FINAL INSPECTION REQUEST FOR MECHANICAL EQUIPMENTS

PROJECT: BUILDING FOR MINISTRY OF HIGHER EDUCATION


Nature of inspection: Location /Area where required: Ref.Drg. Ref.Specs./BOQ Insp.No.

Inspection required at thoroughly

hrs.on

You are requested to inspect the work as the same has been inspected by the under signed and here by confirmed that the work is in accordance to the drawings, specifications. Contractors Representatives Al Adrak LLC Contractors Representatives Al Adrak LLC . CONSULTANT & CLIENT OBSERVATION Inspection carried out at Approved: Comments: hrs.on Approved with comments : Not Approved:

Structural /Civil/Arch/Mech/HVAC Gulf Engineering Consultancy

Client Ministry Of Higher Education

NOTTE : THE APPROVAL WILL NOT RELIEVE THE CONTRACTOR FORANY ERROR/DEFFECTS/NEGLEGENCE TO THE WORK IN ACCORDANCE TO THE CONTRACT ANY DEFECTS OBSERVERED LATER OUGHT TO BE RECTIFIED OR REPLACED AT CONTRACTORS RISK AND COST WITHOUT EXTRA TIME.