Professional Documents
Culture Documents
d) HLR 2. The _____ provides all the control functions and physical links between the MSC and the BTS. a) BSC b) ILR c) OSS d) GMSC 3. The _____ is the functional entity from which the network operator monitors and controls the system. a) BTS b) SS c) VLR d) OSS 4. The RBS 2106 has a maximum capacity of how many transceivers? a) 12 b) 24 c) 16 d) 8
5. In the following diagram, complete the missing labels of the RBS 2106:
6. In the following diagram, complete the missing labels of the RBS 2206:
2. In the following figure, draw the paths of the cooling air from each of the three fans in the combined climate unit of the RBS 2106.
3. The following figure shows the power system for which RBS?
Answer: _________________________________________
Answer: ___________________________________________
Answer: ___________________________________________
7. The following figure shows which type of configuration below (circle the correct answer): a) G9deht_3.6(5)\a b) F9de_2.4 (E-GSM) and F18d_2.4 (GSM 1800) c) F9de_2.8 (E-GSM) and F18d_2.8 (GSM 1800) d) F9det_2.6 (E-GSM) and F18dt_2.6 (GSM 1800)
a) Dont feed the animals warning b) ESD warning c) Radio Frequency (RF) warning d) Hazard warning
What is (are) the possible result(s) if this warning is neglected? a) Likely, a fatal accident may occur b) Likely, a slight burn may occur c) Likely, nothing serious will happen d) Likely, youll have the power to heal others 3. The following tool:
a) Is used to discharge electrostatic voltage b) Should be connected to earth c) Contains a resistor with an ohmic value greater than 1 M d) All of the above 4. When working with ladders, which of the following is correct procedure? a) Always climb the ladder facing it. b) Always keep two points of contact (two feet, two hands, or one hand and one foot). c) When climbing up on a roof, the ladder should never extend above the eaves. d) None of the above 5. A multimeter measures: a) Height, width, depth b) Length of time, ESD, and ohmic value c) Voltage, current, resistance d) None of the above 6. The Anritsu Site Master is used for verifying of: a) BBS 2000 b) RBS 2206/2106 c) Distribution Frame d) Antenna System
cover Distance To Fault (DTF) and Standing Wave Radio (SWR) tests and related procedures. The following resources/tools will be needed to complete this exercise: Anritsu Site Master (model S331C recommended) Precision Open/Short/Load (for Site Master calibration) Laptop/PC with Site Master software Work Order (located on the following page) Test Record for Antenna System Tests (located on the last page of this exercise) Checklist (located on the last page of this exercise) RBS 2106 and 2206 Installation and Integration Manuals, which include: Preconditions Work Process (flowchart) Installation Verification procedures
Procedure
1. Locate the correct procedures for verifying the antenna system in the manual(s). 2. Review the Work Order (following page) and test preconditions. 3. Follow the Work Process precisely, and conduct both DTF and SWR tests. 4. After completing the antenna system tests, complete the Test Record and Checklist. Make sure the instructor sees your results. 5. Be prepared to discuss your results at the end of this exercise.
Work Order
Work area:
General Information DALLAS 01 Newly-installed RBS antenna system needs to be tested for proper installation. DLS 78241 OMC Department D01 DALLAS 400 P1
Identification Work Order Id: Work Order Issued by: Change status (Time): Site id: Site name: Work order priority: Alarm time: Alarm slogan: Fault code subsystem: Work Order History Work Order escalated from: Comments: Task Description Trouble ticket: Task title: Time First start (Time): Last start (Time): Finished at the latest (Time): Reporting Results How to report results: References System documentation: Alarm Printout: Immediately complete Test Record and Checklist, and submit to OMC. -90324 ANTENNA SYSTEM TESTS N/A Perform DTF, SWR and other applicable tests as necessary.
OK
1. Are all outdoor antenna system connectors covered with sealing tape?
2. Is the Test Record completed? 3. Is the Site Installation Documentation complete with the Test Record and Test Record supplements (if necessary)?
