Beaconsfield School Expansion Update, 27th May 2016

This week

Next week

Works:

Planned Works:

We have completed the internal and external

We will have steel inspected by BC

brick and block

We shall pour the slab foundation using a


concrete pump over two days

installed shuttering to these locations

We shall cut in expansion joints when set

We have compacted below slab level and

We will prepare the surface ready for the TF


sole plates

Scaffold will commence towards the end of


the week

We have set out for steel supports and

placed blinding sand

We have laid DPM sheeting and fitted steel


reinforcing mesh on continues hystools

We have shuttered for expansion joints

Deliveries:

What
Concrete and
concrete pump

When
Tues 31st May and
Wed 1st June

Scaffold lorry

Thurs 2nd June and


Fri 3rd June

Skip lorry

Thurs 2nd June

We expect small items to be delivered daily in transit


type vehicles. All deliveries will be managed on and
off site by our trained banks persons

Staff:
1 Site Manager (B. Burns)
3 Groundworkers
3 Brickwork Contractors
1 Banksman
1 Crane Driver