Professional Documents
Culture Documents
TENDER”
Aliyu Muhammad1 and F.A. Orsar2
1
Department of Civil Engineering, Nile University, Abuja
2
Department of Mechanical Engineering, Ahmadu Bello University, Zaria
Correspondent: flxorsar@gmail.com
1.0 INTRODUCTION
It makes an offer for the supply of goods or services. In construction, the main tender process
is generally for the selection of the contractor that will construct the works. However, as
procurement routes have become more complex, tenders may be sought for a wide range of
goods and services (for example, on a construction management contract, the works are
constructed by a number of different trade contractors each contracted to the client) and
An effective tender management process provides a positive evaluation approach that leads not
only to the appointment of appropriate suppliers, but to ensure that the ongoing relationship is
mutually beneficial. A wholly balanced and highly efficient tender management process
improves the quality of the supply chain while reducing costs and managing risks.
Tender procedures will vary depending on the nature of the goods or services that are being
procured, but very broadly they can be classified as either single-stage or two-stage.
1
Invitation to tender: An invitation to tender (ITT - or sometimes 'invitation to treat') is a
Qualified Tenders: Qualified tenders are tenders which include reservations or statements
Construction projects have been procured under a single stage tender process, pursuant to
which the employer issues an invitation to tender to contractors for a particular project and then
selects the most competitive tender, usually based on price (Designing Buildings, 2020; Lloyd,
2016). The most common type of tendering strategy is the single-stage competitive tender used
Also known as traditional tendering, single-stage tendering is when a client issues a tender for
the whole project, with all the relevant information provided at the point of issue. The process
seeks to ensure that the client is able to secure a competitive price and to this end, the contractor
Single-stage tendering is used when all the information necessary to calculate a realistic price
• An invitation to tender is issued to prospective contractors who are all given the chance
to bid for the project based on identical tender documentation (perhaps following
invitation to tender will include information describing the goods or services required
2
• Tenders are prepared and returned by prospective contractors (this may involve
questions and answers and a mid-tender interview to clarify the client’s requirements).
• Submitted tenders are then assessed and compared (this may involve further
interviews).
• Subject to the outcome of those negotiations the preferred tenderer may then be
appointed.
However, increasingly it is becoming useful to obtain input from prospective tenderers before
there is sufficient information available for the main contract to be awarded. This can allow
early input from the main contractor, or early appointment of a specialist contractor, such as a
i. The client benefits from a competitive tendering process which can lead to more
competitive pricing.
ii. The client can also benefit from a fixed price through this tendering process.
i. The number of contractors prepared to bid for the project may be low. Historically,
single-stage procurement was done through an OJEU process, which often resulted in
high tendering costs to the contractors. Because of this many have shifted their focus
to the more cost effective two-stage schemes over time and are no longer willing to
engage in single-stage.
ii. The development scheme is generally designed and costed up by the contractor in
isolation which can often result in the project budget being exceeded. Generally, this
3
is because contractors may not have been consulted on the buildability at the outset
iii. It can be expensive for all concerned, encourages claims if the successful contractor has
under-priced the project (which can easily occur if there was inadequate time to enable
the contractor to evaluate risks) and fails to incentivise value engineering between the
parties.
iv. If elements from the project specification are missing or are unclear, it can lead to
adjustments being made later in the contract, and the final account may be very different
as unforeseen costs mount up. The added pressure may mean contractors look for ways
v. The process also means clients are unable to benefit from early contractor engagement.
As the process can take a long time and contractors are increasingly reluctant to engage
design and build context and is viewed as a real alternative to traditional procurement (Lloyd,
2016).
