You are on page 1of 6

MUST NOT BE COPIED

Purchase specification SPECIFICATION FOR SUPPLY UTILITIES FOR


CHILLER- COOLING TOWER – OAHU MACHINES
CAD/CAM Section OF PCBA-1

FACILITY CONTROL DEPARTMENT


Section : Water treatment & Building Group: Mechanical and Electrical Maintenance group
Spec No. : … ………
Type: E: Electric; M: Mechanic; W: Water; B: Building
JOB SPECIFICATION FOR SUPPLY UTILITIES Type
E M W B
TITLE: FOR CHILLER- COOLING TOWER – OAHU x
MACHINES OF PCBA-1
I. Mechanical works
1. Work Description.

No. Work item & Requirement Q’ty Parameter Standard


A Install City water branch pipe
1.1 Preparation work 05 - Connection City water No have
point branch pipe to City water leakage at
s main pipe on the wall connecting
outside the factory PCBA-1 points
- Refer the attached layout
1.2 Install City water branch pipe (From main Pipe and fittings:
City pipe on the wall outside the factory - Pipe: PN10 Maximum
PCBA-1 (GI pipe 100A) to New Cooling - Fitting: PN10 Working
tower - Material: PPR 1.0MPa
- Maker: The fist/ Binh minh
Pipe supply for Cooling
01 lot For city water
towers
Pipe DN25mm supply for
01 lot Cleaning the Cooling towers For city water
area
01 lot Fitting for all kind For city water
Gate valve: for branch pipe
THREAD BRASS BALL
01 lot For City water
VALVE
Maker kizt/miha/the fist
Ball valve 20A: Water valve
for wash faucet
02
Material: THREAD BRASS For City water
Pcs
BALL VALVE
Maker kizt/miha/the fist
Support: Do not affect
01 lot - V steel + U clamp. TVB
- Epoxy painting 3 layers equipment.
Label name: same as
01 lot
Name City water existing
1.3 Install City water branch pipe (From main Pipe and fittings:
City pipe on the wall outside the factory - Pipe: PN10 Maximum
PCBA-1 (GI pipe 100A) to New Chiller - Fitting: PN10 Working
machine - Material: PPR 1.0MPa
- Maker: The fist/ Binh minh
Pipe supply for Chiller
01 lot For city water
machines
Pipe DN25mm supply for
01 lot Cleaning the Chiller For city water
machines area

SPEC. No.

REV DATE DESIGN CHECK APPR DESCRIPTION


DATE SECTION DESIGN CHECK APPR STD DIV SHEET
18/07/2023 FC N.L.CHAU P.T.HOAN P.T.HOAN TVB INC. 1 / 6
TVB TVB PURCHASE SPECIFICATION SHEET
MUST NOT BE COPIED

Purchase specification SPECIFICATION FOR SUPPLY UTILITIES FOR


CHILLER- COOLING TOWER – OAHU MACHINES
CAD/CAM Section OF PCBA-1

01 lot Fitting for all kind For city water


Gate valve: for branch pipe
THREAD BRASS BALL
01 lot For City water
VALVE
Maker kizt/miha/the fist
Ball valve 20A: Water valve
for wash faucet
02
Material: THREAD BRASS For City water
Pcs
BALL VALVE
Maker kizt/miha/the fist
Support: Do not affect
01 lot - V steel + U clamp. TVB
- Epoxy painting 3 layers equipment.
Label name: same as
01 lot
Name City water existing
1.4 Install City water branch pipe (From main Pipe and fittings:
City pipe on the wall outside the factory - Pipe: PN10 Maximum
PCBA-1 (GI pipe 80A) to New OAHU Area - Fitting: PN10 Working
- Material: PPR 1.0MPa
- Maker: The fist/ Binh minh
Pipe DN25mm supply for
03 lot Cleaning the OAHU For city water
machines area
01 lot Fitting for all kind For city water
Ball valve 20A: Water valve
for wash faucet
06
Material: THREAD BRASS For City water
Pcs
BALL VALVE
Maker kizt/miha/the fist
Support: Do not affect
01 lot - V steel + U clamp. TVB
- Epoxy painting 3 layers equipment.
Label name: same as
01 lot
Name City water existing

B Install pump for sum pit

2.1 Install pump for sum pit #1 02 Install pumps for Sum pit: For
sets Type: Submersible pump wastewater of
380V OAHU
(Design by contractor ) machines
01 Install Control panel For 2 pumps
sets Connect 4-level control
switch according to the
water level of the sump pit
tank
(Level LL: Pump OFF
Level L: Run 1 pump
Level H: Runs 2 pumps
Level HH Sum pit is full
2 pumps automatically run
alternately)
(Design by contractor)

SPEC. No.

REV DATE DESIGN CHECK APPR DESCRIPTION


DATE SECTION DESIGN CHECK APPR STD DIV SHEET
18/07/2023 FC N.L.CHAU P.T.HOAN P.T.HOAN TVB INC. 2 / 6
TVB TVB PURCHASE SPECIFICATION SHEET
MUST NOT BE COPIED

