Lab 1 23.920 8.480 202.84
Standard Lab 1 6.640 8.480 56.31
Store Room 1 4.300 2.400 10.32
Research Labs 2 & 3 2 7.000 9.230 129.22
Standard Lab 2 & 3 2 4.800 9.230 88.61
Research Labs-1 1 13.580 6.275 85.21
1 7.000 3.115 21.81
Electrical Room 1 3.995 3.115 12.44
Stores 1 2.635 3.045 8.02
A.H.U. Room 1 4.085 3.000 12.26
Different Research Labs 2 & 3 2 7.000 9.230 129.22
Standard Lab 2 4.800 9.230 88.61
3.0mt wide Corridor 1 30.905 3.000 92.72
3.0mt wide Corridor 1 24.145 3.000 72.44
Beside Staircase 1 3.640 1.730 6.30
Before Staircase 1 2.400 6.390 15.34
Beside Toilets 1 8.285 1.615 13.38
Before PHC Toilet 1 1.230 3.230 3.97
1 1.130 2.545 2.88
2.40mt wide Corridor 2 2.400 18.185 87.29
Before Staircase 1 4.300 3.780 16.25
2462.55
Say 2463.00 Sqm
b) Granite flooring
i Treads
Staircase 5 22 2.000 0.300 66.00
66.00
Say 66.00 Sqm

ii Risers
Staircase 5 24 2.000 0.150 36.00
36.00

APMSIDC-PALASA DET-SECOND FLOOR 530 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Say 36.00 Sqm

iii Staircase Midlanding 5 1 4.230 2.000 42.30


42.30
Say 43.00 Sqm
d) Non skid ceramic flooring
BLOCK - A4
Toilet in Ante Room 1 1.800 1.500 2.70
Gents & ladies Toilet 2 2.940 3.115 18.32
2 3.830 1.500 11.49
WCs 8 1.200 1.500 14.40
Urinals Area 4 1.200 1.615 7.75
PHC Toilet 2 2.000 1.500 6.00
1.20mt wide Service Corridor 2 1.200 6.060 14.54
MIDDLE
Toilet at House Keeping 1 1.200 1.800 2.16
Toilet at Floor Admin 1 1.200 1.800 2.16
WC 2 1.515 1.200 3.64
WC bath 2 1.515 1.200 3.64
toilet at lab 1 1.200 1.500 1.80
toilet at security 1 1.200 1.500 1.80
Space between WC 1 1.320 1.200 1.58
BLOCK - B3
Ladies Toilet 1 2.515 1.500 3.77
1 1.200 1.615 1.94
WCs 3 1.200 1.500 5.40
Gents Toilet 1 2.630 1.500 3.95
1 1.365 3.115 4.25
WCs 2 1.200 1.500 3.60
PHC Toilet 1 2.545 1.800 4.58
1.20mt wide Service Corridor 1 8.055 1.200 9.67
129.13
Say 130.00 Sqm
d) Cheq. Tiles flooring
Ramp 2 1 18.300 2.400 87.84
Midlanding 1 1 5.100 3.000 15.30
103.14
Say 104.00 Sqm
18 High polished granite platforms
Qty same as Platforms 160.70
160.70
Say 161.00 Sqm

19 High Polished granite stone for Sill


slabs
W1 75 2.260 0.230 38.99
W2 26 1.960 0.230 11.72
V5 60 1.060 0.230 14.63
65.33
Say 66.00 Sqm
20 Skirting
a) Skirting with Vitrified
BLOCK - A4
Seminar Hal 1 30.330 30.33
Lecture Hall 1 50.050 50.05
Stores 1 13.270 13.27

APMSIDC-PALASA DET-SECOND FLOOR 531 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Pantry 1 13.270 13.27
Meeting Hall 1 26.000 26.00
PA Room 1 11.940 11.94
Ante Room 1 18.370 18.37
Superintendent Chamber 1 26.000 26.00
Cabins1-6 6 10.690 64.14
RMO Room 1 15.600 15.60
Pantry 1 15.600 15.60
Head Nurse Room 1 15.600 15.60
AHU Room 2 14.170 28.34
Electrical Room 1 14.220 14.22
Store Rooms 2 11.360 22.72
Before Staircase 1 17.580 17.58
Class IV Room 1 14.220 14.22
Maintainance Section 1 21.830 21.83
Establishment Section 1 21.830 21.83
Command Control Section 1 21.830 21.83
Infront OF staircase 1 16.100 16.10
Communication Center 1 32.580 32.58
InformationEducation Hall 1 32.580 32.58
MIDDLE
Attendants Waiting Room(Female) 1 20.720 20.72
Laboratory 1 12.000 12.00
Attendants Waiting Room(male) 1 20.720 20.72
Security 1 12.000 12.00
House Keeping 1 15.830 15.83
Floor Administrator 1 15.830 15.83
3.0 m wide corridor(H) 1 53.480 53.48
corridor(H) b/w Corridor & Security 1 26.740 26.74
Pressurization 2 10.800 21.60
BLOCK - B4
Electrical Room 1 14.220 14.22
Stores 1 11.360 11.36
A.H.U. Room 1 14.170 14.17
782.67
Say 783.00 Rmt

c) Skirting with Granite


All round the staircase 5 15.568 77.84
77.84
Say 78.00 Rmt

21 Dadooing with Ceramic Tiles


BLOCK - A4
Toilet in Ante Room 1 6.600 2.100 13.86
Gents & ladies Toilet 2 12.110 2.100 50.86
2 10.660 2.100 44.77
WCs 8 5.400 2.100 90.72
Urinals Area 4 5.630 2.100 47.29
PHC Toilet 2 7.000 2.100 29.40
1.20mt wide Service Corridor 2 14.520 2.100 60.98
MIDDLE
Toilet at House Keeping 1 6.000 2.100 12.60
Toilet at Floor Admin 1 6.000 2.100 12.60
WC 2 5.430 2.100 22.81
WC bath 2 5.430 2.100 22.81

APMSIDC-PALASA DET-SECOND FLOOR 532 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
toilet at lab 1 5.400 2.100 11.34
toilet at security 1 5.400 2.100 11.34
Space between WC 1 5.040 2.100 10.58
BLOCK - B3
Ladies Toilet 1 8.030 2.100 16.86
1 5.630 2.100 11.82
WCs 3 5.400 2.100 34.02
Gents Toilet 1 8.260 2.100 17.35
1 8.960 2.100 18.82
WCs 2 5.400 2.100 22.68
PHC Toilet 1 8.690 2.100 18.25
1.20mt wide Service Corridor 1 18.510 2.100 38.87
Deductions
D5 -10 0.900 2.100 -18.90
D6 -36 0.800 2.100 -60.48
541.25
Say 542.00 Sqm

22 Dadooing in wards & corridor


BLOCK - A4
3.0mt wide Corridor 1 67.810 1.500 101.72
3.0mt wide Corridor 1 60.400 1.500 90.60
Beside Staircase 1 10.740 1.500 16.11
2.40mt wide Corridor 2 42.870 1.500 128.61
2.40mt wide Corridor 2 17.350 1.500 52.05
Before Staircase 1 16.160 1.500 24.24
Lobby & Waiting Area 1 27.180 1.500 40.77
MIDDLE
3.0 m wide corridor(H) 1 53.480 1.500 80.22
corridor(H) b/w Corridor & Security 1 26.740 1.500 40.11
Pressurization 2 10.800 1.500 32.40
BLOCK - B3
IPM Lab 1 64.800 1.500 97.20
Standard Lab 1 30.240 1.500 45.36
Store Room 1 13.400 1.500 20.10
Research Labs 2 & 3 2 32.460 1.500 97.38
Standard Lab 2 & 3 2 28.060 1.500 84.18
Research Labs-1 1 39.710 1.500 59.57
1 20.230 1.500 30.35
Different Research Labs 2 & 3 2 32.460 1.500 97.38
Standard Lab 2 28.060 1.500 84.18
3.0mt wide Corridor 1 67.810 1.500 101.72
3.0mt wide Corridor 1 54.290 1.500 81.44
Beside Staircase 1 10.740 1.500 16.11
Before Staircase 1 17.580 1.500 26.37
Beside Toilets 1 19.800 1.500 29.70
Before PHC Toilet 1 8.920 1.500 13.38
1 7.350 1.500 11.03
2.40mt wide Corridor 2 41.170 1.500 123.51
Before Staircase 1 16.160 1.500 24.24
Deductions
D2 -16 1.500 1.500 -36.00
D3 -10 1.200 1.500 -18.00
D5 -14 0.900 1.500 -18.90
1577.10
Say 1578.00 Sqm

APMSIDC-PALASA DET-SECOND FLOOR 533 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY

23 Whiting for ceiling


Same as ceiling plastering 459.00
459.00
Say 459.00 Sqm

24 Wall putty
Same as internal plastering 4894.00
Qty Same as Vitrified flooring 2462.55
7356.55
Say 7357.00 Sqm

25 Plastic Emulsion Paint for interior


faces of walls
Same as internal plastering 4894.00
4894.00
Say 4894.00 Sqm

26 Emulsion paint for external


plastering
Same external plastering @ 60% 1387.20
1387.20
Say 1388.00 Sqm

27 Texture Paint for Exterrnal Walls

Same as of external plastering @ 40% 924.80


924.80
Say 925.00 Sqm

28 Doors
D2 15 1.500 2.600 58.50
58.50
Say 58.50 Sqm

D3 10 1.200 2.600 31.20


31.20
Say 32.00 Sqm

D5 24 0.900 2.100 45.36


45.36
Say 45.36 Sqm

D6 (0.8 X 2.10) - Frame 36 5.000 180.00


180.00
Say 180.00 RM

D6 36 0.800 2.100 60.48


60.48
Say 60.48 Sqm

ALD1 19 2.000 2.600 98.80


98.80
Say 99.00 Sqm
29 UPVC Sliding Windows(Without
Mesh)

APMSIDC-PALASA DET-SECOND FLOOR 534 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
W1 72 1.800 1.800 233.28
W2 35 1.500 1.800 94.50
Total Quantity 327.78 Sqm

30 Ventilators
V5 61 0.600 0.500 18.30
18.30
Say 18.30 Sqm

31
MS Grill for Windows @ 15 Kg/Sqm
W1 75 1.800 1.800 243.00
W2 35 1.500 1.800 94.50
V5 61 0.600 0.500 18.30
355.80 Sqm
Say 356.00 Sqm
5340.00 Kgs
32 RCC Jally Windows
JW 22 1.800 1.800 71.28
71.28
Say 72.00 Sqm

33 Painting to iron Work


Quantity Same as MS Grill 356.00
Say 356.00 Sqm

34 Railing
Staircase
Staircase 5 2 3.500 0.900 31.50
Duct 2 1 6.000 0.900 10.80
42.30
Say 43.00 Sqm
35 RCM Drop
Duct 2 1 6.000 0.450 5.40
5.40
Say 6.00 Sqm
b cupboards
Pay Room 1 18 1.200 2.100 45.36
Dirty Utility 1 2 2.890 2.100 12.14
57.50
Say 58.00 Sqm

35 Grip bar
Staircase 5 14.830 74.15
Ramp 1 47.100 47.10
121.25
Say 122.00 Rmt

36 False ceiling
Qty Same as Vitrified flooring 2462.55
2462.55
Say 2463.00 Sqm
37 Structural glazing
4 2.400 3.600 34.56
2 5.020 3.600 36.14
Staircase 2 1.800 3.000 10.80

APMSIDC-PALASA DET-SECOND FLOOR 535 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
81.50
Say 82.00 Sqm

38 Structural Glazing with top hung


shutters
20% of above quantity 16.30
16.30
Say 17.00 Sqm

39 Cladding with Granite


Lifts 2 2.400 3.450 16.56
Deductions
W -2 2.400 2.600 -12.48
4.08
Say 5.00 Sqm

40 Cinder Filling
Toilet Blocks 6 7.085 4.730 0.300 60.32
60.32
Say 61.00 cum

41 Impervious coat 6 23.630 0.300 42.53


Say 43.00 Sqm

42 Mastic pad
Roof beams
Horizontal 2 3.460 0.450 3.11
3.11
Say 4.00 Sqm

43 Expansion joint treatment


Roof beams
Horizontal 2 3.460 6.92
6.92
Say 7.00 Rmt

44 Aluminium sheet
Roof beams
Horizontal 2 3.460 6.92
6.92
Say 7.00 Rmt

APMSIDC-PALASA DET-SECOND FLOOR 536 OF 1048


#REF!

Detailed Estimate - Terrace Floor


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
1 VRCC
i Columns Upto Roof slab bottom
Staircase Head Room
Block A&B
C6 2 1 0.460 0.600 3.475 1.92
C11 2 3 0.600 0.750 3.475 9.38
C12 2 3 0.600 0.750 3.475 9.38
C13 2 1 0.600 0.750 3.475 3.13
Central
C2 6 0.380 0.600 3.475 4.75
C3 8 0.380 0.600 3.475 6.34
C5 2 0.460 0.600 3.475 1.92
Water Tank
C4 4 1 0.450 0.750 0.900 1.22
C5 4 2 0.460 0.600 0.900 1.99
C6 4 2 0.460 0.600 0.900 1.99
C7 4 1 0.460 0.600 0.900 0.99
C5 4 2 0.460 0.600 0.900 1.99
44.99
Say 45.00 Cum

2 Roof Beams
Staircase Head Room
Staircase(h) 5 2 4.690 0.230 0.380 4.10
Deduction of Columns 5 -4 0.300 0.230 0.380 -0.52
Staircase(v) 5 2 5.346 0.230 0.380 4.67
Deduction of Columns 5 -4 0.450 0.230 0.380 -0.79
Water Tank Bottom
Water Tank Bottom 4 2 7.350 0.230 0.425 5.75
Deduction of Columns 4 -6 0.600 0.230 0.425 -1.41
Water Tank Bottom 4 2 6.620 0.230 0.425 5.18
Deduction of Columns 4 -2 0.300 0.230 0.425 -0.23
16.74
Say 17.00 Cum

3 Roof slab
i) Roof Slab 125mm thick
Staircase Head Room
Staircase Head Room 5 7.700 4.690 180.57
180.57
Say 181.00 Sqm

ii) Roof Slab 150mm thick


Water Tank Bottom
Water Tank Bottom 4 7.350 6.620 194.63
194.63
Say 195.00 Sqm

iii) 150mm thick Side Wall


Water Tank 4 2 7.350 1.500 88.20
Water Tank 4 3 6.620 1.500 119.16

APMSIDC-PALASA DET-TERRACE 537 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
207.36
Say 208.00 Sqm

APMSIDC-PALASA DET-TERRACE 538 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
4 Lintels
D4 5 1.460 0.225 0.175 0.29
W2 5 1.960 0.225 0.175 0.39
10 0.67
Say 1.00 Cum

5 Sunshades
W2 5 1.800 9.00
9.00
Say 9.00 Rmt

6 225 mm thick Fly ash block


masonary
Staircase Head Room
All round the staircase 5 25.740 0.225 3.175 91.94
Deduction of Columns -4 0.300 0.225 3.175 -0.86
Deductions
W1 -5 1.500 0.225 1.800 -3.04
D4 -5 1.000 0.225 2.100 -2.36
85.68
Say 86.00 Cum

7 100 mm thick fly ash block masonry


walls
Parapet wall (All round)
All round the Building 1 410.581 0.900 369.52
All round the Open Courtyard 2 49.150 0.900 88.47
457.99
Say 458.00 Sqm

8 PCC (1:3:6) for Bedblocks


under lintels
D4 2 5 0.300 0.230 0.150 0.10
W2 2 5 0.300 0.230 0.150 0.10
Hold fasts
D4 6 5 0.230 0.230 0.150 0.24
W2 4 5 0.230 0.230 0.150 0.16
0.60
Say 1.00 Cum

9 Dummy columns
Block-A & Ramp Block
C1 13 0.380 0.600 0.900 2.67
C2 14 0.380 0.600 0.900 2.87
C3 4 0.380 0.600 0.900 0.82
C4 1 0.450 0.750 0.900 0.30
C8 2 0.600 0.600 0.900 0.65
C9 2 0.600 0.600 0.900 0.65
C10 2 0.600 0.600 0.900 0.65
C11 1 0.600 0.750 0.900 0.41
C12 11 0.600 0.750 0.900 4.46
C13 10 0.600 0.750 0.900 4.05

APMSIDC-PALASA DET-TERRACE 539 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Columns P.B Top to Roof slab
bottom
Block-(-B)
C4 5 0.450 0.750 0.900 1.52
C5 8 0.460 0.600 0.900 1.99
C6 2 0.460 0.600 0.900 0.50
C7 4 0.460 0.600 0.900 0.99
C8 2 0.600 0.600 0.900 0.65
C9 2 0.600 0.600 0.900 0.65
C10 2 0.600 0.600 0.900 0.65
C11 7 0.600 0.750 0.900 2.84
C12 19 0.600 0.750 0.900 7.70
C13 11 0.600 0.750 0.900 4.46
39.44
Say 40.00 Cum
10 TMT STEEL
Columns upto 3.60 mts levael 44.99 220.000 Kgs/Cum 9898.09

DummyColumns upto 3.60 mts levael 39.44 220.000 Kgs/Cum 8677.75


Roof beams 16.74 220.000 Kgs/Cum 3683.42
125mm thick Roof slab 180.57 10.000 Kgs/Sqm 1805.65
150mm thick Roof slab 194.63 12.000 Kgs/Sqm 2335.54
150mm thick side walls 207.36 12.000 Kgs/Sqm 2488.32
Lintels 1 80.000 Kgs/Cum 80.00
28968.75
Say 29.00 MT

11 Mild Steel
RBM 458.0 0.500 Kgs/Sqm 229.00
229.00
Say 0.23 MT

12 External plastering
All round the Building 5 25.400 3.600 457.20
Parapet wall (All round)
All round the Building 1 410.581 1.915 786.26
All round the Open Courtyard 2 49.150 1.915 188.24
Deductions
W2 -5 1.500 1.800 -13.50
1418.21
Say 1419.00 Sqm

13 Ceiling plastering
Staircase 5 7.000 5.000 175.00
Water tank Bottom 4 6.975 6.745 188.19
363.19
Say 364.00 Sqm

14 Internal plastering 12 mm thick


Staircase alround 5 24.000 3.475 417.00
Deductions
D4 -5 1.000 2.100 -10.50
406.50
Say 407.00 Sqm
15 Impervious Coat
Bottom

APMSIDC-PALASA DET-TERRACE 540 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Tank 4 6.975 6.745 188.19
Sides
Tank sides 4 27.440 1.350 148.18
336.36
Say 337.00 Sqm

16 Whiting for ceiling


Same as ceiling plastering 364.00
Sunshades bottom 5.400
369.40
Say 370.00 Sqm

17 Plastic Emulsion Paint for interior


faces of walls
Same as internal plastering 407.00
407.00
Say 407.00 Sqm

18 Emulsion paint for external


plastering
Same external plastering @ 60% 851.40
Sunshades top 1 9.000 0.600 5.40
856.80
Say 857.00 Sqm

19 Texture Paint for Exterrnal Walls


Same as of external plastering @
40% 567.60
567.60
Say 568.00 Sqm
20 Doors
Wooden Doors
D4 (0.90 X 2.10) 5 0.900 2.100 9.45
9.45 Sqm

21 Windows
W2 5 1.500 1.800 13.50
13.50 Sqm

22 Structural steel@ 1.6kg/sft


Ramp 1 21.500 4.690 100.84
100.84 Sqm
1085.39 Sft
1085.39
Say 1086.00 Kgs
23 Roofing
Staircase 1 21.500 4.690 100.84
100.84
Say 101.00 Sqm

24 Universal glazing clip


Ramp 8 4.690 37.52
37.52
Say 38.00 Rmt

APMSIDC-PALASA DET-TERRACE 541 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
24
MS Grill for Windows @ 15 Kg/Sqm
W2 5 1.500 1.800 13.50
13.50 Sqm
Say 14.00 Sqm
210.00 Kgs

APMSIDC-PALASA DET-TERRACE 542 OF 1048


S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
25 Painting to iron Work
W2 5 1.500 1.800 13.50
MS Tubular pipes
Staircase 1 20.072 0.050 1.00
14.50 Sqm
Say 15.00 Sqm

26 Impervious coat for terrace


Quantity Same as 125mm Thick Slab 283.00
Quantity Same as 150mm Thick Slab 1647.00
Quantity Same as 175mm Thick Slab 944.00
2874.00
Say 2874.00 Sqm

27 PVC down take pipe 72 15.150 1090.80


1090.80
Say 1091.00 Rmt

APMSIDC-PALASA DET-TERRACE 543 OF 1048


DETAILED ESTIMATE OF 4.0 LAKHS LITRES RCC SUMP WITH PUMP ROOM

S.No Description Nos L B D Quantity Unit


I Earth work excavation
Sump 1 16.900 12.80 3.550 767.94
Pump Room Portion 1 7.90 12.80 0.675 68.26
836.19
Say 837.00 Cum

2 Earth work excavation from 0.00 to


3.00mts depth

Sump 1 16.900 12.80 3.000 648.96


648.96
Say 649.00 Cum

3 Earth work excavation from 3.00mts to


4.00mts depth
Sump 1 16.900 12.80 0.50 108.16
Pump Room Portion 1 7.90 7.90 0.675 42.13
150.29
Say 151.00 Cum

4 Plain cement concrete work of mix


(1:4:8) prop.Raft
under sump below
slabRaft concrete 1 16.900 12.80 0.100 21.63
Pump Room Portion 1 7.900 12.80 0.100 10.11
Pump Room Portion - Vertical 4 7.90 12.80 0.100 40.45
72.19
Say 73.00 Cum

5 VRCC M30grade Design Mix (by


machine mixing)
Sump bottom slab 1 16.750 12.50 0.450 94.22
Ded Pump Room area -1 7.200 12.500 0.450 -40.50
Add Pump Room area 1 7.200 12.500 0.450 40.50
94.22
SAY 95.00 CUM

b Haunch concrete
Sump 0.50 1 50.00 0.30 0.300 2.25
Pump Room area 0.50 1 32.00 0.30 0.300 1.44
Steps for staircase 0.50 23 1.00 0.30 0.165 0.57
4.259
SAY 4.300 CUM
c 500 mm Thick Side walls
Sump long walls 2 22.500 0.500 3.275 73.69
Sump short walls 3 10.00 0.500 3.275 49.13
122.813
SAY 123.000 CUM

d 150 mm thick side walls


Collection pit alround 2 2.400 0.150 0.72

DET - SUMP : Page : 544


S.No Description Nos L B D Quantity Unit
0.720
SAY 1.000 Sqm

DET - SUMP : Page : 545


S.No Description Nos L B D Quantity Unit
e Sump Roof beams 3 10.00 0.23 0.380 2.62
SAY 2.700 cum

f 150 mm thick Sump Roof Slab


Sump Top slab 1 16.000 11.00 176.00
176.00
SAY 176.000 Sqm

g Pump Room columns 8 0.230 0.30 2.400 1.32


SAY 1.400 cum

h Pump Room beams


long beams 3 11.000 0.230 0.380 2.88
short beams 3 6.000 0.23 0.380 1.57
Ded for col -2 0.230 0.23 0.380 -0.04
4.42
SAY 4.500 cum

i 125 mm thick Pump Roof Slab


Pump Room portion 1 7.000 11.00 77.00
77.00
SAY 77.000 Sqm
j 150 mm thick Roof Slab
Sump 1 6.000 1.20 7.20
Sump 1 1.000 1.20 1.20
8.40
SAY 8.000 Sqm

k 175 mm thick Waist Slab


Ist Flight 1 3.300 1.00 3.30
IInd Flight 1 3.710 1.00 3.71
Midlanding 1 1.000 1.00 1.00
8.01
SAY 8.000 Sqm

6 TMT Steel Bars


Raft slab 95.00 80.0 Kg/cum 7600.00
Haunch concrete 4.259 80.0 Kg/cum 340.74
Pump Room columns 1.325 200.0 Kg/cum 264.96
Sump Roof beam 2.622 150.0 Kg/cum 393.30
Pump Roof beam 4.417 150.0 Kg/cum 662.58
125mm thick Sump Roof Slab 0.125 176.00 80.0 Kg/cum 1760.00
125mm thick Pump Roof Slab 0.125 77.00 80.0 Kg/cum 770.00
150mm thick Roof Slab 0.15 8.40 80.0 Kg/cum 100.80
175mm thick Staircase Waist Slab 0.175 8.01 80.0 Kg/cum 112.14
375mm thick Side walls 0.375 122.81 80.0 Kg/cum 3684.38
150mm thick Side walls 0.25 0.720 150.0 Kg/cum 27.00
19715.89
Say 19.72 MT

DET - SUMP : Page : 546


S.No Description Nos L B D Quantity Unit
7 Impervious coat Plastering 12mm
thick over roof slab with CM(1:4)
Sumpbottom 1 15.00 10.00 150.00
prop.
Pump Room bottom 1 6.00 10.00 60.00
b Internal walls
sump internal walls 1 50.000 3.275 163.75
Pump room internal walls 1 32.000 3.925 125.60
collection internal 2 2.400 0.15 0.72
c ceiling
Sump bottom 1 15.00 10.00 150.00
Pump Room bottom 1 6.00 10.00 60.00
710.07
SAY 711.000 SQM
8 Impervious coat Plastering 20mm
thick overslab
Sump Top roof slab with CM(1:4) 1 16.000 11.00 176.00
prop.
Pump Room portion 1 7.000 11.00 77.00
253.00
SAY 253.000 SQM
9 225mm thick brick masonry
Pump room long walls 2 11.000 0.225 2.420 11.98
Ded for columns -4 0.300 0.225 2.420 -0.65
Pump room short walls 2 6.460 0.225 2.420 7.03
Ded for columns -4 0.230 0.225 2.420 -0.50
R/S -1 2.300 0.225 2.020 -1.05
D -1 1.000 0.225 2.020 -0.45
W -1 1.200 0.225 1.200 -0.32
Lintels
W -1 1.660 0.225 0.175 -0.07
15.97
SAY 16.000 Cum
10 12mm thick internal platering
Pump room internal 1 32.000 2.800 89.60
Add Rolling shutter jambs 2 0.225 2.020 0.91
lintel bottom 1 2.300 0.225 0.52
Deductions
R/S -1 2.300 2.020 -4.65
86.38
SAY 86.000 Sqm

11 External plastering
Pump room internal 1 36.000 2.925 105.30
Deductions
R/S -1 2.300 2.020 -4.65
D -1 1.000 2.020 -2.02
W -1 1.200 1.200 -1.44
97.19
SAY 98.000 Sqm
12 Basement plastering
Sump alround 1 67.000 0.600 40.20
40.20
SAY 41.000 Sqm

DET - SUMP : Page : 547


S.No Description Nos L B D Quantity Unit

DET - SUMP : Page : 548


S.No Description Nos L B D Quantity Unit
13 Ceiling plastering
Pump room 1 10.000 6.000 60.00
60.00
SAY 60.000 Sqm

14 S & F Rolling shutter 1 2.300 2.000 4.600 Sqm

15 S & F Door 1 1.000 2.000 2.000 Sqm

16 S & F Window 1 1.200 1.200 1.440 Sqm

17 Painting to iron work


R/S 3 1 2.300 2.000 13.800 Sqm
D 0.75 1 1.000 2.000 1.500
15.300
SAY 16.000 Sqm
18 Painting to wood work
D 1.50 1 1.000 2.000 3.000 Sqm
SAY 3.000 Sqm
19 White washing
Quantity same as ceiling plaster 60.000 Sqm

20 Plastic emulsion Painting to intenal


walls
Quantity same as internal walls 86.000 Sqm

21 Plastic emulsion Painting to extenal


walls
Quantity same as external walls 98.000 Sqm

22 SS Railing @ 7.75 Kg/Sqm


Ist Flight 1 3.300 1.00 3.30
IInd Flight 1 3.710 1.00 3.71
7.01
Say 7.10 Sqm

23 Refilling with excavated earth


Qty same as per excavation 836.19
Deductions
Qty same as PCC (1:4:8) -72.192
Qty same as Raft concrete -95.000
sump internal -251.721
Qty same
Qty as Side
same as Side walls
walls 1*6*0.375*2.08 -4.680
2*(20.6+6.0)=53.2 -41.496
-465.089 -465.089
371.103
Say 372.000 Cum

DET - SUMP : Page : 549


PRIMERY TANK , BIOLOGICAL TANKS & TREATED WATER TANK
SEWERAGE TREATMENT PLANT 130 KLD
MBBR TECHNOLOGY
DETAILED ESTIMATE FOR STP
S.No Description Nos L B D Quantity Unit
1 Earth work excavation
Equalization & Oil & Grease 1 6.15 6.00 6.15 226.94
Three sides of Barscreen 1 2.70 1.35 1.00 3.65
Sludge Holding tank 1 1.85 4.70 3.00 26.09
Biological System 1 18.20 5.40 2.10 206.39
Extra For Treated water tank 1 2.00 7.80 2.10 32.76
Columns Under Excvataion 8 1.670 1.67 2.00 44.62
Anoxic Tank 1 4.500 4.10 2.60 47.97
588.41
SAY 589.00 CUM

2 PCC (1:4:8)
Equalization & Oil & Grease 1 6.15 6.00 0.15 5.54
Three sides of Barscreen 1 2.70 1.35 0.15 0.55
Sludge Holding tank 1 1.85 4.70 0.15 1.30
Biological System 1 18.20 5.40 0.15 14.74
Extra For Treated water tank 1 2.00 7.80 0.15 2.34
Columns Under Excvataion 8 1.670 1.67 0.15 3.35
Anoxic Tank 1 4.500 4.10 0.15 2.77

30.58
SAY 31.00 CUM

3 Total Raft Concrete


Equalization & Oil & Grease 1 6.15 6.00 0.600 22.14
Three sides of Barscreen 1 2.70 1.35 0.300 1.09
Sludge Holding tank 1 1.85 4.70 0.450 3.91
Biological System 1 18.20 5.40 0.450 44.23
Extra For Treated water tank 1 2.00 7.80 0.450 7.02
Columns Under Excvataion 8 1.670 1.67 0.300 6.69
Anoxic Tank 1 3.900 3.50 0.450 6.14
91.23
SAY 92.00 CUM

4 Refilling with excavated earth


Quantity same as per excavation 588.41
Deductions
Quantity same as per PCC(1:4:8) -30.58
Quantity same as per Raft concrete -91.23

466.60
SAY 467.00 CUM

5 Disposal of earth
Total earth work excavation 589.00
Refilling with availabe earth 466.60
122.40
SAY 122.00 CUM

DET - STP - Page : 550


S.No Description Nos L B D Quantity Unit
6 300 mm thick RCC Walls
Primary Treatment
Horizontals ( Bar Screen ) 1 2.70 2.250 6.08
Bar screen 2 1.00 2.250 4.50
Buffle Wall 1 0.90 1.500 1.35
Bar screen 1 1.00 0.750 0.75
Oil & Grease 2 0.90 1.350 2.43
Sludge Holding 2 1.50 3.125 9.38
Sludge Holding 1 4.70 3.125 14.69
Bar screen Long Wall 1 2.60 2.25 5.85
45.02
SAY 46.00 SQM

7 450 mm thick RCC Walls


Biological System 2 17.20 3.00 103.20
Another Direction 4 3.500 3.00 42.00
Treated water tank 2 5.000 3.000 30.00
Anoxic Tank 2 3.000 2.000 12.00
Anoxic Tank Long walls 2 3.900 2.000 15.60

202.80
SAY 203.00 SQM

8 PCC
a Steps for Dry Pump Room 1 12 0.600 0.15 0.300 0.32
Feed pumps 1.000 0.600 1.20 0.500 0.36
Sludge pumps 2.000 0.600 0.60 0.600 0.43
Filter Feed pumps 1.000 1.200 0.60 0.600 0.43
1.55
SAY 2.00 CUM

9 Total Column concrete


C1 8 0.230 0.30 1.550 0.86
C1 8 0.230 0.30 3.000 1.66
2.51
SAY 2.60 CUM

10 Roof beams
Treated water tank 2 5.90 0.30 0.450 1.59
Cantilever Beams 6 1.460 0.30 0.450 1.18
Pump room 3 8.460 0.30 0.450 3.43
Pump room 2 6.460 0.30 0.450 1.74
7.95
SAY 8.00 CUM

11 150mm thick Roof slab


i) Equalization tank & Sludge
Holding
1 5.90 4.90 28.91
Treated water tank 1 5.900 5.90 34.81
Cantilever Flatform 1 18.700 1.50 28.05
91.77
SAY 92.00 SQM

DET - STP - Page : 551


S.No Description Nos L B D Quantity Unit
1 125mm thick Roof slabs
over Pump Room 1.00 8.46 6.46 54.65
54.65
Say 55.00 Sqm

DET - STP - Page : 552


S.No Description Nos L B D Quantity Unit
12 SATIRCASE
Flight 2 4.300 1.200 10.32
SAY 10.00 SQM

13 HYSD STEEL
Raft 91.23 80.000 Kgs/Cum 7298.25
Columns 2.51 120.00 Kgs/Cum 301.39
Side walls 45.02 120.00 0.350 Kgs/Cum 1890.74
Side walls 202.80 120.00 0.450 Kgs/Cum 10951.20
Roof beams 7.95 120.00 Kgs/Cum 953.53
Roof slab 91.77 80.000 0.150 Kgs/Cum 1101.24
Staircase 10.00 65.000 0.150 Kgs/Cum 97.50
22593.8
Say 22.60 MT

14 Impervious Coat
Pump room
1 8.460 6.46 54.65
54.65
Say 55.00 Sqm

15 230mm thick brick masonry


long walls 2 8.460 0.23 2.400 9.34
Short walls 2 6.000 0.23 2.400 6.62
Deductions for columns -8 0.230 0.23 2.400 -1.02
Deductions
R/S 1 2.000 0.23 2.400 1.10
Lintel concrete
above R/S 1 2.460 0.23 0.230 0.13
Deduction For V -4 0.750 0.23 0.750 -0.52
Steps 0.50 20 1.000 0.30 0.150 0.45

16.11
Say 17.00 cum

16 Ceiling plastering 1 8.000 6.000 48.00


Say 48.00 cum

1 Chequed tiles 1 8.000 6.000 48.00


Say 48.00 cum

17 Internal plastering
Allround Pump Room 1 28.000 3.000 84.00
Deductions
R/S -1 2.000 2.400 -4.80
79.20
Say 80.00 Sqm

18 External plastering
Allround Pump Room 1 29.840 3.125 93.25

DET - STP - Page : 553


S.No Description Nos L B D Quantity Unit
Deductions
R/S -1 2.000 2.400 -4.80
88.45
Say 89.00 Sqm

DET - STP - Page : 554


S.No Description Nos L B D Quantity Unit
19 TWD
TWD 1 2.000 2.100 4.20
4.20
Say 4.20 Sqm

20 Painting to wood work


TWD 1 1 2.000 2.400 4.80
4.80
Say 5.00 Sqm

21 White cement paint for external


walls
Quantity same as external plastering 89.00

89.00
Say 89.00 Sqm
22 100mm dia MS Sleeves @
12.10Kg/RM
4 0.600 2.40
2.40
Say 3.00 RM
or 29.04
Say 30.00 Kgs
0.0300 MT
Say 0.10 MT

23 Impervious coat
Horizontals ( Bar Screen ) 1 2.70 2.250 6.075
Bar screen 2 1.00 2.250 4.500
Buffle Wall 1 0.90 1.500 1.350
Bar screen 1 1.00 0.750 0.750
Oil & Grease 2 0.90 1.350 2.430
Sludge Holding 2 1.50 3.125 9.375
Sludge Holding 1 4.70 3.125 14.688
Bar screen Long Wall 1 2.60 2.25 5.850

Biological System 2 18.70 3.00 112.200


Another Direction 4 3.500 3.00 42.000
Treated water tank 2 5.000 3.000 30.000
Anoxic Tank 2 3.000 2.000 12.000
Anoxic Tank Long walls 2 3.900 2.000 15.600

Bottom

Equalization Tank 1.0 5.00 4.00 20.000


Sludge Holding Tank 1.0 1.50 4.00 6.000
Bio- Logi cal Tank 2.0 3.50 3.50 24.500

307.318

614.635

SAY 615.00 CUM

DET - STP - Page : 555


S.No Description Nos L B D Quantity Unit

DET - STP - Page : 556


S.No Description Nos L B D Quantity Unit
24 M30 Grade Plinth Beams
Long span 3.000 6.460 0.230 0.300 1.337
Short Span 3.000 6.460 0.230 0.300 1.337

2.67
SAY 3.00 CUM
25 SS Railing
1.00 mt RCC Platform along MBBR- 1 24.250 1.000 24.250
1 to Filter Feed Tank
Staircase 1 3.900 1.500 5.850
Midlanding 2 1.500 1.000 3.000
33.10 Sqm
Say 33.00 Sqm

26 Encapsulated steps 30.00 Nos

27 S&F Manhole covers 2 2.00 Nos

28 PVC down take pipes 1 3.000 3.00 RM

30 GI Sheet 90.00 Sqm

31 MS 50mm pipes 170.00 Rm

32 NCL Windows 1 1.200 1.300 1.560 Sqm

DET - STP - Page : 557


#REF!

ABSTRACT ESTIMATE FOR SLAB PROJECTION AT TERRACE LEVEL


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
1 Hire Charges for access scaffolding using MS Jack
Prop Cup lock Pipe Scaffolds including all
operational, incidental and labour charges and removal
of form work
Ground Floor : 647.00 ONE SQM #REF! #REF!

First Floor : 647.00 ONE SQM #REF! #REF!

Second Floor : 647.00 ONE SQM #REF! #REF!

Third Floor : 647.00 ONE SQM #REF! #REF!

Fourth Floor : 647.00 ONE SQM #REF! #REF!

2 Centering and scaffolding using MS Cup lock


System + MS Plate shuttering including all
operational, incidental and labour charges and removal
of form work
Fifth Floor : 1681.00 ONE SQM #REF! #REF!

Sub Total ::(Civil Works) #REF!


Detailed Estimate - Slab Projection at Terrace Floor
S.NO DESCRIPTION Nos L(M) B(M) D(M) QUANTITY
125mm Thick Slab Projection at
1
Terrace Floor
Block - 1 (0.744+0.753)=1.497
Grid T1-T16 2 38.550 1.497 115.42
Grid T1-B1 1 40.600 1.497 60.78
Grid B16-G16 1 8.940 1.497 13.38
Block - 2
Grid T1-T16 2 38.550 1.497 115.42
Grid T1-B1 1 40.600 1.497 60.78
Grid B16-G16 1 8.940 1.497 13.38
Allround Middle Staircase
2 7.660 1.497 22.93
2 5.860 1.497 17.54
2 1.950 1.497 5.84
1 5.860 1.497 8.77
Allround Ramp
2 10.705 1.497 32.05
2 5.860 1.497 17.54
483.85 SQM
Say 484.00 SQM
125mm Thick Slab Projection at
2
Terrace Floor
Block - 1
Grid T1-T16 2 38.550 2.000 154.20
Grid T1-B1 1 40.600 2.000 81.20
Grid B16-G16 1 8.940 2.000 17.88
Block - 2
Grid T1-T16 2 38.550 2.000 154.20
Grid T1-B1 1 40.600 2.000 81.20
Grid B16-G16 1 8.940 2.000 17.88
Allround Middle Staircase
2 7.660 2.000 30.64
2 5.860 2.000 23.44
2 1.950 2.000 7.80
1 5.860 2.000 11.72
Allround Ramp
2 10.705 2.000 42.82
2 5.860 2.000 23.44
646.42 SQM
Say 647.00 SQM
Sloped Roof 100mm Thick at
3
Terrace Floor
Block - 1
Grid T1-T16 2 38.550 1.700 131.07
Grid T1-B1 1 40.600 1.700 69.02
Grid B16-G16 1 8.940 1.700 15.20
Block - 2
Grid T1-T16 2 38.550 1.700 131.07
Grid T1-B1 1 40.600 1.700 69.02
Grid B16-G16 1 8.940 1.700 15.20
Allround Middle Staircase
2 7.660 1.700 26.04
2 5.860 1.700 19.92
2 1.950 1.700 6.63
1 5.860 1.700 9.96
Allround Ramp
2 10.705 1.700 36.40
2 5.860 1.700 19.92
549.46 SQM
Say 550.00 SQM
#REF!

ABSTRACT ESTIMATE FOR SLAB PROJECTION AT TERRACE LEVEL


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
1 Supply and placing of the Design Mix Concrete M
30 grade corresponding to IS 456 with minimum
cement content of 400 kgs per 1 cum of concrete
using batching and mixing plant of 15 cum per
hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per
IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site, centering using casurina
ballies, bamboos, wooden reapers, runners, wood
posts, wall plates etc., including all operational,
incidental and labour charges ,transporting concrete
using transit mixer, lifting concrete mechnically, laying
concrete using concrete pump, vibrating, curing ,
overheads & contractors profit etc., complete but
excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402)

a) Roof Beams :
un supported height up to 3.66 m
Fifth Floor : 27.00 ONE CUM #REF! #REF!

b) ROOF SLABS :
i) Sloped Roof Slabs 100mm thick :
Fifth Floor : 550.00 ONE SQM #REF! #REF!

ii) Roof Slabs 125mm thick :


Fifth Floor : 647.00 ONE SQM #REF! #REF!
2 Supply and placing of the Design Mix Concrete M
30 grade corresponding to IS 456 with minimum
cement content of 400 kgs per 1 cum of concrete
using batching and mixing plant of 15 cum per
hour capacity with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per
IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site, excluding centering .,
including all operational, incidental and labour
charges ,transporting concrete using transit mixer,
lifting concrete mechnically, laying concrete using
concrete pump, vibrating, curing , overheads &
contractors profit etc., complete but excluding cost of
steel and its fabrication charges for finished item of
work (APSS No. 402)

iii) Roof Slabs 125mm thick :


Fifth Floor : 484.00 ONE SQM #REF! #REF!

3 Centering and scaffolding using MS Cup lock


System + MS Plate shuttering including all
operational, incidental and labour charges and removal
of form work
Fifth Floor : 1681.00 ONE SQM #REF! #REF!

4 Hire Charges for access scaffolding using MS Jack


Prop Cup lock Pipe Scaffolds including all
operational, incidental and labour charges and removal
of form work
Ground Floor : 647.00 ONE SQM #REF! #REF!

First Floor : 647.00 ONE SQM #REF! #REF!

Second Floor : 647.00 ONE SQM #REF! #REF!

Third Floor : 647.00 ONE SQM #REF! #REF!

Fourth Floor : 647.00 ONE SQM #REF! #REF!

5 Filling with well burnt cinder aggregate as per


IS:2686-1977 in sunken slabs including cost and
conveyance of cinder, labour charges for filling,
ramming, overheads and contractor profit etc.,
complete for finished item of work
Fifth Floor : 94.00 ONE CUM #REF! #REF!
6 Providing Thermo Mechanically Treated (TMT) (Fe
500 / Fe 500 D grade as per IS 1786-1979) of
different diameters for RCC works including labour
charges for straightening, cutting, bending to required
sizes and shapes, placing in position with cover blocks
of approved materials and size and tying and lap-
splicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and
drawings, including cost and conveyance of steel bars,
including all wastages such as overlaps, couplings,
chairs, spacer bars including cost and conveyance of
binding wire, cover blocks and all incidental,
operational, labour charges such as cutting, bending,
placing in position, tying etc., and overheads &
contractors profit complete for finished item of work.
( APSS No.126)

Fifth Floor : 20.10 ONE MT #REF! #REF!

7 Providing pitched roof cladding with terracota tiles


of size 125mm x 200mm and 12mm to 15mm thick set
over base coat of CM(1:3) 12mm thick using screened
sand with cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and jointing with
white cement paste mixed with pigment of matching
shade to full depth, including cost of all materials like
tiles, cement, sand and water , scaffolding etc., and
overheads & contractors profit complete for finished
item of work.

Fifth Floor : 550.00 ONE SQM #REF! #REF!

4 Ornamental cornice as per drawing at Terrace


floor by providing average 50 mm thick raised bands
of 750 mm wide in plain cement mortor bands in
CM(1:4) ,including cost and conveyence of all
materials, labour charges and scaffolding s etc.,
curing, overheads & contractors profit etc., complete
for finished item of work.

Fifth Floor : 324.00 ONE RM #REF! #REF!

Sub Total ::(Civil Works) #REF!

Length in Rmt 324


Lenght in Rft 1063
Rate/Rft #REF!
Site Developement-DATA 564 of 1048

DATA - Site development and Roads

S.No. Description Quantity


1 Clearing and grubbing road landby mechanical means including uprooting
grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal o
trees cut earlier and disposal of unserviceable materials and stacking of servicea
used or auctioned, upto a lead of 1000 m including removal and disposal of to
exceeding 150 mm in thickness as per Technical Specification Clause 201 M
including overhead charges & Contractor profit, complete for finished item of work.

RBR-STCL-2- II A
Unit = 1 sqm
Taking output = 1 hectare
In area of non-thorny jungle (light jungle)
a)   Labour
LAB-00120, Mate - Day
Mazdoor (Unskilled)
LAB-00121 CSoR-III - 3, 4 4.160 Day
Add for MAA @ 25% 0.25
b) Machinery
Dozer D 50 with attachment or suitable
machinery for removal of trees & stumps 10.00 hour
Tractor with trolley 3 T HIR-00077 1.00 hour

Overheads & Contractors Profit @13.615% 0.13615


Rate per 10000 sqm
Rate per 1 sqm

2 Cutting of trees, including cutting of trunks, branches and removal of s


refilling, compaction of back filling and stacking of serviceable material by manual m
and lead up to 100m as per Technical Specification Clause 201MORD / M
overhead charges & Contractor profit, complete for finished item of work.

RBR-STCL-3
Unit: Each
a) Girth above 300 mm to 600 mm
a) labour
LAB-00120, Mate - day
Mazdoor (Unskilled) 0.624 day
LAB-00121 CSoR-III - 3, 4
Add for MAA @ 25% 0.25
b) Machinery
Tractor with trolley 3 T HIR-00077 0.070 hour

Overheads & Contractors Profit @13.615% 0.13615


Rate for each tree
Site Developement-DATA 565 of 1048

S.No. Description Quantity


b) Girth above 600 mm to 900 mm
a) labour
LAB-00120, Mate - day
Mazdoor (Unskilled) 0.936 day
LAB-00121 CSoR-III - 3, 4
Add for MAA @ 25% 0.25
b) Machinery
Tractor with trolley 3 T HIR-00077 0.210 hour

Overheads & Contractors Profit @13.615% 0.13615


Rate for each tree

c) Girth above 900 mm to 1800 mm


a) labour
LAB-00120, Mate - day
Mazdoor (Unskilled) 2.080 day
LAB-00121 CSoR-III - 3, 4
Add for MAA @ 25% 0.25
b) Machinery
Tractor with trolley 3 T HIR-00077 0.280 hour

Overheads & Contractors Profit @13.615% 0.13615


Rate for each tree

3 Excavation for roadway in soil by mechanical means including cutting and p


to site of embankment upto a distance of 100 m, including trimming bottom a
accordance with requirements of lines, grades and cross-sections as per Techn
Clause 302.3 MORD / 301 MORTH including overhead charges & Contractor p
finished item of work.

(RBR-EECD-5 ii)
Unit = cum
Taking output : 180.00 cum
LAB-00120, a) Mazdoor
Mazdoor (Unskilled) 2.08 Nos.
LAB-00121 CSoR-III - 3, 4
Add for MAA @ 25% 0.25
b) Machinery
Dozer D-50 @ 50 cum per hour (cutting with
HIR-00072 pushing) 3.60 hours

Overheads & Contractors Profit @13.615% 0.13615


Cost for 180 cum
Rate per 1 cum
Site Developement-DATA 566 of 1048

S.No. Description Quantity


4 Earthwork excavation for road way in ordinary rock by mechanical means i
and pushing the earth to side of embankment upto a lead of 100 metres i
bottom and side slopes in accordance with requirements of lines, grades and cr
complete for finished item of work for trench cutting as per MOR&H specificatio
directed by the Engineer-in-Charge including overhead charges & Contractor p
finished item of work.

(RBR-EECD-8 - I c i
Unit = cum
Taking output : 180.00 cum
LAB-00120, a) Mazdoor
Mazdoor (Unskilled) 2.08 Nos.
LAB-00121 CSoR-III - 3, 4
Add for MAA @ 25% 0.25
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity
HIR-00052 @ 60 cum per hour 3.00 hours

Overheads & Contractors Profit @13.615% 0.13615


Cost for 180 cum
Rate per 1 cum

5 Excavation for roadway in ordinary rock by deploying a dozer D-50 inclu


pushing the cut earth to site of embankment upto a distance of 100 m (ave
trimming bottom and side slopes in accordance with the requirements of lines, g
sections with lift upto 3 m as per Technical Specification Clause 301 MORTH / 302
overhead charges & Contractor profit, complete for finished item of work..

(RBR-EECD-8 - c ii
Unit = cum
Taking output : 108.00 cum
LAB-00120, a) Mazdoor
Mazdoor (Unskilled) 3.12 Nos.
LAB-00121 CSoR-III - 3, 4
Add for MAA @ 25% 0.25
b) Machinery
HIR-00072 Dozer D-50 @ 50% of 100 cum per hour 2.16 hours

Overheads & Contractors Profit @13.615% 0.13615


Cost for 180 cum
Rate per 1 cum
Site Developement-DATA 567 of 1048

S.No. Description Quantity


6 Excavation for roadway in hard rock (requiring blasting) by drilling, blastin
trimming of bottom and side slopes in accordance with requirements of lines, g
sections, loading and disposal of cut rock with all lifts and leads upto 1000 m
Specification Clause 302.3.5 MORD / 301 MORTH including overhead charges &
complete for finished item of work.

RBR-EECD-9 i
Unit = cum
Taking output = 180 cum 180.00 cum
a)  Labour
LAB-00120, Mate - day
Mazdoor (Unskilled)
LAB-00121 CSoR-III - 3, 4 3.220 day
LAB-00003 CSoR-I - 3 Driller 2.00 day
Blaster 0.25 day
Add for MAA @ 25% 0.25
b) Machinery
HIR-00072 Dozer D-50 @ 30 cum per hour 6.00 hour
HIR-00003& LAB-00319 Air compressor, 210 cfm 6.00 hour
HIR-00003& LAB-00319 Crew charges 6.00 hour
HIR-00039 Jack hammers 12.00 hour
HIR-00039 Crew charges 12.00 hour
Add for MAA @ 25% 0.25
Front end loader 1 cum bucket capacity @ 30
HIR-00074 cum / hour 6.00 hour
HIR-00052 Tipper 5.5 cum capacity, 2 trips per hour 16.00 hour
c) Materials
MAT-00264 M - 104 Gelatine 80 per cent 70.00 kg
Electric Detonators @ 1 detonator for 2
MAT-00021 gelatine sticks of 285 gm each 252.00 each

Overheads & Contractors Profit @13.615% 0.13615


Cost for 180 cum
Rate per 1 cum
Site Developement-DATA 568 of 1048

S.No. Description Quantity


7 Excavation for roadway in hard rock (blasting prohibited) by mechanical
breaking rock, loading in tippers and disposal with initial lift of 3 mts and lead u
trimming bottom and side slopes in accordance with requirements of lines, g
sections as per Technical Specification Clause 302.3.5 MORD / 301 MORTH in
charges & Contractor profit, complete for finished item of work.

RBR-EECD-9 ii B
Unit = cum
Taking output = 36 cum 36.00 cum
a)  Labour
LAB-00120, Mate - day
Mazdoor (Unskilled)
LAB-00121 CSoR-III - 3, 4 10.400 day
Add for MAA @ 25% 0.25
b) Machinery
Hydraulic excavator 0.9 cum with rock breaker
HIR-00052 attachment @ 6 cum per hour 6.00 hour
HIR-00052 Tipper 5.5 cum capacity, 1 trip per hour 6.50 hour

Overheads & Contractors Profit @13.615% 0.13615


Cost for 36 cum
Rate per 1 cum

8 Excavation for roadway in hard rock with controlled blasting by drilling, blas
trimming of bottom and side slopes in accordance with requirements of lines, g
sections, loading and disposal of cut rock with all lifts and leads upto 1000 m
Specification Clause 302.3.5 MORD / 301 MORTH including overhead charges &
complete for finished item of work.

RBR-EECD-9 iii
Unit = cum
Taking output = 180 cum 180.00 cum
a)  Labour
LAB-00120, Mate - day
Mazdoor (Unskilled)
LAB-00121 CSoR-III - 3, 4 3.220 day
LAB-00003 CSoR-I - 3 Driller 2.00 day
LAB-00003 CSoR-I - 3 Blaster 0.50 day
Add for MAA @ 25% 0.25
b) Machinery
HIR-00072 Dozer D-50 @ 30 cum per hour 6.00 hour
HIR-00003& LAB-00319 Air compressor, 210 cfm 6.00 hour
HIR-00003& LAB-00319 Crew charges 6.00 hour
HIR-00039 Jack hammers 12.00 hour
HIR-00039 Crew charges 12.00 hour
Add for MAA @ 25% 0.25
HIR-00074 Front end loader 1 cum bucket capacity 6.00 hour
HIR-00052 Tipper 5.5 cum capacity, 4 trips per hour 8.20 hour
Site Developement-DATA 569 of 1048

S.No. Description Quantity


c) Materials
Gelatine 80 per cent 70.00 kg
Electric detonators @ 1 detonator for 2
gelatine stick of 285 gm each 1008.00 each

Cost for 180 cum


Rate per 1 cum
Overheads & Contractors Profit @13.615% 0.13615

9 Providing and constructing dry rubble rock-toe with rubble and stone chips
(Spoil Bank) including cost of all materials, machinery, labour, hand packing rubble
finishing top and sides to required slopes etc., complete with initial lead upto 1
including overhead charges & Contractor profit, complete for finished item of work.

Useful rubble and stone chips will be issued at dump yard at the issue rate for use
chips. Sorting out and breaking charges included in rate analysis.

IRR-DAW-5-9
Unit: 100 cum 100 cum
A.MATERIALS
Useful rubble ( at dump yard ) MAT-00079 100.00 cum
Useful stone chips ( at dump yard )
MAT-00067 15.00 cum
B.MACHINARY
HIR-00052& LAB-00362 Shovel 0.85 cum 2.00 hour
HIR-00186 Crew charges 2.00 hour
Add for MAA @ 25% 0.25
HIR-00052 Tipper 5 cum 6.00 hour
C.LABOUR
LAB-00091 CSoR-II - 35 Mason Class-II 7.00 day
work inspector LAB-00010 1.00 day
LAB-00091
LAB-00120, CSoR-II - 35 Stone breaker 2.00 day

LAB-00121 CSoR-III - 3, 4 mazdoor 21.00 day


Add for MAA @ 25% 0.25
Rate per 100 cum
Rate per 1 cum
Overheads & Contractors Profit @13.615% 0.13615
Site Developement-DATA 570 of 1048

S.No. Description Quantity


10 Providing and constructing 60 cm thick hand packed rough stone revetment
long through stones at 1.50 m c / c over a backing of 45 cm thick graded filter m
sand, 10 mm and 40 mm size approved graded aggregates laid in layers of 1
including cost of all materials, machinery, labour, laying to required slopes, we
finishing etc. complete with initial lead upto 50 m and all lifts including ove
Contractor profit, complete for finished item of work..

IRR-DAW-6-8
Unit: 100 Sqm 100 Sqm
A.MATERIALS
Sand (Un-Screened ) 15.30 cum
Coarse aggregate 10 mm down 15.30 cum
Coarse aggregate 40-20 mm 15.30 cum
Stone chips 9.00 cum
Rough stones ( rubble ) 30 to 45 cm long 57.60 cum
Through stones 65 to 75 cm long
MAT-00078 44 Nos
B.LABOUR
work inspector LAB-00010 1.00 day
LAB-00091
LAB-00120, CSoR-II - 35 Mason Class-II 10.00 day

LAB-00121 CSoR-III - 3, 4 mazdoor 33.00 day


Add for MAA @ 25% 0.25
Rate per 100 sqm
Rate per 1 sqm
Overheads & Contractors Profit @13.615% 0.13615

11 Filling with available excavated earth including pre-watering of soil, removal of to


soils, breaking clods, sectioning and consolidation with Vibratory Road Roller
requirement of table 300-2 of MoRT&H, including all hire and operational
complete for finished item of work as per MoRT&H specification 305 (4th revision)
conveyance of all materials , labour charges , overheads and contractors profit
finished item of work (Payment will be made based on level for finished item of wo

RBR-EECD-4 -iii
Unit = cum
Taking output = 100 cum 100.00 Cum
a)  Labour
LAB-00120, Mate - day
Mazdoor (Unskilled)
LAB-00121 CSoR-III - 3, 4 0.260 day
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity
@ 60 cum per hour (Page No.27 of R&B SOR)
hr
Motor grader for grading @ 200 cum per hour
(Page No.27 of R&B SoR) 1.00 hour
Water tanker 6 kl capacity (Page No.27 of R&B
SoR) 4.00 hour
Vibratory Roller 80 - 100 kN (Page No.27 of
R&B SoR) 1.00 hour
C) Water 24.000 Kl
Total
e) Overheads & Contractors Profit 0.13615
Cost for 100 cum = a+b+c+d+e
Site Developement-DATA 571 of 1048

S.No. Description Quantity


Rate per cum = (a+b+c+d+e)/100
Rate per cum
Site Developement-DATA 572 of 1048

TA - Site development and Roads

Rate Unit Amount


rubbing road landby mechanical means including uprooting wild vegetation,
shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such
and disposal of unserviceable materials and stacking of serviceable material to be
ed, upto a lead of 1000 m including removal and disposal of top organic soil not
mm in thickness as per Technical Specification Clause 201 MORD / MORTH
ead charges & Contractor profit, complete for finished item of work..

525.00 1 Day 2184.00


2184.00 546.00

1907.00 1 hour 19070.00


532.00 1 hour 532.00
22332.00
22332.00 3040.50
25372.50
2.54
Say 3.00

es, including cutting of trunks, branches and removal of stumps & roots,
tion of back filling and stacking of serviceable material by manual means with all lifts
o 100m as per Technical Specification Clause 201MORD / MORTH including
es & Contractor profit, complete for finished item of work.

525.00 1 day 327.60


327.60 81.90

532.00 1 hour 37.24


446.74
446.74 60.82
507.56
Say 508.00
Site Developement-DATA 573 of 1048

Rate Unit Amount

525.00 1 day 491.40


491.40 122.85

532.00 1 hour 111.72


725.97
725.97 98.84
824.81
Say 825.00

525.00 1 day 1092.00


1092.00 273.00

532.00 1 hour 148.96


1513.96
1513.96 206.13
1720.09
Say 1720.00

roadway in soil by mechanical means including cutting and pushing the earth
nkment upto a distance of 100 m, including trimming bottom and side slopes in
h requirements of lines, grades and cross-sections as per Technical Specification
ORD / 301 MORTH including overhead charges & Contractor profit, complete for
work.

1 No.
525.00 1092.00
1092.00 273.00

1907.00 1 Hour 6865.20


8230.20
8230.20 1120.54
9350.74
51.95
Say 52
Site Developement-DATA 574 of 1048

Rate Unit Amount


avation for road way in ordinary rock by mechanical means including cutting
he earth to side of embankment upto a lead of 100 metres including trimming
e slopes in accordance with requirements of lines, grades and cross sections etc.,
ished item of work for trench cutting as per MOR&H specification No.301 and as
Engineer-in-Charge including overhead charges & Contractor profit, complete for
work.

1 No.
525.00 1092.00
1092.00 273.00

3483.70 1 Hour 10451.10


11816.10
11816.10 1608.76
13424.86
74.58
Say 75

roadway in ordinary rock by deploying a dozer D-50 including cutting and


ut earth to site of embankment upto a distance of 100 m (average lead 50 m),
m and side slopes in accordance with the requirements of lines, grades and cross-
upto 3 m as per Technical Specification Clause 301 MORTH / 302 MORD including
es & Contractor profit, complete for finished item of work..

1 No.
525.00 1638.00
1638.00 409.50

1907.00 1 Hour 4119.12


6166.62
6166.62 839.59
7006.21
64.87
Say 65
Site Developement-DATA 575 of 1048

Rate Unit Amount


roadway in hard rock (requiring blasting) by drilling, blasting and breaking,
ttom and side slopes in accordance with requirements of lines, grades and cross-
g and disposal of cut rock with all lifts and leads upto 1000 m as per Technical
ause 302.3.5 MORD / 301 MORTH including overhead charges & Contractor profit,
shed item of work.

1 No.
525.00 1690.50
690.00 1 No. 1380.00
690.00 1 No. 172.50
3243.00 810.75

1907.00 1 hour 11442.00


1452.80 1 hour 8716.80
294.50 1 hour 1767.00
10.60 1 hour 127.20
460.20 1 hour 5522.40
7289.40 1822.35

1983.00 1 hour 11898.00


1199.40 1 hour 19190.40

60.00 1 kg 4200.00

12.00 1 each 3024.00


71763.90
71763.90 9770.65
81534.55
452.97
Say 453
Site Developement-DATA 576 of 1048

Rate Unit Amount


roadway in hard rock (blasting prohibited) by mechanical means including
oading in tippers and disposal with initial lift of 3 mts and lead upto 1000 metres,
m and side slopes in accordance with requirements of lines, grades and cross-
Technical Specification Clause 302.3.5 MORD / 301 MORTH including overhead
actor profit, complete for finished item of work.

1 No.
525.00 5460.00
5460.00 1365.00

3483.70 1 hour 20902.20


1199.40 1 hour 7796.10
35523.30
35523.30 4836.50
40359.80
1121.11
Say 1121

roadway in hard rock with controlled blasting by drilling, blasting and breaking,
om and side slopes in accordance with requirements of lines, grades and cross-
g and disposal of cut rock with all lifts and leads upto 1000 m as per Technical
ause 302.3.5 MORD / 301 MORTH including overhead charges & Contractor profit,
shed item of work.

1 No.
525.00 1690.50
690.00 1 No. 1380.00
690.00 1 No. 345.00
3415.50 853.88

1907.00 1 hour 11442.00


1452.80 1 hour 8716.80
294.50 1 hour 1767.00
10.00 1 hour 120.00
460.20 1 hour 5522.40
7289.40 1822.35
1701.00 1 hour 10206.00
1014.30 1 hour 8317.26
Site Developement-DATA 577 of 1048

Rate Unit Amount

60.00 1 kg 4200.00

12.00 1 each 12096.00


68479.19
80575.19
447.64
447.64 60.95
508.59
Say 509

constructing dry rubble rock-toe with rubble and stone chips from dump yard
uding cost of all materials, machinery, labour, hand packing rubble and stone chips,
d sides to required slopes etc., complete with initial lead upto 1 km and all lifts
ead charges & Contractor profit, complete for finished item of work.

nd stone chips will be issued at dump yard at the issue rate for usefull rubble / stone
ut and breaking charges included in rate analysis.

193.00 1 cum 19300.00

223.00 1 cum 3345.00

3157.40 1 hour 6314.80


326.30 1 hour 652.60
652.60 163.15
1199.40 1 hour 7196.40

565.00 1 No. 3955.00


685.00 1 No. 685.00
565.00 1 No. 1130.00
1 No.
525.00 11025.00
16795.00 4198.75
57965.70
579.66
579.66 78.92
658.58
Say 659
Site Developement-DATA 578 of 1048

Rate Unit Amount


constructing 60 cm thick hand packed rough stone revetment with 65 to 75 cm
ones at 1.50 m c / c over a backing of 45 cm thick graded filter media consisting of
nd 40 mm size approved graded aggregates laid in layers of 15 cm thick each
of all materials, machinery, labour, laying to required slopes, wedging with chips,
omplete with initial lead upto 50 m and all lifts including overhead charges &
, complete for finished item of work..

1061.00 1 cum 16233.30


1454.30 1 cum 22250.79
1727.97 1 cum 26437.89
223.00 1 cum 2007.00
555.75 1 cum 32011.20

69.00 1 No. 3036.00

685.00 1 No. 685.00


565.00 1 No. 5650.00
1 No.
525.00 17325.00
23660.00 5915.00
131551.18
1315.51
1315.51 179.11
1494.62
Say 1495

ilable excavated earth including pre-watering of soil, removal of top soil, spreading
clods, sectioning and consolidation with Vibratory Road Roller @ OMC to meet
table 300-2 of MoRT&H, including all hire and operational charges of T&P
shed item of work as per MoRT&H specification 305 (4th revision) including cost and
all materials , labour charges , overheads and contractors profit etc., complete for
work (Payment will be made based on level for finished item of work).

525.00 1.00 day 136.50

3483.70 1 hr 0.00

3192.00 1 hr 3192.00

806.00 1 hr 3224.00

3479.20 1 hr 3479.20
110.00 1 Kl 2640.00
12671.70
12671.70 1725.25
14396.95
Site Developement-DATA 579 of 1048

Rate Unit Amount


143.97
Say 144.00
Name of the work : Establishment of Government Medical College at Vizianagaram in Vizianagaram
District

Detailed Estimate for Proposed Main Road in front of Medical College Campus at Vizianagaram
S.NO DESCRIPTION NOS L B D QUANTITY

1 Road Length
Road lenth 1 940.00 940.00
940.00
Say 940.00 Rm
2 EARTH WORK EXCAVATION
for Existing Road 1 450.00 7.00 0.500 1575.00

1575.00
Say 1575.00 CUM
3 150mm thick GSB
for Extension Road 1 940.00 7.0 0.150 987.00
987.00
Say 987.00 Cum

4 WMM
for Existing Road 1 940.00 7.00 0.150 987.00
987.00
Say 987.00 CUM

5 Prime coat for WMM


1 940.00 7.0 6580.00
6580.00
Say 6580.00 Sqm

6 Tack coat for WMM


1 940.00 7.0 6580.00
6580.00
Say 6580.00 Sqm
7 BM
1 940.00 7.0 0.050 329.00
329.00
Say 329.00 Cum
8 Tack coat
1 940.00 7.0 6580.00
6580.00
Say 6580.00 Sqm
9 BC
1 940.00 7.0 0.030 197.40
197.40
Say 197.00 Cum
10 Embankment
1 490.00 7.0 1.200 4116.00
4116.00
Say 4116.00 cum
Name of the work : Establishment of Government Medical College at Vizianagaram in
Vizianagaram District
ABSTRACT ESTIMATE FOR CONSTRUCTION OF PROPOSED MAIN ROAD INFRONT OF
MEDICAL COLLEGE CAMPUS

S.No. Description Quantity Unit Rate in Rs. Amount

1 Earth work excavation for foundations (Mechanical 1575.00 CUM 126.00 198450
Means) for buildings in ordinary soils and depositing on
bank for all lifts and with an initial lead of 10m and up
to 3m depth including all operational,incidental, labour
charges such as shoring, sheeting, planking, strutting
etc., and overheads & contractors profit complete for
finished item of work excluding dewatering charges etc.,
as per SS 20 B(APSS 308)

2 Construction of Granular sub-base by providing HBG 987.00 CUM 1663.00 1641381


material confirming to Grading - III of MORT & H Table
400-2 including cost and conveyance of all material to
work site and spreading in uniform layers with motor
grader or by approved means, on prepared surface
mixing by mix place method with Rotavator/ approved
means, at OMC and compacting with vibratory roller to
achieve the desired density etc., complete for finished
item of work as per MoRT& H specification 401 (4th
revision) and as directed by the Engineer- in - charge
(Payment will be made based on levels for finished item
of work)

3 Providing, Laying, Spreading and compacting 987.00 CUM 1916.00 1891092


graded HBG/HBG crushed stone aggregate to Wet
Mix macadem specification including cost of all
materials and including premixing the material with
water at OMC in Mechanical mix plant carriage of mixed
material by tipper to site , laying in uniform layers with
paver in base courses on well prepared surface and
compacting with Vibratory roller to acheive the desired
density etc., as directed by the Engineer-in-Charge and
as per MoRT&H specification.406 (5th revision) for
finished item of work. (Payment based on levels for
finished item of work)

4 Providing and applying primer coat with Bitumen 6580.00 SQM 33.00 217140
Emulsion (Slow Setting-1) on the prepared surface of
granular base including clearing of road surface and
sparaying primer at the rate of 0.70kg/sqm using
mechanical means for finished item of work as per
MoRT&H Specification 502 (5th revision) and as
directed by the Engineer-in-Charge.
5 Providing and applying tack coat with bitumen VG- 6580.00 SQM 15.00 98700
10 bitumen using pressure distributor at the rate of
0.2Kgs per sqm on the prepared bituminous/granular
surface cleaned with mechanical broom for finished
item of work as per MoRT&H Specification 503 (5th
revision) and as directed by the Engineer-in-Charge.

6 Providing and laying of 50mm thick Bituminous 329.00 CUM 8831.00 2905399
Macadam with hot mix plant producing an average
output of 37.5 tonnes per hour using hard blasted
granite crushed aggregates of Grading - II as per table
500-4 of MoRT&H specificaion 504 (5th revision)
premixed with bituminous binder of 60/70 grade @
3.3% by weight of total mixture, transported to site, laid
over a previously prepared surface with mechanical
paver finisher to the required grade, level and alignment
and rolled as per Clauses 501.6 and 501.7 to achieve
the desired compaction for finished item of work as
directed by the Engineer-in-Charge including hire and
opeational charges all T&P and all other contingent
charges necessary including cost of charges on all
materials etc., complete and as per MoRTH
specification No. 504(5th revision)

7 Providing and applying tack coat with bitumen VG- 6580.00 SQM 15.00 98700
10 bitumen using pressure distributor at the rate of
0.2Kgs per sqm on the prepared bituminous/granular
surface cleaned with mechanical broom for finished
item of work as per MoRT&H Specification 503 (5th
revision) and as directed by the Engineer-in-Charge.

8 Providing and Laying 30mm thick Bituminous 27.00 CUM 6335.00 171045
concrete with 40-60 TPH HMP /100 to 120 TPH batch
type hot mix plant using HBG crushed aggregates of
Grading-2 as per table 500-17 of Specification 507 of
MoRT&H (5th revesion), premixed with Bituminious
binder VG-30 Grade @ 5.4% of mix and filler,
transporting the hot mix to work site, laying with paver
finisher to the required grade, level and alignment,
rolling with smooth wheeled,vibratory and tandem
rollers to achieve the desired compaction as per
MoRT&H Specification 507 (5th Revision) complete for
finished item of work in all respects excluding
seiniorage charges and as directed by Engineer-in-
charge
9 Filling with available excavated earth including pre- 4116.00 CUM 144.00 592704
watering of soil, removal of top soil, spreading
soils, breaking clods, sectioning and consolidation
with Vibratory Road Roller @ OMC to meet
requirement of table 300-2 of MoRT&H, including
all hire and operational charges of T&P complete
for finished item of work as per MoRT&H
specification 305 (4th revision) including cost and
conveyance of all materials , labour charges ,
overheads and contractors profit etc., complete for
finished item of work (Payment will be made based
on level for finished item of work).

7814611.00
Conveyance, , loading and unloading charges SoR 2022-23

( No loading and unloading charges allowed for machinery loading and unloading )

(Lead) charges
for trucks and (Lead) charges for (Lead)
(Lead) charges for (Lead) charges for (Lead)
tippers for trucks and tippers charges for
trucks and tippers trucks and tippers for per cu.meter for charges for
for Earth / Sand Rubble/Size stones/ Cement/ Steel/ trucks and
PCC slabs/ trucks and
Sl No. Distance tippers per
/Gravel / Murrum/ Cut Stones/ Coarse RCC poles/ AC tippers for
Shahabad slabs/ cu.meter for
Lime/ Surki/ per aggregate per & GI sheets/ Bricks
CC & Laterite water/ 1000
/1000 nos
cu.meter cu.meter Packed litres
blocks/ Wood/ cum
materials/tonne

1 2 3 4 5 6 7 8
1 Lead up to 1 km 1 36.00 34.70 21.70 51.00 21.90 57.80
2 Lead up to 2 km 2 50.40 48.50 30.30 71.40 30.70 80.90
3 Lead up to 3 km 3 67.20 64.70 40.40 95.20 40.90 107.80
4 Lead up to 4 km 4 81.60 78.60 49.10 115.60 49.70 131.00
5 Lead up to 5 km 5 96.00 92.40 57.80 135.90 58.40 154.10
6 for Every km beyond 5 km up to 30 km 30 14.40 13.90 8.70 20.40 8.80 23.10
7 for Every km beyond 30 km 10000 12.00 11.60 7.20 17.00 7.30 19.30

Rubble/ size stone/


Earth / Sand
cut stone/ Coarse Cement in Bricks
Sl No. Description of item /Gravel Murrum/ / Steel in Rs/Tonne
aggregate, Lime in Rs/Tonne Rs/1000 Nos.
Surki/ Rs / cum
Rs/cum

1 Loading 24.90 49.80 82.10 98.50 68.50

2 Unloading 12.45 24.90 82.10 98.50 68.50


A NAME OF THE WORK :- CONSTRUCTION OF PROPOSED DEGREE COLLEGE AT
VEMPALLI

B Sources and Leads


Material Quarry Lead in KM
1 Cement
2 Steel
3 Sand for concrete, mortar Pulivendula 30.00

4 Sand for plastering Pulivendula 30.00

5 Sand for filling Pulivendula 30.00

6 Second Class Bricks Local 8.00

7 Fly ash bricks 290 x 225 x 140 Proddutur 56.00

8 Fly ash bricks 290 x 100 x 140 Proddutur 56.00

9 40mm HBG Metal Machine crushed konampeta 26.00

10 25mm HBG Metal Machine crushed konampeta 26.00

11 20mm HBG Metal Machine crushed konampeta 26.00

12 12mm HBG Metal Machine crushed konampeta 26.00

13 10mm HBG Metal Machine crushed konampeta 26.00

14 6mm HBG Metal Machine crushed konampeta 26.00


Coarse graded Granular sub-base Material 9.5 26.00
konampeta
15 mm to 4.75mm
Coarse graded Granular sub-base Material 2.36 26.00
konampeta
16 mm & below
konampeta 26.00
17 Rough Stone OTG
konampeta 26.00
18 Rough Stone HBG
konampeta 27.00
19 Gravel
20 Shahabad stone slabs Yerraguntla 42.00

21 Kadapa stone slabs Yerraguntla 42.00

C Cement & Steel Rates June, 2022


1 Cement 4220.00

October, 2022
2 Fe - 500 / Fe - 500 D 64000.00

3 Mild Steel 63000.00

4 Structural Steel 62000.00

5 MS Flats 62000.00

D Allowances
1 Add for MAA @ 20% 0.20
2 Overheads&Contractors Profit @13.615% 0.13615

Water charges
Type of Habitation 2 1 for Rural
2 for Urban
NAME OF THE WORK :- CONSTRUCTION OF PROPOSED DEGREE COLLEGE AT VEMPALLI

LEAD CHART (COMMON SoR 2022-2023) (Cement - June, 2022 & Steel - October, 2022 rates)
Initial
Reference
S.No./ Cost Convey- MA
Sl. Source of to SSR Lead in Looading Unloading
Description Item Unit excluding ance Total
No. Materials page KM charges charges
Code No. seigniorage Charges
number
charges 20%
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
Ordinary Portland Cement 43 / 53
1 1 MT 4220.00 4220.00
grade
2 Reinforcement steel Fe - 500 / 500 D 1 MT 64000.00 64000.00
3 Mild steel bars 1 MT 63000.00 63000.00
4 Structural steel 1 MT 62000.00 62000.00
5 MS flats 1 MT 62000.00 62000.00
6 Sand (un-screened) Pulivendula 12 27(a) 1 Cum 30.00 605.00 456.00 1061.00
7 Sand (unscreened) for filling Pulivendula 12 27(b) 1 Cum 30.00 460.00 456.00 916.00

8 Sand (screened for mortar, plastering Pulivendula 12 28 1 Cum 30.00 700.00 456.00 1156.00
items)

9 Common burnt clay bricks (23x11x7cm) Local 11 BMT-A.01 1000 Nos 8.00 7500.00 223.40 68.50 68.50 13.70 7874.10

Flyash cement / lime solid blocks (50


10 Proddutur 11 BMT-A-10 1000 Nos 56.00 30000.00 6362.01 353.33 353.33 70.67 37139.34
Kgs/ sq.cm) 290mmx225mmx140mm

Flyash cement / lime solid blocks (50


11 Proddutur 12 BMT-A-13 1000 Nos 56.00 14000.00 2827.56 157.04 157.04 31.41 17173.04
Kgs/ sq.cm) 290mmx100mmx140mm

12 Aggregates 40mm nominal size (HBG) konampeta 28 M - 055 1 Cum 26.00 965.00 384.30 1349.30

13 Aggregates 25mm nominal size (HBG) konampeta 28 M - 054 1 Cum 26.00 1501.00 384.30 1885.30

14 Aggregates 20mm nominal size (HBG) konampeta 28 M - 053 1 Cum 26.00 1565.00 384.30 1949.30
Aggregates 13.20 / 12.50mm nominal
15 konampeta 27 M - 052 1 Cum 26.00 1260.00 384.30 1644.30
size (HBG)

16 Aggregates 10mm nominal size (HBG) konampeta 27 M - 051 1 Cum 26.00 1070.00 384.30 1454.30

17 Aggregates 6mm nominal size (HBG) konampeta 27 M - 050 1 Cum 26.00 865.00 384.30 1249.30

(Part II)
18 Rough Stone (OTG) konampeta Roads & 1 1 Cum 26.00 171.45 384.30 555.75
Bridges

(Part II)
19 Rough Stone (HBG) konampeta Roads & 12 1 Cum 26.00 298.00 384.30 682.30
Bridges

20 Gravel / Quarry spall konampeta #REF! M - 008 1 Cum 27.00 149.00 412.80 561.80

Polished Shahabad / Tandur stone


21 Yerraguntla #REF! BMT-B-05 10 Sqm 42.00 1900.00 140.24 8.22 4.11 0.82 2053.39
slabs 15mm to 18mm thick

Polished black Kadapa slabs minimum


22 Yerraguntla #REF! BMT-B-06 10 Sqm 42.00 1750.00 127.49 7.47 3.74 0.75 1889.44
of 15mm thick (0.457m x 0.457m)
Road items
Coarse graded Granular sub-base 23 of Part-
23 konampeta M - 025 1 Cum 26.00 654.00 384.30 1038.30
Material 9.5 mm to 4.75mm I(SoR)
Coarse graded Granular sub-base 26 of Part-
24 Material 2.36 mm konampeta I(SoR 2018- M - 022 1 Cum 26.00 547.00 384.30 931.30
& below 19)
26 of Part-
Aggregate 40mm to 45mm size(IRC &
konampeta I(SoR 2018- M - 022 1 Cum 26.00 696.00 384.30 1080.30
MORTH )
19)
26 of Part-
Aggregate 25mm to 27mm size (IRC &
konampeta I(SoR 2018- M - 022 1 Cum 26.00 1086.00 384.30 1470.30
MORTH )
19)
26 of Part-
Aggregate 19mm to 22mm size (IRC &
konampeta I(SoR 2018- M - 022 1 Cum 27.00 1092.00 398.20 1490.20
MORTH )
19)
26 of Part-
Aggregate 12mm to 14mm size (IRC &
Yerraguntla I(SoR 2018- M - 022 1 Cum 42.00 888.00 579.10 1467.10
MORTH )
19)
26 of Part-
Aggregate 9.5mm to 11.20mm size
Yerraguntla I(SoR 2018- M - 022 1 Cum 42.00 785.00 579.10 1364.10
(IRC & MORTH )
19)
26 of Part-
Aggregate 5.0 mm to 7.00mm size (IRC
0 I(SoR 2018- M - 022 1 Cum 0.00 608.00 0.00 608.00
& MORTH )
19)
26 of Part-
Aggregate 2.36 mm to 5.00mm size
June, 2022 I(SoR 2018- M - 022 1 Cum 0.00 455.00 0.00 455.00
(IRC & MORTH )
19)
Aggregate 2.36 mm below 26 of Part-
4220 I(SoR 2018- M - 022 1 Cum 0.00 547.00 0.00 547.00
19)

Bitumen VG 30 Grade (60/70 Grade) Vizag IOCL 1 MT 60.00 56320.00 105.00 56425.00
Bitumen VG 10 Grade (80/100 Grade) Vizag IOCL 1 MT 60.00 55520.00 105.00 55625.00
Emulsion slow Setting (RS1) Vizag IOCL 1 MT 60.00 35000.00 105.00 35105.00

1) Certified that the leads mentioned in the lead statement are shortest and correct.
2) Certified that metal are to be obtained by blasting.
3) Certified that sufficient quantities & quanlity material are available in the quarries.
4) Certified that for non SSR items lowest market rates are adopted
5) Certified that ---% extra on labour towards Municipal/Agency area allowance is allowed .
Common SoR 2022-23 - Page : 590

COMMON SoR 2022-2023


Reference
S.No./ Item code
S.No Items to SoR CFMS code Rate Unit
No.
page
Buildings SoR
1 Common burnt clay bricks (23x11x7cm) 11 MAT-00721 BMT-A.01 7500.00 1000 Nos.
Flyash cement / lime solid blocks (50 Kgs/ sq.cm)
2 11 MAT-00756 BMT-A-10 30.00 1 No.
290mmx225mmx140mm
Flyash cement / lime solid blocks (50 Kgs/ sq.cm)
3 12 MAT-00759 BMT-A-13 14.00 1 No.
290mmx112/100mmx140mm
Flyash cement / lime solid blocks (50 Kgs/ sq.cm)
4 12 MAT-00760 BMT-A-14 7.00 1 No.
225mmx100mmx60mm
5 Well burnt cinder aggregate 12 MAT-00763 BMT-A-17 650.00 1 Cum
Aerated (Cellular) Autoclaved Concrete Blocks
6 12 MAT-00764 BMT-A-18 53.00 1 No.
600mm x 200mm x 100mm
Aerated (Cellular) Autoclaved Concrete Blocks
7 12 MAT-00765 BMT-A-19 75.00 1 No.
600mm x 200mm x 150mm
Aerated (Cellular) Autoclaved Concrete Blocks
8 12 MAT-00766 BMT-A-20 105.00 1 No.
600mm x 200mm x 200mm
Aerated (Cellular) Autoclaved Concrete Blocks
9 12 MAT-00767 BMT-A-21 115.00 1 No.
600mm x 200mm x 230mm

Polished Shahabad / Tandur stone slabs 15mm to


10 13 MAT-00772 BMT-B-05 1900.00 10 Sqm
18mm thick
Polished black Kadapa slabs minimum of 15mm
11 13 MAT-00773 BMT-B-06 1750.00 10 Sqm
thick (0.457m x 0.457m)

High Polished Granite 16 to 18 mm thick up to 8'-


12 14 MAT-00776 BMT-B-09 2800.00 1 Sqm
00 (2.43 M) other than black and premium colours

High Polished Granite 16 to 18 mm thick up to 8'-


13 14 MAT-00777 BMT-B-10 2500.00 1 Sqm
00 (2.43 M) other than black and regular colours

High Polished Granite 16 to 18 mm thick up to 8'-


14 14 MAT-00778 BMT-B-11 2100.00 1 Sqm
00 (2.43 M) black.
15 16mm to 20mm thick marble slab 13 MAT-00781 BMT-B.14 1070.00 1 Sqm
Granite stone tiles 8mm thick (mirror polished of all
16 14 MAT-00783 BMT-B.16 1100.00 1 Sqm
shades)

Non-skid red or white full body Ceramic floor tiles of


size 300 x 300 mm and thickness between 7-8 mm
17 1st quality of any colour and finish in all shades and 14 MAT-00785 BMT-C.01 370.00 1 Sqm
designs
Non-skid red or white full body Ceramic floor tiles of
size 450 x 450 mm and thickness between 7-8 mm
18 1st quality of any colour and finish in all shades and 14 MAT-00786 BMT-C.02 375.00 1 Sqm
designs
Soluble salt porcelain vitrified tiles screen printed
and polished of size 600mm x 600mm , 8 to 10mm
19 15 MAT-00790 BMT-C.06 425.00 1 Sqm
thick of any colour and finish in all shades and
designs
Nano polished / stain free soluble salt porcelain
vitrified tiles screen printed of size 600mm x 600mm
20 15 MAT-00791 BMT-C.07 450.00 1 Sqm
and thickness between 8 to 10mm of any colour
and finish in all shades and designs

Double charged / multi charged stain free full body


porcelain vitrified tiles with double layer pigment of
21 Size 600 x 600 mm and thickness between 8-10 15 MAT-00793 BMT-C.09 612.00 1 Sqm
mm of any colour and finish in all shades and
designs

Double charged / multi charged stain free full body


porcelain vitrified tiles with double layer pigment of
22 Size 800 x 800 mm and thickness between 9-11 15 MAT-00794 BMT-C.10 758.00 1 Sqm
mm of any colour and finish in all shades and
designs
Common SoR 2022-23 - Page : 591

Digital / polished glazed full body porcelain vitrified


tiles with any type of design texture such as marble
23 finish, wooden, bamboo, stone finishes etc., scratch 16 MAT-00797 BMT-C.13 924.00 1 Sqm
less, stain free and size 900 x 900 mm and
thickness between 9-11 mm
Glazed vitrified tiles with matt finish of size 600
24 16 BMT-C.13(a) 818.00 1 Sqm
x600mm and thickness between 9-10 mm
Glazed red or white full body ceramic wall tiles of
size 200 x 300 mm / 245 mm x 325 mm and
25 16 MAT-00805 BMT-C.21 330.00 1 Sqm
thickness 6 mm of any colour and finish in all
shades and designs
Glazed red or white full body ceramic wall tiles of
size 300 x 450 mm / 320 mm x 400 mm and
26 16 MAT-00806 BMT-C.22 410.00 1 Sqm
thickness 6 mm of any colour and finish in all
shades and designs

Full body porcelain wall tiles of size 300 x 600 mm


with any type of design texture such as marble
27 17 MAT-00808 BMT-C.24 580.00 1 Sqm
finish, wooden, bamboo, stone finishes etc., scratch
less, stain free and thickness between 6-8 mm

Screen printed glazed full body porcelain wall tiles


of size 300 x 600 mm with any type of design
texture such as marble finish, wooden, bamboo,
28 stone finishes etc., scratch less, stain free and 17 MAT-00811 BMT-C.27 625.00 1 Sqm
thickness between 6-8 mm of any colour and finish
in all shades and designs

29 Epoxy flooring light green or blue colour 3mm thick 19 MAT-08734 BMT-C.48 1862.00 1 Sqm

Epoxy coving 50mm x 50mm at the corners of the


30 19 MAT-08735 BMT-C.49 500.00 1 RM
walls

Plain Cement Concrete general purpose tiles of size


31 300 x 300 mm and thickness 20 mm of any shades. 21 MAT-00832 BMT-D.04 255.00 1 Sqm

Chequered Cement Concrete heavy duty tiles


conforming to IS: 13801 using aggregates, cement,
32 pigments of size 300 x 300 mm and thickness 25 21 MAT-00835 BMT-D.07 325.00 1 Sqm
mm of any shades
Precast concrete blocks for paving of M-30 grade
33 and thickness not less than 50 mm for non-traffic 21 MAT-00840 BMT-D.12 350.00 1 Sqm
areas
Precast concrete blocks for paving of M-35 grade
34 and thickness not less than 60 mm for Light traffic 22 MAT-00841 BMT-D.13 390.00 1 Sqm
areas
Precast concrete blocks for paving of M-40 grade
35 and thickness not less than 80 mm for Medium 22 MAT-00842 BMT-D.14 550.00 1 Sqm
traffic areas
Precast concrete blocks for paving of M-50 grade
36 and thickness not less than 100 mm for Heavy 22 MAT-00843 BMT-D.15 610.00 1 Sqm
traffic areas

37 Medium teak wood scantilings up to 2m 23 MAT-00846 BMT - E.01 81950.00 1 Cum


38 Medium teak wood scantilings 2 to 3m 23 MAT-00847 BMT - E.02 92130.00 1 Cum
39 Medium teak wood scantilings above 3m 23 MAT-00848 BMT - E.03 102256.00 1 Cum
40 Medium teak wood planks of any thickness 24 MAT-00849 BMT - E.04 160920.00 1 Cum
39 Best teak wood scantilings up to 2m 24 MAT-00850 BMT - E.05 134500.00 1 Cum
40 Best teak wood scantilings 2 to 3m 24 MAT-00851 BMT - E.06 142480.00 1 Cum
41 Best teak wood scantilings above 3m 24 MAT-00852 BMT - E.07 155000.00 1 Cum
42 Best teak wood planks of any thickness 24 MAT-00853 BMT - E.08 175490.00 1 Cum
43 Burma teak wood scantilings up to 2m 24 MAT-00854 BMT - E.09 178200.00 1 Cum
44 Burma teak wood scantilings 2 to 3m 24 MAT-00855 BMT - E.10 187900.00 1 Cum
45 Burma teak wood scantilings above 3m 24 MAT-00856 BMT - E.11 203000.00 1 Cum
46 Burma teak wood planks of any thickness 24 MAT-00857 BMT - E.12 217106.00 1 Cum
47 Sal wood scantlings any length 24 MAT-00860 BMT - E.15 51000.00 1 Cum
48 Sal wood planks of any thickness 24 MAT-00861 BMT - E.16 63950.00 1 Cum
49 6mm thick corrugated AC sheets 24 MAT-00862 BMT-E.17 229.00 1 Sqm
Plain or Corrugated Galvanized iron sheets as per
50 24 MAT-00865 BMT-E.20 70.00 1 Kg
IS 277(0.1mm to 0.8 mm thickness)
Common SoR 2022-23 - Page : 592

51 Mild Steel Tubes & pipes of all diameters 26 MAT-00871 BMT-F.04 76.00 1 Kg
Stainless Steel Tubes, sections, plates, sheets,
52 27 MAT-00872 BMT-F.06 414.00 1 Kg
pipes of all sizes
Stainless steel fly proof wire mesh of not less than
53 27 MAT-00885 BMT-F.19 564.00 1 Sqm
20 gauge
Rabbit wire mesh (chicken mesh) of not less than
54 26 MAT-00894 BMT-F.28 21.00 1 Sqm
30 gauge
55 Rolling Shutter (80x1.25mm) 25 MAT-00895 BMT-F.29 4025.00 1 Sqm
56 Collapsable steel shutters 25 MAT-00896 BMT-F.30 3508.00 1 Sqm

57 Brass tower bolt 150mm long 27 MAT-00907 BMT-G.02 255.00 1 No.


58 Brass tower bolt 200mm long 27 MAT-00908 BMT-G.03 350.00 1 No.
59 Al. tower bolt 150mm long 28 MAT-00913 BMT-G.08 86.50 1 No.
60 Al. tower bolt 200mm long 28 MAT-00914 BMT-G.09 108.00 1 No.
61 Al. tower bolt 300mm long 28 MAT-00916 BMT-G.11 152.00 1 No.
62 MS powder coated tower bolt 100mm long 28 MAT-00919 BMT-G.14 26.50 1 No.
63 MS powder coated tower bolt 150mm long 28 MAT-00920 BMT-G.15 38.50 1 No.
64 MS powder coated tower bolt 200mm long 28 MAT-00921 BMT-G.16 56.00 1 No.
65 Brass Butt hinges 150mm long 28 MAT-00927 BMT-G.22 356.00 1 No.
66 Al. Butt hinges 150mm long 30 MAT-00931 BMT-G.26 133.00 1 No.
67 Powder coated butt hinges 100mm long 30 MAT-00933 BMT-G.28 20.00 1 No.
68 MS powder coated Butt hinges 150mm long 30 MAT-00935 BMT-G.30 39.00 1 No.
69 Al. handle 75mm long 30 MAT-00936 BMT-G.31 59.00 1 No.
70 Al. handle 100mm long 30 MAT-00937 BMT-G.32 68.00 1 No.
71 Al. handle 125mm long 30 MAT-00938 BMT-G.33 102.00 1 No.
72 Al. handle 150mm long 30 MAT-00939 BMT-G.34 114.00 1 No.
73 MS powder coated handle 125mm long 30 MAT-00940 BMT-G.35 35.00 1 No.
74 MS powder coated handle 150mm long 30 MAT-00941 BMT-G.36 49.00 1 No.
75 Brass aldrop 300mm long 31 MAT-00942 BMT-G.37 1195.00 1 No.
76 Brass aldrop 350mm long 31 MAT-00943 BMT-G.38 2300.00 1 No.
77 Brass aldrop 450mm long 31 MAT-00944 BMT-G.39 3255.00 1 No.
78 Al. aldrop 200mm long 31 MAT-00945 BMT-G.40 265.00 1 No.
79 Al. aldrop 250mm long 31 MAT-00946 BMT-G.41 314.00 1 No.
80 Al. aldrop 300mm long 31 MAT-00947 BMT-G.42 338.00 1 No.
81 MS powder coated aldrop 250mm long 31 MAT-00949 BMT-G.44 129.00 1 No.
82 MS powder coated aldrop 300mm long 31 MAT-00950 BMT-G.45 154.00 1 No.
83 Brass door stopper 34 MAT-00951 BMT-G.46 185.00 1 No.
84 MS powder coated door stopper 34 MAT-00958 BMT-G.53 45.00 1 No.
85 Heavy duty Al.door stopper 34 MAT-00962 BMT-G.57 58.00 1 No.
86 Brass fancy handle 150mm long 30 MAT-00963 BMT-G.58 328.00 1 No.
87 Brass fancy handle 200mm long 30 MAT-00964 BMT-G.59 451.00 1 No.
88 Brass fancy handle 250mm long 30 MAT-00965 BMT-G.60 800.00 1 No.
89 Brass fancy handle 300mm long 30 MAT-00966 BMT-G.61 1015.00 1 No.
90 Brass fancy handle 450mm long 30 MAT-00967 BMT-G.62 1600.00 1 No.
Heavy duty mortise lock 6/7 levers (IS:2209) with
91 33 MAT-00971 BMT-G.66 875.00 1 No.
PC or CP handles complete set
Heavy duty mortise lock 6/7 levers (IS:2209) with
92 34 MAT-00972 BMT-G.67 2036.00 1 No.
brass heavy handles
93 Friction stay hinges for windows 34 MAT-00976 BMT-G.71 100.00 1 No.
94 Cost of hydraulic floor springs 33 MAT-00982 BMT-G.77 3900.00 1 No.

95 Pre construction Anti termite treatment 35 MAT-05352 BMT-H.66 162.00 1 Sqm


Specialised high performance acrylic polymer
96 modified elastomeric cemetitios water proofing 42 MAT-08754 BMT-H.71 (b) 513.00 1 Sqm
system to the wet area / Toilet / Bath room
Specialized polysulphide sealant treatment to the
96 46 MAT-05365 BMT-H.78 702.00 1 RM
expansion joints(size: 25mm x 12mm)
97 Integral cement water proofing admixture 52 MAT-05372 BMT-H.85 205.00 1 Ltr
98 Super plasticizer and water reducing concrete
52 MAT-05375 BMT-H.88 76.00 1 Ltr
admixture
Common SoR 2022-23 - Page : 593

99 5mm thick plain float glass 62 MAT-01053 BMT-I.02 634.00 1 Sqm


100 12mm thick plain float glass 62 MAT-01057 BMT-I.06 1375.00 1 Sqm
101 Cost of 12mm thick tinted glass 63 MAT-01063 BMT-I.12 1800.00 1 Sqm
102 Pin headed glass 4mm thick 62 MAT-01064 BMT-I.13 370.00 1 Sqm
103 Pin headed glass 5mm thick 62 MAT-01065 BMT-I.14 465.00 1 Sqm
104 5mm thick ground glass 63 MAT-01067 BMT-I.16 750.00 1 Sqm

105 Water based Cement Primer of Interior Grade- 1 63 MAT-01073 BMT-J.01 160.00 1 Kg
106 Water based Cement Primer of Exterior Grade- 2 63 MAT-01074 BMT-J.02 200.00 1 Kg
107 Red oxide Primer Paint Grade-I 63 MAT-01075 BMT-J.03 145.00 1 Ltr
108 Zinc Chromate Yellow Oxide Iron Primer paint 63 MAT-01076 BMT-J.04 200.00 1 Ltr
109 Wood primer 63 MAT-01077 BMT-J.05 160.00 1 Ltr
110 Putty for wood work 63 MAT-01079 BMT-J.07 130.00 1 Kg
111 Spirit 64 MAT-01082 BMT-J.10 96.00 1 Ltr
112 Linseed Oil 64 MAT-01083 BMT-J.11 60.00 1 Ltr
113 Thinner for Melamine polish 64 MAT-01084 BMT-J.12 140.00 1 Ltr
114 French Polish 64 MAT-01086 BMT-J.14 200.00 1 Ltr.
115 Melamine Polish 65 MAT-01088 BMT-J.16 325.00 1 Ltr.
116 Interior grade Poly -Urethene polish 65 MAT-01089 BMT-J.17 750.00 1 Ltr.
117 Exterior grade Poly -Urethene polish 65 MAT-01090 BMT-J.18 843.00 1 Ltr.
118 Acrylic based Oil bound Washable Distemper 64 MAT-01093 BMT-J.21 81.00 1 Kg
119 Water proof Cement paint 64 MAT-01095 BMT-J.23 49.00 1 Kg
120 Acrylic interior emulsion paint 64 MAT-01097 BMT-J.24 190.00 1 Ltr
121 Acrylic exterior emulsion paint 64 MAT-01107 BMT-J.34 210.00 1 Ltr

Synthetic polymer luxury plastic emulsion paint of


122 64 MAT-01094 BMT-J.22 450.00 1 Ltr
superior grade

123 Water proof cement paint 64 MAT-01098 BMT-J.25 1009.00 25 Kgs


124 Synthetic enamel paint Grade - I 64 MAT-01102 BMT-J.29 270.00 1 Ltr
Wall putty of White Cement or Polymer or Cement
125 63 MAT-01104 BMT-J.31 600.00 20 Kgs
based
126 Exterior Texture 65 MAT-01105 BMT-J.32 818.00 25 Kgs
127 Gold line Exterior Texture 65 MAT-01106 BMT-J.33 1060.00 25 Kgs
128 Poly - urethane paint 66 MAT-08753 BMT-J.42 500.00 1 Ltr

MDF Board: interior-Both Side Laminated -12 mm


129 69 MAT-01166 BMT-K.58 700.00 1 Sqm
thick
MDF Board Interior - Both Side Laminated 18mm
130 69 MAT-01167 BMT-K.59 801.00 1 Sqm
thick

131 Laminate sheets - Glossy finish: 1mm thick 72 MAT-01205 BMT-L.21 380.00 1 Sqm
132 Laminate sheets - Mat finish: 1mm thick 72 MAT-01208 BMT-L.24 400.00 1 Sqm

133 12.5mm Gypboard Tiles 595mm x 595mm 73 MAT-01236 BMT-M.01 275.00 1 Sqm
134 Gypsom board plain sheets 12.5mm thick 73 MAT-01238 BMT-M.03 221.00 1 Sqm
135 GI Ceiling Angle - 25mm x 10mm x 0.55mm 78 MAT-01239 BMT-M.04 78.00 1 RM
GI Ceiling section - 51.5mm x 26mm x 10.5mm x
136 78 MAT-01240 BMT-M.05 106.00 1 RM
0.55mm thick
Intermediate section - 45mm x 15mm x 15mm x
137 78 MAT-01241 BMT-M.06 78.00 1 RM
0.9mm
Perimeter channel - 20mm x 27mm x 30mm (web)
138 78 MAT-01242 BMT-M.07 69.00 1 RM
of 0.55mm thick
139 GI Angle - Precoated - 25mm x 25mm x0.7mm 78 MAT-01243 BMT-M.08 62.00 1 RM
GI pre coated - T section - 24mm x 38mm x 0.7mm
140 78 MAT-01245 BMT-M.10 60.00 1 RM
thick
Hotdipped GI Angle - Precoated - Grid -
141 78 MAT-01246 BMT-M.11 37.00 1 RM
19mmx19mm
Polyster painted GI - T section 24x32mm and MAT-01247 & MAT-
142 78 BMT-M.12 & 13 50.00 1 RM
24x25mm (sub-cross Tee) 01248
143 Polyster painted GI-T Section - 24mm x 27mm 78 MAT-01249 BMT-M.14 49.00 1 RM
144 Aluminium angle - 24mmx 24mm 78 MAT-01250 BMT-M.15 33.00 1 RM
Anodised Aluminium T section - 24mm x 24.5mm x
145 78 MAT-01251 BMT-M.16 32.00 1 RM
2.4mm
Common SoR 2022-23 - Page : 594

146 Connecting Clips 78 MAT-01252 BMT-M.17 10.00 1 No.


147 Rawl Plug 79 MAT-01253 BMT-M.18 4.00 1 No.
148 6mm Nylon Rawl Plug 79 MAT-01254 BMT-M.19 4.00 1 No.
149 Soffit Cleats 79 MAT-01255 BMT-M.20 5.00 1 No.
150 Drywall screws - 25mm 79 MAT-01256 BMT-M.21 4.00 1 No.
151 Jointing Compound 79 MAT-01257 BMT-M.22 32.00 1 Kg.
152 Jointing Paper tape 79 MAT-01258 BMT-M.23 6.00 1 RM
153 Drywall top coat 79 MAT-01259 BMT-M.24 150.00 1 Ltr
154 Universal Holding Clips 79 MAT-01260 BMT-M.25 4.00 1 No.
155 GI Rod - 4mm dia - Connecting Rod 79 MAT-01261 BMT-M.26 15.00 1 RM
156 2mm dia GI Connecting rod 79 MAT-01262 BMT-M.27 10.00 1 RM
157 12mm Thermocole sheet 73 MAT-01271 BMT-M.36 32.00 1 Sqm
Cement bonded pre-laminated particle boards
158 90 MAT-01310 BMT-M.75 3400.00 1 Sqm
aluminum glazed partitions
Mineral Fibre Ceiling Tile of 0.595m x 0.595m of 13
159 75 MAT-01315 BMT-M.80 353.00 1 Sqm
mm thick Fissura Fine Model
Mineral Fibre Ceiling Tile of 0.595m x 0.595m of 15
160 75 MAT-01319 BMT-M.84 518.00 1 Sqm
mm thick Fissura Fine Model

Supplying and fixing single side prelam solid panel


161 94 MAT-01334 BMT-N-05 400.00 1 RM
PVC door frame (Choukhat)
Providing and fixing 30mm thick factory made
162 105 MAT-01336 BMT-N-07 2600.00 1 Sqm
moulded door shutter- wood free
PVC door cladding to the flush doors
163 117 MAT-01339 BMT-N-10 413.00 1 Sqm
shutters 1.50mm thick
164 30 mm thick flush shutter 99 MAT-01345 BMT-N-16 1400.00 1 Sqm
165 35 mm thick flush shutter 99 MAT-01346 BMT-N-17 1529.00 1 Sqm

Flush door shutters, solid bond wood block board


166 type with teak veneer on one face and commercial 99 MAT-01350 BMT-N-21 2305.00 1 Sqm
ply on another face (lipping): 30 mmthick

Scientific Door with metal door frame (single leaf


167 108 MAT-01374 BMT-N.45 10519.00 1 Sqm
door)
Scientific Door with metal door frame (double leaf
168 109 MAT-01375 BMT-N.46 10989.00 1 Sqm
door)
35mm thick Facotry made Prelaminated ABS
169 103 MAT-01397 BMT-N.68 7000.00 1 Sqm
(Acrolynitrile Butadyne Styrene) Door shutter

Stainless steel Fire Rated doors, frames & shutters


170 112 MAT-01388 BMT-N.59 20800.00 1 Sqm
made of Stainless steel of 304 grade (120 minutes)

Stainless steel Fire Rated doors, frames & shutters


171 113 MAT-01389 BMT-N.60 18600.00 1 Sqm
made of Stainless steel of 304 grade (60 minutes)

Lead Lined Stainless steel Clean room door frames


172 114 MAT-01391 BMT-N.62 24087.00 1 Sqm
and shutters
173 Foamed PVC Door Frame & ABS Shutters 115 MAT-01396 BMT-N.67 15150.00 1 Each
174 uPVC Two track two panels sliding door 120 MAT-05439 BMT-N.85.A 6100.00 1 Sqm
175 uPVC Three track three panels sliding door 120 MAT-05440 BMT-N.85.B 7500.00 1 Sqm

176 Pre painted steel windows with guard bars


i) Double shutters with central mullion 124 MAT-01412 BMT - P.05 6379.00 1 Sqm
MAT-01415 ,
ii) Centre fixed both side openable shutters 125 BMT - P.07,08 5411.00 1 Sqm
MAT-01416
177 Pre painted steel Ventilators
MAT-01418 , MAT-
a) Top hung 147 BMT-P.10, 11 , 12 6798.00 1 Sqm
01419, MAT-01420
MAT-01421 , MAT-
b) Fixed louvered 147 BMT-P.13,14,15 4650.00 1 Sqm
01422, MAT-01423

178 Pre painted steel Windows with fly mesh


MAT-01430,
i) Double shutters with central mullion 128 BMT - P.22,23 7288.00 1 Sqm
MAT-01431
ii) Centre fixed both side openable shutters(5'x4') 128 MAT-01432 BMT - P.24 6625.00 1 Sqm
iii) Centre fixed both side openable shutters(6'x4') 128 MAT-01433 BMT - P.25 5897.00 1 Sqm
Common SoR 2022-23 - Page : 595

Pre painted steel sliding window 2-Track with Two


179 135 MAT-01434 BMT-P.26 6992.00 1 Sqm
sliding shutters.
Pre painted steel sliding window 3-Track with Three
180 148 MAT-01488 BMT-P.77 7636.00 1 Sqm
sliding shutters.
Supply and fixing of UPVC sliding windows 2 track
181 142 MAT-05447 BMT - P.80.A 6460.00 1 Sqm
sliding (Area of window up to 1.75 sqm).
Supply and fixing of UPVC sliding windows 3 track
182 142 MAT-05448 BMT - P.80.B 8622.00 1 Sqm
sliding (Area of window upto 1.75 sqm).
Supply and fixing of UPVC sliding windows 2 track
183 142 MAT-05449 BMT - P.80.C 6655.00 1 Sqm
sliding (Area of window above 1.75 sqm).
Supply and fixing of UPVC sliding windows 2 track
184 sliding (Area of window above 2.50 sqm to 4.00 143 MAT-05450 BMT - P.81 6606.00 1 Sqm
sqm)
Supplying and fixing of UPVC fixed windows /
185 141 MAT-05446 BMT-P.79 6238.00 1 Sqm
ventilators

186 Pre painted steel/ powder coate Structural Glazing 149 MAT-01489 BMT - Q.01 7150.00 1 Sqm

187 Top Hung shutters in Structural Glazing 150 MAT-01490 BMT - Q.02 5645.00 1 Sqm
188 ..
Fixed Glazing 2'-0" x 2'-0" (609.6x609.6mm) and 2'-
a) 152, 153 MAT-01491, 1492 BMT - Q.03&04 5849.00 1 Sqm
0" x 3'-0" (609.6x914.4mm)
Fixed Glazing 3'-0" x 3'-0" (914.4x914.4mm), 3'-0" x
b) 153 MAT-01493 BMT - Q.05&06 4596.00 1 Sqm
4'-0" (914.4x1219.2mm)

189 Dismantling
a) Stone masonry in cement mortar 151 MAT-01498 BMT-S.01 498.00 1 Cum
b) Flat stone in roof or floors including lifting : 151 MAT-01500 BMT-S.03 182.00 10 Sqm
Pan tiled or Mangalore tiled roof with out roof
c) 151 MAT-01501 BMT-S.04 152.00 10 Sqm
timbers :
d) Wrought and framed timber in roofs or floors 151 MAT-01503 BMT-S.06 263.00 1 Cum
e) Old lime mortar plaster 151 MAT-01504 BMT-S.07 60.00 10 Sqm
f) Old cement mortar plaster 151 MAT-01505 BMT-S.08 75.00 10 Sqm

g) Kadapa slabs or shahabad stone slabs on sand bed 151 MAT-01508 BMT-S.11 84.00 10 Sqm
Clean removal of lime plaster from walls and raking
h) out joints 20mm deep or from terraced roof and 152 MAT-01511 BMT-S.14 55.00 10 Sqm
raking out joints 100 mm deep
Clean removal of cement plaster from walls and
i) 152 MAT-01512 BMT-S.15 68.00 10 Sqm
raking out joint 200 mm deep

High performance expansion joint filler board 20mm


190 152 MAT-01514 BMT-U.02 824.00 1 Sqm
thick
Expansion joint filler board for buildings, columns,
191 152 MAT-01517 BMT-U.05 360.00 1 Sqm
beams and slabs 25 mm thick

Labour charges for making, fabricating cup-boards


192 153 LAB-00418 BMM-V.07 666.00 1 Sqm
with shutters, box cup-boards,

Rounding the edges of Kadapa / Shahabad stone


193 154 LAB-00503 BMM-V.09 116.00 1 RM
slab of any thickness including polishing the same

Half rounding the edges of Marble / Granite slabs of


194 154 LAB-00504 BMM-V.10 350.00 1 RM
all thicknesses and polishing the same
Full rounding the edges of Marble / Granite slabs of
195 154 LAB-00505 BMM-V.11 453.00 1 RM
all thicknesses and polishing the same

Machine cutting charges for Marble / Granite slabs


196 154 LAB-00506 BMM-V.12 19.00 1 RM
up to 50mm thickness by mechanical device

Flat nosing Shahabad/Kadapa slabs of any


197 154 LAB-00507 BMM-V.13 55.00 1 RM
thickness

Labour charges for fabricating steel works like


Window Grills, Compound Wall Grills, Iron Doors,
198 154 LAB-00420 BMM-V.14 30.00 1 Kg
Windows including cost of welding rods, power
charges, excluding cost of fixing in position

Labour charges for fixing Iron Doors, Iron Windows


199 154 LAB-00421 BMM-V.15 6.00 1 Kg
and Window Grills in position
Common SoR 2022-23 - Page : 596

Labour charges for fabrication of stainless steel


200 154 LAB-00424 BMM-V.18 144.00 1 Kg
railing works
Labour charges for glass designing work( Etching
201 154 LAB-00426 BMM-V.20 1051.00 1 Sqm
work)
Labour charges for fixing flush door shutters to the
202 155 LAB-00429 BMM-V.23 421.00 1 Sqm
existing door frame
203 Labour charges for fixing glass 155 LAB-00430 BMM-V.24 315.00 1 Sqm

204 Powder coated Al. sections 158 MAT-01575 BMS-W-01 337.00 1 Kg


205 Rubber beading 159 MAT-01580 BMS-W-06 2.00 1 RM
Chloropyriphos Lindane Emulsifiable concentrate of
206 159 MAT-01581 BMS-W-09 239.00 1 Ltr
20%
Aluminium composite cladding 4mm thick with skin
207 159 MAT-01585 BMS-W.13 2626.00 1 Sqm
material thickness of 0.25mm
Aluminium composite cladding 4mm thick with skin
208 159 MAT-01586 BMS-W.14 2946.00 1 Sqm
material thickness of 0.50mm
209 Cement Jally 50mm thick 160 MAT-01589 BMS-W.17 388.00 1 Sqm
210 24 gauge aluminium sheet 160 MAT-01590 BMS-W.18 282.00 1 Sqm
7.5mm thick Aluminium Grill (as approved by the
211 160 MAT-01591 BMS-W.19 1035.00 1 Sqm
department) 3.58 Kg/Sqm
Pre-painted Galvalume Trapezoidal Profile Roofing
212 163 MAT-01625 BMS-W.55 407.00 1 Sqm
sheets with 0.50mm thickness
213 G.I scam bolts & nuts 164 MAT-01632 BMS-W.62 6.00 1 No.
214 8mm dia GI 'j' bolts & nuts 164 MAT-01634 BMS-W.64 11.00 1 No.
215 GI washers 164 MAT-01635 BMS-W.65 2.00 1 No.
216 Limpet washers (for scam & ‘J’ bolts) 164 MAT-01636 BMS-W.66 2.00 1 No.
217 Bitumen washers 164 MAT-01637 BMS-W.67 2.00 1 No.
199 White cement 164 MAT-01638 BMS-W.68 31.00 1 Kg
MS Z Hold fasts - 300 mm long of 40 x 40 x 5 mm
200 164 MAT-01639 BMT-W.69 39.00 1 No.
ISA
201 Rubber/ Nylon door stop bushes 164 MAT-01640 BMT-W.70 11.00 1 No.

