You are on page 1of 1

SMART CHARGE II MANUAL - INDUSTRIAL LEAK DETECTION DIVISION

AUTOMATIC MODE

Standard Unit Operational Steps


1. Install part to test port.
2. If the system was powered in Manual mode, press the MAN key to place it in Automatic mode. The MAN
LED should cease to illuminate.
3. Press the PUMP key. The evacuation pump will be enabled and the PUMP LED will illuminate.
4. Press the Cycle Start pushbutton. The system automatic (AUTO) cycle will run. The sequence of events
and Operator Interface screens are as follows:

The automatic mode is initiated.

AUTOMATIC MODE
READY TO CYCLE

The test part is vented.

AUTOMATIC MODE
VENTING PART

The test part is evacuated.

AUTOMATIC MODE
EVACUATING PART

The test part is leak tested.

AUTOMATIC MODE
LEAK TESTING PART

The test part is Helium charged.

AUTOMATIC MODE
HELIUM CHARGE

861-018 Rev. E 13