Professional Documents
Culture Documents
Push VsPull SlideSet9
Push VsPull SlideSet9
2
Like in EOQ
but last term is a 'Penalty'
factor for investing in setup
reduction rather than other
projects
K hQ
G Q K I a K
Q
2
= + +
ocus on the Pen,Ity ,ctor
We can effectively model this "aK) function as a
'logarithmic' investment function
By logarithmic e imply that there is a an increasing
cost to continue to reduce setup cost
We state, then, that there is a sum of money that can
be invested to yield a fixed percentage of cost
reduction
That is for example) for every investment of $200
the organization can get a 2% reduction in Setup
cost
ocus on the Pen,Ity ,ctor
Lets say that the investment is $7
buys a fixed percent reduction in
K
0
f e get actually get 10% setup
cost reduction for $7, then an
investment of $7 ill mean:
Setup cost drops to: 0.9K
0
A second $7 investment ill lead
to a further 10% reduction or:
.9K-.1*.9K = .81K
0
This continues: K
37
= .729K
0
Generalizing:
0
is 'number' of investments
q is the decimal equivalent of the
amount of reduction the $
investment will buy:
q(1-setup cost reduction)
a q K
7
7 = -
ocus on the Pen,Ity ,ctor
With that "shape e
can remodel the aK)
logarithmically:
aK) = b[lnK
0
) lnK)]
here:
Reverting back to
GQ,K) function and
substituting Q*:
1
ln
b
q
7
=
|
0
2 ln( ) ln
now, minimize w.r.t. K
meaning: G'(K) 0
G K K h I b K K 2 = + -
|
ocus on the Pen,Ity ,ctor
Finding the K* after the minimization:
To determine hat e should do, determine GK)
using K
0
and K*
2 2
2
is MARR for the company
I b
K
h 2
-
=
ets try one:
K
0
: $1000
7: $95 for each 7.5% reduction in setup cost
Annual quantity: 48000
Holding cost: $4.50
MARR is 13%
2 2
95 95
1218.55
.07796
1
ln
1 .075
2 .13 1218.55
$0.232
48000 4.5
b
K
-
= = =
|
- -
= =
-
Continuing:
nvestment to get to K*
Testing for decision
No investment K = K
0
):
At Min K*:
)
1218.55 ln 1000 ln .232
$10195.91
a K =
|
=
0 0
0
2 $20784.61
2
: 4619
G K K h
K
note EOQ pieces
h
2
2
= =
= =
2
316.58 1325.47 $1642
2
70
G K K h Ia K
K
EOQ K
h
2
2
- - -
-
-
= +
|
= + =
= =
SMED
Some terms:
SMED = single minute exchange of dies
hich means quick tooling change and lo
setup time cost)
nside Processes setup functions that
must be done 'inside' the machine or done
hen the machine is stopped
Minimally these ould include unbolting departing
fixtures/dies and positioning and bolting ne fixture/dies
to the machine
More %erms:
Outside Setup activities related to tooling
changes that can be done 'outside' of the
machine structure
These ould include:
Bringing Tooling to Machine
Bringing Ra Materials to Machine
Getting Prints/QC tools to machine
Etc.
ocus on SMED
When moving from "No Plan or Step 1 to
Step 2 separating nside from Outside
activities) investments ould be relatively lo
to accomplish a large amount of time cost)
saving
Essentially a ne set of change plans and a small
amount of training to the Material Handlers so that
they are alerted ahead of time and bring the
tooling out to the machine before it is needed
Moving to Step 3 ,nd Step 4
Require investments in Tooling
Require Design Changes
Require Family tooling and adaptors
Require common bolstering attachments
n general requiring larger and larger
investments in hardare to achieve smaller
and smaller time cost) savings in setup
%herefore, we c,n s,y SMED is:
n reality the essence of
a Logarithmic setup
reduction plan!
ets ook into ine ,I,ncing
This is a process to optimize the assignment of
individual tasks in a process based on a planed
throughput of a manufacturing system
t begins ith the calculation of a system "Takt or
Cycle time to build the required number of units
required over time
From takt time and a structured sequential analysis
of the time and steps required to manufacture
assembly) a product, compute the number of
stations required on the line
Once station count is determined, assign feasible
tasks to stations one-at-a-time filling up to takt time
for each station using rational decision/assignment
rules
ine ,I,ncing
Feasible tasks are ones that have all
predecessors completed or no
predecessors) and take less time
that the remaining time at a station
Feasibility is also subject to physical
constraints:
Zone Restriction the task are physically
separated taking to much movement time
to accomplish both ithin cycle like
attaching tires to front/back axles on a
bus!)
ncompatible tasks the Grinding/Gluing
constraint
Some of the C,IcuI,tions:
Takt Cycle) Time:
Minimum # Workstations req'r:
Prod. time/day Total Time - Allowances (T)
Target output/day Req'r Output (Q)
(min/unit)
Q
= =
=
(Total 1ob Task Time)
t
N
Efficiency C,IcuI,tions:
1
1
i
j
here t is the time actually consummed at the stations
t is the time of any task actually assigned to St K
N
i
i
line
J
$tK
i t
Eff
N
t
Eff
=
=
=
=
=
= = = <
25 33 33 21 40 40 44 19
4.04
63.4
5
i
t
N
N stations
+ + + + + + +
= = =