BILL OF QUANTITY

ADDITIONAL POOL WASH


PROJECT TITLE :
Detail 1
Permanent Pipe Line from Equalization to Make Up Water Cooling Tower
Bill of Quantity

DOC. NO : PRJ-CIV-05 JOB. NO. : 05

0
BREAK DOWN
REV. DATE DSG'D CHK'D. APP'D
PROJECT
ITEM DESCRIPTION Notasi UoM BoQ Unit Price TOTAL PRICE
REQUIREMENT
I. PRELIMINARY WORKS
Mobilization and demobilization of work equipment, work
1 AN.00.a Lot 1.00
materials, manpower, Etc.
2 Safety equipment AN.00.b Lot 1.00

II. SUPPORTING WORKS


Working water and electricity during the implementation
1 Lot 1.00
period
Clearing of working land until project completion and
2 AN.00.c Lot 1.00
Project Safety
3 Project document Lot 1.00
4 Tools for works AN.00.d Lot 1.00
5 Dismantling Existing HDPE Pipe Clogging 3 Inch Lot 1.00

III. ADDITIONAL MAKE UP WATER COOLING TOWER


III.1 Pipping Work
1 Pipe, HDPE SDR 11 PN 10 SDR 11 PN 10 SNI 4829 2:2015 AN.01.a M' 218.40
2 Elbow 90 deg, HDPE SDR 11 PN 10 SDR 11 PN 10 SNI 4829 2:2015 AN.01.b Ea 22.00
3 Eqal Tee, HDPE SDR 11 PN 10 SDR 11 PN 10 SNI 4829 2:2015 AN.01.c Ea 1.00
4 Stub End Flange 3 Inch JIS 10 K, SS304 AN.01.d Ea 8.00
5 Stud Bolt 16x90 Class 150, 16x90 Ea 24.00
6 Bolt Set, Lug Bolt, 16x83 Class 150, 16x83 Ea 16.00
7 Gasket Gasket for HDPE 3 Inch Ea 6.00
8 Butterfly Valve AN.02.d Ea 2.00
III.2 Civil Work
1 Underground Pipe
- Manual Digging AN.02.a M3 3.81
- Back Fill (30% Manual Digging) AN.02.c M3 1.14
- Sand Fill AN.02.b M3 0.76

2 Pipe Support
- Profil L50x50x4 50x50 thk 4 mm AN.02.d Kg 54.74
- Pelat Thk 5 mm Carboon Steel, Thk 5 mm AN.02.d Kg 517.97
- Dynabolt M8-65 M8 Length 65 mm Ea 170.00
- U-Bolt 3 Inch Galvanized Galvanized 3 Inch, + Bolt Ea 85.00
Wirebruss, Primer Jotamastic 70 100 mic, Finish Hardtop
- Painting Steel Structure AN.02.e M 2
4.85
XP RAL 7040 50 mic
TOTAL Rp -
VAT 11% Rp -
TOTAL + VAT 11% Rp -