Introduction:
By this presentation I will do a Summary of the activity develop during the last 17 months in the IDT Company.
From
the
beginning
was
appointed
to
performance the role as Technical Advisor within the Infrastructure Team in the Region, participating in the School, Health, DoJ for Disabilities and High Court Programmes.
Active and systematic participation in the whole building process of the new school Sevengwana High School, within the Eradication of Mud School Programme. This Project started in August of 2008 and finished in April of 2009.
Quality Control Inspection to DoJ Disabilities Program: Setting Technical Report about quality and progress issues to 24 Projects in terms of accomplishment with the Standard Specification for Disabilities People and the works execution according to approved drawings.
Quality Control Inspection to 3 Projects within the Muyexe 100 Days Programme. Setting Technical Report about quality issues and progress to follows Projects:
I was appointed to advice this programme from December 2009 and during this period I have kept the site inspection every Wednesday to different projects which have been in the phase of final closure.
Manganeng (Finished)
Project.
The last February 26 I got the South African Driver License so now we are waiting for the appointment a car in order to be able to go to my site inspections regularly.
Implement the Quality Management System Start the Program for Skill Transference according the
WAY FORWARD
Be able to go to my site inspections regularly using the assigned car. Be able to use all the tools available in the IDT system to check our projects performance Collaborate in the implementation of Quality Management System in the Region. Elaborate and develop the skill transference program in the Region adequately.
Pictures
SITE INSPECTIONS.
Photo Album
by rafaelf
DEPARTMENT OF JUSTICE AND CONSTITUTIONAL FACILITIES FOR THE DISABLED DEVELOPMENT PROGRAMME PHASE 2
The ramp with handrails to the toilets access was built with a correctly gradient (10%), but dont exist the walkway towards the ramp.
The small ramp to access to the Court Hall was built with a correctly gradient too
The disable parking was built according the design and the standard specifications, the vertical signs were placed correctly but the horizontal signs were not put according to the standard specifications
The two new public toilet for disabled people were built with the quality required The door of the disabled toilet have problem also with the incorrectly height the vertical gab bar and the door lock
In side were placed new WC, WHB, mirror, and the steel accessory for disabled and a new door that opens to outside the horizontal grab bar and toilet roll holder have incorrectly height in accordance with the Design
The access to the Court Hall has different level that it must resolve in the second phase like the signs and the other things in the drawing had not put into the Court Hall.
In side were placed new WC, WHB, mirror, and the steel accessory for disabled and a new door that opens to outside the horizontal grab bar and toilet roll holder have incorrectly height in accordance with the Design
General Considerations About this Project on Site. The execution quality is well in general in this Court. The problem with the horizontal grab bar, toilet roll holder, door lock and vertical grab bar must be resolved in the less time possible to the disabled people can use.
Thank you.
Gracias.