Work plan BUILDING No. 603 & 608.

1. Mobilization
1.1.
AL-SHAYAE Est. Contracting Establishment shall prepare the currently

available offices at site for OPM engineers, technicians and employees as well as the engineers and supervisors of SANG supervision office and shall ensure availability of electrical current, water lines from the currently available source if possible or as an alternative, to secure such facilities at the cost of the establishment without any tangible or intangible compensation.

1.2.
1.3.

Provide and prepare bathrooms, ablution place, prayer hall, and cold Provide window type AC units in good operation condition at currently

water for OPM and SANG engineers office's personnel. available office (in case it were not available) or maintain and operate air conditioning units if and were sufficient to fulfill the purpose.

2. Civil works
2.1. Concrete shall not be placed on mud or un-compacted fill (minimum 95% Cement shall be Portland cement and shall meet the requirements of

compactions)

2.2.

ASTM specification C 150. AH concrete in contact with soil shall have high sulfate resistance Type V Portland cement and shall be coated with 2 coats of bitumen paint. 2.3. Water shall be potable, clean, and free from injurious amounts of oils, acids, alkalis, organic materials, or other substances that may be deleterious to concrete or steel. 2.4. 2.5. 2.6. Discharge concrete from a truck within 1-1/2 hours from the time concrete We will remove all existing junk materials at in rooms , hallways , roof , out All old windows and existing wooden will be remove , and we will install new mix poured into the concrete truck. bldg 603 & 608. aluminum windows to all rooms & toilets , with all accessories.

2.7. 2.8.

All existing wooden doors & jambs will be remove , and we will install new Two existing doors in classrooms stage area will romove, and we will

hollow metal doors & jambs for all rooms & aluminum doors for toilets. complete the work as per attached drawings, and we will supply new hollow metal doors (2.00 m width * 2.10 m height with all accessories). 2.9. We will replace all damage steps & risers to all main and secondary entrance stairs & the missing ceramic well tiles to all toilets in bldg 603. 2.10. The sidewalk and curbs on all sides of building will be repair as the attached drawings. 2.11. All cracks of all external & internal will be repair by specil material from FOSAM CO. and we will submit a sample to the OPM & SANG ENG, for approval. 2.12. we will supply "two roof tanks 5000 lit, and new pipe from underground water to 3-latrines, and provide 1-beam pad for the polyethane plastic tanks. 2.13. Clean and repair all downspout drain & paint all with weather resistance paint , match the existing external walls color.

2.14. Water proofing and thermal insulation works. 2.14.1.


Water proofing and thermal insulation works shall be carried out

according to the following items in addition to the instructions of the approved manufacturing company by OPM and SANG engineers. 2.14.2. 2.14.3. Work shall be extended by waterproofing specialized company All preparative works such as hole filling, juts/bulges removal, and shall provide 10 year warrantee for all waterproofing work. surface smoothing, cleaning, supply of ancillary materials of primer coating, or accessories and materials, manpower, equipment, transport services, required testing. 2.14.4. 2.14.5. Measurements shall be in square meter for horizontal projections All areas around roof drains and skirting of AC compressors on AL-SHAYAE est. shall be install new 2 layers , 4 mm (PY40E) . The job includes 20cm skirting with aluminum strips support, and without any additional cost for slopes or skirting for insulation layers. roof shall be included in water proofing application.

2.14.6.
2.14.7.

covering of all gaps, and portion of PVC pipes over roof & canopies of the entire building. 2.15. The expansion joint filler material shall have the following properties: high density, low water absorption, high compressive strength and shall be none-

extruding. sealant shall prevent the penetration of liquid and moisture into the join, direct.

2.16. Painting works:


2.16.1. 2.16.2. 2.16.3. corners. General: All surfaces shall be painted as shown on the drawings Work shall include removal of old paint and repair of all cracks Complete paint application shall be implemented to edges and All surfaces shall be painted with primer coat as required in Surface to be painted shall be prepared, inspected and treated. Price includes: all materials Sigma brand or equivalent, accessories

and according to the manufacturing company instructions. with approved methods prior to new paint.

2.16.4.
2.16.5.

drawings in the manner acceptable to the OPM & SANG engineer.

2.16.6.

items, labor, equipment, scaffolding, transport means, material handling, cleaning, and protecting adjacent surface. Measurement shall be by square meter and the openings shall not be counted. 2.17. Restoration for utility, All excavations for utilities shall be restored to its original conditions. 2.18. Concrete shall not be placed on mud or un-compacted fill (minimum 95% compactions) 2.19. Cement shall be Portland cement and shall meet the requirements of ASTM specification C 150. AH concrete in contact with soil shall have high sulfate resistance Type V Portland cement and shall be coated with 2 coats of bitumen paint. 2.20. Water shall be potable, clean, and free from injurious amounts of oils, acids, alkalis, organic materials, or other substances that may be deleterious to concrete or steel. 2.21. Discharge concrete from a truck within 1-1/2 hours from the time concrete mix poured into the concrete truck.

