You are on page 1of 1

Boiler

Area allocation for commissioning Main Boiler its accessories & critical piping Fans, Milling system Fuel oil, compressed air, valves , dampers & gates Logic Checking, ESP, Mill rejects system Oil system(lube oil, seal oil, jacking oil, EH oil , HP Bypass oil

Sanjay Pradhan,Arpit Agrawal,Dileep Kumar, Rajesh Sing Baghel

Feedwater and condensate system Turbine Stator water system, chemical dozing system, H2&C02 filling system, Valves& dampers Extraction system, Gland sealing system, Main turbine system WTP, DM plant, CW system, cooling tower BOP Fire water, fuel oil unloading compressed air system, consensate make-up, boiler filling CHP & AHP Electrical Switchyard, Transformers LT & MV switchgear, DCDB, UPS,DG

Pallav Dhagat, Arun Agrawal, SaiKrishna, Pankaj Kumar Yadav

Shiju John, Nana Ughade,Hemanth Mohit Bairagi, Abhishek Nayak Raghav Kumar, Pravin Hume Pradeep Kumar Gupta

You might also like