Professional Documents
Culture Documents
CONSOLE
REVISION HISTORY
Rev. Description ERO/ECN #
A Initial Release -----
B Formatting and content revisions. 041252
C Added Revision History page and drawing number in footer. C23257
D Made corrections in text. C24068
E Update figures. C25780
F Add photo numbers. C26023
G Make corrections in text. C26160
H Convert to Word 97 format. C28670
J Minor formatting change. C28926
K Add Table of Contents codes. Correct Level 5 and Level 6 styles and errors. C29222
The Mud Pump Console is not intended for Table 5-1. Mud Pump Console
routine operation of the mud pumps. The Specifications
throttle range from the Mud Pump Console
is restricted to half the range available from
ELECTRICAL
the Driller's Console. In addition, the Rod
Oiler, chain Oiler, and Charging Pump are The Mud Pump Console has dual- and sometimes
not automatically switched on. triple-control circuits, one for Mud Pump 1 and
another for Mud Pump 2. If there is a third circuit, it
would be for Mud Pump 3. Each circuit receives the
The Cement Pump Console can run the following voltages from the SCR units assignable to
cement pumps from zero to full speed (as Mud Pumps:
needed). Assignment power however is
derived from the Driller's Console so the 1. +14 VDC to turn on a POWER ON light.
Driller can maintain control over when the
2. -14 VDC contactor control logic.
cement pumps can be operated.
Each circuit outputs the following voltages to the
SPECIFICATIONS same SCR units.
OPERATING INSTRUCTIONS
(CONCLUDED)
POWER ON
OFF/ON LIGHT
SWITCH
THROTTLE HANDWHEEL
FS-067-04
To operate a pump from the Mud Pump the ON/OFF switch OFF at either of the
Console for maintenance activity, perform consoles prevents operation of the
the following steps: pump from either the Mud Pump
Console or the Driller's Console.
1. Set the MP1 (MP2) OFF/ON switch and
the corresponding throttle to OFF.
MAINTENANCE
2. At the Driller's Console, set the MP1
(MP2) THROTTLE to OFF. Set the Refer to the Section 3 (SCR Unit)
ASSIGNMENT switch to MP1 (MP2) for general instructions regarding
and turn On the corresponding OFF/ON shipping, storage and servicing.
switch.
3. At the Mud Pump Console, the MP 1 INSTALLATION
(MP 2) POWER ON light will illuminate.
4. Set the MP 1 (MP 2) OFF/ON switch to Four stabs are welded to the back panel of
ON and rotate the Mud Pump Console the console to facilitate bulkhead mounting.
THROTTLE HANDWHEEL to achieve
the desired speed. TESTING
5. To resume normal operation from the
Test the affected console after repairing or
Driller's Console, turn the Mud Pump
replacing any of its active components. A
Console THROTTLE HANDWHEEL to
functional test consists of operating the
OFF. Do not turn the Mud Pump
console according to the instructions listed
Console OFF/ON switch OFF. Turning
in the Driller's Console section.
LOCKOUT SWITCH
RHEOSTAT POWER ON
LIGHT
A. DOOR
PC CARD
B. CABINET
FS-017-33, FS-017-36
6265-023-02 Rev. A
6281-010-01 Rev. D
6281-010-01 Rev. D
B. Zero to - 8 VDC throttle reference B. Check for the presence of the signal at the Mud Pump Console
not reaching the DC Control Module. terminal board. If absent, the Mud Pump Throttle Handwheel
rheostat may be faulty.
SPECIFICATIONS