Instructor: Nadeem Khalil

Civil Engg. AMU

Problem 1:

A city’s water demand is 7000 m3 per day. What is the source water (feedwater) flow required for a
brackish water RO, if the plant recovery rate is 78 percent?

Problem 2:
At a brackish water RO treatment plant, the total dissolved solids (TDS) concentrations for the pre-
treated feedwater and the product water are 2800 and 90 mg/L, respectively. Determine the percentage of salt rejection
and salt passage.