Purchase specification SPECIFICATION FOR SUPPLY UTILITIES FOR


CHILLER- COOLING TOWER – OAHU MACHINES
CAD/CAM Section OF PCBA-1

Level control switch FQ-88


+ Terminal box 5 point: 01
pc
+ Clip: 04 pc Level control
01 set + FQ-8: 04 pc (float) switch for
+ Rape: 01 fiber wastewater
+ weight: 01 pc sump pit
(If FQ-88 is not available,
use model the equivalent)
01 lot Install pipe of pumps from
sum pit #1 to sum pit #2
Pipe and fittings:
Maximum
- Pipe: PN10
Working
- Fitting: PN10
1.0MPa
- Material: PVC
- Maker: The fist/ Binh minh
(Design by contractor)
Support: Do not affect
01 lot - V steel + U clamp. TVB
- Epoxy painting 3 layers equipment.
Label name:
same as
01 lot Name wastewater pipe line
existing
C
2.2 Install pump for sum pit #2 02 Install pumps for Sum pit: For
sets Type: Submersible pump wastewater of
380V Chiller &
(Design by contractor ) cooling tower
machines
01 Install Control panel For 2 pumps
sets Connect 4-level control
switch according to the
water level of the sump pit
tank
(Level LL: Pump OFF
Level L: Run 1 pump
Level H: Runs 2 pumps
Level HH Sum pit is full
2 pumps automatically run
alternately)
(Design by contractor)
Level control switch FQ-88
+ Terminal box 5 point: 01
pc
Level control
+ Clip: 04 pc
switch for
01 set + FQ-8: 04 pc (float)
wastewater
+ Rape: 01 fiber
sump pit
+ weight: 01 pc
(If FQ-88 is not available,
use model the equivalent)
01 lot Install pipe of pumps from
sum pit #2 to the pipe after
Maximum
treated water pumps of
Working
PCBA-2
1.0MPa
Pipe and fittings:
- Pipe: PN10
SPEC. No.

REV DATE DESIGN CHECK APPR DESCRIPTION


DATE SECTION DESIGN CHECK APPR STD DIV SHEET
18/07/2023 FC N.L.CHAU P.T.HOAN P.T.HOAN TVB INC. 3 / 6
TVB TVB PURCHASE SPECIFICATION SHEET
MUST NOT BE COPIED

Purchase specification SPECIFICATION FOR SUPPLY UTILITIES FOR


CHILLER- COOLING TOWER – OAHU MACHINES
CAD/CAM Section OF PCBA-1

- Fitting: PN10
- Material: PVC
- Maker: The fist/ Binh minh
(Design by contractor)
Support: Do not affect
01 lot - V steel + U clamp. TVB
- Epoxy painting 3 layers equipment.
Label name:
same as
01 lot Name wastewater pipe line
existing
C
C Running test
Visual check and operation No leaked
01 lot Normal
of equipment check
operation

2. Repair item list.


No Item/Equipment name Q’ty No Item/Equipment name Q’ty
1

3. Material Forecast.

No. Material name Specification Unit Q’ty Remark


1

1. Proposal Schedule

No Working Item Starting Schedule


date W1 W2 W3 W4 W5 W6 W7 W8 Note

1 Document
preparation
2 Purchase procedure
3 Work
implementation
4 Handover

2. Accomplishment test:
No Inspection content Testing Standard value Ins. Method Reference
parameter
1 Equpiment Maker New, right maker Visual check

SPEC. No.

REV DATE DESIGN CHECK APPR DESCRIPTION


DATE SECTION DESIGN CHECK APPR STD DIV SHEET
18/07/2023 FC N.L.CHAU P.T.HOAN P.T.HOAN TVB INC. 4 / 6
TVB TVB PURCHASE SPECIFICATION SHEET
MUST NOT BE COPIED

Purchase specification SPECIFICATION FOR SUPPLY UTILITIES FOR


CHILLER- COOLING TOWER – OAHU MACHINES
CAD/CAM Section OF PCBA-1

3. Warranty.

 The period of warranty is one year.


 The date will start and finish the warranty time must be wrote down on Warranty letter.
 The contact person and telephone number is requested in Warranty Letter.

4. Others.
 Contractor designs the detail structure and bear full responsibility for the technique quality of this design. Any
damages, which cause by the design, contractor has to compensate for them.
 Contractor's drawings of the project are user for at site checking only. This is not a matter upon technique
contract.
 The job shall be performed on Sunday or holiday for stopping utilities that do not make any effect to production
 Keep working area clean and tidy. Protection work must be applied during working time to prevent any
affected to products.
 The contractor has to inform to list of manpower, working time and confirm to TVB when start the job at site
every periods.
 If any trouble happens in working times, the contractor has to inform Facility Control Section.
 Equipment & Material must be kept at a place that is outside of factory, which is decided by TVB.
 Scrap material must be moved out of TVB completely.
 Any activity, which may affect to environment, must be prohibited. If any damage occurs, contractor must
bear the compensation.
 Any item that is not described in this specification or changing specification is decided through agreement of
both parties.
5. Layout City water supply pipe.

SPEC. No.

REV DATE DESIGN CHECK APPR DESCRIPTION


DATE SECTION DESIGN CHECK APPR STD DIV SHEET
18/07/2023 FC N.L.CHAU P.T.HOAN P.T.HOAN TVB INC. 5 / 6
TVB TVB PURCHASE SPECIFICATION SHEET
MUST NOT BE COPIED

Purchase specification SPECIFICATION FOR SUPPLY UTILITIES FOR


CHILLER- COOLING TOWER – OAHU MACHINES
CAD/CAM Section OF PCBA-1

6. Layout location of sum pit.

SPEC. No.

REV DATE DESIGN CHECK APPR DESCRIPTION


DATE SECTION DESIGN CHECK APPR STD DIV SHEET
18/07/2023 FC N.L.CHAU P.T.HOAN P.T.HOAN TVB INC. 6 / 6
TVB TVB PURCHASE SPECIFICATION SHEET

You might also like