SL NO.

PENDING WORK OF TURBINE 1 GSC ARRANGEMENT INSTALLATION PENDING 2 TURBINE DRAIN LINE WELDING PENDING 3 GLAND SEALING CONTROL VALVE INSTALLATION PENDING 7 DAYS 2 DAYS

REMARKS

Requirement manpower, damege material of GSC replacement IBR welder required material to be received, indent raised with HO

4 TG EXTRACTION TO DEARATOR LINE(Bleed line) PENDING

2 DAYS 7 DAYS(under progress,started on 04.07.2011

5 3 way plug valve in contrl oil Filter replacement job pending 01 day 7 DAYS AFTER MATERIAL RECEIVING,indent no:SIL/CPP/BOILER/004/00 16 & manpower to be given by 6 PRDS TO DEARATOR LINE(initial heating line) PENDING SIL/CPP/BOILER/004/0024 Dilip Das 7 DAYS AFTER MATERIAL RECEIVING,indent no: SIL/CPP/TG/002/0023, DT:25.06.2011 UNDER PROGRESS, to be compleated within 20th july UNDER PROGRESS rotor not yet lifted & the job is getting delayed due to Non Availability of instruments indent raised, material yet to received, indent no:SIL/CPP/BOILER/004/00 28

material required, indent raised, indent no.SIL/CPP/GENMISC/008/0018

7 PRDS TO EJECTOR STEAM LINE PENDING

manpower to be given by Dilip Das

8 CSDH TO TURBINE INLATE MAIN STEAM LINE PENDING REPLACEMENT OF HP DOSING FROM DEARATOR FLOOR TO 9 36TPH BOILER

10 TURBINE OVERHAULING & ASSEMBLY

Micrometers, slings, manila rope, slip gauge etc. indent lying with rohit malpani

11 STEAM PIPING SUPPORT 12 DEARATOR INSULATION

manpower to be given by Dilip Das engaged Albert Insulation

13 TURBINE INSULATION 14 ALL STEAM PIPING INSULATION will be completed within 10th July

15 Oil Flushing & fresh oil filling

order to be placed engaged Albert Insulation Part delivery of turbine oil is pending, will reach site by 15th july

Note:Commissioning of turbine will take place after commissioning of DM plant,CHP,boiler. complation of steam line & steam blowing.