You are on page 1of 17

PRESENTATION ON

POWER SECTOR
26 July 2010
By Arjun Srivastav
POWER SECTOR
 India has the fifth largest generation capacity in the world with an installed
capacity of 152 GW as of September 2009, which is about 4 % of global power
generation.

 The Indian government has set ambitious goals in the 11th plan for power
sector owing to which the power sector is poised for significant expansion.

 The Government of India has an ambitious mission of POWER FOR ALL BY


2012. This mission would require that the installed generation capacity should
be at least 200,000 MW by 2012 from the present level of 144,564.97 MW.
Power requirement will double by 2020 to 400,000MW.

 The current installed transmission capacity is only 13 percent of the total


installed generation capacity

.
FOCUS SECTOR - POWER

Contents
 Overview of the sector
 Snapshot of Power Generation Industry
 Snapshot of Power Transmission Industry
 Snapshot of Power Distribution Industry
 Major Players
Overview of the Power Sector
 The Challenge
 India needs to sustain an 8% to 10% economic growth rate, over the next 25 years, if it is to
eradicate poverty and meet its human development goals.
 To deliver a sustained growth rate of 8% through 2031-32 and to meet the lifeline energy
needs of all citizens, India needs, at the very least, to increase its primary energy supply by 3
to 4 times and, its electricity generation capacity/supply by 5 to 6 times of their 2003-04
levels.

 How will India face this challenge ?


 Meeting this vision requires that India pursues all available fuel options and forms of energy,
both conventional and non-conventional.
 India must seek to expand its energy resource base and seek new and emerging
 energy sources.
 Finally, and most importantly, India must pursue technologies that maximize energy
efficiency, demand side management and conservation. ( rational for having a power
consultancy segment)

 Composition of the Power Sector


 The sector consists of 3 industries – Power Generation , transmission and distribution
SNAPSHOT : Power Generation Industry
 Overview
 India’s power generation capacity as on March 2010 was 159,398 MW
 64.28% - Thermal Sources
 23.13% - Hydro Sources
 9.74 - Renewable Sources
 2.86 - Nuclear Sources

 Favorable Trends
 Rapid and progressive evolution
 Capacity Augmentation
 Conventional capacity 9585 MW during 2009-10 ( 2.5 times higher than the
previous year)
 Productivity of power plants has been improving

 Factors leading to growth


 Increased Private Sector Participation
 Contribution has risen from 8.66 % 2003 to 18.2% in 2010

 Pvt. projects aggregating over 100,000 MW are under various stages of development

 Forms of contribution – Private power generation projects & Development of


supercritical technology through Private Investment for Ultra Mega Projects
 Government policy to boost solar and wind power
 Emergence of new and alternate energy sources
 Projects and Opportunities
 Ultra Mega Power Project (UMPP)
 Huge coal based projects with 4000 MW capacity each based on supercritical

technology to be developed through private investment


 Govt. has planned 9 UMPPs

• 4 of the 9 planned UMPPs – Mundra , Sasan , Krishnapatnam and Tilaiya –


have been allotted to private players
• 3 of the 9 planned UMPPs are in line - Sarguja ( Chattisgarh), Bhedabahal
( Orissa ), Cheyyur ( Tamil Nadu)
• Remaining 2 of the UMPPs are yet to be finalized
 Govt is keen to increase the no. of UMPPs from 9 to 14

 Power Finance Corporation ( PFC) is the nodal agency for these projects

 Indigenization of supercritical equipment to meet future demand


 Central Electricity Authority ( CEA) issued a directive to central and state public

sector utilities in Feb 2010 to procure supercritical equipment only from domestic
manufacturers to encourage indigenous manufacturing

 Govt. Policy and Programmes to boost solar power generation


 Jawahar Lal Nehru National Solar mission launched in Nov 2009

• Ambitious target of achieving 20,000 MW of solar capacity by 2022 in three


stages
 Govt. Policy and Programmes to boost solar power generation
 12 MW of solar power is already connected to the grid

 More than 500 MW of solar photovoltaic plants and 350 MW of solar thermal are in

the pipeline

 Plans to increase nuclear power generation


 Govt. is importing nuclear fuel ( uranium) to boost production

 Nuclear Power Corporation of India has commissioned two new reactors of 220

MW each and is set to commission another one


 It also plans to set up 8 reactors of 700 MW each and has begun work on 4 of these

 Plans are also on for setting up imported reactors in various sites in India

 Govt. plans to increase installed nuclear generation capacity from current 4560 MW

to 20,000 MW by 2020 and 60,000 MW by 2030-31

 Emphasis is also on enhancing gas and wind based power generation and Govt. is taking
a series of steps in this direction
 Challenges faced by the Power Generation Sector

 Inadequate equipment capacity

 Fuel and manpower shortage

 Delays in securing clearances and commitments from state utilities for power purchase &

resistance from environmentalists


SNAPSHOT : Power Transmission Industry
 Overview
 As of March 2010 , the State Transmission Units ( STU) and Central Transmission Unit
( CTU) , which are responsible for intra state and interstate transmission network respectively ,
together own and operate a complex transmission system comprising around 236,430 ct. km of
lines and over 305,550 MVA and 14,000 MW of substation capacity of voltages above 220 KV

 Favorable Trends
 Significant Investments at Central and State Level

 National Level Investment


• Powergrid corporation of India ( Powergrid) , the country’s CTU spent a total of Rs.147.1
billion ( Rs. 66.15 billion 2007-08) & (Rs. 80.95 billion in 2008-09)
• It has planned capital expenditure of Rs. 120 billion for 2009-10
• Plans to make an investment of Rs. 550 billion during the current plan period

