PENDING WORK OF TURBINE 1 GSC ARRANGEMENT INSTALLATION PENDING 2 TURBINE DRAIN LINE WELDING PENDING 3 GLAND SEALING CONTROL VALVE INSTALLATION PENDING 7 DAYS 2 DAYS
REMARKS
Requirement manpower, damege material of GSC replacement IBR welder required material to be received, indent raised with HO
5 3 way plug valve in contrl oil Filter replacement job pending 01 day 7 DAYS AFTER MATERIAL RECEIVING,indent no:SIL/CPP/BOILER/004/00 16 & manpower to be given by 6 PRDS TO DEARATOR LINE(initial heating line) PENDING SIL/CPP/BOILER/004/0024 Dilip Das 7 DAYS AFTER MATERIAL RECEIVING,indent no: SIL/CPP/TG/002/0023, DT:25.06.2011 UNDER PROGRESS, to be compleated within 20th july UNDER PROGRESS rotor not yet lifted & the job is getting delayed due to Non Availability of instruments indent raised, material yet to received, indent no:SIL/CPP/BOILER/004/00 28
8 CSDH TO TURBINE INLATE MAIN STEAM LINE PENDING REPLACEMENT OF HP DOSING FROM DEARATOR FLOOR TO 9 36TPH BOILER
Micrometers, slings, manila rope, slip gauge etc. indent lying with rohit malpani
13 TURBINE INSULATION 14 ALL STEAM PIPING INSULATION will be completed within 10th July
order to be placed engaged Albert Insulation Part delivery of turbine oil is pending, will reach site by 15th july
Note:Commissioning of turbine will take place after commissioning of DM plant,CHP,boiler. complation of steam line & steam blowing.