You are on page 1of 13

Critical Path

Vazi Okhandiar, PMP, MCT, MBA, MSCS, BSEE


Critical Path Method (CPM)
 The critical path method is a project modeling technique
developed in the late 1950s by Morgan R. Walker of DuPont
and James E. Kelley, Jr. of Remington Rand. - Wikipedia
Critical Path
 The critical path method was examined by the United States
Navy, and established a version in 1958 called a PERT
(Program Evaluation and Review Technique) analysis. PERT
claimed to reduce project management time by up to 42
percent, and was first used in the development of the Polaris
missile.

Ref: http://www.ehow.com/about_4703555_what-critical-
path.html#ixzz2igTEV3Q7
Critical Path
 A Critical Path is the path with the least amount of float or
slack time. A float time is the amount of time that an activity
can be delayed without delaying the project.
 A Critical Path is the longest amount of time it will take to
complete the project.
 A Critical Path usually has 0 float but may have negative float
if the end task is constrained to an early finish date.
 If any of the task identified in the critical path is late, then the
project will be late.
6. Steps for identifying Critical Path
1. Specify the activates, duration and dependencies
2. Draw a network diagram.
3. Perform the forward pass to identify all Early Start and Early Finish times for
the network.
Early Finish = Early Start + Duration

4. Perform the backward pass to identify all Late Start and Late Finish times
for the network.
Late Start = Late Finish – Duration

5. Calculate the slack time.


Float = Late Start (LS) – Early Start (ES)

6. Identify the task on critical path with 0 float (slack) time.


1. Task/Duration/Predecessor
TASK Duration Predecessor

A 2 ----
B 2 A
C 1 A
D 3 A
E 1 C,D
F 3 B
G 2 E,F
Terminologies
 ID – Task ID
 D- Duration
 ES – Early Start
 EF – Early Finish
 LS – Late Start ES EF
 LF – Late Finish F ID DR
 S - Slack
LS LF
2. Network Diagram

B 2 F 3

Activity

A 2 C 1 G 2

Duration

ES EF

D 3 E 1 F ID DR

LS LF
3. Forward Pass
2 4 4 7
B 2 F 3

Early Early
Start Finish Duration= 9days
7 9
0 2 2 3
G 2
A 2 C 1

2 5 5 6
ES EF
D 3 E 1
1st task starts at 0 F ID DR
EF = ES + DR
LS LF
ES = EF of predecessor
When more than one predecessor, pick the larger #
4. Backward Pass
2 4 4 7
B 2 F 3
2 4 4 7
1st task should end
with LS = 0.
2 3 7 9
0 2
C 1 G 2
A 2
5 6 7 9
0 2

Late Late
Start Finish

2 5 5 6 ES EF
D 3 E 1 F ID DR
LS = LF - DR 3 6 6 7 LS LF
LF = LS of successor

When more than one successor, pick the smallest #


5. Slack / Float
2 4 4 7
0 B 2 0 F 3
2 4 4 7

7 9
0 2 2 3
0 G 2
0 A 2 3 C 1
7 9
0 2 5 6
Float = LS – ES

2 5 5 6 ES EF
1 D 3 1 E 1 F ID DR
3 6 6 7 LS LF

Float = Late Start (LS) – Early Start (ES)


6. Critical Path
The path with 0 Float is 4 7
2 4
the critical path.
0 B 2 0 F 3
2 4 4 7

A-B-F-G is the critical path.


7 9
0 2 5 6
0 A 2 0 C 1 0 G 2
0 2 5 6 7 9

2 5 5 6 ES EF

0 D 3 1 E 1 F ID DR

2 5 6 7 LS LF

LS = LF - DR
LF = LS of successor
Thank You!
Vazi Okhandiar, PMP, MCT, MBA, MSCS, BSEE
NR Computer Learning Center
1835 W. Orangewood, Suite 200
Orange, CA 92868
www.nrclc.com . (714) 505. 3475
info@nrclc.com

You might also like