CPM/PERT
Solution:
Network Diagram:
W
V Y Z
X
Calculating the early start, early finish, late start and late finish of the activities:
ES Activity EF
LS Duration LF
5 W 8
6 3 9
0 V 5
0 5 5 9 Y 11 11 Z 14
9 2 11 11 3 14
5 X 9
5 4 9
Critical Path:
V Y Z
Question 2: Draw network diagram and find the critical path by using the data
from the following table;
Network diagram
Calculating the early start, early finish, late start and late finish of the activities:
Formulas required
Early Start (ES): Early Finish (EF) of the entering arrow Late Start (LS): Late Finish (LF) + t
4 22
3 9 E (7) 16
A (3)
2
C (5)
9 5 G (2)
0 1 B (4) D (5) 4 F (5) H (10) 7 24
0 3 6 24
4 14
4 14