Two stage tendering sometimes referred to as “negotiated tendering” or “two stage selective
tendering”, is typically used for design and build projects and involves engaging a contractor
at a much earlier stage of a project, prior to the completion of all the information required to
enable them to offer a fixed price. In the first stage, a limited appointment is agreed allowing
the contractor to begin work and in the second stage a fixed price is negotiated for the contract
4
3.1 Procurement Structure of two-stage tender
As a first step to implementing a two-stage process, the employer would typically approach
several contractors, on a competitive tender basis, with basic information regarding the project
(i.e. an outline design) and request an indicative price (including details of each contractor’s
profit, overhead and preliminaries) for the works as well as the contractor’s proposal for
executing the project. Following receipt of this basic information, the employer will engage its
Under the pre-construction agreement, the contractor will usually work with the employer’s
design team to resolve buildability issues and undertake a concept programme for the project
price’. To arrive at the maximum ceiling price, the contractor will need to obtain indicative
price quotes for key subcontract packages and the maximum ceiling price should be presented
If the contractor is engaged to take the lead on the design, the employer may instruct the
contractor to develop a concept design into a schematic design. However, it is important that
the employer has the express right to terminate the pre-construction agreement if either the
concept design or the maximum ceiling price fails to meet the approval of the employer
negotiations).
If the contractor is requested to undertake the schematic design, the contractor may also be
required to provide a guaranteed maximum price (also on an open book basis) for completing
the project, which generally should not exceed the maximum ceiling price.
5
As with the concept design, the employer should have the express contractual right to terminate
the pre-construction agreement if either the schematic design or the guaranteed maximum price
The first-stage appointment might be made on the basis of a bespoke agreement, a consultancy
agreement or a pre-construction services agreement (PCSA), with an appendix setting out all
tender items to be applied to the second stage contract, and a clause that makes it clear there is
no obligation to proceed to the second stage, and in such circumstances the first stage fee would
The basis of the appointment for the first stage may include:
• Method statements.
It is important that this appointment is based on as much information as possible and that
The pre-construction services carried out by the contractor in the first phase might include:
6
• Helping the consultant team to develop the design, or the contractor undertaking all
• Helping the consultant team to develop the method of construction, or the contractor
• Obtaining prices for work packages from sub-contractors or suppliers on an open book
basis.
required to ensure that the agreement is properly documented. As well as the ability to terminate
the pre-construction agreement at certain key points, the pre-construction agreement should
also make it clear that the contractor has no expectation of being awarded the construction
contract.
In the event of early termination of the pre-construction agreement, the contractor should
therefore be paid for the pre-construction services performed as at the date of termination (i.e.
principally for buildability and design work undertaken) but liability for such things as loss of
It is also important that intellectual property rights are addressed. In short, any designs
prepared by the contractor should vest in the employer or, alternatively, the employer must be
granted a sufficiently broad license to freely use and develop any designs prepared by the
If the employer is looking to have a design and build contract, the employer will seek to engage
the Contractor for the construction of the project under a design and build contract where the
employer is satisfied with the schematic design and the guaranteed maximum price. This will
7
enable the contractor to simultaneously undertake the detailed design and to commence the
A guaranteed maximum pricing mechanism often provides that the employer and the contractor
may share any savings (i.e. the extent to which the cost of the project is less than the guaranteed
In this situation, the construction contract needs to include an open book pricing mechanism
pursuant to which the employer has full visibility regarding the actual cost of completing the
project.
schemes where the employer is seeking to transfer both design and commercial risks. Two-
i. The contractor has the opportunity to work with the client’s designers ahead of
ii. The two-stage tender allows, in theory, further overlapping of the design and
procurement programmes.
iii. The preferred contractor is strongly motivated to ensure completion of the design to an
iv. The procurement of specialist subcontractors with design responsibility should be more
The contractor’s second stage bid should be based on a thorough understanding of the design
8
However, when tendering on a two-stage basis for large and complex schemes the issues raised
in the second stage negotiation can be both very wide ranging and also difficult to close-down.
As a result, and despite these strong reasons to adopt two-stage tendering on design and build,
clients can find themselves facing some nasty surprises at the end of the second stage
negotiation. Areas of potential disagreement include allowances for design development during
the tender period and risk allowances for the completion of the design. Other risk issues that
The design team remains the responsibility of the employer until novation occurs. As a
consequence, any design development carried out after the second stage will be a variation for
which the client will have some design responsibility. It is a prudent, although possibly
impracticable step, to suspend design work during the second-stage bid period, so there is a
clear relationship between the contract sum and the novated design. Novation can only occur
once the second stage is completed and the main contractor appointed.
