Table

PERT Table

Act. Time              
Code (days) Predecessors ES EF LS LF ST Critical
A 2 0 0 2 0 2 0 Yes
B 4 A 2 6 2 6 0 Yes
C 5 B 6 11 6 11 0 Yes
D 29 C 11 40 11 40 0 Yes
E 10 C,D 40 50 40 50 0 Yes
F 4 C,D,E 50 54 50 54 0 Yes
G 3 F 54 57 54 57 0 Yes

Legend:

ES = Earliest started Time EF = Earliest Finished Time

LS = Lasted Started Time LF = Lasted Finished Time

Table shows the PERT table that indicates the critical path of each activity. In our study, all activities are critical, it

means that the researchers don’t have a time to rest while doing this study.