7.2
Determine
Budget
7.3 Control
Costs
Project Cost Management
7.1
Estimate
Costs
7.2
Determine
Budget
7.3 Control
Costs
7.2 Determine Budget
Project Cost Management
7.1
Estimate
Costs
7.2
Determine
Budget
7.3 Control
Costs
Earned Value Management (EVM)
• At beginning of project
– Estimate at completion (EAC) = Budget at Completion (BAC)
• EAC = AC + Bottom-up ETC
• EAC forecast for ETC work performed at the budgeted rate
– EAC = AC + (BAC – EV)
• EAC forecast for ETC work performed at the present CPI
– EAC = BAC/CPI
• EAC forecast for ETC work considering both SPI and CPI factors
– EAC = AC + [(BAC – AC) /(CPI * SPI)]
• To-Complete Performance Index (TCPI)
– Is projection of CPI that must be achieved on remaining work to meet the
specified goal such as BAC
– TCPI = budget remaining/funds remaining
= (BAC – EV)/(BAC – AC)
EVM Exercise
– You have a project to build a new fence. The fence is four sided, 10
meter long each side. Each side to take 1 week, and budgeted for Rs
1000 per side.
PV CPI
EV SPI
AC EAC
BAC ETC
CV VAC