The switch to negotiation during the second stage makes it much more difficult for the client
to monitor levels of main contractor risk allowances built into subcontractor tenders.
In summary, the adoption of a two-stage tender route on design-and-build jobs gives the
employer a great deal of benefit in terms of the balance between client control over design
development and the eventual transfer of design responsibility to the contractor. However,
there is a premium to pay for this additional risk transfer. The preferred contractor’s role in
design development will strengthen its negotiating position, enabling it to drive a particularly
i. The main advantage of two-stage tendering for the employer is that it facilitates the fast
tracking of the project and this is particularly appealing if the employer is under time
9
pressure to deliver (i.e. perhaps a development agreement imposes aggressive timelines
on the employer). As the employer and the contractor are working together from an
early stage, two-stage tendering will facilitate construction works commencing prior to
ii. Price certainty can also be achieved if a two-stage tender results in a guaranteed
maximum price construction contract being executed. Allied to this point, risks are
more likely to have been properly evaluated and priced by the contractor on account of
the greater visibility afforded to him under during the pre-construction phase, thus
iii. Additionally, the contractor’s involvement with the employer’s designers from an early
stage means that buildability and sequences issues can be addressed and resolved
quickly while there is also greater scope for value engineering, which should also make
the final contract price more competitive (and may facilitate a cost savings mechanism).
iv. The two-stage tendering promotes a more collaborative approach between the parties,
and the possibility of disputes arising during the construction phase is therefore
reduced.
• Early appointment of the contractor, potentially bringing forward the completion date
of the project;
• Second stage tender should be based on more complete information and a better
understanding of the scope of works, so the final account should be closer to the
contract sum;
10
• Improved identification of project risks within a timescale where action can be
undertaken;
• Ability to procure specialist design contractor packages ahead of a first stage main
contract tender that can then be incorporated into the second stage via novation;
the first stage of the tendering process and through to the completion of stage two.
i. Although the pre-construction agreement may provide the employer with the express
right of termination at various points, the employer may, from a practical perspective,
become ever more reluctant to exercise this right as the contractor becomes an
increasingly entrenched member of the design team and this will lead to the employer’s
ii. The strength of the contractor’s bargaining power may increase further if the contractor
iii. Further, the employer may still face difficulties even if the employer terminates the pre-
inevitably some form of fall out (regardless of how well the pre-construction agreement
has been drafted). For example, the contractor may retain possession of key
the employer or to the incoming contractor while the contractor may also retain
possession of the site (assuming that it has been granted access and has started work)
11
iv. Even if the termination process is seamless, the project will almost certainly be delayed
that the employer can ill afford if a two-stage tender was adopted on account of time
prolonging negotiations for as long as possible with two interested parties, thereby
retaining competitive tension. However, negotiating with two contractors can be a time
consuming and expensive exercise which cuts across the underlying principle of
vi. Another option may be for the employer to allow adequate float to provide a buffer
against unforeseen and prolonged negotiations but again this may not be practical in
the circumstances.
vii. Regardless of the above, the main risk for the contractor is that it has no guarantee of
being awarded the construction contract until it has been actually signed. This is a
will adequately compensate it for the extent of the design and collaborative work that
12
• The cost of second stage tenders may be higher than predicted at Stage one (1)
leaving the client with difficult decisions on how to deliver within budget.
• Increased input from client and consultants during the second stage tender;
subcontractor costs;
This section sets out steps that can be taken to improve a client’s negotiating position on a two-
stage tender. The starting point for these actions is the assumption that the project is attractive
to prospective tenderers, and that the client is able, to an extent, to dictate terms. On complex
schemes such as refurbishments, projects for one-off clients, or projects with a very challenging
programme, the client may not be in a position to go out to the market on any basis other than
i. Maintain an exit strategy: Negotiation on two stage tenders relies on a good deal of
11th-hour brinkmanship. To be fair to the contractor, the source of this problem is very
often rooted in the fact that the contractor’s overall risk exposure will only be known
when the design is completed to the required stage and when subcontract bids are
received. Key attributes of the exit strategy are that bidders must know that it exists, it
must be credible and its operation must have a negative consequence for the preferred
This option is particularly effective if some work packages have already been secured
13
• Use the client’s not-to-exceed (NTE) budget as a cost threshold that will trigger a
being used, the preferred second-stage contractor should be advised that they will be
barred from submitting a revised single-stage tender offer on the basis that they have
Both of these options would inevitably incur a time penalty if enacted, but their prime
intention is to strengthen the client’s negotiating position. The client should allow some
programme float at the end of the second stage for this eventuality.
