CACTUS FERTILIZERS, LTD.

HARIPUR

Commissioning Report SSP Plant


Revision: 00 Dated : 29-01-2012 Doc No. CFL-Prod-CM-01 Date: 29-01-2012

Feed Section Return S.C 02-SC3B Return S.C 02-SC3A Forward S.C 02-SC2 B.Elevator 02-EL2 Main Feed S.C 02-SC1 Rotary Valve 02-RV1

Empty Runnig

14:15 14:30 14:45 15:00 15:15 15:30 15:45 16:00

Post Startup Observations: Commissioning of feed section was carried out at minimum feed flow rate due to these issues. y y Driving Belt Slippage problem of all Screw Conveyor was observed. RPM of Main feed Screw Conveyor are less than that of our feed requirement. (Capacity calculation of Main feed screw conveyor and RPM comparison table of all equipments in feed section is attached) Fine rock leakage from feed control plate beneath the main rock hopper was observed. Vibration from forward screw conveyor after a constant time interval was observed.

y y Note: Feed Section commissioning was carried out in the presence of Mr.Aftab (Supervisor Mechanical Department) and his team.

Prepare By: Engineer M Abrar Aslam (Incharge SSP Plant) cc: Mr.Imtiaz Akhtar (Incharge Mechanical Department) cc: General Manager For Info Please

Time

Amp 3.0 3.1 3.1 3.1 3.1 3.1 3.1 3.1


Stopped

Amp 2.1 2.1 2.0 2.0 2.0 2.2 2.3 2.2


Stopped

Amp 1.3 1.6 1.5 1.5 1.5 1.6 1.7 2.1


Stopped

Amp 1 2 2 2 2 2 2 2
Stopped

Amp 0.4 0.4 0.4 0.4 0.4 0.4 0.5 0.5


Stopped

RPM
-------473 474 474 433 472 474 472 Stopped

Approved By:

M Akram Malik (Production Manager)