ELEMENTAL COST ANALYSIS
1.0
BILL NO. 5 - DOUBLE STOREY LINK HOUSES - 22' x 80' INTERMEDIATE UNIT TYPE A1
SINGLE FRONTAGE (WITH PAD FOOTING)
2
215 m
Gross Floor Area =
#
1.1
1.2
2.1
2.2
2.3
2.4
3.1
3.2
3.3
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
Element
Cost/F.S.
(RM)
Cost/m
(RM)
Piling
Work Below Ground Floor Level
29,410.35
12.71
136.79
13.16
Sub-Total (Item 1.1-1.2)
29,410.35
12.71
136.79
13.16
Frame
Upper Floors
Roof Construction
Staircase Construction
25,498.20
10,566.84
13,735.85
3,092.07
11.02
4.57
5.94
1.34
118.60
49.15
63.89
14.38
11.41
4.73
6.15
1.38
Sub-Total (Item 2.1-2.4)
52,892.96
22.86
246.01
23.68
Roof Finishes
Ext. Walls, Doors & Windows
Int. Partitions & Doors
10,102.10
11,335.31
15,159.38
4.37
4.90
6.55
46.99
52.72
70.51
4.52
5.07
6.79
Sub-Total (Item 3.1-3.3)
36,596.79
15.81
170.22
16.38
Ext. Wall Finishes
Int. Wall Finishes
Floor Finishes
Staircase Finishes
Ceiling Finishes
Sundries
Sanitary Fittings
External Works Within Boundary
Ext. Mechanical and Electrical
Int. Mechanical and Electrical
TNB Substation
Infrastructure Works
3,556.42
12,441.22
11,757.66
2,933.72
6,932.10
1,143.45
3,461.49
18,963.51
3,456.10
14,804.74
2,046.51
16,541.90
1.54
5.38
5.08
1.27
3.00
0.49
1.50
8.19
1.49
6.40
0.88
7.15
16.54
57.87
54.69
13.65
32.24
5.32
16.10
88.20
16.07
68.86
9.52
76.94
1.59
5.57
5.26
1.31
3.10
0.51
1.55
8.49
1.55
6.63
0.92
7.40
Sub-Total (Item 4.1-4.12)
98,038.82
42.36
455.99
43.88
216,938.92
93.74
1,009.02
97.10
6,204.91
265.92
2.68
0.11
28.86
1.24
2.78
0.12
223,409.75
96.54
1,039.12
100.00
Sub - Total
5.1
5.2
Cost
(RM)
2,314 F.S.
Preliminaries
Prime Cost and Provisional Sums
Total
02/1361/C3-1
1.
ELEMENTAL COST ANALYSIS
2.0
BILL NO. 6 - DOUBLE STOREY LINK HOUSES - 22' x 80' INTERMEDIATE UNIT TYPE A2
DOUBLE FRONTAGE (WITH FOOTING)
212 m
Gross Floor Area =
#
1.1
1.2
2.1
2.2
2.3
2.4
3.1
3.2
3.3
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
Element
2,282 F.S.
Cost/F.S.
(RM)
Cost/m2
(RM)
Piling
Work Below Ground Floor Level
30,360.02
13.30
143.21
13.27
Sub-Total (Item 1.1-1.2)
30,360.02
13.30
143.21
13.27
Frame
Upper Floors
Roof Construction
Staircase Construction
27,270.27
11,754.16
13,808.60
1,827.14
11.95
5.15
6.05
0.80
128.63
55.44
65.13
8.62
11.92
5.14
6.04
0.80
Sub-Total (Item 2.1-2.4)
54,660.17
23.95
257.83
23.90
Roof Finishes
Ext. Walls, Doors & Windows
Int. Partitions & Doors
11,173.12
11,557.89
14,595.78
4.90
5.06
6.40
52.70
54.52
68.85
4.88
5.05
6.38
Sub-Total (Item 3.1-3.3)
37,326.79
16.36
176.07
16.31
Ext. Wall Finishes
Int. Wall Finishes
Floor Finishes
Staircase Finishes
Ceiling Finishes
Sundries
Sanitary Fittings
External Works Within Boundary
Ext. Mechanical and Electrical
Int. Mechanical and Electrical
TNB Substation
Infrastructure Works
3,418.18
13,115.37
12,338.21
2,626.42
8,614.31
1,394.24
3,461.49
18,698.90
3,456.10
14,598.16
2,046.51
16,311.09
1.50
5.75
5.41
1.15
3.77
0.61
1.52
8.19
1.51
6.40
0.88
7.05
16.12
61.86
58.20
12.39
40.63
6.58
16.33
88.20
16.30
68.86
9.52
75.87
1.49
5.73
5.39
1.15
3.76
0.61
1.51
8.17
1.51
6.38
0.89
7.13
100,078.98
43.74
470.88
43.73
222,425.96
97.36
1,047.99
97.21
6,118.33
262.21
2.68
0.11
28.86
1.24
2.67
0.11
228,806.50
100.15
1,078.09
100.00
Sub-Total (Item 4.1-4.12)
Sub - Total
5.1
5.2
Cost
(RM)
Preliminaries
Prime Cost and Provisional Sums
Total
02/1361/C3-1
2.
