Professional Documents
Culture Documents
PROJECT COST
MANAGEMENT
1
11/3/2014
PROJECT COST
MANAGEMENT
Project cost management includes the processes involved in
estimating, budgeting, and controlling costs so that the
project can be completed within the approved budget
• Plan Cost Management
• Estimate costs
• Determine budget
• Control costs
PROCESSES MAP
2
11/3/2014
COST MANAGEMENT
PLAN
The planning effort of the processes of the cost management
plan is a part of the develop project management plan.
Cost management plan can establish the following:
• Level of accuracy
• Units of measures
• Organizational procedures links (control account)
• Reporting formats
• Process descriptions
• Rules of performance measurement (EVM)
LEVEL OF ACCURACY
Order of Magnitude
• Range: -50% : + 100%
• Typical method of estimating used: Expert opinion
• An approximate estimate made without detailed data; used
during the initial evaluation of the project (Concept)
Budgetary
• Range: -10% : + 25%
• Typical method of estimating used: Top-down or
Analogous; used to establish the funds required for the
project (Development)
3
11/3/2014
LEVEL OF ACCURACY
Definitive
• Range: -5% : + 10%
• Typical method of estimating used: Bottom-up (WBS)
• Prepared from well-defined specifications, data, drawings,
and so forth;, bid evaluations, contract changes, extra
work, legal claims, permit and government approvals
EARNED VALUE
MANAGEMENT ANALYSIS
• One technique used is called earned value technique
(EVT) which compares the cumulative value of the
budgeted cost of work performed (earned at the original
allocated budget amount) to both the budgeted cost of
work scheduled (planned) and to the actual cost of work
performed (actual)
• An important part of cost control is to determine the cause
of a variance, the magnitude of the variance, and to decide
if the variance requires corrective action
4
11/3/2014
EARNED VALUE
MANAGEMENT ANALYSIS
• EVT uses the cost baseline contained in the project
management plan to assess project progress and the
magnitude of any variations that occur
• EVT involves developing these key values for each schedule
activity, work package, or control account
• Earned Value (EV)
• Planned Value (PV), Schedule Variance (SV), Schedule
Performance Index (SPI)
• Actual Cost (AC), Cost Variance (CV), Cost Performance
Index (CPI)
• Estimate to Complete (ETC)
• Estimate at Completion (EAC)
EXAMPLE
We are about to produce 20 tables in 20 days cost is $20 for each.
SV = EV – PV = 60 – 80 = -$20
CV =EV – AC = 60 – 90 = -$30
SPI = EV / PV = 60 / 80 = 0.75
CPI = EV / AC = 60 / 90 = 0.666
5
11/3/2014
PROJECT PERFORMANCE
MANAGEMENT
FORECASTING
• EAC forecast for ETC at new estimate
• EAC forecast for ETC work considering both SPI and CPI factors
6
11/3/2014
VARIANCE AT
COMPLETION (VAC)
B AC what the total job is supposed to cost
E AC what the total job is expected to cost
TO-COMPLETE
PERFORMANCE INDEX
(TCPI)
TCPI is a CPI that
must be achieved in
order to meet a certain
management goal for
the project (such as
BAC or EAC).
7
11/3/2014
EXAMPLE
Wall Construction
Time = 1 week per wall
Cost = $ 1,000 per wall, materials and
labor
Total Schedule = 4 weeks
Total Cost = $ 4,000
Working days 5 day per week
starting on Sunday and finish on
Thursday by 5 PM
Assume production is linear
WALL CONSTRUCTION
5 pm Wednesday, Week 2 How much work
should have been
completed – PV ?
PV = $ 1,800
8
11/3/2014
WALL CONSTRUCTION
5 pm Wednesday, Week 2 What is the budgeted
value of actual work –
EV ?