ii. Don’t start too early: The first-stage tender must be based upon a sufficiently
representative firm design so that the contractor’s programme and preliminaries are not
subject to renegotiation in the second stage. The earliest practical date for the issue of
stage-one tenders is therefore the end of RIBA stage C. At the same time, the client’s
design team must detail the design so that it can be procured securely during the second
stage. Clearly there is no benefit to the client in going down the two-stage route unless
a viable firm price tender can be secured. Where the design team is not to be novated,
iii. Don’t start on site under the direction of the main contractor prior to the
agreement of the second stage tender: Instructing work on the basis of a letter of
intent is a high-risk option on any project, and will undermine the client’s exit strategy
on a two-stage scheme.
iv. Maintain the quality of the design information: Avoid the acceleration of the
production information programme to meet the timescale for the second stage if this
tender in order to ensure that they can be priced on the basis of a competitive rather
14
than a negotiated tender. Clients need, however, to be confident that the scope of work
will not change significantly during the second stage. Package contractors can also
tender directly to the client for later novation to the successful contractor. High-value
contractor-designed packages that require substantial input from the project team such
appointment basis.
vi. Establish clear roles and responsibilities for the tenderers: No pre-construction
services agreement can compel a contractor to submit a competitive bid. However, the
PCSA can clarify the contractor’s role with regard to the continuing development of
the design, their responsibility for the management of the design team during the second
stage and the targets that need to be met to complete the second stage. In effect the
PCSA should aim to set out the basis on which the client can revert to a plan B without
penalty.
vii. Agreement of design development risk allowances as part of the first stage tender:
contracts is the “below the line” risk allowances for design development and so on that
contractors add to second-stage package tenders. These main contractor costs are
usually included within the gross costs of the package tenders and are not subject to any
form of benchmarking. They are potentially a significant source of loss of cost control
during the second stage. Pricing of risk allowances can be included as part of the first
stage bid, but other than the adoption of a wholly open-book approach to pricing, there
15
helps to ensure that the negotiation proceeds on an even-handed basis. Areas where the
project team can contribute include the shortlisting of the subcontractors, the
ix. Maintenance of competition into the second stage: Competition can be extended into
the second stage through the retention of two preferred contractors. The employer will
be liable for the second stage costs of both tenderers and as a result will need to be
confident that the additional costs incurred by both contractors and the project team can
projects, for example, where the aim of the second stage is to get the preferred
contractors’ proposals.
improve on the client’s budget during the second-stage tender using a shared
savings arrangement: The downside of this approach is that the budget must have
some fat in it for the contractor to secure savings to share. Alternatively, they may adopt
a pricing strategy to meet the budget - retaining the full value of the contract rather than
The logic behind two-stage procurement is to bring buildability and supply chain engagement
into the design process to eliminate recurring issues and stimulate ideas, whilst maximising
There are many variants for two-stage tendering and many professionals in the construction
industry see it as a realistic alternative to traditional tendering, yielding positive results for both
the employer and the contractor. As with any other form of contracting, two-stage tendering
16
should be approached with care and both parties need to ensure that their commercial interests
contract.
Construction projects have been procured through either the traditional ‘single-stage’ tender
process or via the ‘two-stage’ approach. The main aim of the single-stage approach is to
generate a firm price at the outset through a competitive tendering process, where-as the two-
stage approach embraces a collaborative open book approach throughout the project.
Historically, the two-stage route has been the most popular within the construction industry,
but in more recent times the single-stage process has gained in popularity - in Q4 2017, nearly
This shift has occurred because property teams are under increasing pressure to manage costs
and need full visibility of these at an earliest stage. However, by doing this they are losing the
potential development flexibility and added value that comes with the collaborative two-stage
process.