ELEMENTAL COST ANALYSIS
3.0
BILL NO. 7 - DOUBLE STOREY LINK HOUSES - 24' x 80' CORNER UNIT TYPE C1
SINGLE FRONTAGE (WITH FOOTING)
269 m2
Gross Floor Area =
#
1.1
1.2
2.1
2.2
2.3
2.4
3.1
3.2
3.3
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
Element
Cost/F.S.
(RM)
Cost/m
(RM)
Piling
Work Below Ground Floor Level
48,533.94
16.76
180.42
15.53
Sub-Total (Item 1.1-1.2)
48,533.94
16.76
180.42
15.53
Frame
Upper Floors
Roof Construction
Staircase Construction
44,742.93
13,334.35
13,794.05
2,805.93
15.45
4.61
4.76
0.97
166.33
49.57
51.28
10.43
14.32
4.27
4.41
0.90
Sub-Total (Item 2.1-2.4)
74,677.26
25.79
277.61
23.90
Roof Finishes
Ext. Walls, Doors & Windows
Int. Partitions & Doors
17,681.11
22,332.73
14,977.16
6.11
7.71
5.17
65.73
83.02
55.68
5.66
7.15
4.79
Sub-Total (Item 3.1-3.3)
54,991.00
18.99
204.43
17.60
Ext. Wall Finishes
Int. Wall Finishes
Floor Finishes
Staircase Finishes
Ceiling Finishes
Sundries
Sanitary Fittings
External Works Within Boundary
Ext. Mechanical and Electrical
Int. Mechanical and Electrical
TNB Substation
Infrastructure Works
6,231.68
18,206.90
15,801.74
2,697.23
10,024.31
1,347.99
3,461.49
23,726.43
3,456.10
18,523.14
2,046.51
20,696.62
2.15
6.29
5.46
0.93
3.46
0.47
1.20
8.19
1.19
6.40
0.71
7.15
23.17
67.68
58.74
10.03
37.27
5.01
12.87
88.20
12.85
68.86
7.61
76.94
1.99
5.83
5.06
0.86
3.21
0.43
1.11
7.59
1.11
5.93
0.65
6.62
126,220.14
43.59
469.22
40.39
304,422.34
105.14
1,131.68
97.41
7,763.35
332.71
2.68
0.11
28.86
1.24
2.48
0.11
312,518.40
107.93
1,161.78
100.00
Sub-Total (Item 4.1-4.12)
Sub - Total
5.1
5.2
Cost
(RM)
2,896 F.S.
Preliminaries
Prime Cost and Provisional Sums
Total
02/1361/C3-1
3.
ELEMENTAL COST ANALYSIS
4.0
BILL NO. 8 - DOUBLE STOREY LINK HOUSES - 24' x 80' CORNER UNIT TYPE C1
DOUBLE FRONTAGE (WITH FOOTING)
2
270 m
Gross Floor Area =
#
1.1
1.2
2.1
2.2
2.3
2.4
3.1
3.2
3.3
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
Element
Cost/F.S.
