LS = LF – Activity time
LS/LF Times
A C F
0 2 2 4 4 7
2 2 3
Start E H
0 0 4 8 13 15
13 15
0 4 2
B D – Activity timeG
LS = LF
0 3 3 7 8 13
3 4 5 LF = EF
of Project
LS/LF Times
A C F
0 2 2 4 4 7
10 13
2 2 3
Start E H
0 0
LF 4= Min(LS
8 of 13 15
following activity) 13 15
0 4 2
B D G
0 3 3 7 8 13
3 4 5
LS/LF Times
LF = Min(4, 10)
A C F
0 2 2 4 4 7
2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
8 13
3 4 5
LS/LF Times
LF = Min(4, 10)
A C F
0 2 2 4 4 7
2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
8 13
3 4 5
LS/LF Times
A C F
0 2 2 4 4 7
0 2 2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5
Computing Slack Time
After computing the ES, EF, LS, and LF times for all
activities, compute the slack or free time for each
activity
Slack = LS – ES or Slack = LF – EF