Professional Documents
Culture Documents
Modification To The FIDIC EPC/Turnkey Contract To Allow For Geotechnical Risk Sharing
Modification To The FIDIC EPC/Turnkey Contract To Allow For Geotechnical Risk Sharing
Presentation Overview
Background and Information on the Kabompo
Gorge Hydropower Project
Reasons for selection of the Contract form
Description
40MW Hydro Project, comprising a 50 m high dam,
significant underground works and E&M Equipment
Contractual
The scheme is being developed under a concession
agreement
Status
Preferred EPC Contractor identified negotiations in
progress
FIDIC Conditions
of Contract for
Construction
(Red Book)
Employer
Contractor
Lender
Geological and
Hydrology risk
Silver book requires
less input from the
Employer than the
Red Book
High degree of
certainty of the
Contract price
Contractor B
Contractor A
Likelihood of
Occurrence
Base case
Significantly worse
than base case
moderate
There is a chance
that this may be
the case
high
More than an
even chance of
occurring
moderate
There is a chance
that this may be
the case
low
Small likelihood
but this could
happen
Very poor to
extremely poor
throughout
very low
Not expected to
happen
Extremely poor
throughout
extremely
low
Virtually
impossible
Interpretation by Contractors
Contractors application of the risk sharing mechanism
Risk Sharing not considered
The difference between the All Risk Price and the Remeasurable Price obtained was marginal
The bids were also close to the feasibility study cost estimate
Conclusion
Its was acknowledged that some type of
risk sharing mechanism may be required
for successful development of this
Hydropower scheme under the EPC/
Turnkey contract
Two prices allowed the Employer to
analyse and select the least risk options
and also understand Contractors
perception of risk
Silver
Book
Disadvantages
Red
Book
Disadvantages
The Risk
Sharing
Mechanism
selected