(RM)
Cost/m
(RM)
Piling
Work Below Ground Floor Level
48,533.94
16.70
179.76
15.52
Sub-Total (Item 1.1-1.2)
48,533.94
16.70
179.76
15.52
Frame
Upper Floors
Roof Construction
Staircase Construction
44,742.93
13,334.35
13,794.05
2,805.93
15.40
4.59
4.75
0.97
165.71
49.39
51.09
10.39
14.30
4.26
4.41
0.90
Sub-Total (Item 2.1-2.4)
74,677.26
25.69
276.57
23.87
Roof Finishes
Ext. Walls, Doors & Windows
Int. Partitions & Doors
17,657.83
22,332.73
14,977.16
6.08
7.68
5.15
65.40
82.71
55.47
5.64
7.14
4.79
Sub-Total (Item 3.1-3.3)
54,967.72
18.92
203.57
17.57
Ext. Wall Finishes
Int. Wall Finishes
Floor Finishes
Staircase Finishes
Ceiling Finishes
Sundries
Sanitary Fittings
External Works Within Boundary
Ext. Mechanical and Electrical
Int. Mechanical and Electrical
TNB Substation
Infrastructure Works
6,231.68
18,206.90
15,851.69
2,697.23
10,024.31
1,347.99
3,461.49
23,814.64
3,456.10
18,592.00
2,046.51
20,773.56
2.14
6.26
5.45
0.93
3.45
0.46
1.19
8.19
1.19
6.40
0.70
7.15
23.08
67.43
58.71
9.99
37.13
4.99
12.82
88.20
12.80
68.86
7.58
76.94
1.99
5.82
5.07
0.86
3.20
0.43
1.11
7.61
1.10
5.94
0.65
6.64
-
126,504.09
43.53
468.53
40.44
304,683.01
104.84
1,128.44
97.40
7,792.21
333.95
2.68
0.11
28.86
1.24
2.49
0.11
312,809.17
107.63
1,158.53
100.00
Sub-Total (Item 4.1-4.12)
Sub - Total
5.1
5.2
Cost
(RM)
2,906 F.S.
Preliminaries
Prime Cost and Provisional Sums
Total
02/1361/C3-1
ELEMENTAL COST ANALYSIS
5.0
4.
BILL NO. 9 - DOUBLE STOREY LINK HOUSES - 24' x 80' SPECIAL CORNER UNIT TYPE C2
SINGLE FRONTAGE (WITH FOOTING)
313 m
Gross Floor Area =
#
1.1
1.2
2.1
2.2
2.3
2.4
3.1
3.2
3.3
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
Element
3,369 F.S.
Cost/F.S.
(RM)
Cost/m2
(RM)
Piling
Work Below Ground Floor Level
49,984.72
14.84
159.70
14.67
Sub-Total (Item 1.1-1.2)
49,984.72
14.84
159.70
14.67
Frame
Upper Floors
Roof Construction
Staircase Construction
44,553.10
17,758.37
14,025.88
2,951.42
13.22
5.27
4.16
0.88
142.34
56.74
44.81
9.43
13.08
5.21
4.12
0.87
Sub-Total (Item 2.1-2.4)
79,288.77
23.53
253.32
23.28
Roof Finishes
Ext. Walls, Doors & Windows
Int. Partitions & Doors
19,290.96
22,919.10
15,088.03
5.73
6.80
4.48
61.63
73.22
48.20
5.66
6.73
4.43
Sub-Total (Item 3.1-3.3)
57,298.09
17.01
183.06
16.82
Ext. Wall Finishes
Int. Wall Finishes
Floor Finishes
Staircase Finishes
Ceiling Finishes
Sundries
Sanitary Fittings
External Works Within Boundary
Ext. Mechanical and Electrical
Int. Mechanical and Electrical
TNB Substation
Infrastructure Works
7,876.54
18,978.05
18,559.76
2,636.90
12,364.75
1,229.43
4,230.71
27,607.34
3,456.10
21,552.94
2,046.51
24,081.94
2.34
5.63
5.51
0.78
3.67
0.36
1.26
8.19
1.03
6.40
0.61
7.15
25.16
60.63
59.30
8.42
39.50
3.93
13.52
88.20
11.04
68.86
6.54
76.94
2.31
5.57
5.45
0.77
3.63
0.36
1.24
8.11
1.01
6.33
0.60
7.07
144,620.97
42.93
462.05
42.46
331,192.55
98.30
1,058.12
97.23
9,033.19
387.14
2.68
0.11
28.86
1.24
2.65
0.11
340,612.87
101.10
1,088.22
100.00
Sub-Total (Item 4.1-4.12)
Sub - Total
5.1
5.2
Cost
(RM)
Preliminaries
Prime Cost and Provisional Sums
Total
02/1361/C3-1
ELEMENTAL COST ANALYSIS
6.0
5.
