Solar PV vs Solar Thermal SL.No.

1 2 3 4 5 6 Capacity 7 8 Location Technology availability High Irradiation required Available in India Description Area Required Cost Efficiency Project schedule Technology Solar PV 5-7 Acres 8-9 Crore/ Mw 10-18 % 16-18 months (50Mw) Crystalline / Thin film/CPV/Hybrid Any Capacity Solar Thermal 8-10 Acres 12-13 Crore / Mw 15% over all (Approx) 24 months (50Mw) Parabolic trough / Solar tower/Fresnel Reflectors Minimum 50 MW ( For commercial viability) High temperature required For solar field we have to depend on Europe/US