2.22. The expansion joint filler material shall have the following properties: high
density, low water absorption, high compressive strength and shall be noneextruding. sealant shall prevent the penetration of liquid and moisture into the join, direct. 2.23. All excavated materials, unless proven suitable materials should be removed from the site and shall not be used as backfilling materials. 2.23.1. AL-SHAYAE Est. will painted all Doors and door jambs, it shall be prepared to be painted and include sanding and painting the doors with rust

proof primer and two coats of oil-base paint color matching existing building doors. 2.23.2. Price includes: all materials Sigma brand or equivalent, accessories items, labor, equipment, scaffolding, transport means, material handling, cleaning, and protecting adjacent surface.

2.23.3.
2.23.4.

The all paint (INTERIOR & EXTERNAL) shall coform with AL-SHAYAE Est. will submit a sample to approved by OPM &

manufactures standards and specifications . SANG Engineers for all paint type.

3. Mechanical.
3.1 Materials and equipment shall be the standard products of a manufacturer regularly engaged in the manufacture of such products and have been in satisfactory use for at least five years prior bid opening. The ventilators shall be totally noise- free and shall be acceptable to the OPM and SANG engineers. 3.1.1 We will supply wheeled fire extinguisher units, dry powder type, 5 kg & include a hose with nozzle . 3.1.2 laying. 3.1.3 3.1.4 3.1.5 3.1.6 The trench shall be backfilled back to its natural ground level after Water manhole in the main water connection it shall be concrete All window A/C units (carrier brand) shall be 24.000 BTU 220V , All Split A/C units (carrier brand) wall mounted type , 24.000 BTU the pressure testing of the water line. with heavy duty standard cast iron ci\over and marks(POTABLE WATER). 60HZ, heat & cool system , The job shall includes dismanting of old A/C units. 220V , 60HZ, heat & cool system , The job includes installation of elcctrical power system. 3.1.7 3.1.8 80). 3.1.9 3.1.10 3.1.11 The CPVC water lines pipe 1/2" Dia(13mm) shall be SCH80). Ceramic eastern commodes & western commodes & hand wash The combination faucet &P-trap & all exposed fittings shall be New elc water pump shall be 1.5 HP 220 V. The all exterior cold water shall be (G.I. pipe 1-1/2" & 1" Dia. SCH All exterior cold water piping (PVC SCH . 80) with warning tape

basins , shall be (SAUDI CERAMIC). GROHE original.

3.1.12

The floor drains,20*20cm , shall be a heavy duty type "ITALIAN All manholes cover shall be (SAUDI CAST) heavy duty type . Water heaters (100 liters & 50 kizef " GRADE 1.

GRADE 1".

3.1.13 3.1.14

4 ELECTRICAL.
4.1 AL-SHAYAE Est. shall furnish complete design, work and materials with

shop drawings of the entire wiring systems for exterior lights and floodlights to include the panel board load schedules prior to any work for approval.

4.2
4.3 4.4 4.5

All conduits to be used for general wiring are rigid steel conduits of 1/2" All joints to the junction box shall be cut square, reamed smooth and draw All bends shall be free of dents or flattening and shall not be more than three All utility and junction boxes shall be metal and sizes shall be determined as All electrical equipment, devices light fixtures shall be new and shall be All new under ground power cables from MDP to the interior panel boards

diameter Minimum size. up tight and shall be secured with box connectors. quarter bends. per actual wiring requirements such as standard junction and utility boxes.

4.6
4.7

subject for the approval of the OPM and SANG engineers, prior installation. shall be CU/STA/PVC/XLPE, 0.6/1KV and shall be protected with cable tiles protector and warning tapes.

SITE WORKS.
5.1 5.2 Carry out engineering survey plans for the entire site on which facilities Carry out grid on engineering plans and drawings of the general site

and existing buildings are shown. layout on which all currently levels including recess or elevation of the site levels are shown in accordance with the thresholds of existing buildings.

TESTING AND COMMISSIONING.

Testing will be the responsibility of AL-SHAYAE EST. and will be performed at the site or approved testing laboratory if requested by OPM engineers.

DEMOBILIZATION.
All temporary structure will be demobilized upon project completion.

ASBUILT DRAWINGS.
AL-SHAYAE Est. will maintain a full size set of subcontract drawing for depicting a daily record of as-built condition. This drawing will be maintained in a current, reproducible condition at all times during the entire subcontract period and will be readily available for review by OPM engineers at all times. The as-built drawing will be updated daily and showing all changes from the subcontract plans, which are made in the work, or additional information which may be uncovered in the course of construction. This information will be recorded on the prints accurately and neatly with details and notes.

INITIAL HANDOVER.
After the project is completed it is time to initially hand over the site to OPM and SANG engineers.

10

FINAL HANDOVER.
One year after the initial hand over, final hand over will take place.

_____________________________________________________________________________

Thank you for your kind consideration. Best regards, Subcontractor Al-Shayae Est For Contracts