Plant Installation Project in Trout Farming

For Juan Manuel Fukushima Simabukuro ecotopicos@hotmail.com

Objective Function: Max ((Time Accelerated+(4*Probable Time)+Normal Time)/6) Subject to: Technical file, Construction of facilities, Culture training, Balanced food shop, Harvesting and marketing 116 Time Accelerated Normal Time/2 Biometric sample Fingerlings purchase and grow Fingerlings purchase and grow Implementation Implementation Parameter set ((Time Accelerated+(4*Probable Time)+Normal Time)/6) 126 Technical file, Construction of facilities, Implementation, Culture training, Fingerlings purchase and grow, balanced food shop, Biometric sample, Parameters set, Harvesting and marketing 0 Critical Path: 116 weeks

FIGURE N 1: CRTICAL PATH

START

D E F G I

FINISH

TABLE N 1: PROJET PROCESS ID A B C D E F G H I TOTAL PROCESS DURACION 4 6 2 4 18 46 38 38 18 174

TECHNICAL FILE CONSTRUCTION OF FACILITIES IMPLEMENTATION CULTURE TRAINING FINGERLINGS PURCHASE AND GROW BALANCED FOOD SHOP BIOMETRIC SAMPLE PARAMETERS SET HARVESTING AND MARKETING

TABLE N 2: ESTRATEGICS PROCESS ID A B D F I TOTAL PROCESS DURACION 4 6 4 46 18 116

TECHNICAL FILE CONSTRUCTION OF FACILITIES CULTURE TRAINING BALANCED FOOD SHOP HARVESTING AND MARKETING

TABLE N 3: PROCESS SUPORT ID C E G H TOTAL PROCESS DURACION 2 18 38 38 58

IMPLEMENTATION FINGERLINGS PURCHASE AND GROW BIOMETRIC SAMPLE PARAMETERS SET

TABLE N 4: ANSWERS REPORT


Microsoft Excel 14.0 Answer Report Worksheet: [matriz competencia engorde.xlsx]REDES Report Created: 05/11/2011 01:47:55 a.m. Result: Solver found a solution. All Constraints and optimality conditions are satisfied. Solver Engine Engine: GRG Nonlinear Solution Time: 0.016 Seconds. Iterations: 2 Subproblems: 0 Solver Options Max Time Unlimited, Iterations Unlimited, Precision 0.000001, Use Automatic Scaling Convergence 0.0001, Population Size 100, Random Seed 0, Derivatives Forward, Require Bounds Max Subproblems Unlimited, Max Integer Sols Unlimited, Integer Tolerance 1%, Assume NonNegative Objective Cell (Max) Cell SUM EXPECTED TIME Name Original Value 102.00 Final Value 126.00

Variable Cells Cell $E$8 $E$9 Name IMPLEMENTATION MORE LIKELY FINGERLINGS PURCHASE AND GROW MORE LIKELY Original Value 0.0 0.0 0.0 0.0 Final Value Integer 7.2 Contin 12.0 Contin 14.4 Contin 2.4 Contin

$E$10 BIOMETRIC SAMPLE MORE LIKELY $E$11 PARAMETERS SET MORE LIKELY Constraints Cell $E$8 $E$9 Name IMPLEMENTATION MORE LIKELY FINGERLINGS PURCHASE AND GROW MORE LIKELY

Cell Value

Formula

Status Not Binding Not Binding Binding

Slack 4.8 2.4 0

7.2 $E$8<=$E$9 12.0 $E$9<=$E$10 126.00 $G$12<=$G$14

$G$12 EXPECTED TIME

TABLE N 5: SENSITIVIYS REPORT Microsoft Excel 14.0 Sensitivity Report Worksheet: [matriz competencia engorde.xlsx]REDES Report Created: 05/11/2011 01:49:05 a.m.

Variable Cells Cell $E$8 $E$9 $E$10 $E$11 Name IMPLEMENTATION MORE LIKELY FINGERLINGS PURCHASE AND GROW MORE LIKELY BIOMETRIC SAMPLE MORE LIKELY PARAMETER SET MORE LIKELY Final Reduced Value Gradient 7.2 0 12 0 14.4 0 2.4 0

Constraints Cell Name $E$8 IMPLEMENTATION MORE LIKELY $E$9 FINGERLINGS PURCHASE AND GROW MORE LIKELY $G$12 EXPECTED TIME Final Lagrange Value Multiplier 7.2 0 12 0 126 1

TABLE N 6: LIMITSS REPORT Microsoft Excel 14.0 Limits Report Worksheet: [matriz competencia engorde.xlsx]REDES Report Created: 05/11/2011 01:49:11 a.m.

Cell $G$12 EXPECTED TIME

Objective Name

Value 126.00

Variable Cell Name $E$8 IMPLEMENTATION MORE LIKELY $E$9 FINGERLINGS PURCHASE AND GROW MORE LIKELY $E$10 BIOMETRIC SAMPLE MORE LIKELY $E$11 PARAMETER SET MORE LIKELY

Value 7.2 12.0 14.4 2.4

Lower Objective Limit Result 0.0 121.2 7.2 122.8 12.0 124.4 0.0 124.4

Upper Objective Limit Result 7.2 126.0 12.0 126.0 14.4 126.0 2.4 126.0

BIBLIOGRAPHY Herramientas de Gestin de Operaciones, Diplomado Gestin de Operaciones en Empresa de Servicio, Universidad Peruana de Ciencia Aplicadas. Sanagoran Project.