Professional Documents
Culture Documents
Part 3: Cost Management Fundamentals By Ted Garrison Garrison Associates www.TedGarrison.com www.StrategicPlanningforContractors.com www.NewConstructionStrategies.com
Therefore, the people performing the work should be part of the planning process. Project cost management is concerned about the cost of the resources need to complete the project.
(c) 2008 Garrison Associates 2
5 Phases of PM
D e fin e P la n
E x e cu te The Loop A d ju s t M o n it o r
C o m p le te
E v a lu a te
6. Prepare, review and revise the plan based on team input avoid analysis paralysis 7. Produce a final plan 8. Create a process for building change in the project plan
(c) 2008 Garrison Associates 8
Steps to Planning
Analyze the project objectives Create a list of the necessary tasks. Match the tasks with the available resources. Develop a schedule and budget. Adapt to the project priorities. Work out the details.
(c) 2008 Garrison Associates 9
Budget Identify potential risks Organizational chart identify all stakeholders Operating Procedures (systems or processes)
(c) 2008 Garrison Associates 10
Outputs
Resource requirements
(c) 2008 Garrison Associates 11
Outputs
Cost estimate Supporting detail Cost management plan (describes how cost variance will be managed)
(c) 2008 Garrison Associates 12
Outputs
Cost baseline
(c) 2008 Garrison Associates 13
Inputs
Cost baseline Performance reports Change requests Cost management plan
Outputs
Revised cost estimate Budget updates Corrective Action Final estimate Lessons learned (c) 2008 Garrison Associates
14
15
What is a WBS?
The WBS is the most important project management tool it is the basis for all other project management planning. The WBS gives the entire construction process structure. It s the list of tasks necessary to complete the project. In construction the specifications are the basis of the WBS.
(c) 2008 Garrison Associates 16
Outline WBS
1.0 Project
1.1 Major Project Subsystem 1.1.1 Task 1 1.1.1.1 Subtask 1 1.1.1.2 Subtask 2 1.1.2 Task 2 1.2 Major Project Subsystem 1.2.1 Task 1 1.2.2 Task 2
(c) 2008 Garrison Associates 19
Vapor Barrier
Place Concrete
Frame Garage
Install Windows
Form Slab
Sheathing
Install Reinforcing
Roofing
20
4 Phases of Estimating
1. Material quantity survey 2. Pricing material, labor and equipment 3. Analysis of subcontractor/vendor bids 4. Compute costs
22
Purpose of Estimates
Get future work cost knowledge Control present work compare costs to progress Control scope of work - dealing with changes Establish and control risk reflects on risk.
(c) 2008 Garrison Associates 23
Estimating Challenges
Priority of the project (specs vs. contract) The project s triple constraints Flexibility in the schedule Variables such as:
Weather, soil conditions, material availability, sub availability, and quality of project team.
24
25
Approximate Estimate:
Detailed systems pricing based on drawing but not pricing of individual items or tasks no quotations.
Detailed Estimate:
Complete quantitative take-off along with quotations.
(c) 2008 Garrison Associates 26
7. Obtain and analyze sub and vendor bids. 8. Summarize and review the costs of all items. 9. Add mark-up which includes general overhead and profit.
28
Project Overhead
Project overhead are all the items that are required to build the building but are not directly part of the project such as direct labor or materials or equipment used to in that aspect. Typical items such as the superintendent, project manager, waste removal, job office, phones, trucks, etc are charged to the project. All corporate expenses that are directly related to a project should be charged to project overhead.
This helps determine true costs of project More accurate than percentage of project
(c) 2008 Garrison Associates 29
General Overhead
These costs are from doing business and not associated with a particular project. When companies don t understand this cost they under charge. If too high will lose business. It usually established on an annual basis, but the key factor is the annual volume.
(c) 2008 Garrison Associates 30
33
Equipment/Materials/Supplies:
Optimistic: Cost Estimate: Labor: Materials: Equipment: Contract: Overhead: Fee: Total: Other important comments:
Pessimistic:
Most Likely:
$ $ $ $ $ $ $
37
Action Steps
Please turn to the inside of the front cover of the resource guide. Write down 1 to 3 action steps that you want to immediately implement from Part 3 of this program.