202 Power Saw cutter - Hand Operated - Hire Charges 166 MAT-00206 BMC-X.02 132.00 1 hour

201 Power Drill - Hand Operated - Hire Charges 166 MAT-00207 BMC-X.03 121.00 1 hour

Reference
Material hire Labour
202 Hire charges for Access Scaffolding to SSR Unit
charges charges
page
A) Brick Masonry / Stone Maasonry
a) 1st floor 179 10.78 84.62 1 Sqm
b) 2nd floor 10.78 121.18 1 Sqm
c) 3rd floor 10.78 157.72 1 Sqm
d) 4th floor 10.78 194.27 1 Sqm
e) 5th floor 10.78 230.81 1 Sqm
f) 6th floor 10.78 267.35 1 Sqm
g) 7th floor 10.78 303.88 1 Sqm
h) 8th floor 10.78 340.43 1 Sqm

B) Plastering to walls
a) 1st floor 180 1.08 8.47 1 Sqm
b) 2nd floor 1.08 12.12 1 Sqm
c) 3rd floor 1.08 15.77 1 Sqm
d) 4th floor 1.08 19.43 1 Sqm
e) 5th floor 1.08 23.08 1 Sqm
f) 6th floor 1.08 26.73 1 Sqm
g) 7th floor 1.08 30.38 1 Sqm
h) 8th floor 1.08 34.05 1 Sqm

203 Hire charges for Stage Scaffolding


Ceiling Plastering
a) 1st floor 180 2.57 16.94 1 Sqm
b) 2nd floor 2.57 24.04 1 Sqm
Common SoR 2022-23 - Page : 597

c) 3rd floor 2.57 31.13 1 Sqm


d) 4th floor 2.57 38.23 1 Sqm
e) 5th floor 2.57 45.33 1 Sqm
f) 6th floor 2.57 52.42 1 Sqm
g) 7th floor 2.57 59.52 1 Sqm
h) 8th floor 2.57 66.62 1 Sqm

204 HIRE CHARGES FOR CENTERING&SCAFFOLDING-centering using Steel scaffolding pipes , jack props , wallers , Foot plate
Reference Material hire
to SoR charges
1st 2nd
3rd Floor
Floor Floor
a) Footings 179 301.00 672.00
b) Bed blocks, Bands 67.00 363.00 399.30 435.60
c) Pedestals 343.00 1069.00
d) Plinth beams 726.50 810.00

205 HIRE CHARGES FOR CENTERING & SCAFFOLDING -Unsupported height of 3.66M - for Steel scaffolding pipes, jack P
Reference Material hire
to SoR charges
1st 2nd
3rd Floor
Floor Floor
a) Lintels 179 1233.00 1720.00 1892.00 2064.00
b) Sunshades of any width 243.00 264.00 290.00 317.00
c) Columns 371.00 2415.00 2657.00 2898.00
d) Beams 2179.00 2027.00 2230.00 2432.00
e) RCC roof slabs upto 150 mm depth 247.00 241.00 265.00 289.00
f) RCC slabs upto 150-300 mm depth 254.00 248.00 273.00 298.00
g) Shear walls, RCC walls, Water tank walls 472.00 510.00 561.00 612.00

Note: - Centering & scaffolding charges for steel scaffolding with pipes, jack props, steel centring plates for unsupported heights of every 610 mm
M, may be allowed at 16.666% more than the basic material hire charges and relevant labour charges of the applicable floor and item
206 HIRE CHARGES FOR CENTERING & SCAFFOLDING -Unsupported height of 3.66M - Casurina Ballies , Bamboos , Wooden Reapers ,
Reference Posts , Wall Plates etc.,
Material hire
to SoR charges
1st 2nd
3rd Floor
Floor Floor
a) Lintels 179 826.00 1332.00 1465.00 1598.00
b) Sunshades of any width 163.00 204.00 224.00 245.00
c) Columns 249.00 1871.00 2058.00 2245.00
d) Beams 1458.00 1569.00 1726.00 1883.00
e) RCC roof slabs upto 150 mm depth 165.00 186.00 205.00 223.00
f) RCC slabs upto 150-300 mm depth 170.00 193.00 212.00 232.00

207
211 (WS&S
MAT-01993 BMW-G.106 1 Each
Items)
PVC Clamps(110mm dia) 17.00

Common SoR
LABOUR CHARGES
SKILLED
208 Bar bender 6 LAB-00001 I-1 750.00 1 Each
209 Blacksmith 6 LAB-00002 I-2 590.00 1 Each
210 Blaster 6 LAB-00003 I-3 690.00 1 Each
211 Carpenter 6 LAB-00004 I-4 705.00 1 Each
212 Work Inspector(Non technical) 6 LAB-00010 I -10 685.00 1 Each
213 Mason / Brick layer 6 LAB-00011 I -11 630.00 1 Each
214 Operator concrete mixer 6 LAB-00016 I -16 615.00 1 Each
215 Operator Jackhammer / Pneumatic tamper 6 LAB-00023 I - 23 615.00 1 Each
216 Painter 7 LAB-00035 I - 35 705.00 1 Each
217 Plumber / Pipe fitter 7 LAB-00036 I - 36 705.00 1 Each
SEMI SKILLED
Common SoR 2022-23 - Page : 598

217 Sprayer(semi skilled) 7 LAB-00057 II - 1 565.00 1 Each


218 Carpenter 7 LAB-00060 II - 4 565.00 1 Each
219 Fitter CL-II 7 LAB-00065 II - 9 565.00 1 Each
219 Mason / Brick layer 8 LAB-00091 II - 35 565.00 1 Each
220 Painter 8 LAB-00093 II - 37 565.00 1 Each
UN SKILLED
221 LAB-00120,
Man Mazdoor / Woman Mazdoor 8,9 LAB-00121 III - 3, 4 525.00 1 Each

Cost of Materials :
222 Binding wire 11 MAT-00003 3 70.00 1 Kg
223 Detonator electric 12 MAT-00021 21 12.00 1 No.
224 Sand (un-screened for concrete items) 12 MAT-00027 27(a) 605.00 1 Cum
225 Sand (unscreened) for filling 12 MAT-00028 27(b) 460.00 1 Cum
226 Sand(screened for mortar, plastering items) 12 MAT-00029 28 700.00 1 Cum
227 Impervious Water proof compound 14 MAT-00081 80 85.00 1 Kg
228 Gravel / Quarry spall 25 MAT-00177 M - 008 149.00 1 Cum
229 Coarse graded Granular sub-base Material 2.36
mm & below 26 MAT-00191 M - 022 547.00 1 Cum
230 Coarse graded Granular sub-base Material 9.5 mm
to 4.75mm 26 MAT-00194 M - 025 654.00 1 Cum
231 Aggregates 6mm nominal size (HBG) 27 MAT-00215 M - 050 865.00 1 Cum
232 Aggregates 10mm nominal size (HBG) 27 MAT-00216 M - 051 1070.00 1 Cum
233
Aggregates 13.20 / 12.50mm nominal size (HBG) 27 MAT-00217 M - 052 1260.00 1 Cum
234 Aggregates 20mm nominal size (HBG) 28 MAT-00218 M - 053 1565.00 1 Cum
235 Aggregates 25mm nominal size (HBG) 28 MAT-00219 M - 054 1501.00 1 Cum
236 Aggregates 40mm nominal size (HBG) 28 MAT-00220 M - 055 965.00 1 Cum
237 Bentonite 28 MAT-00235 M - 071 9.00 1 Kg
238 Gelatin 80% 30 MAT-00264 M - 104 68.00 1 Kg
239 Water charges(Urban) 35 MAT-00332 M - 189(a) 125.00 1 KL
240 Water charges(Rural) 35 MAT-00333 M - 189(b) 95.00 1 KL

Common SoR
241 Reference Hire &
Machinery Charges to SoR Fuel
charges
a) Agitator car / Transit mixer 2 cum 43 HIR-00001& LAB-00317 1 2227.90 1 Hour
b) Air compressor 7 cmm ( diesel) 43 HIR-00003& LAB-00319 3 1452.80 1 Hour
c) Batching plant 0.50 cum (6 cum/hour) 43 HIR-00009& LAB-00325 9 233.80 1 Hour
d) Batching plant 2x1.00 cum(15-20 cum/hour) 43 HIR-00010& LAB-00326 10 758.90 1 Hour
e) Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)capacity 43 HIR-00016& LAB-00329 16 188.10 1 Hour
f) Jack hammer 44 HIR-00039 39 18.60 1 Hour
g) Needle vibrator 40mm( petrol) 44 HIR-00040& LAB-00352 40 38.20 1 Hour
i) Shovel 0.85 cum 110hp 45 HIR-00052& LAB-00362 52 3157.40 1 Hour
j) Lift charges of materials(Winch 35HP- Electric) 46 HIR-00066& LAB-00372 66 340.50 1 Hour
k) Concrete placer pump (25 cum/hr)(Electric) 46 HIR-00071& LAB-00375 71 1417.40 1 Hour

Roads & Bridge works


242 Jute rope 25 MAT-00536 174 8.35 1 RM
243 Poly sheet 125 microns 25 MAT-00539 177 15.25 1 Sqm
244 Rough Stone (OTG) 15 MAT-00405 1 171.45 1 Cum
245 Rough Stone (HBG) 15 MAT-00302 12 298.00 1 Cum
246 Clearing heavy jungle 23 MAT-00479 109 3.20 1 Sqm
247 Clearing light jungle 21 MAT-00480 110 2.80 1 Sqm

248 Drilling 25mm dia. holes with pneumatic compressor 23 MAT-00512 143 167.00 1 RM
Hire charges of plants & machinery
249 Dozer (D50) 27 HIR-00072 2 1907.00 1 Hour
250 Mortar grader 27 HIR-00073 3 3722.00 1 Hour
251 Hydraulic excavator 27 HIR-00052 4 3483.70 1 Hour
252 Front end loader 27 HIR-00074 5 1983.00 1 Hour
Common SoR 2022-23 - Page : 599

253 Tipper 5.5 Cum 27 HIR-00054 6 1199.40 1 Hour


254 Vibratory roller 8T 27 HIR-00062 7 3479.20 1 Hour
255 Water tanker 6 KL 27 HIR-00076 10 806.00 1 Hour
256 Tractor with Rotavator 27 HIR-00078 12 532.00 1 Hour
257 Tractor with ripper attachment 27 HIR-00079 13 532.00 1 Hour
258 Light crane for lifting 28 HIR-00100 35 ( c ) 501.00 1 Hour
259 Kerb casting machine 29 HIR-00103 37 599.00 1 hour

Seigniorage charges G.O.Ms.No.11 of Industries and Commerce (M.II) Dept. dt.11.02.20


i) Coarse aggregate , stone 90.00 1 Cum
ii) Earth , Gravel 45.00 1 Cum
ii) Sand for mortar & filling 100.00 1 Cum
iv) Bricks 80.00 1000 Nos.
v) Colour Granite 16mm to 18mm thick 45.90 1 Sqm
vi) Black Granite 16mm to 18mm thick 58.65 1 Sqm
vii) Polished Shahabad / Tandur stone slabs 15 to
18mm thick 10.00 1 Sqm
viii) Polished black Kadapa slabs minimum of 15mm
thick 6.00 1 Sqm
ix) Marble 16mm to 20mm thick 5.40 1 Sqm

Non SSR items


1
Stainless steel base Plate 25mm dia.(in SS railing) 30.00 1 No.
2 Anchor bars in SS railing 30.00 1 No.
3 Bonding anchor bars in SS railing 15.00 1 No.
4 Labour charges including cost of nails, making
holes to wall and in aluminium sheet for expansion
joint 25.00 1 No.
5 Cup board locks 100.00 1 No.
6 Al. lock with handle 75.00 1 No.
Common SoR 2022-23 - Page : 600

3
Common SoR 2022-23 - Page : 601
Common SoR 2022-23 - Page : 602
Common SoR 2022-23 - Page : 603

BMT-M.12
52
43.5 46
Common SoR 2022-23 - Page : 604
Common SoR 2022-23 - Page : 605

5466
Common SoR 2022-23 - Page : 606
Common SoR 2022-23 - Page : 607

el scaffolding pipes , jack props , wallers , Foot plates , brackets , steel centering plates etc.,

Labour charges
4th 5th 6th 7th 8th
Floor Floor Floor Floor Floor

471.90 508.20 544.50 580.80 617.10

ed height of 3.66M - for Steel scaffolding pipes, jack Props, Steel Centering Plates,etc.,

Labour charges
4th 5th 6th 7th 8th
Floor Floor Floor Floor Floor
2236.00 2408.00 2580.00 2752.00 2924.00
343.00 370.00 396.00 422.00 449.00
3140.00 3381.00 3623.00 3864.00 4106.00
2635.00 2838.00 3041.00 3243.00 3446.00
313.00 337.00 362.00 386.00 410.00
322.00 347.00 372.00 397.00 422.00
663.00 714.00 765.00 816.00 867.00

centring plates for unsupported heights of every 610 mm height above 3.66
bour charges of the applicable floor and item
M - Casurina Ballies , Bamboos , Wooden Reapers , Runners , Wood
s etc.,
Labour charges

4th 5th 6th 7th 8th


Floor Floor Floor Floor Floor
1732.00 1865.00 1998.00 2131.00 2264.00
265.00 286.00 306.00 326.00 347.00
2432.00 2619.00 2807.00 2994.00 3181.00
2040.00 2197.00 2354.00 2510.00 2667.00
242.00 260.00 279.00 298.00 316.00
251.00 270.00 290.00 309.00 328.00

2021-22
700.00
550.00
645.00
655.00
640.00
585.00
575.00
575.00
655.00
655.00
Common SoR 2022-23 - Page : 608

525.00
525.00
525.00
525.00
525.00

490.00

64.00
10.00
605.00
460.00
700.00
79.00
138.00

517.00

593.00
790.00
977.00

1145.00
1418.00
1367.00
881.00
8.00
63.00
116.00
88.00

CFMS Crew
Total
number charges

HIR-00135 391.60 2619.50


HIR-00137 294.50 1747.30
HIR-00144 473.50 707.30
HIR-00145 473.50 1232.40
HIR-00150 306.80 494.90
HIR-00173 460.20 478.80
HIR-00174 220.90 259.10
HIR-00186 326.30 3483.70
HIR-00200 368.20 708.70
HIR-00205 230.10 1647.50

100
0.05
Common SoR 2022-23 - Page : 609

Industries and Commerce (M.II) Dept. dt.11.02.2020


WS & SA SoR 2022-23 : Page-610

Buildings SoR 2022-23

Sl.
No. SoR
ITEM CFMS Code Item code Rate CFMS Code Labour Unit
Page No.

WATER SUPPLY AND SANITARY ITEMS


1 Supply, laying, jointing 101.60 mm dia
SWG pipe
a) up to 1524mm (5') depth 189 MAT-01667 BMW-A.01 419.000 1 RM
b) up to 914.40mm (3') depth 189 MAT-01668 BMW-A.02 417.000 1 RM
2 Supply, laying, jointing 152.40mm dia
SWG pipe
a) up to 1524mm (5') depth 189 MAT-01669 BMW-A.03 620.000 1 RM
b) up to 914.40mm (3') depth 189 MAT-01670 BMW-A.04 609.000 1 RM
3 Labour charges for laying , jointing ,
testing SWG pipes up to 914.40mm (3') 189 LAB-00411 BMW-A.05 LAB-00411 260.00 1 RM
depth
4 Labour charges for laying , jointing ,
testing SWG pipes up to 1524mm (5') 189 LAB-00412 BMW-A.06 LAB-00412 326.00 1 RM
depth
5
Supply of 203.20mm (8") dia SWG pipe 190 MAT-01677 BMW-A.17 448.000 1 RM
6 Supply of 254mm (10") dia SWG pipe 190 MAT-01678 BMW-A.18 821.000 1 RM
7 Supply of 300mm (12") dia SWG pipe 190 MAT-01679 BMW-A.19 1183.000 1 RM
8 150mm x 100mm SWG gully trap 192 MAT-01732 BMW-A.72 533.000 1 Each

9 Inspection chamber 3' dia and upto 3'


193 MAT-05235 BMW-B.03 6118.000 1 Each
depth
10 Inspection chamber 3' dia - 3' above
193 MAT-05236 BMW-B.04 9557.000 1 Each
upto 5' depth
11 Inspection chamber 457.2mm x
457.2mm in brick masonry up to 194 MAT-01738 BMW-B.06 3590.000 1 Each
914.4mm ( 3) depth

12
76.20mm (3") CI Nahany trap 1st quality 197 MAT-01775 BMW-C.41,42 302.000 LAB-00163 57.00 1 Each

13
Orissa pan 580mmx440mm - ISI marked 197 MAT-01783 BMW-D.04,06 1551.000 LAB-00165 428.00 1 Each
14 Brick masonry seat 198 MAT-01786 BMW-D.09 303.000 1 Each
15 C.C Squatting plate 198 MAT-01787 BMW-D.10 90.000 1 Each
16 S&F EWC with'S' trap 198 MAT-01790 BMW-D.14,15 1889.000 LAB-00168 300.00 1 Each
17 S&F Plastic seat and lid for EWC 198 MAT-01791 BMW-D.16,17 850.000 LAB-00169 87.00 1 Each
18 S&F EWC suit CASCADE model white
198 MAT-01792 BMW-D.18,15 9158.000 LAB-00168 300.00 1 Each
colour
19 S&F EWC suit CASCADE model
198 MAT-01793 BMW-D.19,15 13354.000 LAB-00168 300.00 1 Each
coloured
20 S&F EWC suit CASCADE model special
198 MAT-01794 BMW-D.20,15 16994.000 LAB-00168 300.00 1 Each
colour

21
Flat back Wash hand basin 1st quality
199, 200 MAT-01798 BMW-D.24,28 1736.000 LAB-00170 362.00 1 Each
550mmx400mm-single CP Pillar cock

22 S&F flat back bowl urinal 440 x 265 x


200 MAT-01804 BMW-D.33,36 898.000 LAB-00173 144.00 1 Each
315
23 S&F flat back bowl urinal 590 x 375 x
200 MAT-01806 BMW-D.35,36 2935.000 LAB-00173 144.00 1 Each
390
24 S & F vitreous china porcelain sink (600
200 MAT-01807 BMW-D.37,39 4789.000 LAB-00174 362.00 1 Each
x 400 x 250)
25 S & F vitreous china porcelain sink (750
200 MAT-01808 BMW-D.38,39 5371.000 LAB-00174 362.00 1 Each
x 450 x 250)
26 S&F RCC terrazo sink 200 MAT-01809 BMW-D.40,41 781.000 LAB-00175 256.00 1 Each

27 Angle stop cock 12.70mm heavy duty 201 MAT-01812 BMW-E.05,06 453.000 LAB-00178 49.00 1 Each
28 12.70mm NP bib tap(long body) heavy
201 MAT-01813 BMW-E.07,08 387.000 LAB-00179 33.00 1 Each
duty
29 12.70mm NP bib tap(short body) heavy
201 MAT-01814 BMW-E.09,10 248.000 LAB-00180 33.00 1 Each
duty
30 S&F 31.75mm brass plumber union 201 MAT-01815 BMW-E.11,12 68.000 LAB-00181 16.00 1 Each
31 12.7mm dia. NP push cock 202 MAT-01826 BMW-E.29 259.000 1 Each
WS & SA SoR 2022-23 : Page-611

32 GM peet valves
a) 15mm NB 203 MAT-01847 BMW-F.21,22 604.000 LAB-00197 50.00 1 Each
b) 20mm NB 203 MAT-01846 BMW-F.19,20 812.000 LAB-00196 50.00 1 Each
c) 25mm NB 203 MAT-01845 BMW-F.17,18 1165.000 LAB-00195 50.00 1 Each
d) 32mm NB 203 MAT-01848 BMW-F.23,24 1768.000 LAB-00198 43.00 1 Each
e) 40mm NB 203 MAT-01849 BMW-F.25,26 2389.000 LAB-00199 75.00 1 Each
f) 50mm NB 203 MAT-01850 BMW-F.27,28 3498.000 LAB-00200 101.00 1 Each
g) 65mm NB 203 MAT-01851 BMW-F.29,30 5398.000 LAB-00201 119.00 1 Each
h) 80mm NB 203 MAT-01852 BMW-F.31,32 7995.000 LAB-00202 149.00 1 Each
33 S& F Nominal Bore GI pipe Medium
Grade properties & weight
a) 15mm Nominal bore 205 MAT-05243 BMW-F.79,80 199.000 LAB-00233 46.00 1 RM
b) 20mm Nominal bore 205 MAT-05244 BMW-F.81,82 220.000 LAB-00235 46.00 1 RM
c) 25mm Nominal bore 205, 206 MAT-05245 BMW-F.83,84 286.000 LAB-00237 46.00 1 RM
d) 32mm Nominal bore 206 MAT-05246 BMW-F.85,86 398.000 LAB-00239 46.00 1 RM
e) 40mm Nominal bore 206 MAT-05247 BMW-F.87,88 444.000 LAB-00241 50.00 1 RM
f) 50mm Nominal bore 206 MAT-05248 BMW-F.89,90 480.000 LAB-00243 76.00 1 RM
34 65mm Tata or Zenith make or
206 MAT-01870 BMW-F.91 837.000 1 RM
equivalent.
35 S & F 12.70 x 152.00 mm NP shower BMW-
206 MAT-01875 179.000 LAB-00248 22.00 1 Each
rose heavy F.100,101

36 Polyetheylene water storage tank with


207 MAT-01889 BMW-G.01,02 8.500 LAB-00258 1.00 1 Lt
Double layer
37 31.75mm dia. PVC flexible waste pipe,
208 MAT-01892 BMW-G.05 24.000 1 Each
914.4mm length
38
Supply & fixing of PVC low level system
with internal components & short bend

a) 10ltrs capacity single flush 208 MAT-01895 BMW-G.08 1390.000 1 Each


b) 8 lts capacity single flush 208 MAT-01897 BMW-G.10 786.000 1 Each
39 Single socket PVC/SWR pipes 4 kgs/
sqm
a) 75mm dia. 208 MAT-01898 BMW-G.11 236.000 3 RM
b) 90mm dia. 208 MAT-01899 BMW-G.12 375.000 3 RM
c) 110mm dia. 208 MAT-01900 BMW-G.13 447.000 3 RM
d) 160mm dia. 209 MAT-01919 BMW-G.32 1066.000 3 RM
40 110mm dia. plain bend 210 MAT-01944 BMW-G.57 77.000 1 Each
41 110mm dia. coupler 211 MAT-01980 BMW-G.93 53.000 1 Each
42 Pipe clip
a) 75mm dia. 211 MAT-01991 BMW-G.104 15.000 1 Each
b) 90mm dia. 211 MAT-01992 BMW-G.105 16.000 1 Each
c) 110mm dia. 211 MAT-01993 BMW-G.106 17.000 1 Each
d) 160mm dia. 211 MAT-01994 BMW-G.107 33.000 1 Each
43 4" (101.6mm) multi floor trap with jali 212 MAT-02006 BMW-G.119 133.000 1 Each
44 Labour charges for laying, fixing and
213 BMW-G.152 LAB-00259 79.00 1 RM
commissioning the PVC pipes

45 Chiselling the brick masonry wall and


217 MAT-02151 BMW-I.07 34.000 1 RM
repairs as directed by the department
46 Cost of NP chain and rubber plug 218 MAT-02158 BMW-I.18,19 41.000 LAB-00266 7.00 1 Each
47 25.4mm dia & 609.6mm long aluminium
218 MAT-02159 BMW-I.20,21 162.000 LAB-00267 50.00 1 Each
anodized towel rod
48 S & F NP soap dish heavy type with NP
218 MAT-02163 BMW-I.28,29 231.000 LAB-00271 14.00 1 Each
screws
49
Teak wood blocks 76.2mm x 101.6mm 218 MAT-02171 BMW-I.42,43 25.000 LAB-00277 11.00 1 Each
50 Cutting holes in brick masonry 218 BMW-I.46 LAB-00280 54.00 1 Each
51 Cutting holes in RCC slab floor & repairs
219 BMW- I.47 LAB-00281 81.00 1 No.
labour charges only
52 12.70mm PVC connection with brass
219 MAT-02172 BMW-I.48,49 95.000 LAB-00282 19.00 1 Each
union nut CP coated
53 Constructing Brick masonry support for
G.I pipe with CM 304.8x228.6x 228.6
219 MAT-02180 BMW-I.63,64 76.000 LAB-00290 25.00 1 Each
mm size including plastering finishing
etc complete
54 CI frame and cover for gully traps 219 MAT-02181 BMW-I.65,66 122.000 LAB-00291 40.00 1 Each
55 S&F TV shap mirror with plastic frame
220 MAT-02206 BMW-I.105,106 502.000 LAB-00306 132.00 1 Each
size 609.60mm x 457.20mm
WS & SA SoR 2022-23 : Page-612

56 Supplying & fixing stainless steel sink


size 36" x 18" (914.4x457.2mm) 1 mm 221 MAT-02213 BMW-I.119,120 7175.000 LAB-00313 574.00 1 Each
thick with accessories
57 Supplying & fixing stainless steel sink
size 20" x 18" x 8"
221 MAT-02215 BMW-I.123,124 5142.000 MAT-02216 509.00 1 Each
(508x457.2x203.20mm) 1 mm thick with
accessories
58 Supplying & fixing white glazed
porcelain channel 4" x 24" (101.6 x 221 MAT-02217 BMW-I.125 522.000 1 Each
609.6mm)
59 Supplying & fixing steel surgical long
elbow action handle 12.7mm dia bib 221 MAT-02218 BMW-I.126 946.000 1 Each
cock
60 Oval shape basin white (520x410mm)
221 MAT-02221 BMW-I.129 2371.000 1 Each
parry or equivalent
61 15 mm bib tap with flange Chromeum
222 MAT-02232 BMW-I.140 1644.000 1 Each
plated Jaquar make queen series
62 Chrome plated bib cock cum health
faucet jaquar make queen series 222 MAT-02233 BMW-I.141 4166.000 1 Each
Chrome plated
63 Chrome plated bib cock cum health
faucet jaquar make queen series Ivory 222 MAT-02234 BMW-I.142 7006.000 1 Each
Gold
64 Soap dish Jaquar make queen series
223 MAT-02251 BMW-I.159 1602.000 1 Each
Chrome plated
65 Soap dish Jaquar make queen series
223 MAT-02255 BMW-I.163 1214.000 1 Each
Ivory Gold
66 Towel ring Jaquar make Queen series
223 MAT-02256 BMW-I.164 1982.000 1 Each
Ivory Gold
67 Towel coat hook Jaquar make Queen
223 MAT-02257 BMW-I.165 902.000 1 Each
series Chrome plated
68 Bib cock Jaquar Continental series,
223 MAT-02263 BMW-I.171 902.000 1 Each
Chrome Finish
69 Towel rail 24 " Jaquar make Continental
224 MAT-02278 BMW-I.186 1549.000 1 Each
series Chrome finish

70 CPVC Pipes
15.90mm OD pipe - SDR 13.5 227 MAT-02312 BMW-I.220 59.000 1 RM
22.20mm OD pipe - SDR 13.5 MAT-02313 BMW-I.221 94.000 1 RM
28.60mm OD pipe - SDR 13.5 MAT-02314 BMW-I.222 136.000 1 RM
34.90mm OD pipe - SDR 13.5 MAT-02315 BMW-I.223 214.000 1 RM
41.30mm OD pipe - SDR 13.5 MAT-02316 BMW-I.224 295.000 1 RM
54.00mm OD pipe - SDR 13.5 MAT-02317 BMW-I.225 485.000 1 RM
15.90mm OD pipe - SDR 11 MAT-02318 BMW-I.226 68.000 1 RM
22.20mm OD pipe - SDR 11 MAT-02319 BMW-I.227 103.000 1 RM
28.60mm OD pipe - SDR 11 MAT-02320 BMW-I.228 160.000 1 RM
34.90mm OD pipe - SDR 11 MAT-02321 BMW-I.229 254.000 1 RM
41.30mm OD pipe - SDR 11 MAT-02322 BMW-I.230 348.000 1 RM
54.00mm OD pipe - SDR 11 MAT-02323 BMW-I.231 535.000 1 RM

PUBLC HEALTH ITEMS


1 Drilling of bore well by down the hole
hammer drilling to a finished dia of 115 Table 38
165mm
a) up to 90m depth 446.400 1 RM
b) 90m to 150m depth 477.600 1 RM
c) 150m to 250m depth 535.700 1 RM

2 Drilling of bore well by Rotary drilling to


a finished dia of 350mm for insertion of 116 Table 38 1294.600 1 RM
175mm dia PVC blue casing pipe

3 Cost and supply of 175mm dia PVC 117 Table 38 1100.000 1 RM


blue casing pipe

4 Slotting charges for 175mm dia PVC 118 Table 38 350.000 1 RM


blue casing pipe

5 Perforation charges for 180mm dia PVC 118 Table 38 325.000 1 RM


casing pipe
WS & SA SoR 2022-23 : Page-613

6 Supplying & Fixing 180mm dia PVC 118 Table 38 300.000 1 NO.
bore cap

7 Geological survey charges 118 Table 38 1200.000 1 RM

8 UPVC pipes for potable water 180mm


82 MAT-07656 923.000 1 RM
dia 6 kgs/sqcm
Note: Add 10% extra for Agency area on items 1, 2 and 7
Joinery data 2021-22 - Page : 614
JOINERY DATA
COMMON SoR 2022-23

a) Labour charges for wrought and put up (BLD-CSTN-13-1)


LAB-00004 CSoR I - 4 1st class carpenter 5.31 Nos. 705.00 1 Each 3743.55
LAB-00060
LAB-00120, CSoR II - 4 2nd class carpenter 12.39 Nos. 565.00 1 Each 7000.35
LAB-
00121 CSoR III - 3,4 Man Mazdoor 8.80 Nos. 525.00 1 Each 4620.00
Labour charges per 1 cum 15363.90

b) Labour charges for aluminium doors ( S.No.11 of Page No. 396 of SoR 2011-12 )
LAB-00004 CSoR I - 4 1st class carpenter 0.099 Nos. 705.00 Each 69.80
LAB-00060 CSoR II - 4 2nd class carpenter 0.198 Nos. 565.00 Each 111.87
LAB-00004 CSoR I - 4 Power Saw Cutter -Hand Operated -Operator 0.099 Nos. 705.00 Each 69.80
LAB-00004
LAB-00120, CSoR I - 4 Power Drill -Hand Operated -Operator 0.099 Nos. 705.00 Each 69.80
LAB-
00121 CSoR III - 3,4 Mazdoor(Unskilled) 0.297 Nos. 525.00 Each 155.93
LAB-00010 CSoR I -10 Non-technical work inspector 0.099 Nos. 685.00 Each 67.82
Add for MAA @ 20% 0.20 545.00 109.00
Machinery
MAT-00206 BMC-X.02 Power Saw Cutter -Hand Operated -Hire charges 0.793 Hrs 132.00 1 Hour 104.68
MAT-00207 BMC-X.03 Power Drill -Hand Operated -Hire charges 0.793 Hrs 121.00 1 Hour 95.95
854.62
Power charges for Motors 1% 0.01 854.62 8.55
Labour charges per 1 sqm 863.17

c) Labour charges for aluminium sliding windows ( S.No.10 of Page No. 395 of SoR 2011-12 )
LAB-00004 CSoR I - 4 1st class carpenter 0.096 Nos. 705.00 Each 67.68
LAB-00060 CSoR II - 4 2nd class carpenter 0.289 Nos. 565.00 Each 163.29
LAB-00004 CSoR I - 4 Power Saw Cutter -Hand Operated -Operator 0.096 Nos. 705.00 Each 67.68
LAB-00004
LAB-00120, CSoR I - 4 Power Drill -Hand Operated -Operator 0.096 Nos. 705.00 Each 67.68
LAB-
00121 CSoR III - 3,4 Mazdoor(Unskilled) 0.289 Nos. 525.00 Each 151.73
LAB-00010 CSoR I -10 Non-technical work inspector 0.096 Nos. 685.00 Each 65.76
Add for MAA @ 20% 0.20 583.81 116.76
C.Machinery
MAT-00206 BMC-X.02 Power Saw Cutter -Hand Operated -Hire charges 0.771 Hrs 132.00 1 Hour 101.77
MAT-00207 BMC-X.03 Power Drill -Hand Operated -Hire charges 0.771 Hrs 121.00 1 Hour 93.29
895.64
Power charges for Motors 1% 0.01 895.64 8.96
Labour charges per 1 sqm 904.59
Joinery data 2021-22 - Page : 615
Joinery data 2021-22 - Page : 616
d) Labour charges for aluminium partitions partly glazed ( S.No.8 of Page No. 394 of SoR 2011-12 )
LAB-00004 CSoR I - 4 1st class carpenter 0.434 Nos. 705.00 Each 305.97
LAB-00060 CSoR II - 4 2nd class carpenter 0.434 Nos. 565.00 Each 245.21
LAB-00004 CSoR I - 4 Power Saw Cutter -Hand Operated -Operator 0.043 Nos. 705.00 Each 30.32
LAB-00004
LAB-00120, CSoR I - 4 Power Drill -Hand Operated -Operator 0.058 Nos. 705.00 Each 40.89
LAB-
00121 CSoR III - 3,4 Mazdoor(Unskilled) 0.145 Nos. 525.00 Each 76.13
LAB-00010 CSoR I -10 Non-technical work inspector 0.072 Nos. 685.00 Each 49.32
Add for MAA @ 20% 0.20 747.83 149.57
C.Machinery
MAT-00206 BMC-X.02 Power Saw Cutter -Hand Operated -Hire charges 0.347 Hrs 132.00 1 Hour 45.80
MAT-00207 BMC-X.03 Power Drill -Hand Operated -Hire charges 0.463 Hrs 121.00 1 Hour 56.02
999.22
Power charges for Motors 1% 0.01 999.22 9.99
Labour charges per 1 sqm 1009.22

e) Labour charges for aluminium casement windows ( S.No.9 of Page No. 394 of SoR 2011-12 )
LAB-00004 CSoR I - 4 1st class carpenter 0.100 Nos. 705.00 Each 70.50
LAB-00060 CSoR II - 4 2nd class carpenter 0.300 Nos. 565.00 Each 169.50
LAB-00004 CSoR I - 4 Power Saw Cutter -Hand Operated -Operator 0.100 Nos. 705.00 Each 70.50
LAB-00004
LAB-00120, CSoR I - 4 Power Drill -Hand Operated -Operator 0.100 Nos. 705.00 Each 70.50
LAB-
00121 CSoR III - 3,4 Mazdoor(Unskilled) 0.300 Nos. 525.00 Each 157.50
LAB-00010 CSoR I -10 Non-technical work inspector 0.100 Nos. 685.00 Each 68.50
Add for MAA @ 20% 0.20 607.00 121.40
C.Machinery
MAT-00206 BMC-X.02 Power Saw Cutter -Hand Operated -Hire charges 0.800 Hrs 132.00 1 Hour 105.60
MAT-00207 BMC-X.03 Power Drill -Hand Operated -Hire charges 0.800 Hrs 121.00 1 Hour 96.80
930.80
Power charges for Motors 1% 0.01 930.80 9.31
Labour charges per 1 sqm 940.11

g) Supplying of 12mm x 12mm size best teak wood beading


Cost of teak wood (0.012 x 0.012 x 1.00) 0.000144 Cum 134500.00 1 Cum 19.37
Labour charges 0.000144 Cum 15363.90 1 Cum 2.21
Rate per 1 RM 21.58

h) Supplying of 18mm x 12mm size best teak wood beading


Cost of teak wood (0.018 x 0.012 x 1.00) 0.000216 Cum 134500.00 1 Cum 29.05
Labour charges 0.000144 Cum 15363.90 1 Cum 2.21
Rate per 1 RM 31.26
Joinery data 2021-22 - Page : 617
Joinery data 2021-22 - Page : 618
DATA
S.No. CFMS code SoR Ref Description of item Quantity Rate Unit Amount

1 Supply and fixing of two shutter main door cum fixed window as per approved drawing with best teak wood frame of section 150mm x
100 mm with fixed fan light of 500mm at top and fixed panels of 600mm width at sides fixed with 12mm thick Tinted - Bronze/Green glass
using 12mm x 12mm teak wood beading and fixing ornamental grill made of 25mm x 5mm MS flats as per the approved drawing in fan light
portion and fixed panels and 1st class teak wood top and middle rails & styles of section 120mm x 35mm, bottom rail of size 150mm x 35mm
and 12mm thick plain float glass for shutter with ornamental etching including cost and

conveyance to site of teak wood frame, shutters, glass including supply and fixing 6 Nos MS Z hold fasts of size 300 mm x 40 mm x 5mm
including cost of ISI marked brass fixtures of 6 Nos butt hinges(IS:205) 150mm long , 1 No. aldrop (IS:2681) 450mm long, 3 Nos tower bolts-
10mm (IS:204) of 200 mm long , 2 Nos 450 mm long fancy handles, 2 Nos door stoppers, 2 Nos. Rubber / Nylon door stop bushes including
fixing the fixtures to door with required number of screws, bolt and nuts including labour charges for fixing the frame in position, fixing the
shutters to the frame, fixing glass in fan light portion etc., including overheads & contractors profit complete for finished item of work as per
APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for a depth of not less than 40 mm) (3000mm x 2600mm)

Quantity analysis Size : 3.00m x 2.60m 7.80 sqm


Best teak wood frame 2 to 3m long for outer frame 2x3.00 + 2x2.60
= 11.20 RM x 0.15 x 0.10 0.1680 Cum
Best teak wood frame up to 2m long for outer frame 3x0.50+4x0.60++2x1.80
= 7.50 RM x 0.15 x 0.10 0.1125 Cum
Shutter styles 2 x 2 x 2.10
= 8.40 RM x 0.12 x 0.035 0.0353 Cum
Top and middle rail 2 x 2 x 0.90
= 3.60 RM x 0.12 x 0.035 0.0151 Cum
Bottom rail 2 x 0.90
= 1.80 RM x 0.15 x 0.035 0.0095 Cum
0.1724 Cum
2x2x0.60x0.50+2x2x0.90x0.50+2x2x
12 mm thick tinted glass 0.60x1.30 6.12 Sqm
12 mm thick plain float glass 2x0.90x2.10 3.78 Sqm
Teak wood beading
Fan light portion 2x2(0.60+0.50)+2x2(0.90+0.50) 10.00 RM
Side fixed panels 2x6(0.60+1.30) 22.80 RM
Shutter portion 2x2(0.90+2.10) 12.00 RM
44.80 RM

Cost analysis
MAT-00851 BMT - E.06 Cost of best TW frame 2 m to 3m length 0.1680 Cum 142480.00 1 Cum 23936.64
MAT-00850 BMT - E.05 Cost of best TW frame up to 2 m length 0.1724 Cum 134500.00 1 Cum 23187.80
MAT-01063 BMT-I.12 Cost of 12mm thick tinted glass 6.12 Sqm 1800.00 1 Sqm 11016.00
Joinery data 2021-22 - Page : 619
MAT-01057 BMT-I.06 Cost of 12mm thick plain float glass 3.78 Sqm 1375.00 1 Sqm 5197.50
Cost of teak wood beading 44.80 RM 21.58 1 RM 966.78
MAT-00921 BMT-G.22 Cost of 150mm long brass butt hinges 6 Nos 356.00 Each 2136.00
MAT-00967 BMT-G.62 Cost of 450mm long brass fancy handles 2 Nos 1600.00 Each 3200.00
MAT-00944 BMT-G.39 Cost of 450mm long brass heavy duty aldrop 1 No 3255.00 Each 3255.00
MAT-00908 BMT-G.03 Cost of 200mm long brass tower bolts 3 Nos 350.00 Each 1050.00
MAT-00951 BMT-G.46 Cost of brass door stoppers 2 Nos 185.00 Each 370.00
MAT-01639 BMT-W.69 Cost of Z hold fasts 6 Nos 39.00 Each 234.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 2 Nos 11.00 Each 22.00
Cost of MS Ornamental Grill 6.12 Sqm 2262.05 1 Sqm 13843.72
Labour charges 0.3404 Cum 15363.90 1 Cum 5229.87
Add for MAA @ 20% 0.20 5229.87 1045.97
LAB-00430 BMM-V.24 Labour charges for fixing glass 9.90 Sqm 315.00 1 Sqm 3118.50
Add for MAA @ 20% 0.20 3118.50 623.70
LAB-00426 BMM-V.20 Labour charges for glass designing work( Etching work) 3.78 Sqm 1051.00 1 Sqm 3972.78
Add for screws and nails 1.82
Rate for 7.80 sqm ###
Rate for 1 sqm 13129.24
Overheads&Contractors Profit @13.615% 0.13615 13129.24 1787.55
Rate for 1 sqm 14916.79
Say 14917

Supply and fixing of ornamental grill made of 25mm x 5mm MS flats for fixing in fan light portion and side fixed panels for door cum
window as per the approved drawing including cutting the flat to required length, welding, painting with red oxide single coat including cost
and conveyance of all materials, labour charges etc., complete for finished otem of work.
for grill of size 535mm x 435mm 0.2327 Sqm
MS flats: 4(0.535+0.435)+4x0.1+2x0.38 5.04 RM 1 Kg/RM 5.04 Kgs
Cost of MS flats 5.04 Kgs 62000.00 1000 Kgs 312.48
LAB-00420 BMM-V.14 Labour charges for fabrication of steel 5.04 Kgs 30.00 1 Kg 151.20
LAB-00421 BMM-V.15 Labour charges for fixing 5.04 Kgs 6.00 1 Kg 30.24
Add for MAA @ 20% 0.20 90.72 18.14
Painting with red oxide 0.2327 Sqm 617.49 10 Sqm 14.37
Rate per 0.2327 Sqm 526.43
Rate per 1 Sqm 2262.05
Painting with Red oxide
MAT-01075 BMT-J.03 Cost of red oxide 0.70 Ltr 145.00 1 Ltr 101.50
LAB-00035 CSoR I - 35 Painter 1st class 0.21 Nos. 705.00 1 Each 148.05
LAB-00093 CSoR II - 37 Painter 2st class 0.49 Nos. 565.00 1 Each 276.85
Add for MAA @ 20% 0.20 424.90 84.98
Sundries including brushes , ladders etc., @ 1% 0.01 611.38 6.11
617.49
Joinery data 2021-22 - Page : 620

2 Supply and fixing of doors as per approved drawings with best teak wood frame of section 100mm x 65 mm with fixed fan light of 500mm
at the top fixed with 4mm thick pin headed glass using 12mm x 12mm Teak Wood beading and 2 Nos. of 10mm MS Square bars and ISI
marked flush door shutter of 30mm thick double shutters with bond wood solid block board type core having cross bands and face veneers,
hot pressed bonded with water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides
commercial ply with internal lipping on all sides

including cost and conveyance to site of teak wood frame, flush shutter including supply and fixing 6 nos MS Z hold fasts of size 300 mm x
40 mm x 5mm including cost of ISI marked brass fixtures of 6 Nos butt hinges (IS:205) 150mm long , 1 No. aldrop (IS:2681) 300mm long, 2
Nos tower bolts- 10mm (IS:204) of 200 mm long at top, 1 No. tower bolt- 10mm bolt (IS:204) 150mm long at bottom, 2 Nos. 150mm long
fancy handles (IS:208) , 2 Nos door stopper and 2 Nos Rubber / Nylon door stop bushes including fixing the fixtures to door with required
number of screws, bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame, fixing glass in fan light
portion etc., including overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 The vertical frame of door
shall be embedded in flooring for a depth of not less than 10 mm) (2000mm x 2600mm)

(BLD-CSTN-13-16)
Size : 2.00m x 2.60 m 5.20 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393 cum
Outer frame - Horizontal 2 x 2.00 + 0.50
= 4.50 x 0.10 x 0.065 0.02925 cum
0.06318 cum

4 mm thick pin headed glass 2 x 1.00 x 0.50 1.00 sqm


Teak wood beading 2 x 2 (1.00+0.50) 6.00 RM
30 mm thick flush shutter 2 x 0.95 x 2.05 3.895 sqm
10 mm MS square bars 2 x 2.00 x 0.785 3.140 Kgs

Cost analysis
MAT-00851 BMT - E.06 Cost of best TW frame 2 m to 3m length 0.03393 cum 142480.00 1 cum 4834.35
MAT-00850 BMT - E.05 Cost of best TW frame up to 2 m length 0.02925 cum 134500.00 1 cum 3934.13
MAT-01064 BMT-I.13 Cost of 4 mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
Cost of TW beading 6.00 RM 21.58 1 RM 129.48
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 3.895 sqm 1400.00 1 sqm 5453.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00908 BMT-G.03 Cost of brass tower bolt 200mm long 2 Nos. 350.00 Each 700.00
MAT-00907 BMT-G.02 Cost of brass tower bolt 150mm long 1 No. 255.00 Each 255.00
MAT-00921 BMT-G.22 Cost of brass Butt hinges 150mm long 6 Nos. 356.00 Each 2136.00
MAT-00942 BMT-G.37 Cost of brass aldrop 300mm long 1 No. 1195.00 Each 1195.00
MAT-00963 BMT-G.58 Cost of brass fancy handle 150mm long 2 Nos. 328.00 Each 656.00
MAT-00951 BMT-G.46 Cost of brass door stopper 2 Nos. 185.00 Each 370.00
Joinery data 2021-22 - Page : 621
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 2 Nos. 11.00 Each 22.00
Cost of 10mm MS square bars 3.14 Kgs 62000.00 1000 Kgs 194.68
Labour charges for frame work 0.06318 cum 15363.90 1 cum 970.69
Add for MAA @ 20% 0.20 970.69 194.14
LAB-00429 BMM-V.23 Labour charges for fixing flush door shutter to the frame , fixing the
fixtures to the shutter 3.895 sqm 421.00 1 sqm 1639.80
Add for MAA @ 20% 0.20 1639.80 327.96
LAB-00430 BMM-V.24 Labour charges for fixing glass 1.00 sqm 315.00 1 sqm 315.00
Add for MAA @ 20% 0.20 315.00 63.00
Add for nails & screws etc. 0.77
Rate for 5.20 sqm 23994.98
Overheads&Contractors Profit @13.615% 0.13615 23994.98 3266.92
27261.90
Rate for 1 sqm 5242.67
Say 5243

3 Supply and fixing of doors as per approved drawings with best teak wood frame of section 100mm x 65 mm with fixed fan light of 500mm
at the top fixed with 4mm thick pin headed glass using 12mm x 12mm Teak Wood beading and 2 Nos. of 10mm MS Square bars and ISI
marked flush door shutter of 30mm thick double shutters with bond wood solid block board type core having cross bands and face veneers,
hot pressed bonded with water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides
commercial ply with internal lipping on all sides, fixing 1mm thick mat finish laminated sheet to full width and height of the flush shutter
both sides

including cost and conveyance to site of teak wood frame, flush shutter, laminate sheet including supply and fixing 6 nos MS Z hold fasts of
size 300 mm x 40 mm x 5mm including cost of ISI marked brass fixtures of 6 Nos butt hinges (IS:205) 150mm long , 1 No. aldrop (IS:2681)
300mm long, 2 Nos tower bolts- 10mm (IS:204) of 200 mm long at top, 1 No. tower bolt- 10mm bolt (IS:204) 150mm long at bottom, 2 Nos.
150mm long fancy handles (IS:208) , 2 Nos door stopper and 2 Nos Rubber / Nylon door stop bushes including fixing the fixtures to door
with required number of screws, bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame, fixing
glass in fan light portion etc., including overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 The
vertical frame of door shall be embedded in flooring for a depth of not less than 10 mm) (2000mm x 2600mm)

(BLD-CSTN-13-16)
Size : 2.00m x 2.60 m 5.20 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393 cum
Outer frame - Horizontal 2 x 2.00 + 0.50
= 4.50 x 0.10 x 0.065 0.02925 cum
0.06318 cum

4 mm thick pin headed glass 2 x 1.00 x 0.50 1.00 sqm


Joinery data 2021-22 - Page : 622
Teak wood beading 2 x 2 (1.00+0.50) 6.00 RM
30 mm thick flush shutter 2 x 0.95 x 2.05 3.895 sqm
10 mm MS square bars 2 x 2.00 x 0.785 3.140 Kgs
Joinery data 2021-22 - Page : 623
Cost analysis
MAT-00851 BMT - E.06 Cost of best TW frame 2 m to 3m length 0.03393 cum 142480.00 1 cum 4834.35
MAT-00850 BMT - E.05 Cost of best TW frame up to 2 m length 0.02925 cum 134500.00 1 cum 3934.13
MAT-01064 BMT-I.13 Cost of 4 mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
Cost of TW beading 6.00 RM 21.58 1 RM 129.48
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 3.895 sqm 1400.00 1 sqm 5453.00
MAT-01208 BMT-L.24 Cost of 1mm thick mat finish laminated sheet 7.79 sqm 400.00 1 sqm 3116.00
Labour charges for fixing laminated sheet 100.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00908 BMT-G.03 Cost of brass tower bolt 200mm long 2 Nos. 350.00 Each 700.00
MAT-00907 BMT-G.02 Cost of brass tower bolt 150mm long 1 No. 255.00 Each 255.00
MAT-00921 BMT-G.22 Cost of brass Butt hinges 150mm long 6 Nos. 356.00 Each 2136.00
MAT-00942 BMT-G.37 Cost of brass aldrop 300mm long 1 No. 1195.00 Each 1195.00
MAT-00963 BMT-G.58 Cost of brass fancy handle 150mm long 2 Nos. 328.00 Each 656.00
MAT-00951 BMT-G.46 Cost of brass door stopper 2 Nos. 185.00 Each 370.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 2 Nos. 11.00 Each 22.00
Cost of 10mm MS square bars 3.14 Kgs 62000.00 1000 Kgs 194.68
Labour charges for frame work 0.06318 cum 15363.90 1 cum 970.69
Add for MAA @ 20% 0.20 970.69 194.14
LAB-00429 BMM-V.23 Labour charges for fixing flush door shutter to the frame , fixing the
fixtures to the shutter 3.895 sqm 421.00 1 sqm 1639.80
Add for MAA @ 20% 0.20 1639.80 327.96
LAB-00430 BMM-V.24 Labour charges for fixing glass 1.00 sqm 315.00 1 sqm 315.00
Add for MAA @ 20% 0.20 315.00 63.00
Add for nails & screws etc. 3.47
Rate for 5.20 sqm 27213.68
Overheads&Contractors Profit @13.615% 0.13615 27213.68 3705.14
30918.83
Rate for 1 sqm 5945.93
Say 5946
Joinery data 2021-22 - Page : 624
4 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm x 65 mm with fixed fan light of
500mm at the top fixed with 4mm thick pin headed glass using 12mm x 12mm Teak Wood beading and 2 Nos. of 10mm MS Square bars and
ISI marked flush door shutter of 30mm thick double shutters with bond wood solid block board type core having cross bands and face
veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both
sides commercial ply with internal lipping on all sides

including cost and conveyance to site of teak wood frame, flush shutter including supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x
40 mm x 5mm including cost of ISI marked Aluminium fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm
long, 2 Nos. tower bolts - 10mm (IS:204) of 200 mm long at top, 2 Nos. 150mm long handles (IS:208), 2 Nos. door stoppers and 2 Nos.
Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws, bolt and nuts including labour charges
for fixing the frame in position, fixing the shutter to the frame, fixing glass in fan light portion etc., including overheads & contractors profit
complete for finished item of work as per APSS 1001 & 1002 The vertical frame of door shall be embedded in flooring for a depth of not less
than 10 mm) (1800mm x 2600mm)

(BLD-CSTN-13-16)
Size : 1.80m x 2.60m 4.68 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393 cum
Outer frame - Horizontal 2 x 1.80 + 0.50
= 4.10 x 0.10 x 0.065 0.02665 cum
0.06058 cum

4 mm thick pin headed glass 1.80 x 0.50 0.90 sqm


Teak wood beading 2 x 2 (0.90+0.50) 5.60 RM
30 mm thick flush shutter 2 x 0.85 x 2.05 3.485 sqm
10 mm MS square bars 2 x 1.80 x 0.785 2.826 Kgs
Cost analysis
MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.03393 cum 92130.00 1 cum 3125.97
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.02665 cum 81950.00 1 cum 2183.97
MAT-01064 BMT-I.13 Cost of 4 mm thick pin headed glass 0.90 sqm 370.00 1 sqm 333.00
Cost of TW beading 5.60 RM 21.58 1 RM 120.85
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 3.485 sqm 1400.00 1 sqm 4879.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 2 Nos. 108.00 Each 216.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 6 Nos. 133.00 Each 798.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 2 Nos. 58.00 Each 116.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 2 Nos. 11.00 Each 22.00
Cost of 10mm MS square bars 2.826 Kgs 62000.00 1000 Kgs 175.21
Labour charges for frame work 0.06058 cum 15363.90 1 cum 930.75
Joinery data 2021-22 - Page : 625
Add for MAA @ 20% 0.20 930.75 186.15
Labour charges for fixing flush door shutter to the frame , fixing the
LAB-00429 BMM-V.23
fixtures to the shutter 3.485 sqm 421.00 1 sqm 1467.19
Add for MAA @ 20% 0.20 1467.19 293.44
LAB-00430 BMM-V.24 Labour charges for fixing glass 0.90 sqm 315.00 1 sqm 283.50
Add for MAA @ 20% 0.20 283.50 56.70
Add for nails & screws etc. 3.30
Rate for 4.68 sqm 15991.01
Overheads&Contractors Profit @13.615% 0.13615 15991.01 2177.18
18168.19
Rate for 1 sqm 3882.09
Say 3882

5 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm x 65 mm with fixed fan light of
500mm at the top fixed with 4mm thick pin headed glass using 12mm x 12mm Teak Wood beading and 2 Nos. of 10mm MS Square bars and
ISI marked flush door shutter of 30mm thick double shutters with bond wood solid block board type core having cross bands and face
veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both
sides commercial ply with internal lipping on all sides, fixing 1mm thick mat finish laminated sheet to full width and height of the flush
shutter both sides

including cost and conveyance to site of teak wood frame, flush shutter, laminate sheet including supply and fixing 6 Nos. MS Z hold fasts
of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop
(IS:2681) 300mm long, 2 Nos. tower bolts - 10mm (IS:204) of 200 mm long at top, 2 Nos. 150mm long handles (IS:208), 2 Nos. door
stoppers and 2 Nos. Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws, bolt and nuts
including labour charges for fixing the frame in position, fixing the shutter to the frame, fixing glass in fan light portion etc., including
overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 The vertical frame of door shall be embedded in
flooring for a depth of not less than 10 mm) (1800mm x 2600mm)

(BLD-CSTN-13-16)
Size : 1.80m x 2.60m 4.68 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393 cum
Outer frame - Horizontal 2 x 1.80 + 0.50
= 4.10 x 0.10 x 0.065 0.02665 cum
0.06058 cum

4 mm thick pin headed glass 1.80 x 0.50 0.90 sqm


Teak wood beading 2 x 2 (0.90+0.50) 5.60 RM
30 mm thick flush shutter 2 x 0.85 x 2.05 3.485 sqm
10 mm MS square bars 2 x 1.80 x 0.785 2.826 Kgs
Cost analysis
Joinery data 2021-22 - Page : 626
MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.03393 cum 92130.00 1 cum 3125.97
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.02665 cum 81950.00 1 cum 2183.97
MAT-01064 BMT-I.13 Cost of 4 mm thick pin headed glass 0.90 sqm 370.00 1 sqm 333.00
Cost of TW beading 5.60 RM 21.58 1 RM 120.85
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 3.485 sqm 1400.00 1 sqm 4879.00
MAT-01208 BMT-L.24 Cost of 1mm thick mat finish laminated sheet 6.970 sqm 400.00 1 sqm 2788.00
Labour charges for fixing laminated sheet 100.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 2 Nos. 108.00 Each 216.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 6 Nos. 133.00 Each 798.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 2 Nos. 58.00 Each 116.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 2 Nos. 11.00 Each 22.00
Cost of 10mm MS square bars 2.826 Kgs 62000.00 1000 Kgs 175.21
Labour charges for frame work 0.06058 cum 15363.90 1 cum 930.75
Add for MAA @ 20% 0.20 930.75 186.15
Labour charges for fixing flush door shutter to the frame , fixing the
LAB-00429 BMM-V.23
fixtures to the shutter 3.485 sqm 421.00 1 sqm 1467.19
Add for MAA @ 20% 0.20 1467.19 293.44
LAB-00430 BMM-V.24 Labour charges for fixing glass 0.90 sqm 315.00 1 sqm 283.50
Add for MAA @ 20% 0.20 283.50 56.70
Add for nails & screws etc. 4.40
Rate for 4.68 sqm 18880.11
Overheads&Contractors Profit @13.615% 0.13615 18880.11 2570.53
21450.64
Rate for 1 sqm 4583.47
Say 4583

6 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm x 65 mm with split type fan light
of 500mm at the top fixed with 4mm thick pin headed glass using 12mm x 12mm Teak Wood beading and 2 Nos. of 10mm MS Square bars
and ISI marked flush door shutter of 30mm thick double shutters with bond wood solid block board type core having cross bands and face
veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both
sides commercial ply with internal lipping on all sides,

including cost and conveyance to site of teak wood frame, flush shutter including supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x
40 mm x 5mm including cost of ISI marked Alumimium fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm
long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150mm long handles (IS:208), 2 Nos. door stoppers and 2 Nos.
Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws, bolt and nuts including labour charges
for fixing the frame in position, fixing the shutter to the frame, fixing glass in fan light portion etc., including overheads & contractors profit
complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for a depth of not less
than 10 mm) (1500mm x 2600mm)
Joinery data 2021-22 - Page : 627
(BLD-CSTN-13-16)
Size : 1.50m x 2.60m 3.90 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393 cum
Outer frame - Horizontal 2 x 1.50 + 0.50
= 3.50 x 0.10 x 0.065 0.02275 cum
0.05668 cum

4 mm thick pin headed glass 2 x 1.50 x 0.30 0.90 sqm


Teak wood beading 2 x 2 (1.50+2 x 0.30) 8.40 RM
30 mm thick flush shutter 2 x 0.70 x 2.05 2.87 sqm
10 mm MS square bars 2 x 1.50 x 0.785 2.355 Kgs

Cost analysis
MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.03393 cum 92130.00 1 cum 3125.97
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.02275 cum 81950.00 1 cum 1864.36
MAT-01064 BMT-I.13 Cost of 4 mm thick pin headed glass 0.90 sqm 370.00 1 sqm 333.00
Cost of TW beading 8.40 RM 21.58 1 RM 181.27
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 2.87 sqm 1400.00 1 sqm 4018.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 2 Nos. 108.00 Each 216.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 6 Nos. 133.00 Each 798.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 2 Nos. 58.00 Each 116.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 2 Nos. 11.00 Each 22.00
Cost of 10mm MS square bars 2.355 Kgs 62000.00 1000 Kgs 146.01
Labour charges for frame work 0.05668 cum 15363.90 1 cum 870.83
Add for MAA @ 20% 0.20 870.83 174.17
LAB-00429 BMM-V.23 Labour charges for fixing flush door shutter to the frame , fixing the
fixtures to the shutter 2.87 sqm 421.00 1 sqm 1208.27
Add for MAA @ 20% 0.20 1208.27 241.65
LAB-00430 BMM-V.24 Labour charges for fixing glass 0.90 sqm 315.00 1 sqm 283.50
Add for MAA @ 20% 0.20 283.50 56.70
Add for nails & screws etc. 3.36
Rate for 3.90 sqm 14459.09
Overheads&Contractors Profit @13.615% 0.13615 14459.09 1968.61
16427.70
Rate for 1 sqm 4212.23
Say 4212
Joinery data 2021-22 - Page : 628
Joinery data 2021-22 - Page : 629
7 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm x 65 mm with split type fan light
of 500mm at the top fixed with 4mm thick pin headed glass using 12mm x 12mm Teak Wood beading and 2 Nos. of 10mm MS Square bars
and ISI marked flush door shutter of 30mm thick double shutters with bond wood solid block board type core having cross bands and face
veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both
sides commercial ply with internal lipping on all sides, fixing 1mm thick mat finish laminated sheet to full width and height of the flush
shutter both sides

including cost and conveyance to site of teak wood frame, flush shutter, laminate sheet including supply and fixing 6 Nos. MS Z hold fasts of
size 300 mm x 40 mm x 5mm including cost of ISI marked Alumimium fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop
(IS:2681) 300mm long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150mm long handles (IS:208), 2 Nos. door stoppers
and 2 Nos. Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws, bolt and nuts including
labour charges for fixing the frame in position, fixing the shutter to the frame, fixing glass in fan light portion etc., including overheads &
contractors profit complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for a
depth of not less than 10 mm) (1500mm x 2600mm)

(BLD-CSTN-13-16)
Size : 1.50m x 2.60m 3.90 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393 cum
Outer frame - Horizontal 2 x 1.50 + 0.50
= 3.50 x 0.10 x 0.065 0.02275 cum
0.05668 cum

4 mm thick pin headed glass 2 x 1.50 x 0.30 0.90 sqm


Teak wood beading 2 x 2 (1.50+2 x 0.30) 8.40 RM
30 mm thick flush shutter 2 x 0.70 x 2.05 2.87 sqm
10 mm MS square bars 2 x 1.50 x 0.785 2.355 Kgs

Cost analysis
MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.03393 cum 92130.00 1 cum 3125.97
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.02275 cum 81950.00 1 cum 1864.36
MAT-01064 BMT-I.13 Cost of 4 mm thick pin headed glass 0.90 sqm 370.00 1 sqm 333.00
Cost of TW beading 8.40 RM 21.58 1 RM 181.27
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 2.87 sqm 1400.00 1 sqm 4018.00
MAT-01208 BMT-L.24 Cost of 1mm thick mat finish laminated sheet 5.74 sqm 400.00 1 sqm 2296.00
Labour charges for fixing laminated sheet 100.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 2 Nos. 108.00 Each 216.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 6 Nos. 133.00 Each 798.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
Joinery data 2021-22 - Page : 630
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 2 Nos. 58.00 Each 116.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 2 Nos. 11.00 Each 22.00
Cost of 10mm MS square bars 2.355 Kgs 62000.00 1000 Kgs 146.01
Labour charges for frame work 0.05668 cum 15363.90 1 cum 870.83
Add for MAA @ 20% 0.20 870.83 174.17
LAB-00429 BMM-V.23 Labour charges for fixing flush door shutter to the frame , fixing the
fixtures to the shutter 2.87 sqm 421.00 1 sqm 1208.27
Add for MAA @ 20% 0.20 1208.27 241.65
LAB-00430 BMM-V.24 Labour charges for fixing glass 0.90 sqm 315.00 1 sqm 283.50
Add for MAA @ 20% 0.20 283.50 56.70
Add for nails & screws etc. 4.56
Rate for 3.90 sqm 16856.29
Overheads&Contractors Profit @13.615% 0.13615 16856.29 2294.98
19151.27
Rate for 1 sqm 4910.58
Say 4911

8 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm x 65 mm with split type fan light
of 500mm at the top fixed with 4mm thick pin headed glass using 12mm x 12mm Teak Wood beading and 2 Nos. of 10mm MS Square bars
and ISI marked flush door shutter of 30mm thick double shutters with bond wood solid block board type core having cross bands and face
veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both
sides commercial ply with internal lipping on all sides,

including cost and conveyance to site of teak wood frame, flush shutter including supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x
40 mm x 5mm including cost of ISI marked Aluminium fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm
long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150mm long handles (IS:208), 2 Nos. door stoppers and 2 Nos.
Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws, bolt and nuts including labour charges
for fixing the frame in position, fixing the shutter to the frame, fixing glass in fan light portion etc, including overheads & contractors profit
complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for a depth of not less
than 10 mm) (1200mm x 2600mm)

(BLD-CSTN-13-16)
Size : 1.20m x 2.60m 3.12 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393 cum
Outer frame - Horizontal 2 x 1.20 + 0.50
= 2.90 x 0.10 x 0.065 0.01885 cum
0.05278 cum

4 mm thick pin headed glass 2 x 1.20 x 0.30 0.72 sqm


Teak wood beading 2 x 2 (1.20+2 x 0.30) 7.20 RM
Joinery data 2021-22 - Page : 631
30 mm thick flush shutter 2 x 0.55 x 2.05 2.255 sqm
10 mm MS square bars 2 x 1.20 x 0.785 1.884 Kgs
Joinery data 2021-22 - Page : 632
Cost analysis
MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.03393 cum 92130.00 1 cum 3125.97
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.01885 cum 81950.00 1 cum 1544.76
MAT-01064 BMT-I.13 Cost of 4 mm thick pin headed glass 0.72 sqm 370.00 1 sqm 266.40
Cost of TW beading 7.20 RM 21.58 1 RM 155.38
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 2.255 sqm 1400.00 1 sqm 3157.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 2 Nos. 108.00 Each 216.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 6 Nos. 133.00 Each 798.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 2 Nos. 58.00 Each 116.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 2 Nos. 11.00 Each 22.00
Cost of 10mm MS square bars 1.884 Kgs 62000.00 1000 Kgs 116.81
Labour charges for frame work 0.0528 cum 15363.90 1 cum 810.91
Add for MAA @ 20% 0.20 810.91 162.18
LAB-00429 BMM-V.23 Labour charges for fixing flush door shutter to the frame , fixing the
fixtures to the shutter 2.255 sqm 421.00 1 sqm 949.36
Add for MAA @ 20% 0.20 949.36 189.87
LAB-00430 BMM-V.24 Labour charges for fixing glass 0.72 sqm 315.00 1 sqm 226.80
Add for MAA @ 20% 0.20 226.80 45.36
Add for nails & screws etc. 1.57
Rate for 3.12 sqm 12704.36
Overheads&Contractors Profit @13.615% 0.13615 12704.36 1729.70
14434.05
Rate for 1 sqm 4626.30
Say 4626
Joinery data 2021-22 - Page : 633
9 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm x 65 mm with split type fan light
of 500mm at the top fixed with 4mm thick pin headed glass using 12mm x 12mm Teak Wood beading and 2 Nos. of 10mm MS Square bars
and ISI marked flush door shutter of 30mm thick double shutters with bond wood solid block board type core having cross bands and face
veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both
sides commercial ply with internal lipping on all sides, fixing 1mm thick mat finish laminated sheet to full width and height of the flush
shutter both sides

including cost and conveyance to site of teak wood frame, flush shutter, laminate sheet including supply and fixing 6 Nos. MS Z hold fasts of
size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop
(IS:2681) 300mm long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150mm long handles (IS:208), 2 Nos. door
stoppers and 2 Nos. Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws, bolt and nuts
including labour charges for fixing the frame in position, fixing the shutter to the frame, fixing glass in fan light portion etc, including overheads
& contractors profit complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for
a depth of not less than 10 mm) (1200mm x 2600mm)

(BLD-CSTN-13-16)
Size : 1.20m x 2.60m 3.12 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393 cum
Outer frame - Horizontal 2 x 1.20 + 0.50
= 2.90 x 0.10 x 0.065 0.01885 cum
0.05278 cum

4 mm thick pin headed glass 2 x 1.20 x 0.30 0.72 sqm


Teak wood beading 2 x 2 (1.20+2 x 0.30) 7.20 RM
30 mm thick flush shutter 2 x 0.55 x 2.05 2.255 sqm
10 mm MS square bars 2 x 1.20 x 0.785 1.884 Kgs

Cost analysis
MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.03393 cum 92130.00 1 cum 3125.97
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.01885 cum 81950.00 1 cum 1544.76
MAT-01064 BMT-I.13 Cost of 4 mm thick pin headed glass 0.72 sqm 370.00 1 sqm 266.40
Cost of TW beading 7.20 RM 21.58 1 RM 155.38
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 2.255 sqm 1400.00 1 sqm 3157.00
MAT-01208 BMT-L.24 Cost of 1mm thick mat finish laminated sheet 4.51 sqm 400.00 1 sqm 1804.00
Labour charges for fixing laminated sheet 100.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 2 Nos. 108.00 Each 216.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 6 Nos. 133.00 Each 798.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
Joinery data 2021-22 - Page : 634
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 2 Nos. 58.00 Each 116.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 2 Nos. 11.00 Each 22.00
Cost of 10mm MS square bars 1.884 Kgs 62000.00 1000 Kgs 116.81
Labour charges for frame work 0.0528 cum 15363.90 1 cum 810.91
Add for MAA @ 20% 0.20 810.91 162.18
LAB-00429 BMM-V.23 Labour charges for fixing flush door shutter to the frame , fixing the
fixtures to the shutter 2.255 sqm 421.00 1 sqm 949.36
Add for MAA @ 20% 0.20 949.36 189.87
LAB-00430 BMM-V.24 Labour charges for fixing glass 0.72 sqm 315.00 1 sqm 226.80
Add for MAA @ 20% 0.20 226.80 45.36
Add for nails & screws etc. 2.87
Rate for 3.12 sqm 14609.66
Overheads&Contractors Profit @13.615% 0.13615 14609.66 1989.10
16598.76
Rate for 1 sqm 5320.12
Say 5320

10 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm x 65 mm with split type fan light
of 500mm at the top fixed with 4mm thick pin headed glass using 12mm x 12mm Teak Wood beading and 2 Nos. of 10mm MS Square bars
and ISI marked flush door shutter of 30mm thick single shutter with bond wood solid block board type core having cross bands and face
veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both
sides commercial ply with internal lipping on all sides including cost and conveyance to site of teak wood frame, flush shutter including
supply and fixing

6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 3 Nos. butt hinges (IS:205) 150mm
long , 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150mm long handles (IS:208), 1
No. door stopper and 1 No. Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws, bolt and
nuts including labour charges for fixing the frame in position, fixing the shutter to the frame, fixing glass in fan light portion etc, including
overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in
flooring for a depth of not less than 10 mm) (1000mm x 2600mm)

(BLD-CSTN-13-16)
Size : 1.00m x 2.60m 2.60 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393 cum
Outer frame - Horizontal 2 x 1.00
= 2.00 x 0.10 x 0.065 0.01300 cum
0.04693 cum

4 mm thick pin headed glass 2 x 1.00 x 0.30 0.60 sqm


Teak wood beading 2 x (1.00+2 x 0.30) 3.20 RM
Joinery data 2021-22 - Page : 635
30 mm thick flush shutter 2 x 0.90 x 2.05 1.845 sqm
10 mm MS square bars 2 x 1.00 x 0.785 1.570 Kgs
Joinery data 2021-22 - Page : 636
Cost analysis
MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.03393 cum 92130.00 1 cum 3125.97
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.0130 cum 81950.00 1 cum 1065.35
MAT-01064 BMT-I.13 Cost of 4 mm thick pin headed glass 0.60 sqm 370.00 1 sqm 222.00
Cost of TW beading 3.20 RM 21.58 1 RM 69.06
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 1.845 sqm 1400.00 1 sqm 2583.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 1 No. 108.00 Each 108.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 3 Nos. 133.00 Each 399.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 1 No. 58.00 Each 58.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 1 No. 11.00 Each 11.00
Cost of 10mm MS square bars 1.57 Kgs 62000.00 1000 Kgs 97.34
Labour charges for frame work 0.0469 cum 15363.90 1 cum 721.03
Add for MAA @ 20% 0.20 721.03 144.21
LAB-00429 BMM-V.23 Labour charges for fixing flush door shutter to the frame , fixing the
fixtures to the shutter 1.845 sqm 421.00 1 sqm 776.75
Add for MAA @ 20% 0.20 776.75 155.35
LAB-00430 BMM-V.24 Labour charges for fixing glass 0.60 sqm 315.00 1 sqm 189.00
Add for MAA @ 20% 0.20 189.00 37.80
Add for nails & screws etc. 1.02
Rate for 2.60 sqm 10563.86
Overheads&Contractors Profit @13.615% 0.13615 10563.86 1438.27
12002.13
Rate for 1 sqm 4616.21
Say 4616
Joinery data 2021-22 - Page : 637
11 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm x 65 mm with split type fan light
of 500mm at the top fixed with 4mm thick pin headed glass using 12mm x 12mm Teak Wood beading and 2 Nos. of 10mm MS Square bars
and ISI marked flush door shutter of 30mm thick single shutter with bond wood solid block board type core having cross bands and face
veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both
sides commercial ply with internal lipping on all sides fixing 1mm thick mat finish laminated sheet to full width and height of the flush
shutter both sides including cost and conveyance to site of teak wood frame, flush shutter, laminate sheet including supply and fixing

6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 3 Nos. butt hinges (IS:205) 150mm
long , 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150mm long handles (IS:208), 1
No. door stopper and 1 No. Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws, bolt and
nuts including labour charges for fixing the frame in position, fixing the shutter to the frame, fixing glass in fan light portion etc, including
overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in
flooring for a depth of not less than 10 mm) (1000mm x 2600mm)

(BLD-CSTN-13-16)
Size : 1.00m x 2.60m 2.60 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393 cum
Outer frame - Horizontal 2 x 1.00
= 2.00 x 0.10 x 0.065 0.01300 cum
0.04693 cum

4 mm thick pin headed glass 2 x 1.00 x 0.30 0.60 sqm


Teak wood beading 2 x (1.00+2 x 0.30) 3.20 RM
30 mm thick flush shutter 2 x 0.90 x 2.05 1.845 sqm
10 mm MS square bars 2 x 1.00 x 0.785 1.570 Kgs

Cost analysis
MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.03393 cum 92130.00 1 cum 3125.97
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.0130 cum 81950.00 1 cum 1065.35
MAT-01064 BMT-I.13 Cost of 4 mm thick pin headed glass 0.60 sqm 370.00 1 sqm 222.00
Cost of TW beading 3.20 RM 21.58 1 RM 69.06
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 1.845 sqm 1400.00 1 sqm 2583.00
MAT-01208 BMT-L.24 Cost of 1mm thick mat finish laminated sheet 3.69 sqm 400.00 1 sqm 1476.00
Labour charges for fixing laminated sheet 100.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 1 No. 108.00 Each 108.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 3 Nos. 133.00 Each 399.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
Joinery data 2021-22 - Page : 638
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 1 No. 58.00 Each 58.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 1 No. 11.00 Each 11.00
Cost of 10mm MS square bars 1.57 Kgs 62000.00 1000 Kgs 97.34
Labour charges for frame work 0.0469 cum 15363.90 1 cum 721.03
Add for MAA @ 20% 0.20 721.03 144.21
LAB-00429 BMM-V.23 Labour charges for fixing flush door shutter to the frame , fixing the
fixtures to the shutter 1.845 sqm 421.00 1 sqm 776.75
Add for MAA @ 20% 0.20 776.75 155.35
LAB-00430 BMM-V.24 Labour charges for fixing glass 0.60 sqm 315.00 1 sqm 189.00
Add for MAA @ 20% 0.20 189.00 37.80
Add for nails & screws etc. 0.72
Rate for 2.60 sqm 12139.56
Overheads&Contractors Profit @13.615% 0.13615 12139.56 1652.80
13792.37
Rate for 1 sqm 5304.76
Say 5305

12 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm x 65 mm with split type fan light
of 500mm at the top fixed with 4mm thick pin headed glass using 12mm x 12mm Teak Wood beading and 2 Nos. of 10mm MS Square bars
and ISI marked flush door shutter of 30mm thick single shutter with bond wood solid block board type core having cross bands and face
veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both
sides commercial ply with internal lipping on all sides including cost and conveyance to site of teak wood frame, flush shutter including
supply and fixing

6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 3 Nos. butt hinges (IS:205) 150mm
long , 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150mm long handles (IS:208), 1
No. door stopper and 1 No. Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws, bolt and
nuts including labour charges for fixing the frame in position, fixing the shutter to the frame, fixing glass in fan light portion etc, including
overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in
flooring for a depth of not less than 10 mm) (900mm x 2600mm)

(BLD-CSTN-13-16)
Size : 0.90m x 2.60m 2.34 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393 cum
Outer frame - Horizontal 2 x 0.90
= 1.80 x 0.10 x 0.065 0.01170 cum
0.04563 cum

4 mm thick pin headed glass 2 x 0.90 x 0.30 0.54 sqm


Teak wood beading 2 x (0.90+2 x 0.30) 3.00 RM
Joinery data 2021-22 - Page : 639
30 mm thick flush shutter 1 x 0.80 x 2.05 1.64 sqm
10 mm MS square bars 2 x 0.90 x 0.785 1.413 Kgs
Joinery data 2021-22 - Page : 640
Cost analysis
MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.03393 cum 92130.00 1 cum 3125.97
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.0117 cum 81950.00 1 cum 958.82
MAT-01064 BMT-I.13 Cost of 4 mm thick pin headed glass 0.54 sqm 370.00 1 sqm 199.80
Cost of TW beading 3.00 RM 21.58 1 RM 64.74
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 1.640 sqm 1400.00 1 sqm 2296.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 1 No. 108.00 Each 108.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 3 Nos. 133.00 Each 399.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 1 No. 58.00 Each 58.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 1 No. 11.00 Each 11.00
Cost of 10mm MS square bars 1.413 Kgs 62000.00 1000 Kgs 87.61
Labour charges for frame work 0.0456 cum 15363.90 1 cum 701.05
Add for MAA @ 20% 0.20 701.05 140.21
LAB-00429 BMM-V.23 Labour charges for fixing flush door shutter to the frame , fixing the
fixtures to the shutter 1.640 sqm 421.00 1 sqm 690.44
Add for MAA @ 20% 0.20 690.44 138.09
LAB-00430 BMM-V.24 Labour charges for fixing glass 0.54 sqm 315.00 1 sqm 170.10
Add for MAA @ 20% 0.20 170.10 34.02
Add for nails & screws etc. 4.84
Rate for 2.34 sqm 9987.69
Overheads&Contractors Profit @13.615% 0.13615 9987.69 1359.82
11347.51
Rate for 1 sqm 4849.36
Say 4849
Joinery data 2021-22 - Page : 641
13 Supply and fixing of doors as per approved drawings with medium teak wood frame of section 100mm x 65 mm with split type fan light
of 500mm at the top fixed with 4mm thick pin headed glass using 12mm x 12mm Teak Wood beading and 2 Nos. of 10mm MS Square bars
and ISI marked flush door shutter of 30mm thick single shutter with bond wood solid block board type core having cross bands and face
veneers, hot pressed bonded with water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both
sides commercial ply with internal lipping on all sides, fixing 1mm thick mat finish laminated sheet to full width and height of the flush
shutter both sides including cost and conveyance to site of teak wood frame, flush shutter, laminate sheet including supply and fixing

6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 3 Nos. butt hinges (IS:205) 150mm
long , 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150mm long handles (IS:208), 1
No. door stopper and 1 No. Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws, bolt and
nuts including labour charges for fixing the frame in position, fixing the shutter to the frame, fixing glass in fan light portion etc, including
overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in
flooring for a depth of not less than 10 mm) (900mm x 2600mm)

(BLD-CSTN-13-16)
Size : 0.90m x 2.60m 2.34 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.61
= 5.22 x 0.10 x 0.065 0.03393 cum
Outer frame - Horizontal 2 x 0.90
= 1.80 x 0.10 x 0.065 0.01170 cum
0.04563 cum

4 mm thick pin headed glass 2 x 0.90 x 0.30 0.54 sqm


Teak wood beading 2 x (0.90+2 x 0.30) 3.00 RM
30 mm thick flush shutter 1 x 0.80 x 2.05 1.64 sqm
10 mm MS square bars 2 x 0.90 x 0.785 1.413 Kgs

Cost analysis
MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.03393 cum 92130.00 1 cum 3125.97
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.0117 cum 81950.00 1 cum 958.82
MAT-01064 BMT-I.13 Cost of 4 mm thick pin headed glass 0.54 sqm 370.00 1 sqm 199.80
Cost of TW beading 3.00 RM 21.58 1 RM 64.74
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 1.640 sqm 1400.00 1 sqm 2296.00
MAT-01208 BMT-L.24 Cost of 1mm thick mat finish laminated sheet 3.28 sqm 400.00 1 sqm 1312.00
Labour charges for fixing laminated sheet 100.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 1 No. 108.00 Each 108.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 3 Nos. 133.00 Each 399.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 1 No. 58.00 Each 58.00
Joinery data 2021-22 - Page : 642
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 1 No. 11.00 Each 11.00
Cost of 10mm MS square bars 1.413 Kgs 62000.00 1000 Kgs 87.61
Labour charges for frame work 0.0456 cum 15363.90 1 cum 701.05
Add for MAA @ 20% 0.20 701.05 140.21
LAB-00429 BMM-V.23 Labour charges for fixing flush door shutter to the frame , fixing the
fixtures to the shutter 1.640 sqm 421.00 1 sqm 690.44
Add for MAA @ 20% 0.20 690.44 138.09
LAB-00430 BMM-V.24 Labour charges for fixing glass 0.54 sqm 315.00 1 sqm 170.10
Add for MAA @ 20% 0.20 170.10 34.02
Add for nails & screws etc. 1.24
Rate for 2.34 sqm 11396.09
Overheads&Contractors Profit @13.615% 0.13615 11396.09 1551.58
12947.66
Rate for 1 sqm 5533.19
Say 5533

14 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and ISI marked flush door shutters of
30 mm thick double shutters with bond wood solid block board type Core having cross bands and face veneers, hot pressed bonded with
water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides including cost and conveyance to site of teak wood frame, flush shutter including

supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 6 Nos. butt
hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150 mm
long handles (IS:208), 2 Nos. door stoppers and 2 Nos. Rubber / Nylon door stop bushes including fixing the fixtures to door with required
number of screws, bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame etc, including
overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in
flooring for a depth of not less than 10 mm) (2000mm x 2100mm)

(BLD-CSTN-13-16)
Size : 2.00m x 2.10m 4.20 Sqm
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743 cum
Outer frame - Horizontal 1 x 2.00
= 2.00 x 0.10 x 0.065 0.01300 cum
0.04043 cum

30 mm thick flush shutter 2 x 0.95 x 2.05 3.895 sqm

MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.02743 cum 92130.00 1 cum 2527.13
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.01300 cum 81950.00 1 cum 1065.35
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 3.895 sqm 1400.00 1 sqm 5453.00
Joinery data 2021-22 - Page : 643
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 2 Nos. 108.00 Each 216.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 6 Nos. 133.00 Each 798.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 2 Nos. 58.00 Each 116.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 2 Nos. 11.00 Each 22.00
Labour charges for frame work 0.04043 cum 15363.90 1 cum 621.16
Add for MAA @ 20% 0.20 621.16 124.23
Labour charges for fixing flush door shutter to the frame , fixing the
LAB-00429 BMM-V.23
fixtures to the shutter 3.895 sqm 421.00 1 sqm 1639.80
Add for MAA @ 20% 0.20 1639.80 327.96
Add for nails & screws etc. 2.52
Rate for 4.20 sqm 13713.14
Rate for 1 sqm 3265.03
Overheads&Contractors Profit @13.615% 0.13615 3265.03 444.53
Rate for 1 sqm 3709.57
Say 3710

15 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and ISI marked flush door shutters of
30 mm thick double shutters with bond wood solid block board type Core having cross bands and face veneers, hot pressed bonded with
water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides, fixing 1mm thick mat finish laminated sheet to full width and height of the flush shutter both sides including cost
and conveyance to site of teak wood frame, flush shutter, laminate sheet including

supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 6 Nos. butt
hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150 mm
long handles (IS:208), 2 Nos. door stoppers and 2 Nos. Rubber / Nylon door stop bushes including fixing the fixtures to door with required
number of screws, bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame etc, including
overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in
flooring for a depth of not less than 10 mm) (2000mm x 2100mm)

(BLD-CSTN-13-16)
Size : 2.00m x 2.10m 4.20 Sqm
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743 cum
Outer frame - Horizontal 1 x 2.00
= 2.00 x 0.10 x 0.065 0.01300 cum
0.04043 cum

30 mm thick flush shutter 2 x 0.95 x 2.05 3.895 sqm


Joinery data 2021-22 - Page : 644
MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.02743 cum 92130.00 1 cum 2527.13
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.01300 cum 81950.00 1 cum 1065.35
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 3.895 sqm 1400.00 1 sqm 5453.00
MAT-01208 BMT-L.24 Cost of 1mm thick mat finish laminated sheet 7.79 sqm 400.00 1 sqm 3116.00
Labour charges for fixing laminated sheet 100.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 2 Nos. 108.00 Each 216.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 6 Nos. 133.00 Each 798.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 2 Nos. 58.00 Each 116.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 2 Nos. 11.00 Each 22.00
Labour charges for frame work 0.04043 cum 15363.90 1 cum 621.16
Add for MAA @ 20% 0.20 621.16 124.23
Labour charges for fixing flush door shutter to the frame , fixing the
LAB-00429 BMM-V.23
fixtures to the shutter 3.895 sqm 421.00 1 sqm 1639.80
Add for MAA @ 20% 0.20 1639.80 327.96
Add for nails & screws etc. 0.22
Rate for 4.20 sqm 16926.84
Rate for 1 sqm 4030.20
Overheads&Contractors Profit @13.615% 0.13615 4030.20 548.71
Rate for 1 sqm 4578.91
Say 4579

16 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and ISI marked flush door shutters of
30 mm thick double shutters with bond wood solid block board type Core having cross bands and face veneers, hot pressed bonded with
water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides including cost and conveyance to site of teak wood frame, flush shutter including

supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 6 Nos. butt
hinges (IS:205)150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150 mm
long handles (IS:208), 2 Nos. door stoppers and 2 Nos. Rubber / Nylon door stop bushes including fixing the fixtures to door with required
number of screws, bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame etc, including
overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in
flooring for a depth of not less than 10 mm) (1800mm x 2100mm)

(BLD-CSTN-13-16)
Size : 1.80m x 2.10m 3.78 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743 cum
Outer frame - Horizontal 1 x 1.80
Joinery data 2021-22 - Page : 645
= 1.80 x 0.10 x 0.065 0.01170 cum
0.03913 cum

30 mm thick flush shutter 2 x 0.85 x 2.05 3.485 sqm

MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.0274 cum 92130.00 1 cum 2527.13
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.0117 cum 81950.00 1 cum 958.82
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 3.485 sqm 1400.00 1 sqm 4879.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 2 Nos. 108.00 Each 216.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 6 Nos. 133.00 Each 798.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 2 Nos. 58.00 Each 116.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 2 Nos. 11.00 Each 22.00
Labour charges for frame work 0.03913 cum 15363.90 1 cum 601.19
Add for MAA @ 20% 0.20 601.19 120.24
LAB-00429 BMM-V.23 Labour charges for fixing flush door shutter to the frame , fixing the
fixtures to the shutter 3.49 sqm 421.00 1 sqm 1467.19
Add for MAA @ 20% 0.20 1467.19 293.44
Add for nails & screws etc. 3.44
Rate for 3.78 sqm 12802.43
Rate for 1 sqm 3386.89
Overheads&Contractors Profit @13.615% 0.13615 3386.89 461.12
Rate for 1 sqm 3848.01
Say 3848

17 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and ISI marked flush door shutters of
30 mm thick double shutters with bond wood solid block board type Core having cross bands and face veneers, hot pressed bonded with
water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides, fixing 1mm thick mat finish laminated sheet to full width and height of the flush shutter both sides including cost
and conveyance to site of teak wood frame, flush shutter, laminate sheet including

supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 6 Nos. butt
hinges (IS:205)150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150 mm
long handles (IS:208), 2 Nos. door stoppers and 2 Nos. Rubber / Nylon door stop bushes including fixing the fixtures to door with required
number of screws, bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame etc, including
overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in
flooring for a depth of not less than 10 mm) (1800mm x 2100mm)

(BLD-CSTN-13-16)
Size : 1.80m x 2.10m 3.78 sqm
Joinery data 2021-22 - Page : 646
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743 cum
Outer frame - Horizontal 1 x 1.80
= 1.80 x 0.10 x 0.065 0.01170 cum
0.03913 cum

30 mm thick flush shutter 2 x 0.85 x 2.05 3.485 sqm

MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.0274 cum 92130.00 1 cum 2527.13
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.0117 cum 81950.00 1 cum 958.82
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 3.485 sqm 1400.00 1 sqm 4879.00
MAT-01208 BMT-L.24 Cost of 1mm thick mat finish laminated sheet 6.97 sqm 400.00 1 sqm 2788.00
Labour charges for fixing laminated sheet 100.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 2 Nos. 108.00 Each 216.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 6 Nos. 133.00 Each 798.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 2 Nos. 58.00 Each 116.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 2 Nos. 11.00 Each 22.00
Labour charges for frame work 0.03913 cum 15363.90 1 cum 601.19
Add for MAA @ 20% 0.20 601.19 120.24
Labour charges for fixing flush door shutter to the frame , fixing the
LAB-00429 BMM-V.23
fixtures to the shutter 3.49 sqm 421.00 1 sqm 1467.19
Add for MAA @ 20% 0.20 1467.19 293.44
Add for nails & screws etc. 4.54
Rate for 3.78 sqm 15691.53
Rate for 1 sqm 4151.20
Overheads&Contractors Profit @13.615% 0.13615 4151.20 565.19
Rate for 1 sqm 4716.38
Say 4716

18 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and ISI marked flush door shutters of
30 mm thick double shutters with bond wood solid block board type Core having cross bands and face veneers, hot pressed bonded with
water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides including cost and conveyance to site of teak wood frame, flush shutter including
Joinery data 2021-22 - Page : 647
supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 6 Nos. butt
hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150 mm
long handles (IS:208), 2 Nos. door stoppers and 2 Nos. Rubber / Nylon door stop bushes including fixing the fixtures to door with required
number of screws, bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame etc., including
overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in
flooring for a depth of not less than 10 mm) (1500mm x 2100mm)

(BLD-CSTN-13-16)
Size : 1.50m x 2.10m 3.15 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743 cum
Outer frame - Horizontal 1 x 1.50
= 1.50 x 0.10 x 0.065 0.00975 cum
0.03718 cum

30 mm thick flush shutter 2 x 0.70 x 2.05 2.87 sqm


Joinery data 2021-22 - Page : 648
MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.02743 cum 92130.00 1 cum 2527.13
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.00975 cum 81950.00 1 cum 799.01
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 2.87 sqm 1400.00 1 sqm 4018.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 2 Nos. 108.00 Each 216.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 6 Nos. 133.00 Each 798.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 2 Nos. 58.00 Each 116.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 2 Nos. 11.00 Each 22.00
Labour charges for frame work 0.03718 cum 15363.90 1 cum 571.23
Add for MAA @ 20% 0.20 571.23 114.25
Labour charges for fixing flush door shutter to the frame , fixing the
LAB-00429 BMM-V.23
fixtures to the shutter 2.87 sqm 421.00 1 sqm 1208.27
Add for MAA @ 20% 0.20 1208.27 241.65
Add for nails & screws etc. 2.30
Rate for 3.15 sqm 11433.84
Rate for 1 sqm 3629.79
Overheads&Contractors Profit @13.615% 0.13615 3629.79 494.20
Rate for 1 sqm 4123.99
Say 4124

19 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and ISI marked flush door shutters of
30 mm thick double shutters with bond wood solid block board type Core having cross bands and face veneers, hot pressed bonded with
water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides, fixing 1mm thick mat finish laminated sheet to full width and height of the flush shutter both sides including cost
and conveyance to site of teak wood frame, flush shutter, laminate sheet including

supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 6 Nos. butt
hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150 mm
long handles (IS:208), 2 Nos. door stoppers and 2 Nos. Rubber / Nylon door stop bushes including fixing the fixtures to door with required
number of screws, bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame etc., including
overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in
flooring for a depth of not less than 10 mm) (1500mm x 2100mm)

(BLD-CSTN-13-16)
Size : 1.50m x 2.10m 3.15 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743 cum
Outer frame - Horizontal 1 x 1.50
= 1.50 x 0.10 x 0.065 0.00975 cum
Joinery data 2021-22 - Page : 649
0.03718 cum

30 mm thick flush shutter 2 x 0.70 x 2.05 2.87 sqm

MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.02743 cum 92130.00 1 cum 2527.13
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.00975 cum 81950.00 1 cum 799.01
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 2.87 sqm 1400.00 1 sqm 4018.00
MAT-01208 BMT-L.24 Cost of 1mm thick mat finish laminated sheet 5.74 sqm 400.00 1 sqm 2296.00
Labour charges for fixing laminated sheet 100.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 2 Nos. 108.00 Each 216.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 6 Nos. 133.00 Each 798.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 2 Nos. 58.00 Each 116.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 2 Nos. 11.00 Each 22.00
Labour charges for frame work 0.03718 cum 15363.90 1 cum 571.23
Add for MAA @ 20% 0.20 571.23 114.25
LAB-00429 BMM-V.23 Labour charges for fixing flush door shutter to the frame , fixing the
fixtures to the shutter 2.87 sqm 421.00 1 sqm 1208.27
Add for MAA @ 20% 0.20 1208.27 241.65
Add for nails & screws etc. 3.50
Rate for 3.15 sqm 13831.04
Rate for 1 sqm 4390.81
Overheads&Contractors Profit @13.615% 0.13615 4390.81 597.81
Rate for 1 sqm 4988.61
Say 4989

20 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and ISI marked flush door shutters of
30 mm thick double shutters with bond wood solid block board type Core having cross bands and face veneers, hot pressed bonded with
water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides including cost and conveyance to site of teak wood frame, flush shutter including

supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Alumium fixtures of 6 Nos. butt hinges
(IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150 mm long
handles (IS:208), 2 Nos. door stoppers and 2 Nos. Rubber / Nylon door stop bushes including fixing the fixtures to door with required
number of screws, bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame etc., including
overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in
flooring for a depth of not less than 10 mm) (1200mm x 2100mm)

(BLD-CSTN-13-16)
Size : 1.20m x 2.10m 2.52 sqm
Joinery data 2021-22 - Page : 650
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743 cum
Outer frame - Horizontal 1 x 1.20
= 1.20 x 0.10 x 0.065 0.00780 cum
0.03523 cum

30 mm thick flush shutter 2 x 0.55 x 2.05 2.255 sqm

MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.0274 cum 92130.00 1 cum 2527.13
MAT-00846 BMT - E.01 Cost of medium TW frame below 2 m length 0.0078 cum 81950.00 1 cum 639.21
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 2.255 sqm 1400.00 1 sqm 3157.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 2 Nos. 108.00 Each 216.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 6 Nos. 133.00 Each 798.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 2 Nos. 58.00 Each 116.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 2 Nos. 11.00 Each 22.00
Labour charges for frame work 0.035 cum 15363.90 1 cum 541.27
Add for MAA @ 20% 0.20 541.27 108.25
Labour charges for fixing flush door shutter to the frame , fixing the
LAB-00429 BMM-V.23
fixtures to the shutter 2.255 sqm 421.00 1 sqm 949.36
Add for MAA @ 20% 0.20 949.36 189.87
Add for nails & screws etc. 1.17
Rate for 2.52 sqm 10065.26
Rate for 1 sqm 3994.15
Overheads&Contractors Profit @13.615% 0.13615 3994.15 543.80
Rate for 1 sqm 4537.95
Say 4538
Joinery data 2021-22 - Page : 651
21 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and ISI marked flush door shutters of
30 mm thick double shutters with bond wood solid block board type Core having cross bands and face veneers, hot pressed bonded with
water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides, fixing 1mm thick mat finish laminated sheet to full width and height of the flush shutter both sides including cost
and conveyance to site of teak wood frame, flush shutter, laminate sheet including

supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Alumium fixtures of 6 Nos. butt hinges
(IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150 mm long
handles (IS:208), 2 Nos. door stoppers and 2 Nos. Rubber / Nylon door stop bushes including fixing the fixtures to door with required
number of screws, bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame etc., including
overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in
flooring for a depth of not less than 10 mm) (1200mm x 2100mm)

(BLD-CSTN-13-16)
Size : 1.20m x 2.10m 2.52 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743 cum
Outer frame - Horizontal 1 x 1.20
= 1.20 x 0.10 x 0.065 0.00780 cum
0.03523 cum

30 mm thick flush shutter 2 x 0.55 x 2.05 2.255 sqm

MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.0274 cum 92130.00 1 cum 2527.13
MAT-00846 BMT - E.01 Cost of medium TW frame below 2 m length 0.0078 cum 81950.00 1 cum 639.21
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 2.255 sqm 1400.00 1 sqm 3157.00
MAT-01208 BMT-L.24 Cost of 1mm thick mat finish laminated sheet 4.51 sqm 400.00 1 sqm 1804.00
Labour charges for fixing laminated sheet 100.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 2 Nos. 108.00 Each 216.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 6 Nos. 133.00 Each 798.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 2 Nos. 58.00 Each 116.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 2 Nos. 11.00 Each 22.00
Labour charges for frame work 0.035 cum 15363.90 1 cum 541.27
Add for MAA @ 20% 0.20 541.27 108.25
Labour charges for fixing flush door shutter to the frame , fixing the
LAB-00429 BMM-V.23
fixtures to the shutter 2.255 sqm 421.00 1 sqm 949.36
Add for MAA @ 20% 0.20 949.36 189.87
Add for nails & screws etc. 2.47
Joinery data 2021-22 - Page : 652
Rate for 2.52 sqm 11970.56
Rate for 1 sqm 4750.22
Overheads&Contractors Profit @13.615% 0.13615 4750.22 646.74
Rate for 1 sqm 5396.96
Say 5397

22 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and ISI marked flush door shutters of
30 mm thick single shutter with bond wood solid block board type Core having cross bands and face veneers, hot pressed bonded with
water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides including cost and conveyance to site of teak wood frame, flush shutter including supply and

fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 3 Nos. butt hinges (IS:205)
150mm long, 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204) of 200 mm x 10 mm dia at top , 2 Nos. 150 mm long handles
(IS:208), 1 No. door stopper and 1 No. Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws,
bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame etc., including overheads & contractors
profit complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for a depth of not
less than 10 mm) (1000mm x 2100mm)

(BLD-CSTN-13-16)
Size : 1.00m x 2.10m 2.10 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743 cum
Outer frame - Horizontal 1 x 1.00
= 1.00 x 0.10 x 0.065 0.00650 cum
0.03393 cum

30 mm thick flush shutter 0.90 x 2.05 1.845 sqm

Cost analysis
MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.02743 cum 92130.00 1 cum 2527.13
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.00650 cum 81950.00 1 cum 532.68
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 1.845 sqm 1400.00 1 sqm 2583.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 1 No. 108.00 Each 108.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 3 Nos. 133.00 Each 399.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 1 No. 58.00 Each 58.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 1 No. 11.00 Each 11.00
Labour charges for frame work 0.0339 cum 15363.90 1 cum 521.30
Add for MAA @ 20% 0.20 521.30 104.26
Joinery data 2021-22 - Page : 653
Labour charges for fixing flush door shutter to the frame , fixing the
LAB-00429 BMM-V.23
fixtures to the shutter 1.845 sqm 421.00 1 sqm 776.75
Add for MAA @ 20% 0.20 776.75 155.35
Add for nails & screws etc. 2.09
Rate for 2.10 sqm 8578.54
Overheads&Contractors Profit @13.615% 0.13615 8578.54 1167.97
9746.51
Rate for 1 sqm 4641.20
Say 4641

23 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and ISI marked flush door shutters of
30 mm thick single shutter with bond wood solid block board type Core having cross bands and face veneers, hot pressed bonded with
water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides, fixing 1mm thick mat finish laminated sheet to full width and height of the flush shutter both sides including cost
and conveyance to site of teak wood frame, flush shutter, laminated sheet including supply and

fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 3 Nos. butt hinges (IS:205)
150mm long, 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204) of 200 mm x 10 mm dia at top , 2 Nos. 150 mm long handles
(IS:208), 1 No. door stopper and 1 No. Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws,
bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame etc., including overheads & contractors
profit complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for a depth of not
less than 10 mm) (1000mm x 2100mm)

(BLD-CSTN-13-16)
Size : 1.00m x 2.10m 2.10 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743 cum
Outer frame - Horizontal 1 x 1.00
= 1.00 x 0.10 x 0.065 0.00650 cum
0.03393 cum

30 mm thick flush shutter 0.90 x 2.05 1.845 sqm

Cost analysis
MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.02743 cum 92130.00 1 cum 2527.13
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.00650 cum 81950.00 1 cum 532.68
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 1.845 sqm 1400.00 1 sqm 2583.00
MAT-01208 BMT-L.24 Cost of 1mm thick mat finish laminated sheet 3.69 sqm 400.00 1 sqm 1476.00
Labour charges for fixing laminated sheet 100.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 1 No. 108.00 Each 108.00
Joinery data 2021-22 - Page : 654
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 3 Nos. 133.00 Each 399.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 1 No. 58.00 Each 58.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 1 No. 11.00 Each 11.00
Labour charges for frame work 0.0339 cum 15363.90 1 cum 521.30
Add for MAA @ 20% 0.20 521.30 104.26
LAB-00429 BMM-V.23 Labour charges for fixing flush door shutter to the frame , fixing the
fixtures to the shutter 1.845 sqm 421.00 1 sqm 776.75
Add for MAA @ 20% 0.20 776.75 155.35
Add for nails & screws etc. 1.79
Rate for 2.10 sqm 10154.24
Overheads&Contractors Profit @13.615% 0.13615 10154.24 1382.50
11536.74
Rate for 1 sqm 5493.69
Say 5494

24 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and ISI marked flush door shutters of
30 mm thick single shutter with bond wood solid block board type Core having cross bands and face veneers, hot pressed bonded with
water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides including cost and conveyance to site of teak wood frame, flush shutter including supply and

fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 3 Nos. butt hinges (IS:205)
150mm long, 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150 mm long handles
(IS:208), 1 No. door stopper and 1 No. Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws,
bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame etc, including overheads & contractors
profit complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for a depth of not
less than 10 mm) (900mm x 2100mm)

(BLD-CSTN-13-16)
Size : 0.90m x 2.10m 1.89 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743 cum
Outer frame - Horizontal 1 x 0.90
= 0.90 x 0.10 x 0.065 0.00585 cum
0.03328 cum

30 mm thick flush shutter 0.80 x 2.05 1.64 sqm

Cost analysis
MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.02743 cum 92130.00 1 cum 2527.13
Joinery data 2021-22 - Page : 655
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.00585 cum 81950.00 1 cum 479.41
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 1.64 sqm 1400.00 1 sqm 2296.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 1 No. 108.00 Each 108.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 3 Nos. 133.00 Each 399.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 1 No. 58.00 Each 58.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 1 No. 11.00 Each 11.00
Labour charges for frame work 0.03328 cum 15363.90 1 cum 511.31
Add for MAA @ 20% 0.20 511.31 102.26
Labour charges for fixing flush door shutter to the frame , fixing the
LAB-00429 BMM-V.23
fixtures to the shutter 1.64 sqm 421.00 1 sqm 690.44
Add for MAA @ 20% 0.20 690.44 138.09
Add for nails & screws etc. 0.04
Rate for 1.89 sqm 8120.67
Overheads&Contractors Profit @13.615% 0.13615 8120.67 1105.63
9226.30
Rate for 1 sqm 4881.64
Say 4882

25 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm and ISI marked flush door shutters of
30 mm thick single shutter with bond wood solid block board type Core having cross bands and face veneers, hot pressed bonded with
water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides, fixing 1mm thick mat finish laminated sheet to full width and height of the flush shutter both sides including cost
and conveyance to site of teak wood frame, flush shutter, laminate sheet including supply and

fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked Aluminium fixtures of 3 Nos. butt hinges (IS:205)
150mm long, 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150 mm long handles
(IS:208), 1 No. door stopper and 1 No. Rubber / Nylon door stop bushes including fixing the fixtures to door with required number of screws,
bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame etc, including overheads & contractors
profit complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be embedded in flooring for a depth of not
less than 10 mm) (900mm x 2100mm)

(BLD-CSTN-13-16)
Size : 0.90m x 2.10m 1.89 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743 cum
Outer frame - Horizontal 1 x 0.90
= 0.90 x 0.10 x 0.065 0.00585 cum
0.03328 cum
Joinery data 2021-22 - Page : 656
30 mm thick flush shutter 0.80 x 2.05 1.64 sqm

Cost analysis
MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.02743 cum 92130.00 1 cum 2527.13
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.00585 cum 81950.00 1 cum 479.41
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 1.64 sqm 1400.00 1 sqm 2296.00
MAT-01208 BMT-L.24 Cost of 1mm thick mat finish laminated sheet 3.28 sqm 400.00 1 sqm 1312.00
Labour charges for fixing laminated sheet 100.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00914 BMT-G.09 Cost of Aluminium tower bolt 200mm long 1 No. 108.00 Each 108.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 3 Nos. 133.00 Each 399.00
MAT-00947 BMT-G.42 Cost of Aluminium aldrop 300mm long 1 No. 338.00 Each 338.00
MAT-00939 BMT-G.34 Cost of Aluminium handle 150mm long 2 Nos. 114.00 Each 228.00
MAT-00962 BMT-G.57 Cost of Aluminium door stopper 1 No. 58.00 Each 58.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 1 No. 11.00 Each 11.00
Labour charges for frame work 0.03328 cum 15363.90 1 cum 511.31
Add for MAA @ 20% 0.20 511.31 102.26
LAB-00429 BMM-V.23 Labour charges for fixing flush door shutter to the frame , fixing the
fixtures to the shutter 1.64 sqm 421.00 1 sqm 690.44
Add for MAA @ 20% 0.20 690.44 138.09
Add for nails & screws etc. 1.44
Rate for 1.89 sqm 9534.07
Overheads&Contractors Profit @13.615% 0.13615 9534.07 1298.06
10832.14
Rate for 1 sqm 5731.29
Say 5731

26 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65mm and ISI marked flush door shutter of
30mm thick single shutter with bond wood solid block board type Core having cross bands and face veneers, hot pressed bonded with
water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides including cost and conveyance to site of medium teak wood door frame, flush shutter, including suply and fixing 6 Nos.
MS Z hold fasts of size 300mm x 40mm x 5mm including ISI marked Aluminium fixtures 3 Nos. butt hinges (IS:205) of 150mm long, 1 No.
aldrop (IS:2681) 250 mm long,

1 No. tower bolt (IS:204) of 150 mm x 10mm dia, 2 Nos. 125mm long handles (IS:208),1 No. Rubber / Nylon door stop bushes including PVC
door cladding 1.50mm thick to the flush doors shutters pasted with Fevicol complete as per direction of Engineer –in – charge,
manufacturers specification and drawing to full height of the shutter inside including labour charges for fixing the frame in position, fixing the
shutter to the frame etc., including overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002. (The vertical
frame of door shall be embedded in flooring for deth of not less than 10mm) (800mm x 2100mm)

(BLD-CSTN-13-16)
Quantity analysis Size : 0.80m x 2.10m 1.68 sqm
Joinery data 2021-22 - Page : 657
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743 cum
Outer frame - Horizontal 1 x 0.80
= 0.80 x 0.10 x 0.065 0.00520 cum
0.03263 cum

30 mm thick flush shutter 0.70 x 2.05 1.435 sqm

Cost analysis
MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.02743 cum 92130.00 1 cum 2527.13
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.00520 cum 81950.00 1 cum 426.14
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 1.435 sqm 1400.00 1 sqm 2009.00
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00913 BMT-G.08 Cost of Aluminium tower bolt 150mm long 1 No. 86.50 Each 86.50
MAT-00913 BMT-G.08 Cost of Aluminium butt hinges 150mm long 3 Nos. 133.00 Each 399.00
MAT-00931 BMT-G.26 Cost of Aluminium aldrop 250mm long 1 No. 314.00 Each 314.00
MAT-00946 BMT-G.41 Cost of Aluminium handle 125mm long 1 No. 102.00 Each 102.00
MAT-00938 BMT-G.33 Cost of Rubber / Nylon door stop bushes 1 No. 11.00 Each 11.00
MAT-01640 BMT-W.70 Labour charges for frame work 0.0326 cum 15363.90 1 cum 501.32
Add for MAA @ 20% 0.20 501.32 100.26
Labour charges for fixing flush door shutter to the frame , fixing the
LAB-00429 BMM-V.23
fixtures to the shutter 1.435 sqm 421.00 1 sqm 604.14
Add for MAA @ 20% 0.20 604.14 120.83
MAT-01339 BMT-N-10 PVC cladding to flush shutters 1.50mm thick 1.435 sqm 413.00 1 sqm 592.66
Add for nails & screws etc. 4.87
Rate for 1.68 sqm 8032.84
Overheads&Contractors Profit @13.615% 0.13615 8032.84 1093.67
9126.51
Rate for 1 sqm 5432.45
Say 5432

27 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65mm and ISI marked flush door shutter of
30mm thick single shutter with bond wood solid block board type Core having cross bands and face veneers, hot pressed bonded with
water proof phenol formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides including cost and conveyance to site of medium teak wood door frame, flush shutter, including suply and fixing 6 Nos.
MS Z hold fasts of size 300mm x 40mm x 5mm including ISI marked Aluminium fixtures 3 Nos. butt hinges (IS:205) of 150mm long, 1 No.
aldrop (IS:2681) 250 mm long,
Joinery data 2021-22 - Page : 658
1 No. tower bolt (IS:204) of 150 mm x 10mm dia, 2 Nos. 125mm long handles (IS:208),1 No. Rubber / Nylon door stop bushes including PVC
door cladding 1.50mm thick to the flush doors shutters pasted with Fevicol complete as per direction of Engineer –in – charge,
manufacturers specification and drawing to full height of the shutter inside including labour charges for fixing the frame in position, fixing the
shutter to the frame etc., including overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002. (The vertical
frame of door shall be embedded in flooring for deth of not less than 10mm) (750mm x 2100mm)

(BLD-CSTN-13-16)
Quantity analysis Size : 0.75m x 2.10m 1.575 sqm
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743 cum
Outer frame - Horizontal 1 x 0.75
= 0.75 x 0.10 x 0.065 0.00488 cum
0.03231 cum

30 mm thick flush shutter 0.65 x 2.05 1.333 sqm

Cost analysis
MAT-00847 BMT - E.02 Cost of medium TW frame 2 m to 3m length 0.02743 cum 92130.00 1 cum 2527.13
MAT-00846 BMT - E.01 Cost of medium TW frame up to 2 m length 0.00488 cum 81950.00 1 cum 399.92
MAT-01345 BMT-N-16 Cost of 30 mm thick flush shutter 1.333 sqm 1400.00 1 sqm 1866.20
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 6 Nos. 39.00 Each 234.00
MAT-00913 BMT-G.08 Cost of Aluminium tower bolt 150mm long 1 No. 86.50 Each 86.50
MAT-00913 BMT-G.08 Cost of Aluminium butt hinges 150mm long 3 Nos. 133.00 Each 399.00
MAT-00931 BMT-G.26 Cost of Aluminium aldrop 250mm long 1 No. 314.00 Each 314.00
MAT-00946 BMT-G.41 Cost of Aluminium handle 125mm long 1 No. 102.00 Each 102.00
MAT-00938 BMT-G.33 Cost of Rubber / Nylon door stop bushes 1 No. 11.00 Each 11.00
MAT-01640 BMT-W.70 Labour charges for frame work 0.03231 cum 15363.90 1 cum 496.41
Add for MAA @ 20% 0.20 496.41 99.28
Labour charges for fixing flush door shutter to the frame , fixing the
LAB-00429 BMM-V.23
fixtures to the shutter 1.333 sqm 421.00 1 sqm 561.19
Add for MAA @ 20% 0.20 561.19 112.24
MAT-01339 BMT-N-10 PVC cladding to flush shutters 1.50mm thick 1.333 sqm 413.00 1 sqm 550.53
Add for nails & screws etc. 0.81
Rate for 1.575 sqm 7760.20
Overheads&Contractors Profit @13.615% 0.13615 7760.20 1056.55
8816.75
Rate for 1 sqm 5597.94
Say 5598
Joinery data 2021-22 - Page : 659
28 Supplying and fixing single side prelam solid panel PVC door frame (Choukhat): Providing and fixing factory made Pac single side
Prelam door frame of the size 50x47 mm with a wall thickness of 5mm, made out of extruded 5mm rigid Pac single side prelam sheet, meter
cut at two corners and joined with 2 Nos. of 150mm long brackets of 15 x 15mm MS Square tube. The two vertical door profiles are to be
reinforced with 19 x 19mm MS. square tube of 19 guage. The door frame shall be fixed to the wall using 65/100mm long MS. Screws through
the frame by using Pac fasteners. a minimum of 4 Nos. of screws to be provided for each vertical member and minimum 2nos. for horizontal
member etc. complete as per manufacture specification and direction of Engineer-incharge including conveyance of all materials, labour
charges for fixing, overheads & contractors profit complete for finished item of work.