BILL NO. 10 - DOUBLE STOREY LINK HOUSES - 24' x 80' SPECIAL CORNER UNIT TYPE C2
DOUBLE FRONTAGE (WITH FOOTING)
313 m
Gross Floor Area =
#
1.1
1.2
2.1
2.2
2.3
2.4
3.1
3.2
3.3
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
Element
3,369 F.S.
Cost/F.S.
(RM)
Cost/m
(RM)
Piling
Work Below Ground Floor Level
49,984.72
14.84
159.70
14.68
Sub-Total (Item 1.1-1.2)
49,984.72
14.84
159.70
14.68
Frame
Upper Floors
Roof Construction
Staircase Construction
44,553.10
17,758.37
14,025.88
2,951.42
13.22
5.27
4.16
0.88
142.34
56.74
44.81
9.43
13.09
5.22
4.12
0.87
Sub-Total (Item 2.1-2.4)
79,288.77
23.53
253.32
23.29
Roof Finishes
Ext. Walls, Doors & Windows
Int. Partitions & Doors
19,290.96
22,919.10
15,008.03
5.73
6.80
4.45
61.63
73.22
47.95
5.67
6.73
4.41
Sub-Total (Item 3.1-3.3)
57,218.09
16.98
182.81
16.81
Ext. Wall Finishes
Int. Wall Finishes
Floor Finishes
Staircase Finishes
Ceiling Finishes
Sundries
Sanitary Fittings
External Works Within Boundary
Ext. Mechanical and Electrical
Int. Mechanical and Electrical
TNB Substation
Infrastructure Works
7,876.54
18,978.05
18,491.86
12,636.90
2,364.75
1,229.43
4,230.71
27,607.34
3,456.10
21,552.94
2,046.51
24,081.94
2.34
5.63
5.49
3.75
0.70
0.36
1.26
8.19
1.03
6.40
0.61
7.15
25.16
60.63
59.08
40.37
7.56
3.93
13.52
88.20
11.04
68.86
6.54
76.94
2.31
5.57
5.43
3.71
0.69
0.36
1.24
8.11
1.02
6.33
0.60
7.07
144,553.07
42.91
461.83
42.46
331,044.65
98.26
1,057.65
97.23
9,033.19
387.14
2.68
0.11
28.86
1.24
2.65
0.11
340,464.96
101.04
1,087.75
100.00
Sub-Total (Item 4.1-4.12)
Sub - Total
5.1
5.2
Cost
(RM)
Preliminaries
Prime Cost and Provisional Sums
Total
02/1361/C3-1
6.
ELEMENTAL COST ANALYSIS
1.0
BILL NO. 11 - DOUBLE STOREY LINK HOUSES - 22' x 80' INTERMEDIATE UNIT TYPE A1
SINGLE FRONTAGE (WITH PILING)
215 m
Gross Floor Area =
#
1.1
1.2
2.1
2.2
2.3
2.4
3.1
3.2
3.3
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
Element
2,314 F.S.
Cost/F.S.
