contractor

Client: Contractor :

Consultant:

INSPECTION APPROVAL REQUEST NO.: CCC-Q1-IR-M-EL-009

Inspection Date: 19/09/18 at 11:00am To : Consultants

Project Title:

Subject : Inspection Request for Installation of Ground Floor Slab Electrical Works.
The following works have been prepared in accordance with Drawings & Specifications and are ready for
inspection.
Drawing/Shop Drawing Specification Ref./
Sr. No.
Description Ref. Drawing. No./Detail No. Clause No./Page No.
1. .

- The works have been checked by the sub-contractor: M/s. First Choice Elec. Plumb. Cont. LLC.
On: 19/09/18 at 11:00am by: Eng.Gaffar Beag.

- The Contractor / Site Engineer has checked the work:

On: 18/Sep/2018/ by: _________________

 Approved  Approved as Noted  Revise & Resubmit  Not Approved


NOTES:

Inspected by: ……………………………….. Received back by the Contractor


Position : ………………………………..
On: _______/________/_______ at :00 : on: ______/_______/______ at ____: _____
Final Content Approval, Consultant
Site ……………. Specs: …………………

Consultant Engineer: ……………………….