Beaconsfield School Expansion Update, 10th June 2016

This week

Next week

Works:

Planned Works:

We will continue with the scaffold to 1st floor


level

We excavated and installed chambers and soak

We will excavate for incoming services

away system

We will lay ducts and draw cords for services

We prepared for scaffold

We will have service ducts inspected

We commenced scaffold on 6th June in

We will have sole plates for Timber frame


delivered and fixed

We will prepare for Timber frame to follow

We progressed the rain and storm water


drainage

readiness for the Timber frame works

Deliveries:

What
Aggregate lorries

When
Monday 20th and
Thursday 23rd June

Scaffold lorries

Monday 20th,
Tuesday 21st and
Wednesday 22nd June

Skip exchange

Tuesday 21st and


Friday 24th June

We expect small items to be delivered daily in transit


type vehicles. All deliveries will be managed on and
off site by our trained banks persons

Staff:
1 Site Manager (B. Burns)
3 Groundworkers
3 Scaffolders
1 Banksman
1 Crane Driver