(RM)
Cost/m2
(RM)
Piling
Work Below Ground Floor Level
19,528.02
25,288.90
8.44
10.93
90.83
117.62
8.18
10.59
Sub-Total (Item 1.1-1.2)
44,816.92
19.37
208.45
18.77
Frame
Upper Floors
Roof Construction
Staircase Construction
25,498.20
10,566.84
13,735.85
3,092.07
11.02
4.57
5.94
1.34
118.60
49.15
63.89
14.38
10.68
4.42
5.75
1.29
Sub-Total (Item 2.1-2.4)
52,892.96
22.86
246.01
22.15
Roof Finishes
Ext. Walls, Doors & Windows
Int. Partitions & Doors
10,102.10
11,335.31
15,159.38
4.37
4.90
6.55
46.99
52.72
70.51
4.23
4.75
6.35
Sub-Total (Item 3.1-3.3)
36,596.79
15.81
170.22
15.32
Ext. Wall Finishes
Int. Wall Finishes
Floor Finishes
Staircase Finishes
Ceiling Finishes
Sundries
Sanitary Fittings
External Works Within Boundary
Ext. Mechanical and Electrical
Int. Mechanical and Electrical
TNB Substation
Infrastructure Works
3,556.42
12,441.22
11,757.66
2,933.72
6,932.10
1,143.45
3,461.49
18,963.51
3,456.10
14,804.74
2,046.51
16,541.90
1.54
5.38
5.08
1.27
3.00
0.49
1.50
8.19
1.49
6.40
0.88
7.15
16.54
57.87
54.69
13.65
32.24
5.32
16.10
88.20
16.07
68.86
9.52
76.94
1.49
5.21
4.92
1.23
2.90
0.48
1.45
7.94
1.45
6.20
0.86
6.93
Sub-Total (Item 4.1-4.12)
98,038.82
42.36
455.99
41.05
232,345.49
100.40
1,080.68
97.29
6,204.91
265.92
2.68
0.11
28.86
1.24
2.60
0.11
238,816.32
103.19
1,110.77
100.00
Sub - Total
5.1
5.2
Cost
(RM)
Preliminaries
Prime Cost and Provisional Sums
Total
02/1361/C3-1
7.
ELEMENTAL COST ANALYSIS
2.0
BILL NO. 12 - DOUBLE STOREY LINK HOUSES - 24' x 80' CORNER UNIT TYPE C1
SINGLE FRONTAGE (WITH PILING)
2
269 m
Gross Floor Area =
#
1.1
1.2
2.1
2.2
2.3
2.4
3.1
3.2
3.3
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
Element
Cost/F.S.
(RM)
Cost/m2
(RM)
Piling
Work Below Ground Floor Level
24,432.74
38,924.91
8.44
13.44
90.83
144.70
7.46
11.89
Sub-Total (Item 1.1-1.2)
63,357.65
21.88
235.53
19.36
Frame
Upper Floors
Roof Construction
Staircase Construction
44,742.93
13,334.35
13,794.05
2,805.93
15.45
4.61
4.76
0.97
166.33
49.57
51.28
10.43
13.67
4.07
4.21
0.86
Sub-Total (Item 2.1-2.4)
74,677.26
25.79
277.61
22.81
Roof Finishes
Ext. Walls, Doors & Windows
Int. Partitions & Doors
17,681.11
22,332.73
14,977.16
6.11
7.71
5.17
65.73
83.02
55.68
5.40
6.82
4.58
Sub-Total (Item 3.1-3.3)
54,991.00
18.99
204.43
16.80
Ext. Wall Finishes
Int. Wall Finishes
Floor Finishes
Staircase Finishes
Ceiling Finishes
Sundries
Sanitary Fittings
External Works Within Boundary
Ext. Mechanical and Electrical
Int. Mechanical and Electrical
TNB Substation
Infrastructure Works
6,231.68
18,206.90
15,801.74
2,697.23
10,024.31
1,347.99
3,461.49
23,726.43
3,456.10
18,523.14
2,046.51
20,696.62
2.15
6.29
5.46
0.93
3.46
0.47
1.20
8.19
1.19
6.40
0.71
7.15
23.17
67.68
58.74
10.03
37.27
5.01
12.87
88.20
12.85
68.86
7.61
76.94
1.90
5.56
4.83
0.82
3.06
0.41
1.06
7.25
1.06
5.66
0.63
6.32
126,220.14
43.59
469.22
38.56
319,246.04
110.26
1,186.79
97.53
7,763.35
332.71
2.68
0.11
28.86
1.24
2.37
0.10
327,342.10
113.05
1,216.89
100.00
Sub-Total (Item 4.1-4.12)
Sub - Total
5.1
5.2
Cost
(RM)
2,896 F.S.
Preliminaries
Prime Cost and Provisional Sums
Total
02/1361/C3-1
8.