MAT-01334 BMT-N-05 Rate as per SoR 1.00 RM 400.00 1 RM 400.00


Overheads&Contractors Profit @13.615% 0.13615 400.00 54.46
Rate per 1 RM 454.46
Say 454
Joinery data 2021-22 - Page : 660
29 Providing and fixing 30mm thick Brand factory made moulded PVC door shutter- wood free consisting of frame made out of MS. tubes
19 gauge thickness and size of 25mmX25mm for styles, top and bottom rails. MS. Frame shall hav e a coat of steel primers. The inner panel
shall consist of 25mm thick high density EPS conforming to IS 4671-1984 bounded with 2mm thick termite proof, water proof and fire
resistant moulded Pac sheet with 2,4,6 raised panel design in different plain and / or pre-lam colours after routing to the moulded design on
one side and 2mm plain and / or pre-lam Pac sheet on other side of the EPS. The edge of panel to be sealed with lipping of 10mm wide PVC
sheet bottom (made by sticking 2 rigid foam sheet of 5mm thickness using Pac solvent cement) and stiles sides 25mm(5mmX5) thick and
30mm width Pac sheet fitted along MS tube for lock provision for lock height 5mm thick Pac sheet of size 150mmX100mm fixed with upper
and lower face of inner side of EPS panel etc., complete as per direction of Engineer – in-Charge, manufacture specification and drawing
including supplying and fixing ISI marked Aluminium fixtures 3 Nos. butt hinges (IS:205) of 150mm long, 1 No. aldrop (IS:2681) 250 mm long,
1 No. tower bolt (IS:204) of 150 mm x 10mm dia, 2 Nos. 125mm long handles (IS:208),1 No. Rubber / Nylon door stop bushes including
labour charges for fixing the shutter to frame etc., including overheads & contractors profit complete for finished item of work for door of size
800mm x 2100mm

MAT-01336 BMT-N-07 Rate as per SoR 1.435 Sqm 2600.00 1 Sqm 3731.00
MAT-00913 BMT-G.08 Cost of Aluminium tower bolt 150mm long 1 No. 86.50 Each 86.50
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 3 Nos. 133.00 Each 399.00
MAT-00946 BMT-G.41 Cost of Aluminium aldrop 250mm long 1 No. 314.00 Each 314.00
MAT-00938 BMT-G.33 Cost of Aluminium handle 125mm long 1 No. 102.00 Each 102.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 1 No. 11.00 Each 11.00
Add for nails & screws etc. 3.72
Rate for 1.435 sqm 4647.22
Overheads&Contractors Profit @13.615% 0.13615 4647.22 632.72
5279.94
Rate for 1 sqm 3679.40
Say 3679
Joinery data 2021-22 - Page : 661
30 Providing and fixing 30mm thick factory made moulded door shutter- wood free consisting of frame made out of MS. tubes 19gauge
thickness and size of 25mmX25mm for styles, top and bottom rails. MS. Frame shall have a coat of steel primers. The inner panel shall
consist of 25mm thick high density EPS conforming to IS 4671-1984 bounded with 2mm thick termite proof, water proof and fire resistant
moulded Pac sheet with 2,4,6 raised panel design in different plain and / or pre-lam colours after routing to the moulded design on one side
and 2mm plain and / or pre-lam Pac sheet on other side of the EPS. The edge of panel to be sealed with lipping of 10mm wide PVC sheet
bottom (made by sticking 2 rigid foam sheet of 5mm thickness using Pac solvent cement) and stiles sides 25mm(5mmX5) thick and 30mm
width Pac sheet fitted along MS tube for lock provision for lock height 5mm thick Pac sheet of size 150mmX100mm fixed with upper and
lower face of inner side of EPS panel etc., complete as per direction of Engineer – in-Charge, manufacture specification and drawing
including ISI marked Aluminium fixtures 3 Nos. butt hinges (IS:205) of 150mm long, 1 No. aldrop (IS:2681) 250 mm long, 1 No. tower bolt
(IS:204) of 150 mm x 10mm dia, 2 Nos. 125mm long handles (IS:208),1 No. Rubber / Nylon door stop bushes including labour charges for
fixing the shutter to frame etc., including overheads & contractors profit complete for finished item of work for door of size 750mm x
2100mm

Quantity analysis
MAT-01336 BMT-N-07 Rate as per SoR 1.333 Sqm 2600.00 1 Sqm 3465.80
MAT-00913 BMT-G.08 Cost of Aluminium tower bolt 150mm long 1 No. 86.50 Each 86.50
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 3 Nos. 133.00 Each 399.00
MAT-00946 BMT-G.41 Cost of Aluminium aldrop 250mm long 1 No. 314.00 Each 314.00
MAT-00938 BMT-G.33 Cost of Aluminium handle 125mm long 1 No. 102.00 Each 102.00
MAT-01640 BMT-W.70 Cost of Rubber / Nylon door stop bushes 1 No. 11.00 Each 11.00
Add for nails & screws etc. 3.58
Rate for 1.333 sqm 4381.88
Overheads&Contractors Profit @13.615% 0.13615 4381.88 596.59
4978.47
Rate for 1 sqm 3734.79
Say 3735
Joinery data 2021-22 - Page : 662
31 Supply and fixing powder coated aluminium fully glazed swing door as per the approved drawing with fixed fan light of 500mm height
at top door using aluminium sections of 101.60 mmm x 44.45mm , 3.18 mm thick for frame and door shutter made of styles , top and middle
rail of 47.62mm x 44.45mm , 3.18 mm thick and bottom rail of 114.30mm x 44.45 mm , 3.18mm thick,powder coating of alluminium sections
25mm microns thick, 5 mm thick plain float glass fitted with suitable aluminium glazing clips and rubber beading in fan light portion, double
shutters fitted with 5mm thick frosted / ground glass in the top half and MDF Board: interior-Both Side Laminated -12 mm thick in
the bottom half fitted with suitable aluminium glazing clips and rubber beading,shutters mounted on double action hydraulic floor spring of
approved brand manufacture IS : 6315 marked , Hardwyn make M-3000 for doors including cost of cutting floors as required , embedding in
floors

and SS cover plates with brass pivot and sigle piece MS Sheet outer box with slide plate etc.complete (Weight Capacity up to 130 Kgs)
as approved by Engineer-in-Charge including supply and fixing ISI marked powder coated aluminium fixtures of 3 Nos. of butt hinges
(IS:205) of 150mm long(for each shutter), 4 Nos.tower bolts 10mm bolt (IS:204) 300mm long , 4 Nos.alluminium handles (IS:208) 150mm dia
and 2 Nos. aldrops (IS:2681) 300mm long including labour charges for manufacturing door , fixing the door with required No. of screws etc.,
including overheads & contractors profit complete for finished item of work. (The Aluminium section used shall be standard make confirming
to IS 1948 – 1961) and as approved by the Engineer) (2000mm x 2600mm)

(BLD-CSTN-13-31)
Quantity analysis Size : 2.00m x 2.60m 5.20 sqm
Outer frame (101.60 x 44.45, 3.18mm thick) 2 x 2.00 + 2 x 2.60 9.20 RM
Mullions (101.60 x 44.45, 3.18mm thick) 1 x 0.50 0.50 RM
9.70 RM
= 9.70 RM @ 2.404 Kgs / RM 23.319 Kgs.
Shutters, styles and rails(47.62mm x 44.45mm , 3.18 mm thick) 4 x 2.10 + 2 x 2 x 1.00 12.40 RM
= 12.40 RM @1.501 Kgs/ RM 18.612 Kgs.
Bottom rails (114.30 x 44.45. 3.18mm thick) 2 x 1.00 2.00 RM
= 2.00 RM @ 2.646 Kgs / RM 5.292 Kgs.
2 x 2 x 2(1.00+0.50) +
2 x 2 x 2(1.00+1.20) +
Glazing clips 2 x 2 x 2(1.00+0.90) 44.80 RM
= 44.80 RM @ 0.101 Kgs /RM 4.525 Kgs.
51.748 Kgs.
5mm thick plain glass 2 x 1.00 x 0.50 1.00 sqm.
5mm thick ground glass 2 x 1.00 x 1.20 2.40 sqm.
MDF Board: interior-Both Side Laminated - 12 mm thick
2 x 1.00 x 0.90 1.80 sqm.
Rubber beading 2 x 2(1.00+0.50)+2 x 2(1.00+1.20) 14.80 RM
Cost analysis
A.Material :
MAT-01575 BMS-W-01 Cost of powder coated Al. sections 51.748 Kgs. 337.00 1 Kg. 17439.08
MAT-01053 BMT-I.02 Cost of 5mm thick plain glass 1.00 sqm 634.00 1 sqm 634.00
MAT-01067 BMT-I.16 5mm thick ground glass 2.40 sqm 750.00 1 sqm 1800.00
Joinery data 2021-22 - Page : 663
MAT-01166 BMT-K.58 MDF Board: interior-Both Side Laminated - 12 mm thick 1.80 sqm 700.00 1 sqm 1260.00
MAT-01580 BMS-W-06 Cost of rubber beading 14.80 RM 2.00 1 RM 29.60
MAT-00982 BMT-G.77 Cost of floor springs 2 Nos. 3900.00 Each 7800.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 6 Nos. 133.00 Each 798.00
MAT-00916 BMT-G.11 Cost of Al. tower bolts 300mm 4 Nos. 152.00 Each 608.00
MAT-00939 BMT-G.34 Cost of Al. round handles 150mm dia. 4 Nos. 114.00 Each 456.00
MAT-00947 BMT-G.42 Cost of Al. aldrops 300mm 2 Nos. 338.00 Each 676.00
B.Labour charges 5.20 sqm 863.17 1 sqm 4488.48
Add for Screws, Nails, Nuts, Bolts etc., LS 0.30
Rate per 5.20 sqm 35989.46
Overheads&Contractors Profit @13.615% 0.13615 35989.46 4899.96
40889.42
Rate per 1 sqm 7863.35
Say 7863

32 Supply and fixing powder coated aluminium fully glazed swing door as per the approved drawing with fixed fan light of 500mm height
at top door using aluminium sections of 101.60 mmm x 44.45mm , 3.18 mm thick for frame and door shutter made of styles , top and middle
rail of 47.62mm x 44.45mm , 3.18 mm thick and bottom rail of 114.30mm x 44.45 mm , 3.18mm thick,powder coating of alluminium sections
25mm microns thick, 5 mm thick plain float glass fitted with suitable aluminium glazing clips and rubber beading in fan light portion, double
shutters fitted with 5mm thick frosted / ground glass in the top half and MDF Board: interior-Both Side Laminated -12 mm thick in
the bottom half fitted with suitable aluminium glazing clips and rubber beading,shutters mounted on double action hydraulic floor spring of
approved brand manufacture IS : 6315 marked , Hardwyn make M-3000 for doors including cost of cutting floors as required , embedding in
floors

and SS cover plates with brass pivot and sigle piece MS Sheet outer box with slide plate etc.complete( Weight Capacity up to 130 Kgs ) as
approved by Engineer-in-Charge including supply and fixing ISI marked powder coated aluminium fixtures of 3 Nos. of butt hinges (IS:205)
of 150mm long(for each shutter), 4 Nos.tower bolts 10mm bolt (IS:204) 300mm long , 4 Nos.alluminium handles (IS:208) 150mm dia and 2
Nos. aldrops (IS:2681) 300mm long including labour charges for manufacturing door , fixing the door with required No. of screws etc.,
including overheads & contractors profit complete for finished item of work. (The Aluminium section used shall be standard make confirming
to IS 1948 – 1961) and as approved by the Engineer) (1800mm x 2600mm)

(BLD-CSTN-13-31)
Quantity analysis Size : 1.80m x 2.60m 4.68 sqm
Outer frame (101.60 x 44.45, 3.18mm thick) 2 x 1.80 + 2 x 2.60 8.80 RM

Mullions (101.60 x 44.45, 3.18mm thick) 1 x 0.50 0.50 RM


9.30 RM
= 9.30 RM @ 2.404 Kgs / RM 22.357 Kgs.
Shutters, styles and rails(47.62mm x 44.45mm , 3.18 mm thick) 4 x 2.10 + 2 x 2 x 0.90 12.00 RM
= 12.00 RM @1.501 Kgs/ RM 18.012 Kgs.
Bottom rails (114.30 x 44.45. 3.18mm thick) 2 x 0.90 1.80 RM
= 1.80 RM @ 2.646 Kgs / RM 4.763 Kgs.
Joinery data 2021-22 - Page : 664
2 x 2 x 2(0.90+0.50) +
2 x 2 x 2(0.90+1.20) +
Glazing clips 2 x 2 x 2(0.90+0.90) 42.40 RM
= 42.40 RM @ 0.101 Kgs /RM 4.282 Kgs.
49.414 Kgs.
5mm thick plain glass 2 x 0.90 x 0.50 0.90 sqm.
5mm thick ground glass 2 x 0.90 x 1.20 2.16 sqm.
MDF Board: interior-Both Side Laminated - 12 mm thick
2 x 0.90 x 0.90 1.62 sqm.
Rubber beading 2 x 2(0.90+0.50)+2 x 2(0.90+1.20) 14.00 RM
Cost analysis
A.Material :
MAT-01575 BMS-W-01 Cost of powder coated Al. sections 49.414 Kgs. 337.00 1 Kgs. 16652.52
MAT-01053 BMT-I.02 Cost of 5mm thick plain glass 0.90 sqm 634.00 1 sqm 570.60
MAT-01067 BMT-I.16 5mm thick ground glass 2.16 sqm 750.00 1 sqm 1620.00
MDF Board: interior-Both Side Laminated - 12 mm thick
MAT-01166 BMT-K.58
1.62 sqm 700.00 1 sqm 1134.00
MAT-01580 BMS-W-06 Cost of rubber beading 14.00 RM 2.00 1 RM 28.00
MAT-00982 BMT-G.77 Cost of floor springs 2 Nos. 3900.00 Each 7800.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 6 Nos. 133.00 Each 798.00
MAT-00916 BMT-G.11 Cost of Al. tower bolts 300mm 4 Nos. 152.00 Each 608.00
MAT-00939 BMT-G.34 Cost of Al. round handles 150mm dia. 4 Nos. 114.00 Each 456.00
MAT-00947 BMT-G.42 Cost of Al. aldrops 300mm 2 Nos. 338.00 Each 676.00
B.Labour charges 4.68 sqm 863.17 1 sqm 4039.63
Add for Screws, Nails, Nuts, Bolts etc., LS 1.83
Rate per 4.68 sqm 34384.58
Overheads&Contractors Profit @13.615% 0.13615 34384.58 4681.46
39066.04
Rate per 1 sqm 8347.44
Say 8347
Joinery data 2021-22 - Page : 665
33 Supply and fixing powder coated aluminium fully glazed swing door as per the approved drawing with fixed fan light of 500mm height
at top door using aluminium sections of 101.60 mmm x 44.45mm , 3.18 mm thick for frame and door shutter made of styles , top and middle
rail of 47.62mm x 44.45mm , 3.18 mm thick and bottom rail of 114.30mm x 44.45 mm , 3.18mm thick,powder coating of alluminium sections
25mm microns thick, 5 mm thick plain float glass fitted with suitable aluminium glazing clips and rubber beading in fan light portion, double
shutters fitted with 5mm thick frosted / ground glass in the top half and MDF Board: interior-Both Side Laminated -12 mm thick in
the bottom half fitted with suitable aluminium glazing clips and rubber beading,shutters mounted on double action hydraulic floor spring of
approved brand manufacture IS : 6315 marked , Hardwyn make M-3000 for doors including cost of cutting floors as required , embedding in
floors

and SS cover plates with brass pivot and sigle piece MS Sheet outer box with slide plate etc.complete( Weight Capacity up to 130 Kgs ) as
approved by Engineer-in-Charge including supply and fixing ISI marked powder coated aluminium fixtures of 3 Nos. of butt hinges (IS:205)
of 150mm long(for each shutter), 4 Nos.tower bolts 10mm bolt (IS:204) 300mm long , 4 Nos.alluminium handles (IS:208) 150mm dia and 2
Nos. aldrops (IS:2681) 300mm long including labour charges for manufacturing door , fixing the door with required No. of screws etc.,
including overheads & contractors profit complete for finished item of work. (The Aluminium section used shall be standard make confirming
to IS 1948 – 1961) and as approved by the Engineer) (1500mm x 2600mm)

(BLD-CSTN-13-31)
Quantity analysis Size : 1.50m x 2.60m 3.90 sqm
Outer frame (101.60 x 44.45, 3.18mm thick) 2 x 1.50 + 2 x 2.60 8.20 RM
Mullions (101.60 x 44.45, 3.18mm thick) 1 x 0.50 0.50 RM
8.70 RM
= 8.70 RM @ 2.404 Kgs / RM 20.915 Kgs.
Shutters, styles and rails(47.62mm x 44.45mm , 3.18 mm thick) 4 x 2.10 + 2 x 2 x 0.75 11.40 RM
= 11.40 RM @1.501 Kgs/ RM 17.111 Kgs.
Bottom rails (114.30 x 44.45. 3.18mm thick) 2 x 0.75 1.50 RM
= 1.50 RM @ 2.646 Kgs / RM 3.969 Kgs.
2 x 2 x 2(0.75+0.50) +
2 x 2 x 2(0.75+1.20) +
Glazing clips 2 x 2 x 2(0.75+0.90) 38.80 RM
= 38.80 RM @ 0.101 Kgs /RM 3.919 Kgs.
45.914 Kgs.
5mm thick plain glass 2 x 0.75 x 0.50 0.75 sqm.
5mm thick ground glass 2 x 0.75 x 1.20 1.80 sqm.
MDF Board: interior-Both Side Laminated - 12 mm thick
2 x 0.75 x 0.90 1.35 sqm.
Rubber beading 2 x 2(0.75+0.50)+2 x 2(0.75+1.20) 12.80 RM
Cost analysis
A.Material :
MAT-01575 BMS-W-01 Cost of powder coated Al. sections 45.91 Kgs. 337.00 1 Kgs. 15473.02
MAT-01053 BMT-I.02 Cost of 5mm thick plain glass 0.75 sqm 634.00 1 sqm 475.50
MAT-01067 BMT-I.16 5mm thick ground glass 1.80 sqm 750.00 1 sqm 1350.00
Joinery data 2021-22 - Page : 666
MAT-01166 BMT-K.58 MDF Board: interior-Both Side Laminated - 12 mm thick 1.35 sqm 700.00 1 sqm 945.00
MAT-01580 BMS-W-06 Cost of rubber beading 12.80 RM 2.00 1 RM 25.60
MAT-00982 BMT-G.77 Cost of floor springs 2 Nos. 3900.00 Each 7800.00
MAT-00931 BMT-G.26 Cost of Aluminium butt hinges 150mm long 6 Nos. 133.00 Each 798.00
MAT-00916 BMT-G.11 Cost of Al. tower bolts 300mm 4 Nos. 152.00 Each 608.00
MAT-00939 BMT-G.34 Cost of Al. round handles 150mm dia. 4 Nos. 114.00 Each 456.00
MAT-00947 BMT-G.42 Cost of Al. aldrops 300mm 2 Nos. 338.00 Each 676.00
B.Labour charges 3.90 sqm 863.17 1 sqm 3366.36
Add for Screws, Nails, Nuts, Bolts etc., LS 1.31
Rate per 3.90 sqm 31974.79
Overheads&Contractors Profit @13.615% 0.13615 31974.79 4353.37
36328.16
Rate per 1 sqm 9314.91
Say 9315

34 Providing & Fixing of Scientific Doors with metal door frames and door shutters made of galvanize steel (base steel as per IS 513 of
0.58 mm thick D quality, galvanized as per IS 277 with Zinc of 120 GSM)coated with Zinc Phosphate Primer to receive any paint on site or
finished with Thermosetting Polyurethane paint of Aliphatic Grade providing high levels of scratch resistance and durability/Epoxy polyester
powder for powder coating paint thickness 50-60 microns (Dry film thickness) outer frame section of 100 x 58 mm x 1.2 mm thick, shutter
section of 0.80 mm thick galvanized steel sheet pressed (roll formed) for 46mm thick fully flush, double skin door shell seam joints at stile
edges, in-fill of honeycomb Kraft paper used to give the required rigidity and effective acoustic insulation with 6” Tower bolt – 1 No., 6” D
handles – 2 Nos., 10” Aldrops – 1 No., Butt Hinges – 3 Nos, Mortise Lock of approved quality – 1 No, frames fixed to the concrete/masonry
wall by means of self expanding screws including overheads and contractor profit etc.,complete for finished item of work for Single leaf Door

MAT-01374 BMT-N.45 Rate as per SoR 1.00 sqm 10519.00 1 sqm 10519.00
Overheads&Contractors Profit @13.615% 0.14 10519.00 1432.16
Rate per 1 sqm 11951.16
Say 11951

35 Providing & Fixing of Scientific Doors with metal door frames and door shutters made of galvanize steel (base steel as per IS 513 of
0.58 mm thick D quality, galvanized as per IS 277 with Zinc of 120 GSM). coated with Zinc Phosphate Primer to receive any paint on site or
finished with Thermosetting Polyurethane paint of Aliphatic Grade providing high levels of scratch resistance and durability/Epoxy polyester
powder for powder coating paint thickness 50-60 microns (Dry film thickness) outer frame section of 100 x 58 mm x 1.2 mm thick, shutter
section of 0.80 mm thick galvanized steel sheet pressed (roll formed) for 46mm thick fully flush, double skin door shell seam joints at stile
edges, in-fill of honeycomb Kraft paper used to give the required rigidity and effective acoustic insulation with 6” Tower bolt – 2 Nos., 6” D
handles – 2 Nos., 10” Aldrops – 1 No., Butt Hinges – 6 Nos, Mortise Lock of approved quality – 1 No, frames fixed to the concrete/masonry
wall by means of self expanding screws including overheads and contractor profit etc., complete for finished item of work for Double leaf
Door

MAT-01375 BMT-N.46 Rate as per SoR 1.00 sqm 10989.00 1 sqm 10989.00
Joinery data 2021-22 - Page : 667
Overheads&Contractors Profit @13.615% 0.13615 10989.00 1496.15
Rate per 1 sqm 12485.15
Say 12485

36 Supply & Fixing of Lead Lined Stainless steel Clean room door frames and shutters made of Stainless steel grade of 304 hairline
finish, frame with 1.60mm (16SWG) thick hairline finish Stainless steel grade of 304 formed to Single/double rebate profile of size 100 mm x
58mm/ 143 x 58 mm, door frames with a single / multi Layer of Lead sheet varying thickness from 3mm /1mm to 2mm depends on radiation
level, the shutter with 1.2 mm thick hairline finish Stainless steel grade of 304 formed to provide a 46mm thick fully flush, double skin door
shell with Lock Seam joints at stile edges with a single / multi Layer of Lead sheet varying thickness from 3mm /1mm to 2mm depends on
radiation level. The lead sheets extend the full width and height of the door. Lead thickness is to be equal to the shielding in the adjacent wall.
Hardware can be provided with Stainless Steel Ball Bearing Butt Hinges 3 mm thick fixed flush to the frame and shutter etc., including
overheads and contractor profit etc., complete for finished item of work in all floors

MAT-01391 BMT-N.62 Rate as per SoR 1.00 sqm 24087.00 1 sqm 24087.00
Overheads&Contractors Profit @13.615% 0.13615 24087.00 3279.45
Rate per 1 sqm 27366.45
Say 27366

37 Providing & Fixing of Openable Windows with Fly-mesh made of pre-painted steel (Base Steel as per IS 513 of 0.58 mm thick
galvanized as per IS 277 with zinc of 150 GSM) primer coated with epoxy primer of 5-7 microns thick, finish painted with a polyester paint of
12-16 microns thick and back coated with 5-7 microns thick alkyd backer and the section for outer frame of 72 x 55mm, centre mullion of 72 x
50mm, section for fixed glass beading section of 12 x 12 mm and section for shutters of 48 x 25 mm and outer frame & mullion sections with
rebate for glazed shutters, fly mesh and a 20 mm provision for guard bars/grills and fly mesh shutter section of 20 x 40 mm and the sections
cut to length metre joined with corner bracket, centre mullions fixed with mullion cap, stay, handles, latch 2 Nos of heavy duty stainless steel
pivot hinges per shutter and panelled with 5mm thick plain float glass and S.S. Mesh for fly mesh shutter (304 grade), fitted using rubber
gaskets including fixing the windows in the concrete/masonry wall by means of self expanding screws, including 10mm Square guard bars
with 6” (152.4mm) pitch including cost cost and conveyance of all materials, labour charges for fixing, overheads and contractors profit etc.,
complete for finished item of work in all floors.

a Centre fixed both side openable shutter window : 1800mm x1800mm 3.24 sqm
MAT-01433 BMT - P.25 Window portion 2.34 sqm 5897.00 1 sqm 13798.98
Fan light portion
MAT-01492 BMT - Q.05&06
0.90 sqm 4596.00 1 sqm 4136.40
Rate per 3.24 sqm 17935.38
Rate per 1 sqm 5535.61
MAT-01053 BMT-I.02 deduct cost of 5mm plain glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
5271.61
Overheads&Contractors Profit @13.615% 0.13615 5271.61 717.73
Rate per 1 sqm 5989.34
Joinery data 2021-22 - Page : 668
Say 5989
Joinery data 2021-22 - Page : 669
b Centre fixed both side openable shutter window : 1500mm x1800mm 2.70 sqm
MAT-01432 BMT - P.24 Window portion 1.95 sqm 6625.00 1 sqm 12918.75
Fan light portion
MAT-01492 BMT - Q.05&06
0.75 sqm 4596.00 1 sqm 3447.00
Rate per 2.70 sqm 16365.75
Rate per 1 sqm 6061.39
MAT-01053 BMT-I.02 deduct cost of 5mm plain glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
5797.39
Overheads&Contractors Profit @13.615% 0.13615 5797.39 789.31
Rate per 1 sqm 6586.70
Say 6587

c Double shutter window 1200x1800 with fixed fan light of 500mm at top : 2.16 sqm
MAT-01430,
MAT- BMT - P.22,23
Window portion 1.56 sqm 7288.00 1 sqm 11369.28
01431
Fan light portion
MAT-01492 BMT - Q.05&06
0.60 sqm 4596.00 1 sqm 2757.60
Rate per 2.16 sqm 14126.88
Rate per 1 sqm 6540.22
MAT-01053 BMT-I.02 deduct cost of 5mm plain glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
6276.22
Overheads&Contractors Profit @13.615% 0.13615 6276.22 854.51
Rate per 1 sqm 7130.73
Say 7131

d Double shutter window 900x1800 with fixed fan light of 500mm at top : 1.62 sqm
MAT-01430,
MAT- BMT - P.22,23
Window portion 1.17 sqm 7288.00 1 sqm 8526.96
01431
Fan light portion
MAT-01492 BMT - Q.05&06
0.45 sqm 4596.00 1 sqm 2068.20
Rate per 1.62 sqm 10595.16
Rate per 1 sqm 6540.22
MAT-01053 BMT-I.02 deduct cost of 5mm plain glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
6276.22
Overheads&Contractors Profit @13.615% 0.13615 6276.22 854.51
Rate per 1 sqm 7130.73
Say 7131
Joinery data 2021-22 - Page : 670
e Centre fixed both side openable shutter window 1800mmx1300mm : 2.34 sqm
MAT-01433 BMT - P.25 Window portion 2.34 sqm 5897.00 1 sqm 13798.98
Rate per 1 sqm 5897.00
MAT-01053 BMT-I.02 deduct cost of 5mm plain glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
5633.00
Overheads&Contractors Profit @13.615% 0.13615 5633.00 766.93
Rate per 1 sqm 6399.93
Say 6400

f Centre fixed both side openable shutter window 1500mmx1300mm : 1.95 sqm
MAT-01432 BMT - P.24 Window portion 1.95 sqm 6625.00 1 sqm 12918.75
Rate per 1 sqm 6625.00
MAT-01053 BMT-I.02 deduct cost of 5mm plain glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
6361.00
Overheads&Contractors Profit @13.615% 0.13615 6361.00 866.05
Rate per 1 sqm 7227.05
Say 7227

g Double shutter window 1200mmx1300mm : 1.56 sqm


MAT-01430,
MAT- BMT - P.22,23
Window portion 1.56 sqm 7288.00 1 sqm 11369.28
01431
Rate per 1 sqm 7288.00
MAT-01053 BMT-I.02 deduct cost of 5mm plain glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
7024.00
Overheads&Contractors Profit @13.615% 0.13615 7024.00 956.32
Rate per 1 sqm 7980.32
Say 7980

h Double shutter window 900mmx1300mm: 1.17 sqm


MAT-01430,
MAT- BMT - P.22,23
Window portion 1.17 sqm 7288.00 1 sqm 8526.96
01431
Rate per 1 sqm 7288.00
MAT-01053 BMT-I.02 deduct cost of 5mm plain glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
7024.00
Overheads&Contractors Profit @13.615% 0.13615 7024.00 956.32
Rate per 1 sqm 7980.32
Say 7980
Joinery data 2021-22 - Page : 671

38 Supply and fixing of pre-painted steel openable windows base steel as per IS 513 of -0.58 mm thick 'D" quality, galvanized as per IS
277 , finish painted with a polyester paint of 12-16 microns thick and back coated with 5-7 microns thick alkyd backer, section for outer frame
of 46 x 52 mm section and for shutter of 46 x 46 mm section for mullion 46 x 70 mm, and section for beading should be 18 x 25 mm with 5
mm thick plain float glass fitted with Ethyl propylene Diamine monomer Gasket (EPDM) and handle made of high grade aluminium powder
coated with frames fixed to the concrete /masonry wall by means of self expanding screws including 10 mm square guard bars with 6" pitch
C2101

A) WINDOWS
a Centre fixed both side openable shutter window 1800mm x 1800mm with fixed fan light of 500mm at top :
3.24 sqm
MAT-01415 ,
BMT - P.07,08
MAT-01416 Window portion 2.34 sqm 5411.00 1 sqm 12661.74
Fan light portion
MAT-01492 BMT - Q.05&06
0.90 sqm 4596.00 1 sqm 4136.40
Rate per 3.24 sqm 16798.14
Rate per 1 sqm 5184.61
MAT-01053 BMT-I.02 deduct cost of 5mm plain glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
4920.61
Overheads&Contractors Profit @13.615% 0.13615 4920.61 669.94
Rate per 1 sqm 5590.55
Say 5591

b Centre fixed both side openable shutter window 1500x1800 with fixed fan light of 500mm at top : 2.70 sqm
MAT-01415 ,
BMT - P.07,08
MAT-01416 Window portion 1.95 sqm 5411.00 1 sqm 10551.45
Fan light portion
MAT-01492 BMT - Q.05&06
0.75 sqm 4596.00 1 sqm 3447.00
Rate per 2.70 sqm 13998.45
Rate per 1 sqm 5184.61
MAT-01053 BMT-I.02 deduct cost of 5mm plain glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
4920.61
Overheads&Contractors Profit @13.615% 0.13615 4920.61 669.94
Rate per 1 sqm 5590.55
Say 5591
Joinery data 2021-22 - Page : 672
c Double shutter window 1200x1800 with fixed fan light of 500mm at top : 2.16 sqm
MAT-01412 BMT - P.04 Window portion 1.56 sqm 6379.00 1 sqm 9951.24
Fan light portion
MAT-01492 BMT - Q.05&06
0.60 sqm 4596.00 1 sqm 2757.60
Rate per 2.16 sqm 12708.84
Rate per 1 sqm 5883.72
MAT-01053 BMT-I.02 deduct cost of 5mm plain glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
5619.72
Overheads&Contractors Profit @13.615% 0.13615 5619.72 765.13
Rate per 1 sqm 6384.85
Say 6385

d Double shutter window 900x1800 with fixed fan light of 500mm at top : 1.62 sqm
MAT-01412 BMT - P.04 Window portion 1.17 sqm 6379.00 1 sqm 7463.43
Fan light portion
MAT-01492 BMT - Q.05&06
0.45 sqm 4596.00 1 sqm 2068.20
Rate per 1.62 sqm 9531.63
Rate per 1 sqm 5883.72
MAT-01053 BMT-I.02 deduct cost of 5mm plain glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
5619.72
Overheads&Contractors Profit @13.615% 0.13615 5619.72 765.13
Rate per 1 sqm 6384.85
Say 6385

e Centre fixed both side openable shutter window 1800mmx1300mm :


MAT-01415 ,
BMT - P.07,08 Rate as per SoR 1.00 sqm 5411.00 1 sqm 5411.00
MAT-01416
MAT-01053 BMT-I.02 deduct cost of 5mm plain glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
5147.00
Overheads&Contractors Profit @13.615% 0.13615 5147.00 700.76
Rate per 1 sqm 5847.76
Say 5848

f Centre fixed both side openable shutter window 1500mmx1300mm :


MAT-01415 ,
BMT - P.07,08
MAT-01416 Rate as per SoR 1.00 sqm 5411.00 1 sqm 5411.00
MAT-01053 BMT-I.02 deduct cost of 5mm plain glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
5147.00
Joinery data 2021-22 - Page : 673
Overheads&Contractors Profit @13.615% 0.13615 5147.00 700.76
Rate per 1 sqm 5847.76
Say 5848

g Double shutter window 1200mmx1300mm :


MAT-01412 BMT - P.04 Rate as per SoR 1.00 sqm 6379.00 1.00 sqm 6379.00
MAT-01053 BMT-I.02 deduct cost of 5mm plain glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
6115.00
Overheads&Contractors Profit @13.615% 0.13615 6115.00 832.56
Rate per 1 sqm 6947.56
Say 6948

h Double shutter window 900mmx1300mm :


MAT-01412 BMT - P.04 Rate as per SoR 1.00 sqm 6379.00 1.00 sqm 6379.00
MAT-01053 BMT-I.02 deduct cost of 5mm plain glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
6115.00
Overheads&Contractors Profit @13.615% 0.13615 6115.00 832.56
Rate per 1 sqm 6947.56
Say 6948

39 Supplying and fixing of Top Hung Ventilators made of pre - painted steel (base steel as per IS 513 of -0.58 mm thick 'D" quality,
galvanized as per IS 277 with zinc of 120 GSM) primer coated with epoxy primer of 5-7 microns thick, finish painted with a polyester paint of
12-16 microns thick and back coated with 5-7 microns thick alkyd backer, section for outer frame of 46 x 52 mm section and for shutter of 46
x 46 mm section for mullion 46 x 70 mm, The Ventilator to be panelled 4 mm pinhead glass with Ethyl propylene Diamine monomer Gasket
(EPDM) and the sections cut to length mitre joined with corner brocket mullions fixed using mullion cap and with handle made of high grade
aluminium powder coated and nylon receiver, corner brackets made of CRCA with Zinc Phosphate, Mullion caps made of glass filled nylon,
frames fixed to the concrete /masonry wall by means of self expanding screws including 10 mm square guard bars with 6" pitch C2176

MAT-01418 ,
BMT-P.10, 11 ,
MAT-01419,
12
MAT-01420 Top Hung of any size 1.00 sqm 6798.00 1 sqm 6798.00
Overheads&Contractors Profit @13.615% 0.13615 6798.00 925.55
Rate per 1 sqm 7723.55
Say 7724
Joinery data 2021-22 - Page : 674
40 Supplying and fixing of Fixed Louvered Ventilators made of pre - painted steel (base steel as per IS 513 of -0.58 mm thick 'D" quality,
galvanized as per IS 277 with zinc of 120 GSM) primer coated with epoxy primer of 5-7 microns thick, finish painted with a polyester paint of
12-16 microns thick and back coated with 5-7 microns thick alkyd backer, The section for louvered ventilators should be of of 33 x 56 mm Box
section paneled with 4 mm pinhead glass with Ethyl propylene Diamine monomer Gasket (EPDM) and the sections cut to length mitre joined
with corner bracket . corner brackets made of CRCA with Zinc Phosphate. The frames to be fixed to the concrete /masonry wall by means of
self expanding screws including 10 mm square guard bars with 6" pitch including cost cost and conveyance of all materials, labour charges
for fixing, overheads and contractors profit etc., complete for finished item of work in all floors.

MAT-01421 ,
MAT-01422, BMT-P.13,14,15
MAT-01423 Fixed louvered of any size 1.00 sqm 4650.00 1 sqm 4650.00
Overheads&Contractors Profit @13.615% 0.13615 4650.00 633.10
Rate per 1 sqm 5283.10
Say 5283

41 Providing and fixing factory made uPVC white colour sliding glazed window upto 1.50 m in height dimension comprising of uPVC multi-
chambered frame with in-built roller track and sash extruded profiles duly reinforced with 1.60 ± 0.2 mm thick galvanized mild steel section
made from roll forming process of required length (shape & size according to uPVCprofile), appropriate dimension of uPVC extruded glazing
beads and uPVC extruded interlocks, EPDM gasket, wool pile, zinc alloy (white powder coated) touch locks with hook, zinc alloy body with
single nylon rollers (weight bearing capacity to be 40 kg), G.I fasteners 100 x 8 mmsize for fixing frame to finished wall and necessary
stainless steel screwsetc. Profile of frame & sash shall be mitred cut and fusion welded at all corners, including drilling of holes for fixing
hardware and drainage ofwater etc. After fixing frame the gap between frame and adjacent finishedwall shall be filled with weather proof
silicon sealent over backer rod of required size and of approved quality, all complete as per approved drawing & direction of Engineer-in-
Charge inclusive of cost of Single / double glass panes, wire mesh and silicon sealent . Note: For uPVC frame and sash extruded profiles
minus 5% tolerance in dimension i.e. in depth & width of profile shall be acceptable.Variation in profile dimension in higher side shall be
accepted but no extra payment on this account shall be made.

Two track two panels sliding window made of frame 67 x 50 mm & sash 46 x 62 mm both having wall thickness of 2.3 ± 0.2 mm and single
glazing bead / double glazing bead of appropriate dimension (Area of window up to 1.75 sqm).
MAT-05447 BMT - P.80.A Rate as per SoR 1.00 sqm 6460.00 1.00 sqm 6460.00
MAT-01053 BMT-I.02 Deduct cost of 5mm thick plain float glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 Add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
6196.00
Overheads&Contractors Profit @13.615% 0.13615 6196.00 843.59
Rate per 1 sqm 7039.59
Say 7040
Joinery data 2021-22 - Page : 675
42 Providing and fixing factory made uPVC white colour sliding glazed window upto 1.50 m in height dimension comprising of uPVC multi-
chambered frame with in-built roller track and sash extruded profiles duly reinforced with 1.60 ± 0.2 mm thick galvanized mild steel section
made from roll forming process of required length (shape & size according to uPVCprofile), appropriate dimension of uPVC extruded glazing
beads and uPVC extruded interlocks, EPDM gasket, wool pile, zinc alloy (white powder coated) touch locks with hook, zinc alloy body with
single nylon rollers (weight bearing capacity to be 40 kg), G.I fasteners 100 x 8 mmsize for fixing frame to finished wall and necessary
stainless steel screwsetc. Profile of frame & sash shall be mitred cut and fusion welded at all corners, including drilling of holes for fixing
hardware and drainage ofwater etc. After fixing frame the gap between frame and adjacent finishedwall shall be filled with weather proof
silicon sealent over backer rod of required size and of approved quality, all complete as per approved drawing & direction of Engineer-in-
Charge inclusive of cost of Single / double glass panes, wire mesh and silicon sealent . Note: For uPVC frame and sash extruded profiles
minus 5% tolerance in dimension i.e. in depth & width of profile shall be acceptable.Variation in profile dimension in higher side shall be
accepted but no extra payment on this account shall be made.

Two track two panels sliding window made of (big series) frame 67 x 50 mm & sash 46 x 62 mm both having wall thickness of 2.3 ± 0.2
mm and single glazing bead / double glazing bead of appropriate dimension . (Area of window above 1.75 sqm
MAT-05449 BMT - P.80.C Rate as per SoR 1.00 sqm 6655.00 1.00 sqm 6655.00
MAT-01053 BMT-I.02 Deduct cost of 5mm thick plain float glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 Add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
6391.00
Overheads&Contractors Profit @13.615% 0.13615 6391.00 870.13
Rate per 1 sqm 7261.13
Say 7261
43 Providing and fixing factory made uPVC white colour two track two panels sliding glazed window above 1.50 m in height dimension
comprising of uPVC multi-chambered frame with in-built roller track and sash extruded profiles duly reinforced with 1.60 ± 0.2 mm thick
galvanized mild steel section made from rollforming process of required length (shape & size according to uPVCprofile), appropriate
dimension of uPVC extruded glazing beads, uPVCextruded interlocks and uPVC extruded Inline sash adaptor (if required), EPDM gasket,
wool pile, zinc alloy (white powder coated) handle onone side of extreme panel along with zinc plated mild steel multi pointlocking having
transmission gear with keeps, zinc alloy (white powdercoated) touch lock with hook (if required for wire mesh panel), stainlesssteel (SS 304
grade) body with adjustable double nylon rollers (weightbearing capacity to be 120 kg), G.I fasteners 100 x 8 mm size for fixingframe to
finished wall and necessary stainless steel screws etc. Profileof frame & sash shall be mitred cut and fusion welded at all corners,including
drilling of holes for fixing hardware's and drainage of water etc. After fixing frame the gap between frame and adjacent finished wall shallbe
filled with weather proof silicon sealent over backer rod of requiredsize and of approved quality, all complete as per approved drawing &
direction of Engineer-in-Charge inclusive of cost of Single / double glass panes, wire mesh and silicon sealent .

Two track two panels sliding window made of (big series) frame 67 x 50 mm & sash 46 x 62 mm both having wall thickness of 2.3 ± 0.2 mm
and single glazing bead / double glazing bead of appropriate dimension. (Area of window above2.50 sqm upto 4.00 sqm) Note: For uPVC
frame and sash extruded profiles minus 5% tolerancein dimension i.e. in depth & width of profile shall be acceptable.Variation in profile
dimension in higher side shall be accepted but no extra payment on this account shall be made.
MAT-05450 BMT - P.81 Rate as per SoR 1.00 sqm 6606.00 1.00 sqm 6606.00
MAT-01053 BMT-I.02 Deduct cost of 5mm thick plain float glass 1.00 sqm 634.00 1 sqm -634.00
Joinery data 2021-22 - Page : 676
MAT-01064 BMT-I.13 Add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
6342.00
Overheads&Contractors Profit @13.615% 0.13615 6342.00 863.46
Rate per 1 sqm 7205.46
Say 7205

44 Providing and fixing factory made uPVC white colour sliding glazed window comprising of uPVC multi-chambered frame with in-built
roller track and sash extruded profiles duly reinforced with 1.60 ± 0.2 mm thick galvanized mild steel section made from roll forming process
of required length (shape & size according to uPVCprofile), appropriate dimension of uPVC extruded glazing beads and uPVC extruded
interlocks, EPDM gasket, wool pile, zinc alloy (white powder coated) touch locks with hook, zinc alloy body with single nylon rollers (weight
bearing capacity to be 40 kg), G.I fasteners 100 x 8 mmsize for fixing frame to finished wall and necessary stainless steel screwsetc. Profile
of frame & sash shall be mitred cut and fusion welded at all corners, including drilling of holes for fixing hardware and drainage ofwater etc.
After fixing frame the gap between frame and adjacent finishedwall shall be filled with weather proof silicon sealent over backer rod of
required size and of approved quality, all complete as per approved drawing & direction of Engineer-in-Charge inclusive of cost of Single /
double glass panes, wire mesh and silicon sealent . Note: For uPVC frame and sash extruded profiles minus 5% tolerance in dimension i.e. in
depth & width of profile shall be acceptable.Variation in profile dimension in higher side shall be accepted but no extra payment on this
account shall be made.

Three track three panels sliding window with fly proof SS wire mesh (Two nos. glazed & one no. wire mesh panels) made of frame
92 x 44 mm & sash 32 x 60 mmboth having wall thickness of 1.9 ± 0.2 mm and single glazing bead of appropriate dimension

MAT-05448 BMT - P.80.B Rate as per SoR 1.00 sqm 8622.00 1.00 sqm 8622.00
MAT-01053 BMT-I.02 Deduct cost of 5mm thick plain float glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 Add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
8358.00
Overheads&Contractors Profit @13.615% 0.13615 8358.00 1137.94
Rate per 1 sqm 9495.94
Say 9496

45 Providing and fixing factory made uPVC white colour fixed glazed windows / Ventilators comprising of uPVC multi chambered frame
and mullion (where ever required) extruded profiles duly reinforced with 1.60± 0.2 mm thick galvanized mild steel section made from roll
forming process of required length (shape & size according to uPVC profile), uPVC extruded glazing beads of appropriate dimension, EPDM
gasket,G.I fasteners 100 x 8 mm size for fixing frame to finished wall, plastic packers, plastic caps and necessary stainless steel screws etc.
Profileof frame shall be mitred cut and fusion welded at all corners, mullion (if required) shall be also fusion welded including drilling of holes
for fixing hardware and drainage of water etc.
Joinery data 2021-22 - Page : 677
After fixing frame the gap between frame and adjacent finished wall shall be filled with weather proof silicon sealant over backer rod of
required size and of approved quality, all complete as per approved drawing & direction of Engineer-in-Charge inclusive of cost of Single /
double glass panes and silicon sealant. Note: For uPVC frame, sash and mullion extruded profiles minus 5%tolerance in dimension i.e. in
depth & width of profile shall be acceptable.Variation in profile dimension in higher side shall be accepted. But, no extra payment on this
account shall be made.

Fixed windows / Ventilators made of (small series) frame 47 x 50mm & mullion 47 x 68 mm both having wall thickness of 1.9 ±0.2 mm and
single glazing bead of appropriate dimension.

MAT-05446 BMT-P.79 Rate as per SoR 1.00 sqm 6238.00 1.00 sqm 6238.00
Overheads&Contractors Profit @13.615% 0.13615 6238.00 849.30
Rate for 1 sqm 7087.30
Say 7087

46 Supplying and fixing of 7.5mm thick Aluminium Grill (as approved by the department) 3.58 Kg/Sqm including cost and conveyance of
all materials, accessories, labour charges for transportation, erection at site, overheads and contractor profit etc., complete for finished item of
work

MAT-01591 BMS-W.19 Rate as per SoR 1.00 sqm 1035.00 1.00 sqm 1035.00
Overheads&Contractors Profit @13.615% 0.14 1035.00 140.92
Rate per 1 sqm 1175.92
Say 1176

47 Supplying and fixing of MS Grill to windows / in open court yards using 25mm x 6mm MS flat alround and 10mm MS square bars
horizontally at 125mm centre to centre and vertically at 300mm centre to centre including fixing with 4 Nos of MS Z holdfasts (2 on each
side) duly making cutting brick masonry, fixing and making to original surface neatly including cost and conveyance of all materials, cutting,
bending, welding, operational charges, labour charges, overheads and contractor profit etc., complete for finished item of work.

for 1.80mx1.70m size 3.06 sqm


Quantity Anailysis
Cost of 25mm x 6mm MS flat alround 2 ( 1.80+ 1.70 )
7.00 RM @ 1.20 Kgs/RM 7.00 RM 8.40 Kgs

Cost of 10mm M.S square bars @0.785 kg /RM


Vertical bars 6 6 x 1.70 10.20
Horizontal bars 13 13 x 1.80 23.40
33.60 RM 26.38 Kgs
34.78 Kgs
Cost Analysis
Cost of 10mm MS squre bars 26.38 Kgs 62000.00 1000 Kgs 1635.31
Cost of 25mm x 6mm MS Flat 8.40 Kgs 62000.00 1000 Kgs 520.80
MAT-01639 BMT-W.69 Cost of MS Z hold fasts 4 Nos. 39.00 Each 156.00
Joinery data 2021-22 - Page : 678
LAB-00420 BMM-V.14 Labour charges for fabrication of steel 34.78 Kgs 30.00 1 Kg 1043.28
LAB-00421 BMM-V.15 Labour charges for fixing 34.78 6.00 208.66
Add for MAA @ 20% 0.20 625.97 125.19
Rate per 3.06 sqm 3689.24
1205.63
Overheads&Contractors Profit @13.615% 0.13615 1205.63 164.15
1369.78
Rate per 1 sqm Say 1370
Joinery data 2021-22 - Page : 679
48 Supplying and fixing of MS doors, grill to windows / in open court yards using MS angles, flat, square bars including cost and
conveyance of all materials, cutting, bending, welding, all operational charges, labour charges, overheads and contractor profit etc., complete
for finished item of work.

Cost of steel 1.05 Kgs 62000.00 1000 Kgs 65.10


LAB-00420 BMM-V.14 Labour charges for fabrication of steel 1.00 Kgs 30.00 1 Kg 30.00
LAB-00421 BMM-V.15 Labour charges for fixing 1.00 6.00 6.00
Add for MAA @ 20% 0.20 18.00 3.60
104.70
Overheads&Contractors Profit @13.615% 0.13615 104.70 14.25
118.95
Rate per 1 Kg Say 119

49 Providing and fixing Pre painted Steel two track sliding Window fabricated from roll formed sections made of Galvanized steel colour
coated /powder coated (Base Steel as per IS 513 „D‟ quality galvanized as per IS 277 with Zinc of 120 Gms./ Sq.mtr) with total coated
thickness of 0.58mm. Primer Coat with epoxy primer of 5-7 microns thick, finished paint with a polyester paint of 12-16 microns thick and back
coated with Alkyd backer of 5-7 microns or powder coated with pure polyester powder up to 50-60 microns thick. The External Section for two
track Sliding Window should be of 44 x 59mm with a provision for bottom track insert profile of 10x9 mm made of aluminium. Section for
Window glass shutter should be of 35x49mm, Section for Window Euro groove should be of 25x24mm, made of plastic to accommodate
standard accessories, and section for window lap strip should be of 21x4mm made of plastic. Section for Door shutter should be of 35x67mm.

The Window/ to be panelled with 4mm thick pin headed glass. The gaskets are to be made of Ethyl Propylene Diamine Manomer [EPDM].
Corner Brackets for internal and external frame to be made of glass filled nylon. Touch lock to be provided for Window Shutter. Sections are
to be cut to length, joined and assembled by means of corner brackets. The above frame to be fixed to Brick/Concrete masonry by using
Nylon self-expanding caps and driving MS electroplated 80mm screws into the caps through frames. The Grill for safety for windows to be
made of 10mm thick square rod bars with 152mm pitch including cost and conveyance of all materials, labour charges for fixing, overheads
and contractors profit etc., for complete for finished item of work in all floors.

MAT-01434 BMT-P.26 Rate as per SoR 1.00 sqm 6992.00 1.00 sqm 6992.00
MAT-01053 BMT-I.02 Deduct cost of 5mm thick plain float glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 Add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
6728.00
Overheads&Contractors Profit @13.615% 0.13615 6728.00 916.02
Rate per 1 sqm 7644.02
Say 7644
Joinery data 2021-22 - Page : 680
50 Providing and fixing 3 Track 3 Shutter Pre painted Steel sliding Window fabricated from roll formed sections made of Galvanized steel
colour coated /powder coated (Base Steel as per IS 513 „D‟ quality galvanized as per IS 277 with Zinc of 120 Gms./ Sq.mtr) with total coated
thickness of 0.58mm. Primer Coat with epoxy primer of 5-7 microns thick, finished paint with a polyester paint of 12-16 microns thick and back
coated with Alkyd backer of 5-7 microns or powder coated with pure polyester powder up to 50-60 microns thick. The External Section for
Three Track Three Sliding Shutter should be of 44 x 107mm with a provision for bottom track insert profile of 10x9 mm made of aluminium.
Section for Window glass shutter should be of 35x49mm , Section for Window Euro groove should be of 25x24mm made of plastic to
accommodate standard accessories, and section for window lap strip should be of 21x4mm made of plastic. Section for Mesh Shutter should
be of 35x49mm. The Window to be panelled with 4mm thick pin headed glass. The gaskets are to be made of Ethyl Propylene Diamine
Manomer [EPDM]. Corner Brackets for internal and external frame to be made of glass filled nylon. Touch lock to be provided for Window
Shutter. Sections are to be cut to length, joined and assembled by means of corner brackets. The above frame to be fixed to Brick/Concrete
masonry by using Nylon self expanding caps and driving MS electroplated 80mm screws into the caps through frames. The Grill for safety for
windows to be made of 10mm thick square rod bars with 152mm pitch including cost and conveyance of all materials, labour charges for
fixing, overheads and contractors profit etc., for complete for finished item of work in all floors.

MAT-01488 BMT-P.77 Rate as per SoR 1.00 sqm 7636.00 1.00 sqm 7636.00
MAT-01053 BMT-I.02 Deduct cost of 5mm thick plain float glass 1.00 sqm 634.00 1 sqm -634.00
MAT-01064 BMT-I.13 Add cost of 4mm thick pin headed glass 1.00 sqm 370.00 1 sqm 370.00
7372.00
Overheads&Contractors Profit @13.615% 0.13615 7372.00 1003.70
Rate per 1 sqm 8375.70
Say 8376

51 Supply and fixing powder coated alimunium fully glazed 2 shutter windows with fixed panel in between openable shutters as per
approved drawings using anodized aluminium sections of 38.50mm x 33mm , 3mm thick for outer frame, 59mm(3mm) x 33mm(2.5mm) x
30mm(3mm) for mullions and 38.5mm x 33mm , 3mm thick for shutter frame , powder coating of alluminium sections 25mm microns thick
and fixing 5 mm thick plain glass fitted with suitable aluminium galzing clips and rubber beading including supplying and fixing powder
coated aluminium adjustable frictional stay hinges (2 Nos. per shutter), handle with lock (1 No. per shutter) including cost and conveyance to
site of powder coated aluminium sections, glass, rubber beading, fixtures etc., including labour charges for manufacturing window, fixing in
position using wooden blocks and sheet metal screws, etc., complete for finished item of work in all floors. (The aluminium sections used shall
be standard make confirming to IS 1948-1961 and as approved by the Engineer and fixtures shall be of ISI marked) (1800mm x 1300mm).

Quantity analysis Size : 1.80m x 1.30m 2.34 sqm


1) Outer frame ( 38.50mm x 33mm, 3mm thick ) 2 ( 1.80 + 1.30 )
6.20 RM @ 0.775 Kgs / RM 4.81 Kgs.

2) Mullions[59mm (3mm) x 33mm (2.50mm) x 30mm (3mm) ] 2 x 1.30


2.60 RM @ 1.123 Kgs / RM 2.92 Kgs.

3) Shutters Z Section (38.50mm x 33mm x, 3mm thick 3x2(0.60 +1.30)


= 11.40 RM @ 0.663 Kgs/ RM 7.56 Kgs.
4) Glazing clips 3x2(0.60+1.30)
Joinery data 2021-22 - Page : 681
= 11.40 RM @ 0.101 Kgs /RM 1.15 Kgs.
16.44 Kgs.
Cost analysis
MAT-01575 BMS-W-01 Cost of powder coated Al. sections 16.44 Kgs. 337.00 1 Kgs. 5540.28
MAT-01053 BMT-I.02 Cost of 5mm thick plain glass 2.34 sqm 634.00 1 sqm 1483.56
MAT-01580 BMS-W-06 Cost of rubber beading 11.40 RM 2.00 1 RM 22.80
MAT-00976 BMT-G.71 Cost of Al. friction stay hinges 4 Nos. 100.00 1 Each 400.00
Cost of Al. lock with handle 2 Nos. 75.00 1 Each 150.00
Labour charges 2.34 sqm 940.11 1 sqm 2199.85
Add for Screws, Nails, etc., LS 2.79
9799.28
Overheads&Contractors Profit @13.615% 0.13615 9799.28 1334.17
Rate per 2.34 sqm 11133.46
Rate per 1 sqm 4757.89
Say 4758

52 Supply and fixing powder coated alimunium fully glazed top hung ventilators fixed with 5mm thick plain glass using suitable alluminium
glazing clips and rubber beading as per approved drawings using anodized aluminium sections of 38.50mm x 33mm , 3mm thick for outer
frame, 59mm(3mm) x 33mm(2.5mm) x 30mm(3mm) for mullions shutters z section of 38.50mmx33mm,3mm thick,powder coating of all
alluminium sections 25mm microns thick, including cost and conveyance to site of powder coated aluminium sections, glass, rubber beading,
fixtures etc., including labour charges for manufacturing window, fixing in position using wooden blocks and sheet metal screws, etc.,
complete for finished item of work. (The aluminium sections used shall be standard make confirming to IS 1948-1961 and as approved by
the Engineer and fixtures shall be of ISI marked) (900mm x 500mm).

Quantity analysis Size : 0.90mx 0.50m 0.45 sqm


1) Outer frame ( 38.50mm x 33mm, 3mm thick ) 2 ( 0.90 + 0.50 )
= 2.80 RM @ 0.775 Kgs / RM 2.17 Kgs.
2) Shutters Z Section (38.50mm x 33mm x, 3mm thick 2x2(0.45+0.50)
= 3.80 RM @ 0.663 Kgs / RM 2.52 Kgs.
3) Glazing clips 2x2(0.45+0.50)
= 3.80 RM @ 0.101 Kgs /RM. 0.38 Kgs.
5.07 Kgs.
Cost analysis
MAT-01575 BMS-W-01 Cost of powder coated Al. sections 5.07 Kgs. 337.00 1 Kgs. 1708.59
MAT-01053 BMT-I.02 Cost of 5mm thick plain glass 0.45 sqm 634.00 1 sqm 285.30
MAT-01580 BMS-W-06 Cost of rubber beading 3.80 RM 2.00 1 RM 7.60
Labour charges 0.45 sqm 940.11 1 sqm 423.05
Add for Screws, Nails, Nuts, Bolts LS 3.52
2428.06
Overheads&Contractors Profit @13.615% 0.13615 2428.06 330.58
Rate per 0.45 sqm 2758.64
Rate per 1 sqm 6130.31
Joinery data 2021-22 - Page : 682
Say 6130

53 Supplying and fixing powder coated aluminium three track sliding window as per the approved drawing with all required accessories
such as stoppers, bolts, weather stripping etc with top and sides section of window of size 92mm x 31.5mm x 1.50mm thick, sloping outward
for for drainage, fixed and sliding shutters with bottom, sides and top section of 40mm x 18mm x 1.50mm thick, interlocking section 40mm x
28mm x 18mm x 1.50mm thick inter locked for weather scaling and mounted on nylon rollers of lift type and fixing 4mm pin headed glass for
shutters fitted with aluminium glazing clips and SS 20 gauge mesh with shutter frame for bottom, sides and top with section of size 40mm x
18mm x 1.50mm thick, inter locking section 40mm x 28mm x 18mm x 1.50mm thick inter locked for weather scaling and mounted on nylon
rollers of lift type fitted with nylon/polymer mesh on rollers/pulley duly fixed with TPV gaskets / EPDM weather seal resistant accessories like
locking system 1 No. per set of sashes and the system is to be installed at the site using anchor fasteners, silicon rubber sealant, easy
glazing/deglazing at site etc., including fixing of 100mm long Aluminium handle to each shutter, cost and conveyance to site of powder
coated aluminium sections, glass, rubber beading , fixtures etc., including labour charges for manufacturing window, fixing in position using
wooden blocks and sheet metal screws, overheads & contractors profit etc., complete for finished item of work. (The aluminium sections
used shall be standard make confirming to IS 1948-1961 and as approved by the Engineer and fixtures shall be of ISI marked) (1200mm x
1200mm)

Quantity analysis Size : 1.20m x 1.20m 1.44 Sqm


Window frame
bottom : 1.20m 1.26 Kgs/RM 1.512 Kgs.
sides : (10015) 2 x 1.20m 1.099 Kgs/RM 2.638 Kgs.
top : (10015) 1.20m 1.099 Kgs/RM 1.319 Kgs.
Window shutters
bottom : (13005) 2 x 0.60m 0.546 Kgs/RM 0.66 Kgs.
3 x1.20+
plain sides & top : (13005) 2x 0.60) 0.546 Kgs/RM 2.621 Kgs.
sides inter locking : (12004) 3 x 1.20m 0.615 Kgs/RM 2.214 Kgs.
Glazing clips 2x2x(0.60+1.20)
= 7.20 RM @ 0.101 Kgs /RM 7.20 0.727 Kgs.
11.686 Kgs.

4mm thick pin headed glass 1.20m x 1.20m 1.44 sqm


Rubber beading 3.60 RM

Cost analysis
A.Material :
MAT-01575 BMS-W-01 Cost of powder coated Al. sections 11.686 Kgs. 337.00 1 Kgs. 3938.18
MAT-01064 BMT-I.13 Cost of 4mm thick pin headed glass 1.44 sqm. 370.00 1 sqm. 532.80
MAT-01580 BMS-W-06 Cost of rubber beading 3.60 RM 2.00 1 RM 7.20
MAT-00937 BMT-G.32 Cost of aluminium handles 100mm long 3 Nos 68.00 1 Each 204.00
MAT-00885 BMT-F.19 Cost of SS mesh 0.78 sqm. 564.00 1 sqm. 439.92
B.Labour charges 1.44 sqm 904.59 1 sqm 1302.61
Add for screws, nails, nuts, bolts, nylon rollers etc., LS 2.79
Joinery data 2021-22 - Page : 683
Rate per 1.44 Sqm: 6427.50
Overheads&Contractors Profit @13.615% 0.13615 6427.50 875.10
7302.61
Rate per 1 Sqm 5071.26
Say 5071

54 Supplying and fixing powder coated aluminium three track sliding window with fixed fan light of 500mm at top as per the approved
drawing with all required accessories such as stoppers, bolts, weather stripping etc with top and sides section of window of size 92mm x
31.5mm x 1.50mm thick, sloping outward for for drainage, fixed and sliding shutters with bottom, sides and top section of 40mm x 18mm x
1.50mm thick, interlocking section 40mm x 28mm x 18mm x 1.50mm thick inter locked for weather scaling and mounted on nylon rollers of lift
type and fixing 4mm pin headed glass in fan light and for shutters fitted with aluminium glazing clips and SS 20 gauge mesh with shutter
frame for bottom, sides and top with section of size 40mm x 18mm x 1.50mm thick, inter locking section 40mm x 28mm x 18mm x 1.50mm
thick inter locked for weather scaling and mounted on nylon rollers of lift type fitted with nylon/polymer mesh on rollers/pulley duly fixed with
TPV gaskets / EPDM weather seal resistant accessories like locking system 1 No. per set of sashes and the system is to be installed at the
site using anchor fasteners, silicon rubber sealant, easy glazing/deglazing at site etc., and fan light top and side section of size 63.50mm x
38.10mm, 1.53mm thick, powder coating of all Aluminium sections 25 microns thick including fixing of 100mm long Aluminium handle to each
shutter, cost and conveyance to site of powder coated aluminium sections, glass, rubber beading , fixtures etc., including labour charges for
manufacturing window, fixing in position using wooden blocks and sheet metal screws, overheads & contractors profit etc., complete for
finished item of work. (The aluminium sections used shall be standard make confirming to IS 1948-1961 and as approved by the Engineer
and fixtures shall be of ISI marked) (1500mm x 1700mm)

Quantity analysis Size : 1.50m x 1.70m 2.55 Sqm


Window frame
bottom : 1.50m 1.26 Kgs/RM 1.890 Kgs.
sides : (10015) 2 x 1.20m 1.099 Kgs/RM 2.638 Kgs.
top : (10015) 1.50m 1.099 Kgs/RM 1.649 Kgs.
fan light sides & top (4687) 2 x 0.50+1.50 0.942 Kgs/RM 2.748 Kgs.
Window shutters
bottom : (13005) 3 x 0.50m 0.546 Kgs/RM 0.82 Kgs.
3 x1.20+
plain sides & top : (13005) 1.50) 0.546 Kgs/RM 2.785 Kgs.
sides inter locking : (12004) 3 x 1.20m 0.615 Kgs/RM 2.214 Kgs.
Glazing clips 3x2x(0.50+0.50)+3x2x(0.50+1.20)
= 16.20 RM @ 0.101 Kgs /RM 16.20 1.636 Kgs.
16.379 Kgs.

4mm thick pin headed glass 1.50m x 1.70m 2.55 sqm


Rubber beading 8.10 RM

Cost analysis
Joinery data 2021-22 - Page : 684
A.Material :
MAT-01575 BMS-W-01 Cost of powder coated Al. sections 16.379 Kgs. 337.00 1 Kgs. 5519.72
MAT-01064 BMT-I.13 Cost of 4mm thick pin headed glass 2.55 sqm. 370.00 1 sqm. 943.50
MAT-01580 BMS-W-06 Cost of rubber beading 8.10 RM 2.00 1 RM 16.20
MAT-00937 BMT-G.32 Cost of aluminium handles 100mm long 3 Nos 68.00 1 Each 204.00
MAT-00885 BMT-F.19 Cost of SS mesh 0.72 sqm. 564.00 1 sqm. 406.08
B.Labour charges 2.55 sqm 904.59 1 sqm 2306.71
Add for screws, nails, nuts, bolts, nylon rollers etc., LS 0.69
Rate per 2.55 Sqm: 9396.90
Overheads&Contractors Profit @13.615% 0.13615 9396.90 1279.39
10676.29
Rate per 1 Sqm 4186.78
Say 4187

55 Supply and fixing powder coated alimunium sliding window with fixed fan light at top as per approved drawings with all required
accessories such as stoppers,bolts,weather stripping etc. for all sizes and sections in accordance with approved drawings and as per IS
1948-1961 with top section of window of size 62mm x 32mm ,1.47mm thick, window side frames of size 61.85mm x 31.75mm,1.50mm thick
and bottom frame size 61.85mm x 31.75mm,1.50mm thick sloping outwards for drainage and fixed and sliding shutters with bottom,sides and
top with section of 40mm x 18mm ,1.70mm thick,inter locking section 40mm x 28mm x 18mm,1.60mm thick inter locked for weather scaling
and mounted on nylon rollers of lift type and fan light top &side sections of size 63.50mmx38.10mm,1.53mm thick, powder coating of all
alluminium sections 25mm microns thick and fixing 5mm thick plain glass in fan light and for shutters fitted with

alluminium glazing clips and rubber beading including cost and conveyance to site of powder coated aluminium sections, glass, rubber
beading, fixtures etc., including labour charges for manufacturing window, fixing in position using wooden blocks and sheet metal screws,
overheads & contractors profit etc., complete for finished item of work. (The aluminium sections used shall be standard make confirming to IS
1948-1961 and as approved by the Engineer and fixtures shall be of ISI marked) ( 1800mm x 1800mm )

(BLD-CSTN-13-30 & S.No.10 of SoR , page 395)


Size 1.80m x 1.80m 3.24 sqm
Quantity analysis
Window frame
bottom : (8932) 1.80m 0.909 Kgs/RM 1.636 Kgs.
sides : (8931) 2 x 1.30m 0.784 Kgs/RM 2.038 Kgs.
top : (8992) 1.80m 1.005 Kgs/RM 1.809 Kgs.
fan light sides&top(4687) 1.80+2x 0.50 0.942 Kgs/RM 2.638 Kgs.
Window shutters
bottom : (8603) 3 x 0.60m 0.641 Kgs/RM 1.15 Kgs.
plain sides & top : (8604) 3 (1.30+0.60) 0.522 Kgs/RM 2.975 Kgs.
sides inter locking : (8602) 3 x 1.30m 0.663 Kgs/RM 2.586 Kgs.
Glazing clips 3x2(0.60+0.50)+3x2x(0.60+1.30)
= 18.00 RM @ 0.101 Kgs /RM 1.818 Kgs.
Joinery data 2021-22 - Page : 685
16.654 Kgs.

5mm thick plain glass 1.80m x 1.80m 3.24 sqm


Rubber beading 9.00 RM
Joinery data 2021-22 - Page : 686
Cost analysis
A.Material :
MAT-01575 BMS-W-01 Cost of powder coated Al. sections 16.654 Kgs. 337.00 1 Kgs. 5612.40
MAT-01064 BMT-I.13 Cost of 5mm thick plain glass 3.24 sqm 634.00 1 sqm 2054.16
MAT-01580 BMS-W-06 Cost of rubber beading 9.00 RM 2.00 1 RM 18.00
B.Labour charges 3.24 sqm 904.59 1 sqm 2930.88
Add for Screws, Nails, Nuts, Bolts etc., LS 3.09
Rate per 3.24 sqm 10618.52
Overheads&Contractors Profit @13.615% 0.13615 10618.52 1445.71
12064.24
Rate per 1 sqm 3723.53
Say 3724

56 Supply and fixing powder coated alimunium sliding window with fixed fan light at top as per approved drawings with all required
accessories such as stoppers,bolts,weather stripping etc. for all sizes and sections in accordance with approved drawings and as per IS
1948-1961 with top section of window of size 62mm x 32mm ,1.47mm thick, window side frames of size 61.85mm x 31.75mm,1.50mm thick
and bottom frame size 61.85mm x 31.75mm,1.50mm thick sloping outwards for drainage and fixed and sliding shutters with bottom,sides and
top with section of 40mm x 18mm ,1.70mm thick,inter locking section 40mm x 28mm x 18mm,1.60mm thick inter locked for weather scaling
and mounted on nylon rollers of lift type and fan light top &side sections of size 63.50mmx38.10mm,1.53mm thick, powder coating of all
alluminium sections 25mm microns thick and fixing 5mm thick plain glass in fan light and 5mm thick ground glass for shutters fitted with
alluminium glazing clips and rubber beading, powder coating of all alluminium sections 25mm microns thick including cost and conveyance to
site of powder coated aluminium sections, glass,

rubber beading , fixtures etc., including labour charges for manufacturing window, fixing in position using wooden blocks and sheet metal
screws, overheads & contractors profit etc., complete for finished item of work. (The aluminium sections used shall be standard make
confirming to IS 1948-1961 and as approved by the Engineer and fixtures shall be of ISI marked) (1200mm x 1800mm)

Quantity analysis Size : 1.20m x 1.80m 2.16 sqm


Quantity analysis
Window frame
bottom : (8932) 1.20m 0.909 Kgs/RM 1.091 Kgs.
sides : (8931) 2 x 1.30m 0.784 Kgs/RM 2.038 Kgs.
top : (8992) 1.20m 1.005 Kgs/RM 1.206 Kgs.
fan light sides&top(4687) 1.20+2x 0.50 0.942 Kgs/RM 2.072 Kgs.
Window shutters
bottom : (8603) 2 x 0.60m 0.641 Kgs/RM 0.77 Kgs.
plain sides & top : (8604) 2 (1.30+0.60) 0.522 Kgs/RM 1.984 Kgs.
sides inter locking : (8602) 2 x 1.30m 0.663 Kgs/RM 1.724 Kgs.
Glazing clips 2x2(0.60+0.50)+2x2x(0.60+1.30)
= 12.00 RM @ 0.101 Kgs /RM 1.212 Kgs.
12.096 Kgs.
Joinery data 2021-22 - Page : 687

5mm thick plain glass 1.20m x 1.80m 2.16 sqm


Rubber beading 6.00 RM

Cost analysis
A.Material :
MAT-01575 BMS-W-01 Cost of powder coated Al. sections 12.10 Kgs. 337.00 1 Kgs. 4076.35
MAT-01064 BMT-I.13 Cost of 5mm thick plain glass 2.16 sqm 634.00 1 sqm 1369.44
MAT-01580 BMS-W-06 Cost of rubber beading 6.00 RM 2.00 1 RM 12.00
B.Labour charges 2.16 sqm 904.59 1 sqm 1953.92
Add for Screws, Nails, Nuts, Bolts etc., LS 4.77
Rate per 2.16 sqm 7416.48
Overheads&Contractors Profit @13.615% 0.13615 7416.48 1009.75
8426.23
Rate per 1 sqm 3901.03
Say 3901

57 Supply and fixing of cement bonded pre-laminated particle boards aluminum glazed partitions using 10mm cement bonded pre-
laminated particle boards and 5.00 mm thick plain glass to full height. Using with LAM to a height of 0.91 meter at bottom panel and
remaining height with glass and aluminum sections anodized to 12 to 15 microns and of sections of size 37mm x 62mm and 1.5mm thickness
with one meter centre to centre duly fixed with clip beading on both sides including fixing the frame to pillars by M.S. flats, bolts and nuts
including cost and conveyance of all materials etc., complete as directed during execution and overheads & contractors profit etc., complete
for finished item of work

MAT-01310 BMT-M.75 Rate as per SSR 1.00 sqm 3400.00 1 sqm 3400.00
Overheads&Contractors Profit @13.615% 0.13615 3400.00 462.91
Rate for 1 sqm 3862.91
Say 3863
Joinery data 2021-22 - Page : 688
58 Supplying and fixing of two shutter cupboards as per drawing with medium teak wood frames of size 75mm x 40mm and MDF Board
Interior grade both sides laminated 18mm thick for shutters with 18mm x 12mm teak wood beading alround and supplying and fixing powder
coated MS fixtures 3 Nos. butt hinges of size 100mm long(for each shutter), tower bolt 2 Nos. of 100mm x 10mm, 2 Nos of handles 100mm
long and standard locking arrangements for shutters including cost and conveyance of all materials to site, labour charges, over heads and
contractor profit etc., complete for finished item of work.

For Cup board of size 1.20m x 1.80m 2.16 sqm


MAT-00846 BMT - E.01 Cost of medium teak wood frame 0.0180 cum 81950.00 1 cum 1475.10
MAT-01167 BMT-K.59 MDF Board Interior - BSL 18mm thick 2.16 sqm 801.00 1 sqm 1730.16
MAT-00933 BMT-G.28 Powder coated butt hinges 100mm long 6 Nos 20.00 1 Each 120.00
MAT-00919 BMT-G.14 Powder coated tower bolts 100mm long 2 Nos 26.50 1 Each 53.00
Powder coated handles 125mm long 2 Nos 35.00 1 Each 70.00
MAT-00850 BMT - E.05 Teak wood beading 18mm x 12mm 7.20 RM 31.26 1 RM 225.07
Cupboard locks 1 No 100.00 1 Each 100.00
Labour charges for frame work 0.0144 cum 15363.90 1 cum 221.24
LAB-00418 BMM-V.07 Labour charges for shutters and fixing fixtures 2.16 sqm 666.00 1 sqm 1438.56
Add for MAA @ 20% 0.20 1659.80 331.96
Add LS for Screws, Nails etc. 4.98
5770.07
Overheads&Contractors Profit @13.615% 0.14 5770.07 785.60
Rate per 2.16 sqm 6555.67
Rate per 1 sqm 3035.03
Say 3035
CIVIL DATA 2020-21 : Page-689

D A T A ( SoR 2022-23)
NAME OF THE WORK :- CONSTRUCTION OF PROPOSED DEGREE COLLEGE AT VEMPALLI

CEMENT MORTAR PER CUM CM (1:2) CM (1:3) CM (1:4) CM (1:5) CM (1:6)


Cost of Sand for Plastering (1.05 cum ) 1213.80 1213.80 1213.80 1213.80 1213.80
Cost of cement 3038.40 2025.60 1519.20 1215.36 1012.80
Mazdoor ( Unskilled ) for mixing mortar ( 0.20 Nos.) 105.00 105.00 105.00 105.00 105.00
Add for MAA @ 20% 21.00 21.00 21.00 21.00 21.00
Rate per Cum 4378.20 3365.40 2859.00 2555.16 2352.60

20 mm HBG graded metal


Arregates 20mm nominal size 0.60 1949.30 1169.58
Arregates 13.20 / 12.50mm nominal size 0.15 1644.30 246.65
Arregates 10mm nominal size 0.15 1454.30 218.15

Arregates 6mm nominal size 0.10 1249.30 124.93


Rate per Cum 1759.31

12 mm HBG graded metal


Arregates 13.20 / 12.50mm nominal size 0.60 1644.30 986.58
Arregates 10mm nominal size 0.20 1454.30 290.86

Arregates 6mm nominal size 0.20 1249.30 249.86

Rate per Cum 1527.30


CIVIL DATA 2020-21 : Page-690

DATA
Standard Data
S. No. CFMS code SoR Ref Description Quantity Rate (Rs.) Unit
Ref
Dismantling, clearing away and carefully stacking useful materials for re-use and disposal of unserviceable materials with 100m lead as directed by Executive Eng
1
taking actual premeasurements before dismantling including all labour charges , overheads & contractor profit etc., complete
a) (BLD-CSTN-14-9/299) Brick masonry
LAB-00120,
CSoR III - 3,4 Mazdoor(unskilled) 0.409 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 214.73
Rate per 1 cum
Overheads&Contractors Profit @13.615% 0.13615 257.67
Rate per 1 cum
say

b) (BLD-CSTN-14-8/296) Unreinforced cement concrete up to 15cm thickness


LAB-00120,
CSoR III - 3,4 Mazdoor(unskilled) 2.44 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 1281.00
Rate per 1 cum
Overheads&Contractors Profit @13.615% 0.13615 1537.20
Rate per 1 cum
say

c) (BLD-CSTN-14-8/297) Unreinforced cement concrete more than 15cm thickness


LAB-00120,
CSoR III - 3,4 Mazdoor(unskilled) 4.88 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 2562.00
Rate per 1 cum
Overheads&Contractors Profit @13.615% 0.13615 3074.40
Rate per 1 cum
say

d) (BLD-CSTN-14-8/298) Reinforced cement concrete


LAB-00120,
CSoR III - 3,4 Mazdoor(unskilled) 4.32 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 2268.00
Rate per 1 cum
Overheads&Contractors Profit @13.615% 0.13615 2721.60
Rate per 1 cum
say
CIVIL DATA 2020-21 : Page-691

e) Kadapa slabs or shahabad stone slabs on sand bed


MAT-01508 BMT-S.11 Rate as per SoR 10.00 sqm 84.00 10 sqm
Add for MAA @ 20% 0.20 84.00
Rate per 10 sqm
Rate per 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 10.08
Rate per 1 sqm
say

f) Stone masonry in cement mortar


MAT-01498 BMT-S.01 Rate as per SoR 1.00 cum 498.00 1 cum
Add for MAA @ 20% 0.20 498.00
Rate per 1 cum
Overheads&Contractors Profit @13.615% 0.13615 597.60
Rate per 1 cum
say

g) Pan tiled or Mangalore tiled roof with out roof timbers :


MAT-01501 BMT-S.04 Rate as per SoR 10.00 sqm 152.00 10 sqm
Add for MAA @ 20% 0.20 152.00
Rate per 10 sqm
Rate per 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 18.24
Rate per 1 sqm
say

h) Flat stone in roof or floors including lifting :


MAT-01500 BMT-S.03 Rate as per SoR 10.00 sqm 182.00 10 sqm
Add for MAA @ 20% 0.20 182.00
Rate per 10 sqm
Rate per 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 21.84
Rate per 1 sqm
say

i) Wrought and framed timber in roofs or floors ;


MAT-01503 BMT-S.06 Rate as per SoR 1.00 cum 263.00 1 cum
Add for MAA @ 20% 0.20 263.00
Rate per 1 cum
Overheads&Contractors Profit @13.615% 0.13615 315.60
Rate per 1 cum
say
CIVIL DATA 2020-21 : Page-692

j) Old lime mortar plaster


MAT-01504 BMT-S.07 Rate as per SoR 10.00 sqm 60.00 10 sqm
Add for MAA @ 20% 0.20 60.00
Rate per 10 sqm
Rate per 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 7.20
Rate per 1 sqm
say
k) Old cement mortar plaster
MAT-01505 BMT-S.08 Rate as per SoR 10.00 sqm 75.00 10 sqm
Add for MAA @ 20% 0.20 75.00
Rate per 10 sqm
Rate per 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 9.00
Rate per 1 sqm
say

Clean removal of lime plaster from walls and raking out joints
l) 20mm deep or from terraced roof and raking out joints 100 mm
deep
MAT-01511 BMT-S.14 Rate as per SoR 10.00 sqm 55.00 10 sqm
Add for MAA @ 20% 0.20 55.00
Rate per 10 sqm
Rate per 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 6.60
Rate per 1 sqm
say

Clean removal of cement plaster from walls and raking out joint
m)
200 mm deep
MAT-01512 BMT-S.15 Rate as per SoR 10.00 sqm 68.00 10 sqm
Add for MAA @ 20% 0.20 68.00
Rate per 10 sqm
Rate per 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 8.16
Rate per 1 sqm
say
CIVIL DATA 2020-21 : Page-693

Dismantling doors , windows and clear storey windows, Ventilators etc., ( wood or steel ) shutters including Chowkhats , architraves,hold fasts and other attachm
2
and stacking them within 100m lead including labour charge etc., and overheads & contractors profit complete for finished item of work
a) (BLD-CSTN-14-11 - i) Not exceeding 3 sqm in area :
Details of cost per each :
LAB-00091 CSoR II - 35 2nd class mason 0.10 Nos. 565.00 1 No.
LAB-00120 CSoR III - 3 Mazdoor(Male) 0.20 Nos. 525.00 1 No.
LAB-00091 CSoR II - 35 2nd class Blacksmith 0.05 Nos. 565.00 1 No.
Add for MAA @ 20% 0.20 189.75

Overheads&Contractors Profit @13.615% 0.13615 227.70


Cost per each
Say

b) (BLD-CSTN-14-11 - ii) Exceeding 3 sqm in area :


Details of cost per each :
LAB-00091 CSoR II - 35 2nd class mason 0.13 Nos. 565.00 1 No.
LAB-00120 CSoR III - 3 Mazdoor(Male) 0.27 Nos. 525.00 1 No.
LAB-00091 CSoR II - 35 2nd class Blacksmith 0.07 Nos. 565.00 1 No.
Add for MAA @ 20% 0.20 254.75

Overheads&Contractors Profit @13.615% 0.13615 305.70


Cost per each
Say

Dismantling of existing dilapidated buildings including items like un-reinforced concrete, reinforced concrete, brick masonry, stone masonry etc., using Doze
3
including all hire, operational, incidental, labour charges and overheads & contractors profit etc. complete finished item of work
HIR-00072 CSoR 2 Rate as per Common SoR 1.00 Hour 1907.00 1 Hour
Overheads&Contractors Profit @13.615% 0.13615 1907.00
Rate per 1 cum
say
CIVIL DATA 2020-21 : Page-694

Earth work excavation for foundations (Manual Means) of buildings, septic tank, sump, compound wall in ordinary soils and depositing on bank with an initi
4 BLD-CSTN-2-1 10m and depth up to 3m including all operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc., and overheads & contractors profit com
finished item of work excluding dewatering charges etc., as per SS 20 B(APSS 308)
Ordinary Soil - Manual Means up to 3m depth
Unit : 1 cum
Taking output : 10.00 cum
a) Labour
LAB-00120,
CSoR III - 3,4 Mazdoor ( Unskilled) 3.64 Nos. 525.00 1 No.
LAB-00121
Add for MAA @ 20% 0.20 1911.00

b&c)
Overheads&Contractors Profit @13.615% 0.13615 2293.20
Cost for 10 cum ( a+b+c)
Rate per cum (a+b+c) / 10
Rate per 1 cum Say

Earth work excavation for foundations (Mechanical Means) for buildings in ordinary soils and depositing on bank for all lifts and with an initial lead of 10m and
5 BLD-CSTN-2-2 depth including all operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc., and overheads & contractors profit complete for finished ite
excluding dewatering charges etc., as per SS 20 B(APSS 308)
Ordinary Soil - Mechanical Means up to 3m depth
Unit : 1 cum
Taking output : 240.00 cum
a) Labour
LAB-00120,
CSoR III - 3,4 Mazdoor ( Unskilled) 8.32 Nos. 525.00 1 No.
LAB-00121
Add for MAA @ 20% 0.20 4368.00
b) Machinery
HIR-00052 &
CSoR 52 Shovel 0.85 cum 110hp 6.00 hours 3157.40 1 Hour
LAB-00362
HIR-00186 CSoR 52 Crew charges 6.00 hours 326.30 1 Hour
Add MA on crew charges 0.20 1957.80

c&d)
Overheads&Contractors Profit @13.615% 0.13615 26535.36
Cost for 240 cum ( a+b+c+d)
Rate per 1 cum (a+b+c+d) / 240
Say
CIVIL DATA 2020-21 : Page-695

Earth work excavation for foundations (Mechanical Means) for buildings in ordinary soils and depositing on bank for all lifts and with an initial lead of 10m and
6 BLD-CSTN-2-3 depth including all operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc., and overheads & contractors profit complete for finishe
work excluding dewatering charges etc., as per SS 20 B(APSS 308)
Ordinary Soil - Mechanical Means up to 3m to 6m depth
Unit : 1 cum
Taking output : 210.00 cum
a) Labour
LAB-00120,
CSoR III - 3,4 Mazdoor ( Unskilled) 8.32 Nos. 525.00 1 No.
LAB-00121
Add for MAA @ 20% 0.20 4368.00
b) Machinery
HIR-00052& LAB-
CSoR 52 Shovel 0.85 cum 110hp 6.00 hours 3157.40 1 Hour
00362
HIR-00186 CSoR 52 Crew charges 6.00 hours 326.30 1 Hour
Add MA on crew charges 0.20 1957.80

c&d)
Overheads&Contractors Profit @13.615% 0.13615 26535.36
Cost for 210 cum ( a+b+c+d)
Rate per 1 cum (a+b+c+d) / 210
Rate per 1 cum Say

Earth work excavation for foundations (Manual Means) of buildings in ordinary rock ( not requiring blasting ) and depositing on bank with an initial lead of
7 BLD-CSTN-2-4 depth up to 3m including all operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc., and overheads & contractors profit complete fo
item of work excluding dewatering charges etc., as per SS 20 B(APSS 308)
Ordinary rock(not requiring blasting) - Manual Means up to 3m depth
Unit : 1 cum
Taking output : 10.00 cum
a) Labour
LAB-00120,
CSoR III - 3,4 Mazdoor ( Unskilled) 5.20 Nos. 525.00 1 No.
LAB-00121
Add for MAA @ 20% 0.20 2730.00

b&c)
Overheads&Contractors Profit @13.615% 0.13615 3276.00
Cost for 10 cum ( a+b+c)
Rate per 1 cum (a+b+c) / 10
Rate per 1 cum Say
CIVIL DATA 2020-21 : Page-696

Earth work excavation for foundations (Mechanical Means) for buildings in ordinary rock (not requiring blasting) and depositing on bank for all lifts and with
8 BLD-CSTN-2-5 lead of 10m and up to 3m depth including all operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc., and overheads & contrac
complete for finished item of work excluding dewatering charges etc., as per SS 20 B(APSS 308)
Ordinary rock(not requiring blasting)- Mechanical Means up to 3m depth
Unit : 1 cum
Taking output : 180.00 cum
a) Labour
LAB-00120,
CSoR III - 3,4 Mazdoor ( Unskilled) 6.24 Nos. 525.00 1 No.
LAB-00121
Add for MAA @ 20% 0.20 3276.00
b) Machinery
HIR-00052& LAB-
CSoR 52 Shovel 0.85 cum 110hp 6.00 hours 3157.40 1 Hour
00362
HIR-00186 CSoR 52 Crew charges 6.00 hours 326.30 1 Hour
Add MA on crew charges 0.20 1957.80

c&d)
Overheads&Contractors Profit @13.615% 0.13615 25224.96
Cost for 180 cum ( a+b+c+d)
Rate per 1 cum (a+b+c+d) / 180
Rate per 1 cum Say
CIVIL DATA 2020-21 : Page-697

Earth work excavation for foundations for buildings in hard rock (requiring blasting) and depositing on bank for all lifts and with an initial lead of 10m and
9 BLD-CSTN-2-6 depth including all operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc., and overheads & contractors profit complete for finished ite
excluding dewatering charges etc., as per SS 20 B(APSS 308)
Hard rock (requiring blasting)- up to 3m depth
Unit : 1 cum
Taking output : 10.00 cum
a) Labour
LAB-00023 CSoR 39 Driller 0.50 Nos. 460.20 1 No.
LAB-00003 CSoR I - 3 Blaster 0.25 Nos. 690.00 1 No.
LAB-00120,
CSoR III - 3,4 Mazdoor ( Unskilled) 8.35 Nos. 525.00 1 No.
LAB-00121
Add for MAA @ 20% 0.20 4786.35
b) Machinery
HIR-00003 &
CSoR 3 Air compressor 7cmm (diesel) 1.00 hour 1452.80 1 Hour
LAB-00319
HIR-00039 CSoR 39 Jack hammer/Pneumatic braker 2.00 hours 18.60 1 Hour
Crew charges
HIR-00137 CSoR 3 Air compressor 1.00 Hours 294.50 1 Hour
HIR-00173 CSoR 39 Jack hammer/Pneumatic braker 2.00 Hours 460.20 1 Hour
Add MA on crew charges 0.20 1214.90
c)Material
MAT-00264 M - 104 Gelatin 80% 3.50 Kgs 68.00 1 Kg
MAT-00021 CSoR 21 Detonator electric 14 Nos. 12.00 1 No.

c&d)
Overheads&Contractors Profit @13.615% 0.13615 9097.50
Cost for 10 cum ( a+b+c+d)
Rate per 1 cum (a+b+c+d) / 10
Rate per 1 cum Say
CIVIL DATA 2020-21 : Page-698

Earth work excavation for foundations for buildings in hard rock (blasting prohibited) and depositing on bank for all lifts and with an initial lead of 10m and
10 BLD-CSTN-2-7 depth including all operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc., and overheads & contractors profit complete for finished ite
excluding dewatering charges etc., as per SS 20 B(APSS 308)
Hard rock (blasting prohibited)- up to 3m depth
Unit : 1 cum
Taking output : 10.00 cum
a) Labour
LAB-00120,
CSoR III - 3,4 Mazdoor ( Unskilled) 5.20 Nos. 525.00 1 No.
LAB-00121
Add for MAA @ 20% 0.20 2730.00
b) Machinery
HIR-00003& LAB-
CSoR 3 Air compressor 6.00 Hours 1452.80 1 Hour
00319
HIR-00039 CSoR 39 Jack hammer/Pneumatic braker 12.00 Hours 18.60 1 Hour
Crew charges
HIR-00137 CSoR 3 Air compressor 6.00 Hours 294.50 1 Hour
HIR-00173 CSoR 39 Jack hammer/Pneumatic braker 12.00 Hours 460.20 1 Hour
Add MA on crew charges 0.20 7289.40

c&d)
Overheads&Contractors Profit @13.615% 0.13615 20963.28
Cost for 10 cum ( a+b+c+d)
Rate per 1 cum (a+b+c+d) / 10
Rate per 1 cum Say