Total = $1,600
WALL CONSTRUCTION
5 pm Wednesday, Week 2 Total Cost to date – AC
AC = $ 2,250
9
11/3/2014
WALL CONSTRUCTION
5 pm Wednesday, Week 2 Performance Indices
PV $1,800
EV $1,600
AC $2,250
Schedule Variance = EV - PV
= $1,600 - $1,800
= ($200)
Cost Variance = EV - AC
= $1,600 - $2,250
= ($650)
WALL CONSTRUCTION
5 pm Wednesday, Week 2 Performance Indices
PV $1,800
EV $1,600
AC $2,250
SPI = EV / PV
= $1,600 / $1,800
= .9
CPI = EV / AC
= $1,600 / $2,250
= .7
10
11/3/2014
EXERCISE
You are the project manager on the case study project:
As a team, using your previously created activity list
resources, Bar chart …
1. Calculate the cost of each activity (work package)
2. Calculate the total project cost
3. Create and Draw the cumulative S-Curve (cost
baseline)
TYPES OF COSTS
Direct Costs – Cost that are directly attributable to
the work on project. Examples are team travel,
team wages, recognition and cost of material used
on the project
Indirect Costs – Overhead items or costs incurred
for the benefit of more than one project. Examples
include taxes, fringe benefits, and janitorial
services.
11
11/3/2014
PRESENT VALUE
Budgeting technique that
debates the future value of
money based on inflation, etc.
PV = FV___
(1 + r)t
12
11/3/2014
PAYBACK PERIOD
The exact length of time needed to recover an initial
investment as calculated from cash inflows.
13
11/3/2014
INTERNAL RATE OF
RETURN (IRR)
• The interest (discount) rate where the present value of the
benefits exactly equals the costs.
EXERCISE:
ACCOUNTING STANDARDS
14
11/3/2014
PROJECT COST
MANAGEMENT
15
11/3/2014
PLAN COST
MANAGEMENT
• Plan Schedule Management is the process that establishes the
policies, procedures, and documentation for planning,
managing, expending, and controlling project costs.
PLAN COST
MANAGEMENT
INPUTS
OUTPUTS
16
11/3/2014
PLAN COST
MANAGEMENT
The cost management plan can establish the following:
• Units of measure.
• Level of precision.
• Level of accuracy.
• Organizational procedures links. (accounting system)
• Control thresholds.
• Rules of performance measurement.
ESTIMATE COSTS
INPUTS
TOOLS & TECHNIQUES
1. Cost management plan
2. Human resource management plan 1. Expert judgment
3. Scope baseline 2. Analogous estimating
4. Project schedule 3. Parametric estimating
5. Risk register 4. Bottom-up estimating
6. Enterprise environmental factors 5. Three-point estimating
7. Organizational process assets 6. Reserve analysis
7. Cost of quality
8. Project management software
9. Vendor bid analysis
10. Group decision-making techniques
OUTPUTS
1. Activity cost estimates
2. Basis of estimates
3. Project documents updates
17
11/3/2014
ESTIMATE COSTS
Estimates supporting documentation should provide a clear and
complete understanding of how the cost estimate was derived.
• Documentation of the basis of the estimate (i.e., how it was
developed),
• Documentation of all assumptions made,
• Documentation of any known constraints,
• Indication of the range of possible estimates (e.g., $10,000
(±10%) to indicate that the item is expected to cost between a
range of values), and
• Indication of the confidence level of the final estimate.
18
11/3/2014
DETERMINE BUDGET
INPUTS
1. Cost management plan
2. Scope baseline
3. Activity cost estimates
4. Basis of estimates TOOLS & TECHNIQUES
5. Project schedule
6. Resource Calendar
1. Cost aggregation
7. Risk register
2. Reserve analysis
8. Agreements
3. Expert judgment
9. Organizational process assets
4. Historical relationships
5. Funding limit reconciliation
OUTPUTS
1. Cost baseline
2. Project Funding Requirements
3. Project documents updates
DETERMINE BUDGET
19
11/3/2014
CONTROL COSTS
INPUTS
20
11/3/2014
QUESTIONS
21
11/3/2014
22
11/3/2014
23
11/3/2014
24
11/3/2014
25
11/3/2014
26