Professional Documents
Culture Documents
Chap 006
Chap 006
Operations Management
William J. Stevenson
8th edition
6-2
CHAPTER
McGraw-Hill/Irwin
Operations Management, Eighth Edition, by William J. Stevenson Copyright 2005 by The McGraw-Hill Companies, Inc. All rights reserved.
6-3
Introduction
y
Process selection
y
Major implications
Capacity planning y Layout of facilities y Equipment y Design of work systems
y
6-4
Forecasting
Capacity Planning
Layout
Technological Change
Work Design
6-5
Process Strategy
Key aspects of process strategy
6-6
Process Selection
y
Variety
y
Batch Repetitive
Flexibility
y
Volume
y
Continuous
6-7
Process Types
y
Job shop
y
Small scale Moderate volume High volumes of standardized goods or services Very high volumes of non-discrete goods
Batch
y
Repetitive/assembly line
y
Continuous
y
6-8
Not feasible
Repetitive
Continuous (flow)
Not feasible
6-9
Automation
y
Automation: Machinery that has sensing and control devices that enables it to operate
Fixed automation y Programmable automation
y
Automation
Computer-aided design and manufacturing systems (CAD/CAM) Numerically controlled (NC) machines Robot Manufacturing cell Flexible manufacturing systems(FMS) Computer-integrated manufacturing (CIM)
Facilities Layout
y
Layout: the configuration of departments, work centers, and equipment, with particular emphasis on movement of work (customers or materials) through the system
Accidents
The introduction of new products or services
Safety hazards
Product layout
y
Layout that uses standardized processing operations to achieve smooth, rapid, highvolume flow Layout that can handle varied processing requirements Layout in which the product or project remains stationary, and workers, materials, and equipment are moved as needed
Process layout
y
Product Layout
Figure 6.4
Station 4
Finished item
In
4 5
Workers
6
Out
10
Process Layout
Figure 6.7
Dept. B
Dept. D
Dept. F
Product Layout
Figure 6.7 (contd)
Can handle a variety of processing requirements y Not particularly vulnerable to equipment failures y Equipment used is less costly y Possible to use individual incentive plans
Cellular Layouts
y
Cellular Production
y
Layout in which machines are grouped into a cell that can process items that have similar processing requirements The grouping into part families of items with similar design or manufacturing characteristics
Group Technology
y
Functional
many longer variable greater higher higher higher higher lower few shorter fixed shorter lower lower lower lower higher
Cellular
Line Balancing is the process of assigning tasks to workstations in such a way that the workstations have approximately equal time requirements.
Cycle Time
Cycle time is the maximum time allowed at each workstation to complete its set of tasks on a unit.
N =
Precedence Diagram
Figure 6.10
Precedence diagram: Tool used in line balancing to display elemental tasks and sequence requirements
0.1 min. 1.0 min.
a c
0.7 min.
b d
0.5 min.
e
0.2 min.
Example 1 Solution
Time Remaining
1.0 0.9 0.2 1.0 1.0 0.5 0.3
Workstation
1
Eligible
a, c c none b d e -
Assign Task
a c b d e -
2 3
Positional weight is the sum of each tasks time and the times of all following tasks.
Example 2
0.2
0.2
0.3
a
0.8
b
0.6
f
1.0
g
0.4
h
0.3
Solution to Example 2
Station 1
Station 2
Station 3
Station 4
a c
e f d g h
Parallel Workstations
1 min. 30/hr. 1 min. 30/hr. 2 min. 30/hr. 1 min. 30/hr.
Bottleneck
30/hr. 1 min. 60/hr. 1 min. 30/hr. 1 min. 30/hr. 1 min. 30/hr. 1 min. 60/hr.
Parallel Workstations
Figure 6.12
30 1 170 3 10 0 2
Authors note:
y
The following three slides are not in the 8e, but I like to use them for alternate examples.
Process Layout
Milling Assembly & Test Grinding
Drilling
Plating
Functional Layout
222 444
Mill
222
Drill
1111 2222
Grind
3333
Assembly
111
Lathes
Heat treat
Gear cutting
111 444
222222222
Mill
Drill
3333333333
Lathe Mill
Grind - 3333
44444444444444
Mill
Flexible Manufacturing
Location/Criteria
Process Overview