Conveyance of un-useful excavated earth to a distance of 5 KM for disposal including hire charges of T & P, labour charges etc., and overheads & contrac
11
complete for finished item of work.
Rate as per SoR 1 cum 96.00 1 cum
Overheads&Contractors Profit @13.615% 0.13615 96.00

Rate per 1 cum Say


CIVIL DATA 2020-21 : Page-699

Pre construction Anti termite treatment is a process in which chemical toxic to subterrean tremites is apply/ inject into soil during early stage of building Const
Treatement of soil Beneath the building and around the foundations conduct and chemical use as per BIS - IS 6313 (Part -2) 2013 code specification & CIB RC
termiticide which creates a continuous chemical barrier beneath the building which kills or repels terminates & impervious to tremite entry 3. Imidacloprid 30.5% SC (
dissolve 2.1 Ml/1 liter of water and apply emulsion/solution @ 7.5 Litres/Square meter (Sqm) of internal, external vertical surface of the colums, plinth beams (Back fil
12
and floor junction, external perimeters, along reatining wall @ 5.0 Liters/Sqm of the horizontal surface of basement top surface of the basement filling below flooring be
& @ 2.0 Litres/ Line meter at expansion joints. The substructure of a depth of 500mm around coulmns & 300mm deep around plinth beams, basements & floor f
including excavation channel along the wall & rodding etc. cost & Conveyance of all materials to the site, cost of labour for sparying, rodding, overheads and contractor
complete for furnished item of work as per the approval of the Engineer-in-charge

Unit : 1 sqm
MAT-05352 BMT-H.66 Rate as per SoR 1 sqm 162.00 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 162.00
Rate per 1 sqm

BLD-CSTN-2-8 &
Addendum
Filling with carted gravel in trenches,sides of foundations and basement with initial lead in layers not exceeding 15cm thick,watering and ramming including
dt.14.05.2019 of
13 conveyance of water to work site and all operaitonal,incidental, labour charges,hire charges of T&P etc., and overheads & contractors profit complete for fnishe
the Chief
work(APSS NO.309&310)
Engineer (R&B)
Buildings

Unit : 1 cum
Taking output 6.00 cum
a) Labour
LAB-00120,
CSoR III - 3,4 Mazdoor ( Unskilled ) 0.31 Nos. 525.00 1 No.
LAB-00121
Add for MAA @ 20% 0.20 162.75
b)Material :
MAT-00177 M - 008 Gravel 6.00 cum 561.80 1 cum

Add for water @ 1% 0.01 3566.10


Rate per 6 cum
Overheads&Contractors Profit @13.615% 0.13615 3601.76

Rate per 1 cum


Say
BLD-CSTN-2-8 &
Addendum
Filling with carted coarse sand in trenches, sides of foundations and basement with initial lead in layers not exceeding 15cm thick,watering and ramming including
dt.14.05.2019 of
14 conveyance of water to work site and all peraitonal,incidental ,labour charges,hire charges of T&P etc., and overheads & contractors profit complete for fnishe
the Chief
work(APSS NO.309&310)
Engineer (R&B)
Buildings
CIVIL DATA 2020-21 : Page-700

Unit : 1 cum
Taking output 6.00 cum
a) Labour
LAB-00120,
CSoR III - 3,4 Mazdoor ( Unskilled ) 0.31 Nos. 525.00 1 No.
LAB-00121
Add for MAA @ 20% 0.20 162.75
b)Material :
MAT-00028 CSoR 27(b) Coarse sand for filling 6.00 cum 916.00 1 cum

Add for water @ 1% 0.01 5691.30


Rate per 6 cum
Overheads&Contractors Profit @13.615% 0.13615 5748.21
Rate per 1 cum

Say

BLD-CSTN-2-9 &
Addendum Filling with useful available excavated earth (excluding rock) with a lead of 50 m in trenches, sides of foundations and basement with initial lead in layers not exceed
15 dt.14.05.2019 of the thick, watering and ramming including cost and conveyance of water to work site and all operaitonal, incidental, labour charges, hire charges of T&P etc., and ove
Chief Engineer (R&B) contractors profit complete for fnished item of work (APSS NO.309&310)
Buildings

Unit : 1 cum
Taking output : 6.00 cum
a) Labour
LAB-00120,
CSoR III - 3,4 Mazdoor ( Unskilled ) 0.31 Nos. 525.00 1 No.
LAB-00121
Add for MAA @ 20% 0.20 162.75

Add for water @ 1% 0.01 195.30


Rate per 6 cum (a+b+c)
Overheads&Contractors Profit @13.615% 0.13615 197.25

Rate per 1 cum


Say

Plain Cement Concrete (1:4:8) (cement: fine aggregate: Coarse aggregate) for foundations using coarse aggregate 40mm size hard , machine crushed gra
approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity including cost and conveyance of all materials like cement, sand, coarse aggregate, water e
16 BLD-CSTN-3-5
including all charges for machine mixing and hire charges of concrete mixer, laying concrete in foundations and under flooring bed, ramming in 15 cm layers finishing to
to the required level curing etc.,and overheads & contractors profit complete for finished item of work. (APSS No. 402)

Unit : 1 cum
A.MATERIALS :
CIVIL DATA 2020-21 : Page-701

Cement 162.00 Kgs 4220.00 1000 Kgs


MAT-00220 CSoR M - 055 Coarse aggregate 40mm 0.90 Cum 1349.30 1 Cum
MAT-00027 CSoR 27(a) Fine aggregate ( Sand ) 0.45 Cum 1061.00 1 Cum
MAT-00332,
M - 189(a),(b) Water(including for curing) 1.20 kl 116.00 1 kl
MAT-00333
B.MACHINERY :
HIR-00016& LAB-
CSoR 16 Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)capacity 1.00 hour 188.10 1 hour
00329
HIR-00150 CSoR 16 Crew charges 1.00 hour 306.80 1 hour
Add MA on crew charges 0.20 306.80
C.LABOUR :
LAB-00011 CSoR I -11 1st class mason 0.10 Nos. 630.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (unskilled) 1.39 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 792.75
Rate per 1 cum
Overheads&Contractors Profit @13.615% 0.13615 4022.22
Rate per 1 cum
Say
CIVIL DATA 2020-21 : Page-702

Plain Cement Concrete (1:5:10) (cement: fine aggregate: Coarse aggregate) for foundations and under flooring bed using coarse aggregate 40mm size hard
crushed granite from approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity including cost and conveyance of all materials like cement, san
17 BLD-CSTN-3-7
aggregate, water etc. to site including all charges for machine mixing and hire charges of concrete mixer, laying concrete in foundations and under flooring bed, ramm
cm layers finishing top surface to the required level curing etc.,and overheads & contractors profit complete for finished item of work. (APSS No. 402)

Unit : 1 cum
A.MATERIALS :
Cement 129.60 Kgs 4220.00 1000 Kgs
MAT-00220 CSoR M - 055 Coarse aggregate 40mm 0.90 Cum 1349.30 1 Cum
MAT-00027 CSoR 27(a) Fine aggregate ( Sand ) 0.45 Cum 1061.00 1 Cum
MAT-00332,
M - 189(a),(b) Water(including for curing) 1.20 kl 116.00 1 kl
MAT-00333
B.MACHINERY :
HIR-00016& LAB-
CSoR 16 Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity 1.00 hour 188.10 1 hour
00329
HIR-00150 CSoR 16 Crew charges 1.00 hour 306.80 1 hour
Add MA on crew charges 0.20 306.80
C.LABOUR :
LAB-00011 CSoR I -11 1st class mason 0.10 Nos. 630.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (unskilled) 1.39 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 792.75
Rate per 1 cum
Overheads&Contractors Profit @13.615% 0.13615 3885.49
Rate per 1 cum
Say
CIVIL DATA 2020-21 : Page-703

Random Rubble stone masonry in CM (1:8) prop: (Cement: Sand) using hard other than granite stones carted from approved quarry including cost and conveya
18 BLD-CSTN-6-13 materials like cement, screened sand, water, stones etc., from approved quarry, to site, including labour for cutting stones to required size and shape, mixing, of cemen
construction, curing etc.,and overheads & contractors profit complete for finished item of work in foundation and basement. (APSS No. 601 & 615)

Unit = 1 cum
A.MATERIALS
Cement 59.40 Kgs 4220.00 1000 Kgs
MAT-00405 CSoR 1 Rough stone (OTG) 1.10 Cum 555.75 1 Cum
MAT-00029 CSoR 28 Fine aggregate(sand) 0.33 Cum 1156.00 1 Cum
B) LABOUR
LAB-00011 CSoR I -11 1st class mason 1.20 Nos. 630.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (unskilled) 2.00 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 1806.00

Add water charges 0.01 3410.67


Rate per 1 cum
Overheads&Contractors Profit @13.615% 0.13615 3444.78
Rate per 1 cum
Say

Random Rubble stone masonry in CM (1:8) prop: (Cement: Sand) using hard granite stones carted from approved quarry including cost and conveyance of all ma
19 BLD-CSTN-6-13 cement, screened sand, water, stones etc., from approved quarry, to site including labour for cutting stones to required size and shape, mixing, of cement, mortar, con
curing etc.,and overheads & contractors profit complete for finished item of work in foundation and basement. (APSS No. 601 & 615)

Unit = 1 cum
A.MATERIALS
Cement 59.40 Kgs 4220.00 1000 Kgs
MAT-00302 CSoR 12 Rough stone (HBG) 1.10 Cum 682.30 1 Cum
MAT-00029 CSoR 28 Fine aggregate(sand) 0.33 Cum 1156.00 1 Cum
B) LABOUR
LAB-00011 CSoR I -11 1st class mason 1.20 Nos. 630.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (unskilled) 2.00 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 1806.00

Add water charges 0.01 3549.88


Rate per 1 cum
Overheads&Contractors Profit @13.615% 0.13615 3585.38
CIVIL DATA 2020-21 : Page-704

Rate per 1 cum


Say

Vibrated Plain Cement Concrete (1:3:6) nominal mix using 40mm size machine crushed hard granite metal and 20mm graded machine crushed hard granite met
BLD-CSTN-3-10 aggregate) in (2:1) ratio from approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity including cost and conveyance of all materials like cement, fine a
20
& 11 (sand), coarse aggregate, water etc. to site, all charges for mixing and hire charges of concrete mixer, centering charges, laying concrete in position, vibrating, curing,
charges, overheads & contractors profit etc.,for finished item of work for footings and basement .
Unit : 1cum
A.MATERIALS :
MAT-00220 CSoR M - 055 HBG 40mm size metal 0.60 Cum 1349.30 1 Cum
HBG 20mm size graded metal 0.30 Cum 1759.31 1 Cum
MAT-00027 CSoR 27(a) Sand 0.45 Cum 1061.00 1 Cum
Cement 220.00 Kgs 4220.00 1 MT
MAT-00332,
M - 189(a),(b) Water(including for curing) 1.20 kl 116.00 1 kl
MAT-00333
B.MACHINERY :
HIR-00016& LAB-
CSoR 16 Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity 1.00 hour 188.10 1 hour
00329
HIR-00150 CSoR 16 Crew Charges 1.00 hour 306.80 1 hour
Add MA on crew charges 0.20 306.80
HIR-00040& LAB-
CSoR 40 Needle vibrator 40mm ( petrol ) 1.00 hours 38.20 1 hour
00352
HIR-00174 CSoR 40 Crew charges 1.00 hours 220.90 1 hour
Add MA on crew charges 0.20 220.90
C.LABOUR :
LAB-00011 CSoR I -11 1st class mason 0.10 Nos. 630.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (Unskilled) 1.39 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 792.75
Hire charges for Centering & Scaffolding 1.00 Cum 67.00 1 Cum
Centering & Scaffolding (Labour) 1.00 Cum 363.00 1 Cum
Add for MAA @ 20% 0.20 363.00
Rate for 1 cum
Overheads&Contractors Profit @13.615% 0.13615 5195.86
Rate per 1 cum
Say
CIVIL DATA 2020-21 : Page-705

Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with cement content of 380 kgs per 1 cum of concrete using weigh batch
with 20mm size graded machine crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry including
21 BLD-CSTN-3-14 conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site, centering using steel scaffolding pipes , jack props , wall
plates , brackets , steel centering plates etc., including all operational, incidental and labour charges such as weigh batching, machine mixing, lifting of concrete m
laying concrete, vibrating, curing etc., and overheads & contractors profit complete but excluding cost of steel and its fabrication charges for finished item of work (APSS

FOUNDATIONS , PLINTH , PEDESTALS ( Below Plinth)


A.MATERIALS :
Cement 380.00 Kgs 4220.00 1000 Kgs
20mm HBG graded metal 0.80 Cum 1759.31 1 Cum
MAT-00027 CSoR 27(a) Sand 0.40 Cum 1061.00 1 Cum
B.LABOUR :
LAB-00011 CSoR I -11 1st class Mason 0.133 Nos 630.00 1 Each
LAB-00091 CSoR II - 35 2nd class Mason 0.267 Nos 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (both men&women) 4.60 Nos 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 2649.65
C.MACHINERY :
HIR-00009& LAB-
CSoR 9 Batching plant 0.50 cum 1.333 hours 233.80 1 hour
00325
HIR-00144 CSoR 9 Crew charges 1.333 hours 473.50 1 hour
HIR-00040& LAB-
CSoR 40 Needle vibrator 40mm ( petrol ) 1.333 hours 38.20 1 hour
00352
HIR-00174 CSoR 40 Crew charges 1.333 hours 220.90 1 hour
Add MA on crew charges 0.20 925.64
MAT-00332,
M - 189(a),(b) Water (including for curing) 1.20 kl 116.00 1 kl
MAT-00333
Rate per 1 cum

a Footings
Rate for Design mix M 25 1.00 Cum 8227.56 1 Cum
Hire charges of centering and scaffolding 1.00 Cum 301.00 1 Cum
Labour charges 1.00 Cum 672.00 1 Cum
Add for MAA @ 20% 0.20 672.00

Overheads&Contractors Profit @13.615% 0.13615 9334.96


Rate per 1 cum
Say
CIVIL DATA 2020-21 : Page-706

b Column pedestals
Rate for Design mix M 25 1.00 Cum 8227.56 1 Cum
Hire charges of centering and scaffolding 1.00 Cum 343.00 1 Cum
Labour charges 1.00 Cum 1069.00 1 Cum
Add for MAA @ 20% 0.20 1069.00

Overheads&Contractors Profit @13.615% 0.13615 9853.36


Rate per 1 cum
Say

c Plinth Beams
Rate for Design mix M 25 1.00 Cum 8227.56 1 Cum
Hire charges of centering and scaffolding 1.00 Cum 726.50 1 Cum
Labour charges 1.00 Cum 810.00 1 Cum
Add for MAA @ 20% 0.20 810.00

Overheads&Contractors Profit @13.615% 0.13615 9926.06


Rate per 1 cum
Say
d Base slab for Sump / Septic tank :
Rate for Design mix M 25 1.00 Cum 8227.56 1 Cum
Hire charges of centering and scaffolding 1.00 Cum 67.00 1 Cum
Labour charges 1.00 Cum 363.00 1 Cum
Add for MAA @ 20% 0.20 363.00

Overheads&Contractors Profit @13.615% 0.13615 8730.16


Rate per 1 cum
Say
CIVIL DATA 2020-21 : Page-707

Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with cement content of 380 kgs per 1 cum of concrete using weigh batch
with 20mm size graded machine crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry including
22 BLD-CSTN-3-18 conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site, centering using casurina ballies, bamboos, wooden reapers,
wood posts, wall plates etc., including all operational, incidental and labour charges such as weigh batching, machine mixing, lifting of concrete manually, laying
vibrating, curing , overheads & contractors profit etc., complete but excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402)

COLUMNS, LINTELS, WATER TANKS, RCC WALL IN BUILDINGS:


A.MATERIALS :
Cement 380.00 Kgs 4220.00 1000 Kgs
20mm HBG graded metal 0.80 Cum 1759.31 1 Cum
MAT-00027 CSoR 27(a) Sand 0.40 Cum 1061.00 1 Cum
B.LABOUR :
LAB-00011 CSoR I -11 1st class Mason 0.167 Nos 630.00 1 Each
LAB-00091 CSoR II - 35 2nd class Mason 0.167 Nos 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (both men&women) 5.60 Nos 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 3139.57
C.MACHINERY :
HIR-00009& LAB-
CSoR 9 Batching plant 0.50 cum 1.333 hours 233.80 1 hour
00325
HIR-00144 CSoR 9 Crew charges 1.333 hours 473.50 1 hour
HIR-00040& LAB-
CSoR 40 Needle vibrator 40mm ( petrol ) 1.333 hours 38.20 1 hour
00352
HIR-00174 CSoR 40 Crew charges 1.333 hours 220.90 1 hour
Add MA on crew charges 0.20 925.64
MAT-00332,
M - 189(a),(b) Water(including for curing) 1.20 kl 116.00 1 kl
MAT-00333
Rate per 1 cum

a) COLUMNS :
un supported height up to 3.66 m
Rate for other Floors F1 F2 F3 F4
Rate as above 8815.46 8815.46 8815.46 8815.46
Hire charges of centering and scaffolding 249.00 249.00 249.00 249.00
Labour charges 1871.00 2058.00 2245.00 2432.00
Add for MAA @ 20% 374.20 411.60 449.00 486.40
Lift charges of materials(Manual) 0.00 313.96 627.91 941.87
Add for MAA @ 20% 0.00 62.79 125.58 188.37
Rate per 1 cum 11309.66 11910.81 12511.96 13113.11
Overheads&Contractors Profit @13.615% 1539.81 1621.66 1703.50 1785.35
Rate per 1 cum 12849.47 13532.47 14215.46 14898.46
CIVIL DATA 2020-21 : Page-708

Say 12849 13532 14215 14898

b) LINTELS :
Rate for other Floors F1 F2 F3 F4
Rate as above 8815.46 8815.46 8815.46 8815.46
Hire charges of centering and scaffolding 826.00 826.00 826.00 826.00
Labour charges 1332.00 1465.00 1598.00 1732.00
Add for MAA @ 20% 266.40 293.00 319.60 346.40
Lift charges of materials(Manual) 0.00 313.96 627.91 941.87
Add for MAA @ 20% 0.00 62.79 125.58 188.37
Rate per 1 cum 11239.86 11776.21 12312.56 12850.11
Overheads&Contractors Profit @13.615% 1530.31 1603.33 1676.36 1749.54
Rate per 1 cum 12770.17 13379.54 13988.92 14599.65
Say 12770 13380 13989 14600

C) SIDE WALLS
i) 115mm thick side walls
Cost of M 25 design mix 0.12 cum 8815.46 1.00 cum

Rate for other Floors F1 F2 F3


Rate as above 1013.78 1013.78 1013.78
Hire charges of centering and scaffolding 472.00 472.00 472.00
Labour charges 510.00 561.00 612.00
Add for MAA @ 20% 102.00 112.20 122.40
Lift charges of materials(Manual) 0.00 36.10 72.21
Add for MAA @ 20% 0.00 7.22 14.44
Rate per 10 sqm 2097.78 2202.30 2306.83
Overheads&Contractors Profit @13.615% 285.61 299.84 314.07
Rate per 1 sqm 2383.39 2502.14 2620.90
Say 2383 2502 2621

i) 125mm thick side walls


Cost of M 25 design mix 0.13 cum 8815.46 1.00 cum

Rate for other Floors F1 F2 F3


Rate as above 1101.93 1101.93 1101.93
Hire charges of centering and scaffolding 472.00 472.00 472.00
Labour charges 510.00 561.00 612.00
Add for MAA @ 20% 102.00 112.20 122.40
Lift charges of materials(Manual) 0.00 39.24 78.49
Add for MAA @ 20% 0.00 7.85 15.70
Rate per 10 sqm 2185.93 2294.23 2402.52
CIVIL DATA 2020-21 : Page-709

Overheads&Contractors Profit @13.615% 297.61 312.36 327.1


Rate per 1 sqm 2483.54 2606.59 2729.62
Say 2484 2607 2730

i) 150mm thick side walls


Cost of M 25 design mix 0.15 cum 8815.46 1.00 cum

Rate for other Floors F1 F2 F3 F4


Rate as above 1322.32 1322.32 1322.32 1322.32
Hire charges of centering and scaffolding 472.00 472.00 472.00 472.00
Labour charges 510.00 561.00 612.00 663.00
Add for MAA @ 20% 102.00 112.20 122.40 132.60
Lift charges of materials(Manual) 0.00 47.09 94.19 141.28
Add for MAA @ 20% 0.00 9.42 18.84 28.26
Rate per 10 sqm 2406.32 2524.03 2641.74 2759.46
Overheads&Contractors Profit @13.615% 327.62 343.65 359.67 375.7
Rate per 1 sqm 2733.94 2867.68 3001.41 3135.16
Say 2734 2868 3001 3135

i) 175mm thick side walls


Cost of M 25 design mix 0.18 cum 8815.46 1.00 cum

Rate for other Floors F1 F2 F3 F4


Rate as above 1542.71 1542.71 1542.71 1542.71
Hire charges of centering and scaffolding 472.00 472.00 472.00 472.00
Labour charges 510.00 561.00 612.00 663.00
Add for MAA @ 20% 102.00 112.20 122.40 132.60
Lift charges of materials(Manual) 0.00 47.09 94.19 141.28
Add for MAA @ 20% 0.00 9.42 18.84 28.26
Rate per 10 sqm 2626.71 2744.42 2862.13 2979.84
Overheads&Contractors Profit @13.615% 357.63 373.65 389.68 405.71
Rate per 1 sqm 2984.34 3118.07 3251.81 3385.55
Say 2984 3118 3252 3386
ii) 200mm thick side walls
Cost of M 25 design mix 0.20 cum 8815.46 1.00 cum

Rate for other Floors F1 F2 F3


Rate as above 1763.09 1763.09 1763.09
Hire charges of centering and scaffolding 472.00 472.00 472.00
Labour charges 510.00 561.00 612.00
Add for MAA @ 20% 102.00 112.20 122.40
Lift charges of materials(Manual) 0.00 62.79 125.58
CIVIL DATA 2020-21 : Page-710

Add for MAA @ 20% 0.00 12.56 25.12


Rate per 10 sqm 2847.09 2983.64 3120.19
Overheads&Contractors Profit @13.615% 387.63 406.22 424.81
Rate per 1 sqm 3234.72 3389.86 3545.00
Say 3235 3390 3545
ii) 230mm thick side walls
Cost of M 25 design mix 0.23 cum 8815.46 1.00 cum

Rate for other Floors F1 F2 F3


Rate as above 2027.56 2027.56 2027.56
Hire charges of centering and scaffolding 472.00 472.00 472.00
Labour charges 510.00 561.00 612.00
Add for MAA @ 20% 102.00 112.20 122.40
Lift charges of materials(Manual) 0.00 72.21 144.42
Add for MAA @ 20% 0.00 14.44 28.88
Rate per 10 sqm 3111.56 3259.41 3407.26
Overheads&Contractors Profit @13.615% 423.64 443.77 463.9
Rate per 1 sqm 3535.20 3703.18 3871.16
Say 3535 3703 3871

Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with cement content of 380 kgs per 1 cum of concrete using weigh batch
with 20mm size graded machine crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry including
23 BLD-CSTN-3-19 conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site, centering using casurina ballies, bamboos, wooden reapers,
wood posts, wall plates etc., including all operational, incidental and labour charges such as weigh batching, machine mixing, lifting of concrete manually, laying
vibrating, curing , overheads & contractors profit etc., complete but excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402)

RCC SLABS , BEAMS :


A.MATERIALS :
Cement 380.00 Kgs 4220.00 1000 Kgs
20mm HBG graded metal 0.80 Cum 1759.31 1 Cum
MAT-00027 CSoR 27(a) Sand 0.40 Cum 1061.00 1 Cum
B.LABOUR :
LAB-00011 CSoR I -11 1st class Mason 0.067 Nos 630.00 1 Each
LAB-00091 CSoR II - 35 2nd class Mason 0.133 Nos 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (both men&women) 3.077 Nos 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 1732.78
C.MACHINERY :
HIR-00009& LAB-
CSoR 9 Batching plant 0.50 cum 0.308 hours 233.80 1 hour
00325
HIR-00144 CSoR 9 Crew charges 0.308 hours 473.50 1 hour
CIVIL DATA 2020-21 : Page-711

HIR-00040& LAB-
CSoR 40 Needle vibrator 40mm ( petrol ) 0.308 hours 38.20 1 hour
00352
HIR-00174 CSoR 40 Crew charges 0.308 hours 220.90 1 hour
Add MA on crew charges 0.20 213.88
MAT-00332,
M - 189(a),(b) Water(including for curing) 1.20 kl 116.00 1 kl
MAT-00333
Rate per 1 cum

A) BEAMS :
un supported height up to 3.66 m
Rate for other Floors F1 F2 F3 F4
Rate as above 5994.41 5994.41 5994.41 5994.41
Hire charges of centering and scaffolding 1458.00 1458.00 1458.00 1458.00
Labour , lift charges for scaffolding 1569.00 1726.00 1883.00 2040.00
Add for MAA @ 20% 313.80 345.20 376.60 408.00
Lift charges of materials(Manual) 0.00 173.28 346.56 519.83
Add for MAA @ 20% 0.00 34.66 69.31 103.97
Rate for 1 cum 9335.21 9731.54 10127.88 10524.21
Overheads&Contractors Profit @13.615% 1270.99 1324.95 1378.91 1432.87
Rate per 1 cum 10606.20 11056.49 11506.79 11957.08
Say 10606 11056 11507 11957

B) RCC SLABS :
a) Roof Slabs 125mm thick :
un supported height up to 3.66 m
Rate for Design mix M 25 0.125 Cum 5994.41 1 Cum

Rate for other Floors F1 F2 F3 F4


Rate as above 749.30 749.30 749.30 749.30
Hire charges of centering and scaffolding 165.00 165.00 165.00 165.00
Labour , lift charges for scaffolding 186.00 205.00 223.00 242.00
Add for MAA @ 20% 37.20 41.00 44.60 48.40
Lift charges of materials(Manual) 0.00 21.66 43.32 64.98
Add for MAA @ 20% 0.00 4.33 8.66 13.00
Rate per 1 sqm 1137.50 1186.29 1233.88 1282.68
Overheads&Contractors Profit @13.615% 154.87 161.51 167.99 174.64
Rate per 1 sqm 1292.37 1347.80 1401.87 1457.32
Say 1292 1348 1402 1457

b) Roof Slabs 150mm thick :


Rate for Design mix M 25 0.15 Cum 5994.41 1 Cum
CIVIL DATA 2020-21 : Page-712

un supported height up to 3.66 m


Rate for other Floors F1 F2 F3 F4
Rate as above 899.16 899.16 899.16 899.16
Hire charges of centering and scaffolding 165.00 165.00 165.00 165.00
Lift charges for scaffolding 186.00 205.00 223.00 242.00
Add for MAA @ 20% 37.20 41.00 44.60 48.40
Lift charges of materials(Manual) 0.00 25.99 51.98 77.98
Add for MAA @ 20% 0.00 5.20 10.40 15.60
Rate per 1 sqm 1287.36 1341.35 1394.14 1448.13
Overheads&Contractors Profit @13.615% 175.27 182.63 189.81 197.16
Rate per 1 sqm 1462.63 1523.98 1583.95 1645.29
Say 1463 1524 1584 1645
CIVIL DATA 2020-21 : Page-713

c) Roof Slabs 175mm thick :


Rate for Design mix M 25 0.175 Cum 5994.41 1 Cum

un supported height up to 3.66 m


Rate for other Floors F1 F2 F3
Rate as above 1049.02 1049.02 1049.02
Hire charges of centering and scaffolding 170.00 170.00 170.00
Labour , lift charges for scaffolding 193.00 212.00 232.00
Add for MAA @ 20% 38.60 42.40 46.40
Lift charges of materials(Manual) 0.00 30.32 60.65
Add for MAA @ 20% 0.00 6.06 12.13
Rate per 1 sqm 1450.62 1509.81 1570.20
Overheads&Contractors Profit @13.615% 197.5 205.56 213.78
Rate per 1 sqm 1648.12 1715.37 1783.98
Say 1648 1715 1784

d) Roof Slabs 200mm thick :


Rate for Design mix M 25 0.20 Cum 5994.41 1 Cum

for un supported height of 3.66 m


Rate for other Floors F1 F2 F3
Rate as above 1198.88 1198.88 1198.88
Hire charges of centering and scaffolding 170.00 170.00 170.00
Labour, lift charges for scaffolding 193.00 212.00 232.00
Add for MAA @ 20% 38.60 42.40 46.40
Lift charges of materials(Manual) 0.00 34.66 69.31
Add for MAA @ 20% 0.00 6.93 13.86
Rate per 1 sqm 1600.48 1664.87 1730.46
Overheads&Contractors Profit @13.615% 217.91 226.67 235.6
Rate per 1 sqm 1818.39 1891.54 1966.06
Say 1818 1892 1966

Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with minimum cement content of 380 kgs per 1 cum of concrete using weig
/ mixer with 20mm size graded machine crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry inclu
1 and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site, centering using steel scaffolding pipes , jack props , wall
plates , brackets , steel centering plates etc. including all operational, incidental and labour charges such as weigh batching, machine mixing, lifting of concrete
laying concrete, vibrating, curing , overheads & contractors profit etc., complete but excluding cost of steel and its fabrication charges for finished item of work (APSS N

A) BEAMS :
un supported height up to 4.27 m
Rate for other Floors F1
CIVIL DATA 2020-21 : Page-714

Rate as above 5994.41


Hire charges of centering and scaffolding 2179.00
Extra staging (Hire) 363.15
Labour , lift charges for scaffolding 2027.00
Extra staging (Labour) 337.82
Add for MAA @ 20% 472.96
Lift charges of materials(Manual) 0.00
Add for MAA @ 20% 0.00
Rate for 1 cum 11374.34
Overheads&Contractors Profit @13.615% 1548.62
Rate per 1 cum 12922.96
Say 12923

A) BEAMS :
un supported height up to 7.32 m
Rate for other Floors F1
Rate as above 5994.41
Hire charges of centering and scaffolding 2179.00
Extra staging (Hire) 2178.91
Labour , lift charges for scaffolding 2027.00
Extra staging (Labour) 2026.92
Add for MAA @ 20% 810.78
Lift charges of materials(Manual) 0.00
Add for MAA @ 20% 0.00
Rate for 1 cum 15217.02
Overheads&Contractors Profit @13.615% 2071.8
Rate per 1 cum 17288.82
Say 17289

a) Roof Slabs 125mm thick :


un supported height up to 4.27 m
Rate for Design mix M 25 0.125 Cum 5994.41 1 Cum

Rate for other Floors F1


Rate as above 749.30
Hire charges of centering and scaffolding 247.00
Extra staging (Hire) 41.17
Labour , lift charges for scaffolding 241.00
Extra staging (Labour) 40.17
Add for MAA @ 20% 56.23
Lift charges of materials(Manual) 0.00
Add for MAA @ 20% 0.00
CIVIL DATA 2020-21 : Page-715

Rate per 1 sqm 1374.88


Overheads&Contractors Profit @13.615% 187.19
Rate per 1 sqm 1562.07
Say 1562

b) Roof Slabs 150mm thick :


Rate for Design mix M 25 0.15 Cum 5994.41 1 Cum

un supported height up to 7.32 m


Rate for other Floors F1
Rate as above 899.16
Hire charges of centering and scaffolding 247.00
Extra staging (Hire) 246.99
Lift charges for scaffolding 241.00
Extra staging (Labour) 240.99
Add for MAA @ 20% 96.40
Lift charges of materials(Manual) 0.00
Add for MAA @ 20% 0.00
Rate per 1 sqm 1971.54
Overheads&Contractors Profit @13.615% 268.43
Rate per 1 sqm 2239.97
Say 2240
CIVIL DATA 2020-21 : Page-716

Supply and placing of the Design Mix Concrete M 25 grade corresponding to IS 456 with cement content of 380 kgs per 1 cum of concrete using weigh b
mixer with 20mm size graded machine crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry inclu
and conveyance of all materials like cement, fine aggregate (sand), coarse aggregate, water etc., to site, centering using casurina ballies , bamboos , wooden reapers ,
24 BLD-CSTN-3-19
wood posts , wall plates etc., for 60cm wide sun-shades 7.5cm thick at fixed end and 5cm thick at free end with an average thickness of 6.25cm including all op
incidental and labour charges such as weigh batching, machine mixing, lifting of concrete manually, laying concrete, curing, overheads & contractors profit complete
excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402, 403 & 903)

A.MATERIALS :
Cement 380.00 Kgs 4220.00 1000 Kgs
20mm HBG graded metal 0.80 Cum 1759.31 1 Cum
MAT-00027 CSoR 27(a) Sand 0.40 Cum 1061.00 1 Cum
B.LABOUR :
LAB-00011 CSoR I -11 1st class Mason 0.067 Nos 630.00 1 Each
LAB-00091 CSoR II - 35 2nd class Mason 0.133 Nos 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (both men&women) 3.077 Nos 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 1732.78

C.MACHINERY :
HIR-00009& LAB-
CSoR 9 Batching plant 0.50 cum 0.308 hours 233.80 1 hour
00325
HIR-00144 CSoR 9 Crew charges 0.308 hours 473.50 1 hour
Add MA on crew charges 0.20 145.84
MAT-00332,
M - 189(a),(b) Water(including for curing) 1.20 kl 116.00 1 kl
MAT-00333
Rate per 1 cum

Cost of RCC M 25 design mix 0.0375 cum 5901.00 1 cum

Rate for other Floors F1 F2 F3


Rate as above 221.29 221.29 221.29
Hire charges of centering and scaffolding 97.80 97.80 97.80
Labour , lift charges for scaffolding 122.40 134.40 147.00
Add for MAA @ 20% 24.48 26.88 29.40
Lift charges of materials(Manual) 0.00 6.50 13.00
Add for MAA @ 20% 0.00 1.30 2.60
Rate per 1 RM 465.97 488.17 511.08
Overheads&Contractors Profit @13.615% 63.44 66.46 69.58
Rate per 1 RM 529.41 554.63 580.66
Say 529 555 581
CIVIL DATA 2020-21 : Page-717

Brick masonry for panel walls in superstructure with CM (1:8) prop: (Cement : Sand) using common burnt clay bricks of class as per Table- I of IS:1077-1
Modular or traditional size 23 x 11 x 7 cms from approved source having minimum crushing strength of 40 Kg/Sqcm. including cost and conveyance of all materials lik
25 BLD-CSTN-5-5
screened sand, bricks, water etc., to site, labour charges, like mixing cement mortar, scaffolding charges, constructing masonry, lift charges, curing, etc.,and ove
contractors profit complete for finished item of work. (APSS No. 501 & 504).
Unit : 1cum
A.MATERIALS :
Cement 36.00 Kgs 4220.00 1000 Kgs
MAT-00721 BMT-A.01 Common burnt clay bricks 23x11x7cms 512 Nos 7874.10 1000 Nos
MAT-00029 CSoR 28 Fine aggregate ( Sand ) 0.20 cu.m. 1156.00 1 cu.m.
B.LABOUR :
LAB-00011 CSoR I -11 1st class mason 0.24 Nos. 630.00 1 Each
LAB-00091 CSoR II - 35 2nd class mason 0.56 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (Unskilled) 1.89 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 1459.85
water charges @ 1% 0.01 6166.48
Rate per 1 cum

a Up to basement
Rate as worked out above 1.00 Cum 6228.14 1 Cum
Overheads&Contractors Profit @13.615% 0.13615 6228.14
Rate per 1 cum
Say

b) Superstructure :
i) un supported height up to 3.66 m
Rate for other Floors F1 F2 F3 F4
Rate as worked out above 6228.14 6228.14 6228.14 6228.14
Hire charges for Access Scaffolding 46.87 46.87 46.87 46.87
Labour charges for scaffolding 367.91 526.87 685.74 844.65
Add for MAA @ 20% 73.58 105.37 137.15 168.93
Lift charges ( Page 131 of Std. Data ) 0.00 145.99 291.97 437.96
Add for MAA @ 20% 0.00 29.20 58.39 87.59
Rate per 1 cum 6716.51 7082.45 7448.27 7814.15
Overheads&Contractors Profit @13.615% 914.45 964.27 1014.08 1063.9
Rate per 1 cum 7630.96 8046.72 8462.35 8878.05
Say 7631 8047 8462 8878
CIVIL DATA 2020-21 : Page-718

Reinforced Brick Masonry for partition walls (11.0 cm thick) in CM (1:4) prop. (Cement : Sand) using common burnt clay bricks of class as per Table- I of IS:1
Non- Modular or traditional size 23 x 11 x 7 cms from approved source having minimum crushing strength of 40 Kg/Sq.cm and placing 2 Nos. of 6mm M.S plain rod
26 BLD-CSTN-5-12 third layer with free ends of the reinforcement pegged into mortar joints of main brick walls where applicable including cost and conveyance of all materials like cem
sand, bricks, water etc., to site, all operational, incidental charges such as labour charges for mixing cement mortar, scaffolding charges, constructing masonry, lift
curing, etc., and overheads & contractors profit but excluding cost of steel and its fabrication charges complete for finished item of work. (APSS No. of 501 & 509)

Unit - 10sqm
A.MATERIALS :
MAT-00721 BMT-A.01 Common burnt clay bricks 23x11x7cms 512 Nos. 7874.10 1000 Nos.
Cement 72.00 Kgs 4220.00 1000 Kgs
MAT-00029 CSoR 28 Fine aggregate ( Sand ) 0.21 cu.m. 1156.00 1 cu.m.
B.LABOUR :
LAB-00011 CSoR I -11 1st class mason 0.60 Nos. 630.00 1 Each
LAB-00091 CSoR II - 35 2nd class mason 0.60 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (Unskilled) 2.75 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 2160.75
water charges @ 1% 0.01 7171.04
Rate per 10 sqm
Rate per 1 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 724.27 724.27 724.27 724.27
Hire charges for Access Scaffolding 10.78 10.78 10.78 10.78
Labour charges for scaffolding 84.62 121.18 157.72 194.27
Add for MAA @ 20% 16.92 24.24 31.54 38.85
Lift charges ( Page 131 of Std. Data ) 0.00 21.61 43.22 64.82
Add for MAA @ 20% 0.00 4.32 8.64 12.96
Rate per 1 sqm 836.59 906.40 976.18 1045.96
Overheads&Contractors Profit @13.615% 113.90 123.41 132.91 142.41
Rate per 1 sqm 950.49 1029.81 1109.09 1188.37
Say 950 1030 1109 1188
CIVIL DATA 2020-21 : Page-719

Masonry work in CM(1:6) prop (Cement : Sand) in superstructure with fly ash cement / lime solid blocks of size 290mm x 225mm x 140mm from approved sour
minimum crushing strength of 50 Kg/Sqcm. including cost and conveyance of all materials like cement, sand, fly ash cement / lime solid blocks, water etc., to si
27 BLD-CSTN-5-17
charges, like mixing cement mortar, scaffolding charges, constructing masonry, lift charges, curing, overheads and contrctor profit etc., complete for finished item of wo
No. 501 & 504).
Unit = 1 Cum
A.MATERIALS
MAT-00756 BMT-A-10 No of blocks required for 1 Cum of Masonry 110 Nos 37139.34 1000 Nos
Cement 24.00 Kgs 4220.00 1000 Kgs
MAT-00029 CSoR 28 Fine aggregate ( Sand ) 0.10 cu.m. 1156.00 1 cu.m.
B .LABOUR
LAB-00011 CSoR I -11 1st class mason 0.24 Nos. 630.00 1 Each
LAB-00091 CSoR II - 35 2nd class mason 0.56 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (Unskilled) 1.89 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 1459.85
water charges @ 1% 0.01 6054.03
Rate per 1 cum

a) Rate for Foundation , Basement , Compound wall


Rate as above 1.00 cum 6114.57 1 cum
Overheads&Contractors Profit @13.615% 0.13615 6114.57
Rate per 1 cum
say

b) Superstructure :
i) un supported height up to 3.66 m
Rate for other Floors F1 F2 F3 F4
Rate as worked out above 6114.57 6114.57 6114.57 6114.57
Hire charges for Access Scaffolding 47.91 47.91 47.91 47.91
Labour charges for scaffolding 376.09 538.58 700.98 863.42
Add for MAA @ 20% 75.22 107.72 140.20 172.68
Lift charges ( Page 131 of Std. Data ) 0.00 145.99 291.97 437.96
Add for MAA @ 20% 0.00 29.20 58.39 87.59
6613.79 6983.96 7354.02 7724.13
Overheads&Contractors Profit @13.615% 900.47 950.87 1001.25 1051.64
Rate per 1 cum 7514.26 7934.83 8355.27 8775.77
Say 7514 7935 8355 8776
CIVIL DATA 2020-21 : Page-720

Reinforced Masonry for partition walls (100 mm thick) in CM (1:4) prop. (Cement : Sand) using fly ash cement / lime solid blocks of size 290mm x 100mm
having minimum compressive strength of 50 Kg/Sq.cmand placing 2 Nos. of 6mm M.S plain rods in every third layer with free ends of the reinforcement pegged into mo
28 BLD-CSTN-5-12 of main brick walls where applicable including cost and conveyance of all materials like cement, steel, sand, fly ash cement / lime solid blocks, water etc., to site, all op
incidental charges such as labour charges for mixing cement mortar, scaffolding charges, constructing masonry, lift charges, curing, etc., and overheads & contractors
excluding cost of steel and its fabrication charges complete for finished item of work. (APSS No. of 509)

Unit - 10sqm
A.MATERIALS :
MAT-00759 BMT-A-13 Flyash lime solid blocks 247 Nos. 17173.04 1000 Nos.
Cement 36.00 Kgs 4220.00 1000 Kgs
MAT-00029 CSoR 28 Fine aggregate ( Sand ) 0.10 cu.m. 1156.00 1 cu.m.
B.LABOUR :
LAB-00011 CSoR I -11 1st class mason 0.60 Nos. 630.00 1 Each
LAB-00091 CSoR II - 35 2nd class mason 0.60 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (Unskilled) 2.75 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 2160.75
water charges @ 1% 0.01 7102.16
Rate per 10 sqm
Rate per 1 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 717.32 717.32 717.32 717.32
Hire charges for Access Scaffolding 10.78 10.78 10.78 10.78
Labour charges for scaffolding 84.62 121.18 157.72 194.27
Add for MAA @ 20% 16.92 24.24 31.54 38.85
Lift charges ( Page 131 of Std. Data ) 0.00 21.61 43.22 64.82
Add for MAA @ 20% 0.00 4.32 8.64 12.96
Rate per 1 sqm 829.64 899.45 969.23 1039.01
Overheads&Contractors Profit @13.615% 112.96 122.46 131.96 141.46
Rate per 1 sqm 942.60 1021.91 1101.19 1180.47
Say 943 1022 1101 1180
CIVIL DATA 2020-21 : Page-721

Plain Cement Concrete (1:3:6) nominal mix using 20mm size graded machine crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Par
BLD-CSTN-3-10 8) from approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity including cost and conveyance of all materials like cement, fine aggregate(sand
29
& 11 aggregate, water etc. to site including all charges for machine mixing, hire charges of concrete mixer, centering charges, laying concrete in position, curing etc., & lift
and overheads & contractors profit for bed blocks & hold fasts for finished item of work. (APSS No. 402)
Unit : 1cum
A.MATERIALS :
HBG 20mm size metal 0.90 Cum 1759.31 1 Cum
MAT-00027 CSoR 27(a) Sand 0.45 Cum 1061.00 1 Cum
Cement 220.00 Kgs 4220.00 1 MT
MAT-00332,
M - 189(a),(b) Water ( including for curing ) 1.20 Kl 116.00 1 Kl
MAT-00333
B.MACHINERY :
HIR-00016& LAB-
CSoR 16 Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)capacity 1.00 hour 188.10 1 hour
00329
HIR-00150 CSoR 16 Crew Charges 1.00 hour 306.80 1 hour
Add MA on crew charges 0.20 306.80
C.LABOUR :
LAB-00011 CSoR I -11 1st class mason 0.10 Nos. 630.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (Unskilled) 1.39 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 792.75
Rate per 1 cum

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 4635.99 4635.99 4635.99 4635.99
Hire charges of centering and scaffolding 67.00 67.00 67.00 67.00
Lift charges for scaffolding 363.00 399.30 435.60 471.90
Add for MAA @ 20% 72.60 79.86 87.12 94.38
Lift charges ( Page 131 of Std. Data ) 0.00 79.28 158.55 237.83
Add for MAA @ 20% 0.00 15.86 31.71 47.57
Rate per 1 cum 5138.59 5277.29 5415.97 5554.67
Overheads&Contractors Profit @13.615% 699.62 718.50 737.38 756.27
Rate per 1 cum 5838.21 5995.79 6153.35 6310.94
say 5838 5996 6153 6311
CIVIL DATA 2020-21 : Page-722

Plain Cement Concrete (1:2:4) using 20mm size graded machine crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Pa
approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity including cost and conveyance of all materials like cement, fine aggregate(sand), coarse a
30 BLD-CSTN-3-11
water etc. to site including all charges for machine mixing, hire charges of concrete mixer, laying concrete in position, curing etc., & lift charges , and overheads & c
profit for septic tank bed, in sunken slabs for finished item of work. (APSS No. 402)
Unit : 1cum
A.MATERIALS :
HBG 20mm size metal 0.90 Cum 1759.31 1 Cum
MAT-00027 CSoR 27(a) Sand 0.45 Cum 1061.00 1 Cum
Cement 330.00 Kgs 4220.00 1 MT
MAT-00332,
M - 189(a),(b) Water ( including for curing ) 1.20 Kl 116.00 1 Kl
MAT-00333
B.MACHINERY :
HIR-00016& LAB-
CSoR 16 Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)capacity 1.00 hour 188.10 1 hour
00329
HIR-00150 CSoR 16 Crew Charges 1.00 hour 306.80 1 hour
Add MA on crew charges 0.20 306.80
C.LABOUR :
LAB-00011 CSoR I -11 1st class mason 0.10 Nos. 630.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (Unskilled) 1.39 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 792.75
Rate per 1 cum

Rate for other Floors F1 F2 F3 F4


Cost of M 20 nominal mix 5100.19 5100.19 5100.19 5100.19
Lift charges ( Page 131 of Std. Data ) 0.00 79.28 158.55 237.83
Add for MAA @ 20% 0.00 15.86 31.71 47.57
Rate per 1 cum 5100.19 5195.32 5290.45 5385.58
Overheads&Contractors Profit @13.615% 694.39 707.34 720.29 733.25
Rate per 1 cum 5794.58 5902.66 6010.74 6118.83
Say 5795 5903 6011 6119
CIVIL DATA 2020-21 : Page-723

Plain Cement Concrete M 20 nominal mix using 20mm size graded machine crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1
from approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity including cost and conveyance of all materials like cement, fine aggregate(sand), coarse a
31 BLD-CSTN-3-11
water etc. to site including all charges centering, labour charges such as weigh batching, machine mixing, hire charges of concrete mixer, centering charges, laying c
position, curing etc., & lift charges , and overheads & contractors profit for steps for finished item of work. (APSS No. 402)

Unit : 1cum
A.MATERIALS :
HBG 20mm size metal 0.90 Cum 1759.31 1 Cum
MAT-00027 CSoR 27(a) Sand 0.45 Cum 1061.00 1 Cum
Cement 330.00 Kgs 4220.00 1000 Kgs
MAT-00332,
M - 189(a),(b) Water ( including for curing ) 1.20 Kl 116.00 1 Kl
MAT-00333
B.MACHINERY :
HIR-00016& LAB-
CSoR 16 Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)capacity 1.00 hour 188.10 1 hour
00329
HIR-00150 CSoR 16 Crew Charges 1.00 hour 306.80 1 hour
Add MA on crew charges 0.20 306.80
HIR-00040& LAB-
CSoR 40 Needle vibrator 40mm ( petrol ) 1.00 hours 38.20 1 hour
00352
HIR-00174 CSoR 40 Crew charges 1.00 hours 220.90 1 hour
Add MA on crew charges 0.20 220.90
C.LABOUR :
LAB-00011 CSoR I -11 1st class mason 0.100 Nos. 630.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (Unskilled) 1.390 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 792.75
Rate per 1 cum

Rate for other Floors F1 F2 F3 F4


Cost of M 20 nominal mix 5403.47 5403.47 5403.47 5403.47
Hire charges of centering and scaffolding 67.00 67.00 67.00 67.00
Lift charges for scaffolding 363.00 399.30 435.60 471.90
Add for MAA @ 20% 72.60 79.86 87.12 94.38
Lift charges ( Page 131 of Std. Data ) 0.00 79.28 158.55 237.83
Add for MAA @ 20% 0.00 15.86 31.71 47.57
Rate per 1 cum 5906.07 6044.76 6183.45 6322.14
Overheads&Contractors Profit @13.615% 804.11 822.99 841.88 860.76
Rate per 1 cum 6710.18 6867.75 7025.33 7182.90
Say 6710 6868 7025 7183
CIVIL DATA 2020-21 : Page-724

Reinforced Cement Concrete M 20 nominal mix using 12mm size hard granite machine crushed graded metal (coarse aggregate - as per IS 383 - 1970 and IS 2386
Part 8) from approved quarry, using a minimum quantity of 330 kgs. of cement per 1 cum of concrete using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity including
32 BLD-CSTN-3-13 - Aconveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site including centering, shuttering, labour charges such as weigh
machine mixing, hire charges of concrete mixer, laying concrete, lift charges, curing etc., and overheads & contractors profit complete for finished item of work (APSS N
403) for sill slabs.

A.MATERIALS :
Cement 330.00 Kgs 4220.00 1000 Kgs
12mm HBG graded metal 0.90 Cum 1527.30 1 Cum
MAT-00027 CSoR 27(a) Sand 0.45 Cum 1061.00 1 Cum
B.LABOUR :
LAB-00011 CSoR I -11 1st class Mason 0.133 Nos 630.00 1 Each
LAB-00091 CSoR II - 35 2nd class Mason 0.267 Nos 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (both Men & Women) 3.60 Nos 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 2124.65
C.MACHINERY :
HIR-00016& LAB-
CSoR 16 Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)capacity 1.00 hour 188.10 1 hour
00329
HIR-00150 CSoR 16 Crew Charges 1.00 hour 306.80 1 hour
Add MA on crew charges 0.20 306.80
MAT-00332,
M - 189(a),(b) Water(including for curing) 1.20 kl 116.00 1 kl
MAT-00333
Basic cost per 1 cum

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 6489.65 6489.65 6489.65 6489.65
Hire charges of centering and scaffolding 67.00 67.00 67.00 67.00
Lift charges for scaffolding 363.00 399.30 435.60 471.90
Add for MAA @ 20% 72.60 79.86 87.12 94.38
Lift charges ( Page 131 of Std. Data ) 0.00 212.46 424.93 637.39
Add for MAA @ 20% 0.00 42.49 84.99 127.48
Rate per 1 cum 6992.25 7290.77 7589.29 7887.81
Overheads&Contractors Profit @13.615% 952.00 992.64 1033.28 1073.92
Rate per 1 cum 7944.25 8283.41 8622.57 8961.73
Say 7944 8283 8623 8962
CIVIL DATA 2020-21 : Page-725

Reinforced Cement Concrete M 20 nominal mix using 12mm size hard granite machine crushed graded metal (coarse aggregate - as per IS 383 - 1970 and IS 2386
Part 8) from approved quarry, using a minimum quantity of 330 kgs. of cement per 1 cum of concrete using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity including
33 BLD-CSTN-3-13 conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site including centering, shuttering, labour charges such as weigh
machine mixing, hire charges of concrete mixer, laying concrete, lift charges, curing etc., and overheads & contractors profit complete for finished item of work (APSS N
403) for platforms and shelves.

A.MATERIALS :
Cement 330.00 Kgs 4220.00 1000 Kgs
12mm HBG graded metal 0.90 Cum 1527.30 1 Cum
MAT-00027 CSoR 27(a) Sand 0.45 Cum 1061.00 1 Cum
B.LABOUR :
LAB-00011 CSoR I -11 1st class Mason 0.067 Nos 630.00 1 Each
LAB-00091 CSoR II - 35 2nd class Mason 0.133 Nos 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (both men&women) 2.500 Nos 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 1429.86
C.MACHINERY :
HIR-00016& LAB-
CSoR 16 Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)capacity 1.00 hour 188.10 1 hour
00329
HIR-00150 CSoR 16 Crew Charges 1.00 hour 306.80 1 hour
Add MA on crew charges 0.20 306.80
MAT-00332,
M - 189(a),(b) Water(including for curing) 1.20 kl 116.00 1 kl
MAT-00333
Basic cost per 1 cum

a) 50mm thick platforms / lofts:


Cost of M 20 nominal mix 0.05 cum 5655.91 1 cum
Rate per 1 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 282.80 282.80 282.80 282.80
Hire charges of centering and scaffolding
82.50 82.50 82.50 82.50
(50% of roof slab)
Lift charges for scaffolding 93.00 102.50 111.50 121.00
Add for MAA @ 20% 18.60 20.50 22.30 24.20
Lift charges ( Page 131 of Std. Data ) 0.00 7.15 14.30 21.45
Add for MAA @ 20% 0.00 1.43 2.86 4.29
Rate per 1 sqm 476.90 496.87 516.25 536.23
Overheads&Contractors Profit @13.615% 64.93 67.65 70.29 73.01
Rate per 1 sqm 541.82 564.52 586.54 609.24
Say 542 565 587 609
CIVIL DATA 2020-21 : Page-726
CIVIL DATA 2020-21 : Page-727

b) 25mm thick shelves :


Cost of M 20 nominal mix 0.025 cum 5655.91 1 cum
Rate per 1 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 141.40 141.40 141.40 141.40
Hire charges of centering and scaffolding (25% of roof
41.25 41.25 41.25 41.25
slab)
Lift charges for scaffolding 46.50 51.25 55.75 60.50
Add for MAA @ 20% 9.30 10.25 11.15 12.10
Lift charges ( Page 131 of Std. Data ) 0.00 3.57 7.15 10.72
Add for MAA @ 20% 0.00 0.71 1.43 2.14
Rate per 1 sqm 238.45 248.44 258.13 268.12
Overheads&Contractors Profit @13.615% 32.46 33.82 35.14 36.50
Rate per 1 sqm 270.91 282.26 293.27 304.62
Say 271 282 293 305

Providing Thermo Mechanically Treated (TMT) (Fe 500 / Fe 500 D grade as per IS 1786-1979) of different diameters for RCC works including labour ch
BLD-CSTN-4.2
straightening, cutting, bending to required sizes and shapes, placing in position with cover blocks of approved materials and size and tying and lap-splicing with bindi
& Amendment
34 18 SWG, forming grills for reinforcement work as per approved designs and drawings, including cost and conveyance of steel bars, including all wastages such as
in SoR 2011-12
couplings, chairs, spacer bars including cost and conveyance of binding wire, cover blocks and all incidental, operational, labour charges such as cutting, bending,
page No. 392
position, tying etc., and overheads & contractors profit complete for finished item of work.( APSS No.126)

Unit - 1 MT
a) Material
TMT bars including 5% for overlaps and wastage 1.05 MT 64000.00 1 MT
MAT-00003 CSoR 3 Binding wire 6.00 Kgs 70.00 1 Kgs
Labour for cutting , bending , shifting to site , tying and
b)
placing in position
LAB-00001 CSoR I - 1 1st class Blacksmith / Barbender 3.00 Nos. 750.00 1 Each
LAB-00002 CSoR I - 2 2nd class Blacksmith / Barbender 7.00 Nos. 590.00 1 Each
LAB-00120, LAB-
CSoR III - 3,4 Mazdoor(Unskilled) 10.00 Nos. 525.00 1 Each
00121
Add for MAA @ 20% 0.20 11630.00

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 81576.00 81576.00 81576.00 81576.00
Lift charges ( Page 131 of Std. Data )
0.00 1163.00 2326.00 3489.00
Add for MAA @ 20% 0.00 232.60 465.20 697.80
Rate per 1 MT 81576.00 82971.60 84367.20 85762.80
Overheads&Contractors Profit @13.615% 11106.57 11296.58 11486.59 11676.61
Rate per 1 MT 92682.57 94268.18 95853.79 97439.41
CIVIL DATA 2020-21 : Page-728

Say 92683 94268 95854 97439

Providing Mild steel (MS) steel bars (Fe 250 grade as per IS 432) of different diameters including labour charges for straightening, cutting, bending to required
BLD-CSTN-4.2
shapes, placing in position with cover blocks of approved materials and size and tying and lap-splicing with binding wire of 18 SWG, forming grills for reinforcement wo
& Amendment
35 approved designs and drawings, including cost and conveyance of steel bars, including all wastages such as overlaps, couplings, chairs, spacer bars including
in SoR 2011-12
conveyance of binding wire, cover blocks and all incidental, operational, labour charges such as cutting, bending, placing in position, tying etc., and overheads & co
page No. 392
profit complete for finished item of work.( APSS No.126)
Unit - 1 MT
a) Material
Mild steel bars including 5% for overlaps and wastage 1.05 MT 63000.00 1 MT
MAT-00003 CSoR 3 Binding wire 6.00 Kgs 70.00 1 Kgs
Labour for cutting, bending, shifting to site, tying and
b)
placing in position
LAB-00001 CSoR I - 1 1st class Blacksmith / Barbender 3.00 Nos. 750.00 1 Each
LAB-00002 CSoR I - 2 2nd class Blacksmith / Barbender 7.00 Nos. 590.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(Unskilled) 10.00 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 11630.00

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 80526.00 80526.00 80526.00 80526.00
Lift charges ( Page 131 of Std. Data )
0.00 1163.00 2326.00 3489.00
Add for MAA @ 20% 0.00 232.60 465.20 697.80
Rate per 1 MT 80526.00 81921.60 83317.20 84712.80
Overheads&Contractors Profit @13.615% 10963.61 11153.63 11343.64 11533.65
Rate per 1 MT 91489.61 93075.23 94660.84 96246.45
Say 91490 93075 94661 96246
CIVIL DATA 2020-21 : Page-729

As per Ornamental ceiling plastering 12mm thick single coat in CM (1:5) using screened sand including cost and conveyance of all materials like cement, sand, water e
36 amendment in and all operational, incidental charges on materials and including cost of all labour charges for mixing mortar, finishing, curing as directed by Engineer-in-charge
SoR 2016-17 overheads & contractors profit complete for finished item of work.(SS 901,903 & 904)
Unit : 10 sqm
A.MATERIALS :
Cement 43.20 Kgs 4220.00 1000 Kgs
MAT-00029 CSoR 28 Fine aggregate ( Sand ) 0.15 cu.m. 1156.00 1 cu.m.
B.LABOUR :
LAB-00001 CSoR I - 1 1st Class Mason 0.45 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 2nd Class Mason 1.05 Nos. 565.00 1 Each
LAB-00120, LAB-
CSoR III - 3,4 Mazdoor (Unskilled) 2.80 Nos. 525.00 1 Each
00121
Add for MAA @ 20% 0.20 2346.75
water charges @ 1% 0.01 3171.80
Rate per 10 sqm
Rate per 1 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 320.35 320.35 320.35 320.35
Hire charges for Access Scaffolding 2.57 2.57 2.57 2.57
Labour charges for scaffolding 16.94 24.04 31.13 38.23
Add for MAA @ 20% 3.39 4.81 6.23 7.65
Lift charges ( Page 131 of Std. Data ) 0.00 23.47 46.94 70.40
Add for MAA @ 20% 0.00 4.69 9.39 14.08
Rate per 1 sqm 343.25 379.93 416.61 453.28
Overheads&Contractors Profit @13.615% 46.73 51.73 56.72 61.71
Rate per 1 sqm 389.98 431.66 473.33 514.99
Say 390 432 473 515
CIVIL DATA 2020-21 : Page-730

Plastering 12mm thick in two coats using screened sand with base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in CM (1:4) with dubara sponge finishing
cost and conveyance of all materials like cement, sand, water etc., to site and all operational, incidental charges on materials and including cost of all labour charges
37 BLD-CSTN-8-10
mortar, finishing, scaffolding, lift charges, curing, including cutting grooves as directed by Engineer - in - charge etc., and overheads & contractors profit complete fo
item of work. (SS 901,903 & 904)
Unit : 10 sqm
A.MATERIALS :
Base coat in CM(1:6) , 8mm thick
Cement 26.40 Kgs 4220.00 1000 Kgs
MAT-00029 CSoR 28 Fine aggregate (Sand) 0.11 Cum 1156.00 1 Cum
Top coat in CM(1:4) , 4mm thick
Cement 14.40 Kgs 4220.00 1000 Kgs
MAT-00029 CSoR 28 Fine aggregate (Sand) 0.04 Cum 1156.00 1 Cum
B.LABOUR :
LAB-00001 CSoR I - 1 1st Class Mason 0.63 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 2nd Class Mason 1.47 Nos. 565.00 1 Each
LAB-00120, LAB-
CSoR III - 3,4 Mazdoor (Unskilled) 3.90 Nos. 525.00 1 Each
00121
Add for MAA @ 20% 0.20 3274.95
water charges @ 1% 0.01 4275.52
Rate per 10 sqm
Rate per 1 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 431.83 431.83 431.83 431.83
Hire charges for Access Scaffolding 1.08 1.08 1.08 1.08
Labour charges for scaffolding 8.47 12.12 15.77 19.43
Add for MAA @ 20% 1.69 2.42 3.15 3.89
Lift charges ( Page 131 of Std. Data ) 0.00 32.75 65.50 98.25
Add for MAA @ 20% 0.00 6.55 13.10 19.65
Rate per 1 sqm 443.07 486.75 530.43 574.13
Overheads&Contractors Profit @13.615% 60.32 66.27 72.22 78.17
Rate per 1 sqm 503.39 553.02 602.65 652.30
Say 503 553 603 652
CIVIL DATA 2020-21 : Page-731

As per Plastering 12mm thick single coat in CM(1:5) using screened sand including cost and conveyance of all materials like cement, sand, water etc., to site and all op
38 amendment in incidental charges on materials and including cost of all labour charges for mixing mortar, finishing, curing as directed by Engineer-in-charge etc., and overheads & c
SoR 2016-17 profit complete for finished item of work (SS 901,903 & 904)
Unit : 10 sqm
A.MATERIALS :
Cement 43.20 Kgs 4220.00 1000 Kgs
MAT-00029 CSoR 28 Fine aggregate ( Sand ) 0.15 cu.m. 1156.00 1 cu.m.
B.LABOUR :
LAB-00001 CSoR I - 1 1st Class Mason 0.45 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 2nd Class Mason 1.05 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (Unskilled) 2.80 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 2346.75
water charges @ 1% 0.01 3171.80
Rate per 10 sqm
Rate per 1 sqm

a) up to basement
Rate as worked out above 1.00 sqm 320.35 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 320.35
Rate per 1 sqm
Say

b) Superstructure
Rate for other Floors F1 F2 F3 F4
Rate as worked out above 320.35 320.35 320.35 320.35
Hire charges for Access Scaffolding 1.08 1.08 1.08 1.08
Labour charges for scaffolding 8.47 12.12 15.77 19.43
Add for MAA @ 20% 1.69 2.42 3.15 3.89
Lift charges ( Page 131 of Std. Data ) 0.00 32.75 65.50 98.25
Add for MAA @ 20% 0.00 6.55 13.10 19.65
Rate per 1 sqm 331.59 375.27 418.95 462.65
Overheads&Contractors Profit @13.615% 45.15 51.09 57.04 62.99
Rate per 1 sqm 376.74 426.36 475.99 525.64
Say 377 426 476 526
CIVIL DATA 2020-21 : Page-732

Plastering 20mm thick in two coats using screened sand with base coat of 16mm thick in CM(1:6) and top coat of 4mm thick in CM(1:4) with dubara sponge finishing
cost and conveyance of all materials like cement, sand, water etc., to site and all operational, incidental charges on materials and including cost of all labour charges
39 BLD-CSTN-8-9
mortar, finishing, scaffolding, lift charges, curing, including cutting grooves as directed by Engineer-in-charge etc., and overheads & contractors profit complete for fini
of work .(SS 901,903 & 904)

Unit : 10 sqm
A.MATERIALS :
Base coat in CM(1:6) , 16mm thick
Cement 43.20 Kgs 4220.00 1000 Kgs
MAT-00029 CSoR 28 Fine aggregate (Sand) 0.18 Cum 1156.00 1 Cum
Top coat in CM(1:4) , 4mm thick
Cement 14.40 Kgs 4220.00 1000 Kgs
MAT-00029 CSoR 28 Fine aggregate (Sand) 0.04 Cum 1156.00 1 Cum
B.LABOUR :
LAB-00001 CSoR I - 1 1st Class Mason 0.63 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 2nd Class Mason 1.47 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (Unskilled) 3.90 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 3274.95
water charges @ 1% 0.01 4427.33
Rate per 10 sqm
Rate per 1 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 447.16 447.16 447.16 447.16
Hire charges for Access Scaffolding 1.08 1.08 1.08 1.08
Labour charges for scaffolding 8.47 12.12 15.77 19.43
Add for MAA @ 20% 1.69 2.42 3.15 3.89
Lift charges ( Page 131 of Std. Data ) 0.00 32.75 65.50 98.25
Add for MAA @ 20% 0.00 6.55 13.10 19.65
Rate per 1 sqm 458.40 502.08 545.76 589.46
Overheads&Contractors Profit @13.615% 62.41 68.36 74.31 80.25
Rate per 1 sqm 520.81 570.44 620.07 669.71
Say 521 570 620 670
CIVIL DATA 2020-21 : Page-733

As per Plastering 20mm thick single coat in CM(1:5) using screened sand including cost and conveyance of all materials like cement, sand, water etc., to site and all op
40 amendment in incidental charges on materials and including cost of all labour charges for mixing mortar, finishing, curing as directed by Engineer-in-charge etc., and overheads & c
SoR 2016-17 profit complete for finished item of work for basement. (SS 901,903 & 904)
Unit : 10 sqm
A.MATERIALS :
Cement 60.48 Kgs 4220.00 1000 Kgs
MAT-00029 CSoR 28 Fine aggregate (Sand) 0.21 Cum 1156.00 1 Cum
B.LABOUR :
LAB-00001 CSoR I - 1 1st Class Mason 0.45 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 2nd Class Mason 1.05 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (Unskilled) 2.80 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 2346.75
water charges @ 1% 0.01 3314.09
Rate per 10 sqm
Rate per 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 334.72
Rate per 1 sqm
Say Say
CIVIL DATA 2020-21 : Page-734

Providing impervious coat to exposed RCC roof slab surfaces to required slopes with CM (1:3) prop. using screened sand 20mm thick (average) mixed with integr
water proofing admixture confirming to IS: 2645-2003 manufactured by reputed manufacturers as approved by Engineer-in-charge at 100ml per one bag of cement, laid
41 BLD-CSTN-10-25slab when it is green, finished smooth with a floating coat of neat cement and thread lining at regular intervals of 45cmx45cm including cost and conveyance of all mat
cement, sand, water proofing compound, water etc., to site, operational, incidental, and labour charges for mixing mortar, laying, lift charges, rendering smooth and thre
curing including rounding off junctions of wall and slab etc., and overheads & contractors profit complete for finished item of work. (APSS No. 901 & 903).

Unit : 10 sqm
A.MATERIALS :
Cement 100.80 Kgs 4220.00 1000 Kgs
MAT-00029 CSoR 28 Fine aggregate (Sand) 0.21 Cum 1156.00 1 Cum
MAT-05372 BMT-H.85 Integral cement water proofing admixture 0.20 Ltrs 205.00 1.00 Ltrs
B.LABOUR :
LAB-00001 CSoR I - 1 1st Class Mason 0.66 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 2nd Class Mason 1.54 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (Unskilled) 3.70 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 3228.40
water charges @ 1% 0.01 4583.22
Rate per 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 4629.05 4629.05 4629.05 4629.05
Lift charges ( Page 131 of Std. Data ) 0.00 322.84 645.68 968.52
Add for MAA @ 20% 0.00 64.57 129.14 193.70
4629.05 5016.46 5403.86 5791.27
Overheads&Contractors Profit @13.615% 630.24 682.99 735.74 788.48
Rate per 10 sqm 5259.29 5699.45 6139.60 6579.75
Rate per 1 sqm 525.93 569.94 613.96 657.98
Say 526 570 614 658
CIVIL DATA 2020-21 : Page-735

Providing impervious coat to exposed RCC roof slab surfaces of sump , sump side wall,sump bottom slab,in side of septic tank , in sunken slabs etc. to
slopes with CM (1:3) prop. using screened sand 12mm thick mixed with integral cement water proofing admixture confirming to IS: 2645-2003 manufactured b
As per
manufacturers as approved by Engineer-in-charge at 100ml per one bag of cement, laid over roof slab when it is green, finished smooth with a floating coat of neat ce
42 amendment in
thread lining at regular intervals of 45cmx45cm where ever necessary including cost and conveyance of all materials like cement, sand, water proofing compound, wat
SoR 2016-17
site, operational, incidental, and labour charges for mixing mortar, laying, lift charges, rendering smooth and thread lining, curing including rounding off junctions of wal
etc., and overheads & contractors profit complete for finished item of work. (APSS No. 901 & 903).

A.MATERIALS :
Cement 72.00 Kgs 4220.00 1000 Kgs
MAT-00029 CSoR 28 Fine aggregate (Sand) 0.15 Cum 1156.00 1 Cum
MAT-05372 BMT-H.85 Integral cement water proofing admixture 0.144 Ltrs 205.00 1.00 Ltrs
B.LABOUR :
LAB-00001 CSoR I - 1 1st Class Mason 0.45 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 2nd Class Mason 1.05 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (Unskilled) 2.80 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 2346.75
water charges @ 1% 0.01 3322.86
Rate per 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 3356.09 3356.09 3356.09 3356.09
Lift charges ( Page 131 of Std. Data ) 0.00 234.68 469.35 704.03
Add for MAA @ 20% 0.00 46.94 93.87 140.81
3356.09 3637.70 3919.31 4200.92
Overheads&Contractors Profit @13.615% 456.93 495.27 533.61 571.96
Rate per 10 sqm 3813.02 4132.97 4452.92 4772.88
Rate per 1 sqm 381.30 413.30 445.29 477.29
Say 381 413 445 477
CIVIL DATA 2020-21 : Page-736

RCM facia 50mm thick in CM(1:3) using screened sand for drop walls, fins with rabbit wire mesh & nomianl reinforcement as directred by Engineer - In - Charge wi
sponge finishing,including cost and conveyance of all materials to site, operationals &incidental,cost and conveyance of cement,wire mesh,water
43 BLD-CSTN-8-11
site,centering,scaffolding and form work,lift charges etc., and overheads & contractors profit complete for finished item of work but excluding cost of steel and its f
charges for finished item of work(APSS NO.403&903)
Unit : 10 sqm
A)MATERIALS
MAT-00894 BMT-F.28 Rabbit wire mesh 13.30 sqm 21.00 1 sqm
Cement for CM(1:3) 25mm thick 120.00 Kgs 4220.00 1000 Kgs
MAT-00029 CSoR 28 Fine aggregate (Sand) for CM(1:3) 25mm thick 0.26 cu.m. 1156.00 1 cu.m.
Dry Cement for lumps 50.00 Kgs 4220.00 1000 Kgs
12mm plastering 2 coats in CM(1:3) both sides
Cement for 2 coats platering in CM(1:3) 144.00 Kgs 4220.00 1000 Kgs
MAT-00029 CSoR 28 Fine aggregate (Sand) for CM(1:3) 25mm thick 0.30 cu.m. 1156.00 1 cu.m.

Excluding TMT steel/mild steel & binding wire


B) LABOUR CHARGES
LAB-00001 CSoR I - 1 1st Class Mason 8.00 Nos. 630.00 1 Each
LAB-00016 CSoR I -16 Operator concrete mixer 1.00 Nos. 615.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (Unskilled) 10.00 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 10905.00
C)Machinery :
HIR-00016& LAB-
CSoR 16 Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)capacity 2.00 hours 188.10 1 hours
00329
HIR-00150 CSoR 16 Crew charges 2.00 hours 306.80 1 hours
Add MA on crew charges 0.20 306.80
water charges @ 1% 0.01 16450.26
Rate per 10 sqm
Rate per 1 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 1661.48 1661.48 1661.48 1661.48
Hire charges for Access Scaffolding 1.08 1.08 1.08 1.08
Labour charges for scaffolding 8.47 12.12 15.77 19.43
Add for MAA @ 20% 1.69 2.42 3.15 3.89
Lift charges ( Page 131 of Std. Data ) 0.00 109.05 218.10 327.15
Add for MAA @ 20% 0.00 21.81 43.62 65.43
Rate per 1 sqm 1672.72 1807.96 1943.20 2078.46
Overheads&Contractors Profit @13.615% 227.74 246.15 264.57 282.98
CIVIL DATA 2020-21 : Page-737

Rate per 1 sqm 1900.46 2054.11 2207.77 2361.44


Say 1900 2054 2208 2361

Flooring with polished shahabad / Tandur stone slabs of 15 mm to 18 mm thick set over a base coat of CM (1:8) , 12mm thick using screened sand over alread
bed / RCC roof slab including neat cement slurry of honey like consistency spread @ 3.3 Kgs per sqm and jointed with neat cement to full depth including cost and co
44 BLD-CSTN-9-1
of all materials like cement, sand, water, flooring stones etc. complete including all labour charges like dressing of flooring stones to the required size, mixing of ceme
laying, lift charges , cost of base coat, water charges etc., and overheads & contractors profit complete for finished item of work. (APSS No.703 & 701)

Unit = 10 sqm.
A. MATERIALS:

MAT-00772 BMT-B-05 Polished shahabad stone 15 to 18mm thick 11.00 sqm 2053.39 10 sqm

Cement for CM (1:8) proportion for base coat 21.60 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
Cement for pointing 20.00 Kgs 4220.00 1000 Kgs
MAT-00029 CSoR 28 Sand for CM(1:8) 0.12 Cum 1156.00 1 Cum
B .LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 3.10 Nos 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 1.10 Nos 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(un skilled) 0.86 Nos 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 3026.00
Add water charges 1% 0.01 6343.46
Rate for 10 sqm

Rate for other floors F1 F2 F3 F4


Rate as worked out above 6406.90 6406.90 6406.90 6406.90
Lift charges ( Page 131 of Std. Data ) 0.00 302.60 605.20 907.80
Add for MAA @ 20% 0.00 60.52 121.04 181.56
6406.90 6770.02 7133.14 7496.26
Overheads&Contractors Profit @13.615% 872.30 921.74 971.18 1020.62
Rate per 10 sqm 7279.20 7691.76 8104.32 8516.88
Rate per 1 sqm 727.92 769.18 810.43 851.69
Say 728 769 810 852
CIVIL DATA 2020-21 : Page-738

Flooring with Polished black Kadapa slabs minimum of 15 mm thick of size 0.457m x 0.457m set over a base coat of CM (1:8) , 12mm thick using screened
already laid CC bed / RCC roof slab including neat cement slurry of honey like consistency spread @ 3.3 Kgs per sqm and jointed with neat cement to full depth inclu
45 BLD-CSTN-9-1
and conveyance of all materials like cement, sand, water, flooring stones etc. complete including all labour charges like dressing of flooring stones to the required size,
cement mortar, laying, lift charges , cost of base coat, water charges etc., and overheads & contractors profit complete for finished item of work. (APSS No.703 & 701)

Unit = 10 sqm.
A. MATERIALS:

MAT-00773 BMT-B-06 Polished black Kadapa slabs minimum of 15mm thick 11.00 sqm 1889.44 10 sqm

Cement for CM (1:8) proportion for base coat 21.60 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
Cement for pointing 20.00 Kgs 4220.00 1000 Kgs
MAT-00029 CSoR 28 Sand for CM(1:8) 0.12 Cum 1156.00 1 Cum
B .LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 3.10 Nos 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 1.10 Nos 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(un skilled) 0.86 Nos 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 3026.00
Add water charges 1% 0.01 6163.12
Rate for 10 sqm

Rate for other floors F1 F2 F3 F4


Rate as worked out above 6224.75 6224.75 6224.75 6224.75
Lift charges ( Page 131 of Std. Data ) 0.00 302.60 605.20 907.80
Add for MAA @ 20% 0.00 60.52 121.04 181.56
6224.75 6587.87 6950.99 7314.11
Overheads&Contractors Profit @13.615% 847.50 896.94 946.38 995.82
Rate per 10 sqm 7072.25 7484.81 7897.37 8309.93
Rate per 1 sqm 707.22 748.48 789.74 830.99
Say 707 748 790 831
CIVIL DATA 2020-21 : Page-739

Flooring with non-skid red or white full body Ceramic floor tiles of size 300 mm x 300 mm and thickness between 7-8 mm 1st quality conforming to IS:13711,
IS:13630 (Parts 1 to 15) of any colour and finish in all shades and designs as approved by Engineer-in-charge, set over base coat of cement mortar (1:8), 12mm th
46 BLD-CSTN-9-6 screened sand over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency spread @ 3.3 Kgs per sqm & jointed neatly with whi
paste to full depth mixed with pigment of matching shade, including cost of all materials like cement, screened sand , water and tiles etc., and overheads & contrac
complete for finished item of work. (APSS No.701 & 707)
Unit = 10 sqm.
A. MATERIALS:
MAT-00785 BMT-C.01 Ceramic tiles 7 to 8mm thick (300mm x 300mm) 10.50 sqm 370.00 1 sqm
Cement for CM(1:8) proportion for base coat 21.60 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
MAT-01638 BMS-W.68 White Cement 2.00 Kgs 31.00 1 Kg
MAT-00029 CSoR 28 Sand for CM(1:8) 0.12 Cum 1156.00 1 Cum
B .LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 0.96 Nos 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 2.24 Nos 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(un skilled) 3.30 Nos 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 3602.90
Add water charges 1% 0.01 8639.61
Rate for 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 8726.01 8726.01 8726.01 8726.01
Lift charges ( Page 131 of Std. Data ) 0.00 360.29 720.58 1080.87
Add for MAA @ 20% 0.00 72.06 144.12 216.17
8726.01 9158.36 9590.70 10023.05
Overheads&Contractors Profit @13.615% 1188.05 1246.91 1305.77 1364.64
Rate per 10 sqm 9914.06 10405.27 10896.47 11387.69
Rate per 1 sqm 991.41 1040.53 1089.65 1138.77
Say 991 1041 1090 1139

Flooring with soluble salt porcelain vitrified tiles screen printed and polished of size 600 x 600 mm and thickness between 8-10 mm 1st quality conforming to
IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all shades and designs with borders and design as per the approved flooring pattern as directed by the En
-Charge, laying tiles using spacers of 2mm thick, set over a base coat of CM (1:8) prop. 12mm thick using screened sand over CC bed already laid or RCC r
47 BLD-CSTN-9-5 including neat cement slurry of honey like consistancy spread @ 3.3 kgs per sqm. and jointed neately with white cement paste to full depth mixed with pigment of
shade including cost and conveyance of all materials like cement, sand, water, tiles, white cement etc., to site (excluding cost of C.C. bed) including cost of base
all labour charges for mixing of cement mortar, laying tiles to required slope as directed by the Engineer- in-charge etc.,and overheads & contractors profit com
finished item of work. (APSS No.701 & 707)
Unit = 10 sqm.
A. MATERIALS:
CIVIL DATA 2020-21 : Page-740

MAT-00790 BMT-C.06 Vitrified tiles 8 to 10mm thick of size 600mm x 600mm 10.50 sqm 425.00 1 sqm
Cement for CM(1:8)proportion for base coat 21.60 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
MAT-01638 BMS-W.68 White Cement 6.00 Kgs 31.00 1 Kg
MAT-00029 CSoR 28 Sand for CM(1:8) 0.12 Cum 1156.00 1 Cum
B .LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 0.96 Nos 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 2.24 Nos 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(un skilled) 3.30 Nos 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 3602.90
Add water charges 1% 0.01 9341.11
Rate for 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 9434.52 9434.52 9434.52 9434.52
Lift charges ( Page 131 of Std. Data ) 0.00 360.29 720.58 1080.87
Add for MAA @ 20% 0.00 72.06 144.12 216.17
9434.52 9866.87 10299.22 10731.57
Overheads&Contractors Profit @13.615% 1284.51 1343.37 1402.24 1461.10
Rate per 10 sqm 10719.03 11210.24 11701.46 12192.67
Rate per 1 sqm 1071.90 1121.02 1170.15 1219.27
Say 1072 1121 1170 1219

Flooring with non-skid Double charged / multi charged stain free full body porcelain vitrified tiles with double layer pigment of size 600 x 600 mm and
between 8-10 mm 1st quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all shades and designs with borders and design a
approved flooring pattern as directed by the Engineer-In -Charge, laying tiles using spacers of 2mm thick, set over a base coat of CM (1:8) prop. 12mm thick using
48 BLD-CSTN-9-5 sand over CC bed already laid or RCC roof slab , including neat cement slurry of honey like consistancy spread @ 3.3 kgs per sqm. and jointed neately with whit
paste to full depth mixed with pigment of matching shade including cost and conveyance of all materials like cement, sand, water, tiles, white cement etc., to site (
cost of C.C. bed) including cost of base coat and all labour charges for mixing of cement mortar, laying tiles to required slope as directed by the Engineer- i
etc.,and overheads & contractors profit complete for finished item of work. (APSS No.701 & 707)

Unit = 10 sqm.
A. MATERIALS:
MAT-00793 BMT-C.09 Vitrified tiles 8 to 10mm thick of size 600mm x 600mm 10.50 sqm 612.00 1 sqm
Cement for CM(1:8)proportion for base coat 21.60 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
MAT-01638 BMS-W.68 White Cement 6.00 Kgs 31.00 1 Kg
MAT-00029 CSoR 28 Sand for CM(1:8) 0.12 Cum 1156.00 1 Cum
B .LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 0.96 Nos 630.00 1 Each
CIVIL DATA 2020-21 : Page-741

LAB-00002 CSoR I - 2 Mason 2nd class 2.24 Nos 565.00 1 Each


LAB-00120,
CSoR III - 3,4 Mazdoor(un skilled) 3.30 Nos 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 3602.90
Add water charges 1% 0.01 11304.61
Rate for 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 11417.66 11417.66 11417.66 11417.66
Lift charges ( Page 131 of Std. Data ) 0.00 360.29 720.58 1080.87
Add for MAA @ 20% 0.00 72.06 144.12 216.17
11417.66 11850.01 12282.35 12714.70
Overheads&Contractors Profit @13.615% 1554.51 1613.38 1672.24 1731.11
Rate per 10 sqm 12972.17 13463.39 13954.59 14445.81
Rate per 1 sqm 1297.22 1346.34 1395.46 1444.58
Say 1297 1346 1395 1445

Providing window sills with 16 mm to 18 mm thick high polished granite stone slabs black colour as approved by the Engineer-in-Charge set over base coat
mortar (1:8) , 20mm thick using screened sand over CC bed already laid including neat grey cement slurry of honey like consistency spread @ 3.3 Kg per sqm and join
49 BLD-CSTN-9-7 with white cement paste mixed with pigment of matching shade to full depth including cost and conveyance of all materials like cement , sand , water , granite slabs etc
site and all operational, incidental labour & lift charges, half rounding the edge , polishing charges, cost of base coat and overheads & contractors profit complete for fini
of work (S.S.701 & special)
Unit = 10 sqm.
A. MATERIALS:
MAT-00778 BMT-B-11 High polished granite slabs black 16 to 18mm thick 10.50 sqm 2100.00 1 sqm
Cement for CM(1:8) for base coat 36.00 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
MAT-01638 BMS-W.68 White cement for jointing 6.00 Kgs 31.00 1 Kg
MAT-00029 CSoR 28 Sand for CM(1:8) 0.20 Cum 1156.00 1 Cum
B .LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 3.00 Nos 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 1.00 Nos 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(un skilled) 8.00 Nos 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 6655.00
Machine cutting charges 43.48 RM 19.00 1 RM
Half rounding the edges 43.48 RM 350.00 1 RM
Add for MAA @ 20% 0.20 6417.65
Add water charges 1% 0.01 48072.03
Rate for 10 sqm

Rate for other Floors F1 F2 F3 F4


CIVIL DATA 2020-21 : Page-742

Rate as worked out above 48552.75 48552.75 48552.75 48552.75


Lift charges ( Page 131 of Std. Data ) 0.00 665.50 1331.00 1996.50
Add for MAA @ 20% 0.00 133.10 266.20 399.30
48552.75 49351.35 50149.95 50948.55
Overheads&Contractors Profit @13.615% 6610.46 6719.19 6827.92 6936.65
Rate per 10 sqm 55163.21 56070.54 56977.87 57885.20
Rate per 1 sqm 5516.32 5607.05 5697.79 5788.52
Say 5516 5607 5698 5789

Flooring with 16 mm to 18 mm thick high polished granite stone slabs other than black and regular colours (i.e. of shades like paradiso / bala flower / copper
red / lavender blue) with borders and design as per the pattern approved by the Engineer-in-Charge of length not less than 2.43 mts set over base coat of cement mo
20mm thick using screened sand over CC bed already laid or RCC roof slab including neat grey cement slurry of honey like consistency spread @ 3.3 Kg per sqm a
1 BLD-CSTN-9-7
neatly with white cement paste mixed with pigment of matching shade to full depth including cost and conveyance of all materials like cement , sand , water , granite sla
work site and all operational, incidental labour & lift charges, polishing charges, cost of base coat and overheads & contractors profit complete for finished item of work
& special)
Unit = 10 sqm.
A. MATERIALS:
High polished granite slabs other than black 16 to 18mm
MAT-00778 BMT-B-11 10.50 sqm 2500.00 1 sqm
thick
Cement for CM(1:8) for base coat 36.00 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
MAT-01638 BMS-W.68 White cement for jointing 6.00 Kgs 31.00 1 Kg
MAT-00029 CSoR 28 Sand for CM(1:8) 0.20 Cum 1156.00 1 Cum
B .LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 3.00 Nos 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 1.00 Nos 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(un skilled) 8.00 Nos 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 6655.00
Add water charges 1% 0.01 34944.38
Rate for 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 35293.82 35293.82 35293.82 35293.82
Lift charges ( Page 131 of Std. Data ) 0.00 665.50 1331.00 1996.50
Add for MAA @ 20% 0.00 133.10 266.20 399.30
35293.82 36092.42 36891.02 37689.62
Overheads&Contractors Profit @13.615% 4805.25 4913.98 5022.71 5131.44
Rate per 10 sqm 40099.07 41006.40 41913.73 42821.06
Rate per 1 sqm 4009.91 4100.64 4191.37 4282.11
Say 4010 4101 4191 4282
CIVIL DATA 2020-21 : Page-743

Granolithic Concrete flooring 20 mm thick with (1:1:2), using 6mm to 12 mm size hard granite machine crushed metal and screened sand laid over CC bed alrea
50 BLD-CSTN-9-13 RCC roof slab, in alternate panels of size not exceeding 1.50 m x 1.50 m, using glass strips and finishing the top surface to required smoothness and slopes and thr
including cost of all materials like cement, metal sand and water and overheads & contractors profit complete for finished item of work. (APSS No.701 & 710)

Unit : 10sqm
A.MATERIALS :
6mm to 12mm HBG Metal 0.17 Cum 1527.30 1 Cum
Cement 120.00 Kgs 4220.00 1000 Kgs
MAT-00027 CSoR 27(a) Sand 0.085 Cum 1061.00 1 Cum
B. LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 1.25 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 0.06 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (unskiled) 3.00 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 2396.40
Add water charges 1% 0.01 3731.91
Rate per 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 3769.23 3769.23 3769.23 3769.23
Lift charges ( Page 131 of Std. Data ) 0.00 239.64 479.28 718.92
Add for MAA @ 20% 0.00 47.93 95.86 143.78
3769.23 4056.79 4344.36 4631.93
Overheads&Contractors Profit @13.615% 513.18 552.33 591.48 630.64
Rate per 10 sqm 4282.41 4609.12 4935.84 5262.57
Rate per 1 sqm 428.24 460.91 493.58 526.26
Say 428 461 494 526
CIVIL DATA 2020-21 : Page-744

Flooring with chequered Cement Concrete heavy duty tiles conforming to IS: 13801 using aggregates, cement, pigments of size 300mm x 300 mm and thicknes
of any shades as approved by Engineer - In - Charge set over base coat of cement mortar (1:6), 12 mm thick using screened sand over CC bed already laid or RCC
51 BLD-CSTN-9-4
including neat cement slurry of honey like consistency spread @ 3.3 kgs per sqm and jointed with neat white cement to full depth mixed with pigment of matchi
including cost and conveyance of all materials like cement, sand, water and tiles etc.,and overheads & contractors profit complete for finished item of work.

Unit : 10sqm
A.MATERIALS :
MAT-00835 BMT-D.07 Chequred tiles 25mm thick 10.50 sqm 325.00 1 sqm
Cement for CM(1:6) proportion for base coat 28.80 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
MAT-01638 BMS-W.68 White cement for jointing & pointing 6.00 Kgs 31.00 1.00 Kgs
MAT-00029 CSoR 28 Sand for CM(1:6) proportion 0.12 Cum 1156.00 1 Cum
B. LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 0.96 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 2.24 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (unskiled) 3.30 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 3602.90
Add water charges 1% 0.01 8321.50
Rate per 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 8404.71 8404.71 8404.71 8404.71
Lift charges ( Page 131 of Std. Data ) 0.00 360.29 720.58 1080.87
Add for MAA @ 20% 0.00 72.06 144.12 216.17
8404.71 8837.06 9269.41 9701.75
Overheads&Contractors Profit @13.615% 1144.30 1203.17 1262.03 1320.89
Rate per 10 sqm 9549.01 10040.23 10531.44 11022.64
Rate per 1 sqm 954.90 1004.02 1053.14 1102.26
Say 955 1004 1053 1102

Supply and application of epoxy flooring of light green or light blue colour in Operation Theatres and labour rooms - SIKA Epoxy seamless joint free finish
52 thickness and anti slip & water washable chemical resistance durable and non particle shedding with attractive finishing including cost and conveyance of all materia
labour charges, overheads and contractor profit etc., complete for finished item of work in all floors.
MAT-00734 BMT-C.48 Rate as per SoR 1 sqm 1862.00 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 1862.00
Rate per 1 sqm
Say
CIVIL DATA 2020-21 : Page-745

Providing and laying of precast concrete blocks for paving of M-40 grade and thickness not less than 80 mm for medium traffic areas conforming to IS 15658:2
RBR-CCPV- 13 shapes and designs as per the manufacturer's specification including cost and conveyanace cost of all materilas like cement, sand water and Pavers etc., Complete per
53
(i) and techinical specification clause 1504 MORD including cost and conveyance of all materials and all labour charges, overheads and contractor profit etc., complete fo
item of work.
Unit: 1 sqm Taking out put 225.00
a) Labour
LAB-00002 CSoR I - 2 Mason 2nd class 18.00 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (unskiled) 8.00 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 14370.00
b) Machinery
HIR-000076 CSoR 10 Water Tanker 6 Kl capacity 2.00 Hour 806.00 1 hour
c) Material
i) High Strength cement concrete inter lcoking designer
MAT-00842 BMT-D.14 225.00 Sqm 550.00 1 Sqm
pavers tile 80mm thick
(ii) Edge blocks 60 m x 2 120.00 RM 10.00 1 RM
MAT-00028 CSoR 27(b) (iii) Sand as per Table 1500.5 7.23 Cum 916.00 1 Cum
Bed = 603x75x 0.03 = 6.75 cum
Joints = 60x0.08 = 0.48 cum
MAT-00332,
M - 189(a),(b) (iv)water for wetting of sand bed 3.00 Kl 116.00 1 Kl
MAT-00333
Cost for 225 sqm = a+b+c
Rate per 1 Sqm
Overheads&Contractors Profit @13.615% 0.13615 670.12

Say
CIVIL DATA 2020-21 : Page-746

Providing polished shahabad / Tandur stone slabs of 15 mm to 18 mm thick in single piece as specified set over a base coat of CM (1:5) , 12mm thick using
sand over already laid CC bed / RCC roof slab including neat cement slurry of honey like consistency spread @ 3.3 Kgs per sqm and jointed with neat cement to
54 including cost and conveyance of all materials like cement, sand, water, flooring stones etc. complete including all labour charges like dressing of flooring stones to the
size, flat nosing the edges, mixing of cement mortar, laying, lift charges , cost of base coat, water charges etc., and overheads & contractors profit complete for finishe
work for treads and risers. (APSS No.703 & 701)
a) BLD-CSTN-9-1 Treads of 0.30m wide :
Unit = 10 sqm.
A. MATERIALS:
MAT-00772 BMT-B-05 Polished shahabad stone 15 to 18mm thick 11.00 sqm 2053.39 10 sqm
Cement for CM (1:5) proportion for base coat 34.56 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
Cement for jointing 20.00 Kgs 4220.00 1000 Kgs
MAT-00029 CSoR 28 Sand for CM(1:5) 0.12 Cum 1156.00 1 Cum
B .LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 3.10 Nos 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 1.10 Nos 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(un skilled) 0.86 Nos 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 3026.00
LAB-00507 BMM-V.13 Flat nosing the edges 33.33 RM 55.00 1 RM
Add for MAA @ 20% 0.20 733.26
Add water charges 1% 0.01 8377.95
Rate for 10 sqm

Rate for other floors F1 F2 F3 F4


Rate as worked out above 8461.73 8461.73 8461.73 8461.73
Lift charges ( Page 131 of Std. Data ) 0.00 302.60 605.20 907.80
Add for MAA @ 20% 0.00 60.52 121.04 181.56
8461.73 8824.85 9187.97 9551.09
Overheads&Contractors Profit @13.615% 1152.07 1201.50 1250.94 1300.38
Rate per 10 sqm 9613.80 10026.35 10438.91 10851.47
Rate per 1 sqm 961.38 1002.64 1043.89 1085.15
Say 961 1003 1044 1085
CIVIL DATA 2020-21 : Page-747

b) BLD-CSTN-9-23 Risers of 0.15m height :


Unit = 10 sqm
A.MATERIALS :
MAT-00772 BMT-B-05 Cost of shahabad stone slabs 11.00 sqm 2053.39 10 sqm
MAT-00029 CSoR 28 Sand for CM(1:5) base coat 0.12 cum 1156.00 1 cum
Cement for CM(1:5) base coat 34.56 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
B.LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 0.96 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 2.24 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(unskilled) 3.10 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 3497.90
Add water charges 1% 0.01 6880.03
Rate for 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 6948.83 6948.83 6948.83 6948.83
Lift charges ( Page 131 of Std. Data ) 0.00 349.79 699.58 1049.37
Add for MAA @ 20% 0.00 69.96 139.92 209.87
6948.83 7368.58 7788.33 8208.08
Overheads&Contractors Profit @13.615% 946.08 1003.23 1060.38 1117.53
Rate per 10 sqm 7894.91 8371.81 8848.71 9325.61
Rate per 1 sqm 789.49 837.18 884.87 932.56
Say 789 837 885 933
CIVIL DATA 2020-21 : Page-748

Providing Polished black Kadapa slabs minimum of 15 mm thick in single piece as specified set over a base coat of CM (1:5) , 12mm thick using screened
already laid CC bed / RCC roof slab including neat cement slurry of honey like consistency spread @ 3.3 Kgs per sqm and jointed with neat cement to full depth inclu
55 and conveyance of all materials like cement, sand, water, flooring stones etc. complete including all labour charges like dressing of flooring stones to the required size, f
the edges, mixing of cement mortar, laying, lift charges , cost of base coat, water charges etc., and overheads & contractors profit complete for finished item of work f
and risers. (APSS No.703 & 701)
a) BLD-CSTN-9-1 Treads of 0.30m wide :
Unit = 10 sqm.
A. MATERIALS:

MAT-00773 BMT-B-06 Polished black Kadapa slabs minimum of 15mm thick 11.00 sqm 2834.16 10 sqm

Cement for CM (1:5) proportion for base coat 34.56 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
Cement for jointing 20.00 Kgs 4220.00 1000 Kgs
MAT-00029 CSoR 28 Sand for CM(1:5) 0.12 Cum 1156.00 1 Cum
B .LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 3.10 Nos 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 1.10 Nos 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(un skilled) 0.86 Nos 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 3026.00
LAB-00507 BMM-V.13 Flat nosing the edges 33.33 RM 55.00 1 RM
Add for MAA @ 20% 0.20 733.26
Add water charges 1% 0.01 9236.80
Rate for 10 sqm

Rate for other floors F1 F2 F3 F4


Rate as worked out above 9329.17 9329.17 9329.17 9329.17
Lift charges ( Page 131 of Std. Data ) 0.00 302.60 605.20 907.80
Add for MAA @ 20% 0.00 60.52 121.04 181.56
9329.17 9692.29 10055.41 10418.53
Overheads&Contractors Profit @13.615% 1270.17 1319.61 1369.04 1418.48
Rate per 10 sqm 10599.34 11011.90 11424.45 11837.01
Rate per 1 sqm 1059.93 1101.19 1142.44 1183.70
Say 1060 1101 1142 1184
CIVIL DATA 2020-21 : Page-749

b) BLD-CSTN-9-23 Risers of 0.15m height :


Unit = 10 sqm
A.MATERIALS :
MAT-00773 BMT-B-06 Cost of Kadapa stone slabs 11.00 sqm 2834.16 10 sqm
MAT-00029 CSoR 28 Sand for CM(1:5) base coat 0.12 cum 1156.00 1 cum
Cement for CM(1:5) base coat 34.56 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
B.LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 0.96 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 2.24 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(unskilled) 3.10 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 3497.90
Add water charges 1% 0.01 7738.88
Rate for 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 7816.27 7816.27 7816.27 7816.27
Lift charges ( Page 131 of Std. Data ) 0.00 349.79 699.58 1049.37
Add for MAA @ 20% 0.00 69.96 139.92 209.87
7816.27 8236.02 8655.76 9075.51
Overheads&Contractors Profit @13.615% 1064.18 1121.33 1178.48 1235.63
Rate per 10 sqm 8880.45 9357.35 9834.24 10311.14
Rate per 1 sqm 888.04 935.73 983.42 1031.11
Say 888 936 983 1031
CIVIL DATA 2020-21 : Page-750

Providing 16 mm to 18 mm thick high polished leather finish granite stone slabs (steel grey or pearl black) with borders and design as per the pattern approv
Engineer-in-Charge of length not less than 2.43 mts set over base coat of cement mortar (1:5) , 12mm thick using screened sand over CC bed already laid or RCC
including neat grey cement slurry of honey like consistency spread @ 3.3 Kg per sqm and jointed neatly with white cement paste mixed with pigment of matching sha
56
depth including cost and conveyance of all materials like cement , sand , water , granite slabs etc., to work site and all operational, incidental labour & lift charges, ful
the edges of treads , providing 3 grooves of size 2mm x 1mm for the full length of treads , polishing charges, cost of base coat and overheads & contractors profit com
finished item of work for treads and risers (S.S.701 & special)

a) BLD-CSTN-9-7 Treads of 0.30m wide :


Unit = 10 sqm.
A. MATERIALS:
High polished granite slabs other than black 16 to 18mm
MAT-00777 BMT-B-10 10.50 sqm 2500.00 1 sqm
thick
Cement for CM(1:5) for base coat 34.56 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
MAT-01638 BMS-W.68 White cement for jointing 6.00 Kgs 31.00 1 Kg
MAT-00029 CSoR 28 Sand for CM(1:5) 0.12 Cum 1156.00 1 Cum
B .LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 3.00 Nos 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 1.00 Nos 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(un skilled) 8.00 Nos 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 6655.00
Machine cutting charges 33.33 RM 19.00 1 RM
Full rounding the edges 33.33 RM 453.00 1 RM
Add for MAA @ 20% 0.20 6292.70
Add water charges 1% 0.01 51836.12
Rate for 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 52354.49 52354.49 52354.49 52354.49
Lift charges ( Page 131 of Std. Data ) 0.00 665.50 1331.00 1996.50
Add for MAA @ 20% 0.00 133.10 266.20 399.30
52354.49 53153.09 53951.69 54750.29
Overheads&Contractors Profit @13.615% 7128.06 7236.79 7345.52 7454.25
Rate per 10 sqm 59482.55 60389.88 61297.21 62204.54
Rate per 1 sqm 5948.25 6038.99 6129.72 6220.45
Say 5948 6039 6130 6220
CIVIL DATA 2020-21 : Page-751

b) BLD-CSTN-9-19 Risers of 0.15m height :


Unit = 10 sqm
A.MATERIALS :
MAT-00777 BMT-B-10 Cost of high polished granite 10.50 sqm 2500.00 1 sqm
MAT-00029 CSoR 28 Sand for CM(1:5) base coat 0.12 cum 1156.00 1 cum
Cement for CM(1:5) base coat 34.56 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
MAT-01638 BMS-W.68 White cement for jointing & pointing 5.00 Kgs 31.00 1 Kg
LAB-00506 BMM-V.12 Machine cutting charges 66.67 RM 19.00 1 RM
Add for MAA @ 20% 0.20 506.69
B.LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 2.10 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 4.90 Nos 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(un skilled) 8.00 Nos 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 8291.50
Add water charges 1% 0.01 38146.69
Rate for 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 38528.16 38528.16 38528.16 38528.16
Lift charges ( Page 131 of Std. Data ) 0.00 829.15 1658.30 2487.45
Add for MAA @ 20% 0.00 165.83 331.66 497.49
38528.16 39523.14 40518.12 41513.10
Overheads&Contractors Profit @13.615% 5245.61 5381.08 5516.54 5652.01
Rate per 10 sqm 43773.77 44904.22 46034.66 47165.11
Rate per 1 sqm 4377.38 4490.42 4603.47 4716.51
Say 4377 4490 4603 4717
CIVIL DATA 2020-21 : Page-752

Providing skirting to internal walls to 10 cm height with Polished Shahabad/Tandur stone slabs 15mm to 18mm thick, length equal to flooring stones set over ba
CM(1:5) 12 mm thick using screened sand with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointing with white cement paste m
57 BLD-CSTN-9-23
pigment of matching shade to full depth, including cost of all materials like tiles, cement, sand and water etc., complete and overheads & contractors profit complete fo
item of work.(APSS No.701 &707)
Unit = 10 sqm
A.MATERIALS :
MAT-00772 BMT-B-05 Cost of shahabad stone slabs 11.00 sqm 2053.39 10 sqm
MAT-00029 CSoR 28 Sand for CM(1:5) base coat 0.12 cum 1156.00 1 cum
Cement for CM(1:5) base coat 34.56 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
B.LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 0.96 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 2.24 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(unskilled) 3.10 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 3497.90
Add water charges 1% 0.01 6880.03
Rate for 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 6948.83 6948.83 6948.83 6948.83
Lift charges ( Page 131 of Std. Data ) 0.00 349.79 699.58 1049.37
Add for MAA @ 20% 0.00 69.96 139.92 209.87
6948.83 7368.58 7788.33 8208.08
Overheads&Contractors Profit @13.615% 946.08 1003.23 1060.38 1117.53
Rate per 10 sqm 7894.91 8371.81 8848.71 9325.61
Rate per 1 RM 78.95 83.72 88.49 93.26
Say 79 84 88 93
CIVIL DATA 2020-21 : Page-753

Providing skirting to internal walls to 10 cm height with Polished Kadapa stone slabs minimum of 15mm thick, length equal to flooring stones set over bas
CM(1:5) 12 mm thick using screened sand with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointing with white cement paste m
58 BLD-CSTN-9-22
pigment of matching shade to full depth, including cost of all materials like tiles, cement, sand and water etc., complete and overheads & contractors profit complete fo
item of work.(APSS No.701 &707)

Unit = 10 sqm
A.MATERIALS :
MAT-00773 BMT-B-06 Cost of Kdapa stone slabs 10.50 sqm 1889.44 10 sqm
MAT-00029 CSoR 28 Sand for CM(1:5) base coat 0.12 cum 1156.00 1 cum
Cement for CM(1:5) base coat 34.56 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
B.LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 0.96 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 2.24 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(unskilled) 3.10 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 3497.90
Add water charges 1% 0.01 6605.22
Rate for 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 6671.27 6671.27 6671.27 6671.27
Lift charges ( Page 131 of Std. Data ) 0.00 349.79 699.58 1049.37
Add for MAA @ 20% 0.00 69.96 139.92 209.87
6671.27 7091.02 7510.76 7930.51
Overheads&Contractors Profit @13.615% 908.29 965.44 1022.59 1079.74
Rate per 10 sqm 7579.56 8056.46 8533.35 9010.25
Rate per 1 RM 75.80 80.56 85.33 90.10
Say 76 81 85 90
CIVIL DATA 2020-21 : Page-754

Providing skirting to internal walls to 10 cm height with Soluble salt porcelain vitrified tiles screen printed and polished of 8 to 10mm thick of any colour and f
shades and designs, length equal to flooring tiles, set over base coat of CM(1:5) 12 mm thick using screened sand with cement slurry of honey like consistency spread a
59 BLD-CSTN-9-20
of 3.30 kgs per sqm and jointing with white cement paste mixed with pigment of matching shade to full depth, including cost of all materials like tiles, cement, sand a
etc.,and overheads & contractors profit complete for finished item of work.(APSS No.701 &707)

Unit = 10 sqm
MAT-00790 BMT-C.06 Cost of vitrified tiles 8-10mm thick 10.50 sqm 425.00 1 sqm
MAT-00029 CSoR 28 Sand for CM(1:5) base coat 0.12 cum 1156.00 1 cum
Cement for CM(1:5) base coat 34.56 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
MAT-01638 BMS-W.68 White cement for jointing & pointing 2.00 Kgs 31.00 1 Kg

B.LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 0.96 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 2.24 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(unskilled) 3.30 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 3602.90
Add water charges 1% 0.01 9271.80
Rate for 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 9364.52 9364.52 9364.52 9364.52
Lift charges ( Page 131 of Std. Data ) 0.00 360.29 720.58 1080.87
Add for MAA @ 20% 0.00 72.06 144.12 216.17
9364.52 9796.87 10229.22 10661.57
Overheads&Contractors Profit @13.615% 1274.98 1333.84 1392.71 1451.57
Rate per 10 sqm 10639.50 11130.71 11621.93 12113.14
Rate per 1 RM 106.40 111.31 116.22 121.13
Say 106 111 116 121
CIVIL DATA 2020-21 : Page-755

Providing skirting 10 cm height with Double charged / multi charged stain free full body porcelain vitrified tiles with double layer pigment of Size 600 x 600
thickness between 8-10 mm of any colour and finish in all shades and designs, length equal to flooring tiles, flushed to wall surface to set over base coat of CM(1:
60 BLD-CSTN-9-20 thick using screened sand with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointing with white cement paste mixed with p
matching shade to full depth, including cost of all materials like tiles, cement, sand and water etc.,and overheads & contractors profit complete for finished item of wo
No.701 &707)

Unit = 10 sqm
MAT-00793 BMT-C.09 Cost of vitrified tiles 8-10mm thick 10.50 sqm 612.00 1 sqm
MAT-00029 CSoR 28 Sand for CM(1:5) base coat 0.12 cum 1156.00 1 cum
Cement for CM(1:5) base coat 34.56 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
MAT-01638 BMS-W.68 White cement for jointing & pointing 2.00 Kgs 31.00 1 Kg

B.LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 0.96 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 2.24 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(unskilled) 3.30 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 3602.90
Add water charges 1% 0.01 11235.30
Rate for 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 11347.66 11347.66 11347.66 11347.66
Lift charges ( Page 131 of Std. Data ) 0.00 360.29 720.58 1080.87
Add for MAA @ 20% 0.00 72.06 144.12 216.17
11347.66 11780.00 12212.35 12644.70
Overheads&Contractors Profit @13.615% 1544.98 1603.85 1662.71 1721.58
Rate per 10 sqm 12892.64 13383.85 13875.06 14366.28
Rate per 1 RM 128.93 133.84 138.75 143.66
Say 129 134 139 144

Supply and application of epoxy coving with SIKA brand with 50mmx50mm width at the corners of the all walls in Operation Theatres, labour rooms including
61
conveyance of all materials and labour charges, overheads and contractor profit etc., complete for finished item of work .

