PROJECT: 122 MWp / 105 MWac SOLAR POWER PLANT AT

VALLE ESCONDIDO

Client: EPC Contractor:

Doc. name:
CL35-130-PRO-EL-SWI-001

Revision: 00 Total Pages 10

Title:

TESTING & COMMISSIONING PLAN-INTRODUCTION

Name Signature

M. Sanmugaraj /Pravesh
Prepared by
Kumar Tiwari

Reviewed by T. Raja

Approved by Krishna Pal Singh

Date 30-10-2021

1|P ag e
Content
1.Overview: ............................................................................................................................................................. 3
2. Brief description of Project: ................................................................................................................................. 3

3. Sequence and tests for commissioning: ............................................................................................................... 4

4.Approval Flow: ...................................................................................................................................................... 6

5.Schedule: .............................................................................................................................................................. 7

6.Commissioning log:............................................................................................................................................... 7

7.Turn Over: ............................................................................................................................................................ 7

8 Test Report: .......................................................................................................................................................... 7

9. Safety:................................................................................................................................................................ 10

10. Quality: ............................................................................................................................................................ 10

2|P ag e
1.Overview:

Commissioning protocols describe the outline for the process and procedures that will be used during the
testing and commissioning throughout the different stages of:
• Construction and Mechanical completion stage.
• Cold Commissioning and Grid Connection Readiness stage.
• Energization and Hot Commissioning stage.
• Reliability run and Performance Test.

Commissioning PV systems verifies that the installation has been satisfactorily and safely completed
according to plans and procedures.

Key steps of testing and commissioning include:

1. Electromechanical Completion test


2. Commissioning
3. Performance tests.

2. Brief description of Project:

▪Project Capacity – 122 MWp / 105 MWac

▪Project Location – The project site is in Copiapó region of Atacama Chile, 65 km south of Copiapó City.

▪Geographical Coordinates - The approximate latitude and longitude for the site is 27.81°S and 70.28°W.

▪Scope – The design, supply, construction, assembly and delivery of the plant by the EPC of the plant with
an operations and maintenance proposal for 2 years extendable option up to 15 years, on a turnkey basis
limited up to plant boundary with plant SS in EPC scope. Voltage Levels 33kV/220 kV. Power Transformer
is free issue item.

3|P ag e
3. Sequence and tests for commissioning:
After Electromechanical Completion Test, PV facility Commissioning (Cold & Hot) will start
followed by performance test (Trial Operation Period)
Cold & Hot commissioning will be done as per approved Testing and Commissioning
procedures, this includes:
1) PV array commissioning test
2) Inverter commissioning test
3) I&C equipment test
4) Grid compliance test

4|P ag e
Performance test:
After completion of commissioning, ten qualified days PR test will be carried out as per the
approved procedure.
Actual export capacity calculation (AC):
After completion of performance test, Actual export capacity calculation (AC) will be carried
out.

5|P ag e
4. Approval Flow:

Test Preformed as per EPC -GTR-5

Approved and Inspect by EPC T&C


team

Approved and Inspect by Project


Company –(Mainstream)

Approved by Independent Engineer


who perform the concerned test

Approved by CEN authorities.

Review/ Inspection

6|P ag e
5.Schedule:

The commissioning schedule is dictated by installation/construction completion. Key commissioning


milestones include initial energization/synchronization, initial acceptance and final acceptance.

The commissioning schedules will be provided at a later stage to keep project on track.

6.Commissioning log:

It’s necessary to track all issues and observations during commissioning activities and startup. This will serve
as a close out document and record resolution of any issues.

All key issues will be verified in closure, on Initial acceptance, any open issues will be added to the project
punch list. Repeated or critical failure shall be tracked by Quality compliance report.

7.Turn Over:

The turnover of the facility from construction to commissioning will occur section or Block. As each
section/Block is completed by construction, jurisdiction will be transferred commissioning.

Example: -
Once block 1 installation is completed as compared with ICL of all equipment’s the same block is handed
over to commissioning team for Testing purpose.

After that the area will be under safety actions and precautions with proper barriers and signages to perform
the respective test.

8 Test Report:
Checklist and commissioning reports as applicable shall be used along with procedures for testing and
commissioning. The checklist including commissioning reports shall be part of the record and
documentation. The test reports shall be submitted on daily basis or section/block wise.

7|P ag e
Sr.
CCL NO. DOCUMENT NAME
No.

