Department of Electrical & Electronic Engineering Khulna university of Engineering and Technology

Course No:EE-2200

Project on internal wiring,Estimating & Costing of


KUET CAFETERIA
Submitted by Name: Udoy Paul Roll: 0803027 Department: EEE Section: A

Objectives:
The objectives of the project are:1.To design the wiring plan for KUET CAFETERA. 2.To show the circuit run & also the power circuit run. 3.To calculate illumination & number of Lights according to the required illumination. 4.To find out the total conduit,wire & various loads required for every part of the cafeteria. 5.Estimating total cost required for the wiring of cafeteria including labour cost.

Result:
Total conduit required= 780ft. Total wire required = (2268+874+196+713+504) = 4555ft. Total cost=74285.00TK.

Discussion:
The project helped to have a sensisible experience in designing & estimating a house wiring system. The design was pre pared