MAT-00735 BMT-C.49 Rate as per SoR 1 RM 500.00 1 RM


Overheads&Contractors Profit @13.615% 0.13615 500.00
Rate per 1 RM
Say
CIVIL DATA 2020-21 : Page-756

Providing skirting to internal walls 10 cm height with High Polished Granite 16 mm to 18 mm thick up to 8'-00 (2.43 M) other than black and regular colours, len
to flooring slabs set over base coat of CM(1:5) 12 mm thick using screened sand with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm an
62 BLD-CSTN-9-19
with white cement paste mixed with pigment of matching shade to full depth, including cost of all materials like tiles, cement, sand and water etc., and overheads & c
profit complete for finished item of work.

Unit = 10 sqm
A.MATERIALS :
MAT-00777 BMT-B-10 Cost of high polished granite 10.50 sqm 2500.00 1 sqm
MAT-00029 CSoR 28 Sand for CM(1:5) base coat 0.12 cum 1156.00 1 cum
Cement for CM(1:5) base coat 34.56 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
MAT-01638 BMS-W.68 White cement for jointing & pointing 5.00 Kgs 31.00 1 Kg
LAB-00506 BMM-V.12 Machine cutting charges 66.67 RM 19.00 1 RM
Add for MAA @ 20% 0.20 506.69
B.LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 2.10 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 4.90 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Man Mazdoor(Beldar) 8.00 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 8291.50
Add water charges 1% 0.01 38146.69
Rate for 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 38528.16 38528.16 38528.16 38528.16
Lift charges ( Page 131 of Std. Data ) 0.00 829.15 1658.30 2487.45
Add for MAA @ 20% 0.00 165.83 331.66 497.49
38528.16 39523.14 40518.12 41513.10
Overheads&Contractors Profit @13.615% 5245.61 5381.08 5516.54 5652.01
Rate per 10 sqm 43773.77 44904.22 46034.66 47165.11
Rate per 1 RM 437.74 449.04 460.35 471.65
Say 438 449 460 472
CIVIL DATA 2020-21 : Page-757

Providing cladding to walls with High Polished Granite 16 mm to 18 mm thick up to 8'-00 (2.43 M) other than black and regular colours, length equal to flooring
over base coat of CM(1:3) 12 mm thick using screened sand with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointing with whi
63 BLD-CSTN-9-19
paste mixed with pigment of matching shade to full depth, including cost of all materials like tiles, cement, sand and water etc., and overheads & contractors profit com
finished item of work.

Unit = 10 sqm
A.MATERIALS :
MAT-00777 BMT-B-10 Cost of high polished granite 10.50 sqm 2500.00 1 sqm
MAT-00029 CSoR 28 Sand for CM(1:3) base coat 0.12 cum 1156.00 1 cum
Cement for CM(1:3) base coat 57.60 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
MAT-01638 BMS-W.68 White cement for jointing & pointing 5.00 Kgs 31.00 1 Kg
B.LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 2.10 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 4.90 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Man Mazdoor(Beldar) 8.00 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 8291.50
Add water charges 1% 0.01 36875.85
Rate for 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 37244.61 37244.61 37244.61 37244.61
Lift charges ( Page 131 of Std. Data ) 0.00 829.15 1658.30 2487.45
Add for MAA @ 20% 0.00 165.83 331.66 497.49
37244.61 38239.59 39234.57 40229.55
Overheads&Contractors Profit @13.615% 5070.85 5206.32 5341.79 5477.25
Rate per 10 sqm 42315.46 43445.91 44576.36 45706.80
Rate per 1 sqm 4231.55 4344.59 4457.64 4570.68
Say 4232 4345 4458 4571
CIVIL DATA 2020-21 : Page-758

Providing dadooing with glazed red or white full body ceramic wall tiles of size 300 x 450 mm / 320 mm x 400 mm and thickness 6 mm 1st quality conforming to
IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all shades and designs with borders as approved by Engineer-in-Charge flushed to wall surface set
64 BLD-CSTN-9-18 coat of CM(1:5) 12 mm thick using screened sand with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointing with white cement pa
with pigment of matching shade to full depth, including cost of all materials like tiles, cement, sand and water etc., and overheads & contractors profit complete for fini
of work.
Unit = 10 sqm
A.MATERIALS :
MAT-00806 BMT-C.22 Cost of glazed coloured tiles 10.50 sqm 410.00 1 sqm
MAT-00029 CSoR 28 Sand for CM(1:5) base coat 0.12 cum 1156.00 1 cum
Cement for CM(1:5) base coat 34.56 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
MAT-01638 BMS-W.68 White cement for jointing & pointing 6.00 Kgs 31.00 1 Kg
B.LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 0.77 Nos. 630.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(unskilled) 0.80 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 905.10
Add water charges 1% 0.01 6000.94
Rate for 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 6060.95 6060.95 6060.95 6060.95
Lift charges ( Page 131 of Std. Data ) 0.00 90.51 181.02 271.53
Add for MAA @ 20% 0.00 18.10 36.20 54.31
6060.95 6169.56 6278.18 6386.79
Overheads&Contractors Profit @13.615% 825.20 839.99 854.77 869.56
Rate per 10 sqm 6886.15 7009.55 7132.95 7256.35
Rate per 1 sqm 688.62 700.96 713.29 725.63
Say 689 701 713 726
CIVIL DATA 2020-21 : Page-759

Providing dadooing with glazed full body porcelain wall tiles of size 300mm x 600 mm with any type of design texture such as marble finish, wooden, bamb
finishes etc., scratch less, stain free and thickness between 6-8 mm 1st quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in a
65 BLD-CSTN-9-20 and designs with borders and design as per the approved pattern as approved by Engineer-in-Charge flushed to wall surface set over base coat of CM(1:5) 12 mm t
screened sand with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointing with white cement paste mixed with pigment of matching
full depth, including cost of all materials like tiles, cement, sand and water etc., and overheads & contractors profit complete for finished item of work.

Unit = 10 sqm
A.MATERIALS :
MAT-00808 BMT-C.24 Cost of porcelain wall tiles 10.50 sqm 580.00 1 sqm
MAT-00029 CSoR 28 Sand for CM(1:5) base coat 0.12 cum 1156.00 1 cum
Cement for CM(1:5) base coat 34.56 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
MAT-01638 BMS-W.68 White cement for jointing & pointing 2.00 Kgs 31.00 1 Kg
B.LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 0.96 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 2.24 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(unskilled) 3.30 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 3602.90
Add water charges 1% 0.01 10899.30
Rate for 10 sqm

Rate for other Floors F1 F2 F3 F4


Rate as worked out above 11008.30 11008.30 11008.30 11008.30
Lift charges ( Page 131 of Std. Data ) 0.00 360.29 720.58 1080.87
Add for MAA @ 20% 0.00 72.06 144.12 216.17
11008.30 11440.64 11872.99 12305.34
Overheads&Contractors Profit @13.615% 1498.78 1557.64 1616.51 1675.37
Rate per 10 sqm 12507.08 12998.28 13489.50 13980.71
Rate per 1 sqm 1250.71 1299.83 1348.95 1398.07
Say 1251 1300 1349 1398
CIVIL DATA 2020-21 : Page-760

Flooring with plain Cement Concrete general purpose tiles conforming to IS: 13801 using aggregates, cement, pigments of size 300 x 300 mm and thickness 20 m
shade set over base coat of cement mortar (1:6), 12 mm thick using screened sand over CC bed already laid of any shades as approved by Engineer - In - Charge inclu
66 BLD-CSTN-9-4
cement slurry of honey like consistency spread @ 3.3 kgs per sqm and jointed with neat white cement to full depth mixed with pigment of matching shade including
conveyance of all materials like cement, sand, water and tiles etc.,and overheads & contractors profit complete for finished item of work.

Unit : 10sqm
A.MATERIALS :
MAT-00832 BMT-D.04 Plain cement concrete tiles 300mm x 300mm 10.50 sqm 255.00 1 sqm
Cement for CM(1:6) proportion for base coat 28.80 Kgs 4220.00 1000 Kgs
Cement for slurry 33.00 Kgs 4220.00 1000 Kgs
MAT-01638 BMS-W.68 White cement for jointing & pointing 6.00 Kgs 31.00 1.00 Kgs
MAT-00029 CSoR 28 Sand for CM(1:6) proportion 0.12 Cum 1156.00 1 Cum
B. LABOUR
LAB-00001 CSoR I - 1 Mason 1st class 0.96 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 Mason 2nd class 2.24 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (unskiled) 3.30 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 3602.90
Add water charges 1% 0.01 7586.50
Rate per 10 sqm
Rate per 1 sqm

Providing plinth protection using plain Cement Concrete general purpose tiles conforming to IS: 13801 using aggregates, cement, pigments of size 300 x 300
thickness 20 mm of any shade for a width of 1200mm set over base coat of cement mortar (1:6), 12 mm thick using screened sand over PCC(1:5:10) bed 100mm th
with drain constructed with 225 mm thick walls using fly ash cement / lime solid blocks of size 290mm x 225mm x 140mm from approved source having minimum
67
strength of 50 Kg/Sqcm. and plastering 12mm thick two coats with base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in CM (1:4) for brick masonry drain
tiles in between basement of the building and brick wall and as directed by the Engineer - in - charge including cost and conveyance of all materials to site, all labou
like mixing of cement concrete, laying, curing, overheads & contractor profit etc., complete for finished item of work.

Earth work excavation 0.6544 Cum 125.62 1 Cum


P.C.C.(1:5:10) 0.1970 Cum 3885.49 1 Cum
Masonry in CM(1:6) 0.2025 Cum 6114.57 1 Cum
Plastering 12 mm thick two coats 1.65 Sqm 431.83 1 Sqm
Cement concrete tiles flooring 1.20 Cum 766.24 1 Cum
Rate per 1.00 RM (1.20 Sqm)
Rate per 1 Sqm
Overheads&Contractors Profit @13.615% 0.13615 3098.21

Say
CIVIL DATA 2020-21 : Page-761

Filling with light weight concrete in Cement Concrete (1:5:10) proportion using brick jelly for low roofs including cost and conveyance of all materials like ceme
68 BLD-CSTN-3-7 brick bats etc., to site including cost of all labour charges for laying concrete, ramming, curing , overheads & contractors profit etc., complete for finished item of wor
No. 402)

Unit: 1 Cum
A. Materials :-
Cement 129.60 Kgs 4220.00 1000 Kgs
MAT-00721 BMT-A.01 Cost of brick jelly 20mm size(1/3rd rate) 460 Nos. 7874.10 1000 Nos.
MAT-00027 CSoR 27(a) Fine aggregate ( Sand ) 0.45 Cum 1061.00 1 Cum
MAT-00332,
M - 189(a),(b) Water (including curing) 1.20 kl 116.00 1 kl
MAT-00333
B.MACHINERY :
HIR-00016& LAB-
CSoR 16 Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)capacity 1.00 hour 188.10 1 hour
00329
HIR-00150 CSoR 16 Crew Charges 1.00 hour 306.80 1 hour
Add MA on crew charges 0.20 306.80
C.LABOUR :
LAB-00001 CSoR I - 1 1st class mason 0.10 Nos. 630.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (unskilled) 1.39 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 792.75

Rate for other Floors F1 F2 F3


Rate as above 3878.48 3878.48 3878.48
Lift charges ( Page 131 of Std. Data ) 0.00 79.28 158.55
Add for MAA @ 20% 0.00 15.86 31.71
Rate per 1 cum 3878.48 3973.62 4068.74
Overheads&Contractors Profit @13.615% 528.06 541.01 553.96
Rate per 1 cum 4406.54 4514.63 4622.70
Say 4407 4515 4623
CIVIL DATA 2020-21 : Page-762

BLD-CSTN-2-8
& Addendum
dt.14.05.2019 of Filling with well burnt cinder aggregate as per IS:2686-1977 in sunken slabs including cost and conveyance of cinder, labour charges for filling, ramming, overh
69
the Chief contractor profit etc., complete for finished item of work
Engineer (R&B)
Buildings
Unit : 1 cum
Taking output 6.00 cum
a) Labour
LAB-00120,
CSoR III - 3,4 Mazdoor ( Unskilled ) 0.31 Nos. 525.00 1 No.
LAB-00121
Add for MAA @ 20% 0.20 162.75
b)Material :
MAT-00763 BMT-A-17 Cost of well burnt cinder aggregate 6.00 cum 650.00 1 cum
Rate per 6 cum

Rate for other Floors F1 F2 F3


Rate as above 4095.30 4095.30 4095.30
Lift charges ( Page 131 of Std. Data ) 0.00 16.28 32.55
Add for MAA @ 20% 0.00 3.26 6.51
Rate per 1 cum 4095.30 4114.84 4134.36
Overheads&Contractors Profit @13.615% 557.58 560.23 562.89
Rate per 6 cum 4652.88 4675.07 4697.25
Rate per 1 cum 775.48 779.18 782.88
Say 775 779 783
CIVIL DATA 2020-21 : Page-763

Reinforced cement concrete (1:5:10) proportion (Cement: fine aggregates: coarse aggregate) using 40mm size (SS5) hard granite metal (coarse aggregate) from
quarry including cost and conveyance of all materials like cement, fine aggregate (sand), coarse aggregate, water etc., to site including centering using Casurina
70 BLD-CSTN-3-13 Bamboos , Wooden Reapers , Runners , Wood Posts , Wall Plates etc., shuttering, machine mixing, laying concrete, lifting concrete manually , vibrating, curing,
overheads & contractors profit complete as per drawings but excluding cost of steel and it's fabrication charges for finished item of work (APSS NO. 402 & 403) fo
columns.
Unit: 1 Cum
A.MATERIALS :
Cement 129.60 Kgs 4220.00 1000 Kgs
MAT-00220 M - 055 40mm HBG metal 0.90 Cum 1349.30 1 Cum
MAT-00027 CSoR 27(a) Sand 0.45 Cum 1061.00 1 Cum
B.LABOUR :
LAB-00001 CSoR I - 1 1st class Mason 0.167 Nos 630.00 1 Each
LAB-00002 CSoR I - 2 2nd class Mason 0.167 Nos 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor (unskilled) 4.70 Nos 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 2667.07
C.MACHINERY :
HIR-00016& LAB-
CSoR 16 Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)capacity 1.00 hour 188.10 1 hour
00329
HIR-00150 CSoR 16 Crew charges 1.00 hour 306.80 1 hour
HIR-00040& LAB-
CSoR 40 Needle vibrator 40mm ( petrol ) 1.00 hour 38.20 1 hour
00352
HIR-00174 CSoR 40 Crew charges 1.00 hour 220.90 1 hour
Add MA on crew charges 0.20 527.70
MAT-00332,
M - 189(a),(b) Water(including for curing) 1.20 kl 116.00 1 kl
MAT-00333
Basic cost per 1 cum

Rate for other Floors F2 F3 F4


Rate as above 6437.95 6437.95 6437.95
Hire charges of centering and scaffolding 249.00 249.00 249.00
Labour , lift charges for scaffolding 2058.00 2245.00 2432.00
Add for MAA @ 20% 411.60 449.00 486.40
Lift charges 266.71 533.41 800.12
Add for MAA @ 20% 53.34 106.68 160.02
Rate per 1 cum 9476.60 10021.04 10565.49
Overheads&Contractors Profit @13.615% 1290.24 1364.36 1438.49
Rate per 1 cum 10766.84 11385.40 12003.98
Say 10767 11385 12004
CIVIL DATA 2020-21 : Page-764

Supplying and fixing of stainless steel (grade 304) hand railing as per approved drawing with top rail of 50mm dia pipe and 2mm thick medium class and vertica
25mm dia and 1.6mm thick medium class 1 No for each step fixed with base plate of 25mm dia using bonding agent and anchor fastner and welding, drilling of 25mm
71
with pneumatic compressor for fixing railing, buffing, polishing all members of the railing thouroughly , lacquer finishing to present seamless finish including
conveyance of all materials, electrodes, welding charges, cost of all consumables, labour charges , overheads & contractors profit etc., complete for finished item of wor

For a flight length of 4.60 M. 4.60 RM


Cost of 50mm dia SS pipe (1x4.60) 4.60 RM
Cost of 25mm dia SS pipe (13x0.90) 11.70 RM
50mm pipe (4.60 x 2.39 Kgs/RM) 10.99 Kgs
25mm pipe (11.70x 0.89 Kgs/RM) 10.41 Kgs
MAT-00872 BMT-F.06 Cost of stainless steel pipes 21.40 Kgs 414.00 1 Kg
LAB-00424 BMM-V.18 Labour charges for fabrication 21.40 Kgs 144.00 1 Kg
MAT-00512 CSoR 143 Drilling of 25mm dia hole(13 x 0.10) 1.30 RM 167.00 1 RM
Base Plate 25mm dia. 13 Nos. 30.00 1 Each
Add for anchor bars 13 Nos. 30.00 1 No
Add for bonding 13 Nos. 15.00 1 No

Rate per 1 RM
Rate per 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 3172.29

say

Supplying and fixing of stainless steel (grade 304) railing for ramp as per approved drawing with top rail of 50mm dia pipe and 2mm thick medium class fixed in to
25mm dia pipe of 0.30m length @ 1m centre to centre and welding, buffing, polishing all members of the railing thouroughly , lacquer finishing to present seaml
72
including cost and conveyance of all materials, electrodes, welding charges, cost of all consumables, labour charges , overheads & contractors profit etc., complete fo
item of work.

For a length of 10.00 M. 10.00 RM


Cost of 50mm dia SS pipe (1x10.00) 10.00 RM
Cost of 25mm dia SS pipe (9x0.30) 2.70 RM
50.00mm pipe (10.00 x 2.39 Kgs/RM) 23.90 Kgs
25mm pipe (2.70x 0.89 Kgs/RM) 2.40 Kgs
MAT-00872 BMT-F.06 Cost of stainless steel pipes 26.30 Kgs 414.00 1 Kg
LAB-00424 BMM-V.18 Labour charges for fabrication 26.30 Kgs 144.00 1 Kg
MAT-00512 CSoR 143 Drilling of 25mm dia hole(9 x 0.10) 0.90 RM 167.00 1 RM
Base Plate 25mm dia. 9 Nos. 30.00 1 Each

Rate per 10 RM
Overheads&Contractors Profit @13.615% 0.13615 1509.57
CIVIL DATA 2020-21 : Page-765

say

Supplying and fixing of stainless steel (grade 304) grip bars 200mm length bars in toilets as per approved drawing with 25mm dia pipe with base plates 2 Nos
73 polishing thouroughly , lacquer finishing to present seamless finish including cost and conveyance of all materials, labour charges , overheads & contractors profit etc.,
for finished item of work.

25mm pipe {(2x(0.10+0.20)x 0.89 Kgs/RM} 0.36 Kgs


MAT-00872 BMT-F.06 Cost of stainless steel pipes 0.36 Kgs 414.00 1 Kg
LAB-00424 BMM-V.18 Labour charges for fabrication 0.36 Kgs 144.00 1 Kg
MAT-00512 CSoR 143 Drilling of 25mm dia hole(2 x 0.10) 0.20 RM 167.00 1 RM
Base Plate 2 Nos. 30.00 1 Each
Rate per Each
Overheads&Contractors Profit @13.615% 0.13615 294.28

say

Providing 110 mm Dia ISI marked PVC down water take pipes with single socket , 2.5mm thick 4.0 kg/sq.cm pressure of ISI marked including cost of necessary PV
74 couplers, shoes, iron / PVC clamps and all other accessories and fixing in position including cost and conveyance of all materials, operational & incidental charges inc
labour charges for fixing at site etc., and overheads & contractors profit complete for finished item of work. (APSS No. 1328)

BMW-G.13 MAT-01900 PVC pipe 110mm dia 6.00 RM 447.30 3.00 RM


BMW-G.57 MAT-01944 PVC 110mm dia plain bend 1 Nos. 76.65 1 Each
BMW-G.93 MAT-01980 PVC 110mm coupler 1 Nos. 52.50 1 Each
MAT-01993 BMW-G.106 MS Clamps 3 Nos. 17.00 1 Each
LAB-00280 MAT-01993 Cutting holes in brick masonry 1 No. 53.50 1 Each
LAB-00259 BMW-G.152 Labour charges for fixing pipes 6.00 RM 79.18 1 RM
Rate per 6 RM

Overheads&Contractors Profit @13.615% 0.13615 267.22


Rate per 1 RM
Say
CIVIL DATA 2020-21 : Page-766

Supply and fixing jallies ( cement concrete ) of 50mm thick as per the design approved by the Engineer-in-Charge including cost and conveyance of materials t
75
labour charges etc., overheads & contractors profit complete for finished item of work.
MAT-01589 BMS-W.17 Cost of 50mm thick jali 1.00 sqm 388.00 1 sqm
LAB-00001 CSoR I - 1 1st class mason 0.06 Nos. 630.00 1 Each
LAB-00002 CSoR I - 2 2nd class mason 0.06 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(unskilled) 0.275 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 216.08

Rate for other Floors F1 F2 F3


Rate as worked out above 647.29 647.29 647.29
Hire charges for Access Scaffolding 10.78 10.78 10.78
Labour charges for scaffolding 84.62 121.18 157.72
Add for MAA @ 20% 16.92 24.24 31.54
Lift charges ( Page 131 of Std. Data ) 0.00 21.61 43.22
Add for MAA @ 20% 0.00 4.32 8.64
Rate for 1 sqm 759.61 829.42 899.20
Overheads&Contractors Profit @13.615% 103.42 112.93 122.43
Rate per 1 sqm 863.03 942.35 1021.63
Say 863 942 1022

White washing two coats with white cement to ceiling to give an even shade after thouroughly brushing the surface to remove all dirt and remains of loose
76 BLD-CSTN-11-5 materials including cost of all materials , labour charges and incidental such as scaffolding , lift charges etc., and overheads & contractors profit complete for finished ite
in all floors.

Unit : 10 sqm
A.MATERIALS :
MAT-01638 BMS-W.68 White cement 2.00 kgs 31.00 1 kgs
B.LABOUR :
LAB-00035 CSoR I - 35 Painter 1st class 0.063 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 Painter 2nd class 0.147 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(unskilled) 0.32 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 295.47
Sundries including brushes , ladders etc., @ 1% 1% 416.56
Rate per 10 sqm
Overheads&Contractors Profit @13.615% 0.13615 420.73
Rate per 10 sqm
Rate per 1 sqm
CIVIL DATA 2020-21 : Page-767

Say

Providing and applying Wall putty of White Cement or Polymer or Cement based of average 1 to 2 mm thickness over plastered surface to prepare the surface
As per
smooth after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials, applying emery paper, Sand the surface, clean & wipe off lo
77 Amendment in
applying knifing paste filler by putty knife / muslin pad, air dry for 2 - 3 hrs, sand with 180 and 320 No., emery paper for the surface preparation including cost and conv
SoR 2011-12
all materials to work site and all operational, incidental, labour charges, over heads and contractors profit etc., complete for finished item of work in all floors for internal

Unit = 10 sqm
MAT-01104 BMT-J.31 wall putty 23.00 Kgs 600.00 20 Kg
LAB-00035 CSoR I - 35 Painter 1st class 0.273 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 Painter 2nd class 0.637 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor 0.91 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 1030.12
Sundries for emery papers, fillers, knife etc., @ 1% 0.01 1926.14

Overheads&Contractors Profit @13.615% 0.13615 1945.41


Rate per 10 sqm
Rate per 1 sqm
Say

Providing and applying exterior texture of average 2 to 3 mm thickness over plastered surface to prepare the surface even and smooth after thoroughly brushing th
As per
to remove all dirt and remains of loose powdered materials, applying emery paper, Sand the surface, clean & wipe off loose dust, applying putty/ texture paint filler by pu
78 Amendment in
muslin pad, air dry for 2 - 3 hrs for the surface preparation including cost and conveyance of all materials to work site and all operational, incidental, labour
SoR 2011-12
scaffolding charges, overheads and contractors profit etc., complete for finished item of work in all floors for external walls

Unit = 10 sqm
MAT-01105 BMT-J.32 exterior texture 34.50 Kgs 818.00 25 Kg
LAB-00035 CSoR I - 35 Painter 1st class 0.273 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 Painter 2nd class 0.637 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor 0.91 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 1030.12
Sundries for emery papers, fillers, knife etc., @ 1% 0.01 2364.98
Hire charges for Access Scaffolding 10 sqm 1.08 1 sqm
Labour charges for scaffolding 10 sqm 8.47 1 sqm
Add for MAA @ 20% 0.20 84.70

Overheads&Contractors Profit @13.615% 0.13615 2501.07


Rate per 10 sqm
Rate per 1 sqm
CIVIL DATA 2020-21 : Page-768

Say

Painting to new walls with 2 coats of Acrylic based Oil bound Washable Distemper having VOC content less than 50 grams/litre over promer coat using white
approved by Engineer-In-Charge, making 3 coats in all to give an even shade after thourughly brushing the surface to remove all dirt and remains of loose powdered
79 BLD-CSTN-12-1
including cost and conveyance of all materials to work site and all operational, incidental, labour charges etc., and overheads & contractors profit complete for finishe
work as per APSS 911 for internal walls in all floors.
Unit = 10 sqm
MAT-01638 BMS-W.68 Cost of white cement 0.50 Kg 31.00 1 Kg
LAB-00035 CSoR I - 35 Painter 1st class 0.08 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 Painter 2nd class 0.19 Nos. 565.00 1 Each
MAT-01093 BMT-J.21 Cost of washable oil bound distemper 1.70 Ltrs 81.00 1 Ltr
LAB-00035 CSoR I - 35 Painter 1st class 0.36 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 Painter 2nd class 0.84 Nos. 565.00 1 Each
Add for MAA @ 20% 0.20 892.15
Sundries including brushes , ladders etc., @ 1% 0.01 1223.78

Overheads&Contractors Profit @13.615% 0.13615 1236.02


Rate per 10 sqm
Rate per 1 sqm
Say

Painting to old walls with 2 coats of Acrylic based Oil bound Washable Distemper having VOC content less than 50 grams/litre as approved by Engineer-In-C
BLD-CSTN-11-
80 give an even shade after thourughly brushing the old surface to remove all dirt and remains of loose powdered materials, including cost and conveyance of all materia
10
site and all operational, incidental, labour charges etc., and overheads & contractors profit complete for finished item of work as per APSS 911 for internal walls in all f

Unit = 10 sqm
MAT-01093 BMT-J.21 Cost of washable oil bound distemper 1.70 Ltrs 81.00 1 Ltr
LAB-00035 CSoR I - 35 Painter 1st class 0.36 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 Painter 2nd class 0.84 Nos. 565.00 1 Each
Add for MAA @ 20% 0.20 728.40
Sundries including brushes , ladders etc., @ 1% 0.01 1011.78

Overheads&Contractors Profit @13.615% 0.13615 1021.90


Rate per 10 sqm
Rate per 1 sqm
Say
CIVIL DATA 2020-21 : Page-769

Painting to new walls with 2 coats of water proof cement paint of shade as approved by the Engineer-In-Charge over a base coat of aproved white cement
BLD-CSTN-12-1
81 making 3 coats in all to give an even shade after thourughly brushing the surface to remove all dirt and remains of loose powdered materials, including cost and conv
& 12-5
all materials to work site and all operational, incidental, labour charges etc., and overheads & contractors profit complete for finished item of work as per SS 912 in all flo

MAT-01638 BMS-W.68 Cost of white cement for base coat 1.00 Kgs 31.00 1 Kgs
LAB-00035 CSoR I - 35 Painter 1st class 0.08 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 Painter 2nd class 0.19 Nos. 565.00 1 Each
MAT-01098 BMT-J.25 Water proof cement paint 2.00 Kgs 1009.00 25 Kgs
LAB-00035 CSoR I - 35 Painter 1st class 0.15 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 Painter 2nd class 0.35 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(unskilled) 1.50 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 1254.75
Sundries including brushes , ladders etc., @ 1% 0.01 1617.42

Overheads&Contractors Profit @13.615% 0.13615 1633.59


Rate per 10 sqm
Rate per 1 sqm
Say

Painting to old walls with 2 coats of water proof cement paint of shade as approved by the Engineer-In-Charge to give an even shade after thourughly brushing th
82 BLD-CSTN-12-4 to remove all dirt and remains of loose powdered materials, including cost and conveyance of all materials to work site and all operational, incidental, labour charges
overheads & contractors profit complete for finished item of work as per SS 912 in all floors.

MAT-01098 BMT-J.25 Water proof cement paint 2.00 Kgs 1009.00 25 Kgs
LAB-00035 CSoR I - 35 Painter 1st class 0.15 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 Painter 2nd class 0.35 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor(unskilled) 1.50 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 1091.00
Sundries including brushes , ladders etc., @ 1% 0.01 1389.92

Overheads&Contractors Profit @13.615% 0.13615 1403.82


Rate per 10 sqm
Rate per 1 sqm
Say
CIVIL DATA 2020-21 : Page-770

BLD-CSTN-12- Supply & application of one coat water based cement primer of interior grade I and two coats of acrylic emulsion paint having VOC (Volatile Organic C
83 2& Amendment content less than 50 grams/litre for internal walls including cost and conveyance of all materials to site, incidental, operational and all labour charges etc.,and ove
in SoR 2011-12 contractors profit complete for finished item of work in all floors.

Unit 10 sqm.
A. Materials:-
MAT-01073 BMT-J.01 Cost of cement primer interior grade I 1.00 Kg 160.00 1 Kg
LAB-00035 CSoR I - 35 Painter 1st class 0.21 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 Painter 2nd class 0.49 Nos. 565.00 1 Each
MAT-01097 BMT-J.24 Acrylic emulsion paint 0.80 Ltrs 190.00 1 Ltrs
LAB-00035 CSoR I - 35 Painter 1st class 0.36 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 Painter 2nd class 0.84 Nos. 565.00 1 Each
Add for MAA @ 20% 0.20 1153.30
Sundries including brushes , ladders etc., @ 1% 0.01 1695.96

Overheads&Contractors Profit @13.615% 0.13615 1712.92


Rate per 10 sqm
Rate per 1 sqm
Say

BLD-CSTN-12- Supply & application of one coat water based cement primer of interior grade I and two coats of synthetic polymer luxury plastic emulsion paint of super
84 2& Amendment having VOC (Volatile Organic Compound) content less than 50 grams/litre for internal walls including cost and conveyance of all materials to site, incidental, operation
in SoR 2011-12 labour charges etc., and overheads & contractors profit complete for finished item of work in all floors.
Unit 10 sqm.
A. Materials:-
MAT-01073 BMT-J.01 Cost of cement primer interior grade I 1.00 Kg 160.00 1 Kg
LAB-00035 CSoR I - 35 Painter 1st class 0.21 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 Painter 2nd class 0.49 Nos. 565.00 1 Each
MAT-01094 BMT-J.22 Synthetic polymer luxury plastic emulsion paint 0.80 Ltrs 450.00 1 Ltrs
LAB-00035 CSoR I - 35 Painter 1st class 0.36 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 Painter 2nd class 0.84 Nos. 565.00 1 Each
Add for MAA @ 20% 0.20 1153.30
Sundries including brushes , ladders etc., @ 1% 0.01 1903.96

Overheads&Contractors Profit @13.615% 0.13615 1923.00


Rate per 10 sqm
Rate per 1 sqm
Say
CIVIL DATA 2020-21 : Page-771

BLD-CSTN-12- Supply & application of one coat water based cement primer of exterior grade II and two coats of acrylic exterior emulsion paint having VOC (Volatil
85 2& Amendment Compound) content less than 50 grams/litre for exterior walls including cost and conveyance of all materials to site, incidental, operational and all labour charge
in SoR 2011-12 overheads & contractors profit complete for finished item of work in all floors.
Unit 10 sqm.
A. Materials:-
MAT-01074 BMT-J.02 Cost of cement primer exterior grade II 1.00 Kg 200.00 1 Kg
LAB-00035 CSoR I - 35 Painter 1st class 0.21 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 Painter 2nd class 0.49 Nos. 565.00 1 Each
MAT-01107 BMT-J.34 Acrylic emulsion paint 0.80 Ltrs 210.00 1 Ltrs
LAB-00035 CSoR I - 35 Painter 1st class 0.21 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 Painter 2nd class 0.49 Nos. 565.00 1 Each
LAB-00120, LAB-
CSoR III - 3,4 Mazdoor(Unskilled) 1.50 Nos. 525.00 1 Each
00121
Add for MAA @ 20% 0.20 1637.30
Sundries including brushes , ladders etc., @ 1% 0.01 2332.76

Overheads&Contractors Profit @13.615% 0.13615 2356.09


Rate per 10 sqm
Rate per 1 sqm
Say

BLD-CSTN-12- Supply & application of one coat water based cement primer of exterior grade II and two coats of synthetic polymer luxury plastic emulsion paint of super
86 2& Amendment having VOC (Volatile Organic Compound) content less than 50 grams/litre for exterior walls including cost and conveyance of all materials to site, incidental, operation
in SoR 2011-12 labour charges etc., and overheads & contractors profit complete for finished item of work in all floors.
Unit 10 sqm.
A. Materials:-
MAT-01074 BMT-J.02 Cost of cement primer exterior grade II 1.00 Kg 200.00 1 Kg
LAB-00035 CSoR I - 35 Painter 1st class 0.21 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 Painter 2nd class 0.49 Nos. 565.00 1 Each
MAT-01094 BMT-J.22 Synthetic polymer luxury plastic emulsion paint 0.80 Ltrs 450.00 1 Ltrs
LAB-00035 CSoR I - 35 Painter 1st class 0.21 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 Painter 2nd class 0.49 Nos. 565.00 1 Each
LAB-00120, LAB-
CSoR III - 3,4 Mazdoor(Unskilled) 1.50 Nos. 525.00 1 Each
00121
Add for MAA @ 20% 0.20 1637.30
Sundries including brushes , ladders etc., @ 1% 0.01 2524.76

Overheads&Contractors Profit @13.615% 0.13615 2550.01


Rate per 10 sqm
Rate per 1 sqm
Say
CIVIL DATA 2020-21 : Page-772

Providing and applying water proof wall putty of white cement or polymer or cement based of average 1 to 2 mm thickness over plastered surface to prepare th
even and smooth after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials, applying emery paper, Sand the surface, clean &
As per
loose dust, applying knifing paste filler by putty knife / muslin pad, air dry for 2 - 3 hrs, sand with 180 and 320 No., emery paper for the surface preparation, applying on
87 Amendment in
cement primer of interior grade-1 and two coats of poy-urethane paint (MRF) of light green or light blue colour with 1mm thickness with anti fungal and ant
SoR 2011-12
chemical resistance durable and non particle shedding including cost and conveyance of all materials to work site and all operational, incidental, labour charges, over h
contractors profit etc., complete for finished item of work in all floors for internal walls and ceiling of Operation Theatre and labour rooms.

Unit = 10 Sqm
a) wall putty
MAT-01104 BMT-J.31 wall putty 23.00 Kgs 600.00 20 Kg
LAB-00035 CSoR I - 35 Painter 1st class 0.273 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 Painter 2nd class 0.637 Nos. 565.00 1 Each
LAB-00120,
CSoR III - 3,4 Mazdoor 0.91 Nos. 525.00 1 Each
LAB-00121
Add for MAA @ 20% 0.20 1030.12
Sundries for emery papers, fillers, knife etc., @ 1% 0.01 1926.14

b) primer coat
MAT-01073 BMT-J.01 Cost of cement primer interior grade I 1.00 Kg 160.00 1 Kg
LAB-00035 CSoR I - 35 Painter 1st class 0.21 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 Painter 2nd class 0.49 Nos. 565.00 1 Each
Add for MAA @ 20% 0.20 424.90
Sundries including brushes , ladders etc., @ 1% 0.01 669.88

c) poly-urethane paint 2 coats


Cost of poly-urethane Paint 1.35 Ltr 500.00 1 Ltr
LAB-00035 CSoR I - 35 1st Class Painter 0.36 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 2nd Class Painter 0.84 Nos. 565.00 1 Each
Add for MAA @ 20% 0.20 728.40
Sundries including brushes , ladders etc., @ 1% 0.01 1549.08

Total (a+b+c)
Overheads&Contractors Profit @13.615% 0.13615 4186.56
Rate per 10 sqm
Rate per 1 sqm
Say
CIVIL DATA 2020-21 : Page-773

Painting to new wood work and flush shutters with lappam finish , over a primary coat and painting two coats of synthetic enamel paint Grade-I VOC (Volatil
BLD-CSTN-12-6
88 Compound) content less than 50 grams/litre of approved shade including cost and conveyance of all materials to site cost of primer coat and all labour charges etc.
& 12-12-195
including applying sand paper on lappam coats for neat finish and overheads & contractors profit complete in all floors (APSS No.1200, 1207 & 1211).

MAT-01079 BMT-J.07 Cost of Putty for wood work 1 Kg 130.00 1 Kg


Primer Coat
MAT-01077 BMT-J.05 Cost of Wood Primer 0.70 Ltr 160.00 1 Ltr
LAB-00035 CSoR I - 35 1st Class Painter 0.21 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 2nd Class Painter 0.49 Nos. 565.00 1 Each
2 coats of Enamel painting
MAT-01102 BMT-J.29 Cost of Synthetic Enamel Paint 1.20 Ltr 270.00 1 Ltr
LAB-00035 CSoR I - 35 1st Class Painter 0.36 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 2nd Class Painter 0.84 Nos. 565.00 1 Each
Add for MAA @ 20% 0.20 1153.30
Sundries including brushes , ladders etc., @ 1% 0.01 1949.96

Overheads&Contractors Profit @13.615% 0.13615 1969.46


Rate per 10 sqm
Rate per 1 sqm
Say
1.70mts 1.80mts

Painting to old wood work and flush shutters with two coats of synthetic enamel paint Grade-II VOC (Volatile Organic Compound) content less than 50 gra
BLD-CSTN-12-
89 approved brand and shade including cost and conveyance of all materials to site and all labour charges etc. complete and overheads & contractors profit complete in
12-196
(APSS No.1200, 1207 & 1211) .

MAT-01102 BMT-J.29 Cost of Synthetic Enamel Paint 1.10 Ltr 270.00 1 Ltr
LAB-00035 CSoR I - 35 1st Class Painter 0.36 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 2nd Class Painter 0.84 Nos. 565.00 1 Each
Add for MAA @ 20% 0.20 728.40
Sundries including brushes , ladders etc., @ 1% 0.01 1171.08

Overheads&Contractors Profit @13.615% 0.13615 1182.79


Rate per 10 sqm
Rate per 1 sqm
Say
CIVIL DATA 2020-21 : Page-774

Painting primer coat on new wood work using red oxide Iron primer paint grade - 1 of approved brand including cost and conveyance of all materials to site ,
90 BLD-CSTN-12-7
charges etc., and overheads & contractors profit complete in all floors.(APSS No. 1201, 1212 & 1207).

Unit : 10 sqm
A.MATERIALS :
MAT-01075 BMT-J.03 Red oxide primer 0.70 Ltr 145.00 1 Ltr
B.LABOUR :
LAB-00035 CSoR I - 35 1st Class Painter 0.21 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 2nd Class Painter 0.49 Nos. 565.00 1 Each
Add for MAA @ 20% 0.20 424.90
Sundries including brushes , ladders etc., @ 1% 0.01 611.38

Overheads&Contractors Profit @13.615% 0.13615 617.49


Rate per 10 sqm
Rate per 1 sqm
Say

Painting two coats with synthetic enamel paint Grade-I VOC (Volatile Organic Compound) content less than 50 grams/litre to new iron work including
BLD-CSTN-12-
91 conveyance of all materials to site, incidental, operational and all labour charges etc., and overheads & contractors profit complete for finished item of work in all floors
12-197
1201, 1212 & 1207).

Unit : 10 sqm
A.MATERIALS :
MAT-01102 BMT-J.29 Cost of Synthetic Enamel Paint 1.10 Ltr 270.00 1 Ltr
B.LABOUR :
LAB-00035 CSoR I - 35 1st Class Painter 0.33 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 2nd Class Painter 0.77 Nos. 565.00 1 Each
Add for MAA @ 20% 0.20 667.70
Sundries including brushes , ladders etc., @ 1% 0.01 1098.24

Overheads&Contractors Profit @13.615% 0.13615 1109.22


Rate per 10 sqm
Rate per 1 sqm
Say
CIVIL DATA 2020-21 : Page-775

Painting two coats with synthetic enamel paint Grade-II VOC (Volatile Organic Compound) content less than 50 grams/litre over primer coat of red oxide to
BLD-CSTN-12-7
92 work including cost and conveyance of all materials to site, incidental, operational and all labour charges etc., and overheads & contractors profit complete for finishe
& 12-12-197
work in all floors. (SS No. 1201, 1212 & 1207).

Unit : 10 sqm
A.MATERIALS :
MAT-01075 BMT-J.03 Red oxide primer 0.70 Ltr 145.00 1 Ltr
MAT-01102 BMT-J.29 Cost of Synthetic Enamel Paint 1.10 Ltr 270.00 1 Ltr
B.LABOUR :
for primer coat
LAB-00035 CSoR I - 35 1st Class Painter 0.21 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 2nd Class Painter 0.49 Nos. 565.00 1 Each
for enamel painting
LAB-00035 CSoR I - 35 1st Class Painter 0.33 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 2nd Class Painter 0.77 Nos. 565.00 1 Each
Add for MAA @ 20% 0.20 1092.60
Sundries including brushes , ladders etc., @ 1% 0.01 1709.62

Overheads&Contractors Profit @13.615% 0.13615 1726.72


Rate per 10 sqm
Rate per 1 sqm
Say

Painting two coats with synthetic enamel paint Gr-I having VOC (Volatile Organic Compound) content less than 50 grams/litre to old iron work including
BLD-CSTN-12-
93 conveyance of all materials to site, incidental, operational and all labour charges and overheads & contractors profit etc., complete for finished item of work in all floors
12-198
1201, 1212 & 1207).

Unit : 10 sqm
A.MATERIALS :
MAT-01102 BMT-J.29 Cost of Synthetic Enamel Paint 0.90 Ltr 270.00 1 Ltr
B.LABOUR :
LAB-00035 CSoR I - 35 1st Class Painter 0.33 Nos. 705.00 1 Each
LAB-00093 CSoR II - 37 2nd Class Painter 0.77 Nos. 565.00 1 Each
Add for MAA @ 20% 0.20 667.70
Sundries including brushes , ladders etc., @ 1% 0.01 1044.24

Overheads&Contractors Profit @13.615% 0.13615 1054.68


Rate per 10 sqm
Rate per 1 sqm
Say
CIVIL DATA 2020-21 : Page-776

BLD-CSTN-12- Polishing two coats to teak wood doors using French spirit polish of approved brand for new wood work to teak wood frame and shutters including sand papering
94
15 surfaces etc. including cost and conveyance of all materials to site, all labour charges etc., complete for finished item of work in all floors.

A.Materials
MAT-01086 BMT-J.14 French polish 0.228 Ltrs 200.00 1 Ltrs
MAT-01082 BMT-J.10 cost of spirit 1.63 Ltrs 96.00 1 Ltrs
B.Labour
LAB-00035 CSoR I - 35 1st Class Painter 0.96 Nos. 705.00 1 Nos.
LAB-00093 CSoR II - 37 2nd Class Painter 2.24 Nos. 565.00 1 Nos.
Add for MAA @ 20% 0.20 1942.40
Sundries for terpentaine, sand paper, putty, wood filler,
0.01 2532.96
white woolen cloth, linseed oil, cotton etc., @ 1%

Overheads&Contractors Profit @13.615% 0.13615 2558.29


Rate per 10 sqm
Rate per 1 sqm
Say

Supply & applying Melamine Polish Glossy/ Matt finish to the wood works duly cleaning the surface and applying emery paper, sand the wood with 180 No., em
As per and then with 320 No., emery paper, clean & wipe off loose dust, applying suitable knifing paste filler / wood filler by putty knife / muslin pad, air dry for 2 - 3 hrs, sand
95 Amendment in and 320 No., emery paper, apply two component wood sealer, air dry for 24 hrs, sand with 320 No emery paper, applying one coat of approved spraying thinner (for
SoR 2011-12 applying one coat of approved brushing thinner or general purpose thinner (for brushing) and apply (either with spray or brush) two coats of approved brand melamine
cost & labour charges, emery papers, cost of thinner & melamine polish, over heads and contractors profit etc., complete for finished item of work

Unit : 1 sqm
A.Materials
MAT-01088 BMT-J.16 Melamine polish 0.065 Ltrs 325.00 1 Ltrs
MAT-01084 BMT-J.12 Thinner for Poly Uretene polish 0.033 Ltrs 140.00 1 Ltrs
B.Labour
LAB-00035 CSoR I - 35 1st Class Painter 0.24 Nos. 705.00 1 Nos.
LAB-00093 CSoR II - 37 2nd Class Painter 0.56 Nos. 565.00 1 Nos.
LAB-00120,
CSoR III - 3,4 Helper 0.80 Nos. 525.00 1 Nos.
LAB-00121
Add for MAA @ 20% 0.20 905.60
Sundries for spraying machine etc., @ 1% 0.01 1112.47

Overheads&Contractors Profit @13.615% 0.13615 1123.59


Rate per 1 sqm
Say
CIVIL DATA 2020-21 : Page-777

Supply & applying Poly-Urethane Water Proof Polish Glossy/ Matt finish to the wood works duly cleaning the surface and applying emery paper, sand the wood
No., emery paper and then with 320 No., emery paper, clean & wipe off loose dust, applying suitable knifing paste filler / wood filler by putty knife / muslin pad, air dr
As per hrs, sand with 180 and 320 No., emery paper, applying two component wood sealer, after the surface preparation applying one coat of approved spraying PU th
96 Amendment in spraying) / applying one coat of approved brushing PU thinner or general purpose thinner (for brushing) and apply one coat of PU by brush or spray, air-dry overn
SoR 2011-12 again with 180 No. emery paper and removing dust, applying second coat of PU, air drying for 4 - 6 Hrs, sand with 320 No emery paper, and applying (either with spray
two coats of approved brand PU including cost & labour charges, emery papers, cost of thinner & Poly-Urethane Water Proof Polish, over heads and contracors p
complete for finished item of work

Unit : 1 sqm
A.Materials
MAT-01089 BMT-J.17 Poly-Urethene polish Interior grade 0.065 Ltrs 750.00 1 Ltrs
MAT-01084 BMT-J.12 Thinner for Poly Uretene polish 0.033 Ltrs 140.00 1 Ltrs
B.Labour
LAB-00035 CSoR I - 35 1st Class Painter 0.24 Nos. 705.00 1 Nos.
LAB-00093 CSoR II - 37 2nd Class Painter 0.56 Nos. 565.00 1 Nos.
LAB-00120,
CSoR III - 3,4 Helper 0.80 Nos. 525.00 1 Nos.
LAB-00121
Add for MAA @ 20% 0.20 905.60
Sundries for spraying machine etc., @ 1% 0.01 1140.09

Overheads&Contractors Profit @13.615% 0.13615 1151.49


Rate per 1 sqm
Say

Supply & fixing of Rolling shutter made of 80 x 1.25 mm machine rolled CRCA laths, interlocked together through their entire length and jointed together at the end
locks, mounted on specially designed pipe shaft of 50mm dia nominal bore MS B class pipe with brackets, plates, guide channels, stoppers, bottom locking p
97
arrangements for inside & outside locking with push-pull operations including cost of hood cover and springs complete, painted with one coat of approved steel primer,
bearings, all accessories etc., overheads & contractors profit complete for finished item of work as per special spn: 1108

MAT-00895 BMT-F.29 Rate as per SSR 1.00 sqm 4025.00 1 sqm


Overheads&Contractors Profit @13.615% 0.13615 4025.00
Rate per 1 sqm
Say

Supplying & fixing collapsible steel shutters with vertical, double channel of 20 x10x2 mm of 100 mm centre, Bracers with flat iron 40x40x6 mm with 38 mm dia ste
the top, bottom and side vertical frames of the collapsible gate with 65x65mmx8mm MS Angle and middle guide rail at site height with 65mmx8mm MS flat for the
98
guide and fixed with necessary hold fasts, bolts, nuts, rivets, locking arrangements, stoppers, handles, all accessories all fixtures and painted with one coat of appro
primer etc., overheads & contractors profit complete for finished item of work as per special spn 1105
MAT-00896 BMT-F.30 Rate as per SSR 1.00 sqm 3508.00 1 sqm
Overheads&Contractors Profit @13.615% 0.14 3508.00
Rate per 1 sqm
CIVIL DATA 2020-21 : Page-778

Say

Providing specialized polysulphide sealant treatment to the expansion joints on terrace (Size : 25mm x 12mm): Application of one coat of-High performance
designed SBR latex polymer based bonding agent– ROOFBOND SBR (Armstrong) / POWER n BOND SBR (EBT) / NITOBOND SBR (Fosroc) ZORIBOND SBR (PMC
LATEX (Sika) WATERSHIELD BOND SBRASTM - C 920 -95 /DIN 18549 TT -S-00227E or equivalent mixing with cement as per manufacturers c] Providing and app
Acrylic Polymer modified reinstatement concrete/mortar admixture with - OOFCRETE AR (Armstrong ) / ZORIGROUT CMG (PMCC) / POWER n GUARD ARM
WATERSHIELD AR / Fosroc to finish the damaged edges of joint and making the groove. d]. Providing and fixing of masking tape on top of the joint both sides. e]. Prov
fixing of Back up support material of Polyethelene foam to leave the depth of 12mm on the joint. f]. Providing and application of one coat of polysulphide prim
99
Polysulphide primer on inner edge on joints. g]. Providing and application of Two part Polysulphide sealant to a width of 25mm and 12mm depth with - ROOF
(Armstrong ) / POWER n SEAL PS (EBT) /NITOSEAL PS 200 (Fosroc)/ ZORISEAL PS (PMCC) / SIKA POLYSULPHIDE (Sika) / WATERSHIELD PSComplies with BS
or equavalent with putty knife and neat finish. h]. Removing of masking tape and providing and application of two coats of Acrylic elastomeric cementitious coati
ROOFSEAL PS (Armstrong ) / POWER n SEAL PS (EBT) /NITOSEAL PS 200 (Fosroc)/ ZORISEAL PS (PMCC) / SIKA POLYSULPHIDE (Sika) / WATERSHIELD PS
cost and conveyance of all materials, labour charges, overheads & contractors profit etc., complete for finished item of work

MAT-05365 BMT-H.78 Rate as per SSR 1.00 RM 702.00 1 RM


Overheads&Contractors Profit @13.615% 0.13615 702.00
Rate per 1 RM
Say

Providing and fixing of Expansion joint filler board for buildings, columns, beams and slabs 25 mm thick including cost and conveyance of all materials
100
incidental, operational, labour charges etc.overheads & contractors profit complete for finished item of work as per approved drawing for all floors

MAT-01517 BMT-U.05 Rate as per SSR 1.00 sqm 360.00 1 sqm


Overheads&Contractors Profit @13.615% 0.13615 360.00
Rate per 1 sqm
Say
1.70mts 1.80mts Alround M.S flat of
size 25 x 6mm

Providing and fixing of 24 gauge alluminium sheet over expansion joint groove of width 15cm fixed to walls / columns at one edge and resting over the o
walls/columns concealing expansion joint with slotted holes for free edge of aluminium sheet to facilitate free movement of aluminium sheet over the finished s
101
expansion joint and wall face using sheet metal screws with nylon receiver complete including cost and conveyance of all materials to site, all incidental, operation
charges , overheads & contractors profit etc., complete for finished item of work as per approved drawing (for all floors for vertical joints and bottom of slab)

MAT-01590 BMS-W.18 Cost of aluminium sheet 24 gauge 1.00 sqm 282.00 1 sqm
Add for labour charges including cost of nails, making
6.60 RM 25.00 1 RM
holes to wall and in aluminium sheet etc.
Rate per 1 sqm
Rate per 1 RM
Overheads&Contractors Profit @13.615% 0.13615 68.00
CIVIL DATA 2020-21 : Page-779

Say

Supplying and fixing aluminium composite cladding 4mm thick of approved make with skin material 0.50 mm thick aluminium sheet cover material natural po
aluminium cladding panel fixed with extruded aluminium basis frame (50x25x1.5mm) angle cleats, weather sealants, rivets, GI brackets all as approved, using suitabl
102
structural steel work including necessary accessories complete in all respects including all scaffolding and labour charges , overheads & contractors profit etc., com
finished item of work but excluding cost of structural steel fabrication if any.

MAT-01586 BMS-W.14 Rate as per SSR 1.00 sqm 2946.00 1 sqm


Overheads&Contractors Profit @13.615% 0.13615 2946.00
Rate per 1 sqm
Say

Providing and Fixing Structural Glazing fabricated from Roll formed sections made of Pre-painted Steel / Powder coated (Base steel as per IS 513 of ‘D
galvanized as per IS 277 with Zinc of 120 Gm/sqm) with total coated thickness of 0.72mm. The glass holding section made of 304 grade stainless steel of 0.6mm thick a
design requirement & calculations as given in IS: 875. Primer coat with epoxy primer of 5 – 7 microns thick, finish painted with a polyester paint of 12-16 microns thick
103 coated with Alkyd backer of 5-7 microns or powder coated with pure polyester powder up to 50-60 microns thick. The vertical section should be of 50mm x100mm x
33mm x 58mm x 0.72mm for frame horizontal section, stiffener section should be 48mm x 98mm x 1mm, cover profiles sections should be of 20mm x 58mm x 0.58m
holding section should be of 37mm x 37mm & 37mm x 18mm. Including 5mm thick Ocean Blue reflective glass. Brackets made of CRCA powder coated/Electroplated
used to connect vertical to horizontal, vertical to slab, to fix verticals at top & bottom as per site requirement.

Gasket made of Ethyl Propylene Diamine Monomer. Natural cure, with Good U.V. Resistance Silicon to be used. Wall fixing of sections to concrete/masonry wall shou
self-expanding cap & screws. The rate is inclusive of cost and conveyance of all materials to site, all labour charges, incidental charges, cost of all consumables
scaffolding charges, form work , overheads & contractors profit etc., complete for finished item of work in all floors.
MAT-01489 BMT - Q.01 Rate as per SSR 1.00 sqm 7150.00 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 7150.00
Rate per 1 sqm
Say

Providing and Fixing Top Hung shutters in Structural Glazing fabricated from Roll formed sections made of Pre-painted Steel / Powder coated (Base steel
513 of ‘D’ quality, galvanized as per IS 277 with Zinc of 120 Gm/sqm) with total coated thickness of 0.72mm. The glass holding section made of 304 grade stainles
0.6mm thick. Galvanized steel sections are to be used as stiffeners inside the colour coated steel/powder coated sections as per the design requirement. Design ca
are made to suit wind pressures as given in IS 875. Primer coat with epoxy primer of 5-7 microns thick and back coated with Alkyd backer of 5-7 microns or powder co
104
pure polyester powder up to 50-60 microns thick. The outer frame should be of 20mm x 58mm x 0.6mm, Shutter section should be of 58mm x 33mm x 0.72 mm
section should be 56mm x 31mm x 1mm. EARL Bihari Hinges – 2 Nos for each shutter and Aluminium Stays – 2 Nos. for each shutter, Aluminium Handle – 1 no
shutter. The rate is inclusive of cost and conveyance of all materials to site, all labour charges, incidental charges, cost of all consumables etc. and scaffolding char
work, overheads & contractor profit etc. complete for finished item of work in all floors.

MAT-01490 BMT - Q.02 Rate as per SSR 1.00 sqm 5645.00 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 5645.00
CIVIL DATA 2020-21 : Page-780

Rate per 1 sqm


Say

Providing and fixing in true horizontal level 13 mm - Mineral Fiber Ceiling tile of 595 x 595 (Square edge Fissura fine model) using hot dipped Galvanized Ste
BLD-CSTN-10-
exposed surface with pre-coated capping, main Tee of size 24 x 32 mm at every 1200 mm c/c maximum and rotary stitched cross tee of size 24 x 27 mm at every 60
33 & vide Page
105 and sub-cross tee of size 24 mm x 25 mm at 1200 mm c/c and wall angle of size 19 x 19 mm fixed to periphery of the wall and the above grid is suspended at every 120
No. 391 of SoR
in both directions using 2.0 mm thick pre-straightened GI Wire including cost and conveyance of all materials and labour charges such as cutting , fixing of standing
2011-12
work exposing roof making, overheads & contractor profit etc., complete for finished item of work in all floor in all floors.

Unit 1 sqm
A) Material requirement
MAT-01315 BMT-M.80 13mm Mineral Fiber sheet 600 x 600 1.00 sqm 353.00 1 sqm
Hotdipped GI Angle - Precoated - Grid -
MAT-01246 BMT-M.11 0.40 RM 37.00 1 RM
19mmx19mmX0.7mm
MAT-01247 & BMT-M.12 & Polyster painted GI - T section - 1200mm - 24x32mm and
1.60 RM 50.00 1 RM
MAT-01248 13 24x25mm (sub-cross Tee)
MAT-01249 BMT-M.14 Polyster painted GI-T Section - 300mm - 24mm x 27mm 1.60 RM 49.00 1 RM
MAT-01262 BMT-M.27 GI Rod - prestraightened - 2.0mm dia -Connecting Rod 1.28 RM 10.00 1 RM
MAT-01253 BMT-M.18 6mm Nylon Rawl Plug 1.28 Nos. 4.00 1 No.
B) Labour charges
LAB-00004 CSoR I - 4 1st Class Carpenter 0.12 Nos. 705.00 1 No.
LAB-00060 CSoR II - 4 2nd Class Carpenter 0.12 Nos. 565.00 1 No.
LAB-00004 CSoR I - 4 Power Saw cutter - Hand Operated - Operator 0.012 Nos. 705.00 1 No.
LAB-00004 CSoR I - 4 Power Drill - Hand Operated - Operator 0.012 Nos. 705.00 1 No.
LAB-00120,
CSoR III - 3,4 Unskilled Mazdoor 0.072 Nos. 525.00 1 No.
LAB-00121
Add for MAA @ 20% 0.20 207.12
C) Machinery
MAT-00206 BMC-X.02 Power Saw cutter - Hand Operated - Hire Charges 0.32 Hours 132.00 1 hour
MAT-00207 BMC-X.03 Power Drill - Hand Operated - Hire Charges 0.32 Hours 121.00 1 hour

Scaffolding charges 1% 0.01 873.62


Basic Cost per 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 882.36
Rate per 1 sqm
Say
CIVIL DATA 2020-21 : Page-781

Providing and fixing in true horizontal level 15 mm - Mineral Fiber Ceiling tile of 595 x 595 (Square edge Fissura fine model) using hot dipped Galvanized Ste
BLD-CSTN-10-
exposed surface with pre-coated capping, main Tee of size 24 x 32 mm at every 1200 mm c/c maximum and rotary stitched cross tee of size 24 x 27 mm at every 60
33 & vide Page
106 and sub-cross tee of size 24 mm x 25 mm at 1200 mm c/c and wall angle of size 19 x 19 mm fixed to periphery of the wall and the above grid is suspended at every 120
No. 391 of SoR
in both directions using 2.0 mm thick pre-straightened GI Wire including cost and conveyance of all materials and labour charges such as cutting , fixing of standing
2011-12
work exposing roof making, overheads & contractor profit etc., complete for finished item of work in all floor in all floors.

Unit 1 sqm
A) Material requirement
MAT-01319 BMT-M.84 15mm Mineral Fiber sheet 600 x 600 1.00 sqm 518.00 1 sqm
Hotdipped GI Angle - Precoated - Grid -
MAT-01246 BMT-M.11 0.40 RM 37.00 1 RM
19mmx19mmX0.7mm
MAT-01247 & BMT-M.12 & Polyster painted GI - T section - 1200mm - 24x32mm and
1.60 RM 50.00 1 RM
MAT-01248 13 24x25mm (sub-cross Tee)
MAT-01249 BMT-M.14 Polyster painted GI-T Section - 300mm - 24mm x 27mm 1.60 RM 49.00 1 RM
MAT-01262 BMT-M.27 GI Rod - prestraightened - 2.0mm dia -Connecting Rod 1.28 RM 10.00 1 RM
MAT-01253 BMT-M.18 6mm Nylon Rawl Plug 1.28 Nos. 4.00 1 No.
B) Labour charges
LAB-00004 CSoR I - 4 1st Class Carpenter 0.12 Nos. 705.00 1 No.
LAB-00060 CSoR II - 4 2nd Class Carpenter 0.12 Nos. 565.00 1 No.
LAB-00004 CSoR I - 4 Power Saw cutter - Hand Operated - Operator 0.012 Nos. 705.00 1 No.
LAB-00004 CSoR I - 4 Power Drill - Hand Operated - Operator 0.012 Nos. 705.00 1 No.
LAB-00120,
CSoR III - 3,4 Unskilled Mazdoor 0.072 Nos. 525.00 1 No.
LAB-00121
Add for MAA @ 20% 0.20 207.12
C) Machinery
MAT-00206 BMC-X.02 Power Saw cutter - Hand Operated - Hire Charges 0.32 Hours 132.00 1 hour
MAT-00207 BMC-X.03 Power Drill - Hand Operated - Hire Charges 0.32 Hours 121.00 1 hour

Scaffolding charges 1% 0.01 1038.62


Basic Cost per 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 1049.01
Rate per 1 sqm
Say
CIVIL DATA 2020-21 : Page-782

Supplying and fixing Gyp Board Suspended regular single layer false ceiling (GS-MFSC-4.1) using 12.5 mm thick Gyp Board conforming to IS 2095 - 1993 fixi
steel GI perimeter channels of size 20 mm x 27 mm x 30 mm(web) of 0.55 mm thick along the perimeter of ceiling screw fixed to brick work/ partition at 610 mm
BLD-CSTN-10-
suspending the frame work using Intermediate channels (45 mm x 15mm x 15mm x 0.9 mm) from soffit at 1220 mm c/c with ceiling angle (25 mm x 10 mm x 0.55 mm)
31 & vide Page
107 GI Cleat and steel expansion fasteners & connecting clip to the ceiling channels (with knurled web of 51.5 mm x 26 mm x 10.5 mm x 0.55 mm) fixed in direction perpen
No. 389 of SoR
the intermediate channel at 457 mm c/c and fixing the 12.5 mm tapered edge Gypboard with 25 mm drywall screws at 230 mm c/c & jointing and finishing using joint c
2011-12
and paper tape to have a flush look including filling the tapered & square edges with jointing compound, two coats of drywall top coat including overheads and contra
etc., complete for finished item of work
Unit - 1 sqm A) Material requirement as per India Gypsum
12.5mm Gypboard
MAT-01238 BMT-M.03 1219mm x 1829mm size Boards 1.03 sqm 221.00 1 sqm
MAT-01239 BMT-M.04 GI Ceiling Angle - 25mm x 10mm x 0.5mm 0.64 RM 78.00 1 RM
GI Ceiling section - 51.5mm x 26mm x 10.5mm x 0.55mm
MAT-01240 BMT-M.05 0.84 RM 106.00 1 RM
thick
MAT-01241 BMT-M.06 Intermediate channel - 45mm x 15mm x 15mm x 0.9mm 0.84 RM 78.00 1 RM
Perimeter channel - 20mm x 27mm x 30mm (web) of
MAT-01242 BMT-M.07 0.40 RM 69.00 1 RM
0.55mm thick
MAT-01252 BMT-M.17 Connecting Clips 1.84 Nos. 10.00 1 No.
MAT-01253 BMT-M.18 Rawl Plug 0.64 Nos. 4.00 1 No.
MAT-01255 BMT-M.20 Soffit Cleats 0.64 Nos. 5.00 1 No.
MAT-01256 BMT-M.21 Drywall screws - 25mm 18.00 Nos. 4.00 1 No.
MAT-01257 BMT-M.22 Jointing Compound 0.55 Kgs. 32.00 1 Kg.
MAT-01258 BMT-M.23 Jointing Paper tape 1.46 RM 6.00 1 RM
MAT-01259 BMT-M.24 Drywall top coat 0.15 Ltrs 150.00 1 Ltr
B) Labour Charges
LAB-00004 CSoR I - 4 1st Class Carpenter 0.12 Nos. 705.00 1 No.
LAB-00060 CSoR II - 4 2nd Class Carpenter 0.12 Nos. 565.00 1 No.
LAB-00035 CSoR I - 35 1st Class Painter 0.024 Nos. 705.00 1 No.
LAB-00093 CSoR II - 37 2nd Class Painter 0.024 Nos. 565.00 1 No.
LAB-00004 CSoR I - 4 Power Saw cutter - Hand Operated - Operator 0.012 Nos. 705.00 1 No.
LAB-00004 CSoR I - 4 Power Drill - Hand Operated - Operator 0.024 Nos. 705.00 1 No.
LAB-00120, LAB-
CSoR III - 3,4 Unskilled Mazdoor 0.072 Nos. 525.00 1 No.
00121
Add for MAA @ 20% 0.20 246.06
C) Machinery
MAT-00206 BMC-X.02 Power Saw cutter - Hand Operated - Hire Charges 0.32 Hours 132.00 1 Hour
MAT-00207 BMC-X.03 Power Drill - Hand Operated - Hire Charges 0.64 Hours 121.00 1 Hour

Scaffolding charges 1% 0.01 1019.68


Rate per 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 1029.88
CIVIL DATA 2020-21 : Page-783

Say

Supplying and fixing Gyp board Fine line Grid false ceiling (GS-FLC-4.6)using 12.5mm thick Gyp Board sheet tiles of size 595mm x 595mm conforming to IS 20
BLD-CSTN-10- fixing to Gyp steel precoated GI wall angle of size 25mm x 25mm x 0.70mm thick along the perimeter of ceiling screw fixed to brick work / partition at 610mm center to c
32 & vide Page suspending the frame work using precoated GI Tee section (24mm x 38mm x 0.7mm) from soffit at 1220mm center to center fixed with GI Soffit Cleat, rawl plugs
108
No. 390 of SoR expansion fasteners & connecting clip to the GI Tee section with 4mm dia GI rod with galvanised spring steel level clip of PVC unversal holding clips system at 1200mm
2011-12 center and fixing the 12.5mm Gypboard sheet tiles of size 595mm x 595mm and finishing two coats of drywall top coat, overheads and contractor profit complete for fini
of work in all floors.

Unit - 1 sqm
A) Material requirement as per India Gypsum
12.5mm Gypboard Tiles
MAT-01236 BMT-M.01 595mm x 595mm 1.00 sqm 275.00 1 sqm
MAT-01243 BMT-M.08 GI Angle - Precoated - 25mm x 25mm x0.7mm 0.40 RM 62.00 1 RM

GI pre coated - T section - 3600mm long - 24mm x 38mm


MAT-01245 BMT-M.10 3.20 RM 60.00 1 RM
x 0.7mm thick
MAT-01261 BMT-M.26 GI Rod - 4mm dia - Connecting Rod 1.28 RM 15.00 1 RM
MAT-01253 BMT-M.18 Rawl Plug 1.28 Nos. 4.00 1 No.
MAT-01255 BMT-M.20 Soffit Cleats 1.28 Nos. 5.00 1 No.
MAT-01260 BMT-M.25 Universal Holding Clips 5.36 Nos. 4.00 1 No.
MAT-01259 BMT-M.24 Drywall Top coat 0.15 Ltrs 150.00 1 Ltr
B) Labour Charges
LAB-00004 CSoR I - 4 1st Class Carpenter 0.12 Nos. 705.00 1 No.
LAB-00060 CSoR II - 4 2nd Class Carpenter 0.12 Nos. 565.00 1 No.
LAB-00035 CSoR I - 35 1st Class Painter 0.02 Nos. 705.00 1 No.
LAB-00093 CSoR II - 37 2nd Class Painter 0.024 Nos. 565.00 1 No.
LAB-00004 CSoR I - 4 Power Saw cutter - Hand Operated - Operator 0.012 Nos. 705.00 1 No.
LAB-00004 CSoR I - 4 Power Drill - Hand Operated - Operator 0.012 Nos. 705.00 1 No.
LAB-00120,
CSoR III - 3,4 Unskilled Mazdoor 0.072 Nos. 525.00 1 No.
LAB-00121
Add for MAA @ 20% 0.20 237.60
C) Machinery
MAT-00206 BMC-X.02 Power Saw cutter - Hand Operated - Hire Charges 0.32 Hours 132.00 1 Hour
MAT-00207 BMC-X.03 Power Drill - Hand Operated - Hire Charges 0.32 Hours 121.00 1 Hour

Scaffolding charges @ 1% 0.01 932.54


Basic Cost per 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 941.87
CIVIL DATA 2020-21 : Page-784

Rate per 1 sqm


Say

Providing and fixing Thermocole False ceiling in true horizontal level 600mm x 600mm using 12mm thick Thermocole sheet, anodized Aluminium Tee section
BLD-CSTN-10-
24.50mm x 24.0mm x 2.4mm in grid with cross tee of size 24mm x 24.5mm at every 600mm center to center and anodised aluminium wall angle of size 24mm x 24m
34 & vide Page
109 periphery of the wall and the above grid is suspended at every 1200mm center to center in both directions using 2.0mm thick GI wire for finished of size 600mm
No. 392 of SoR
including cost and conveyance of all materials and labour charges such as cutting , fixing of standing of frame work exposing roof complete for finished item of work in
2011-12
(The rate is inclusive of overheads & contractor profit).
Unit 1 sqm
A) Material requirement
MAT-01271 BMT-M.36 12mm Thermocole sheet 1.00 sqm 32.00 1 sqm
MAT-01250 BMT-M.15 Aluminium angle - 24mmx 24mm 0.40 RM 33.00 1 RM
MAT-01251 BMT-M.16 Anodised Aluminium T section - 24mm x 24.5mm x 2.4mm 3.20 RM 32.00 1 RM
MAT-01262 BMT-M.27 GI rod-prestraightened 2.0mm dia. - Connecting rod 1.28 Nos. 10.00 1 No.
MAT-01253 BMT-M.18 Rawl plugs 1.28 Nos. 4.00 1 No.
B) Labour charges
LAB-00004 CSoR I - 4 1st Class Carpenter 0.11 Nos. 705.00 1 No.
LAB-00060 CSoR II - 4 2nd Class Carpenter 0.11 Nos. 565.00 1 No.
LAB-00004 CSoR I - 4 Power Saw cutter - Hand Operated - Operator 0.02 Nos. 705.00 1 No.
LAB-00004 CSoR I - 4 Power Drill - Hand Operated - Operator 0.04 Nos. 705.00 1 No.
LAB-00120,
CSoR III - 3,4 Unskilled Mazdoor 0.20 Nos. 525.00 1 No.
LAB-00121
Add for MAA @ 20% 0.20 284.46
C) Machinery
MAT-00206 BMC-X.02 Power Saw cutter - Hand Operated - Hire Charges 0.16 Hours 132.00 1 hour
MAT-00207 BMC-X.03 Power Drill - Hand Operated - Hire Charges 0.32 Hours 121.00 1 hour

Scaffolding charges 1% 0.01 566.71


Basic Cost per 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 572.38
Rate per 1 sqm
Say

Supplying and fixing 50mm dia nominal bore Medium Grade properties & weight as per IS 1239 ISI mark MS Tube for fixing of GI Sheet including cost and conveya
110
materials to work site and all operational, incidental, labour charges etc., complete for finished item of work in all floors for stair case head room roof.

MAT-00871 BMT-F.04 Cost of MS Tube 5.10 Kgs 76.00 1 Kgs


LAB-00420 BMM-V.14 Labour charges for fabrication 5.10 Kgs 30.00 1 Kgs
LAB-00421 BMM-V.15 Labour charges for fixing 5.10 Kgs 6.00 Kgs
Add for MAA @ 20% 0.20 91.80
Rate per 1 RM
CIVIL DATA 2020-21 : Page-785

Overheads&Contractors Profit @13.615% 0.13615 589.56

Say

Supplying and fixing of Pre-painted Galvalume Trapezoidal Profile Roofing sheets with 0.50mm thickness, Coating: Alu-Zinc coating AZ150 GSM. Tensile Stre
MPA. Paint coating: Regular Modified Polyester painting. Painting Thickness (Top): 18 to 20 Microns, (Bottom): 5 to 7 Microns. Sheet Width: 1.020, Length: Maximum 1
111 BLD-CSTN-8-1 with Regular Range Colours fixed with G.I ‘J’ bolts & nuts 8 mm dia with bitumen & G.I limpet washers filled with white lead & including a coat of approved steel prime
coats of approved paint on over lapping of sheets complete (up to a pitch of 600) etc., complete, excluding the cost of purlins, rafters, trusses including cost and conv
all materials , labour charges , overheads and contractors profit etc., complete for finished item of work in all floors.

Unit : 10 sqm
A. MATERIALS:
MAT-01625 BMS-W.55 Galvalume sheet 0.50mm thick 10.50 sqm 407.00 1 sqm
MAT-01632 BMS-W.62 G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884 47.91 Nos. 6.00 1 No.

G.I ‘J’ bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos = 810 nos.


MAT-01634 BMS-W.64 43.90 Nos. 11.00 1 No.
with washers or srews, if wooden battens used.

MAT-01636 BMS-W.66 Limpet washers (for scam & ‘J’ bolts) 91.82 Nos. 2.00 1 No.
MAT-01637 BMS-W.67 Bitumen washers 91.82 Nos. 2.00 1 No.
B. LABOUR
For roofing
LAB-00060 CSoR II - 4 Carpenter II class 0.84 Nos. 565.00 1 No.
LAB-00120,
CSoR III - 3,4 Man mazdoor (beldar) 0.91 Nos. 525.00 1 No.
LAB-00121
Add for MAA @ 20% 0.20 952.35
Rate per 10 sqm
Rate per 1 sqm
Overheads&Contractors Profit @13.615% 0.13615 655.40
Rate per 1 sqm
Say

Supply and delivery of encapsulated plastic steps for man holes manufactured as per companies standard specification including cost of materials packing as per co
1 BLD-CSTN-8-1 standards, loading, transportation, unloading and stacking at site of work , and taxes such as complete sales tax,C.E.D and others etc., as applicable including labou
for fixing, overheads and contractor profit etc., complete for finished item of work.

Overheads&C
Rate as per
ontractors
MAT-01310
SSR
Profit 1.00 sqm 166.00 1 sqm 166.00
@13.615% 0.13615 166.00 22.60
CIVIL DATA 2020-21 : Page-786

Rate for 1
sqm 188.60
Say 189

Supply and placing in postion water stopper 8 - 10 mm thick 310 mm wide including cost and conveyance of all materials to site and sales and other taxes on all materi
1 BLD-CSTN-8-1
etc., complete for finished item of work

Overheads&C
Rate as per
ontractors
MAT-01310
SSR
Profit 1.00 sqm 495.00 1 sqm 495.00
@13.615% 0.13615 495.00 67.39
Rate for 1
sqm 562.39
Say 562

Providing, laying Reinforced cement concrete Hume pipes of 300mm Dia., NP-3 class for cross ducts including cost and conveyance of Pipes etc., complete an
2 charges for laying, jointing of 300mm dia. R.C.C Hume pipes in position including lifting, aligning, lowering and hoisting etc., as per drawing and as per MoRT&H Spe
2900, 2905 and 2906 (5th revision) and IRC Special Publication No: 13 and as directed by the Engineer-in-Charge for finished item of work

Unit : metre Page 272,273 of MoRT&H SDB


Taking output = 12.5 metre
300 mm Dia.,
a) Labour
LAB-00011 CSoR I -11 Mate 0.14 day 630.00 1 day
LAB-00011 CSoR I -11 Mason 0.50 day 525.00 1.00 day
LAB-00120,
CSoR III - 3, 4 Mazdoor (Unskilled) 3.00 day 525.00 1.00 day
LAB-00121
Add for MAA @ 20% 0.20 1837.50
b) Material
Cost of 300mm Dia., pipes 12.50 RM 917 1 RM
12.50 75
RM 1 RM
Lead charges 15 KM
Rate for 12.5 RM
Rate for 1 RM
Overheads&Contractors Profit @13.615% 0.13615 1175.77
Total
Rate per 1 RM Say
CIVIL DATA 2020-21 : Page-787

ROAD WORKS

Forming embankment with Side earth by mechanical means including pre-watering of soil, removal of top soil, excavation of soils, depositing the soils on the emb
spreading soils, breaking clods, sectioning and consolidation with Vibratory Road Roller @ OMC to meet requirement of table 300-2 of MoRT&H, including al
112 RBR-EECD-4 - 4 -
operational charges of T&P and seigniorage charges, complete for finished item of work as per MoRT&H specification 305 (4th revision) including cost and conveya
materials , labour charges , overheads and contractors profit etc., complete for finished item of work (Payment will be made based on level for finished item of work).

Unit = cum
Taking output = 100 cum 100.00 Cum
a)  Labour
Mate - day
LAB-00120,
CSoR III - 3, 4 Mazdoor (Unskilled) 0.52 day 525.00 1.00 day
LAB-00121
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60 cum
HIR-00052 CSoR 4 1.67 hr 3483.70 1 hr
per hour
HIR-00073 CSoR 3 Motor grader for grading @ 200 cum per hour 1.00 hour 3722.00 1 hr
HIR-00076 CSoR 10 Water tanker 6 kl capacity 4.00 hour 806.00 1 hr
HIR-00062 CSoR 7 Vibratory Roller 80 - 100 kN 1.00 hour 3479.20 1 hr
MAT-00332, CSoR M -
c) Water 24 Kl 116.00 1 Kl
MAT-00333 189(a), (b)
Total
d) Overheads & Contractors Profit 0.13615 19299.98
Cost for 100 cum
Rate per cum = (a+b+c+d)/100
Rate per cum Say
CIVIL DATA 2020-21 : Page-788

Construction of Granular sub-base by providing HBG material confirming to Grading - III of MORT & H Table 400-2 including cost and conveyance of all materi
site and spreading in uniform layers with motor grader or by approved means, on prepared surface mixing by mix place method with Rotavator/ approved means, at
RBR-SBSS-
113 compacting with vibratory roller to achieve the desired density etc., complete for finished item of work as per MoRT& H specification 401 (4th revision) and as direct
2/2(A)
Engineer- in - charge including cost and conveyance of all materials , labour charges , overheads and contractors profit etc., complete for finished item of work (Payme
made based on levels for finished item of work)
Unit : 1 cum
Taking output : 300 cum
a) Labour
Mate day 1 day
LAB-00120,
CSoR III - 3, 4 Mazdoor (Unskilled) 2.40 day 525.00 1.00 day
LAB-00121
LAB-00120,
CSoR III - 3, 4 Mazdoor (Unskilled) 8.00 day 525.00 1.00 day
LAB-00121
Add for MAA @ 20% 0.20 5460.00
b) Machinery
HIR-00073 CSoR 3 Mortar Grader 110 HP @ 50 cum per hour 6.00 hr 3722.00 1 hr
HIR-00062 CSoR 7 Vibratory roller 8T 6.00 hr 3479.20 1 hr
HIR-00076 CSoR 10 Water tanker 6 KL 3.00 hr 806.00 1 hr
c) Material Grading III
Coarse graded Granular sub-base Material 9.5 mm to
MAT-00194 CSoR M - 025 255.00 cum 1038.30 1 cum
4.75 mm @ 66%
Coarse graded Granular sub-base Material 2.36 mm &
MAT-00191 CSoR M - 022 below @ 34% 129.00 cum 931.30 1 cum
MAT-00332, CSoR M -
Water 18.00 Kl 116.00 1 Kl
MAT-00333 189(a), (b)

Basic rate per 1 cum GSB


Overheads&Contractors Profit @13.615% 0.13615 1463.90
Total
Rate per 1 cum Say
CIVIL DATA 2020-21 : Page-789

Cement Concrete Pavement

Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a pre
base, with 43 grade cement or any other type as per Clause 1501.2.2 M 30 (Grade), coarse and fine aggregates conforming to IS : 383, maximum in a concrete mixer o
than 0.2 cum capacity and appropeiate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 mic
polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with sholvels, rakes, compacted using needle, scareed
114 RBR-CCPV-5
vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant, dowel b
approaches to bridge / culvert and construction joints, admixtures as approved, curing of concrete slabs for 14- days, curing compound (where specified) and water fi
lines and grade as per drawing and Technical Specification Clause 1501 MORD including cost and conveyance of all materials , labour charges , overheads and c
profit etc., complete for finished item of work.

Unit = cum
Taking output = 75 cum (172.50 t) 75 cum
(100 x 3.75 x 0.200)
a)  Labour
Mate day -
LAB-00011 CSoR I -11 Mason 1st Class 5.00 day 630.00 1 day
LAB-00091 CSoR II - 35 Mason (2nd class) 5.00 day 565.00 1 day
LAB-00120,
CSoR III - 3, 4 Mazdoor (Unskilled) 150.00 day 525.00 1 day
LAB-00121
LAB-00120,
CSoR III - 3, 4 Mazdoor (Skilled) 6.00 day 525.00 1 day
LAB-00121
LAB-00120,
CSoR III - 3, 4 Mazdoor ( semi skilled) 6.00 day 525.00 1 day
LAB-00121
Blacksmith for cutting of dowel bars including removal of
LAB-00002 CSoR I - 2 1.00 day 590.00 1 day
burrs, fabrications & fixing of dowel bars.
Add for MAA @ 20% 0.20 91615.00
b) Machinery
HIR-00016& LAB- Concrete mixer 0.28 / 0.4 cum capacity (6 mixers) with
CSoR 16 36.00 hour 188.10 1 hour
00329 weigh batcher and suitable capacity calibrated water tank
HIR-00150 CSoR 16 crew charges 36.00 hour 306.80 1 hour
Add for MAA @ 20% 0.20 11044.80
HIR-00040& LAB-
CSoR 40 Needle vibrator hire charges 9.00 hour 38.20 1 hour
00352
HIR-00174 CSoR 40 crew charges 9.00 hour 220.90 1 hour
Add for MAA @ 20% 0.20 1988.10
Screed vibrator 9.00 hour 50.00 1 hour
Plate vibrator 9.00 hour 48.00 1 hour
Concrete joint cutting machine for initial & final cuts 4.00 hour 100.00 1 hour
HIR-00076 CSoR 10 Water tanker 6 kl capacity) 5.00 hour 806.00 1 hour
CIVIL DATA 2020-21 : Page-790

HIR-00003& LAB-
CSoR 3 Air Compressor 2 hour 1452.80 1 hour
00319
crew charges 2.00 hour 294.50 1 hour
Add for MAA @ 20% 0.20 589.00
c) Material

Crushed stone coarse aggregates, grading will be as per


Clause 1501.2.4.1 (Table 1500.1) of specifications @ 0.90 67.50 cum 1764.80 1 cum
cum/cum of concrete (25 mm & 12.5 mm blending)

Sand as per IS:383 and conforming to Clause 1500.2.4.2


MAT-00027 CSoR 27(a) 33.75 cum 1061.00 1 cum
@ 0.45 cum/cum of concrete
Cement 26.25 MT 4220.00 1 MT
Polythene sheet 125 micron 412.50 sqm 15.25 1 sqm
Mild steel dowel bar 25 mm dia of grade S 240. 500 mm
long 20 Nos. at culvert/bridge slab and at construction
joint including 5 per cent wastage.
(4 x 20 x 0.500) + 5 per cent wastage = 42 m @ 2.80 kg
0.12 MT 63000.00 1 MT
per m = 117.6 kg.
Bituminous sealant 800 ml per joint for 23 joints ( BMT-
19.00 litre 96.00 1 litre
H.93)(SoR 2014-15)
MAT-00536 CSoR 174 Jute rope 12 mm dia including 5 per cent wastage 90.00 RM 8.35 1 RM
Polythene sheathing, covering 2/3rd dowel bars (20x23)
483.00 Nos. 0.60 1 No.
and tight fit including 5 per cent wastage
MAT-05375 BMT-H.88 Plasticizer 200ml to 300ml per 50 kgs of cement 122.00 litre 76.00 1 litre
MAT-00332, CSoR M -
Water for curing 18.00 kl 116.00 1 kl
MAT-00333 189(a), (b)
MAT-01514 BMT-U.02 Joint filler board 20 mm thick as per IS:1838 3.00 sqm 824.00 1 sqm
Total
d) Formwork @ 3% of (a+b+c) 0.03 437721.76

e&f) Overheads & Contractors Profit 0.13615 450853.41


Cost for 75 cum = a+b+c+d+e+f
Rate per 1 cum = (a+b+c+d+e+f)/75
Say

Providing, Laying, Spreading and compacting graded HBG/HBG crushed stone aggregate to Wet Mix macadem specification
cost
Pageof110,111
all materials and including
of MoRT&H SDB premixing the material with water at OMC in Mechanical mix plant carriage of mixed material by
Unit = cum
Taking output = 225 cum
A) Labour
CIVIL DATA 2020-21 : Page-791

Mate 0.48 Nos. 610.50 1 No.


Mazdoor skilled 2.00 Nos. 525.00 1 No.
Mazdoor 10.00 Nos. 525.00 1 No.
Add for MAA @ 25% 0.25 6593.04
Total
B) Machinery
Wet mix plant of 60 tonne hr. capacity -HIR-00080 6.60 hours 1945.00 1 Hour
Electric generator 125 KVA - HIR-00111 6.00 hours 1800.00 1 Hour
Front end loader 1 cum capacity -HIR-00074 6.00 hours 1983.00 1 Hour
Mechanical Paver finisher-HIR-00089 6.00 hours 2805.00 1 Hour
Vibratory roller 8 - 10 tonne -HIR-00062 3.90 hours 3479.20 1 Hour
Water tanker 6 KL capacity -HIR-00076 3.00 hours 806.00 1 Hour
Total
C)Material

45 to 22.40mm IRC&MoRT&H HBG M/C metal@ 30% 89.10 cum 1346.93 1.00 cum
(Av. Of 40-45, 25-27, 19-22mm )
22.4 to 2.36mm IRC&MoRT&H HBG M/C metal@40% 118.80 cum 1076.88 1.00 cum
(Av. Of 19-22mm, 12-14mm, 9.5-11.2mm, 5-7mm, 2.36 -
5mm )
2.36mm to 75 micron @ 30% (2.36mm & below) 89.10 cum 547.00 1.00 cum
Total
D)Over head charges @
Add for Over head charges on (A)+(B)+( C) 0.05 373275.98

(E) Total of (A) + (B)+( C)+(D)


e&f) Overheads & Contractors Profit at 10% on (E) 0.1 391939.7832
Cost per 225 cum (E) + (F)
Rate per 1 cum
Say

Providing and applying primer coat with Bitumen Emulsion (Slow Setting-1) on the prepared surface of granular base
clearing
Page 123ofofroad surfaceSDB
MoRT&H and sparaying primer at the rate of 0.70kg/sqm using mechanical means for finished item of work as per
Unit = Sqm
Taking output =3500 Sqm
A) Labour
Mate 0.08 Nos. 610.50 1 No.
Mazdoor 2.00 Nos. 525.00 1 No.
Add for MAA @ 25% 0.25 1098.84
CIVIL DATA 2020-21 : Page-792

Total
B) Machinery
Mechanical broom Hydraulic @ 1250 sqm/hr. -HIR-00081
2.80 hours 446.00 1 Hour
Air compressor 250 cfm -HIR-00136 2.80 hours 612.70 1 Hour

Bitumen pressure distributor @1750 sqm/hr -HIR-00082 2.00 hours 1603.00 1 Hour
Water tanker 6 KL capacity -HIR-00076 1.00 hours 691.00 1 Hour
Total
C)Material
@ 0.70 Kgs/sqm 2.45 MT 35105.00 1.00 MT
Cost of water 6.00 KL 806.00 1.00 KL
Total
D)Over head charges @
Add for Over head charges on (A)+(B)+( C) 0.05 99078.16

(E) Total of (A) + (B)+( C)+(D)


(F) Overheads & Contractors Profit at 10% on (E) 0.1 104032.068
Cost per 3500 Sqm (E) + (F)
Rate per 1 Sqm
Say

Providing and applying tack coat with bitumen VG-10 bitumen using pressure distributor at the rate of 0.2Kgs per sqm on the
bituminous/granular
Page 124 of MoRT&H surface
SDB cleaned with mechanical broom for finished item of work as per MoRT&H Specification 503 (5th revisio
Unit = Sqm
Taking output =3500 Sqm
A) Labour
Mate 0.08 Nos. 610.50 1 No.
Mazdoor 2.00 Nos. 525.00 1 No.
Add for MAA @ 25% 0.25 1098.84
Total
B) Machinery
Mechanical broom Hydraulic @ 1250 sqm/hr. -HIR-00081
2.80 hours 446.00 1 Hour
Air compressor 250 cfm -HIR-00136 2.80 hours 612.70 1 Hour

Bitumen pressure distributor @1750 sqm/hr -HIR-00082 2.00 hours 1603.00 1 Hour
Total
C)Material
Bitumen VG-10 @ 0.20 Kgs/sqm 0.70 MT 55625.00 1.00 MT
CIVIL DATA 2020-21 : Page-793

Total
D)Over head charges @
Add for Over head charges on (A)+(B)+( C) 0.05 46481.41

(E) Total of (A) + (B)+( C)+(D)


(F) Overheads & Contractors Profit at 10% on (E) 0.1 48805.4805
Cost per 3500 Sqm (E) + (F)
Rate per 1 Sqm
Say

Providing and laying of 50mm thick Bituminous Macadam with hot mix plant producing an average output of 37.5 tonnes per h
hard
Page blasted granite
125,126,127 of crushed
MoRT&Haggregates
SDB of Grading - II as per table 500-4 of MoRT&H specificaion 504 (5th revision) prem
Unit = cum
Taking out put = 205 cum (450 tonne)
A) Labour
Mate 0.84 Nos. 610.50 1 No.
Mazdoor working with HMP, mechanical broom, paver, 14.00 Nos. 525.00 1 No.
roller, asphalt cutter and assistance for setting out lines,
levels and layout of construction.
Mazdoor skilled 5.00 Nos. 525.00 1 No.
Add for MAA @ 25% 0.25 10487.82
Total
B) Machinery
Hot Mix Plant 40 to 60 TPH -HIR-00087 12.00 hours 26556 1 Hour
Air compressor 250 cfm -HIR-00136 2.20 hours 612.70 1 Hour
Mechanical Paver finisher 100 TPH -HIR-00089 6.00 hours 3815 1 Hour
Generator 250 KVA - HIR-00110 6.00 hours 2522 1 Hour
Front end loader 1 cum capacity -HIR-00074 6.00 hours 1983 1 Hour
Smooth wheeled roller 8-10 tonnes for initial break down
rolling -HIR-00075 3.90 hours 1726.1 1 Hour
Vibratory roller 8 - 10 tonne -HIR-00062 3.90 hours 3479.2 1 Hour
Finish rolling with 6-8 tonnes smooth wheeled tandem
roller. HIR-00091 3.90 hours 2165 1 Hour
Total
C)Material
Bitumen 60/70 @ 3.3 % of weight of mix=205x2.2=450
tonne 14.85 MT 56425.00 1.00 MT
ii) Aggregate
Total weight of mix = 450 tonnes
weight of bitumen - 14.85 tonnes
CIVIL DATA 2020-21 : Page-794

Weight of aggregate = 450-14.85 = 435.15 tonnes


Taking density of aggregate = 1.5 tonne/cum
Volume of aggregate = 290.1 cum
Grading - II (19 mm nominal size)
116.04 Cum of 25-10mm @ 40%

IRC &MORT&H HBG M/C chips 25 to 10mm @ 40% 116.04 cum 1447.93 1.00 cum
Average rate of IRC&MoRT&H HBG M/C metal of sizes
25-27mm, 19-22mm, 12-14mm, 9.5-11.2mm
IRC &MORT&H HBG M/C chips 10 to 5mm @ 40% 116.04 cum 986.05 1.00 cum
Average rate of IRC&MoRT&H HBG M/C metal of sizes
9.5-11.2mm, 5 to 7mm

IRC &MORT&H HBG M/C chips 5mm and below @ 20% 58.02 cum 608.00 1.00 cum
Average rate of IRC&MoRT&H HBG M/C metal of sizes
2.36 to 5mm and 2.36mm& below
Total
D)Over head charges @
Add for Over head charges on (A)+(B)+( C) 0.05 1567419.75

(E) Total of (A) + (B)+( C)+(D)


(F) Overheads & Contractors Profit at 10% on (E) 0.1 1645790.7417
Cost per 205 cum (E) + (F)
Rate per 1 cum
Say

Providing and Laying 30mm thick Bituminous concrete with 40-60 TPH HMP /100 to 120 TPH batch type hot mix plant u
crushed aggregates of Grading-2 as per table 500-17 of Specification 507 of MoRT&H (5th revesion), premixed with Bituminious bind
Grade @ 5.4% of mix and filler, transporting the hot mix to work site, laying with paver finisher to the required grade, level and a
rolling with smooth wheeled,vibratory and tandem rollers to achieve the desired compaction as per MoRT&H Specification 507 (5th
complete for finished item of work in all respects excluding seiniorage charges and as directed by Engineer-in-charge

Page 138 of MoRT&H SDB


Unit = cum
Taking output = 191 cum (450 tonnes.)
A) Labour
Mate 0.84 Nos. 610.50 1 No.
CIVIL DATA 2020-21 : Page-795

Mazdoor working with HMP, Mechanical broom, 14.00 Nos. 525.00 1 No.
paver,roller,asphalt cutter and assistance for setting
outlines,levels and layout of construction.
Skilled Mazdoor for checking line and levels. 5.00 Nos. 525.00 1 No.
Add for MAA @ 25% 0.25 10487.82
Total
B) Machinery
Hot mix Plant – 100 TPH capacity- HIR-00085 6.00 hours 29614 1 Hour
Mechanical Paver finisher 100 TPH -HIR-00089 6.00 hours 2805 1 Hour
Generator 250 KVA - HIR-00110 6.00 hours 2522.00 1 Hour
Front end loader 1 cum capacity -HIR-00074 6.00 hours 1983.00 1 Hour
Power road roller 8 tonne for initial break down rolling -
HIR-00075 3.90 hours 1726.10 1 Hour
Pneumatic road Roller -HIR-00092 3.90 hours 1768 1 Hour
Finish rolling with 6-8 tonnes smooth wheeled tandem
roller. HIR-00091 3.90 hours 2165.00 1 Hour
Total
C)Material
(I) Bitumen VG-30 @ 5.40% by weight of mix
=191*2.356=450 ton 24.30 MT 24991.00 1.00 MT
ii) Aggregate
total wt of mix 450T-24.30=425.70T
For Grading II
IRC &MORT&H HBG M/C chip Avg. of (14-12),(9.5-11.2)
@ 20% 56.76 cum 1478.65 1.00 cum
IRC &MORT&H HBG M/C chipsAvg. of (9.5-11.2),( 5-7)
25% 70.95 cum 986.05 1.00 cum
IRC &MORT&H HBG M/C chips2.36 to 5mm, 2.36 & 150.410
above 53% cum 501.00 1.00 cum
Filler @ 1% of weight of aggregates. 2.838 cum 547.00 1.00 cum
Filler (Cement) @ 1% of weight of aggregates. 4.257 MT 4220.00 1.00 MT
Total
D)Over head charges @
Add for Over head charges on (A)+(B)+( C) 0.05 1112766.323

(E) Total of (A) + (B)+( C)+(D)


(F) Overheads & Contractors Profit at 10% on (E) 0.1 1168404.638625
Cost per 191 cum (E) + (F)
Rate per 1 cum
Say
CIVIL DATA 2020-21 : Page-796

A T A ( SoR 2022-23)
ION OF PROPOSED DEGREE COLLEGE AT VEMPALLI

CM (1:8)
1213.80
759.60
105.00
21.00
2099.40
CIVIL DATA 2020-21 : Page-797

DATA
Amount (Rs.)

als for re-use and disposal of unserviceable materials with 100m lead as directed by Executive Engineer duly
bour charges , overheads & contractor profit etc., complete

214.73
42.95
257.67
35.08
292.75
293

1281.00
256.20
1537.20
209.29
1746.49
1746

2562.00
512.40
3074.40
418.58
3492.98
3493

2268.00
453.60
2721.60
370.55
3092.15
3092
CIVIL DATA 2020-21 : Page-798

84.00
16.80
100.80
10.08
1.37
11.45
11

498.00
99.60
597.60
81.36
678.96
679

152.00
30.40
182.40
18.24
2.48
20.72
21

182.00
36.40
218.40
21.84
2.97
24.81
25

263.00
52.60
315.60
42.97
358.57
359
CIVIL DATA 2020-21 : Page-799

60.00
12.00
72.00
7.20
0.98
8.18
8

75.00
15.00
90.00
9.00
1.23
10.23
10

55.00
11.00
66.00
6.60
0.90
7.50
7

68.00
13.60
81.60
8.16
1.11
9.27
9
CIVIL DATA 2020-21 : Page-800

tilators etc., ( wood or steel ) shutters including Chowkhats , architraves,hold fasts and other attachments etc.,
and overheads & contractors profit complete for finished item of work

56.50
105.00
28.25
37.95
227.70
31.00
258.70
259

73.45
141.75
39.55
50.95
305.70
41.62
347.32
347

s like un-reinforced concrete, reinforced concrete, brick masonry, stone masonry etc., using Dozer (D 50)
heads & contractors profit etc. complete finished item of work
1907.00
259.64
2166.64
2167
CIVIL DATA 2020-21 : Page-801

ldings, septic tank, sump, compound wall in ordinary soils and depositing on bank with an initial lead of
our charges such as shoring, sheeting, planking, strutting etc., and overheads & contractors profit complete for
S 20 B(APSS 308)

1911.00
382.20
2293.20

312.22
2605.42
260.54
261

or buildings in ordinary soils and depositing on bank for all lifts and with an initial lead of 10m and up to 3m
s shoring, sheeting, planking, strutting etc., and overheads & contractors profit complete for finished item of work

4368.00
873.60

18944.40
1957.80
391.56
26535.36

3612.79
30148.15
125.62
126
CIVIL DATA 2020-21 : Page-802

or buildings in ordinary soils and depositing on bank for all lifts and with an initial lead of 10m and 3m to 6m
as shoring, sheeting, planking, strutting etc., and overheads & contractors profit complete for finished item of
08)

4368.00
873.60

18944.40
1957.80
391.56
26535.36

3612.79
30148.15
143.56
144

uildings in ordinary rock ( not requiring blasting ) and depositing on bank with an initial lead of 10m and
es such as shoring, sheeting, planking, strutting etc., and overheads & contractors profit complete for finished
PSS 308)

2730.00
546.00
3276.00

446.03
3722.03
372.20
372
CIVIL DATA 2020-21 : Page-803

or buildings in ordinary rock (not requiring blasting) and depositing on bank for all lifts and with an initial
dental, labour charges such as shoring, sheeting, planking, strutting etc., and overheads & contractors profit
etc., as per SS 20 B(APSS 308)

3276.00
655.20

18944.40
1957.80
391.56
25224.96

3434.38
28659.34
159.22
159
CIVIL DATA 2020-21 : Page-804

rock (requiring blasting) and depositing on bank for all lifts and with an initial lead of 10m and up to 3m
s shoring, sheeting, planking, strutting etc., and overheads & contractors profit complete for finished item of work

230.10
172.50
4383.75
957.27

1452.80
37.20

294.50
920.40
242.98

238.00
168.00
9097.50

1238.62
10336.12
1033.61
1034
CIVIL DATA 2020-21 : Page-805

rock (blasting prohibited) and depositing on bank for all lifts and with an initial lead of 10m and up to 3m
s shoring, sheeting, planking, strutting etc., and overheads & contractors profit complete for finished item of work

2730.00
546.00

8716.80
223.20

1767.00
5522.40
1457.88
20963.28

2854.15
23817.43
2381.74
2382

5 KM for disposal including hire charges of T & P, labour charges etc., and overheads & contractors profit

96.00
13.07
109.07
109
CIVIL DATA 2020-21 : Page-806

h chemical toxic to subterrean tremites is apply/ inject into soil during early stage of building Construction 2.
tions conduct and chemical use as per BIS - IS 6313 (Part -2) 2013 code specification & CIB RC registered
the building which kills or repels terminates & impervious to tremite entry 3. Imidacloprid 30.5% SC (IS 63131)
5 Litres/Square meter (Sqm) of internal, external vertical surface of the colums, plinth beams (Back filling) walls
Liters/Sqm of the horizontal surface of basement top surface of the basement filling below flooring bed (Plinth)
e of a depth of 500mm around coulmns & 300mm deep around plinth beams, basements & floor filling area
Conveyance of all materials to the site, cost of labour for sparying, rodding, overheads and contractor profit etc.
gineer-in-charge

162.00
22.06
184.06
184

nd basement with initial lead in layers not exceeding 15cm thick,watering and ramming including cost and
, labour charges,hire charges of T&P etc., and overheads & contractors profit complete for fnished item of

162.75
32.55

3370.80
3566.10
35.66
3601.76
490.38
4092.14
682.02
682

ns and basement with initial lead in layers not exceeding 15cm thick,watering and ramming including cost and
labour charges,hire charges of T&P etc., and overheads & contractors profit complete for fnished item of
CIVIL DATA 2020-21 : Page-807

162.75
32.55

5496.00
5691.30
56.91
5748.21
782.62
6530.83
1088.47
1088

with a lead of 50 m in trenches, sides of foundations and basement with initial lead in layers not exceeding 15cm
water to work site and all operaitonal, incidental, labour charges, hire charges of T&P etc., and overheads &
9&310)

162.75
32.55
195.30
1.95
197.25
26.86
224.11
37.35
37

se aggregate) for foundations using coarse aggregate 40mm size hard , machine crushed granite from
capacity including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site
rete mixer, laying concrete in foundations and under flooring bed, ramming in 15 cm layers finishing top surface
t complete for finished item of work. (APSS No. 402)
CIVIL DATA 2020-21 : Page-808

683.64
1214.37
477.45
139.20

188.10
306.80
61.36

63.00
729.75
158.55
4022.22
547.63
4569.85
4570
CIVIL DATA 2020-21 : Page-809

rse aggregate) for foundations and under flooring bed using coarse aggregate 40mm size hard , machine
0 / 7 cft (0.2 / 0.8 cum) capacity including cost and conveyance of all materials like cement, sand, coarse
xing and hire charges of concrete mixer, laying concrete in foundations and under flooring bed, ramming in 15
d overheads & contractors profit complete for finished item of work. (APSS No. 402)

546.91
1214.37
477.45
139.20

188.10
306.80
61.36

63.00
729.75
158.55
3885.49
529.01
4414.50
4415
CIVIL DATA 2020-21 : Page-810

nd) using hard other than granite stones carted from approved quarry including cost and conveyance of all
proved quarry, to site, including labour for cutting stones to required size and shape, mixing, of cement, mortar,
plete for finished item of work in foundation and basement. (APSS No. 601 & 615)

250.67
611.33
381.48

756.00
1050.00
361.20
3410.67
34.11
3444.78
469.01
3913.79
3914

nd) using hard granite stones carted from approved quarry including cost and conveyance of all materials like
, to site including labour for cutting stones to required size and shape, mixing, of cement, mortar, construction,
ed item of work in foundation and basement. (APSS No. 601 & 615)

250.67
750.53
381.48

756.00
1050.00
361.20
3549.88
35.50
3585.38
488.15
CIVIL DATA 2020-21 : Page-811

4073.53
4074

0mm size machine crushed hard granite metal and 20mm graded machine crushed hard granite metal (coarse
xer 10 / 7 cft (0.2 / 0.8 cum) capacity including cost and conveyance of all materials like cement, fine aggregate
g and hire charges of concrete mixer, centering charges, laying concrete in position, vibrating, curing, centering
ork for footings and basement .

