CPM

Critical Path Method


CPM
• Activities timing are deterministic
• Single duration
• Longest path of the network
• Earliest start time – forward pass
– Formula ESj = maxi (ESi + Dij)
• Latest completion time – backward pass
– Formula LCi = minj (LCj - Dij)
Earliest start time - Forward Pass
6
8
2 D(2)
0 A(6)
5

1 I(5)
B(3) 3 17
3 E(3)
8
C(4)
6 9
F(5)
H(5) J(3)
4
4 G(3) 7
14
Latest completion time – backward pass
10
6 12
8
0 2 D(2)
0 A(6)
5
6 17
1 I(5)
B(3) 3 17
3 E(3)
9
8
C(4)
6 9
F(5)
H(5) J(3)
4 4
4 G(3) 7 14
14
CPM - Conditions
1. ESi = LCi (starting node)
2. ESj = LCj (ending node)
3. ESj – ESi = LCj – LCi = Dij
10
6 12
8
0 2 D(2)
0 A(6)
5
6 17
1 I(5) 17
B(3) 3
3 E(3) 9
9 8
6
C(4)
F(5)
H(5) J(3)
4 4
4
G(3) 7 14
14
Activity
Activity Predecessor O M P Mean = Variance =
(O+4M+P)/ 6 [(P – O)/6]2
A - 2 3 4
B - 2 3 4
C B 6 7 8
D A 5 6 7
E A 4 5 6
F C, D 4 8 12
G C, D 4 5 6
H G 2 3 4
I E 2 4 6

Construct the network and find the critical path after


forward and backward pass