Project: Flowmeter 23BJ30 & 23BJ31 piping modification

Subject: Project Costing Estimate


Project Owner: RCF
WO: 329656
PR:

Item Description Qty Units u/ rates Amount


Piping Modification
1 Task
Isolation, drainage, others 1 hr
Dismantle instrument 1 hr
Cutting piping 2 hr
Welding 3 hr
Reinstall instrument 2 hr

2 Manpower
Welder - 6G, SS pipe, GTAW 1 man
Pipe Fitter 1 man
Helper 1 man

3 Material / Tools
Welding Set 1 set
Hand grinder with cutting disc 1 set
Filler Rod 1 lot
Spana Set 1 set
DN 15 SS Seemless pipe 3 feet

0.00
Remarks