809.58
527.79
477.45
928.40
139.20

188.10
306.80
61.36
38.20
220.90
44.18

63.00
729.75
158.55
67.00
363.00
72.60
5195.86
707.42
5903.28
5903
CIVIL DATA 2020-21 : Page-812

orresponding to IS 456 with cement content of 380 kgs per 1 cum of concrete using weigh batcher / mixer
arse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry including cost and
coarse aggregate, water etc., to site, centering using steel scaffolding pipes , jack props , wallers , foot
erational, incidental and labour charges such as weigh batching, machine mixing, lifting of concrete manually,
s profit complete but excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402)

1603.60
1407.45
424.40

83.79
150.86
2415.00
529.93

311.66
631.18
50.92
294.46
185.13
139.20
8227.56

8227.56
301.00
672.00
134.40
9334.96
1270.95
10605.92
10606
CIVIL DATA 2020-21 : Page-813

8227.56
343.00
1069.00
213.80
9853.36
1341.53
11194.90
11195

8227.56
726.50
810.00
162.00
9926.06
1351.43
11277.49
11277

8227.56
67.00
363.00
72.60
8730.16
1188.61
9918.77
9919
CIVIL DATA 2020-21 : Page-814

orresponding to IS 456 with cement content of 380 kgs per 1 cum of concrete using weigh batcher / mixer
arse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry including cost and
oarse aggregate, water etc., to site, centering using casurina ballies, bamboos, wooden reapers, runners,
al and labour charges such as weigh batching, machine mixing, lifting of concrete manually, laying concrete,
ut excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402)

1603.60
1407.45
424.40

105.21
94.36
2940.00
627.91

311.66
631.18
50.92
294.46
185.13
139.20
8815.46
CIVIL DATA 2020-21 : Page-815

1013.78

1101.93
CIVIL DATA 2020-21 : Page-816

1322.32

1542.71

1763.09
CIVIL DATA 2020-21 : Page-817

2027.56

orresponding to IS 456 with cement content of 380 kgs per 1 cum of concrete using weigh batcher / mixer
arse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry including cost and
oarse aggregate, water etc., to site, centering using casurina ballies, bamboos, wooden reapers, runners,
al and labour charges such as weigh batching, machine mixing, lifting of concrete manually, laying concrete,
ut excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402)

1603.60
1407.45
424.40

42.21
75.15
1615.43
346.56

72.01
145.84
CIVIL DATA 2020-21 : Page-818

11.77
68.04
42.78
139.20
5994.41

749.30

899.16
CIVIL DATA 2020-21 : Page-819
CIVIL DATA 2020-21 : Page-820

1049.02

1198.88

orresponding to IS 456 with minimum cement content of 380 kgs per 1 cum of concrete using weigh batcher
tal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry including cost
d) coarse aggregate, water etc., to site, centering using steel scaffolding pipes , jack props , wallers , foot
erational, incidental and labour charges such as weigh batching, machine mixing, lifting of concrete manually,
etc., complete but excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402)
CIVIL DATA 2020-21 : Page-821

749.30
CIVIL DATA 2020-21 : Page-822

899.16
CIVIL DATA 2020-21 : Page-823

corresponding to IS 456 with cement content of 380 kgs per 1 cum of concrete using weigh batcher /
al (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved quarry including cost
d), coarse aggregate, water etc., to site, centering using casurina ballies , bamboos , wooden reapers , runners ,
thick at fixed end and 5cm thick at free end with an average thickness of 6.25cm including all operational,
mixing, lifting of concrete manually, laying concrete, curing, overheads & contractors profit complete etc., but
of work (APSS No. 402, 403 & 903)

1603.60
1407.45
424.40

42.21
75.15
1615.43
346.56

72.01
145.84
29.17
139.20
5901.00

221.29
CIVIL DATA 2020-21 : Page-824

8) prop: (Cement : Sand) using common burnt clay bricks of class as per Table- I of IS:1077-1992, Non-
e having minimum crushing strength of 40 Kg/Sqcm. including cost and conveyance of all materials like cement,
mixing cement mortar, scaffolding charges, constructing masonry, lift charges, curing, etc.,and overheads &
01 & 504).

151.92
4031.54
231.20

151.20
316.40
992.25
291.97
61.66
6228.14

6228.14
847.96
7076.11
7076
CIVIL DATA 2020-21 : Page-825

in CM (1:4) prop. (Cement : Sand) using common burnt clay bricks of class as per Table- I of IS:1077-1992,
d source having minimum crushing strength of 40 Kg/Sq.cm and placing 2 Nos. of 6mm M.S plain rods in every
r joints of main brick walls where applicable including cost and conveyance of all materials like cement, steel,
es such as labour charges for mixing cement mortar, scaffolding charges, constructing masonry, lift charges,
t of steel and its fabrication charges complete for finished item of work. (APSS No. of 501 & 509)

4031.54
303.84
242.76

378.00
339.00
1443.75
432.15
71.71
7242.75
724.27
CIVIL DATA 2020-21 : Page-826

ure with fly ash cement / lime solid blocks of size 290mm x 225mm x 140mm from approved source having
conveyance of all materials like cement, sand, fly ash cement / lime solid blocks, water etc., to site, labour
ting masonry, lift charges, curing, overheads and contrctor profit etc., complete for finished item of work. (APSS

4085.33
101.28
115.60

151.20
316.40
992.25
291.97
60.54
6114.57

6114.57
832.50
6947.07
6947
CIVIL DATA 2020-21 : Page-827

M (1:4) prop. (Cement : Sand) using fly ash cement / lime solid blocks of size 290mm x 100mm x 140mm
g 2 Nos. of 6mm M.S plain rods in every third layer with free ends of the reinforcement pegged into mortar joints
ce of all materials like cement, steel, sand, fly ash cement / lime solid blocks, water etc., to site, all operational,
tar, scaffolding charges, constructing masonry, lift charges, curing, etc., and overheads & contractors profit but
shed item of work. (APSS No. of 509)

4241.74
151.92
115.60

378.00
339.00
1443.75
432.15
71.02
7173.18
717.32
CIVIL DATA 2020-21 : Page-828

raded machine crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part
0.8 cum) capacity including cost and conveyance of all materials like cement, fine aggregate(sand), coarse
xing, hire charges of concrete mixer, centering charges, laying concrete in position, curing etc., & lift charges ,
or finished item of work. (APSS No. 402)

1583.38
477.45
928.40
139.20

188.10
306.80
61.36

63.00
729.75
158.55
4635.99
CIVIL DATA 2020-21 : Page-829

ine crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from
capacity including cost and conveyance of all materials like cement, fine aggregate(sand), coarse aggregate,
harges of concrete mixer, laying concrete in position, curing etc., & lift charges , and overheads & contractors
ork. (APSS No. 402)

1583.38
477.45
1392.60
139.20

188.10
306.80
61.36

63.00
729.75
158.55
5100.19
CIVIL DATA 2020-21 : Page-830

ded machine crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
m) capacity including cost and conveyance of all materials like cement, fine aggregate(sand), coarse aggregate,
such as weigh batching, machine mixing, hire charges of concrete mixer, centering charges, laying concrete in
profit for steps for finished item of work. (APSS No. 402)

1583.38
477.45
1392.60
139.20

188.10
306.80
61.36
38.20
220.90
44.18

63.00
729.75
158.55
5403.47
CIVIL DATA 2020-21 : Page-831

size hard granite machine crushed graded metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to
gs. of cement per 1 cum of concrete using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity including cost and
), coarse aggregate, water etc., to site including centering, shuttering, labour charges such as weigh batching,
ift charges, curing etc., and overheads & contractors profit complete for finished item of work (APSS No. 402 &

1392.60
1374.57
477.45

83.79
150.86
1890.00
424.93

188.10
306.80
61.36
139.20
6489.65
CIVIL DATA 2020-21 : Page-832

size hard granite machine crushed graded metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to
gs. of cement per 1 cum of concrete using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity including cost and
), coarse aggregate, water etc., to site including centering, shuttering, labour charges such as weigh batching,
ift charges, curing etc., and overheads & contractors profit complete for finished item of work (APSS No. 402 &

1392.60
1374.57
477.45

42.21
75.15
1312.50
285.97

188.10
306.80
61.36

139.20

5655.91

282.80
282.80
CIVIL DATA 2020-21 : Page-833
CIVIL DATA 2020-21 : Page-834

141.40
141.40

e 500 D grade as per IS 1786-1979) of different diameters for RCC works including labour charges for
cing in position with cover blocks of approved materials and size and tying and lap-splicing with binding wire of
designs and drawings, including cost and conveyance of steel bars, including all wastages such as overlaps,
binding wire, cover blocks and all incidental, operational, labour charges such as cutting, bending, placing in
or finished item of work.( APSS No.126)

67200.00
420.00

2250.00
4130.00
5250.00
2326.00
81576.00
CIVIL DATA 2020-21 : Page-835

S 432) of different diameters including labour charges for straightening, cutting, bending to required sizes and
ls and size and tying and lap-splicing with binding wire of 18 SWG, forming grills for reinforcement work as per
e of steel bars, including all wastages such as overlaps, couplings, chairs, spacer bars including cost and
rational, labour charges such as cutting, bending, placing in position, tying etc., and overheads & contractors

66150.00
420.00

2250.00
4130.00
5250.00
2326.00
80526.00
CIVIL DATA 2020-21 : Page-836

(1:5) using screened sand including cost and conveyance of all materials like cement, sand, water etc., to site
ng cost of all labour charges for mixing mortar, finishing, curing as directed by Engineer-in-charge etc., and
SS 901,903 & 904)

182.30
173.40

283.50
593.25
1470.00
469.35
31.72
3203.52
320.35
CIVIL DATA 2020-21 : Page-837

base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in CM (1:4) with dubara sponge finishing including
c., to site and all operational, incidental charges on materials and including cost of all labour charges for mixing
g grooves as directed by Engineer - in - charge etc., and overheads & contractors profit complete for finished

111.41
127.16

60.77
46.24

396.90
830.55
2047.50
654.99
42.76
4318.27
431.83
CIVIL DATA 2020-21 : Page-838

sand including cost and conveyance of all materials like cement, sand, water etc., to site and all operational,
harges for mixing mortar, finishing, curing as directed by Engineer-in-charge etc., and overheads & contractors

182.30
173.40

283.50
593.25

1470.00

469.35
31.72
3203.52
320.35

320.35
43.62
363.97
364
CIVIL DATA 2020-21 : Page-839

base coat of 16mm thick in CM(1:6) and top coat of 4mm thick in CM(1:4) with dubara sponge finishing including
c., to site and all operational, incidental charges on materials and including cost of all labour charges for mixing
g grooves as directed by Engineer-in-charge etc., and overheads & contractors profit complete for finished item

182.30
208.08

60.77
46.24

396.90
830.55
2047.50
654.99
44.27
4471.61
447.16
CIVIL DATA 2020-21 : Page-840

sand including cost and conveyance of all materials like cement, sand, water etc., to site and all operational,
harges for mixing mortar, finishing, curing as directed by Engineer-in-charge etc., and overheads & contractors
03 & 904)

255.23
242.76

283.50
593.25
1470.00
469.35
33.14
3347.23
334.72
45.57
380.29
380
CIVIL DATA 2020-21 : Page-841

s to required slopes with CM (1:3) prop. using screened sand 20mm thick (average) mixed with integral cement
ed by reputed manufacturers as approved by Engineer-in-charge at 100ml per one bag of cement, laid over roof
cement and thread lining at regular intervals of 45cmx45cm including cost and conveyance of all materials like
ational, incidental, and labour charges for mixing mortar, laying, lift charges, rendering smooth and thread lining,
verheads & contractors profit complete for finished item of work. (APSS No. 901 & 903).

425.38
242.76
41.00

415.80
870.10
1942.50
645.68
45.83
4629.05
CIVIL DATA 2020-21 : Page-842

es of sump , sump side wall,sump bottom slab,in side of septic tank , in sunken slabs etc. to required
mixed with integral cement water proofing admixture confirming to IS: 2645-2003 manufactured by reputed
one bag of cement, laid over roof slab when it is green, finished smooth with a floating coat of neat cement and
ssary including cost and conveyance of all materials like cement, sand, water proofing compound, water etc., to
, laying, lift charges, rendering smooth and thread lining, curing including rounding off junctions of wall and slab
of work. (APSS No. 901 & 903).

303.84
173.40
29.52

283.50
593.25
1470.00
469.35
33.23
3356.09
CIVIL DATA 2020-21 : Page-843

p walls, fins with rabbit wire mesh & nomianl reinforcement as directred by Engineer - In - Charge with dubara
aterials to site, operationals &incidental,cost and conveyance of cement,wire mesh,water to work
erheads & contractors profit complete for finished item of work but excluding cost of steel and its fabrication

279.30
506.40
300.56
211.00

607.68
346.80

5040.00
615.00
5250.00
2181.00

376.20
613.60
122.72
164.50
16614.76
1661.48
CIVIL DATA 2020-21 : Page-844

mm to 18 mm thick set over a base coat of CM (1:8) , 12mm thick using screened sand over already laid CC
nsistency spread @ 3.3 Kgs per sqm and jointed with neat cement to full depth including cost and conveyance
plete including all labour charges like dressing of flooring stones to the required size, mixing of cement mortar,
erheads & contractors profit complete for finished item of work. (APSS No.703 & 701)

2258.73

91.15
139.26
84.40
138.72

1953.00
621.50
451.50
605.20
63.43
6406.90
CIVIL DATA 2020-21 : Page-845

mm thick of size 0.457m x 0.457m set over a base coat of CM (1:8) , 12mm thick using screened sand over
of honey like consistency spread @ 3.3 Kgs per sqm and jointed with neat cement to full depth including cost
stones etc. complete including all labour charges like dressing of flooring stones to the required size, mixing of
ges etc., and overheads & contractors profit complete for finished item of work. (APSS No.703 & 701)

2078.38

91.15
139.26
84.40
138.72

1953.00
621.50
451.50
605.20
61.63
6224.75
CIVIL DATA 2020-21 : Page-846

iles of size 300 mm x 300 mm and thickness between 7-8 mm 1st quality conforming to IS:13711, IS:13712,
nd designs as approved by Engineer-in-charge, set over base coat of cement mortar (1:8), 12mm thick using
ing neat cement slurry of honey like consistency spread @ 3.3 Kgs per sqm & jointed neatly with white cement
ding cost of all materials like cement, screened sand , water and tiles etc., and overheads & contractors profit

3885.00
91.15
139.26
62.00
138.72

604.80
1265.60
1732.50
720.58
86.40
8726.01

ted and polished of size 600 x 600 mm and thickness between 8-10 mm 1st quality conforming to IS:13711,
hades and designs with borders and design as per the approved flooring pattern as directed by the Engineer-In
ase coat of CM (1:8) prop. 12mm thick using screened sand over CC bed already laid or RCC roof slab ,
@ 3.3 kgs per sqm. and jointed neately with white cement paste to full depth mixed with pigment of matching
ent, sand, water, tiles, white cement etc., to site (excluding cost of C.C. bed) including cost of base coat and
required slope as directed by the Engineer- in-charge etc.,and overheads & contractors profit complete for
CIVIL DATA 2020-21 : Page-847

4462.50
91.15
139.26
186.00
138.72

604.80
1265.60
1732.50
720.58
93.41
9434.52

n free full body porcelain vitrified tiles with double layer pigment of size 600 x 600 mm and thickness
IS:13630 (Parts 1 to 15) of any colour and finish in all shades and designs with borders and design as per the
, laying tiles using spacers of 2mm thick, set over a base coat of CM (1:8) prop. 12mm thick using screened
cement slurry of honey like consistancy spread @ 3.3 kgs per sqm. and jointed neately with white cement
ing cost and conveyance of all materials like cement, sand, water, tiles, white cement etc., to site (excluding
harges for mixing of cement mortar, laying tiles to required slope as directed by the Engineer- in-charge
of work. (APSS No.701 & 707)

6426.00
91.15
139.26
186.00
138.72

604.80
CIVIL DATA 2020-21 : Page-848

1265.60
1732.50
720.58
113.05
11417.66

shed granite stone slabs black colour as approved by the Engineer-in-Charge set over base coat of cement
ady laid including neat grey cement slurry of honey like consistency spread @ 3.3 Kg per sqm and jointed neatly
o full depth including cost and conveyance of all materials like cement , sand , water , granite slabs etc., to work
ing the edge , polishing charges, cost of base coat and overheads & contractors profit complete for finished item

22050.00
151.92
139.26
186.00
231.20

1890.00
565.00
4200.00
1331.00
826.12
15218.00
1283.53
480.72
48552.75
CIVIL DATA 2020-21 : Page-849

one slabs other than black and regular colours (i.e. of shades like paradiso / bala flower / copper silk / laka
pproved by the Engineer-in-Charge of length not less than 2.43 mts set over base coat of cement mortar (1:8) ,
CC roof slab including neat grey cement slurry of honey like consistency spread @ 3.3 Kg per sqm and jointed
hade to full depth including cost and conveyance of all materials like cement , sand , water , granite slabs etc., to
shing charges, cost of base coat and overheads & contractors profit complete for finished item of work (S.S.701

26250.00
151.92
139.26
186.00
231.20

1890.00
565.00
4200.00
1331.00
349.44
35293.82
CIVIL DATA 2020-21 : Page-850

6mm to 12 mm size hard granite machine crushed metal and screened sand laid over CC bed already laid or
x 1.50 m, using glass strips and finishing the top surface to required smoothness and slopes and thread lining
nd overheads & contractors profit complete for finished item of work. (APSS No.701 & 710)

259.64
506.40
90.19

787.50
33.90
1575.00
479.28
37.32
3769.23
CIVIL DATA 2020-21 : Page-851

onforming to IS: 13801 using aggregates, cement, pigments of size 300mm x 300 mm and thickness 25 mm
ase coat of cement mortar (1:6), 12 mm thick using screened sand over CC bed already laid or RCC roof slab
@ 3.3 kgs per sqm and jointed with neat white cement to full depth mixed with pigment of matching shade
water and tiles etc.,and overheads & contractors profit complete for finished item of work.

3412.50
121.54
139.26
186.00
138.72

604.80
1265.60
1732.50
720.58
83.21
8404.71

ht blue colour in Operation Theatres and labour rooms - SIKA Epoxy seamless joint free finish with 3mm
rable and non particle shedding with attractive finishing including cost and conveyance of all materials and all
finished item of work in all floors.
1862.00
253.51
2115.51
2116
CIVIL DATA 2020-21 : Page-852

f M-40 grade and thickness not less than 80 mm for medium traffic areas conforming to IS 15658:2006 in all
ding cost and conveyanace cost of all materilas like cement, sand water and Pavers etc., Complete per drawings
d conveyance of all materials and all labour charges, overheads and contractor profit etc., complete for finished

Sqm

10170.00
4200.00
2874.00

1612.00

123750.00
1200.00
6622.68

348.00
150777
670.12
91.24
761.36
761.00
CIVIL DATA 2020-21 : Page-853

m to 18 mm thick in single piece as specified set over a base coat of CM (1:5) , 12mm thick using screened
ement slurry of honey like consistency spread @ 3.3 Kgs per sqm and jointed with neat cement to full depth
water, flooring stones etc. complete including all labour charges like dressing of flooring stones to the required
harges , cost of base coat, water charges etc., and overheads & contractors profit complete for finished item of

2258.73
145.84
139.26
84.40
138.72

1953.00
621.50
451.50
605.20
1833.15
146.65
83.78
8461.73
CIVIL DATA 2020-21 : Page-854

2258.73
138.72
145.84
139.26

604.80
1265.60
1627.50
699.58
68.80
6948.83
CIVIL DATA 2020-21 : Page-855

thick in single piece as specified set over a base coat of CM (1:5) , 12mm thick using screened sand over
of honey like consistency spread @ 3.3 Kgs per sqm and jointed with neat cement to full depth including cost
stones etc. complete including all labour charges like dressing of flooring stones to the required size, flat nosing
base coat, water charges etc., and overheads & contractors profit complete for finished item of work for treads

3117.58

145.84
139.26
84.40
138.72

1953.00
621.50
451.50
605.20
1833.15
146.65
92.37
9329.17
CIVIL DATA 2020-21 : Page-856

3117.58
138.72
145.84
139.26

604.80
1265.60
1627.50
699.58
77.39
7816.27
CIVIL DATA 2020-21 : Page-857

h granite stone slabs (steel grey or pearl black) with borders and design as per the pattern approved by the
se coat of cement mortar (1:5) , 12mm thick using screened sand over CC bed already laid or RCC roof slab
ad @ 3.3 Kg per sqm and jointed neatly with white cement paste mixed with pigment of matching shade to full
, sand , water , granite slabs etc., to work site and all operational, incidental labour & lift charges, full rounding
the full length of treads , polishing charges, cost of base coat and overheads & contractors profit complete for

26250.00
145.84
139.26
186.00
138.72

1890.00
565.00
4200.00
1331.00
633.27
15098.49
1258.54
518.36
52354.49
CIVIL DATA 2020-21 : Page-858

26250.00
138.72
145.84
139.26
155.00
1266.73
101.34

1323.00
2768.50
4200.00
1658.30
381.47
38528.16
CIVIL DATA 2020-21 : Page-859

hed Shahabad/Tandur stone slabs 15mm to 18mm thick, length equal to flooring stones set over base coat of
honey like consistency spread at the rate of 3.30 kgs per sqm and jointing with white cement paste mixed with
erials like tiles, cement, sand and water etc., complete and overheads & contractors profit complete for finished

2258.73
138.72
145.84
139.26

604.80
1265.60
1627.50
699.58
68.80
6948.83
CIVIL DATA 2020-21 : Page-860

olished Kadapa stone slabs minimum of 15mm thick, length equal to flooring stones set over base coat of
honey like consistency spread at the rate of 3.30 kgs per sqm and jointing with white cement paste mixed with
erials like tiles, cement, sand and water etc., complete and overheads & contractors profit complete for finished

1983.91
138.72
145.84
139.26

604.80
1265.60
1627.50
699.58
66.05
6671.27
CIVIL DATA 2020-21 : Page-861

ble salt porcelain vitrified tiles screen printed and polished of 8 to 10mm thick of any colour and finish in all
oat of CM(1:5) 12 mm thick using screened sand with cement slurry of honey like consistency spread at the rate
with pigment of matching shade to full depth, including cost of all materials like tiles, cement, sand and water
of work.(APSS No.701 &707)

4462.50
138.72
145.84
139.26
62.00

604.80
1265.60
1732.50
720.58
92.72
9364.52
CIVIL DATA 2020-21 : Page-862

charged stain free full body porcelain vitrified tiles with double layer pigment of Size 600 x 600 mm and
s and designs, length equal to flooring tiles, flushed to wall surface to set over base coat of CM(1:5) 12 mm
sistency spread at the rate of 3.30 kgs per sqm and jointing with white cement paste mixed with pigment of
les, cement, sand and water etc.,and overheads & contractors profit complete for finished item of work.(APSS

6426.00
138.72
145.84
139.26
62.00

604.80
1265.60
1732.50
720.58
112.35
11347.66

50mmx50mm width at the corners of the all walls in Operation Theatres, labour rooms including cost and
ontractor profit etc., complete for finished item of work .

500.00
68.08
568.08
568
CIVIL DATA 2020-21 : Page-863

olished Granite 16 mm to 18 mm thick up to 8'-00 (2.43 M) other than black and regular colours, length equal
screened sand with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointing
o full depth, including cost of all materials like tiles, cement, sand and water etc., and overheads & contractors

26250.00
138.72
145.84
139.26
155.00
1266.73
101.34

1323.00
2768.50
4200.00
1658.30
381.47
38528.16
CIVIL DATA 2020-21 : Page-864

mm to 18 mm thick up to 8'-00 (2.43 M) other than black and regular colours, length equal to flooring slabs set
h cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointing with white cement
ng cost of all materials like tiles, cement, sand and water etc., and overheads & contractors profit complete for

26250.00
138.72
243.07
139.26
155.00

1323.00
2768.50
4200.00
1658.30
368.76
37244.61
CIVIL DATA 2020-21 : Page-865

c wall tiles of size 300 x 450 mm / 320 mm x 400 mm and thickness 6 mm 1st quality conforming to IS:13711,
shades and designs with borders as approved by Engineer-in-Charge flushed to wall surface set over base
urry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointing with white cement paste mixed
materials like tiles, cement, sand and water etc., and overheads & contractors profit complete for finished item

4305.00
138.72
145.84
139.26
186.00

485.10
420.00
181.02
60.01
6060.95
CIVIL DATA 2020-21 : Page-866

es of size 300mm x 600 mm with any type of design texture such as marble finish, wooden, bamboo, stone
mm 1st quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in all shades
n as approved by Engineer-in-Charge flushed to wall surface set over base coat of CM(1:5) 12 mm thick using
d at the rate of 3.30 kgs per sqm and jointing with white cement paste mixed with pigment of matching shade to
nd water etc., and overheads & contractors profit complete for finished item of work.

6090.00
138.72
145.84
139.26
62.00

604.80
1265.60
1732.50
720.58
108.99
11008.30
CIVIL DATA 2020-21 : Page-867

onforming to IS: 13801 using aggregates, cement, pigments of size 300 x 300 mm and thickness 20 mm of any
ng screened sand over CC bed already laid of any shades as approved by Engineer - In - Charge including neat
qm and jointed with neat white cement to full depth mixed with pigment of matching shade including cost and
,and overheads & contractors profit complete for finished item of work.

2677.50
121.54
139.26
186.00
138.72

604.80
1265.60
1732.50
720.58
75.86
7662.36
766.24

neral purpose tiles conforming to IS: 13801 using aggregates, cement, pigments of size 300 x 300 mm and
base coat of cement mortar (1:6), 12 mm thick using screened sand over PCC(1:5:10) bed 100mm thick along
ement / lime solid blocks of size 290mm x 225mm x 140mm from approved source having minimum crushing
th base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in CM (1:4) for brick masonry drain, laying of
directed by the Engineer - in - charge including cost and conveyance of all materials to site, all labour charges
ctor profit etc., complete for finished item of work.

82.20
765.44
1238.20
712.52
919.48
3717.85
3098.21
421.82
3520.03
3520
CIVIL DATA 2020-21 : Page-868

0) proportion using brick jelly for low roofs including cost and conveyance of all materials like cement, sand,
ng concrete, ramming, curing , overheads & contractors profit etc., complete for finished item of work. (APSS.

546.91
1207.36
477.45
139.20

188.10
306.80
61.36

63.00
729.75
158.55
3878.48
CIVIL DATA 2020-21 : Page-869

in sunken slabs including cost and conveyance of cinder, labour charges for filling, ramming, overheads and

162.75
32.55

3900.00
4095.30
CIVIL DATA 2020-21 : Page-870

e aggregates: coarse aggregate) using 40mm size (SS5) hard granite metal (coarse aggregate) from approved
ent, fine aggregate (sand), coarse aggregate, water etc., to site including centering using Casurina Ballies ,
ates etc., shuttering, machine mixing, laying concrete, lifting concrete manually , vibrating, curing, etc., and
cluding cost of steel and it's fabrication charges for finished item of work (APSS NO. 402 & 403) for dummy

546.91
1214.37
477.45

105.21
94.36
2467.50
533.41

188.10
306.80
38.20
220.90
105.54
139.20
6437.95
CIVIL DATA 2020-21 : Page-871

ng as per approved drawing with top rail of 50mm dia pipe and 2mm thick medium class and vertical posts of
d with base plate of 25mm dia using bonding agent and anchor fastner and welding, drilling of 25mm dia holes
all members of the railing thouroughly , lacquer finishing to present seamless finish including cost and
all consumables, labour charges , overheads & contractors profit etc., complete for finished item of work.

8859.60
3081.60
217.10
390.00
390.00
195.00
13133.30
2855.07
3172.29
431.91
3604.20
3604

ramp as per approved drawing with top rail of 50mm dia pipe and 2mm thick medium class fixed in to wall with
ding, buffing, polishing all members of the railing thouroughly , lacquer finishing to present seamless finish
ng charges, cost of all consumables, labour charges , overheads & contractors profit etc., complete for finished

10888.20
3787.20
150.30
270.00
15095.70
1509.57
205.53
1715.10
CIVIL DATA 2020-21 : Page-872

1715

200mm length bars in toilets as per approved drawing with 25mm dia pipe with base plates 2 Nos., buffing,
sh including cost and conveyance of all materials, labour charges , overheads & contractors profit etc., complete

149.04
51.84
33.40
60.00
294.28
40.07
334.35
334

with single socket , 2.5mm thick 4.0 kg/sq.cm pressure of ISI marked including cost of necessary PVC Bends,
d fixing in position including cost and conveyance of all materials, operational & incidental charges including all
profit complete for finished item of work. (APSS No. 1328)

894.60
76.65
52.50
51.00
53.50
475.08
1603.33
267.22
36.38
303.60
304
CIVIL DATA 2020-21 : Page-873

as per the design approved by the Engineer-in-Charge including cost and conveyance of materials to site and
nished item of work.
388.00
37.80
33.90
144.38
43.22
647.29

ve an even shade after thouroughly brushing the surface to remove all dirt and remains of loose powdered
ental such as scaffolding , lift charges etc., and overheads & contractors profit complete for finished item of work

62.00

44.42
83.06
168.00
59.09
4.17
420.73
57.28
478.01
47.80
CIVIL DATA 2020-21 : Page-874

48

mer or Cement based of average 1 to 2 mm thickness over plastered surface to prepare the surface even and
nd remains of loose powdered materials, applying emery paper, Sand the surface, clean & wipe off loose dust,
2 - 3 hrs, sand with 180 and 320 No., emery paper for the surface preparation including cost and conveyance of
rges, over heads and contractors profit etc., complete for finished item of work in all floors for internal walls

690.00
192.47
359.91
477.75
206.02
19.26
1945.41
264.87
2210.27
221.03
221

thickness over plastered surface to prepare the surface even and smooth after thoroughly brushing the surface
ng emery paper, Sand the surface, clean & wipe off loose dust, applying putty/ texture paint filler by putty knife /
n including cost and conveyance of all materials to work site and all operational, incidental, labour charges,
ete for finished item of work in all floors for external walls

1128.84
192.47
359.91
477.75
206.02
23.65
10.80
84.70
16.94
2501.07
340.52
2841.60
284.16
CIVIL DATA 2020-21 : Page-875

284

d Washable Distemper having VOC content less than 50 grams/litre over promer coat using white cemnt as
n even shade after thourughly brushing the surface to remove all dirt and remains of loose powdered materials,
all operational, incidental, labour charges etc., and overheads & contractors profit complete for finished item of

15.50
56.40
107.35
137.70
253.80
474.60
178.43
12.24
1236.02
168.28
1404.30
140.43
140

Washable Distemper having VOC content less than 50 grams/litre as approved by Engineer-In-Charge, to
emove all dirt and remains of loose powdered materials, including cost and conveyance of all materials to work
eads & contractors profit complete for finished item of work as per APSS 911 for internal walls in all floors.

137.70
253.80
474.60
145.68
10.12
1021.90
139.13
1161.03
116.10
116
CIVIL DATA 2020-21 : Page-876

aint of shade as approved by the Engineer-In-Charge over a base coat of aproved white cement base coat
hing the surface to remove all dirt and remains of loose powdered materials, including cost and conveyance of
rges etc., and overheads & contractors profit complete for finished item of work as per SS 912 in all floors

31.00
56.40
107.35
80.72
105.75
197.75
787.50
250.95
16.17
1633.59
222.41
1856.01
185.60
186

t of shade as approved by the Engineer-In-Charge to give an even shade after thourughly brushing the surface
uding cost and conveyance of all materials to work site and all operational, incidental, labour charges etc., and
as per SS 912 in all floors.

80.72
105.75
197.75
787.50
218.20
13.90
1403.82
191.13
1594.95
159.49
159
CIVIL DATA 2020-21 : Page-877

er of interior grade I and two coats of acrylic emulsion paint having VOC (Volatile Organic Compound)
t and conveyance of all materials to site, incidental, operational and all labour charges etc.,and overheads &

160.00
148.05
276.85
152.00
253.80
474.60
230.66
16.96
1712.92
233.21
1946.13
194.61
195

r of interior grade I and two coats of synthetic polymer luxury plastic emulsion paint of superior grade
ams/litre for internal walls including cost and conveyance of all materials to site, incidental, operational and all
for finished item of work in all floors.

160.00
148.05
276.85
360.00
253.80
474.60
230.66
19.04
1923.00
261.82
2184.82
218.48
218
CIVIL DATA 2020-21 : Page-878

mer of exterior grade II and two coats of acrylic exterior emulsion paint having VOC (Volatile Organic
including cost and conveyance of all materials to site, incidental, operational and all labour charges etc.,and
n all floors.

200.00
148.05
276.85
168.00
148.05
276.85
787.50
327.46
23.33
2356.09
320.78
2676.87
267.69
268

of exterior grade II and two coats of synthetic polymer luxury plastic emulsion paint of superior grade
ams/litre for exterior walls including cost and conveyance of all materials to site, incidental, operational and all
for finished item of work in all floors.

200.00
148.05
276.85
360.00
148.05
276.85
787.50
327.46
25.25
2550.01
347.18
2897.19
289.72
290
CIVIL DATA 2020-21 : Page-879

nt or polymer or cement based of average 1 to 2 mm thickness over plastered surface to prepare the surface
e all dirt and remains of loose powdered materials, applying emery paper, Sand the surface, clean & wipe off
air dry for 2 - 3 hrs, sand with 180 and 320 No., emery paper for the surface preparation, applying one coat of
hane paint (MRF) of light green or light blue colour with 1mm thickness with anti fungal and anti bacterial
cost and conveyance of all materials to work site and all operational, incidental, labour charges, over heads and
rs for internal walls and ceiling of Operation Theatre and labour rooms.

690.00
192.47
359.91
477.75
206.02
19.26
1945.41

160.00
148.05
276.85
84.98
6.70
676.58

675.00
253.80
474.60
145.68
15.49
1564.57
4186.56
570.00
4756.55
475.66
476
CIVIL DATA 2020-21 : Page-880

nish , over a primary coat and painting two coats of synthetic enamel paint Grade-I VOC (Volatile Organic
including cost and conveyance of all materials to site cost of primer coat and all labour charges etc. complete
overheads & contractors profit complete in all floors (APSS No.1200, 1207 & 1211).

130.00

112.00
148.05
276.85

324.00
253.80
474.60
230.66
19.50
1969.46
268.14
2237.60
223.76
224

s of synthetic enamel paint Grade-II VOC (Volatile Organic Compound) content less than 50 grams/litre of
materials to site and all labour charges etc. complete and overheads & contractors profit complete in all floors

297.00
253.80
474.60
145.68
11.71
1182.79
161.04
1343.83
134.38
134
CIVIL DATA 2020-21 : Page-881

n primer paint grade - 1 of approved brand including cost and conveyance of all materials to site , all labour
oors.(APSS No. 1201, 1212 & 1207).

101.50

148.05
276.85
84.98
6.11
617.49
84.07
701.57
70.16
70

C (Volatile Organic Compound) content less than 50 grams/litre to new iron work including cost and
labour charges etc., and overheads & contractors profit complete for finished item of work in all floors. (SS No.

297.00

232.65
435.05
133.54
10.98
1109.22
151.02
1260.24
126.02
126
CIVIL DATA 2020-21 : Page-882

(Volatile Organic Compound) content less than 50 grams/litre over primer coat of red oxide to new iron
ental, operational and all labour charges etc., and overheads & contractors profit complete for finished item of

101.50
297.00

148.05
276.85

232.65
435.05
218.52
17.10
1726.72
235.09
1961.81
196.18
196

g VOC (Volatile Organic Compound) content less than 50 grams/litre to old iron work including cost and
labour charges and overheads & contractors profit etc., complete for finished item of work in all floors. (SS No.

243.00

232.65
435.05
133.54
10.44
1054.68
143.60
1198.28
119.83
120
CIVIL DATA 2020-21 : Page-883

olish of approved brand for new wood work to teak wood frame and shutters including sand papering to smooth
e, all labour charges etc., complete for finished item of work in all floors.

45.60
156.48

676.80
1265.60
388.48
25.33
2558.29
348.31
2906.60
290.66
291

e wood works duly cleaning the surface and applying emery paper, sand the wood with 180 No., emery paper
applying suitable knifing paste filler / wood filler by putty knife / muslin pad, air dry for 2 - 3 hrs, sand with 180
r dry for 24 hrs, sand with 320 No emery paper, applying one coat of approved spraying thinner (for spraying)/
se thinner (for brushing) and apply (either with spray or brush) two coats of approved brand melamine including
polish, over heads and contractors profit etc., complete for finished item of work

21.13
4.62

169.20
316.40
420.00
181.12
11.12
1123.59
152.98
1276.57
1277
CIVIL DATA 2020-21 : Page-884

/ Matt finish to the wood works duly cleaning the surface and applying emery paper, sand the wood with 180
wipe off loose dust, applying suitable knifing paste filler / wood filler by putty knife / muslin pad, air dry for 2 - 3
mponent wood sealer, after the surface preparation applying one coat of approved spraying PU thinner (for
or general purpose thinner (for brushing) and apply one coat of PU by brush or spray, air-dry overnight, sand
ond coat of PU, air drying for 4 - 6 Hrs, sand with 320 No emery paper, and applying (either with spray or brush)
es, emery papers, cost of thinner & Poly-Urethane Water Proof Polish, over heads and contracors profit etc.,

48.75
4.62

169.20
316.40
420.00
181.12
11.40
1151.49
156.78
1308.27
1308

ine rolled CRCA laths, interlocked together through their entire length and jointed together at the ends by end-
nominal bore MS B class pipe with brackets, plates, guide channels, stoppers, bottom locking plates and
ns including cost of hood cover and springs complete, painted with one coat of approved steel primer, locks, ball
plete for finished item of work as per special spn: 1108

4025.00
548.00
4573.00
4573

ble channel of 20 x10x2 mm of 100 mm centre, Bracers with flat iron 40x40x6 mm with 38 mm dia steel pulleys,
with 65x65mmx8mm MS Angle and middle guide rail at site height with 65mmx8mm MS flat for the pulleys to
king arrangements, stoppers, handles, all accessories all fixtures and painted with one coat of approved steel
em of work as per special spn 1105
3508.00
477.61
3985.61
CIVIL DATA 2020-21 : Page-885

3986

expansion joints on terrace (Size : 25mm x 12mm): Application of one coat of-High performance specially
D SBR (Armstrong) / POWER n BOND SBR (EBT) / NITOBOND SBR (Fosroc) ZORIBOND SBR (PMCC)/ SIKA
N 18549 TT -S-00227E or equivalent mixing with cement as per manufacturers c] Providing and application of
ure with - OOFCRETE AR (Armstrong ) / ZORIGROUT CMG (PMCC) / POWER n GUARD ARM (EBT) /
and making the groove. d]. Providing and fixing of masking tape on top of the joint both sides. e]. Providing and
ve the depth of 12mm on the joint. f]. Providing and application of one coat of polysulphide primer with –
application of Two part Polysulphide sealant to a width of 25mm and 12mm depth with - ROOFSEAL PS
osroc)/ ZORISEAL PS (PMCC) / SIKA POLYSULPHIDE (Sika) / WATERSHIELD PSComplies with BS 4254 - 83
masking tape and providing and application of two coats of Acrylic elastomeric cementitious coating with –
SEAL PS 200 (Fosroc)/ ZORISEAL PS (PMCC) / SIKA POLYSULPHIDE (Sika) / WATERSHIELD PS including
& contractors profit etc., complete for finished item of work

702.00
95.58
797.58
798

dings, columns, beams and slabs 25 mm thick including cost and conveyance of all materials to site, all
rs profit complete for finished item of work as per approved drawing for all floors

360.00
49.01
409.01
409

pansion joint groove of width 15cm fixed to walls / columns at one edge and resting over the other block
free edge of aluminium sheet to facilitate free movement of aluminium sheet over the finished surface of
on receiver complete including cost and conveyance of all materials to site, all incidental, operational, labour
d item of work as per approved drawing (for all floors for vertical joints and bottom of slab)

282.00
165.00
447.00
68.00
9.26
77.26
CIVIL DATA 2020-21 : Page-886

77

ick of approved make with skin material 0.50 mm thick aluminium sheet cover material natural polyethylene
ame (50x25x1.5mm) angle cleats, weather sealants, rivets, GI brackets all as approved, using suitable bolts on
in all respects including all scaffolding and labour charges , overheads & contractors profit etc., complete for
on if any.

2946.00
401.10
3347.10
3347

ll formed sections made of Pre-painted Steel / Powder coated (Base steel as per IS 513 of ‘D’ quality,
ted thickness of 0.72mm. The glass holding section made of 304 grade stainless steel of 0.6mm thick as per the
at with epoxy primer of 5 – 7 microns thick, finish painted with a polyester paint of 12-16 microns thick and back
pure polyester powder up to 50-60 microns thick. The vertical section should be of 50mm x100mm x 0.72mm,
ection should be 48mm x 98mm x 1mm, cover profiles sections should be of 20mm x 58mm x 0.58mm, Glass
cluding 5mm thick Ocean Blue reflective glass. Brackets made of CRCA powder coated/Electroplated should be
ls at top & bottom as per site requirement.

, with Good U.V. Resistance Silicon to be used. Wall fixing of sections to concrete/masonry wall should be with
conveyance of all materials to site, all labour charges, incidental charges, cost of all consumables etc. and
c., complete for finished item of work in all floors.
7150.00
973.47
8123.47
8123

g fabricated from Roll formed sections made of Pre-painted Steel / Powder coated (Base steel as per IS
/sqm) with total coated thickness of 0.72mm. The glass holding section made of 304 grade stainless steel of
ners inside the colour coated steel/powder coated sections as per the design requirement. Design calculations
with epoxy primer of 5-7 microns thick and back coated with Alkyd backer of 5-7 microns or powder coated with
ame should be of 20mm x 58mm x 0.6mm, Shutter section should be of 58mm x 33mm x 0.72 mm, stiffener
– 2 Nos for each shutter and Aluminium Stays – 2 Nos. for each shutter, Aluminium Handle – 1 no. for each
rials to site, all labour charges, incidental charges, cost of all consumables etc. and scaffolding charges, form
of work in all floors.

5645.00
768.57
CIVIL DATA 2020-21 : Page-887

6413.57
6414

Fiber Ceiling tile of 595 x 595 (Square edge Fissura fine model) using hot dipped Galvanized Steel section
32 mm at every 1200 mm c/c maximum and rotary stitched cross tee of size 24 x 27 mm at every 600 mm c/c
all angle of size 19 x 19 mm fixed to periphery of the wall and the above grid is suspended at every 1200 mm c/c
ncluding cost and conveyance of all materials and labour charges such as cutting , fixing of standing of frame
mplete for finished item of work in all floor in all floors.

353.00
14.80

80.00

78.40
12.80
5.12

84.60
67.80
8.46
8.46
37.80
41.42

42.24
38.72
873.62
8.74
882.36
120.13
1002.49
1002
CIVIL DATA 2020-21 : Page-888

Fiber Ceiling tile of 595 x 595 (Square edge Fissura fine model) using hot dipped Galvanized Steel section
32 mm at every 1200 mm c/c maximum and rotary stitched cross tee of size 24 x 27 mm at every 600 mm c/c
all angle of size 19 x 19 mm fixed to periphery of the wall and the above grid is suspended at every 1200 mm c/c
ncluding cost and conveyance of all materials and labour charges such as cutting , fixing of standing of frame
mplete for finished item of work in all floor in all floors.

518.00
14.80

80.00

78.40
12.80
5.12

84.60
67.80
8.46
8.46
37.80
41.42

42.24
38.72
1038.62
10.39
1049.01
142.82
1191.83
1192
CIVIL DATA 2020-21 : Page-889

ayer false ceiling (GS-MFSC-4.1) using 12.5 mm thick Gyp Board conforming to IS 2095 - 1993 fixing to Gyp
web) of 0.55 mm thick along the perimeter of ceiling screw fixed to brick work/ partition at 610 mm c/c and
x 15mm x 15mm x 0.9 mm) from soffit at 1220 mm c/c with ceiling angle (25 mm x 10 mm x 0.55 mm) fixed with
eiling channels (with knurled web of 51.5 mm x 26 mm x 10.5 mm x 0.55 mm) fixed in direction perpendicular to
apered edge Gypboard with 25 mm drywall screws at 230 mm c/c & jointing and finishing using joint compound
& square edges with jointing compound, two coats of drywall top coat including overheads and contractor profit

227.63
49.92
89.04

65.52

27.60
18.40
2.56
3.20
72.00
17.60
8.76
22.50

84.60
67.80
16.92
13.56
8.46
16.92
37.80
49.21

42.24
77.44
1019.68
10.20
1029.88
140.22
CIVIL DATA 2020-21 : Page-890

1170.10
1170

GS-FLC-4.6)using 12.5mm thick Gyp Board sheet tiles of size 595mm x 595mm conforming to IS 2095 - 1992
x 0.70mm thick along the perimeter of ceiling screw fixed to brick work / partition at 610mm center to center and
mm x 38mm x 0.7mm) from soffit at 1220mm center to center fixed with GI Soffit Cleat, rawl plugs and steel
4mm dia GI rod with galvanised spring steel level clip of PVC unversal holding clips system at 1200mm center to
m x 595mm and finishing two coats of drywall top coat, overheads and contractor profit complete for finished item

275.00
24.80

192.00
19.20
5.12
6.40
21.44
22.50

84.60
67.80
16.92
13.56
8.46
8.46
37.80
47.52

42.24
38.72
932.54
9.33
941.87
128.23
CIVIL DATA 2020-21 : Page-891

1070.10
1070

ontal level 600mm x 600mm using 12mm thick Thermocole sheet, anodized Aluminium Tee sections of size
x 24.5mm at every 600mm center to center and anodised aluminium wall angle of size 24mm x 24mm fixed to
1200mm center to center in both directions using 2.0mm thick GI wire for finished of size 600mm x 600mm
s such as cutting , fixing of standing of frame work exposing roof complete for finished item of work in all floors.

32.00
13.20
102.40
12.80
5.12

76.14
61.02
14.10
28.20
105.00
56.89

21.12
38.72
566.71
5.67
572.38
77.93
650.31
650

roperties & weight as per IS 1239 ISI mark MS Tube for fixing of GI Sheet including cost and conveyance of all
es etc., complete for finished item of work in all floors for stair case head room roof.

387.60
153.00
30.60
18.36
589.56
CIVIL DATA 2020-21 : Page-892

80.27
669.83
670

Profile Roofing sheets with 0.50mm thickness, Coating: Alu-Zinc coating AZ150 GSM. Tensile Strength: 550
g Thickness (Top): 18 to 20 Microns, (Bottom): 5 to 7 Microns. Sheet Width: 1.020, Length: Maximum 12 Meters
dia with bitumen & G.I limpet washers filled with white lead & including a coat of approved steel primer and two
o a pitch of 600) etc., complete, excluding the cost of purlins, rafters, trusses including cost and conveyance of
c., complete for finished item of work in all floors.

4273.50
287.46

482.90

183.64
183.64

474.60
477.75
190.47
6553.96
655.40
89.23
744.63
745

manufactured as per companies standard specification including cost of materials packing as per companiess
of work , and taxes such as complete sales tax,C.E.D and others etc., as applicable including labour charges
ed item of work.
CIVIL DATA 2020-21 : Page-893

mm wide including cost and conveyance of all materials to site and sales and other taxes on all materials to site

f 300mm Dia., NP-3 class for cross ducts including cost and conveyance of Pipes etc., complete and Labour
position including lifting, aligning, lowering and hoisting etc., as per drawing and as per MoRT&H Specification
No: 13 and as directed by the Engineer-in-Charge for finished item of work

88.20
262.50
1575.00
367.50

11462.50
941.38
14697.08
1175.77
160.08
1335.85
1336.00
CIVIL DATA 2020-21 : Page-894

cluding pre-watering of soil, removal of top soil, excavation of soils, depositing the soils on the embankment,
ith Vibratory Road Roller @ OMC to meet requirement of table 300-2 of MoRT&H, including all hire and
for finished item of work as per MoRT&H specification 305 (4th revision) including cost and conveyance of all
complete for finished item of work (Payment will be made based on level for finished item of work).

273.00

5817.78
3722.00
3224.00
3479.20
2784.00
19299.98
2627.69
21927.67
219.28
219.00
CIVIL DATA 2020-21 : Page-895

al confirming to Grading - III of MORT & H Table 400-2 including cost and conveyance of all material to work
roved means, on prepared surface mixing by mix place method with Rotavator/ approved means, at OMC and
c., complete for finished item of work as per MoRT& H specification 401 (4th revision) and as directed by the
ials , labour charges , overheads and contractors profit etc., complete for finished item of work (Payment will be

0.00
1260.00

4200.00
1092.00

22332.00
20875.20
2418.00

264766.50

120137.70

2088.00
439169.40
1463.90
199.31
1663.21
1663.00
CIVIL DATA 2020-21 : Page-896

nd construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub
1.2.2 M 30 (Grade), coarse and fine aggregates conforming to IS : 383, maximum in a concrete mixer of not less
proved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 mictron thick
work as per drawing), spreading the concrete with sholvels, rakes, compacted using needle, scareed and plate
of contraction and expansion, construction joints, applying debonding strips, primer, sealant, dowel bars, near
s as approved, curing of concrete slabs for 14- days, curing compound (where specified) and water finishing to
use 1501 MORD including cost and conveyance of all materials , labour charges , overheads and contractors

3150.00
2825.00
78750.00

3150.00

3150.00

590.00
18323.00

6771.60

11044.80
2208.96
343.80
1988.10
397.62
450.00
432.00
400.00
4030.00
CIVIL DATA 2020-21 : Page-897

2905.60
589.00
117.80

119124.00

35808.75
110775.00
6290.63

7408.80

1824.00
751.50
289.80
9272.00
2088.00
2472.00
437721.76
13131.65
450853.41
61383.69
512237.10
6829.83
6830

g and compacting graded HBG/HBG crushed stone aggregate to Wet Mix macadem specification including
ding premixing the material with water at OMC in Mechanical mix plant carriage of mixed material by tipper to
CIVIL DATA 2020-21 : Page-898

293.04
1050.00
5250.00
1648.26
8241.30

12837.00
10800.00
11898.00
16830.00
13568.88
2418.00
68351.88

120011.76

127933.34

48737.70
296682.80

18663.80

391939.78
39193.98
431133.76
1916.15
1916

mer coat with Bitumen Emulsion (Slow Setting-1) on the prepared surface of granular base including
paraying primer at the rate of 0.70kg/sqm using mechanical means for finished item of work as per MoRT&H

48.84
1050.00
274.71
CIVIL DATA 2020-21 : Page-899

1373.55

1248.80
1715.56

3206.00
691.00
6861.36

86007.25
4836.00
90843.25

4953.91

104032.07
10403.21
114435.27
32.70
33

coat with bitumen VG-10 bitumen using pressure distributor at the rate of 0.2Kgs per sqm on the prepared
eaned with mechanical broom for finished item of work as per MoRT&H Specification 503 (5th revision) and as

48.84
1050.00
274.71
1373.55

1248.80
1715.56

3206.00
6170.36

38937.50
CIVIL DATA 2020-21 : Page-900

38937.50

2324.07

48805.48
4880.55
53686.03
15.34
15.00

m thick Bituminous Macadam with hot mix plant producing an average output of 37.5 tonnes per hour using
aggregates of Grading - II as per table 500-4 of MoRT&H specificaion 504 (5th revision) premixed with

512.82

7350.00
2625.00
2621.96
13109.78

318672.00
1347.94
22890.00
15132.00
11898.00

6731.79
13568.88

8443.50
398684.11

837911.25
CIVIL DATA 2020-21 : Page-901

168017.22

114421.24

35276.16

1155625.87

78370.99

1645790.74
164579.07
1810369.82
8831.07
8831.00

m thick Bituminous concrete with 40-60 TPH HMP /100 to 120 TPH batch type hot mix plant using HBG
g-2 as per table 500-17 of Specification 507 of MoRT&H (5th revesion), premixed with Bituminious binder VG-30
er, transporting the hot mix to work site, laying with paver finisher to the required grade, level and alignment,
bratory and tandem rollers to achieve the desired compaction as per MoRT&H Specification 507 (5th Revision)
ork in all respects excluding seiniorage charges and as directed by Engineer-in-charge

512.82
CIVIL DATA 2020-21 : Page-902

7350.00
2625.00
2621.96
13109.78

177684.00
16830.00
15132.00
11898.00

6731.79
6895.20

8443.50
243614.49

607281.30

83928.17

69960.25

75355.41
1552.39
17964.54
856042.06

55638.32

1168404.64
116840.46
1285245.10
6729.03
6729
WS & SA DATA 2021-22 - Page : 903

DATA FOR WATER SUPPLY AND SANITARY ITEMS


Agency area allowance 20%
S.No CFMS code SoR Ref Description Qty Unit Rate Per Unit Amount
1 Supplying and laying, filling, jointing and testing SWG SP-1 pipe conforming to ISI 651 & 4127 with air tight Cement joints in CM (1.5:1) prop. including
excavation of trenches and socket pits in any soil (except rock requiring blasting) and refilling with watering and tamping to the required slope including cost and
conveyance of all materials to site and all labour charges , overheads & contractor profit etc., complete for finished item of work (APSS NO 1301 & 1318)

a) 101.60mm dia up to 914.40mm (3') depth


MAT-01668 BMW-A.02 Rate as per SoR 1.00 RM 417.00 1 RM 417.00
Overheads&Contractors Profit @13.615% 0.13615 417.00 56.77
473.77
Rate per 1 RM say 474

b) 152.40mm dia upto 1524.0mm (5') depth


MAT-01669 BMW-A.03 Rate as per SoR 1.00 RM 620.00 1 RM 620.00
Overheads&Contractors Profit @13.615% 0.13615 620.00 84.41
704.41
Rate per 1 RM say 704

c) 203.20mm dia upto 1524mm (5') depth


MAT-01677 BMW-A.17 Cost of SWG pipe 1.00 RM 448.00 1 RM 448.00
labour charges for laying , jointing , testing 1.00 RM 326.00 1 RM 326.00
Add for MAA @ 20% 0.20 326.00 65.20
839.20
Overheads&Contractors Profit @13.615% 0.13615 839.20 114.26
Rate per 1 RM 953.46
say 953

d) 254mm dia upto 1524mm (5') depth


MAT-01678 BMW-A.18 Cost of SWG pipe 1.00 RM 821.00 1 RM 821.00
labour charges for laying, jointing, testing 1.00 RM 326.00 1 RM 326.00
Add for MAA @ 20% 0.20 326.00 65.20
1212.20
Overheads&Contractors Profit @13.615% 0.13615 1212.20 165.04
Rate per 1 RM 1377.24
say 1377
WS & SA DATA 2021-22 - Page : 904

e) 300mm dia upto 1524mm (5') depth


MAT-01679 BMW-A.19 Cost of SWG pipe 1.00 RM 1183.00 1 RM 1183.00
labour charges for laying , jointing , testing 1.00 RM 326.00 1 RM 326.00
Add for MAA @ 20% 0.20 326.00 65.20
1574.20
Overheads&Contractors Profit @13.615% 0.13615 1574.20 214.33
Rate per 1 RM 1788.53
say 1789

2 Constructing 904.0 mm (3’0”) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986 with cement mortar (1:6) prop using 2nd Class Clay Bricks
of 225 mm thick from approved source having a minimum crushing strength of 5 N/sq.mm including plastering with cement mortar 1:3 prop; ½” thick both inside
and outside fitted with 20” dia RCC manhole covers and frames including excavating pits up to a depth of 904 mm (3'-0") in all sorts of soils (exculding rock)
and laying cement conrete (1:4:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as per Standard specification and
including cost and conveyance of all materials like cement, sand, bricks, water etc., to site and all incidental and operational, labour charges like mixing cement
mortar, constructing masonry, lift charges, curing , overheads & contractors profit etc., complete for finished item of work as per Standard specification.

MAT-05235 BMW-B.03 Rate as per SoR 1 No. 6118.00 Each 6118.00


Overheads&Contractors Profit @13.615% 0.13615 6118.00 832.97
6950.97
Rate per Each say 6951

3 Constructing 904.0 mm (3’0”) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986 with cement mortar (1:6) prop using 2nd Class Clay Bricks
of 225 mm thick from approved source having a minimum crushing strength of 5 N/sq.mm including plastering with cement mortar 1:3 prop; ½” thick both inside
and outside fitted with 20” dia RCC manhole covers and frames including excavating pits up to a depth of 1524 mm (5'-0") in all sorts of soils (exculding rock)
and laying cement conrete (1:4:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as per Standard specification and
including cost and conveyance of all materials like cement, sand, bricks, water etc., to site and all incidental and operational, labour charges like mixing cement
mortar, constructing masonry, lift charges, curing , overheads & contractors profit etc., complete for finished item of work as per Standard specification.

MAT-05236 BMW-B.04 Rate as per SoR 1 No. 9557.00 Each 9557.00


Overheads&Contractors Profit @13.615% 0.13615 9557.00 1301.19
10858.19
Rate per Each say 10858
WS & SA DATA 2021-22 - Page : 905

4 Constructing 457.2 mm x 457.2 mm (1'6"x1'6") brick in CM 1:6 prop. Masonry. Inspection chamber upto 914.4 mm (3'0") and fitted with light weight 457.2
mm x 457.2 mm (1'6"x1'6") C.I frame and cover of 20 Kg including cost and conveyance of all materials like cement, sand, bricks, water etc., to site and all
incidental and operational, labour charges like mixing cement mortar, constructing masonry, lift charges, curing , overheads & contractors profit etc., complete for
finished item of work as per Standard specification.

MAT-01738 BMW-B.06 Rate as per SoR 1 No. 3590.00 Each 3590.00


Overheads&Contractors Profit @13.615% 0.13615 3590.00 488.78
4078.78
Rate per Each say 4079

5 Supplying and fixing of SWG Gully traps 150mm x 100mm of ISI make confirming to IS 651 & 4127 with C.I grating & constructing cement brick masonry in CM
(1:6) prop., intermediate chamber and fitted with 304.8 mm X 288.6 mm (12"x9") C.I Frame with hinged cover of standard make as approved including cost and
conveyance of all materials to site, labour charges, overheads & contractors profit etc., complete for finished item of work.

MAT-01732 BMW-A.72 Rate as per SoR 1 No. 533.00 1 Each 533.00


Overheads&Contractors Profit @13.615% 0.13615 533.00 72.57
605.57
Rate per Each say 606

6 Supplying and fixing of 4" (101.6mm) multi floor trap with jali - UPVC/SWR pipe fittings as per site requirements with standard practice for all floors including
cost and conveyance of all materials to site, labour charges , overheads & contractors profit etc., complete for finished item of work.

MAT-02006 BMW-G.119 Rate as per SoR 1 No. 133.00 1 Each 133.00


Overheads&Contractors Profit @13.615% 0.13615 133.00 18.11
151.11
Rate per Each say 151
WS & SA DATA 2021-22 - Page : 906

7 Supplying and fixing 580mm x 440mm long Orissa pan white glazed Water Closet 1st quality ISI marked confirming to IS:2556-Part-3-1981 with "P" or "S"
trap, ISI marked and providing masonry seat, CC squatting plate and 10 litres capacity single flush PVC low level cistern with internal components fixed on 2
Nos. of teak wood blocks of size 76.20mm x 101.60mm using required size of nails, screws as approved by Engineer-in-charge, angle stop cock 12.70mm dia.
first quality Indian make heavy duty, 12.70mm PVC connection with brass union nuts CP coated , 31.75mm brass plumber union, P trap or S trap of Indian W.C.
shall be encased on CC (1:2:4) 150mm alround well above the joint to stop leakage at the joint etc., complete including cost and conveyance of all materials to
site, cost of CC bed, labour charges, overheads & contractors profit etc., complete for finished item of work.

MAT-01783 BMW-D.04 Cost of Orissa pan 1 No. 1551.00 1 Each 1551.00


LAB-00165 BMW-D.06 Add MA on labour charges for fixing Orissa pan 0.20 428.00 85.60
MAT-01786 BMW-D.09 Cost of Brick masonry seat 1 No. 303.00 1 Each 303.00
MAT-01787 BMW-D.10 Cost of C C squatting plate 1 No. 90.00 1 Each 90.00
MAT-01895 BMW-G.08 Cost of slim line PVC flush tank 10 Ltrs. capacity single flush 1 No. 1390.00 1 Each 1390.00
MAT-01812 BMW-E.05 Angle stop cock 12.70mm 1 No. 453.00 1 Each 453.00
LAB-00178 BMW-E.06 Add MA on labour charges for fixing angle stop cock 0.20 49.00 9.80
MAT-02172 BMW-I.48, 12.70mm PVC connection with brass union nuts 1 No. 95.00 1 Each 95.00
Add MA on labour charges for fixing PVC connection with brass union
LAB-00282 BMW-I.49 nuts
0.20 19.00 3.80
MAT-01815 BMW-E.11 31.75mm brass plumber union 1 No. 68.00 1 Each 68.00
LAB-00181 BMW-E.12 Add MA on labour charges for fixing 31.75mm brass plumber union 0.20 16.00 3.20
LAB-00280 BMW-I.46 Cutting holes in brick masonry 1 No. 54.00 1 Each 54.00
Add MA on labour charges for cutting holes in brick masonry 0.20 54.00 10.80
MAT-02171 BMW-I.42 Teak wood blocks 76.2mm x 101.6mm 2 Nos. 25.00 1 Each 50.00
LAB-00277 BMW-I.43 Add MA on labour charges for fixing Teak wood blocks 0.20 11.00 2.20
4169.40
Overheads&Contractors Profit @13.615% 0.13615 4169.40 567.66
4737.06
Rate per Each 4737

8 Supplying and fixing European Water Closet of 1st quality conforming to IS:2556-Part-2-1973 of white glazed with 'S' trap,supplying and fixing best Indian
make plastic seat and lid for European water closets with rubber or plastic Buffers as per IS 2548-1996 and 10 litres capacity single flush PVC low level cistern
with internal components and fixed using required size of nails and screws, angle stop cock 12.70mm dia. first quality Indian make heavy duty, 12mm PVC
connections with brass union nuts CP coated including cost and conveyance of all materials to site, overheads & contractors profit etc., complete for finished item
of work for all floors.

MAT-01790 BMW-D.14 Cost of EWC with 'S' trap 1 No 1889.00 1 Each 1889.00
LAB-00168 BMW-D.15 Add MA on labour charges for fixing EWC 0.20 300.00 60.00
MAT-01895 BMW-G.08 Supply and fixing of 10 lts. Capacity lowdown PVC flushing tank 1 No 1390.00 1 Each 1390.00
MAT-01791 BMW-D.16 Plastic seat and lid for European Water Closet and rubber buffers 1 No 850.00 1 Each 850.00
WS & SA DATA 2021-22 - Page : 907

Add MA on labour charges for fixing Plastic seat and lid for EWC and
LAB-00169 BMW-D.17 rubber buffers
0.20 87.00 17.40
MAT-01812 BMW-E.05 Angle stop cock 12.70mm 1 No. 453.00 1 Each 453.00
LAB-00178 BMW-E.06 Add MA on labour charges for fixing angle stop cock 0.20 49.00 9.80
MAT-02172 BMW-I.48 12.70mm dia PVC connection with brass union nuts 1 No 95.00 1 Each 95.00
Add MA on labour charges for fixing PVC connection with brass union
LAB-00282 BMW-I.49 nuts
0.20 19.00 3.80
LAB-00280 BMW-I.46 Cutting holes in brick masonry 1 No. 54.00 1 Each 54.00
Add MA on labour charges for cutting holes in brick masonry
0.20 54.00 10.80
MAT-02171 BMW-I.42 Cost of 76.2 x 101.60 mm teakwood blocks 2 Nos 25.00 1 Each 50.00
LAB-00277 BMW-I.43 Add MA on labour charges for fixing Teak wood blocks 0.20 11.00 2.20
4885.00
Overheads&Contractors Profit @13.615% 0.13615 4885.00 665.09
5550.09
Rate per Each 5550
WS & SA DATA 2021-22 - Page : 908

9 Supplying and fixing Indian make Flat Back Wash Hand Basin 1st quality conforming to IS:2556-Part-4:1972 of size 550mm x 400mm with 32 mm nominal
size C.P. Fitting with parallel pipe thread conforming to IS:2963-1979 and fitted with 15 mm nominal bore Chromium Plated Pillar Tap of 1st quality Indian make
heavy duty complete with standard CI brackets including wooden blocks ,1 No.12.70mm PVC connection with brass union nuts CP coated , angle stop cock
12.70mm dia. first quality Indian make heavy duty, 31.75mm dia. PVC flexible waste pipe 914.4mm length of 1st quality including cost and conveyance of all
materials to site, labour charges , overheads & contractors profit for finished item of work

MAT-01798 BMW-D.24 Cost of Wash hand basin 1 No. 1736.00 1 Each 1736.00
LAB-00170 BMW-D.28 Add MA on labour charges for fixing Wash hand basin 0.20 362.00 72.40
MAT-01812 BMW-E.05 Angle stop cock 12.70mm 1 No. 453.00 1 Each 453.00
LAB-00178 BMW-E.06 Add MA on labour charges for fixing angle stop cock 0.20 49.00 9.80
MAT-02172 BMW-I.48 12.70mm PVC connection with brass union nuts 1 No. 95.00 1 Each 95.00
Add MA on labour charges for fixing PVC connection with brass union
LAB-00282 BMW-I.49 nuts
0.20 19.00 3.80
MAT-02158 BMW-I.18 Deduct cost of NP chain and rubber plug 1 No. 41.00 1 Each -41.00
MAT-01892 BMW-G.05 31.75mm dia. PVC flexible waste pipe 1 No. 24.00 1 Each 24.00
2353.00
Overheads&Contractors Profit @13.615% 0.13615 2353.00 320.36
2673.36
Rate per Each say 2673

10 Supplying and fixing NP soap dish heavy type of approved make ISI quality with NP screws etc., complete including cost and conveyance of all materials,
labour charges for fixing , overheads & contractors profit for finished item of work in all floors
MAT-02163 BMW-I.28 Cost of NP soap dish 1 No. 231.00 1 Each 231.00
LAB-00271 BMW-I.29 Add for MAA @ 20% 0.20 14.00 2.80
233.80
Overheads&Contractors Profit @13.615% 0.13615 233.80 31.83
265.63
Rate per Each say 266

11 Supplying and fixing TV shape mirror with plastic frame of size 609.6mm x 457.2mm , plywood back with NP screws 1st quality including cost and
conveyance of all materials, labour charges , overheads & contractors profit for finished item of work in all floors.
MAT-02206 BMW-I.105 Rate as per SoR 1 No. 502.00 Each 502.00
LAB-00306 BMW-I.106 Add for MAA @ 20% 0.20 132.00 26.40
528.40
Overheads&Contractors Profit @13.615% 0.13615 528.40 71.94
600.34
Rate per Each say 600
WS & SA DATA 2021-22 - Page : 909

12 Supplying and fixing of 25.4mm dia , 609.6mm long aluminium anodized towel rods with brackets and aluminium screws including cost and conveyance of
all materials, labour charges , overheads & contractors profit for finished item of work.

MAT-02159 BMW-I.20 Rate as per SoR 1 No. 162.00 Each 162.00


LAB-00267 BMW-I.21 Add for MAA @ 20% 0.20 50.00 10.00
172.00
Overheads&Contractors Profit @13.615% 0.13615 172.00 23.42
195.42
Rate per Each say 195

13 Supplying and fixing steel surgical long elbow action handle 12.7mm dia bib cock as approved by the Engineer-In-Charge including cost and conveyance of
all materials, labour charges , overheads & contractors profit complete for finished item of work in all floors.

MAT-02218 BMW-I.126 Rate as per SoR 1 No. 946.00 Each 946.00


Overheads&Contractors Profit @13.615% 0.13615 946.00 128.80
1074.80
Rate per Each say 1075

14 Supplying and fixing NP bib taps of size 12.70mm dia of Indian make heavy duty (short body) as approved by the Engineer-In-Charge including cost and
conveyance of all materials, labour charges , overheads & contractors profit complete for finished item of work in all floors.

MAT-01814 BMW-E.09 Rate as per SoR 1 No. 248.00 Each 248.00


LAB-00180 BMW-E.10 Add for MAA @ 20% 0.20 33.00 6.60
254.60
Overheads&Contractors Profit @13.615% 0.13615 254.60 34.66
289.26
Rate per Each say 289

15 Supplying and fixing NP bib taps of size 12.70mm dia of Indian make heavy duty (long body) as approved by the Engineer-In-Charge including cost and
conveyance of all materials, labour charges , overheads & contractors profit complete for finished item of work in all floors.
MAT-01813 BMW-E.07 Rate as per SoR 1 No. 387.00 Each 387.00
LAB-00179 BMW-E.08 Add for MAA @ 20% 0.20 33.00 6.60
393.60
Overheads&Contractors Profit @13.615% 0.13615 393.60 53.59
447.19
Rate per Each say 447
1 Supply & fixing bib cock cum health faucet with 1 m long flexible tube and wall hook ofJaquar make queen series with 7 years warranty Chrome plated including
overheads & contractors profit for finished item of work in all floors.
WS & SA DATA 2021-22 - Page : 910

MAT-02233 BMW-I.141 Rate as per SoR 1 No. 4166.00 Each 4166.00


4166.00
Overheads&Contractors Profit @13.615% 0.13615 4166.00 567.20
4733.20
Rate per Each say 4733

16 Supplying and fixing of SWR PVC pipes (Prince/Sudhakar/Kisan/Supreme or any ISI brand) 4 Kg/Sq.cm. and fixing all special such as plain bends, off sets,
door bends, single junctions, double junctions as per site requirement, fixing with PVC clamps if necessary with required number of Bombay nails including cost
and conveyance of all materials to site, labour charges, overheads & contractors profit complete for finished item of work at all floor levels. (APSS No. 1302 1319
& 1326)

a) 75mm dia
Data for 6 RM
MAT-01898 BMW-G.11 Cost of 75mm dia pipe 6.00 RM 236.00 3 RM 472.00
MAT-01991 BMW-G.104 Cost of PVC clamps 3 Nos. 15.00 Each 45.00
LAB-00259 BMW-G.152 Labour charges 6.00 RM 79.00 1 RM 474.00
991.00
Rate per 1 RM 165.17
Overheads&Contractors Profit @13.615% 0.13615 165.17 22.49
187.66
say 188

b) 90mm dia
Data for 6 RM
MAT-01899 BMW-G.12 Cost of 90mm dia pipe 6.00 RM 375.00 3 RM 750.00
MAT-01992 BMW-G.105 Cost of PVC clamps 3 Nos. 16.00 Each 48.00
LAB-00259 BMW-G.152 Labour charges 6 RM 79.00 1 RM 474.00
1272.00
Rate per 1 RM 212.00
Overheads&Contractors Profit @13.615% 0.13615 212.00 28.86
240.86
say 241

c) 110mm dia
Data for 6 RM
MAT-01900 BMW-G.13 Cost of 110mm dia pipe 6.00 RM 447.00 3 RM 894.00
MAT-01993 BMW-G.106 Cost of PVC clamps 3 Nos. 17.00 Each 51.00
LAB-00259 BMW-G.152 Labour charges 6 RM 79.00 1 RM 474.00
1419.00
WS & SA DATA 2021-22 - Page : 911

Rate per 1 RM 236.50


Overheads&Contractors Profit @13.615% 0.13615 236.50 32.20
268.70
say 269
WS & SA DATA 2021-22 - Page : 912

d) 160mm dia
Data for 6 RM
MAT-01919 BMW-G.32 Cost of 160mm dia pipe 6.00 RM 1066.00 3 RM 2132.00
MAT-01994 BMW-G.107 Cost of PVC clamps 3 Nos. 33.00 Each 99.00
LAB-00259 BMW-G.152 Labour charges 6 RM 79.00 1 RM 474.00
2705.00
Rate per 1 RM 450.83
Overheads&Contractors Profit @13.615% 0.13615 450.83 61.38
512.21
say 512

17 Supply and fixing of Ashirvad/ Ajay/ Astral Flowguard or equivalent CPVC Pipes and Fittings SDR 11 to meet the requirement of ASTM-D 2846 and are
produced in CTS (Copper Tube Sizes 1/2" to 2") for hot and cold water (IS 15778:2007) including cost and conveyance of all materials to site, labour charges for
fixing, overheads & contractors profit complete for finished item of work at all floor levels.
a) 15.90mm OD pipe
MAT-02318 BMW-I.226 Rate as per SoR 1 No. 68.00 Each 68.00
Overheads&Contractors Profit @13.615% 0.13615 68.00 9.26
Rate per 1 RM 77.26
say 77

b) 22.20mm OD pipe
MAT-02319 BMW-I.227 Rate as per SoR 1 No. 103.00 Each 103.00
Overheads&Contractors Profit @13.615% 0.13615 103.00 14.02
Rate per 1 RM 117.02
say 117

c) 28.60mm OD pipe
MAT-02320 BMW-I.228 Rate as per SoR 1 No. 160.00 Each 160.00
Overheads&Contractors Profit @13.615% 0.13615 160.00 21.78
Rate per 1 RM 181.78
say 182

d) 34.90mm OD pipe
MAT-02321 BMW-I.229 Rate as per SoR 1 No. 254.00 Each 254.00
Overheads&Contractors Profit @13.615% 0.13615 254.00 34.58
Rate per 1 RM 288.58
say 289
WS & SA DATA 2021-22 - Page : 913

e) 41.30mm OD pipe
MAT-02322 BMW-I.230 Rate as per SoR 1 No. 348.00 Each 348.00
Overheads&Contractors Profit @13.615% 0.13615 348.00 47.38
Rate per 1 RM 395.38
say 395

f) 54.00mm OD pipe
MAT-02323 BMW-I.231 Rate as per SoR 1 No. 535.00 Each 535.00
Overheads&Contractors Profit @13.615% 0.13615 535.00 72.84
Rate per 1 RM 607.84
say 608

18 Supplying & fixing GI pipe Medium Grade properties & weight as per IS 1239 ISI mark in ground or on wall including cost of tees, elbows, bends, reducers,
couplings, running joints, union flanges, unions etc. with necessary excavation in all types of soils except rock requiring blasting, refilling, chiselling masonry walls
and making good the walls & floors to the original surface and fixing MS clamps on TW blocks on walls including cost and conveyance of all materials and labour
charges , overheads & contractors profit complete for finished item of work.

a) 15mm Nominal bore


MAT-05243 BMW-F.79 Rate as per SoR 1.00 RM 199.00 1 RM 199.00
LAB-00233 BMW-F.80 Add for MAA @ 20% 0.20 46.00 9.20
208.20
Overheads&Contractors Profit @13.615% 0.13615 208.20 28.35
236.55
Rate per 1 RM say 237

b) 20mm Nominal bore


MAT-05244 BMW-F.81 Rate as per SoR 1.00 RM 220.00 1 RM 220.00
LAB-00235 BMW-F.82 Add for MAA @ 20% 0.20 46.00 9.20
229.20
Overheads&Contractors Profit @13.615% 0.13615 229.20 31.21
260.41
Rate per 1 RM say 260

c) 25mm Nominal bore


MAT-05245 BMW-F.83 Rate as per SoR 1.00 RM 286.00 1 RM 286.00
LAB-00237 BMW-F.84 Add for MAA @ 20% 0.20 46.00 9.20
295.20
Overheads&Contractors Profit @13.615% 0.13615 295.20 40.19
335.39
WS & SA DATA 2021-22 - Page : 914

Rate per 1 RM say 335

d) 32mm Nominal bore


MAT-05246 BMW-F.85 Rate as per SoR 1.00 RM 398.00 1 RM 398.00
LAB-00239 BMW-F.86 Add for MAA @ 20% 0.20 46.00 9.20
407.20
Overheads&Contractors Profit @13.615% 0.13615 407.20 55.44
462.64
Rate per 1 RM say 463

e) 40mm Nominal bore


MAT-05247 BMW-F.87 Rate as per SoR 1.00 RM 444.00 1 RM 444.00
LAB-00241 BMW-F.88 Add for MAA @ 20% 0.20 50.00 10.00
454.00
Overheads&Contractors Profit @13.615% 0.13615 454.00 61.81
515.81
Rate per 1 RM say 516

f) 50mm Nominal bore


MAT-05248 BMW-F.89 Rate as per SoR 1.00 RM 480.00 1 RM 480.00
LAB-00243 BMW-F.90 Add for MAA @ 20% 0.20 76.00 15.20
495.20
Overheads&Contractors Profit @13.615% 0.13615 495.20 67.42
562.62
Rate per 1 RM say 563

19 Supplying and fixing 65 mm Nominal Bore GI pipe Medium Grade properties & weight as per IS 1239 in ground or on wall with GI fittings such as elbows
tees couplings, nipples, plugs including excavation for trenches and refilling the trenches ,chiselling masonry walls and making good the walls & floors to the
original surface and fixing MS clamps on TW blocks on walls including cost and conveyance of all materials and labour charges , overheads & contractors profit
complete for finished item of work except for GI bends union and GI connectors with checkout and socket Tata or Zenith make or equivalent

MAT-01870 BMW-F.91 Rate as per SoR 1.00 RM 837.00 1 RM 837.00


Overheads&Contractors Profit @13.615% 0.13615 837.00 113.96
950.96
Rate per 1 RM say 951
WS & SA DATA 2021-22 - Page : 915

20 Supplying and fixing Gunmetal Gate ( GM peet ) valve as per IS-778 Class - I , Indian make heavy type including cost and conveyance of all materials , labour
charges , overheads & contractors profit complete for finished item of work.

a) 15mm Nominal bore


MAT-01847 BMW-F.21 Rate as per SoR 1 No. 604.00 Each 604.00
LAB-00197 BMW-F.22 Add for MAA @ 20% 0.20 50.00 10.00
614.00
Overheads&Contractors Profit @13.615% 0.13615 614.00 83.60
697.60
Rate per Each say 698

b) 20mm Nominal bore


MAT-01846 BMW-F.19 Rate as per SoR 1 No. 812.00 Each 812.00
LAB-00196 BMW-F.20 Add for MAA @ 20% 0.20 50.00 10.00
822.00
Overheads&Contractors Profit @13.615% 0.13615 822.00 111.92
933.92
Rate per Each say 934

c) 25mm Nominal bore


MAT-01845 BMW-F.17 Rate as per SoR 1 No. 1165.00 Each 1165.00
LAB-00195 BMW-F.18 Add for MAA @ 20% 0.20 50.00 10.00
1175.00
Overheads&Contractors Profit @13.615% 0.13615 1175.00 159.98
1334.98
Rate per Each say 1335

d) 32mm Nominal bore


MAT-01848 BMW-F.23 Rate as per SoR 1 No. 1768.00 Each 1768.00
LAB-00198 BMW-F.24 Add for MAA @ 20% 0.20 43.00 8.60
1776.60
Overheads&Contractors Profit @13.615% 0.13615 1776.60 241.88
2018.48
Rate per Each say 2018
WS & SA DATA 2021-22 - Page : 916

e) 40mm Nominal bore


MAT-01849 BMW-F.25 Rate as per SoR 1 No. 2389.00 Each 2389.00
LAB-00199 BMW-F.26 Add for MAA @ 20% 0.20 75.00 15.00
2404.00
Overheads&Contractors Profit @13.615% 0.13615 2404.00 327.30
2731.30
Rate per Each say 2731

f) 50mm Nominal bore


MAT-01850 BMW-F.27 Rate as per SoR 1 No. 3498.00 Each 3498.00
LAB-00200 BMW-F.28 Add for MAA @ 20% 0.20 101.00 20.20
3518.20
Overheads&Contractors Profit @13.615% 0.13615 3518.20 479.00
3997.20
Rate per Each say 3997

g) 65mm Nominal bore


MAT-01851 BMW-F.29 Rate as per SoR 1 No. 5398.00 Each 5398.00
LAB-00201 BMW-F.30 Add for MAA @ 20% 0.20 119.00 23.80
5421.80
Overheads&Contractors Profit @13.615% 0.13615 5421.80 738.18
6159.98
Rate per Each say 6160

h) 80mm Nominal bore


MAT-01852 BMW-F.31 Rate as per SoR 1 No. 7995.00 Each 7995.00
LAB-00202 BMW-F.32 Add for MAA @ 20% 0.20 149.00 29.80
8024.80
Overheads&Contractors Profit @13.615% 0.13615 8024.80 1092.58
9117.38
Rate per Each say 9117

21 Providing and placing on terrace (at all floor levels)polyetheylene water storage tank with double layer approved brand and manufacture with cover and
suitable locking arrangement and making necessary holes for inlet and outlets and over flow pipes but without fittings and base support for tanks including cost
and conveyance of all materials and labour charges , overheads & contractors profit complete for finished item of work.
MAT-01889 BMW-G.01 Rate as per SoR 1 Ltr 8.50 1 Ltr 8.50
LAB-00258 BMW-G.02 Add for MAA @ 20% 0.20 1.00 0.20
8.70
WS & SA DATA 2021-22 - Page : 917

Overheads&Contractors Profit @13.615% 0.13615 8.70 1.18


Rate per 1 Ltr 9.88

22 Supplying and fixing of stainless steel sink of size 508.00mm x 457.2mm x 203.20mm, 1mm thick of Indian make fixed on cantilever brackets including
supply and fixing 31.75mm C.P. waste coupling, 31.75 mm dia PVC flexible waste pipe of 914.4 mm length of Ist quality ncluding chiselling brick masonry wall
and making good & restoring to original surfaces , overheads & contractors profit complete for finished item of work in all floors
MAT-02215 BMW-I.123 Rate as per SoR 1 No 5142.00 Each 5142.00
MAT-02216 BMW-I.124 Add for MAA @ 20% 0.20 509.00 101.80
LAB-00280 BMW-I.46 Cutting holes in brick masonry 1 No. 54.00 1 Each 54.00
5297.80
Overheads&Contractors Profit @13.615% 0.13615 5297.80 721.30
6019.10
Rate per Each say 6019

23 Supplying and fixing of stainless steel sink of size 914.4 mm x457.2mm, 1mm thick of Indian make fixed on cantilever brackets including supply and fixing
31.75mm C.P. waste coupling, 31.75 mm dia PVC flexible waste pipe of 914.4 mm length of Ist quality ncluding chiselling brick masonry wall and making good &
restoring to original surfaces overheads & contractors profit complete.for finished item of work in all floors.

MAT-02213 BMW-I.119 Rate as per SoR 1 No 7175.00 Each 7175.00


LAB-00313 BMW-I.120 Add for MAA @ 20% 0.20 574.00 114.80
LAB-00280 BMW-I.46 Cutting holes in brick masonry 1 No. 54.00 1 Each 54.00
7343.80
Overheads&Contractors Profit @13.615% 0.13615 7343.80 999.86
8343.66
Rate per Each say 8344

24 Supplying and fixing of vitreous porcelain sink of size 600 mm x 400 mm x 250mm of Indian make fixed conforming to IS:2556-Part-5-1994 on cantilever
brackets with 32 mm nominal size C.P. Fitting with parallel pipe thread conforming to IS:2963-1979, PVC flexible waste pipe of 914.4 mm length of Ist quality
including supply and fixing all materials, chiselling brick masonry wall and making good & restoring to original surfaces, overheads & contractors profit complete.for
finished item of work in all floors.

MAT-01807 BMW-D.37 Rate as per SoR 1 No 4789.00 Each 4789.00


LAB-00174 BMW-D.39 Add for MAA @ 20% 0.20 362.00 72.40
MAT-02158 BMW-I.18 Deduct cost of NP chain and rubber plug 1 No. 41.00 1 Each -41.00
MAT-01892 BMW-G.05 31.75mm dia. PVC flexible waste pipe 1 No. 24.00 1 Each 24.00
LAB-00280 BMW-I.46 Cutting holes in brick masonry 1 No. 54.00 1 Each 54.00
4898.40
Overheads&Contractors Profit @13.615% 0.13615 4898.40 666.92
5565.32
WS & SA DATA 2021-22 - Page : 918

Rate per Each say 5565

25 Supplying and fixing of vitreous porcelain sink of size 750 mm x 450 mm x 250mm of Indian make fixed conforming to IS:2556-Part-5-1994 on cantilever
brackets with 32 mm nominal size C.P. Fitting with parallel pipe thread conforming to IS:2963-1979, PVC flexible waste pipe of 914.4 mm length of Ist quality
including supply and fixing all materials, chiselling brick masonry wall and making good & restoring to original surfaces, overheads & contractors profit complete.for
finished item of work in all floors.

MAT-01808 BMW-D.38 Rate as per SoR 1 No 5371.00 Each 5371.00


LAB-00174 BMW-D.39 Add for MAA @ 20% 0.20 362.00 72.40
MAT-02158 BMW-I.18 Deduct cost of NP chain and rubber plug 1 No. 41.00 1 Each -41.00
MAT-01892 BMW-G.05 31.75mm dia. PVC flexible waste pipe 1 No. 24.00 1 Each 24.00
LAB-00280 BMW-I.46 Cutting holes in brick masonry 1 No. 54.00 1 Each 54.00
5480.40
Overheads&Contractors Profit @13.615% 0.13615 5480.40 746.16
6226.56
Rate per Each say 6227

26 Supplying and fixing white glazed flat back Bowl urinals of size 440 mm x 265 mm x 315 mm with integral flushing rim fixed with screws complete Indian
make (HSW/Parry/Neycer) conforming to IS:2556-1995 as approved by Engineer-in-charge, including supply and fixing 12.7mm PVC connection with brass
plumber union nuts CP coated, 12.70mm push cock 1st quality of approved make , 31.75 mm dia PVC flexible waste pipe of 914.4 mm length of Ist quality
including cost and conveyance of all materials to site, labour charges , overheads & contractors profit complete for finished item of work for all floors.

MAT-01804 BMW-D.33 Rate as per SoR 1 No 898.00 Each 898.00


LAB-00173 BMW-D.36 Add for MAA @ 20% 0.20 144.00 28.80
MAT-02172 BMW-I.48 12.7mm PVC connections with brass plumber union nuts 1 No 95.00 Each 95.00
LAB-00282 BMW-I.49 Add for MAA @ 20% 0.20 19.00 3.80
MAT-01826 BMW-E.29 12.70mm NP push cock 1 No 259.00 Each 259.00
MAT-01892 BMW-G.05 31.75mm dia. PVC flexible waste pipe 1 No 24.00 Each 24.00
1308.60
Overheads&Contractors Profit @13.615% 0.13615 1308.60 178.17
1486.77
Rate per Each Say 1487
WS & SA DATA 2021-22 - Page : 919

27 Supplying and fixing white glazed flat back half stall urinals of size 590 mm x 375 mm x 390 mm with integral flushing rim fixed with screws complete Indian
make (HSW/Parry/Neycer) conforming to IS:2556-1995 as approved by Engineer-in-charge, including supply and fixing 12.7mm PVC connection with brass
plumber union nuts CP coated, 12.70mm push cock 1st quality of approved make , 31.75 mm dia PVC flexible waste pipe of 914.4 mm length of Ist quality
including cost and conveyance of all materials to site, labour charges etc., overheads & contractors profit complete for finished item of work for all floors.

MAT-01806 BMW-D.35 Rate as per SoR 1 No 2935.00 Each 2935.00


LAB-00173 BMW-D.36 Add for MAA @ 20% 0.20 144.00 28.80
MAT-02172 BMW-I.48 12.7mm PVC connections with brass plumber union nuts 1 No 95.00 Each 95.00
LAB-00282 BMW-I.49 Add for MAA @ 20% 0.20 19.00 3.80
MAT-01826 BMW-E.29 12.70mm NP push cock 1 No 259.00 Each 259.00
MAT-01892 BMW-G.05 31.75mm dia. PVC flexible waste pipe 1 No 24.00 Each 24.00
3345.60
Overheads&Contractors Profit @13.615% 0.13615 3345.60 455.50
3801.10
Rate per Each Say 3801

28 Supplying and fixing of 16mm to 20 mm thick polished marble slab partitioins of size 4' 0" x 2' 0" for urinals including full rounding the edges , fixing in
position, polishing, including cost and conveyance of all materials and labour charges , overheads & contractors profit complete for finished item of work for all
floors.

MAT-00781 BMT-B.14 Rate as per SoR 0.72 Sqm 1070.00 1 Sqm 770.40
MAT-02151 BMW-I.07 Chiselling the brick masonry wall 1.20 RM 34.00 1 RM 40.80
Add for MAA @ 20% 0.20 40.80 8.16
LAB-00505 BMM-V.11 Rounding the edges of marble 2.40 RM 453.00 1 RM 1087.20
Labour charges for fixing ( dadooing labour charges ) 0.72 Sqm 905.10 10 Sqm 65.17
Add for MAA @ 20% 0.20 65.17 13.03
1984.76
Overheads&Contractors Profit @13.615% 0.13615 1984.76 270.23
2254.99
Rate per Each Say 2255
WS & SA DATA 2021-22 - Page : 920

29 Supplying and fixing of 101.60mm x 609.60mm white glazed porcelain channels 1st quality fixed in brick masonry to the required slopes , white cement
pointing including cost and conveyance of all materials and labour charges , overheads & contractors profit complete for finished item of work for all floors.

MAT-02217 BMW-I.125 Rate as per SoR 1 No 522.00 1 Each 522.00


Rate for 1 RM (1/0.6096) 522.00 856.30
Overheads&Contractors Profit @13.615% 0.13615 856.30 116.59
972.89
Say 973

30 Construction of brick masonry support for GI pipe of size 304.80mm x 228.60mm x 228.60 mm in CM (1:8) prop including plastering and finishing with 12mm
thick in CM (1:5) including cost and conveyance of all materials and all labour charges, overheads & contractors profit complete for finished item of work for all
floors.

MAT-02180 BMW-I.63 Rate as per SoR 1 No 76.00 1 Each 76.00


LAB-00290 BMW-I.64 Add for MAA @ 20% 0.20 25.00 5.00
81.00
Overheads&Contractors Profit @13.615% 0.13615 81.00 11.03
92.03
Rate per Each Say 92
31 Supply and delivery of "Resilient Seated Soft Sealing" Gate Valves (Sluice Valves) with Body and Bonnet of Ductile Iron GGG-40/SG-400/15 or GGG-50/SG-
500/7 or Equivalent as per IS1865, IS:3896-2 and Wedge fully Rubber Lined with food grade quality grade W270 grade EPDM, Replaceable Spindle Nut without
gland packing with 3-O ring protection system on the Shaft and Seals of NBR. The Valves should be Vacuum tight and 100% leak proof with face to face
dimensions as BS:5163 Type A/IS:14846. All the valves should be with fusion bonded Electrostatic Powder coating both inside and outside (Min 250 Microns)-
RAL 5005 with Pocket Less Straight through body Passage conforming to Design standards of DIN-3202F4/BS:5163 Type A Flange drilling as per IS - 1538
excluding all taxes, duties and transportation.PN 1.60

MAT-08069 Rate as per SoR 1 No 12957.00 1 Each 12957.00


12957.00
Overheads&Contractors Profit @13.615% 0.13615 12957.00 1764.10
14721.10
Rate per Each Say 14721
1 Supply, Delivery of D.I Double Flanged Swing Check type Reflux valves (Non Return Valves) of following dia. conforming to IS- 5312 (Pts-1&2) (with amendments
up to date, if any) having Body, Cover, Door, Bearing holder with D.I; Hinge pin, Door pin, Door suspension pin with Stainless Steel (IS 6603); Body seat ring ,
Door face ring, Bearing bushes, Plugs for hinge pin with Leaded Tin Bronze ( IS 318 ); Bolts, Nuts with Carbon steel; Gaskets with Rubber; Hinges with Cast steel;
excluding transportation and all taxes
complete.PN 1.6 (MPa)
WS & SA DATA 2021-22 - Page : 921

MAT-08047 Rate as per SoR 1 No 18975.00 1 Each 18975.00


18975.00
Overheads&Contractors Profit @13.615% 0.13615 18975.00 2583.45
21558.45
Rate per Each Say 21558
1 Centrifugally cast (Spun) Ductile Iron pressure pipes for water, gas and sewage with Socket Spigot ends conforming to IS.: 8329/2000 in standard working lengths
of 4, 5 5.5 & 6 meter for classification K9 & K7 suitable for push-on-joint (rubber gasket d jointing) with cement mortar lining inside the pipes with outside zinc
coating. Rates are ex-factory, excluding transportation and all taxes.

PH Table 24 Rate as per SoR 1 No 996.00 1 Each 996.00


996.00
Overheads&Contractors Profit @13.615% 0.13615 996.00 135.61
1131.61
Rate per Each Say 1132
1 Manufacture, Supply and delivery of DI D/F Butterfly Valves, Body and disc of Ductile Iron of grade GGG-40/SG-400/15 or GGG-50/SG-500/7 or Equivalent as per
IS1865, IS:3896-2 Double eccentrically designed Disc., with renewable soft seal on the disc and Integral Body seat face of nickel-chromium overlay welding
(Fusion Bonded) micro finished, 100 % leak tight in both directions, Medium free bearings and with minimum thickness of 250 microns Fusion bonded food grade
epoxy coating and 1200mm dia. and above food grade liquid Epoxy coating of minimum 150 microns applied on both body and disc inside and outside.
Face to face dimensions as per EN558-1/IS 13095 body or IS: 13095 long body design standard as per EN 593/IS 5163 Flange drilling as per EN 1092-2/ IS 1538
the Valve should be suitable for buried application.PN 1.6 (MPa)

MAT-08173 Rate as per SoR 150mm dia 1 No 24475.00 1 Each 24475.00


24475.00
Overheads&Contractors Profit @13.615% 0.13615 24475.00 3332.27
27807.27
Rate per Each Say 27807
31 Geological survey charges for finalisation of location of bore well including cost, transportation of all euipment, incidental charges, labour charges, overheads
and contractor profit etc., complete for finished item of work.

Table 38 of PH items Rate as per SoR 1 No 1200.00 1 No. 1200.00


add 10% extra for Agency area 0.20 1200.00 240.00
1440.00
Overheads&Contractors Profit @13.615% 0.13615 1440.00 196.06
Rate per Each 1636.06
Say 1636
WS & SA DATA 2021-22 - Page : 922
WS & SA DATA 2021-22 - Page : 923

32 Drilling of bore well by down the hole hammer drilling to a finished dia of 165mm in all formations suitable for down the hole hammer drilling such as
medium rock formation to hard rock formation, all consolidated formation and drilling in over burden to a dia of not less than 200mm etc., and reaming the bore
well to suit insertion of casing pipe with couplings, caps and any other relavant materials up to required depth as directed by the Department including
transportation of drilling rig and supporting vehicles and including bore development (Flushing of bore well at an average pressure of 150 PSI), conducting yileld
test, consumable charges, crew charges required in fixation of pipe assembly completely done to the satisfaction of the Department and including all labour
charges, overheads and contractor profit but excluding cost of casing pipe, couplings, cap etc., The entire work shall be done as per IS - 2800 Part I & II 1979 and
amended from time to time

a) up to 90m depth
Table 38 of PH items Rate as per SoR 1.00 RM 446.40 1 RM 446.40
add 10% extra for Agency area 0.20 446.40 89.28
535.68
Overheads&Contractors Profit @13.615% 0.13615 535.68 72.93
Rate per RM 608.61
Say 609

b) 90m to 150m depth


Table 38 of PH items Rate as per SoR 1.00 RM 477.60 1 RM 477.60
add 10% extra for Agency area 0.20 477.60 95.52
573.12
Overheads&Contractors Profit @13.615% 0.13615 573.12 78.03
Rate per RM 651.15
Say 651

33 Supply and fixing of 180mm dia 6 kgs/sqm PVC casing pipe including cost and conveyance of all materials and labour charges , overheads & contractors
profit complete for finished item of work

MAT-07656 Rate as per SoR (Table 20 of PHE items) 1 RM 923.00 1 RM 923.00


Overheads&Contractors Profit @13.615% 0.13615 923.00 125.67
Rate per 1 RM 1048.67
Say 1049

34 Supply and fixing of 180mm dia PVC bore cap including cost and conveyance of all materials and labour charges , overheads & contractors profit complete for
finished item of work
Table 38 of PH items Rate as per SoR (Table 38 of PHE items) 1.00 RM 300.00 1 RM 300.00
Overheads&Contractors Profit @13.615% 0.13615 300.00 40.85
Rate per Each 340.85
Say 341
ABSTRACT ESTIMATE FOR SECURITY BUILDING

Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)

1 Earth work excavation for foundations (Mechanical Means) for 25.00 ONE CUM #REF! #REF!
buildings in ordinary soils and depositing on bank for all lifts and
with an initial lead of 10m and up to 3m depth including all
operational,incidental, labour charges such as shoring, sheeting,
planking, strutting etc., and overheads & contractors profit
complete for finished item of work excluding dewatering charges
etc., as per SS 20 B(APSS 308)

2 Pre construction Anti termite treatment is a process in which 33.00 ONE Sqm #REF! #REF!
chemical toxic to subterrean tremites is apply/ inject into soil
during early stage of building Construction 2. Treatement of soil
Beneath the building and around the foundations conduct and
chemical use as per BIS - IS 6313 (Part -2) 2013 code
specification & CIB RC registered termiticide which creates a
continuous chemical barrier beneath the building which kills or
repels terminates & impervious to tremite entry 3. Imidacloprid
30.5% SC (IS 63131) dissolve 2.1 Ml/1 liter of water and apply
emulsion/solution @ 7.5 Litres/Square meter (Sqm) of internal,
external vertical surface of the colums, plinth beams (Back filling)
walls and floor junction, external perimeters, along reatining wall
@ 5.0 Liters/Sqm of the horizontal surface of basement top
surface of the basement filling below flooring bed (Plinth) & @ 2.0
Litres/ Line meter at expansion joints. The substructure of a
depth of 500mm around coulmns & 300mm deep around plinth
beams, basements & floor filling area including excavation
channel along the wall & rodding etc. cost & Conveyance of all
materials to the site, cost of labour for sparying, rodding,
overheads and contractor profit etc. complete for furnished item
of work as per the approval of the Engineer-in-charge

3 Plain Cement Concrete (1:4:8) (cement: fine aggregate: 2.10 ONE CUM #REF! #REF!
Coarse aggregate) for foundations using coarse aggregate
40mm size hard , machine crushed granite from approved
quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
including cost and conveyance of all materials like cement, sand,
coarse aggregate, water etc. to site including all charges for
machine mixing and hire charges of concrete mixer, laying
concrete in foundations and under flooring bed, ramming in 15
cm layers finishing top surface to the required level curing
etc.,and overheads & contractors profit complete for finished
item of work. (APSS No. 402) For Foundation

APMSIDC-KADAPA Security Building - Civil - Abs 924 of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)

4 Plain Cement Concrete (1:5:10) (cement: fine aggregate: 4.20 ONE CUM #REF! #REF!
Coarse aggregate) for foundations and under flooring bed
using coarse aggregate 40mm size hard , machine crushed
granite from approved quarry using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, sand, coarse aggregate, water etc. to site
including all charges for machine mixing and hire charges of
concrete mixer, laying concrete in foundations and under flooring
bed, ramming in 15 cm layers finishing top surface to the required
level curing etc.,and overheads & contractors profit complete for
finished item of work. (APSS No. 402)

5 Filling with useful available excavated earth (excluding rock) 20.00 ONE CUM #REF! #REF!
with a lead of 50 m in trenches, sides of foundations and
basement with initial lead in layers not exceeding 15cm thick,
watering and ramming including cost and conveyance of water to
work site and all operaitonal, incidental, labour charges, hire
charges of T&P etc., and overheads & contractors profit
complete for fnished item of work (APSS NO.309&310)

6 Filling with carted gravel in trenches,sides of foundations and 28.00 ONE CUM #REF! #REF!
basement with initial lead in layers not exceeding 15cm
thick,watering and ramming including cost and conveyance of
water to work site and all peraitonal,incidental, labour
charges,hire charges of T&P etc., and overheads & contractors
profit complete for fnished item of work(APSS NO.309&310)

7 Supply and placing of the Design Mix Concrete M 25 grade


corresponding to IS 456 with minimum cement content of 380
kgs per 1 cum of concrete using weigh batcher / mixer with
20mm size graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand) coarse aggregate,
water etc., to site, centering using steel scaffolding pipes ,
jack props , wallers , foot plates , brackets , steel centering
plates etc., including all operational, incidental and labour
charges such as weigh batching, machine mixing, lifting of
concrete manually, laying concrete, vibrating, curing etc., and
overheads & contractors profit complete but excluding cost of
steel and its fabrication charges for finished item of work (APSS
No. 402)

a) Footings 2.73 ONE CUM #REF! #REF!

b) Column Pedastals 0.73 ONE CUM #REF! #REF!

c) Plinth Beams 1.71 ONE CUM #REF! #REF!

d) Tie Beam 1.71 ONE CUM #REF! #REF!

APMSIDC-KADAPA Security Building - Civil - Abs 925 of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)

8 Supply and placing of the Design Mix Concrete M 25 grade


corresponding to IS 456 with minimum cement content of
380 kgs per 1 cum of concrete using weigh batcher / mixer with
20mm size graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry including cost and conveyance of all
materials like cement, fine aggregate (sand) coarse aggregate,
water etc., to site, centering using casurina ballies, bamboos,
wooden reapers, runners, wood posts, wall plates etc.,
including all operational, incidental and labour charges such as
weigh batching, machine mixing, lifting of concrete manually,
laying concrete, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)

a) Columns :
1st Floor : 2.00 ONE CUM #REF! #REF!

b) 175mm thick RCC side wall


1st Floor : 29.00 ONE SQM #REF! #REF!

c) Roof Beams :
1st Floor : 1.50 ONE CUM #REF! #REF!

d) ROOF SLABS :
i) 125mm thick :
1st Floor : 33.00 ONE SQM #REF! #REF!

e) Lintels
1st Floor : 0.60 ONE CUM #REF! #REF!

9 Brick masonry for panel walls in superstructure with CM


(1:8) prop: (Cement : Sand) using common burnt clay bricks
of class as per Table- I of IS:1077-1992, Non- Modular or
traditional size 23 x 11 x 7 cms from approved source having
minimum crushing strength of 40 Kg/Sqcm. including cost and
conveyance of all materials like cement, screened sand, bricks,
water etc., to site, labour charges, like mixing cement mortar,
scaffolding charges, constructing masonry, lift charges, curing,
etc.,and overheads & contractors profit complete for finished
item of work. (APSS No. 501 & 504).

1st Floor : 7.20 ONE CUM #REF! #REF!

APMSIDC-KADAPA Security Building - Civil - Abs 926 of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)

10 Reinforced Brick Masonry for partition walls (11.0 cm thick)


in CM (1:4) prop. (Cement : Sand) using common burnt clay
bricks of class as per Table- I of IS:1077-1992, Non- Modular or
traditional size 23 x 11 x 7 cms from approved source having
minimum crushing strength of 40 Kg/Sq.cm and placing 2 Nos. of
6mm M.S plain rods in every third layer with free ends of the
reinforcement pegged into mortar joints of main brick walls where
applicable including cost and conveyance of all materials like
cement, steel, sand, bricks, water etc., to site, all operational,
incidental charges such as labour charges for mixing cement
mortar, scaffolding charges, constructing masonry, lift charges,
curing, etc., and overheads & contractors profit but excluding
cost of steel and its fabrication charges complete for finished item
of work. (APSS No. of 501 & 509)

1st Floor : 19.00 ONE SQM #REF! #REF!

11 Plain Cement Concrete (1:3:6) nominal mix using 20mm size


graded machine crushed hard granite metal (coarse aggregate -
as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved
quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
including cost and conveyance of all materials like cement, fine
aggregate(sand), coarse aggregate, water etc. to site including all
charges for machine mixing, hire charges of concrete mixer,
laying concrete in position, curing etc., & lift charges , and
overheads & contractors profit for bed blocks & hold fasts for
finished item of work. (APSS No. 402)

1st Floor : 0.40 ONE CUM #REF! #REF!

