You are on page 1of 76

DOOSAN - PT.

HUTAMA KARYA CONSORTIUM


JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building &ESP Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 17.00 v
DATE / PRIODE : Saturday, 01 Oktober 2022 19.00 - 22.00

ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Welding Joint parsial 1 joint 34 34 0 0 34 0
2 Repair Fit up internal di area CCB partial 2 lot 19 0 3 3 3 16 By QC WI- IBB
3 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 64 0 0 64 1
Pipe dia 2 inch (branch) btg 7 6 0 0 6 1
Pipe dia 3 inch (mainline + riser) btg 14 13 0 0 13 1
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 12 0 0 12 2
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP
1 Hanger support Threadrod M8, M10, M12 Lt 2 titik 139 6 44 44 50 89 Dynaset,threadrod & nut, belum hanger clamp
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0 Dynaset,threadrod & nut, belum hanger clamp
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 16 0 0 0 0 16
Pipe dia 1.5 inch (branch) btg 33 0 0 0 0 33
Pipe dia 2 inch (branch) btg 7 0 0 0 0 7
Pipe dia 3 inch (mainline + riser) btg 5 0 0 0 0 5
Pipe dia 4 inch (mainline + riser) btg 6 0 0 0 0 6
Pipe dia 6 inch (mainline + riser) btg 14 0 0 0 0 14
Pipe dia 8 inch (mainline + riser) btg 3 0 0 0 0 3
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 Pemasangan jalur hydrant lt 2 & Lt 3
2 Finishing branch tapping ke mainline dengan epoxy
B FGD & ESP lt 2
Marking & pemasangan fix support
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 1 Trafo Las (2 set)


2 HSE person 1 2 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 1 5 5 Bor Besi (2 set)
6 Skill person 1 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 2 8
Jumlah 9 9
REMARK
ESP, area sudah rapat ladder
CCB, area lt 3 ada pekerjaan pemasangan hebel, menghambat pemasangan instalasi hydrant
area lt GF ada area outdoor ada pekerjaan erection struktur

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED

…...................

SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER


Saturday, 01 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Morning toolbox meeting ESP & FGD, Fabrikasi thread rod menyesuaikan panjang BOP ESP & FGD lt 2, marking & pemasangan hanger clamp

Proses repair fit up internal WI Indobara partial 2 untuk sisa


ESP & FGD, Scafolding mobile sudah dibangun di lt 2 Proses repair fit up internal WI Indobara partial 2 untuk sisa weldingan Joint No 63
weldingan Joint No 62

Material receiving HK & IRT Material receiving HK & IRT


Material receiving HK & IRT
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Approved item by owner


Approved item by owner Approved item by owner

Approved item by owner Approved item by owner Approved item by owner

Approved item by owner Approved item by owner Approved item by owner


DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building &ESP Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 17.00 v
DATE / PRIODE : Monday, 03 Oktober 2022 19.00 - 22.00

ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Welding Joint parsial 1 joint 34 34 0 0 34 0
2 Repair Fit up internal di area CCB partial 2 lot 19 3 3 3 6 13 By QC WI- IBB
3 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 64 0 0 64 1
Pipe dia 2 inch (branch) btg 7 6 0 0 6 1
Pipe dia 3 inch (mainline + riser) btg 14 13 0 0 13 1
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 12 0 0 12 2
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP
1 Hanger support Threadrod M8, M10, M12 Lt 2 titik 139 50 0 0 50 89 Dynaset,threadrod & nut, belum hanger clamp
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0 Dynaset,threadrod & nut, belum hanger clamp
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 16 0 0 0 0 16
Pipe dia 1.5 inch (branch) btg 33 0 0 0 0 33
Pipe dia 2 inch (branch) btg 7 0 0 0 0 7
Pipe dia 3 inch (mainline + riser) btg 5 0 0 0 0 5
Pipe dia 4 inch (mainline + riser) btg 6 0 0 0 0 6
Pipe dia 6 inch (mainline + riser) btg 14 0 0 0 0 14
Pipe dia 8 inch (mainline + riser) btg 3 0 0 0 0 3
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 Pemasangan jalur hydrant lt 2 & Lt 3
2 Finishing branch tapping ke mainline dengan epoxy
B FGD & ESP lt 2
Marking & pemasangan fix support
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 Resibon poles 4 inch 2 ea 1 Trafo Las (2 set)


2 HSE person 1 2 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 0 5 5 Bor Besi (2 set)
6 Skill person 1 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 1 8
Jumlah 7 9
REMARK
ESP, area sudah rapat ladder
CCB, area lt 3 ada pekerjaan pemasangan hebel, menghambat pemasangan instalasi hydrant
area lt GF ada area outdoor ada pekerjaan erection struktur
area CCB lt 1 sedang berjalan cleaning area untuk epoxy lantai

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED
…...................

SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER


Monday, 03 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Morning toolbox meeting Prefabrikasi workshop, moving pipa untuk persiapan fabrikasi Prefabrikasi workshop, moving pipa untuk persiapan fabrikasi

Proses repair fit up internal WI Indobara partial 2 untuk sisa


Proses repair fit up internal WI Indobara partial 2 untuk sisa Update pergeseran laydown untuk kontainer weldingan Joint No 59
weldingan Joint No 59

Proses repair fit up internal WI Indobara partial 2 Joint 60 Housekeeping area kerja
Rapair fit up join 61
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building &ESP Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 17.00 v
DATE / PRIODE : Tuesday, 04 Oktober 2022 19.00 - 22.00 v
ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Welding Joint parsial 2 joint 57 0 2 2 2 55 Total 12 Dinch
2 Repair Fit up internal di area CCB partial 2 lot 19 0 3 3 3 16 By QC WI- IBB
3 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 64 1 1 65 0
Pipe dia 2 inch (branch) btg 7 6 0 0 6 1
Pipe dia 3 inch (mainline + riser) btg 14 13 1 1 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 12 1 1 13 1
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP
1 Hanger support Threadrod M8, M10, M12 Lt 2 titik 139 50 0 0 50 89 Dynaset,threadrod & nut, belum hanger clamp
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0 Dynaset,threadrod & nut, belum hanger clamp
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 16 0 0 0 0 16
Pipe dia 1.5 inch (branch) btg 33 0 0 0 0 33
Pipe dia 2 inch (branch) btg 7 0 0 0 0 7
Pipe dia 3 inch (mainline + riser) btg 5 0 0 0 0 5
Pipe dia 4 inch (mainline + riser) btg 6 0 0 0 0 6
Pipe dia 6 inch (mainline + riser) btg 14 0 0 0 0 14
Pipe dia 8 inch (mainline + riser) btg 3 0 0 0 0 3
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 Pemasangan jalur hydrant lt 2 & Lt 3
2 Finishing branch tapping ke mainline dengan epoxy
B FGD & ESP lt 2
Marking & pemasangan fix support
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 1 Trafo Las (2 set)


2 HSE person 1 2 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 1 5 5 Bor Besi (2 set)
6 Welder person 1 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 1 8
Jumlah 8 9
REMARK
ESP, area sudah rapat ladder
CCB, area lt 3 ada pekerjaan pemasangan hebel, menghambat pemasangan instalasi hydrant
area lt GF ada area outdoor ada pekerjaan erection struktur

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED
…...................

SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER


Tuesday, 04 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Morning toolbox meeting Prefabrikasi Pluit, fabrikasi manifold untuk hydrotest Erection pipa riser 2

Pngecekan gap & bevel angle riser 2 Welding inspeksi internal, visual Welding inspeksi visual

Proses welding Housekeeping area kerja


pross welding
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building &ESP Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 17.00 v
DATE / PRIODE : Wednesday, 05 Oktober 2022 19.00 - 22.00 v
ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Welding Joint parsial 2 joint 57 2 11 11 13 44 Total 61.5 Dinch
2 Repair Fit up internal di area CCB partial 2 lot 19 10 7 7 17 2 By QC WI- IBB
3 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 65 0 0 65 0
Pipe dia 2 inch (branch) btg 7 6 0 0 6 1
Pipe dia 3 inch (mainline + riser) btg 14 14 0 0 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 13 0 0 13 1
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP
1 Hanger support Threadrod M8, M10, M12 Lt 2 titik 139 50 0 0 50 89 Dynaset,threadrod & nut, belum hanger clamp
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0 Dynaset,threadrod & nut, belum hanger clamp
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 16 0 0 0 0 16
Pipe dia 1.5 inch (branch) btg 33 0 0 0 0 33
Pipe dia 2 inch (branch) btg 7 0 0 0 0 7
Pipe dia 3 inch (mainline + riser) btg 5 0 0 0 0 5
Pipe dia 4 inch (mainline + riser) btg 6 0 0 0 0 6
Pipe dia 6 inch (mainline + riser) btg 14 0 0 0 0 14
Pipe dia 8 inch (mainline + riser) btg 3 0 0 0 0 3
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 Pemasangan jalur hydrant lt 2 & Lt 3
2 Finishing branch tapping ke mainline dengan epoxy
B FGD & ESP lt 2
Marking & pemasangan fix support
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 Kawat Las LB 52 U 5 kg 1 Trafo Las (2 set)


2 HSE person 1 2 Con Red 3 x 2-1/2 inch 13 ea 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 1 5 5 Bor Besi (2 set)
6 Welder person 1 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 1 8
Jumlah 8 9
REMARK
ESP, area sudah rapat ladder
CCB, area lt 3 ada pekerjaan pemasangan hebel, menghambat pemasangan instalasi hydrant
area lt GF ada area outdoor ada pekerjaan erection struktur

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED
…...................

SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER


Wednesday, 05 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Morning toolbox meeting Prefabrikasi Pluit, fabrikasi manifold untuk hydrotest Repair fit up

Pngecekan gap & bevel angle Fit up inspeksi setelah repair Welding gap inspection after repair

Aligment inspeksi setelah repair Lanjut welding overtime kedua


pross welding
Wednesday, 05 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Hasil welding pipa butweld dia inch


Hasil welding pipa butweld dia inch Hasil welding pipa butweld dia inch

Hasil welding pipa butweld dia inch Hasil welding pipa butweld dia inch Hasil welding pipa butweld dia inch

Hasil welding pipa butweld dia inch Hasil welding pipa butweld dia inch Housekeeping area kerja
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building &ESP Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 17.00 v
DATE / PRIODE : Thuesday, 06 Oktober 2022 19.00 - 22.00

ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Welding Joint parsial 2 joint 57 13 10 10 23 34 Total 61.5 Dinch
2 Repair Fit up internal di area CCB partial 2 lot 19 17 2 2 19 0 By QC WI- IBB
3 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 65 0 0 65 0
Pipe dia 2 inch (branch) btg 7 6 0 0 6 1
Pipe dia 3 inch (mainline + riser) btg 14 14 0 0 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 13 0 0 13 1
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP
1 Hanger support Threadrod M8, M10, M12 Lt 2 titik 139 50 0 0 50 89 Dynaset,threadrod & nut, belum hanger clamp
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0 Dynaset,threadrod & nut, belum hanger clamp
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 16 0 0 0 0 16
Pipe dia 1.5 inch (branch) btg 33 0 0 0 0 33
Pipe dia 2 inch (branch) btg 7 0 0 0 0 7
Pipe dia 3 inch (mainline + riser) btg 5 0 0 0 0 5
Pipe dia 4 inch (mainline + riser) btg 6 0 0 0 0 6
Pipe dia 6 inch (mainline + riser) btg 14 0 0 0 0 14
Pipe dia 8 inch (mainline + riser) btg 3 0 0 0 0 3
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 Pemasangan jalur hydrant lt 2 & Lt 3
2 Finishing branch tapping ke mainline dengan epoxy
B FGD & ESP lt 2
Marking & pemasangan fix support
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 Kawat Las LB 52 U 5 kg 1 Trafo Las (2 set)


2 HSE person 1 2 13 ea 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 1 5 5 Bor Besi (2 set)
6 Welder person 1 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 1 8
Jumlah 8 9
REMARK
ESP, area sudah rapat ladder
CCB, area lt 3 ada pekerjaan pemasangan hebel, menghambat pemasangan instalasi hydrant
area lt GF ada area outdoor ada pekerjaan erection struktur
Hasil welding perlu dibrush sebelum di visual check

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED
…...................

SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER


Thuesday, 06 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Morning toolbox meeting Inspeksi Full Body Harnest Fabrikasi fit test piece 4 inch, 5 set

Pngecekan gap & bevel angle Fit up inspeksi setelah repair Fabrikasi test piece 2 inch, 5 set

Aligment inspeksi setelah repair RFI material receiving


pross welding
Thuesday, 06 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Hasil welding pipa butweld dia inch


Hasil welding pipa butweld dia inch Hasil welding pipa butweld dia inch

Hasil welding pipa butweld dia inch Hasil welding pipa butweld dia inch Hasil welding pipa butweld dia inch

Hasil welding pipa butweld dia inch Hasil welding pipa butweld dia inch Housekeeping area kerja
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building &ESP Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 17.00 v
DATE / PRIODE : Friday, 07 Oktober 2022 19.00 - 22.00 v
ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Welding Joint parsial 2 joint 57 23 17 17 40 17 Total 53.5 Dinch
2 Hydrant instalation to IHB riser (F set) set 8 2 2 2 4 4
3 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 65 0 0 65 0
Pipe dia 2 inch (branch) btg 7 6 0 0 6 1
Pipe dia 3 inch (mainline + riser) btg 14 14 0 0 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 13 0 0 13 1
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP
1 Hanger support Threadrod M8, M10, M12 Lt 2 titik 139 50 0 0 50 89 Dynaset,threadrod & nut, belum hanger clamp
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0 Dynaset,threadrod & nut, belum hanger clamp
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 16 0 0 0 0 16
Pipe dia 1.5 inch (branch) btg 33 0 0 0 0 33
Pipe dia 2 inch (branch) btg 7 0 0 0 0 7
Pipe dia 3 inch (mainline + riser) btg 5 0 0 0 0 5
Pipe dia 4 inch (mainline + riser) btg 6 0 0 0 0 6
Pipe dia 6 inch (mainline + riser) btg 14 0 0 0 0 14
Pipe dia 8 inch (mainline + riser) btg 3 0 0 0 0 3
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 Pemasangan jalur hydrant lt 2 & Lt 3
2 Finishing branch tapping ke mainline dengan epoxy
B FGD & ESP lt 2
Marking & pemasangan fix support
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 Kawat Las LB 52 U 5 kg 1 Trafo Las (2 set)


2 HSE person 1 2 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 1 5 5 Bor Besi (2 set)
6 Welder person 1 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 1 8
Jumlah 8 9
REMARK
ESP, area sudah rapat ladder
CCB, area lt 3 ada pekerjaan pemasangan hebel, menghambat pemasangan instalasi hydrant
area lt GF ada area outdoor ada pekerjaan erection struktur
Hasil welding perlu dibrush sebelum di visual check
Listrik padam antara jam 13.30 sd 15.00

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED
…...................

SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER


Friday, 07 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Morning toolbox meeting Prefab Pluit, pipa on site Prefab luit, pipa onsite

Instalasi bevel angle Instalasi fixing branch dengan epoxy setelah welding Instalasi fixing branch dengan epoxy setelah welding

Welding joint, belum di cleaning dan belum visual check Welding joint, belum di cleaning dan belum visual check
Welding joint, belum di cleaning dan belum visual check
Friday, 07 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Welding joint, belum di cleaning dan belum visual check


Welding joint, belum di cleaning dan belum visual check Welding joint, belum di cleaning dan belum visual check

Welding joint, belum di cleaning dan belum visual check Welding joint, belum di cleaning dan belum visual check Welding joint, belum di cleaning dan belum visual check

Welding joint, belum di cleaning dan belum visual check


Welding joint, belum di cleaning dan belum visual check Housekeeping area kerja
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building & ESP (Field & workshop) Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 17.00 v
DATE / PRIODE : Saturday, 08 Oktober 2022 19.00 - 22.00

ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Welding Joint parsial 2 joint 57 40 9 9 49 8 Total 28 Dinch
2 Hydrant instalation to IHB riser (F set) set 8 4 2 2 6 2 Riser 2 Lt 2 & Lt 3
3 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 65 0 0 65 0
Pipe dia 2 inch (branch) btg 7 6 0 0 6 1
Pipe dia 3 inch (mainline + riser) btg 14 14 0 0 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 13 0 0 13 1
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP
1 Hanger support Threadrod M8, M10, M12 Lt 2 titik 139 50 0 0 50 89 Dynaset,threadrod & nut, belum hanger clamp
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0 Dynaset,threadrod & nut, belum hanger clamp
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Painting Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 16 0 0 0 0 16
Pipe dia 1.5 inch (branch) btg 33 0 0 0 0 33
Pipe dia 2 inch (branch) btg 7 0 0 0 0 7
Pipe dia 3 inch (mainline + riser) btg 5 0 0 0 0 5
Pipe dia 4 inch (mainline + riser) btg 6 0 2 2 2 4 Surface preparation & painting primer
Pipe dia 6 inch (mainline + riser) btg 14 0 3 3 3 11
Pipe dia 8 inch (mainline + riser) btg 3 0 1 1 1 2
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 Pemasangan jalur hydrant lt 2 & Lt 3
2 Finishing branch tapping ke mainline dengan epoxy
B FGD & ESP lt 2
Marking & pemasangan fix support
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 Kawat Las LB 52 U 5 kg 1 Trafo Las (2 set)


2 HSE person 1 2 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 1 5 5 Bor Besi (2 set)
6 Welder person 1 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 1 8
Jumlah 8 9
REMARK
ESP, area sudah rapat ladder
CCB, area lt 3 ada pekerjaan pemasangan hebel, menghambat pemasangan instalasi hydrant
area lt GF ada area outdoor ada pekerjaan erection struktur
Hasil welding perlu dibrush sebelum di visual check

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED
…...................

SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER


Saturday, 08 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Morning toolbox meeting Site, pemasangan instalasi hydrant landing calve lt 2 dan Lt 3 Site, leveling instalasi

Prefab Pluit ESP, site preparation painting mainline Prefab Pluit ESP, painting primer mainline Prefab Pluit mainline, primer coat

Site, welding on site Cleaning area


Site, beveling test piece untuk WQT
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building & ESP (Field & workshop) Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 17.00 v
DATE / PRIODE : Sunday, 09 Oktober 2022 19.00 - 22.00

ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Welding Joint parsial 2 joint 57 40 0 0 40 17 Total 28 Dinch
2 Hydrant instalation to IHB riser (F set) set 8 4 0 0 4 4 Riser 2 Lt 2 & Lt 3
3 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 65 0 0 65 0
Pipe dia 2 inch (branch) btg 7 6 0 0 6 1
Pipe dia 3 inch (mainline + riser) btg 14 14 0 0 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 13 0 0 13 1
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP
1 Hanger support Threadrod M8, M10, M12 Lt 2 titik 139 50 0 0 50 89 Dynaset,threadrod & nut, belum hanger clamp
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0 Dynaset,threadrod & nut, belum hanger clamp
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Painting Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 16 0 0 0 0 16
Pipe dia 1.5 inch (branch) btg 33 0 0 0 0 33
Pipe dia 2 inch (branch) btg 7 0 0 0 0 7
Pipe dia 3 inch (mainline + riser) btg 5 0 0 0 0 5
Pipe dia 4 inch (mainline + riser) btg 6 0 0 0 0 6 Surface preparation & painting primer
Pipe dia 6 inch (mainline + riser) btg 14 0 0 0 0 14
Pipe dia 8 inch (mainline + riser) btg 3 0 0 0 0 3
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 Pemasangan jalur hydrant lt 2 & Lt 3
2 Finishing branch tapping ke mainline dengan epoxy
B FGD & ESP lt 2
Marking & pemasangan fix support
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 5 kg 1 Trafo Las (2 set)


2 HSE person 2 2 ELCB box (1 set)
3 Supervisor/ Foreman person 0 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 0 4 4 Bor Beton (3 set)
5 Fitter person 0 5 5 Bor Besi (2 set)
6 Welder person 0 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 0 7 7 Lampu Tembak ( 4 set)
8 Helper person 0 8
Jumlah 1 9
REMARK
Stanby di Suralaya, tidak ada kegiatan di site

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED
…...................

SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER


DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building & ESP (Field & workshop) Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 17.00 v
DATE / PRIODE : Monday, 10 Oktober 2022 19.00 - 22.00

ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Welding Joint parsial 2 joint 57 49 8 8 57 0 Total 28.5 Dinch (Belum visual check & repair)
2 Hydrant instalation to IHB riser (F set) set 8 6 1 1 7 1 Riser 1 lantai GF
3 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 65 0 0 65 0
Pipe dia 2 inch (branch) btg 7 6 1 1 7 0
Pipe dia 3 inch (mainline + riser) btg 14 14 0 0 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 13 0 0 13 1
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP
1 Hanger support Threadrod M8, M10, M12 Lt 2 titik 139 50 0 0 50 89 Dynaset,threadrod & nut, belum hanger clamp
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0 Dynaset,threadrod & nut, belum hanger clamp
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Painting Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 16 0 16 16 16 0
Pipe dia 1.5 inch (branch) btg 33 0 25 25 25 8
Pekerjaan dilakukan di Workshop Pluit
Pipe dia 2 inch (branch) btg 7 0 0 0 0 7
Pipe dia 3 inch (mainline + riser) btg 5 0 2 2 2 3
Pipe dia 4 inch (mainline + riser) btg 6 2 2 2 4 2 Surface preparation & painting primer
Pipe dia 6 inch (mainline + riser) btg 14 3 4 4 7 7 Thickness Primer layer, > 80 Micron
Pipe dia 8 inch (mainline + riser) btg 3 1 1 0 1 2
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 Pemasangan jalur hydrant lt 2 & Lt 3
2 Finishing branch tapping ke mainline dengan epoxy
B FGD & ESP lt 2
Marking & pemasangan fix support
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 Kawat Las LB 52 U 1 kg 1 Trafo Las (2 set)


2 HSE person 1 2 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 1 5 5 Bor Besi (2 set)
6 Welder person 1 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 1 8
Jumlah 8 9
REMARK
ESP, area sudah rapat ladder
CCB, area lt 3 ada pekerjaan pemasangan hebel, menghambat pemasangan instalasi hydrant
area lt GF ada area outdoor ada pekerjaan erection struktur
Hasil welding perlu dibrush sebelum di visual check

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED
…...................

SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER


Monday, 10 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Morning toolbox meeting Kondisi terakhir laydown kontainer Site, pemasangan jalur hydrant riser 1 area GF

Site, Cleaning welding & pemasangan F instalasi landing valve GF Site, wellding joint belum cleaning & visual check internal Site, wellding joint belum cleaning & visual check internal

Site, wellding joint belum cleaning & visual check internal Cleaning area
Site, wellding joint belum cleaning & visual check internal
Monday, 10 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Prefab Pluit, Thickness check layer primer pipa 3 inch mainline


Prefab Pluit, Thickness check layer primer pipa 3 inch mainline Prefab Pluit, Thickness check layer primer pipa 6 inch mainline

Prefab Pluit, Thickness check layer primer pipa 1-1/2 inch mainline Prefab Pluit, Thickness check layer primer pipa 6 inch mainline Prefab Pluit, Thickness check layer primer pipa 6 inch mainline

Prefab Pluit, Thickness check layer primer pipa 6 inch mainline


Prefab Pluit, Thickness check layer primer pipa 1 inc
Prefab Pluit, Thickness check layer primer pipa 1 inch
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building & ESP (Field & workshop) Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 17.00 v
DATE / PRIODE : Tuesday, 11 Oktober 2022 19.00 - 22.00

ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Welding Visually check joint 57 0 22 22 22 35 By QC IBB
2 Hydrant instalation to IHB riser (F set) set 8 6 1 1 7 1 Riser 1 lantai GF
3 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 65 0 0 65 0
Pipe dia 2 inch (branch) btg 7 6 1 1 7 0
Pipe dia 3 inch (mainline + riser) btg 14 14 0 0 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 13 0 0 13 1
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP
1 Hanger support Threadrod M8, M10, M12 Lt 2 titik 139 50 0 0 50 89 Dynaset,threadrod & nut, belum hanger clamp
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0 Dynaset,threadrod & nut, belum hanger clamp
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Painting Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 16 16 0 0 16 0
Pipe dia 1.5 inch (branch) btg 33 25 8 8 33 0
Pekerjaan dilakukan di Workshop Pluit
Pipe dia 2 inch (branch) btg 7 0 7 7 7 0
Pipe dia 3 inch (mainline + riser) btg 5 2 3 3 5 0
Pipe dia 4 inch (mainline + riser) btg 6 4 2 2 6 0 Surface preparation & painting primer
Pipe dia 6 inch (mainline + riser) btg 14 7 7 7 14 0 Thickness Primer layer, > 80 Micron
Pipe dia 8 inch (mainline + riser) btg 3 1 0 0 1 2
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 Pemasangan jalur hydrant lt 2 & Lt 3
2 Finishing branch tapping ke mainline dengan epoxy
B FGD & ESP lt 2
Marking & pemasangan fix support
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 Mata Gerinda potong 4 inch 1 box 1 Trafo Las (2 set)
2 HSE person 1 2 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 1 5 5 Bor Besi (2 set)
6 Welder person 1 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 1 8
Jumlah 8 9
REMARK

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED
…...................

SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER


Tuesday, 11 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Morning toolbox meeting Houseekping area Visual check welding internal

Visual check welding internal QC IBB, selanjutnya akan di FU untuk Visual check welding internal QC IBB, selanjutnya akan di FU Koordinasi terkait inspeks dengan Spv QC HK
repair welding untuk repair welding

Visual check welding internal QC IBB, selanjutnya akan di FU untuk Cleaning area
repair welding Site, wellding joint belum cleaning & visual check internal
Tuesday, 11 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Prefab Pluit, proses welding joint manifold


Prefab Pluit, welding manifold flangs inner & thredoulet Prefab Pluit, welding flangs manifold

Prefab Pluit, threading pipa branch Prefab Pluit, threading pipa branch

Prefab Pluit, threading pipa branch


Prefab Pluit, Perapihan dan tagging spool pipe
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building & ESP (Field & workshop) Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 17.00 v
DATE / PRIODE : Wednesday, 12 Oktober 2022 19.00 - 22.00

ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Welding Visually check joint 57 22 35 35 57 0 By QC IBB (on progress repair by welder borongan)
2 Hydrant instalation to IHB riser (F set) set 8 7 0 0 7 1 Riser 1 lantai GF
3 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 65 0 0 65 0
Pipe dia 2 inch (branch) btg 7 6 1 1 7 0
Pipe dia 3 inch (mainline + riser) btg 14 14 0 0 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 13 0 0 13 1
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP
1 Hanger support Threadrod M8, M10, M12 Lt 2 titik 139 50 0 0 50 89 Dynaset,threadrod & nut, belum hanger clamp
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0 Dynaset,threadrod & nut, belum hanger clamp
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Painting Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 16 16 0 0 16 0
Pipe dia 1.5 inch (branch) btg 33 25 8 8 33 0
Pekerjaan dilakukan di Workshop Pluit
Pipe dia 2 inch (branch) btg 7 0 7 7 7 0
Pipe dia 3 inch (mainline + riser) btg 5 2 3 3 5 0
Pipe dia 4 inch (mainline + riser) btg 6 4 2 2 6 0 Surface preparation & painting primer
Pipe dia 6 inch (mainline + riser) btg 14 7 7 7 14 0 Thickness Top Coat layer, > 180 Micron
Pipe dia 8 inch (mainline + riser) btg 3 1 0 0 1 2
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 Pemasangan jalur hydrant lt 2 & Lt 3
2 Finishing branch tapping ke mainline dengan epoxy
B FGD & ESP lt 2
Marking & pemasangan fix support
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 Mata Gerinda potong 4 inch 1 box 1 Trafo Las (2 set)
2 HSE person 1 2 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 1 5 5 Bor Besi (2 set)
6 Welder person 1 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 1 8
Jumlah 8 9
REMARK
ESP, area sudah rapat ladder
CCB, area lt 3 ada pekerjaan pemasangan hebel, menghambat pemasangan instalasi hydrant
area lt GF ada area outdoor ada pekerjaan erection struktur
Hasil welding on going repair

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED
…...................

SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER


Wednesday, 12 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Morning toolbox meeting Houseekping area Visual check welding internal

Visual check welding internal QC IBB, selanjutnya akan di FU untuk Visual check welding internal QC IBB, selanjutnya akan di FU Koordinasi terkait inspeks dengan Spv QC HK
repair welding untuk repair welding

Visual check welding internal QC IBB, selanjutnya akan di FU untuk Cleaning area
repair welding Site, wellding joint belum cleaning & visual check internal
Wednesday, 12 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Prefab Pluit, packaging pipa mainline


Prefab Pluit, assembly joint Prefab Pluit, threading wuality check, 2 putaran hand tight. sisa 2-
3 drat untuk dikencangkan dengan kunci pipa

Prefab Pluit, painting report thickness top coat mainline Prefab Pluit, painting report thickness top coat mainline Prefab Pluit, painting report thickness top coat mainline

Prefab Pluit, painting report thickness top coat mainline


Prefab Pluit, painting report thickness top coat mainline
Prefab Pluit, painting report thickness top coat mainline
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building & ESP (Field & workshop) Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 17.00 v
DATE / PRIODE : Thursday, 13 Oktober 2022 19.00 - 22.00 v
ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Welding Visually check joint 57 22 35 35 57 0 By QC IBB (on progress repair by welder borongan)
2 Hydrant instalation to IHB riser (F set) set 8 7 0 0 7 1 Riser 1 lantai GF
3 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 65 0 0 65 0
Pipe dia 2 inch (branch) btg 7 6 1 1 7 0
Pipe dia 3 inch (mainline + riser) btg 14 14 0 0 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 13 0 0 13 1
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP
1 Hanger support Threadrod M8, M10, M12 Lt 2 titik 139 50 0 0 50 89 Dynaset,threadrod & nut, belum hanger clamp
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0 Dynaset,threadrod & nut, belum hanger clamp
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Painting Mainline, riser & threading branch (Total)
Pipe dia 1 inch (branch) btg 16 16 0 0 16 0
Pipe dia 1.5 inch (branch) btg 33 33 0 0 33 0
Pekerjaan dilakukan di Workshop Pluit
Pipe dia 2 inch (branch) btg 7 7 0 0 7 0
Pipe dia 3 inch (mainline + riser) btg 5 5 0 0 5 0
Pipe dia 4 inch (mainline + riser) btg 6 6 0 0 6 0 Surface preparation & painting primer
Pipe dia 6 inch (mainline + riser) btg 14 14 0 0 14 0 Thickness Top Coat layer, > 180 Micron
Pipe dia 8 inch (mainline + riser) btg 3 1 0 0 1 2
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 Pemasangan jalur hydrant lt 2 & Lt 3
2 Finishing branch tapping ke mainline dengan epoxy
B FGD & ESP lt 2
Marking & pemasangan fix support
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 Mata Gerinda potong 4 inch 1 box 1 Trafo Las (2 set)
2 HSE person 1 2 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 1 5 5 Bor Besi (2 set)
6 Welder person 1 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 1 8
Jumlah 8 9
REMARK
ESP, area sudah rapat ladder
CCB, area lt 3 ada pekerjaan pemasangan hebel, menghambat pemasangan instalasi hydrant
area lt GF ada area outdoor ada pekerjaan erection struktur
Hasil welding on going repair

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED
…...................

SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER


Thursday, 13 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Morning toolbox meeting Open RFI WQT Eksternal HK & Owner IRT

Mobilisasi pressure pump keluar site untuk dilakukan pressure Gate pass keluar pressure pump Koordinasi terkait inspeks dengan Spv QC HK
test manifold

Area mobilisasi antara CCB & ESP terhalang crane sehingga Manifold sudah di vendor titian untuk sertifikasi
transfer toolbox terhambat
Thursday, 13 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Prefab Pluit, packaging pipa mainline


Prefab Pluit, assembly joint Prefab Pluit, threading wuality check, 2 putaran hand tight. sisa 2-
3 drat untuk dikencangkan dengan kunci pipa

Persiapan pressure test manifold Pressure test tahap 1, 10 bar holding time 2 jam Pressure test tahap 2, 20 bar holding time 2 jam

Ball valve untuk tapping air


Rankaian manifold yang di pressure test, menggunakan pressure
gauge kalibrasi
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building & ESP (Field & workshop) Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 17.00 v
DATE / PRIODE : Friday, 14 Oktober 2022 19.00 - 22.00 v
ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Welding Visually check joint 57 22 35 35 57 0 By QC IBB (on progress repair by welder borongan)
2 Welder Qualify test set 4 0 4 4 4 0
3 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 65 0 0 65 0
Pipe dia 2 inch (branch) btg 7 6 1 1 7 0
Pipe dia 3 inch (mainline + riser) btg 14 14 0 0 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 13 0 0 13 1
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP
1 Hanger support Threadrod M8, M10, M12 Lt 2 titik 139 50 0 0 50 89 Dynaset,threadrod & nut, belum hanger clamp
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0 Dynaset,threadrod & nut, belum hanger clamp
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Painting Mainline, riser & threading branch (Total)
Pipe dia 1 inch (branch) btg 16 16 0 0 16 0
Pipe dia 1.5 inch (branch) btg 33 33 0 0 33 0
Pekerjaan dilakukan di Workshop Pluit
Pipe dia 2 inch (branch) btg 7 7 0 0 7 0
Pipe dia 3 inch (mainline + riser) btg 5 5 0 0 5 0
Pipe dia 4 inch (mainline + riser) btg 6 6 0 0 6 0 Surface preparation & painting primer
Pipe dia 6 inch (mainline + riser) btg 14 14 0 0 14 0 Thickness Top Coat layer, > 180 Micron
Pipe dia 8 inch (mainline + riser) btg 3 1 0 0 1 2
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 Pemasangan jalur hydrant lt 2 & Lt 3
2 Finishing branch tapping ke mainline dengan epoxy
B FGD & ESP lt 2
Marking & pemasangan fix support
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 Mata Gerinda potong 4 inch 1 box 1 Trafo Las (2 set)
2 HSE person 1 2 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 1 5 5 Bor Besi (2 set)
6 Welder person 1 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 1 8
Jumlah 8 9
REMARK
Area mobilisasi antara CCB & ESP terhalang super Crane yg sdang erection, menghambat transfer toolbox & material

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED
…...................

SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER


Friday, 14 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Morning toolbox meeting Visual check internal setelah repair SAfety induction visitor welder

Internal visual check setelah repair welding CCB lt 1 Internal visual check setelah repair welding CCB lt 1 SAfety induction visitor welder

Area mobilisasi antara CCB & ESP masih terhalang crane sehingga Cleaning area CCB lt 1 seelah toolbox dipindah
transfer toolbox terhambat
Friday, 14 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Briefing sebelum inspeksi welder qualify test Pengecekan tembusan hasil welding

Welder 01 dan 02 on going welding test piece pipa 2 inch dan pipa Pengecekan kawat las sesuai WPS Pengecekan dokumen all kandidat
4 inch

Welder 03 dan 04 on going welding test piece pipa 2 inch dan pipa
4 inch Test piece welder 03 dan 04
Test piece welder 01 dan 02
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building & ESP (Field & workshop) Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 17.00 v
DATE / PRIODE : Saturday, 15 Oktober 2022 19.00 - 22.00

ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Welding Visually check joint 57 22 35 35 57 0 By QC IBB (on progress repair by welder borongan)
2 Welder Qualify test set 4 0 4 4 4 0 Visual check by QC HK & IRT
3 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 65 0 0 65 0
Pipe dia 2 inch (branch) btg 7 6 1 1 7 0
Pipe dia 3 inch (mainline + riser) btg 14 14 0 0 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 13 0 0 13 1
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP
1 Hanger support Threadrod M8, M10, M12 Lt 2 titik 139 50 0 0 50 89 Dynaset,threadrod & nut, belum hanger clamp
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0 Dynaset,threadrod & nut, belum hanger clamp
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Painting Mainline, riser & threading branch (Total)
Pipe dia 1 inch (branch) btg 16 16 0 0 16 0
Pipe dia 1.5 inch (branch) btg 33 33 0 0 33 0
Pekerjaan dilakukan di Workshop Pluit
Pipe dia 2 inch (branch) btg 7 7 0 0 7 0
Pipe dia 3 inch (mainline + riser) btg 5 5 0 0 5 0
Pipe dia 4 inch (mainline + riser) btg 6 6 0 0 6 0 Surface preparation & painting primer
Pipe dia 6 inch (mainline + riser) btg 14 14 0 0 14 0 Thickness Top Coat layer, > 180 Micron
Pipe dia 8 inch (mainline + riser) btg 3 1 0 0 1 2
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 Pemasangan jalur hydrant lt 2 & Lt 3
2 Finishing branch tapping ke mainline dengan epoxy
B FGD & ESP lt 2
Marking & pemasangan fix support
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 1 box 1 Trafo Las (2 set)


2 HSE person 1 2 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 0 5 5 Bor Besi (2 set)
6 Welder candidat person 4 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 1 8
Jumlah 10 9
REMARK
Area mobilisasi antara CCB & ESP terhalang super Crane yg sdang erection, menghambat transfer toolbox & material
Hasil Visual check 1 welder lolos speciment pipa 4 inch an Hasim, untuk test piecce 2 inch reject semua

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED
…...................

SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER


Saturday, 15 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Morning toolbox meeting Fabrikasi support manifold Wrappng lubang pipa

Prefab, painting mainline Prefab, assembly fitting branch Prefab assembly fittnig branch

Prefab, painting mainline Cleaning area CCB lt 1 seelah toolbox dipindah


Prefab panting mainline
Saturday, 15 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Perpanjangan izin kerja Pengecekan hasil welding seteah repair, internal

Hasil welding test piece pipa 2 inch Hasil welding test piece pipa 4 inch

Visual check bersama QC HK QC IRT


Visual check bersama QC HK QC IRT
Visual check bersama QC HK QC IRT
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building & ESP (Field & workshop) Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 17.00 v
DATE / PRIODE : Monday, 17 Oktober 2022 19.00 - 22.00

ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Welding Visually check joint 57 22 35 35 57 0 By QC IBB (on progress repair by welder borongan)
2 Welder Qualify test set 4 0 4 4 4 0 Visual check by QC HK & IRT
3 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 65 0 0 65 0
Pipe dia 2 inch (branch) btg 7 6 1 1 7 0
Pipe dia 3 inch (mainline + riser) btg 14 14 0 0 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 13 0 0 13 1
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP
1 Hanger support Threadrod M8, M10, M12 Lt 2 titik 139 50 0 0 50 89 Dynaset,threadrod & nut, belum hanger clamp
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0 Dynaset,threadrod & nut, belum hanger clamp
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Painting Mainline, riser & threading branch (Total)
Pipe dia 1 inch (branch) btg 16 16 0 0 16 0
Pipe dia 1.5 inch (branch) btg 33 33 0 0 33 0
Pekerjaan dilakukan di Workshop Pluit
Pipe dia 2 inch (branch) btg 7 7 0 0 7 0
Pipe dia 3 inch (mainline + riser) btg 5 5 0 0 5 0
Pipe dia 4 inch (mainline + riser) btg 6 6 0 0 6 0 Surface preparation & painting primer
Pipe dia 6 inch (mainline + riser) btg 14 14 0 0 14 0 Thickness Top Coat layer, > 180 Micron
Pipe dia 8 inch (mainline + riser) btg 3 1 0 0 1 2
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 Pemasangan jalur hydrant lt 2 & Lt 3
2 Finishing branch tapping ke mainline dengan epoxy
B FGD & ESP lt 2
Marking & pemasangan fix support
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 1 box 1 Trafo Las (2 set)


2 HSE person 1 2 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 0 5 5 Bor Besi (2 set)
6 Welder candidat person 4 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 1 8
Jumlah 10 9
REMARK
Area mobilisasi antara CCB & ESP terhalang super Crane yg sdang erection, menghambat transfer toolbox & material
Hasil Visual check 1 welder lolos speciment pipa 4 inch an Hasim, untuk test piecce 2 inch reject semua

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED
…...................

SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER


Monday, 17 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Morning toolbox meeting Fabrikasi support manifold Wrappng lubang pipa

Prefab, painting mainline Prefab, assembly fitting branch Prefab assembly fittnig branch

Prefab, painting mainline Cleaning area CCB lt 1 seelah toolbox dipindah


Prefab panting mainline
Monday, 17 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Perpanjangan izin kerja Pengecekan hasil welding seteah repair, internal

Hasil welding test piece pipa 2 inch Hasil welding test piece pipa 4 inch

Visual check bersama QC HK QC IRT


Visual check bersama QC HK QC IRT
Visual check bersama QC HK QC IRT
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building & ESP (Field & workshop) Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 17.00 v
DATE / PRIODE : Tuesday, 18 Oktober 2022 19.00 - 22.00

ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Pembuatan test piece WQT 2 set 3 0 3 3 3 0 untuk 2 kandidat welder
2 Pemindahan toolx box ke area ESP lt GF lot 1 0 1 1 1 0
3 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 65 0 0 65 0
Pipe dia 2 inch (branch) btg 7 7 0 0 7 0
Pipe dia 3 inch (mainline + riser) btg 14 14 0 0 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 13 0 0 13 1
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP
1 Hanger support Threadrod M8, M10, M12 Lt 2 titik 139 50 0 0 50 89 Dynaset,threadrod & nut, belum hanger clamp
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0 Dynaset,threadrod & nut, belum hanger clamp
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Painting Mainline, riser & threading branch (Total)
Pipe dia 1 inch (branch) btg 16 16 0 0 16 0
Pipe dia 1.5 inch (branch) btg 33 33 0 0 33 0
Pekerjaan dilakukan di Workshop Pluit
Pipe dia 2 inch (branch) btg 7 7 0 0 7 0
Pipe dia 3 inch (mainline + riser) btg 5 5 0 0 5 0
Pipe dia 4 inch (mainline + riser) btg 6 6 0 0 6 0 Surface preparation & painting primer
Pipe dia 6 inch (mainline + riser) btg 14 14 0 0 14 0 Thickness Top Coat layer, > 180 Micron
Pipe dia 8 inch (mainline + riser) btg 3 1 0 0 1 2
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 Pemasangan jalur hydrant lt 2 & Lt 3
2 Finishing branch tapping ke mainline dengan epoxy
B FGD & ESP lt 2
Marking & pemasangan fix support
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 1 ea 1 Trafo Las (2 set)


2 HSE person 1 2 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 0 5 5 Bor Besi (2 set)
6 Welder candidat person 0 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 1 8
Jumlah 6 9
REMARK
Pekerja tambahan sedang perjalanan ke site
Est material onsite rabu 19 Oktober 2022

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED
…...................

SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER


Tuesday, 18 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Morning toolbox meeting Pemasangan flangs riser 2 MCU pekerja fitter baru

Koordinasi dengan QC HK Internal material receiving & line check dengan inspector HK Internal material receiving & line check dengan inspector HK

Pengecekan aktual mill sertifikat fitting terpasang Cleaning area CCB lt 1 seelah toolbox dipindah
Pembuatan test piece
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building & ESP (Field & workshop) Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 17.00 v
DATE / PRIODE : Wednesday, 19 Oktober 2022 19.00 - 22.00

ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Pembuatan test piece WQT 2 set 3 0 3 3 3 0 untuk 2 kandidat welder
2 Pemindahan toolx box ke area ESP lt GF lot 1 0 1 1 1 0
3 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 65 0 0 65 0
Pipe dia 2 inch (branch) btg 7 7 0 0 7 0
Pipe dia 3 inch (mainline + riser) btg 14 14 0 0 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 13 0 0 13 1
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP
1 Hanger support Threadrod M8, M10, M12 Lt 2 titik 139 50 0 0 50 89 Dynaset,threadrod & nut, belum hanger clamp
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0 Dynaset,threadrod & nut, belum hanger clamp
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Painting Mainline, riser & threading branch (Total)
Pipe dia 1 inch (branch) btg 16 16 0 0 16 0
Pipe dia 1.5 inch (branch) btg 33 33 0 0 33 0
Pekerjaan dilakukan di Workshop Pluit
Pipe dia 2 inch (branch) btg 7 7 0 0 7 0
Pipe dia 3 inch (mainline + riser) btg 5 5 0 0 5 0
Pipe dia 4 inch (mainline + riser) btg 6 6 0 0 6 0 Surface preparation & painting primer
Pipe dia 6 inch (mainline + riser) btg 14 14 0 0 14 0 Thickness Top Coat layer, > 180 Micron
Pipe dia 8 inch (mainline + riser) btg 3 1 0 0 1 2
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 Pemasangan jalur hydrant lt 2 & Lt 3
2 Finishing branch tapping ke mainline dengan epoxy
B FGD & ESP lt 2
Marking & pemasangan fix support
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 1 ea 1 Trafo Las (2 set)


2 HSE person 1 2 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 0 5 5 Bor Besi (2 set)
6 Welder candidat person 0 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 1 8
Jumlah 6 9
REMARK
Pekerja tambahan sedang perjalanan ke site
Est material onsite rabu 19 Oktober 2022

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED
…...................

SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER


Wednesday, 19 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Morning toolbox meeting Pemasangan flangs riser 2 MCU pekerja fitter baru

Koordinasi dengan QC HK Internal material receiving & line check dengan inspector HK Internal material receiving & line check dengan inspector HK

Pengecekan aktual mill sertifikat fitting terpasang Cleaning area CCB lt 1 seelah toolbox dipindah
Pembuatan test piece
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building & ESP (Field & workshop) Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 19.00 v
DATE / PRIODE : Thursday, 20 Oktober 2022 19.00 - 22.00

ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Internal test welder 2 kandidat dr Jakarta (Trial) set 2 0 2 2 2 0 Sample 2 inch & 3 inch
2 Material receiving eksternal IRT owner & HK lot 1 0 1 1 1 0 Report Material receiving acc, officaly closing RFI
3 Pipe Erection Mainline, riser & branch (Total) menunggu Filed ITP rev Approved
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 65 0 0 65 0
Pipe dia 2 inch (branch) btg 7 7 0 0 7 0
Pipe dia 3 inch (mainline + riser) btg 14 14 0 0 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 13 0 0 13 1
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP
1 Unloading material ESP lot 1 0 1 1 1 0
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Erection Mainline, riser & threading branch (Total)
Pipe dia 1 inch (branch) btg 16 0 0 0 0 16
Pipe dia 1.5 inch (branch) btg 33 0 0 0 0 33
Pipe dia 2 inch (branch) btg 7 0 0 0 0 7
Pipe dia 3 inch (mainline + riser) btg 5 0 0 0 0 5
Pipe dia 4 inch (mainline + riser) btg 6 0 0 0 0 6
Pipe dia 6 inch (mainline + riser) btg 14 0 0 0 0 14
Pipe dia 8 inch (mainline + riser) btg 3 0 0 0 0 3
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 Pemasangan jalur hydrant lt 2 & Lt 3
2 Finishing branch tapping ke mainline dengan epoxy
B FGD & ESP lt 2
Marking & pemasangan fix support
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 1 ea 1 Trafo Las (2 set)


2 HSE person 1 2 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 1 5 5 Bor Besi (2 set)
6 Welder candidat person 2 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 3 8
Jumlah 11 9
REMARK
WQT 2 dilakukan hari Jumat 21/20/2022

Closing RFI material receiving menunggu filefd ITP status approved


Submit revisi Field ITP menunggu status Line List HK approved, terkait persentase NDT

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED
…...................

SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER


Thursday, 20 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Morning toolbox meeting Proses unloading material ESP & FGD Fitting & consumable on site

Proses unloading material Spool material pipa diletakan di rak


Proses unloading material ESP & FGD

Transfer material pipa di lokasi ESP & FGD GF, diletakkan di atas QC, pengecekan mill sertifikat material yang datang
rak Sign & pengecekan item quantity Surat Jalan
Thursday, 20 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

QC, koordinasi dengan Spv QC HK untuk revisi dokumen Field ITP Material Receiving CCB bersama IRT owner & HK untuk material CCB

Inspeksi material receiving CCB fitting Sign report material receiving CCB Inspeksi material receiving CCB fitting terpasang

Inspeksi material receiving CCB fitting terpasang Cleaning area kerja ESP & FGD lt GF
Internal welding test untuk kandidat welder, trial
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building & ESP (Field & workshop) Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 18.00 v
DATE / PRIODE : Thursday, 21 Oktober 2022 19.00 - 22.00

ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Internal test welder 2 kandidat dr Jakarta (Trial) ke 2 set 2 0 2 2 2 0 Sample 2 inch & 3 inch
2 Material receiving eksternal IRT owner & HK lot 1 1 0 0 1 0 Report Material receiving acc, officaly closing RFI
3 Pipe Erection Mainline, riser & branch (Total) menunggu Filed ITP rev Approved
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 65 0 0 65 0
Pipe dia 2 inch (branch) btg 7 7 0 0 7 0
Pipe dia 3 inch (mainline + riser) btg 14 14 0 0 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 13 0 0 13 1
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP GF
1 Unloading material ESP lot 1 1 0 0 1 0
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Erection Mainline, riser & threading branch (Total)
Pipe dia 1 inch (branch) btg 16 0 7 7 7 9
Pipe dia 1.5 inch (branch) btg 33 0 6 6 6 27
Pipe dia 2 inch (branch) btg 7 0 0 0 0 7
Pipe dia 3 inch (mainline + riser) btg 5 0 0 0 0 5
Pipe dia 4 inch (mainline + riser) btg 6 0 0 0 0 6
Pipe dia 6 inch (mainline + riser) btg 14 0 0 0 0 14
Pipe dia 8 inch (mainline + riser) btg 3 0 0 0 0 3
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 WQT ke 2
2
B FGD & ESP lt GF
Erection Branch
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 Spool pipa 1-1/2 inch 13 set 1 Trafo Las (2 set)
2 HSE person 1 2 Spool pipa 1 inch 12 set 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 1 5 5 Bor Besi (2 set)
6 Welder candidat person 1 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 3 8
Jumlah 10 9
REMARK
WQT 2 dilakukan hari Jumat 21/20/2022

Closing RFI material receiving menunggu filefd ITP status approved


Submit revisi Field ITP menunggu status Line List HK approved, terkait persentase NDT

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED

…...................
SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER
Thursday, 21 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Morning toolbox meeting Pembuatan Welding test piece, 8 set dan painting scafolding Erection Branch lt GF

Erection Branch lt GF Pengecekan persiapan erection branch oleh FE HK


Mapping instalasi branch terpasang

Trial welding test dari jakarta, 2 kandidat Trial welding test welder dari jakarta untuk persiapan WQT Cleaning area kerja
2
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building & ESP (Field & workshop) Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 18.00 v
DATE / PRIODE : Saturday, 22 Oktober 2022 19.00 - 22.00

ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Eksternal test welder 4 kandidat lot 4 0 4 4 4 0 2 welder lolos test piece 3 inch, 1 welder lolos 2 inch
2 Material receiving eksternal IRT owner & HK lot 1 1 0 0 1 0 Report Material receiving acc, officaly closing RFI
3 Pipe Erection Mainline, riser & branch (Total) menunggu Filed ITP rev Approved
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 65 0 0 65 0
Pipe dia 2 inch (branch) btg 7 7 0 0 7 0
Pipe dia 3 inch (mainline + riser) btg 14 14 0 0 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 13 0 0 13 1
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP GF
1 Unloading material ESP lot 1 1 0 0 1 0
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Erection Mainline, riser & threading branch (Total)
Pipe dia 1 inch (branch) btg 16 7 4 4 11 5
Pipe dia 1.5 inch (branch) btg 33 6 4 4 10 23
Pipe dia 2 inch (branch) btg 7 0 0 0 0 7
Pipe dia 3 inch (mainline + riser) btg 5 0 0 0 0 5
Pipe dia 4 inch (mainline + riser) btg 6 0 0 0 0 6
Pipe dia 6 inch (mainline + riser) btg 14 0 0 0 0 14
Pipe dia 8 inch (mainline + riser) btg 3 0 0 0 0 3
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 Inspeksi Fit Up btg 3 0 3 3 3 0
2 Pipe Erection Mainline, riser & branch (Total)
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 WQT ke 2

B FGD & ESP lt GF


Erection Branch
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 Spool pipa 1-1/2 inch 8 set 1 Trafo Las (2 set)
2 HSE person 1 2 Spool pipa 1 inch 7 set 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 1 5 5 Bor Besi (2 set)
6 Welder candidat person 1 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 3 8
Jumlah 10 9
REMARK
WQT 2 meloloskan 3 test piece visual check HK & owner IRT

Closing RFI material receiving menunggu filefd ITP status approved


Submit revisi Field ITP menunggu status Line List HK approved, terkait persentase NDT

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED

…...................
SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER
Saturday, 22 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Briefing eksternal oleh inspektor IRT & HK kepada kandidat