SWITCHYARD EQUIPMENTS

1 SW-CCL-PTR-001 COMMISSIONING CHECKLIST FOR POWER TRANSFORMER

2 SW-CCL-ZTR-002 COMMISSIONING CHECKLIST FOR ZIG ZAG TRANSFORMER

3 SW-CCL-CT-003A COMMISSIONING CHECKLIST FOR CURRENT TRANSFORMER

4 SW-CCL-CT-003B COMMISSIONING CHECKLIST FOR CURRENT TRANSFORMER

5 SW-CCL-VT-004A COMMISSIONING CHECKLIST FOR POTENTIAL TRANSFORMER

6 SW-CCL-VT-004B COMMISSIONING CHECKLIST FOR POTENTIAL TRANSFORMER

7 SW-CCL-NCT-005A COMMISSIONING CHECKLIST FOR NEUTRAL CT

8 SW-CCL-NCT-005B COMMISSIONING CHECKLIST FOR NEUTRAL CT

9 SW-CCL-LA-006 COMMISSIONING CHECKLIST FOR LIGHTING ARRESTER

10 SW-CCL-ISO-007 COMMISSIONING CHECKLIST FOR ISOLATOR

11 SW-CCL-SF6CB-008 COMMISSIONING CHECKLIST FOR SF6 CIRCUIT BREAKER

12 SW-CCL-CRP-009 COMMISSIONING CHECKLIST FOR CONTROL RELAY PANEL

13 SW-CCL-EAR-010 COMMISSIONING CHECKLIST FOR EARTHING

MCR EQUIPMENTS

14 SW-CCL-ATR-011 COMMISSIONING CHECKLIST FOR AUXILARY TRANSFORMER

15 SW-CCL-MVCT-012A COMMISSIONING CHECKLIST FOR MV CURRENT TRANSFORMER

16 SW-CCL-MVCT-012B COMMISSIONING CHECKLIST FOR MV CURRENT TRANSFORMER

17 SW-CCL-MVPT-013A COMMISSIONING CHECKLIST FOR MV POTENTIAL TRANSFORMER

18 SW-CCL-MVPT-013B COMMISSIONING CHECKLIST FOR MV POTENTIAL TRANSFORMER

SW-CCL-MV SWGR &


19 COMMISSIONING CHECKLIST FOR MV SWITCHGEAR AND PANEL
PANEL-014

SW-CCL-LTDB-PDB-AUX
20 COMMISSIONING CHECKLIST FOR LT DISTRIBUTION BOARD
DB-015

21 SW-AUX LTP-016A COMMISSIONING CHECKLIST FOR AUXILLARY LT PANEL

P age |8
Sr.
CCL NO. DOCUMENT NAME
No.
SW-CCL-MAIN AUX LTP-
22 COMMISSIONING CHECKLIST FOR MAIN AUXILLARY LT PANEL
016B

23 SW-CCL-BATCHG-017 COMMISSIONING CHECKLIST FOR BATTERY CHARGER

24 SW-CCL-EDG-018 COMMISSIONING CHECKLIST FOR EMERGENCY DIESEL GENERATOR

25 SW-CCL-UPS-019 COMMISSIONING CHECKLIST FOR UPS SYSTEM

26 SW-CCL-BAT-20 COMMISSIONING CHECKLIST FOR BATTERY BANK

27 SW-CCL-DCDB-21 COMMISSIONING CHECKLIST FOR DC DISRIBUTION BOARD

28 SW-CCL-UPS DB-022 COMMISSIONING CHECKLIST FOR UPS DB

SW-CCL-OC & EF RLY-


29 COMMISSIONING CHECKLIST FOR OVER CURRENT AND EARTH FAULT RELAY
023

SW-CCL-MV SWGR VCB-


30 COMMISSIONING CHECKLIST FOR MV SWITCH GEAR VCB
024A

SW-CCL-MV SWGR
31 COMMISSIONING CHECKLIST FOR MV SWITCH GEAR BUS BAR
BUSBAR-024B

32 SW-CCL-MVCAB-025 COMMISSIONING CHECKLIST FOR MV CABLE

33 SW-CCL-MET-026 COMMISSIONING CHECKLIST FOR METERING PANEL

34 SW-CCL-FAS-027 COMMISSIONING CHECKLIST FOR FIRE ALARM SYSTEM

35 SW-CCL-CCTV-028 COMMISSIONING CHECKLIST FOR CCTV

PV PLANT EQUIPMENT

SW-CCL -DC-STRING
36 COMMISSIONING CHECKLIST FOR DC STRING CABLE IR
CAB-IR-029

37 SW-CCL-VOC-030 COMMISSIONING CHECKLIST FOR STRING CABLE VOC

38 SW-CCL-ISC-031 COMMISSIONING CHECKLIST FOR STRING CABLE ISC

39 SW-CCL-IVCURVE-032 COMMISSIONING CHECKLIST STRING CABLE IV CURVE

40 SW-CCL -LV-CAB-IR-033 COMMISSIONING CHECKLIST FOR LV CABLE INSULATION RESISTANCE TEST

41 SW-CCL-EAR-034 COMMISSIONING CHECKLIST FOR EARTHING SYSTEM

P age |9
42 SW-CCL-FOB-035 COMMISSIONING CHECKLIST FOR FIBER OPTIC CABLE

43 SW-CCL-WMS-036 COMMISSIONING CHECKLIST FOR WEATHER MONITERING SYSTEM

44 SW-CCL-SMS-037 COMMISSIONING CHECKLIST FOR SOIL MONITERING SYSTEM

9. Safety:

Testing and commissioning work will be in line with project HSSE-CESMP plan no personal will be allowed in
energised area which is in control of commissioning without proper training and authorization by Site
commissioning Manager or his representative. Standard electrical system safety practices should be used
during the evaluation or testing of grid- interactive inverters and photovoltaic systems. All countries have
installation codes and standards that help to assure the safe installation of hardware and systems, however,
testing of a system may involve working with a system or component that has wiring errors or unsafe
conditions. Only qualified personnel should conduct the tests described in this document. Safe practices
must be observed. It is recommended that for each installation, a “Safe Operating Procedure” be written,
reviewed and approved before work in the field begins. The “Safe Operating Procedure” must always be
adhered to . Any changes to the procedure must be reviewed and approved before testing continues.

10. Quality:

All the testing and commissioning will be carried out with high quality in compliance project quality plan
and quality assurance.