12 Reinforced Cement Concrete M 20 nominal mix using 12mm


size hard granite machine crushed graded metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft (0.2
/ 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse aggregate,
water etc., to site including centering, shuttering, labour charges
such as weigh batching, machine mixing, hire charges of
concrete mixer, laying concrete, lift charges, curing etc., and
overheads & contractors profit complete for finished item of work
(APSS No. 402 & 403) for sill slabs.

1st Floor : 0.40 ONE CUM #REF! #REF!

APMSIDC-KADAPA Security Building - Civil - Abs 927 of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)

13 Reinforced Cement Concrete M 20 nominal mix using 12mm


size hard granite machine crushed graded metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft (0.2
/ 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse aggregate,
water etc., to site including centering, shuttering, labour charges
such as weigh batching, machine mixing, hire charges of
concrete mixer, laying concrete, lift charges, curing etc., and
overheads & contractors profit complete for finished item of work
(APSS No. 402 & 403) for platforms and shelves

a) 50 mm thick Platforms & lofts


1st Floor : 5.00 ONE SQM #REF! #REF!

b) 25mm thick Shelves


1st Floor : 2.00 ONE SQM #REF! #REF!

14 Providing Thermo Mechanically Treated (TMT) (Fe 500 / Fe


500 D grade as per IS 1786-1979) of different diameters for
RCC works including labour charges for straightening, cutting,
bending to required sizes and shapes, placing in position with
cover blocks of approved materials and size and tying and lap-
splicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and drawings,
including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars
including cost and conveyance of binding wire, cover blocks and
all incidental, operational, labour charges such as cutting,
bending, placing in position, tying etc., and overheads &
contractors profit complete for finished item of work.( APSS
No.126)

1st Floor : 2.10 ONE MT #REF! #REF!

15 Providing Mild steel (MS) steel bars (Fe 250 grade as per IS
432) of different diameters including labour charges for
straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and
size and tying and lap-splicing with binding wire of 18 SWG,
forming grills for reinforcement work as per approved designs and
drawings, including cost and conveyance of steel bars, including
all wastages such as overlaps, couplings, chairs, spacer bars
including cost and conveyance of binding wire, cover blocks and
all incidental, operational, labour charges such as cutting,
bending, placing in position, tying etc., and overheads &
contractors profit complete for finished item of work.( APSS
No.126)

1st Floor : 0.10 ONE MT #REF! #REF!

APMSIDC-KADAPA Security Building - Civil - Abs 928 of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)

16 Ornamental ceiling plastering 12mm thick single coat in CM


(1:5) using screened sand including cost and conveyance of all
materials like cement, sand, water etc., to site and all operational,
incidental charges on materials and including cost of all labour
charges for mixing mortar, finishing, curing as directed by
Engineer-in-charge etc., and overheads & contractors profit
complete for finished item of work.(SS 901,903 & 904)

1st Floor : 29.00 ONE SQM #REF! #REF!

17 Plastering 12mm thick in two coats using screened sand with


base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in
CM (1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site
and all operational, incidental charges on materials and including
cost of all labour charges for mixing mortar, finishing, scaffolding,
lift charges, curing, including cutting grooves as directed by
Engineer - in - charge etc., and overheads & contractors profit
complete for finished item of work. (SS 901,903 & 904) For
Internal Walls

1st Floor : 48.00 ONE SQM #REF! #REF!

18 Plastering 20mm thick in two coats using screened sand with


base coat of 16mm thick in CM(1:6) and top coat of 4mm thick in
CM(1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site
and all operational, incidental charges on materials and including
cost of all labour charges for mixing mortar, finishing, scaffolding,
lift charges, curing, including cutting grooves as directed by
Engineer-in-charge etc., and overheads & contractors profit
complete for finished item of work .(SS 901,903 & 904) for
internal walls .

1st Floor : 32.00 ONE SQM #REF! #REF!

19 Plastering 20mm thick in two coats using screened sand with


base coat of 16mm thick in CM(1:6) and top coat of 4mm thick in
CM(1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site
and all operational, incidental charges on materials and including
cost of all labour charges for mixing mortar, finishing, scaffolding,
lift charges, curing, including cutting grooves as directed by
Engineer-in-charge etc., and overheads & contractors profit
complete for finished item of work .(SS 901,903 & 904) for
external walls .

1st Floor : 87.00 ONE SQM #REF! #REF!

20 Plastering 12mm thick single coat in CM(1:5) using screened 12.00 ONE SQM #REF! #REF!
sand including cost and conveyance of all materials like cement,
sand, water etc., to site and all operational, incidental charges on
materials and including cost of all labour charges for mixing
mortar, finishing, curing as directed by Engineer-in-charge etc.,
and overheads & contractors profit complete for finished item of
work.(SS 901,903 & 904) for basement

APMSIDC-KADAPA Security Building - Civil - Abs 929 of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)

21 Providing impervious coat to exposed RCC roof slab surfaces


to required slopes with CM (1:3) prop. using screened sand
20mm thick (average) mixed with integral cement water proofing
liquid confirming to IS: 2645-2003 manufactured by reputed
manufacturers as approved by Engineer-in-charge at 200ml per
one bag of cement, laid over roof slab when it is green, finished
smooth with a floating coat of neat cement and thread lining at
regular intervals of 45cmx45cm including cost and conveyance of
all materials like cement, sand, water proofing compound, water
etc., to site, operational, incidental, and labour charges for mixing
mortar, laying, lift charges, rendering smooth and thread lining,
curing including rounding off junctions of wall and slab etc., and
overheads & contractors profit complete for finished item of work.
(APSS No. 901 & 903).

Over 1st Floor : 33.00 ONE SQM #REF! #REF!

22 RCM facia 50mm thick in CM(1:3) using screened sand for


drop walls, fins with rabbit wire mesh & nomianl reinforcement
as directred by Engineer - In - Charge with dubara sponge
finishing,including cost and conveyance of all materials to site,
operationals &incidental,cost and conveyance of cement, wire
mesh water to work site, centering, scaffolding and form work,lift
charges etc., and overheads & contractors profit complete for
finished item of work but excluding cost of steel and its fabrication
charges for finished item of work(APSS NO.403&903)

1st Floor : 11.00 ONE SQM #REF! #REF!

23 Flooring with non-skid white full body Ceramic floor tiles of


size 300 mm x 300 mm and thickness between 7-8 mm 1st
quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to
15) of any colour and finish in all shades and designs as
approved by Engineer-in-charge, set over base coat of cement
mortar (1:8), 12mm thick using screened sand over CC bed
already laid or RCC roof slab, including neat cement slurry of
honey like consistency spread @ 3.3 Kgs per sqm & jointed
neatly with white cement paste to full depth mixed with pigment of
matching shade, including cost of all materials like cement,
screened sand , water and tiles etc., and overheads &
contractors profit complete for finished item of work. (APSS
No.701 & 707) For Toilets

1st Floor : 2.70 ONE SQM #REF! #REF!

APMSIDC-KADAPA Security Building - Civil - Abs 930 of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)

24 Flooring with non-skid Double charged / multi charged stain


free full body porcelain vitrified tiles with double layer
pigment of Size 600 x 600 mm and thickness between 8-10 mm
1st quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1
to 15) of any colour and finish in all shades and designs with
borders and design as per the approved flooring pattern as
directed by the Engineer-In -Charge, laying tiles using spacers of
2mm thick, set over a base coat of CM (1:8) prop. 12mm thick
using screened sand over CC bed already laid or RCC roof slab ,
including neat cement slurry of honey like consistancy spread
@ 3.3 kgs per sqm. and jointed neately with white cement paste
to full depth mixed with pigment of matching shade including
cost and conveyance of all materials like cement, sand, water,
tiles, white cement etc., to site (excluding cost of C.C. bed)
including
1st Floorcost
: of base coat and all labour charges for mixing of 17.00 ONE SQM #REF! #REF!
cement mortar, laying tiles to required slope as directed by
the Engineer- in-charge etc.,and overheads & contractors profit
25 Flooring with
complete for 16 mm
finished toof18work.
item mm (APSS
thick No.701
high polished
& 707) granite
stone slabs black colour as approved by the Engineer-in-
Charge of length not less than 2.43 mts set over base coat of
cement mortar (1:8) , 20mm thick using screened sand over CC
bed already laid or RCC roof slab including neat grey cement
slurry of honey like consistency spread @ 3.3 Kg per sqm and
jointed neatly with white cement paste mixed with pigment of
matching shade to full depth including cost and conveyance of all
materials like cement , sand , water , granite slabs etc., to work
site and all operational, incidental labour & lift charges, half
rounding the edge , polishing charges, cost of base coat and
overheads & contractors profit complete for finished item of work
for platforms (S.S.701 & special)

1st Floor : 3.10 ONE SQM #REF! #REF!

26 Providing 16 mm to 18 mm thick high polished leather finish


granite stone slabs (steel grey or pearl black) with borders
and design as per the pattern approved by the Engineer-in-
Charge of length not less than 2.43 mts set over base coat of
cement mortar (1:5) , 12mm thick using screened sand over CC
bed already laid or RCC roof slab including neat grey cement
slurry of honey like consistency spread @ 3.3 Kg per sqm and
jointed neatly with white cement paste mixed with pigment of
matching shade to full depth including cost and conveyance of all
materials like cement , sand , water , granite slabs etc., to work
site and all operational, incidental labour & lift charges, full
rounding the edges of treads , polishing charges, cost of base
coat and overheads & contractors profit complete for finished
item of work for treads and risers (S.S.701 & special)

a) Treads of 0.30m wide :


1st Floor : 2.00 ONE SQM #REF! #REF!

b) Risers of 0.15m height :


1st Floor : 0.90 ONE SQM #REF! #REF!

APMSIDC-KADAPA Security Building - Civil - Abs 931 of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)

27 Providing skirting 10 cm height with Double charged / multi


charged stain free full body porcelain vitrified tiles with
double layer pigment of Size 600 x 600 mm and thickness
between 8-10 mm of any colour and finish in all shades and
designs, length equal to flooring tiles, flushed to wall surface to
set over base coat of CM(1:5) 12 mm thick using screened sand
with cement slurry of honey like consistency spread at the rate of
3.30 kgs per sqm and jointing with white cement paste mixed with
pigment of matching shade to full depth, including cost of all
materials like tiles, cement, sand and water etc.,and overheads &
contractors profit complete for finished item of work.(APSS
No.701 &707)

1st Floor : 25.00 ONE RM #REF! #REF!

28 Providing dadooing with glazed white full body ceramic wall


tiles of size 200mm x 300 mm / 245 mm x 325 mm and
thickness 6 mm 1st quality conforming to IS:13711, IS:13712,
IS:13630 (Parts 1 to 15) of any colour and finish in all shades and
designs with borders as approved by Engineer-in-Charge
flushed to wall surface set over base coat of CM(1:5) 12 mm
thick using screened sand with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per sqm and jointing
with white cement paste mixed with pigment of matching shade
to full depth, including cost of all materials like tiles, cement, sand
and water etc., and overheads & contractors profit complete for
finished item of work.

1st Floor : 9.00 ONE SQM #REF! #REF!

29 Providing 110 mm Dia ISI marked PVC down water take pipes 3.60 ONE RM #REF! #REF!
with socket , 2.5mm thick 4.0 kg/sq.cm pressure of ISI marked
including cost of necessary PVC Bends, shoes, iron / PVC
clamps and all other accessories and fixing in position including
cost and conveyance of all materials, operational & incidental
charges including all labour charges for fixing at site etc., and
overheads & contractors profit complete for finished item of work.
(APSS No. 1328)

30 Supply and fixing doors as per drawings with medium teak


wood frame of section 100mm x 65 mm and ISI marked flush
door shutters of 30 mm thick double shutters with bond wood
solid block board type Core having cross bands and face
veneers, hot pressed bonded with water proof phenol
formaldehyde synthetic resin factory made conforming to IS
2202-1991 (Part-I) both sides commercial ply with internal lipping
on all sides, fixing 1mm thick mat finish laminated sheet to
full width and height of the flush shutter both sides including
cost and conveyance to site of teak wood frame, flush shutter,
laminate sheet including

APMSIDC-KADAPA Security Building - Civil - Abs 932 of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)

supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm


x 5mm including cost of ISI marked Aluminium fixtures of 6 Nos.
butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm
long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm dia at top, 2
Nos. 150 mm long handles (IS:208), 2 Nos. door stoppers and 2
Nos. Rubber / Nylon door stop bushes including fixing the
fixtures to door with required number of screws, bolt and nuts
including labour charges for fixing the frame in position, fixing the
shutter to the frame etc., including overheads & contractors profit
complete for finished item of work as per APSS 1001 & 1002
(The vertical frame of door shall be embedded in flooring for a
depth of not less than 10 mm) (1500mm x 2100mm)

1st Floor : 3.15 ONE SQM #REF! #REF!

31 Supply and fixing doors as per drawings with medium teak


wood frame of section 100mm x 65 mm and ISI marked flush
door shutters of 30 mm thick single shutter with bond wood solid
block board type Core having cross bands and face veneers, hot
pressed bonded with water proof phenol formaldehyde synthetic
resin factory made conforming to IS 2202-1991 (Part-I) both
sides commercial ply with internal lipping on all sides, fixing
1mm thick mat finish laminated sheet to full width and height
of the flush shutter both sides including cost and conveyance
to site of teak wood frame, flush shutter, laminate sheet including
supply and
fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm
including cost of ISI marked Aluminium fixtures of 3 Nos. butt
hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long,
1 No. tower bolt (IS:204) of 200 mm x 10 mm dia at top, 2 Nos.
150 mm long handles (IS:208), 1 No. door stopper and 1 No.
Rubber / Nylon door stop bushes including fixing the fixtures to
door with required number of screws, bolt and nuts including
labour charges for fixing the frame in position, fixing the shutter to
the frame etc, including overheads & contractors profit complete
for finished item of work as per APSS 1001 & 1002 (The vertical
frame of door shall be embedded in flooring for a depth of not
less than 10 mm) (900mm x 2100mm)

1st Floor : 1.89 ONE SQM #REF! #REF!

32 Supplying and fixing single side prelam solid panel PVC


door frame (Choukhat): Providing and fixing factory made Pac
single side Prelam door frame of the size 50x7 mm with a wall
thickness of 5mm, made out of extruded 5mm rigid Pac single
side prelam sheet, meter cut at two corners and joined with 2
Nos. of 150mm long brackets of 15 x 15mm MS Square tube.
The two vertical door profiles are to be reinforced with 19 x 19mm
MS. square tube of 19 guage. The door frame shall be fixed to
the wall using 65/100mm long MS. Screws through the frame by
using Pac fasteners. a minimum of 4 Nos. of screws to be
provided for each vertical member and minimum 2nos. for
horizontal member etc. complete as per manufacture
specification and direction of Engineer-incharge including
conveyance of all materials, labour charges for fixing, overheads
& contractors profit complete for finished item of work.

1st Floor : 5.00 ONE RM #REF! #REF!

APMSIDC-KADAPA Security Building - Civil - Abs 933 of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)

33 Providing and fixing 30mm thick factory made moulded door


shutter- wood free consisting of frame made out of MS. tubes
19gauge thickness and size of 25mmX25mm for styles, top and
bottom rails. MS. Frame shall have a coat of steel primers. The
inner panel shall consist of 25mm thick high density EPS
conforming to IS 4671-1984 bounded with 2mm thick termite
proof, water proof and fire resistant moulded Pac sheet with 2,4,6
raised panel design in different plain and / or pre-lam colours
after routing to the moulded design on one side and 2mm plain
and / or pre-lam Pac sheet on other side of the EPS. The edge of
panel to be sealed with lipping of 10mm wide PVC sheet bottom
(made by sticking 2 rigid foam sheet of 5mm thickness using Pac
solvent cement) and stiles sides 25mm(5mmX5) thick and 30mm
width Pac sheet fitted along MS tube for lock provision for lock
height 5mm thick Pac sheet of size 150mmX100mm fixed with
upper and lower face of inner side of EPS panel etc., complete as
per direction of Engineer – in-Charge, manufacture specification
and drawing including ISI marked Aluminium fixtures 3 Nos. butt
hinges (IS:205) of 150mm long, 1 No. aldrop (IS:2681) 250 mm
long, 1 No. tower bolt (IS:204) of 150 mm x 10mm dia, 2 Nos.
125mm long handles (IS:208),1 No. Rubber / Nylon door stop
bushes including labour charges for fixing the shutter to frame
1st Floor : 1.68 ONE SQM #REF! #REF!

34 Providing and fixing factory made uPVC white colour sliding


glazed window comprising of uPVC multi-chambered frame with
in-built roller track and sash extruded profiles duly reinforced with
1.60 ± 0.2 mm thick galvanized mild steel section made from roll
forming process of required length (shape & size according to
uPVC profile), appropriate dimension of uPVC extruded glazing
beads and uPVC extruded interlocks, EPDM gasket, wool pile,
zinc alloy (white powder coated) touch locks with hook, zinc alloy
body with single nylon rollers (weight bearing capacity to be 40
kg), G.I fasteners 100 x 8 mm size for fixing frame to finished wall
and necessary stainless steel screws etc. Profile of frame & sash
shall be mitred cut and fusion

welded at all corners, including drilling of holes for fixing


hardware's and drainage of water etc. After fixing frame the gap
between frame and adjacent finished wall shall be filled with
weather proof silicon sealent over backer rod of required size and
of approved quality, all complete as per approved drawing &
direction of Engineer-in-Charge inclusive of cost of Single /
double glass panes of 4mm thick pin headed glass, wire mesh
and silicon sealent . Note: For uPVC frame and sash extruded
profiles minus 5% tolerancein dimension i.e. in depth & width of
profile shall be acceptable.Variation in profile dimension in higher
side shall be accepted. But no extra payment on this account
shall be made.

Two track two panels sliding window made of frame 67 x 50


mm & sash 46 x 62 mm both having wall thickness of 2.3 ± 0.2
mm and single glazing bead / double glazing bead of appropriate
dimension .
1st Floor : 9.36 ONE SQM #REF! #REF!

APMSIDC-KADAPA Security Building - Civil - Abs 934 of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)

35 Providing and fixing factory made uPVC white colour fixed


glazed windows / Ventilators comprising of uPVC multi
chambered frame and mullion (where ever required) extruded
profiles duly reinforced with 1.60± 0.2 mm thick galvanized mild
steel section made from roll forming process of required length
(shape & size according to uPVC profile), uPVC extruded glazing
beads of appropriate dimension, EPDM gasket,G.I fasteners 100
x 8 mm size for fixing frame to finished wall, plastic packers,
plastic caps and necessary stainless steel screws etc. Profileof
frame shall be mitred cut and fusion welded at all corners, mullion
(if required) shall be also fusion welded including drilling of holes
for fixing hardware and drainage of water etc.

After fixing frame the gap between frame and adjacent finished
wall shall be filled with weather proof silicon sealant over backer
rod of required size and of approved quality, all complete as per
approved drawing & direction of Engineer-in-Charge inclusive of
cost of Single / double glass panes and silicon sealant. Note: For
uPVC frame, sash and mullion extruded profiles minus
5%tolerance in dimension i.e. in depth & width of profile shall be
acceptable.Variation in profile dimension in higher side shall be
accepted. But, no extra payment on this account shall be made.

Fixed windows / Ventilators made of (small series) frame 47 x


50mm & mullion 47 x 68 mm both having wall thickness of 1.9
±0.2 mm and single glazing bead of appropriate dimension.

1st Floor : 0.30 ONE SQM #REF! #REF!

36 Supplying and fixing of MS doors, grill to windows / in open


court yards using MS angles, flat, square bars including cost and
conveyance of all materials, cutting, bending, welding, all
operational charges, labour charges, overheads and contractor
profit etc., complete for finished item of work. For All Floors

1st Floor : 141.00 ONE KGS #REF! #REF!

37 White washing two coats with white cement to ceiling to give


an even shade after thouroughly brushing the surface to remove
all dirt and remains of loose powdered materials including cost of
all materials , labour charges and incidental such as scaffolding ,
lift charges etc., and overheads & contractors profit complete for
finished item of work in all floors.

1st Floor : 29.00 ONE SQM #REF! #REF!

38 Supply & application of one coat water based cement primer


of interior grade I and two coats of synthetic polymer luxury
plastic emulsion paint of superior grade having VOC (Volatile
Organic Compound) content less than 50 grams/litre for internal
walls including cost and conveyance of all materials to site,
incidental, operational and all labour charges etc., and overheads
& contractors profit complete for finished item of work in all floors.

APMSIDC-KADAPA Security Building - Civil - Abs 935 of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)

1st Floor : 80.00 ONE SQM #REF! #REF!

39 Supply & application of one coat water based cement primer


of exterior grade II and two coats of synthetic polymer luxury
plastic emulsion paint of superior grade having VOC (Volatile
Organic Compound) content less than 50 grams/litre for exterior
walls including cost and conveyance of all materials to site,
incidental, operational and all labour charges etc., and overheads
& contractors profit complete for finished item of work in all floors.

1st Floor : 99.00 ONE SQM #REF! #REF!

40 Painting two coats with synthetic enamel paint Grade-II VOC


(Volatile Organic Compound) content less than 50 grams/litre
over primer coat of red oxide to new iron work including cost
and conveyance of all materials to site, incidental, operational
and all labour charges etc., and overheads & contractors profit
complete for finished item of work in all floors. (SS No. 1201,
1212 & 1207).

1st Floor : 9.00 ONE SQM #REF! #REF!

TOTAL : #REF!

APMSIDC-KADAPA Security Building - Civil - Abs 936 of 1048


Detailed Estimate - Security
S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
1 Earth Work Excavation
Earth work excavation by Machinary
upto 3.0m depth
F1 6 1.500 1.500 1.800 24.30
For Entrance Steps 1 2.100 0.900 0.300 0.57
24.87
Say 25.00 Cum
2 PCC (1:4:8) for column footings
F1 6 1.500 1.500 0.150 2.03
2.03
Say 2.10 Cum
3 PCC (1:5:10)
alround the bldg 1 18.920 0.600 0.150 1.70
Ded for col -2 0.230 0.600 0.150 -0.04
-4 0.300 0.600 0.150 -0.11
Internal plinth beam ( Inner to Inner) 1 6.660 0.450 0.150 0.45
Under Flooring
Qty same as ceramic tiles 1 2.700 0.100 0.27
Qty same as vitrified tiles 1 16.518 0.100 1.65
For Entrance Steps 1 2.100 0.900 0.150 0.28
4.21
Say 4.20 Cum

A Earth filling with available earth


Qty as per excavation 25.00 25.00
Deductions
a Qty as per PCC (1:4:8) -2.10
b Qty as per PCC (1:5:10) -4.21
c Qty as per footing -2.73
d Qty as per pedestals -0.73
e Qty as per 175mm thick side walls -4.98
f Qty as per columns upto Ground level -0.33
9.91 -15.09
B Basement Filling
Qty same as vitrified tiles 16.52 2.000 33.04
Quantity same as ceramic tile flooring
area 2.70 2.000 5.40
48.35
Say 48.00 Cum

g Total Earth to be filled 48.00 Cum

4 Filling with available earth


80% of Excavated earth 20.00
Say 20.00 Cum
5 Filling with carted gravel
Total filling quantity 48.00
available excavated excavation 20.00
28.00
Say 28.00 Cum
6 Antiermite treatment
Slab area 1 6.660 3.330 22.18
Slab area 1 5.460 2.030 11.08
33.26
Say 33.00 Sqm

7 175mm thick side walls


alround the bldg 1 18.920 1.650 31.22
Deduction for Columns -2 0.230 1.650 -0.76
Deduction for Columns -4 0.300 1.650 -1.98
28.48
Say 29.00 Sqm

8 VRCC M25 design mix


a Footings
F1 6 1.350 1.350 0.250 2.73
2.73
Say 2.73 Cum

b Pedestals for Columns


F1 6 0.450 0.450 0.600 0.73
0.73
Say 0.73 Cum

9 Plinth beams
Horizontals 2 4.860 0.230 0.350 0.78
Horizontals 1 4.860 0.230 0.450 0.50
verticals 2 4.460 0.230 0.350 0.72
Ded for col -6 0.230 0.230 0.350 -0.11
Secondary beam 1 1.800 0.230 0.450 -0.19
1.71
Say 1.71 Cum

10 Tie beams
Quantity same as Plinth beam 1.71
Say 1.71 Cum
11 Columns
Columns Upto GL
C1 6 0.230 0.300 0.800 0.33
0.33
Say 0.30 Cum
Above GL to Plinth beam level
C1 6 0.230 0.300 2.000 0.83
0.83
Say 0.80 Cum
P.B Top to Roof slab bottom
C1 6 0.230 0.300 2.875 1.19
1.19
Say 1.20 Cum
Total Columns
Columns Upto GL 0.33
above GL to PB 0.83
P.B Top to Roof slab bottom 1.19
2.35 Cum
Say 2.00 Cum

12 Roof beams
Horizontals 3 5.460 0.230 0.300 1.13
Deduction for Columns -6 0.300 0.230 0.300 -0.12
verticals 2 4.460 0.230 0.300 0.62
Deduction for Columns -6 0.230 0.230 0.300 -0.10
1.53
Say 1.50 Cum
13 Roof slab
i 125mm thick Slab
Slab area 1 6.660 3.330 22.18
Slab area 1 5.460 2.030 11.08
33.26
Say 33.00 Sqm

14 Lintels
D2 1 1.960 0.230 0.175 0.08
D3 1 1.360 0.115 0.175 0.03
D4 1 1.260 0.115 0.175 0.03
SW1 1 2.260 0.230 0.175 0.09
SW2 2 1.960 0.230 0.175 0.16
SW3 2 1.660 0.230 0.175 0.13
V 1 1.060 0.230 0.175 0.04
0.56
Say 0.60 Cum
15 RCC M20grade Nominal Mix
a 50mm thick Platforms & Lofts
Platforms
2 2.080 0.450 1.87
2 1.300 0.450 1.17
3.04
Say 3.00 Sqm

Lofts
2 2.080 0.450 1.87
1.87
Say 2.00 Sqm

Total Platforms & lofts 5.00 Sqm


Say 5.00 Sqm
b 25mm thick Shelves
2 2.080 0.450 1.87
1.87
Say 2.00 Sqm

c Sill slabs
SW1 1 2.100 0.230 0.150 0.07
SW2 2 1.800 0.230 0.150 0.12
SW3 2 1.500 0.230 0.150 0.10
0.30
Say 0.40 Cum
16 230mm thick brick masonary
Horizontals 2 5.460 0.230 2.575 6.47
Deduction for Columns -4 0.300 0.230 2.575 -0.71
verticals 2 4.460 0.230 2.575 5.28
Deduction for Columns -6 0.230 0.230 2.575 -0.82
Entrance steps 1 2.100 0.600 0.150 0.19
Entrance steps 1 2.100 0.450 0.150 0.14
Entrance steps 1 2.100 0.300 0.150 0.09
Deductions
D2 -1 1.500 0.230 2.100 -0.72
SW1 -1 1.800 0.230 1.300 -0.54
SW2 -2 1.500 0.230 1.300 -0.90
SW3 -2 1.200 0.230 1.300 -0.72
V5 -1 0.600 0.230 0.500 -0.07
Lintels
D2 -1 1.960 0.230 0.175 -0.08
SW1 -1 2.260 0.230 0.175 -0.09
SW2 -2 1.960 0.230 0.175 -0.16
SW3 -2 1.660 0.230 0.175 -0.13
V5 -1 1.060 0.230 0.175 -0.04
7.20
Say 7.20 Cum

17 Brick Work 110 mm thick walls


Horizontal 1 5.000 2.575 12.88
Toilet 1 1.800 2.575 4.64
Parapet wall alround 1 19.840 0.300 5.95
Deductions
D3 -1 0.900 2.100 -1.89
D4 -1 0.800 2.100 -1.68
Lintel
D3 -1 1.360 0.175 -0.24
D4 -1 1.260 0.175 -0.22
19.43
Say 19.00 Sqm
18 PCC (1:3:6) for Bedblocks
under lintels
D2 2 1 0.300 0.230 0.150 0.02
D3 2 1 0.300 0.115 0.150 0.01
D4 2 1 0.300 0.115 0.150 0.01
SW1 2 1 0.300 0.230 0.150 0.02
SW2 2 2 0.300 0.230 0.150 0.04
SW3 2 2 0.300 0.230 0.150 0.04
V 2 1 0.300 0.230 0.150 0.02
Hold fasts
D2 6 1 0.230 0.230 0.150 0.05
D3 6 1 0.230 0.115 0.150 0.02
D4 6 1 0.230 0.115 0.150 0.02
SW1 4 1 0.230 0.230 0.150 0.03
SW2 4 2 0.230 0.230 0.150 0.06
SW3 4 2 0.230 0.230 0.150 0.06
V 2 1 0.230 0.230 0.150 0.02
0.44
Say 0.40 Cum
19 TMT STEEL
Footings 2.73 60.000 Kgs/Cum 163.80
Pedestals 0.73 110.000 Kgs/Cum 80.30
175 mm thick side walls 28.48 80.000 0.175 Kgs/Cum 398.71
Plinth Beams 1.71 120.000 Kgs/Cum 205.20
Tie Beams 1.71 120.000 Kgs/Cum 204.74
Columns 2.00 180.000 Kgs/Cum 360.00
Roof Beams 1.50 160.000 Kgs/Cum 240.00
125 mm thick roof slab 33.00 80.000 0.125 Kgs/Cum 330.00
Lintels 0.60 80.000 Kgs/Cum 48.00
Sill Slabs 0.40 80.000 Kgs/Cum 32.00
Platforms 3.00 80.000 0.050 Kgs/Cum 12.00
Lofts 2.00 80.000 0.050 Kgs/Cum 8.00
2082.74
Say 2.10 MT
20 Mild Steel
Shelves 2 80.000 0.025 Kgs/Cum 4.00
RBM 19 3.000 Kgs/Sqm 57.00
61.00
Say 0.10 MT

21 Ceiling plastering
Qty same as Vitrified tile flooring 17.00
Qty same as Non-skid tiles 2.70
Front Projection 1 6.660 0.900 5.99
Side Projection 2 2.430 0.600 2.92
28.61
Say 29.00 Sqm
22 12mm thick plastering
a External Plastering
Allround the Building 1 19.840 3.000 59.52
Parapet wall alround 1 19.840 0.715 14.19
Deductions
SW1 -1 1.800 1.800 3.24
SW2 -2 1.500 1.800 5.40
SW3 -2 1.200 1.800 4.32
V -1 0.600 0.500 0.30
86.97
Say 87.00 Sqm
b Basement Plastering
Allround the Building 1 19.840 0.600 11.90
11.90
Say 12.00 Sqm
12 mm thick plastering Internal
c plastering
Toilet 1 6.600 2.875 18.98
Security 1 14.170 2.875 40.74
Rest room 1 10.370 2.875 29.81
Deductions
D2 1 1.500 2.100 3.15
D3 1 0.900 2.100 -1.89
D4 1 0.800 2.100 -1.68
Deduction for Dadooing with glazed tiles -8.70
80.41
Say 80.00 Sqm

b 12mm thick internal plastering


60% of internal plastering area 0.600 80.000 48.00
Say 48.00 Sqm

23 20mm thick internal plastering


40% of internal plastering area 0.400 80.000 32.00
Say 32.00 Sqm

20mm thick Impervious coat to roof


24 slab
Slab area 1 6.660 3.330 22.18
Slab area 1 5.460 2.030 11.08
33.26
Say 33.00 Sqm

25 Ceramic Non-Skid tiles 300 x 300


Toilet 1 1.500 1.800 2.70
2.70
Say 2.70 Sqm

26 Polished Vitrified Tile flooring


a Flooring
Security room 1 5.000 2.085 10.43
Rest room 1 3.385 1.800 6.09
16.52
Say 17.00 Sqm
27 Polished Granite slab
b Treads
Steps 1 3 2.100 0.300 1.89
1.89
Say 2.00 Sqm
b Risers
Steps 1 3 2.100 0.150 0.95
0.95
Say 0.90 Sqm

28 Polished granite slabs for Platforms


2 1.300 0.450 1.17
2 2.085 0.450 1.88
3.05
Say 3.10 Sqm

29 Dadooing to walls
Toilet 1 6.600 1.500 9.90
Deductions
D4 -1 0.800 1.500 -1.20
8.70
Say 9.00 Sqm

30 Vitrified tiles Skirting / Riser


a Skirting
Security 1 14.170 14.17
Rest room 1 10.370 10.37
24.54
Say 25.00 Rm
31 Whiting to ceiling
Same as ceiling plastering area 28.61
28.61
Say 29.00 Sqm
32 Painting to Internal walls
Same as internal plastering area 80.41
80.41
Say 80.00 Sqm
33 Painting to External walls
Same as external plastering area 87.00
Same as Basement plastering area 11.90
98.90
Say 99.00 Sqm

34 Painting to wood work


D2 2.24 1 1.500 2.100 7.06
D3 2.24 1 0.900 2.100 4.23
D4 2.24 1 0.800 2.100 3.76
8.00
Say 8.00 Sqm
35 Painting to iron work
SW1 1 1.800 1.300 2.34 Sqm
SW2 2 1.500 1.300 3.90 Sqm
SW3 2 1.200 1.300 3.12 Sqm
9.36
Say 9.00 Sqm
RCM Facia
Front side 1 6.660 0.900 5.99
sides 2 2.930 0.900 5.27
11.27
Say 11.00 Sqm

36 Supply & Fixing of Joinery


Wooden Doors
D2 1 1.500 2.100 3.15 Sqm
Say 3.20 Sqm

D3 1 0.900 2.100 1.89 Sqm


Say 1.89 Sqm

D4 (Frame) 1 5.000 5.00 Rmt


Say 5.00 Rmt

D4 (Shutter) 1 0.800 2.100 1.68 Sqm


Say 1.68 Sqm

37 Windows
i SW1 1 1.800 1.300 2.34 Sqm
SW2 2 1.500 1.300 3.90 Sqm
SW3 2 1.200 1.300 3.12 Sqm
Say 9.36 Sqm

ii Ventilators
V 1 0.600 0.500 0.30
0.30
Say 0.30 Sqm
1 MS Grill
SW1 1 1.800 1.300 2.34 Sqm
SW2 2 1.500 1.300 3.90 Sqm
SW3 2 1.200 1.300 3.12 Sqm
Say 9.36 Sqm
141.00 Kgs

2 PVC down take pipes


110mm dia 1 3.600 3.60
Say 3.60 Rm
ABSTRACT ESTIMATE FOR PATIENT ATTENDANT DORMITORY BUILDING
Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)
1 Earth work excavation for foundations (Mechanical Means) 128.00 ONE CUM #REF! #REF!
for buildings in ordinary soils and depositing on bank for all
lifts and with an initial lead of 10m and up to 3m depth
including all operational,incidental, labour charges such as
shoring, sheeting, planking, strutting etc., and overheads &
contractors profit complete for finished item of work excluding
dewatering charges etc., as per SS 20 B(APSS 308)

2 Pre construction Anti termite treatment is a process in which 160.00 ONE SQM #REF! #REF!
chemical toxic to subterrean tremites is apply/ inject into soil
during early stage of building Construction 2. Treatement of soil
Beneath the building and around the foundations conduct and
chemical use as per BIS - IS 6313 (Part -2) 2013 code
specification & CIB RC registered termiticide which creates a
continuous chemical barrier beneath the building which kills or
repels terminates & impervious to tremite entry 3. Imidacloprid
30.5% SC (IS 63131) dissolve 2.1 Ml/1 liter of water and apply
emulsion/solution @ 7.5 Litres/Square meter (Sqm) of internal,
external vertical surface of the colums, plinth beams (Back
filling) walls and floor junction, external perimeters, along
reatining wall @ 5.0 Liters/Sqm of the horizontal surface of
basement top surface of the basement filling below flooring bed
(Plinth) & @ 2.0 Litres/ Line meter at expansion joints. The
substructure of a depth of 500mm around coulmns & 300mm
deep around plinth beams, basements & floor filling area
including excavation channel along the wall & rodding etc. cost
& Conveyance of all materials to the site, cost of labour for
sparying, rodding, overheads and contractor profit etc.
complete for furnished item of work as per the approval of the
Engineer-in-charge

2 Plain Cement Concrete (1:4:8) (cement: fine aggregate: 10.60 ONE CUM #REF! #REF!
Coarse aggregate) for foundations using coarse aggregate
40mm size hard , machine crushed granite from approved
quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
including cost and conveyance of all materials like cement,
sand, coarse aggregate, water etc. to site including all charges
for machine mixing and hire charges of concrete mixer, laying
concrete in foundations and under flooring bed, ramming in 15
cm layers finishing top surface to the required level curing
etc.,and overheads & contractors profit complete for finished
item of work. (APSS No. 402) For Foundation

APMSIDC- PAB- Civil Abs 945of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)
3 Plain Cement Concrete (1:5:10) (cement: fine aggregate: 22.00 ONE CUM #REF! #REF!
Coarse aggregate) for foundations and under flooring bed
using coarse aggregate 40mm size hard , machine crushed
granite from approved quarry using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, sand, coarse aggregate, water etc. to
site including all charges for machine mixing and hire charges
of concrete mixer, laying concrete in foundations and under
flooring bed, ramming in 15 cm layers finishing top surface to
the required level curing etc.,and overheads & contractors profit
complete for finished item of work. (APSS No. 402)

4 Filling with useful available excavated earth (excluding rock) 102.00 ONE CUM #REF! #REF!
with a lead of 50 m in trenches, sides of foundations and
basement with initial lead in layers not exceeding 15cm thick,
watering and ramming including cost and conveyance of water
to work site and all operaitonal, incidental, labour charges, hire
charges of T&P etc., and overheads & contractors profit
complete for fnished item of work (APSS NO.309&310)

5 Filling with carted gravel in trenches,sides of foundations and 236.00 ONE CUM #REF! #REF!
basement with initial lead in layers not exceeding 15cm
thick,watering and ramming including cost and conveyance of
water to work site and all peraitonal,incidental, labour
charges,hire charges of T&P etc., and overheads & contractors
profit complete for fnished item of work(APSS NO.309&310)

6 Supply and placing of the Design Mix Concrete M 25 grade


corresponding to IS 456 with minimum cement content of
380 kgs per 1 cum of concrete using weigh batcher / mixer
with 20mm size graded machine crushed hard granite metal
(coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to
Part 8) from approved quarry including cost and conveyance of
all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site, centering using steel
scaffolding pipes , jack props , wallers , foot plates ,
brackets , steel centering plates etc., including all
operational, incidental and labour charges such as weigh
batching, machine mixing, lifting of concrete manually, laying
concrete, vibrating, curing etc., and overheads & contractors
profit complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)

a) Footings 24.80 ONE CUM #REF! #REF!

b) Column Pedastals 3.00 ONE CUM #REF! #REF!

c) Plinth Beams 8.50 ONE CUM #REF! #REF!

d) Tie Beam 8.50 ONE CUM #REF! #REF!

APMSIDC- PAB- Civil Abs 946of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)
7 Supply and placing of the Design Mix Concrete M 25 grade
corresponding to IS 456 with minimum cement content of
380 kgs per 1 cum of concrete using weigh batcher / mixer
with 20mm size graded machine crushed hard granite metal
(coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to
Part 8) from approved quarry including cost and conveyance of
all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site, centering using casurina
ballies, bamboos, wooden reapers, runners, wood posts,
wall plates etc., including all operational, incidental and labour
charges such as weigh batching, machine mixing, lifting of
concrete manually, laying concrete, vibrating, curing ,
overheads & contractors profit etc., complete but excluding
cost of steel and its fabrication charges for finished item of work
(APSS No. 402)

a) Columns :
First Floor : 8.00 ONE CUM #REF! #REF!

b) 175mm thick RCC side wall


First Floor : 78.00 ONE SQM #REF! #REF!

c) Roof Beams :
un supported height up to 3.66 m
First Floor : 7.40 ONE CUM #REF! #REF!

d) ROOF SLABS :
i) 125mm thick :
First Floor : 55.00 ONE SQM #REF! #REF!

ii) 150mm thick :


First Floor : 97.00 ONE SQM #REF! #REF!

iii) 175mm thick :


First Floor : 17.00 ONE SQM #REF! #REF!

e) Lintels
First Floor : 1.60 ONE CUM #REF! #REF!

8 Supply and placing of the Design Mix Concrete M 25 grade


corresponding to IS 456 with minimum cement content of
380 kgs per 1 cum of concrete using weigh batcher / mixer
with 20mm size graded machine crushed hard granite metal
(coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to
Part 8) from approved quarry including cost and conveyance of
all materials like cement, fine aggregate (sand), coarse
aggregate, water etc., to site, centering using casurina ballies ,
bamboos , wooden reapers , runners , wood posts , wall plates
etc., for 60cm wide sun-shades 7.5cm thick at fixed end
and 5cm thick at free end with an average thickness of
6.25cm including all operational, incidental and labour charges
such as weigh batching, machine mixing, lifting of concrete
manually, laying concrete, curing, overheads & contractors
profit complete etc., but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402,
403 & 903)

APMSIDC- PAB- Civil Abs 947of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)
First Floor : 11.00 ONE RM #REF! #REF!

9 Brick masonry for panel walls in superstructure with CM


(1:8) prop: (Cement : Sand) using common burnt clay
bricks of class as per Table- I of IS:1077-1992, Non- Modular
or traditional size 23 x 11 x 7 cms from approved source
having minimum crushing strength of 40 Kg/Sqcm. including
cost and conveyance of all materials like cement, screened
sand, bricks, water etc., to site, labour charges, like mixing
cement mortar, scaffolding charges, constructing masonry, lift
charges, curing, etc.,and overheads & contractors profit
complete for finished item of work. (APSS No. 501 & 504).

First Floor : 26.00 ONE CUM #REF! #REF!

10 Reinforced Brick Masonry for partition walls (11.0 cm thick)


in CM (1:4) prop. (Cement : Sand) using common burnt clay
bricks of class as per Table- I of IS:1077-1992, Non- Modular
or traditional size 23 x 11 x 7 cms from approved source
having minimum crushing strength of 40 Kg/Sq.cm and placing
2 Nos. of 6mm M.S plain rods in every third layer with free ends
of the reinforcement pegged into mortar joints of main brick
walls where applicable including cost and conveyance of all
materials like cement, steel, sand, bricks, water etc., to site, all
operational, incidental charges such as labour charges for
mixing cement mortar, scaffolding charges, constructing
masonry, lift charges, curing, etc., and overheads & contractors
profit but excluding cost of steel and its fabrication charges
complete for finished item of work. (APSS No. of 501 & 509)

First Floor : 135.00 ONE SQM #REF! #REF!

11 Plain Cement Concrete (1:3:6) nominal mix using 20mm


size graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8
cum) capacity including cost and conveyance of all materials
like cement, fine aggregate(sand), coarse aggregate, water etc.
to site including all charges for machine mixing, hire charges of
concrete mixer, laying concrete in position, curing etc., & lift
charges , and overheads & contractors profit for bed blocks &
hold fasts for finished item of work. (APSS No. 402)

First Floor : 1.20 ONE CUM #REF! #REF!

APMSIDC- PAB- Civil Abs 948of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)
11 Reinforced Cement Concrete M 20 nominal mix using
12mm size hard granite machine crushed graded metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for sill slabs.

First Floor : 0.30 ONE CUM #REF! #REF!

12 Reinforced Cement Concrete M 20 nominal mix using


12mm size hard granite machine crushed graded metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8)
from approved quarry, using a minimum quantity of 350 kgs. of
cement per 1 cum of concrete using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate (Sand), coarse
aggregate, water etc., to site including centering, shuttering,
labour charges such as weigh batching, machine mixing, hire
charges of concrete mixer, laying concrete, lift charges, curing
etc., and overheads & contractors profit complete for finished
item of work (APSS No. 402 & 403) for platforms and
shelves

a) 50 mm thick Platforms & lofts


First Floor : 4.00 ONE SQM #REF! #REF!

b) 25mm thick Shelves


First Floor : 3.00 ONE SQM #REF! #REF!

13 Providing Thermo Mechanically Treated (TMT) (Fe 500 / Fe


500 D grade as per IS 1786-1979) of different diameters for
RCC works including labour charges for straightening, cutting,
bending to required sizes and shapes, placing in position with
cover blocks of approved materials and size and tying and lap-
splicing with binding wire of 18 SWG, forming grills for
reinforcement work as per approved designs and drawings,
including cost and conveyance of steel bars, including all
wastages such as overlaps, couplings, chairs, spacer bars
including cost and conveyance of binding wire, cover blocks
and all incidental, operational, labour charges such as cutting,
bending, placing in position, tying etc., and overheads &
contractors profit complete for finished item of work.( APSS
No.126)

First Floor : 10.10 ONE MT #REF! #REF!

APMSIDC- PAB- Civil Abs 949of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)
14 Providing Mild steel (MS) steel bars (Fe 250 grade as per IS
432) of different diameters including labour charges for
straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and
size and tying and lap-splicing with binding wire of 18 SWG,
forming grills for reinforcement work as per approved designs
and drawings, including cost and conveyance of steel bars,
including all wastages such as overlaps, couplings, chairs,
spacer bars including cost and conveyance of binding wire,
cover blocks and all incidental, operational, labour charges
such as cutting, bending, placing in position, tying etc., and
overheads & contractors profit complete for finished item of
work.( APSS No.126)

First Floor : 0.30 ONE MT #REF! #REF!

15 Ornamental ceiling plastering 12mm thick single coat in


CM (1:5) using screened sand including cost and conveyance
of all materials like cement, sand, water etc., to site and all
operational, incidental charges on materials and including cost
of all labour charges for mixing mortar, finishing, curing as
directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work.(SS
901,903 & 904)

First Floor : 141.00 ONE SQM #REF! #REF!

16 Plastering 12mm thick in two coats using screened sand


with base coat of 8mm thick in CM (1:6) and top coat of 4mm
thick in CM (1:4) with dubara sponge finishing including cost
and conveyance of all materials like cement, sand, water etc.,
to site and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer - in - charge etc., and overheads &
contractors profit complete for finished item of work. (SS
901,903 & 904) For Internal Walls

First Floor : 187.00 ONE SQM #REF! #REF!

17 Plastering 20mm thick in two coats using screened sand


with base coat of 16mm thick in CM(1:6) and top coat of 4mm
thick in CM(1:4) with dubara sponge finishing including cost
and conveyance of all materials like cement, sand, water etc.,
to site and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work .(SS
901,903 & 904) for internal walls .

First Floor : 125.00 ONE SQM #REF! #REF!

APMSIDC- PAB- Civil Abs 950of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)
18 Plastering 20mm thick in two coats using screened sand
with base coat of 16mm thick in CM(1:6) and top coat of 4mm
thick in CM(1:4) with dubara sponge finishing including cost
and conveyance of all materials like cement, sand, water etc.,
to site and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing,
scaffolding, lift charges, curing, including cutting grooves as
directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work .(SS
901,903 & 904) for external walls .

First Floor : 258.00 ONE SQM #REF! #REF!

19 Plastering 12mm thick single coat in CM(1:5) using 32.00 ONE SQM #REF! #REF!
screened sand including cost and conveyance of all materials
like cement, sand, water etc., to site and all operational,
incidental charges on materials and including cost of all labour
charges for mixing mortar, finishing, curing as directed by
Engineer-in-charge etc., and overheads & contractors profit
complete for finished item of work.(SS 901,903 & 904) for
basement

20 Providing impervious coat to exposed RCC roof slab


surfaces to required slopes with CM (1:3) prop. using screened
sand 20mm thick (average) mixed with integral cement water
proofing liquid confirming to IS: 2645-2003 manufactured by
reputed manufacturers as approved by Engineer-in-charge at
200ml per one bag of cement, laid over roof slab when it is
green, finished smooth with a floating coat of neat cement and
thread lining at regular intervals of 45cmx45cm including cost
and conveyance of all materials like cement, sand, water
proofing compound, water etc., to site, operational, incidental,
and labour charges for mixing mortar, laying, lift charges,
rendering smooth and thread lining, curing including rounding
off junctions of wall and slab etc., and overheads & contractors
profit complete for finished item of work. (APSS No. 901 &
903).

Over First Floor : 152.00 ONE SQM #REF! #REF!

21 RCM facia 50mm thick in CM(1:3) using screened sand for


drop walls, fins with rabbit wire mesh & nomianl reinforcement
as directred by Engineer - In - Charge with dubara sponge
finishing,including cost and conveyance of all materials to site,
operationals &incidental,cost and conveyance of cement, wire
mesh water to work site, centering, scaffolding and form
work,lift charges etc., and overheads & contractors profit
complete for finished item of work but excluding cost of steel
and its fabrication charges for finished item of work(APSS
NO.403&903)

First Floor : 4.00 ONE SQM #REF! #REF!

APMSIDC- PAB- Civil Abs 951of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)
22 Flooring with non-skid white full body Ceramic floor tiles of
size 300 mm x 300 mm and thickness between 7-8 mm 1st
quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to
15) of any colour and finish in all shades and designs as
approved by Engineer-in-charge, set over base coat of cement
mortar (1:8), 12mm thick using screened sand over CC bed
already laid or RCC roof slab, including neat cement slurry of
honey like consistency spread @ 3.3 Kgs per sqm & jointed
neatly with white cement paste to full depth mixed with pigment
of matching shade, including cost of all materials like cement,
screened sand , water and tiles etc., and overheads &
contractors profit complete for finished item of work. (APSS
No.701 & 707) For Toilets

First Floor : 30.00 ONE SQM #REF! #REF!

23 Flooring with non-skid Double charged / multi charged


stain free full body porcelain vitrified tiles with double layer
pigment of Size 600 x 600 mm and thickness between 8-10
mm 1st quality conforming to IS:13711, IS:13712, IS:13630
(Parts 1 to 15) of any colour and finish in all shades and
designs with borders and design as per the approved flooring
pattern as directed by the Engineer-In -Charge, laying tiles
using spacers of 2mm thick, set over a base coat of CM (1:8)
prop. 12mm thick using screened sand over CC bed already
laid or RCC roof slab , including neat cement slurry of honey
like consistancy spread @ 3.3 kgs per sqm. and jointed
neately with white cement paste to full depth mixed with
pigment of matching shade including cost and conveyance of
all materials like cement, sand, water, tiles, white cement etc.,
to site (excluding cost of C.C. bed) including cost of base
coat and all
First Floor : labour charges for mixing of cement mortar, 112.00 ONE SQM #REF! #REF!
laying tiles to required slope as directed by the Engineer-
24 in-charge
Flooring withetc.,and overheads
16 mm & contractors
to 18 mm thick highprofit complete
polished for
granite
finished item of work. (APSS No.701 & 707)
stone slabs black colour as approved by the Engineer-in-
Charge of length not less than 2.43 mts set over base coat of
cement mortar (1:8) , 20mm thick using screened sand over CC
bed already laid or RCC roof slab including neat grey cement
slurry of honey like consistency spread @ 3.3 Kg per sqm and
jointed neatly with white cement paste mixed with pigment of
matching shade to full depth including cost and conveyance of
all materials like cement , sand , water , granite slabs etc., to
work site and all operational, incidental labour & lift charges,
half rounding the edge , polishing charges, cost of base coat
and overheads & contractors profit complete for finished item of
work for platforms (S.S.701 & special)

First Floor : 3.00 ONE SQM #REF! #REF!

APMSIDC- PAB- Civil Abs 952of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)
25 Providing 16 mm to 18 mm thick high polished leather
finish granite stone slabs (steel grey or pearl black) with
borders and design as per the pattern approved by the
Engineer-in-Charge of length not less than 2.43 mts set over
base coat of cement mortar (1:5) , 12mm thick using screened
sand over CC bed already laid or RCC roof slab including neat
grey cement slurry of honey like consistency spread @ 3.3 Kg
per sqm and jointed neatly with white cement paste mixed with
pigment of matching shade to full depth including cost and
conveyance of all materials like cement , sand , water , granite
slabs etc., to work site and all operational, incidental labour &
lift charges, full rounding the edges of treads , polishing
charges, cost of base coat and overheads & contractors profit
complete for finished item of work for treads and risers
(S.S.701 & special)
a) Treads of 0.30m wide :
First Floor : 3.00 ONE SQM #REF! #REF!

b) Risers of 0.15m height :


First Floor : 2.00 ONE SQM #REF! #REF!

26 Providing skirting 10 cm height with Double charged / multi


charged stain free full body porcelain vitrified tiles with
double layer pigment of Size 600 x 600 mm and thickness
between 8-10 mm of any colour and finish in all shades and
designs, length equal to flooring tiles, flushed to wall surface to
set over base coat of CM(1:5) 12 mm thick using screened
sand with cement slurry of honey like consistency spread at the
rate of 3.30 kgs per sqm and jointing with white cement paste
mixed with pigment of matching shade to full depth, including
cost of all materials like tiles, cement, sand and water etc.,and
overheads & contractors profit complete for finished item of
work.(APSS No.701 &707)

First Floor : 94.00 ONE RM #REF! #REF!

27 Providing dadooing with glazed white full body ceramic


wall tiles of size 200mm x 300 mm / 245 mm x 325 mm and
thickness 6 mm 1st quality conforming to IS:13711, IS:13712,
IS:13630 (Parts 1 to 15) of any colour and finish in all shades
and designs with borders as approved by Engineer-in-Charge
flushed to wall surface set over base coat of CM(1:5) 12 mm
thick using screened sand with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per sqm and jointing
with white cement paste mixed with pigment of matching shade
to full depth, including cost of all materials like tiles, cement,
sand and water etc., and overheads & contractors profit
complete for finished item of work.

First Floor : 90.00 ONE SQM #REF! #REF!

APMSIDC- PAB- Civil Abs 953of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)
28 Supplying and fixing of stainless steel (grade 304) hand 7.00 ONE SQM #REF! #REF!
railing as per approved drawing with top rail of 50mm dia pipe
and 2mm thick medium class and vertical posts of 25mm dia
and 1.6mm thick medium class 1 No for each step fixed with
base plate of 75mm dia using bonding agent and anchor
fastner and welding, drilling of 25mm dia holes with pneumatic
compressor for fixing railing, buffing, polishing all members of
the railing thouroughly , lacquer finishing to present seamless
finish including cost and conveyance of all materials,
electrodes, welding charges, cost of all consumables, labour
charges , overheads & contractors profit etc., complete for
finished item of work. for all floors

29 Providing 110 mm Dia ISI marked PVC down water take 11.00 ONE RM #REF! #REF!
pipes with socket , 2.5mm thick 4.0 kg/sq.cm pressure of ISI
marked including cost of necessary PVC Bends, shoes, iron /
PVC clamps and all other accessories and fixing in position
including cost and conveyance of all materials, operational &
incidental charges including all labour charges for fixing at site
etc., and overheads & contractors profit complete for finished
item of work. (APSS No. 1328)

30 Supply and fixing doors as per drawings with medium teak


wood frame of section 100mm x 65 mm and ISI marked flush
door shutters of 30 mm thick double shutters with bond wood
solid block board type Core having cross bands and face
veneers, hot pressed bonded with water proof phenol
formaldehyde synthetic resin factory made conforming to IS
2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides, fixing 1mm thick mat finish laminated
sheet to full width and height of the flush shutter both
sides including cost and conveyance to site of teak wood
frame, flush shutter, laminate sheet including

supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40


mm x 5mm including cost of ISI marked Aluminium fixtures of 6
Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681)
300mm long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm
dia at top, 2 Nos. 150 mm long handles (IS:208), 2 Nos. door
stoppers and 2 Nos. Rubber / Nylon door stop bushes
including fixing the fixtures to door with required number of
screws, bolt and nuts including labour charges for fixing the
frame in position, fixing the shutter to the frame etc., including
overheads & contractors profit complete for finished item of
work as per APSS 1001 & 1002 (The vertical frame of door
shall be embedded in flooring for a depth of not less than 10
mm) (1500mm x 2100mm)

First Floor : 9.45 ONE SQM #REF! #REF!

APMSIDC- PAB- Civil Abs 954of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)
31 Supply and fixing doors as per drawings with medium teak
wood frame of section 100mm x 65 mm and ISI marked flush
door shutters of 30 mm thick single shutter with bond wood
solid block board type Core having cross bands and face
veneers, hot pressed bonded with water proof phenol
formaldehyde synthetic resin factory made conforming to IS
2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides, fixing 1mm thick mat finish laminated
sheet to full width and height of the flush shutter both
sides including cost and conveyance to site of teak wood
frame, flush shutter, laminate sheet including supply and

fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm


including cost of ISI marked Aluminium fixtures of 3 Nos. butt
hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm
long, 1 No. tower bolt (IS:204) of 200 mm x 10 mm dia at top, 2
Nos. 150 mm long handles (IS:208), 1 No. door stopper and 1
No. Rubber / Nylon door stop bushes including fixing the
fixtures to door with required number of screws, bolt and nuts
including labour charges for fixing the frame in position, fixing
the shutter to the frame etc, including overheads & contractors
profit complete for finished item of work as per APSS 1001 &
1002 (The vertical frame of door shall be embedded in flooring
for a depth of not less than 10 mm) (900mm x 2100mm)

First Floor : 5.67 ONE SQM #REF! #REF!

32 Supplying and fixing single side prelam solid panel PVC


door frame (Choukhat): Providing and fixing factory made Pac
single side Prelam door frame of the size 50x7 mm with a wall
thickness of 5mm, made out of extruded 5mm rigid Pac single
side prelam sheet, meter cut at two corners and joined with 2
Nos. of 150mm long brackets of 15 x 15mm MS Square tube.
The two vertical door profiles are to be reinforced with 19 x
19mm MS. square tube of 19 guage. The door frame shall be
fixed to the wall using 65/100mm long MS. Screws through the
frame by using Pac fasteners. a minimum of 4 Nos. of screws
to be provided for each vertical member and minimum 2nos. for
horizontal member etc. complete as per manufacture
specification and direction of Engineer-incharge including
conveyance of all materials, labour charges for fixing,
overheads & contractors profit complete for finished item of
work.

First Floor : 30.00 ONE RM #REF! #REF!

APMSIDC- PAB- Civil Abs 955of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)
33 Providing and fixing 30mm thick factory made moulded
door shutter- wood free consisting of frame made out of MS.
tubes 19gauge thickness and size of 25mmX25mm for styles,
top and bottom rails. MS. Frame shall have a coat of steel
primers. The inner panel shall consist of 25mm thick high
density EPS conforming to IS 4671-1984 bounded with 2mm
thick termite proof, water proof and fire resistant moulded Pac
sheet with 2,4,6 raised panel design in different plain and / or
pre-lam colours after routing to the moulded design on one side
and 2mm plain and / or pre-lam Pac sheet on other side of the
EPS. The edge of panel to be sealed with lipping of 10mm wide
PVC sheet bottom (made by sticking 2 rigid foam sheet of 5mm
thickness using Pac solvent cement) and stiles sides
25mm(5mmX5) thick and 30mm width Pac sheet fitted along
MS tube for lock provision for lock height 5mm thick Pac sheet
of size 150mmX100mm fixed with upper and lower face of inner
side of EPS panel etc., complete as per direction of Engineer –
in-Charge, manufacture specification and drawing including ISI
marked Aluminium fixtures 3 Nos. butt hinges (IS:205) of
150mm long, 1 No. aldrop (IS:2681) 250 mm long, 1 No. tower
bolt (IS:204) of 150 mm x 10mm dia, 2 Nos. 125mm long
handles (IS:208),1 No. Rubber / Nylon door stop bushes
including labour charges for fixing the shutter to frame etc.,
First Floor : 10.08 ONE SQM #REF! #REF!

34 Providing and fixing factory made uPVC white colour


sliding glazed window comprising of uPVC multi-chambered
frame with in-built roller track and sash extruded profiles duly
reinforced with 1.60 ± 0.2 mm thick galvanized mild steel
section made from roll forming process of required length
(shape & size according to uPVC profile), appropriate
dimension of uPVC extruded glazing beads and uPVC extruded
interlocks, EPDM gasket, wool pile, zinc alloy (white powder
coated) touch locks with hook, zinc alloy body with single nylon
rollers (weight bearing capacity to be 40 kg), G.I fasteners 100
x 8 mm size for fixing frame to finished wall and necessary
stainless steel screws etc. Profile of frame & sash shall be
mitred cut and fusion

welded at all corners, including drilling of holes for fixing


hardware's and drainage of water etc. After fixing frame the gap
between frame and adjacent finished wall shall be filled with
weather proof silicon sealent over backer rod of required size
and of approved quality, all complete as per approved drawing
& direction of Engineer-in-Charge inclusive of cost of Single /
double glass panes of 4mm thick pin headed glass, wire mesh
and silicon sealent . Note: For uPVC frame and sash extruded
profiles minus 5% tolerancein dimension i.e. in depth & width of
profile shall be acceptable.Variation in profile dimension in
higher side shall be accepted. But no extra payment on this
account shall be made.

Two track two panels sliding window made of frame 67 x 50


mm & sash 46 x 62 mm both having wall thickness of 2.3 ± 0.2
mm and single glazing bead / double glazing bead of
appropriate dimension .
First Floor : 16.20 ONE SQM #REF! #REF!

APMSIDC- PAB- Civil Abs 956of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)
35 Providing and fixing factory made uPVC white colour fixed
glazed windows / Ventilators comprising of uPVC multi
chambered frame and mullion (where ever required) extruded
profiles duly reinforced with 1.60± 0.2 mm thick galvanized mild
steel section made from roll forming process of required length
(shape & size according to uPVC profile), uPVC extruded
glazing beads of appropriate dimension, EPDM gasket,G.I
fasteners 100 x 8 mm size for fixing frame to finished wall,
plastic packers, plastic caps and necessary stainless steel
screws etc. Profileof frame shall be mitred cut and fusion
welded at all corners, mullion (if required) shall be also fusion
welded including drilling of holes for fixing hardware and
drainage of water etc.

After fixing frame the gap between frame and adjacent finished
wall shall be filled with weather proof silicon sealant over
backer rod of required size and of approved quality, all
complete as per approved drawing & direction of Engineer-in-
Charge inclusive of cost of Single / double glass panes and
silicon sealant. Note: For uPVC frame, sash and mullion
extruded profiles minus 5%tolerance in dimension i.e. in depth
& width of profile shall be acceptable.Variation in profile
dimension in higher side shall be accepted. But, no extra
payment on this account shall be made.

Fixed windows / Ventilators made of (small series) frame 47 x


50mm & mullion 47 x 68 mm both having wall thickness of 1.9
±0.2 mm and single glazing bead of appropriate dimension.

First Floor : 1.80 ONE SQM #REF! #REF!

36 Supplying and fixing of MS doors, grill to windows / in open


court yards using MS angles, flat, square bars including cost
and conveyance of all materials, cutting, bending, welding, all
operational charges, labour charges, overheads and contractor
profit etc., complete for finished item of work. For All Floors

First Floor : 345.00 ONE KG #REF! #REF!

37 Supplying and fixing of two shutter cupboards as per


drawing with medium teak wood frames of size 75mm x 40mm
and MDF Board Interior grade both sides laminated 18mm thick
for shutters with 18mm x 12mm teak wood beading alround
and supplying and fixing powder coated MS fixtures 3 Nos.
butt hinges of size 100mm long(for each shutter), tower bolt 2
Nos. of 100mm x 10mm, 2 Nos of handles 100mm long and
standard locking arrangements for shutters including cost and
conveyance of all materials to site, labour charges, over heads
and contractor profit etc., complete for finished item of work.

First Floor : 4.06 ONE SQM #REF! #REF!

APMSIDC- PAB- Civil Abs 957of 1048


Amount
Sl.No. Description of Work Quantity Unit Rate
(Rs.)
29 White washing two coats with white cement to ceiling to give
an even shade after thouroughly brushing the surface to
remove all dirt and remains of loose powdered materials
including cost of all materials , labour charges and incidental
such as scaffolding , lift charges etc., and overheads &
contractors profit complete for finished item of work in all floors.

First Floor : 141.00 ONE SQM #REF! #REF!

30 Supply & application of one coat water based cement


primer of interior grade I and two coats of synthetic
polymer luxury plastic emulsion paint of superior grade
having VOC (Volatile Organic Compound) content less than 50
grams/litre for internal walls including cost and conveyance of
all materials to site, incidental, operational and all labour
charges etc., and overheads & contractors profit complete for
finished item of work in all floors.

First Floor : 312.00 ONE SQM #REF! #REF!

31 Supply & application of one coat water based cement


primer of exterior grade II and two coats of synthetic
polymer luxury plastic emulsion paint of superior grade
having VOC (Volatile Organic Compound) content less than 50
grams/litre for exterior walls including cost and conveyance of
all materials to site, incidental, operational and all labour
charges etc., and overheads & contractors profit complete for
finished item of work in all floors.

First Floor : 289.00 ONE SQM #REF! #REF!

32 Painting two coats with synthetic enamel paint Grade-II


VOC (Volatile Organic Compound) content less than 50
grams/litre over primer coat of red oxide to new iron work
including cost and conveyance of all materials to site,
incidental, operational and all labour charges etc., and
overheads & contractors profit complete for finished item of
work in all floors. (SS No. 1201, 1212 & 1207).

First Floor : 23.00 ONE SQM #REF! #REF!

33 Reinforced cement concrete (1:5:10) proportion (Cement:


fine aggregates: coarse aggregate) using 40mm size (SS5)
hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand), coarse aggregate, water etc., to site
including centering using Casurina Ballies , Bamboos , Wooden
Reapers , Runners , Wood Posts , Wall Plates etc., shuttering,
machine mixing, laying concrete, lifting concrete manually ,
vibrating, curing, etc., and overheads & contractors profit
complete as per drawings but excluding cost of steel and it's
fabrication charges for finished item of work (APSS NO. 402 &
403) for dummy columns.

Second Floor : 1.30 ONE CUM #REF! #REF!

TOTAL : #REF!

APMSIDC- PAB- Civil Abs 958of 1048


Detailed Estimate - ATTENDANTS DORMITORY
S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Earth work excavation by Machinary up
1 to 3.0m
F1 2 1.850 1.850 1.800 12.32
F2 2 1.950 1.950 1.800 13.69
F3 5 2.150 2.150 1.800 41.60
F4 3 2.450 2.450 1.800 32.41
F5 2 2.750 2.750 1.800 27.23
127.25
Say 128.00 Cum

2 PCC (1:4:8) for column footings


For Column Footings
F1 2 1.850 1.850 0.150 1.03
F2 2 1.950 1.950 0.150 1.14
F3 5 2.150 2.150 0.150 3.47
F4 3 2.450 2.450 0.150 2.70
F5 2 2.750 2.750 0.150 2.27
10.60
Say 10.60 Cum

3 PCC (1:5:10)
All round the Building 1 52.520 0.600 0.150 4.73
Deductions
C1 -5 0.450 0.600 0.150 -0.20
C1 -1 0.230 0.600 0.150 -0.02
C2 -2 0.450 0.600 0.150 -0.08
C3 -2 0.450 0.600 0.150 -0.08
under internal plinth beam
Horizontals
B1-B3 1 3.570 0.450 0.150 0.24
B3-B5 2 11.060 0.450 0.150 1.49
Ded for columns -2 0.230 0.450 0.150 -0.03
Ded for columns -2 0.450 0.450 0.150 -0.06
C2-C3 1 2.780 0.450 0.150 0.19
Verticals
A3-B3 1 2.000 0.450 0.150 0.14
B3-D3, B4-D4 2 8.500 0.450 0.150 1.15
Ded for columns -6 0.230 0.450 0.150 -0.09
Secondary beams 1 3.850 0.450 0.150 0.26
Secondary beams 1 3.960 0.450 0.150 0.27
Under Flooring
Qty same as Vitrified tile Flooring 1 77.111 0.100 7.71
Qty same as Ceramic Flooring 1 29.420 0.100 2.94
Qty same as Chequered Flooring 1 33.659 0.100 3.37
21.91
Say 22.00 Cum

4 Earth filling with available earth


Qty as per excavation 128.000 128.00
Deductions
a Qty as per PCC (1:4:8) -10.604
b Qty as per PCC (1:5:10) -22.000
c Qty as per footing -24.845

d Qty as per 175mm thick side Wall upto GL -13.497


e Qty as per columns upto Ground level -1.000
56.054 -71.95
56.05
Say 57.00 Cum
5 Basement Filling
Qty same as Vitrified tile Flooring 1 77.111 2.000 154.22
Qty same as Ceramic Flooring 1 29.420 2.000 58.84
Qty same as Chequered Flooring 1 33.659 2.000 67.32
280.38
Say 281.00 Cum

6 Total Earth to be Filled


Basement filling 280.38
Quantity same as filling sides of
foundation and Plinth 57.00
337.38
Say 338.00 Cum

7 Filling with Available Earth 0.80 127.251 101.80


Say 102.00 Cum

8 Filling with Carted Gravel 236.00


Say 236.00 Cum

9 175mm thick side walls


All round the Building 1 52.520 1.550 81.41
Deductions
C1 -6 0.230 1.550 -2.14
C2 -2 0.230 1.550 -0.71
C3 -3 0.230 1.550 -1.07
C4 -1 0.230 1.550 -0.36
77.13
Say 78.00 Sqm

10 Antitermite treatment
Alround the slab As per CAD 1 159.190 159.19
159.19
Say 160.00 Sqm

10 VRCC M25 design mix


a) Footings
F1 2 1.700 1.700 0.300 1.73
F2 2 1.800 1.800 0.325 2.11
F3 5 2.000 2.000 0.375 7.50
F4 3 2.300 2.300 0.425 6.74
F5 2 2.600 2.600 0.500 6.76
24.84
Say 24.80 Cum
b) Pedastals
F1 2 0.600 0.600 0.600 0.43
F2 2 0.600 0.600 0.600 0.43
F3 5 0.600 0.600 0.600 1.08
F4 3 0.600 0.600 0.600 0.65
F5 2 0.600 0.600 0.600 0.43
3.02
Say 3.00 Cum

c) Plinth beams
Horizontals
A1-A3 1 3.570 0.230 0.450 0.37
B1-B3 1 3.570 0.230 0.450 0.37
B3-B5 3 11.060 0.230 0.450 3.43
Ded for columns -3 0.230 0.230 0.450 -0.07
Ded for columns -3 0.450 0.230 0.450 -0.14
C2-C3 1 2.780 0.230 0.400 0.26
D2-D3 1 2.780 0.230 0.400 0.26
Verticals
A1-B1, A3-B3 2 2.000 0.230 0.400 0.37
B2-D2 1 8.268 0.230 0.400 0.76
Ded for columns -2 0.450 0.230 0.400 -0.08
B3-D3, B4-D4 2 8.500 0.230 0.400 1.56
Ded for columns -6 0.230 0.230 0.400 -0.13
Secondary beams 1 3.850 0.230 0.400 0.35
Secondary beams 1 3.960 0.230 0.400 0.36
B5-D5 1 8.500 0.230 0.450 0.88
Ded for columns -3 0.450 0.230 0.450 -0.14
8.41
Say 8.50 Cum
d) Tie beam
Quantity same as plinth beam 8.41
Say 8.50 Cum

11 VRCC
i Columns upto GL
C1/F1 2 0.230 0.450 0.750 0.16
C1/F2 2 0.230 0.450 0.725 0.15
C1/F3 1 0.230 0.450 0.675 0.07
C1/RF1/F3 1 0.230 0.450 0.675 0.07

C2/F3 2 0.230 0.450 0.675 0.14


C2/F4 1 0.230 0.450 0.625 0.06

C3/F3 1 0.230 0.450 0.675 0.07


C3/F4 1 0.230 0.450 0.625 0.06
C3/RF2/F4 1 0.230 0.450 0.625 0.06

C4/F5 2 0.230 0.450 0.550 0.11


14 0.96
Say 1.00 Cum
ii GL to Plinth top level
C1 6 0.230 0.450 2.000 1.24
C2 3 0.230 0.450 2.000 0.62
C3 3 0.230 0.450 2.000 0.62
C4 2 0.230 0.450 2.000 0.41
14 2.90
Say 2.90 Cum

iii Columns P.B Top to Roof slab bottom


C1 6 0.230 0.450 2.875 1.79
C2 3 0.230 0.450 2.875 0.89
C3 3 0.230 0.450 2.875 0.89
C4 2 0.230 0.450 2.875 0.60
14 4.17
Say 4.20 Cum
Total Qty of Columns
i Upto G.L 0.96
ii From GL to Plinth level 2.90
iii Above plinth 4.17
8.03
Say 8.00 Cum
12 Roof Beams @3.6 Mts Level
Horizontal
A1-A5 1 15.530 0.230 0.300 1.07
Ded for columns -2 0.450 0.230 0.300 -0.06
B1-B3 1 3.570 0.230 0.300 0.25
B3-B4 1 5.850 0.230 0.380 0.51
B4-B5 1 4.460 0.230 0.300 0.31
C2-C3 1 2.780 0.230 0.300 0.19
C3-C4 1 5.960 0.230 0.380 0.52
C4-C5 1 4.460 0.230 0.300 0.31
D2-D3 1 2.780 0.230 0.300 0.19
D3-D4 1 5.960 0.230 0.380 0.52
D4-D5 1 4.530 0.230 0.300 0.31
Verticals
MLB 1 2.000 0.230 0.350 0.16
A3-B3 1 2.000 0.230 0.300 0.14
A4-B4, A5-B5 2 2.000 0.230 0.325 0.30
B2-D2 1 8.269 0.230 0.300 0.57
Ded for columns -2 0.450 0.230 0.300 -0.06
B3-D3, B4-D4, B5-D5 3 8.498 0.230 0.300 1.76
Ded for columns -6 0.230 0.230 0.300 -0.10
Ded for columns -3 0.450 0.230 0.300 -0.09
Secondary beam 1 3.960 0.230 0.300 0.27
Secondary beam 1 3.850 0.230 0.300 0.27
7.34
Say 7.40 Cum

13 Roof slab
i) Roof Slab 125mm thick
Alround the slab As per CAD 1 159.190 159.19
Deduction of 150mm thick slab -1 11.400 8.500 -96.90
Deduction of staircase -1 4.010 2.000 -8.02
54.27
Say 55.00 Sqm
ii) Roof Slab 150mm thick
150mm thick slab 1 11.400 8.500 96.90
96.90
Say 97.00 Sqm
ii) Roof Slab 175mm thick
Staircase 2 3.500 2.000 14.00
Midlanding 1 2.115 1.000 2.12
16.12
Say 17.00 Sqm

14 Lintels
Opening at Entrance 1 2.500 0.230 0.175 0.10
D2 3 1.960 0.230 0.175 0.24
D3 3 1.360 0.115 0.175 0.08
D3 6 1.260 0.115 0.175 0.15
SW1 5 2.260 0.230 0.175 0.45
SW3 2 1.660 0.230 0.175 0.13
SW4 2 1.360 0.230 0.175 0.11
V 6 1.060 0.230 0.175 0.26
27 1.53
Say 1.60 Cum

15 Sunshades
SW1 3 2.100 6.30
SW3 2 1.500 3.00
SW4 1 1.360 1.36
6 10.66
Say 11.00 Rmt
16 Sill slabs
SW1 5 2.260 0.230 0.050 0.13
SW3 2 1.660 0.230 0.050 0.04
SW4 2 1.360 0.230 0.050 0.03
V 6 1.060 0.230 0.050 0.07
15 0.27
Say 0.30 Cum

17 Platforms
Kitchen platform 1 4.515 0.600 2.71
Wash basin 1 1.500 0.600 0.90
3.61
Say 4.00 Sqm

18 Shelves
Kitchen platform 1 4.515 0.450 2.03
2.03
Say 3.00 Sqm

17 230 mm thick brick masonary


Horizantal
Staircase walls 1 4.470 0.230 2.575 2.65
Ded for col -2 0.230 0.230 2.575 -0.27
Dormitory 1 5.850 0.230 2.470 3.32
Entrance 1 4.530 0.230 2.550 2.66
Bath 1 2.780 0.230 2.575 1.65
Dormitory Female 1 5.960 0.230 2.470 3.39
Passage to Wash area 1 4.530 0.230 2.550 2.66
Ded Wall for jally wall -1 1.800 0.230 1.300 -0.54
Verticals
Staircase 1 2.000 0.230 2.525 1.16
Male Toilets 1 3.630 0.230 2.575 2.15
Female Toilets 1 3.743 0.230 2.575 2.22
Dormitory male 1 3.890 0.230 2.550 2.28
Dormitory Male 1 3.700 0.230 2.550 2.17
Along the Passage 1 8.040 0.230 2.850 5.27
Kitchen to Wash area 1 8.500 0.230 2.550 4.99
Ded for col -3 0.450 0.230 2.550 -0.79
Ded for grill -1 3.180 0.230 1.300 -0.95
Deductions
Entrance opening -1 2.040 0.230 2.100 -0.99
D2 -3 1.500 0.230 2.100 -2.17
SW1 -5 1.800 0.230 1.300 -2.69
SW3 -2 1.200 0.230 0.900 -0.50
SW4 -2 0.900 0.230 1.300 -0.54
V -6 0.600 0.230 0.500 -0.41
Lintels
Entrance opening -1 2.500 0.230 0.175 -0.10
D2 -3 1.960 0.230 0.175 -0.24
SW1 -5 2.260 0.230 0.175 -0.45
SW3 -2 1.660 0.230 0.175 -0.13
SW4 -2 1.360 0.230 0.175 -0.11
V -6 1.060 0.230 0.175 -0.26
25.41
Say 26.00 Cum

18 110 mm brick walls


Staircase walls 1 4.470 2.575 11.51
Ded for col -2 0.230 2.575 -1.18
wc walls H 4 1.500 2.875 17.25
Toilets H 1 2.780 2.575 7.16
wc to Bath 2 3.963 2.575 20.41
wc to Bath 1 3.963 2.575 10.20
wc to Bath 1 4.080 2.575 10.51
Ded for col -1 0.230 2.575 -0.59
Dormitory H 1 5.960 2.470 14.72
Kitchen 1 1.800 2.850 5.13
Parapet wall 1 52.520 0.900 47.27
Front side 1 13.290 0.900 11.96
Ded opneing -1 2.000 0.900 -1.80
Deductions
D3 -3 0.900 2.100 -5.67
D4 -6 0.800 2.100 -10.08
Lintels
D3 -3 1.360 0.175 -0.71
D4 -6 1.260 0.175 -1.32
134.76
Say 135.00 Sqm

19 PCC (1:3:6) for Bedblocks


under lintels
D2 2 3 0.300 0.230 0.150 0.06
D3 2 3 0.300 0.115 0.150 0.03
D4 2 6 0.300 0.115 0.150 0.06
SW1 2 5 0.300 0.230 0.150 0.10
SW3 2 2 0.300 0.230 0.150 0.04
SW4 2 2 0.300 0.230 0.150 0.04
V 2 6 0.300 0.230 0.150 0.12
Hold fasts
D2 6 3 0.230 0.230 0.150 0.14
D3 6 3 0.230 0.115 0.150 0.07
D4 6 6 0.230 0.115 0.150 0.14
SW1 4 5 0.230 0.230 0.150 0.16
SW3 4 2 0.230 0.230 0.150 0.06
SW4 4 2 0.230 0.230 0.150 0.06
V 2 6 0.230 0.230 0.150 0.10
1.20
Say 1.20 Cum
20 Dummy columns
C1 6 0.230 0.450 0.900 0.56
C2 3 0.230 0.450 0.900 0.28
C3 3 0.230 0.450 0.900 0.28
C4 2 0.230 0.450 0.900 0.19
1.30
Say 1.30 Cum

21 TMT STEEL
Columns Footings 25 60.000 Kgs/Cum 1490.69
Column pedestals 3 100.000 Kgs/Cum 302.40
175 mm thick side walls 78 80.000 0.175 Kgs/Cum 1092.00
Plinth beams 8 100.000 Kgs/Cum 841.49
Tie beam 8 100.000 Kgs/Cum 841.49
Columns upto 3.60 mts levael 8 200.000 Kgs/Cum 1605.29
Dummy columns 1.3 200.000 Kgs/Cum 260.82
Roof Beams upto 3.60 mts level 7 200.000 Kgs/Cum 1480.00
125mm thick Roof slab 55 80.000 0.125 Kgs/Cum 550.00
150mm thick Roof slab 97 80.000 0.150 Kgs/Cum 1164.00
175mm thick Roof slab 16 80.000 0.175 Kgs/Cum 225.61
sill slab 0.27 80.000 Kgs/Cum 21.80
Sunshades 0.6 10.66 80.000 0.063 Kgs/Cum 31.98
Platforms & Lofts 3.61 80.000 0.050 Kgs/Cum 14.44
Lintels 2 80.000 Kgs/Cum 128.00
###
Say 10.10 MT
22 Mild Steel
RBM 135 2.000 Kgs/Sqm 270.00
RCM Facia 3.99 2.000 Kgs/Sqm 7.97
Shelves 2.03 2.000 Kgs/Sqm 4.06
282.04
Say 0.30 MT

23 RCM Facia
Front side 1 13.290 0.300 3.99
Say 4.00 Sqm

24 External plastering
All round the Building 1 52.520 3.000 157.56
Front side 1 13.290 1.915 25.45
Ded opneing -1 2.000 1.915 -3.83
Terrace
Parapet wall 1 52.520 1.915 100.58
Deductions
Grill -1 1.800 1.300 -2.34
Grill -1 3.180 1.300 -4.13
SW1 -5 1.800 1.300 -11.70
SW3 -2 1.200 0.900 -2.16
SW4 -2 0.900 1.300 -2.34
257.08
Say 258.00 Sqm
25 Ceiling plastering
Qty Same as Vitrified tile flooring 77.11
Qty Same as Ceramic tile flooring 29.42
Qty Same as Chequered flooring 33.66
140.19
Say 141.00 Sqm
26 Internal plastering 12 mm thick
Dormitory male 1 20.270 2.875 58.28
Dormitory female 1 20.270 2.875 58.28
Passage 1 21.080 2.875 60.61
Kitchen 1 12.630 2.875 36.31
W.C 6 5.400 2.875 93.15
Passage 2 10.926 2.875 62.82
Wash area 1 10.860 2.875 31.22
Staircase three sides 1 10.595 2.875 30.46
Deduct Dadooing -89.83
Deduct opening -1 2.000 2.100 -4.20
Deductions
D2 -3 1.500 2.100 -9.45
D3 -3 0.900 2.100 -5.67
D4 -6 0.800 2.100 -10.08
311.90
Say 312.00 Sqm

a 12 mm thick internal plastering


60% of above quantity (internal) 187.20
Say 187.00 Sqm
b 20 mm thick Internal plastering
40% of above quantity (external) 124.80
Say 125.00 Sqm
27 Basement plastering
All round the Building 1 52.520 0.600 31.51
31.51
Say 32.00 Sqm
28 Flooring
a) Vitrified tile flooring
Dormitory male 1 6.180 3.955 24.44
Dormitory female 1 6.180 3.955 24.44
Kitchen 1 1.800 4.515 8.13
Passage 1 8.040 2.500 20.10
77.11
Say 78.00 Sqm
a) Ceramic tile flooring
W.C 6 1.500 1.200 10.80
Passage 2 3.963 1.500 11.89
Wash area 1 1.915 3.515 6.73
29.42
Say 30.00 Sqm

b) Chequered flooring
2230 mm wide portico 1 11.300 2.230 25.20
Under staircase 1 4.000 2.115 8.46
33.66
Say 34.00 Sqm
High Polished granite for kitchen
c) platform
Kitchen 1 4.515 0.600 2.71
Say 3.00 Sqm
High Polished granite for Treads &
d) Risers
i Treads
at entrance 3 3.000 0.300 2.70
Say 3.00 Sqm
ii Risers
at entrance 4 3.000 0.150 1.80
Say 2.00 Sqm
f) Impervious Coat
Terrace 1 159.190 159.19
Deduction of Stiarcase -1 4.010 2.000 -8.02
151.17
Say 152.00 Sqm
g) Skirting with vitrified tiles
Dormitory male 1 20.270 20.27
Dormitory female 1 20.270 20.27
Passage 1 21.080 21.08
Kitchen 1 12.630 12.63
Staircase three sides 1 10.595 10.60
Front passage 1 13.290 13.29
Deduct opening -2 2.000 -4.00
94.14
Say 94.00 Rmt
h) Dadooing with glazed tiles
Bath 6 5.400 1.500 48.60
Passage 2 10.920 1.500 32.76
Wash area 1 10.860 1.500 16.29
above kithcen platform 1 5.715 0.600 3.43
Deductions
D3 -3 0.900 1.500 -4.05
D4 -6 0.800 1.500 -7.20
89.83
Say 90.00 Sqm

29 SS Railing
Staircase 2 3.500 0.900 6.30
Say 7.00 Sqm

30 Whiting for ceiling


Same as ceiling plastering 140.19
Say 141.00 Sqm

Plastic Emulsion Paint for interior faces


31 of walls
Same as internal plastering 311.90
Say 312.00 Sqm

Plastic emulsion paint for external


32 plastering
Same external plastering 257.08
Quantity same as basement plastering 31.51
288.59
Say 289.00 Sqm

33 Doors
D2 1 3 1.500 2.100 9.45 Sqm

D3 1 3 0.900 2.100 5.67 Sqm

D4 (Frame) 1 6 5.000 30.00 Rmt

D4 (Shutter) 1 6 0.800 2.100 10.08 Sqm

34 Windows
SW1 1 5 1.800 1.300 11.70
SW3 1 2 1.200 0.900 2.16
SW4 1 2 0.900 1.300 2.34
16.20
Say 16.20 Sqm

35 V
6 0.600 0.500 1.80 Sqm

36 Cupboards
Kitchen 1 4.515 0.900 4.06 Sqm

37 MS Grill
SW1 1 5 1.800 1.300 11.70
SW3 1 2 1.200 0.900 2.16
SW4 1 2 0.900 1.300 2.34
Grill 1 1 1.800 1.300 2.34
Grill 1 1 3.180 1.300 4.13
22.67 Sqm
Say 345.00 Kgs

38 Painting to iron work


SW1 1 5 1.800 1.300 11.70
SW3 1 2 1.200 0.900 2.16
SW4 1 2 0.900 1.300 2.34
Grill 1 1 1.800 1.300 2.34
Grill 1 1 3.180 1.300 4.13
22.67 Sqm
Say 23.00 Sqm

39 Painting to Doors
D2 2.25 3 1.500 2.100 21.26 Sqm

D3 2.25 3 0.900 2.100 12.76 Sqm

D4 2.25 6 0.800 2.100 22.68 Sqm


56.70 Sqm
Say 57.00 Sqm

36 PVC down take pipe 3 3.600 10.80


10.80
Say 11.00 Rmt
#REF!
ABSTRACT ESTIMATE FOR WATER SUPPLY & SANITARY ARRANGEMENTS
Sl. No. Description of Work Quantity Unit Rate

1 Supplying and laying, filling, jointing and testing SWG SP-1 pipe
conforming to ISI 651 & 4127 with air tight Cement joints in CM (1.5:1)
prop. including excavation of trenches and socket pits in any soil
(except rock requiring blasting) and refilling with watering and tamping
to the required slope including cost and conveyance of all materials to
site and all labour charges , overheads & contractor profit etc.,
complete for finished item of work (APSS NO 1301 & 1318)

152.40mm dia upto 1524.0mm (5') depth 50.00 Rmt #REF!

2 Supplying and fixing of SWG Gully traps 150mm x 100mm of ISI 5.00 NO #REF!
make confirming to IS 651 & 4127 with C.I grating & constructing
cement brick masonry in CM (1:6) prop., intermediate chamber and
fitted with 304.8 mm X 288.6 mm (12"x9") C.I Frame with hinged cover
of standard make as approved including cost and conveyance of all
materials to site, labour charges, overheads & contractors profit etc.,
complete for finished item of work.

3 Constructing 457.2 mm x 457.2 mm (1'6"x1'6") brick in CM 1:6 5.00 NO #REF!


prop. Masonry. Inspection chamber upto 914.4 mm (3'0") and fitted
with light weight 457.2 mm x 457.2 mm (1'6"x1'6") C.I frame and cover
of 20 Kg including cost and conveyance of all materials like cement,
sand, bricks, water etc., to site and all incidental and operational,
labour charges like mixing cement mortar, constructing masonry, lift
charges, curing , overheads & contractors profit etc., complete for
finished item of work as per Standard specification.

4 Constructing 904.0 mm (3’0”) dia brick masonry inspection 5.00 NO #REF!


chamber as per IS - 4111: Part-1:1986 with cement mortar (1:6) prop
using 2nd Class Clay Bricks of 225 mm thick from approved source
having a minimum crushing strength of 5 N/sq.mm including plastering
with cement mortar 1:3 prop; ½” thick both inside and outside fitted
with 20” dia RCC manhole covers and frames including excavating
pits up to a depth of 904 mm (3'-0") in all sorts of soils (exculding
rock) and laying cement conrete (1:4:8) 150 mm thick using 40 mm
HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as
per Standard specification and including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site and all incidental
and operational, labour charges like mixing cement mortar,
constructing masonry, lift charges, curing , overheads & contractors
profit etc., complete for finished item of work as per Standard
specification.

5 Supplying and fixing of 4" (101.6mm) multi floor trap with jali - 12.00 NO #REF!
UPVC/SWR pipe fittings as per site requirements with standard
practice for all floors including cost and conveyance of all materials to
site, labour charges , overheads & contractors profit etc., complete for
finished item of work..
6 Supplying and fixing European Water Closet of 1st quality 2.00 NO #REF!
conforming to IS:2556-Part-2-1973 of white glazed with 'S'
trap,supplying and fixing best Indian make plastic seat and lid for
European water closets with rubber or plastic Buffers as per IS 2548-
1996 and 10 litres capacity single flush PVC low level cistern with
internal components and fixed using required size of nails and screws,
angle stop cock 12.70mm dia. first quality Indian make heavy duty,
12mm PVC connections with brass union nuts CP coated including
cost and conveyance of all materials to site, overheads & contractors
profit etc., complete for finished item of work for all floors.

7 Supplying and fixing 580mm x 440mm long Orissa pan white 2.00 NO #REF!
glazed Water Closet 1st quality ISI marked confirming to IS:2556-Part-
3-1981 with "P" or "S" trap, ISI marked and providing masonry seat,
CC squatting plate and 10 litres capacity single flush PVC low level
cistern with internal components fixed on 2 Nos. of teak wood blocks of
size 76.20mm x 101.60mm using required size of nails, screws as
approved by Engineer-in-charge, angle stop cock 12.70mm dia. first
quality Indian make heavy duty, 12.70mm PVC connection with brass
union nuts CP coated , 31.75mm brass plumber union, P trap or S trap
of Indian W.C. shall be encased on CC (1:2:4) 150mm alround well
above the joint to stop leakage at the joint etc., complete including cost
and conveyance of all materials to site, cost of CC bed, labour
charges, overheads & contractors profit etc., complete for finished item
of work.

8 Supplying and fixing Indian make Flat Back Wash Hand Basin 1st 3.00 NO #REF!
quality conforming to IS:2556-Part-4:1972 of size 550mm x 400mm
with 32 mm nominal size C.P. Fitting with parallel pipe thread
conforming to IS:2963-1979 and fitted with 15 mm nominal bore
Chromium Plated Pillar Tap of 1st quality Indian make heavy duty
complete with standard CI brackets including wooden blocks ,1
No.12.70mm PVC connection with brass union nuts CP coated , angle
stop cock 12.70mm dia. first quality Indian make heavy duty, 31.75mm
dia. PVC flexible waste pipe 914.4mm length of 1st quality including
cost and conveyance of all materials to site, labour charges ,
overheads & contractors profit for finished item of work

9 Supplying and fixing NP soap dish heavy type of approved make ISI 3.00 NO #REF!
quality with NP screws etc., complete including cost and conveyance of
all materials, labour charges for fixing , overheads & contractors profit
for finished item of work in all floors

10 Supplying and fixing TV shape mirror with plastic frame of size 3.00 NO #REF!
609.6mm x 457.2mm , plywood back with NP screws 1st quality
including cost and conveyance of all materials, labour charges ,
overheads & contractors profit for finished item of work in all floors.

11 Supplying and fixing of 25.4mm dia , 609.6mm long aluminium 3.00 NO #REF!
anodized towel rods with brackets and aluminium screws including
cost and conveyance of all materials, labour charges , overheads &
contractors profit for finished item of work.
12 Supplying and fixing white glazed flat back half stall urinals of 2.00 NO #REF!
size 590 mm x 375 mm x 390 mm with integral flushing rim fixed with
screws complete Indian make (HSW/Parry/Neycer) conforming to
IS:2556-1995 as approved by Engineer-in-charge, including supply and
fixing 12.7mm PVC connection with brass plumber union nuts CP
coated, 12.70mm push cock 1st quality of approved make , 31.75 mm
dia PVC flexible waste pipe of 914.4 mm length of Ist quality including
cost and conveyance of all materials to site, labour charges etc.,
overheads & contractors profit complete for finished item of work for all
floors

13 Supplying and fixing of 16mm to 20 mm thick polished marble 1.00 NO #REF!


slab partitioins of size 4' 0" x 2' 0" for urinals including full rounding
the edges , fixing in position, polishing, including cost and conveyance
of all materials and labour charges , overheads & contractors profit
complete for finished item of work for all floors.

14 Supplying and fixing of 101.60mm x 609.60mm white glazed 2.00 RM #REF!


porcelain channels 1st quality fixed in brick masonry to the required
slopes , white cement pointing including cost and conveyance of all
materials and labour charges , overheads & contractors profit complete
for finished item of work for all floors.

15 Supplying and fixing of stainless steel sink of size 508.00mm x 1.00 NO #REF!
457.2mm x 203.20mm, 1mm thick of Indian make fixed on cantilever
brackets including supply and fixing 31.75mm C.P. waste coupling,
31.75 mm dia PVC flexible waste pipe of 914.4 mm length of Ist
quality ncluding chiselling brick masonry wall and making good &
restoring to original surfaces , overheads & contractors profit complete
for finished item of work in all floors

16 Supplying and fixing NP bib taps of size 12.70mm dia of Indian 3.00 NO #REF!
make heavy duty (long body) as approved by the Engineer-In-
Charge including cost and conveyance of all materials, labour
charges , overheads & contractors profit complete for finished item of
work in all floors.

17 Supplying and fixing NP bib taps of size 12.70mm dia of Indian 4.00 NO #REF!
make heavy duty (short body) as approved by the Engineer-In-
Charge including cost and conveyance of all materials, labour
charges , overheads & contractors profit complete for finished item of
work in all floors.
18 Supply and fixing of Ashirvad/ Ajay/ Astral Flowguard or
equivalent CPVC Pipes and Fittings SDR 11 to meet the requirement
of ASTM-D 2846 and are produced in CTS (Copper Tube Sizes 1/2" to
2") for hot and cold water (IS 15778:2007) including cost and
conveyance of all materials to site, labour charges for fixing, overheads
& contractors profit complete for finished item of work at all floor levels

a) 15.90mm OD pipe 11.00 Rmt #REF!

b) 22.20mm OD pipe 42.00 Rmt #REF!

c) 28.60mm OD pipe 10.00 Rmt #REF!

d) 34.90mm OD pipe 35.00 Rmt #REF!

e) 41.30mm OD pipe 45.00 Rmt #REF!

19 Supplying and fixing Gunmetal Gate ( GM peet ) valve as per IS-


778 Class - I , Indian make heavy type including cost and conveyance
of all materials , labour charges , overheads & contractors profit
complete for finished item of work.
20mm Nominal bore 4.00 NO #REF!

25mm Nominal bore 2.00 NO #REF!

20 Supplying and fixing of SWR PVC pipes


(Prince/Sudhakar/Kisan/Supreme or any ISI brand) 4 Kg/Sq.cm. and
fixing all special such as plain bends, off sets, door bends, single
junctions, double junctions as per site requirement, fixing with PVC
clamps if necessary with required number of Bombay nails including
cost and conveyance of all materials to site, labour charges, overheads
& contractors profit complete for finished item of work at all floor levels.
(APSS No. 1302 1319 & 1326)

a) 75mmdia 20.00 Rmt #REF!

b) 110mmdia 10.00 Rmt #REF!

21 Construction of brick masonry support for GI pipe of size 25.00 NO #REF!


304.80mm x 228.60mm x 228.60 mm in CM (1:8) prop including
plastering and finishing with 12mm thick in CM (1:5) including cost and
conveyance of all materials and all labour charges, overheads &
contractors profit complete for finished item of work for all floors.

22 Providing and placing on terrace (at all floor levels)polyetheylene 1500.00 NO #REF!
water storage tank with double layer approved brand and
manufacture with cover and suitable locking arrangement and making
necessary holes for inlet and outlets and over flow pipes but without
fittings and base support for tanks including cost and conveyance of
all materials and labour charges , overheads & contractors profit
complete for finished item of work.

Sub Total (WS): 1810.00


ENTS
Amount
(Rs.)

#REF!

#REF!

#REF!

#REF!

#REF!
#REF!

#REF!

#REF!

#REF!

#REF!

#REF!
#REF!

#REF!

#REF!

#REF!

#REF!

#REF!
#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!
#REF!

Detailed Estimate for water supply and Arrangements


Sl.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
External Sewerage
1 Supply, Laying, Jointing SWG line
a) SWG PIPE
4" dia SWG line(100mm Dia) 50 50
Say 50 Rmt

2 Gully traps 5
Say 5 Nos

3 Inspection Chambers 5
Say 5 Nos

4 Manholes
3' - 0' Depth 5
Say 5 Nos

Internal sewerage system


5 Floor Traps
Ground Floor 12 12
Say 12 Nos

6 Indian IWC
Ground Floor 2 2
Say 2 Nos

7 European EWC
Ground Floor 2 2
Say 2 Nos

8 Wash hand basins


Ground Floor 3 3
Say 3 Nos

9 Soap dish
Ground Floor 3 3
Say 3 Nos
10 Mirrors
Ground Floor 3 3
Say 3 Nos

11 Towel rods
Ground Floor 3 3
Say 3 Nos

12 Sink
Ground Floor 1 1
Say 1 Nos

13 NP bib taps
a) Long Body taps (Bath& wash Taps)
Ground Floor 3 3
Say 3 Nos
b) Long Body taps (Drinking water Taps)
Ground Floor 4 4
Say 4 Nos

14 Urinals
Ground Floor 2 2
Say 2 Nos

15 Marble Partitions
Ground Floor 1 1
Say 1 Nos

16 Porcelain Channels
Ground Floor 2 0.6 1.2
1.20
Say 2.00 Rmt

ASHIRVAD / AJAY / ASTRAL CPVC Pipes


17
a) 15.90mm OD pipe
EWC
Ground Floor 2 0.75 1.50

IWC
Ground Floor 2 0.3 0.60

TAPS
Long Body taps (Bath & wash Taps)
Ground Floor 3 0.9 2.70

Long Body Taps (Drinking water Taps )

Ground Floor 4 0.9 3.60

Wash Basin
Ground Floor 3 0.8 2.40
10.80 Rmt
Say 11 Rmt

b) 22.20mm OD pipe(Domestic water)


Internal Connection
Ground Floor 1 20.0 20
20
Say 20 Rmt
c) 22.20mm OD pipe (Drinking water)
Internal Connection
Ground Floor 1 10.0 10
10
Say 10 Rmt

Drinking water Downtake Pipes


d) 22.20mm OD pipe
Down Take pipes 1 3.00 3.0
3.0
Say 3.0 Rmt
Domestic water Downtake Pipes
e) 22.20mm OD pipe
Down Take pipes 3 3.00 9.0
9.0
Say 9.0 Rmt

18 SWR PVC pipes


a) 75mm dia
Internal Connections
Ground Floor 1 20 20.0
20.00
Say 20.00 Rmt

b) 110 mm dia down take pipe


Internal Connections
Ground Floor 1 10 10.0
10.00
Say 10.00 Rmt

19 CPVC Pipes
Terrace Ring Main
DOMESTIC WATER
a) 40.00 mm OD 45.00 Rmt
b) 32.00 mm OD 35.00 Rmt
c) 28.60 mm OD 10.00 Rmt

20 Gun Metal Valves


20mm Dia 4 No's

25mm Dia 2 No's

21 HDPE Tank
Domestic water 1000 Litrs
Drinking water 500 Litrs

22 Construction of brick masonry support 25 No's


ABSTRACT ESTIMATE FOR CANTEEN

Unit Rate Amount


Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)

1 Earth work excavation for foundations (Mechanical Means) 75.00 One CUM #REF! #REF!
for buildings in ordinary soils and depositing on bank for all
lifts and with an initial lead of 10m and up to 3m depth
including all operational,incidental, labour charges such as
shoring, sheeting, planking, strutting etc., and overheads &
contractors profit complete for finished item of work excluding
dewatering charges etc., as per SS 20 B(APSS 308)

2 Pre construction Anti termite treatment is a process in 70.0 One Sqm #REF! #REF!
which chemical toxic to subterrean tremites is apply/ inject
into soil during early stage of building Construction 2.
Treatement of soil Beneath the building and around the
foundations conduct and chemical use as per BIS - IS 6313
(Part -2) 2013 code specification & CIB RC registered
termiticide which creates a continuous chemical barrier
beneath the building which kills or repels terminates &
impervious to tremite entry 3. Imidacloprid 30.5% SC (IS
63131) dissolve 2.1 Ml/1 liter of water and apply
emulsion/solution @ 7.5 Litres/Square meter (Sqm) of
internal, external vertical surface of the colums, plinth beams
(Back filling) walls and floor junction, external perimeters,
along reatining wall @ 5.0 Liters/Sqm of the horizontal
surface of basement top surface of the basement filling below
flooring bed (Plinth) & @ 2.0 Litres/ Line meter at expansion
joints. The substructure of a depth of 500mm around coulmns
& 300mm deep around plinth beams, basements & floor
filling area including excavation channel along the wall &
rodding etc. cost & Conveyance of all materials to the site,
cost of labour for sparying, rodding, overheads and
contractor profit etc. complete for furnished item of work as
per the approval of the Engineer-in-charge

3 Plain Cement Concrete (1:4:8) (cement: fine aggregate: 7.00 One CUM #REF! #REF!
Coarse aggregate) for foundations using coarse aggregate
40mm size hard , machine crushed granite from approved
quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
including cost and conveyance of all materials like cement,
sand, coarse aggregate, water etc. to site including all
charges for machine mixing and hire charges of concrete
mixer, laying concrete in foundations and under flooring bed,
ramming in 15 cm layers finishing top surface to the required
level curing etc.,and overheads & contractors profit complete
for finished item of work. (APSS No. 402) For Foundation

APMSIDC-Kadapa Canteen-Civil Abs 981of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
4 Plain Cement Concrete (1:5:10) (cement: fine aggregate: 11.00 One CUM #REF! #REF!
Coarse aggregate) for foundations and under flooring bed
using coarse aggregate 40mm size hard , machine crushed
granite from approved quarry using concrete Mixer 10 / 7 cft
(0.2 / 0.8 cum) capacity including cost and conveyance of all
materials like cement, sand, coarse aggregate, water etc. to
site including all charges for machine mixing and hire
charges of concrete mixer, laying concrete in foundations and
under flooring bed, ramming in 15 cm layers finishing top
surface to the required level curing etc.,and overheads &
contractors profit complete for finished item of work. (APSS
No. 402)

5 Filling with useful available excavated earth (excluding 59.00 One CUM #REF! #REF!
rock) with a lead of 50 m in trenches, sides of foundations
and basement with initial lead in layers not exceeding 15cm
thick, watering and ramming including cost and conveyance
of water to work site and all operaitonal, incidental, labour
charges, hire charges of T&P etc., and overheads &
contractors profit complete for fnished item of work (APSS
NO.309&310)

6 Filling with carted gravel in trenches,sides of foundations 98.10 One CUM #REF! #REF!
and basement with initial lead in layers not exceeding 15cm
thick,watering and ramming including cost and conveyance of
water to work site and all peraitonal,incidental, labour
charges,hire charges of T&P etc., and overheads &
contractors profit complete for fnished item of work(APSS
NO.309&310)

APMSIDC-Kadapa Canteen-Civil Abs 982of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
7 Supply and placing of the Design Mix Concrete M 25
grade corresponding to IS 456 with minimum cement
content of 380 kgs per 1 cum of concrete using weigh
batcher / mixer with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970
and IS 2386 Part 1 to Part 8) from approved quarry including
cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using steel scaffolding pipes , jack props ,
wallers , foot plates , brackets , steel centering plates
etc., including all operational, incidental and labour charges
such as weigh batching, machine mixing, lifting of concrete
manually, laying concrete, vibrating, curing etc., and
overheads & contractors profit complete but excluding cost of
steel and its fabrication charges for finished item of work
(APSS No. 402)

a) Footings 10.70 One CUM #REF! #REF!

b) Pedestals 2.60 One CUM #REF! #REF!

c) Plinth beams 4.30 One CUM #REF! #REF!

d) Tie beam 4.30 One CUM #REF! #REF!

