INSPECTION AND TEST PLAN for Junction Box Installation

Project Name:

Dok. No:

FR.752.38

Yay.Tar.

25.01.2013

Rev. No.

Rev. Tarihi
ctivity

Point

Specifications

Relevant Document

KESIR
ENGINEERING

CUSTOMER

--

CONTRACTOR

Notes

Junction Box Installation


1

Structural Steel, Building, foundation ready for junction box


installatiom

Verify completion of structural steel. Verify completion of buildings or initial


setting of equipment. Verify completion of foundations. Release for junction
box installation

Visual

Junction box installed correctly

Verify as per applicable specifications. Verify as per installation drawings and


plot plan. Verify correct tag number and IP rating. Verify holding down bolts
tightened

Visual

Junction box installation complete

Verify inspection complete and conformant

H/A

Visual

Visual

Visual

Visual

Visual

Report+Analysis

Report

10

Report

11

Report

12

Report

13

Report

14

Report

otes

Abbreviations
E : Works Execution

R
Revision
0

: Records review

Modifications

: Witness point
: Hold point

Prepared by

sw : Spot Witness point


A : Approval