ELEMENTAL COST ANALYSIS
3.0
BILL NO. 13 - DOUBLE STOREY LINK HOUSES - 24' x 80' CORNER UNIT TYPE C2
SINGLE FRONTAGE (WITH PILLING)
2
313 m
Gross Floor Area =
#
1.1
1.2
2.1
2.2
2.3
2.4
3.1
3.2
3.3
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
Element
Cost/F.S.
(RM)
Cost/m2
(RM)
Piling
Work Below Ground Floor Level
28,429.17
39,596.42
8.44
11.75
90.83
126.51
7.93
11.04
Sub-Total (Item 1.1-1.2)
68,025.59
20.19
217.33
18.97
Frame
Upper Floors
Roof Construction
Staircase Construction
44,553.10
17,758.37
14,025.88
2,951.42
13.22
5.27
4.16
0.88
142.34
56.74
44.81
9.43
12.42
4.95
3.91
0.82
Sub-Total (Item 2.1-2.4)
79,288.77
23.52
253.31
22.11
Roof Finishes
Ext. Walls, Doors & Windows
Int. Partitions & Doors
19,290.96
22,919.10
15,088.03
5.73
6.80
4.48
61.63
73.22
48.20
5.38
6.39
4.21
Sub-Total (Item 3.1-3.3)
57,298.09
17.02
183.05
15.98
Ext. Wall Finishes
Int. Wall Finishes
Floor Finishes
Staircase Finishes
Ceiling Finishes
Sundries
Sanitary Fittings
External Works Within Boundary
Ext. Mechanical and Electrical
Int. Mechanical and Electrical
TNB Substation
Infrastructure Works
7,876.54
18,978.05
18,559.76
2,636.90
12,364.75
1,229.43
4,230.71
27,607.34
3,456.10
21,552.94
2,046.51
24,081.94
2.34
5.63
5.51
0.78
3.67
0.36
1.26
8.19
1.03
6.40
0.61
7.15
25.16
60.63
59.30
8.42
39.50
3.93
13.52
88.20
11.04
68.86
6.54
76.94
2.20
5.29
5.17
0.74
3.45
0.34
1.18
7.70
0.96
6.01
0.57
6.71
144,620.97
42.93
462.05
40.32
349,233.41
103.66
1,115.74
97.37
9,033.19
387.14
2.68
0.11
28.86
1.24
2.52
0.11
358,653.74
106.45
1,145.84
100.00
Sub-Total (Item 4.1-4.12)
Sub - Total
5.1
5.2
Cost
(RM)
3,369 F.S.
Preliminaries
Prime Cost and Provisional Sums
Total
02/1361/C3-1
9.
Based
Based
C3-1 With Footin
#
1.1
1.2
Element
Piling
Work Below Ground Floor Level
Sub-Total (Item 1.1-1.2)
2.1
2.2
2.3
2.4
Frame
Upper Floors
Roof Construction
Staircase Construction
Sub-Total (Item 2.1-2.4)
3.1
3.2
3.3
Roof Finishes
Ext. Walls, Doors & Windows
Int. Partitions & Doors
Sub-Total (Item 3.1-3.3)
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
Ext. Wall Finishes
Int. Wall Finishes
Floor Finishes
Staircase Finishes
Ceiling Finishes
Sundries
Sanitary Fittings
External Works Within Boundary
Ext. Mechanical and Electrical
Int. Mechanical and Electrical
TNB Substation
Infrastructure Works
Sub-Total (Item 4.1-4.12)
5.1
5.2
Preliminaries
Prime Cost and Provisional Sums
Sub-Total (Item 5.1-5.2)
Total
A1
A1
A2
A2
Single
Frontage
Single
Frontage
Double
Frontage
Double
Frontage
Cost/F.S
Cost/F.S
Cost/F.S
Cost/F.S
Based
Based
Based
Based
Based
C3-1 With Footing
With Piling
C1
C1
C1
C1
C2
C2
A1
A1
C1
Single
Frontage
Single
Frontage
Double
Frontage
Double
Frontage
Double
Frontage
Double
Frontage
Single
Frontage
Single
Frontage
Single
Frontage
Cost/F.S
Cost/F.S
Cost/F.S
Cost/F.S
Cost/F.S
Cost/F.S
Cost/F.S
Cost/F.S
Cost/F.S