8 Supply and placing of the Design Mix Concrete M 25


grade corresponding to IS 456 with minimum cement
content of 380 kgs per 1 cum of concrete using weigh
batcher / mixer with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970
and IS 2386 Part 1 to Part 8) from approved quarry including
cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden
reapers, runners, wood posts, wall plates etc., including
all operational, incidental and labour charges such as weigh
batching, machine mixing, lifting of concrete manually, laying
concrete, vibrating, curing , overheads & contractors profit
etc., complete but excluding cost of steel and its fabrication
charges for finished item of work (APSS No. 402)

a) Columns upto 3.66mts level


First Floor : 6.60 One CUM #REF! #REF!

b) 175mm thick RCC side wall


First Floor : 51.00 One SQM. #REF! #REF!

c) Roof beams @ 3.66mts level


First floor 4.60 One CUM #REF! #REF!

d) Roof Slab @ 3.66mt level


i) Slabs 125 mm thick for Roof Slabs
First floor 70.0 One SQM. #REF! #REF!

e) Lintels
First floor 1.20 One CUM #REF! #REF!

APMSIDC-Kadapa Canteen-Civil Abs 983of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
9 Supply and placing of the Design Mix Concrete M 25
grade corresponding to IS 456 with minimum cement
content of 380 kgs per 1 cum of concrete using weigh
batcher / mixer with 20mm size graded machine crushed
hard granite metal (coarse aggregate - as per IS 383 - 1970
and IS 2386 Part 1 to Part 8) from approved quarry including
cost and conveyance of all materials like cement, fine
aggregate (sand), coarse aggregate, water etc., to site,
centering using casurina ballies , bamboos , wooden
reapers , runners , wood posts , wall plates etc., for 60cm
wide sun-shades 7.5cm thick at fixed end and 5cm thick
at free end with an average thickness of 6.25cm including
all operational, incidental and labour charges such as weigh
batching, machine mixing, lifting of concrete manually, laying
concrete, curing, overheads & contractors profit complete
etc., but excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402, 403 & 903)

First Floor : 11.00 ONE RM #REF! #REF!

10 Brick masonry for panel walls in superstructure with CM


(1:8) prop: (Cement : Sand) using common burnt clay
bricks of class as per Table- I of IS:1077-1992, Non-
Modular or traditional size 23 x 11 x 7 cms from approved
source having minimum crushing strength of 40 Kg/Sqcm.
including cost and conveyance of all materials like cement,
screened sand, bricks, water etc., to site, labour charges, like
mixing cement mortar, scaffolding charges, constructing
masonry, lift charges, curing, etc.,and overheads &
contractors profit complete for finished item of work. (APSS
No. 501 & 504).

APMSIDC-Kadapa Canteen-Civil Abs 984of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
First Floor : 13.00 One CUM #REF! #REF!

11 Reinforced Brick Masonry for partition walls (11.0 cm


thick) in CM (1:4) prop. (Cement : Sand) using common
burnt clay bricks of class as per Table- I of IS:1077-1992,
Non- Modular or traditional size 23 x 11 x 7 cms from
approved source having minimum crushing strength of 40
Kg/Sq.cm and placing 2 Nos. of 6mm M.S plain rods in every
third layer with free ends of the reinforcement pegged into
mortar joints of main brick walls where applicable including
cost and conveyance of all materials like cement, steel, sand,
bricks, water etc., to site, all operational, incidental charges
such as labour charges for mixing cement mortar, scaffolding
charges, constructing masonry, lift charges, curing, etc., and
overheads & contractors profit but excluding cost of steel
and its fabrication charges complete for finished item of work.
(APSS No. of 501 & 509)

First Floor : 118.00 One SQM #REF! #REF!

12 Plain Cement Concrete (1:3:6) nominal mix using 20mm


size graded machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part
8) from approved quarry using concrete Mixer 10 / 7 cft (0.2 /
0.8 cum) capacity including cost and conveyance of all
materials like cement, fine aggregate(sand), coarse
aggregate, water etc. to site including all charges for machine
mixing, hire charges of concrete mixer, laying concrete in
position, curing etc., & lift charges , and overheads &
contractors profit for bed blocks & hold fasts for finished
item of work. (APSS No. 402)

For bed blocks and hold fasts


First Floor : 0.90 One CUM #REF! #REF!

13 Reinforced Cement Concrete M 20 nominal mix using


12mm size hard granite machine crushed graded metal
(coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1
to Part 8) from approved quarry, using a minimum quantity of
350 kgs. of cement per 1 cum of concrete using concrete
Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity including cost and
conveyance of all materials like cement, fine aggregate
(Sand), coarse aggregate, water etc., to site including
centering, shuttering, labour charges such as weigh batching,
machine mixing, hire charges of concrete mixer, laying
concrete, lift charges, curing etc., and overheads &
contractors profit complete for finished item of work (APSS
No. 402 & 403) for sill slabs.

First Floor : 0.20 One CUM #REF! #REF!

APMSIDC-Kadapa Canteen-Civil Abs 985of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
14 Reinforced Cement Concrete M 20 nominal mix using
12mm size hard granite machine crushed graded metal
(coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1
to Part 8) from approved quarry, using a minimum quantity of
350 kgs. of cement per 1 cum of concrete using concrete
Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity including cost and
conveyance of all materials like cement, fine aggregate
(Sand), coarse aggregate, water etc., to site including
centering, shuttering, labour charges such as weigh batching,
machine mixing, hire charges of concrete mixer, laying
concrete, lift charges, curing etc., and overheads &
contractors profit complete for finished item of work (APSS
No. 402 & 403) for platforms and shelves

a Platforms & Lofts


First Floor : 8.00 One SQM #REF! #REF!

b Shelves
First Floor : 5.00 One SQM #REF! #REF!

15 Providing Thermo Mechanically Treated (TMT) (Fe 500 /


Fe 500 D grade as per IS 1786-1979) of different
diameters for RCC works including labour charges for
straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials
and size and tying and lap-splicing with binding wire of 18
SWG, forming grills for reinforcement work as per approved
designs and drawings, including cost and conveyance of
steel bars, including all wastages such as overlaps,
couplings, chairs, spacer bars including cost and conveyance
of binding wire, cover blocks and all incidental, operational,
labour charges such as cutting, bending, placing in position,
tying etc., and overheads & contractors profit complete for
finished item of work.( APSS No.126)

First Floor : 5.60 One MT #REF! #REF!

16 Providing Mild steel (MS) steel bars (Fe 250 grade as per
IS 432) of different diameters including labour charges for
straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials
and size and tying and lap-splicing with binding wire of 18
SWG, forming grills for reinforcement work as per approved
designs and drawings, including cost and conveyance of
steel bars, including all wastages such as overlaps,
couplings, chairs, spacer bars including cost and conveyance
of binding wire, cover blocks and all incidental, operational,
labour charges such as cutting, bending, placing in position,
tying etc., and overheads & contractors profit complete for
finished item of work.( APSS No.126)

First Floor : 0.30 One MT #REF! #REF!

APMSIDC-Kadapa Canteen-Civil Abs 986of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
17 Ornamental ceiling plastering 12mm thick single coat in
CM (1:5) using screened sand including cost and
conveyance of all materials like cement, sand, water etc., to
site and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar,
finishing, curing as directed by Engineer-in-charge etc., and
overheads & contractors profit complete for finished item of
work.(SS 901,903 & 904)

First Floor : 62.00 One SQM. #REF! #REF!

18 Plastering 12mm thick in two coats using screened sand


with base coat of 8mm thick in CM (1:6) and top coat of 4mm
thick in CM (1:4) with dubara sponge finishing including cost
and conveyance of all materials like cement, sand, water etc.,
to site and all operational, incidental charges on materials
and including cost of all labour charges for mixing mortar,
finishing, scaffolding, lift charges, curing, including cutting
grooves as directed by Engineer - in - charge etc., and
overheads & contractors profit complete for finished item of
work. (SS 901,903 & 904) For Internal Walls

First Floor : 144.00 One SQM. #REF! #REF!

19 Plastering 20mm thick in two coats using screened sand


with base coat of 16mm thick in CM(1:6) and top coat of 4mm
thick in CM(1:4) with dubara sponge finishing including cost
and conveyance of all materials like cement, sand, water etc.,
to site and all operational, incidental charges on materials
and including cost of all labour charges for mixing mortar,
finishing, scaffolding, lift charges, curing, including cutting
grooves as directed by Engineer-in-charge etc., and
overheads & contractors profit complete for finished item of
work .(SS 901,903 & 904) for internal walls .

First Floor : 96.00 One SQM. #REF! #REF!

20 Plastering 20mm thick in two coats using screened sand


with base coat of 16mm thick in CM(1:6) and top coat of 4mm
thick in CM(1:4) with dubara sponge finishing including cost
and conveyance of all materials like cement, sand, water etc.,
to site and all operational, incidental charges on materials
and including cost of all labour charges for mixing mortar,
finishing, scaffolding, lift charges, curing, including cutting
grooves as directed by Engineer-in-charge etc., and
overheads & contractors profit complete for finished item of
work .(SS 901,903 & 904) for external walls .

First Floor : 168.00 One SQM. #REF! #REF!

21 Plastering 12mm thick single coat in CM(1:5) using


screened sand including cost and conveyance of all
materials like cement, sand, water etc., to site and all
operational, incidental charges on materials and including
cost of all labour charges for mixing mortar, finishing, curing
as directed by Engineer-in-charge etc., and overheads &
contractors profit complete for finished item of work.(SS
901,903 & 904) for basement

APMSIDC-Kadapa Canteen-Civil Abs 987of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
21.00 One SQM. #REF! #REF!

22 Providing impervious coat to exposed RCC roof slab


surfaces to required slopes with CM (1:3) prop. using
screened sand 20mm thick (average) mixed with integral
cement water proofing liquid confirming to IS: 2645-2003
manufactured by reputed manufacturers as approved by
Engineer-in-charge at 200ml per one bag of cement, laid over
roof slab when it is green, finished smooth with a floating coat
of neat cement and thread lining at regular intervals of
45cmx45cm including cost and conveyance of all materials
like cement, sand, water proofing compound, water etc., to
site, operational, incidental, and labour charges for mixing
mortar, laying, lift charges, rendering smooth and thread
lining, curing including rounding off junctions of wall and slab
etc., and overheads & contractors profit complete for finished
item of work. (APSS No. 901 & 903).

Over 1st Floor 70.00 One SQM. #REF! #REF!

23 Flooring with non-skid white full body Ceramic floor tiles


of size 300 mm x 300 mm and thickness between 7-8 mm 1st
quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1
to 15) of any colour and finish in all shades and designs as
approved by Engineer-in-charge, set over base coat of
cement mortar (1:8), 12mm thick using screened sand over
CC bed already laid or RCC roof slab, including neat cement
slurry of honey like consistency spread @ 3.3 Kgs per sqm &
jointed neatly with white cement paste to full depth mixed
with pigment of matching shade, including cost of all
materials like cement, screened sand , water and tiles etc.,
and overheads & contractors profit complete for finished item
of work. (APSS No.701 & 707) For Toilets

First Floor : 15.00 One SQM. #REF! #REF!

24 Flooring with non-skid Double charged / multi charged


stain free full body porcelain vitrified tiles with double
layer pigment of Size 600 x 600 mm and thickness between
8-10 mm 1st quality conforming to IS:13711, IS:13712,
IS:13630 (Parts 1 to 15) of any colour and finish in all shades
and designs with borders and design as per the approved
flooring pattern as directed by the Engineer-In -Charge,
laying tiles using spacers of 2mm thick, set over a base coat
of CM (1:8) prop. 12mm thick using screened sand over CC
bed already laid or RCC roof slab , including neat cement
slurry of honey like consistancy spread @ 3.3 kgs per sqm.
and jointed neately with white cement paste to full depth
mixed with pigment of matching shade including cost and
conveyance of all materials like cement, sand, water, tiles,
white cement etc., to site (excluding cost of C.C. bed)
including cost of base coat and all labour charges for
mixing of cement mortar, laying tiles to required slope as
directed by the Engineer- in-charge etc.,and overheads &
contractors profit complete for finished item of work. (APSS
No.701 & 707)

First Floor : 47.00 One SQM. #REF! #REF!

APMSIDC-Kadapa Canteen-Civil Abs 988of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
25 Flooring with 16 mm to 18 mm thick high polished
granite stone slabs black colour as approved by the
Engineer-in-Charge of length not less than 2.43 mts set over
base coat of cement mortar (1:8) , 20mm thick using
screened sand over CC bed already laid or RCC roof slab
including neat grey cement slurry of honey like consistency
spread @ 3.3 Kg per sqm and jointed neatly with white
cement paste mixed with pigment of matching shade to full
depth including cost and conveyance of all materials like
cement , sand , water , granite slabs etc., to work site and all
operational, incidental labour & lift charges, half rounding the
edge , polishing charges, cost of base coat and overheads &
contractors profit complete for finished item of work for
platforms (S.S.701 & special)

First Floor : 6.00 One SQM. #REF! #REF!

26 Providing 16 mm to 18 mm thick high polished leather


finish granite stone slabs (steel grey or pearl black) with
borders and design as per the pattern approved by the
Engineer-in-Charge of length not less than 2.43 mts set over
base coat of cement mortar (1:5) , 12mm thick using
screened sand over CC bed already laid or RCC roof slab
including neat grey cement slurry of honey like consistency
spread @ 3.3 Kg per sqm and jointed neatly with white
cement paste mixed with pigment of matching shade to full
depth including cost and conveyance of all materials like
cement , sand , water , granite slabs etc., to work site and all
operational, incidental labour & lift charges, full rounding the
edges of treads , polishing charges, cost of base coat and
overheads & contractors profit complete for finished item of
work for treads and risers (S.S.701 & special)

a Treads
First Floor : 2.10 One SQM. #REF! #REF!

b Risers
First Floor : 1.10 One SQM #REF! #REF!

27 Providing skirting 10 cm height with Double charged /


multi charged stain free full body porcelain vitrified tiles
with double layer pigment of Size 600 x 600 mm and
thickness between 8-10 mm of any colour and finish in all
shades and designs, length equal to flooring tiles, flushed to
wall surface to set over base coat of CM(1:5) 12 mm thick
using screened sand with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per sqm and
jointing with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials
like tiles, cement, sand and water etc.,and overheads &
contractors profit complete for finished item of work.(APSS
No.701 &707)
First Floor : 51.00 One RM #REF! #REF!

APMSIDC-Kadapa Canteen-Civil Abs 989of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
28 Providing dadooing with glazed white full body ceramic
wall tiles of size 200mm x 300 mm / 245 mm x 325 mm
and thickness 6 mm 1st quality conforming to IS:13711,
IS:13712, IS:13630 (Parts 1 to 15) of any colour and finish in
all shades and designs with borders as approved by
Engineer-in-Charge flushed to wall surface set over base
coat of CM(1:5) 12 mm thick using screened sand with
cement slurry of honey like consistency spread at the rate of
3.30 kgs per sqm and jointing with white cement paste mixed
with pigment of matching shade to full depth, including cost of
all materials like tiles, cement, sand and water etc., and
overheads & contractors profit complete for finished item of
work.

First Floor : 50.00 One SQM. #REF! #REF!

29 Supplying and fixing of stainless steel (grade 304) hand


railing as per approved drawing with top rail of 50mm dia
pipe and 2mm thick medium class and vertical posts of
25mm dia and 1.6mm thick medium class 1 No for each step
fixed with base plate of 75mm dia using bonding agent and
anchor fastner and welding, drilling of 25mm dia holes with
pneumatic compressor for fixing railing, buffing, polishing all
members of the railing thouroughly , lacquer finishing to
present seamless finish including cost and conveyance of all
materials, electrodes, welding charges, cost of all
consumables, labour charges , overheads & contractors profit
etc., complete for finished item of work. for all floors

First Floor : 2.00 One Sqm #REF! #REF!

30 Providing 110 mm Dia ISI marked PVC down water take


pipes with socket , 2.5mm thick 4.0 kg/sq.cm pressure of ISI
marked including cost of necessary PVC Bends, shoes, iron /
PVC clamps and all other accessories and fixing in position
including cost and conveyance of all materials, operational &
incidental charges including all labour charges for fixing at
site etc., and overheads & contractors profit complete for
finished item of work. (APSS No. 1328)

Terrace Floor : 9.00 One RM #REF! #REF!

31 Supply and fixing of doors as per approved drawings with


medium teak wood frame of section 100mm x 65 mm with
split type fan light of 500mm at the top fixed with 4mm
thick pin headed glass using 12mm x 12mm Teak Wood
beading and 2 Nos. of 10mm MS Square bars and ISI
marked flush door shutter of 30mm thick double shutters with
bond wood solid block board type core having cross bands
and face veneers, hot pressed bonded with water proof
phenol formaldehyde synthetic resin factory made
conforming to IS 2202-1991 (Part-I) both sides commercial
ply with internal lipping on all sides, fixing 1mm thick mat
finish laminated sheet to full width and height of the
flush shutter both sides

APMSIDC-Kadapa Canteen-Civil Abs 990of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
including cost and conveyance to site of teak wood frame,
flush shutter, laminate sheet including supply and fixing 6
Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm
including cost of ISI marked Alumimium fixtures of 6 Nos. butt
hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm
long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm dia at
top, 2 Nos. 150mm long handles (IS:208), 2 Nos. door
stoppers and 2 Nos. Rubber / Nylon door stop bushes
including fixing the fixtures to door with required number of
screws, bolt and nuts including labour charges for fixing the
frame in position, fixing the shutter to the frame, fixing glass
in fan light portion etc., including overheads & contractors
profit complete for finished item of work as per APSS 1001 &
1002 (The vertical frame of door shall be embedded in
flooring for a depth of not less than 10 mm) (1500mm x
2600mm)

First Floor : 3.90 One Sqm #REF! #REF!

32 Supply and fixing of doors as per approved drawings with


medium teak wood frame of section 100mm x 65 mm with
split type fan light of 500mm at the top fixed with 4mm thick
pin headed glass using 12mm x 12mm Teak Wood beading
and 2 Nos. of 10mm MS Square bars and ISI marked flush
door shutter of 30mm thick single shutter with bond wood
solid block board type core having cross bands and face
veneers, hot pressed bonded with water proof phenol
formaldehyde synthetic resin factory made conforming to IS
2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides, fixing 1mm thick mat finish laminated
sheet to full width and height of the flush shutter both
sides including cost and conveyance to site of teak wood
frame, flush shutter, laminate sheet including supply and
fixing

6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm


including cost of ISI marked Aluminium fixtures of 3 Nos. butt
hinges (IS:205) 150mm long , 1 No. aldrop (IS:2681) 300mm
long, 1 No. tower bolt (IS:204) of 200 mm x 10 mm dia at top,
2 Nos. 150mm long handles (IS:208), 1 No. door stopper and
1 No. Rubber / Nylon door stop bushes including fixing the
fixtures to door with required number of screws, bolt and nuts
including labour charges for fixing the frame in position, fixing
the shutter to the frame, fixing glass in fan light portion etc,
including overheads & contractors profit complete for finished
item of work as per APSS 1001 & 1002 (The vertical frame of
door shall be embedded in flooring for a depth of not less
than 10 mm) (900mm x 2600mm) .

First Floor : 2.34 One SQM. #REF! #REF!

APMSIDC-Kadapa Canteen-Civil Abs 991of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
33 Supplying and fixing single side prelam solid panel PVC
door frame (Choukhat): Providing and fixing factory made
Pac single side Prelam door frame of the size 50x7 mm with
a wall thickness of 5mm, made out of extruded 5mm rigid
Pac single side prelam sheet, meter cut at two corners and
joined with 2 Nos. of 150mm long brackets of 15 x 15mm MS
Square tube. The two vertical door profiles are to be
reinforced with 19 x 19mm MS. square tube of 19 guage. The
door frame shall be fixed to the wall using 65/100mm long
MS. Screws through the frame by using Pac fasteners. a
minimum of 4 Nos. of screws to be provided for each vertical
member and minimum 2nos. for horizontal member etc.
complete as per manufacture specification and direction of
Engineer-incharge including conveyance of all materials,
labour charges for fixing, overheads & contractors profit
complete for finished item of work.

First Floor : 35.00 One RM #REF! #REF!

34 Providing and fixing 30mm thick factory made moulded


door shutter- wood free consisting of frame made out of MS.
tubes 19gauge thickness and size of 25mmX25mm for styles,
top and bottom rails. MS. Frame shall have a coat of steel
primers. The inner panel shall consist of 25mm thick high
density EPS conforming to IS 4671-1984 bounded with 2mm
thick termite proof, water proof and fire resistant moulded
Pac sheet with 2,4,6 raised panel design in different plain
and / or pre-lam colours after routing to the moulded design
on one side and 2mm plain and / or pre-lam Pac sheet on
other side of the EPS. The edge of panel to be sealed with
lipping of 10mm wide PVC sheet bottom (made by sticking 2
rigid foam sheet of 5mm thickness using Pac solvent cement)
and stiles sides 25mm(5mmX5) thick and 30mm width Pac
sheet fitted along MS tube for lock provision for lock height
5mm thick Pac sheet of size 150mmX100mm fixed with
upper and lower face of inner side of EPS panel etc.,
complete as per direction of Engineer – in-Charge,
manufacture specification and drawing including ISI marked
Aluminium fixtures 3 Nos. butt hinges (IS:205) of 150mm
long, 1 No. aldrop (IS:2681) 250 mm long, 1 No. tower bolt
(IS:204) of 150 mm x 10mm dia, 2 Nos. 125mm long handles
(IS:208),1 No. Rubber / Nylon door stop bushes including
First Floor : 11.76 One SQM. #REF! #REF!

35 Providing and fixing factory made uPVC white colour


sliding glazed window comprising of uPVC multi-
chambered frame with in-built roller track and sash extruded
profiles duly reinforced with 1.60 ± 0.2 mm thick galvanized
mild steel section made from roll forming process of required
length (shape & size according to uPVC profile), appropriate
dimension of uPVC extruded glazing beads and uPVC
extruded interlocks, EPDM gasket, wool pile, zinc alloy (white
powder coated) touch locks with hook, zinc alloy body with
single nylon rollers (weight bearing capacity to be 40 kg), G.I
fasteners 100 x 8 mm size for fixing frame to finished wall
and necessary stainless steel screws etc. Profile of frame &
sash shall be mitred cut and fusion

APMSIDC-Kadapa Canteen-Civil Abs 992of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
welded at all corners, including drilling of holes for fixing
hardware's and drainage of water etc. After fixing frame the
gap between frame and adjacent finished wall shall be filled
with weather proof silicon sealent over backer rod of required
size and of approved quality, all complete as per approved
drawing & direction of Engineer-in-Charge inclusive of cost of
Single / double glass panes of 4mm thick pin headed glass,
wire mesh and silicon sealent . Note: For uPVC frame and
sash extruded profiles minus 5% tolerancein dimension i.e. in
depth & width of profile shall be acceptable.Variation in
profile dimension in higher side shall be accepted. But no
extra payment on this account shall be made.

Two track two panels sliding window made of frame 67 x


50 mm & sash 46 x 62 mm both having wall thickness of 2.3
± 0.2 mm and single glazing bead / double glazing bead of
appropriate dimension .
First Floor : 15.24 ONE SQM #REF! #REF!

36 Providing and fixing factory made uPVC white colour


fixed glazed windows / Ventilators comprising of uPVC
multi chambered frame and mullion (where ever required)
extruded profiles duly reinforced with 1.60± 0.2 mm thick
galvanized mild steel section made from roll forming process
of required length (shape & size according to uPVC profile),
uPVC extruded glazing beads of appropriate dimension,
EPDM gasket,G.I fasteners 100 x 8 mm size for fixing frame
to finished wall, plastic packers, plastic caps and necessary
stainless steel screws etc. Profileof frame shall be mitred cut
and fusion welded at all corners, mullion (if required) shall be
also fusion welded including drilling of holes for fixing
hardware and drainage of water etc.

After fixing frame the gap between frame and adjacent


finished wall shall be filled with weather proof silicon sealant
over backer rod of required size and of approved quality, all
complete as per approved drawing & direction of Engineer-in-
Charge inclusive of cost of Single / double glass panes and
silicon sealant. Note: For uPVC frame, sash and mullion
extruded profiles minus 5%tolerance in dimension i.e. in
depth & width of profile shall be acceptable.Variation in
profile dimension in higher side shall be accepted. But, no
extra payment on this account shall be made.

Fixed windows / Ventilators made of (small series) frame 47 x


50mm & mullion 47 x 68 mm both having wall thickness of
1.9 ±0.2 mm and single glazing bead of appropriate
dimension.
First Floor : 2.10 ONE SQM #REF! #REF!

37 Supplying and fixing of MS doors, grill to windows / in


open court yards using MS angles, flat, square bars including
cost and conveyance of all materials, cutting, bending,
welding, all operational charges, labour charges, overheads
and contractor profit etc., complete for finished item of work.
For All Floors

First Floor : 315.00 ONE KGS #REF! #REF!

APMSIDC-Kadapa Canteen-Civil Abs 993of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)
38 Supplying and fixing of two shutter cupboards as per
drawing with medium teak wood frames of size 75mm x
40mm and MDF Board Interior grade both sides laminated
18mm thick for shutters with 18mm x 12mm teak wood
beading alround and supplying and fixing powder coated MS
fixtures 3 Nos. butt hinges of size 100mm long(for each
shutter), tower bolt 2 Nos. of 100mm x 10mm, 2 Nos of
handles 100mm long and standard locking arrangements for
shutters including cost and conveyance of all materials to
site, labour charges, over heads and contractor profit etc.,
complete for finished item of work.

First Floor : 8.00 One SQM. #REF! #REF!

39 White washing two coats with white cement to ceiling to


give an even shade after thouroughly brushing the surface to
remove all dirt and remains of loose powdered materials
including cost of all materials , labour charges and incidental
such as scaffolding , lift charges etc., and overheads &
contractors profit complete for finished item of work in all
floors.

First Floor : 69.00 One SQM #REF! #REF!

40 Providing and applying Wall putty of White Cement or


Polymer or Cement based of average 1 to 2 mm thickness
over plastered surface to prepare the surface even and
smooth after thoroughly brushing the surface to remove all
dirt and remains of loose powdered materials, applying
emery paper, Sand the surface, clean & wipe off loose dust,
applying knifing paste filler by putty knife / muslin pad, air dry
for 2 - 3 hrs, sand with 180 and 320 No., emery paper for the
surface preparation including cost and conveyance of all
materials to work site and all operational, incidental, labour
charges, over heads and contractors profit etc., complete for
finished item of work in all floors for internal walls

First Floor : 252.00 One SQM. #REF! #REF!

40 Supply & application of one coat water based cement


primer of interior grade I and two coats of synthetic
polymer luxury plastic emulsion paint of superior grade
having VOC (Volatile Organic Compound) content less than
50 grams/litre for internal walls including cost and
conveyance of all materials to site, incidental, operational and
all labour charges etc., and overheads & contractors profit
complete for finished item of work in all floors.

First Floor : 252.00 One SQM. #REF! #REF!

41 Supply & application of one coat water based cement


primer of exterior grade II and two coats of synthetic
polymer luxury plastic emulsion paint of superior grade
having VOC (Volatile Organic Compound) content less than
50 grams/litre for exterior walls including cost and
conveyance of all materials to site, incidental, operational and
all labour charges etc., and overheads & contractors profit
complete for finished item of work in all floors.

First Floor : 196.00 One SQM. #REF! #REF!

APMSIDC-Kadapa Canteen-Civil Abs 994of 1048


Unit Rate Amount
Sl. No. Description of Work Quantity
(in words) In Figures (Rs.)

42 Painting two coats with synthetic enamel paint Grade-II


VOC (Volatile Organic Compound) content less than 50
grams/litre over primer coat of red oxide to new iron work
including cost and conveyance of all materials to site,
incidental, operational and all labour charges etc., and
overheads & contractors profit complete for finished item of
work in all floors. (SS No. 1201, 1212 & 1207).

First Floor : 21.00 One SQM. #REF! #REF!


Sub Total ::(Civil Works) #REF!

APMSIDC-Kadapa Canteen-Civil Abs 995of 1048


Detailed Estimate - Canteen
S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
1 Earth work Excavation
F1 8 1.750 1.750 1.800 44.10
F2 4 2.050 2.050 1.800 30.26
74.36
Say 75.00 Cum

2 PCC (1:4:8) for column footings


F1 8 1.750 1.750 0.150 3.68
F2 4 2.050 2.050 0.150 2.52
6.20
Say 7.00 Cum

3 PCC (1:5:10)
All round the Building 1 33.68 0.600 0.150 3.03
Deductions
Long Columns -10 0.380 0.600 0.150 -0.34
Under internal plinth beams
Horizontals
IPB1 - B1-B4 1 9.380 0.450 0.150 0.63
Ded for columns -2 0.230 0.450 0.150 -0.03
Ded for columns -2 0.300 0.450 0.150 -0.04
Secondary beams 2 2.695 0.450 0.150 0.36
Verticals
IPB1 - A2-B2, A3-B3 2 2.400 0.450 0.150 0.32
IPB2 - B2-C2, B3-C3 2 4.370 0.450 0.150 0.59
IPB1 - Secondary Beam 1 2.400 0.450 0.150 0.16
Under Flooring
Qty Same as ceramic flooring 14.792 0.100 1.48
Qty Same as Vitrified tile flooring 47.000 0.100 4.70
10.87
Say 11.00 Cum

4 Earth filling with available earth


Qty as per excavation 74.36 74.36
Deductions
a Qty as per PCC (1:4:8) -6.20
b Qty as per PCC (1:5:10) -11.0
c Qty as per footing -10.7
d Qty as per pedestals -2.59
Qty as per 175mm thick side Wall upto
f GL -8.89
g Qty as per columns upto Ground level -0.81
34.18 -40.18
34.18
Say 34.00 Cum

5 Basement Filling
Qty Same as ceramic flooring 14.792 2.000 29.58
Qty Same as Vitrified tile flooring 47.000 2.000 94.00
123.58
Say 124.00 Cum
6 Total Earth to be filled 157.58
Say 158.00 Cum

7 Available Excavated earth


80% of Eacavated eatrh 0.80 74.358 59.49
Say 59.00 Cum
8 Filling with carted gravel
98.10
Say 98.10 Cum

9 Antitermite treatment
69.97
Say 70.00 Sqm
10 175mm thick RCC side wall
a For Foundation
Alround the Building 1 33.68 1.700 57.26
Ded for columns -10 0.380 1.700 -6.46
50.80
Say 51.00 Sqm
11 VRCC M25 design mix
a) Footings
F1 8 1.600 1.600 0.275 5.63
F2 4 1.900 1.900 0.350 5.05
10.69
Say 10.70 Cum

b) Pedestals
F1 8 0.600 0.600 0.600 1.73
F2 4 0.600 0.600 0.600 0.86
2.59
Say 2.60 Cum

c) Plinth beams
Horizontals
EPB1 - A1-A4,C1-C4 2 9.380 0.230 0.300 1.29
Ded for columns -4 0.230 0.230 0.300 -0.06
Ded for columns -4 0.380 0.230 0.300 -0.10
IPB1 - B1-B4 1 9.380 0.230 0.300 0.65
Ded for columns -2 0.230 0.230 0.300 -0.03
Ded for columns -2 0.380 0.230 0.300 -0.05
Secondary beams 2 2.695 0.230 0.300 0.37
Verticals
EPB1 - A1-B1, A4-B4 2 2.260 0.230 0.300 0.31
IPB1 - A2-B2, A3-B3 2 2.400 0.230 0.300 0.33
EPB2 - B1-C1, B4-C4 2 4.300 0.230 0.350 0.69
IPB2 - B2-C2, B3-C3 2 4.370 0.230 0.350 0.70
IPB1 - Secondary Beam 1 2.400 0.230 0.300 0.17
4.27
Say 4.30 Cum
d) Tie beams
Qty same as plinth beam 4.27
Say 4.30 Cum
12 VRCC
i Columns upto G.L
C1/F1 3 0.230 0.380 0.800 0.21
C1/F2 1 0.230 0.380 0.725 0.06
C2/F1 5 0.230 0.380 0.800 0.35
C2/F2 3 0.230 0.380 0.725 0.19
12 0.81
Say 0.90 Cum

ii GL to Plinth top level


C1 4 0.230 0.380 2.000 0.70
C2 8 0.230 0.380 2.000 1.40
12 2.10
Say 2.10 Cum

Columns P.B Top to Roof slab


iii bottom
C1 4 0.230 0.380 3.475 1.21
C2 8 0.230 0.380 3.475 2.43
12 3.64
Say 3.70 Cum
Total Qty of Columns
i Upto G.L 0.81
ii From GL to Plinth level 2.10
iii Above plinth 3.64
6.56
Say 6.60 Cum

13 Roof beams
Horizontals
A1-A4 3 9.380 0.230 0.300 1.94
Ded for columns -6 0.230 0.230 0.300 -0.10
Ded for columns -6 0.380 0.230 0.300 -0.16
Secondary beams 2 2.695 0.230 0.300 0.37
Verticals
A1-C1 4 7.460 0.230 0.300 2.06
Ded for columns -6 0.230 0.230 0.300 0.10
Ded for columns -6 0.380 0.230 0.300 0.16
Secondary beams 1 2.400 0.230 0.300 0.17
4.54
Say 4.60 Cum

14 Roof slab
i) Roof Slab 125mm thick
Alround slab As per CAD 1 9.380 7.460 69.97
69.97
Say 70.00 Sqm

15 Lintels
above Entrance opening 1 2.745 0.230 0.175 0.11
D2 1 1.960 0.115 0.175 0.04
D3 1 1.360 0.115 0.175 0.03
D6 7 1.260 0.115 0.175 0.18
SW1 2 2.260 0.230 0.175 0.18
SW2 3 1.960 0.230 0.175 0.24
SW4 1 1.360 0.230 0.175 0.05
V 7 1.060 0.230 0.175 0.30
23 1.13
Say 1.20 Cum

16 Sunshades
SW1 2 2.100 4.20
SW2 3 1.800 5.40
SW4 1 1.200 1.20
10.80
Say 11.00 Rmt

17 Sill slabs
SW1 2 2.260 0.230 0.050 0.05
SW2 3 1.960 0.230 0.050 0.07
SW4 1 1.360 0.230 0.050 0.02
0.14
Say 0.20 cum

18 RCC M20 grade mix


i Lofts 50mm thick
Store 1 1.500 0.600 0.90
Kitchen 1 2.000 0.550 1.10
2.00
Say 2.00 Sqm

ii Platforms
Wash basin 2 1.980 0.600 2.38
Kitchen 1 4.185 0.600 2.51
Kitchen 1 2.000 0.550 1.10
5.99
Say 6.00 Sqm

iii Racks and shelves 25mm


Store 3 1 1.500 0.450 2.03
Kitchen 3 1 2.000 0.450 2.70
4.73
Say 5.00 Sqm

19 230 mm thick fly ash block masonary


Horizantal
Dining to Wash 1 9.380 0.230 3.175 6.85
Ded of Columns -2 0.230 0.230 3.175 -0.34
Ded of Columns -2 0.380 0.230 3.175 -0.55
Ded of Opening 1 1.490 0.230 1.800 -0.62
Vertical
WC to Dining 2 7.460 0.230 3.175 10.90
Ded of Columns -8 0.300 0.230 3.175 -1.75
Ded of Opening 1 1.430 0.230 1.800 -0.59
Entrance steps 1 2.285 0.900 0.150 0.31
Entrance steps 1 2.285 0.900 0.300 0.62
Entrance steps 1 2.285 0.900 0.450 0.93
Entrance steps 1 2.285 0.900 0.600 1.23
Deductions
SW1 -2 1.800 0.230 1.800 -1.49
SW2 -2 1.500 0.230 1.800 -1.24
SKW2 -1 1.500 0.230 1.400 -0.48
SKW4 -1 0.900 0.230 1.400 -0.29
V -7 0.600 0.230 0.500 -0.48
Lintels
SW1 -2 2.260 0.230 0.175 -0.18
SW2 -3 1.960 0.230 0.175 -0.24
SW4 -1 1.360 0.230 0.175 -0.05
V5 -7 1.060 0.230 0.175 -0.30
12.22
Say 13.00 Cum

20 115 mm thick brick walls


Horizontals
Store to Wash H 1 2.930 3.475 10.18
W.C 1 1.500 2.100 3.15
Ch.Room to Toilet 1 2.810 3.475 9.76
Dining 1 6.000 3.175 19.05
Ded of Columns -1 0.380 3.175 -1.21
WC to Toilet (front side) 1 9.380 3.175 29.78
Ded of Columns -2 0.380 3.175 -2.41
Ded of Columns -2 0.230 3.175 -1.46
Ded of Opening -1 2.285 3.175 -7.25
Verticals
WC to WC 1 2.630 3.475 9.14
Lobby 1 2.860 3.175 9.08
Ded of Columns -2 0.230 3.175 -1.46
Toilet V 1 1.200 3.475 4.17
Ch. Room to Toilet 1 7.000 3.175 22.23
Ded of Columns -1 0.230 3.175 -0.73
Ded of Opening -1 2.000 1.200 -2.40
between Store & Wash 1 1.500 3.475 5.21
Platform wall sides 3 0.600 0.900 1.62
Perapet wall alround 1 33.680 0.900 30.31
Deductions
D2 1 1.500 2.600 -3.90
D3 1 0.900 2.100 -1.89
D4 7 0.800 2.100 -11.76
Lintels
D2 1 1.960 0.175 -0.34
D3 1 1.360 0.175 -0.24
D4 7 1.260 0.175 -1.54
117.09
Say 118.00 Sqm

21 PCC (1:3:6) for Bedblocks


under lintels
D2 2 1 0.300 0.115 0.150 0.01
D3 2 1 0.300 0.115 0.150 0.01
D4 2 7 0.300 0.115 0.150 0.07
SW1 2 2 0.300 0.230 0.150 0.04
SW2 2 3 0.300 0.230 0.150 0.06
SW4 2 1 0.300 0.230 0.150 0.02
V5 2 7 0.300 0.230 0.150 0.14
Hold fasts
D2 6 1 0.230 0.115 0.150 0.02
D3 6 1 0.230 0.115 0.150 0.02
D4 6 7 0.230 0.115 0.150 0.17
SW1 4 2 0.230 0.230 0.150 0.06
SW2 4 3 0.230 0.230 0.150 0.10
SW4 4 1 0.230 0.230 0.150 0.03
V5 2 7 0.230 0.230 0.150 0.11
0.88
Say 0.90 Cum

22 TMT STEEL
Columns Footings 10.7 60.000 Kgs/Cu 641.16
Pedestals 2.6 100.000 Kgs/Cu 260.00
Plinth beams 4.27 110.000 Kgs/Cu 469.21
Tie beams 4.27 110.000 Kgs/Cu 469.21
175mm thick side walls 50.8 80.000 0.175 Kgs/Cu 711.14
Columns upto 3.60 mts levael 6.56 200.000 Kgs/Cu 1311.00
Roof Beams upto 3.60 mts level 4.6 200.000 Kgs/Cu 920.00
125mm thick slab 70.0 80.000 0.125 Kgs/Cu 699.75
Lintels 1 80.000 Kgs/Cu 96.00
5577.48
Say 5.60 MT

23 Mild Steel
Platforms 6 0.075 80.000 Kgs/Cu 36.00
Lofts 2 0.050 80.000 Kgs/Cu 8.00
Shelves 5 0.025 80.000 Kgs/Cu 10.00
Sunshades 0.6 11 0.063 80.000 Kgs/Cu 32.40
Sillslab 0.14 80.000 Kgs/Cu 10.82
RBM 118 2.000 Kgs/Sq 236.00
333.22
Say 0.30 MT

24 External plastering
All round 1 33.680 3.600 121.25
Terrace
All round 1 33.680 1.915 64.50
Deductions
SW1 -2 1.800 1.800 -6.48
SW2 -2 1.500 1.800 -5.40
SKW2 -1 1.500 1.400 -2.10
SW4 -1 0.900 1.400 -1.26
V5 -7 0.600 0.500 -2.10
168.41
Say 168.00 Sqm

25 Ceiling plastering
Qty Same as ceramic flooring 14.79
Qty Same as Vitrified tile flooring 47.00
61.79
Say 62.00 Sqm

26 Internal plastering 12 mm thick


Lobby 1 10.060 3.475 34.96
Dining hall 1 20.770 3.475 72.18
Store 1 5.400 3.475 18.77
Kitchen 1 13.990 3.475 48.62
WCs 2 5.500 3.475 38.23
Lobby 1 9.220 3.475 32.04
Ch. Room 1 4.790 3.475 16.65
Toilet 1 5.400 3.475 18.77
Wash 1 6.450 3.475 22.41
Dining hall beam sides 2 4.385 0.300 2.63
Deductions
D2 -1 1.500 2.600 -3.90
D3 -1 0.900 2.100 -1.89
D4 -7 0.800 2.100 -11.76
Ded for Dadooing with glazed tiles -49.29
238.39
Say 239.00 Sqm

a 12 mm thick internal plastering


60% of above quantity (internal) 143.04
Say 144.00 Sqm
b 20 mm thick Internal plastering
40% of above quantity (external) 95.36
Say 96.00 Sqm

27 Basement plastering
All round the Building 1 33.68 0.600 20.21
20.21
Say 21.00 Sqm

28 Flooring
a) Non skid Ceramic Tiles
WCs 2 1.500 1.250 3.75
Lobby 1 1.980 2.630 5.21
Ch. Room 1 1.195 1.200 1.43
Toilet 1 1.500 1.200 1.80
Wash area 1 1.610 1.615 2.60
14.79
Say 15.00 Sqm

c) Vitrified Tile Flooring 600x600


Lobby 1 2.285 2.745 6.27
Store 1 1.200 1.500 1.80
Dining hall 1 6.000 4.385 26.31
Kitchen 1 2.810 4.185 11.76
46.14
Say 47.00 Sqm

29 Skirting with Vitrified tiles


Lobby 1 10.060 10.06
Dining hall 1 20.770 20.77
Store 1 5.400 5.40
Kitchen 1 13.990 13.99
50.22
Say 51.00 Rmt
30 Dadooing with glazed tiles
WCs 2 5.500 1.500 16.50
Lobby 1 9.220 1.500 13.83
Ch. Room 1 4.790 1.500 7.19
Toilet 1 5.400 1.500 8.10
Wash area 1 6.450 1.500 9.68
Deductions
D4 -5 0.800 1.500 -6.00
49.29
Say 50.00 sqm

31 Polished Granite slab


i Treads
Entrance 1 3 2.285 0.300 2.06
2.06
Say 2.10 Sqm

ii Risers
Entrance 1 3 2.285 0.150 1.03
1.03
Say 1.10 Sqm

32 High polished granite Platforms


Qty same as Platforms 5.99
Say 6.00 Sqm

33 Whiting for ceiling


Same as ceiling plastering 61.79
Sunshades bottom 1 10.800 0.600 6.48
68.27
Say 69.00 Sqm

Plastic Emulsion Paint for interior


34 faces of walls
Same as internal plastering 238.39
Shelves sides(top and Bottom) 9.45
Loft sides(top and Bottom) 4.00
251.84
Say 252.00 Sqm

35 Wall putty
Same as internal plastering 238.39
Shelves sides(top and Bottom) 9.45
Loft sides(top and Bottom) 4.00
251.84
Say 252.00 Sqm

Plastic Emulsion Paint for external


36 plastering
Same as external plastering 168.41

Quantity same as basement plastering 20.21


Sunshades top 1 10.800 0.600 6.48
195.09
Say 196.00 Sqm
37 Painting to wood work
D2 2.24 1 1.500 2.600 8.74
D5 2.24 3 0.900 2.600 15.72
24.46
Say 25.00 Sqm

38 Painting to iron work


SW1 2 1.800 1.800 6.48
SW2 2 1.500 1.800 5.40
SKW2 1 1.500 1.400 2.10
SKW4 1 0.900 1.400 1.26
Wash 1 1.490 1.800 2.68
Wash 1 1.430 1.800 2.57
20.50
Say 21.00 Sqm
39 Wooden Doors
D2 1 1.500 2.600 3.90
Say 3.90 Sqm

D3 1 0.900 2.600 2.34


Say 2.34 Sqm

D4 (Frame) 7 5.000 35.00


Say 35.00 Rmt

D4 (Shutter) 7 0.800 2.100 11.76


Say 11.76 Sqm

40 Windows
SW1 2 1.800 1.800 6.48
6.48
Say 6.48 Sqm

SW2 2 1.500 1.800 5.40


5.40
Say 5.40 Sqm
SKW2 1 1.500 1.400 2.10
2.10
Say 2.10 Sqm

SKW4 1 0.900 1.400 1.26


1.26
Say 1.26 Sqm

41 Ventilators
V5 7 0.600 0.500 2.10
Say 2.10 Sqm

42 MS Grill to windows
SW1 2 1.800 1.800 6.48
SW2 2 1.500 1.800 5.40
SKW2 1 1.500 1.400 2.10
SKW4 1 0.900 1.400 1.26
Wash 1 1.490 1.800 2.68
Wash 1 1.430 1.800 2.57
20.50 Sqm
Say 315.00 Kgs

42 SS Railing
Entrance Steps wall 2 0.900 0.900 1.62
1.62
Say 2.00 Sqm

43 Cupboard
Store 1 1.500 2.100 3.15
Kitchen 1 2.000 2.100 4.20
7.35
Say 8.00 Sqm
44 Impervious coat
1 9.380 7.460 69.97
69.97
Say 70.00 Sqm

45 PVC Down take pipes

2 4.200 8.40
8.40
Say 9.00 RM
#REF!
ABSTRACT ESTIMATE FOR WATER SUPPLY & SANITARY ARRANGEMENTS
Sl. No. Description of Work Quantity Unit Rate

1 Supplying and laying, filling, jointing and testing SWG SP-1 pipe
conforming to ISI 651 & 4127 with air tight Cement joints in CM (1.5:1)
prop. including excavation of trenches and socket pits in any soil
(except rock requiring blasting) and refilling with watering and tamping
to the required slope including cost and conveyance of all materials to
site and all labour charges , overheads & contractor profit etc.,
complete for finished item of work (APSS NO 1301 & 1318)

152.40mm dia upto 1524.0mm (5') depth 50.00 Rmt #REF!

2 Supplying and fixing of SWG Gully traps 150mm x 100mm of ISI 5.00 NO #REF!
make confirming to IS 651 & 4127 with C.I grating & constructing
cement brick masonry in CM (1:6) prop., intermediate chamber and
fitted with 304.8 mm X 288.6 mm (12"x9") C.I Frame with hinged cover
of standard make as approved including cost and conveyance of all
materials to site, labour charges, overheads & contractors profit etc.,
complete for finished item of work.

3 Constructing 457.2 mm x 457.2 mm (1'6"x1'6") brick in CM 1:6 5.00 NO #REF!


prop. Masonry. Inspection chamber upto 914.4 mm (3'0") and fitted
with light weight 457.2 mm x 457.2 mm (1'6"x1'6") C.I frame and cover
of 20 Kg including cost and conveyance of all materials like cement,
sand, bricks, water etc., to site and all incidental and operational,
labour charges like mixing cement mortar, constructing masonry, lift
charges, curing , overheads & contractors profit etc., complete for
finished item of work as per Standard specification.

4 Constructing 904.0 mm (3’0”) dia brick masonry inspection 5.00 NO #REF!


chamber as per IS - 4111: Part-1:1986 with cement mortar (1:6) prop
using 2nd Class Clay Bricks of 225 mm thick from approved source
having a minimum crushing strength of 5 N/sq.mm including plastering
with cement mortar 1:3 prop; ½” thick both inside and outside fitted
with 20” dia RCC manhole covers and frames including excavating
pits up to a depth of 904 mm (3'-0") in all sorts of soils (exculding
rock) and laying cement conrete (1:4:8) 150 mm thick using 40 mm
HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as
per Standard specification and including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site and all incidental
and operational, labour charges like mixing cement mortar,
constructing masonry, lift charges, curing , overheads & contractors
profit etc., complete for finished item of work as per Standard
specification.

5 Supplying and fixing of 4" (101.6mm) multi floor trap with jali - 12.00 NO #REF!
UPVC/SWR pipe fittings as per site requirements with standard
practice for all floors including cost and conveyance of all materials to
site, labour charges , overheads & contractors profit etc., complete for
finished item of work..
6 Supplying and fixing European Water Closet of 1st quality 2.00 NO #REF!
conforming to IS:2556-Part-2-1973 of white glazed with 'S'
trap,supplying and fixing best Indian make plastic seat and lid for
European water closets with rubber or plastic Buffers as per IS 2548-
1996 and 10 litres capacity single flush PVC low level cistern with
internal components and fixed using required size of nails and screws,
angle stop cock 12.70mm dia. first quality Indian make heavy duty,
12mm PVC connections with brass union nuts CP coated including
cost and conveyance of all materials to site, overheads & contractors
profit etc., complete for finished item of work for all floors.

7 Supplying and fixing 580mm x 440mm long Orissa pan white 1.00 NO #REF!
glazed Water Closet 1st quality ISI marked confirming to IS:2556-Part-
3-1981 with "P" or "S" trap, ISI marked and providing masonry seat,
CC squatting plate and 10 litres capacity single flush PVC low level
cistern with internal components fixed on 2 Nos. of teak wood blocks of
size 76.20mm x 101.60mm using required size of nails, screws as
approved by Engineer-in-charge, angle stop cock 12.70mm dia. first
quality Indian make heavy duty, 12.70mm PVC connection with brass
union nuts CP coated , 31.75mm brass plumber union, P trap or S trap
of Indian W.C. shall be encased on CC (1:2:4) 150mm alround well
above the joint to stop leakage at the joint etc., complete including cost
and conveyance of all materials to site, cost of CC bed, labour
charges, overheads & contractors profit etc., complete for finished item
of work.

8 Supplying and fixing Indian make Flat Back Wash Hand Basin 1st 4.00 NO #REF!
quality conforming to IS:2556-Part-4:1972 of size 550mm x 400mm
with 32 mm nominal size C.P. Fitting with parallel pipe thread
conforming to IS:2963-1979 and fitted with 15 mm nominal bore
Chromium Plated Pillar Tap of 1st quality Indian make heavy duty
complete with standard CI brackets including wooden blocks ,1
No.12.70mm PVC connection with brass union nuts CP coated , angle
stop cock 12.70mm dia. first quality Indian make heavy duty, 31.75mm
dia. PVC flexible waste pipe 914.4mm length of 1st quality including
cost and conveyance of all materials to site, labour charges ,
overheads & contractors profit for finished item of work

9 Supplying and fixing NP soap dish heavy type of approved make ISI 4.00 NO #REF!
quality with NP screws etc., complete including cost and conveyance of
all materials, labour charges for fixing , overheads & contractors profit
for finished item of work in all floors

10 Supplying and fixing TV shape mirror with plastic frame of size 4.00 NO #REF!
609.6mm x 457.2mm , plywood back with NP screws 1st quality
including cost and conveyance of all materials, labour charges ,
overheads & contractors profit for finished item of work in all floors.

11 Supplying and fixing of 25.4mm dia , 609.6mm long aluminium 4.00 NO #REF!
anodized towel rods with brackets and aluminium screws including
cost and conveyance of all materials, labour charges , overheads &
contractors profit for finished item of work.
12 Supplying and fixing of stainless steel sink of size 508.00mm x 1.00 NO #REF!
457.2mm x 203.20mm, 1mm thick of Indian make fixed on cantilever
brackets including supply and fixing 31.75mm C.P. waste coupling,
31.75 mm dia PVC flexible waste pipe of 914.4 mm length of Ist
quality ncluding chiselling brick masonry wall and making good &
restoring to original surfaces , overheads & contractors profit complete
for finished item of work in all floors

13 Supplying and fixing NP bib taps of size 12.70mm dia of Indian 4.00 NO #REF!
make heavy duty (long body) as approved by the Engineer-In-
Charge including cost and conveyance of all materials, labour
charges , overheads & contractors profit complete for finished item of
work in all floors.

14 Supplying and fixing NP bib taps of size 12.70mm dia of Indian 4.00 NO #REF!
make heavy duty (short body) as approved by the Engineer-In-
Charge including cost and conveyance of all materials, labour
charges , overheads & contractors profit complete for finished item of
work in all floors.
15 Supply and fixing of Ashirvad/ Ajay/ Astral Flowguard or
equivalent CPVC Pipes and Fittings SDR 11 to meet the requirement
of ASTM-D 2846 and are produced in CTS (Copper Tube Sizes 1/2" to
2") for hot and cold water (IS 15778:2007) including cost and
conveyance of all materials to site, labour charges for fixing, overheads
& contractors profit complete for finished item of work at all floor levels

a) 15.90mm OD pipe 11.00 Rmt #REF!

b) 22.20mm OD pipe 42.00 Rmt #REF!

c) 28.60mm OD pipe 10.00 Rmt #REF!

d) 34.90mm OD pipe 35.00 Rmt #REF!

e) 41.30mm OD pipe 45.00 Rmt #REF!

16 Supplying and fixing Gunmetal Gate ( GM peet ) valve as per IS-


778 Class - I , Indian make heavy type including cost and conveyance
of all materials , labour charges , overheads & contractors profit
complete for finished item of work.
20mm Nominal bore 4.00 NO #REF!

25mm Nominal bore 2.00 NO #REF!

17 Supplying and fixing of SWR PVC pipes


(Prince/Sudhakar/Kisan/Supreme or any ISI brand) 4 Kg/Sq.cm. and
fixing all special such as plain bends, off sets, door bends, single
junctions, double junctions as per site requirement, fixing with PVC
clamps if necessary with required number of Bombay nails including
cost and conveyance of all materials to site, labour charges, overheads
& contractors profit complete for finished item of work at all floor levels.
(APSS No. 1302 1319 & 1326)

a) 75mmdia 20.00 Rmt #REF!

b) 110mmdia 10.00 Rmt #REF!

18 Construction of brick masonry support for GI pipe of size 25.00 NO #REF!


304.80mm x 228.60mm x 228.60 mm in CM (1:8) prop including
plastering and finishing with 12mm thick in CM (1:5) including cost and
conveyance of all materials and all labour charges, overheads &
contractors profit complete for finished item of work for all floors.

19 Providing and placing on terrace (at all floor levels)polyetheylene 1500.00 NO #REF!
water storage tank with double layer approved brand and
manufacture with cover and suitable locking arrangement and making
necessary holes for inlet and outlets and over flow pipes but without
fittings and base support for tanks including cost and conveyance of
all materials and labour charges , overheads & contractors profit
complete for finished item of work.

Sub Total (WS): 1809.00


ENTS
Amount
(Rs.)

#REF!

#REF!

#REF!

#REF!

#REF!
#REF!

#REF!

#REF!

#REF!

#REF!

#REF!
#REF!

#REF!

#REF!
#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!
#REF!

Detailed Estimate for water supply and Arrangements


Sl.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
External Sewerage
1 Supply, Laying, Jointing SWG line
a) SWG PIPE
4" dia SWG line(100mm Dia) 50 50
Say 50 Rmt

2 Gully traps 5
Say 5 Nos

3 Inspection Chambers 5
Say 5 Nos

4 Manholes
3' - 0' Depth 5
Say 5 Nos

Internal sewerage system


5 Floor Traps
Ground Floor 12 12
Say 12 Nos

6 Indian IWC
Ground Floor 1 1
Say 1 Nos

7 European EWC
Ground Floor 2 2
Say 2 Nos

8 Wash hand basins


Ground Floor 4 4
Say 4 Nos

9 Soap dish
Ground Floor 4 4
Say 4 Nos
10 Mirrors
Ground Floor 4 4
Say 4 Nos

11 Towel rods
Ground Floor 4 4
Say 4 Nos

12 Sink
Ground Floor 1 1
Say 1 Nos

13 NP bib taps
a) Long Body taps (Bath& wash Taps)
Ground Floor 4 4
Say 4 Nos
b) Long Body taps (Drinking water Taps)
Ground Floor 4 4
Say 4 Nos

ASHIRVAD / AJAY / ASTRAL CPVC Pipes


14
a) 15.90mm OD pipe
EWC
Ground Floor 2 0.75 1.50

IWC
Ground Floor 2 0.3 0.60

TAPS
Long Body taps (Bath & wash Taps)
Ground Floor 3 0.9 2.70

Long Body Taps (Drinking water Taps )

Ground Floor 4 0.9 3.60

Wash Basin
Ground Floor 3 0.8 2.40
10.80 Rmt
Say 11 Rmt

b) 22.20mm OD pipe(Domestic water)


Internal Connection
Ground Floor 1 20.0 20
20
Say 20 Rmt
c) 22.20mm OD pipe (Drinking water)
Internal Connection
Ground Floor 1 10.0 10
10
Say 10 Rmt

Drinking water Downtake Pipes


d) 22.20mm OD pipe
Down Take pipes 1 3.00 3.0
3.0
Say 3.0 Rmt

Domestic water Downtake Pipes


e) 22.20mm OD pipe
Down Take pipes 3 3.00 9.0
9.0
Say 9.0 Rmt

15 SWR PVC pipes


a) 75mm dia
Internal Connections
Ground Floor 1 20 20.0
20.00
Say 20.00 Rmt
b) 110 mm dia down take pipe
Internal Connections
Ground Floor 1 10 10.0
10.00
Say 10.00 Rmt

16 CPVC Pipes
Terrace Ring Main
DOMESTIC WATER
a) 40.00 mm OD 45.00 Rmt
b) 32.00 mm OD 35.00 Rmt
c) 28.60 mm OD 10.00 Rmt

17 Gun Metal Valves


20mm Dia 4 No's

25mm Dia 2 No's

18 HDPE Tank
Domestic water 1000 Litrs
Drinking water 500 Litrs

19 Construction of brick masonry support 25 No's


ABSTRACT ESTIMATE FOR AMBULANCE GARAGE

Sl.No. Description of Work Quantity Unit Rate


1 Earth work excavation for foundations (Mechanical Means) for 1 33.00 ONE CUM #REF!
buildings in ordinary soils and depositing on bank for all lifts and
with an initial lead of 10m and up to 3m depth including all
operational,incidental, labour charges such as shoring, sheeting,
planking, strutting etc., and overheads & contractors profit complete
for finished item of work excluding dewatering charges etc., as per
SS 20 B(APSS 308)

2 Plain Cement Concrete (1:4:8) (cement: fine aggregate: Coarse 1 3.00 ONE CUM #REF!
aggregate) for foundations using coarse aggregate 40mm size
hard , machine crushed granite from approved quarry using
concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity including cost and
conveyance of all materials like cement, sand, coarse aggregate,
water etc. to site including all charges for machine mixing and hire
charges of concrete mixer, laying concrete in foundations and under
flooring bed, ramming in 15 cm layers finishing top surface to the
required level curing etc.,and overheads & contractors profit
complete for finished item of work. (APSS No. 402) For Foundation

3 Plain Cement Concrete (1:5:10) (cement: fine aggregate: Coarse 1 8.00 ONE CUM #REF!
aggregate) for foundations and under flooring bed using coarse
aggregate 40mm size hard , machine crushed granite from
approved quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity including cost and conveyance of all materials like cement,
sand, coarse aggregate, water etc. to site including all charges for
machine mixing and hire charges of concrete mixer, laying concrete
in foundations and under flooring bed, ramming in 15 cm layers
finishing top surface to the required level curing etc.,and overheads
& contractors profit complete for finished item of work. (APSS No.
402)

4 Filling with useful available excavated earth (excluding rock) with 1 26.00 ONE CUM #REF!
a lead of 50 m in trenches, sides of foundations and basement with
initial lead in layers not exceeding 15cm thick, watering and
ramming including cost and conveyance of water to work site and all
operaitonal, incidental, labour charges, hire charges of T&P etc.,
and overheads & contractors profit complete for fnished item of work
(APSS NO.309&310)

5 Filling with carted gravel in trenches,sides of foundations and 1 73.00 ONE CUM #REF!
basement with initial lead in layers not exceeding 15cm
thick,watering and ramming including cost and conveyance of water
to work site and all peraitonal,incidental, labour charges,hire
charges of T&P etc., and overheads & contractors profit complete
for fnished item of work(APSS NO.309&310)

APMIDC-Kadapa Garage Building - Civil - Abs 1017 of 1048


Sl.No. Description of Work Quantity Unit Rate
6 Supply and placing of the Design Mix Concrete M 25 grade
corresponding to IS 456 with minimum cement content of 380
kgs per 1 cum of concrete using weigh batcher / mixer with 20mm
size graded machine crushed hard granite metal (coarse aggregate
- as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved
quarry including cost and conveyance of all materials like cement,
fine aggregate (sand) coarse aggregate, water etc., to site,
centering using steel scaffolding pipes , jack props , wallers ,
foot plates , brackets , steel centering plates etc., including all
operational, incidental and labour charges such as weigh batching,
machine mixing, lifting of concrete manually, laying concrete,
vibrating, curing etc., and overheads & contractors profit complete
but excluding cost of steel and its fabrication charges for finished
item of work (APSS No. 402)

a) Footings 1 3.65 ONE CUM #REF!

b) Column Pedastals 1 1.00 ONE CUM #REF!

c) Plinth Beams 1 2.90 ONE CUM #REF!

d) Tie Beam 1 2.90 ONE CUM #REF!

7 Supply and placing of the Design Mix Concrete M 25 grade


corresponding to IS 456 with minimum cement content of 380
kgs per 1 cum of concrete using weigh batcher / mixer with 20mm
size graded machine crushed hard granite metal (coarse aggregate
- as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved
quarry including cost and conveyance of all materials like cement,
fine aggregate (sand) coarse aggregate, water etc., to site,
centering using casurina ballies, bamboos, wooden reapers,
runners, wood posts, wall plates etc., including all operational,
incidental and labour charges such as weigh batching, machine
mixing, lifting of concrete manually, laying concrete, vibrating, curing
, overheads & contractors profit etc., complete but excluding cost of
steel and its fabrication charges for finished item of work (APSS No.
402)

a) Columns :
1st Floor : 1 4.00 ONE CUM #REF!

b) Lintels
1st Floor : 1 0.80 ONE CUM #REF!

c) 175mm thick RCC side wall


1st Floor : 1 45.00 ONE SQM #REF!

APMIDC-Kadapa Garage Building - Civil - Abs 1018 of 1048


Sl.No. Description of Work Quantity Unit Rate
8 Supply and placing of the Design Mix Concrete M 25 grade
corresponding to IS 456 with minimum cement content of 380
kgs per 1 cum of concrete using weigh batcher / mixer with 20mm
size graded machine crushed hard granite metal (coarse aggregate
- as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved
quarry including cost and conveyance of all materials like cement,
fine aggregate (sand) coarse aggregate, water etc., to site,
centering using steel scaffolding pipes , jack props , wallers ,
foot plates , brackets , steel centering plates etc., including all
operational, incidental and labour charges such as weigh batching,
machine mixing, lifting of concrete manually, laying concrete,
vibrating, curing , overheads & contractors profit etc., complete but
excluding cost of steel and its fabrication charges for finished item of
work (APSS No. 402)

a) Roof Beams un supported height up to 4.27 m:


1st Floor : 1 3.00 ONE CUM #REF!

b) ROOF SLABS :
i) Slabs 125 mm thick upto an un-supported height of 4.27m
1st Floor : 1 51.00 ONE SQM #REF!

9 Supply and placing of the Design Mix Concrete M 25 grade


corresponding to IS 456 with minimum cement content of 380
kgs per 1 cum of concrete using weigh batcher / mixer with 20mm
size graded machine crushed hard granite metal (coarse aggregate
- as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved
quarry including cost and conveyance of all materials like cement,
fine aggregate (sand), coarse aggregate, water etc., to site,
centering using casurina ballies , bamboos , wooden reapers ,
runners , wood posts , wall plates etc., for 60cm wide sun-shades
7.5cm thick at fixed end and 5cm thick at free end with an
average thickness of 6.25cm including all operational, incidental
and labour charges such as weigh batching, machine mixing, lifting
of concrete manually, laying concrete, curing, overheads &
contractors profit complete etc., but excluding cost of steel and its
fabrication charges for finished item of work (APSS No. 402, 403 &
903)

1st Floor : 1 4.00 ONE RM #REF!

10 Brick masonry for panel walls in superstructure with CM (1:8)


prop: (Cement : Sand) using common burnt clay bricks of class
as per Table- I of IS:1077-1992, Non- Modular or traditional size 23
x 11 x 7 cms from approved source having minimum crushing
strength of 40 Kg/Sqcm. including cost and conveyance of all
materials like cement, screened sand, bricks, water etc., to site,
labour charges, like mixing cement mortar, scaffolding charges,
constructing masonry, lift charges, curing, etc.,and overheads &
contractors profit complete for finished item of work. (APSS No. 501
& 504).

1st Floor : 1 19.00 ONE CUM #REF!

APMIDC-Kadapa Garage Building - Civil - Abs 1019 of 1048


Sl.No. Description of Work Quantity Unit Rate
11 Reinforced Brick Masonry for partition walls (11.0 cm thick) in
CM (1:4) prop. (Cement : Sand) using common burnt clay bricks
of class as per Table- I of IS:1077-1992, Non- Modular or traditional
size 23 x 11 x 7 cms from approved source having minimum
crushing strength of 40 Kg/Sq.cm and placing 2 Nos. of 6mm M.S
plain rods in every third layer with free ends of the reinforcement
pegged into mortar joints of main brick walls where applicable
including cost and conveyance of all materials like cement, steel,
sand, bricks, water etc., to site, all operational, incidental charges
such as labour charges for mixing cement mortar, scaffolding
charges, constructing masonry, lift charges, curing, etc., and
overheads & contractors profit but excluding cost of steel and its
fabrication charges complete for finished item of work. (APSS No. of
501 & 509)

1st Floor : 1 27.00 ONE SQM #REF!

12 Plain Cement Concrete (1:3:6) nominal mix using 20mm size


graded machine crushed hard granite metal (coarse aggregate - as
per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved
quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
including cost and conveyance of all materials like cement, fine
aggregate(sand), coarse aggregate, water etc. to site including all
charges for machine mixing, hire charges of concrete mixer, laying
concrete in position, curing etc., & lift charges , and overheads &
contractors profit for bed blocks & hold fasts for finished item of
work. (APSS No. 402)

1st Floor : 1 0.50 ONE CUM #REF!

13 Providing Thermo Mechanically Treated (TMT) (Fe 500 / Fe 500


D grade as per IS 1786-1979) of different diameters for RCC
works including labour charges for straightening, cutting, bending to
required sizes and shapes, placing in position with cover blocks of
approved materials and size and tying and lap-splicing with binding
wire of 18 SWG, forming grills for reinforcement work as per
approved designs and drawings, including cost and conveyance of
steel bars, including all wastages such as overlaps, couplings,
chairs, spacer bars including cost and conveyance of binding wire,
cover blocks and all incidental, operational, labour charges such as
cutting, bending, placing in position, tying etc., and overheads &
contractors profit complete for finished item of work.( APSS No.126)

1st Floor : 1 3.50 ONE MT #REF!

14 Providing Mild steel (MS) steel bars (Fe 250 grade as per IS 432)
of different diameters including labour charges for straightening,
cutting, bending to required sizes and shapes, placing in position
with cover blocks of approved materials and size and tying and lap-
splicing with binding wire of 18 SWG, forming grills for reinforcement
work as per approved designs and drawings, including cost and
conveyance of steel bars, including all wastages such as overlaps,
couplings, chairs, spacer bars including cost and conveyance of
binding wire, cover blocks and all incidental, operational, labour
charges such as cutting, bending, placing in position, tying etc., and
overheads & contractors profit complete for finished item of work.
( APSS No.126)

1st Floor : 1 0.10 ONE MT #REF!

APMIDC-Kadapa Garage Building - Civil - Abs 1020 of 1048


Sl.No. Description of Work Quantity Unit Rate
15 Ornamental ceiling plastering 12mm thick single coat in CM
(1:5) using screened sand including cost and conveyance of all
materials like cement, sand, water etc., to site and all operational,
incidental charges on materials and including cost of all labour
charges for mixing mortar, finishing, curing as directed by Engineer-
in-charge etc., and overheads & contractors profit complete for
finished item of work.(SS 901,903 & 904)

1st Floor : 1 45.00 ONE SQM #REF!

16 Plastering 12mm thick in two coats using screened sand with


base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in CM
(1:4) with dubara sponge finishing including cost and conveyance of
all materials like cement, sand, water etc., to site and all operational,
incidental charges on materials and including cost of all labour
charges for mixing mortar, finishing, scaffolding, lift charges, curing,
including cutting grooves as directed by Engineer - in - charge etc.,
and overheads & contractors profit complete for finished item of
work. (SS 901,903 & 904) For Internal Walls

1st Floor : 1 109.00 ONE SQM #REF!

17 Plastering 20mm thick in two coats using screened sand with


base coat of 16mm thick in CM(1:6) and top coat of 4mm thick in
CM(1:4) with dubara sponge finishing including cost and
conveyance of all materials like cement, sand, water etc., to site and
all operational, incidental charges on materials and including cost of
all labour charges for mixing mortar, finishing, scaffolding, lift
charges, curing, including cutting grooves as directed by Engineer-
in-charge etc., and overheads & contractors profit complete for
finished item of work .(SS 901,903 & 904) for external walls .

1st Floor : 1 165.00 ONE SQM #REF!

18 Plastering 12mm thick single coat in CM(1:5) using screened 1 17.00 ONE SQM #REF!
sand including cost and conveyance of all materials like cement,
sand, water etc., to site and all operational, incidental charges on
materials and including cost of all labour charges for mixing mortar,
finishing, curing as directed by Engineer-in-charge etc., and
overheads & contractors profit complete for finished item of work.
(SS 901,903 & 904) for basement

19 Providing impervious coat to exposed RCC roof slab surfaces to


required slopes with CM (1:3) prop. using screened sand 20mm
thick (average) mixed with integral cement water proofing liquid
confirming to IS: 2645-2003 manufactured by reputed
manufacturers as approved by Engineer-in-charge at 200ml per one
bag of cement, laid over roof slab when it is green, finished smooth
with a floating coat of neat cement and thread lining at regular
intervals of 45cmx45cm including cost and conveyance of all
materials like cement, sand, water proofing compound, water etc., to
site, operational, incidental, and labour charges for mixing mortar,
laying, lift charges, rendering smooth and thread lining, curing
including rounding off junctions of wall and slab etc., and overheads
& contractors profit complete for finished item of work. (APSS No.
901 & 903).

Over 1st Floor : 1 51.00 ONE SQM #REF!

APMIDC-Kadapa Garage Building - Civil - Abs 1021 of 1048


Sl.No. Description of Work Quantity Unit Rate
20 RCM facia 50mm thick in CM(1:3) using screened sand for drop
walls, fins with rabbit wire mesh & nomianl reinforcement as
directred by Engineer - In - Charge with dubara sponge
finishing,including cost and conveyance of all materials to site,
operationals &incidental,cost and conveyance of cement, wire mesh
water to work site, centering, scaffolding and form work,lift charges
etc., and overheads & contractors profit complete for finished item of
work but excluding cost of steel and its fabrication charges for
finished item of work(APSS NO.403&903)

1st Floor : 1 2.00 ONE SQM #REF!

20 Granolithic Concrete flooring 20 mm thick with (1:1:2), using


6mm to 12 mm size hard granite machine crushed metal and
screened sand laid over CC bed already laid or RCC roof slab, in
alternate panels of size not exceeding 1.50 m x 1.50 m, using glass
strips and finishing the top surface to required smoothness and
slopes and thread lining including cost of all materials like cement,
metal sand and water and overheads & contractors profit complete
for finished item of work. (APSS No.701 & 710)

1st Floor : 1 50.00 ONE SQM #REF!

21 Providing 110 mm Dia ISI marked PVC down water take pipes 1 11.00 ONE RM #REF!
with socket , 2.5mm thick 4.0 kg/sq.cm pressure of ISI marked
including cost of necessary PVC Bends, shoes, iron / PVC clamps
and all other accessories and fixing in position including cost and
conveyance of all materials, operational & incidental charges
including all labour charges for fixing at site etc., and overheads &
contractors profit complete for finished item of work. (APSS No.
1328)

22 Providing and fixing factory made uPVC white colour sliding


glazed window comprising of uPVC multi-chambered frame with in-
built roller track and sash extruded profiles duly reinforced with 1.60
± 0.2 mm thick galvanized mild steel section made from roll forming
process of required length (shape & size according to uPVC profile),
appropriate dimension of uPVC extruded glazing beads and uPVC
extruded interlocks, EPDM gasket, wool pile, zinc alloy (white
powder coated) touch locks with hook, zinc alloy body with single
nylon rollers (weight bearing capacity to be 40 kg), G.I fasteners 100
x 8 mm size for fixing frame to finished wall and necessary stainless
steel screws etc. Profile of frame & sash shall be mitred cut and
fusion

welded at all corners, including drilling of holes for fixing hardware's


and drainage of water etc. After fixing frame the gap between frame
and adjacent finished wall shall be filled with weather proof silicon
sealent over backer rod of required size and of approved quality, all
complete as per approved drawing & direction of Engineer-in-
Charge inclusive of cost of Single / double glass panes of 4mm thick
pin headed glass, wire mesh and silicon sealent . Note: For uPVC
frame and sash extruded profiles minus 5% tolerancein dimension
i.e. in depth & width of profile shall be acceptable.Variation in profile
dimension in higher side shall be accepted. But no extra payment on
this account shall be made.

Two track two panels sliding window made of frame 67 x 50 mm


& sash 46 x 62 mm both having wall thickness of 2.3 ± 0.2 mm and
single glazing bead / double glazing bead of appropriate dimension .

APMIDC-Kadapa Garage Building - Civil - Abs 1022 of 1048


Sl.No. Description of Work Quantity Unit Rate
1st Floor : 1 12.00 ONE SQM #REF!

23 Supply & fixing of Rolling shutter made of 80 x 1.25 mm machine


rolled CRCA laths, interlocked together through their entire length
and jointed together at the ends by end-locks, mounted on specially
designed pipe shaft of 50mm dia nominal bore MS B class pipe with
brackets, plates, guide channels, stoppers, bottom locking plates
and arrangements for inside & outside locking with push-pull
operations including cost of hood cover and springs complete,
painted with one coat of approved steel primer, locks, ball bearings,
all accessories etc., overheads & contractors profit complete for
finished item of work as per special spn: 1108

1st Floor : 1 9.00 ONE SQM #REF!

24 White washing two coats with white cement to ceiling to give an


even shade after thouroughly brushing the surface to remove all dirt
and remains of loose powdered materials including cost of all
materials , labour charges and incidental such as scaffolding , lift
charges etc., and overheads & contractors profit complete for
finished item of work in all floors.

1st Floor : 1 45.00 ONE SQM #REF!

25 Supply & application of one coat water based cement primer of


interior grade I and two coats of synthetic polymer luxury
plastic emulsion paint of superior grade having VOC (Volatile
Organic Compound) content less than 50 grams/litre for internal
walls including cost and conveyance of all materials to site,
incidental, operational and all labour charges etc., and overheads &
contractors profit complete for finished item of work in all floors.

1st Floor : 1 110.00 ONE SQM #REF!

26 Supply & application of one coat water based cement primer of


exterior grade II and two coats of synthetic polymer luxury
plastic emulsion paint of superior grade having VOC (Volatile
Organic Compound) content less than 50 grams/litre for exterior
walls including cost and conveyance of all materials to site,
incidental, operational and all labour charges etc., and overheads &
contractors profit complete for finished item of work in all floors.

1st Floor : 1 182.00 ONE SQM #REF!

26 Painting two coats with synthetic enamel paint Grade-II VOC


(Volatile Organic Compound) content less than 50 grams/litre over
primer coat of red oxide to new iron work including cost and
conveyance of all materials to site, incidental, operational and all
labour charges etc., and overheads & contractors profit complete for
finished item of work in all floors. (SS No. 1201, 1212 & 1207).

1st Floor : 1 27.00 ONE SQM #REF!

TOTAL :

APMIDC-Kadapa Garage Building - Civil - Abs 1023 of 1048


T ESTIMATE FOR AMBULANCE GARAGE
Amount
(Rs.)
#REF!

#REF!

#REF!

#REF!

#REF!

APMIDC-Kadapa Garage Building - Civil - Abs 1024 of 1048


Amount
(Rs.)

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

APMIDC-Kadapa Garage Building - Civil - Abs 1025 of 1048


Amount
(Rs.)

#REF!

#REF!

#REF!

#REF!

APMIDC-Kadapa Garage Building - Civil - Abs 1026 of 1048


Amount
(Rs.)

#REF!

#REF!

#REF!

#REF!

APMIDC-Kadapa Garage Building - Civil - Abs 1027 of 1048


Amount
(Rs.)

#REF!

#REF!

#REF!

#REF!

#REF!

APMIDC-Kadapa Garage Building - Civil - Abs 1028 of 1048


Amount
(Rs.)

#REF!

#REF!

#REF!

APMIDC-Kadapa Garage Building - Civil - Abs 1029 of 1048


Amount
(Rs.)
#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

APMIDC-Kadapa Garage Building - Civil - Abs 1030 of 1048


Detailed Estimate - AMBULANCE GARRAGE
S.NO DESCRIPTION NOS L(M) B(M) D(M) QUANTITY
Earth work excavation by Machinary
1 up to 3.0m
F1 8 1.500 1.500 1.800 32.40

32.40
Say 33.00 Cum

2 PCC (1:4:8) for column footings


For Column Footings
F1 8 1.500 1.500 0.150 2.70
2.70
Say 3.00 Cum

3 PCC (1:5:10)
All round the Building 1 28.92 0.600 0.150 2.60
Deductions
C1 -8 0.230 0.600 0.150 -0.17
Under Flooring
Qty same as Granolithic Flooring 1 50.000 0.100 5.00
7.44
Say 8.00 Cum

4 Earth filling with available earth


Qty as per excavation 33.000 33.00
Deductions
a Qty as per PCC (1:4:8) -2.700
b Qty as per PCC (1:5:10) -8.000
c Qty as per footing -3.645
d Qty as per Pedestals -0.972
d Qty as per RCC Wall upto GL -7.819
e Qty as per columns upto Ground level -0.500
9.364 -23.64
9.36
Say 10.00 Cum
5 Basement Filling
Qty same as Granolithic Flooring 1 44.320 2.000 88.64
88.64
Say 89.00 Cum

6 Total Earth to be Filled


Basement filling 88.64
Quantity same as filling sides of
foundation and Plinth 10.00
98.64
Say 99.00 Cum

7 Filling with Available Earth 0.80 32.400 25.92


Say 26.00 Cum

8 Filling with Carted Gravel 73.00


Say 73.00 Cum

9 175mm thick RCC side wall


All round the Building 1 28.92 1.650 47.72
Deductions
C1 -8 0.230 1.650 -3.04
44.68
Say 45.00 Sqm

10 VRCC M25 design mix


a) Footings
F1 8 1.350 1.350 0.250 3.65
3.65
Say 3.65 Cum
b) Pedastrals
F1 8 0.450 0.450 0.600 0.97
0.97
Say 1.00 Cum

c) Plinth beams
Horizontals
IPB2 - A1-A2, D1-D2 2 6.140 0.230 0.350 0.99
Ded for columns -4 0.300 0.230 0.350 -0.10
B1-B2, C1-C2 2 6.140 0.230 0.350 0.99
Ded for columns -4 0.300 0.230 0.350 -0.10
Verticals
A1-D1, A2-D2 2 8.460 0.230 0.300 1.17
Ded for columns -8 0.230 0.230 0.300 -0.13
2.82
Say 2.90 Cum

d) Tie beams
Quantity same as plinth beam 2.82
Say 2.90 Cum

11 VRCC
i Columns upto GL
C1/F1 8 0.230 0.300 0.800 0.44
8 0.44
Say 0.50 Cum

ii GL to Plinth top level


C1 8 0.230 0.300 2.000 1.10
8 1.10
Say 1.20 Cum

Columns P.B Top to Roof slab


iii bottom
C1 8 0.230 0.300 4.375 2.42
8 2.42
Say 2.50 Cum
Total Qty of Columns
i Upto G.L 0.44
ii From GL to Plinth level 1.10
iii Above plinth 2.42
3.96
Say 4.00 Cum
12 Roof Beams @3.6 Mts Level
Horizontal
A1-A2,B1-B2,C1-C2,D1-D2 4 6.140 0.230 0.380 2.15
Ded for columns -8 0.300 0.230 0.380 -0.21
Verticals
A1-D1, A2-D2 2 8.460 0.230 0.300 1.17
Ded for columns -8 0.230 0.230 0.300 -0.13
2.98
Say 3.00 Cum

13 Roof slab
i) Roof Slab 125mm thick
A1-A2 X A1-D1 1 6.000 8.460 50.76
50.76
Say 51.00 Sqm

14 Lintels
R/S 1 3.460 0.230 0.175 0.14
V2 8 1.960 0.230 0.175 0.63
8 0.77
Say 0.80 Cum
15 Sun-Shade
R/S 1 3.600 3.60
Say 4.00 RM

16 230 mm thick brick masonary


Horizantals 2 6.140 0.230 3.995 11.28
Ded for col -4 0.300 0.230 3.995 -1.10
Verticals 2 8.460 0.230 4.075 15.86
Ded for col -8 0.230 0.230 4.075 -1.72
Deductions
R/S -1 3.000 0.230 3.000 -2.07
V2 -8 1.500 0.230 1.000 -2.76
Lintels
V2 -8 1.960 0.230 0.175 -0.63
R/S -1 3.460 0.230 0.175 -0.14
18.71
Say 19.00 Cum

17 110 mm brick walls


Parapet wall 1 28.92 0.900 26.03
26.03
Say 27.00 Sqm

18 PCC (1:3:6) for Bedblocks


under lintels
V2 2 8 0.300 0.230 0.150 0.17
R/S 2 1 0.300 0.230 0.150 0.02
Hold fasts
V2 4 8 0.230 0.230 0.150 0.25
R/S 6 1 0.230 0.230 0.150 0.05
0.49
Say 0.50 Cum
19 TMT STEEL
Columns Footings 4 50.000 Kgs/Cum 182.25
Columns Pedestals 0.97 100.000 Kgs/Cum 97.20
Plinth beams 3 125.000 Kgs/Cum 353.05
Tie beams 3 125.000 Kgs/Cum 353.05
175mm thick side walls 45 70.000 0.175 Kgs/Cum 547.35
Columns upto 3.60 mts levael 4 225.000 Kgs/Cum 891.14
Roof Beams upto 3.60 mts level 3 180.000 Kgs/Cum 540.00
125mm thick Roof slab 51 70.000 0.125 Kgs/Cum 446.25
Sunshade 0.6 4 80.000 0.063 Kgs/Cum 10.80
Lintels 1 80.000 Kgs/Cum 64.00
3485.09
Say 3.50 MT
20 Mild Steel
RBM 27 2.000 Kgs/Sqm 54.00
RCM facia 2 3.000 Kgs/Sqm 6.00
60.00
Say 0.10 MT

21 External plastering
All round the Building 1 28.92 4.500 130.14
Terrace
Parapet wall 1 28.92 1.915 55.38
Deductions
V2 -8 1.500 1.000 -12.00
R/S -1 3.000 3.000 -9.00
164.52
Say 165.00 Sqm
22 Ceiling plastering
Qty Same as Granolithic flooring 44.32
44.32
Say 45.00 Sqm
23 Internal plastering 12 mm thick
alround the room 1 27.080 4.375 118.48
Deductions
R/S -1 3.000 3.000 -9.00
109.48
Say 109.00 Sqm

24 Basement plastering
All round the Building 1 28.92 0.600 17.35
17.35
Say 17.00 Sqm
25 Flooring
a) Granolithic Flooring
Ambulance garrage 1 5.540 8.000 44.32
44.32
Say 45.00 Sqm

b) Granolithic Flooring
Ramp 1 3.600 1.200 4.32
4.32
Say 5.00 Sqm
c) Impervious Coat
Terrace 1 6.000 8.460 50.76
50.76
Say 51.00 Sqm
26 Whiting for ceiling
Same as ceiling plastering 44.32
Say 45.00 Sqm

Plastic Emulsion Paint for interior


27 faces of walls
Same as internal plastering 109.48
Say 110.00 Sqm

Plastic emulsion paint for external


28 plastering
Same external plastering 164.52

Quantity same as basement plastering 17.35


181.87
Say 182.00 Sqm

29 Painting to iron woork


R/S 3 1 3.000 3.000 27.00
27.00
Say 27.00 Sqm

R/S 1 1 3.000 3.000 9.00


9.00
Say 9.00 Sqm
30 V2
8 1.500 1.000 12.00 Sqm

31 RCM Drop
R/S 1 4.200 0.450 1.89
1.89
Say 2.00 Sqm

32 PVC down take pipe 2 5.100 10.20


10.20
Say 11.00 Rmt
#REF!

ABSTRACT ESTIMATE FOR INTERNAL CC ROAD


Rate
Unit Amount
Sl. No. Description of Work Quantity In
(in words) (Rs.)
Figures
1 #REF! 32.00 CUM ONE CUM #REF! #REF!

2 Providing, Laying, Spreading and compacting graded 1088.00 CUM ONE CUM #REF! #REF!
HBG/HBG crushed stone aggregate to Wet Mix
macadem specification including cost of all materials
and including premixing the material with water at
OMC in Mechanical mix plant carriage of mixed
material by tipper to site , laying in uniform layers
with paver in base courses on well prepared surface
and compacting with Vibratory roller to acheive the
desired density etc., as directed by the Engineer-in-
Charge and as per MoRT&H specification.406 (5th
revision) for finished item of work. (Payment based
on levels for finished item of work)

3 Construction of Granular sub-base by providing 1814.00 CUM ONE CUM #REF! #REF!
HBG material confirming to Grading - III of MORT
& H Table 400-2 including cost and conveyance of
all material to woek site and spreading in uniform
layers with motor grader or by approved means, on
prepared surface mixing by mix place method with
Rotavator/ approved means, at OMC and
compacting with vibratory roller to achieve the
desired density etc., complete for finished item of
work as per MoRT& H specification 401 (4th revision)
and as directed by the Engineer- in - charge
(Payment will be made based on levels for finished
item of work)

4 Plain Cement Concrete (1:4:8) (cement: fine 777.00 CUM One CUM #REF! #REF!
aggregate: Coarse aggregate) for foundations
using coarse aggregate 40mm size hard , machine
crushed granite from approved quarry using
concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
including cost and conveyance of all materials like
cement, sand, coarse aggregate, water etc. to site
including all charges for machine mixing and hire
charges of concrete mixer, laying concrete in
foundations and under flooring bed, ramming in 15
cm layers finishing top surface to the required level
curing etc.,and overheads & contractors profit
complete for finished item of work. (APSS No. 402)
for DLC
Rate
Unit Amount
Sl. No. Description of Work Quantity In
(in words) (Rs.)
Figures
5 Plain Cement Concrete (1:5:10) (cement: fine 17.00 CUM ONE CUM #REF! #REF!
aggregate: Coarse aggregate) for foundations and
under flooring bed using coarse aggregate 40mm
size hard , machine crushed granite from approved
quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity including cost and conveyance of all
materials like cement, sand, coarse aggregate, water
etc. to site including all charges for machine mixing
and hire charges of concrete mixer, laying concrete
in foundations and under flooring bed, ramming in 15
cm layers finishing top surface to the required level
curing etc.,and overheads & contractors profit
complete for finished item of work. (APSS No. 402)

6 Plain Cement Concrete M 20 nominal mix using 312.00 CUM ONE CUM #REF! #REF!
20mm size graded machine crushed hard granite
metal (coarse aggregate - as per IS 383 - 1970 and
IS 2386 Part 1 to Part 8) from approved quarry using
concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
including cost and conveyance of all materials like
cement, fine aggregate(sand), coarse aggregate,
water etc. to site including all charges centering,
labour charges such as weigh batching, machine
mixing, hire charges of concrete mixer, laying
concrete in position, curing etc., & lift charges , and
overheads & contractors profit for Kerb stone &
Sasur Drains for finished item of work. (APSS No.
402)

7 Construction of un-reinforced, dowel jointed at 1451.00 CUM ONE CUM #REF! #REF!
expansion and construction joint only, plain cement
concrete pavement, thickness as per design, over a
prepared sub base, with 43 grade cement or any
other type as per Clause 1501.2.2 M30 (Grade),
coarse and fine aggregates conforming to IS : 383,
maximum in a concrete mixer of not less than 0.2
cum capacity and appropeiate weigh batcher using
approved mix design, laid in approved fixed side
formwork (steel channel, laying and fixing of 125
mictron thick polythene film, wedges, steel plates
including levelling the formwork as per drawing),
spreading the concrete with sholvels, rakes,
compacted using needle, scareed and plate vibrators
and finished in continuous operation including
provision of contraction and expansion, construction
joints, applying debonding strips, primer, sealant,
dowel bars, near approaches to bridge / culvert and
construction joints, admixtures as approved, curing of
concrete slabs for 14- days, curing compound (where
specified) and water finishing to lines and grade as
per drawing and Technical Specification Clause
1501 MORD.
Rate
Unit Amount
Sl. No. Description of Work Quantity In
(in words) (Rs.)
Figures

8 Plastering 12mm thick single coat in CM(1:5) using 4326.00 SQM ONE SQM #REF! #REF!
screened sand including cost and conveyance of all
materials like cement, sand, water etc., to site and all
operational, incidental charges on materials and
including cost of all labour charges for mixing mortar,
finishing, curing as directed by Engineer-in-charge
etc., and overheads & contractors profit complete for
finished item of work.(SS 901,903 & 904)

9 Supply and placing of the Design Mix Concrete M 25 89.00 SQM ONE SQM #REF! #REF!
grade corresponding to IS 456 with minimum cement
content of 380 kgs per 1 cum of concrete using
weigh batcher / mixer with 20mm size graded
machine crushed hard granite metal (coarse
aggregate - as per IS 383 - 1970 and IS 2386 Part 1
to Part 8) from approved quarry including cost and
conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to
site, centering using casurina ballies, bamboos,
wooden reapers, runners, wood posts, wall plates
etc., including all operational, incidental and labour
charges such as weigh batching, machine mixing,
lifting of concrete manually, laying concrete,
vibrating, curing , overheads & contractors profit etc.,
complete but excluding cost of steel and its
fabrication charges for finished item of work (APSS
No. 402) For 230mm thick Retaing wall

10 Providing Thermo Mechanically Treated (TMT) (Fe 2.00 MT ONE MT #REF! #REF!
500 / Fe 500 D grade as per IS 1786-1979) of
different diameters for RCC works including labour
charges for straightening, cutting, bending to
required sizes and shapes, placing in position with
cover blocks of approved materials and size and
tying and lap-splicing with binding wire of 18 SWG,
forming grills for reinforcement work as per approved
designs and drawings, including cost and
conveyance of steel bars, including all wastages
such as overlaps, couplings, chairs, spacer bars
including cost and conveyance of binding wire, cover
blocks and all incidental, operational, labour charges
such as cutting, bending, placing in position, tying
etc., and overheads & contractors profit complete for
finished item of work.( APSS No.126)
Rate
Unit Amount
Sl. No. Description of Work Quantity In
(in words) (Rs.)
Figures
11 Flooring with chequered Cement Concrete heavy 125.00 SQM ONE SQM #REF! #REF!
duty tiles conforming to IS: 13801 using aggregates,
cement, pigments of size 300mm x 300 mm and
thickness 25 mm of any shades as approved by
Engineer - In - Charge set over base coat of cement
mortar (1:6), 12 mm thick using screened sand over
CC bed alredy laid or RCC roof slab including neat
cement slurry of honey like consistency spread @
3.3 kgs per sqm and jointed with neat white cement
to full depth mixed with pigment of matching shade
including cost and conveyance of all materials like
cement, sand, water and tiles etc.,and overheads &
contractors profit complete for finished item of work.

#REF!
#REF!

Detailed Estimate for CC Road


S.NO DESCRIPTION NOS L B D QUANTITY
1a Length of Road with Central Median

Part- II -
Type-I(6.0m road with central median )
1 84.610 84.61
Add for variations 4.23
88.84
Say 89.00 RM
1b Type-II (6.0m road)
Part- I
alround the Parking area 1 328.510 328.51
Part- II
along compound wall towards 1 116.610 116.61
Attendants Dormitory
along Attendants Dormitory to 1 91.720 91.72
Hospital Bldg
along Hospital Bldg 1 90.470 90.47
along Hospital Bldg to DG Room 1 151.140 151.14

Add for variations 38.00


816.45
Say 816.00 RM
Type-III(4.5m road )
Part- I -
alround the Parking area 1 273.770 273.77
Add for variations 13.69
287.46
Say 287.00 RM
2 250mm thick GSB
6.0m Road with central median 2 89.000 6.00 0.250 267.00
6.0m Road 1 816.000 6.00 0.250 1224.00
4.5m Road 1 287.000 4.50 0.250 322.88
1813.88
Say 1814.00 Cum
3 150mm thick WMM
6.0m Road with central median 2 89.000 6.00 0.150 160.20
6.0m Road 1 816.000 6.00 0.150 734.40
4.5m Road 1 287.000 4.50 0.150 193.73
1088.33
Say 1088.00 Cum
4 100 mm thick -PCC(DLC)
6.0m Road with central median 2 89.000 6.00 0.100 106.80
6.0m Road 1 816.000 6.00 0.100 489.60
4.5m Road 1 287.000 4.50 0.100 129.15
725.55
Say 726.00 Cum

DET - Road : Page : 1040


S.NO DESCRIPTION NOS L B D QUANTITY
5 200 mm thick -M30 Grade concrete for CC Roads
6.0m Road with central median 2 89.000 6.00 0.200 213.60
6.0m Road 1 816.000 6.00 0.200 979.20
4.5m Road 1 287.000 4.50 0.200 258.30
1451.10
Say 1451.00 Cum
KERB STONE
6 Earth work excavation for Kerb
6.0m Road with central median 2 89.000 0.25 0.400 17.80
6.0m Road 2 816.000 0.25 0.400 163.20
4.5m Road 2 287.000 0.25 0.400 57.40
238.400
Say 238.00 Cum
7 Disposal of unuseful excavated earth(at 5m
distance)
Disposal of earth 1 238.400 0
Say 0.00 Cum
8 PCC (1:4:8)
Under kerb stone
6.0m Road with central median 2 89.000 0.25 0.075 3.34
6.0m Road 2 816.000 0.25 0.075 30.60
4.5m Road 2 287.000 0.25 0.075 10.76
Under VPCC Wall
6.0m Road with central median 2 89.000 0.45 0.075 6.01
50.71
Say 51.00 Cum
9 Kerb stone
6.0m Road with central median 2 89.000 0.15 0.750 20.03
6.0m Road 2 816.000 0.15 0.750 183.60
4.5m Road 2 287.000 0.15 0.750 64.58
268.20
Say 268.00 Cum

DET - Road : Page : 1041


S.NO DESCRIPTION NOS L B D QUANTITY
10 Saucer drain
Area of saucer drain 0.017 Sqm
6.0m Road with central median 4 89.000 0.017 6.05
6.0m Road 2 816.000 0.017 27.74
4.5m Road 2 287.000 0.017 9.76
43.55
Say 44.00 cum
11 Plastering to Kerb wall
6.0m Road with central median 2 89.000 1.650 293.70
6.0m Road 2 816.000 1.650 2692.80
4.5m Road 2 287.000 1.650 947.10
3933.60
Say 3934.00 SQM
12 Painting to Kerb wall
6.0m Road with central median 2 89.000 1.650 293.70
6.0m Road 2 816.000 1.650 2692.80
4.5m Road 2 287.000 1.650 947.10
3933.60
Say 3934.00 SQM
FOOTPATH
13 PCC (1:5:10)
6.0m Road with central median 2 89.000 0.70 0.075 9.35
9.35
Say 9.00 SQM
14 Pavement Tiles for foot path
6.0m Road with central median 2 89.000 0.70 124.60
124.60
Say 125.00 SQM

DET - Road : Page : 1042


S.NO DESCRIPTION NOS L B D QUANTITY
MEDIAN
15 Earth work excavation
6.0m Road with central median 2 89.000 0.45 0.400 32.04
32.04
Say 32.00 Cum
16 Disposal of unuseful excavated earth (at 5m distance)
Disposal of earth 1 32.040 32.04
Say 32.00 Cum
17 PCC (1:5:10)
6.0m Road with central median 2 89.000 0.45 0.100 8.01
8.01
Say 8.00 Cum
18 V.P.C.C.(1:3:6)
6.0m Road with central median 2 89.000 0.25 1.000 44.50
44.50
Say 45.00 Cum
19 12mm thick single coat plastering

6.0m Road with central median 2 89.000 2.200 391.60


391.60
Say 392.00 Cum
20 Painting to V.P.C.C
6.0m Road with central median 2 89.000 2.200 391.60
391.60
Say 392.00 Cum
21 Filling with gravel
6.0m Road with central median 2 89.000 6.00 1.000 1068.00
6.0m Road 1 816.000 6.00 1.000 4896.00
4.5m Road 1 287.000 4.50 1.000 1291.50
7255.50
Say 7256.00 Cum

DET - Road : Page : 1043


S.NO DESCRIPTION NOS L B D QUANTITY
1 Disposal of soil
32.04
0.00
32.04
Say 32.00 cum
1 230mm thick retaining wall
6.0m Road with central median 1 89.000 1.000 89.00
89.00
Say 89.00 Sqm
2 HYSD STEEL
230mm thick side walls 0.23 89.000 110.00 Kg/cum 2251.70 Kgs
2.25 MT
Say 2.00 MT

DET - Road : Page : 1044


#REF!

Detailed Estimate for Storm water drain


S.NO DESCRIPTION NOS L B D QUANTITY

1 Storm water drain


SD2
900
Say 900.00 RM
2 Earth work excavation
SD2 1 900.00 0.800 0.625 450.000
450.000
Say 450.00 Cum

3 PCC(1:3:6)
SD2 1 900.00 0.800 0.075 54.000
54.000
Say 54.00 Cum
4 RCC M25 grade
Drain bottom
SD2 1 900.00 0.650 0.100 58.500
58.500
Say 59.00 Cum

5 RCC M25 grade


100mm thick Drain side walls
SD2 2 900.00 0.450 810.000
810.000
Say 810.00 Sqm

6 100mm thick Precast slabs


SD2 1 900.00 0.650 585.000
585.000
Say 585.00 Sqm

7 TMT STEEL
Drain bottom 58.5 50.00 Kgs/Cum 2925.00
100mm thick drain side walls 810.0 80.00 0.100 Kgs/Cum 6480.00
100mm thick precast slab 585.0 60.00 0.100 Kgs/Cum 3510.00
12915.00
Say 13.00 MT
ABSTRACT ESTIMATE FOR SEPTIC TANK 100 USERS

S.No Description Quantity Unit Rate Amount

1 Earth work excavation for foundations (Mechanical Means) for 71.00 Cum 86.00 6106
buildings in ordinary soils and depositing on bank for all lifts and
with an initial lead of 10m and up to 3m depth including all
operational,incidental, labour charges such as shoring, sheeting, planking,
strutting etc., and overheads & contractors profit complete for finished
item of work excluding dewatering charges etc., as per SS 20 B(APSS
308)

2 Plain Cement Concrete (1:5:10) (cement: fine aggregate: Coarse 3.30 Cum 3401.00 11223
aggregate) for foundations and under flooring bed using coarse
aggregate 40mm size hard , machine crushed granite from approved
quarry using concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity including
cost and conveyance of all materials like cement, sand, coarse aggregate,
water etc. to site including all charges for machine mixing and hire
charges of concrete mixer, laying concrete in foundations and under
flooring bed, ramming in 15 cm layers finishing top surface to the required
level curing etc.,and overheads & contractors profit complete for finished
item of work. (APSS No. 402)

3 Filling with useful available excavated earth (excluding rock) with a 15.00 Cum 25.00 375
lead of 50 m in trenches, sides of foundations and basement with initial
lead in layers not exceeding 15cm thick, watering and ramming including
cost and conveyance of water to work site and all operaitonal, incidental,
labour charges, hire charges of T&P etc., and overheads & contractors
profit complete for fnished item of work (APSS NO.309&310)

3 Supply and placing of the Design Mix Concrete M 25 grade


corresponding to IS 456 with minimum cement content of 380 kgs per
1 cum of concrete using weigh batcher / mixer with 20mm size graded
machine crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry including cost
and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site, centering using steel scaffolding pipes ,
jack props , wallers , foot plates , brackets , steel centering plates
etc., including all operational, incidental and labour charges such as
weigh batching, machine mixing, lifting of concrete manually, laying
concrete, vibrating, curing etc., and overheads & contractors profit
complete but excluding cost of steel and its fabrication charges for
finished item of work (APSS No. 402)

a Base slab 8.60 Cum 7596.00 65326

4 Supply and placing of the Design Mix Concrete M 25 grade


corresponding to IS 456 with minimum cement content of 380 kgs per
1 cum of concrete using weigh batcher / mixer with 20mm size graded
machine crushed hard granite metal (coarse aggregate - as per IS 383 -
1970 and IS 2386 Part 1 to Part 8) from approved quarry including cost
and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site, centering using casurina ballies,
bamboos, wooden reapers, runners, wood posts, wall plates etc.,
including all operational, incidental and labour charges such as weigh
batching, machine mixing, lifting of concrete manually, laying concrete,
vibrating, curing , overheads & contractors profit etc., complete but
excluding cost of steel and its fabrication charges for finished item of work
(APSS No. 402)

a Roof slab 125 mm thick 25.00 Sqm 1038.00 25950

APMSIDC- KADAPA ABS-Septic tank 1046 of 1048


S.No Description Quantity Unit Rate Amount

b 150 mm thick side walls 6.00 SQM 2273.00 13638

c 275 mm thick side walls 53.00 SQM 3221.00 170713

5 Providing Thermo Mechanically Treated (TMT) (Fe 500 / Fe 500 D grade 2.20 MT 55353.00 121777
as per IS 1786-1979) of different diameters for RCC works including
labour charges for straightening, cutting, bending to required sizes and
shapes, placing in position with cover blocks of approved materials and
size and tying and lap-splicing with binding wire of 18 SWG, forming grills
for reinforcement work as per approved designs and drawings, including
cost and conveyance of steel bars, including all wastages such as
overlaps, couplings, chairs, spacer bars including cost and conveyance of
binding wire, cover blocks and all incidental, operational, labour charges
such as cutting, bending, placing in position, tying etc., and overheads &
contractors profit complete for finished item of work.( APSS No.126)

6 Plastering 20mm thick single coat in CM(1:5) using screened sand 12.00 Sqm 269.00 3228
including cost and conveyance of all materials like cement, sand, water
etc., to site and all operational, incidental charges on materials and
including cost of all labour charges for mixing mortar, finishing, curing as
directed by Engineer-in-charge etc., and overheads & contractors profit
complete for finished item of work . (SS 901,903 & 904)

7 Providing impervious coat to exposed RCC roof slab surfaces of 95.00 Sqm 273.00 25935
sump , sump side wall,sump bottom slab,in side of septic tank , in
sunken slabs etc. to required slopes with CM (1:3) prop. using screened
sand 12mm thick mixed with integral cement water proofing liquid
confirming to IS: 2645-2003 manufactured by reputed manufacturers as
approved by Engineer-in-charge at 200ml per one bag of cement, laid
over roof slab when it is green, finished smooth with a floating coat of neat
cement and thread lining at regular intervals of 45cmx45cm where ever
necessary including cost and conveyance of all materials like cement,
sand, water proofing compound, water etc., to site, operational, incidental,
and labour charges for mixing mortar, laying, lift charges, rendering
smooth and thread lining, curing including rounding off junctions of wall
and slab etc., and overheads & contractors profit complete for finished
item of work. (APSS No. 901 & 903).

8 Providing impervious coat to exposed RCC roof slab surfaces to 25.00 Sqm 377.00 9425
required slopes with CM (1:3) prop. using screened sand 20mm thick
(average) mixed with integral cement water proofing liquid confirming to
IS: 2645-2003 manufactured by reputed manufacturers as approved by
Engineer-in-charge at 200ml per one bag of cement, laid over roof slab
when it is green, finished smooth with a floating coat of neat cement and
thread lining at regular intervals of 45cmx45cm including cost and
conveyance of all materials like cement, sand, water proofing compound,
water etc., to site, operational, incidental, and labour charges for mixing
mortar, laying, lift charges, rendering smooth and thread lining, curing
including rounding off junctions of wall and slab etc., and overheads &
contractors profit complete for finished item of work. (APSS No. 901 &
903).

APMSIDC- KADAPA ABS-Septic tank 1047 of 1048


S.No Description Quantity Unit Rate Amount

9 RCM facia 50mm thick in CM(1:3) using screened sand for drop walls, fins 3.00 Sqm 1317.00 3951
with rabbit wire mesh & nomianl reinforcement as directred by Engineer -
In - Charge with dubara sponge finishing,including cost and conveyance
of all materials to site, operationals &incidental,cost and conveyance of
cement, wire mesh water to work site, centering, scaffolding and form
work,lift charges etc., and overheads & contractors profit complete for
finished item of work but excluding cost of steel and its fabrication charges
for finished item of work(APSS NO.403&903)

10 Supply and delivery of encapsulated plastic steps for man holes 32.00 Each 189.00 6048
manufactured as per companies standard specification including cost of
materials packing as per companiess standards, loading, transportation,
unloading and stacking at site of work including labour charges for fixing,
overheads and contractor profit etc., complete for finished item of work.

463695

APMSIDC- KADAPA ABS-Septic tank 1048 of 1048

You might also like