There are undoubtedly pros and cons to both routes, and which one is right for you will depend
on the project, the project team and the organisation’s outlook on cost management and
planning.
adopted by clients and their contractors, while still delivering value for money, or does its use
- in that the main benefit of two-stage tendering, speed of programme, inevitably comes at the
price of some degree of cost premium. Furthermore, for clients following a public sector
17
procedure, limits on their discretion to engage in any negotiation with the preferred tenderer
Where clients need lump-sum cost commitment from their contractor and they have the time
available, single-stage tendering continues to be a viable route for obtaining good-quality bids.
However, in an increasingly time-driven and consolidated tender market and with a greater
transfer of design responsibility to the supply chain, many clients find themselves having little
option but to go down the two-stage route. In the final analysis, whether the two-stage route
adds value will depend more on the quality of the design information and post-contract
relationships than on the basis on which the contract was bought (Langdon and Rawlinson,
2006).
5.0 CONCLUSION
and to secure an appointment on the basis of the right team, agreed costs, programme and
appropriate transfer of risk. This seemingly innocuous objective has become increasingly more
difficult to achieve as programmes have accelerated and as both employers and contractors
seek, in particular, to strengthen their position with regard to the apportionment of risk.
Historically, clients have mostly chosen contractors on the basis of lowest cost. Although many
arrangements, many clients continue to seek the reassurance of some element of competition
in their tendering processes. Indeed, there is evidence to demonstrate that, where lump-sum
contracts are in use, this approach can still deliver good-value solutions if the process is not
abused. Value and cost certainty still count for a great deal in the overall balance of most
clients’ priorities and as a result, some form of competitive tendering will continue to be used
18
REFERENCES
Aitken, F., and Bourne, C., (2019). “Single Stage” versus “Two Stage” Tendering within the
YORhub frameworks. Proceedings of the workshop on Construction Frameworks for
Yorkshire and Humber, USA, pp. 1-28
BRODIES, (2020). Two stage tenders: a means of managing risk for contractors. Retrieved
May 25th, 2022 at https://brodies.com/insights/
Denham, S., (2022). A simple approach to the procurement of capital projects. Retrieved May
25th, 2022 at https://www.denham.biz
Executive Compass, (2019). Tender Writing and Bid Management: The Future of PQQs.
Retrieved May 25th, 2022 at
https://www.executivecompass.co.uk/blog/bid-management/
Garner, B., (2020). The Benefits of Two-Stage Procurement. Retrieved May 25th, 2022 at
https://procurepartnerships.co.uk
Heming, P., (2019). “Two Stage Tendering”: Commercial and Project Management Contracts
and Disputes. Retrieved May 25th, 2022 at https://c-link.com/blog
Jansen, C., (2019). Two Stage Tendering for Construction Projects in the Netherlands. CMS
PP Forum, Amsterdam
Langdon, D., and Rawlinson, S., (2006). Procurement: Two-stage tendering. Retrieved May
25th, 2022 at https://www.building.co.uk
Lloyd, E., (2016). Two-stage Tendering and GMPs. Retrieved May 25th, 2022 at
https://www.tamimi.com
PAGABO, (2018). Single Stage vs Two Stage: which is right for you? Retrieved May 25th,
2022 at https://www.pagabo.co.uk
19
RICS, (2014). Tendering Strategies. RICS guidance note, UK, 1st edition. Retrieved May
25th, 2022 at https://rics.org/guidance
Scottish Government (2018). Construction Procurement Handbook: Guidance for public sector
contracting authorities on the procurement of construction works. Retrieved May 25th,
2022 at https://www.gov.scot/publicationa/
Tetlow, C., (2015). Why single stage procurement is the way ahead for the public sector.
Retrieved May 25th, 2022 at https://www.cips.org/supply-management/opinion/
Tolson, S., (2007). Procurement and Supply Contracts in the Construction Industry. Retrieved
May 25th, 2022 at https://www.fenwickelliot.co.uk
20