Morning toolbox meeting welder Root inspection hasil welding by HK

Proses welding di site workshop PT KOIN Visual check oleh inspektor HK & IRT, Ahmad 3 inch acc, Visual check oeh insoektor HK &IRT, SUmarto 3 inch acc, Yasin 2
Hermanto all fail inch ACC

Instalasi branch ESP lt GF Cleaning area kerja


Instalasi branch ESP lt GF
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building & ESP Building Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 18.00 v
DATE / PRIODE : Monday, 24 Oktober 2022 19.00 - 22.00

ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Unloading material APD & clamm scafolding lot 1 0 1 1 1 0
2 RFI WQT 3 lot 1 0 1 1 1 0 2 kandidat, dilakukan di ESP (retest kandidat)
3 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 65 0 0 65 0
Pipe dia 2 inch (branch) btg 7 7 0 0 7 0
Pipe dia 3 inch (mainline + riser) btg 14 14 0 0 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 13 0 0 13 1 Elbow 6 inch riser 2 terpasang
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP GF
1 Marking area untuk loading kontainer lot 1 1 0 0 1 0
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Erection Mainline, riser & threading branch (Total)
Pipe dia 1 inch (branch) btg 16 7 4 4 11 5
Pipe dia 1.5 inch (branch) btg 33 6 4 4 10 23
Pipe dia 2 inch (branch) btg 7 0 0 0 0 7
Pipe dia 3 inch (mainline + riser) btg 5 0 0 0 0 5
Pipe dia 4 inch (mainline + riser) btg 6 0 0 0 0 6
Pipe dia 6 inch (mainline + riser) btg 14 0 0 0 0 14
Pipe dia 8 inch (mainline + riser) btg 3 0 0 0 0 3
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 WQT 3 btg 2 0 2 2 2 0
2 Unoading kontainer
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 WQT ke 2

B FGD & ESP lt GF


Fabrikasi outset branch adjustment on site
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 Spool pipa 1-1/2 inch 5 set 1 Trafo Las (2 set)
2 HSE person 1 2 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 2 5 5 Bor Besi (2 set)
6 Welder candidat person 1 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 3 8
Jumlah 11 9
REMARK
WQT 3 untuk medapatkan test piece yang banyak lolos visual check HK & owner IRT, memperbesar peluang lolos RT
Material receiving
Closing RFI material receiving menunggu filefd ITP status approved
Submit revisi Field ITP menunggu status Line List HK approved, terkait persentase NDT

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED

…...................
SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER
Monday, 24 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Briefing eksternal oleh inspektor IRT & HK kepada kandidat


Morning toolbox meeting welder Root inspection hasil welding by HK

Proses welding di site workshop PT KOIN Visual check oleh inspektor HK & IRT, Ahmad 3 inch acc, Visual check oeh insoektor HK &IRT, SUmarto 3 inch acc, Yasin 2
Hermanto all fail inch ACC

Instalasi branch ESP lt GF Cleaning area kerja


Instalasi branch ESP lt GF
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DAILY ACTIVITIES REPORT

LOCATION : Central Control Building & ESP Building Timing Clear Cloudy Drizzle Rainy Hard rainy
07.00 - 10.00 v
ITEM WORK : Fire Hydrant & Springkler System 10.00 - 14.00 v
14.00 - 18.00 v
DATE / PRIODE : Tuesday, 25 Oktober 2022 19.00 - 22.00

ACTIVITY TODAY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB Lt.1
1 Unloading toilet protable lot 1 0 1 1 1 0
2 WQT 3 lot 1 0 0 0 0 1 2 kandidat, dilakukan di ESP (retest kandidat), reschedule
3 Pipe Erection Mainline, riser & branch (Total)
Pipe dia 1 inch (branch) btg 32 32 0 0 32 0
Pipe dia 1.5 inch (branch) btg 65 65 0 0 65 0
Pipe dia 2 inch (branch) btg 7 7 0 0 7 0
Pipe dia 3 inch (mainline + riser) btg 14 14 0 0 14 0
Pipe dia 4 inch (mainline + riser) btg 9 9 0 0 9 0
Pipe dia 6 inch (mainline + riser) btg 14 13 0 0 13 1 Elbow 6 inch riser 2 terpasang
Pipe dia 8 inch (mainline + riser) btg 2 0 0 0 0 2
B FGD & ESP GF
1 Marking area untuk loading kontainer lot 1 1 0 0 1 0
2 Hanger support Threadrod M8, M10, M12 GF titik 116 116 0 0 116 0
3 Fix support PS-01 & PS-02 titik 18 0 0 0 0 18
4 Pipe Erection Mainline, riser & threading branch (Total)
Pipe dia 1 inch (branch) btg 16 11 0 0 11 5
Pipe dia 1.5 inch (branch) btg 33 10 0 0 10 23
Pipe dia 2 inch (branch) btg 7 0 0 0 0 7
Pipe dia 3 inch (mainline + riser) btg 5 0 0 0 0 5
Pipe dia 4 inch (mainline + riser) btg 6 0 0 0 0 6
Pipe dia 6 inch (mainline + riser) btg 14 0 0 0 0 14
Pipe dia 8 inch (mainline + riser) btg 3 0 0 0 0 3
ACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Description
Qty. last the day the day until day

A CCB
1 WQT 3 btg 2 0 2 2 2 0
2 Unoading kontainer
B FGD & ESP
1 Marking & pemasangan fix support lot 1 0 1 1 1 0
UNACHIEVED ACTIVITY

Total Accum. Plan for Actual on Cumm.


No. Description UOM Remaining Reason Description
Qty. last the day the day until day

A CCB
- 0 0 0 0 0 0 0

TOMORROW ACTIVITY PLAN

Total Accum. Plan for Actual on Cumm. Remaining


No. Description UOM Description
Qty. last tomorrow the day until day Plan

A CCB
1 WQT ke 2

B FGD & ESP lt GF


Fabrikasi outset branch adjustment on site
MAN POWER MATERIAL EQUIPMENT
Unit of
No. Description Measurement
Qty. No. Description Qty. No. Description

1 Site Manager person 1 1 Pipa 6 incg 4 ea 1 Trafo Las (2 set)


2 HSE person 1 2 Pipa 4 inch 3 ea 2 ELCB box (1 set)
3 Supervisor/ Foreman person 1 3 3 Kabel Power NYYHY 3x2.5 mm (3 set)
4 Storeman person 1 4 4 Bor Beton (3 set)
5 Fitter person 2 5 5 Bor Besi (2 set)
6 Welder candidat person 1 6 6 Gerinda Tangan (6 set)
7 Welding inspector-QC person 1 7 7 Lampu Tembak ( 4 set)
8 Helper person 3 8
Jumlah 11 9
REMARK
WQT 3 resechedue karena dibutuhkan tang ampere kalibrasi untuk engetahui ampere sesuai WPS
Material receiving internal direschudule

Musim hujan menghambat mobilisasi pekerjaan

PT INDOBARA BAHANA HUTAMA KARYA HUTAMA KARYA


PREPARED CHECKED BY HK CHECKED

…...................
SM IBB SUPERVISOR HK FIELD ENGINEER CONSTRUCTION MANAGER SITE MANAGER
Tuesday, 25 Oktober 2022
DOOSAN - PT. HUTAMA KARYA CONSORTIUM
JAWA 9 & 10 COAL FIRED POWER PLANT
2X1000 MW PROJECT

DOCUMENTATION

Morning toolbox meeting ESP, preparing pipa untuk marking titik bor thredoulet & erection Unloading toilet portable

Proses lubangin thredoulet Pengecekan proses persiapan pipa oleh Field Engineer HK
Tagging hijau scafolding mobile ESP

CCB, instalasi riser 1 setelah bobok dinding Cleaning area kerja


Persiapan WQT 3