Procedure
1. Locate the correct procedures for verifying the RBS 2106 site installation in the Installation and Integration manual. 2. Review the Work Order (following page) and verify preconditions. 3. Follow the Work Process precisely, and conduct all procedures and installation verifications. 4. After completing the antenna system tests, complete the Test Record and Checklist. Make sure the instructor sees your results. 5. Be prepared to discuss your results at the end of this exercise.
Test Record
Checklist
1. Are all fault indicators off? 2. Is the Local indicator on the DXU off (or flashing if no PCM link is connected)?
3. Are all other indicators on the DXU off? 4. Are the Local indicators on all dTRUs off (or flashing if no PCM link is connected)? 5. Are all RF off indicators on all dTRUs on? 6. Are all other indicators on all dTRUs off? 7. Are all other green operational indicators on? 8. Are all yellow indicators off? 9. Has all installation verification equipment been disconnected from the RBS? 10. Is the cabinet dry inside? 11. Are the inside and the outside of the cabinet free of damage? 12. Are all cables free of damage? 13. Are all EMC sealants and cable penetrations intact? 14. Is a back-up copy of the IDB saved on a disk? 15. Are all tools accounted for? 16. Is the cabinet door locked? 17. Is the external air intake free of obstructions? 18. Is all necessary paperwork completed?
In the following exercise, you will be integrating the RBS with the BSC and then testing to verify the integration. The exercise will cover bringing the RBS into service and making test calls on the air interface. The instructor will assign you/your team to the RBS model you will be integrating/testing. The following resources/tools will be needed to complete this exercise: TEMS Laptop/PC with TEMS software Work Order (located after the Procedure section) Completed Test Record for Antenna System Tests (Exercise 4) Completed Test Record for Site Installation Tests (Exercise 5.1 or 5.2) Test Record for RBS Site Integration (located after the Work Order) Checklist (located on the second to the last page of this exercise) Network Element Acceptance Certificate (located on the last page of this exercise) RBS 2106 and 2206 Installation and Integration Manuals, which include: Preconditions at the RBS and the BSC Work Process (flowchart) Installation verification procedures
Procedure
1. Locate the correct procedures for verifying the RBS site integration in the Installation and Integration manual for your assigned RBS. 2. Review the Work Order (following page) and installation verification preconditions. 3. Follow the Work Process precisely, and conduct all site integration tests. 4. After completing the site integration tests, complete the Test Record, Checklist, and the Network Element Acceptance Certificate. Make sure the instructor sees your results. 5. Be prepared to discuss your results at the end of this exercise.
Identification Work Order Id: Work Order Issued by: Change status (Time): Site id: Site name: Work order priority: Alarm time: Alarm slogan: Fault code subsystem: Work Order History Work Order escalated from: Comments: Task Description Trouble ticket: Task title: Time First start (Time): Last start (Time): Finished at the latest (Time): Reporting Results How to report results: Immediately complete Test Record, Checklist, and Network Element Acceptance Certificate, and submit to OMC. -90327 SITE INTEGRATION N/A Perform all necessary tests to verify RBS is integrated correctly.
Test Record
Checklist
1. Are all green operational indicators on? 2. Are all other indicators off? 3. Has all installation verification equipment been disconnected from the RBS? 4. Is the RBS cabinet dry inside? 5. Are the inside and the outside of the cabinet free of damage? 6. Is the RBS free from foreign objects? 7. Are all cables free of damage? 8. Is a back-up copy of the IDB saved on a disk? 9. Have all tools been accounted for? 10. Is the external air intake free from obstructions? 11. Has the RBS door been locked? 12. Is all necessary paperwork completed?
EXERCISE 7.2
In the following exercise, perform the corrective action on the assigned RBS: While troubleshooting the RBS, you receive the following dTRU fault: Fault No.: SO TRXC 12A: 13 1. Review and take any necessary corrective actions on the fault. 2. Complete a Trouble Report (opposite page). 3. If necessary, complete a Repair Delivery Note (below) for the faulty unit. 4. Be prepared to review your results with the instructor.