 State Level Investment


• STUs spent Rs. 185.84 billion during the 1st two years of the plan period ( 23% of the
total utility spending during the period)

 Increased private sector participation


 Projects and Opportunities

 Development of the National Grid by the CTU


 High Voltage Transmission Corridors
 Powergrid is taking steps to develop 7 high voltage transmission corridors

( 800KV and 770 kv ) over the next 5 years – investment of Rs. 489 billion – to
facilitate smooth transmission of about 55,000 MW of capacity that is proposed to
be generated by private power plants in the states of Chattisgarh , Orissa and
Jharkhand
 2 more transmission corridors are expected to be developed by CTU to wheel power

from coastal Tamil Nadu , where private projects based on imported coal are coming
up . For this , Powergrid has signed long term transmission agreements with 37
private developers for a gross combined generation capacity of over 42,000 MW
 Development of Transmission Systems by Private Players
 Transmission systems associated with private generation projects are being

developed by private players independently or in joint venture with the CTU and
STU
 This includes Adani Power’s Rs. 15 billion dedicated 1000km long bi-polar 500
KV high voltage direct current line from its Mundra Project in Gujrat to
Mohindergarh in Haryana.
 The company is also developing a 765 KV line in joint venture with Mahatransco in

Maharashtra to secure evacuation of power from its upcoming power plant in the
state
 100% Private Investment invited for Transmission Projects

 14 transmission projects identified by the Power Ministry for 100% private


investment
 The bidding process for the first 3 projects has been completed by the 2 nodal
agencies – Power Finance Corporation & Rural Electrification Corporation
 The 1st Project – East North Interconnection – was awarded to Sterlite Technologies
 Other 2 projects – North Karanoura and TALCHER II – were bagged by RPTL
 The bids for the remaining projects were invited by the nodal agencies in March
2010
 Some states including Uttar Pradesh and Haryana have also invited tenders for state
level projects

 Challenges faced by the Power Transmission Sector


 Delays in clearances
 Inadequate margins in the system
 Grid indiscipline
 Lack of basic infrastructure
 Unco-ordinated planning
 Inadequate equipment manufacturing capacity
 Fast changing technology leading to obsocelence
 Slow progress in strengthening and augmentation of networks
SNAPSHOT : Power Distribution Industry

Overview

 India’s distribution infrastructure include more than Rs. 6.9 million ct. km of lines and
over 284,365 MVA of distribution of transformer capacity as of march 2008
 It is growing at a rate of 2.07% and 7.65% respectively over the period of 2002-03 and
2007-08

 Favorable Trends

 The level of metering has shown improvement


 Sales of power and state utility revenues are showing a steady increase every year
 Cash collections are improving
 A few utilities / State Electricity Boards have also registered an improvement in cash
profits like West Bengal , Assam , Orissa , Andhra Pradesh , Punjab , Kerala and UP and
Meghalaya
 More and more distribution companies are adopting sophisticated IT systems to improve
operations and customer service – spot billing , call centers , remote meter reading
,automated billing and energy accounting
 Projects and Opportunities

 Accelerated Power Development and Reform Programme ( 2002-03)


 Objective- reducing AT&C losses , improving the quality of power supply and

consumer satisfaction

 Restructured Accelerated Power Development and Reform Programme


 Larger in scale than the original programme ( Rs. 500 Billion)

 It will be implemented in two parts – Part A ( Rs. 400 billion) and Part B ( Rs. 100

billion)
 Part A – establishment of baseline data and IT applications for enegery accounting

/auditing and IT based consumer centre


 Part B – Regular Distribution Strengthening Projects

 Nodal Agency – Power Finance Corporation

 Rajiv Gandhi Gramin Vidyuti Karan Yojana


 Provides focus and funds to rural distribution systems as of April 2010

 573 projects under the programme


 Privatization of distribution

 Process has been slow to take off


 Orissa -1st state to privatize distribution followed by Delhi
 Benefits - Bringing down AT& C losses and improvement of customer services
 Franchise Model in privatization of distribution
• 1st Franchise operation launched in Maharashtra with the state transferring the rights
to supply , maintain , recover electricity dues in certain sectors to Pvt. players
• UP Govt. introduced input based franchises in urban areas for power distribution
• Other states will also follow on the same model ( plans in place for Rajasthan ,
Karnataka and Maharashtra and Madhya Pradesh)

 Setting up of State Electrification Regulatory Commissions

 Established in 23 Indian States


 Has led to tariff rationalization
 Challenges faced by the Power Distribution Industry

 High aggregate technical and commercial losses

 Rampant power thefts

 Technical issues

 Policies of offering subsidized or free power

 Dilapidated networks

 Inadequate metering

 Poor recovery of dues

 Poor operational and financial management

 Lack of customer orientation


Major Players in the Power Sector
 National Thermal Power Corporation
- Single largest power producer in India

 National Hydro Power Corporation


-Largest hydro power generator in India

 Power Grid Corporation of India


- Largest Transmission Utility in India

 Power Trading Company


- 1st Power trading company of India ( 1999)

 Power Finance Corporation


- State run power sector financing corporation

 Bharat Heavy Electricals Ltd


- The largest engineering and manufacturing enteroprise in India

 Tata Power Company


- Biggest integrated power player in India
THANK YOU!

You might also like